Procurement Plan ALBANIA ALBANIA HEALTH SYSTEM IMPROVEMENT PROJECT (HSIP) LOAN NO: 8466 AL. PROJECT ID NUMBER: P144688 I. General 1. Bank’s approval Date of the procurement Plan Original: December 1, 2015 Revision 1-st of Updated Procurement Plan: January 18, 2017 Revision 2-st of Updated Procurement Plan: January 26, 2017 2. Date of General Procurement Notice: October 22, 2015 3. Period covered by this procurement plan: The procurement period of project covered from year December 2015 to June 7, 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: 2. Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) ≥ 1,000,000 All 2. NCB (Goods) <1,000,000 First contract 3. ICB (Works) ≥ 5,000,000 First contract 4. NCB (Works) <5,000,000 First contract 5. Shopping (Goods and ≤ 100,000 First contract Works) 6. Direct Contracting "none" US$ ≥ 60,000 or EUR 54,054, subject to justification 3. Pre-qualification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. JUNE 9, 2017 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan 8466 AL, Health System Improvement Project issued by Ministry of Health/ Project Coordination Unit on December 18, 2015. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. No. Description Estimate Package Domestic Review Comme d s Preference by Bank nts Cost (yes/no) (Prior / EUR$ Post) million HSIP/CW/ICB/ Rehabilitation of 3.98 1 No Prior ICB 02-2017 Pediatric Hospital (QSUT) HSIP/CW/NCB Rehabilitation of 2.48 1 No Prior NCB /02-2017 infrastructure of selected hospitals under HMP HSIP/CW/NCB Upgrading of the 0.3 1 No Prior NCB /04-2017 NHIC building ("first contract CW under NCB") HSIP/G/ICB/0 Medical Equipment 5.6 1 No Prior ICB 1-2016 for Hospitals HSIP/CW/ICB/ Health Data Center 1.2 1 No Prior ICB 03-2017 IT equipment HSIP/G/ICB/0 Health Insurance 1.4 1 No Prior ICB 1-2018 Information System (HIIS) procurement: Software, Networking Hardware, Main hardware shared at NHIC HSIP/G/ICB/0 Supply and 9.1 1 No Prior ICB 2-2017 Installation of Regional Hospital Information System (RHIS) including training HSIP/CW/ICB/ DRG Grouper 0.23 1 No Prior ICB 04-2018 Software HSIP/G/NCB/ Supply & installation 0.4 1 No Prior NCB 06-2017 of Financial Management System Software in about 420 PHCs ("first JUNE 9, 2017 contract Goods under NCB") HSIP/G/NCB/ Furniture and 0.95 1 No Post NCB 05-2017 Furnishing for NHIC HSIP/G/SH/04 Biomedical 0.02 1 No Post SH -2015 Engineering Application Software HSIP/G/SH/01 IT Equipment for PCU 0.02 1 No Post SH -2015 staff HSIP/G/SH/02 Project Accounting 0.005 1 No Post SH -2015 Software Application HSIP/G/SH/03 Furniture for PCU 0.015 1 No Post SH -2015 staff offices III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) ≥ 300,000 First QCBS and all above US$ 500,000; First CQS 2. Consultant (Individual) None All US$ ≥ 200,000 or EUR 3. Single Source (Firms and None* US$ ≥ 5,000 or EUR Individuals)* 4,500 4. ToRs for Consulting Contracts All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Assignment Estimated Packa Review Comment Cost ges by Bank s EUR$ (Prior / million Post) HSIP/CS/QCBS Review of the hospital legal 0.64 1 Prior QCBS / 02-2017 framework including the establishment and implementation of training program for Board of Directors HSIP/CS/QCBS QSUT international management 1.1 1 Prior QCBS JUNE 9, 2017 /01-2016 team support - Implementation of the New Management Strategy for QSUT HSIP/CS/QCBS Develop annual business plans, 0.39 1 Prior QCBS /3-2017 automization strategy, monitoring indicators and provider Payment Reform in Primary Health Care including workshops and study tours HSIP/CS/CQS/ Review of the Existing Hospital 0.092 1 Prior CQ/CQBS 05-2015 Master Plan (Health Facility Rationalization Plan) HSIP/CS/CQ/0 Project Architectonic Design, 0.92 1 Prior CQ 1-2015 Inspection and Supervision of Civil Works for Reconstruction of Design and Supervision of National Health Information Center (NHIC) - (First "CQS" Contract) HSIP/CS/CQ/6- Establish an Accountability 0.08 1 Post CQ 2018 Tracking system using M&E indicators: to develop M&E accountability tracking system HSIP/CS/CQ/5- TA to the MoH Management on 0.23 1 Post CQ 2017 Health Reform HSIP/CS/CQ/7- Improving patient management, 0.08 1 Post CQ 2018 facility management and accountability: International TA social accountability mechanisms in the EU and globally HSIP/CS/CQ/8- Public Communication Campaign 0.04 1 Post CQ 2018 on Hospital Master Plan HSIP/CS/CQ/0 Communication campaign for 0.04 1 Post CQ 3-2015 hospitals’ reform HSIP/CS/CQ/0 Developing National Health 0.04 1 Post CQ 2-2015 Accounts HSIP/CS/CQ/0 For Technical assessment, design 0.2 1 Post CQ 4-2015 of civil work , specifications, estimated cost and supervision of civil works, Installation of medical devises and Furniture’s plot of existing pediatric hospital building. HSIP/CS/CQ/0 Medical Equipment Management 0.14 1 Post CQ 6-2017 Team to provide TA, Training & Study Tours HSIP/CS/CQ/0 Design and supervision services for 0.15 1 Post CQ 8-2017 rehabilitation of selected hospitals under HMP HSIP/CS/CQ/0 Final expection and validation of 0.05 1 Post CQ 9-2017 Pediatric Hospital and selected regional hospitals JUNE 9, 2017 HSIP/CS/CQ/1 Creating the Master Plan for 0.13 1 Post CQ 1-2017 HMIS/eHealth Activities (2016- 2020) & Health Data Dictionary HSIP/CS/CQ/1 Creating the first version of the 0.185 1 Post CQ 2-2017 Essential Registries for HMIS, including implementation and update mechanisms populating and validating registries HSIP/CS/CQ/1 Design services for Health Date 0.273 1 Post CQ 3-2017 Center architecture & topology, CRM, help desk/user support center & training center and CRM system HSIP/ST/01- IT Capacity building 0.8 1 Post CQ 2017 HSIP/CS/CQ/1 Requirements Study & Prepare 0.2 1 Post CQ 0- 2017 Tender (Requirements Analysis and Preparation of Technical Specifications for Implementation of Regional Hospitals Information System in Albania) HSIP/CS/CQ/9- Requirements Study, High-level 0.1 1 Post CQ 2018 Conceptual Design and Preparation of Tender of HIIS HSIP/CS/CQ/1 Provider Payment Reform in 0.22 1 Post CQ 4-2017 Hospital, inclidog study tours in Europe and high level workshops in Europe for 50 people, 2 days HSIP/CS/CQ/1 Develop DRG hospital funding and 0.17 1 Post CQ 5-2017 impact model at HIF, annual business plans, monitoring indicators and provider Payment Reform in Hospitals HSIP/CS/CQ/1 Review of coding system for 0.15 1 Post CQ 6-2017 diagnosis and procedures of pharmaceutical, PHCs and hospitals HSIP/CS/CQ/1 Develop P4P for performance 0.15 1 Post CQ 7-2018 models and introduce P4P with evaluation of the pilots HSIP/CS/CQ/1 Restructuring of existing 0.1 1 Post CQ 7-2017 reimbursed drug list & development HTA capacity for staff in chage of reviewing submissions from companies that seek reimbursement for medicine (MOH, HIF) HSIP/CS/CQ/1 Development generic drugs 0.08 1 Post CQ 0-2018 promotion campaign & training of staff in regional committees JUNE 9, 2017 HSIP/CS/CQ/1- Piloting expanded coverage of 0.048 1 Post CQ 2019 outpatient drug benefit package HSIP/CS/CQ/1 Development of Health Insurance 0.15 1 Post CQ 9-2017 Organization "Road Map" including study tours HSIP/CS/CQ/2 Training abroad of HI organization 0.15 1 Post CQ 0-2017 experts, management/claims auditing expeerts, fraud detection experts, management dashboards HSIP/CS/CQ/2- Performance Measurement System 0.056 1 Post CQ 2019 HSIP/CS/CQ/3- Moving to general 0.116 1 Post CQ 2019 revenue/expenditure and revenue model including training/workshop HSIP/CS/IC/01 Project Manager 0.0875 1 Prior IC -2015 HSIP/CS/IC/02 Procurement Consultant 0.0875 1 Prior IC -2015 HSIP/CS/IC/03 Financial Management Consultant 0.007 1 Prior IC -2015 HSIP/CS/IC/04 QSUT management assessment & 0.004 1 Post IC -2015 preparation of TOR for the international management team- HSIP/CS/IC/05 IT Consultant - E-health 0.007 1 Post IC -2015 Coordinator HSIP/CS/IC/08 Supervising / Civil works Engineer 0.008 2 Post IC -2015 HSIP/CS/IC/09 Office Assistant 0.004 1 Post IC -2015 HSIP/CS/IC/12 Legal services for non-profit 0.001 1 Post IC -2017 community based organizations HSIP/CS/IC/10 Improving patient management, 0.004 1 Post IC - 2019 facility management and accountability: International TA using administrative data to improve quality and performance HSIP/CS/IC/09 Design of Biomedical Equipment 0.012 1 Post IC -2017 Maintenance Unit and IT equipment maintenance HSIP/CS/IC/07 Preparation of ToR for "Creating 0.0015 1 Post IC -2016 the Master Plan for HMIS/eHealth Activities (2016-2020) & Health Data Stadardization Framework" HSIP/CS/IC/01 Capacity building: Training on HIF 0.005 1 Post IC -2018 business processes as a factory & automated claims shop HSIP/CS/IC/01 Develop quality assurance systems 0.003 1 Post IC -2019 in conjunction with new payment systems HSIP/CS/IC/06 Design of technical specifications 0.002 1 Post IC JUNE 9, 2017 -2015 of Supply & installation of Financial Management System Software in about 420 PHCs HSIP/CS/IC/08 IT Assessment Consultant for 0.0004 1 Post IC - 2017 Health Insurance Fund JUNE 9, 2017 PROCUREMENT Albania : Health System Improvement Project PLAN General Information Country: Albania Bank’s Approval Date of the Original Procurement Plan: 2016-10-21 2018-10-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144688 GPN Date: Project Name: Health System Improvement Project Loan / Credit No: IBRD / 84660 Executing Agency(ies): Ministry of Health WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HSIP/CW/NCB/03-2017 / Pending Rehabilitation of Single Stage - One IBRD / 84660 Prior Request for Bids Open - National 0.00 Implementati 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 infrastructure of selected Envelope on hospitals under HMP HSIP/CW/NCB/04-2017 / Pending Upgrading of the NHIC Single Stage - One IBRD / 84660 Prior Request for Bids Open - National 0.00 Implementati 2017-09-30 2017-10-05 2017-11-16 2017-12-16 2018-01-20 2018-07-19 building ("first contract CW Envelope on under NCB") HSIP/CW/ICB/02-2017 / Under Open - Single Stage - One Rehabilitation of Pediatric IBRD / 84660 Prior Request for Bids 0.00 Implementati 2018-09-10 2018-09-30 2018-11-11 2018-12-11 2019-01-15 2019-07-14 International Envelope Hospital (QSUT) Buildings on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Under HSIP/ICB/01-2016 / Medical Open - Single Stage - One IBRD / 84660 Prior Request for Bids 0.00 Implementati 2017-01-30 2017-02-04 2017-03-18 2017-04-17 2017-05-22 2017-11-18 Equipment for Hospitals International Envelope on HSIP/G/SH/04-2015 / Pending Request for Open - Single Stage - One Biomedical Engineering IBRD / 84660 Post 0.00 Implementati 2017-06-06 2017-08-01 2018-01-28 Quotations International Envelope Application Software on HSIP/CW/ICB/03-2017 / Pending Open - Single Stage - One Health Data Center IT IBRD / 84660 Prior Request for Bids 0.00 Implementati 2017-02-28 2017-03-05 2017-04-16 2017-05-16 2017-06-20 2017-12-17 International Envelope equipment on HSIP/G/NCB/05-2017 / Pending Single Stage - One Furniture and Furnishing for IBRD / 84660 Post Request for Bids Open - National 0.00 Implementati 2017-02-01 2017-02-06 2017-03-20 2017-04-19 2017-05-24 2017-11-20 Envelope NHIC on HSIP/G/ICB/02-2017 / Supply and Installation of Pending Open - Single Stage - One Regional Hospital IBRD / 84660 Prior Request for Bids 0.00 Implementati 2017-11-20 2017-11-25 2018-01-06 2018-02-05 2018-03-12 2018-09-08 International Envelope Information System (RHIS) on including training HSIP/G/ICB/01-2018 / Health Insurance Information Pending System (HIIS) procurement: Open - Single Stage - One IBRD / 84660 Prior Request for Bids 0.00 Implementati 2018-09-03 2018-09-08 2018-10-20 2018-11-19 2018-12-24 2019-06-22 Software, Networking International Envelope on Hardware, Main hardware shared at NHIC Page 1 HSIP/G/NCB/06-2017 / Supply & installation of Pending Financial Management Open - Single Stage - One IBRD / 84660 Post Request for Bids 0.00 Implementati 2017-12-26 2017-12-31 2018-02-11 2018-03-13 2018-04-17 2018-10-14 System Software in about International Envelope on 420 PHCs ("first contract Goods under NCB") Pending HSIP/CW/ICB/04-2018 / Open - Single Stage - One IBRD / 84660 Prior Request for Bids 0.00 Implementati 2018-11-01 2018-11-06 2018-12-18 2019-01-17 2019-02-21 2019-08-20 DRG Grouper Software International Envelope on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HSIP/CS/CQ/01-2015 / Project Architectonic Design, Inspection and Supervision Consultant Open - of Civil Works for IBRD / 84660 Prior Qualification 102,438.71 Signed 2015-08-29 2015-11-27 2015-12-27 2016-02-25 2017-02-19 International Reconstruction of National Selection Health InformationCenter (NHIC) HSIP/CS/QCBS/02-2017 / Review of the hospital legal framework including the Quality And Cost- Open - Pending establishment and IBRD / 84660 Prior 0.00 2017-10-10 2017-10-31 2017-12-14 2018-01-11 2018-02-10 2018-03-17 2018-04-21 2019-04-21 Based Selection International Implementation implementation of training program for Board of Directors HSIP/CS/CQ/6-2017 / Establish an Accountability Consultant Tracking system using M&E Pending IBRD / 84660 Post Qualification Open - National 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2019-02-03 indicators: to develop M&E Implementation Selection accountability tracking system HSIP/CS/CQ/5-2017 / TA to Consultant Open - Pending the MoH Management on IBRD / 84660 Post Qualification 0.00 2017-05-30 2017-06-20 2017-08-03 2017-09-02 2017-10-07 2018-04-05 International Implementation Health Reform Selection HSIP/CS/CQ/7-2018 / Improving patient management, facility Consultant management and Pending IBRD / 84660 Post Qualification Open - National 0.00 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2019-04-07 accountability: International Implementation Selection TA social accountability mechanisms in the EU and globally HSIP/CS/QCBS/01-2016 / QSUT international management team support - Quality And Cost- Open - Under IBRD / 84660 Prior 0.00 2017-01-18 2017-02-08 2017-03-24 2017-04-21 2017-05-21 2017-06-25 2017-07-30 2018-07-30 Implementation of the New Based Selection International Implementation Management Strategy for QSUT Page 2 HSIP/CS/CQ/8-2018 / Public Consultant Open - Pending Communication Campaign on IBRD / 84660 Post Qualification 0.00 2018-04-25 2018-05-16 2018-06-29 2018-07-29 2018-09-02 2019-03-01 International Implementation Hospital Master Plan Selection HSIP/CS/CQ/06-2017 / Medical Equipment Consultant Pending Management Team to IBRD / 84660 Post Qualification Open - National 0.00 2017-06-01 2017-06-22 2017-08-05 2017-09-04 2017-10-09 2018-04-07 Implementation provide TA, Training & Selection Study Tours HSIP/CS/CQ/08-2017 / Design and supervision Consultant Pending services for rehabilitation of IBRD / 84660 Post Qualification Open - National 0.00 2017-02-01 2017-02-22 2017-04-07 2017-05-07 2017-06-11 2017-12-08 Implementation selected hospitals under Selection HMP HSIP/CS/CQ/09-2017 / Final Consultant Inspection and validation of Pending IBRD / 84660 Post Qualification Open - National 0.00 2017-12-01 2017-12-22 2018-02-04 2018-03-06 2018-04-10 2018-10-07 Pediatric Hospital and Implementation Selection selected regional hospitals HSIP/CS/CQ/10-2017 / Creating the Master Plan Consultant Open - Pending for HMIS/e Health Activities IBRD / 84660 Post Qualification 0.00 2017-03-17 2017-04-07 2017-05-21 2017-06-20 2017-07-25 2018-01-21 International Implementation (2016-2020) & Health Data Selection Dictionary HSIP/CS/CQ/11-2017 / Creating the first version of the Essential Registries for Consultant Open - Pending HMIS, including IBRD / 84660 Post Qualification 0.00 2017-07-05 2017-07-26 2017-09-08 2017-10-08 2017-11-12 2018-05-11 International Implementation implementation and update Selection mechanisms populating and validating registries HSIP/CS/CQ/12-2017 / Design services for Health Date Center architecture & Consultant Open - Pending topology, CRM, help IBRD / 84660 Post Qualification 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-04 2018-02-08 2018-08-07 International Implementation desk/user support center & Selection training center and CRM system Consultant HSIP/ST/01-2017 / IT Open - Pending IBRD / 84660 Post Qualification 0.00 2017-09-10 2017-10-01 2017-11-14 2017-12-14 2018-01-18 2018-07-17 Capacity building International Implementation Selection HSIP/CS/CQ/10- 2017 / Requirements Study & Prepare Tender (Requirements Analysis and Consultant Pending Preparation of Technical IBRD / 84660 Post Qualification Open - National 0.00 2017-01-30 2017-02-20 2017-04-05 2017-05-05 2017-06-09 2017-12-06 Implementation Specifications for Selection Implementation of Regional Hospitals Information System in Albania) HSIP/CS/CQ/9-2018 / Requirements Study, High- Consultant Pending level Conceptual Design and IBRD / 84660 Post Qualification Open - National 0.00 2018-05-01 2018-05-22 2018-07-05 2018-08-04 2018-09-08 2019-03-07 Implementation Preparation of Tender of Selection HIIS HSIP/CS/QCBS/3-2017 / Develop annual business plans, atomization strategy, monitoring indicators and Quality And Cost- Open - Pending IBRD / 84660 Post 0.00 2017-09-10 2017-10-01 2017-11-14 2017-12-12 2018-01-11 2018-02-15 2018-03-22 2019-03-22 provider Payment Reform in Based Selection International Implementation Primary Health Care including workshops and study tours Page 3 HSIP/CS/CQ/14-2017 / Provider Payment Reform in Consultant Hospital, include study tours Open - Pending IBRD / 84660 Post Qualification 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-04 2018-02-08 2018-08-07 in Europe and high level International Implementation Selection workshops in Europe for 50 people, 2 days HSIP/CS/CQ/15-2017 / Develop DRG hospital funding and impact model at Consultant Pending HIF, annual business plans, IBRD / 84660 Post Qualification Open - National 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-04 2018-02-08 2018-08-07 Implementation monitoring indicators and Selection provider Payment Reform in Hospitals HSIP/CS/CQ/16-2017 / Review of coding system for Consultant Pending diagnosis and procedures of IBRD / 84660 Post Qualification Open - National 0.00 2017-06-01 2017-06-22 2017-08-05 2017-09-04 2017-10-09 2018-04-07 Implementation pharmaceutical, PHCs and Selection hospitals HSIP/CS/CQ/17-2018 / Consultant Develop P4P for performance Open - Pending IBRD / 84660 Post Qualification 0.00 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2019-04-07 models and introduce P4P International Implementation Selection with evaluation of the pilots HSIP/CS/CQ/17-2017 / Restructuring of existing reimbursed drug list & development HTA capacity Consultant Pending for staff in change of IBRD / 84660 Post Qualification Open - National 0.00 2017-05-01 2017-05-22 2017-07-05 2017-08-04 2017-09-08 2018-03-07 Implementation reviewing submissions from Selection companies that seek reimbursement for medicine (MOH, HIF) HSIP/CS/CQ/10-2018 / Development generic drugs Consultant Pending promotion campaign & IBRD / 84660 Post Qualification Open - National 0.00 2018-01-01 2018-01-22 2018-03-07 2018-04-06 2018-05-11 2018-11-07 Implementation training of staff in regional Selection committees HSIP/CS/CQ/1-2019 / Consultant Piloting expanded coverage Pending IBRD / 84660 Post Qualification Open - National 0.00 2019-01-07 2019-01-28 2019-03-13 2019-04-12 2019-05-17 2019-11-13 of outpatient drug benefit Implementation Selection package HSIP/CS/CQ/20-2017 / Training abroad of HI organization experts, Consultant Pending management/claims auditing IBRD / 84660 Post Qualification Open - National 0.00 2017-05-01 2017-05-22 2017-07-05 2017-08-04 2017-09-08 2018-03-07 Implementation expeerts, fraud detection Selection experts, management dashboards PERFORMANCE Consultant MEASUREMENT SYSTEM / Pending IBRD / 84660 Post Qualification Open - National 0.00 2019-02-01 2019-02-22 2019-04-07 2019-05-07 2019-06-11 2019-12-08 Performance Measurement Implementation Selection System HSIP/CS/CQ/3-2019 / Moving to general Consultant Pending revenue/expenditure and IBRD / 84660 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2020-01-05 Implementation revenue model including Selection training/workshop HSIP/CS/CQS/05-2015 / Review of the Existing Consultant Open - Hospital Master Plan IBRD / 84660 Post Qualification 0.00 Canceled 2016-12-22 2017-01-12 2017-02-25 2017-03-27 2017-05-01 2017-10-28 International (Health Facility Selection Rationalization Plan) Page 4 HSIP/CS/CQ/19-2017 / Development of Health Consultant Insurance Organization IBRD / 84660 Post Qualification Open - National 0.00 Canceled 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 "Road Map" including study Selection tours HSIP/CS/QCBS/05-2015 / Review of the Existing Hospital Master Plan Quality And Cost- Open - Pending IBRD / 84660 Prior 0.00 2018-10-24 2018-11-14 2018-12-28 2019-01-25 2019-02-24 2019-03-31 2019-05-05 2020-05-04 (Health Facility Based Selection International Implementation Rationalization Plan) in Albania INDIVIDUAL CONSULTANTS Page 5