Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 21, 2016. 2. Date of General Procurement Notice: September 28, 2016. 3. Period covered by this procurement plan: January 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million 3. ICB (Works) Above US$ 10 million 4. NCB (Works) Above US$ 2 million 5. Non-Consultant Services Above US$2 million 6 Consultants (firms) Above US$ 1 million 7. Consultant Individuals Above 0.3 million 2. Prequalification. Not applicable. 4. Any Other Special Procurement Arrangements: Retroactive financing up to 5 million. July 9, 2010 PROCUREMENT Mexico : Energy Efficiency in Public Facilities Project (PRESEMEH) PLAN General Information Country: Mexico Bank’s Approval Date of the Original Procurement Plan: 2016-11-29 2019-12-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149872 GPN Date: 2016-09-28 Project Name: Energy Efficiency in Public Facilities Project (PRESEMEH) Loan / Credit No: IBRD / 85940 Executing Agency(ies): Secretaria de Energia WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-FIDE-LPN- AP-GTO-2017-01 / Municipal energy efficiency Solicitud de Single Stage - One ALUMBRADO PUBLICO EN IBRD / 85940 Posterior Open - National 7,890,213.00 0.00 Cancelado 2017-09-15 2017-09-21 2017-10-12 2017-11-08 2017-11-27 2018-02-23 investments ofertas Envelope EL MUNICIPIO DE LEON, GUANAJUATO SENER-DGESE-FIDE-LPN- BA-TLAX-2017-02 / Municipal energy efficiency Solicitud de Single Stage - One BOMBEO DE AGUA EN EL IBRD / 85940 Posterior Open - National 676,304.00 0.00 Cancelado 2017-10-18 2017-10-23 2017-11-14 2017-11-29 2017-12-27 2018-06-27 investments ofertas Envelope MUNICIPIO DE HUAMANTLA, TLAXCALA SENER-DGESE-FIDE-LPN- AP-GTO-2017-01-A / ALUMBRADO PUBLICO EN Municipal energy efficiency Solicitud de Single Stage - One EL MUNICIPIO DE LEON, IBRD / 85940 Posterior Open - National 7,890,213.00 0.00 En ejecución 2017-09-15 2017-09-21 2017-10-12 2017-11-08 2017-11-27 2018-02-23 investments ofertas Envelope GUANAJUATO SENER- DGESE-FIDE-LPN-AP-GTO- 2017-01 SENER-DGESE-FIDE-LPN- BA-TLAX-2017-02-A / BOMBEO DE AGUA EN EL Municipal energy efficiency Solicitud de Single Stage - One Ejecución MUNICIPIO DE IBRD / 85940 Posterior Open - National 676,304.00 0.00 2018-03-21 2018-04-03 2018-05-15 2018-06-08 2018-06-29 2018-10-29 investments ofertas Envelope pendiente HUAMANTLA, TLAXCALA SENER-DGESE-FIDE-LPN- BA-TLAX-2017-02 SENER-DGESE-FIDE-LPN- EM-PUE-2018-01 / PROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One Ejecución IBRD / 85940 Posterior Open - National 360,000.00 0.00 2018-04-03 2018-04-17 2018-05-24 2018-06-11 2018-07-03 2018-10-31 EDIFICACIONES EN EL investments ofertas Envelope pendiente MUNICIPIO DE PUEBLA, PUEBLA SENER-DGESE-FIDE-LPN- AP-DMH-2018-02 / PROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One Ejecución ALUMBRADO PUBLICO EN IBRD / 85940 Posterior Open - National 5,698,598.93 0.00 2018-04-19 2018-04-25 2018-05-09 2018-05-28 2018-06-16 2018-09-14 investments ofertas Envelope pendiente LA DELEGACION MIGUEL HIDALGO, CIUDAD DE MEXICO SENER-DGESE-FIDE-LPN- AP-HJUAPAN-2018-04 / SUBPROYECTO DE ALUMBRADO PUBLICO Municipal energy efficiency Solicitud de Single Stage - One Ejecución PARA EL MUNICIPIO DE IBRD / 85940 Posterior Open - National 4,000,000.00 0.00 2018-07-17 2018-08-03 2018-09-14 2018-10-03 2018-10-29 2019-01-14 investments ofertas Envelope pendiente HUAJUAPAN DE LEON OAXACA SENER-DGESE- FIDE-LPN-AP-HJUAPAN- 2018-04 Page 1 SENER-DGESE-FIDE-LPN- AP-OAX-2018-05 / SUBPROYECTO DE ALUMBRADO PÚBLICO Municipal energy efficiency Solicitud de Single Stage - One IBRD / 85940 Previa Open - National 7,600,000.00 7,349,433.53 Firmado 2018-11-26 2018-12-11 2019-01-01 2019-02-12 2019-03-06 2019-05-20 PARA EL MUNICIPIO DE investments ofertas Envelope OAXACA DE JUÁREZ SENER-DGESE-FIDE-LPN- AP-OAX-2018-05 SENER-DGESE-FIDE-LPN- AP-CUL-2018-06 / SUBPROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One Ejecución ALUMBRADO PÚBLICO IBRD / 85940 Previa Open - National 12,000,000.00 0.00 2018-12-17 2019-01-01 2019-01-22 2019-03-05 2019-03-27 2019-06-10 investments ofertas Envelope pendiente PARA EL MUNICIPIO DE CULIACÁN SENER-DGESE- FIDE-LPN-AP-CUL-2018-06 SENER-DGESE-FIDE-LPN- AP-COZ-2018-03 / SUBPROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One Ejecución ALUMBRADO PÚBLICO IBRD / 85940 Posterior Open - National 6,500,000.00 0.00 2018-08-08 2018-08-23 2018-09-13 2018-10-25 2018-11-20 2019-02-03 investments ofertas Envelope pendiente PARA EL MUNICIPIO DE COZUMEL SENER-DGESE- FIDE-LPN-AP-COZ-2018-03 SENER-DGESE-FIDE-LPN- AP-COZ-2019-01 / SUBPROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One Ejecución ALUMBRADO PÚBLICO IBRD / 85940 Posterior Open - National 3,250,000.00 0.00 2019-12-27 2020-01-12 2020-02-06 2020-03-07 2020-04-01 2020-06-30 investments ofertas Envelope pendiente PARA EL MUNICIPIO DE COZUMEL, SENER-DGESE- FIDE-LPN-AP-COZ-2019-01 SENER-DGESE-FIDE-LPN- AP-COAT-2019-02 / SUBPROYECTO DE ALUMBRADO PÚBLICO Municipal energy efficiency Solicitud de Single Stage - One Ejecución PARA EL MUNICIPIO DE IBRD / 85940 Posterior Open - National 4,139,780.00 0.00 2020-02-20 2020-02-25 2020-04-07 2020-05-07 2020-06-11 2020-12-08 investments ofertas Envelope pendiente COATZACOALCOS, VERACRUZ, SENER- DGESE-FIDE-LPN-AP-COAT- 2019-02 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-FIDE-LPI- AP-GTO-2016-01 / Municipal energy efficiency Solicitud de Open - Single Stage - One IBRD / 85940 Previa 12,000,000.00 0.00 Cancelado 2017-01-27 2017-02-11 2017-03-28 2017-05-02 2017-05-27 2018-01-02 ALUMBRADO PUBLICO EN investments ofertas International Envelope EL MUNICIPIO DE LEON SENER-DGESE-FIDE-LPN- BA-TLAX-2016-01 / Municipal energy efficiency Solicitud de Single Stage - One BOMBEO DE AGUA EN EL IBRD / 85940 Previa Open - National 3,600,000.00 0.00 Cancelado 2017-01-13 2017-01-28 2017-02-17 2017-03-19 2017-04-05 2017-10-23 investments ofertas Envelope MUNICIPIO DE HUAMANTLA. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 SENER-DGESE-CP-S-2016- 02 / CAPACITACION POR PARTE DEL BANCO MUNDIAL DIRIGIDA A FUNCIONARIOS DE LA SENER, CONUEE, UREP, Policy development and Solicitud de Single Stage - One Ejecución IBRD / 85940 Posterior Open - National 15,000.00 0.00 2017-01-23 2017-03-19 2017-04-06 MUNICIPIOS Y institutional strengthening cotizaciones Envelope pendiente CONSULTORES, PARA LA HERRAMIENTA CLIMATE ACTION FOR URBAN SUSTAINABILITY (CURB) AL CONTEXTO MEXICANO. SENER-DGESE-CP-S-2016- 01 / DISENO, EDICION E IMPRESION DE LOS INFORMES DE RESULTADOS DE 7 Policy development and Solicitud de Single Stage - One Ejecución ESTUDIOS (LEDS; IBRD / 85940 Posterior Open - National 50,000.00 0.00 2016-10-31 2016-12-04 2017-02-02 institutional strengthening cotizaciones Envelope pendiente HOSPITALES; CENTROS DE ACOPIO; ESCUELAS, IMPACTO DEL PROYECTO, HOTELES E IMPORTACIONES). SENER-DGESE-CP-S-2017- 01 / LICENCIA DE USO Policy development and Solicitud de Single Stage - One Ejecución IBRD / 85940 Posterior Limited 268.00 0.00 2017-06-23 2017-07-25 2018-07-25 DEL SISTEMA CONTABLE institutional strengthening cotizaciones Envelope pendiente CONTPAQ i SENER-DGESE-CP-S-2018- 01 / LICENCIA DE USO Policy development and Solicitud de Single Stage - One IBRD / 85940 Posterior Limited 270.00 270.87 En ejecución 2018-11-20 2018-12-22 2019-12-22 DEL SISTEMA CONTABLE institutional strengthening cotizaciones Envelope CONTPAQi CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-SCC-2016- 01 / DESARROLLO DE UNA PLATAFORMA EN LINEA DE SEGUIMIENTO Selección basada Policy development and Ejecución DE RESULTADOS DEL IBRD / 85940 Posterior en calificaciones Open - National 100,000.00 0.00 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 institutional strengthening pendiente PRESEM (DIAGNOSTICOS de consultores Y EL MONITOREO DE LAS INTERVENCIONES EN MUNICIPIOS) SENER-DGESE-SCC-2016- 02 / DEFINICION DE LOS PARAMETROS A Selección basada Policy development and REPORTAR PARA EL IBRD / 85940 Posterior en calificaciones Open - National 150,000.00 0.00 En ejecución 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 institutional strengthening ESTABLECIMIENTO DE de consultores UNA LINEA BASE PARA MONITOREO DEL PRESEM SENER-DGESE-SCC-2016- 03 / DISENO Y DESARROLLO DE UNA PAGINA WEB PARA DIFUSION DE LOS Selección basada RESULTADOS Y CASOS DE Policy development and Ejecución IBRD / 85940 Posterior en calificaciones Open - National 45,000.00 0.00 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 EXITO DEL PRESEM (SE institutional strengthening pendiente de consultores ESTA REVISANDO SI SERA UNA FIRMA O UN CONSULTOR INDIVIDUAL, DE SER ESTE ULTIMO SE HARA EL AJUSTE CORRESPONDIENTE) Page 3 SENER-DGESE-SCC-2016- 04 / DISENO E IMPARTICION DE 9 Selección basada TALLERES DE EFICIENCIA Policy development and IBRD / 85940 Posterior en calificaciones Open - National 270,000.00 0.00 Cancelado 2017-01-06 2017-01-10 2017-02-10 2017-02-16 2017-02-27 2017-08-31 ENERGETICA: 3 PARA LA institutional strengthening de consultores REGION NORTE, 3 PARA LA REGION CENTRO Y 3 PARA LA REGION SUR SENER-DGESE-SCC-2016- 06 / EVALUACION DE Selección basada Policy development and Ejecución IMPACTO DEL IBRD / 85940 Posterior en calificaciones Open - National 150,000.00 0.00 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 institutional strengthening pendiente ECOCREDITO de consultores EMPRESARIAL SENER-DGESE-SCC-2017- 01 / DISEÑO DE MECANISMO PARA EL Selección basada APOYO ECONOMICO AL Policy development and Ejecución IBRD / 85940 Posterior en calificaciones Open - National 45,000.00 0.00 2017-11-24 2017-12-11 2018-01-16 2018-02-15 2018-02-25 2018-05-26 CUMPLIMIENTO DE LA institutional strengthening pendiente de consultores NOM-020-ENER PARA VIVIENDA DE INTERES SOCIAL SENER-DGESE-SCC-2017- 02 / DISENO E IMPARTICION DE 3 TALLERES DE EFICIENCIA Selección basada Policy development and Ejecución ENERGETICA EN LOS IBRD / 85940 Posterior en calificaciones Open - National 80,000.00 0.00 2017-12-11 2018-01-30 2018-02-26 2018-03-05 2018-03-23 2018-05-25 institutional strengthening pendiente MUNICIPIOS DE de consultores MONTERREY NUEVO LEON GUADALAJARA JALISCO Y VILLAHERMOSA TABASCO INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-CI-3CV-2016- 02 / EJECUTIVO DE GESTION FINANCIERA DE LA UNIDAD Policy development and IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-11-03 2016-11-13 2016-11-20 2016-12-01 2021-10-31 RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 03 / ASISTENTE CONTABLE DE LA Policy development and Ejecución UNIDAD RESPONSABLE IBRD / 85940 Previa Individual Limited 99,157.26 0.00 2017-02-13 2017-02-28 2017-03-07 2017-03-17 2021-10-31 institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 04 / EJECUTIVO DE ADQUISICIONES DE LA Policy development and UNIDAD RESPONSABLE IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-10-24 2016-10-25 2016-10-26 2016-11-01 2021-10-31 institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 05 / ASISTENTE EN ADQUISICIONES DE LA Policy development and Ejecución UNIDAD RESPONSABLE IBRD / 85940 Previa Individual Limited 99,157.26 0.00 2017-02-24 2017-03-01 2017-03-22 2017-04-26 2021-10-31 institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEM) Page 4 SENER-DGESE-CI-3CV-2016- 08 / ESPECIALISTA TECNICO DE LA UNIDAD Policy development and RESPONSABLE IBRD / 85940 Previa Individual Limited 99,157.26 0.00 En ejecución 2016-11-21 2016-12-06 2016-12-20 2017-01-02 2021-10-31 institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 10 / CONSULTOR EXPERTO PARA SUPERVISAR LOS DIAGNOSTICOS Policy development and Ejecución IBRD / 85940 Previa Individual Limited 253,042.81 0.00 2017-04-28 2017-05-13 2017-05-21 2017-06-01 2021-05-31 MUNICIPALES EN institutional strengthening pendiente EFICIENCIA ENERGETICA Y ANALISIS DE RESULTADOS DEL PRESEM SENER-DGESE-CI-3CV-2016- 11 / CONSULTOR PARA LA ADAPTACION DEL "MANUAL PARA LA Policy development and Ejecución IBRD / 85940 Previa Individual Limited 124,257.89 0.00 2017-01-20 2017-02-03 2017-02-20 2017-03-02 2021-03-01 IMPLEMENTACION DE UN institutional strengthening pendiente SISTEMA DE GESTION DE LA ENERGIA DE LA CONUEE" EN MUNICIPIOS. SENER-DGESE-CI-3CV-2016- Policy development and 12 / GESTOR MUNICIPAL IBRD / 85940 Previa Individual Limited 271,446.48 0.00 Cancelado 2016-10-21 2016-10-22 2016-10-23 2016-11-01 2021-10-31 institutional strengthening REGION NORTE SENER-DGESE-CI-3CV-2016- Policy development and 13 / GESTOR MUNICIPAL IBRD / 85940 Previa Individual Limited 271,446.48 0.00 En ejecución 2016-10-21 2016-10-22 2016-10-23 2016-11-21 2021-10-31 institutional strengthening REGION SUR SENER-DGESE-CI-3CV-2016- 09 / EJECUTIVO EN NORMATIVIDAD Y Policy development and SEGUIMIENTO DE LA IBRD / 85940 Previa Individual Limited 155,913.90 0.00 En ejecución 2016-03-16 2016-03-21 2016-05-24 2016-05-31 2021-10-31 institutional strengthening UNIDAD RESPONSABLE EJECUTORA DEL PROYECTO (UREP). SENER-DGESE-CI-3CV-2016- 06 / ASISTENTE Policy development and IBRD / 85940 Posterior Individual Limited 61,039.42 0.00 En ejecución 2016-03-07 2016-03-12 2016-05-17 2016-05-20 2021-10-31 ADMINISTRATIVO Y DE institutional strengthening SISTEMAS DE LA UREP SENER-DGESE-CI-3CV-2016- 01 / COORDINADOR GENERAL DE LA UNIDAD Policy development and IBRD / 85940 Previa Individual Limited 460,207.73 0.00 En ejecución 2016-03-07 2016-03-12 2016-05-11 2016-05-17 2021-10-31 RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO (UREP) SENER-DGESE-CI-3CV-2016- 07 / COORDINADOR TECNICO DE LA UNIDAD Policy development and IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-03-14 2016-03-19 2016-04-09 2016-05-17 2021-10-31 RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO (UREP) SENER-DGESE-CI-3CV-2016- 14 / COORDINADOR GENERAL DE LA UNIDAD Policy development and IBRD / 85940 Posterior Individual Limited 32,253.46 0.00 En ejecución 2017-01-13 2017-01-18 2017-01-23 2017-02-06 2017-08-05 RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO UREP/PRESEM. Page 5 SENER-DGESE-CI-3CV-2016- 15 / EVALUACION Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-10-24 ENERGETICA URBANA EN institutional strengthening pendiente EL MUNICIPIO 1 SENER-DGESE-CI-3CV-2016- 16 / EVALUACION Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN institutional strengthening pendiente EL MUNICIPIO 2 SENER-DGESE-CI-3CV-2016- 17 / EVALUACION Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN institutional strengthening pendiente EL MUNICIPIO 3 SENER-DGESE-CI-3CV-2016- 18 / EVALUACION Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN institutional strengthening pendiente EL MUNICIPIO 4 SENER-DGESE-CI-3CV-2016- 19 / EVALUACION Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN institutional strengthening pendiente EL MUNICIPIO 5 SENER-DGESE-CI-3CV-2016- 20 / EVALUACION Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN institutional strengthening pendiente EL MUNICIPIO 6 SENER-DGESE-CI-3CV-2016- 21 / DESARROLLO DE Policy development and Ejecución GUIA DE APOYOS IBRD / 85940 Posterior Individual Limited 25,000.00 0.00 2017-03-10 2017-03-15 2017-03-23 2017-04-05 2017-10-02 institutional strengthening pendiente FINANCIEROS A MUNICIPIOS SENER-DGESE-CI-3CV-2016- 22 / ESPECIALISTA EN Policy development and IBRD / 85940 Posterior Individual Limited 33,000.00 0.00 En ejecución 2017-01-16 2017-01-21 2017-01-24 2017-02-13 2018-02-13 COMUNICACION DEL institutional strengthening PRESEM SENER-DGESE-CI-3CV-2016- 23 / ASISTENTE TECNICO EN EFICIENCIA ENERGETICA DE LA Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 2017-04-10 2017-04-15 2017-04-26 2017-05-08 2017-11-04 UNIDAD RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO UREP/PRESEM 1 SENER-DGESE-CI-3CV-2016- 24 / ASISTENTE TECNICO EN EFICIENCIA ENERGETICA DE LA Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 2017-04-10 2017-04-15 2017-04-24 2017-05-08 2017-11-04 UNIDAD RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO UREP/PRESEM 2 SENER-DGESE-CI-3CV-2016- 25 / ASISTENTE TECNICO EN EFICIENCIA ENERGETICA DE LA Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 2017-04-10 2017-04-15 2017-04-24 2017-05-08 2017-11-04 UNIDAD RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO UREP/PRESEM 3 Page 6 SENER-DGESE-CI-3CV-2017- 01 / ASISTENTE ADMINISTRATIVO DE LA Policy development and Ejecución UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 70,363.42 0.00 2017-06-23 2017-06-26 2017-07-11 2017-08-01 2021-10-29 institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2017- 02 / EJECUTIVO EN NORMATIVIDAD Y SEGUIMIENTO DE Policy development and Ejecución ACUERDOS DE LA IBRD / 85940 Posterior Individual Limited 120,298.96 0.00 2017-06-23 2017-06-26 2017-07-17 2017-08-01 2021-10-29 institutional strengthening pendiente UNIDAD RESPONSABLE EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CF-SD-2017- 01 / TALLER DE CAPACITACION EN EL MANEJO Y ENSEÑANZA Policy development and Selección directa Ejecución IBRD / 85940 Posterior Direct 9,000.00 0.00 2017-09-14 2017-09-18 2017-09-29 2017-11-22 DE LA HERRAMIENTA institutional strengthening de consultores pendiente CLIMATE ACTION FOR URBAN SUSTAINABILITY (CURB) SENER-DGESE-CI-CD-2016- 1 / CONSULTOR ESPECIALISTA EN EL MANEJO Y ENSENANZA Policy development and Selección directa IBRD / 85940 Posterior Direct 8,000.00 0.00 Cancelado 2017-02-01 2017-02-11 2017-02-27 2017-03-06 DE LA HERRAMIENTA institutional strengthening de consultores CLIMATE ACTION FOR URBAN SUSTAINABILITY (CURB) SENER-DGESE-CI-CD-2017- 01 / COORDINADOR GENERAL DE LA UNIDAD Policy development and Ejecución RESPONSABLE IBRD / 85940 Posterior Individual Direct 260,668.61 0.00 2017-11-23 2017-11-23 2017-11-24 2017-12-01 2021-10-29 institutional strengthening pendiente EJECUTORA DEL PROYECTO 2 (UREP/PRESEM) SENER-DGESE-CF-SD-2016- Policy development and Selección directa 01 / AUDITORIA DEL IBRD / 85940 Posterior Direct 100,000.00 0.00 Cancelado 2017-02-15 2017-02-15 2017-03-09 2017-06-07 institutional strengthening de consultores PROYECTO SENER-DGESE-CI-3CV-2018- 02 / EJECUTIVO DE ADQUISICIONES DE LA Policy development and Ejecución UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 127,326.24 0.00 2018-02-23 2018-02-28 2018-03-21 2018-04-25 2021-10-31 institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-CD-2018- Policy development and Selección directa Ejecución IBRD / 85940 Posterior Direct 180,968.32 0.00 2018-06-27 2018-06-27 2018-07-02 2021-10-29 01 / GESTOR MUNICIPAL institutional strengthening de consultores pendiente SENER-DGESE-CI-3CV-2016- 12-30-06-2018 / GESTOR Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 271,446.48 0.00 2016-10-21 2016-10-22 2016-10-23 2017-01-02 2018-06-30 MUNICIPAL REGION institutional strengthening pendiente NORTE SENER-DGESE-CI-3CV-2018- 01 / COORDINADOR GENERAL DE LA UNIDAD Policy development and RESPONSABLE IBRD / 85940 Posterior Individual Limited 260,668.61 0.00 En ejecución 2018-02-28 2018-03-05 2018-03-26 2018-04-30 2021-10-31 institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEM) Page 7 SENER-DGESE-CI-3CV-2018- 03 / COORDINADOR TECNICO DE LA UNIDAD Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 119,415.00 0.00 2018-08-08 2018-08-13 2018-08-23 2018-09-10 2021-10-31 RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP) SENER-DGESE-CI-3CV-2019- 03 / EJECUTIVO DE ADQUISICIONES DE LA Policy development and Ejecución UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 66,081.96 0.00 2019-12-27 2019-12-27 2020-01-17 2020-02-21 2021-10-31 institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEMEH) SENER-DGESE-CI-3CV-2019- 01 / COORDINADOR TECNICO DE LA UNIDAD Policy development and Ejecución RESPONSABLE IBRD / 85940 Posterior Individual Limited 66,081.96 0.00 2019-12-27 2020-01-01 2020-01-22 2020-02-26 2021-10-31 institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEMEH) Page 8