PROCUREMENT PLAN (Textual Part) Project information: Country: Afghanistan Project name: Citizens' Charter Afghanistan Project Project ID: P160567 Project Implementation agency: MRRD Date of the Procurement Plan: July 9, 2017 Period covered by this Procurement Plan: Only three packages provided not the full procurement plan. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the procurement documents agreed by the bank will be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Law of the Islamic Republic of Afghanistan dated 27/06/13965 (September 17, 2016) published in the Official Gazette No.1223, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions Agreed Procedures for National Competitive Bidding: I. Standard bidding documents approved by the Association shall be used. II. Invitations to bid shall be advertised in at least one (1) widely circulated national daily newspaper and bidding documents shall be made available to prospective bidders, at least twenty-eight (28) days prior to the deadline for the submission of bids. III. Bids shall not be invited on the basis of percentage premium or discount over the estimated cost. IV. Bidding documents shall be made available, by mail or in person, to all who are willing to pay the required fee. V. Foreign bidders shall not be precluded from bidding. VI. Qualification criteria (in case pre-qualifications were not carried out) shall be stated on the bidding documents, and if a registration process is required, a foreign firm determined to be the lowest evaluated bidder shall be given reasonable opportunity of registering, without any hindrance. VII. Bidders may deliver bids, at their option, either in person or by courier service or by mail. VIII. All bidders shall provide bid security or a bid security declaration form as indicated in the bidding documents. A bidder’s bid security or the declaration form shall apply only to a specific bid. IX. Bids shall be opened in public in one place preferably immediately, but no later than one hour, after the deadline for submission of bids. X. Evaluation of bids shall be made in strict adherence to the criteria disclosed in the bidding documents, in a format, and within the specified period, agreed with the Association. XI. Bids shall not be rejected merely on the basis of a comparison with an official estimate without the prior concurrence of the Association. XII. Split award or lottery in award of contracts shall not be carried out. When two (2) or more bidders quote the same price, an investigation shall be made to determine any evidence of collusion, following which: (A) if collusion is determined, the parties involved shall be disqualified and the award shall then be made to the next lowest evaluated and qualified bidder; and (B) if no evidence of collusion can be confirmed, then fresh bids shall be invited after receiving the concurrence of the Association; XIII. Contracts shall be awarded to the lowest evaluated bidders within the initial period of bid validity so that extensions are not necessary. Extension of bid validity may be sought only under exceptional circumstances. XIV. Extension of bid validity shall not be allowed without the prior concurrence of the Association (A) for the first request for extension if it is longer than four (4) weeks, and (B) for all subsequent requests for extensions irrespective of the period in case of prior review. XV. Negotiations shall not be allowed with the lowest evaluated or any other bidders. XVI. Re-bidding shall not be carried out without the Association’s prior concurrence in case of prior review; and XVII. All contractors or suppliers shall provide performance security as indicated in the contract documents. A contractor’s or a supplier’s performance security shall apply to a specific contract under which it was furnished. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; NA Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; NA Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. Procurement for CDC will be conducted in line with the agreed manual prepared by the project and has been agreed by the bank. Also the Procurement in Situations of Urgent Need of Assistance or Capacity Constraints apply for the project. PROCUREMENT Afghanistan : Citizens' Charter Afghanistan Project PLAN General Information Country: Afghanistan Bank’s Approval Date of the Original Procurement Plan: 2016-08-25 2021-01-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160567 GPN Date: Project Name: Citizens' Charter Afghanistan Project Loan / Credit No: / , TF / A3827, IDA / D1390 Ministry of Rural Rehablitation Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CCAP-I/MRRD/WR-096 / 4. Project Implementation Request for Single Stage - One 2019-04- IDA / D1390 Post Open - National 9,500.00 9,954.43 Signed 2018-08-25 2018-10-20 2018-12-08 Deep Well and Management Quotations Envelope 18 CCAP-I/MRRD/WR-097 / One 4. Project Implementation Request for Single Stage - One 2019-06- IDA / D1390 Post Open - National 70,000.00 0.00 Canceled 2018-10-20 2018-12-15 Floor 3D Panel Building and Management Quotations Envelope 13 MRRD/CCAP/WR/194 / One 4. Project Implementation Request for Single Stage - One 2020-02- IDA / D1390 Post Open - National 70,000.00 84,609.19 Signed 2019-06-25 2019-09-04 2019-08-20 2020-01-04 Floor 3D Panel Building and Management Quotations Envelope 16 MRRD/CCAP/WR/183 / Missing components of 4. Project Implementation Request for Single Stage - One 2020-02- Takhar, Badakhshan, Kunduz, IDA / D1390 Post Open - National 21,900.00 22,140.85 Signed 2019-06-25 2019-09-07 2019-08-20 2019-12-05 and Management Quotations Envelope 16 and Baghlan of the Administrative Buildings MRRD/CCAP/WR/184 / Missing components of 4. Project Implementation Request for Single Stage - One 2020-02- IDA / D1390 Post Open - National 51,500.00 53,527.02 Signed 2019-06-25 2019-09-07 2019-08-20 2020-01-15 Nuristan Province of the and Management Quotations Envelope 16 Administrative Building MRRD/CCAP/WR/185 / Missing components of 4. Project Implementation Request for Single Stage - One 2020-02- Laghman, and Kunar IDA / D1390 Post Open - National 44,000.00 26,902.50 Signed 2019-06-25 2019-09-07 2019-08-20 2019-12-05 and Management Quotations Envelope 16 Provinces of the Administrative Buildings MRRD/CCAP/WR/186 / Missing components of 4. Project Implementation Request for Single Stage - One 2020-02- IDA / D1390 Post Open - National 8,000.00 7,795.58 Signed 2019-06-25 2019-09-07 2019-08-20 2019-12-05 Panjshir Province of the and Management Quotations Envelope 16 Administrative Building MRRD/CCAP/WR/189 / Missing components of 4. Project Implementation Request for Single Stage - One 2020-02- Jawzjan, Balkh, and Samangan IDA / D1390 Post Open - National 26,000.00 21,405.64 Signed 2019-06-25 2019-09-07 2019-08-20 2019-12-05 and Management Quotations Envelope 16 Provinces of the Administrative Buildings MRRD/CCAP/WR/190 / Missing components of Uruzgan, Helmand, Kandahar, 4. Project Implementation Request for Single Stage - One 2020-02- IDA / D1390 Post Open - National 30,000.00 35,826.78 Signed 2019-06-25 2019-09-07 2019-08-20 2019-12-10 Nimroz, and Zabul Provinces and Management Quotations Envelope 16 of the Administrative Buildings MRRD/CCAP/WR/188 / Missing components of 4. Project Implementation Request for Single Stage - One 2020-02- Bamyan, and Ghazni Provinces IDA / D1390 Post Open - National 16,000.00 0.00 Canceled 2019-06-25 2019-09-07 2019-08-20 and Management Quotations Envelope 16 of the Administrative Buildings MRRD/CCAP/WR/188-2 / Missing components of Under 4. Project Implementation Request for Single Stage - One 2020-12- Bamyan, and Ghazni Provinces IDA / D1390 Post Open - National 16,000.00 17,452.86 Implementat 2020-04-16 2020-06-11 and Management Quotations Envelope 08 of the Administrative ion Buildings MRRD/CCAP/WR/187 / Missing components of Logar, 4. Project Implementation Request for Single Stage - One 2020-02- Paktya, Khost, and Paktika IDA / D1390 Post Open - National 36,000.00 0.00 Canceled 2019-06-25 2019-09-07 2019-08-20 and Management Quotations Envelope 16 Provinces of the Administrative Buildings MRRD/CCAP/WR/187-2 / Missing components of Logar, Pending 4. Project Implementation Request for Single Stage - One 2020-12- Paktya, Khost, and Paktika IDA / D1390 Post Open - National 50,000.00 0.00 Implementat 2020-04-16 2020-06-11 and Management Quotations Envelope 08 Provinces of the ion Administrative Buildings MRRD/CCAP/WR/167 / Canal Joint Project of 16 CDCs, Single Stage - One 2020-05- IDA / D1390 1. Service Standards Grants Post Request for Bids Open - National 590,000.00 0.00 Canceled 2019-08-01 2019-10-19 2019-08-06 2019-10-22 2019-09-17 2019-11-18 2019-10-17 2019-11-21 Herat Province, Zinda Jan Envelope 19 District MRRD/CCAP/WR/257 / Pending 4. Project Implementation Request for Single Stage - One 2021-06- Repairing of the foot path of IDA / D1390 Post Limited 25,400.00 0.00 Implementat 2020-11-06 2021-01-01 and Management Quotations Envelope 30 CCAP Both Buildings ion MRRD/CCAP/WR/295 / Joint Pending Project Water Supply Joint Single Stage - One 2022-01- IDA / D1390 1. Service Standards Grants Post Request for Bids Open - National 202,000.00 0.00 Implementat 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 Project Bagrami District Kabul Envelope 06 ion Province MRRD/CCAP/WR/296 / Pending Kakraks’ Joint Project of Canal Single Stage - One 2022-01- IDA / D1390 1. Service Standards Grants Post Request for Bids Open - National 202,000.00 0.00 Implementat 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 Rehabilitation and Envelope 06 ion Construction of Weir GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CCEP/MRRD/GDS/GDS-7 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 42,000.00 22,233.07 Signed 2016-11-27 2017-01-22 2017-11-30 2017-07-21 Communication Equipment and Management Quotations Envelope CCEP-I/MRRD/GDS/GDS-1 / 4. Project Implementation Single Stage - One / Post Request for Bids Open - National 578,236.00 0.00 Canceled 2016-11-01 2016-11-08 2016-11-06 2016-12-18 2017-01-17 2017-02-21 2017-08-20 Office & IT equipment and Management Envelope CCAP/MRRD/GD-28 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 48,000.00 29,913.74 Signed 2017-05-20 2017-07-15 2017-08-26 2018-07-14 Software licensing and Management Quotations Envelope CCAP-I/MRRD/GDS-2 / 4. Project Implementation Single Stage - One TF / A3827 Post Request for Bids Open - National 120,000.00 87,185.43 Signed 2017-08-25 2017-08-26 2017-08-30 2017-11-08 2017-10-11 2017-09-25 2017-11-10 2017-10-23 2017-12-15 2017-11-29 2018-06-13 Office Furniture and Management Envelope CCEP-I/MRRD/GDS/GDS-2 / 4. Project Implementation Single Stage - One / Prior Request for Bids Open - International 308,000.00 0.00 Canceled 2016-11-14 2017-02-06 2016-11-19 2016-12-31 2017-01-30 2017-03-06 2017-09-02 Office furniture and Management Envelope CCEP/MRRD/GDS/GDS-4 / IT 4. Project Implementation Single Stage - One Equipment for HQ, Province IDA / D1390 Post Request for Bids Open - International 280,000.00 196,140.43 Signed 2017-08-25 2017-11-01 2017-08-30 2017-11-01 2017-10-11 2017-12-17 2017-11-10 2017-12-30 2017-12-15 2018-02-07 2018-06-13 and Management Envelope and Districts CCEP/MRRD/GDS/GDS-5 / Generator: 5KW for 22 Under 4. Project Implementation Single Stage - One districts, 8.6 KVA for 14 IDA / D1390 Post Request for Bids Open - International 250,000.00 0.00 Implementati 2017-09-20 2017-10-31 2017-09-25 2017-10-31 2017-11-06 2017-12-06 2018-01-10 2018-07-09 and Management Envelope Districts and on 20KVA for 3 Provinces MRRD/CCAP/GD/029 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 48,000.00 38,733.30 Signed 2017-08-25 2017-10-20 2017-09-18 2018-04-18 Engineering Equipment and Management Quotations Envelope CCEP-I/MRRD/GDS/GDS-6 / 4. Project Implementation Single Stage - One IDA / D1390 Prior Request for Bids Open - International 312,500.00 0.00 Canceled 2017-05-10 2017-05-15 2017-06-26 2017-07-26 2017-08-30 2018-02-26 Engineering Equipment and Management Envelope MRRD/CCAP/GD-80 / A-3 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 4,000.00 2,359.14 Signed 2018-04-08 2018-06-03 2018-04-21 2018-11-30 Printers for Schools Project and Management Quotations Envelope CCEP/MRRD/GDS/GDS-8 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 44,000.00 13,531.73 Signed 2018-05-25 2018-07-20 2018-07-31 2019-01-16 Electrical Equipment and Management Quotations Envelope CCAP-I/MRRD/GDS - 101 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 40,000.00 26,257.66 Signed 2018-05-31 2018-07-26 2018-07-04 2019-01-22 Office Furniture and Management Quotations Envelope Under CCAP-I/MRRD/GDS - 102 / 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - International 405,000.00 352,596.00 Implementati 2018-05-20 2018-07-10 2018-05-25 2018-07-11 2018-07-06 2018-08-27 2018-08-05 2018-09-15 2018-09-09 2019-03-08 IT Equipment and Management Envelope on CCAP-I/MRRD/GDS - 104 / Under Generator: 25KW for 3 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - International 425,000.00 374,299.79 Implementati 2018-05-20 2018-06-25 2018-05-25 2018-06-27 2018-07-06 2018-08-07 2018-08-05 2018-09-12 2018-09-09 2019-03-08 Provincial offices and 7.5 KW and Management Envelope on for 47 District offices CCAP-I/MRRD/GD-110 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 6,000.00 6,365.73 Signed 2018-05-25 2018-07-20 2018-06-23 2019-01-16 Conex Containers and Management Quotations Envelope CCAP-I/MRRD/GD-111 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 5,000.00 784.94 Signed 2018-06-01 2018-07-27 2018-09-10 2019-01-23 Security Equipment and Management Quotations Envelope CCAP-I/MRRD/GD-095 / 4. Project Implementation Request for Single Stage - One Armored doors and windows IDA / D1390 Post Open - National 48,500.00 33,895.90 Signed 2018-08-20 2018-10-15 2018-10-14 2019-04-13 and Management Quotations Envelope for CCAP two Buildings MRRD/CCAP/GD/029-A / Engineering Equipment - 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - National 170,688.00 0.00 Canceled 2018-01-15 2018-03-12 2018-01-20 2018-03-27 2018-03-03 2018-04-02 2018-05-07 2018-11-03 General Technical Tools for and Management Envelope All Sectors MRRD/CCAP/GD/029-B / 4. Project Implementation Request for Single Stage - One Engineering Equipment - IDA / D1390 Post Open - National 7,735.00 0.00 Canceled 2018-01-20 2018-03-17 2018-09-13 and Management Quotations Envelope Power Technical Tools MRRD/CCAP/GD/029-C / Engineering Equipment - 4. Project Implementation IDA / D1390 Post Direct Selection Direct 147,052.00 0.00 Canceled 2018-01-15 2018-01-20 2018-02-24 2018-08-23 Water Quality Test + Power and Management Equipments CCAP-I/MRRD/GD-107 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 40,000.00 7,299.99 Signed 2018-11-04 2018-12-30 2018-12-26 2019-06-28 Software licensing and Management Quotations Envelope MRRD/CCAP/GD/117 / 4. Project Implementation Engineering Equipment - 3 - IDA / D1390 Post Direct Selection Direct 31,500.00 0.00 Canceled 2018-09-15 2018-09-20 2018-10-25 2019-04-23 and Management SEAWARD MRRD/CCAP/GD/116 / 4. Project Implementation Engineering Equipment - 2- IDA / D1390 Post Direct Selection Direct 46,000.00 0.00 Canceled 2018-09-15 2018-09-20 2018-10-25 2019-04-23 and Management Bep Edu World MRRD/CCAP/GD/119 / 4. Project Implementation Engineering Equipment - 5 - IDA / D1390 Post Direct Selection Direct 63,000.00 0.00 Canceled 2018-09-15 2018-09-20 2018-10-25 2019-04-23 and Management Wagtech MRRD/CCAP/GD/120 / 4. Project Implementation Engineering Equipment - 6 - IDA / D1390 Post Direct Selection Direct 40,000.00 0.00 Canceled 2018-09-15 2018-09-20 2018-10-25 2019-04-23 and Management Palintest MRRD/CCAP/GD/121 / 4. Project Implementation Engineering Equipment - 7 - IDA / D1390 Post Direct Selection Direct 8,500.00 0.00 Canceled 2018-09-15 2018-09-20 2018-10-25 2019-04-23 and Management WTW MRRD/CCAP/GD/134 / 4. Project Implementation Request for Single Stage - One Container 20 Feet for Baghlan IDA / D1390 Post Open - National 2,500.00 1,273.56 Signed 2019-01-25 2019-03-22 2019-06-30 2019-09-18 and Management Quotations Envelope Province MRRD/CCAP/GD/118 / Engineering Equipment - 4 - 4. Project Implementation IDA / D1390 Post Direct Selection Direct 70,000.00 0.00 Canceled 2019-03-05 2019-03-10 2019-04-14 2019-10-11 Standard Supply Agencies, and Management Pakistan Page 2 MRRD/CCAP/GD/133 / Office 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 48,000.00 31,979.12 Signed 2019-03-07 2019-05-02 2019-06-08 2019-10-29 Furniture for the year 2019 and Management Quotations Envelope MRRD/CCAP/GD/135 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 5,000.00 2,491.93 Signed 2019-03-07 2019-05-02 2019-12-01 2019-10-29 Heaters for HQ and Provinces and Management Quotations Envelope MRRD/CCAP/GD/136 / Media 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 17,000.00 16,458.11 Signed 2019-03-07 2019-05-02 2019-08-15 2019-10-29 Equipment and Management Quotations Envelope MRRD/CCAP/GD/137 / 4. Project Implementation Request for Single Stage - One Security Equipments for Farah IDA / D1390 Post Open - National 3,000.00 2,451.60 Signed 2019-03-10 2019-05-05 2019-06-29 2019-11-01 and Management Quotations Envelope Province CCAP-I/MRRD/GDS -150 / IT 4. Project Implementation Single Stage - One Equipment for HQ and field IDA / D1390 Post Request for Bids Open - International 405,000.00 401,536.58 Signed 2019-03-05 2019-07-07 2019-03-10 2019-07-08 2019-04-21 2019-08-27 2019-05-21 2019-12-10 2019-06-25 2019-12-30 2019-12-22 and Management Envelope offices MRRD/CCAP/GD/115 / 4. Project Implementation Engineering Equipment - 1- IDA / D1390 Post Direct Selection Direct 120,000.00 0.00 Canceled 2019-03-05 2019-03-10 2019-04-14 2019-10-11 and Management Hilti Germany CCAP-I/MRRD/GDS-106 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Open - National 15,000.00 0.00 Canceled 2019-03-15 2019-05-10 2019-11-06 Telephone for complaining and Management Quotations Envelope MRRD/CCAP/GD/174 / 4. Project Implementation Request for Single Stage - One Electrical Equipment for HQ IDA / D1390 Post Limited 41,800.00 20,720.41 Signed 2019-06-30 2020-09-11 2019-08-25 2020-07-05 2020-02-21 and Management Quotations Envelope and Provincial Offices MRRD/CCAP/GD/161 / IT 4. Project Implementation Single Stage - One Equipment for Provincial, IDA / D1390 Post Request for Bids Open - International 317,010.00 292,898.01 Signed 2019-07-20 2019-08-26 2019-07-25 2019-08-27 2019-09-05 2019-10-08 2019-10-05 2019-12-09 2019-11-09 2019-12-11 2020-05-07 and Management Envelope District and HQ offices MRRD/CCAP/GD/168 / 4. Project Implementation Single Stage - One Engineering Equipment for IDA / D1390 Post Request for Bids Open - National 192,875.00 231,839.70 Signed 2019-07-17 2020-02-05 2019-07-22 2019-12-11 2019-09-02 2020-03-04 2019-10-02 2020-05-06 2019-11-06 2020-05-19 2020-05-04 and Management Envelope Provincial and District Offices MRRD/CCAP/GD/182 / Office 4. Project Implementation Single Stage - One Furniture for Provincial and IDA / D1390 Post Request for Bids Open - International 332,070.00 197,245.18 Signed 2019-07-15 2019-08-26 2019-07-20 2019-08-26 2019-08-31 2019-10-09 2019-09-30 2019-12-29 2019-11-04 2020-03-08 2020-05-02 and Management Envelope District Offices MRRD/CCAP/GD/193 / Call 4. Project Implementation Center for Complain Handling IDA / D1390 Post Direct Selection Direct 9,000.00 0.00 Canceled 2019-06-20 2019-06-25 2019-07-30 2020-01-26 and Management from AWCC MRRD/CCAP/GD/249 / Office 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Limited 5,020.00 0.00 Canceled 2020-06-20 2020-08-15 2021-02-11 Equipment for Herat Region and Management Quotations Envelope MRRD/CCAP/GD/247 / Office 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Limited 5,560.00 0.00 Canceled 2020-06-20 2020-08-15 2021-02-11 Equipment for Kunduz Region and Management Quotations Envelope MRRD/CCAP/GD/248 / Office 4. Project Implementation Request for Single Stage - One Equipment for Kandahar IDA / D1390 Post Limited 4,250.00 0.00 Canceled 2020-06-20 2020-08-15 2021-02-11 and Management Quotations Envelope Region MRRD/CCAP/GD/250 / Office 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Limited 2,760.00 0.00 Canceled 2020-06-20 2020-08-15 2021-02-11 Equipment for HQ and Management Quotations Envelope MRRD/CCAP/GD/246 / Office 4. Project Implementation Request for Single Stage - One Equipment for Nangarhar IDA / D1390 Post Limited 4,090.00 0.00 Canceled 2020-06-20 2020-08-15 2021-02-11 and Management Quotations Envelope Region MRRD/CCAP/GD/245 / Office 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Limited 10,300.00 0.00 Canceled 2020-06-20 2020-08-15 2021-02-11 Equipment for Kabul Region and Management Quotations Envelope MRRD/CCAP/GD/244 / Office 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Limited 2,600.00 0.00 Canceled 2020-06-20 2020-08-15 2021-02-11 Equipment for Balkh Region and Management Quotations Envelope MRRD/CCAP/GD/175 / 4. Project Implementation Request for Single Stage - One Security System and Cameras IDA / D1390 Post Limited 49,000.00 33,330.42 Signed 2020-11-30 2020-07-04 2021-01-25 2020-08-06 2021-07-24 and Management Quotations Envelope for HQ and Provincial Offices MRRD/CCAP/GD/159 / Heavy Pending 4. Project Implementation Request for Single Stage - One Duty Server and Hard Disks IDA / D1390 Post Limited 20,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 and Management Quotations Envelope for Financial Documents on MRRD/CCAP/GD/256 / Pending 4. Project Implementation Request for Single Stage - One Equipment for the MRRD Rural IDA / D1390 Post Limited 10,200.00 0.00 Implementati 2020-11-30 2021-01-25 2021-07-24 and Management Quotations Envelope Data Center on Pending MRRD/CCAP/GD/279 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Limited 15,000.00 0.00 Implementati 2021-01-04 2021-03-01 2021-08-28 Container for HQ Office and Management Quotations Envelope on MRRD/CCAP/GD/292 / IT Pending 4. Project Implementation Single Stage - One Equipment for HQ and Field IDA / D1390 Post Request for Bids Open - International 388,340.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 and Management Envelope Office - The year 2021 on MRRD/CCAP/GD/243 / IT 4. Project Implementation Single Stage - One Equipment for HQ and Field IDA / D1390 Post Request for Bids Open - International 388,340.00 0.00 Canceled 2020-07-01 2020-07-29 2020-07-06 2020-08-06 2020-08-17 2020-09-13 2020-09-16 2020-10-21 2021-04-19 and Management Envelope Office - The year 2020 MRRD/CCAP/GD/293 / Pending 4. Project Implementation Request for Single Stage - One Conex with Instalation for IDA / D1390 Post Limited 18,000.00 0.00 Implementati 2021-03-25 2021-05-20 2021-11-16 and Management Quotations Envelope Exam Center on MRRD/CCAP/GD/297 / Pending 4. Project Implementation Single Stage - One Engineering Equipment for IDA / D1390 Post Request for Bids Open - National 56,055.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 and Management Envelope Field Offices on Pending MRRD/CCAP/GD/298 / 4. Project Implementation Request for Single Stage - One IDA / D1390 Post Limited 2,000.00 0.00 Implementati 2021-03-25 2021-05-20 2021-11-16 Container for Baghlan PMU and Management Quotations Envelope on Page 3 MRRD/CCAP/GD/299 / Office Pending 4. Project Implementation Single Stage - One and Electrical Equipment for IDA / D1390 Post Request for Bids Open - National 90,310.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 and Management Envelope field offices on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CCAP/MRRD/SR-1 / One year 4. Project Implementation Single Stage - One Internet Services for HQ, IDA / D1390 Post Request for Bids Open - International 700,000.00 462,455.04 Signed 2017-04-22 2017-04-25 2017-04-29 2017-06-10 2017-06-12 2017-06-10 2017-06-18 2017-06-28 2017-06-29 2018-06-30 and Management Envelope Provinces and Districts CCAP/MRRD/SR-3 / One year 4. Project Implementation Internet Services of Fiber IDA / D1390 Post Direct Selection Direct 50,000.00 30,704.14 Signed 2017-06-01 2017-06-17 2017-06-06 2017-06-19 2017-07-01 2017-06-26 2018-06-30 and Management Optic with Afghan Telecom CCAP/MRRD/SR-27 / 3G 4. Project Implementation Internet Services for Senior IDA / D1390 Post Direct Selection Direct 6,000.00 0.00 Canceled 2017-04-22 2017-04-24 2017-05-09 2018-05-08 and Management Staff with AWCC CCAP-I/MRRD/SR-108 / One 4. Project Implementation Single Stage - One year Internet Services for HQ, IDA / D1390 Post Request for Bids Open - International 560,000.00 343,219.28 Signed 2018-05-15 2018-06-20 2018-05-20 2018-06-24 2018-07-01 2018-08-01 2018-07-31 2018-08-16 2018-09-04 2018-09-12 2019-03-03 and Management Envelope Provinces and Districts CCAP-I/MRRD/SR-109 / One 4. Project Implementation year Internet Services of Fiber IDA / D1390 Post Direct Selection Direct 50,000.00 28,467.87 Signed 2018-06-16 2018-06-21 2018-07-26 2018-06-25 2019-01-22 and Management Optic with Afghan Telecom MRRD/CCAP/SR/191 / 4. Project Implementation Internet for HQ through Fiber IDA / D1390 Post Direct Selection Direct 50,000.00 27,584.45 Signed 2019-07-01 2019-06-13 2019-07-06 2019-06-22 2019-08-10 2019-06-25 2020-02-06 and Management from Afghan Telecom MRRD/CCAP/SR/192 / 4. Project Implementation Single Stage - One Internet Services for Provincial IDA / D1390 Post Request for Bids Open - International 421,920.00 188,569.82 Signed 2019-08-24 2019-09-15 2019-08-29 2019-09-15 2019-10-10 2019-10-27 2019-11-09 2019-12-09 2019-12-14 2019-12-30 2020-06-11 and Management Envelope and District offices MRRD/CCAP/SR/160 / Mail Pending 4. Project Implementation Server Hosting with Zoho IDA / D1390 Post Direct Selection Direct 15,000.00 0.00 Implementati 2020-10-20 2020-10-25 2020-11-29 2021-05-28 and Management Company on MRRD/CCAP/SR/255 / One Pending 4. Project Implementation year Internet Services of Fiber IDA / D1390 Post Direct Selection Direct 32,000.00 0.00 Implementati 2020-09-20 2020-09-25 2020-10-30 2021-04-28 and Management Optic with Afghan Telecom on MRRD/CCAP/GD/281 / 4. Project Implementation Single Stage - One Internet Services for Provinces IDA / D1390 Post Request for Bids Open - International 394,480.00 219,431.41 Signed 2020-09-30 2020-10-07 2020-10-05 2020-10-12 2020-11-16 2020-11-18 2020-12-16 2020-11-30 2021-01-20 2020-12-13 2021-07-19 and Management Envelope and District Offices MRRD/CCAP/SR/300 / The Pending hiring of the firm for rental 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - International 256,800.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 vehicles of filed offices - and Management Envelope on Cluster One MRRD/CCAP/SR/301 / The Pending hiring of the firm for rental 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - National 180,240.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 vehicles of filed offices - and Management Envelope on Cluster Two Provinces MRRD/CCAP/SR/302 / The Pending hiring of the firm for rental 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - International 362,480.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 vehicles of filed offices - and Management Envelope on Cluster Three Provinces MRRD/CCAP/SR/303 / The Pending hiring of the firm for rental 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - International 372,900.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 vehicles of filed offices - and Management Envelope on Cluster Four Provinces MRRD/CCAP/SR/304 / The Pending hiring of the firm for rental 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - International 513,600.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 vehicles of filed offices - and Management Envelope on Cluster Five Provinces MRRD/CCAP/SR/305 / The Pending hiring of the firm for rental 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - International 434,640.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 vehicles of filed offices - and Management Envelope on Cluster Six Provinces MRRD/CCAP/SR/306 / The Pending hiring of the firm for rental 4. Project Implementation Single Stage - One IDA / D1390 Post Request for Bids Open - International 392,520.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-06-05 2021-07-10 2022-01-06 vehicles of filed offices - and Management Envelope on Cluster Seven Provinces MRRD/CCAP/GD/280 / Pending Database Hosting Services 4. Project Implementation IDA / D1390 Post Direct Selection Direct 15,000.00 0.00 Implementati 2021-01-20 2021-01-25 2021-03-01 2021-08-28 with Sepia Solution firm based and Management on in the USA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CCEP-I/MRRD/CN/EVAL-2 / 3. M&E, Knowledge Quality And Cost- Under Evaluation: CDC/CCDC/GA / Post Open - International 350,000.00 0.00 2018-01-13 2018-02-03 2018-03-19 2016-11-06 2018-04-16 2018-05-16 2018-06-20 2018-07-25 2019-07-25 Learning Based Selection Implementation study CCEP-I/MRRD/CN/EVAL-6 / 3. M&E, Knowledge Quality And Cost- TF / A3827 Post Open - International 350,000.00 349,948.00 Signed 2018-01-13 2017-03-14 2018-02-03 2017-04-19 2018-03-19 2017-07-04 2018-04-16 2017-08-02 2018-05-16 2017-09-06 2018-06-20 2017-11-21 2018-07-25 2017-12-19 2019-07-25 Study: Conflict & Fragility Learning Based Selection Page 4 CCEP-I/MRRD/CS/FP-14 / Fixed Budget Facilitation Partner - 14 TF / A3827 2. Institution Building Prior Open - International 7,889,000.00 14,162,281.54 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-24 2016-08-28 2016-12-05 2016-09-27 2017-01-26 2016-11-01 2017-04-18 2016-12-06 2017-05-16 2017-12-06 Selection (Khost, Nangarhar, Paktya) CCEP-I/MRRD/CS/FP-13 / Fixed Budget Facilitation Partner - 13 TF / A3827 2. Institution Building Prior Open - International 6,307,750.00 6,307,750.00 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-24 2016-08-28 2016-12-05 2016-09-27 2017-01-26 2016-11-01 2017-03-28 2016-12-06 2017-05-06 2017-12-06 Selection (Ghazni, Paktika) CCEP-I/MRRD/CS/FP-12 / Fixed Budget Facilitation Partner - 12 TF / A3827 2. Institution Building Prior Open - International 5,474,000.00 5,474,000.00 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-14 2016-08-28 2016-11-29 2016-09-27 2017-01-26 2016-11-01 2017-04-02 2016-12-06 2017-05-06 2017-12-06 Selection (Kabul, Logar, Wardak) CCEP-I/MRRD/CS/FP-11 / Fixed Budget Facilitation Partner - 11 TF / A3827 2. Institution Building Prior Open - International 4,887,500.00 4,850,731.00 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-11 2016-08-28 2016-11-30 2016-09-27 2017-01-26 2016-11-01 2017-04-19 2016-12-06 2017-05-16 2017-12-06 Selection (Nuristan, Kunar, Laghman) CCEP-I/MRRD/CS/FP-10 / Fixed Budget Facilitation Partner - 10 TF / A3827 2. Institution Building Prior Open - International 3,300,500.00 3,300,500.00 Under Review 2016-06-24 2016-07-04 2016-07-31 2016-10-14 2016-08-28 2016-11-30 2016-09-27 2017-01-26 2016-11-01 2017-04-10 2016-12-06 2017-05-06 2017-12-06 Selection (Kapisa, Panjshir, Parwan) CCEP-I/MRRD/CS/FP-9 / Fixed Budget Facilitation Partner - 9 TF / A3827 2. Institution Building Prior Open - International 6,859,750.00 6,859,750.00 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-24 2016-08-28 2016-12-05 2016-09-27 2017-01-26 2016-11-01 2017-09-12 2016-12-06 2017-11-18 2017-12-06 Selection (Takhar, Badakshan) CCEP-I/MRRD/CS/FP-8 / Fixed Budget Facilitation Partner - 8 TF / A3827 2. Institution Building Prior Open - International 4,881,750.00 4,881,750.00 Signed 2016-06-24 2016-12-03 2016-07-04 2016-07-31 2016-10-11 2016-08-28 2016-11-29 2016-09-27 2017-01-26 2016-11-01 2017-04-05 2016-12-06 2017-05-06 2017-12-06 Selection (Baghlan, Kunduz, Samangan) CCEP-I/MRRD/CS/FP-7 / Fixed Budget Facilitation Partner - 7 TF / A3827 2. Institution Building Prior Open - International 3,450,000.00 3,450,000.00 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-11 2016-08-28 2016-11-29 2016-09-27 2017-01-26 2016-11-01 2017-04-10 2016-12-06 2017-05-06 2017-12-06 Selection (Bamyan, Daikundi) CCEP-I/MRRD/CS/FP-6 / Fixed Budget Facilitation Partner - 6 (Balkh, TF / A3827 2. Institution Building Prior Open - International 4,473,500.00 4,473,500.00 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-11 2016-08-28 2016-11-29 2016-09-27 2017-01-26 2016-11-01 2017-05-08 2016-12-06 2017-05-29 2017-12-06 Selection Jawzjan, Sarepul) CCEP-I/MRRD/CS/FP-5 / Fixed Budget Facilitation Partner - 5 TF / A3827 2. Institution Building Prior Open - International 3,277,500.00 4,145,750.00 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-13 2016-08-28 2016-11-29 2016-09-27 2017-01-26 2016-11-01 2017-03-28 2016-12-06 2017-05-06 2017-12-06 Selection (Badghis, Faryab) CCEP-I/MRRD/CS/FP-4 / Fixed Budget Facilitation Partner - 4 (Ghor, TF / A3827 2. Institution Building Prior Open - International 6,762,000.00 6,762,000.00 Signed 2016-06-24 2016-07-04 2016-07-31 2016-10-24 2016-08-28 2016-12-05 2016-09-27 2017-01-26 2016-11-01 2017-03-28 2016-12-06 2017-05-06 2017-12-06 Selection Hirat) CCEP-I/MRRD/CS/FP-3 / Fixed Budget Facilitation Partner - 3 TF / A3827 2. Institution Building Prior Open - International 3,070,500.00 3,070,500.00 Under Review 2016-06-24 2016-07-04 2016-07-31 2016-10-11 2016-08-28 2016-11-29 2016-09-27 2017-01-26 2016-11-01 2017-03-28 2016-12-06 2017-05-06 2017-12-06 Selection (Nimroz, Farah) CCEP-I/MRRD/CS/FP-2 / Fixed Budget Facilitation Partner - 2 IDA / D1390 2. Institution Building Prior Open - International 6,739,000.00 5,640,750.00 Signed 2016-08-08 2016-08-29 2016-10-12 2016-10-24 2016-11-09 2016-12-05 2016-12-09 2017-05-07 2017-01-13 2017-06-26 2017-02-17 2017-07-24 2018-02-17 Selection (Kandahar, Helmand) CCEP-I/MRRD/CS/FP-1 / Fixed Budget Facilitation Partner - 1 TF / A3827 2. Institution Building Prior Open - International 4,304,420.00 4,210,584.66 Signed 2016-08-08 2016-08-29 2016-10-12 2016-10-11 2016-11-09 2016-11-29 2016-12-09 2017-01-26 2017-01-13 2017-04-17 2017-02-17 2017-05-16 2018-02-17 Selection (Uruzgan, Zabul) CCEP-I/MRRD/CN/EVAL-3 / 3. M&E, Knowledge Quality And Cost- IDA / D1390 Post Open - International 150,000.00 152,425.57 Signed 2018-01-13 2019-06-03 2018-02-03 2019-06-29 2018-03-19 2019-10-08 2018-04-16 2019-11-06 2018-05-16 2020-06-13 2018-06-20 2020-06-13 2018-07-25 2020-07-29 2019-07-25 Study: Gender Learning Based Selection CCAP/MRRD/CN/EVAL-9/SIG 3. M&E, Knowledge Quality And Cost- IDA / D1390 Post Open - International 150,000.00 0.00 Canceled 2019-07-27 2019-06-29 2019-08-17 2019-09-30 2019-10-28 2019-11-27 2020-01-01 2020-02-05 2021-02-04 / Evaluation of SIG Learning Based Selection CCAP/MRRD/CN/09 / Social Consultant 3. M&E, Knowledge Inclusion Grant (SIG) and IDA / D1390 Post Qualification Open - International 150,000.00 0.00 Under Review 2020-04-11 2020-03-24 2020-05-02 2020-06-15 2020-07-15 2020-08-19 2021-02-15 Learning Grain Banks Study Selection CCEP-I/MRRD/CN/EVAL-8 / 3. M&E, Knowledge Quality And Cost- Pending IDA / D1390 Prior Open - International 1,000,000.00 0.00 2020-10-10 2020-10-31 2020-12-14 2021-01-11 2021-02-10 2021-03-17 2021-04-21 2022-04-21 Evaluation: Final Impact Learning Based Selection Implementation Consultant CCAP/MRRD/CN/19 / MCCG 3. M&E, Knowledge Pending IDA / D1390 Post Qualification Open - International 150,000.00 0.00 2021-01-05 2021-01-26 2021-03-11 2021-04-10 2021-05-15 2021-11-11 Study Learning Implementation Selection CCEP-I/MRRD/CN/EVAL-1 / Evaluation: Improved service 3. M&E, Knowledge Quality And Cost- Pending IDA / D1390 Prior Open - International 1,000,000.00 0.00 2021-01-05 2021-01-26 2021-03-11 2021-04-08 2021-05-08 2021-06-12 2021-07-17 2022-07-17 delivery - CDC/CCDC/GA Learning Based Selection Implementation study CCEP-I/MRRD/CN/EVAL-4 / 3. M&E, Knowledge Quality And Cost- Pending External: Technical quality of IDA / D1390 Post Open - International 200,000.00 0.00 2021-01-05 2021-01-26 2021-03-11 2021-04-08 2021-05-08 2021-06-12 2021-07-17 2022-07-17 Learning Based Selection Implementation infrastructure CCEP-I/MRRD/CN/EVAL-7 / 3. M&E, Knowledge Quality And Cost- Pending IDA / D1390 Post Open - International 250,000.00 0.00 2021-01-05 2021-01-26 2021-03-11 2021-04-08 2021-05-08 2021-06-12 2021-07-17 2022-07-17 Evaluation: Mid Term Learning Based Selection Implementation CCEP-I/MRRD/CN/EVAL-5 / 3. M&E, Knowledge Quality And Cost- Pending Study: Service Delivery & State IDA / D1390 Post Open - International 400,000.00 0.00 2021-01-05 2021-01-26 2021-03-11 2021-04-08 2021-05-08 2021-06-12 2021-07-17 2022-07-17 Learning Based Selection Implementation Legitimacy INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CCEP-I/MRRD/CN/IC-4 / Individual 4. Project Implementation Under Operations Advisor / Prior Consultant Direct 540,000.00 0.00 2016-09-25 2016-12-22 2016-10-05 2016-10-26 2016-11-30 2019-11-30 and Management Implementation (International) Selection CCEP-I/MRRD/CN/IC-3 / Individual 4. Project Implementation Under Program & Policy Advisor / Prior Consultant Direct 540,000.00 0.00 2016-09-25 2016-12-22 2016-10-05 2016-10-26 2016-11-30 2019-11-30 and Management Implementation (International) Selection Page 5 CCAP-I/MRRD/CS/FP-1-B / Facilitating Partner for the CCAP Additional financing in TF / A3827 2. Institution Building Post Direct Selection Direct 98,000.00 98,500.00 Signed 2017-07-25 2017-08-05 2017-08-04 2017-10-08 2017-08-28 2018-04-06 select rural communities in the provinces of Zabul and Uruzgan CCAP-I/MRRD/CS/FP-2-B / Facilitating Partner for the CCAP Additional financing in IDA / D1390 2. Institution Building Prior Direct Selection Direct 1,006,250.00 1,006,250.00 Signed 2017-07-25 2017-08-04 2017-07-10 2017-10-08 2017-09-25 2018-04-06 select rural communities in the provinces of kandahar and helmand CCAP-I/MRRD/CS/FP-3-B / Facilitating Partner for the CCAP additional financing in TF / A3827 2. Institution Building Post Direct Selection Direct 72,000.00 72,000.00 Signed 2017-07-25 2017-08-05 2017-08-04 2017-10-08 2017-08-28 2018-04-06 select rural communities in the provinces of nimroz and farah CCAP-I/MRRD/CS/FP-8-B / Facilitating Partner for the CCAP additional financing in TF / A3827 2. Institution Building Post Direct Selection Direct 731,250.00 731,250.00 Signed 2017-07-25 2017-08-05 2017-08-04 2017-10-08 2017-09-25 2018-04-06 select rural communities in the province of baghlan, kunduz and samangan CCAP-I/MRRD/CS/FP-9-B / Facilitating Partner for the CCAP additional financing in TF / A3827 2. Institution Building Prior Direct Selection Direct 2,062,500.00 2,062,500.00 Signed 2017-07-25 2017-08-04 2017-10-08 2018-06-13 2018-04-06 select rural communities in the provinces of takhar and badakhshan CCAP-I/MRRD/CS/FP-11-B / Facilitating Partner for the CCAP Additional financing in TF / A3827 2. Institution Building Post Direct Selection Direct 75,000.00 75,000.00 Signed 2017-07-25 2017-08-05 2017-08-04 2017-10-08 2017-08-28 2018-04-06 select rural communities in the provinces of NURISTAN, KUNAR AND LAGHMAN CCAP-I/MRRD/CS/FP-13-B / Facilitating Partner for the CCAP Additional financing in TF / A3827 2. Institution Building Prior Direct Selection Direct 1,131,250.00 1,131,250.00 Signed 2017-07-25 2017-08-04 2017-10-08 2017-09-25 2018-04-06 select rural communities in the provinces of ghazni and paktika CCAP-I/MRRD/CS/FP-14-B / Facilitating Partner for the CCAP Additional financing in TF / A3827 2. Institution Building Prior Direct Selection Direct 2,594,500.00 2,593,770.56 Signed 2017-07-25 2017-08-04 2017-10-08 2017-09-25 2018-04-06 select rural communities in the provinces of khost, nangarhar and paktya CCAP-I/MRRD/CN/-101 / Citizens' Charter "Booster" to 4. Project Implementation IDA / D1390 Post Direct Selection Direct 112,000.00 0.00 Under Review 2018-05-27 2018-05-10 2018-06-06 2018-08-10 2019-02-06 the 2018 Survey of the Afghan and Management People CCEP-I/MRRD/CN/IC-5 / Individual 4. Project Implementation Financial Management Advisor IDA / D1390 Post Consultant Open 210,000.00 168,000.00 Signed 2019-07-27 2019-07-24 2019-09-14 2020-07-08 2019-10-05 2020-07-15 2019-11-09 2020-08-04 2020-05-07 and Management (International) Selection MRRD/CCAP/IC/197 / Individual 4. Project Implementation Program & Policy Advisor IDA / D1390 Post Consultant Open 210,000.00 147,600.00 Signed 2019-07-27 2019-08-06 2019-09-14 2020-06-04 2019-10-05 2020-06-09 2019-11-09 2020-06-15 2021-11-08 and Management (International) Selection CCEP-I/MRRD/CN/IC-1 / Individual 4. Project Implementation Advisor to the Minister's IDA / D1390 Prior Consultant Open 360,000.00 0.00 Canceled 2019-01-09 2019-02-27 2019-03-20 2019-04-24 2021-04-23 and Management Office (International) Selection CCEP-I/MRRD/CN/IC-2 / Individual Advisor to the Deputy 4. Project Implementation IDA / D1390 Prior Consultant Open - National 360,000.00 0.00 Canceled 2018-11-03 2018-12-22 2019-01-12 2019-02-16 2021-02-15 Minister's Office and Management Selection (International) MRRD/CCAP/IC/196 / Individual 4. Project Implementation Operations Advisor IDA / D1390 Post Consultant Open 210,000.00 0.00 Canceled 2019-07-27 2019-07-24 2019-09-14 2019-10-05 2019-11-09 2021-11-08 and Management (International) Selection MRRD/CCAP/IC/195 / Individual 4. Project Implementation International Consultant for IDA / D1390 Post Consultant Open - National 210,000.00 0.00 Canceled 2019-07-27 2019-07-24 2019-09-14 2019-10-05 2019-11-09 2021-11-08 and Management Engineering Division Selection Page 6