PROCUREMENT PLAN (Textual Part) Project information: Niger, Niger, Solar Electricity Access Project (NESAP), P-160170 Project Implementation agency: ANPER and NIGELEC Date of the Procurement Plan: September 14, 2017 Period covered by this Procurement Plan: From July 2017 to December 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable Other Relevant Procurement Information. NA PROCUREMENT Niger : Niger Solar Electricity Access Project (NESAP) PLAN General Information Country: Niger Bank’s Approval Date of the Original Procurement Plan: 2017-09-14 2022-02-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160170 GPN Date: 2018-10-04 Project Name: Niger Solar Electricity Access Project (NESAP) Loan / Credit No: IDA / 60820 A Executing Agency(ies): GENCE NIGERIENNE DE PROMOTION DE L’ELECTRIFICATION EN MILIEU RURAL - ANPER WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned C-20/UEP/NESAP/2018 / Component 4: Single Stage - One 2018-06- Réfection des bureaux au IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 9,000.00 6,756.52 Achevé 2018-05-02 2018-05-31 2018-05-30 2018-06-25 Envelope 06 CNES Technical Assistance 001/AP/NESAP/2019 / CONCESSIONS PORTANT SUR Component 2: Rural LA REALISATION ET Demande de Single Stage - Two En cours 2021-07- IDA / 60820 Electrification through Service- A posteriori Open - National 3,777,889.00 0.00 2019-07-29 2019-08-30 2019-09-16 2019-10-15 2019-09-30 2020-04-27 2019-08-19 2019-08-31 2019-11-14 2020-06-26 2019-12-19 2020-11-05 2020-01-23 L'EXPLOITATION DE PROJETS propositions Envelope d'exécution 16 based Solar Hybrid Mini-grids D'ELECTRIFICATION RURALE AUTONOME HORS RESEAUX UCP_NESAP_C1_003__2020 / Component 4: Single Stage - One En attente 2020-08- Câblage internet pour IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 6,000.00 0.00 2020-06-03 2020-07-08 Envelope d'exécution 07 l'ANERSOL Technical Assistance GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AON-01/UEP/NESAP/2017 / Acquisition de 04 vehicles au Component 4: profit de l'ANPER, CNES et Single Stage - One IDA / 60820 Implementation Support and A posteriori Appel d'offres Open - National 240,000.00 194,053.65 Achevé 2017-10-20 2017-10-25 2017-12-06 2017-10-24 2018-01-05 2017-12-03 2018-02-09 2018-02-23 2018-08-08 2018-04-04 Ministère de l'Energie pour la Envelope Technical Assistance supervision et le suivi du projet CF-12/UEP/NESAP/2017 / Component 4: Acquisition logiciel de gestion Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 45,000.00 39,182.72 Achevé 2017-10-15 2017-10-02 2017-12-10 2018-02-01 2018-06-08 2018-02-15 financière (multi -sites) pour Envelope Technical Assistance l'UEP ANPER AOIR-01/NIGELEC/2017 / Component 3: Solar PV Hybridation solaire, Hybridization of Isolated Single Stage - One Extension, réhabilitation et IDA / 60820 A priori Appel d'offres Limited 10,000,000.00 0.00 Annulé 2017-11-27 2017-12-02 2018-01-13 2018-02-12 2018-03-19 2018-09-15 Thermal Mini-grids and Envelope renforcement des postes 1ere Expansion of Access phase CF-10/UEP/NESAP/2017 / Component 4: Single Stage - One Entretien et gardiennage du IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2017-10-25 2017-12-20 2018-06-18 Envelope local de UEP ANPER Technical Assistance CF-03/UEP/NESAP/2017 / Component 4: Single Stage - One Matériel informatique et IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 15,000.00 15,170.72 Achevé 2018-02-28 2017-12-07 2018-04-04 2018-02-09 2018-04-18 2018-02-12 Envelope consommables Technical Assistance AON-02/UEP/NESAP/2017 / Component 4: Fourniture d'équipements de Single Stage - One IDA / 60820 Implementation Support and A posteriori Appel d'offres Open - National 60,000.00 0.00 Annulé 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2018-09-18 control et demonstration Envelope Technical Assistance CNES CF-19/UEP/NESAP/2017 / Component 4: Single Stage - One Achat de carburant pour les IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2017-12-05 2018-01-30 2018-07-29 Envelope véhicules de l'UEP ANPER Technical Assistance CF-17-2/UEP/NESAP/2017 / Component 4: Single Stage - One Réfrigérateur et materiel de IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2017-10-27 2017-12-22 2018-06-20 Envelope café pour l'UEP ANPER Technical Assistance CF-01/UEP/NESAP/2017 / Mobilier pour les bureaux, la Component 4: Single Stage - One salle de réunion et Armoires + IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 35,000.00 33,153.76 Achevé 2018-01-31 2017-12-14 2018-03-07 2017-12-27 2018-03-21 2018-01-29 Envelope Etagère de classement des Technical Assistance dossier ANPER CF-13/UEP/NESAP/2017 / Component 4: Single Stage - One Matériel et mobilier de bureau IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 12,000.00 8,242.59 Achevé 2018-05-04 2018-05-18 2018-05-30 2018-05-30 2018-06-13 2018-06-05 Envelope au profit du CNES et la DGFOR Technical Assistance CF-14/UEP/NESAP/2017 / Component 4: Matériel informatique et Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 26,000.00 23,034.94 Achevé 2018-05-03 2018-05-15 2018-05-31 2018-05-15 2018-06-14 2018-05-30 logiciel au profit du CNES et Envelope Technical Assistance la DGFOR C-18/UEP/NESAP/2018 / Component 4: Besoin complémentaire en Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 20,000.00 15,518.19 Achevé 2018-04-30 2018-05-15 2018-05-26 2018-05-28 2018-06-09 2018-05-30 matériel informatique à l'UEP Envelope Technical Assistance ANPER C-19/UEP/NESAP/2018 / Component 4: Single Stage - One Acquisition des armoires au IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 10,000.00 6,119.20 Achevé 2018-05-01 2018-05-29 2018-05-30 2018-06-12 2018-06-04 Envelope profit de l'UEP ANPER Technical Assistance C-22/UEP/NESAP/2018 / Component 4: Acquisition d'équipement Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 5,000.00 4,030.64 Achevé 2018-05-04 2018-05-18 2018-06-01 2018-05-30 2018-06-15 2018-06-06 divers au profit du CNES et la Envelope Technical Assistance DGFOR Page 1 CF-09/UEP/NESAP/2017 / Component 4: Single Stage - One Groupe électrogène 55 KVA IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 34,000.00 28,706.76 Achevé 2018-06-01 2018-12-14 2018-06-29 2019-01-03 2018-07-13 2019-01-23 Envelope ANPER Technical Assistance CF-02/UEP/NESAP/2017 / Component 4: Single Stage - One Fournitures de bureau à l'UCP IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 10,000.00 10,233.41 Achevé 2018-05-04 2018-04-05 2018-05-23 2018-04-16 2018-06-06 2018-04-27 Envelope ANPER Technical Assistance CF-05/UEP/NESAP/2017 / Component 4: Matériel de communication Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 20,000.00 18,523.04 Achevé 2018-05-02 2018-05-03 2018-05-30 2018-05-15 2018-06-13 2018-06-04 ANPER ( Internet, téléphones Envelope Technical Assistance câblage réseau etc...) C-03/UEP/NESAP/2018 / Component 4: Single Stage - One Acquisition d'un véhicule 4X4 IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 54,000.00 51,201.72 Achevé 2018-09-07 2018-10-23 2018-10-22 2018-12-11 2018-11-21 2019-02-22 Envelope double cabine pour la DGOFR Technical Assistance C-21/UEP/NESAP/2018 / Component 4: Matériel informatique pour le Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 12,500.00 12,944.67 Achevé 2018-09-07 2018-09-12 2018-10-19 2018-12-11 2018-11-09 2018-12-17 compte du Ministère de Envelope Technical Assistance l'Energie C-22/UEP/NESAP/2018 / Component 4: Single Stage - One Mobilier de bureau pour le IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 7,000.00 6,593.96 Achevé 2018-09-07 2018-09-25 2018-10-19 2018-12-11 2018-11-09 2018-12-17 Envelope Ministère de l'Energie Technical Assistance 03ED/NESAP/2018 / Component 4: Passation de Acquisition de logiciel HOMER IDA / 60820 Implementation Support and A posteriori marché de gré à Direct 12,000.00 9,000.00 Achevé 2018-11-16 2019-05-31 2018-11-21 2019-05-31 2019-01-09 2019-06-01 2020-01-04 2019-06-20 au profit de l'Unité de Technical Assistance gré coordination du projet COT-001-NESAP-2019 / Component 4: Single Stage - One Acquisition de matériel de IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 20,000.00 21,583.19 Achevé 2019-05-05 2019-06-10 2019-06-09 2019-07-15 2019-06-30 2019-08-07 Envelope terrain Technical Assistance COT-004-NESAP-2019 / Component 4: Single Stage - One Acquisition de matériel IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 8,000.00 7,227.55 Achevé 2019-05-05 2019-06-10 2019-06-02 2019-07-02 2019-06-16 2019-07-04 Envelope informatique complémentaire Technical Assistance AON-02/UEP/NESAP/2017 Component 4: MOD / Fourniture Single Stage - One IDA / 60820 Implementation Support and A posteriori Appel d'offres Open - National 60,000.00 0.00 Annulé 2018-06-29 2018-07-04 2018-08-15 2018-09-14 2018-10-19 2018-12-18 d'équipements de contrôle et Envelope Technical Assistance de démonstration au CNES UCP_NESAP_C1_004_2020 / Component 4: Acquisition d'équipements de Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 60,000.00 53,273.14 Achevé 2020-06-05 2020-06-30 2020-07-17 2020-07-14 2020-08-16 2020-10-12 contrôle et de démonstration Envelope Technical Assistance pour l'ANERSOL UCP_NESAP_C1_002-2020 / Component 4: Mobilier de bureau pour la Single Stage - One En attente IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 6,000.00 0.00 2020-06-03 2020-07-15 2020-07-29 salle de réunion des Envelope d'exécution Technical Assistance Consultants à l'ANERSOL COVID19/DC- 001/ANPER/UCP/2021 / Component 5: Contingency Single Stage - One En attente IDA / 60820 A posteriori Demande de prix Limited 1,925,000.00 0.00 2021-04-05 2021-06-16 2021-12-13 Electrification de Centres de Emergency Response Envelope d'exécution Santé COVID19/DC- Component 5: Contingency Single Stage - One 002/ANPER/UCP/2021 / IDA / 60820 A posteriori Demande de prix Limited 620,000.00 0.00 Annulé 2021-04-05 2021-06-16 2021-12-13 Emergency Response Envelope Electrification des écoles NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CBUR-001-NESAP-2019 / Component 4: Single Stage - One Création du site web pour le IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 11,000.00 8,371.00 Achevé 2019-06-05 2019-12-24 2019-07-31 2020-01-09 2019-09-29 2020-03-27 Envelope projet et pour l'ANERSOL Technical Assistance COT-003-NESAP-2019 / Conception et impression des Component 4: Single Stage - One affiches de sensibilisation IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 16,900.00 7,771.81 Achevé 2019-05-28 2020-06-09 2019-07-02 2020-06-17 2019-07-23 2020-07-08 Envelope pour la composante 1 du Technical Assistance projet CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C-24/UEP/NESAP/2017 / Recrutement d'un ingénieur conseil - Supervision de la Component 3: Solar PV construction, mise en œuvre Sélection fondée Hybridization of Isolated de l'hybridation solaire et IDA / 60820 A priori sur la qualité et le Open - International 2,200,000.00 0.00 Annulé 2017-09-21 2017-10-05 2017-10-19 2017-11-23 2017-12-14 2017-12-28 2018-01-25 2020-01-25 Thermal Mini-grids and expansion des réseaux de coût Expansion of Access distribution et réhabilitation et renforcement des sous- stations (Composante 3) C-03/UEP/NESAP/2017 MOD / Recrutement d'un cabinet pour l'élaboration, la mise en œuvre et le suivi de la Component 4: Sélection fondée stratégie de communication IDA / 60820 Implementation Support and A posteriori sur la qualité et le Open - International 400,000.00 172,984.97 Achevé 2017-12-04 2017-12-18 2017-12-18 2018-05-04 2018-01-08 2018-07-30 2018-02-05 2018-09-21 2018-02-19 2018-09-25 2018-03-05 2018-11-06 2018-03-26 2019-01-03 2019-03-26 2020-01-10 pour la vulgarisation de Technical Assistance coût technologies photovoltaïques hors-réseau de qualité pour le CNES Page 2 C-03/UEP/NESAP/2017 / Recrutement d'une firme/ONG pour l'élaboration, la mise en œuvre et le suivi de la Component 4: Sélection fondée stratégie de communication IDA / 60820 Implementation Support and A priori sur la qualité et le Open - International 400,000.00 0.00 Annulé 2017-11-25 2017-12-09 2017-11-29 2017-12-23 2018-01-20 2018-02-03 2018-02-17 2018-03-03 2019-03-03 pour la vulgarisation de Technical Assistance coût technologies photovoltaïques hors-réseau de qualité pour le CNES C-01/UEP/NESAP/2017 / Assistance technique (recrutement d'une firme) Component 4: Sélection fondée pour la définition du IDA / 60820 Implementation Support and A priori sur la qualité et le Open - International 350,000.00 0.00 Annulé 2017-10-31 2017-11-21 2018-01-04 2018-02-01 2018-03-03 2018-04-07 2018-05-12 2019-05-12 mécanisme financier avec Technical Assistance coût l'intermédiaire financier de la Composante 1 du NESAP C-23/UEP/NESAP/2017 / Recrutement d'un ingénieur Component 2: Rural Sélection fondée conseil - Supervision de la IDA / 60820 Electrification through Service- A priori sur la qualité et le Open - International 1,500,000.00 1,429,129.00 Signé 2018-01-30 2018-03-23 2018-02-13 2018-03-30 2018-03-13 2018-07-26 2018-04-10 2018-09-21 2018-04-24 2018-12-14 2018-05-08 2019-05-16 2018-06-05 2019-06-11 2021-06-04 construction, mise en œuvre based Solar Hybrid Mini-grids coût de mini-réseaux solaires (Composante 2) C-01/UEP/NESAP/2017 MOD / Assistance technique (recrutement d'une firme) Component 4: Sélection fondée pour la définition du IDA / 60820 Implementation Support and A posteriori sur la qualité et le Open - International 350,000.00 0.00 Annulé 2018-06-29 2018-07-13 2018-08-03 2018-08-31 2018-09-14 2018-09-28 2018-10-19 2019-10-19 mécanisme financier avec Technical Assistance coût l'intermédiaire financier de la Composante 1 du NESAP C-01/UEP/NESAP/2018 / Sélection fondée Assistance technique aux Component 4: sur les banques dans le cadre de IDA / 60820 Implementation Support and A posteriori Open - International 200,000.00 0.00 Annulé 2018-06-28 2018-07-19 2018-07-06 2018-08-16 2018-08-30 2018-09-13 2019-09-08 qualifications des gestion de la ligne de crédit Technical Assistance consultants de la composante 1 C-02/UEP/NESAP/2018 / Assistance technique aux Sélection fondée Component 4: institutions de micro finance sur les IDA / 60820 Implementation Support and A posteriori Open - International 150,000.00 0.00 Annulé 2018-06-28 2018-07-19 2018-07-06 2018-08-16 2018-08-23 2018-09-13 2019-09-08 dans le cadre de la gestion de qualifications des Technical Assistance la ligne de crédit de la consultants composante 1 Sélection fondée C-31/UEP/NESAP/2017 / Component 2: Rural sur les Elaboration PAR et EIES IDA / 60820 Electrification through Service- A posteriori Open - International 150,000.00 0.00 Annulé 2018-06-29 2018-07-20 2018-09-02 2018-10-02 2018-11-06 2019-05-05 qualifications des composante 2 based Solar Hybrid Mini-grids consultants C-08/UEP/NESAP/2017 / Recrutement d'un bureau Sélection fondée d'études pour élaborer et Component 4: sur les mettre en œuvre un système IDA / 60820 Implementation Support and A posteriori Open - International 200,000.00 0.00 Annulé 2018-06-29 2018-07-20 2018-09-02 2018-10-02 2018-11-06 2019-11-06 qualifications des de suivi et évaluation des Technical Assistance consultants Composantes 1 et 2 du Projet sur la base d'un SIG C- Sélection fondée Component 4: 001/NESAP/COMP1/DGOFR20 sur les IDA / 60820 Implementation Support and A posteriori Open - International 200,000.00 204,986.10 Signé 2019-10-31 2019-10-02 2019-11-21 2019-10-04 2019-12-12 2020-02-04 2019-12-26 2020-03-09 2020-01-30 2020-07-02 2020-05-29 19 / Assistance techniques qualifications des Technical Assistance aux banques consultants C- Sélection fondée Component 4: 002/NESAP/COMP1/DGOFR20 sur les IDA / 60820 Implementation Support and A posteriori Open - International 150,000.00 130,318.66 Signé 2019-10-31 2019-10-04 2019-11-21 2019-10-04 2019-12-12 2020-02-04 2020-01-11 2020-03-06 2020-02-15 2020-04-28 2020-05-15 19 / Assistance technique aux qualifications des Technical Assistance Institutions de micro finance consultants UCP_NESAP_C1_001_ANERSOL / Recrutement d'une firme de Sélection fondée communication pour la mise à Component 4: sur les En attente jour de la stratégie et plan de IDA / 60820 Implementation Support and A posteriori Open - International 120,000.00 0.00 2020-06-30 2020-07-21 2020-08-25 2020-09-08 2020-10-06 2021-10-06 qualifications des d'exécution communication de la Technical Assistance consultants composante 1 ainsi que sa mise en oeuvre. UCP_NESAP_C4_005-2020 / Component 4: Sélection fondée En cours Audit externe du projet pour IDA / 60820 Implementation Support and A posteriori sur la qualité et le Open - National 37,120.00 0.00 2020-08-20 2020-08-10 2020-09-10 2020-08-10 2020-10-01 2020-10-31 2020-11-14 2020-12-05 2021-01-09 2022-05-31 d'exécution les exercices 2020 et 2021 Technical Assistance coût INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RC2-UCP/ANPER / Component 4: Recrutement d'un second IDA / 60820 Implementation Support and A posteriori Individuel Open 24,000.00 17,235.51 Achevé 2017-12-04 2017-12-17 2018-01-05 2018-04-06 2018-01-12 2018-05-28 2018-01-26 2018-05-31 2019-01-26 2019-05-31 Comptable à l'UCP/ANPER Technical Assistance C-02/UEP/NESAP/2017 / Assistance technique Component 4: (Consultant individuel) pour IDA / 60820 Implementation Support and A posteriori Individuel Open 150,000.00 37,333.22 Achevé 2018-02-27 2018-01-12 2018-04-10 2018-05-25 2018-04-24 2018-06-01 2018-05-15 2018-06-15 2019-05-15 2018-12-31 l'appui au developpement du Technical Assistance marché solaire au CNES C-18/UEP/NESAP/2017 / Component 4: Recrutement d'un spécialiste IDA / 60820 Implementation Support and A priori Individuel Limited 25,000.00 0.00 Annulé 2017-11-02 2017-11-07 2017-11-28 2018-01-02 2018-07-01 en contrôle technique d'appui Technical Assistance au CNES C-19/UEP/NESAP/2017 / Recrutement d'un consultant Component 4: individuel chargé d'appuyer IDA / 60820 Implementation Support and A priori Individuel Limited 200,000.00 0.00 Annulé 2017-09-18 2017-10-02 2017-09-15 2017-10-16 2017-10-30 2019-10-30 l'ANPER dans la mise en Technical Assistance oeuvre de projects d'electrification rurale Page 3 C-14/UEP/NESAP/2017 / Recrutement d'un consultant Component 4: individuel spécialiste en IDA / 60820 Implementation Support and A priori Individuel Limited 24,000.00 0.00 Annulé 2017-10-30 2017-11-04 2017-11-25 2017-12-30 2018-06-28 sauvegardes d'appui à l'UEP Technical Assistance de l'ANPER C-16/UEP/NESAP/2017 / Component 4: Recrutement d'un spécialiste IDA / 60820 Implementation Support and A priori Individuel Limited 25,000.00 0.00 Annulé 2017-11-06 2017-11-11 2017-12-02 2018-01-06 2018-07-05 en communication d'appui au Technical Assistance CNES C-16/UEP/NESAP/2017 MOD Component 4: / Recrutement d'un spécialiste IDA / 60820 Implementation Support and A posteriori Individuel Open 25,000.00 25,061.03 Achevé 2017-12-04 2017-10-24 2018-01-22 2018-01-16 2018-02-12 2018-01-30 2018-02-26 2018-01-30 2019-02-26 2020-02-28 en communication d'appui au Technical Assistance CNES C-17/UEP/NESAP/2017 / Component 4: Recrutement d'un spécialiste IDA / 60820 Implementation Support and A priori Individuel Limited 25,000.00 0.00 Annulé 2017-11-24 2017-11-29 2017-12-20 2018-01-24 2018-07-23 en suivi et évaluation d'appui Technical Assistance au CNES C-13/UEP/NESAP/2017 / Component 4: Recrutement d'un expert en IDA / 60820 Implementation Support and A priori Individuel Limited 24,000.00 0.00 Annulé 2017-10-15 2017-10-20 2017-11-10 2017-12-15 2018-06-13 developpement d'affaires de Technical Assistance l'ANPER C-13/UEP/NESAP/2017 MOD Component 4: / Recrutement d'un expert en IDA / 60820 Implementation Support and A posteriori Individuel Open 24,000.00 23,948.80 Achevé 2017-12-04 2017-07-06 2018-01-13 2018-01-17 2018-01-27 2018-01-22 2018-02-17 2018-01-18 2019-02-17 2019-08-30 développement d'affaires de Technical Assistance l'ANPER Component 4: Sélection de C-25/UEP/NESAP/2017 / IDA / 60820 Implementation Support and A priori consultants par Direct 124,128.00 0.00 Annulé 2017-10-23 2017-11-04 2017-12-25 2021-04-30 Audit externe Technical Assistance entente directe C-17/UEP/NESAP/2017 MOD Component 4: / Recrutement d'un spécialiste IDA / 60820 Implementation Support and A posteriori Individuel Open 25,000.00 25,043.34 Signé 2017-12-04 2017-10-24 2018-01-06 2018-01-16 2018-01-27 2018-01-18 2018-02-17 2018-02-01 2019-02-17 en suivi et évaluation d'appui Technical Assistance au CNES C-06/UEP/NESAP/2017 / Assistance Technique pour Component 4: Sélection de l'incubation des compagnies IDA / 60820 Implementation Support and A posteriori consultants par Direct 363,460.00 290,105.40 Signé 2018-05-17 2018-05-29 2018-07-26 2018-07-17 2020-07-25 (solaires et de pompage Technical Assistance entente directe solaire) Component 4: Sélection de C-25/UEP/NESAP/2017 MOD IDA / 60820 Implementation Support and A posteriori consultants par Direct 124,128.00 37,379.10 Achevé 2018-06-29 2018-07-09 2018-09-12 2018-06-04 2022-01-16 2020-06-30 / Audit externe Technical Assistance entente directe C-18/UEP/NESAP/2017 MOD Component 4: / Recrutement d'un spécialiste IDA / 60820 Implementation Support and A posteriori Individuel Open 25,000.00 0.00 Annulé 2017-12-22 2018-01-24 2018-02-07 2018-02-21 2019-02-21 en contrôle technique d'appui Technical Assistance au CNES C-18-NESAP / Recrutement d'un consultant individuel Component 4: chargé d'appuyer l'ANPER IDA / 60820 Implementation Support and A priori Individuel Limited 200,000.00 0.00 Annulé 2017-10-20 2017-10-25 2017-07-18 2017-11-24 2018-01-05 2020-01-05 dans la mise en oeuvre du Technical Assistance projet d'électrification rurale C-14/UEP/NESAP/2017 MOD / Recrutement d'un consultant Component 4: individuel spécialiste en IDA / 60820 Implementation Support and A posteriori Individuel Limited 24,000.00 0.00 Annulé 2017-12-04 2017-12-09 2017-12-30 2018-01-20 2019-01-20 sauvegardes d'appui à l'UEP Technical Assistance de l'ANPER NE- NESAP-27952-CS-INDV Component 4: / Recrutement d'un analyste IDA / 60820 Implementation Support and A posteriori Individuel Limited 25,000.00 0.00 Annulé 2017-09-20 2017-09-25 2017-10-16 2017-11-20 2018-11-20 financier à la DGFOR Technical Assistance C-14-UEP-NESAP-2017 MOD Component 4: / Recrutement d'un Expert en IDA / 60820 Implementation Support and A posteriori Individuel Open 24,000.00 1,949.84 Achevé 2017-09-28 2017-09-08 2017-11-16 2017-01-18 2017-12-07 2017-01-30 2018-01-11 2018-01-30 2019-01-11 2021-01-31 sauvegarde environnementale Technical Assistance et sociale NE-NESAP-27952-CS-INDV / Component 4: Recutement d'un Analyste IDA / 60820 Implementation Support and A posteriori Individuel Open 25,000.00 2,319.87 Signé 2017-09-11 2017-08-01 2017-10-30 2017-12-04 2017-11-20 2017-12-12 2017-12-25 2017-12-29 2018-12-25 financier à la DGOFR Technical Assistance C-18-NESAP-2019 / Component 4: Recrutement d'un Expert en IDA / 60820 Implementation Support and A posteriori Individuel Limited 100,000.00 8,500.00 Achevé 2017-09-11 2017-07-09 2017-09-16 2017-09-11 2017-10-07 2017-11-01 2017-11-11 2017-11-08 2018-11-06 2019-12-31 électrification rurale Technical Assistance CIND-001-NESAP-2019 / Recrutement d'un consultant Component 4: individuel pour élaborer des IDA / 60820 Implementation Support and A posteriori Individuel Limited 20,000.00 13,593.87 Achevé 2019-05-15 2019-05-23 2019-05-20 2019-05-23 2019-06-03 2019-06-21 2019-06-11 2019-06-26 2019-08-10 2019-09-30 NIES pour les cinq (5) grappes Technical Assistance de la phase pilote. AVENANT AU CONTRAT Component 4: Sélection de 002/NESAP/2017 / Avenant IDA / 60820 Implementation Support and A posteriori consultants par Direct 28,544.00 2,344.59 Signé 2019-05-14 2016-10-24 2019-05-20 2019-12-27 2019-06-01 2019-06-01 2020-05-26 au contrat de l'Auditeur Technical Assistance entente directe Interne du projet AVENANT AU CONTRAT Component 4: Sélection de 003/NESAP/2017 / Avenant IDA / 60820 Implementation Support and A posteriori consultants par Direct 28,544.00 2,344.59 Signé 2019-05-14 2016-12-30 2019-05-20 2017-04-17 2019-06-01 2019-06-01 2020-05-26 au contrat de la Comptable Technical Assistance entente directe Principale C-IND-001/NESAP/2019 / Component 4: Sélection de Consultant Local d'Appui à la IDA / 60820 Implementation Support and A posteriori consultants par Direct 25,000.00 2,427.59 Achevé 2019-07-31 2019-06-10 2019-08-10 2019-06-11 2019-10-14 2019-06-28 2020-10-13 2021-02-01 Mise en Oeuvre de la Technical Assistance entente directe Composante 1 du projet AVENANT/001/SPM/2019 / Component 4: Sélection de Avenant au contrat du IDA / 60820 Implementation Support and A posteriori consultants par Direct 28,544.00 2,268.45 Achevé 2019-12-27 2016-12-16 2019-12-27 2019-11-08 2019-12-27 2019-11-30 2020-12-01 2021-05-31 Spécialiste en passation des Technical Assistance entente directe marchés Page 4 C-001/ANPER/UCP/C- INDIV/2021 / Recrutement Component 4: En attente d'un Expert en Sauvegarde IDA / 60820 Implementation Support and A posteriori Individuel Limited 25,000.00 0.00 2021-02-26 2021-03-03 2021-03-24 2021-04-28 2022-04-28 d'exécution Environnementale, Sociale et Technical Assistance Genre ANPER/NESAP/UGP/CI/SPM / Component 4: En cours Recrutement d'un Spécialiste IDA / 60820 Implementation Support and A posteriori Individuel Open 38,000.00 0.00 2021-05-14 2021-05-17 2021-06-25 2021-07-09 2021-08-06 2022-08-01 d'exécution en Passation de Marchés Technical Assistance NE-ANPER-253545-CS-INDV Component 4: En cours / Recrutement d'un Analyste IDA / 60820 Implementation Support and A posteriori Individuel Open 35,000.00 0.00 2021-12-30 2021-10-29 2022-02-24 2022-03-17 2022-04-21 2023-04-16 d'exécution financier Technical Assistance NE-ANPER-260627-CS-INDV / Recrutement d'un Component 4: Consultant chargé de la mise En cours IDA / 60820 Implementation Support and A posteriori Individuel Open 35,000.00 0.00 2021-12-31 2021-11-06 2022-02-18 2022-03-11 2022-04-15 2023-04-10 en œuvre des activités de d'exécution Technical Assistance développement du marché solaire NE-ANPER-270332-CS-INDV Component 4: / Recrutement d'un IDA / 60820 Implementation Support and A posteriori Individuel Open 18,500.00 0.00 En cours d'examen 2022-03-25 2022-01-19 2022-05-13 2022-06-03 2022-07-08 2023-07-03 Comptable à l'ANPER Technical Assistance NE-ANPER-273808-CS-INDV Component 4: En attente / Recrutement d'un Auditeur IDA / 60820 Implementation Support and A posteriori Individuel Open 36,000.00 0.00 2022-01-25 2022-03-15 2022-04-05 2022-05-10 2023-05-05 d'exécution Interne pour l'ANPER Technical Assistance Page 5