PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive 1. 3M and above All contracts Bidding (ICB) (Goods) National Competitive Bidding 2. less than 3M 2M and above (NCB) (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated : May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages LN 8421 PH Procurement Plan Updated June 2018 (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Comment Ref. No. Description g ent US$1= Source nce by Bank Opening s Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review No. Selection Method Method Threshold US$ Threshold US$ 1. Competitive Methods 0.3M & above (may be used for 1m and above (QCBS, QBS, FBS) also less than 0.3M) (Firms) 2. Competitive Method less than 0.3M None CQS (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to Firms: 1M and Individuals) justification in accordance with above; paras. 3.9 and 5.4 respectively of Individuals 0.3M and Consultant Guidelines at the above. Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref Description of Procurin Expected Bid Estimated Cost (USD Funding Selection Comm . Contract g Opening million) Source Method ents No. Package Agency Date Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 LP/GoP Selection million) US$1,042,75 Single Source Luzon A ( Php59.152 LP/GoP Selection million) LN 8421 PH Procurement Plan Updated June 2018 US$1,042,75 Single Source Luzon B ( Php48.614 LP/GoP Selection million) US$1,042,75 Single Source Visaya ( Php29.612 LP/GoP Selection million) US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2019-03-11 2022-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 88160, IBRD / 84210, IBRD / 92710 PRDP PSO Luzon B, Dept of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PRDP-IB-R005-CAT-009- Pending 000-000-2017-AF / Component 2: Infrastructure Single Stage - One 2,490,137.0 2018-08- 2018-08- 2018-10- 2018-11- 2018-12- 2019-10- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Concreting of Junction Development Envelope 0 24 30 02 01 06 25 tion Sabangan-Datag East FMR, Caramoran PRDP-IB-R04A-BTG-003- Pending 000-000-2018-AF / Component 2: Infrastructure Single Stage - One 2,109,275.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Concreting of Sapangan- Development Envelope 0 22 27 08 07 11 10 tion Libato, San Juan FMR PRDP-IB-R04A-BTG-007- SAL-006-2018-AF / Pending Component 2: Infrastructure Single Stage - One 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- Rehabilitation of Farm-to- IBRD / 88160 Post Request for Bids Open - National 866,882.00 0.00 Implementa Development Envelope 22 27 08 07 11 10 Market Road of Calumpang tion East and Calumpang West PRDP-IB-R04A-LAG-004- Pending PAN-004-2017-AF / Component 2: Infrastructure Single Stage - One 1,078,431.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Construction of Pangil Development Envelope 0 22 27 08 07 11 10 tion Potable Water System PRDP-IB-R04A-LAG-003- SAA-003-2018-AF / Pending Concreting of Kayhakat- Component 2: Infrastructure Single Stage - One 2,048,686.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Bubucal-Inayapan-Calangay- Development Envelope 0 22 27 08 07 11 10 tion Coralan-Bagumbayan-Farm- to-Market Road PRDP-IB-R04A-QUE-041- CAT-001-2017-AF / Concreting of San Isidro Bolo Component 2: Infrastructure Single Stage - One 3,090,333.0 3,377,578. 2018-10- 2019-02- 2018-10- 2018-12- 2019-03- 2019-01- 2019-05- 2019-02- 2019-09- 2019-08- San Vicente Kanluran-San IBRD / 88160 Post Request for Bids Open - National Signed Development Envelope 0 21 22 15 27 08 19 07 14 11 24 10 Vicente Silangan-Sta.Maria Dao Farm-To-Market Road Sub-Project PRDP-IB-R04A-QUE-042- SAI-001-2017-AF / Rehabilitation and Component 2: Infrastructure Single Stage - One 3,817,275.0 3,691,616. 2018-10- 2019-01- 2018-10- 2018-12- 2019-02- 2019-01- 2019-05- 2019-02- 2019-08- 2019-08- IBRD / 88160 Post Request for Bids Open - National Signed Concreting of Concepcion Development Envelope 0 50 22 21 27 08 20 07 14 11 02 10 Palasan to Manggalang Kiling Farm-To-Market-Road with Line Canal PRDP-IB-R04B-MAR-002- 000-000-2016-AF / Pending Component 2: Infrastructure Single Stage - One 1,339,235.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- Improvement / Upgrading of IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Development Envelope 0 22 27 08 07 11 10 Pantayin-Jolo-Napo Farm-to- tion Market Road PRDP-IB-R04B-ORM-006- Pending 000-000-2015-AF / Component 2: Infrastructure Single Stage - One 1,224,471.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Concreting of Tigkan- Development Envelope 0 22 27 08 07 11 10 tion General Esco-Mahabang Parang FMR PRDP-IB-R04B-PAL-005- 000-000-2014-AF / Component 2: Infrastructure Single Stage - One 3,817,725.0 3,906,290. 2018-10- 2019-01- 2018-10- 2018-12- 2019-10- 2019-01- 2019-10- 2019-02- 2020-02- 2019-08- Construction and Upgrading IBRD / 88160 Post Request for Bids Open - National Signed Development Envelope 0 93 22 21 27 08 10 07 09 11 24 10 of Junction Salban-Culasian- Magsaysay FMR PRDP-IB-R04B-PAL-014- ROX-003-2016-AF / Pending Component 2: Infrastructure Single Stage - One 2,835,373.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- Construction and Upgrading IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Development Envelope 0 22 27 08 07 11 10 of Antonio-Taradungan FMR tion with 30 L.M. RCDG Bridge PRDP-IB-R04B-PAL-009- Pending PUE-003-2015-AF / Component 2: Infrastructure Single Stage - One 4,760,000.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Construction and Concreting Development Envelope 0 22 27 08 07 11 10 tion of Maruyugon to Macarascas FMR PRDP-IB-R005-ALB-006- TAB-001-2017-AF / Component 2: Infrastructure Single Stage - One 3,896,059.0 3,796,825. 2018-10- 2019-01- 2018-10- 2018-12- 2019-02- 2019-01- 2019-05- 2019-02- 2019-09- 2019-08- IBRD / 88160 Post Request for Bids Open - National Signed Rehabilitation / Improvement Development Envelope 0 80 22 21 27 08 20 07 09 11 06 10 of Hacienda to Rawis Farm to Market Road PRDP-IB-R005-ALB-004- Pending MAN-001-2018-AF / Component 2: Infrastructure Single Stage - One 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 698,039.00 0.00 Implementa Construction of Level II Development Envelope 22 27 08 07 11 10 tion Potable Water System PRDP-IB-R005-CAN-010- JOS-010-2017-AF / Pending Component 2: Infrastructure Single Stage - One 4,078,431.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- Upgrading of Nakalaya- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Development Envelope 0 22 27 08 07 11 10 Sta.Elena-San Isidro- tion Sta.Cruz-Dayhagan FMR in Jose Panganiban PRDP-IB-R005-MAS-003- ARO-001-2017-AF / Component 2: Infrastructure Single Stage - One 4,829,588.0 4,778,208. 2018-10- 2019-01- 2018-10- 2018-12- 2019-02- 2019-01- 2019-03- 2019-02- 2019-06- 2019-08- IBRD / 88160 Post Request for Bids Open - National Signed Concreting of San Agustin to Development Envelope 0 86 22 21 27 08 21 07 01 11 28 10 Tibgao Farm to Market Road PRDP-IB-R005-SOR-004- Pending 000-000-2017-AF / Component 2: Infrastructure Single Stage - One 1,443,627.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Rehabilitation of Cumadcad- Development Envelope 0 22 27 08 07 11 10 tion Canjela Farm-to-Market Road in Castilla PRDP-IB-R04A-BTG-005- 000-000-2018-AF / Pending Component 2: Infrastructure Single Stage - One 3,755,294.0 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- Concreting and Improvement IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Development Envelope 0 22 27 08 07 11 10 of Brgy. Leviste Calantas, tion Matamis and Nasi, Rosario, Batangas FMR PRDP-IB-R005-CAT-010- Pending 000-000-2020-AF / Component 2: Infrastructure Single Stage - One 3,610,800.0 2021-03- 2021-04- 2021-05- 2021-06- 2021-07- 2022-12- IBRD / 88160 Post Request for Bids Open - National 0.00 Implementa Concreting of Junction Development Envelope 0 29 05 05 04 25 08 tion Ogbong to Mabini Farm to Market Road PRDP-IB-R04A-QUE-039- National PAN-001-2015-AF / Procurement Pending Component 2: Infrastructure Single Stage - One 2,621,952.0 2021-10- 2021-10- 2021-12- 2021-12- 2022-02- 2022-08- Concreting of Poblacion - IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 15 20 01 31 04 03 Pinag-agan Farm to Market Envelope process tion Road of Panukulan, Quezon (Non Bank-SPD) PRDP-IB-R04A-QUE-032- TAG-002-2015-AF / National Concreting of Sta. Monica - Procurement Pending Component 2: Infrastructure Single Stage - One 2,105,504.0 2021-10- 2021-10- 2021-12- 2022-01- 2022-02- 2022-08- Sto. Niño - San Roque - IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 22 27 08 07 11 10 Manato Station with San Envelope process tion Isidro - Kinatakutan Segment (Non Bank-SPD) FMR of Tagkwayan, Quezon PRDP-IB-R04A-BTG-017- National AGO-015-2020 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 1,793,584.0 2021-10- 2021-11- 2021-12- 2022-01- 2022-02- 2022-08- of Barigon-Bilibinwang Farm- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 29 03 15 14 18 17 to-Market Road (Agoncillo, Envelope process tion Batangas) (Non Bank-SPD) National PRDP-IB-R04A-LAG-009- Procurement Pending RIZ-009-2020 / Concreting Component 2: Infrastructure Single Stage - One 2021-11- 2021-11- 2021-12- 2022-01- 2022-02- 2022-08- IBRD / 92710 Post Request for Bids Open - National Document - 1 986,864.00 0.00 Implementa of Brgy. Tala-Antipolo Farm Development Envelope 05 10 22 21 25 24 Envelope process tion to Market Road (Rizal, (Non Bank-SPD) Laguna) PRDP-IB-R04B-MAR-003- National 000-000-2020 / Procurement Pending Improvement/ Upgrading of Component 2: Infrastructure Single Stage - One 1,725,344.0 2021-10- 2021-11- 2021-12- 2022-01- 2022-02- 2022-08- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Caganhao - Amoingon - Development Envelope 0 29 03 15 14 18 17 Envelope process tion Maybo Farm To Market Road (Non Bank-SPD) of Boac, Marinduque PRDP-IB-R04B-MAR-005- National SAN-005-2020 / Procurement Pending Rehabilitation/ Improvement Component 2: Infrastructure Single Stage - One 2,112,576.0 2021-11- 2021-11- 2021-12- 2022-01- 2022-02- 2022-08- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa of Kaganhao - Banogbog Development Envelope 0 05 10 22 21 25 24 Envelope process tion Barangay Road Farm To (Non Bank-SPD) Market Road (Sta. Cruz, Marinduque) PRDP-IB-R04B-MAR-004- National BOA-004-2019 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 2,895,248.0 2021-10- 2021-10- 2021-12- 2022-01- 2022-02- 2022-08- of Cawit - Tugos Farm To IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 22 27 08 07 11 10 Market Road (Boac, Envelope process tion Marinduque) (Non Bank-SPD) PRDP-IB-R04B-ORM-011- National SAN-011-2018-AF / Procurement Pending Concreting of Barangay Component 2: Infrastructure Single Stage - One 1,858,304.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Bigaan - Saclag, Caagutayan Development Envelope 0 08 15 26 26 30 29 Envelope process tion Farm To Market Road with (Non Bank-SPD) Bridge (San Teodoro, Oriental Mindoro) Page 1 PRDP-IB-R005-MAS-001- National 000-000-2019 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 3,946,064.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- of Del Carmen to Malatawan IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 08 13 24 24 28 27 Farm to Market Road of Envelope process tion Uson, Palanas, Dimasalang, (Non Bank-SPD) Masbate PRDP-IB-R005-MAS-002- National 000-000-2019 / Concreting Procurement Pending of Cabangcalan to Malatawan Component 2: Infrastructure Single Stage - One 3,993,600.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Farm to Market Road with Development Envelope 0 08 13 24 24 28 27 Envelope process tion Bridge of Placer-Cataingan- (Non Bank-SPD) Palanas, Masbate PRDP-IB-R005-MAS-003- National 000-000-2019 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 3,989,488.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- of Del Carmen to San Ramon IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 06 11 22 22 26 25 Farm to Market Road with Envelope process tion Bridge of Uson, Masbate (Non Bank-SPD) PRDP-IB-R005-MAS-004- National 000-000-2019 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 3,923,616.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- of San Antonio to San Carlos IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 08 13 24 24 28 27 Farm to Market Road with Envelope process tion Bridge of Milagros, Masbate (Non Bank-SPD) PRDP-IB-R005-MAS-005- National 000-000-2019 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 3,116,976.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- of San Carlos to Magsalangui IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 08 13 24 24 28 27 Farm to Market Road of Envelope process tion Milagros, Masbate (Non Bank-SPD) PRDP-IB-R005-MAS-021- National 000-000-2020 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 2,074,656.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- of Calpi to Cawayan Farm to IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 08 13 24 24 28 27 Market Road of Claveria, Envelope process tion Masbate (Non Bank-SPD) PRDP-IB-R005-MAS-020- National 000-000-2020 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 3,987,936.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- of Junction Gaway-Gaway to IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 08 13 24 24 28 27 Pasig FMR of Claveria, Envelope process tion Masbate (Non Bank-SPD) National PRDP-IB-R005-MAS-025- Procurement Pending 000-000-2020 / Concreting Component 2: Infrastructure Single Stage - One 3,982,688.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa of San Pedro to Malaking Ilog Development Envelope 0 08 13 24 24 28 27 Envelope process tion FMR of San Pascual, Masbate (Non Bank-SPD) National PRDP-IB-R005-MAS-026- Procurement Pending 000-000-2020 / Concreting Component 2: Infrastructure Single Stage - One 2,717,296.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa of Mabuhay to Sta. Cruz FMR Development Envelope 0 10 15 26 26 30 29 Envelope process tion of San Pascual, Masbate (Non Bank-SPD) National PRDP-IB-R005-MAS-011- Procurement Pending 000-000-2020 / Concreting Component 2: Infrastructure Single Stage - One 2,076,576.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa of Mapina to Batuhan FMR of Development Envelope 0 08 13 24 24 28 27 Envelope process tion Masbate City, Masbate (Non Bank-SPD) PRDP-IB-R005-MAS-008- National 000-000-2020 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 3,963,552.0 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- of Manlut-od to IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 08 13 24 24 28 27 Guindawahan FMR of Pio V Envelope process tion Corpuz, Placer, Esperanza, (Non Bank-SPD) Masbate PRDP-IB-R005-MAS-007- National CAW-002-2019 / Procurement Pending Concreting of Segment( A) Component 2: Infrastructure Single Stage - One 4,007,872.0 2021-11- 2021-11- 2021-12- 2022-01- 2022-02- 2022-08- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Palobandera to Dalipe and Development Envelope 0 05 10 22 21 25 24 Envelope process tion Segment (B) Calumpang to (Non Bank-SPD) Iraya Farm to Market Road PRDP-IB-R005-ALB-009- National PIO-001-2019 / Procurement Pending Rehabilitation/Concreting of Component 2: Infrastructure Single Stage - One 3,224,016.0 2021-11- 2021-11- 2021-12- 2022-01- 2022-02- 2022-08- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Barangay Caratagan to Buyo Development Envelope 0 05 10 22 21 25 24 Envelope process tion Farm to Market Road of (Non Bank-SPD) Pioduran, Albay PRDP-IB-R04A-BTG-006- National TAY-005-2018-AF / Procurement Pending Component 2: Infrastructure Single Stage - One 2,201,380.0 2021-03- 2021-03- 2021-04- 2021-05- 2021-07- 2021-12- Concreting and Improvement IBRD / 88160 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 07 14 13 13 03 30 of Sto. Nino-Pina Farm to Envelope process tion Market Road of Taysan, (Non Bank-SPD) Batangas National PRDP-IB-R005-ALB-008- Procurement Pending POL-001-2019 / Component 2: Infrastructure Single Stage - One 3,200,000.0 2021-09- 2021-10- 2021-10- 2021-11- 2021-12- 2022-01- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Construction of Level II Development Envelope 0 27 04 07 06 11 08 Envelope process tion Potable Water System (Non Bank-SPD) (Polangui, Albay) PRDP-IB-R005-MAS-010- National PLA-003-2019 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 2,240,000.0 2021-09- 2021-10- 2021-11- 2021-12- 2022-01- 2022-07- of Matagangtang to Manlut- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 27 02 01 01 05 04 od Farm to Market Road with Envelope process tion Bridge (Placer, Masbate) (Non Bank-SPD) PRDP-IB-R005-MAS-016- National ARO-003-2020 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 3,996,400.0 2021-09- 2021-10- 2021-11- 2021-12- 2022-01- 2022-10- of San Agustin to Macabug IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 27 04 03 03 07 14 Farm to Market Road with Envelope process tion Bridge (Aroroy, Masbate) (Non Bank-SPD) PRDP-IB-R005-MAS-018- National DIM-001-2020 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 3,680,000.0 2021-09- 2021-10- 2021-11- 2021-12- 2022-01- 2022-10- of Gregorio Aliño to IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 27 04 03 03 07 14 Cabanoyoan FMR Envelope process tion (Dimasalang, Masbate) (Non Bank-SPD) PRDP-IB-R04B-OCM-006- National RIZ-001-2018 / Upgrading Procurement Pending of Brgy. Manoot Farm to Component 2: Infrastructure Single Stage - One 3,599,248.0 2021-12- 2022-01- 2022-02- 2022-03- 2022-04- 2023-04- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Market Road and Development Envelope 0 26 02 01 03 07 02 Envelope process tion Construction of Manoot (Non Bank-SPD) Bridge II (Rizal, Occidental Mindoro) National PRDP-IB-R005-ALB-011- Procurement Pending TIW-001-2019 / Component 2: Infrastructure Single Stage - One 3,865,712.0 2021-09- 2021-10- 2021-11- 2021-12- 2022-01- 2023-01- IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Construction of Tiwi Level II Development Envelope 0 27 04 03 03 07 02 Envelope process tion Water System (Tiwi, Albay) (Non Bank-SPD) PRDP-IB-R005-MAS-034- National PAL-001-2020 / Concreting Procurement Pending Component 2: Infrastructure Single Stage - One 4,000,000.0 2022-02- 2022-02- 2022-03- 2022-04- 2022-05- 2023-05- of Malibas to San Isidro Farm IBRD / 92710 Post Request for Bids Open - National Document - 1 0.00 Implementa Development Envelope 0 01 08 22 21 26 26 to Market Road (Palanas, Envelope process tion Masbate) (Non Bank-SPD) GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IS-LUB-020-R000- Pending 000-2022-AF / Laptops and Component 4: Project Request for Single Stage - One 2022-02- 2022-04- 2022-10- IBRD / 92710 Post Open - National 68,160.00 0.00 Implementat Desktop Computers with Implementation Support Quotations Envelope 07 04 01 ion Accessories PRDP-IS-LUB-021-R000- Pending Component 4: Project Request for Single Stage - One 2022-02- 2022-04- 2022-10- 000-2022-AF / Floor IBRD / 92710 Post Open - National 4,800.00 0.00 Implementat Implementation Support Quotations Envelope 07 04 01 Mounted Air Conditioner ion PRDP-IS-LUB-022-R000- Pending Component 4: Project Request for Single Stage - One 2022-02- 2022-04- 2022-10- 000-2022-AF / Mobile IBRD / 92710 Post Open - National 7,040.00 0.00 Implementat Implementation Support Quotations Envelope 07 04 01 Phone/Tablet ion NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IB-LUB-001-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / IBUILD IBRD / 84210 Post Direct Selection Direct 7,412.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Component Head PRDP-IB-LUB-002-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Roads and IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Bridges Specialist Page 2 PRDP-IB-LUB-003-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 14,294.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Infrastructure Engineer (RIE) PRDP-IS-LUB-001-R000- Component 2: Infrastructure 2017-12- 2018-02- 2018-08- 000-2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 3,706.00 0.00 Canceled 2017-11-27 Development 07 10 09 Assistant (EA) PRDP-IS-LUB-002-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 6,353.00 0.00 Canceled 2017-11-27 000-2018-AF / Driver Implementation Support 07 10 09 PRDP-IS-LUB-003-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,824.00 0.00 Canceled 2017-11-27 000-2018-AF / Legal Officer Implementation Support 07 10 09 PRDP-IS-LUB-004-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 1,906.00 0.00 Canceled 2017-11-27 000-2018-AF / Messenger Implementation Support 07 10 09 PRDP-IS-LUB-005-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 000-2018-AF / Economist Implementation Support 07 10 09 PRDP-IS-LUB-006-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Assistant IBRD / 84210 Post Direct Selection Direct 4,765.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Economist PRDP-IS-LUB-007-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 000-2018-AF / Training Implementation Support 07 10 09 Specialist PRDP-IS-LUB-008-R000- 000-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 Development Associate Implementation Support 07 10 09 (Office of the Project Director) PRDP-IS-LUB-009-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 000-2018-AF / M&E Officer Implementation Support 07 10 09 PRDP-IS-LUB-010-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,765.00 0.00 Canceled 2017-11-27 000-2018-AF / MIS Officer Implementation Support 07 10 09 PRDP-IS-LUB-011-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 000-2018-AF / GIS Data Implementation Support 07 10 09 Specialist PRDP-IS-LUB-012-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,765.00 0.00 Canceled 2017-11-27 000-2018-AF / GIS Data Implementation Support 07 10 09 Officer PRDP-IS-LUB-013-R000- 000-2018-AF / SES Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 Specialist / Environment Implementation Support 07 10 09 Safeguards Specialist PRDP-IS-LUB-014-R000- 000-2018-AF / SES Officer / Component 4: Project 2017-12- 2018-02- 2018-08- Environment Safeguards IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Officer/Social Safeguards Officer PRDP-IS-LUB-015-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Development Associate (SES) PRDP-IS-LUB-016-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 7,412.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Administrative Head PRDP-IS-LUB-017-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 3,706.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Administrative Officer III PRDP-IS-LUB-018-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Administrative Officer PRDP-IS-LUB-019-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / IBRD / 84210 Post Direct Selection Direct 12,706.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Administrative Assistant PRDP-IS-LUB-020-R000- 000-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 Development Associate Implementation Support 07 10 09 (Admin Unit) PRDP-IS-LUB-021-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 000-2018-AF / Utility Implementation Support 07 10 09 PRDP-IS-LUB-022-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 7,412.00 0.00 Canceled 2017-11-27 000-2018-AF / Procurement Implementation Support 07 10 09 Head PRDP-IS-LUB-023-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Specialist PRDP-IS-LUB-026-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 8,471.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Procurement Officer PRDP-IS-LUB-027-R000- 000-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 Development Associate Implementation Support 07 10 09 (Procurement Unit) PRDP-IS-LUB-028-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 7,412.00 0.00 Canceled 2017-11-27 000-2018-AF / Finance Unit Implementation Support 07 10 09 Head PRDP-IS-LUB-029-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Financial IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Analyst III / Finance Specialist PRDP-IS-LUB-030-R000- Individual Component 4: Project Under 2018-01- 2018-08- 2018-09- 2018-10- 2019-04- 000-2018-AF / Financial IBRD / 84210 Post Consultant Open 4,235.00 0.00 2018-07-09 Implementation Support Implementation 01 27 17 22 20 Analyst I Selection PRDP-IS-LUB-031-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 8,471.00 0.00 Canceled 2017-11-27 000-2018-AF / Financial Implementation Support 07 10 09 Analyst I PRDP-IS-LUB-032-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,765.00 0.00 Canceled 2017-11-27 000-2018-AF / Financial Implementation Support 07 10 09 Analyst II PRDP-IS-LUB-033-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 000-2018-AF / Budget Implementation Support 07 10 09 Specialist PRDP-IS-LUB-034-R000- 000-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,176.00 0.00 Canceled 2017-11-27 Development Associate Implementation Support 07 10 09 (Finance Unit) PRDP-IS-LUB-035-R000- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,235.00 0.00 Canceled 2017-11-27 000-2018-AF / Writer Implementation Support 07 10 09 PRDP-IS-LUB-036-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Graphic IBRD / 84210 Post Direct Selection Direct 3,706.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Layout Artist PRDP-IB-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- 001-2018-AF / Alternate IBRD / 84210 Post Direct Selection Direct 7,059.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Component Head PRDP-IB-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- 002-2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 9,412.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Infrastructure Engineer PRDP-IB-LUB-000-R04A- Individual Component 4: Project Under 2018-01- 2018-08- 2018-09- 2018-10- 2019-04- 003-2018-AF / Rural IBRD / 84210 Post Consultant Open 5,647.00 0.00 2018-07-09 Implementation Support Implementation 01 27 17 22 20 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- 004-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 2,941.00 0.00 Canceled 2017-11-27 Development Associate for Implementation Support 07 10 09 I-BUILD PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- 001-2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Assistant for RED PRDP-IS-LUB-000-R04A- 002-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 2,914.00 0.00 Canceled 2017-11-27 Development Associate for Implementation Support 07 10 09 DRPD PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- 003-2018-AF / IBRD / 84210 Post Direct Selection Direct 1,764.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Administrative Assistant PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,118.00 0.00 Canceled 2017-11-27 004-2018-AF / Financial Implementation Support 07 10 09 Analyst I PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,706.00 0.00 Canceled 2017-11-27 005-2018-AF / Financial Implementation Support 07 10 09 Analyst II Page 3 PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- 006-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 4,706.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Officer PRDP-IS-LUB-000-R04A- Individual 007-2018-AF / Project Component 4: Project Under 2018-01- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 84210 Post Consultant Open 2,941.00 0.00 2018-07-09 Development Associate for Implementation Support Implementation 01 27 17 22 20 Selection Procurement PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,118.00 0.00 Canceled 2017-11-27 008-2018-AF / Writer Implementation Support 07 10 09 PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 2,353.00 0.00 Canceled 2017-11-27 009-2018-AF / Driver Implementation Support 07 10 09 Individual PRDP-IS-LUB-000-R04A- Component 4: Project Under 2018-01- 2018-08- 2018-09- 2018-10- 2019-04- IBRD / 84210 Post Consultant Open 5,294.00 0.00 2018-07-09 010-2018-AF / Economist Implementation Support Implementation 01 27 17 22 20 Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- 011-2018-AF / Compliance IBRD / 84210 Post Consultant Open 4,235.00 0.00 2018-07-09 Implementation Support Implementation 27 17 22 20 Officer Selection PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- 012-2018-AF / Monitoring IBRD / 84210 Post Direct Selection Direct 9,412.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 and Evaluation Officer PRDP-IS-LUB-000-R04A- Individual Component 4: Project Pending 2018-08- 2018-09- 2018-10- 2019-04- 013-2018-AF / Monitoring IBRD / 84210 Post Consultant Open 5,294.00 0.00 2018-07-09 Implementation Support Implementation 27 17 22 20 and Evaluation Specialist Selection PRDP-IS-LUB-000-R04A- 014-2018-AF / SES Component 4: Project 2017-12- 2018-02- 2018-08- Specialist/Social Safeguards IBRD / 84210 Post Direct Selection Direct 5,294.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Specialist/ Environmental Safeguards Specialist PRDP-IS-LUB-000-R04A- 015-2018-AF / SES Component 4: Project 2017-12- 2018-02- 2018-08- Officer/Social Safeguards IBRD / 84210 Post Direct Selection Direct 4,706.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Officer/ Environmental Safeguards Officer PRDP-IS-LUB-000-R04A- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,706.00 0.00 Canceled 2017-11-27 016-2018-AF / GIS Data Implementation Support 07 10 09 Officer PRDP-IB-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- 001-2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 22,588.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Infrastructure Engineer (RIE) PRDP-IB-LUB-000-R04B- 002-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-27 Development Associate for Implementation Support 07 10 09 I-BUILD PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- 001-2018-AF / Monitoring IBRD / 84210 Post Direct Selection Direct 11,294.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 & Evaluation (M&E) Officer PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 9,882.00 0.00 Canceled 2017-11-27 002-2018-AF / Financial Implementation Support 07 10 09 Analyst I PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2018-01- 2018-01- 2018-02- 2018-03- 2018-09- 003-2018-AF / Financial IBRD / 84210 Post Consultant Open 4,941.00 0.00 2017-11-27 Implementation Support Implementation 01 15 05 12 08 Analyst I Selection PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- 004-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Officer PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- 005-2018-AF / Associate IBRD / 84210 Post Direct Selection Direct 9,882.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Procurement Officer PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- 006-2018-AF / Natural IBRD / 84210 Post Direct Selection Direct 6,353.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Resource Management Specialist PRDP-IS-LUB-000-R04B- 007-2018-AF / Social Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 6,353.00 0.00 Canceled 2017-11-27 Environment Safeguards Implementation Support 07 10 09 Specialist PRDP-IS-LUB-000-R04B- Individual 008-2018-AF / Social Component 4: Project Under 2018-01- 2018-01- 2018-02- 2018-03- 2018-09- IBRD / 84210 Post Consultant Open 3,765.00 0.00 2017-11-27 Environment Safeguards Implementation Support Implementation 01 15 05 12 08 Selection Officer PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-27 009-2018-AF / GIS Data Implementation Support 07 10 09 Officer PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,941.00 0.00 Canceled 2017-11-27 010-2018-AF / Writer Implementation Support 07 10 09 PRDP-IS-LUB-000-R04B- Individual Component 4: Project Pending 2018-01- 2018-02- 2018-03- 2018-09- 011-2018-AF / IBRD / 84210 Post Consultant Open 2,941.00 0.00 2017-11-27 Implementation Support Implementation 15 05 12 08 Administrative Officer Selection PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- 012-2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,059.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Development Associate PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2018-01- 2018-03- 2018-04- 2018-05- 2018-11- 013-2018-AF / IBRD / 84210 Post Consultant Open 706.00 0.00 2018-01-24 Implementation Support Implementation 01 14 04 09 05 Administrative Assistant Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Pending 2018-04- 2018-05- 2018-06- 2018-12- 014-2018-AF / Executive IBRD / 84210 Post Consultant Open 3,529.00 0.00 2018-02-24 Implementation Support Implementation 14 05 09 06 Assisstant (EA) Selection PRDP-IS-LUB-000-R04B- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-27 015-2018-AF / Driver Implementation Support 07 10 09 PRDP-IB-LUB-000-R005- Component 4: Project 2017-12- 2018-02- 2018-08- 001-2018-AF / RIE (Roads IBRD / 84210 Post Direct Selection Direct 6,353.00 0.00 Canceled 2017-11-28 Implementation Support 08 11 10 and Bridges) Specialist PRDP-IB-LUB-000-R005- Component 4: Project 2017-12- 2018-02- 2018-08- 002-2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 28,235.00 0.00 Canceled 2017-11-28 Implementation Support 08 11 10 Infrastructure Engineer (RIE) PRDP-IS-LUB-000-R005- Component 4: Project 2017-12- 2018-02- 2018-08- 001-2018-AF / Training IBRD / 84210 Post Direct Selection Direct 4,941.00 0.00 Canceled 2017-11-28 Implementation Support 08 11 10 Coordinator/Project Assistant PRDP-IS-LUB-000-R005- 002-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 Development Associate for I- Implementation Support 08 11 10 PLAN PRDP-IS-LUB-000-R005- 003-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 Development Associate for Implementation Support 08 11 10 Econ PRDP-IS-LUB-000-R005- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 7,059.00 0.00 Canceled 2017-11-28 004-2018-AF / PDA for Implementation Support 08 11 10 Finance PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2018-10- 2018-11- 2018-12- 2019-06- 005-2018-AF / PDA for IBRD / 84210 Post Consultant Open 3,529.00 0.00 2018-09-08 Implementation Support Implementation 27 17 22 20 Finance Selection PRDP-IS-LUB-000-R005- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 2,824.00 0.00 Canceled 2017-11-28 006-2018-AF / Driver Implementation Support 08 11 10 Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2018-01- 2018-10- 2018-11- 2018-12- 2019-06- IBRD / 84210 Post Consultant Open 2,824.00 0.00 2018-09-08 007-2018-AF / Driver Implementation Support Implementation 01 27 17 22 20 Selection PRDP-IS-LUB-000-R005- Component 4: Project 2018-03- 2018-05- 2018-11- IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2018-03-09 008-2018-AF / Admin Implementation Support 19 23 19 Officer I PRDP-IS-LUB-000-R005- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 4,235.00 0.00 Canceled 2017-11-28 009-2018-AF / Admin Implementation Support 08 11 10 Assistant PRDP-IS-LUB-000-R005- Component 4: Project 2018-03- 2018-05- 2018-11- 010-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2018-03-09 Implementation Support 19 23 19 Officer PRDP-IS-LUB-000-R005- 011-2018-AF / Project Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 Development Associate for Implementation Support 08 11 10 Procurement PRDP-IS-LUB-000-R005- 012-2018-AF / Program Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 Development Associate for Implementation Support 08 11 10 Writer Page 4 PRDP-IS-LUB-000-R005- 013-2018-AF / Program Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 7,059.00 0.00 Canceled 2017-11-28 Development Associate for Implementation Support 08 11 10 SES PRDP-IS-LUB-000-R005- Component 4: Project 2017-12- 2018-02- 2018-08- 014-2018-AF / Monitoring IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-28 Implementation Support 08 11 10 & Evaluation (M&E) Officer PRDP-IS-LUB-000-R005- 015-2018-AF / Program Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 3,529.00 0.00 Canceled 2017-11-28 Development Associate for Implementation Support 08 11 10 M&E PRDP-IS-LUB-000-R005- Component 4: Project 2017-12- 2018-02- 2018-08- IBRD / 84210 Post Direct Selection Direct 5,647.00 0.00 Canceled 2017-11-28 016-2018-AF / GIS Data Implementation Support 08 11 10 Officer PRDP-IS-LUB-000-R005- Individual 017-2018-AF / Program Component 4: Project Under 2018-01- 2018-01- 2018-02- 2018-03- 2018-09- IBRD / 84210 Post Consultant Open 3,529.00 0.00 2017-11-28 Development Associate for Implementation Support Implementation 01 16 06 13 09 Selection GGU PRDP-IS-LUB-024-R000- Individual Component 4: Project Under 2018-01- 2018-08- 2018-09- 2018-10- 2019-04- 000-2018-AF / Procurement IBRD / 84210 Post Consultant Open 9,529.00 0.00 2018-07-09 Implementation Support Implementation 01 27 17 22 20 Officer Selection PRDP-IS-LUB-025-R000- Component 4: Project 2017-12- 2018-02- 2018-08- 000-2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 9,529.00 0.00 Canceled 2017-11-27 Implementation Support 07 10 09 Officer PRDP-IB-LUB-001-R000- Individual Component 4: Project 2018-11- 2019-01- 2019-01- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-01- 000-2019-AF / I-BUILD IBRD / 88160 Post Consultant Direct 19,765.00 19,815.21 Completed 2019-01-03 Implementation Support 15 13 07 03 01 10 01 06 08 Component Head Selection PRDP-IB-LUB-002-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Rural IBRD / 88160 Post Consultant Direct 14,118.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Infrastructure Specialist Selection PRDP-IB-LUB-003-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Rural IBRD / 88160 Post Consultant Direct 25,412.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Infrastructure Engineer (RIE) Selection PRDP-IB-LUB-003-R000- Individual Component 4: Project 2018-12- 2019-01- 2019-01- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-01- 001-2019-AF / Rural IBRD / 88160 Post Consultant Direct 25,412.00 12,758.42 Completed 2019-01-03 Implementation Support 13 13 07 03 08 10 08 06 08 Infrastructure Engineer (RIE) Selection PRDP-IB-LUB-004-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,412.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Development Associate Selection PRDP-IB-LUB-005-R000- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 000-2019-AF / Project IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Development Associate Selection PRDP-IS-LUB-001-R000- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 000-2019-AF / Compliance IBRD / 88160 Post Consultant Direct 11,765.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Officer Selection PRDP-IS-LUB-002-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / IBRD / 88160 Post Consultant Direct 18,353.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Administrative Unit Head Selection PRDP-IS-LUB-003-R000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Executive IBRD / 88160 Post Consultant Direct 1,647.00 0.00 2019-01-03 Implementation Support Implementation 13 03 10 06 Assistant (EA) Selection PRDP-IS-LUB-004-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Administrative Officer III Selection PRDP-IS-LUB-005-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / IBRD / 88160 Post Consultant Direct 7,765.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Administrative Officer II Selection PRDP-IS-LUB-007-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 001-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Development Associate Selection PRDP-IS-LUB-007-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 002-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Development Associate Selection PRDP-IS-LUB-007-R000- Individual Component 4: Project Under 2018-12- 2019-01- 2019-02- 2019-03- 2019-09- 003-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-03 Implementation Support Implementation 13 13 03 10 06 Development Associate Selection Individual PRDP-IS-LUB-015-R000- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 2,118.00 0.00 2019-01-03 000-2019-AF / MIS Officer Implementation Support Implementation 01 13 03 10 06 Selection PRDP-IS-LUB-017-R000- Individual 000-2019-AF / Social and Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 2,118.00 0.00 2019-01-03 Environmental Safeguards Implementation Support Implementation 01 13 03 10 06 Selection Officer PRDP-IS-LUB-018-R000- Individual 000-2019-AF / Social and Component 4: Project 2018-12- 2019-01- 2019-03- 2019-02- 2019-04- 2019-03- 2019-04- 2019-09- 2019-04- IBRD / 88160 Post Consultant Direct 11,765.00 10,614.25 Completed 2019-01-03 Environmental Safeguards Implementation Support 13 13 26 03 16 10 16 06 16 Selection Specialist PRDP-IS-LUB-019-R000- Individual 000-2019-AF / Social and Component 4: Project 2018-12- 2019-01- 2019-03- 2019-02- 2019-03- 2019-03- 2019-03- 2019-09- 2019-03- IBRD / 88160 Post Consultant Direct 12,706.00 10,625.95 Completed 2019-01-03 Environmental Safeguards Implementation Support 13 13 26 03 26 10 26 06 26 Selection Officer PRDP-IS-LUB-020-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,412.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Development Associate Selection PRDP-IS-LUB-021-R000- Individual 000-2019-AF / Social and Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 10,588.00 0.00 2019-01-03 Environmental Safeguards Implementation Support Implementation 01 13 03 10 06 Selection Officer PRDP-IS-LUB-022-R000- Individual Component 4: Project 2018-12- 2019-01- 2019-01- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-01- 000-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 18,353.00 18,475.75 Completed 2019-01-03 Implementation Support 13 13 07 03 07 10 07 06 08 Unit Head Selection PRDP-IS-LUB-023-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 12,706.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Officer Selection PRDP-IS-LUB-024-R000- Individual Component 4: Project 2018-12- 2019-01- 2019-07- 2019-02- 2019-08- 2019-03- 2019-08- 2019-09- 2019-08- 000-2019-AF / Associate IBRD / 88160 Post Consultant Direct 11,294.00 989.89 Completed 2019-01-03 Implementation Support 13 13 25 03 02 10 02 06 02 Procurement Officer Selection PRDP-IS-LUB-025-R000- Individual Component 4: Project 2018-12- 2019-01- 2019-02- 2019-02- 2018-12- 2019-03- 2018-12- 2019-09- 2019-01- 000-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 2,118.00 10,627.83 Completed 2019-01-03 Implementation Support 13 13 26 03 13 10 13 06 08 Officer Selection PRDP-IS-LUB-027-R000- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 000-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 10,588.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Officer Selection PRDP-IS-LUB-030-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Finance Unit IBRD / 88160 Post Consultant Direct 18,353.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Head Selection PRDP-IS-LUB-031-R000- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Budget IBRD / 88160 Post Consultant Direct 2,353.00 0.00 2019-01-03 Implementation Support Implementation 13 03 10 06 Specialist Selection PRDP-IS-LUB-032-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Finance IBRD / 88160 Post Consultant Direct 2,353.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analyst III Selection PRDP-IS-LUB-033-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Finance IBRD / 88160 Post Consultant Direct 2,118.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analyst II Selection PRDP-IS-LUB-034-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Finance IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analyst I Selection PRDP-IS-LUB-036-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Finace IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analyst I Selection PRDP-IS-LUB-037-R000- Individual Component 4: Project 2018-12- 2019-04- 2018-12- 2019-05- 2019-02- 2019-06- 2019-01- 2019-12- 2019-02- 000-2019-AF / Budget IBRD / 88160 Post Consultant Direct 11,294.00 11,285.27 Completed 2019-04-02 Implementation Support 13 12 31 03 28 07 09 04 28 Analyst Selection PRDP-IS-LUB-038-R000- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 000-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,412.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Development Associate Selection Individual PRDP-IS-LUB-040-R000- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 12,706.00 0.00 2019-01-03 000-2019-AF / Economist Implementation Support Implementation 01 13 03 10 06 Selection Page 5 Individual PRDP-IS-LUB-041-R000- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 000-2019-AF / Writer Implementation Support Implementation 01 13 03 10 06 Selection Individual PRDP-IS-LUB-042-R000- Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 000-2019-AF / Writer Implementation Support Implementation 01 12 03 07 04 Selection PRDP-IS-LUB-043-R000- Individual Component 4: Project 2018-12- 2019-01- 2019-01- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-01- 000-2019-AF / Media IBRD / 88160 Post Consultant Direct 9,882.00 9,948.48 Completed 2019-01-03 Implementation Support 13 13 07 03 07 10 07 06 08 Production Officer Selection PRDP-IB-LUB-000-R04A- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 001-2019-AF / Rural IBRD / 88160 Post Consultant Direct 10,588.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Infrastructure Specialist Selection PRDP-IB-LUB-000-R04A- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 002-2019-AF / Rural IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 003-2019-AF / Rural IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 4: Project Under 2020-01- 2019-01- 2019-02- 2019-03- 2019-09- 004-2019-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 005-2019-AF / Rural IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Infrastructure Engineer Selection PRDP-IS-LUB-000-R04A- Individual 001-2019-AF / Program Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 Development Associate for Implementation Support Implementation 01 13 03 10 06 Selection RDPD PRDP-IS-LUB-000-R04A- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 002-2019-AF / Financial IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analyst I Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 003-2019-AF / Budget IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analsyt Selection Individual PRDP-IS-LUB-000-R04A- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 005-2019-AF / Economist Implementation Support Implementation 01 13 03 10 06 Selection Individual PRDP-IS-LUB-000-R04A- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 006-2019-AF / GIS Officer Implementation Support Implementation 01 13 03 10 06 Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 007-2019-AF / Infoace IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Writer Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2018-12- 2019-01- 2019-02- 2019-02- 2019-02- 2019-03- 2019-02- 2019-09- 2019-02- 008-2019-AF / Monitoring IBRD / 88160 Post Consultant Direct 11,294.00 10,592.39 Completed 2019-01-03 Implementation Support 13 13 26 03 27 10 27 06 28 and Evaluation Officer Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2018-12- 2019-01- 2019-02- 2019-02- 2019-01- 2019-03- 2019-02- 2019-09- 2019-02- 009-2019-AF / Monitoring IBRD / 88160 Post Consultant Direct 1,882.00 12,695.93 Completed 2019-01-03 Implementation Support 13 13 26 03 08 10 28 06 28 and Evaluation Officer Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 010-2019-AF / Associate IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 M&E Officer Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2019-01- 2019-01- 2019-01- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-01- 011-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.00 12,790.90 Completed 2019-01-03 Implementation Support 07 13 07 03 07 10 07 06 08 Officer Selection PRDP-IS-LUB-000-R04A- Individual 012-2019-AF / Social and Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 Environmental Safeguards Implementation Support Implementation 01 13 03 10 06 Selection Officer PRDP-IB-LUB-000-R04B- Individual 013-2019-AF / Social and Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 Environmental Safeguards Implementation Support Implementation 01 13 03 10 06 Selection Officer PRDP-IB-LUB-000-R04B- Individual 014-2019-AF / Program Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-01-03 Development Associate Implementation Support Implementation 01 13 03 10 06 Selection (IPLAN) PRDP-IS-LUB-000-R04B- Individual 015-2019-AF / Program Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-01-03 Development Associate Implementation Support Implementation 01 13 03 10 06 Selection (IBUILD) PRDP-IS-LUB-000-R04B- Individual 016-2019-AF / Program Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-01-03 Development Associate Implementation Support Implementation 01 13 03 10 06 Selection (ISUPPORT) PRDP-IS-LUB-000-R04B- Individual 019-2019-AF / Program Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 5,882.00 0.00 2019-01-03 Development Associate Implementation Support Implementation 01 13 03 10 06 Selection (INFO) PRDP-IB-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 003-2019-AF / Rural IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Infrastructure Engineer (RIE) Selection PRDP-IB-LUB-000-R04B- Individual 004-2019-AF / Project Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-04-02 Development Associate for Implementation Support Implementation 01 12 03 07 04 Selection IBUILD PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 001-2019-AF / Monitoring IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 & Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R04B- Individual 002-2019-AF / Associate Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 Monitoring & Evaluation Implementation Support Implementation 01 13 03 10 06 Selection (M&E) Officer PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 003-2019-AF / Financial IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analyst I Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 004-2019-AF / Financial IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Analyst I Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 005-2019-AF / Financial IBRD / 88160 Post Consultant Direct 1,647.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analyst I Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 006-2019-AF / Financial IBRD / 88160 Post Consultant Direct 1,647.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Analyst I Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2018-12- 2019-04- 2019-02- 2019-05- 2019-02- 2019-06- 2019-02- 2019-12- 2019-03- 007-2019-AF / Budget IBRD / 88160 Post Consultant Direct 8,235.00 9,434.89 Completed 2019-04-02 Implementation Support 13 12 26 03 26 07 26 04 01 Analyst Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 008-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Officer Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 009-2019-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Procurement Officer Selection PRDP-IS-LUB-000-R04B- Individual 010-2019-AF / Social & Component 4: Project 2018-12- 2019-01- 2019-01- 2019-02- 2019-01- 2019-03- 2019-01- 2019-09- 2019-01- IBRD / 88160 Post Consultant Direct 11,294.00 12,737.10 Completed 2019-01-03 Environmental Safeguards Implementation Support 13 13 07 03 07 10 07 06 08 Selection Officer PRDP-IS-LUB-000-R04B- Individual 011-2019-AF / Associate Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 Social & Environmental Implementation Support Implementation 01 13 03 10 06 Selection Safeguards Officer Individual PRDP-IS-LUB-000-R04B- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 012-2019-AF / GIS Officer Implementation Support Implementation 01 13 03 10 06 Selection Individual PRDP-IS-LUB-000-R04B- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 9,882.00 0.00 2019-01-03 013-2019-AF / Writer Implementation Support Implementation 01 13 03 10 06 Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 014-2019-AF / Executive IBRD / 88160 Post Consultant Direct 1,412.00 0.00 2019-01-03 Implementation Support Implementation 13 03 10 06 Assistant (EA) Selection Page 6 PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 018-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Development Associate Selection Individual PRDP-IS-LUB-000-R04B- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 020-2019-AF / Economist Implementation Support Implementation 01 13 03 10 06 Selection PRDP-IB-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 002-2019-AF / Rural IBRD / 88160 Post Consultant Direct 1,882.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Infrastructure Engineer (RIE) Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 001-2019-AF / IBRD / 88160 Post Consultant Direct 5,882.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Administrative Officer II Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 002-2019-AF / IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Administrative Officer I Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Pending 2019-01- 2019-02- 2019-03- 2019-09- 003-2019-AF / Training IBRD / 88160 Post Consultant Direct 1,647.00 0.00 2019-01-03 Implementation Support Implementation 13 03 10 06 Coordinator Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Direct 9,412.00 0.00 2019-04-02 006-2019-AF / Economist Implementation Support Implementation 01 12 03 07 04 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 007-2019-AF / Program IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Development Associate-Econ Selection PRDP-IS-LUB-000-R005- Individual 008-2019-AF / Program Component 4: Project Under 2018-12- 2019-04- 2019-02- 2019-05- 2019-02- 2019-06- 2019-12- IBRD / 88160 Post Consultant Direct 7,059.00 0.00 2019-04-02 Development Associate- Implementation Support Implementation 13 12 26 03 26 07 04 Selection IBUILD PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 013-2019-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Officer Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 014-2019-AF / Associate IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 Procurement Officer Selection PRDP-IS-LUB-000-R005- Individual 015-2019-AF / Program Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 Development Associate- Implementation Support Implementation 01 13 03 10 06 Selection Procurement Individual PRDP-IS-LUB-000-R005- Component 4: Project 2018-12- 2019-04- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-12- IBRD / 88160 Post Consultant Direct 8,235.00 984.84 Signed 2019-04-02 016-2019-AF / Writer Implementation Support 13 12 29 03 30 07 30 04 Selection PRDP-IS-LUB-000-R005- Individual 017-2019-AF / Program Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 Development Associate- Implementation Support Implementation 01 13 03 10 06 Selection InfoAce Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-04-02 018-2019-AF / SES Officer Implementation Support Implementation 01 12 03 07 04 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 019-2019-AF / Associate IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 SES Officer Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 020-2019-AF / Program IBRD / 88160 Post Consultant Direct 1,176.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 Development Associate-SES Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- 021-2019-AF / Monitoring IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 Implementation Support Implementation 01 13 03 10 06 & Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2019-01- 2019-04- 2019-05- 2019-06- 2019-12- 022-2019-AF / Associate IBRD / 88160 Post Consultant Direct 8,235.00 0.00 2019-04-02 Implementation Support Implementation 01 12 03 07 04 M&E Officer Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2019-01- 2019-01- 2019-02- 2019-03- 2019-09- IBRD / 88160 Post Consultant Direct 11,294.00 0.00 2019-01-03 023-2019-AF / GIS Officer Implementation Support Implementation 01 13 03 10 06 Selection PRDP-SLU-001-IB-001- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / I-BUILD IBRD / 88160 Post Consultant Direct 19,764.71 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Component Head Selection PRDP-SLU-002-IB-002- Individual Component 4: Project Under 2020-01- 2020-05- 2020-06- 2020-07- 2021-01- 2020-AF / Rural IBRD / 88160 Post Consultant Open 12,705.88 0.00 2020-04-01 Implementation Support Implementation 01 20 10 15 11 Infrastructure Engineer (RIE) Selection PRDP-SLU-003-IB-003- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-004-IB-004- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Rural IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-005-IB-005- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Project IBRD / 88160 Post Consultant Direct 8,470.59 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Development Associate Selection PRDP-SLU-006-DPD-001- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Compliance IBRD / 88160 Post Consultant Direct 14,117.65 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Officer Selection PRDP-SLU-007-DPD-002- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Administrative IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Officer III Selection PRDP-SLU-008-ADM-001- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Administrative IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Unit Head Selection PRDP-SLU-009-ADM-002- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Administrative IBRD / 88160 Post Consultant Direct 8,470.59 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Officer II Selection Individual PRDP-SLU-010-MNE-001- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 14,117.65 0.00 2020-01-02 2020-AF / M&E Specialist Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-011-MNE-002- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / M&E Officer Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-012-MNE-003- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / M&E Officer Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-013-GGU-001- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / GIS Data Officer Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-014-GGU-002- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / GIS Data Officer Implementation Support Implementation 01 12 02 08 04 Selection PRDP-SLU--015-SES-001- Individual 2020-AF / Social and Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 14,117.65 0.00 2020-01-02 Environmental Safeguards Implementation Support Implementation 01 12 02 08 04 Selection Specialist PRDP-SLU-016-SES-002- Individual 2020-AF / Social and Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Environmental Safeguards Implementation Support Implementation 01 12 02 08 04 Selection Officer PRDP-SLU-017-SES-003- Individual 2020-AF / Social and Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Environmental Safeguards Implementation Support Implementation 01 12 02 08 04 Selection Officer PRDP-SLU-018-PRO-001- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Procurement Unit IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Head Selection PRDP-SLU-019-PRO-002- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Procurement IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Officer Selection PRDP-SLU-020-PRO-003- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Procurement IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Officer Selection PRDP-SLU-021-PRO-004- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Associate IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Procurement Officer Selection Page 7 PRDP-SLU-022-PRO-005- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 2020-AF / Associate IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Procurement Officer Selection Individual PRDP-SLU-023-FIN-001- Component 4: Project Under 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2020-01-02 2020-AF / Finance Unit Head Implementation Support Implementation 12 02 08 04 Selection Individual PRDP-SLU-024-FIN-002- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / Finance Analyst II Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-025-FIN-003- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / Finance Analyst II Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-026-FIN-004- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / Finance Analyst II Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-027-FIN-005- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 2020-AF / Finance Analyst I Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-028-BUD-001- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 2020-AF / Budget Analyst I Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-029-DPD-001- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 2020-AF / Economist Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-030-ACE-001- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 2020-AF / Writer Implementation Support Implementation 01 12 02 08 04 Selection PRDP-SLU-031ACE-002- Individual Component 4: Project Under 2020-01- 2020-03- 2020-04- 2020-05- 2020-11- 2020-AF / Media Production IBRD / 88160 Post Consultant Open 9,882.35 0.00 2020-02-03 Implementation Support Implementation 01 23 13 18 14 Officer Selection PRDP-SLU-R04A-001-FIN- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Financial IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Analyst I Selection PRDP-SLU-R04A-002-BUD- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Budget IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Analsyt Selection Individual PRDP-SLU-R04A-003-DPD- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / Economist Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-R04A-004-GGU- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / GIS Officer Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-R04A-005-ACE- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 001-2020-AF / Writer Implementation Support Implementation 01 12 02 08 04 Selection PRDP-SLU-R04A-006-ACE- Individual 002-2020-AF / Program Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Development Associate Implementation Support Implementation 01 12 02 08 04 Selection (INFO) Individual PRDP-SLU-R04A-007-MNE- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / M&E Officer Implementation Support Implementation 01 12 02 08 04 Selection PRDP-SLU-R04A-008-MNE- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 M&E Officer Selection PRDP-SLU-R04A-009-PRO- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Officer Selection PRDP-SLU-R04A-010-SES- Individual 001-2020-AF / Social and Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Environmental Safeguards Implementation Support Implementation 01 12 02 08 04 Selection Officer PRDP-SLU-R04A-011-SES- Individual 002-2020-AF / Social and Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Environmental Safeguards Implementation Support Implementation 01 12 02 08 04 Selection Officer PRDP-SLU-R04A-012-ISP- Individual 001-2020-AF / Program Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Development Associate Implementation Support Implementation 01 12 02 08 04 Selection (ISUPPORT) PRDP-SLU-R04A-013-DPD- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Program IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Development Associate Selection PRDP-SLU-R04A-014-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Specialst (RIS) Selection PRDP-SLU-R04A-015-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-R04A-016-IB- Individual 003-2020-AF / Project Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Development Associate for Implementation Support Implementation 01 12 02 08 04 Selection IBUILD PRDP-SLU-R04B-001-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-R04B-002-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-R04B-003-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-R04B-004-IB- Individual 004-2020-AF / Project Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Development Associate for Implementation Support Implementation 01 12 02 08 04 Selection IBUILD PRDP-SLU-R04B-005-DPD- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Administrative Officer II Selection Individual PRDP-SLU-R04B-006-DPD- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 002-2020-AF / Economist Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-R04B-007-GGU- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / GIS Officer Implementation Support Implementation 01 12 02 08 04 Selection PRDP-SLU-R04B-008-PRO- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Officer Selection PRDP-SLU-R04B-009-PRO- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Procurement Officer Selection PRDP-SLU-R04B-010-MNE- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Monitoring IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 & Evaluation (M&E) Officer Selection PRDP-SLU-R04B-011-MNE- Individual 002-2020-AF / Associate Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Monitoring & Evaluation Implementation Support Implementation 01 12 02 08 04 Selection (M&E) Officer PRDP-SLU-R04B-012-SES- Individual 001-2020-AF / Social and Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Environmental Safeguards Implementation Support Implementation 01 12 02 08 04 Selection Officer PRDP-SLU-R04B-013-SES- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 SES Officer Selection Individual PRDP-SLU-R04B-014-ACE- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 001-2020-AF / Writer Implementation Support Implementation 01 12 02 08 04 Selection Page 8 PRDP-SLU-R04B-015-FIN- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Financial IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Analyst I Selection PRDP-SLU-R04B-016-ACT- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Financial IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Analyst I Selection PRDP-SLU-R04B-017-BUD- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Budget IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Analyst Selection PRDP-SLU-R005-001-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-R005-002-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-R005-003-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 003-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-R005-004-IB- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 004-2020-AF / Rural IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Infrastructure Engineer (RIE) Selection PRDP-SLU-R005-005-IB- Individual 005-2020-AF / Program Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Development Associate- Implementation Support Implementation 01 12 02 08 04 Selection IBUILD PRDP-SLU-R005-006-DPD- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Administrative Officer II Selection Individual PRDP-SLU-R005-007-DPD- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 002-2020-AF / Economist Implementation Support Implementation 01 12 02 08 04 Selection Individual PRDP-SLU-R005-008-GGU- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 001-2020-AF / GIS Officer Implementation Support Implementation 01 12 02 08 04 Selection PRDP-SLU-R005-009-PRO- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Procurement IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Officer Selection PRDP-SLU-R005-010-PRO- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Procurement Officer Selection PRDP-SLU-R005-011-MNE- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Monitoring IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 & Evaluation (M&E) Officer Selection PRDP-SLU-R005-012-MNE- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 M&E Officer Selection PRDP-SLU-R005-013-SES- Individual 001-2020-AF / Social and Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2020-01-02 Environmental Safeguards Implementation Support Implementation 01 12 02 08 04 Selection Officer PRDP-SLU-R005-014-SES- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 002-2020-AF / Associate IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 SES Officer Selection Individual PRDP-SLU-R005-015-ACE- Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 001-2020-AF / Writer Implementation Support Implementation 01 12 02 08 04 Selection PRDP-SLU-R005-016-FIN- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Analyst I Selection PRDP-SLU-R005-017-ACT- Individual Component 4: Project Under 2020-01- 2020-01- 2020-02- 2020-03- 2020-09- 001-2020-AF / Finance IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2020-01-02 Implementation Support Implementation 01 12 02 08 04 Analyst I Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure Under 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- 001-2021-AF / Rural IBRD / 88160 Post Consultant Open 5,000.00 0.00 2021-02-03 Development Implementation 01 24 14 19 15 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure Under 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- 002-2021-AF / Rural IBRD / 88160 Post Consultant Open 5,000.00 0.00 2021-02-03 Development Implementation 01 24 14 19 15 Infrastructure Engineer Selection PRDP-IS-LUB-000-R04A- Individual 005-2021-AF / Social and Component 4: Project Under 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IBRD / 88160 Post Consultant Open 5,000.00 0.00 2021-02-03 Environmental Safeguards Implementation Support Implementation 01 24 14 19 15 Selection Officer PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2021-01- 2020-12- 2020-12- 2021-01- 2021-12- 015-2021-AF / Procurement IBRD / 88160 Post Consultant 5,000.00 0.00 2020-12-10 Implementation Support Implementation 04 20 22 01 31 Officer Selection PRDP-IB-LUB-001-R000- Individual Component 2: Infrastructure 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / I-BUILD IBRD / 88160 Post Consultant Direct 7,000.00 1,647.77 Completed 2020-12-10 Development 01 20 04 10 04 14 04 13 04 Component Head Selection PRDP-IB-LUB-002-R000- Individual Component 2: Infrastructure 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / Rural IBRD / 88160 Post Consultant Direct 4,500.00 1,058.01 Completed 2020-12-10 Development 01 20 04 10 04 14 04 13 04 Infrastructure Engineer Selection PRDP-IB-LUB-003-R000- Individual Component 2: Infrastructure Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 001-2021-AF / Rural IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2020-12-10 Development Implementation 01 20 10 14 13 Infrastructure Engineer Selection PRDP-IB-LUB-004-R000- Individual Component 2: Infrastructure Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 000-2021-AF / Project IBRD / 88160 Post Consultant Direct 3,917.00 0.00 2020-12-10 Development Implementation 04 20 10 14 13 Development Associate Selection PRDP-IS-LUB-001-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / IBRD / 88160 Post Consultant Direct 8,125.00 1,520.11 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Administrative Unit Head Selection PRDP-IS-LUB-002-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / IBRD / 88160 Post Consultant Direct 4,375.00 816.95 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Administrative Officer III Selection PRDP-IS-LUB-003-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / IBRD / 88160 Post Consultant Direct 3,750.00 706.19 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Administrative Officer II Selection PRDP-IS-LUB-004-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / M&E IBRD / 88160 Post Consultant Direct 6,250.00 1,171.94 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Specialist Selection Individual PRDP-IS-LUB-005-R000- Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 5,625.00 1,056.54 Completed 2020-12-10 000-2021-AF / M&E Officer Implementation Support 01 20 04 10 04 14 04 13 04 Selection Individual PRDP-IS-LUB-005-R000- Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 5,625.00 1,059.28 Completed 2020-12-10 001-2021-AF / M&E Officer Implementation Support 01 20 04 10 04 14 04 13 04 Selection PRDP-IS-LUB-006-R000- Individual Component 4: Project Under 2020-12- 2020-12- 2021-01- 2021-02- 2021-08- 000-2021-AF / GIS Data IBRD / 88160 Post Consultant Direct 5,625.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Officer Selection PRDP-IB-LUB-000-R04B- Individual Component 2: Infrastructure Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 001-2021-AF / Rural IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Development Implementation 01 20 10 14 13 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04B- Individual Component 2: Infrastructure Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 002-2021-AF / Rural IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Development Implementation 01 20 10 14 13 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04B- Individual 003-2021-AF / Project Component 2: Infrastructure 2021-01- 2020-12- 2021-01- 2020-12- 2021-01- 2020-12- 2021-01- 2021-12- 2021-01- IBRD / 88160 Post Consultant Direct 3,125.00 583.68 Completed 2020-12-11 Development Associate Development 04 21 04 23 04 30 04 31 04 Selection (IBUILD) PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 001-2021-AF / Monitoring IBRD / 88160 Post Consultant Direct 5,000.00 935.45 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 05 & Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R04B- Individual 002-2021-AF / Associate Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 4,375.00 821.76 Completed 2020-12-10 Monitoring & Evaluation Implementation Support 01 20 04 10 04 14 04 13 04 Selection (M&E) Officer PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 003-2021-AF / Financial IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Analyst I (Finance) Selection Page 9 PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 004-2021-AF / Financial IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Analyst I (Accounting) Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-08- 005-2021-AF / Budget IBRD / 88160 Post Consultant Direct 4,375.00 818.52 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 31 Analyst Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 006-2021-AF / Procurement IBRD / 88160 Post Consultant Direct 5,000.00 933.51 Completed 2020-12-10 Implementation Support 04 20 04 10 04 14 04 13 04 Officer Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 007-2021-AF / Associate IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Procurement Officer Selection PRDP-IB-LUB-000-R04B- Individual 008-2021-AF / Social and Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Environmental Safeguards Implementation Support Implementation 01 20 10 14 13 Selection Officer Individual PRDP-IS-LUB-000-R04B- Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-08- IBRD / 88160 Post Consultant Direct 5,000.00 935.45 Completed 2020-12-10 009-2021-AF / Economist Implementation Support 01 20 04 10 04 14 04 13 31 Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 010-2021-AF / GIS Data IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Officer Selection Individual PRDP-IS-LUB-000-R04B- Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 011-2021-AF / Writer Implementation Support Implementation 01 20 10 14 13 Selection PRDP-IB-LUB-000-R005- Individual Component 2: Infrastructure Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 001-2021-AF / Rural IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Development Implementation 01 20 10 14 13 Infrastructure Engineer Selection PRDP-IB-LUB-001-R005- Individual Component 2: Infrastructure 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 002-2021-AF / Rural IBRD / 88160 Post Consultant Direct 5,000.00 939.52 Completed 2020-12-10 Development 04 20 04 10 04 14 04 13 04 Infrastructure Engineer Selection PRDP-IB-LUB-002-R005- Individual Component 2: Infrastructure 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 003-2021-AF / Rural IBRD / 88160 Post Consultant Direct 5,000.00 939.52 Completed 2020-12-10 Development 04 20 06 10 06 14 06 13 06 Infrastructure Engineer Selection PRDP-IB-LUB-003-R005- Individual Component 2: Infrastructure 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 004-2021-AF / Rural IBRD / 88160 Post Consultant Direct 5,000.00 933.51 Completed 2020-12-10 Development 04 20 04 10 04 14 04 13 04 Infrastructure Engineer Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 005-2021-AF / Economist Implementation Support Implementation 01 20 10 14 13 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 006-2021-AF / IBRD / 88160 Post Consultant Direct 3,125.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Administrative Officer II Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 5,000.00 933.89 Completed 2020-12-10 007-2021-AF / GIS Officer Implementation Support 04 20 04 10 04 14 04 13 04 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 008-2021-AF / Finance IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Analyst I (Finance) Selection PRDP-IS-LUB-0001-R005- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 009-2021-AF / Finance IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Analyst I (Accounting) Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 010-2021-AF / Monitoring IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 & Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 011-2021-AF / Associate IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 M&E Officer Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 5,000.00 939.52 Completed 2020-12-10 012-2021-AF / SES Officer Implementation Support 04 20 04 10 04 14 04 13 04 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 013-2021-AF / Associate IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 SES Officer Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 014-2021-AF / Writer Implementation Support Implementation 01 20 10 14 13 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 016-2021-AF / Associate IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 04 20 10 14 13 Procurement Officer Selection PRDP-IS-LUB-006-R000- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 001-2021-AF / GIS Data IBRD / 88160 Post Consultant Direct 5,625.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Officer Selection PRDP-IS-LUB-007-R000- Individual 000-2021-AF / Social and Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 6,250.00 1,171.94 Completed 2020-12-10 Environmental Safeguards Implementation Support 01 20 04 10 04 14 04 13 04 Selection Specialist PRDP-IS-LUB-008-R000- Individual 000-2021-AF / Social and Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 5,625.00 1,050.36 Completed 2020-12-10 Environmental Safeguards Implementation Support 01 20 04 10 04 14 04 13 04 Selection Officer PRDP-IS-LUB-008-R000- Individual 001-2021-AF / Social and Component 4: Project 2021-07- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 5,625.00 1,058.01 Completed 2020-12-10 Environmental Safeguards Implementation Support 01 20 04 10 04 14 04 13 04 Selection Officer PRDP-IS-LUB-009-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / Procurement IBRD / 88160 Post Consultant Direct 8,125.00 1,518.99 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Unit Head Selection PRDP-IS-LUB-010-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / Procurement IBRD / 88160 Post Consultant Direct 5,625.00 1,052.39 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Officer Selection PRDP-IS-LUB-010-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 001-2021-AF / Procurement IBRD / 88160 Post Consultant Direct 5,625.00 1,059.28 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Officer Selection PRDP-IS-LUB-011-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / Associate IBRD / 88160 Post Consultant Direct 5,000.00 954.54 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Procurement Officer Selection PRDP-IS-LUB-011-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 001-2021-AF / Associate IBRD / 88160 Post Consultant Direct 5,000.00 933.65 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Procurement Officer Selection PRDP-IS-LUB-012-R000- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 000-2021-AF / Finance Unit IBRD / 88160 Post Consultant Direct 6,500.00 0.00 2020-12-10 Implementation Support Implementation 04 20 10 14 13 Head Selection PRDP-IS-LUB-013-R000- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 000-2021-AF / Financial IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Analyst II Selection PRDP-IS-LUB-013-R000- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 001-2021-AF / Financial IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Analyst II Selection PRDP-IS-LUB-013-R000- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 002-2021-AF / Financial IBRD / 88160 Post Consultant Direct 4,500.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Analyst II Selection PRDP-IS-LUB-014-R000- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 000-2021-AF / Financial IBRD / 88160 Post Consultant Direct 4,000.00 0.00 2020-12-10 Implementation Support Implementation 04 20 10 14 13 Analyst I Selection PRDP-IS-LUB-015-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / Budget IBRD / 88160 Post Consultant Direct 4,000.00 941.58 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Analyst Selection Individual PRDP-IS-LUB-016-R000- Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 5,625.00 1,056.52 Completed 2020-12-10 000-2021-AF / Economist Implementation Support 01 20 04 10 04 14 04 13 04 Selection Individual PRDP-IS-LUB-017-R000- Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- IBRD / 88160 Post Consultant Direct 5,000.00 934.76 Completed 2020-12-10 000-2021-AF / Writer Implementation Support 01 20 04 10 04 14 04 13 04 Selection PRDP-IS-LUB-018-R000- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-01- 000-2021-AF / Media IBRD / 88160 Post Consultant Direct 4,375.00 1,050.36 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 04 Production Officer Selection Page 10 PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 000-2021-AF / Rural IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Development Implementation 01 20 10 14 13 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 003-2021-AF / Project IBRD / 88160 Post Consultant Direct 3,125.00 0.00 2020-12-10 Development Implementation 04 20 10 14 13 Development Associate Selection PRDP-IS-LUB-000-R04A- Individual 004-2021-AF / Social and Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Environmental Safeguards Implementation Support Implementation 01 20 10 14 13 Selection Officer PRDP-IS-LUB-000-R04A- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 006-2021-AF / GIS Data IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Officer Selection Individual PRDP-IS-LUB-000-R04A- Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 007-2021-AF / Writer Implementation Support Implementation 01 20 10 14 13 Selection PRDP-IS-LUB-000-R04A- Individual 008-2021-AF / Project Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88160 Post Consultant Direct 3,125.00 0.00 2020-12-10 Development Associate Implementation Support Implementation 01 20 10 14 13 Selection (InfoACE) Individual PRDP-IS-LUB-000-R04A- Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-02- IBRD / 88160 Post Consultant Direct 5,000.00 941.58 Completed 2020-12-10 009-2021-AF / Economist Implementation Support 01 20 04 10 04 14 04 13 11 Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-02- 010-2021-AF / Monitoring IBRD / 88160 Post Consultant Direct 5,000.00 934.62 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 11 & Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R04A- Individual 011-2021-AF / Associate Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-02- 2021-08- 2021-02- IBRD / 88160 Post Consultant Direct 4,375.00 817.79 Completed 2020-12-10 Monitoring & Evaluation Implementation Support 01 20 04 10 04 14 11 13 11 Selection (M&E) Officer PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-01- 2021-08- 2021-02- 012-2021-AF / Budget IBRD / 88160 Post Consultant Direct 4,375.00 817.79 Completed 2020-12-10 Implementation Support 01 20 04 10 04 14 04 13 11 Analyst Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 013-2021-AF / Financial IBRD / 88160 Post Consultant Direct 4,375.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Analyst I Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 014-2021-AF / Procurement IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Implementation Support Implementation 01 20 10 14 13 Officer Selection PRDP-IS-LUB-000-R04A- Individual 015-2021-AF / Project Component 4: Project Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- IBRD / 88160 Post Consultant Direct 3,125.00 0.00 2020-12-10 Development Associate Implementation Support Implementation 01 20 10 14 13 Selection (Procurement) PRDP-IB-LUB-000-R04B- Individual Component 2: Infrastructure Under 2021-01- 2020-12- 2021-01- 2021-02- 2021-08- 000-2021-AF / Rural IBRD / 88160 Post Consultant Direct 5,000.00 0.00 2020-12-10 Development Implementation 01 20 10 14 13 Infrastructure Engineer Selection PRDP-IP-LUB-001-R000- Individual Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / I-PLAN IBRD / 92710 Post Consultant Direct 16,128.00 0.00 Under Review 2021-12-05 National Level Planning 22 13 18 01 31 Component Head Selection PRDP-IP-LUB-002-R000- Individual Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Planning IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 National Level Planning 29 13 18 01 31 Officer Selection PRDP-IP-LUB-002-R000- Individual Component 1: Local and 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 001-2022-AF / Planning IBRD / 92710 Post Consultant Open 10,368.00 0.00 Under Review 2022-01-02 National Level Planning 22 15 19 02 31 Officer Selection PRDP-IP-LUB-003-R000- Individual Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Project IBRD / 92710 Post Consultant Direct 6,912.00 0.00 Under Review 2021-12-05 National Level Planning 29 13 18 01 31 Development Associate Selection PRDP-IB-LUB-001-R000- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / I-BUILD IBRD / 92710 Post Consultant Direct 16,128.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Component Head Selection PRDP-IB-LUB-002-R000- Individual Component 2: Infrastructure 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 000-2022-AF / Roads & IBRD / 92710 Post Consultant Open 11,520.00 0.00 Under Review 2022-01-02 Development 29 16 19 02 31 Bridges Specialist Selection PRDP-IB-LUB-003-R000- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Rural IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-003-R000- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Rural IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Development 22 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-003-R000- Individual Component 2: Infrastructure Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Rural IBRD / 92710 Post Consultant Direct 10,368.00 0.00 2021-12-05 Development Implementation 29 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-004-R000- Individual Component 2: Infrastructure 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 000-2022-AF / Project IBRD / 92710 Post Consultant Open 6,912.00 0.00 Under Review 2022-01-02 Development 29 16 19 02 31 Development Associate Selection PRDP-IR-LUB-001-R000- Individual Component 3. Enterprise Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / I-REAP IBRD / 92710 Post Consultant Direct 16,128.00 0.00 2021-12-05 Development Implementation 29 13 18 01 31 Component Head Selection PRDP-IR-LUB-002-R000- Individual 000-2022-AF / Enterprise Component 3. Enterprise Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 2021-12-05 Development & Marketing Development Implementation 22 13 18 01 31 Selection Specialist PRDP-IR-LUB-002-R000- Individual 001-2022-AF / Enterprise Component 3. Enterprise Under 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- IBRD / 92710 Post Consultant Open 11,520.00 0.00 2022-01-02 Development & Marketing Development Implementation 22 15 19 02 31 Selection Specialist PRDP-IR-LUB-003-R000- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Business IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Development 22 13 18 01 31 Development Officer Selection PRDP-IR-LUB-003-R000- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Business IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IS-LUB-001-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / IBRD / 92710 Post Consultant Direct 14,976.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Administrative Unit Head Selection PRDP-IS-LUB-002-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Administrative Officer III Selection PRDP-IS-LUB-003-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / IBRD / 92710 Post Consultant Direct 6,912.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Administrative Officer II Selection PRDP-IS-LUB-004-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / M&E IBRD / 92710 Post Consultant Direct 11,520.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Specialist Selection Individual PRDP-IS-LUB-005-R000- Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 000-2022-AF / M&E Officer Implementation Support 29 13 18 01 31 Selection Individual PRDP-IS-LUB-005-R000- Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 001-2022-AF / M&E Officer Implementation Support 22 13 18 01 31 Selection PRDP-IS-LUB-006-R000- Individual Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / GIS Data IBRD / 92710 Post Consultant Direct 10,368.00 0.00 2021-12-05 Implementation Support Implementation 22 13 18 01 31 Officer Selection PRDP-IS-LUB-006-R000- Individual Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / GIS Data IBRD / 92710 Post Consultant Direct 10,368.00 0.00 2021-12-05 Implementation Support Implementation 22 13 18 01 31 Officer Selection PRDP-IS-LUB-007-R000- Individual 000-2022-AF / Social and Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 11,520.00 0.00 Under Review 2021-12-05 Environmental Safeguards Implementation Support 22 13 18 01 31 Selection Specialist PRDP-IS-LUB-008-R000- Individual 000-2022-AF / Social and Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Environmental Safeguards Implementation Support 22 13 18 01 31 Selection Officer PRDP-IS-LUB-008-R000- Individual 001-2022-AF / Social and Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Environmental Safeguards Implementation Support 29 13 18 01 31 Selection Officer Page 11 PRDP-IS-LUB-009-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Procurement IBRD / 92710 Post Consultant Direct 14,976.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Unit Head Selection PRDP-IS-LUB-010-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Procurement IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Officer Selection PRDP-IS-LUB-010-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Procurement IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Officer Selection PRDP-IS-LUB-011-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Associate IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Procurement Officer Selection PRDP-IS-LUB-011-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Associate IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Procurement Officer Selection PRDP-IS-LUB-012-R000- Individual Component 4: Project Under 2021-12- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Finance Unit IBRD / 92710 Post Consultant Direct 14,976.00 0.00 2021-12-05 Implementation Support Implementation 15 13 18 01 31 Head Selection PRDP-IS-LUB-013-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Financial IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Analyst II Selection PRDP-IS-LUB-013-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Financial IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Analyst II Selection PRDP-IS-LUB-013-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Financial IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Analyst II Selection PRDP-IS-LUB-014-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Financial IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Analyst I Selection PRDP-IS-LUB-015-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Budget IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Analyst Selection Individual PRDP-IS-LUB-016-R000- Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 000-2022-AF / Economist Implementation Support 22 13 18 01 31 Selection Individual PRDP-IS-LUB-017-R000- Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 000-2022-AF / Writer Implementation Support Implementation 22 13 18 01 31 Selection PRDP-IS-LUB-018-R000- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Media IBRD / 92710 Post Consultant Direct 10,368.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Production Officer Selection PRDP-IS-LUB-019-R000- Individual Component 4: Project 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 000-2022-AF / Compliance IBRD / 92710 Post Consultant Open 11,520.00 0.00 Under Review 2022-01-02 Implementation Support 22 15 19 02 31 Officer Selection PRDP-IP-LUB-000-R04A- Individual Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Planning IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 National Level Planning 29 13 18 01 31 Officer Selection PRDP-IP-LUB-000-R04A- Individual Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Planning IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 National Level Planning 29 13 18 01 31 Officer Selection PRDP-IP-LUB-000-R04A- Individual Component 1: Local and Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 003-2022-AF / Project IBRD / 92710 Post Consultant Direct 5,760.00 0.00 2021-12-05 National Level Planning Implementation 29 13 18 01 31 Development Associate Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Development Implementation 22 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 003-2022-AF / Rural IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 Development 29 16 19 02 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 004-2022-AF / Rural IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 Development 29 16 19 02 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure Under 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 005-2022-AF / Rural IBRD / 92710 Post Consultant Open 9,216.00 0.00 2022-01-02 Development Implementation 22 15 20 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04A- Individual Component 2: Infrastructure Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 006-2022-AF / Project IBRD / 92710 Post Consultant Direct 5,760.00 0.00 2021-12-05 Development Implementation 22 13 18 01 31 Development Associate Selection PRDP-IR-LUB-000-R04A- Individual 000-2022-AF / Enterprise Component 3. Enterprise 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- IBRD / 92710 Post Consultant Open 10,368.00 0.00 Under Review 2022-01-02 Development & Marketing Development 29 16 19 02 31 Selection Specialist PRDP-IR-LUB-000-R04A- Individual Component 3. Enterprise Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Development Implementation 22 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R04A- Individual Component 3. Enterprise Under 2021-01- 2022-01- 2022-01- 2022-02- 2022-08- 002-2022-AF / Business IBRD / 92710 Post Consultant Open 9,216.00 0.00 2022-01-02 Development Implementation 01 21 28 11 10 Development Officer Selection PRDP-IR-LUB-000-R04A- Individual Component 3. Enterprise Under 2021-01- 2021-12- 2021-12- 2022-01- 2022-12- 003-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Development Implementation 01 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R04A- Individual Component 3. Enterprise 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 004-2022-AF / Business IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 Development 29 16 19 02 31 Development Officer Selection PRDP-IR-LUB-000-R04A- Individual Component 3. Enterprise Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 005-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Development Implementation 22 13 18 01 31 Infrastructure Engineer Selection (IREAP) PRDP-IS-LUB-000-R04A- Individual 000-2022-AF / Social and Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Environmental Safeguards Implementation Support Implementation 22 13 18 01 31 Selection Officer PRDP-IS-LUB-000-R04A- Individual 001-2022-AF / Social and Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Environmental Safeguards Implementation Support Implementation 22 13 18 01 31 Selection Officer PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / GIS Data IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Officer Selection Individual PRDP-IS-LUB-000-R04A- Component 4: Project 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- IBRD / 92710 Post Consultant Open 8,064.00 0.00 Under Review 2022-01-02 003-2022-AF / Writer Implementation Support 29 16 19 02 31 Selection PRDP-IS-LUB-000-R04A- Individual 004-2022-AF / Project Component 4: Project Pending 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 5,760.00 0.00 2021-12-05 Development Associate Implementation Support Implementation 13 18 01 31 Selection (InfoACE) Individual PRDP-IS-LUB-000-R04A- Component 4: Project 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 005-2022-AF / Economist Implementation Support 22 16 19 02 31 Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 006-2022-AF / Monitoring IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 & Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R04A- Individual 007-2022-AF / Associate Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Monitoring & Evaluation Implementation Support 29 13 18 01 31 Selection (M&E) Officer PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 008-2022-AF / Budget IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Analyst Selection PRDP-IS-LUB-000-R04A- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 009-2022-AF / Financial IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Analyst I Selection Page 12 PRDP-IS-LUB-000-R04A- Individual Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 010-2022-AF / Procurement IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Implementation Support Implementation 29 13 18 01 31 Officer Selection PRDP-IS-LUB-000-R04A- Individual 011-2022-AF / Project Component 4: Project Pending 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 5,760.00 0.00 2021-12-05 Development Associate Implementation Support Implementation 13 18 01 31 Selection (Procurement) PRDP-IP-LUB-000-R04B- Individual Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Planning IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 National Level Planning 22 13 18 01 31 Officer Selection PRDP-IP-LUB-000-R04B- Individual Component 1: Local and 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 001-2022-AF / Planning IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 National Level Planning 22 16 19 02 31 Officer Selection PRDP-IB-LUB-000-R04B- Individual Component 2: Infrastructure Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Development Implementation 22 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04B- Individual Component 2: Infrastructure Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Development Implementation 29 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04B- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04B- Individual Component 2: Infrastructure Under 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 003-2022-AF / Rural IBRD / 92710 Post Consultant Open 9,216.00 0.00 2022-01-02 Development Implementation 22 15 19 02 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04B- Individual Component 2: Infrastructure 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 004-2022-AF / Rural IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 Development 29 16 19 02 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R04B- Individual 005-2022-AF / Project Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 5,760.00 0.00 Under Review 2021-12-05 Development Associate Development 22 13 18 01 31 Selection (IBUILD) PRDP-IR-LUB-000-R04B- Individual 000-2022-AF / Enterprise Component 3. Enterprise Under 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- IBRD / 92710 Post Consultant Open 10,368.00 0.00 2022-01-02 Development & Marketing Development Implementation 22 16 19 02 31 Selection Specialist PRDP-IR-LUB-000-R04B- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R04B- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R04B- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 003-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R04B- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 004-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R04B- Individual 005-2022-AF / Project Component 3. Enterprise Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 5,760.00 0.00 2021-12-05 Development Associate Development Implementation 29 13 18 01 31 Selection (IREAP) PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Monitoring IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 & Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R04B- Individual 001-2022-AF / Associate Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Monitoring & Evaluation Implementation Support 22 13 18 01 31 Selection (M&E) Officer PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Financial IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Analyst I (Finance) Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 003-2022-AF / Financial IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Analyst I (Accounting) Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 004-2022-AF / Budget IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Analyst I Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 005-2022-AF / Procurement IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Implementation Support Implementation 29 13 18 01 31 Officer Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 006-2022-AF / Associate IBRD / 92710 Post Consultant Direct 8,064.00 0.00 2021-12-05 Implementation Support Implementation 29 13 18 01 31 Procurement Officer Selection PRDP-IS-LUB-000-R04B- Individual 007-2022-AF / Social and Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Environmental Safeguards Implementation Support 22 13 18 01 31 Selection Officer PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 008-2022-AF / Associate IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 SES Officer Selection Individual PRDP-IS-LUB-000-R04B- Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 009-2022-AF / Economist Implementation Support 29 13 18 01 31 Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 010-2022-AF / GIS Data IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Officer Selection Individual PRDP-IS-LUB-000-R04B- Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 8,064.00 0.00 2021-12-05 011-2022-AF / Writer Implementation Support Implementation 29 13 18 01 31 Selection PRDP-IS-LUB-000-R04B- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 012-2022-AF / IBRD / 92710 Post Consultant Direct 5,760.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Administrative Officer II Selection PRDP-IP-LUB-000-R005- Individual Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Planning IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 National Level Planning 29 13 18 01 31 Officer Selection PRDP-IP-LUB-000-R005- Individual Component 1: Local and 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 001-2022-AF / Planning IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 National Level Planning 29 16 19 02 31 Officer Selection PRDP-IP-LUB-000-R005- Individual 002-2022-AF / Project Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 5,760.00 0.00 Under Review 2021-12-05 Development Associate National Level Planning 29 13 18 01 31 Selection (IPLAN) PRDP-IP-LUB-000-R005- Individual 003-2022-AF / Project Component 1: Local and 2021-11- 2021-12- 2021-12- 2022-01- 2022-02- IBRD / 92710 Post Consultant Direct 5,760.00 0.00 Under Review 2021-12-05 Development Associate National Level Planning 22 13 18 01 06 Selection (IPLAN) PRDP-IB-LUB-000-R005- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 000-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R005- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R005- Individual Component 2: Infrastructure 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 22 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R005- Individual Component 2: Infrastructure Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 003-2022-AF / Rural IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 Development Implementation 22 13 18 01 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R005- Individual Component 2: Infrastructure 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 004-2022-AF / Rural IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 Development 29 16 19 02 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R005- Individual Component 2: Infrastructure 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 005-2022-AF / Rural IBRD / 92710 Post Consultant Open 9,216.00 0.00 Under Review 2022-01-02 Development 22 16 19 02 31 Infrastructure Engineer Selection PRDP-IB-LUB-000-R005- Individual Component 2: Infrastructure 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 006-2022-AF / Project IBRD / 92710 Post Consultant Open 5,760.00 0.00 Under Review 2022-01-02 Development 29 16 19 02 31 Development Associate Selection Page 13 PRDP-IR-LUB-000-R005- Individual 000-2022-AF / Enterprise Component 3. Enterprise 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- IBRD / 92710 Post Consultant Open 10,368.00 0.00 Under Review 2022-01-02 Development & Marketing Development 22 16 19 02 31 Selection Specialist PRDP-IR-LUB-000-R005- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R005- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 002-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R005- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 003-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R005- Individual Component 3. Enterprise 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 004-2022-AF / Business IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Development 29 13 18 01 31 Development Officer Selection PRDP-IR-LUB-000-R005- Individual 005-2022-AF / Project Component 3. Enterprise Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 5,760.00 0.00 2021-12-05 Development Associate Development Implementation 29 13 18 01 31 Selection (IREAP) Individual PRDP-IS-LUB-000-R005- Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 000-2022-AF / Economist Implementation Support 22 13 18 01 31 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 001-2022-AF / IBRD / 92710 Post Consultant Direct 5,760.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Administrative Officer II Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 002-2022-AF / GIS Officer Implementation Support Implementation 22 13 18 01 31 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 003-2022-AF / Finance IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Analyst I (Finance) Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 004-2022-AF / Finance IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 Analyst I (Accounting) Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 005-2022-AF / Monitoring IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 29 13 18 01 31 & Evaluation (M&E) Officer Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 006-2022-AF / Associate IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 M&E Officer Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 9,216.00 0.00 2021-12-05 007-2022-AF / SES Officer Implementation Support Implementation 29 13 18 01 31 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 008-2022-AF / Associate IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 SES Officer Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2022-01- 2022-01- 2022-02- 2022-12- 009-2022-AF / Associate IBRD / 92710 Post Consultant Open 8,064.00 0.00 Under Review 2022-01-02 Implementation Support 22 16 19 02 31 SES Officer Selection Individual PRDP-IS-LUB-000-R005- Component 4: Project Under 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- IBRD / 92710 Post Consultant Direct 8,064.00 0.00 2021-12-05 010-2022-AF / Writer Implementation Support Implementation 22 13 18 01 31 Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 011-2022-AF / Procurement IBRD / 92710 Post Consultant Direct 9,216.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Officer Selection PRDP-IS-LUB-000-R005- Individual Component 4: Project 2021-11- 2021-12- 2021-12- 2022-01- 2022-12- 012-2022-AF / Associate IBRD / 92710 Post Consultant Direct 8,064.00 0.00 Under Review 2021-12-05 Implementation Support 22 13 18 01 31 Procurement Officer Selection Page 14