Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan: March, 2017 3. Date of General Procurement Notice: June 14, 2013. 4. Period covered by this procurement plan: March 31 to Jan 2018. II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold Comments (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High installation of plant and equipment and PPP) 2. (Goods; Information Technology & 1.5 High Non-Consulting Services) 3. Consultant Services (Firms) 0.5 High 4. Consultant Services (Individual 0.2 High Consultants) 2. Pre-qualification NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. March 17, 2017 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 17, 2017 PROCUREMENT Uganda : Competitiveness and Enterprise Development Project (CEDP) PLAN General Information Country: Uganda 2017-05-03 Bank’s Approval Date of the Original Procurement Plan: 2022-08-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P130471 GPN Date: Project Name: Competitiveness and Enterprise Development Project (CEDP) Loan / Credit No: IDA / 52690, IDA / 65380 Ministry of Lands, Housing and Urban Development Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MLHUD-13936-CW-RFB / Single Stage - One E 4,715,949.4 2017-08-0 IDA / 52690 Land Administration Reform Prior Request for Bids Open - National Signed 2016-10-19 2016-10-24 2016-12-05 2017-03-10 2017-01-04 2017-06-13 2017-02-08 2017-07-13 Construction of 10 zonal land nvelope 0 7 offices GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MLHUD-13942-GO-DIR / Design, Supply, Installation a IDA / 52690 Land Administration Reform Prior Direct Selection Direct 0.00 Canceled 2014-06-18 2014-06-18 2014-07-09 2015-01-05 nd Implementation of Nation al Land Information System ( DeSINLISI) UG-MLHUD-14334-GO-RFB / Single Stage - One E Under Imple Procurement of specialized e IDA / 52690 Land Administration Reform Prior Request for Bids Open - National 0.00 2017-05-08 2017-05-13 2017-06-24 2017-07-24 2017-08-28 2018-02-24 nvelope mentation quipment for SMD, Valuation , PPD, ISLM UG-MLHUD-30814-GO-DIR / Hardware and Software Upgr IDA / 52690 Land Administration Reform Prior Direct Selection Direct 0.00 Canceled 2017-10-13 2018-03-05 2017-10-18 2017-11-22 2018-05-21 ade for the 6 LIS Phase I MZO s UG-MLHUD-30816-GO-RFB / Single Stage - One E Procurement of office furnitur IDA / 52690 Land Administration Reform Prior Request for Bids Open - National 0.00 Canceled 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 2018-08-04 nvelope e for MZOs UG-MLHUD-40342-GO-RFB / Development, Supply and Im Open - Internationa Single Stage - One E plementation of Computer As IDA / 52690 Land Administration Reform Prior Request for Bids 0.00 Canceled 2017-12-22 2017-12-27 2018-02-07 2018-03-09 2018-04-13 2018-10-10 l nvelope sisted Mass Appraisal Inform ation System for Uganda (CA MAIS Project) UG-MLHUD-47906-GO-RFQ / Procurement of 18 vehicles ( Request for Quota Single Stage - One E Under Revie 15 pickups, 2 station wagons IDA / 52690 Land Administration Reform Prior Limited 0.00 2018-03-05 2018-05-04 2018-04-30 2018-10-27 tions nvelope w and 1 van) - Phase 2 (for MZ Os, CLAs and Litigation, Judic iary, and ULC) UG-MLHUD-56524-GO-RFB / Single Stage - One E Procurement of office furnitur IDA / 52690 Land Administration Reform Post Request for Bids Open - National 594,195.00 Completed 2018-04-06 2018-04-10 2018-04-11 2018-05-23 2018-05-28 2018-06-22 2018-06-20 2018-07-27 2018-08-24 2019-01-23 2019-01-31 nvelope e for MZOs UG-MLHUD-143095-GO-DIR / Design, Supply, Installation a Under Revie nd Implementation of Nation IDA / 52690 Land Administration Reform Prior Direct Selection Direct 0.00 2015-02-10 2019-10-28 2015-02-15 2015-03-22 2015-09-18 w al Land Information System I nfrastructure (DeSINLISI) UG-MLHUD-235544-GO-RFB / Design, Development and I Open - Internationa Single Stage - One E Pending Impl mplementation of the Land V IDA / 65380 Land Administration Reform Prior Request for Bids 0.00 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-05-08 l nvelope ementation aluation Management Inform ation System (LaVMIS) UG-MLHUD-235324-GO-DIR / Pending Impl Enhancement of the Uganda IDA / 65380 Land Administration Reform Prior Direct Selection Direct 0.00 2021-07-16 2021-07-21 2021-08-25 2022-02-21 ementation National Land Information Sy stem (UgNLIS) UG-MLHUD-304405-GO-DIR / Direct - Internation Pending Impl National Land Information Sy IDA / 65380 Land Administration Reform Prior Direct Selection 0.00 2022-08-01 2022-08-06 2022-09-10 2023-03-09 al ementation stem Enhancement Project ( NaLISEP) UG-MLHUD-310588-GO-RFQ Request for Quota Single Stage - One E Pending Impl IDA / 65380 Land Administration Reform Post Limited 0.00 2022-09-03 2022-10-29 2023-04-27 / Procurement of Generator tions nvelope ementation UG-MLHUD-310581-GO-RFQ / Procurement of GIS Softwar e for the Institute of Surveys Request for Quota Single Stage - One E Pending Impl IDA / 65380 Land Administration Reform Post Limited 0.00 2022-09-21 2022-11-16 2023-05-15 and Land Management (ISLM tions nvelope ementation ) and Department of Geomati cs and Land Management, M akerere University (DGLM) UG-MLHUD-310572-GO-RFQ / Procurement of Security, Ac Request for Quota Single Stage - One E Pending Impl cess and Control Equipment f IDA / 65380 Land Administration Reform Post Limited 0.00 2022-09-17 2022-11-12 2023-05-11 tions nvelope ementation or National Land Information Centre (NLIC) and 22 Ministry Zonal Offices (MZOs) UG-MLHUD-307288-GO-RFQ / Procurement of IEC, Trainin Request for Quota Single Stage - One E Pending Impl IDA / 65380 Land Administration Reform Post Limited 0.00 2022-09-07 2022-11-02 2023-05-01 g and Sensitization Materials tions nvelope ementation for Rapid Physical Planning A ppraisal (RaPPA) UG-MLHUD-235517-GO-RFB / Procurement of 207 Compu ters, 22 Central UPS for deskt Single Stage - One E Pending Impl ops, 26 Access Switches, 8 Pr IDA / 65380 Land Administration Reform Prior Request for Bids Open - National 0.00 2022-09-16 2022-09-21 2022-11-02 2022-12-02 2023-01-06 2023-07-05 nvelope ementation ojectors (Normal and Smart P rojector), 4 Digital Cameras, 196 Printers, 3 LAN & Power cabling for various beneficiari es. Page 1 UG-MLHUD-310569-GO-RFQ / Procurement of 129 chairs a Request for Quota Single Stage - One E Pending Impl IDA / 65380 Land Administration Reform Post Limited 0.00 2022-09-14 2022-11-09 2023-05-08 nd 44 tables for Surveys and tions nvelope ementation Mapping Department UG-MLHUD-310557-GO-RFB / Procurement of assorted Su rvey and Mapping Equipment for the Physical Planning Dep Single Stage - One E Pending Impl artment (PPD), Institute of Su IDA / 65380 Land Administration Reform Post Request for Bids Open - National 0.00 2022-09-16 2022-09-21 2022-11-02 2022-12-02 2023-01-06 2023-07-05 nvelope ementation rvey and Land Management ( ISLM), Surveys and Mapping Department (SMD) and Depa rtment of Geomatics and Lan d Management (DGLM), MUK. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MLHUD-13927-NC-RFB / Open - Internationa Single Stage - One E Pending Impl Production of base maps for l IDA / 52690 Land Administration Reform Prior Request for Bids 0.00 2014-10-01 2014-10-06 2014-11-17 2014-12-17 2015-01-21 2015-07-20 l nvelope ementation and administration in Uganda UG-MLHUD-13945-NC-RFB / Open - Internationa Single Stage - One E Geodetic Reference Frame fo IDA / 52690 Land Administration Reform Prior Request for Bids 3,823,567.93 Signed 2016-02-02 2016-02-07 2016-03-20 2016-04-19 2017-05-05 2016-05-24 2017-04-20 2016-11-20 l nvelope r Land Administration in Uga nda” (UGRF) UG-MLHUD-14331-NC-RFB / Open - Internationa Single Stage - One E Systematic Land Adjudication IDA / 52690 Land Administration Reform Prior Request for Bids 2,885,000.00 Signed 2017-05-08 2017-05-05 2017-05-13 2017-06-14 2017-06-24 2017-08-10 2017-07-24 2018-04-19 2017-08-28 2018-07-04 2018-02-24 l nvelope and Certification (SLAAC) UG-MLHUD-280572-NC-RFB / Procurement of Non Consulti Open - Internationa Single Stage - One E Pending Impl ng Services for Systematic La IDA / 65380 Land Administration Reform Prior Request for Bids 0.00 2022-08-05 2022-08-10 2022-09-21 2022-10-21 2022-11-25 2023-05-24 l nvelope ementation nd Adjudication and Certifica tion Project (Lots 1-5) UG-MLHUD-235316-NC-DIR / Enhancement of the Uganda IDA / 65380 Land Administration Reform Prior Direct Selection Direct 0.00 Canceled 2021-07-16 2021-07-21 2021-08-25 2022-02-21 Geodetic Reference Framewo rk (UGRF) UG-MLHUD-304408-NC-DIR / Direct - Internation Pending Impl Enhancement of the Uganda IDA / 65380 Land Administration Reform Prior Direct Selection 0.00 2022-09-02 2022-09-07 2022-10-12 2023-04-10 al ementation Geodetic Reference Framewo rk (UGRF) UG-MLHUD-235562-NC-DIR / Systematic Land Adjudication Direct - Internation Pending Impl and Certification of 142,000 IDA / 65380 Land Administration Reform Prior Direct Selection 0.00 2022-09-02 2022-09-07 2022-10-12 2023-04-10 al ementation parcels in both peri-urban an d rural areas of Oyam, Marac ha and Apac (SOMAp) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MLHUD-13926-CS-QCBS Quality And Cost- Open - Internationa Under Implement / Preparation of National Phy IDA / 52690 Land Administration Reform Prior 0.00 2014-06-24 2014-07-15 2014-08-28 2014-09-25 2014-10-25 2014-11-29 2015-01-03 2016-01-03 Based Selection l ation sical Development Plan (NPD P) UG-MLHUD-13938-CS-QCBS / Baseline Study of the curre Quality And Cost- Open - Internationa Pending Impleme IDA / 52690 Land Administration Reform Post 0.00 2014-11-11 2014-12-02 2015-01-15 2015-02-12 2015-03-14 2015-04-18 2015-05-23 2016-05-22 nt planning system as bench Based Selection l ntation mark for evaluating projects UG-MLHUD-13948-CS-CQS / Development of a comprehe Consultant Qualifi Open - Internationa IDA / 52690 Land Administration Reform Prior 0.00 Canceled 2016-02-25 2016-03-17 2016-04-30 2017-06-27 2016-05-30 2016-07-04 2016-12-31 nsive, multimedia, state of th cation Selection l e art Communication Strateg y for the Land sector UG-MLHUD-13933-CS-QCBS / Construction Supervision of Nine (9) Ministry Zonal Office Quality And Cost- Open - Internationa Pending Impleme IDA / 52690 Land Administration Reform Post 0.00 2014-06-24 2014-07-15 2014-08-28 2014-09-25 2014-10-25 2014-11-29 2015-01-03 2016-01-03 s, and a Hostel and Multi-Pur Based Selection l ntation pose Hall for the Institute of Surveying and Land Manage ment UG-MLHUD-14332-CS-CQS / Consultant Qualifi Development of Real Estate ( IDA / 52690 Land Administration Reform Prior Open - National 0.00 Canceled 2017-05-08 2017-06-30 2017-05-29 2017-12-28 2017-07-12 2017-08-11 2017-09-15 2018-03-14 cation Selection Agency and Management) Bil l UG-MLHUD-13940-CS-QCBS Quality And Cost- Open - Internationa Pending Impleme / Improving Physical Planning IDA / 52690 Land Administration Reform Post 0.00 2015-10-02 2015-10-23 2015-12-06 2016-01-03 2016-02-02 2016-03-08 2016-04-12 2017-04-12 Based Selection l ntation Legislation in Uganda UG-MLHUD-14333-CS-CQS / Consultant Qualifi Development of Building Sta IDA / 52690 Land Administration Reform Prior Open - National 0.00 Canceled 2017-05-08 2017-05-23 2017-05-29 2017-07-12 2017-08-11 2017-09-15 2018-03-14 cation Selection ndards for Earthquake Prone Areas UG-MLHUD-27394-CS-CQS / Consultant Qualifi Development of Building Sta IDA / 52690 Land Administration Reform Post Open - National 0.00 Canceled 2017-09-07 2017-09-28 2017-11-11 2017-12-11 2018-01-15 2018-07-14 cation Selection ndards for Earthquake Prone Areas in Uganda UG-MLHUD-235304-CS-QCB Quality And Cost- Open - Internationa Pending Impleme S / Review of the Land Admin IDA / 65380 Land Administration Reform Prior 0.00 2022-07-18 2022-08-08 2022-09-21 2022-10-19 2022-11-18 2022-12-23 2023-01-27 2024-01-27 Based Selection l ntation istration Legal Framework INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 UG-MLHUD-13929-CS-CDS / Hiring of Consultant to concl Pending Impleme ude the Design, Developmen IDA / 52690 Land Administration Reform Post Direct Selection Direct 0.00 2016-10-05 2016-10-05 2016-10-26 2017-04-24 ntation t and Implementation of the Data Capture Software/Syste m UG-MLHUD-13939-CS-CDS / Environmental and Social Im IDA / 52690 Land Administration Reform Prior Direct Selection Direct 0.00 Canceled 2016-12-28 2016-12-28 2017-01-18 2017-07-17 pact Assessment of the plann ed construction works UG-MLHUD-13930-CS-CDS / Pending Impleme IDA / 52690 Land Administration Reform Post Direct Selection Direct 0.00 2016-02-14 2016-02-14 2016-03-06 2016-09-02 Records Management Special ntation ist UG-MLHUD-13935-CS-CDS / Pending Impleme Consultancy Services for Affo IDA / 52690 Land Administration Reform Post Direct Selection Direct 0.00 2016-09-07 2016-09-07 2016-09-28 2017-03-27 ntation rdable Housing Finance Feasi bility Analysis UG-MLHUD-13937-CS-CDS / Preparation of Technical Req uirements for the Design and IDA / 52690 Land Administration Reform Prior Direct Selection Direct 0.00 Canceled 2016-01-11 2016-01-11 2016-02-01 2016-07-30 Implementation of the Comp uter Assisted Mass Appraisal (CAMA) Project in Uganda UG-MLHUD-15985-CS-INDV / Individual Consult Under Implement IDA / 52690 Land Administration Reform Prior Open 0.00 2014-11-11 2015-03-12 2015-04-28 2017-12-19 2015-06-22 2015-07-27 Hiring of Physical Planning A ant Selection ation dvisor UG-MLHUD-40468-CS-CDS / Under Implement Renewal of contract for the P IDA / 52690 Land Administration Reform Prior Direct Selection Direct 0.00 2017-12-22 2017-12-28 2018-01-01 2018-01-03 2018-03-07 2018-09-03 ation hysical Planning Advisor UG-MLHUD-53007-CS-CDS / Under Implement Specialized ICT Training for M IDA / 52690 Land Administration Reform Post Direct Selection Direct 0.00 2018-03-12 2018-04-10 2018-03-22 2018-04-24 2018-05-26 2018-11-22 ation LHUD ICT officers UG-MLHUD-235327-CS-CDS / Conducting an Environmenta l and Social Impact Assessme Under Implement IDA / 65380 Land Administration Reform Post Direct Selection Direct 0.00 2021-07-08 2021-09-30 2021-07-18 2021-09-21 2022-03-20 nt of the planned constructio ation n works under MLHUD (arch ival center and one floor on NLIC) UG-MLHUD-235533-CS-CDS / SLAAC Data Capture and Pro cessing Software upgrade an Under Implement d Maintenance. The function IDA / 65380 Land Administration Reform Post Direct Selection Direct 0.00 2021-07-08 2021-08-17 2021-07-18 2021-09-21 2022-03-20 ation alities of the software to be u pgraded should allow for mas sive parcel geometry data ca pture and titles certification. UG-MLHUD-235551-CS-CQS / Design Review and Construct ion Supervision of Constructi Pending Impleme IDA / 65380 Land Administration Reform Post Direct Selection Direct 0.00 2021-07-12 2021-07-22 2021-09-25 2022-03-24 on of Land Administration str ntation uctures to support enhance d service delivery (archival c enter and one floor on NLIC) UG-MLHUD-226382-CS-CDS / Engagement of the Project T echnical Advisor (TA) who wil l be responsible for providing Under Implement IDA / 65380 Land Administration Reform Post Direct Selection Direct 0.00 2021-07-16 2021-08-17 2021-07-26 2020-08-19 2021-09-29 2022-03-28 oversight and technical advic ation e in all project activities as w ell as providing quality contr ol ensuring that Project objec tives are met UG-MLHUD-226391-CS-CDS / Engagement of the Services Under Implement of the Procurement Specialist IDA / 65380 Land Administration Reform Post Direct Selection Direct 0.00 2021-07-16 2021-08-17 2021-07-26 2021-09-29 2022-03-28 ation to ensure smooth operations of the Project Procurement A ctivities UG-MLHUD-235313-CS-CDS / Pending Impleme IDA / 65380 Land Administration Reform Post Direct Selection Direct 0.00 2021-07-16 2021-07-26 2021-09-29 2022-03-28 Review of SLAAC Manuals ntation UG-MLHUD-242872-CS-CDS / Pending Impleme Review of SLAAC Manuals - S IDA / 65380 Land Administration Reform Post Direct Selection Direct - National 0.00 2022-08-08 2022-08-18 2022-10-22 2023-04-20 ntation urveyor/GIS Expert UG-MLHUD-309307-CS-INDV Individual Consult Pending Impleme / Recruitment of Monitoring a IDA / 65380 Land Administration Reform Post Open - National 0.00 2022-08-19 2022-10-07 2022-10-28 2022-12-02 2023-05-31 ant Selection ntation nd Evaluations Officer UG-MLHUD-304399-CS-CDS / Pending Impleme Technical Advisor (Richard O IDA / 65380 Land Administration Reform Post Direct Selection Direct - National 0.00 2022-07-18 2022-07-28 2022-10-01 2023-03-30 ntation put) Contract Renewal UG-MLHUD-309313-CS-INDV Individual Consult Pending Impleme / Recruitment of a Procureme IDA / 65380 Land Administration Reform Post Open - National 0.00 2022-08-19 2022-10-07 2022-10-28 2022-12-02 2023-05-31 ant Selection ntation nt Assistant UG-MLHUD-309311-CS-INDV Individual Consult Pending Impleme / Recruitment of Project Acco IDA / 65380 Land Administration Reform Post Open - National 0.00 2022-08-19 2022-10-07 2022-10-28 2022-12-02 2023-05-31 ant Selection ntation unts Officer (PAO) UG-MLHUD-304401-CS-CDS / Pending Impleme Procurement Specialist (John IDA / 65380 Land Administration Reform Post Direct Selection Direct - National 0.00 2022-07-18 2022-07-28 2022-10-01 2023-03-30 ntation Obore) Contract Renewal UG-MLHUD-242875-CS-CDS / Pending Impleme Review of SLAAC Manuals - C IDA / 65380 Land Administration Reform Post Direct Selection Direct - National 0.00 2022-08-08 2022-08-18 2022-10-22 2023-04-20 ntation ommunications Expert UG-MLHUD-242873-CS-CDS / Pending Impleme Review of SLAAC Manuals - L IDA / 65380 Land Administration Reform Post Direct Selection Direct - National 0.00 2022-08-08 2022-08-18 2022-10-22 2023-04-20 ntation egal Expert UG-MLHUD-309320-CS-CDS / Procurement of LIS Superviso Direct - Internation Pending Impleme IDA / 65380 Land Administration Reform Post Direct Selection 0.00 2022-09-09 2022-09-19 2022-11-23 2023-05-22 r - Mike Cheremshynskyi - (C al ntation ontract Renewal) Page 3 UG-MLHUD-242874-CS-CDS / Pending Impleme Review of SLAAC Manuals - S IDA / 65380 Land Administration Reform Post Direct Selection Direct - National 0.00 2022-09-09 2022-09-19 2022-11-23 2023-05-22 ntation ociologist/Development Expe rt Page 4