The World Bank                                                                                        Implementation Status & Results Report
         Poyang Lake Basin Town Water Environment Management Project (P153604)



Poyang Lake Basin Town Water Environment Management Project (P153604)


 EAST ASIA AND PACIFIC | China | Water Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 11 | ARCHIVED on 17-Dec-2021 | ISR48611 |


 Implementing Agencies: People's Republic of China, Jiangxi Provincial Development and Reform Commission



 Key Dates


  Key Project Dates

   Bank Approval Date: 16-Mar-2017                                              Effectiveness Date: 13-Oct-2017
   Planned Mid Term Review Date: 12-Mar-2020                                    Actual Mid-Term Review Date: 12-Nov-2019
   Original Closing Date: 31-Dec-2022                                           Revised Closing Date: 31-Dec-2022
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The project development objectives are to reduce the pollutant discharge into selected waterways, and improve management of water quality in
  selected counties in the Poyang Lake basin within Jiangxi Province.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component 1: Institutional Strengthening for Water Management:(Cost $26.38 M)
 Component 2: Lake and River Restoration and Improvement of Wastewater Management:(Cost $112.14 M)
 Component 3: Improvements in Solid Waste Management:(Cost $16.40 M)
 Component 4: Project Implementation Support:(Cost $20.22 M)

 Overall Ratings

 Name                                                                         Previous Rating                           Current Rating

 Progress towards achievement of PDO                                          Moderately Satisfactory                  Moderately Satisfactory
 Overall Implementation Progress (IP)                                         Moderately Unsatisfactory                Moderately Satisfactory
 Overall Risk Rating                                                          Moderate                                 Moderate


 Implementation Status and Key Decisions

  The project is on track towards the achievement of the PDO. In this reporting period, significant implementation progress and results have been
  achieved although the overall implementation is still behind schedule. About half of the Lake Management Platforms (LMPs) planned are either in
  trail operation or getting ready for trial operation while the rest are in advanced stage of development, contributing to lake/river protection and the
  integrated water and environment management with active public participation. Significant progress in the wastewater management and lake
  restoration activities is also made with a large percentage of the wastewater management works completed, resulting in substantial reduction
  in different water pollutant discharges. The smart domestic solid waste monitoring and supervisory system/platform is at advanced stage of
  development in the four project counties concerned. The disbursement rate is 39.1% with an increment of 13.5% compared to the last mission. As a
  result of those achievements, the number of total project beneficiaries has increased substantially to 700,457. A detailed review of the results
  targets in connection with project progress projection indicates the project development objective is achievable by the current loan closing date.


12/17/2021                                                                                                                      Page 1 of 7
            The World Bank                                                                                   Implementation Status & Results Report
            Poyang Lake Basin Town Water Environment Management Project (P153604)



  The next Bank mission is tentatively planned for April/May 2022 with an interim review scheduled for end February, 2022.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                            Rating at Approval              Previous Rating               Current Rating

  Political and Governance                                 Low                            Low                          Low
  Macroeconomic                                            Moderate                       Moderate                     Moderate
  Sector Strategies and Policies                           Moderate                       Moderate                     Moderate
  Technical Design of Project or Program                   Substantial                    Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                           Substantial                    Moderate                     Moderate
  Sustainability
  Fiduciary                                                Moderate                       Moderate                     Moderate
  Environment and Social                                   Moderate                       Moderate                     Moderate
  Stakeholders                                             Substantial                    Moderate                     Moderate
  Other                                                    Substantial                    Substantial                  Substantial
  Overall                                                  Substantial                    Moderate                     Moderate



  Results


 PDO Indicators by Objectives / Outcomes



   PDO Indicators

    IN01050043
    ►Direct project beneficiary (Number, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                             0.00                        576,546.00                  700,457.00                 2,746,000.00

    Date                              01-Jan-2017                 11-Jun-2021                 30-Nov-2021               31-Dec-2022

      IN01050044
      Female beneficiaries (Percentage, Custom Supplement)

                                     Baseline                   Actual (Previous)            Actual (Current)           End Target

     Value                           0.00                       50.00                       50.00                       50.00

    IN01050045




12/17/2021                                                                                                                   Page 2 of 7
           The World Bank                                                                                    Implementation Status & Results Report
           Poyang Lake Basin Town Water Environment Management Project (P153604)




    ►Volume(mass) of COD pollution load reduction achieved under the project (Tones/year, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                         435.03                       1,016.01                   1,896.00

    Date                             31-Dec-2016                  11-Jun-2021                  30-Nov-2021                31-Dec-2022

    IN01050066
    ►Nutrient load reduction (Nitrogen(N)) achieved under the project (Tones/year, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                         41.75                        112.96                     201.00

    Date                             31-Dec-2016                  11-Jun-2021                  30-Nov-2021                31-Dec-2022

    IN01050067
    ►Nutrient load reduction (Phosphorus(P)) achieved under the project (Tones/year, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                         5.71                         15.94                      22.00

    Date                             31-Dec-2016                  11-Jun-2021                  30-Nov-2021                31-Dec-2022

    IN01050068
    ►Industrial or municipal solid waste reduced or recycled under the project (Tones/year, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                         21,898.00                    32,577.00                  49,645.00

    Date                             31-Dec-2016                  11-Jun-2021                  30-Nov-2021                31-Dec-2022
                                      At MTR, it was agreed that this indicator only measures achievement in Shangli county. The quantity of
                                      domestic solid waste reduced or recycled under the project is based on the amount verified during the
   Comments:
                                      Nov 2021 mission.

    IN01050069
    ►Number of project counties that use participatory water quality management system. (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                         7.00                         7.00                       7.00

    Date                             31-Dec-2016                  11-Jun-2021                  11-Jun-2021                31-Dec-2022

                                      Participatory water environment activities have been ongoing in project counties.
   Comments:

    IN01050070
    ►Lake Management Platform established and operational (Text) (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                         1.00                         3.00                       6.00



12/17/2021                                                                                                                   Page 3 of 7
           The World Bank                                                                                  Implementation Status & Results Report
           Poyang Lake Basin Town Water Environment Management Project (P153604)




    Date                             31-Dec-2016                11-Jun-2021                  30-Nov-2021               31-Dec-2022
                                     The LMP development in Fengxin, Poyang and Duchang county are largely completed with trial
                                     operation. The other LMPs are at different stages of development with several scheduled for completion in
   Comments:
                                     the first quarter of 2022.



 Intermediate Results Indicators by Components



   Component 1: Institutional Strengthening for Water Management

    IN01050071
    ►Newly established water quality monitoring stations/sites (Number, Custom)

                                     Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                       13.00                        24.00                     49.00

    Date                             31-Dec-2016                11-Jun-2021                  30-Nov-2021               31-Dec-2022



   Component 2: Lake and River Restoration and Improvement of Wastewater Management

    IN01050074
    ►New household sewer connections constructed under the project - urban (Number, Custom)

                                     Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                       17,604.00                    33,625.00                 60,567.00

    Date                             31-Dec-2016                11-Jun-2021                  30-Nov-2021               31-Dec-2022

    IN01050076
    ►New household sewer connections constructed under the project - rural (Number, Custom)

                                     Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                       0.00                         0.00                      5,893.00

    Date                             31-Dec-2016                11-Jun-2021                  30-Nov-2021               31-Dec-2022

                                     The contract of the rural wastewater works was signed with the implementation at early stage.
   Comments:

    IN01050078
    ►Volume (mass) of BOD pollution load removed by the treatment plant under the project (Tones/year, Custom)

                                     Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                       187.46                       467.41                    710.00

    Date                             31-Dec-2016                11-Jun-2021                  30-Nov-2021               31-Dec-2022

    IN01050079
    ►Volume of sewage decreased to Poyang Lake (million m3/year) (Cubic meters/year, Custom)



12/17/2021                                                                                                                Page 4 of 7
           The World Bank                                                                                   Implementation Status & Results Report
           Poyang Lake Basin Town Water Environment Management Project (P153604)




                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        3.69                         6.54                      13.00

    Date                             31-Dec-2016                 11-Jun-2021                  30-Nov-2021              31-Dec-2022



   Component 3: Improvements in Solid Waste Management

   IN01050075
   ►Number of project counties that have a smart domestic solid waste management monitoring and control system operational (Number,
   Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        1.00                         2.00                      4.00

    Date                             27-Nov-2020                 11-Jun-2021                  30-Nov-2021              31-Dec-2022
                                      The smart domestic solid waste management monitoring and control system/platform in Jing'an county is
   Comments:                          partially functional and requires improvement.

    IN01050077
    ►Solid waste collection rate (Percentage, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            51.00                       80.00                        82.00                     80.00

    Date                             31-Dec-2016                 11-Jun-2021                  30-Nov-2021              31-Dec-2022



   Component 4: Project Implementation Support

    IN01050072
    ►Number of people trained for public participation (Number, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        26,646.00                    73,566.00                 90,000.00

    Date                             31-Dec-2016                 11-Jun-2021                  30-Nov-2021              31-Dec-2022

    IN01050073
    ►Number of people participated in domestic and international training and study tour for project implementation (Number, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        446.00                       446.00                    920.00

    Date                             31-Dec-2016                 11-Jun-2021                  30-Nov-2021              31-Dec-2022



 Performance-Based Conditions



 Data on Financial Performance


12/17/2021                                                                                                                 Page 5 of 7
           The World Bank                                                                                  Implementation Status & Results Report
           Poyang Lake Basin Town Water Environment Management Project (P153604)




 Disbursements (by loan)

 Project       Loan/Credit/TF    Status      Currency        Original   Revised     Cancelled     Disbursed      Undisbursed                % Disbursed


 P153604       IBRD-87040        Effective   USD             150.00      150.00           0.00         58.64           91.36                       39%


 Key Dates (by loan)

 Project        Loan/Credit/TF   Status      Approval Date       Signing Date     Effectiveness Date     Orig. Closing Date      Rev. Closing Date

 P153604        IBRD-87040       Effective   16-Mar-2017         06-Jun-2017      13-Oct-2017            31-Dec-2022             31-Dec-2022


Cumulative Disbursements




 PBC Disbursement

                                                                                       Achievement      Disbursed amount in         Disbursement %
 PBC ID                   PBC Type     Description            Coc       PBC Amount
                                                                                       Status           Coc                         for PBC




12/17/2021                                                                                                                    Page 6 of 7
         The World Bank                                                          Implementation Status & Results Report
         Poyang Lake Basin Town Water Environment Management Project (P153604)




  Restructuring History


  Level 2 Approved on 13-Jul-2020 ,Level Approved on 20-Aug-2020


  Related Project(s)


 There are no related projects.




12/17/2021                                                                                      Page 7 of 7