Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: 2015 2. Date of General Procurement Notice: July, 10, 2015 3. Period covered by this procurement plan: The Project Period II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,500,000 All 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 1,500,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guideline 4. Any Other Special Procurement Arrangements: Given the prevailing impact of the ISIS conflict on Iraq, and need to address the urgent and developing requirements, procurement is being processed under paragraph 20 of OP 11.00 “Procurement under Situations of Urgent Need of Assistance or Capacity Constraints”, where “Simplified Procurement Procedures” may apply in accordance with paragraph 12 of the Bank OP 10.00 for investment project financing33. Procurement activities of this Project will include goods, works and both non-consultancy and consultant services under different Components. As they are identified, the activities will be packaged and finalized. 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) July 9, 2010 Refer to the Procurement Plan III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Given the prevailing impact of the ISIS conflict on Iraq, and need to address the urgent and developing requirements, procurement is being processed under paragraph 20 of OP 11.00 “Procurement under Situations of Urgent Need of Assistance or Capacity Constraints”, where “Simplified Procurement Procedures” may apply in accordance with paragraph 12 of the Bank OP 10.00 for investment project financing33. Procurement activities of this Project will include goods, works and both non- consultancy and consultant services under different Components. As they are identified, the activities will be packaged and finalized. 4. Consultancy Assignments with Selection Methods and Time Schedule Refer to the Procurement Plan July 9, 2010 PROCUREMENT Iraq : Emergency Operation for Development PLAN General Information Country: Iraq 2017-09-11 Bank’s Approval Date of the Original Procurement Plan: 2022-11-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155732 GPN Date: Project Name: Emergency Operation for Development Loan / Credit No: IBRD / 85200, IBRD / 87930 Ministry of Municipalities and Public Works - Roads & Bridges Directorate Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EODP/MOCHPM/W2/3 / Maint Restoring Electricity Infrastr 9,011,223.0 enance of 20 KM of Khanaqin IBRD / 85200 Prior Direct Selection Direct Signed 2016-04-04 ucture and Connectivity 5 - Naft Khanna Road in Diyala Governorate EODP/MOCHPM/W8 / Rehabil Restoring Electricity Infrastr 4,296,601.9 itation of Al-Muthana Bridge ( IBRD / 85200 Prior Direct Selection Direct Signed 2016-08-10 ucture and Connectivity 4 North Baghdad) EODP/MOCHPM/W10/1 / Reh Restoring Electricity Infrastr abilitation of New and Old Al- IBRD / 85200 Prior Direct Selection Direct 952,321.28 Signed 2016-04-04 ucture and Connectivity Haronyah Bridges in Diyala G overnorate EODP/MOCHPM/W10/2 / Reh Restoring Electricity Infrastr 1,908,996.2 abilitation (4) & (7) Imam Wa IBRD / 85200 Prior Direct Selection Direct Signed 2016-04-04 ucture and Connectivity 9 ys Bridges in Diyala Governo rate EODP/MOCHPM/W10/7 / Reh abilitation of Steel & Concret Restoring Electricity Infrastr 1,622,873.8 IBRD / 85200 Prior Direct Selection Direct Signed 2016-04-04 e Bridge at Noreen river (on ucture and Connectivity 9 Qarataba - Omarmandan roa d) in Diyala Governorate EODP/MOCHPM/W10/3 / Reh Restoring Electricity Infrastr abilitation of Al-Suodoor Brid IBRD / 85200 Prior Direct Selection Direct 954,336.58 Signed 2016-04-04 ucture and Connectivity ge in Diyala Governorate EODP/MOCHPM/W2/2 / Maint Restoring Electricity Infrastr 9,227,740.8 enance of 42.5KM OF Naft Kh IBRD / 85200 Prior Direct Selection Direct Signed 2016-04-04 ucture and Connectivity 7 anna -Mimili Road in Diyala G overnorate EODP/MOCHPM/W5 / Rehabil itation of Al-Sheesheen Bridg Restoring Electricity Infrastr 2,124,471.8 IBRD / 85200 Prior Direct Selection Direct Signed 2016-04-04 es (left & right sides) in Salah ucture and Connectivity 5 Ad-Din Governorate EODP/MOCHPM/W7 / Rehabil itation of Al-Dhuluiya big & s Restoring Electricity Infrastr 4,788,393.2 IBRD / 85200 Prior Direct Selection Direct Signed 2016-04-04 mall Bridges and Approaches ucture and Connectivity 0 in Salah Ad-Din Governorate EODP/MOCHPM/W3/R1 / Reh Restoring Transport Infrastru abilitation of Sammarra diver cture and Developing a Hous Open - Internationa Single Stage - One E Pending Imp 2019-04-3 IBRD / 85200 Prior Request for Bids 0.00 2017-04-16 2017-06-21 2017-07-26 2017-08-31 2017-10-02 sion bridge and Approaches ( ing Reconstruction Subsidy l nvelope lementation 0 on Baghdad-Muosel road) Scheme EODP-AF/MOCHPM/W1-M / R Restoring Transport Infrastru 8,611,834.2 2019-12-1 ehabilitation of Mosel 2nd bri IBRD / 87930 cture and Developing a Hous Prior Direct Selection Direct Signed 2018-12-10 2018-12-10 2018-12-12 2018-12-26 6 2 dge ing Reconstruction Subsidy Scheme EODP-AF/MOCHPM/W4-A/1 / Restoring Transport Infrastru Rehabilitation of Fallujah inte cture and Developing a Hous Single Stage - One E 2,676,050.0 2020-02-2 IBRD / 87930 Post Request for Bids Open - National Signed 2018-12-25 2019-05-22 2019-01-02 2019-01-23 2019-06-17 2019-02-07 2019-07-11 2019-02-21 2019-10-09 rchange (Right & Left ) at sta ing Reconstruction Subsidy nvelope 0 1 tion 29 on Expressway No.1 Scheme / R9 EODP-AF/MOCHPM/W4-A/2 / Restoring Transport Infrastru Rehabilittaion of two bridges cture and Developing a Hous Single Stage - One E 2,761,400.0 2019-12-1 (underpass bridges ) at statio IBRD / 87930 Post Request for Bids Open - National Signed 2018-12-25 2019-05-27 2019-01-02 2019-01-23 2019-06-17 2019-02-07 2019-07-11 2019-02-21 2019-10-09 ing Reconstruction Subsidy nvelope 0 8 n 31.2 & 51+culverts betwee Scheme n two stations on Expresswa y No1/ R9 EODP/MOCHPM/W2/10/A / Th Restoring Transport Infrastru e Rehabilitation of Al-Khalis - cture and Developing a Hous Open - Internationa Single Stage - One E 2020-06-1 IBRD / 85200 Prior Request for Bids 0.00 Canceled 2018-10-16 2018-10-18 2018-10-17 2018-10-18 2018-11-14 2018-12-02 2018-12-05 2018-12-17 Adheem road (on Baghdad-Ki ing Reconstruction Subsidy l nvelope 4 rkuk road)-Part A Scheme EODP/MOCHPM/W6 / Rehabil Restoring Transport Infrastru 8,475,654.0 2018-07-2 itation of Tikreet bridge (on T IBRD / 85200 cture and Developing a Hous Prior Direct Selection Direct Signed 2017-05-29 2017-06-14 2017-08-24 2017-08-24 5 0 ikreet-Alam road) ing Reconstruction Subsidy Scheme EODP-AF/MOCHPM/W4-A/3-P Restoring Transport Infrastru ART 1 / Rehabilittaion of culv cture and Developing a Hous Single Stage - One E 5,485,707.0 2020-09-0 IBRD / 87930 Prior Request for Bids Open - National Signed 2019-07-07 2019-09-18 2019-07-12 2019-10-12 2019-08-02 2019-11-11 2019-08-16 2020-02-24 2019-09-06 2020-03-04 erts between(s0.0-s28.8km) ing Reconstruction Subsidy nvelope 0 5 and stations (s52-s90km)on Scheme Expressway No1/ R9 EODP-AF/MOCHPM/W4-A/3-P Restoring Transport Infrastru ART 2 / Rehabilitation of culv cture and Developing a Hous Single Stage - One E 6,528,518.7 Under Revie 2020-09-0 IBRD / 87930 Prior Request for Bids Open - National 2019-07-07 2019-09-18 2019-07-12 2019-10-12 2019-08-02 2019-11-11 2019-08-16 2020-01-22 2019-09-06 2020-01-30 erts between(St90 R9 -St11 ing Reconstruction Subsidy nvelope 0 w 5 R10) and rehabilitation of bri Scheme dge at station (St11 R10) EODP-AF/MOCHPM/W4-A/4 / Restoring Transport Infrastru Rehabilitation of WADI HORA cture and Developing a Hous Single Stage - One E 3,334,380.0 2020-09-1 IBRD / 87930 Post Request for Bids Open - National Signed 2019-07-10 2019-07-23 2019-07-16 2019-07-23 2019-08-06 2019-08-27 2019-08-27 2019-10-21 2019-09-13 2019-10-07 N BRIDGE + Two bridges at s ing Reconstruction Subsidy nvelope 0 2 tation(St361 ,St 262 KM) Scheme EODP-AF/MOCHPM/W4-A/5 / Restoring Transport Infrastru Rehabilitation of Two bridges cture and Developing a Hous Single Stage - One E 2,227,330.0 2020-09-1 IBRD / 87930 Post Request for Bids Open - National Signed 2019-07-10 2019-07-23 2019-07-16 2019-07-23 2019-08-06 2019-08-27 2019-08-27 2019-12-02 2019-09-13 2019-12-15 at stations (St 335 ,St 355km ing Reconstruction Subsidy nvelope 0 2 ) on Expressway No.1/ R9 Scheme EODP-AF/MOCHPM/W4-A/6 / Restoring Transport Infrastru Rehabilitation of Two bridges cture and Developing a Hous Single Stage - One E 2,540,000.0 2020-09-1 IBRD / 87930 Post Request for Bids Open - National Signed 2019-07-10 2019-07-23 2019-07-16 2019-07-23 2019-08-06 2019-08-27 2019-08-27 2019-09-17 2019-09-13 2019-09-26 at stations (St 313 ,St 280km ing Reconstruction Subsidy nvelope 0 2 ) on Expressway No.1/ R9 Scheme Page 1 EODP/MOCHPM/W2/10/A/R1 Restoring Transport Infrastru / The Rehabilitation of Al-Kha cture and Developing a Hous Open - Internationa Single Stage - One E 12,093,100. 2020-12-1 IBRD / 85200 Prior Request for Bids Signed 2019-07-03 2019-09-17 2019-07-13 2019-09-17 2019-08-10 2019-08-07 2019-09-07 2019-09-18 2019-09-21 2019-11-14 lis -Adheem road (on Baghda ing Reconstruction Subsidy l nvelope 00 4 d-Kirkuk road)-Part A Scheme EODP-AF/MOCHPM/W2/10/B Restoring Transport Infrastru / REHABILITATION & MAINTE cture and Developing a Hous Open - Internationa Single Stage - One E 11,611,953. 2021-06-3 IBRD / 87930 Prior Request for Bids Signed 2020-01-24 2020-02-11 2020-01-31 2020-04-01 2020-02-28 2020-04-29 2020-03-20 2020-10-24 2020-04-06 2020-12-13 NANCE OF KHALIS- ETHAIM ing Reconstruction Subsidy l nvelope 00 0 HIGHWAY 50 KM (Part 2) Km Scheme 38 -Km 63 EODP-AF/MOCHPM/W5/R1 / Restoring Transport Infrastru REHABILITATION OF 30 KM O cture and Developing a Hous Open - Internationa Single Stage - One E 11,438,660. 2021-06-3 IBRD / 87930 Prior Request for Bids Signed 2020-01-24 2020-02-09 2020-01-31 2020-03-31 2020-02-28 2020-04-29 2020-03-20 2020-10-24 2020-04-06 2020-12-21 F AL SHERQAT intersection - ing Reconstruction Subsidy l nvelope 00 0 RAMADHANYAT ROAD (TWO Scheme WAY) EODP-AF/MOCHPM/W2-M / R Restoring Transport Infrastru Open - Internationa Single Stage - One E 2022-04-3 ehabilitation of mosel 4th bri IBRD / 87930 cture and Developing a Hous Prior Request for Bids 0.00 Canceled 2020-01-27 2020-02-09 2020-02-03 2020-04-20 2020-03-16 2020-04-29 2020-04-13 2020-08-30 2020-04-30 l nvelope 0 dge crossing tigris river ing Reconstruction Subsidy Scheme EODP-AF/MOCHPM/W3-M / R Restoring Transport Infrastru Open - Internationa Single Stage - One E 2022-05-0 ehabilitation of mosel 5th bri IBRD / 87930 cture and Developing a Hous Prior Request for Bids 0.00 Canceled 2020-01-27 2020-02-09 2020-02-06 2020-04-20 2020-03-19 2020-04-29 2020-04-16 2020-09-18 2020-05-03 l nvelope 3 dge crossing tigris river ing Reconstruction Subsidy Scheme EODP/MOCHPM/W11 / Rehab Restoring Transport Infrastru ilitation of Al-Baqaq Concrete cture and Developing a Hous 2,475,402.3 2021-04-2 IBRD / 85200 Post Direct Selection Direct Signed 2020-08-10 2020-07-02 2020-08-10 2020-06-18 2020-08-24 2020-09-22 Bridge and Approaches in Ni ing Reconstruction Subsidy 4 1 neveh Governorate Scheme EODP-AF/MOCHPM/W2-M/R1 Restoring Transport Infrastru Open - Internationa Single Stage - One E 12,336,405. 2022-03-1 / Rehabilitation of mosel 4th IBRD / 87930 cture and Developing a Hous Prior Request for Bids Signed 2020-09-14 2020-09-30 2020-09-20 2020-10-01 2020-10-18 2020-11-03 2020-11-17 2020-12-24 2020-12-22 2021-03-18 l nvelope 00 7 bridge crossing tigris river (r ing Reconstruction Subsidy ebidding) Scheme EODP-AF/MOCHPM/K-W1 / M Restoring Transport Infrastru aintenance of (32.11) Km of cture and Developing a Hous Single Stage - One E 3,904,800.0 Under Revie 2021-12-0 IBRD / 87930 Prior Request for Bids Open - National 2020-09-18 2021-09-16 2020-09-22 2021-09-28 2020-10-13 2021-10-27 2020-11-03 2021-12-14 2020-12-07 2022-01-24 KIRKUK-MANZALAH-HAWIJAH ing Reconstruction Subsidy nvelope 0 w 7 ROAD in Kirkuk Governorate Scheme EODP-AF/MOCHPM/K-W2 / R Restoring Transport Infrastru Single Stage - One E 2021-08-0 ehabilitation of Maktab Khali IBRD / 87930 cture and Developing a Hous Post Request for Bids Open - National 844,130.00 Signed 2020-09-18 2020-09-22 2020-09-22 2021-11-23 2020-10-13 2021-12-15 2020-11-10 2021-12-30 2020-12-09 2022-03-16 nvelope 6 d Bridge in Kirkuk Governora ing Reconstruction Subsidy te Scheme EODP-AF/MOCHPM/K-W3 / R Restoring Transport Infrastru Single Stage - One E 1,407,500.0 2021-10-2 ehabilitation Sadar Al-Nahr B IBRD / 87930 cture and Developing a Hous Post Request for Bids Open - National Signed 2020-09-28 2021-11-23 2020-10-11 2021-11-23 2020-11-01 2021-12-15 2020-12-01 2022-03-28 2020-12-29 2022-05-22 nvelope 0 5 ridge in Kirkuk Governorate ing Reconstruction Subsidy Scheme EODP-AF/MOCHPM/B-SW1 / Restoring Transport Infrastru Request for Quota Single Stage - One E Pending Imp 2021-03-1 Renovation of Elevators of R IBRD / 87930 cture and Developing a Hous Post Limited 0.00 2020-09-21 2020-11-15 tions nvelope lementation 5 BD Building ing Reconstruction Subsidy Scheme EODP-AF/MOCHPM/W3-M/R1 Restoring Transport Infrastru Open - Internationa Single Stage - One E 15,563,940. 2022-03-1 / Rehabilitation of mosel 5th IBRD / 87930 cture and Developing a Hous Prior Request for Bids Signed 2020-09-23 2020-10-26 2020-09-27 2020-10-26 2020-10-25 2020-12-01 2020-11-24 2021-01-15 2020-12-21 2021-05-24 l nvelope 00 6 bridge crossing tigris river (r ing Reconstruction Subsidy ebidding) Scheme Request for EODP-AF/MOCHPM/W5-M / R Restoring Transport Infrastru Quotations - ehabilitation of Al-Baqaq (old cture and Developing a Hous Small Works Pending Imp 2023-07-2 IBRD / 87930 Post Direct Selection Direct - National 0.00 2022-11-30 2022-12-10 2023-01-29 Bridge ) and Approaches in N ing Reconstruction Subsidy (Emergency) lementation 8 ineveh Governorate Scheme SPD -Non Co mpetitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOCH/G1 / Procurement of P Restoring Electricity Infrastr IBRD / 85200 Prior Direct Selection Direct 11,018,664.00 Signed 2015-12-10 refabricated Steel Panels ucture and Connectivity NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOCHPM/C7 / Construction S Restoring Transport Infrastru Quality And Cost- Open - Internationa upervision (AL KHALIS ADHEE IBRD / 85200 cture and Developing a Hous Prior 1,222,410.00 Signed 2018-10-16 2019-08-01 2018-10-17 2018-10-17 2018-11-05 2019-01-10 2018-11-28 2019-03-05 2018-12-12 2019-08-02 2018-12-24 2020-06-20 2019-01-14 2019-12-12 2020-07-12 Based Selection l M ROAD ) ing Reconstruction Subsidy Scheme EODP-AF/MOCHPM/M-C1 / C Restoring Transport Infrastru ONSTRUCTION SUPERVISION cture and Developing a Hous Quality And Cost- Open - Internationa IBRD / 87930 Prior 388,800.00 Signed 2018-12-10 2018-12-11 2018-12-12 2019-01-03 2019-01-07 2019-02-27 2019-01-21 2019-04-18 2019-02-03 2019-06-04 2019-02-11 2019-06-23 2020-02-11 SEVRICES FOR MOSUL 2ND B ing Reconstruction Subsidy Based Selection l RIDGE (AL HURRIYA) Scheme EODP-AF/MOCHPM/A-C4 / (D esign Review and constructio Restoring Transport Infrastru n supervision ) For Damaged cture and Developing a Hous Quality And Cost- Open - Internationa Under Implement IBRD / 87930 Prior 0.00 2019-07-15 2019-09-25 2019-07-18 2019-09-25 2019-08-09 2019-12-27 2019-08-30 2020-01-30 2019-09-09 2020-05-07 2019-09-23 2019-10-07 2020-10-06 Wadi bridges (under passes ) ing Reconstruction Subsidy Based Selection l ation and over pass along the we Scheme stern stretch of expressway No.1 EODP-AF/MOCHPM/M-C2 / Co Restoring Transport Infrastru nsultancy services (Design R cture and Developing a Hous Quality And Cost- Open - Internationa IBRD / 87930 Prior 806,720.00 Signed 2019-10-03 2020-01-22 2019-10-10 2019-11-07 2021-02-02 2019-12-05 2020-04-22 2019-12-19 2021-03-15 2020-01-09 2021-05-05 2020-01-23 2021-06-01 2022-01-22 eview and construction super ing Reconstruction Subsidy Based Selection l vision ) for mosel 4th bridge Scheme EODP-AF/MOCHPM/M-C3 / Co Restoring Transport Infrastru nsultancy services (Design R cture and Developing a Hous Quality And Cost- Open - Internationa IBRD / 87930 Prior 824,838.40 Signed 2019-10-03 2020-01-22 2019-10-10 2020-01-23 2019-11-07 2020-04-23 2019-12-05 2020-05-21 2019-12-19 2021-11-22 2020-01-09 2022-02-01 2020-01-23 2022-04-21 2020-04-05 eview and construction super ing Reconstruction Subsidy Based Selection l vision ) for mosel5th bridge Scheme Page 2 EODP-AF/MOCHPM/D-C6 / Co Restoring Transport Infrastru nstruction Supervision of RE cture and Developing a Hous Quality And Cost- Open - Internationa Under Implement IBRD / 87930 Prior 0.00 2020-09-17 2020-11-11 2020-09-22 2020-11-17 2020-10-22 2021-01-18 2020-11-19 2021-02-18 2020-11-20 2021-03-30 2020-12-25 2021-06-07 2021-01-29 2022-01-29 HABILITATION & MAINTENAN ing Reconstruction Subsidy Based Selection l ation CE OF KHALIS- ETHAIM HIGH Scheme WAY Part (2) EODP-AF/MOCHPM/S-C7 / Co Restoring Transport Infrastru nstruction Supervision of RE cture and Developing a Hous Quality And Cost- Open - Internationa HABILITATION OF 30 KM OF A IBRD / 87930 Prior 868,550.00 Signed 2020-09-18 2020-10-24 2020-10-09 2020-10-27 2020-11-08 2020-12-17 2020-11-29 2021-01-18 2020-12-20 2021-03-02 2021-01-24 2021-03-22 2021-02-28 2021-04-18 2022-02-28 ing Reconstruction Subsidy Based Selection l L SHERQAT intersection - RA Scheme MADHANYAT ROAD (TWO WA Y) EODP-AF/MOCHPM/K-C9 / Co Restoring Transport Infrastru Quality And Cost- Open - Internationa Under Implement nstruction Supervision of Kirk IBRD / 87930 cture and Developing a Hous Post 0.00 2020-09-28 2020-09-26 2020-10-19 2021-07-29 2020-12-02 2020-12-30 2021-01-29 2021-03-05 2021-04-08 2021-04-10 Based Selection l ation uk projects (Two Bridges and ing Reconstruction Subsidy one Road) Scheme INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EODP-AF/MOCHPM/M4-D1 / Restoring Transport Infrastru Consultancy services Design IBRD / 87930 cture and Developing a Hous Post Direct Selection Direct 160,000.00 Signed 2019-07-21 2019-07-24 2019-07-24 2019-08-27 2019-07-31 2019-09-30 2019-10-29 for mosel 4th bridge ing Reconstruction Subsidy Scheme EODP-AF/MOCHPM/M5-D2 / Restoring Transport Infrastru Consultancy services Design IBRD / 87930 cture and Developing a Hous Post Direct Selection Direct 100,000.00 Signed 2019-07-21 2019-07-24 2019-07-24 2019-08-27 2019-07-31 2019-09-26 2019-10-29 for mosel 5th bridge ing Reconstruction Subsidy Scheme MOCHPM/C11 / Construction Restoring Transport Infrastru Under Implement supervision (Tikrit ala alm bri IBRD / 85200 cture and Developing a Hous Post Direct Selection Direct 0.00 2019-08-20 2019-09-12 2019-08-22 2019-08-29 2020-11-21 ation dge ing Reconstruction Subsidy Scheme EODP-AF/MOCHPM/M-C8 / As Restoring Transport Infrastru Individual Consult Under Implement sessment of Safety of Renov IBRD / 87930 cture and Developing a Hous Post Limited 0.00 2020-09-20 2020-10-01 2020-09-25 2020-10-19 2020-10-09 2020-11-06 2021-05-05 ant Selection ation ation Work for mosel 2nd bri ing Reconstruction Subsidy dge Scheme EODP-AF/MOCHPM/R-C11 / R Restoring Transport Infrastru Individual Consult Pending Impleme oad Safety Audit for EODP-AF IBRD / 87930 cture and Developing a Hous Post Limited 0.00 2022-04-24 2022-04-29 2022-05-13 2022-06-02 2022-11-29 ant Selection ntation contracts under RBD compon ing Reconstruction Subsidy ent Scheme EODP/MOCHPM/T-C10 / Train Restoring Transport Infrastru Direct - Internation Under Implement ing of PMT and RE's on the co IBRD / 85200 cture and Developing a Hous Post Direct Selection 0.00 2022-08-15 2022-08-16 2022-08-25 2022-09-29 2022-10-29 2023-04-27 al ation ntract management of FIDIC ing Reconstruction Subsidy contracts Scheme Page 3