Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other July 9, 2010 methods July 9, 2010 PROCUREMENT China : Poyang Lake Basin Town Water Environment Management Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2018-04-23 2022-01-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153604 GPN Date: 2017-10-16 Project Name: Poyang Lake Basin Town Water Environment Management Project Loan / Credit No: IBRD / 87040 P Executing Agency(ies): oyang Lake PMO WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned JAX-CW-02 / Civil works construction for 1 water quality monitoring and control Component 2: Lake and River Single Stage - One 2,760,852.3 2019-12- center, 3 river-side water IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 2,582,200.00 Signed 2018-04-18 2020-06-01 2018-04-18 2018-05-18 2018-05-10 2018-05-28 2018-05-15 2018-07-02 2018-07-10 Envelope 3 24 quality automatic monitoring of Wastewater Management stations and 9 water quality test&report points JSX-CW-01 / 27356m sewera ge pipe, 531 sets of accessor y structures 15200m rain pip Component 2: Lake and River Single Stage - One 18,340,100.0 13,034,238. 2020-01- e, rain pipe accessory structur IBRD / 87040 Restoration and Improvement Prior Request for Bids Open - National Signed 2018-04-18 2019-04-08 2018-05-08 2019-04-23 2018-06-19 2019-05-23 2018-06-26 2020-02-07 2018-07-31 2020-03-16 Envelope 0 80 22 es, and one unit of Extension of Wastewater Management sewerage pump station from 10000m3/d to 15000m3/d DCX-CW-02 / 11344m sewerage pipe network, 8742m rain pipe, 340 units of sewerage pipe accessory Component 2: Lake and River Single Stage - One 9,692,969.5 2020-04- structures, 249 units of rain IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 9,630,200.00 Signed 2018-08-14 2020-05-31 2018-08-15 2020-05-30 2018-09-24 2018-10-20 2018-10-01 2018-10-20 2018-11-05 2019-03-12 Envelope 0 28 pipe accessory structures, of Wastewater Management 4000m household connecting pipes, 52980 square meter of road demolition and recovery. FXX-CW-02 / Sewerage pipe network works in the south district of Fengxin county (The diameter of rainwater Component 2: Lake and River pipe d300-d1650 with total Single Stage - One 5,747,554.7 2020-10- IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 6,100,000.00 Signed 2019-07-08 2019-07-12 2019-07-08 2019-08-06 2019-08-12 2019-09-05 2019-08-12 2019-10-06 2019-09-30 length 4549m, sewage pipe Envelope 5 05 of Wastewater Management diameter DN200-DN600 with total length 4484m, sewage pressure pipe 215m, traction pipe 77m and road repair) FXX-CW-03 / Fengxin county Pump station lift supply and installation and ancillary civil engineering (an integrated Component 2: Lake and River Under Single Stage - One 2020-08- sewage pumping station, with IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 6,120,000.00 0.00 Implementat 2019-07-21 2019-08-18 2019-07-22 2019-09-09 2019-07-25 2019-07-26 2019-08-03 Envelope 02 a recent scale of 4000m3/d of Wastewater Management ion and a long-term scale of 8000m3/d; an integrated irrigation pumping station) FXX-CW-01 / Sewerage pipe network works in the north district of Fengxin county (The diameter of rainwater Component 2: Lake and River Under pipe is d300-d1800 with total Single Stage - One 15,690,000.0 2020-09- IBRD / 87040 Restoration and Improvement Prior Request for Bids Open - National 0.00 Implementat 2019-07-21 2019-08-02 2019-07-26 2019-08-21 2019-08-25 2019-09-26 2019-09-04 2019-10-20 2019-09-30 length 13843m, sewage pipe Envelope 0 29 of Wastewater Management ion diameter DN150-DN1200 with total length 11476m, pipe 635m, channel 789.1m, box culvert 1222.1m etc.) JSX-CW-02 / The integration Component 2: Lake and River Under Single Stage - One 2020-11- of sewerage pumping station IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 743,900.00 0.00 Implementat 2019-09-01 2020-04-13 2019-09-06 2019-10-07 2019-10-14 2019-11-18 Envelope 17 civil Works. of Wastewater Management ion DCX-CW-01 / Construct 4.34km sewerage inception pipeline of HDPE DN300-1000 Component 2: Lake and River pipes, rehabilitate 1.65km of Single Stage - One 2021-05- IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 8,181,800.00 0.00 Canceled 2019-09-09 2019-09-10 2019-09-14 2019-10-21 2019-10-21 2019-10-31 2019-11-07 2019-11-26 a small river, undertake Envelope 19 of Wastewater Management wetlands restoration, landscaping and ancillary facilities, etc. DCX-CW-01A / Rebidding description:Newly-built sewage intercepting trunk pipe 4.34 kilometers; Component 2: Lake and River renovating1. 65 km long river Single Stage - One 8,319,955.0 2021-10- IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 8,181,800.00 Signed 2020-01-10 2020-01-20 2020-01-15 2020-02-26 2020-03-24 2020-03-27 2020-03-24 2020-05-01 2020-04-29 section, 167,243 square Envelope 3 23 of Wastewater Management meters of land area and 119,576 square meters of water area; wetland restoration, landscaping etc. FXX-CW-01A / Rebidding description: Rainwater pipe diameter d300-d1800 with total length 13843m, sewage Component 2: Lake and River pipe diameter DN150- Single Stage - One 17,480,000.0 10,374,449. 2021-09- IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National Signed 2020-02-14 2020-03-10 2020-02-28 2020-03-29 2020-04-13 2020-04-08 2020-04-14 2020-05-04 2020-06-02 DN1200 with total length Envelope 0 08 13 of Wastewater Management 11476m, pipe 635m, channel 789.1m, box culvert 1222.1m, dredging 4929m,and road repair etc. Page 1 JAX-CW-01 / The construction of a new drainage pipe network of 38.124km ,of which, sewage Component 2: Lake and River Pending pipe 37.986 km (including Single Stage - One 10,663,600.0 2022-02- IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 0.00 Implementat 2020-05-11 2020-05-16 2020-06-27 2020-07-27 2020-08-31 sewage pipe linked to the Envelope 0 22 of Wastewater Management ion household), storm pipe 0.138 km; Existing old pipe network desilting and rehabilitating 24.16 km. JSX-CW-03 / Civil works cons truction for water quality moni toring station and points in Jis Component 1: Institutional hui country 1 water quality Single Stage - One 2021-12- IBRD / 87040 Strengthening for Water Post Request for Bids Open - National 757,600.00 841,590.53 Signed 2020-11-06 2020-11-02 2020-11-11 2020-12-23 2020-12-03 2021-01-22 2020-12-03 2021-02-26 2021-01-18 monitoring and control center Envelope 31 Management and civil works construction f or 2 water quality automatic monitoring stations on shore. YGX-CW-01 / Urban sewage Component 2: Lake and River Single Stage - One 19,903,300.0 10,919,849. 2021-11- collection pipe network IBRD / 87040 Restoration and Improvement Prior Request for Bids Open - National Signed 2021-01-29 2021-03-17 2021-02-03 2021-03-17 2021-04-20 2021-04-16 2021-05-05 2021-05-21 2021-06-05 Envelope 0 06 17 project in Yugan county. of Wastewater Management SLX-CW-01 / Civil works construction and affiliated euipment supply and installation for garbage Under Component 3: Improvements 2021-11- collection station (green IBRD / 87040 Post Request for Bids 8,589,900.00 0.00 Implementat 2021-01-29 2021-04-26 2021-02-03 2021-03-17 2021-04-26 2021-04-16 2021-04-26 2021-05-21 in Solid Waste Management 17 banks), garbage collection ion connecting roads and solid waste transportation station in Shangli county. YGX-CW-02 / Yugan County pumping station upgrade, Component 2: Lake and River Under Single Stage - One 2021-11- supply installation and IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 560,000.00 0.00 Implementat 2021-01-29 2021-02-01 2021-02-03 2021-03-17 2021-04-16 2021-05-21 Envelope 17 auxiliary civil engineering of Wastewater Management ion project. PYX-CW-01 / Rural sewage Component 2: Lake and River Under collection pipe network and Single Stage - One 13,092,200.0 2021-12- IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 0.00 Implementat 2021-02-26 2021-06-04 2021-03-03 2021-04-14 2021-07-07 2021-05-14 2021-07-07 2021-06-18 treatment project in zhuhu Envelope 0 15 of Wastewater Management ion river basin of Poyang County. PYX-CW-02 / Urban sewage Component 2: Lake and River Under Single Stage - One 14,555,800.0 2021-12- collection pipe network IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 0.00 Implementat 2021-02-26 2021-04-28 2021-03-03 2021-12-19 2021-04-14 2021-07-08 2021-05-14 2021-07-08 2021-06-18 Envelope 0 15 project in Poyang county. of Wastewater Management ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Under JX-EP-01 / computers, Component 4: Project Request for Single Stage - One IBRD / 87040 Post Limited 115,200.00 0.00 Implementati 2018-01-01 2018-03-07 2018-09-03 printing machines etc. Implementation Support Quotations Envelope on JAX-EP-01 / Jin'an Water Monitoring and River-Lake Management Platform. It includes service system for county border cross-section Component 1: Institutional Single Stage - One water quality automatic IBRD / 87040 Strengthening for Water Prior Request for Bids Open - National 5,673,800.00 4,959,706.23 Signed 2019-12-10 2020-04-19 2019-12-15 2020-01-26 2020-06-11 2020-02-25 2020-07-23 2020-03-31 2020-08-25 2020-09-27 Envelope monitoring stations , Management township cross-section water quality automatic reporting points, monitoring services etc. JAX-EP-03 / Various desks, Component 4: Project Request for Single Stage - One chairs and filing cabinets etc. IBRD / 87040 Post Open - National 87,900.00 86,381.03 Signed 2020-04-25 2020-06-20 2020-06-19 2020-12-17 Implementation Support Quotations Envelope for the control center. JAX-EP-04 / Printers, portable computers, video conference tablet computers, conference room liquid crystal Component 4: Project Request for Single Stage - One IBRD / 87040 Post Open - National 116,700.00 111,061.39 Signed 2020-04-25 2020-06-20 2020-08-10 2020-12-17 display systems (including two- Implementation Support Quotations Envelope color LED display), projector LED display (for door), air conditioners and other sets. Component 4: Project Request for Single Stage - One JAX-EP-05 / 1 set of elevator IBRD / 87040 Post Open - National 63,000.00 62,762.13 Signed 2020-04-25 2020-06-20 2020-06-17 2020-12-17 Implementation Support Quotations Envelope SLX-EP-02 / 14 3T compression trucks, 16 8t compression trucks, 6 street sweepers (5 tons), 4 street Under Component 3: Improvements Single Stage - One sweepers (8 tons), 10 IBRD / 87040 Post Request for Bids Open - National 5,476,600.00 0.00 Implementati 2020-07-17 2020-07-17 2020-07-22 2020-07-20 2020-09-02 2020-08-19 2020-10-02 2020-08-19 2020-10-30 2021-01-28 in Solid Waste Management Envelope sprinkler trucks (12 tons), 11 on sprinkler trucks (4 tons), 13 14T waste transfer trucks and 8 suction trucks. FXX-EP-01 / Sewage pipe Component 3: Improvements Request for Single Stage - One dredging and suction utility IBRD / 87040 Post Limited 90,900.00 92,494.49 Signed 2020-07-22 2020-12-10 2020-09-16 2021-01-04 2021-03-15 in Solid Waste Management Quotations Envelope vehicle JSX-EP-01 / water environment monitoring, and Component 3: Improvements Single Stage - One digital integration system and IBRD / 87040 Prior Request for Bids Open - National 3,539,700.00 0.00 Canceled 2020-08-11 2020-08-11 2020-08-16 2020-09-27 2020-09-29 2020-10-27 2021-02-08 2020-12-01 2021-05-30 in Solid Waste Management Envelope equipment procurement for LMP Page 2 SLX-EP-01 / water environment monitoring, solid waste collection and transfer monitoring, and the extension of digital integration system Component 3: Improvements Single Stage - One IBRD / 87040 Prior Request for Bids Open - National 4,818,200.00 0.00 Canceled 2020-08-11 2020-08-30 2020-08-16 2020-09-27 2020-10-13 2020-10-27 2021-02-04 2020-12-01 2021-05-30 and equipment procurement in Solid Waste Management Envelope for LMP; monitoring equipment procurement and auxiliary civil works construction,etc. FXX-EP-02 / Extension of water environment monitoring and LMP digital integration Component 1: Institutional Single Stage - One system, monitoring IBRD / 87040 Strengthening for Water Prior Request for Bids Open - National 2,349,300.00 1,688,177.01 Signed 2020-10-19 2020-10-19 2020-10-24 2020-12-05 2020-12-01 2021-01-04 2020-12-30 2021-02-08 2021-02-01 2021-08-07 Envelope equipment procurement and Management auxiliary civil works construction. DCX-EP-01 / Water environment monitoring, solid waste collection and transfer Component 1: Institutional Under Single Stage - One monitoring, and LMP digital IBRD / 87040 Strengthening for Water Post Request for Bids Open - National 1,212,100.00 769,912.65 Implementati 2020-10-19 2020-11-06 2020-10-24 2020-12-05 2020-12-09 2021-01-04 2020-12-09 2021-02-08 2021-08-07 Envelope integration and equipment Management on and auxiliary civil works construction,etc. JAX-EP-02 / 1 set of patrol Component 1: Institutional Under Request for Single Stage - One boat, 12 sets of garbage IBRD / 87040 Strengthening for Water Post Open - National 165,300.00 174,414.30 Implementati 2020-10-16 2020-12-11 2021-06-09 Quotations Envelope salvage vessel. Management on PYX-EP-01 / Water environment monitoring and Component 1: Institutional LMP digital integration and Single Stage - One IBRD / 87040 Strengthening for Water Prior Request for Bids Open - National 2,679,800.00 2,723,126.35 Signed 2020-11-27 2021-01-25 2020-12-02 2021-01-13 2021-03-23 2021-02-12 2021-03-31 2021-03-19 2021-04-30 2021-09-15 equipment and auxiliary civil Envelope Management works construction in Poyang country YGX-EP-01 / Water environm ent monitoring, solid waste co llection and transfer monitorin g, and LMP digital integration Component 1: Institutional Single Stage - One system and equipment and au IBRD / 87040 Strengthening for Water Prior Request for Bids Open - National 3,487,400.00 2,630,760.69 Signed 2020-11-27 2020-12-30 2020-12-02 2021-01-13 2021-02-22 2021-02-12 2021-03-04 2021-03-19 2021-05-24 2021-09-15 Envelope xiliary civil works construction Management in Yugan country etc; On line detection of water quality in u rban sewage pipe network. SLX-EP-01A / Solid waste collection and transfer monitoring; water environment monitoring and Component 1: Institutional Single Stage - One digital integration system and IBRD / 87040 Strengthening for Water Prior Request for Bids Open - National 4,818,200.00 2,521,848.75 Signed 2021-03-01 2021-03-04 2021-03-06 2021-04-17 2021-04-14 2021-05-17 2021-06-17 2021-06-21 2021-07-15 2021-12-18 Envelope equipment procurement for Management LMP; auxiliary civil works construction in Shangli county. JSX-EP-01A / Water environment monitoring and Component 1: Institutional Under Single Stage - One digital integration system and IBRD / 87040 Strengthening for Water Prior Request for Bids Open - National 3,539,700.00 0.00 Implementati 2021-02-26 2021-03-05 2021-03-03 2021-04-14 2021-04-16 2021-05-14 2021-06-09 2021-06-18 2021-12-15 Envelope equipment procurement for Management on LMP in Jishui county. YGX-EP-03 / Garbage sorting equipment, including: garbag e bins for garbage sorting 10 0 , classification booths 10 Pending Component 3: Improvements Request for Single Stage - One , intelligent garbage sorting m IBRD / 87040 Post Open - National 409,100.00 0.00 Implementati 2022-02-28 2022-04-04 2022-07-02 in Solid Waste Management Quotations Envelope achines 15 , intelligent garb on age sorting houses 5 , lawn mowers 10 , garbage sortin g boxes 40 , etc YGX-EP-04 / Pipe network detection equipment; Pipeline Component 2: Lake and River Pending Single Stage - One dredging equipment; IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 963,600.00 0.00 Implementati 2022-01-31 2022-03-31 2022-05-12 2022-06-11 2022-06-25 2022-12-22 Envelope Trenchless pipeline repair of Wastewater Management on equipment. PYX-EP-02 / Water intake water quantity monitoring Component 2: Lake and River Pending station, video monitoring Single Stage - One IBRD / 87040 Restoration and Improvement Prior Request for Bids Open - National 2,856,900.00 0.00 Implementati 2022-02-10 2022-02-15 2022-03-29 2022-04-28 2022-05-06 2022-11-02 point, water quality online Envelope of Wastewater Management on monitoring of water inlet of waterworks, etc. YGX-EP-02 / Construction of 183 sets of video monitoring points, water environment Component 2: Lake and River Pending Single Stage - One and water quality testing IBRD / 87040 Restoration and Improvement Post Request for Bids Open - National 2,252,700.00 0.00 Implementati 2022-02-01 2022-02-28 2022-02-28 2022-02-28 2022-03-07 2022-09-06 Envelope laboratory, garbage transfer of Wastewater Management on and disposal supervision module, etc NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JX-SSS-01 / Participatory Component 4: Project Under IBRD / 87040 Post Direct Selection Direct 100,000.00 0.00 2020-08-28 2020-08-01 2020-09-07 2020-11-11 2021-05-10 work Implementation Support Implementation Page 4