The World Bank                                                                                       Implementation Status & Results Report
           Second Regional and Municipal Infrastructure Development Project (P147521)



Second Regional and Municipal Infrastructure Development Project (P147521)


 EUROPE AND CENTRAL ASIA | Georgia | Urban, Resilience and Land Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 15 | ARCHIVED on 05-Apr-2022 | ISR50740 |


 Implementing Agencies: Georgia Municipal Development Fund, Ministry of Finance



 Key Dates


  Key Project Dates

   Bank Approval Date: 03-Jul-2014                                               Effectiveness Date: 16-Dec-2014
   Planned Mid Term Review Date: 31-Oct-2017                                     Actual Mid-Term Review Date: 18-Sep-2017
   Original Closing Date: 30-Jun-2019                                            Revised Closing Date: 30-Aug-2024
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  To improve the efficiency and reliability of targeted municipal services and infrastructure.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  Yes

  Board Approved Revised Project Development Objective (If project is formally restructured)
  To improve access to quality municipal services and infrastructure


 Components Table

 Name
 Infrastructure Investments:(Cost $90.89 M)
 Institutional Development:(Cost $8.75 M)
 Contingent Emergency Response Component

 Overall Ratings

 Name                                                                          Previous Rating                          Current Rating

 Progress towards achievement of PDO                                           Satisfactory                            Satisfactory
 Overall Implementation Progress (IP)                                          Moderately Satisfactory                 Moderately Satisfactory
 Overall Risk Rating                                                           Moderate                                Moderate


 Implementation Status and Key Decisions

  Under the completed investments, over 330,000 people (51% female) are benefiting from improved access to basic infrastructure including safe
  water supply, better mobility, and road safety through road rehabilitation, and better social services (including for ethnic minorities), through
  rehabilitation of kindergartens and sports/community centers. Additionally, ongoing Technical Assistance (TA) is supporting the development of an
  online municipal services platform in 63 municipalities across the country that aims to improve the government to citizens interface at the municipal
  level. The new platform has been successfully installed in all 63 municipalities and the capacity-building activities for the operationalization of the
  new platform are currently ongoing.



4/5/2022                                                                                                                         Page 1 of 7
            The World Bank                                                                                   Implementation Status & Results Report
            Second Regional and Municipal Infrastructure Development Project (P147521)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                             Rating at Approval            Previous Rating                Current Rating

  Political and Governance                                  --                            Moderate                      Moderate
  Macroeconomic                                             --                            Moderate                      Moderate
  Sector Strategies and Policies                            --                            Moderate                      Moderate
  Technical Design of Project or Program                    --                            Moderate                      Moderate
  Institutional Capacity for Implementation and
                                                            --                            Moderate                      Moderate
  Sustainability
  Fiduciary                                                 --                            Moderate                      Moderate
  Environment and Social                                    --                            Low                           Low
  Stakeholders                                              --                            Moderate                      Moderate
  Other                                                     --                            --                             --
  Overall                                                   --                            Moderate                      Moderate



  Results


 PDO Indicators by Objectives / Outcomes



   To improve access to quality municipal services and infrastructure

    IN01119422
    ►People provided with improved urban living conditions (Number, Corporate)

                                       Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                       330,000.00                   330,000.00                450,000.00

    Date                               02-Apr-2020                04-Oct-2021                  30-Mar-2022              30-Aug-2024

     IN01119423
     People provided with improved urban living conditions - Female (RMS requirement) (Number, Corporate Supplement)

                                     Baseline                    Actual (Previous)         Actual (Current)             End Target

     Value                           0.00                        178,500.00                178,500.00                   229,500.00

    IN01119424
    ►Average number of hours per day of piped water service in selected municipalities (Hours, Custom)

                                       Baseline                   Actual (Previous)            Actual (Current)          End Target

4/5/2022                                                                                                                      Page 2 of 7
           The World Bank                                                                                    Implementation Status & Results Report
           Second Regional and Municipal Infrastructure Development Project (P147521)




    Value                             7.00                        24.00                        24.00                      24.00

    Date                              31-Dec-2013                 04-Oct-2021                  30-Mar-2022               30-Aug-2024
                                      This indicator is related with two subprojects: Villages Nikozi (Zeda and Kveda) and Zemo Kviti (Gori,
   Comments:                          Shida Kartli) water supply rehabilitation which includes drinking water supply for 24 hours/day.

    IN01119425
    ►Percentage of LSGs with improved asset management system (Percentage, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                             0.00                        66.00                        66.00                      70.00

    Date                              31-Dec-2013                 04-Oct-2021                  30-Mar-2022               30-Aug-2024



 Intermediate Results Indicators by Components



   Infrastructure Investments

    IN01119427
    ►Roads rehabilitated (Kilometers, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                             0.00                        54.28                        54.28                      110.00

    Date                              31-Dec-2013                 04-Oct-2021                  30-Mar-2022               30-Aug-2024

    IN01119429
    ►Water supply pipes rehabilitated (Kilometers, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                             0.00                        53.04                        53.04                      210.00

    Date                              30-Jun-2014                 04-Oct-2021                  30-Mar-2022               30-Aug-2024

    IN01119431
    ►Public facilities rehabilitated (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                             0.00                        21.00                        21.00                      26.00

    Date                              30-Jun-2014                 04-Oct-2021                  30-Mar-2022               30-Aug-2024

    IN01119433
    ►Wastewater network rehabilitated (Kilometers, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                             0.00                        16.25                        16.25                      16.00



4/5/2022                                                                                                                     Page 3 of 7
           The World Bank                                                                                   Implementation Status & Results Report
           Second Regional and Municipal Infrastructure Development Project (P147521)




    Date                              30-Jun-2014                04-Oct-2021                  30-Mar-2022              30-Aug-2024

    IN01119436
    ►Citizens/beneficiaries reporting that investment decisions represented their views and met their needs (Percentage, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       0.00                         0.00                      70.00

    Date                              19-Mar-2020                04-Oct-2021                  30-Mar-2022              30-Aug-2024

     IN01119437
     Gender disaggregation (Percentage, Custom Supplement)

                                    Baseline                    Actual (Previous)           Actual (Current)           End Target

     Value                          0.00                        0.00                        0.00                       50.00

    IN01119438
    ►Citizens/beneficiaries reporting that engagement processes are effective and respond to their feedback (Percentage, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       70.00                        70.00                     70.00

    Date                              19-Mar-2020                04-Oct-2021                  30-Mar-2022              30-Aug-2024
                                      MDF has been conducting community meetings for the initiated investments to discuss the intended
                                      interventions, review the design packages and discuss the ESMP with the concerned beneficiaries. The
   Comments:                          details of each meeting have been documented in the respective minutes and shared with the Bank as
                                      part of the proposed investment report package.

     IN01119439
     Gender disaggregation (Percentage, Custom Supplement)

                                    Baseline                    Actual (Previous)           Actual (Current)           End Target

     Value                          0.00                        50.00                       50.00                      50.00

    IN01119440
    ►Women participation in decision-making processes for investment screening, prioritization and selection (Percentage, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       30.00                        30.00                     30.00

    Date                              02-Apr-2020                04-Oct-2021                  30-Mar-2022              30-Aug-2024



   Institutional Development

    IN01119426
    ►Percentage of LSGs with established PCM systems and procedures (Percentage, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       66.00                        66.00                     70.00




4/5/2022                                                                                                                   Page 4 of 7
           The World Bank                                                                                     Implementation Status & Results Report
           Second Regional and Municipal Infrastructure Development Project (P147521)




    Date                              31-Dec-2013                 04-Oct-2021                   30-Mar-2022                30-Aug-2024

    IN01119428
    ►Percentage of LSGs with staff that can operate PCM systems (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        66.00                         66.00                      70.00

    Date                              31-Dec-2013                 04-Oct-2021                   30-Mar-2022                30-Aug-2024
                                      This indicator is related with Component 2 of the project under which training activities and preparation of
   Comments:                          guidebooks/manuals have started.

    IN01119430
    ►Percentage of LSGs with functioning, budgeting and accounting systems (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        66.00                         66.00                      70.00

    Date                              31-Dec-2013                 04-Oct-2021                   30-Mar-2022                30-Aug-2024

    IN01119432
    ►Percentage of LSGs with staff that can operate budgeting and accounting systems (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        66.00                         66.00                      70.00

    Date                              31-Dec-2013                 04-Oct-2021                   30-Mar-2022                30-Aug-2024
                                      This indicator is related with Component 2 of the project under which training activities and preparation of
   Comments:                          guidebooks/manuals have started.

    IN01119434
    ►Percentage of LSGs with established asset planning and management systems (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        66.00                         66.00                      70.00

    Date                              31-Dec-2013                 04-Oct-2021                   30-Mar-2022                30-Aug-2024
                                      This indicator is related with Component 2 of the project under which training activities and preparation of
   Comments:                          guidebooks/manuals have started.

    IN01119435
    ►Percentage of LSGs with staff that can plan and manage LSG assets (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        66.00                         66.00                      70.00

    Date                              31-Dec-2013                 04-Oct-2021                   30-Mar-2022                30-Aug-2024
   Comments:                          This indicator is related with Component 2 of the project under which training activities and preparation of
                                      guidebooks/manuals have started.


4/5/2022                                                                                                                       Page 5 of 7
           The World Bank                                                                                   Implementation Status & Results Report
           Second Regional and Municipal Infrastructure Development Project (P147521)




 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status       Currency        Original   Revised     Cancelled     Disbursed      Undisbursed                % Disbursed


 P147521       IBRD-83800        Effective    USD               30.00      30.00           0.00         28.82             1.18                      96%

 P147521       IBRD-90990        Effective    USD               40.60      40.60           0.00          3.93           36.79                      9.6%

 P147521       TF-18090          Effective    USD                5.00       5.00           0.00          4.88             0.12                      98%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date       Signing Date     Effectiveness Date     Orig. Closing Date      Rev. Closing Date

 P147521        IBRD-83800        Effective   03-Jul-2014         18-Aug-2014      16-Dec-2014            30-Jun-2019             30-Aug-2024
 P147521        IBRD-90990        Effective   18-May-2020         21-May-2020      05-Aug-2020            30-Aug-2024             30-Aug-2024
 P147521        TF-18090          Effective   03-Jul-2014         01-May-2015      11-Jun-2015            31-Dec-2018             31-Dec-2022


Cumulative Disbursements




4/5/2022                                                                                                                       Page 6 of 7
           The World Bank                                                                                 Implementation Status & Results Report
           Second Regional and Municipal Infrastructure Development Project (P147521)




  Restructuring History


  Level 2 Approved on 29-May-2019


  Related Project(s)


  P169082-Additional Financing for the Second Regional and Municipal Infrastructure Development Project




4/5/2022                                                                                                                 Page 7 of 7