The World Bank Implementation Status & Results Report Second Regional and Municipal Infrastructure Development Project (P147521) Second Regional and Municipal Infrastructure Development Project (P147521) EUROPE AND CENTRAL ASIA | Georgia | Urban, Resilience and Land Global Practice | IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 15 | ARCHIVED on 05-Apr-2022 | ISR50740 | Implementing Agencies: Georgia Municipal Development Fund, Ministry of Finance Key Dates Key Project Dates Bank Approval Date: 03-Jul-2014 Effectiveness Date: 16-Dec-2014 Planned Mid Term Review Date: 31-Oct-2017 Actual Mid-Term Review Date: 18-Sep-2017 Original Closing Date: 30-Jun-2019 Revised Closing Date: 30-Aug-2024 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve the efficiency and reliability of targeted municipal services and infrastructure. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured) To improve access to quality municipal services and infrastructure Components Table Name Infrastructure Investments:(Cost $90.89 M) Institutional Development:(Cost $8.75 M) Contingent Emergency Response Component Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions Under the completed investments, over 330,000 people (51% female) are benefiting from improved access to basic infrastructure including safe water supply, better mobility, and road safety through road rehabilitation, and better social services (including for ethnic minorities), through rehabilitation of kindergartens and sports/community centers. Additionally, ongoing Technical Assistance (TA) is supporting the development of an online municipal services platform in 63 municipalities across the country that aims to improve the government to citizens interface at the municipal level. The new platform has been successfully installed in all 63 municipalities and the capacity-building activities for the operationalization of the new platform are currently ongoing. 4/5/2022 Page 1 of 7 The World Bank Implementation Status & Results Report Second Regional and Municipal Infrastructure Development Project (P147521) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and -- Moderate Moderate Sustainability Fiduciary -- Moderate Moderate Environment and Social -- Low Low Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Moderate Moderate Results PDO Indicators by Objectives / Outcomes To improve access to quality municipal services and infrastructure IN01119422 ►People provided with improved urban living conditions (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 330,000.00 330,000.00 450,000.00 Date 02-Apr-2020 04-Oct-2021 30-Mar-2022 30-Aug-2024 IN01119423 People provided with improved urban living conditions - Female (RMS requirement) (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 178,500.00 178,500.00 229,500.00 IN01119424 ►Average number of hours per day of piped water service in selected municipalities (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target 4/5/2022 Page 2 of 7 The World Bank Implementation Status & Results Report Second Regional and Municipal Infrastructure Development Project (P147521) Value 7.00 24.00 24.00 24.00 Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 This indicator is related with two subprojects: Villages Nikozi (Zeda and Kveda) and Zemo Kviti (Gori, Comments: Shida Kartli) water supply rehabilitation which includes drinking water supply for 24 hours/day. IN01119425 ►Percentage of LSGs with improved asset management system (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 66.00 66.00 70.00 Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 Intermediate Results Indicators by Components Infrastructure Investments IN01119427 ►Roads rehabilitated (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 54.28 54.28 110.00 Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 IN01119429 ►Water supply pipes rehabilitated (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 53.04 53.04 210.00 Date 30-Jun-2014 04-Oct-2021 30-Mar-2022 30-Aug-2024 IN01119431 ►Public facilities rehabilitated (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 21.00 21.00 26.00 Date 30-Jun-2014 04-Oct-2021 30-Mar-2022 30-Aug-2024 IN01119433 ►Wastewater network rehabilitated (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 16.25 16.25 16.00 4/5/2022 Page 3 of 7 The World Bank Implementation Status & Results Report Second Regional and Municipal Infrastructure Development Project (P147521) Date 30-Jun-2014 04-Oct-2021 30-Mar-2022 30-Aug-2024 IN01119436 ►Citizens/beneficiaries reporting that investment decisions represented their views and met their needs (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 19-Mar-2020 04-Oct-2021 30-Mar-2022 30-Aug-2024 IN01119437 Gender disaggregation (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 IN01119438 ►Citizens/beneficiaries reporting that engagement processes are effective and respond to their feedback (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 70.00 70.00 70.00 Date 19-Mar-2020 04-Oct-2021 30-Mar-2022 30-Aug-2024 MDF has been conducting community meetings for the initiated investments to discuss the intended interventions, review the design packages and discuss the ESMP with the concerned beneficiaries. The Comments: details of each meeting have been documented in the respective minutes and shared with the Bank as part of the proposed investment report package. IN01119439 Gender disaggregation (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 50.00 50.00 50.00 IN01119440 ►Women participation in decision-making processes for investment screening, prioritization and selection (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 30.00 30.00 30.00 Date 02-Apr-2020 04-Oct-2021 30-Mar-2022 30-Aug-2024 Institutional Development IN01119426 ►Percentage of LSGs with established PCM systems and procedures (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 66.00 66.00 70.00 4/5/2022 Page 4 of 7 The World Bank Implementation Status & Results Report Second Regional and Municipal Infrastructure Development Project (P147521) Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 IN01119428 ►Percentage of LSGs with staff that can operate PCM systems (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 66.00 66.00 70.00 Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 This indicator is related with Component 2 of the project under which training activities and preparation of Comments: guidebooks/manuals have started. IN01119430 ►Percentage of LSGs with functioning, budgeting and accounting systems (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 66.00 66.00 70.00 Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 IN01119432 ►Percentage of LSGs with staff that can operate budgeting and accounting systems (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 66.00 66.00 70.00 Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 This indicator is related with Component 2 of the project under which training activities and preparation of Comments: guidebooks/manuals have started. IN01119434 ►Percentage of LSGs with established asset planning and management systems (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 66.00 66.00 70.00 Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 This indicator is related with Component 2 of the project under which training activities and preparation of Comments: guidebooks/manuals have started. IN01119435 ►Percentage of LSGs with staff that can plan and manage LSG assets (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 66.00 66.00 70.00 Date 31-Dec-2013 04-Oct-2021 30-Mar-2022 30-Aug-2024 Comments: This indicator is related with Component 2 of the project under which training activities and preparation of guidebooks/manuals have started. 4/5/2022 Page 5 of 7 The World Bank Implementation Status & Results Report Second Regional and Municipal Infrastructure Development Project (P147521) Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P147521 IBRD-83800 Effective USD 30.00 30.00 0.00 28.82 1.18 96% P147521 IBRD-90990 Effective USD 40.60 40.60 0.00 3.93 36.79 9.6% P147521 TF-18090 Effective USD 5.00 5.00 0.00 4.88 0.12 98% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P147521 IBRD-83800 Effective 03-Jul-2014 18-Aug-2014 16-Dec-2014 30-Jun-2019 30-Aug-2024 P147521 IBRD-90990 Effective 18-May-2020 21-May-2020 05-Aug-2020 30-Aug-2024 30-Aug-2024 P147521 TF-18090 Effective 03-Jul-2014 01-May-2015 11-Jun-2015 31-Dec-2018 31-Dec-2022 Cumulative Disbursements 4/5/2022 Page 6 of 7 The World Bank Implementation Status & Results Report Second Regional and Municipal Infrastructure Development Project (P147521) Restructuring History Level 2 Approved on 29-May-2019 Related Project(s) P169082-Additional Financing for the Second Regional and Municipal Infrastructure Development Project 4/5/2022 Page 7 of 7