PROCUREMENT PLAN (Textual Part) Project information: São Tomé and Principe; STP Girls Empowerment and Quality Education for All Project; P169222 Project Implementation agency: Ministry of Education, with fiduciary functions to be carried by AFAP Date of the Procurement Plan: 15 June 2020 Period covered by this Procurement Plan: 15 June to 30 September 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used – Not applicable. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information All Direct Contract will be prior reviewed during the first year of project’s implementation. At the end of that period, an assessment will be made to revise the requirement, if needed. PROCUREMENT Sao Tome and Principe : Girls Empowerment and Quality Education for All Project PLAN General Information Country: Sao Tome and Principe 2020-06-16 Bank’s Approval Date of the Original Procurement Plan: 2022-08-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169222 GPN Date: Project Name: Girls Empowerment and Quality Education for All Project Loan / Credit No: IDA / V3070, IDA / D7340, TF / B3318 Project Fiduciary and Administrative Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Project Coordination, Monito 04/W/GEE/2020 / Rehabilitati Solicitação de Cot Single Stage - One E 2021-04-0 IDA / V3070 ring and Evaluation, and Cap Posterior Open - National 30,000.00 27,416.49 Concluído 2020-08-16 2020-10-11 2020-10-07 on of PCU office in the MEES ações nvelope 9 acity Building 20/G/GEE/2020 / Rehabilitati Empowering Girls through th on and construction of bathr e Acquisition of Life Skills an Solicitação de Ofe Single Stage - One E 2021-10-0 IDA / V3070 Posterior Open - National 1,600,000.00 0.00 Cancelado 2020-12-21 2020-12-26 2021-02-06 2021-03-08 2021-04-12 ooms and water suplply in sc d the Promotion of a Safe Sc rtas nvelope 9 hools hool Environment National Procure 48/W/GEE/2022 / Hiring a co Empowering Girls through th ment Document - Em fase de I nstruction company to build e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E 2023-01-2 IDA / D7340 Posterior Open - National 1 Envelope proce 47,539.74 52,420.20 mplementa 2022-05-29 2022-07-24 a room (medium-sized physic d the Promotion of a Safe Sc ações nvelope 0 ss (Non Bank-SPD ção al space for backstage int th hool Environment ) e MEES) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 03/G/GEE/2020 / Acquisition Project Coordination, Monito Solicitação de Cot Single Stage - One E of officve furniture for PIU (Mi IDA / V3070 ring and Evaluation, and Cap Posterior Limited 3,000.00 4,322.05 Concluído 2020-05-05 2020-11-16 2020-06-30 2020-12-14 2020-12-27 2021-06-17 ações nvelope nistry of Education) acity Building Project Coordination, Monito 14/G/GEE/2020 / Purchase of Solicitação de Cot Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Posterior Limited 10,000.00 5,035.30 Concluído 2020-05-13 2020-04-21 2020-07-08 2020-07-09 2021-01-04 2020-08-12 ITC Equipments for DPIE ações nvelope acity Building Project Coordination, Monito 01/G/GEE/2020 / Axquisition Solicitação de Cot Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Posterior Open - National 50,000.00 60,391.62 Concluído 2020-08-01 2020-09-26 2020-11-24 2021-03-25 2021-02-10 of two (2) vehicles ações nvelope acity Building 02/G/GEE/2020 / Purchase of Project Coordination, Monito ITC equipment (5 Desktops, Solicitação de Cot Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Posterior Limited 15,500.00 17,018.05 Concluído 2020-08-29 2020-10-12 2020-10-24 2020-11-11 2021-04-22 2021-06-15 1 multifunction printer, 4 po ações nvelope acity Building wer stations, 2 laptops) for P CU 19/G/GEE/2020 / Design, edi Solicitação de Ofe Open - Internationa Single Stage - One E Implementaç ting and printing of Teaching IDA / V3070 Tackling Learning Poverty Posterior 500,000.00 0.00 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2021-06-20 rtas l nvelope ão Pendente learning materials (TLMS) for Basic education 18/C/GEE/2020 / Editing and Empowering Girls through th Printing of communication m e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E IDA / V3070 Posterior Limited 50,000.00 0.00 Cancelado 2021-02-15 2021-04-12 2021-10-09 aterials (tamps, logos, etc.) f d the Promotion of a Safe Sc ações nvelope or PEREQT hool Environment Project Coordination, Monito 01/G/GEE/2021 / Aquisição d Solicitação de Cot Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Posterior Limited 28,000.00 29,713.52 Concluído 2021-01-24 2021-01-20 2021-03-21 2021-01-22 2021-09-17 2021-06-17 e 19 Computadores Portáteis ações nvelope acity Building 37/G/GEE/2021 / Acquisition of 40 Tablets and Technology Equipment (2 video-conferen Solicitação de Cot Single Stage - One E IDA / D7340 Tackling Learning Poverty Posterior Limited 30,000.00 22,203.12 Concluído 2022-01-03 2021-06-30 2022-02-28 2021-08-26 2022-08-27 2021-10-25 cing systems and 4 Laptops) ações nvelope to support the implementatio n of Basic Education classroo m observation (TEACH) 46/G/GEE/2022 / Acquisition Project Coordination, Monito and installation of Generator Solicitação de Cot Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Posterior Limited 31,252.85 22,593.03 Assinado 2022-04-02 2022-03-16 2022-05-28 2022-06-27 2022-11-24 and Electric Pump (including ações nvelope acity Building Construction of Generator Ho use). 44/G/GEE/2022 / Acquisition Project Coordination, Monito Solicitação de Cot Single Stage - One E of Equipment and Furniture f IDA / D7340 ring and Evaluation, and Cap Posterior Limited 12,770.22 0.00 Cancelado 2022-03-05 2022-03-01 2022-04-30 2022-10-27 ações nvelope or MEES acity Building 09/G/GEE/2020 / Editing and Contingency Emergency Res Solicitação de Cot Single Stage - One E Implementaç IDA / V3070 Posterior Open - National 70,000.00 0.00 2023-01-04 2023-03-01 2023-08-28 printing of materials on COVI ponse Component (CERC) ações nvelope ão Pendente D19 17/G/GEE/2020 / Purchase of Empowering Girls through th ITC equipments for schools (c e Acquisition of Life Skills an Solicitação de Ofe Open - Internationa Single Stage - One E Implementaç IDA / D7340 Posterior 700,000.00 0.00 2022-06-29 2022-07-04 2022-08-15 2022-09-14 2022-10-19 2023-04-17 omuers,pritrs, ablets, laptops d the Promotion of a Safe Sc rtas l nvelope ão Pendente , power stations) hool Environment Project Coordination, Monito Em fase de I 59/G/GEE/2022 / Purchasing Solicitação de Cot Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Posterior Limited 9,000.00 0.00 mplementaç 2022-07-05 2022-07-22 2022-08-30 2023-02-26 a UPS for AFAP ações nvelope acity Building ão Empowering Girls through th 63/G/GEE/2022 / Acquisition e Acquisition of Life Skills an Solicitação de Ofe Single Stage - One E Implementaç of 5 off-road vehicles to supe IDA / D7340 Posterior Open - National 211,168.60 0.00 2022-09-21 2022-09-26 2022-11-07 2022-12-07 2023-01-11 2023-07-10 d the Promotion of a Safe Sc rtas nvelope ão Pendente rvise the Project's activities. hool Environment 49/G/GEE/2022 / Acquisition Empowering Girls through th of 4 vehicles to supervise the e Acquisition of Life Skills an Solicitação de Ofe Single Stage - One E IDA / D7340 Posterior Open - National 175,000.00 0.00 Cancelado 2022-05-20 2022-05-25 2022-07-06 2022-08-05 2022-09-09 2023-03-08 works of Bathrooms in School d the Promotion of a Safe Sc rtas nvelope s hool Environment NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 06/S/GEE/2020 / Updadte of Project Coordination, Monito Tompro for Eduication Projec IDA / V3070 ring and Evaluation, and Cap Posterior Aquisição Direta Direct 15,000.00 16,500.00 Concluído 2020-05-29 2021-05-28 2020-06-03 2021-05-31 2020-07-08 2021-06-08 2021-01-04 2021-07-01 t acity Building 37/NC/GEE/2020 / Editing an Empowering Girls through th d printing of communication e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E IDA / V3070 Posterior Limited 40,000.00 4,088.74 Concluído 2021-06-22 2021-09-10 2021-08-17 2021-11-02 2022-02-13 2021-12-01 materials (tamps, logos, etc.) d the Promotion of a Safe Sc ações nvelope for PEREQT hool Environment 18/S/GEE/2020 / Editing and Empowering Girls through th Printing of communication m e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E IDA / V3070 Posterior Open - National 50,000.00 0.00 Cancelado 2021-03-15 2021-05-10 2021-11-06 aterials (tamps, logos, etc.) f d the Promotion of a Safe Sc ações nvelope or PEREQT hool Environment 05/G/GEE/220 / Internet Serv IDA / V3070 Tackling Learning Poverty Posterior Aquisição Direta Direct 20,000.00 0.00 Cancelado 2020-07-31 2020-08-05 2020-09-09 2021-03-08 ice for MEES Empowering Girls through th 60/S/GEE/2022 / Provision of Em fase de I e Acquisition of Life Skills an services to MEES/PEREQT in t IDA / D7340 Posterior Aquisição Direta Direct - National 72,750.00 0.00 mplementaç 2022-08-30 2022-07-27 2022-09-04 2022-07-28 2022-10-09 2023-04-07 d the Promotion of a Safe Sc he area of ​communication ão hool Environment CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 10/C/GEE/2020 / Capacity bu Project Coordination, Monito Seleção Baseada Open - Internationa ilding activity on large scale IDA / V3070 ring and Evaluation, and Cap Posterior nas Qualificações 80,000.00 0.00 Cancelado 2020-09-14 2020-10-05 2020-11-18 2020-12-18 2021-01-22 2021-07-21 l student learning assessment acity Building dos Consultores 27/C/GEE/2020 / TA to imple Seleção Baseada Open - Internationa ment the Professional develo IDA / V3070 Tackling Learning Poverty Posterior na Qualidade e Cu 350,000.00 0.00 Cancelado 2021-01-28 2021-02-18 2021-04-03 2021-05-01 2021-05-31 2021-07-05 2021-08-09 2022-08-09 l pment program for pre-schoo sto l teachers 26/C/GEE/2020 / TA to condu Seleção Baseada ct large-scale students learni Open - Internationa IDA / V3070 Tackling Learning Poverty Posterior na Qualidade e Cu 300,000.00 0.00 Cancelado 2021-04-22 2021-02-11 2021-05-13 2021-02-18 2021-06-26 2021-07-24 2021-08-23 2021-09-27 2021-11-01 2022-11-01 ng assessment in primary an l sto d secondarybschools (ALLEB and ALLES) 42/C/GEE/2022 / Selection a nd contracting of a Consultan Empowering Girls through th Seleção Baseada cy Office/Company to develo e Acquisition of Life Skills an IDA / V3070 Posterior nas Qualificações Open - National 79,296.00 30,764.97 Assinado 2022-01-26 2022-01-17 2022-02-16 2022-01-24 2022-04-01 2022-04-05 2022-05-01 2022-05-09 2022-06-05 2022-05-25 2022-12-02 p architectural and structural d the Promotion of a Safe Sc dos Consultores projects for the construction hool Environment and rehabilitation of bathroo ms in schools 45/C/GEE/2022 / Hiring a co Project Coordination, Monito Seleção Baseada Em fase de Imple mpany to teach the English c IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações Open - National 24,000.00 24,773.57 2022-03-30 2022-03-14 2022-04-20 2022-06-03 2022-06-06 2022-07-03 2022-08-08 2022-08-07 2023-02-03 mentação ourse for MEES´s Technicians acity Building dos Consultores . Empowering Girls through th 29/C/GEE/2020 / TA to imple Seleção Baseada e Acquisition of Life Skills an Open - Internationa ment the Girls' Empweremen IDA / V3070 Posterior na Qualidade e Cu 220,000.00 0.00 Cancelado 2021-01-04 2021-01-25 2021-03-10 2021-04-07 2021-05-07 2021-06-11 2021-07-16 2022-07-16 d the Promotion of a Safe Sc l t Program sto hool Environment 28/C/GEE/2020 / TA to imple ment the Professional Develo Seleção Baseada Open - Internationa Implementação P pment Program for Elementa IDA / D7340 Tackling Learning Poverty Prévia na Qualidade e Cu 1,840,000.00 0.00 2022-06-30 2022-07-21 2022-09-03 2022-10-01 2022-10-31 2022-12-05 2023-01-09 2024-01-09 l endente ry School Teachers (Elaborati sto on of Structured Materials) 23/C/GEE/2020 / Technical A Seleção Baseada Open - Internationa Implementação P ssistance for implementation TF / B3318 Tackling Learning Poverty Posterior na Qualidade e Cu 210,000.00 0.00 2022-11-24 2022-12-15 2023-01-28 2023-02-25 2023-03-27 2023-05-01 2023-06-05 2024-06-04 l endente of the accelerated Education sto Program 22/C/GEE/2020 / Technical a Project Coordination, Monito Seleção Baseada ssistance to conduct the M&E Open - Internationa Implementação P IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações 140,000.00 0.00 2022-11-16 2022-12-07 2023-01-20 2023-02-19 2023-03-26 2023-09-22 System for Pre-school based l endente acity Building dos Consultores on MELQO instrument 53/C/GEE/2022 / T.A to prom Project Coordination, Monito Seleção Baseada ote Inclusive Education that r Open - Internationa Implementação P IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações 145,000.00 0.00 2022-06-30 2022-07-21 2022-09-03 2022-10-03 2022-11-07 2023-05-06 esponds to the challenges of l endente acity Building dos Consultores the Framework Law 54/C/GEE/2022 / Hiring a co Project Coordination, Monito Seleção Baseada Open - Internationa Implementação P nsultancy to update the Scho IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações 50,000.00 0.00 2022-06-22 2022-07-13 2022-08-26 2022-09-25 2022-10-30 2023-04-28 l endente ol Charter acity Building dos Consultores 55/C/GEE/2022 / Project com Project Coordination, Monito Seleção Baseada munication strategy (Educati IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações Open - National 52,500.00 0.00 Cancelado 2022-06-24 2022-07-15 2022-08-28 2022-09-27 2022-11-01 2023-04-30 on Strengthening, Inclusive E acity Building dos Consultores ducation) 61/C/GEE/2022 / PREPARATI Project Coordination, Monito Seleção Baseada Open - Internationa Em fase de Imple ON OF ENVIRONMENTAL AND IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações 35,843.00 0.00 2022-08-30 2022-07-20 2022-09-20 2022-08-02 2022-11-03 2022-12-03 2023-01-07 2023-07-06 l mentação SOCIAL MANAGEMENT PLANS acity Building dos Consultores (ESMP) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 11/C/GEE/2020 / Technical a Project Coordination, Monito ssistance to elaborate the En IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 40,000.00 0.00 Cancelado 2020-07-19 2020-09-06 2020-09-27 2020-11-01 2021-04-30 vironmental and Social Fram acity Building ework instruments 13/C/GEE/2020 / Technical a Project Coordination, Monito ssistance for training and for IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 40,000.00 0.00 Cancelado 2020-06-26 2020-08-14 2020-09-04 2020-10-09 2021-04-07 providing specialized support acity Building to the statics staff Page 2 08/CGEE/2020 / Hiring Envir Project Coordination, Monito onmental and Social Develop IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 32,000.00 39,150.00 Assinado 2020-05-14 2020-12-04 2020-07-02 2021-03-05 2020-07-23 2021-03-24 2020-08-27 2021-03-29 2021-02-23 ment specialist for PIU (MEES acity Building ) 07/C/GEE/2020 / Hiring Moni Project Coordination, Monito toring and Evaluation speciali IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 32,000.00 0.00 Cancelado 2020-07-13 2020-07-10 2020-08-31 2020-08-06 2020-09-21 2020-10-26 2021-04-24 st acity Building Project Coordination, Monito 15/C/GEE/2020 / Hiring a Pro IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 100,000.00 0.00 Cancelado 2020-06-30 2020-07-06 2020-08-18 2020-09-10 2020-09-08 2020-10-13 2021-04-11 ject Management Expert acity Building Empowering Girls through th 16/C/GEE/2020 / Hiring a Co e Acquisition of Life Skills an IDA / V3070 Posterior Individual Open 35,000.00 0.00 Cancelado 2020-07-03 2020-07-10 2020-08-21 2020-09-11 2020-10-16 2021-04-14 ordinator for PCU d the Promotion of a Safe Sc hool Environment 24/C/GEE/2020 / TA to imple Reaching the Most Vulnerabl Implementação P ment an Early warning syste IDA / V3070 Posterior Individual Open 199,000.00 0.00 2020-12-16 2021-02-03 2021-02-24 2021-03-31 2021-09-27 e endente m to signal students in learn dificulties 30/C/GEE/2020 / Technical a Project Coordination, Monito Seleção Direta de ssistance to elaborate the en IDA / V3070 ring and Evaluation, and Cap Posterior Direct 40,000.00 15,000.00 Concluído 2020-08-14 2020-08-14 2020-08-24 2020-08-10 2020-10-28 2020-08-31 2021-04-26 2021-12-17 Consultores vironmental &Social framewo acity Building rk instruments Empowering Girls through th 31/C/GEE/2020 / Hiring Moni e Acquisition of Life Skills an toring and Evaluation speciali IDA / V3070 Posterior Individual Open 32,000.00 68,232.60 Assinado 2020-10-08 2020-09-30 2020-11-26 2020-11-04 2020-12-17 2020-11-17 2021-01-21 2020-12-01 2021-07-20 d the Promotion of a Safe Sc st hool Environment Empowering Girls through th 32/C/GEE/2020 / Hiring a Co e Acquisition of Life Skills an IDA / V3070 Posterior Individual Open 35,000.00 16,200.00 Assinado 2020-10-08 2020-09-29 2020-11-26 2020-11-27 2020-12-17 2020-11-30 2021-01-21 2020-12-01 2021-07-20 ordinator for PCU d the Promotion of a Safe Sc hool Environment Empowering Girls through th 33/C/GEE/2020 / Hiring a Pro e Acquisition of Life Skills an IDA / V3070 Posterior Individual Open 100,000.00 93,176.52 Concluído 2020-10-13 2020-09-30 2020-12-01 2020-11-17 2020-12-22 2020-11-24 2021-01-26 2020-12-01 2021-07-25 2021-11-26 ject Management Expert d the Promotion of a Safe Sc hool Environment Empowering Girls through th 36/C/GEE/2020 / Design of c e Acquisition of Life Skills an ommunication materials (ta IDA / V3070 Posterior Individual Limited 10,000.00 13,750.00 Concluído 2021-04-05 2021-03-18 2021-04-10 2021-03-22 2021-05-01 2021-05-17 2021-06-05 2021-05-21 2021-12-02 2021-11-08 d the Promotion of a Safe Sc mps, logos, etc.) for PEREQT hool Environment 35/C/GEE/2020 / TA to condu ct Large-Scale Students Lear Seleção Direta de IDA / D7340 Tackling Learning Poverty Prévia Direct 300,000.00 327,424.09 Assinado 2021-03-31 2021-03-29 2021-04-10 2021-03-30 2021-06-14 2022-01-14 2021-12-11 ning Assessment in Primary a Consultores nd Secondarybschools (AALE B AND AALES) 34/C/GEE/2020 / Techical As Seleção Direta de sistance to conduct the Lear IDA / D7340 Tackling Learning Poverty Prévia Direct 290,000.00 141,459.43 Assinado 2021-03-31 2021-03-30 2021-04-10 2021-04-15 2021-06-14 2021-12-02 2021-12-11 Consultores ning Assessment PASEC Empowering Girls through th 08/C/GEE/2021 / Hiring a Co e Acquisition of Life Skills an IDA / V3070 Posterior Individual Open 32,000.00 45,000.00 Assinado 2021-06-10 2021-06-07 2021-07-29 2021-08-06 2021-08-19 2021-08-19 2021-09-23 2021-08-27 2022-03-22 ordinator for PCU d the Promotion of a Safe Sc hool Environment Empowering Girls through th 09/C/GEE/2021 / Hiring Civil e Acquisition of Life Skills an IDA / D7340 Posterior Individual Open 26,400.00 0.00 Cancelado 2021-09-28 2021-06-09 2021-11-16 2021-12-07 2022-01-11 2022-07-10 Construction Engineer d the Promotion of a Safe Sc hool Environment Empowering Girls through th 38/C/GEE/2021 / Hiring a Civ e Acquisition of Life Skills an IDA / D7340 Posterior Individual Open 33,840.00 48,600.00 Assinado 2021-07-28 2021-06-23 2021-09-15 2021-09-29 2021-10-06 2021-10-06 2021-11-10 2021-10-06 2022-05-09 il Construction Engineer d the Promotion of a Safe Sc hool Environment 39/C/GEE/2021 / TECHNICAL ASSISTANCE FOR TRAINING A ND SUPPORT IN DATA ANALY IDA / D7340 Tackling Learning Poverty Posterior Individual Open 42,500.00 0.00 Cancelado 2021-09-22 2021-06-23 2021-11-10 2021-12-01 2022-01-05 2022-07-04 SIS FOR THE STATISTICS AND EDUCATIONAL EVALUATION T EAM 40/C/GEE/2021 / Hiring an in Project Coordination, Monito dividual consultant to survey IDA / D7340 ring and Evaluation, and Cap Posterior Individual Limited 2,500.00 2,500.00 Concluído 2021-09-22 2021-09-08 2021-09-27 2021-09-10 2021-10-18 2021-10-18 2021-11-22 2021-10-19 2022-05-21 2021-12-06 the conditions of the MEES el acity Building ectrical system 41/C/GEE/2021 / TA FOR TRA INING PRESCHOOL EDUCATIO N TEACHERS, CONCEPTION, Seleção Direta de IDA / V3070 Tackling Learning Poverty Posterior Direct 1,151,003.00 1,151,003.00 Assinado 2021-12-20 2021-12-17 2021-12-30 2021-12-20 2022-03-05 2022-01-17 2022-09-01 CONSTRUCTION AND ACQUIS Consultores ITION OF SUPPORT MATERIAL S FOR THE TEACHING AND LE ARNING OF CHILDREN 43/C/GEE/2022 / TECHNICAL ASSISTANCE FOR TRAINING A ND SUPPORT IN DATA ANALY IDA / D7340 Tackling Learning Poverty Posterior Individual Open 78,200.00 75,167.84 Assinado 2022-01-26 2022-01-17 2022-03-16 2022-04-27 2022-04-06 2022-06-13 2022-05-11 2022-06-30 2022-11-07 SIS FOR THE EDUCATIONAL S TATISTICS AND EVALUATION TEAM IN SAO TOME AND PRI NCIPE Empowering Girls through th 56/C/GEE/2022 / Financial M e Acquisition of Life Skills an IDA / D7340 Posterior Individual Direct 45,627.24 45,627.24 Assinado 2022-04-18 2022-05-19 2022-04-28 2022-06-13 2022-05-19 2022-06-14 2022-06-23 2022-06-15 2022-12-20 anager for AFAP d the Promotion of a Safe Sc hool Environment Empowering Girls through th 58/C/GEE/2022 / Senior Acco e Acquisition of Life Skills an IDA / D7340 Posterior Individual Direct 32,340.00 32,340.00 Assinado 2022-04-18 2022-05-19 2022-04-28 2022-06-13 2022-05-19 2022-06-14 2022-06-23 2022-06-15 2022-12-20 untant for AFAP d the Promotion of a Safe Sc hool Environment Empowering Girls through th 57/C/GEE/2022 / Specialist i e Acquisition of Life Skills an n Environmental and Social S IDA / D7340 Posterior Individual Direct 44,465.76 0.00 Em Análise 2022-04-18 2022-05-20 2022-04-28 2022-05-19 2022-06-23 2022-12-20 d the Promotion of a Safe Sc afeguards for AFAP hool Environment Empowering Girls through th 47/C/GEE/2022 / TA to imple e Acquisition of Life Skills an Seleção Direta de ment the Girls' Empweremen IDA / D7340 Posterior Direct 761,584.00 726,207.00 Assinado 2022-06-28 2022-05-10 2022-07-08 2022-05-19 2022-09-11 2022-06-02 2023-03-10 d the Promotion of a Safe Sc Consultores t Program hool Environment Page 3