PROCUREMENT PLAN (Textual Part) Project information: GUYANA – SECONDARY EDUCATION IMPROVEMENT PROJECT – P147924 Project Implementation agency: MINISTRY OF EDUCATION Date of the Procurement Plan: AUGUST 27, 2021 Period covered by this Procurement Plan: 2021-2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: Not Applicable. Works: Not Applicable. Other Relevant Procurement Information. Not Applicable. PROCUREMENT Guyana : Guyana Secondary Education Improvement PLAN General Information Country: Guyana 2021-08-27 Bank’s Approval Date of the Original Procurement Plan: 2022-09-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147924 GPN Date: Project Name: Guyana Secondary Education Improvement Loan / Credit No: IDA / 54730, IDA / 68250 Ministry of Education of Guyana Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - SEIP/W/RFB/2022/01 / Constr Component 2: Expansion of Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-12-0 IDA / 54730 Post Request for Bids 5,200,000.00 0.00 2022-11-21 2023-01-09 2023-02-23 2023-03-25 2023-05-25 uction of Prospect GSS General Secondary School F l nvelope (1 envelope proce lementation 6 acilities ss) SEIP/DC/W/2021/01 / Compl Component 2: Expansion of Other (with field f 2022-05-2 IDA / 54730 Post Direct Selection Direct 2,400,000.00 0.00 Canceled 2021-09-13 2021-11-10 2021-10-04 2021-11-29 etion of Good Hope Secondar General Secondary School F or explanation) 8 y School acilities Request for Bids - SEIP/ICB/W/01/2018 / School Component 2: Expansion of Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2020-03-2 IDA / 54730 Post Request for Bids 1,500,000.00 0.00 2018-03-15 2018-03-19 2018-05-02 2018-08-03 2018-10-01 Construction Westminister (C General Secondary School F l nvelope (1 envelope proce lementation 9 ivil Works) acilities ss) Request for Bids - SEIP/ICB/W/02/2018 / Constr Component 2: Expansion of Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2020-03-0 IDA / 54730 Post Request for Bids 4,082,506.80 0.00 2018-03-15 2018-03-19 2018-05-02 2018-08-03 2018-09-12 uction of Good Hope Seconda General Secondary School F l nvelope (1 envelope proce lementation 5 ry School acilities ss) Request for Bids - GSEIP/W/RFB/2022/02 / Com Component 1: Strengthen th Single Stage - One E Small Works SPD Pending Imp 2022-12-0 pletion of Electrical Works at IDA / 54730 e Capacity of Secondary Sch Post Request for Bids Open - National 571,000.00 0.00 2022-02-18 2022-02-25 2022-03-29 2022-04-28 2022-06-11 nvelope (1 envelope proce lementation 8 Good Hope Secondary School ool Mathematics Teachers N ss) ationwide Request for Quota GSEIP/W/RFQ/2022/01 / Com Component 1: Strengthen th Request for Quota Single Stage - One E tions - Small Work 2022-07-2 pletion of Plumbing Works at IDA / 54730 e Capacity of Secondary Sch Post Limited 240,000.00 0.00 Canceled 2022-02-25 2022-04-26 tions nvelope s (Emergency) SP 5 Goodhope Secondary School ool Mathematics Teachers N D -Competitive ationwide Request for Bids - GSEIP/W/RFB/2022/04 / Com Component 1: Strengthen th Single Stage - One E Small Works SPD Pending Imp 2022-12-0 pletion of External Works at IDA / 54730 e Capacity of Secondary Sch Post Request for Bids Open - National 340,000.00 0.00 2022-02-18 2022-02-25 2022-03-29 2022-04-28 2022-06-11 nvelope (1 envelope proce lementation 8 Goodhope Secondary School ool Mathematics Teachers N ss) ationwide GSEIP/W/RFQ/2022/02 / Com Component 1: Strengthen th Request for Quota pletion of Windows & Doors a e Capacity of Secondary Sch Request for Quota Single Stage - One E tions - Small Work 2022-07-2 IDA / 54730 Post Limited 150,000.00 0.00 Canceled 2022-02-25 2022-04-26 nd Roof Works at Goodhope ool Mathematics Teachers N tions nvelope s (Emergency) SP 5 Secondary School ationwide D -Competitive Request for Bids - GSEIP/W/RFB/2022/05 / Com Component 1: Strengthen th Single Stage - One E Small Works SPD Pending Imp 2022-08-2 pletion of Windows & Doors a IDA / 54730 e Capacity of Secondary Sch Post Request for Bids Open - National 150,000.00 0.00 2022-03-04 2022-03-06 2022-03-29 2022-04-28 2022-05-26 nvelope (1 envelope proce lementation 4 nd Roof Works at Goodhope ool Mathematics Teachers N ss) Secondary School ationwide Request for Bids - GSEIP/W/RFB/2022/03 / Com Component 1: Strengthen th Single Stage - One E Small Works SPD Pending Imp 2022-08-2 pletion of Plumbing Works at IDA / 54730 e Capacity of Secondary Sch Post Request for Bids Open - National 240,000.00 0.00 2022-03-04 2022-03-06 2022-03-29 2022-04-28 2022-05-26 nvelope (1 envelope proce lementation 4 Goodhope Secondary School ool Mathematics Teachers N ss) ationwide National Procure GSEIP/W/RFB/2022/06 / Clea Component 2: Expansion of ment Document - Single Stage - One E Pending Imp 2022-08-2 ning and clearing of compou IDA / 54730 General Secondary School F Post Request for Bids Open - National 1 Envelope proce 10,000.00 0.00 2022-03-04 2022-03-06 2022-03-29 2022-04-28 2022-05-26 nvelope lementation 4 nd at Goodhope School acilities ss (Non Bank-SPD ) Request for Bids - SEIP/W/RFB/2022/06 / Install Component 2: Expansion of Single Stage - One E Small Works SPD Pending Imp 2023-07-2 ation of Drains and Walkways IDA / 68250 General Secondary School F Post Request for Bids Open - National 125,000.00 0.00 2022-10-10 2022-10-15 2022-11-26 2022-12-26 2023-01-30 nvelope (1 envelope proce lementation 9 at Westminister Secondary S acilities ss) chool GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SEIP/G/RFB/2021/03 / Procur Component 1: Strengthen th Open - Internationa Single Stage - One E Pending Impl ement of Equipment for Sma IDA / 54730 e Capacity of Secondary Sch Post Request for Bids 1,000,000.00 0.00 2021-10-11 2021-10-18 2021-11-17 2021-12-17 2022-02-02 2022-06-02 l nvelope ementation rt Classroom ool Mathematics Teachers N ationwide SEIP/G/RFB/2021/02 / Procur Component 1: Strengthen th Single Stage - One E ement of Auxilliary Hardware IDA / 54730 e Capacity of Secondary Sch Post Request for Bids Open - National 56,550.00 0.00 Canceled 2021-10-11 2021-10-18 2021-11-17 2021-12-17 2022-02-02 2022-06-02 nvelope - Tablets ool Mathematics Teachers N ationwide SEIP/G/RFB/2021/05 / School Component 2: Expansion of Single Stage - One E Pending Impl IDA / 54730 Post Request for Bids Open - National 700,000.00 0.00 2024-02-12 2024-03-01 2024-04-02 2024-05-02 2024-06-23 2024-12-27 Furnishing - Prospect GSS General Secondary School F nvelope ementation acilities SEIP/G/RFB/2021/01 / Procur Component 1: Strengthen th Single Stage - One E Pending Impl ement of Tablets for Student IDA / 54730 e Capacity of Secondary Sch Post Request for Bids Open - National 600,000.00 0.00 2021-10-11 2021-10-18 2021-11-17 2021-12-17 2022-02-02 2022-06-02 nvelope ementation s and Teachers Hardware ool Mathematics Teachers N ationwide SEIP/NCB/G/03/2019 / Procur Component 2: Expansion of ement of TVET materials for Single Stage - One E Pending Impl IDA / 54730 General Secondary School F Post Request for Bids Open - National 158,031.00 0.00 2019-09-01 2019-09-29 2019-10-29 2019-11-28 2019-12-17 2020-06-14 Good Hope and Westministe nvelope ementation acilities r Secondary Schools SEIP/NCB/G/02/2019 / Procur Component 2: Expansion of ement of Lab Equipment for Single Stage - One E Pending Impl IDA / 54730 General Secondary School F Post Request for Bids Open - National 142,054.40 0.00 2019-09-01 2019-09-29 2019-10-29 2019-11-28 2019-12-17 2020-03-17 Good Hope and Westminister nvelope ementation acilities Secondary Schools. SEIP/NCB/G/04/2019 / Procur Component 2: Expansion of ement of Home Economics E Single Stage - One E Pending Impl IDA / 54730 General Secondary School F Post Request for Bids Open - National 171,563.06 0.00 2019-09-01 2019-09-29 2019-10-29 2019-11-28 2019-12-17 2020-03-17 quipment for Good Hope and nvelope ementation acilities West Minister Secondary Sch ools. GSEIP/G/DC/2022/01 / Conte Component 1: Strengthen th Under Imple nt Server for Computing Devi IDA / 54730 e Capacity of Secondary Sch Post Direct Selection Direct 56,000.00 0.00 2022-02-28 2022-07-07 2022-03-21 2022-05-23 2022-11-19 mentation ces ool Mathematics Teachers N ationwide SEIP/G/RFB/2022/01 / Supply Component 2: Expansion of and Installation of 4 Elevator Single Stage - One E Pending Impl IDA / 68250 General Secondary School F Post Request for Bids Open - National 250,000.00 0.00 2022-10-24 2022-10-29 2022-11-28 2022-12-19 2023-01-23 2023-07-22 Lifts at Westminister and Go nvelope ementation acilities od Hope Secondary Schools Page 1 SEIP/G/RFQ/2022/01 / Supply Component 2: Expansion of of Digitally printed signes at Request for Quota Single Stage - One E Pending Impl IDA / 68250 General Secondary School F Post Limited 3,000.00 0.00 2022-09-19 2022-11-14 2023-01-13 West Minister Secondary Sch tions nvelope ementation acilities ool to meet TVET requiremen ts. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SEIP/NCS/RFQ/2021/02 / Con Component 1: Strengthen th duct Training session for mas e Capacity of Secondary Sch Request for Quota Single Stage - One E Pending Impl IDA / 54730 Post Limited 5,000.00 0.00 2022-04-18 2022-06-20 2022-07-27 ter trainers (MT local travel, ool Mathematics Teachers N tions nvelope ementation meals & materials/supplies) - ationwide Smart Classrooms SEIP/NCS/IC/2021/03 / Follow Component 1: Strengthen th up visits of master trainers to IDA / 54730 e Capacity of Secondary Sch Post Direct Selection Direct 1,000.00 0.00 Canceled 2021-06-28 2021-07-05 2021-08-09 2021-08-23 teachers in schools (2 years) ool Mathematics Teachers N ationwide SEIP/NCS/IC/2021/01 / Traini Component 1: Strengthen th ng of master trainers (MT loc IDA / 54730 e Capacity of Secondary Sch Post Direct Selection Direct 5,000.00 0.00 Canceled 2021-07-05 2021-07-06 2021-08-09 2021-08-23 al time, meals & honoraria) ool Mathematics Teachers N ationwide SEIP/NCS/RFQ/2022/02 / Trai Component 1: Strengthen th ning sessions to train (50) te e Capacity of Secondary Sch Request for Quota Single Stage - One E Pending Impl IDA / 54730 Post Limited 95,000.00 0.00 2022-04-18 2022-06-20 2022-07-27 achers in regions (1 week) (L ool Mathematics Teachers N tions nvelope ementation ocal travel, Meals, Accomoda ationwide tion & Honoraria for MT) SEIP/NC/RFQ/2021/01 / Train Component 1: Strengthen th ing of master trainers (in use e Capacity of Secondary Sch Request for Quota Single Stage - One E Pending Impl IDA / 54730 Post Limited 10,000.00 0.00 2022-04-18 2022-06-20 2022-07-27 of Tablets) course in Georget ool Mathematics Teachers N tions nvelope ementation own - (MT local travel, Meals ationwide & Materials/Supplies) SEIP/NCS/DC/2021/01 / Tem Component 2: Expansion of Under Imple porary Storage of Furniture a IDA / 54730 General Secondary School F Post Direct Selection Direct 23,770.00 0.00 2021-09-27 2021-10-29 2021-10-18 2021-11-22 2021-12-22 mentation nd Equipment: Good Hope an acilities d West Minister SEIP/NCS/RFQ/2022/04 / Trai Component 1: Strengthen th Request for Quota Single Stage - One E Pending Impl ning Sessions to train teache IDA / 68250 e Capacity of Secondary Sch Post Limited 11,000.00 0.00 2022-04-18 2022-06-20 2022-07-27 tions nvelope ementation rs in use of smart classrooms ool Mathematics Teachers N ationwide GSEIP/NCS/RFQ/2022/01 / Cl Component 2: Expansion of Request for Quota Single Stage - One E eaning and clearing of comp IDA / 54730 General Secondary School F Post Limited 10,000.00 0.00 Canceled 2022-02-25 2022-04-22 2022-05-06 tions nvelope ound at Goodhope School acilities SEIP/NCS/DC/2022/01 / Provi Component 2: Expansion of sion of Services to connect al Pending Impl IDA / 68250 General Secondary School F Post Direct Selection Direct - National 5,000.00 0.00 2022-09-14 2022-09-19 2022-10-24 2023-04-22 l TVET equipment at West Mi ementation acilities nister Secondary School. SEIP/NCS/DC/2022/02 / Provi Component 2: Expansion of Pending Impl sion of Service for the install IDA / 68250 General Secondary School F Post Direct Selection Direct - National 5,000.00 0.00 2022-09-14 2022-09-19 2022-10-24 2023-04-22 ementation ation of LPG at West Minister acilities Secondary School CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SEIP/CS/QCBS/2021/01 / Des Component 2: Expansion of Quality And Cost- Open - Internationa ign and Supervision of Works IDA / 68250 General Secondary School F Post 825,166.00 0.00 Under Review 2021-04-13 2021-06-24 2021-10-12 2021-12-20 2022-02-03 2022-02-24 2022-03-31 2022-05-05 2023-05-05 Based Selection l for Prospect Secondary Scho acilities ol SEIP/QCBS/03/2018 / Superv Component 2: Expansion of Quality And Cost- Open - Internationa ision of Works - Good Hope & IDA / 54730 General Secondary School F Post 423,000.00 0.00 Under Review 2016-03-29 2016-04-03 2016-04-13 2016-09-08 2016-10-25 2017-02-10 2017-06-12 2017-09-07 2018-01-05 Based Selection l Westminster acilities SEIP/QCBS/01/2015 / Design Component 2: Expansion of Quality And Cost- Open - Internationa Pending Impleme of Civil Works 3 General seco IDA / 54730 General Secondary School F Post 346,066.92 0.00 2015-03-19 2015-04-08 2015-07-01 2015-11-11 2016-01-13 2016-01-21 2016-03-11 2018-08-15 Based Selection l ntation ndary schools acilities INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Strengthen In SEIP/CS/DC/2021/03 / Financ Under Implement IDA / 54730 stitutional Capacity and Proj Post Direct Selection Direct 38,429.00 0.00 2021-03-28 2021-03-01 2021-03-28 2021-04-01 2022-03-31 e Officer ation ect Management Component 3: Strengthen In SEIP/CS/DC/2021/04 / Financ Under Implement IDA / 54730 stitutional Capacity and Proj Post Direct Selection Direct 6,000.00 0.00 2021-03-28 2021-03-01 2021-03-29 2021-04-01 2022-03-31 e Assistant ation ect Management Component 3: Strengthen In SEIP/CS/DC/2021/05 / Monito Under Implement IDA / 54730 stitutional Capacity and Proj Post Direct Selection Direct 8,635.00 0.00 2021-04-01 2021-03-01 2021-04-01 2021-04-01 2022-03-31 ring and Evaluation Officer ation ect Management Component 3: Strengthen In SEIP/CS/DC/2021/01 / Projec IDA / 54730 stitutional Capacity and Proj Post Direct Selection Direct 49,758.00 0.00 Canceled 2021-03-24 2021-03-24 2021-04-01 2022-03-31 t Coordinator ect Management SEIP/CS/IC/2021/011 / Consu Component 1: Strengthen th Individual Consult Pending Impleme ltancy to Train Master Teach IDA / 54730 e Capacity of Secondary Sch Post Limited 15,000.00 0.00 2022-03-07 2022-04-11 2022-04-25 2022-05-30 2022-06-29 ant Selection ntation ers - Smart Classrooms ool Mathematics Teachers N ationwide SEIP/CS/DC/2022/03 / Master Component 1: Strengthen th Pending Impleme trainer #3 to train teachers i IDA / 54730 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-09 2023-09-02 ntation n use of smart classrooms. ool Mathematics Teachers N ationwide Page 2 SEIP/CS/DC/2021/08 / Consul Component 1: Strengthen th tant to adapt software to curr e Capacity of Secondary Sch Under Implement IDA / 54730 Post Direct Selection Direct 90,000.00 0.00 2022-03-28 2022-06-20 2022-04-18 2022-06-06 2022-07-13 iculum/ develop and execute ool Mathematics Teachers N ation training of master trainers-Ta ationwide blets SEIP/CS/DC/2022/06 / Master Component 1: Strengthen th Pending Impleme Trainer#1 to Train teachers i IDA / 68250 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-11 2023-09-04 ntation n use of Tablets ool Mathematics Teachers N ationwide SEIP/CS/DC/2022/07 / Master Component 1: Strengthen th Pending Impleme trainer #2 to train teachers i IDA / 68250 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-11 2023-09-04 ntation n use of Tablets ool Mathematics Teachers N ationwide SEIP/CS/DC/2022/08 / Master Component 1: Strengthen th Pending Impleme Trainer #3 to train teachers i IDA / 68250 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-11 2023-09-04 ntation n use of Tablets ool Mathematics Teachers N ationwide SEIP/CS/DC/2022/09 / Master Component 1: Strengthen th Pending Impleme Trainer #4 to train teachers i IDA / 68250 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-11 2023-09-04 ntation n use of Tablets ool Mathematics Teachers N ationwide Component 1: Strengthen th SEIP/CS/DC/2022/10 / Master Pending Impleme IDA / 68250 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-11 2023-09-04 trainer #5 to train Teachers ntation ool Mathematics Teachers N ationwide SEIP/CS/DC/2022/01 / Master Component 1: Strengthen th Pending Impleme trainer #1 to train teachers i IDA / 54730 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-09 2023-09-02 ntation n use of smart classrooms. ool Mathematics Teachers N ationwide SEIP/CS/DC/2022/02 / Master Component 1: Strengthen th Pending Impleme trainer #2 to train teachers i IDA / 54730 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-09 2023-09-02 ntation n use of smart classrooms. ool Mathematics Teachers N ationwide SEIP/CS/DC/2022/04 / Master Component 1: Strengthen th Pending Impleme trainer #4 to train teachers i IDA / 54730 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-09 2023-09-02 ntation n use of smart classrooms. ool Mathematics Teachers N ationwide SEIP/CS/DC/2022/05 / Master Component 1: Strengthen th Pending Impleme trainer #5 to train teachers i IDA / 54730 e Capacity of Secondary Sch Post Direct Selection Direct 2,000.00 0.00 2022-05-09 2022-05-21 2022-06-09 2023-09-02 ntation n use of smart classrooms. ool Mathematics Teachers N ationwide SEIP/CS/IC/2021/01 / Adapta Component 1: Strengthen th tion of software to curriculum e Capacity of Secondary Sch Individual Consult IDA / 54730 Post Open 15,000.00 0.00 Canceled 2021-06-01 2021-07-06 2021-07-20 2021-07-27 2021-10-02 / develop and execute trainin ool Mathematics Teachers N ant Selection g of master trainers ationwide SEIP/CS/DC/2021/06 / Enviro Component 3: Strengthen In Under Implement nment and Social Developme IDA / 54730 stitutional Capacity and Proj Post Direct Selection Direct 19,800.00 0.00 2021-04-01 2021-03-01 2021-04-01 2021-04-01 2022-03-31 ation nt Specialist ect Management SEIP/CS/DC/2021/30 / Prepar Component 2: Expansion of Pending Impleme ation of documents to compl IDA / 68250 General Secondary School F Post Direct Selection Direct 28,420.00 0.00 2021-06-01 2021-06-24 2021-10-14 2022-02-11 ntation ete Good Hope Secondary Sc acilities hool Component 3: Strengthen In SEIP/CS/DC/2021/10 / Projec Pending Impleme IDA / 68250 stitutional Capacity and Proj Post Direct Selection Direct 57,758.21 0.00 2021-06-30 2021-07-10 2021-08-01 2022-08-01 t Engineer/ Coordinator ntation ect Management Component 3: Strengthen In SEIP/CS/DC/2021/09 / Procur Under Implement IDA / 68250 stitutional Capacity and Proj Post Direct Selection Direct 6,000.00 0.00 2021-03-01 2021-03-01 2021-03-15 2021-04-01 2022-04-01 ement Officer ation ect Management Component 3: Strengthen In SEIP/CS/DC/2021/02 / Projec IDA / 54730 stitutional Capacity and Proj Post Direct Selection Direct 49,758.00 0.00 Canceled 2021-03-24 2021-03-24 2021-04-01 2022-03-31 t Engineer ect Management Page 3