The World Bank Implementation Status & Results Report Honduras Tropical Cyclones Eta and Iota Emergency Recovery Project (P175977) Honduras Tropical Cyclones Eta and Iota Emergency Recovery Project (P175977) LATIN AMERICA AND CARIBBEAN | Honduras | Urban, Resilience and Land Global Practice | IBRD/IDA | Investment Project Financing | FY 2021 | Seq No: 4 | ARCHIVED on 16-Oct-2022 | ISR53015 | Implementing Agencies: Republic of Honduras, SEDECOAS (Secretaría de Desarrollo Comunitario, Agua y Saneamiento) Key Dates Key Project Dates Bank Approval Date: 18-Dec-2020 Effectiveness Date: 04-Jun-2021 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2026 Revised Closing Date: 31-Dec-2026 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to support Honduras' response and recovery needs and strengthen institutional capacity to manage a resilient and inclusive recovery and reconstruction. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Emergency relief, response and public health and safety operations:(Cost $17.30 M) Component 2: Resilient rehabilitation and reconstruction of public and community infrastructure and resumption of public services:(Cost $121.70 M) Component 3: Institutional support to the Government recovery and reconstruction program:(Cost $11.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The Project was approved by the World Bank on December 18, 2020. The Project Financing Agreement was signed on March 9 and became effective on June 4, 2021. To date, the Government has established the Project Implementation Unit, finalized all the environmental and social safeguards instruments, and supported the immediate response relief needs following Eta and Iota though delivery of food and nonfood items. The project has commenced with the works component, starting with the school reconstruction and repairs works. A solid pipeline of water and transport sector reconstruction works is also under preparation. 10/16/2022 Page 1 of 7 The World Bank Implementation Status & Results Report Honduras Tropical Cyclones Eta and Iota Emergency Recovery Project (P175977) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Moderate Substantial Substantial Technical Design of Project or Program Moderate Substantial Substantial Institutional Capacity for Implementation and High High High Sustainability Fiduciary High High High Environment and Social High High High Stakeholders Substantial Substantial Substantial Other Substantial Substantial Substantial Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Support Honduras' response and recovery needs IN01188933 ►People benefiting from sustained livelihoods through emergency response and relief services from the GoH (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 300,000.00 100,000.00 Date 09-Nov-2020 12-Mar-2021 06-Oct-2022 31-Dec-2026 This indicator will measure the number of people benefiting from sustained livelihoods through emergency Comments: response and relief services from the GoH financed by this Project. IN01188935 Percentage of which are women (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 48.00 IN01189041 Percentage of which are IPs and ADs (Text, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target 10/16/2022 Page 2 of 7 The World Bank Implementation Status & Results Report Honduras Tropical Cyclones Eta and Iota Emergency Recovery Project (P175977) Value 0.00 0.00 0.00 TBD IN01189042 ►People benefiting from restored public services in a resilient manner (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 800,000.00 Date 09-Nov-2020 12-Mar-2021 12-Mar-2021 31-Dec-2026 This indicator will measure the number of people benefiting from restored public services in a resilient Comments: manner financed by this Project. IN01189043 Percentage of which are women (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 48.00 IN01189044 Percentage of which are IPs and ADs (Text, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 TBD strengthen institutional capacity to manage resilientand inclusive reconstruction and recovery from IN01188934 ►Local recovery participatory planning processes (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 09-Nov-2020 12-Mar-2021 12-Mar-2021 31-Dec-2026 This indicator will measure the number of local recovery participatory planning processes. Local planning Comments: process might include, among others local stakeholders, local governments and organizations of IPs and ADs. Overall Comments PDO Pending the disaggregation of the data. Intermediate Results Indicators by Components Emergency relief, response and public health and safety operations IN01189045 ►People benefiting from food/non food items distribution (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target 10/16/2022 Page 3 of 7 The World Bank Implementation Status & Results Report Honduras Tropical Cyclones Eta and Iota Emergency Recovery Project (P175977) Value 0.00 0.00 300,000 72,000 Date 09-Nov-2020 12-Mar-2021 04-Oct-2022 31-Dec-2021 This indicator will measure the number of people benefiting from food-non food items distribution financed Comments: by the Project. IN01189049 Percentage of which are IPs/ADs (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 TBD Date 02-Nov-2020 12-Mar-2021 12-Mar-2021 31-Dec-2026 Resilient rehab. and reconstruction of public and community infra. and resumption of public services IN01189046 ►Number of repaired, reconstructed or new public infrastructure (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 200.00 Date 09-Nov-2020 12-Mar-2021 12-Mar-2021 31-Dec-2026 This indicator will measure the number of repaired, reconstructed or new public infrastructure financed by Comments: this Project. IN01189048 ►People benefiting from restored access to an all-season road (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80,000 Date 02-Nov-2020 12-Mar-2021 12-Mar-2021 31-Dec-2026 This indicator will measure the number of people benefitting from restored access to an all-season road Comments: financed by the Project. IN01189052 Percentage of which are women (Text, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 48.00 IN01189054 Percentage of which are IPs and ADs (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 TBD Date 02-Nov-2020 12-Mar-2021 12-Mar-2021 31-Dec-2026 IN01189055 ►Average citizen satisfaction rate with at least one subproject provided under component 2 (Percentage, Custom) 10/16/2022 Page 4 of 7 The World Bank Implementation Status & Results Report Honduras Tropical Cyclones Eta and Iota Emergency Recovery Project (P175977) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 85.00 Date 02-Nov-2020 12-Mar-2021 12-Mar-2021 31-Dec-2026 This indicator will measure the average citizen satisfaction rate with at least one subproject provided Comments: under component 2 Institutional support to the Government recovery and reconstruction program IN01189047 ►Staff trained in recovery planning and/or project management (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 200.00 Date 02-Feb-2021 12-Mar-2021 12-Mar-2021 31-Dec-2026 This indicator will measure the number of staff trained in recovery planning and/or project management Comments: financed by the Project. Trained Staff can include personnel from the PIU, staff from the PIU institution, and local government personnel. IN01189050 Percentage of which are women (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 48.00 IN01189051 Percentage of which are IPs and ADs (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 TBD Date 02-Feb-2021 12-Mar-2021 12-Mar-2021 31-Dec-2026 IN01189053 ►Number of information and communication outputs related to recovery and reconstruction program (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 500.00 Date 01-Feb-2021 12-Mar-2021 12-Mar-2021 31-Dec-2026 This indicator will measure the number of information and communication activities related to the recovery Comments: and reconstruction program financed by the Project. Information and communication activities will be defined in the MOP. IN01189056 ►Grievances responded to in the stipulated time (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 98.00 100.00 10/16/2022 Page 5 of 7 The World Bank Implementation Status & Results Report Honduras Tropical Cyclones Eta and Iota Emergency Recovery Project (P175977) Date 01-Feb-2021 12-Mar-2021 04-Oct-2022 31-Dec-2026 The indicator will measure the proportion of grievances responded to in the stipulated time, as defined by Comments: the safeguards documents. Overall Comments IR Results in this reporting period include 300,000 people benefiting from food and nonfood items following the emergency. This is a 316 percent increase from estimated 72,000 beneficiaries targeted. The disaggregation of the data has not been analyzed currently. In addition, 98 percent of the grievances received until August 2022 have been responded to by the PIU. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P175977 IDA-68220 Effective USD 150.00 150.00 0.00 21.19 128.81 14% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P175977 IDA-68220 Effective 18-Dec-2020 08-Mar-2021 04-Jun-2021 31-Dec-2026 31-Dec-2026 Cumulative Disbursements 10/16/2022 Page 6 of 7 The World Bank Implementation Status & Results Report Honduras Tropical Cyclones Eta and Iota Emergency Recovery Project (P175977) Restructuring History Level 2 Approved on 16-Dec-2021 Related Project(s) There are no related projects. 10/16/2022 Page 7 of 7