The World Bank                                                                                      Implementation Status & Results Report
         IN National Ganga River Basin Project (P119085)



IN National Ganga River Basin Project (P119085)


 SOUTH ASIA | India | Water Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2011 | Seq No: 22 | ARCHIVED on 17-Dec-2021 | ISR49607 |


 Implementing Agencies: India, Ministry of Jal Shakti, Department of Water Resources, River Development and Ganga Rejuvenation, National
 Mission for Clean Ganga



 Key Dates


  Key Project Dates

   Bank Approval Date: 31-May-2011                                            Effectiveness Date: 18-Aug-2011
   Planned Mid Term Review Date: 18-Jul-2015                                  Actual Mid-Term Review Date: 18-Jul-2015
   Original Closing Date: 31-Dec-2019                                         Revised Closing Date: 30-Dec-2021
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The objectives of the project are to support the National Ganga River Basin Authority (NGRBA) in:
  (a) building capacity of its nascent operational-level institutions, so that they can manage the long-term Ganga clean-up and conservation
  program; and
  (b) implementing a diverse set of demonstrative investments for reducing point-source pollution loads in a sustainable manner, at priority locations
  on the Ganga.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component One: Institutional Development:(Cost $10.00 M)
 Component Two: Priority Infrastructure Investments:(Cost $1116.00 M)

 Overall Ratings

 Name                                                                       Previous Rating                          Current Rating

 Progress towards achievement of PDO                                        Moderately Satisfactory                 Moderately Satisfactory
 Overall Implementation Progress (IP)                                       Moderately Satisfactory                 Moderately Satisfactory
 Overall Risk Rating                                                        Substantial                             Substantial


 Implementation Status and Key Decisions

  The Ganga 1 is on track to meet its Development Objective at closing on December 30, 2021 and fully disburse. Selected investments will be
  carried forward to the follow-on Ganga 2 Project once Ganga 1 closes.




12/17/2021                                                                                                                   Page 1 of 7
            The World Bank                                                                                     Implementation Status & Results Report
            IN National Ganga River Basin Project (P119085)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                               Rating at Approval            Previous Rating                Current Rating

  Political and Governance                                    --                            Moderate                      Moderate
  Macroeconomic                                               --                            Moderate                      Moderate
  Sector Strategies and Policies                              --                            Substantial                   Substantial
  Technical Design of Project or Program                      --                            Substantial                   Substantial
  Institutional Capacity for Implementation and
                                                              --                            Substantial                   Substantial
  Sustainability
  Fiduciary                                                   --                            Moderate                      Moderate
  Environment and Social                                      --                            Substantial                   Substantial
  Stakeholders                                                --                            Moderate                      Moderate
  Other                                                       --                            --                             --
  Overall                                                     --                            Substantial                   Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Building institutional capacity

    IN01080757
    ►New Programme institutions are set up & are effectively functioning (Number, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                              0.00                        6.00                          5.00                      6.00

    Date                               31-May-2011                 30-Apr-2021                   10-Dec-2021              31-Dec-2021

   IN01080759
   ►Sanitation Operators with O&M management plan and related staff capacity building program approved and under implementation
   (Number, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                              0.00                        0.00                          0.00                      4.00

    Date                               31-May-2011                 30-Apr-2021                   10-Dec-2021              31-Dec-2021



   Reducing point source pollution load

    IN01080758



12/17/2021                                                                                                                      Page 2 of 7
           The World Bank                                                                                   Implementation Status & Results Report
           IN National Ganga River Basin Project (P119085)




    ►Direct project beneficiaries (number in million) (Number, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       2.82                         3.48                      3.57

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021              31-Dec-2021

    IN01080760
    ►Amount of BOD pollution load abated by sewage treatment plants built or rehabilitated under the Project (Metric tons/year, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       13,395.00                    16,537.00                 16,500.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021              31-Dec-2021

    IN01080766
    ►Households connected to network sanitation systems under the Project (Number, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       229,296.00                   310,324.00                325,000.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021              31-Dec-2021

    IN01080767
    ►Volume of untreated wastewater prevented from entering the Ganga due to project interventions (MLD) (Number, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       305.00                       376.00                    386.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021              31-Dec-2021



 Intermediate Results Indicators by Components



   Component One : Institutional Development

    IN01080768
    ►Capacity building plan for regulators approved and under implementation (Yes/No, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             No                         No                           No                        Yes

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021              31-Dec-2021

    IN01080770
    ►Number of Water quality monitoring stations generating real time data (Number, Custom)

                                      Baseline                   Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                       36.00                        55.00                     70.00


12/17/2021                                                                                                                 Page 3 of 7
           The World Bank                                                                                    Implementation Status & Results Report
           IN National Ganga River Basin Project (P119085)




    Date                              31-May-2011                 30-Apr-2021                  10-Dec-2021               31-Dec-2021

    IN01080774
    ►Grievance Redressal System in place at the national level, in each State and at sites of each sub-project (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        6.00                         6.00                      6.00

    Date                              31-May-2019                 30-Apr-2021                  10-Dec-2021               31-Dec-2021

    IN01080776
    ►Percentage of planned professional staff positions filled in NMCG central and state-level institutions (Percentage, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             5.00                        85.00                        74.00                     100.00

    Date                              31-May-2011                 30-Apr-2021                  10-Dec-2021               31-Dec-2021

    IN01080778
    ►Number of ULBs with an approved plan for covering the O&M costs of the sanitation service beyond the project period (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        0.00                         0.00                      4.00

    Date                              31-Jul-2019                 30-Apr-2021                  10-Dec-2021               31-Dec-2021

   IN01080779
   ►Number of cities where community outreach campaigns are being implemented to promote household connections to sewer networks
   (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        3.00                         7.00                      4.00

    Date                              31-May-2011                 30-Apr-2021                  10-Dec-2021               31-Dec-2021

    IN01080780
    ►Share of grievances addressed within 30 days from receipt (Percentage, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        98.40                        100.00                    80.00

    Date                              31-May-2011                 30-Apr-2021                  10-Dec-2021               31-Dec-2021

    IN01080781
    ►Number of investments funded under the Project showing physical completion rates of 70% or more (Percentage, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        76.50                        81.00                     80.00

    Date                              31-May-2011                 30-Apr-2021                  10-Dec-2021               31-Dec-2021




12/17/2021                                                                                                                   Page 4 of 7
           The World Bank                                                                                   Implementation Status & Results Report
           IN National Ganga River Basin Project (P119085)




   Component Two : Priority Infrastructure Investments

    IN01080769
    ►Share of BOD pollution load from point source in priority locations abated under the Project (Percentage, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                             0.00                       36.00                        71.00                      70.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021                31-Dec-2021

    IN01080771
    ►% of targeted river front management investments completed (Percentage, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                             0.00                       93.00                        100.00                     100.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021                31-Dec-2021

    IN01080772
    ►Wastewater treatment capacity created (per day) (Liters (Million), Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                             0.00                       231.00                       280.00                     344.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021                31-Dec-2021

    IN01080773
    ►Number of cities/towns following the one-city one operator model (Number, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                             0.00                       3.00                         5.00                       5.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021                31-Dec-2021

   IN01080775
   ►Infrastructure investments by value with 10 years or more of O&M including DBOT or PPP – Hybrid Annuity under the Project (Percentage,
   Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                             0.00                       95.00                        95.00                      95.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021                31-Dec-2021

    IN01080777
    ►Length of sewerage network laid under the Project (Kilometers, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)           End Target

    Value                             0.00                       2,496.00                     2,595.00                   2,700.00

    Date                              31-May-2011                30-Apr-2021                  10-Dec-2021                31-Dec-2021




12/17/2021                                                                                                                  Page 5 of 7
           The World Bank                                                                                    Implementation Status & Results Report
           IN National Ganga River Basin Project (P119085)




 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status       Currency        Original   Revised     Cancelled     Disbursed       Undisbursed                % Disbursed


 P119085       IBRD-80650        Effective    USD             801.00      340.30        460.70          322.04           18.26                       95%

 P119085       IDA-49550         Effective    USD             199.00      199.00           0.00         179.41             0.00                     100%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date       Signing Date     Effectiveness Date      Orig. Closing Date      Rev. Closing Date

 P119085        IBRD-80650        Effective   31-May-2011         14-Jun-2011      18-Aug-2011             31-Dec-2019             30-Dec-2021
 P119085        IDA-49550         Effective   31-May-2011         14-Jun-2011      18-Aug-2011             31-Dec-2019             30-Dec-2021


Cumulative Disbursements




12/17/2021                                                                                                                      Page 6 of 7
          The World Bank                                                                            Implementation Status & Results Report
          IN National Ganga River Basin Project (P119085)



 PBC Disbursement

                                                                                 Achievement     Disbursed amount in     Disbursement %
 PBC ID                   PBC Type    Description           Coc   PBC Amount
                                                                                 Status          Coc                     for PBC




  Restructuring History

  Level 2 Approved on 24-Jun-2015 ,Level 2 Approved on 27-Dec-2016 ,Level 2 Approved on 12-Jun-2017 ,Level 2 Approved on 12-Aug-2019
  ,Level 2 Approved on 04-Oct-2019 ,Level 2 Approved on 26-Jul-2021

  Related Project(s)


 There are no related projects.