The World Bank                                                                                         Implementation Status & Results Report
          Digital Governance and Identification Management System Project- PRODIGY (P169413)



Digital Governance and Identification Management System Project- PRODIGY (P169413)


 EASTERN AND SOUTHERN AFRICA | Madagascar | Governance Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2021 | Seq No: 5 | ARCHIVED on 23-Dec-2022 | ISR54516 |


 Implementing Agencies: Government of Madagascar, PRODIGY PIU



 Key Dates


  Key Project Dates

   Bank Approval Date: 29-Sep-2020                                               Effectiveness Date: 12-Oct-2020
   Planned Mid Term Review Date: --                                              Actual Mid-Term Review Date:
   Original Closing Date: 31-Dec-2024                                            Revised Closing Date: 31-Dec-2024
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective is to strengthen the Identity Management ("ID-M") system and government capacity to deliver services in
  Selected Sectors.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Creation of a Consolidated and Interoperable Identity Management System:(Cost $86.00 M)
 Digital and Mobile Government Services:(Cost $52.00 M)
 Project Management and Implementation:(Cost $5.00 M)

 Overall Ratings

 Name                                                                          Previous Rating                           Current Rating

 Progress towards achievement of PDO                                           Moderately Satisfactory                  Moderately Unsatisfactory
 Overall Implementation Progress (IP)                                          Moderately Satisfactory                  Moderately Unsatisfactory
 Overall Risk Rating                                                           Moderate                                 Substantial


 Implementation Status and Key Decisions

  The project has been effective since June 2021. Overall, there has been limited progress towards achieving all project development objectives and
  results indicators. Operational planning of activities is slower that expected with total project disbursement level remaining very low at 8.4%. This is
  partly due to the late preparation of a roadmap for the implementation of component 1 in the context of limited institutional stability and coordination
  as well as delays in the adoption of key regulations.
  Despite limited overall progress, the project has achieved several important milestones and results, including:
  -     Under Component 1, Creation of a Consolidated and Interoperable Identity Management System (relating to the management of the identity
  system): Positive progress on the institutional side has been achieved, namely the creation and continued operationalization of the CNECI and the
  elaboration of an operation project roadmap. Several actions have been identified to expand systematic and retroactive birth registration and
  attribute the unique identity number progressively.



12/23/2022                                                                                                                       Page 1 of 8
            The World Bank                                                                                     Implementation Status & Results Report
            Digital Governance and Identification Management System Project- PRODIGY (P169413)



  -    Under Component 2, Digital and Mobile Government Services (relating to the transformation of public services): There are several notable
  achievements realized including : digitization of a number of key government services (including the vaccination platform VAKSINY and the
  business registration platform ORINASA.mg), the roll-out of an interoperability platform integrating 6 government services and information systems,
  and the publication of government service portal.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval              Previous Rating               Current Rating

  Political and Governance                                   Substantial                    Substantial                  Substantial
  Macroeconomic                                              Moderate                       Moderate                     Moderate
  Sector Strategies and Policies                             Moderate                       Moderate                     Moderate
  Technical Design of Project or Program                     Moderate                       Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                             Moderate                       Moderate                     Substantial
  Sustainability
  Fiduciary                                                  Substantial                    Moderate                     Substantial
  Environment and Social                                     Moderate                       Moderate                     Moderate
  Stakeholders                                               Moderate                       Moderate                     Moderate
  Other                                                      Substantial                    Substantial                  Substantial
  Overall                                                    Moderate                       Moderate                     Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Improved access to civil registration and upgraded national identity credentials

    IN01234844
    ►PDO 1- Share of population with new identity credential comprising their Unique Identity Number (UIN) (Percentage, Custom)

                                       Baseline                     Actual (Previous)           Actual (Current)           End Target

    Value                              0.00                        0.00                         0.00                       50.00

    Date                               01-Jun-2020                 20-Jun-2022                  20-Jun-2022               31-Dec-2024
                                       The UIN structure was technically validated in December 2021. A draft decree on the attribution and
                                       management of the UIN was elaborated but is pending adoption. The Government has requested TA
   Comments:
                                       support to finalize the decree and its operating manual.

      IN01234846
      Of which are female (Percentage, Custom Breakdown)


12/23/2022                                                                                                                    Page 2 of 8
           The World Bank                                                                                    Implementation Status & Results Report
           Digital Governance and Identification Management System Project- PRODIGY (P169413)




                                    Baseline                     Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                         0.00                         0.00                       50.00

     Date                           01-Jun-2020                  10-Dec-2021                  10-Dec-2021                31-Dec-2024


   Improved government capacity to deliver services in selected sectors.

    IN01234845
    ►PDO 2- Users benefiting from services compliant with new service standards (Number, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                         627,531.00                   627,531.00                 5,000,000.00

    Date                             01-Jun-2020                  15-Dec-2021                  15-Dec-2021                31-Dec-2024
                                      To date, three services are certified compliant with service standards:
                                      - Orinasa.Edbm.mg : a digital platform for enterprise creation : with a total of 18,824 users
                                      - Vaksiny.gov.mg : a digital platform primarily to manage the COVID-19 vaccine campaign but could be
   Comments:                          extend to other types of vaccines : with a total of 359,497 users
                                      - Torolalana.gov.mg : a digital one-stop-shop platform to get information on administrative procedures:
                                      with a total of 2729 users



 Intermediate Results Indicators by Components



   Creation of a consolidated and interoperable identity management system

    IN01234847
    ►C1-01. Modernization of the ID-M system (Text, Custom, PBC)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target
                                                                                               UIN structure
                                                                  UIN structure technically                               DGU has tested the
                                                                                               technically validated
                                                                  validated by Government                                 upgraded ID-M
                                     No UIN nor system                                         by Government but
    Value                                                         but pending official                                    credentials and
                                     architecture available                                    pending official
                                                                  adoption through a                                      published related test
                                                                                               adoption through a
                                                                  decree                                                  reports
                                                                                               decree
    Date                             01-Jun-2020                  20-Jun-2022                  20-Jun-2022                31-Dec-2024
                                      The Government has requested legal assistance to finalize the draft decree on UIN and its subsequent
   Comments:                          operation manual. Corresponding ToR are being finalized

   IN01234849
   ►C1-02. Share of civil registration entities implementing standard operating procedures (SOP) for registration of vital events (Percentage,
   Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                         0.00                         0.00                       70.00

    Date                             01-Jun-2020                  20-Jun-2022                  20-Jun-2022                31-Dec-2024




12/23/2022                                                                                                                   Page 3 of 8
           The World Bank                                                                                        Implementation Status & Results Report
           Digital Governance and Identification Management System Project- PRODIGY (P169413)



                                       Draft Standards Operating Procedures were developed is available and is currently being adjusted based
                                       on in field mission inputs. Additionally, the project has identified a first batch of pilot communes (up to 600
   Comments:
                                       communes out of a total of 1697) to test the SOP for the next 6 months

   IN01234851
   ►C1-03. Share of civil registration entities with secure access to the CR database/system connectivity with the national data base
   (Percentage, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                              0.00                         0.00                           0.00                       50.00

    Date                               01-Jun-2020                  20-Jun-2022                    20-Jun-2022                31-Dec-2024
                                       The pilot communes have been identified (up to 600 communes) and reflections on Communes
                                       connectivity ongoing with different TA planned (assessment of connectivity penetration rate
                                       The decree establishing the NCRIC was adopted in December 2020 but is pending operationalization. A
   Comments:                           draft organizational chart was elaborated but has yet to be finalized and adopted. The recruitment of
                                       CNECI's General Director is underway and should be finalized by mid-July. Recruitment of other key staff
                                       should be finalized by end of August.

    IN01234854
    ►C1-04. Share of children below one year old whose birth is registered (Percentage, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                              78.00                        78.00                          78.00                      95.00

    Date                               01-Jun-2020                  20-Jun-2022                    20-Jun-2022                31-Dec-2024
                                       Updated and accurate data birth of children under 1 year old is not available due to scattered data
                                       reporting at the district level. It is expected that the operationalization of the NCRIC would help address
   Comments:
                                       this shortcoming.

    IN01234856
    ►C1-05. Digitalized civil registration records (Number, Custom)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                              0.00                         0.00                           0.00                       2,000,000.00

    Date                               01-Jun-2020                  20-Jun-2022                    20-Jun-2022                31-Dec-2024
                                       This activity is pending the roll out process of the UIN expected to start in October 2022 with the new ID-M
   Comments:                           system in place



   Digital and Mobile Government Services

    IN01234848
    ►C2-06. Establishment of institutional, legal and infrastructural foundations for digital transformation (Text, Custom, PBC)

                                       Baseline                     Actual (Previous)              Actual (Current)           End Target
                                       Institutional, legal and
                                                                    The Government                 The Government             30% of DGU budget to
                                       infrastructural
                                                                    adopted a decree               adopted a decree           be financed by the
    Value                              foundations for digital
                                                                    establishing the DGU’s         establishing the DGU’s     Recipient’s internal
                                       transformation are not in
                                                                    institutional framework        institutional framework    resources
                                       place.




12/23/2022                                                                                                                        Page 4 of 8
           The World Bank                                                                                    Implementation Status & Results Report
           Digital Governance and Identification Management System Project- PRODIGY (P169413)




    Date                              01-Jun-2020                 20-Jun-2022                  20-Jun-2022                31-Dec-2024

                                       The proof of concept of the Digital Service Standards Manual is available
   Comments:

    IN01234850
    ►C2-07. Implementation of institutional and policy framework for data privacy and protection (Text, Custom, PBC)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target
                                                                                                                          CMIL has published a
                                                                  The draft of the decree      The draft of the decree    report on data privacy
                                      No effective data           operationalizing the CMIL    operationalizing the       and protection and
    Value
                                      protection                  is available and pending     CMIL is available and      organized a regional
                                                                  adoption.                    pending adoption.          public debate on the
                                                                                                                          findings of the report
    Date                              01-Jun-2020                 20-Jun-2022                  20-Jun-2022                31-Dec-2024
                                      The draft of the decree operationalizing the CMIL is available and pending adoption. The Manual of
   Comments:                          procedures is being drafted. The recruitment of a data protection TA is currently underway.

    IN01234852
    ►C2-08. Implementation of institutional and policy framework for civilian cybersecurity (Text, Custom, PBC)

                                      Baseline                    Actual (Previous)            Actual (Current)           End Target
                                                                  An early draft of the        An early draft of the
                                                                  strategy is available but    strategy is available      CERT has reviewed
                                      No effective civilian       needs further refining.      but needs further          (including through
    Value                             cybersecurity policy and    The CERT                     refining. The CERT         public consultations),
                                      strategy                    operationalization is        operationalization is      updated and published
                                                                  pending the recruitment      pending the                the NCCS
                                                                  of a TA                      recruitment of a TA
    Date                              01-Jun-2020                 20-Jun-2022                  20-Jun-2022                31-Dec-2024
                                       The operationalization of the CIRT encompasses the definition of its organizational chart, strategy and
                                      subsequent action plan, its manual of procedures, and budget. The recruitment of a cybersecurity TA is
   Comments:
                                      currently underway

    IN01234853
    ►C2-09. Systems that are compliant with DGU interoperability standards (cumulative) (Number, Custom, PBC)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                        6.00                         6.00                       10.00

    Date                              01-Jun-2020                 20-Jun-2022                  20-Jun-2022                31-Dec-2024

                                      6 information systems are interoperable (EDBM, INSTAT, DGI, MINJUS, SANTE and OPERATORS).
   Comments:

    IN01234855
    ►C2-10. People certified on DGU compliant digital training (Number, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                        549.00                       549.00                     5,000.00

    Date                              01-Jun-2020                 20-Jun-2022                  20-Jun-2022                31-Dec-2024
   Comments:                          2022 training schedule is available and further reach out to potential beneficiaries will be done by DGU


12/23/2022                                                                                                                   Page 5 of 8
           The World Bank                                                                                     Implementation Status & Results Report
           Digital Governance and Identification Management System Project- PRODIGY (P169413)




     IN01234857
     Of which are female (Number, Custom Breakdown)

                                      Baseline                   Actual (Previous)             Actual (Current)           End Target

     Value                            0.00                       164.00                        164.00                     2,500.00

     Date                             01-Jun-2020                20-Jun-2022                   20-Jun-2022                31-Dec-2024

    IN01234858
    ►C2-11. Services included in performance dashboard (Citizen engagement Indicator) (Number, Custom)

                                       Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                        0.00                         0.00                       15.00

    Date                               01-Jun-2020                 20-Jun-2022                  20-Jun-2022               31-Dec-2024

                                       The performance dashboard is under development
   Comments:



 Performance-Based Conditions




   IN01234859
    ►PBC 1 C1-01. Modernization of the ID-M system (Text, Intermediate Outcome, 7,500,000.00, 0.00%)


                                 Baseline                       Actual (Previous)             Actual (Current)              2024
                                                                                              There are current
                                                                                              discussions initiated by
                                                                UIN structure validated       government to review the
                                 No UIN nor system              by the steering               UIN structure and adopt a
    Value                                                                                                                   --
                                 architecture available         committee and will be         random structure. The
                                                                soon adopted by decree.       final decision will
                                                                                              formalized in the future
                                                                                              UIN decree.
    Date                         --                             20-Jun-2022                   15-Dec-2022                   --




   IN01234860
   ►PBC 2 C2-06. Establishment of institutional, legal and infrastructural foundations for digital transformation (Text, Process, 1,700,000.00,
   1.19%)


                                 Baseline                       Actual (Previous)             Actual (Current)              2024
                                 Institutional, legal and       The Government                The Government
                                 infrastructural foundations    adopted a decree              adopted a decree
    Value                                                                                                                   --
                                 for digital transformation     establishing the DGU’s        establishing the DGU’s
                                 are not in place.              institutional framework       institutional framework
    Date                         --                             20-Jun-2022                   20-Jun-2022                   --



12/23/2022                                                                                                                       Page 6 of 8
           The World Bank                                                                                       Implementation Status & Results Report
           Digital Governance and Identification Management System Project- PRODIGY (P169413)




   IN01234861
    ►PBC 3 C2-07. Implementation of institutional and policy framework for data privacy and protection (Text, Process, 1,700,000.00, 0.00%)


                                 Baseline                         Actual (Previous)             Actual (Current)                2024
                                                                  The draft of the decree       The draft of the decree
                                                                  operationalizing the CMIL     operationalizing the CMIL
    Value                        No effective data protection                                                                   --
                                                                  is available and pending      is available and pending
                                                                  adoption.                     adoption.
    Date                         --                               20-Jun-2022                   20-Jun-2022                     --




   IN01234862
    ►PBC 4 C2-08. Implementation of institutional and policy framework for civilian cybersecurity (Text, Process, 1,600,000.00, 0.00%)


                                 Baseline                         Actual (Previous)             Actual (Current)                2024
                                                                                                An early draft of the
                                                                  An early draft of the
                                                                                                strategy is available but
                                                                  strategy is available but
                                                                                                needs further refining. A
                                 No effective civilian            needs further refining.
                                                                                                substantial TA activity has
    Value                        cybersecurity policy and         The CERT                                                      --
                                                                                                been mobilized to support
                                 strategy                         operationalization is
                                                                                                the CIRT
                                                                  pending the recruitment
                                                                                                operationalization. Work is
                                                                  of a TA
                                                                                                underway.
    Date                         --                               20-Jun-2022                   15-Dec-2022                     --




   IN01234863
    ►PBC 5 C2-09. Systems that are compliant with DGU interoperability standards (cumulative) (Number, Output, 10,000,000.00, 6.99%)


                                 Baseline                         Actual (Previous)             Actual (Current)                2024

    Value                        0.00                             6.00                          6.00                            --

    Date                         --                               20-Jun-2022                   20-Jun-2022                     --



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status      Currency       Original      Revised      Cancelled       Disbursed     Undisbursed                   % Disbursed


 P169413       IDA-67800         Effective   USD                140.00      140.00            0.00        11.74               128.26                     8.4%

 P169413       TF-B4035          Effective   USD                  3.00        3.00            0.00          0.00                3.00                       0%


12/23/2022                                                                                                                           Page 7 of 8
           The World Bank                                                                           Implementation Status & Results Report
           Digital Governance and Identification Management System Project- PRODIGY (P169413)




 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date   Signing Date   Effectiveness Date   Orig. Closing Date      Rev. Closing Date

 P169413        IDA-67800         Effective   29-Sep-2020     12-Oct-2020    03-Jun-2021          31-Dec-2024             31-Dec-2024
 P169413        TF-B4035          Effective   29-Sep-2020     12-Oct-2020    12-Oct-2020          31-Dec-2024             31-Dec-2024


Cumulative Disbursements




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


 There are no related projects.




12/23/2022                                                                                                             Page 8 of 8