PROCUREMENT PLAN (Textual Part) Project information: Eastern Recovery Project (P145196) Project Implementation agency: FSRDC Date of the Procurement Plan: February 2018 Period covered by this Procurement Plan: January 2018 – December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Eastern Recovery Project PLAN General Information Country: Congo, Democratic Republic of 2022-06-29 Bank’s Approval Date of the Original Procurement Plan: 2022-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145196 GPN Date: Project Name: DRC Eastern Recovery Project Loan / Credit No: IDA / 66650 Social Funds DRC, Nord Kivu Antenna Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-FSRDC NK-294376-CW-R FQ / 12(NK-C1) Construction de 5 écoles primaires dans le s quartiers Biautu, Benengul Request for Quota 1. Support to Community Re Single Stage - One E En attente d 2023-02-0 e, lyakobo, lubahembe et But IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 650,000.00 0.00 2022-06-18 2022-08-13 silience nvelope 'exécution 9 anuka de la commune de Be PD) u, ville de Beni, Province du Nord-Kivu. en 5 lots distingue s: lots: 1EPKilewe,2EPKisolok ele,3Mukulya,4Matoya et Bu tanuka ZR-FSRDC NK-294388-CW-R FQ / 13(NK-C1) Construction de 5 école primaire dans les Request for Quota 1. Support to Community Re Single Stage - One E En attente d 2023-02-1 quartiers Mukulia, Mambang IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 650,000.00 0.00 2022-06-20 2022-08-15 silience nvelope 'exécution 1 u, Pasisi,Mabolio et Residenti PD) els de la commune de BUNG ULU, ville de Beni, Province d u Nord-Kivu. En 5 lots disting ues ZR-FSRDC NK-294509-CW-R FQ / 14(NK-C1) Construction de 5 écoles primaire dans les Request for Quota quartiers cité Belge, Kanzulin 1. Support to Community Re Single Stage - One E En attente d 2023-02-1 IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 650,000.00 0.00 2022-06-20 2022-08-15 zuli,Malepe,Rwangoma et Ma silience nvelope 'exécution 1 PD) tembo des communes de Bu ngulu, Beu et Rwenzori dans la ville de Beni, Province du Nord-Kivu. En 5 lots distingue s: ZR-FSRDC NK-294515-CW-R FQ / 15(NK-C1) Construction de 5 écoles primaire dans les Request for Quota quartiers Sayo, Mabakanga, 1. Support to Community Re Single Stage - One E En attente d 2023-02-1 IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 650,000.00 0.00 2022-06-20 2022-08-15 Kasabinyole, Paida et Boiken silience nvelope 'exécution 1 PD) e de la commune de RWENZ ORI dans la ville de Beni, Pro vince du Nord Kivu. En 5 lots distingues : ZR-FSRDC NK-294521-CW-R FQ / 16 (NK-C1) Construction Request for Quota de 3 écoles primaires dans l 1. Support to Community Re Single Stage - One E En attente d 2023-02-1 IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 390,000.00 0.00 2022-06-20 2022-08-15 es quartiers Masiani, Ngongol silience nvelope 'exécution 1 PD) io et Butsili dans la commune de Mulekera dans la ville de Beni, Province du Nord-Kivu ZR-FSRDC NK-294532-CW-R FQ / 17(NK-C1) Construction des écoles primaires dans les Request for Quota 1. Support to Community Re Single Stage - One E En attente d 2023-02-1 quartiers Kalinda, Matongé et IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 390,000.00 0.00 2022-06-20 2022-08-15 silience nvelope 'exécution 1 Ngadi dans les communes de PD) Mulekera et Rwenzori dans la ville de Beni, Province du Nor d-Kivu. ZR-FSRDC NK-294536-CW-R FQ / 18 (NK-C1) Construction des centres de Santé dans le Request for Quota s quartiers Kasanga tuha et 1. Support to Community Re Single Stage - One E En attente d 2023-02-1 IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 260,000.00 0.00 2022-06-20 2022-08-15 Nzuma dans la commune de silience nvelope 'exécution 1 PD) mulekera dans la ville de Ben i, Province du Nord-Kivu. En 2 lots distingues: lot 1 CS ND INDI et lot 2 CS Divine ZR-FSRDC NK-294543-CW-R FQ / 19 (NK-C1) Forage et ad Request for Quota duction d'eau dans les quarti 1. Support to Community Re Single Stage - One E En attente d 2023-02-1 IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 260,000.00 0.00 2022-06-20 2022-08-15 ers Tamende et Bunzi dans l silience nvelope 'exécution 1 PD) a commune de Mulekera, vill e de Beni ,province du Nord- Kivu. en 2 lots distingues: ZR-FSRDC NK-294567-CW-R FQ / 20(NK-C1) Construction des 10 Bureaux des CLD des Request for Quota quartiers les volcans,Himbi K 1. Support to Community Re Single Stage - One E En attente d 2023-02-2 IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 100,000.00 0.00 2022-07-04 2022-08-29 yeshero, lac-vert, Mapendo, silience nvelope 'exécution 5 PD) Murara, Mikeno, Katindo, Buj ovo et majengo dans la ville de Goma, Province du Nord-k ivu .(en raison de 10 000 US D par CLD). ZR-FSRDC NK-294570-CW-R FQ / 21(NK-C1) Construction des 10 Bureaux des CLD des quartiers Katoyi,Ndosho,Kah Request for Quota 1. Support to Community Re Single Stage - One E En attente d 2023-02-2 embe,Mabanga-Sud, Mabang IDA / 66650 A posteriori Demande de prix Limited tions (Non Bank-S 100,000.00 0.00 2022-07-04 2022-08-29 silience nvelope 'exécution 5 a-Nord,Kasika, Mungunga et PD) Virunga et les groupements des Munigi et Kiba dans la vil le de Goma, Province du Nor d-kivu .(en raison de 10 000 USD par CLD). GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 ZR-FSRDC NK-284228-GO-R FQ / 14 (NK-C2) Acquisition d es outillages (petits matériels ) dans le cadre de la mise en 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 300,000.00 0.00 2022-06-01 2022-07-20 2022-08-03 œuvre des chantiers dans la ent Generation nvelope exécution ville de Beni (30 chantiers), r épartit en quatre lots. en 4 lo ts. Lot 1C/BEU, lot 2 C/Rwenz orie, lot 3Mulekera et lot 4 B ungulu ZR-FSRDC NK-284236-GO-R FQ / 15(NK-C2) Acquisition de s kits médicaux d’urgence da 2. Livelihoods and Employm Single Stage - One E En attente d' ns le cadre de la mise en œu IDA / 66650 A posteriori Demande de prix Limited 30,000.00 0.00 2022-06-04 2022-07-23 2022-08-06 ent Generation nvelope exécution vre de chantiers de travaux à haute intensité de la main d’ œuvre à Beni dans la provinc e du Nord Kivu (30 chantiers ZR-FSRDC NK-284271-GO-R FQ / 16 (NK-C2) Acquisition d es fournitures et kits de recru tement des bénéficiaires da 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 30,000.00 0.00 2022-06-02 2022-07-21 2022-08-04 ns le cadre de la mise en œu ent Generation nvelope exécution vre des chantiers de travaux à haute intensité de la main d’œuvre à Beni dans la provi nce du Nord Kivu (30 chantie rs) ZR-FSRDC NK-284279-GO-R FQ / 17(NK-C2) Acquisition de 60 panneaux métalliques po ur le mécanisme de gestion d 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 15,000.00 0.00 2022-06-04 2022-07-23 2022-08-06 es plaintes dans le cadre de l ent Generation nvelope exécution a mise en œuvre de 30 chant iers de travaux à haute inten sité de la main d’œuvre dans les 30 quartiers de la Ville de Beni ZR-FSRDC NK-284281-GO-R FQ / 19 (NK-C2) Acquisition d e 630 panneaux de signalisat 2. Livelihoods and Employm Single Stage - One E En attente d' ion des chantiers dans le cad IDA / 66650 A posteriori Demande de prix Limited 31,500.00 0.00 2022-06-04 2022-07-23 2022-08-06 ent Generation nvelope exécution re de la mise en œuvre de ch antiers de travaux à haute in tensité de la main d’œuvre d ans la Ville de Beni ZR-FSRDC NK-284284-GO-R FQ / 20 (NK-C2) Acquisition d es fournitures des bureaux p our les bureaux des chantier 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 21,000.00 0.00 2022-06-04 2022-07-23 2022-08-06 s (installation des chantiers) ent Generation nvelope exécution dans le cadre de la mise en œuvre de chantier de travau x à haute intensité de la mai n d’œuvre dans la Ville de Be ni (30 chantiers) ZR-FSRDC NK-284286-GO-R FQ / 21 (NK-C2) Location des salles et Sélection des servic es traiteurs pour la formation 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 34,650.00 0.00 2022-06-04 2022-07-23 2022-08-06 des CC (36), CE (330), PFES ( ent Generation nvelope exécution 40) et AST (40) dans le cadre de la mise en œuvre de chan tiers de THIMO dans les 30 q uartiers de la ville de Beni ZR-FSRDC NK-284451-GO-R FQ / 23 (NK-C2) Fourniture d es Latérites/Limonites pour le 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 210,000.00 0.00 2022-09-01 2022-10-20 2022-11-03 rechargement des axes dans ent Generation nvelope exécution le cadre des chantiers THIMO à Beni. Répartit en quatre lot s ZR-FSRDC NK-284461-GO-R FQ / 24 (NK-C2) Fourniture d e pelouse, de bambous, fleur s, plantes et vetivers pour l’ 2. Livelihoods and Employm Single Stage - One E En attente d' embellissement et protection IDA / 66650 A posteriori Demande de prix Limited 90,000.00 0.00 2022-09-06 2022-10-25 2022-11-08 ent Generation nvelope exécution des accotements dans le cad re des chantiers THIMO de B eni.4 lots: Lot 1 : C/BEU (Q R wangoma... lot2:CRwenzorie ,Lot3:C/Mulekera Lot4:C/Bun gulu, ZR-FSRDC NK-285068-GO-R FQ / 64 (NK-C2) Acquisition d es panneaux de signalisation 2. Livelihoods and Employm Single Stage - One E En attente d' des chantiers dans le cadre d IDA / 66650 A posteriori Demande de prix Limited 20,034.00 0.00 2022-06-22 2022-08-10 2022-08-24 ent Generation nvelope exécution e la mise en œuvre de chanti ers de travaux a haute intens ité de la main d’œuvre à Go ma dans la province du Nord Kivu ZR-FSRDC NK-285069-GO-R FQ / 65 (NK-C2) Acquisition d es fournitures des bureaux p our les bureaux des chantier 2. Livelihoods and Employm Single Stage - One E En attente d' s ( installation des chantiers) IDA / 66650 A posteriori Demande de prix Limited 8,000.00 0.00 2022-07-06 2022-08-24 2022-09-07 ent Generation nvelope exécution dans le cadre de la mise en œuvre de chantier de travau x à haute intensité de la mai n d’œuvre à Goma dans la pr ovince du Nord Kivu ZR-FSRDC NK-294014-GO-R FQ / 5(NK-C1) Acquisition des équipements scolaires des 5 écoles primaires dans 5 quar 1. Support to Community Re Single Stage - One E En attente d' tiers de la commune de Beu, IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2022-07-27 2022-09-14 2022-10-05 silience nvelope exécution ville de Beni de la Province d u Nord-Kivu. En 5 lots disting ues : - Lt 1 ES EP Kilewe, -Lt 2 : ÉS EPKisolokele -Lot 3 : ES EP Lyakobo, ZR-FSRDC NK-294019-GO-R FQ / 6 (NK-C1) Acquisition de s équipements scolaires des 1. Support to Community Re Single Stage - One E En attente d' 5 écoles primaires dans 5 qu IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2022-06-20 2022-08-15 2022-09-05 silience nvelope exécution artiers de la commune de Bul ungu, ville de Beni de la Prov ince du Nord Kivu. En 5 lots d istingues : ZR-FSRDC NK-294020-GO-R FQ / 7 (NK-C1) Acquisition de s équipements scolaires des 1. Support to Community Re Single Stage - One E En attente d' 5 écoles primaires dans 5 qu IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2022-06-20 2022-08-15 2022-09-05 silience nvelope exécution artiers de la commune de Rw enzori, ville de Beni de la Pro vince du Nord Kivu. En 5 lots distingues : Page 2 ZR-FSRDC NK-294022-GO-R FQ / 8(NK-C1) Acquisition des équipements scolaires des 5 1. Support to Community Re Single Stage - One E En attente d' écoles primaires dans 5 quar IDA / 66650 A posteriori Demande de prix Limited 75,000.00 0.00 2022-06-20 2022-08-15 2022-09-05 silience nvelope exécution tiers des communes de Bung ulu, Beu et Rwenzori dans la ville de Beni de la Province d u Nord Kivu. En 5 lots disting ues : ZR-FSRDC NK-294023-GO-R FQ / 9 (NK-C1) Acquisition de s équipements scolaires des 1. Support to Community Re Single Stage - One E En attente d' 3 écoles primaires dans 3 qu IDA / 66650 A posteriori Demande de prix Limited 45,000.00 0.00 2022-06-20 2022-08-15 2022-09-05 silience nvelope exécution artiers de communes de Mul ekera, dans la ville de Beni d e la Province du Nord Kivu. E n 3 lots distingues ZR-FSRDC NK-294109-GO-R FQ / 2 (NK-C2) Acquisition de 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 10,000.00 0.00 2022-06-04 2022-07-23 2022-08-06 s smartphone et accessoire p ent Generation nvelope exécution our les 30 AST de TMI. ZR-FSRDC NK-294358-GO-R FQ / 10 (NK-C1)Acquisition de s équipements scolaires des 3 écoles primaires dans 3 qu 1. Support to Community Re Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 45,000.00 0.00 2022-06-04 2022-07-30 2022-08-20 artiers des communes de Mul silience nvelope exécution ekera et RWENZORI , dans la ville de Beni de la P rovince du Nord Kivu. En 3 lo ts distingues ZR-FSRDC NK-294363-GO-R FQ / 11(NK-C1) Acquisition d 1. Support to Community Re Single Stage - One E En attente d' es équipements des centres IDA / 66650 A posteriori Demande de prix Limited 50,000.00 0.00 2022-07-05 2022-08-30 2022-09-20 silience nvelope exécution des santés dans 2 quartiers d ans la commune de Mulekera . ZR-FSRDC NK-294598-GO-R FQ / 11 (NK-C4) Acquisition d Single Stage - One E En attente d' IDA / 66650 4. Project Management A posteriori Demande de prix Limited 20,000.00 0.00 2022-07-06 2022-08-24 2022-09-07 es matériels roulants 2 roues nvelope exécution (4 motos de terrain dont 2 po ur l'équipe de Zone) ZR-FSRDC NK-294613-GO-R FQ / 23(NK-C4) Acquisition de Single Stage - One E En attente d' IDA / 66650 4. Project Management A posteriori Demande de prix Limited 22,800.00 0.00 2022-06-22 2022-08-10 2022-08-24 s équipements et mobiliers d nvelope exécution u Bureau pour l'antenne du N ord-Kivu. ZR-FSRDC NK-294642-GO-R FQ / 9 (NK-C4) Acquisition de Single Stage - One E En attente d' s groupes électrogènes pour IDA / 66650 4. Project Management A posteriori Demande de prix Limited 16,000.00 0.00 2022-06-27 2022-08-15 2022-08-29 nvelope exécution les Bureaux de Zone de Beni et Butembo dans la Province du Nord-Kivu. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC NK-294125-NC-RF Q / 3 (NK-C2) Sélection des p restataires de services financ iers pour faciliter les TMI en f 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 270,000.00 0.00 2022-06-25 2022-08-20 2023-02-16 aveurs de 30000 bénéficiaire ent Generation nvelope exécution s. (les prestataires de service s financiers assurent la distri bution d'environ 9000000$ a ux 30000 bénéficiaires), ZR-FSRDC NK-294133-NC-DI R / 4 (NK-C2) Contractualisati on avec FBN BANK/Agence d 2. Livelihoods and Employm Passation de marc En attente d' e la ville de Goma pour facilit IDA / 66650 A posteriori Direct 37,600.00 0.00 2022-05-28 2022-06-02 2022-07-07 2023-01-03 ent Generation hé de gré à gré exécution er le payement des Bénéficia ires et les encadreurs THIMO dans le cadre de la mise en d es THIMO dans la ville de Go ma. ZR-FSRDC NK-294782-NC-RF Q / 25 (NK-C2) Sélection d'un prestataire de services financ iers pour faciliter la paye de 2. Livelihoods and Employm Single Stage - One E En attente d' IDA / 66650 A posteriori Demande de prix Limited 85,000.00 0.00 2022-07-03 2022-08-28 2023-02-24 7500 bénéficiaires THIMO, 30 ent Generation nvelope exécution 0 chef d'équipe, 30 chef des chantiers,30 PFES et 30 AST dans la ville de Beni, Provinc e du Nord-Kivu. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC NK-294780-CS-CQ S / Recrutement de 09 ONGs Sélection fondée s Chargées d’administrer les m 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori ur les qualification Open - National 135,000.00 0.00 2022-06-28 2022-07-19 2022-09-01 2022-10-01 2022-11-05 2023-05-04 esures d’accompagnement ( ent Generation ution s des consultants MEDAC) aux 4 500 bénéficiai res THIMO dans la ville de Go ma INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC NK-283491-CS-IN DV / 1 (NK-C2) Recrutement des 7 consultants Individuels 2. Livelihoods and Employm En attente d'exéc IDA / 66650 A posteriori Individuel Limited 63,000.00 0.00 2022-05-28 2022-06-11 2022-07-02 2022-07-30 2023-01-26 pour la mission de supervisio ent Generation ution n des chantiers THIMO dans l a ville de Beni au Nord Kivu Page 3 ZR-FSRDC NK-283499-CS-IN DV / 2 (NK-C2) Recrutement 2. Livelihoods and Employm En attente d'exéc des 30 consultants Individuel IDA / 66650 A posteriori Individuel Limited 72,000.00 0.00 2022-05-28 2022-06-11 2022-07-02 2022-07-30 2023-01-26 ent Generation ution s pour la mission de chef de chantier des THIMO dans la v ille de Beni au Nord Kivu ZR-FSRDC NK-284128-CS-IN DV / 4 (NK-C2) Recrutement 2. Livelihoods and Employm En attente d'exéc des 30 consultants Individuel IDA / 66650 A posteriori Individuel Limited 54,000.00 0.00 2022-05-28 2022-06-11 2022-07-02 2022-07-30 2023-01-26 ent Generation ution s pour la mission de PFE des chantiers THIMO à Beni au N ord Kivu ZR-FSRDC NK-284137-CS-IN DV / 5 (NK-C4) Recrutement des 30 consultants Individuel En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 54,000.00 0.00 2022-05-28 2022-06-11 2022-07-02 2022-07-30 2023-01-26 s pour la mission des Agents ution de suivi de terrain (AST) des chantiers THIMO à Beni au N ord Kivu ZR-FSRDC NK-284152-CS-IN DV / 7 (NK-C4) Recrutement En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 2022-05-28 2022-06-11 2022-07-02 2022-07-30 2023-01-26 d’un consultant superviseur ution des activités des AST à Beni ZR-FSRDC NK-284177-CS-IN DV / 8 (NK-C4) Recrutement En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 2022-05-28 2022-06-11 2022-07-02 2022-07-30 2023-01-26 un consultant Assistant Admi ution nistratif de l’équipe de zone des activités à Beni ZR-FSRDC NK-284191-CS-IN DV / 10 (NK-C4) Recrutement En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Limited 12,000.00 0.00 2022-05-28 2022-06-11 2022-07-02 2022-07-30 2023-01-26 d’un consultant point focal d ution e l’équipe de zone des activit és à Beni ZR-FSRDC NK-293186-CS-IN DV / 1(NK-C1) Recrutement d e 30 consultants Individuels DPO pour le contrôle et surve 1. Support to Community Re En attente d'exéc IDA / 66650 A posteriori Individuel Limited 213,750.00 0.00 2022-06-15 2022-06-22 2022-07-06 2022-07-27 2023-01-23 illance des 30 IDB travaux d’i silience ution nfrastructures communautair es dans la ville de Beni, dans la Province du Nord Kivu à rai son d'un DPO pour 1 IDB ZR-FSRDC NK-294003-CS-IN DV / 2(NK-C1)Recrutement d e 3 consultants Individuels su perviseur pour le contrôle et 1. Support to Community Re En attente d'exéc surveillance des 30 travaux IDA / 66650 A posteriori Individuel Limited 27,000.00 0.00 2022-06-06 2022-06-13 2022-06-27 2022-07-18 2023-01-14 silience ution d'infrastructures communaut aires dans la ville de Beni, da ns la Province du Nord-Kivu. En raison d'un superviseur p our 10 DPO ainsi que 10 IDB ZR-FSRDC NK-294004-CS-IN DV / 3(NK-C1) Recrutement d es 30 consultants Individuels 1. Support to Community Re En attente d'exéc pour la mission de PFES des IDA / 66650 A posteriori Individuel Limited 55,800.00 0.00 2022-06-08 2022-06-15 2022-06-29 2022-07-20 2023-01-16 silience ution chantiers IDB dans la ville de Beni, dans la Province du Nor d-Kivu. En raison d'un PFES par chantier (communauté) ZR-FSRDC NK-294011-CS-IN DV / 3 (NK-C2)Recrutement d es 300 consultants Individuel 2. Livelihoods and Employm En attente d'exéc s pour une mission de Chef d IDA / 66650 A priori Individuel Limited 360,000.00 0.00 2022-05-28 2022-06-04 2022-06-18 2022-07-09 2023-01-05 ent Generation ution 'équipe des chantiers THIMO dans la ville de Beni au Nord- Kivu. En raison de 10 chefs d' équipes par chantier (Quartie r) Page 4