The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) SOUTH ASIA | Afghanistan | Social Sustainability and Inclusion Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 8 | ARCHIVED on 21-Oct-2022 | ISR53488 | Implementing Agencies: Ministry of Economy, Ministry of Finance, Aid Management Directorate Key Dates Key Project Dates Bank Approval Date: 19-Dec-2018 Effectiveness Date: 06-Feb-2019 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to strengthen the enabling environment for economic opportunities in cities where there is a high influx of displaced people. This will be pursued by increasing the returnees' access to civil documents, providing short-term employment opportunities, improving market enabling infrastructure, and supporting investor friendly regulatory reforms. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Regional and National Integration of Displaced Persons:(Cost $4.50 M) Short Term Employment Opportunities, Reforms, and Market Enabling Infrastructure under IDLG:(Cost $121.80 M) Prioritized Urban Investments in Four Provincial Capital Cities:(Cost $18.75 M) Market Enabling Infrastructure and Reforms for Kabul Municipality:(Cost $40.00 M) Red Carpet and Program Coordination:(Cost $8.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating High High Implementation Status and Key Decisions The Afghanistan Reconstruction Trust Fund (ARTF) in the project was canceled based on the consideration that the project cannot be effectively implemented under the current extraordinary situation in Afghanistan. Undisbursed IDA grants under this project will remain suspended until a decision is made by the World Bank. 10/21/2022 Page 1 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic High High High Sector Strategies and Policies High High High Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary High High High Environment and Social Substantial Substantial Substantial Stakeholders Substantial High High Other Substantial -- Substantial Overall High High High Results PDO Indicators by Objectives / Outcomes ACCESS TO CIVIL DOCUMENTS IN01204341 ►Percentage of Afghan Passport Applications in Pakistan Processed (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 During the project implementation period, number of Afghan Passport Applications in Pakistan processed, divided by the number of Afghan Passport Application received in Pakistan. Comments: The Afghan missions in Pakistan has not been able to process machine readable passports yet, since required equipment has not been procured. IN01204344 Percentage of Afghan Passport Applications in Pakistan Processed (for female applicants) (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 10/21/2022 Page 2 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) SHORT-TERM EMPLOYMENT OPPORTUNITIES IN01204330 ►Number of vulnerable households in high IDP/returnee cities provided with short term employment support (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 6,932.00 6,932.00 80,000.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 277,287 labor days were generated for 6,932 households (average 40 labor days per household). Comments: IN01204343 Of which IDP/Returnee households (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10,000.00 Date 01-Nov-2018 15-Aug-2021 15-Aug-2021 31-Dec-2023 RED CARPET REFORMS AND MARKET FACILITATING INVESTMENTS IN01204329 ►Number of market enabling infrastructure built or upgraded (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 1,115.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of infrastructure built, upgraded, or maintained through MCCG, Gozar and Business Gozar Comments: Grants, and Priority Investment Projects. IN01204342 Of which at the community level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 900.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204345 Of which at the Gozar level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 180.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204346 Of which at the Business Gozar level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target 10/21/2022 Page 3 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 0.00 0.00 30.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204347 Of which at the city level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 5.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204348 ►Number of processing steps reduced for specific Doing Business reform indicators in four cities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 13.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Comments: Number of processing steps reduced for obtaining construction permits for commercial properties IN01204349 Of which in the three cities of Jalalabad, Herat, and Kandahar (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204350 Of which in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Intermediate Results Indicators by Components Support for Afghan Refugees in Pakistan IN01204351 ►Number of passports issued to Afghan refugees in Pakistan during the project implementation period (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,500,000.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of machine-readable passports issued for the applications received at the Afghan Embassy and Comments: consulates in Pakistan. 10/21/2022 Page 4 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) IN01204357 of which women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 600,000.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204359 ►Percentage of passport applications processed within ten (10) working days (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 The number of machine-readable passports issued within 10 working days of application received, divided by the number of complete passport applications received during the reporting period at the Afghan Comments: Embassy and consulates in Pakistan. The baseline is zero, as machine-readable passports have not been issued in Pakistan, and there is no monitoring system in place. IN01204363 of which women (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204367 ►Number of people reached through communications activities implemented through the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 750,000.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Sum of the numbers of (a) followers of the social media accounts created by the project; (b) help/support Comments: cases logged by helplines and information centers; and (c) people reached by awareness campaigns. IN01204370 of which women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 300,000.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Short-Term Employment Opportunities IN01204353 ►% of CDC members who are women (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target 10/21/2022 Page 5 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 50.00 50.00 40.00 Date 01-Nov-2018 15-Aug-2021 15-Aug-2021 31-Dec-2023 3,484 of 6,991 CDC members elected for 309 CDCs to date are women. Comments: IN01204355 ►Number of COVID-19 economic recovery related work days created in Kabul (Days, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 277,287.00 277,287.00 850,000.00 Date 01-Sep-2020 15-Aug-2021 15-Aug-2021 30-Jun-2021 Market Facilitating Investments IN01204354 ►Number of municipalities where IDLG holds EZ-Kar coordination meetings with government authorities, Gozar assemblies and Business Gozar assemblies (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3.00 3.00 11.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of cities that have held meetings with EZ-Kar stakeholders in the cities where Gozar and Comments: Business Gozar Grants are implemented. IN01204358 ►Number of Gozars (hh and business) that have prepared their Gozar economic development plans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3.00 3.00 276.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Comments: Number of approved Gozar Economic Development Plans IN01204361 ►Businesses in urban areas provided with access to “Improved Water Sources” under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of businesses that are provided with access to improved water sources through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project Comments: takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN01204362 Of which through Priority Projects in Kabul (Number, Custom Breakdown) 10/21/2022 Page 6 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204368 Of which through Priority Projects in the four cities of Herat, Kandahar, Khost, and Jalalabad (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204371 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204373 ►Businesses in urban areas provided with access to "Improved Sanitation" under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of businesses that are provided with access to improved sanitation through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes Comments: on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN01204375 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204377 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204379 ►Businesses in urban areas provided with access to all-season roads within a 500-meter range under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 10/21/2022 Page 7 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of businesses that are provided with access to all-season roads within a 500-meter range through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, Comments: since this Project takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN01204380 KM of roads constructed (Kilometers, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.62 2.62 0.00 IN01204381 KM of roads rehabilitated (Kilometers, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 IN01204382 ►Businesses in urban areas provided with access to regular solid waste collection at the markets under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of businesses that are provided with access to regular solid waste collection through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Comments: Project takes on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN01204383 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204384 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204385 ►Businesses in urban areas provided with access to electricity under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 10/21/2022 Page 8 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of businesses that are provided with access to electricity through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes Comments: on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN01204386 Generation Capacity of Renewable Energy (other than hydropower) rehabilitated under the project (Megawatt, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 IN01204387 Generation Capacity of Renewable Energy (other than hydropower) constructed under the project (Megawatt, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 IN01204388 ►Businesses with improved access to ICT services under the project (number of business subscribers) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of businesses that are provided with access to ICT services through Priority Projects and Gozar/Business Gozar Grants. Target value for this indicator is currently set at ‘0’, since this Project takes Comments: on a demand-driven approach and the types and numbers of subprojects to be implemented under the Project cannot/should not be predetermined, as it will not be accurate. The target value may be set by the mid-term review by when there will be more information from implementation. IN01204389 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204390 Of which through Priority Projects in the four cities of Herat, Kandahar, Khost, and Jalalabad (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204391 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 10/21/2022 Page 9 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204392 ►Number of market enabling investments under the project that address the gender gap in access to urban economic centers/ markets (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 35.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of market enabling investments under the project that close gender gaps in women’s access to markets, which can be in the form of (i) specific subprojects exclusively for women, e.g. restoration of Comments: women's markets, rehabilitation of toilet facilities for markets; or (ii) subprojects that are inclusive for (and do not exclude) women, such as extension and upgrading of pedestrian walkways, bus stops and street lighting that link to markets. IN01204393 Of which through Priority Projects in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204394 Of which through Priority Projects in the four cities of Herat, Jalalabad, Kandahar, and Khost (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204395 Of which through Gozar and Business Gozar Grants (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204396 ►Number of businesses receiving cash grants (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20,000.00 Date 01-Sep-2020 27-Jun-2021 27-Jun-2021 30-Jun-2021 IN01204397 Of which women owned (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 01-Sep-2020 27-Jun-2021 27-Jun-2021 30-Jun-2021 10/21/2022 Page 10 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Red Carpet Reforms IN01204352 ►Number of reform implementation plans prepared (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 5.00 5.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Comments: Number of construction permit reform implementation plans prepared IN01204356 Of which at national level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 1.00 1.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204360 Of which in the three cities of Herat, Jalalabad, and Kandahar (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3.00 3.00 3.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204364 Of which in Kabul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 1.00 1.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204366 ►Reduction in time taken to obtain a construction permit for commercial properties in Jalalabad, Kandahar, Herat, and Kabul (Days, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 77.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Comments: Number of average days reduced for obtaining construction permits for commercial properties IN01204372 Of which in Jalalabad (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 14.00 10/21/2022 Page 11 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204374 Of which in Kandahar (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 6.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204376 Of which in Herat (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 18.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 IN01204378 Of which in Kabul (Days, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 39.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Project Management IN01204365 ►Number of access to information inquiries responded to within agreed service standards (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 5.00 50.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 Number of individuals and organizations (including media and NGOs) that received project related Comments: information in accordance with agreed service standards. IN01204369 ►Percentage of complaints / grievances resolved following agreed EZ-Kar service standards (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 80.00 Date 01-Nov-2018 27-Jun-2021 27-Jun-2021 31-Dec-2023 The number of project related complaints or grievances resolved in accordance with EZ-Kar service Comments: standards, divided by the number of project related complaints or grievances received. Performance-Based Conditions 10/21/2022 Page 12 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P166127 IDA-D4160 Effective USD 150.00 150.00 0.00 22.02 124.29 15% P166127 TF-A9092 Effective USD 50.00 7.40 42.60 6.21 1.20 84% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P166127 IDA-D4160 Effective 19-Dec-2018 06-Feb-2019 06-Feb-2019 31-Dec-2023 31-Dec-2023 P166127 TF-A9092 Effective 19-Dec-2018 06-Feb-2019 06-Feb-2019 31-Dec-2023 31-Dec-2023 Cumulative Disbursements Restructuring History Level 2 Approved on 09-Oct-2020 Related Project(s) 10/21/2022 Page 13 of 14 The World Bank Implementation Status & Results Report Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project (P166127) There are no related projects. 10/21/2022 Page 14 of 14