PROCUREMENT PLAN (Textual Part) Project information: West Bank and Gaza, PFM Improvement, P-162850 Project Implementation agency: MINISTRY OF FINANCE AND PLANNING Date of the Procurement Plan: 10 July 2018 Period covered by this Procurement Plan: First 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” PROCUREMENT West Bank and Gaza : Public Financial Management Improvement Project PLAN General Information Country: West Bank and Gaza Bank’s Approval Date of the Original Procurement Plan: 2018-07-11 2022-01-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162850 GPN Date: 2018-07-17 Project Name: Public Financial Management Improvement Project Loan / Credit No: TF / A6949, / P Executing Agency(ies): alestinian Authority-Ministry of Finance and Planning WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4: Project GZ-MOFP-114614-GO-RFQ / Request for Single Stage - One TF / A6949 Implementation Support and Post Limited 78,364.00 Completed 2019-10-29 2019-11-25 2019-12-24 2020-01-09 2020-06-21 2020-02-13 PMU and MOFP Equipment Quotations Envelope Management Costs GZ-MOFP-177544-GO-RFQ / Component 2: Improving Request for Single Stage - One Equipment for the benefit of TF / A6949 Financial Accountability of Post Limited 59,658.00 Completed 2020-06-12 2020-06-15 2020-08-07 2020-08-09 2020-10-06 2020-09-22 Quotations Envelope SAACB. the PFM System Component 1: Improving GZ-MOFP-198841-GO-RFQ / Request for Single Stage - One TF / A6949 Budget Expenditure Post Limited 35,484.00 Completed 2020-11-13 2020-11-08 2021-01-08 2020-12-20 2021-03-09 2021-03-11 Office and IT Equipment Quotations Envelope Management and Control GZ-MOFP-213643-GO-RFQ / Component 2: Improving Request for Single Stage - One Office equipment/software for TF / A6949 Financial Accountability of Post Limited 54,650.00 Signed 2021-04-04 2021-04-06 2021-05-30 2021-07-01 2021-08-08 Quotations Envelope the benefit of SAACB the PFM System GZ-MOFP-248428-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One IT equipment for the benefit TF / A6949 Budget Expenditure Post Limited 0.00 Implementati 2021-09-05 2021-10-31 2021-12-30 Quotations Envelope of the MOF Management and Control on GZ-MOFP-273158-GO-RFQ / Component 1: Improving Pending IT Equipment for the benefit Request for Single Stage - One TF / A6949 Budget Expenditure Post Limited 0.00 Implementati 2022-01-24 2022-03-21 2022-05-20 of the Public Debt Quotations Envelope Management and Control on Management NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MOFP-88245-CS-QCBS / Component 4: Project Quality And Cost- Hiring an external auditor to TF / A6949 Implementation Support and Post Open - National 6,612.00 Completed 2018-11-26 2018-11-26 2018-11-26 2018-11-26 2018-11-26 2019-01-06 2019-01-06 2019-01-16 2019-01-06 2019-01-24 2019-01-06 2019-02-21 2019-04-15 2021-06-15 2021-06-30 Based Selection audit the PFMI project Management Costs GZ-MOFP-114617-CS-QCBS Component 1: Improving Consultant / Modernize the Functions of TF / A6949 Budget Expenditure Post Qualification Limited 88,879.20 Completed 2019-08-08 2019-08-21 2019-08-22 2019-09-08 2019-09-21 2019-10-16 2019-10-26 2019-12-26 2020-04-23 2021-03-09 Financial Controller Management and Control Selection GZ-MOFP-158890-CS-QCBS / Consultantancy firm to work Component 1: Improving on the Israeli deduction from Quality And Cost- TF / A6949 Budget Expenditure Post Open - National 0.00 Canceled 2020-02-16 2020-02-16 2020-03-08 2020-04-21 2020-05-19 2020-06-18 2020-07-23 2020-08-27 2021-08-27 Clearance Revenues Based Selection Management and Control transferred to the Palestinian Government. Component 1: Improving GZ-MOFP-215235-CS-QCBS Quality And Cost- TF / A6949 Budget Expenditure Post Open - National 0.00 Canceled 2021-02-28 2021-04-01 2021-03-21 2021-05-04 2021-06-01 2021-07-01 2021-08-05 2021-09-09 2022-09-09 / Recruiting an IT Audit Firm Based Selection Management and Control GZ-MOFP-239377-CS-CQS / Component 1: Improving Consultant Advisory Support for the Audit Under TF / A6949 Budget Expenditure Post Qualification Limited 0.00 2021-06-20 2021-05-20 2021-07-04 2021-07-01 2021-08-03 2021-09-07 2022-03-06 of BISAN System (FMIS) at Implementation Management and Control Selection Ministry of Finance INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MOFP-68910-CS-INDV / Component 4: Project Individual PMU Financial Management TF / A6949 Implementation Support and Post Consultant Direct 33,600.00 Completed 2018-07-10 2018-07-12 2018-07-10 2018-06-07 2018-07-10 2018-06-10 2018-07-10 2018-07-01 2019-07-09 2019-06-30 Specialist Management Costs Selection Component 4: Project Individual GZ-MOFP-68920-CS-INDV / TF / A6949 Implementation Support and Post Consultant Open 4,000.00 Completed 2018-07-10 2018-07-12 2018-08-13 2018-09-17 2018-08-18 2018-12-20 2018-09-01 2019-02-03 2019-08-31 2020-02-02 PMU Manager Management Costs Selection Page 1 Component 4: Project Individual GZ-MOFP-68927-CS-INDV / TF / A6949 Implementation Support and Post Consultant Open 34,800.00 Completed 2018-07-10 2018-07-12 2018-08-13 2018-09-17 2018-08-18 2018-09-30 2018-09-01 2018-11-01 2019-08-31 2019-10-31 PMU Procurement Specialist Management Costs Selection GZ-MOFP-111771-CS-CDS / Component 2: Improving Individual Financial Expert to Reduce the TF / A6949 Financial Accountability of Post Consultant Direct 64,000.00 Completed 2019-04-29 2019-04-29 2019-04-29 2019-04-29 2019-04-29 2019-04-29 2019-05-01 2019-05-01 2019-12-31 2019-12-31 Backlog of Financial the PFM System Selection Statements of the PA GZ-MOFP-69928-CS-CDS / Component 1: Improving Business process analyst for TF / A6949 Budget Expenditure Post Direct Selection Direct 40,020.00 Completed 2018-07-17 2018-07-17 2018-07-22 2018-11-04 2018-08-10 2018-11-11 2018-12-10 2019-04-11 payroll system Management and Control GZ-MOFP-114611-CS-INDV Component 4: Project Individual / Financial Management TF / A6949 Implementation Support and Post Consultant Direct 35,280.00 Completed 2019-05-30 2019-05-23 2019-06-09 2019-05-30 2019-06-14 2019-05-30 2019-07-01 2019-07-01 2020-06-30 2020-06-30 Specialist Management Costs Selection GZ-MOFP-114615-CS-CDS / Component 1: Improving Introducing changes to Bisan Pending TF / A6949 Budget Expenditure Post Direct Selection Direct 0.00 2019-08-11 2019-08-21 2019-10-25 2020-04-22 system- Commitment Control Implementation Management and Control Module and training of users. GZ-MOFP-114612-CS-INDV / Accountant # 1 to support the Accountant General and Component 2: Improving Individual General Accounts Department TF / A6949 Financial Accountability of Post Consultant Open 10,800.00 Completed 2019-08-18 2019-08-25 2019-10-06 2019-11-03 2019-10-27 2019-11-10 2019-12-01 2019-12-03 2020-11-30 2021-01-04 (full-time) (first year) the PFM System Selection budgeted around $1,000 each per month. GZ-MOFP-126227-CS-INDV / Accountant # 2 to support the Accountant General and Component 2: Improving Individual General Accounts Department TF / A6949 Financial Accountability of Post Consultant Open 10,800.00 Completed 2019-08-18 2019-08-25 2019-10-06 2019-11-03 2019-10-27 2019-11-10 2019-12-01 2019-12-03 2020-11-30 2021-01-04 (full-time) (first year) the PFM System Selection budgeted around $1,000 each per month GZ-MOFP-126228-CS-INDV / Accountant # 3 to support the Accountant General and Component 2: Improving Individual General Accounts Department TF / A6949 Financial Accountability of Post Consultant Open 10,800.00 Completed 2019-08-18 2019-08-25 2019-10-06 2019-11-03 2019-10-27 2019-11-10 2019-12-01 2019-12-03 2020-11-30 2021-01-04 (full-time) (first year) the PFM System Selection budgeted around $1,000 each per month Component 4: Project Individual GZ-MOFP-141041-CS-INDV TF / A6949 Implementation Support and Post Consultant Direct 38,280.00 Completed 2019-10-17 2019-10-17 2019-10-17 2019-10-20 2019-10-17 2019-10-20 2019-11-01 2019-11-01 2020-10-31 2020-10-31 / PMU Procurement Specialist Management Costs Selection Component 1: Improving Individual GZ-MOFP-68932-CS-INDV / / Budget Expenditure Post Consultant Open 0.00 Canceled 2018-07-10 2018-07-12 2018-08-28 2018-09-18 2019-01-01 2019-12-31 PFM Advisor Management and Control Selection GZ-MOFP-139966-CS-CDS / IPSAS Expert (Mirabo Component 2: Improving Individual Shammas) for the adoption of TF / A6949 Financial Accountability of Post Consultant Direct 29,881.60 Completed 2019-11-25 2019-12-09 2019-12-05 2019-11-18 2019-12-14 2019-12-15 2020-01-06 2019-12-15 2021-01-04 2021-06-30 International Public Sector the PFM System Selection Accounting Standards GZ-MOFP-146530-CS-INDV Component 2: Improving Individual / Financial Expert to Reduce TF / A6949 Financial Accountability of Post Consultant Direct 48,000.00 Completed 2019-11-28 2019-12-09 2019-12-08 2019-12-10 2019-12-29 2019-12-10 2020-02-02 2020-01-01 2020-09-30 2020-08-31 the Backlog of Financial the PFM System Selection Statements of the PA. GZ-MOFP-149443-CS-INDV / Majed Ayyad "IT Expert for Component 1: Improving Individual the supervision and TF / A6949 Budget Expenditure Post Consultant Direct 48,000.00 Signed 2019-12-09 2020-03-12 2019-12-19 2020-06-09 2019-12-20 2020-06-09 2019-12-23 2020-06-29 2022-06-30 implementation of the Payroll Management and Control Selection System" GZ-MOFP-153081-CS-INDV Component 4: Project Individual / PMU Project Manager- TF / A6949 Implementation Support and Post Consultant Direct 50,400.00 Completed 2020-01-15 2020-01-16 2020-01-25 2020-01-02 2020-01-26 2020-01-02 2020-02-03 2020-02-03 2021-02-02 2021-02-02 Renewal Management Costs Selection Component 2: Improving Individual GZ-MOFP-153084-CS-INDV TF / A6949 Financial Accountability of Post Consultant Direct 19,200.00 Completed 2020-01-16 2020-02-16 2020-01-26 2020-03-09 2020-02-16 2020-03-09 2020-03-22 2020-04-01 2021-03-21 2021-03-31 / Auditor # 1 for SAACB the PFM System Selection Component 2: Improving Individual GZ-MOFP-153089-CS-INDV TF / A6949 Financial Accountability of Post Consultant Limited 17,400.00 Completed 2020-01-16 2020-02-16 2020-01-21 2020-03-09 2020-02-11 2020-03-09 2020-03-17 2020-04-01 2021-03-16 2021-03-31 / Auditor # 2 for SAACB the PFM System Selection Component 2: Improving Individual GZ-MOFP-153091-CS-INDV TF / A6949 Financial Accountability of Post Consultant Limited 17,400.00 Completed 2020-01-16 2020-02-16 2020-01-21 2020-03-09 2020-02-11 2020-03-17 2020-04-01 2021-03-16 2021-03-31 / Auditor # 3 for SAACB the PFM System Selection GZ-MOFP-173517-CS-INDV Component 4: Project Individual / Financial Management TF / A6949 Implementation Support and Post Consultant Direct 35,280.00 Signed 2020-05-29 2020-05-17 2020-06-08 2020-05-19 2020-06-13 2020-05-19 2020-06-30 2020-07-01 2021-06-30 Specialist Management Costs Selection Component 2: Improving Individual GZ-MOFP-182809-CS-INDV TF / A6949 Financial Accountability of Post Consultant Direct 48,000.00 Completed 2020-07-16 2020-07-16 2020-07-26 2020-07-21 2020-08-16 2020-07-21 2020-09-01 2020-09-01 2021-04-30 2021-04-30 / Financial Expert the PFM System Selection GZ-MOFP-123226-CS-INDV / Individual Consultant to Component 1: Improving Individual work on the Israeli Deductions TF / A6949 Budget Expenditure Post Consultant Limited 0.00 Canceled 2019-07-31 2019-12-01 2019-08-05 2019-08-26 2019-09-30 2019-12-31 from Clearance Revenues Management and Control Selection transferred to the Palestinian Government GZ-MOFP-195439-CS-INDV Component 2: Improving Individual / Accountant # 4 to work on TF / A6949 Financial Accountability of Post Consultant Limited 10,800.00 Signed 2020-09-30 2020-09-17 2020-10-05 2020-10-07 2020-10-26 2020-10-07 2020-11-30 2020-12-01 2021-05-29 Net Lending the PFM System Selection GZ-MOFP-195441-CS-INDV Component 2: Improving Individual / Accountant # 5 to work on TF / A6949 Financial Accountability of Post Consultant Limited 10,800.00 Signed 2020-09-30 2020-09-17 2020-10-05 2020-10-07 2020-10-26 2020-10-07 2020-11-30 2020-12-01 2021-05-29 Net Lending the PFM System Selection Page 2 GZ-MOFP-195299-CS-INDV Component 4: Project Individual / Procurement and Grants TF / A6949 Implementation Support and Post Consultant Direct 46,800.00 Completed 2020-09-30 2020-09-01 2020-09-30 2020-09-01 2020-09-30 2020-09-01 2020-11-01 2020-10-06 2021-10-31 2021-10-31 Specialist Management Costs Selection GZ-MOFP-198031-CS-INDV / Contract Renewal for Component 2: Improving Individual Accountant # 1 to support the TF / A6949 Financial Accountability of Post Consultant Direct 10,800.00 Signed 2020-11-30 2020-10-19 2020-12-05 2020-11-01 2020-12-16 2020-11-01 2021-01-05 2020-12-08 2022-01-04 Accountant General and the PFM System Selection General Accounts Department GZ-MOFP-198032-CS-INDV / Contract Renewal for Component 2: Improving Individual Accountant # 2 to support the TF / A6949 Financial Accountability of Post Consultant Direct 10,800.00 Signed 2020-11-30 2020-10-19 2020-12-05 2020-11-01 2020-12-16 2020-11-01 2021-01-05 2020-12-08 2022-01-04 Accountant General and the PFM System Selection General Accounts Department GZ-MOFP-198034-CS-INDV / Contract Renewal for Component 2: Improving Individual Accountant # 3 to support the TF / A6949 Financial Accountability of Post Consultant Direct 10,800.00 Signed 2020-11-30 2020-10-19 2020-12-05 2020-11-01 2020-12-16 2020-11-01 2021-01-05 2020-12-08 2022-01-04 Accountant General and the PFM System Selection General Accounts Department GZ-MOFP-208240-CS-INDV Component 4: Project Individual / PMU Project Manager - TF / A6949 Implementation Support and Post Consultant Direct 50,400.00 Signed 2020-12-17 2020-12-10 2020-12-27 2020-12-10 2020-12-28 2020-12-15 2021-02-03 2021-02-03 2022-02-02 Contract renewal. Management Costs Selection Component 2: Improving Individual GZ-MOFP-211945-CS-INDV TF / A6949 Financial Accountability of Post Consultant Direct 48,000.00 Signed 2021-02-28 2021-02-25 2021-03-10 2021-04-13 2021-03-31 2021-04-29 2021-05-01 2021-04-29 2021-12-31 / Financial Expert the PFM System Selection GZ-MOFP-211946-CS-INDV Component 2: Improving Individual / Contract Renewal of Auditor TF / A6949 Financial Accountability of Post Consultant Direct 19,200.00 Signed 2021-01-31 2021-01-11 2021-02-10 2021-01-18 2021-03-03 2021-01-18 2021-04-01 2021-04-01 2022-03-31 # 1 for the benefit of SAACB the PFM System Selection GZ-MOFP-211947-CS-INDV Component 2: Improving Individual / Contract renewal Auditor # TF / A6949 Financial Accountability of Post Consultant Direct 17,400.00 Signed 2021-01-31 2021-01-11 2021-02-10 2021-01-18 2021-03-03 2021-01-18 2021-04-01 2021-04-01 2022-03-31 2 for SAACB the PFM System Selection GZ-MOFP-211950-CS-INDV Component 2: Improving Individual / Contract Renewal for TF / A6949 Financial Accountability of Post Consultant Direct 17,400.00 Signed 2021-01-31 2021-01-11 2021-02-10 2021-01-18 2021-03-03 2021-01-18 2021-04-01 2021-04-01 2021-09-28 Auditor # 3 SAACB the PFM System Selection Component 1: Improving GZ-MOFP-211920-CS-CDS / Under TF / A6949 Budget Expenditure Post Direct Selection Direct 0.00 2020-12-31 2020-12-17 2021-01-31 2021-03-23 2021-12-31 Bisan Service Agreement Implementation Management and Control GZ-MOFP-214311-CS-CDS / Component 4: Project Hiring an external auditor for TF / A6949 Implementation Support and Post Direct Selection Direct 6,000.00 Signed 2021-01-31 2021-01-26 2021-02-10 2021-04-06 2021-04-16 2021-06-17 2022-12-31 the Project Management Costs GZ-MOFP-214317-CS-INDV Component 2: Improving Individual / IT Consultant for the benefit TF / A6949 Financial Accountability of Post Consultant Limited 24,000.00 Terminated 2021-02-07 2021-01-28 2021-02-26 2021-04-05 2021-03-19 2021-04-27 2021-04-23 2021-06-06 2022-04-22 of SAACB the PFM System Selection Component 1: Improving Individual GZ-MOFP-214323-CS-INDV Under TF / A6949 Budget Expenditure Post Consultant Open 0.00 2021-01-31 2021-01-27 2021-03-21 2021-04-11 2021-05-16 2022-05-15 / IT Expert-Part Time Implementation Management and Control Selection Component 1: Improving Individual GZ-MOFP-214327-CS-INDV Under TF / A6949 Budget Expenditure Post Consultant Open 0.00 2021-01-31 2021-01-27 2021-03-21 2021-04-11 2021-05-16 2022-05-15 / Resident Senior Accountant Implementation Management and Control Selection GZ-MOFP-226305-CS-INDV Component 4: Project Individual / PMU-Financial Management TF / A6949 Implementation Support and Post Consultant Direct 37,044.00 Signed 2021-04-29 2021-04-11 2021-05-09 2021-04-14 2021-05-14 2021-04-14 2021-05-17 2021-05-03 2022-06-30 Specialist-Contract Renewal Management Costs Selection GZ-MOFP-235900-CS-INDV Component 2: Improving Individual / Replacement Accountant # 1 TF / A6949 Financial Accountability of Post Consultant Direct 10,800.00 Signed 2021-06-03 2021-05-25 2021-06-06 2021-06-10 2021-06-11 2021-06-10 2021-07-01 2021-06-22 2022-06-30 to Support the general the PFM System Selection accounts department. GZ-MOFP-235906-CS-INDV / Hire an individual consultant to develop Financial and Component 1: Improving Individual Institutional/administrative TF / A6949 Budget Expenditure Post Consultant Limited 30,000.00 Completed 2021-07-06 2021-05-25 2021-07-11 2021-06-10 2021-08-01 2021-06-17 2021-09-05 2021-07-10 2022-03-04 2021-12-10 framework for the net lending Management and Control Selection department established at the MoF GZ-MOFP-248660-CS-CDS / Component 1: Improving Pending SLA with IFMIS Bisan until June TF / A6949 Budget Expenditure Post Direct Selection Direct 0.00 2021-12-06 2022-01-06 2022-02-26 2022-06-30 Implementation 30, 2022. Management and Control GZ-MOFP-249277-CS-CDS / Component 1: Improving Implementing DMFAS 6 at the Under TF / A6949 Budget Expenditure Post Direct Selection Direct 0.00 2021-08-19 2021-07-01 2021-08-29 2021-11-02 2022-06-30 Ministry of Finance of the Implementation Management and Control State of Palestine GZ-MOFP-241603-CS-INDV Component 4: Project Individual / Contract Renewal of the Under TF / A6949 Implementation Support and Post Consultant Direct 0.00 2021-09-30 2021-08-12 2021-10-25 2021-10-25 2021-11-01 2022-06-30 Procurement & Grants Implementation Management Costs Selection Specialist. GZ-MOFP-260352-CS-INDV Component 4: Project Individual / Procurement Expert- Under TF / A6949 Implementation Support and Post Consultant Direct 0.00 2021-10-28 2021-10-28 2021-10-30 2021-10-30 2021-11-01 2022-04-30 Consultancy Agreement for 6 Implementation Management Costs Selection Months GZ-MOFP-260357-CS-INDV Component 4: Project Individual Under / Hiring of a new procurement TF / A6949 Implementation Support and Post Consultant Limited 0.00 2021-10-31 2021-10-14 2021-11-05 2021-11-26 2021-12-31 2022-06-30 Implementation specialist for the project. Management Costs Selection GZ-MOFP-260360-CS-INDV Component 2: Improving Individual Under / Bages Petro-Financial TF / A6949 Financial Accountability of Post Consultant Direct 0.00 2021-11-16 2021-10-13 2021-11-26 2021-12-17 2022-01-01 2022-06-30 Implementation Advisor the PFM System Selection Page 3 GZ-MOFP-260364-CS-INDV Component 2: Improving Individual / Fadi Naser-Accountant # 4- Under TF / A6949 Financial Accountability of Post Consultant Direct 0.00 2021-10-31 2021-11-01 2021-11-05 2021-11-16 2021-12-01 2022-06-30 Net Lending-Contract Implementation the PFM System Selection Renewal. GZ-MOFP-260367-CS-INDV Component 2: Improving Individual / Rawand Fadaleh-Accountant Under TF / A6949 Financial Accountability of Post Consultant Direct 0.00 2021-10-31 2021-11-01 2021-11-05 2021-11-16 2021-12-01 2022-06-30 # 5-Net Lending-Contract Implementation the PFM System Selection Renewal GZ-MOFP-267787-CS-INDV / Contract Renewal for Component 2: Improving Individual Under Accountant # 2 to support the TF / A6949 Financial Accountability of Post Consultant Direct 0.00 2021-12-16 2021-12-12 2021-12-21 2021-12-26 2022-01-05 2022-06-30 Implementation Accountant General and the PFM System Selection General Accounts Department. GZ-MOFP-267788-CS-INDV / Contract Renewal for Component 2: Improving Individual Under Accountant # 3 to support the TF / A6949 Financial Accountability of Post Consultant Direct 0.00 2021-12-16 2021-12-12 2021-12-21 2021-12-22 2022-01-05 2022-06-30 Implementation Accountant General and the PFM System Selection General Accounts Department. GZ-MOFP-267791-CS-INDV Component 4: Project Individual Under / PMU Project Manager- TF / A6949 Implementation Support and Post Consultant Direct 0.00 2022-01-06 2021-12-16 2022-01-16 2022-01-17 2022-02-03 2022-06-30 Implementation Contract Renewal Management Costs Selection Component 1: Improving Individual GZ-MOFP-271031-CS-INDV Under TF / A6949 Budget Expenditure Post Consultant Direct 0.00 2021-12-31 2021-12-30 2022-01-10 2022-01-10 2022-02-01 2022-05-01 / Debt Law Consultant Implementation Management and Control Selection GZ-MOFP-273159-CS-INDV Component 2: Improving Individual / Accountant # 1 for the Pending TF / A6949 Financial Accountability of Post Consultant Limited 0.00 2022-01-19 2022-01-24 2022-01-29 2022-01-31 2022-06-30 benefit of the Debt Implementation the PFM System Selection Directorate. GZ-MOFP-273160-CS-INDV Component 2: Improving Individual / Accountant # 2 for the Pending TF / A6949 Financial Accountability of Post Consultant Limited 0.00 2022-01-19 2022-01-24 2022-01-29 2022-01-31 2022-06-30 benefit of the Debt Implementation the PFM System Selection Directorate. GZ-MOFP-274427-CS-INDV Component 2: Improving Individual Pending / Contract Renewal for TF / A6949 Financial Accountability of Post Consultant Direct 0.00 2022-02-16 2022-02-26 2022-03-12 2022-04-01 2022-06-30 Implementation Auditor # 1-SAACB the PFM System Selection GZ-MOFP-274430-CS-INDV Component 2: Improving Individual Pending / Contract Renewal for TF / A6949 Financial Accountability of Post Consultant Direct 0.00 2022-02-16 2022-02-26 2022-03-19 2022-04-01 2022-06-30 Implementation Auditor # 3-SAACB the PFM System Selection GZ-MOFP-274432-CS-INDV Component 2: Improving Individual Pending / Contract Renewal for TF / A6949 Financial Accountability of Post Consultant Direct 0.00 2022-02-16 2022-02-26 2022-03-19 2022-04-01 2022-06-30 Implementation Auditor # 2-SAACB the PFM System Selection Page 4