PROCUREMENT PLAN (Textual Part) Project information: BRAZIL Ceara Water Security and Governance Project (P165055) Project Implementation agency: Economic Research and Strategy Institute (Instituto de Pesquisa e Estratégia Econômica do Ceará - IPECE) Date of the Procurement Plan: May 2, 2019 Period covered by this Procurement Plan: 2019 – 2026 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Brazil : Ceará Water Security and Governance PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2019-05-03 2022-01-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165055 GPN Date: 2020-03-04 Project Name: Ceará Water Security and Governance Loan / Credit No: IBRD / 90060, / I Executing Agency(ies): PECE Institute of Economic Research of the State of Ceara WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-CAGECE-CE-01-CW-RFB / CAGECE: Controle e Redução Improving the Efficiency of Solicitação de Single Stage - One 2025-06- de Perdas na Região IBRD / 90060 Posterior 0.00 Cancelado 2020-04-01 2020-04-06 2020-05-18 2020-06-17 2020-07-22 Water Services Ofertas Envelope 26 Metropolitana de Fortaleza por Setores Hidraúlicos (01 a 06) National BR-CAGECE-CE-1-CW-RFB / Procurement CAGECE: Controle e Redução Improving the Efficiency of Solicitação de Single Stage - One Document - 1 2022-11- de Perdas na Região IBRD / 90060 Posterior Open - National 0.00 Cancelado 2020-08-10 2022-01-24 2020-08-15 2020-09-26 2020-10-26 2020-11-30 Water Services Ofertas Envelope Envelope 20 Metropolitana de Fortaleza process (Non por Setores Hidráulicos (01 a Bank-SPD) 06). BR-SRH-CE-01-CW-RFP / Solicitação de Single Stage - Two 2025-09- SRH: Sistema Adutor IBRD / 90060 Increasing Water Security Prévia Open - International 0.00 Cancelado 2020-05-04 2020-05-09 2020-06-20 2020-09-02 2020-10-07 Propostas Envelope 11 Banabuiú - Sertão Central. BR-SRH-CE-01-CW-RFB / Solicitação de Single Stage - Two 2026-01- SRH: Sistema Adutor Banabuiú IBRD / 90060 Increasing Water Security Prévia Open - International 0.00 Cancelado 2020-09-01 2020-11-11 2020-09-06 2021-04-19 2020-10-18 2021-05-06 2020-12-31 2021-02-04 Ofertas Envelope 09 - Sertão Central. Request for BR-SRH-CE-01-CW-RFB-2 / Bids - Works Em fase de Solicitação de Single Stage - Two 2026-03- SRH: Sistema Adutor Banabuiú IBRD / 90060 Increasing Water Security Prévia Open - International (without 0.00 Implementaç 2020-11-11 2020-11-16 2020-12-16 2021-02-28 2021-10-12 2021-04-04 Ofertas Envelope 09 - Sertão Central. prequalificati ão on) SPD National BR-CAGECE-CE-274955-CW- Procurement RFB / CAGECE: Controle e Improving the Efficiency of Solicitação de Single Stage - One Document - 1 Implementaç 2025-12- Reducao de Perdas na Regiao IBRD / 90060 Prévia Open - National 0.00 2022-01-25 2022-01-30 2022-03-13 2022-04-12 2022-05-17 Water Services Ofertas Envelope Envelope ão Pendente 27 Metropolitana de Fortaleza process (Non por Setores Hidraulicos (01 a Bank-SPD) 06). GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-FUNCEME-CE-09-GO-RFB / FUNCEME: Aquisição de Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - International 0.00 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2021-06-20 Radar Polarimétrico de Banda Ofertas Envelope o Pendente X. BR-FUNCEME-CE-11-GO- RFQ / FUNCEME: Aquisição de equipamentos para a Sala de Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-03-20 2020-05-15 2020-11-11 Situação e para suporte ao Cotações Envelope o Pendente Monitoramento e Previsão Hidro-ambiental. BR-IPECE-CE-03-GO-RFQ / IPECE: Suporte em Aquisições Strengthening Public Sector Solicitação de Single Stage - One Implementaçã IBRD / 90060 Posterior Open - National 0.00 2020-01-20 2020-03-16 2020-09-12 de Bens para Unidade de Management Cotações Envelope o Pendente Gerenciamento de Projetos. BR-COGERH-CE-03-GO-RFB / COGERH: Aquisição de Solicitação de Single Stage - One Implementaçã equipamentos para uso da IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-02-01 Ofertas Envelope o Pendente Fiscalização de Recursos Hídricos. BR-TCE-CE-02-GO-RFQ / TCE: Aquisição de equipamentos (Vant's), Strengthening Public Sector Solicitação de Single Stage - One Implementaçã software e treinamento para / Posterior Open - National 0.00 2020-07-06 2020-08-31 2021-02-27 Management Cotações Envelope o Pendente auditoria e monitoramento de obras de infraestrutura hídrica. BR-SRH-CE-04-GO-RFQ / SRH: Aquisição de GPS Solicitação de Single Stage - One Implementaçã Geodésico para suporte ao IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-04-06 2020-06-01 2020-11-28 Cotações Envelope o Pendente Projeto Malha D'Água e às ações de regulação de uso. BR-FUNCEME-CE-02-GO-DIR Implementaçã / FUNCEME: Aquisição de IBRD / 90060 Increasing Water Security Posterior Aquisição Direta Direct 0.00 2020-04-01 2020-04-06 2020-05-11 2020-11-07 o Pendente licença do ArcGis. BR-FUNCEME-CE-12-GO-RFB / FUNCEME: Cluster para modernização do Sistema de Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-01-15 2020-01-20 2020-03-02 2020-04-01 2020-05-06 2020-11-02 Previsão climática e de Ofertas Envelope o Pendente afluências aos principais reservatórios do Estado. BR-FUNCEME-CE-01-GO-RFB / FUNCEME: Aquisição de equipamentos para Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-02-07 2020-02-12 2020-03-25 2020-04-24 2020-05-29 2020-11-25 instrumentação e Ofertas Envelope o Pendente monitoramento de bacias hidráulicas. Page 1 BR-FUNCEME-CE-03-GO- RFQ / FUNCEME: Aquisição de Solicitação de Single Stage - One IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 Cancelado 2020-03-11 2020-05-06 2020-11-02 réguas limnimétricas e outros Cotações Envelope materiais. BR-FUNCEME-SEDET-CE-10- Solicitação de Single Stage - One Implementaçã GO-RFB / FUNCEME / SEDET: IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-05-01 2020-05-06 2020-06-17 2020-07-17 2020-08-21 2021-02-17 Ofertas Envelope o Pendente Aquisição de Drones. BR-FUNCEME-CE-05-GO-RFB / FUNCEME: Aquisição de equipamentos e insumos para Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-05-03 2020-05-08 2020-06-19 2020-07-19 2020-08-23 2021-02-19 laboratório, destinados à Ofertas Envelope o Pendente realização de análises de água. (CAGECE) BR-COGERH-CE-06-GO-RFB Solicitação de Single Stage - One Implementaçã / Aquisições de Estações de IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-06-30 2020-07-05 2020-08-16 2020-09-15 2020-10-20 2021-10-15 Ofertas Envelope o Pendente Medição Portáteis. BR-FUNCEME-CE-14-GO-DIR / Fornecimento e instalação de Plataformas Automáticas Implementaçã IBRD / 90060 Increasing Water Security Posterior Aquisição Direta Direct 0.00 2020-09-01 2020-09-06 2020-10-11 2021-04-09 de Coleta de Dados para o Pendente Metodologia Surface Renewal (SR). BR-FUNCEME-SEDET-CE-07- GO-RFB / FUNCEME: Aquisição e Instalação de Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2021-06-20 Plataformas Automáticas de Ofertas Envelope o Pendente Coleta de Dados Agrometeorológico. BR-COGERH-CE-01-GO-RFB / COGERH: Aquisições de Solicitação de Single Stage - One Implementaçã Estações de Medição Fixas, IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-07-12 2020-07-17 2020-08-28 2020-09-27 2020-11-01 2021-04-30 Ofertas Envelope o Pendente visando a universalização da macromedição da COGERH. BR-TCE-03-GO-RFQ / TCE: Aquisição de equipamentos para instalação de Sala de Strengthening Public Sector Solicitação de Single Stage - One Situação para monitoramento IBRD / 90060 Posterior Open - National 0.00 Cancelado 2019-06-06 2019-08-01 2020-01-28 Management Cotações Envelope de obras de infraestrutura hídrica no Âmbito do Controle Externo no Estado do Ceará. BR-SRH-CE-03-GO-RFB / SRH: Aquisição de Solicitação de Single Stage - One Implementaçã equipamentos de TI para IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2021-02-01 2021-02-06 2021-03-20 2021-04-19 2021-05-24 2021-11-20 Ofertas Envelope o Pendente suporte ao Projeto Malha D'Água. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-FUNCEME-SEDET-CE-08- NC-RFQ / FUNCEME: Serviços Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-04-07 2020-06-02 2021-05-28 de engenharia para instalação Cotações Envelope o Pendente de estações meteorológicas. BR-FUNCEME-CE-13-NC- RFQ / FUNCEME: Capacitação Solicitação de Single Stage - One Implementaçã / Increasing Water Security Posterior Open - National 0.00 2020-06-06 2020-08-01 2020-09-06 e Treinamento de Técnicos da Cotações Envelope o Pendente Funceme. BR-IPECE-CE--NC-RFQ / Serviços Técnicos de Tradução Strengthening Public Sector Solicitação de Single Stage - One Implementaçã IBRD / 90060 Posterior Open - National 0.00 2020-03-08 2020-05-03 2020-10-30 para Documentos de Management Cotações Envelope o Pendente Aquisições. BR-IPECE-CE-04-NC-RFQ / Strengthening Public Sector Solicitação de Single Stage - One IPECE: Serviços de Tradução / Posterior Open - National 0.00 Cancelado 2019-06-06 2019-08-01 2020-01-28 Management Cotações Envelope para Documentos do IPF. BR-FUNCEME-CE-04-NC- RFQ / FUNCEME: Pequenos serviços de engenharia para Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-05-06 2020-07-01 2020-12-28 instalação dos equipamentos Cotações Envelope o Pendente de monitoramento de bacias hidráulicas. BR-IPECE-CE-14-NC-DIR / Aquisição de Licença para utilização de dois contratos (Inglês e Português) do Strengthening Public Sector Implementaçã documento: Plant and Design- IBRD / 90060 Posterior Aquisição Direta Direct 0.00 2020-03-09 2020-03-14 2020-04-18 2020-10-15 Management o Pendente Build Contract 1st Ed (1999 Yellow Book) da Federação Internacional de Engenheiros de Consultoria - FIDIC. BR-COGERH-CE-06-NC-RFQ / COGERH: Levantamento, caracterização e diagníostico das fontes Solicitação de Single Stage - One / Increasing Water Security Posterior Open - National 0.00 Cancelado 2020-03-06 2020-05-01 2021-04-26 poluidoralocalizadas no Cotações Envelope entorno do reservatório e bacia hidrográfica do Banabuiú (Salvaguardas) Page 2 BR-FUNCEME-ADECE-CE-08- NC-RFB / FUNCEME/SEDET: Serviços técnicos especializados para realização Strengthening Public Sector Solicitação de Single Stage - One de 60 cursos com os IBRD / 90060 Posterior Open - National 0.00 Cancelado 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Management Ofertas Envelope seguintes temas: Manejo Eficiente da Água no Setor Agropecuário e Avaliação de Sistemas de Irrigação. BR-COGERH-CE-07-NC-RFB / COGERH: Pequenos serviços Solicitação de Single Stage - One Implementaçã IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-08-08 2020-10-03 2021-09-28 de engenharia para instalação Cotações Envelope o Pendente de medidores de vazão. BR-IPECE-CE-05-NC-RFQ / IPECE: Capacitação Strengthening Public Sector Solicitação de Single Stage - One socioambiental, incluindo as IBRD / 90060 Posterior Open - National 0.00 Cancelado 2020-05-09 2020-07-04 2020-12-31 Management Cotações Envelope salvaguardas do Banco Mundial (Salvaguardas) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SCIDADES-CE-01-CS- QCBS / SCIDADES: Contratação de Serviços Especializados para Seleção Baseada Strengthening Public Sector Em fase de Elaboração do Plano Estadual IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-02-02 2021-10-18 2020-02-23 2020-04-07 2020-05-05 2020-06-04 2020-07-09 2020-08-13 2021-08-13 Management Implementação de Abastecimento de Água e Custo Esgotamento Sanitário do Ceará (PAAES) e Planos Correlatos. BR-FUNCEME-SEDET-CE-05- NC-RFB / FUNCEME/SEDET: Levantamento cadastral de irrigantes e determinação de Strengthening Public Sector Seleção Baseada Em fase de IBRD / 90060 Posterior Open - National 0.00 2020-05-01 2021-03-01 2020-05-22 2020-07-05 2021-10-20 2020-08-02 2020-09-01 2020-10-06 2020-11-10 2021-05-09 demanda hídrica para o setor Management no Menor Custo Implementação agropecuário das bacias do baixo, médio e alto Jaguaribe, Banabuiú e Salgado. BR-CAGECE-CE-05-CS-CQS / CAGECE: Consultoria Seleção Baseada Especializada para Improving the Efficiency of Em fase de IBRD / 90060 Posterior nas Qualificações Open - National 0.00 2019-11-07 2020-11-24 2019-11-28 2020-01-11 2020-02-10 2020-03-16 2020-09-12 Implantação de Melhorias nos Water Services Implementação dos Consultores Processos de Gestão De Empreendimentos da CAGECE. BR-IPECE-ADECE-CE-01-CS- QCBS / IPECE/SEDET: Sistema Estratégico para o Assessoramento à Irrigação- Seleção Baseada SEAI do Programa de Strengthening Public Sector Em fase de IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-02-03 2021-07-21 2020-02-24 2020-04-08 2021-10-08 2020-05-06 2021-11-19 2020-06-05 2020-07-10 2020-08-14 2021-08-14 Eficiência do Uso da Água no Management Implementação Custo Setor Agropecuário para Cinco Bacias do Estado do Ceará (Alto, Médio e Baixo Jaguaribe, Banabuiú e Salgado). BR-ARCE-CE-03-CS-QCBS / ARCE: Consultoria especializada para melhoria Seleção Baseada de processos de controle, Strengthening Public Sector Implementação IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-02-03 2020-02-24 2020-04-08 2020-05-06 2020-06-05 2020-07-10 2020-08-14 2021-08-14 fiscalização e certificação de Management Pendente Custo informações para regulação dos serviços de saneamento básico. BR-CGE-CE-01-CS-QCBS / CGE: Consultoria para o Desenvolvimento e Seleção Baseada Strengthening Public Sector Em fase de Implementação do Sistema de IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-02-03 2021-02-11 2020-02-24 2020-04-08 2021-08-18 2020-05-06 2021-09-27 2020-06-05 2020-07-10 2020-08-14 2021-08-14 Management Implementação Controle de Instrumentos Custo Contratuais do Poder Executivo do Estado do Ceará. BR-ARCE-CE-02-CS-QCBS / ARCE: Assistência Técnica para Modernização da Gestão Seleção Baseada Strengthening Public Sector Em fase de e da Atividade Regulatória da IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-02-03 2020-12-08 2020-02-24 2020-04-08 2021-06-08 2020-05-06 2021-07-22 2020-06-05 2020-07-10 2020-08-14 2021-08-14 Management Implementação Agência Reguladora de Custo Serviços Públicos Delegados do Estado do Ceará. BR-ARCE-CE-01-CS-QCBS / ARCE: Assistência Técnica para Elaboração de Manual de Controle Patrimonial Seleção Baseada Destinado aos Setores de Strengthening Public Sector Em fase de IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-03-02 2020-08-18 2020-03-23 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-09-11 Distribuição de Gás Management Implementação Custo Canalizado, de Abastecimento de Água e de Esgotamento Sanitário, no Âmbito do Estado do Ceará. BR-COGERH-CE-02-CS-QCBS / COGERH: Prestação de serviços de consultoria, Seleção Baseada contemplando as ações de IBRD / 90060 Increasing Water Security Posterior na Qualidade e Open - National 0.00 Cancelado 2020-03-04 2020-03-25 2020-05-08 2020-06-05 2020-07-05 2020-08-09 2020-09-13 2021-09-13 Regularização de Recursos Custo Hídricos para as 12 (doze) Bacias Hidrográficas do Estado do Ceará. BR-CAGECE-CE-03-CS-QCBS / CAGECE: Consultoria para Seleção Baseada Revisão do Modelo de Gestão Improving the Efficiency of Em fase de IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-01-15 2020-06-08 2020-02-05 2020-03-20 2021-05-20 2020-04-17 2020-05-17 2020-06-21 2020-07-26 2021-07-26 Estratégica e de Negócio e Water Services Implementação Custo Melhoria do Desempenho Empresarial da CAGECE. Page 3 BR-SEPLAG-CE-01-CS-QCBS / SEPLAG: Desenvolvimento e Seleção Baseada Implantação do Sistema de Strengthening Public Sector Em fase de IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-02-17 2021-06-17 2020-03-09 2020-04-22 2021-10-18 2020-05-20 2020-06-19 2020-07-24 2020-08-28 2021-08-28 Gestão de Investimento Management Implementação Custo Público (GIP) do Poder Executivo do Estado do Ceará. BR-CAGECE-CE-04-CS-QCBS / CAGECE: Elaboração de Estudo de Mercado e da Seleção Baseada Improving the Efficiency of Em fase de Estrutura Tarifária da IBRD / 90060 Posterior na Qualidade e Open - National 189,197.67 2020-01-06 2020-03-24 2020-01-27 2020-03-11 2021-01-14 2020-04-08 2021-03-04 2020-05-08 2021-05-14 2020-06-12 2021-09-01 2020-07-17 2021-07-17 Water Services Implementação Concessionária para os Custo Serviços de Abastecimento de Água e Esgotamento Sanitário. BR-IPECE-CE-13-CS-QCBS / Empresa Especializada para Realização de Treinamentos com Foco no “Fortalecimento Institucional Do Instituto De Seleção Baseada Strengthening Public Sector Em fase de Pesquisa E Estratégia IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-04-01 2021-04-29 2020-04-22 2020-06-05 2021-06-21 2020-07-03 2021-08-03 2020-08-02 2021-09-21 2020-09-06 2020-10-11 2021-08-07 Management Implementação Econômica do Ceará (IPECE), Custo Através da Capacitação em Análise de Dados, Ferramentas de Business Inteligence (BI) e Avalia BR-FUNCEME-SEDET-CE-08- CS-LCS / FUNCEME/SEDET: Serviços técnicos especializados para realização Strengthening Public Sector Seleção Baseada Em fase de de 60 cursos com os IBRD / 90060 Posterior Open - National 0.00 2020-04-01 2021-09-14 2020-04-22 2020-06-05 2020-07-03 2020-08-02 2020-09-06 2020-10-11 2021-10-06 Management no Menor Custo Implementação seguintes temas: Manejo Eficiente da Água no Setor Agropecuário e Avaliação de Sistemas de Irrigação. BR-CAGECE-CE-02-CS-LCS / CAGECE: Serviços de Engenharia Consultiva para Improving the Efficiency of Seleção Baseada Em fase de Gerenciamento, Fiscalização e IBRD / 90060 Posterior Open - National 0.00 2020-03-03 2021-04-15 2020-03-24 2020-05-07 2020-06-04 2020-07-04 2020-08-08 2020-09-12 2021-09-07 Water Services no Menor Custo Implementação Assessoria Técnica da Obra de Controle de Perdas no município de Fortaleza. BR-SRH-CE-02-CS-LCS / SRH: Serviços de Engenharia Consultiva para Gerenciamento, Fiscalização e Seleção Baseada IBRD / 90060 Increasing Water Security Prévia Open - International 0.00 Cancelado 2020-09-01 2020-11-11 2020-09-22 2020-12-03 2020-11-05 2020-12-03 2021-01-02 2021-02-06 2021-03-13 2026-02-15 Assessoria Técnica da Obra de no Menor Custo Implantação do Sistema Adutor Banabuiú - Sertão Central. BR-SRH-CE-02-CS-QCBS / SRH: Serviços de Engenharia Consultiva para Gerenciamento, Fiscalização e Seleção Baseada IBRD / 90060 Increasing Water Security Prévia Open - National 0.00 Cancelado 2020-04-01 2020-04-22 2020-06-05 2020-07-03 2020-08-02 2020-09-06 2020-10-11 2025-09-15 Assessoria Técnica da Obra de no Menor Custo Implantação do Sistema Adutor Banabaiú - Sertão Central. BR-TCE-CE-01-CS-QCBS / TCE: Desenvolver e Aplicar Estratégias e Instrumentos Tecnológicos de Informação e Seleção Baseada Comunicação para Strengthening Public Sector Em fase de IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2020-07-15 2021-01-14 2020-08-05 2020-09-18 2021-08-20 2020-10-16 2021-10-15 2020-11-15 2020-12-20 2021-01-24 2022-01-24 Desenvolvimento de Sistema Management Implementação Custo de Gerenciamento de Obras para Atender às Necessidades e Procedimentos do Controle Externo no Âmbito das Obras. BR-COGERH-CE-05-CS-QCBS Seleção Baseada / COGERH: Planos de Em fase de IBRD / 90060 Increasing Water Security Posterior na Qualidade e Open - National 0.00 2020-10-01 2021-06-09 2020-10-22 2020-12-05 2021-01-02 2021-02-01 2021-03-08 2021-04-12 2023-04-02 Segurança das Barragens Implementação Custo Banabuiú e Gavião BR-CAGECE-CE-02-CS-QCBS / CAGECE: Serviços de Engenharia Consultiva para Seleção Baseada Improving the Efficiency of Gerenciamento, Fiscalização e / Posterior na Qualidade e Open - National 0.00 Cancelado 2019-06-01 2019-06-22 2019-08-05 2019-09-02 2019-10-02 2019-11-06 2019-12-11 2020-12-10 Water Services Assessoria Técnica da Obra de Custo Controle de Perdas no município de Fortaleza. BR-COGERH-CE-02-CS-LCS / Contratação de Serviços de Cadastro e Regularização de Seleção Baseada Em fase de IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 2020-11-30 2021-03-24 2020-12-21 2021-02-03 2021-10-28 2021-03-03 2021-04-02 2021-05-07 2021-06-11 2022-07-06 Uso de Recursos Hídricos das no Menor Custo Implementação 12 (Doze) Bacias Hidrográficas do Estado do Ceará. BR-IPECE-CE-07-CS-LCS / IPECE: Estudos e Pesquisas nas Áreas de Recursos Hídricos, Agronegócio e Gestão Econômica da Água: Strengthening Public Sector Seleção Baseada IBRD / 90060 Posterior Open - National 0.00 Cancelado 2020-02-03 2020-02-24 2020-04-08 2020-05-06 2020-06-05 2020-07-10 2020-08-14 2021-06-10 Aproveitamento Hidro Management no Menor Custo Agrícola dos Corpos Hídricos Existentes na Região no Sistema Adutor Banabuiú–Sertão Central. BR-IPECE-CE-06-CS-QCBS / IPECE: Consultoria Especializada para a Realização de Estudo do Seleção Baseada Strengthening Public Sector Agronegócio e Gestão IBRD / 90060 Posterior na Qualidade e Open - National 0.00 Cancelado 2020-01-15 2020-02-05 2020-03-20 2020-04-17 2020-05-17 2020-06-21 2020-07-26 2021-07-26 Management Econômica da Água no Ceará: Custo Estudo de 10 Cadeias Produtivas do Setor Agropecuário. Page 4 BR-IPECE-CE-16-CS-QCBS / IPECE: Consultoria para Desenvolvimento de Metodologia do Cálculo do PIB do Agronegócio e do PIB da Seleção Baseada Strengthening Public Sector Em fase de Agricultura Familiar do Estado IBRD / 90060 Posterior na Qualidade e Open - National 0.00 2021-01-18 2021-05-07 2021-02-08 2021-03-24 2021-11-19 2021-04-21 2021-05-21 2021-06-25 2021-07-30 2022-07-30 Management Implementação do Ceará e Uso de Custo Instrumentos de Análise de Impactos Econômicos Com Enfoque nos Recursos Hídricos do Estado do Ceará. BR-FUNCEME-CE-17-CS-CSQ / FUNCEME: Monitoramento utilizando técnicas de modelagem hidrológica e de Seleção Baseada Em fase de sensoriamento remoto dos IBRD / 90060 Increasing Water Security Posterior nas Qualificações Open - National 0.00 2020-10-27 2020-10-27 2020-11-17 2020-12-31 2021-01-30 2021-03-06 2022-06-29 Implementação pequenos açudes visando sua dos Consultores incorporação na estimativa de aporte aos reservatórios estratégicos do Estado. BR-SRH-CE-05-CS-LCS / SRH: Programa de Capacitação Seleção Baseada IBRD / 90060 Increasing Water Security Posterior Open - National 0.00 Cancelado 2020-07-01 2020-07-22 2020-09-04 2020-10-02 2020-11-01 2020-12-06 2021-01-10 2022-01-05 Técnica em Recursos Hídricos no Menor Custo e Gestão Pública. BR-IPECE-CE-225127-CS- QCBS / SRH: Serviços de Engenharia Consultiva para Seleção Baseada Gerenciamento, Fiscalização e Em fase de IBRD / 90060 Increasing Water Security Prévia na Qualidade e Open - International 0.00 2021-03-16 2021-03-23 2021-05-06 2021-03-24 2021-06-03 2021-07-16 2021-07-03 2021-11-11 2021-08-07 2022-01-04 2021-09-11 2022-09-11 Assessoria Técnica da Obra de Implementação Custo Implantação do Sistema Adutor Banabuiú - Sertão Central INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-FUNCEME-CE-06-CS-CDS / FUNCEME: Assessoria técnica à implementação do Seleção Direta de Em fase de IBRD / 90060 Increasing Water Security Posterior Direct 0.00 2020-05-01 2020-09-15 2020-05-11 2020-07-15 2021-07-10 monitoramento da qualidade Consultores Implementação de água por sensoriamento remoto. BR-FUNCEME-SEDET-CE-06- CS-CDS / FUNCEME/SEDET: Acompanhamento de Strengthening Public Sector Seleção Direta de Em fase de implantação da metodologia IBRD / 90060 Posterior Direct 0.00 2020-04-02 2021-04-19 2020-04-12 2020-06-16 2020-12-13 Management Consultores Implementação de determinação de coeficientes de cultivo "Surface Renewal". BR-FUNCEME-SEDET-CE-07- CS-CDS / FUNCEME/SEDET: Implantação da Metodologia Strengthening Public Sector Seleção Direta de Implementação IBRD / 90060 Posterior Direct 0.00 2020-04-02 2020-04-12 2020-06-16 2020-12-13 de Determinação de Management Consultores Pendente Coeficientes de Cultivo "Surface Renewal". BR-SRH-CE-06-CS-CDS / SRH: Painel de Especialistas Seleção Direta de para as Barragens Banabuiú e IBRD / 90060 Increasing Water Security Posterior Direct 60,907.17 Assinado 2020-03-09 2020-02-27 2020-03-19 2020-06-18 2020-05-23 2020-09-23 2021-05-18 Consultores Gavião: Especialista em Engenheiro Geotécnico. BR-SRH-CE-07-CS-CDS / SRH: Painel de Especialistas Seleção Direta de para as Barragens Banabuiú e IBRD / 90060 Increasing Water Security Posterior Direct 34,937.31 Assinado 2020-03-09 2020-02-27 2020-03-19 2020-06-18 2020-05-23 2020-08-26 2021-05-18 Consultores Gavião: Especialista em Hidromecânica. BR-SRH-CE-08-CS-CDS / SRH: Painel de Especialistas Seleção Direta de para as Barragens Banabuiú e IBRD / 90060 Increasing Water Security Posterior Direct 48,828.45 Assinado 2020-03-09 2020-02-27 2020-03-19 2020-06-18 2020-05-23 2020-08-28 2021-05-18 Consultores Gavião: Especialista em Hidrologista. BR-IPECE-CE-02-CS-INDV / IPECE: Consultor Individual para o serviço de Suporte Strengthening Public Sector IBRD / 90060 Posterior Individual Open 18,099.89 Assinado 2020-04-01 2020-12-18 2020-05-20 2021-03-04 2020-06-10 2021-03-08 2020-07-15 2021-05-06 2021-07-10 Operacional e Logístico para Management Unidade Gerenciamento de Projetos. BR-IPECE-CE-12-CS-INDV / IPECE: Consultor Individual para prestar Suporte Técnico Strengthening Public Sector a UGP no Atendimento as IBRD / 90060 Posterior Individual Open 30,811.46 Assinado 2020-04-01 2020-06-04 2020-05-20 2020-08-18 2020-06-10 2020-09-04 2020-07-15 2020-10-06 2021-07-10 Management Salvaguardas Socioambientais durante a implementação do IPF-Ceará. BR-IPECE-CE-11-CS-INDV / IPECE: Consultor Individual - Strengthening Public Sector IBRD / 90060 Posterior Individual Open 29,959.85 Assinado 2020-04-01 2020-08-28 2020-05-20 2020-11-18 2020-06-10 2020-11-18 2020-07-15 2020-12-30 2021-07-10 Analista de Monitoramento e Management Controle. BR-IPECE-CE-08-CS-CDS / IPECE: Consultoria Individual Strengthening Public Sector Seleção Direta de IBRD / 90060 Posterior Direct 35,100.10 Assinado 2020-02-19 2020-02-20 2020-02-29 2020-03-05 2020-05-04 2020-03-13 2021-05-04 de Especialista Pleno em Management Consultores Aquisições e Contratos. BR-IPECE-CE-01-CS-CDS / IPECE: Consultoria Individual Strengthening Public Sector Seleção Direta de IBRD / 90060 Posterior Direct 45,083.52 Assinado 2020-02-19 2020-02-21 2020-02-29 2020-03-05 2020-05-04 2020-03-13 2021-05-04 de Especialista Sênior em Management Consultores Aquisições e Contratos. Page 5 BR-IPECE-CE-10-CS-INDV / IPECE: Consultor Individual Strengthening Public Sector IBRD / 90060 Posterior Individual Open 0.00 Cancelado 2020-05-01 2020-06-19 2020-07-10 2020-08-14 2021-02-10 Analista Pleno em Aquisições Management e Contratos. BR-IPECE-CE-09-CS-CDS / IPECE: Consultor Individual Strengthening Public Sector Seleção Direta de IBRD / 90060 Posterior Direct 28,738.66 Assinado 2020-02-19 2020-02-20 2020-02-29 2020-03-05 2020-05-04 2020-03-13 2021-05-04 Analista Sênior em Aquisições Management Consultores e Contratos. BR-FUNCEME-CE-17-CS-CDS / FUNCEME: Monitoramento utilizando técnicas de modelagem hidrológica e de Seleção Direta de Em fase de sensoriamento remoto dos IBRD / 90060 Increasing Water Security Posterior Direct 0.00 2020-09-02 2020-10-27 2020-09-12 2020-11-16 2021-11-11 Consultores Implementação pequenos açudes visando sua incorporação na estimativa de aporte aos reservatórios estratégicos do estado. BR-IPECE-CE-15-CS-CDS / Consultor Individual para Serviço de Tradução do Edital Tipo “Turnkey” da Obra do Sistema Adutor Banabuiú - Strengthening Public Sector Seleção Direta de Em fase de IBRD / 90060 Posterior Direct 0.00 2020-03-23 2020-03-25 2020-04-02 2020-06-06 2020-12-03 Sertão Central do Projeto de Management Consultores Implementação Apoio Melhoria da Segurança Hídrica e Fortalecimento da Inteligência na Gestão Pública do Estado do Ceará. BR-IPECE-CE-16-CS-CDS / Consultor Analista em Strengthening Public Sector Seleção Direta de Implementação IBRD / 90060 Posterior Direct 0.00 2020-05-29 2020-06-08 2020-08-12 2021-08-12 Gerenciamento Financeiro Management Consultores Pendente para apoio a UGP do IPECE BR-IPECE-CE-245565-CS- INDV / SCIDADES: Consultor Jurídico Individual, Especialista em Saneamento Strengthening Public Sector IBRD / 90060 Posterior Individual Open 0.00 Cancelado 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Básico, para Adequação do Management Marco Regulatório da Política Estadual de Abastecimento de Água e Esgotamento Sanitário. BR-SCIDADES-CE-02-CS- INDV / SCIDADES: Consultor Jurídico Individual, Especialista em Saneamento Strengthening Public Sector Em fase de IBRD / 90060 Posterior Individual Open 0.00 2021-09-28 2021-11-16 2021-11-16 2021-12-07 2022-01-11 2022-07-10 Básico, para Adequação do Management Implementação Marco Regulatório da Política Estadual de Abastecimento de Água e Esgotamento Sanitário. Page 6