PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Congo, Republic of : Urban Development and Poor Neighborhood Upgrading Project PLAN General Information Country: Congo, Republic of 2017-06-29 Bank’s Approval Date of the Original Procurement Plan: 2022-12-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146933 GPN Date: 2017-11-13 Project Name: Urban Development and Poor Neighborhood Upgrading Project Loan / Credit No: IBRD / 85880 Urban Development and Poor Neighborhood Upgrading Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CG-003-TX-AOI / Travaux de Integration and Neighborhoo Open - Internationa Single Stage - Two E 17,100,000.0 2019-01-2 construction des voiries urbai IBRD / 85880 A priori Appel d'offres 0.00 Annulé 2018-02-22 2018-02-27 2018-04-10 2018-06-23 2018-07-28 d Upgrading l nvelope 0 4 nes à Brazzaville et Pointe-N oire phase 2 CG-DURQUAP-005-TX-AOI / T ravaux de construction des v Integration and Neighborhoo Open - Internationa Single Stage - Two E 10,477,483. 2019-12-0 IBRD / 85880 A priori Appel d'offres 8,550,000.00 Signé 2019-01-07 2019-02-15 2019-01-12 2019-02-18 2019-02-23 2019-04-30 2019-05-08 2019-06-21 2019-06-12 2019-06-15 oiries urbaines et assainisse d Upgrading l nvelope 65 9 ment à Brazzaville Phase 1 CG-OO1-TX-AOI / Travaux de construction des voiries urbai Integration and Neighborhoo Open - Internationa Single Stage - Two E 6,632,142.0 2019-12-0 IBRD / 85880 A priori Appel d'offres 8,550,000.00 Signé 2019-01-07 2019-02-15 2019-01-12 2019-02-18 2019-02-23 2019-05-08 2019-05-19 2019-06-12 2019-06-15 nes et assainissement à Poin d Upgrading l nvelope 3 9 te-Noire phase 1 CG-DURQUAP-085-TX-AON / Travaux marché Soukissa- Tr Integration and Neighborhoo Single Stage - Two E 2,400,086.9 2020-06-0 IBRD / 85880 A posteriori Appel d'offres Open - National 2,450,000.00 Signé 2019-07-05 2019-10-03 2019-07-10 2019-10-09 2019-08-21 2019-12-13 2019-11-03 2020-04-18 2019-12-08 2020-02-27 avaux de réhabilitation du m d Upgrading nvelope 6 5 arché de SOUKISSA à Brazza ville CG-DURQUAP-001BIS-TX-AOI / Travaux de construction de 10,363 km des voiries urbain es par pavage, des ouvrages Integration and Neighborhoo Open - Internationa Single Stage - One E 7,000,435.5 2016-10-0 IBRD / 85880 A priori Appel d'offres 8,550,000.00 Signé 2015-12-17 2019-08-02 2015-12-22 2019-09-02 2016-02-02 2019-03-29 2016-03-03 2019-09-13 2016-04-07 2019-06-15 connexes et de drainage des d Upgrading l nvelope 7 4 eaux pluviales dans les quart iers MBOUKOU (Lot 1) et TCH INIAMBI1 (Lot 2) à Pointe Noir e répartis CG-DURQUAP-093-TX-CF / Tr Project Management, Coordi Single Stage - One E 2020-03-1 IBRD / 85880 A posteriori Demande de prix Limited 7,000.00 8,254.42 Achevé 2019-07-27 2019-07-12 2019-09-21 2019-08-22 avaux d’aménagement de bu nation and Evaluation nvelope 9 reaux CG-004-TX-AON / Travaux E au et Elec-Travauxdans les ré Integration and Neighborhoo Single Stage - Two E 2020-03-0 IBRD / 85880 A posteriori Appel d'offres Open - National 3,500,000.00 0.00 Annulé 2019-04-02 2019-04-07 2019-05-19 2019-08-01 2019-09-05 seaux eau et électricité à Bra d Upgrading nvelope 3 zzaville et Pointe-Noire CG-002-TX-AON / Travaux Er osion-Travaux de traitement Integration and Neighborhoo Single Stage - Two E 2020-03-0 IBRD / 85880 A posteriori Appel d'offres Open - National 3,000,000.00 0.00 Annulé 2019-04-02 2019-04-07 2019-05-19 2019-08-01 2019-09-05 des zones en proie aux érosi d Upgrading nvelope 3 ons à Brazzaville CG-DURQUAP-084-TX-AON / Travaux Stade-Travaux de ré Integration and Neighborhoo Single Stage - Two E 2020-08-1 habilitation du stade TATA L IBRD / 85880 A posteriori Appel d'offres Open - National 1,800,000.00 0.00 Annulé 2019-09-09 2019-09-14 2019-10-26 2020-01-08 2020-02-12 d Upgrading nvelope 0 OBOKO à Pointe Noire au qua rtier MBOUKOU à Pointe-Noir e CG-DURQUAP-083-TX-AON / Travaux Ecoles- Travaux de r Integration and Neighborhoo Single Stage - Two E 2020-08-0 éhabilitation des écoles Mou IBRD / 85880 A posteriori Appel d'offres Open - National 2,700,000.00 0.00 Annulé 2019-09-06 2019-09-11 2019-10-23 2020-01-05 2020-02-09 d Upgrading nvelope 7 ntou Mavoungou et PAMBOU Benjamin à Pointe Noire au q uartier TCHINIAMBI CG-DURQUAP-086-TX-AON / Travaux marche Tchiniambi- Integration and Neighborhoo Single Stage - Two E 2020-08-1 IBRD / 85880 A posteriori Appel d'offres Open - National 2,400,000.00 0.00 Annulé 2019-09-09 2019-09-14 2019-10-26 2020-01-08 2020-02-12 Travaux de réhabilitation du d Upgrading nvelope 0 marché de TCHINIAMBI à Poi nte-Noire CG-DURQUAP-004-TX-AOI / I Integration and Neighborhoo Open - Internationa Single Stage - Two E 22,000,000.0 2018-11-1 nvestissement en vue de la r IBRD / 85880 A priori Appel d'offres 0.00 Annulé 2017-12-15 2017-12-20 2018-01-31 2018-04-15 2018-05-20 d Upgrading l nvelope 0 6 estructuration-Equipement d e quartiers CG-DURQUAP-083 BIS-TX-AO N / Tx Ecoles/Travaux de réh Integration and Neighborhoo Single Stage - One E 2021-01-1 abiliation des Ecoles Mounto IBRD / 85880 A posteriori Appel d'offres Open - National 3,000,000.00 0.00 Annulé 2020-04-02 2020-04-07 2020-05-19 2020-06-18 2020-07-23 d Upgrading nvelope 9 u Mavoungou et Pambou Ben jamin à Pointe Noire. CG-DURQUAP-002 BIS-TX-AO N / Tx Erosion-Travaux de tra Integration and Neighborhoo Single Stage - One E 2020-11-1 IBRD / 85880 A posteriori Appel d'offres Open - National 3,500,000.00 0.00 Annulé 2020-01-31 2020-02-05 2020-03-18 2020-04-17 2020-05-22 itement de la zone en proie a d Upgrading nvelope 8 ux érosions à Brazzaville CG-DURQUAP-004 BIS-TX-AO I / Tx Eau et Elec-Travaux de Integration and Neighborhoo Open - Internationa Single Stage - One E 12,000,000.0 2021-01-3 IBRD / 85880 A priori Appel d'offres 0.00 Annulé 2020-04-13 2020-04-18 2020-05-30 2020-06-29 2020-08-03 réhabilitation des réseaux ea d Upgrading l nvelope 0 0 u et électricité à Brazzaville e t à pointe-Noire CG-DURQUAP-086 BIS-TX-AO N / Tx Marché Tchi/Travaux d Integration and Neighborhoo Single Stage - One E 2021-02-0 IBRD / 85880 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2020-04-18 2020-04-23 2020-06-04 2020-07-04 2020-08-08 e réhabilitation marché Tchi d Upgrading nvelope 4 niambi à Pointe Noire CG-DURQUAP-084 BIS-TX-AO N / Tx-Stade/Travaux de réha Integration and Neighborhoo Single Stage - One E 2021-01-1 IBRD / 85880 A priori Appel d'offres Open - National 8,000,000.00 0.00 Annulé 2020-04-02 2020-04-07 2020-05-19 2020-06-18 2020-07-23 bilitation du stade TATA LOB d Upgrading nvelope 9 OKO au quartier Mboukou à P ointe-Noire Page 1 CG-DURQUAP- 005 BIS-TX-A OI / Travaux de construction de 10,211 km des voiries urb aines par pavage, des ouvra Integration and Neighborhoo Open - Internationa Single Stage - One E 2016-08-2 IBRD / 85880 A priori Appel d'offres 8,550,000.00 0.00 Annulé 2015-11-10 2015-11-15 2015-12-27 2016-01-26 2016-03-01 ges connexes et de drainage d Upgrading l nvelope 8 des eaux pluviales dans les q uartiers SUKISSA (Lot 1) et M OUKOUNDZI NGOUAKA (Lot 2 ) à Brazzaville CG-DURQUAP-020-CERC-TX- ED / Travaux de curage et de faucardage du cours d’eau N Integration and Neighborhoo Passation de marc 2021-04-2 IBRD / 85880 A posteriori Direct 138,000.00 0.00 Annulé 2020-09-15 2020-09-20 2020-10-25 GANDA COULOIR et le collect d Upgrading hé de gré à gré 3 eur traversant les rues Kindo mbi, Loualou et Likibi au qua rtier SOUKISSA CG -DURQUAP-0018-CERC-T X-ED / Travaux de curage et de faucardage des rivières L Integration and Neighborhoo Passation de marc 2021-04-1 IBRD / 85880 A posteriori Direct 138,000.00 0.00 Annulé 2020-09-10 2020-09-15 2020-10-20 OUKA, MALADIE DU SOMMEIL d Upgrading hé de gré à gré 8 et le collecteur ''1500 '' au q uartier MOUKOUNDZI-NGOUA KA CG-DURQUAP-017-CERC-TX- CF / Travaux d'assainisseme nt et de nettoyage des marc Integration and Neighborhoo Single Stage - One E 2021-03-1 IBRD / 85880 A posteriori Demande de prix Limited 345,000.00 0.00 Annulé 2020-09-21 2020-11-16 hés Tié-Tié et Grand-marché d Upgrading nvelope 6 et des sites de dépôt sauvag e des ordures à Pointe Noire CG-DURQUAP-015-CERC-TX- ED / Travaux d'assainisseme nt du Marché Total de Brazza Integration and Neighborhoo Passation de marc 2021-04-2 ville: curage du réseau d'ass IBRD / 85880 A posteriori Direct 517,000.00 0.00 Annulé 2020-09-14 2020-09-19 2020-10-24 d Upgrading hé de gré à gré 2 ainissement, nettoyage des s ites de dépôts sauvages d'or dures, traitement des terre-p leins et autres points noirs CG-DURQUAP-014-CERC-TX- CF / Travaux de curage et de faucardage du cours d’eau (S Integration and Neighborhoo Single Stage - One E 2021-05-0 IBRD / 85880 A posteriori Demande de prix Limited 776,000.00 0.00 Annulé 2020-09-15 2020-11-10 ongolo) en amont et en aval d Upgrading nvelope 9 de l’ouvrage à réhabiliter Arr ondissement 04 - LOANDJILI CG-DURQUAP-004 BIS-TX-AO I-2 / Travaux de réhabilitatio Integration and Neighborhoo Open - Internationa Single Stage - One E 12,000,000.0 2021-05-0 IBRD / 85880 A priori Appel d'offres 0.00 Annulé 2020-08-21 2020-08-24 2020-09-23 2020-10-07 2020-11-04 n des réseaux eau et électrici d Upgrading l nvelope 0 3 té à Brazzaville et à pointe-N oire CG-DURQUAP-086 BIS-TX-AO Integration and Neighborhoo Single Stage - One E 2021-04-2 N-2 / Travaux de réhabilitatio IBRD / 85880 A posteriori Appel d'offres Open - National 2,400,000.00 0.00 Annulé 2020-08-10 2020-08-13 2020-08-15 2020-08-14 2020-09-14 2020-09-29 2020-09-28 2021-01-04 2020-10-26 d Upgrading nvelope 4 n du marché de TCHINIAMBI à Pointe-Noire CG-DURQUAP-083 BIS-TX-AO N-2 / Travaux de réhabilitatio Integration and Neighborhoo Single Stage - One E 2021-04-2 n des établissements scolaire IBRD / 85880 A posteriori Appel d'offres Open - National 3,000,000.00 0.00 Annulé 2020-08-14 2020-08-14 2020-08-18 2020-08-14 2020-09-17 2020-09-30 2020-10-01 2021-01-02 2020-10-29 d Upgrading nvelope 7 s publics PAMBOU Benjamin et MOUNTOU MAVOUNGOU B ernard à Pointe Noire CG-DURQUAP-084 BIS-TX-AO N-2 / Travaux de réhabilitatio Integration and Neighborhoo Single Stage - One E 2021-03-3 IBRD / 85880 A priori Appel d'offres Open - National 8,000,000.00 0.00 Annulé 2020-08-14 2020-08-26 2020-08-18 2020-08-31 2020-08-21 2020-10-01 2020-09-04 2020-10-02 n du stade TATA LOBOKO au d Upgrading nvelope 1 quartier Mboukou à Pointe-N oire CG-DURQUAP-086 BIS-TX-AO Request for Bids - N-2021 / TRAVAUX DE REHA Integration and Neighborhoo Single Stage - One E Works French Civi 4,450,470.3 2022-03-1 IBRD / 85880 A posteriori Appel d'offres Open - National 3,500,000.00 Signé 2021-06-28 2021-06-15 2021-07-03 2021-06-15 2021-08-02 2020-09-29 2021-08-16 2021-07-28 2021-09-13 2021-08-13 BILITATION DU MARCHE DOM d Upgrading nvelope l Law (French) SP 6 2 ANIAL DE TCHINIAMBI 1 A PO D INTE-NOIRE. CG-DURQUAP-083-TX-AON-2 021 / Travaux de réhabilitatio n de l'école La SORBONNE et Request for Bids - Amélioration du système d'al Integration and Neighborhoo Single Stage - One E Works French Civi 3,872,808.5 2022-03-1 IBRD / 85880 A posteriori Appel d'offres Open - National 1,500,000.00 Signé 2021-06-30 2021-08-03 2021-07-05 2021-08-04 2021-08-04 2021-09-02 2021-08-18 2021-11-18 2021-09-15 2021-10-30 imentation en eau et d'assai d Upgrading nvelope l Law (French) SP 2 4 nissement et Renforcement D de la sensibilisation de la pop ulation bénéficiaire sur la CO VID-19. CG-DURQUAP-01-TX-ED-202 1 / Travaux de construction d Request for Quota es voiries urbaines par pavag tions - Small Work e dans les quartiers MBOUKO Integration and Neighborhoo Passation de marc 7,485,070.8 2022-04-2 IBRD / 85880 A posteriori Direct s (Emergency) SP 2,167,459.00 Signé 2021-09-20 2021-09-06 2021-09-25 2021-09-06 2021-10-30 2021-11-27 U et TCHINIAMBI 1 à Pointe-N d Upgrading hé de gré à gré 3 8 D -Non Competiti oire & Renforcement de la se ve nsibilisation de la population bénéficiaire sur la COVID-19 en deux Lots distincts. CG-DURQUAP-002-TX-ED-20 21 / Travaux de construction de des voiries urbaines par p Request for Quota avage, à MOUKOUNDZI NGO tions - Small Work Integration and Neighborhoo Passation de marc 5,222,856.6 2022-04-2 UAKA et SUKISSA à Brazzavill IBRD / 85880 A posteriori Direct s (Emergency) SP 4,850,000.00 Signé 2021-09-20 2021-09-06 2021-09-25 2021-09-06 2021-10-30 2021-11-22 d Upgrading hé de gré à gré 8 8 e répartis en 02 lots D -Non Competiti Distincts & Amélioration du s ve ystème d’AE et d’assainisse ment ainsi que le Renforcem ent de la sensibilisation sur l a COVID-19 CG-DURQUAP-12-TX-AON-20 21 / Travaux de réhabilitation Request for Bids - des établissements publics s Integration and Neighborhoo Single Stage - One E Small Works SPD 3,399,066.6 2022-07-1 IBRD / 85880 A posteriori Appel d'offres Open - National 2,850,000.00 Signé 2021-10-30 2021-10-23 2021-11-03 2021-10-23 2021-12-03 2021-10-23 2021-12-17 2021-10-26 2022-01-14 2021-10-26 colaires de Bernard MOUNTO d Upgrading nvelope (1 envelope proce 3 3 U MAVOUNGOU et Benjamin ss) PAMBOU à POINTE NOIRE CG-DURQUAP-084 BIS-TX-AO Request for Bids - N-2021 / TRAVAUX DE REHA Integration and Neighborhoo Single Stage - One E Works French Civi 10,000,000.0 2022-02-0 BILITATION DU STADE TATA L IBRD / 85880 A priori Appel d'offres Open - National 0.00 Annulé 2021-06-21 2021-06-17 2021-06-25 2021-06-21 2021-06-28 2020-10-01 2021-07-12 2021-08-09 d Upgrading nvelope l Law (French) SP 0 5 OBOKO DANS LE QUARTIER D MBOUKOU A POINTE-NOIRE. Request for Quota CG-DURQUAP-15-TX-ED-202 tions - Small Work 2 / TRAVAUX DE RENOVATIO Integration and Neighborhoo Passation de marc 2022-09-0 IBRD / 85880 A posteriori Direct s (Emergency) SP 28,000.00 25,596.36 Signé 2022-01-25 2022-01-11 2022-01-30 2022-01-11 2022-03-06 2022-01-17 N DU SITE D'INSTALLATION D d Upgrading hé de gré à gré 2 D -Non Competiti E L'OBSERVATOIRE URBAIN A ve BRAZZAVILLE. Page 2 Request for Quota CG-DURQUAP-16-TX-ED-202 tions - Small Work 2 / TRAVAUX DE RENOVATIO Integration and Neighborhoo Passation de marc 2022-09-0 IBRD / 85880 A posteriori Direct s (Emergency) SP 66,000.00 71,539.96 Signé 2022-01-25 2022-01-11 2022-01-30 2022-01-11 2022-03-06 2022-01-24 N DU SITE D'INSTALLATION D d Upgrading hé de gré à gré 2 D -Non Competiti E L'OBSERVATOIRE URBAIN A ve POINTE-NOIRE. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-002-F-CF / Acquisition M Integration and Neighborhoo Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 7,060.00 13,698.03 Achevé 2017-10-25 2018-01-12 2017-12-20 2018-04-05 2018-06-18 2018-06-23 atériel Informatique UC d Upgrading nvelope CG-DURQUAP-003-BIS-F-CF / Integration and Neighborhoo Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 211,000.00 196,458.63 Achevé 2017-09-18 2018-02-15 2017-11-14 2018-03-29 2018-05-13 2018-04-25 Acquisition véhicules UC d Upgrading nvelope CG-003-F-CF / Acquisition vé Integration and Neighborhoo Single Stage - One E IBRD / 85880 A posteriori Demande de prix Open - National 400,000.00 0.00 Annulé 2017-07-05 2017-08-30 2018-02-26 hicules UC d Upgrading nvelope CG-DURQUAP-001-F-CF / Équ Integration and Neighborhoo Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 4,000.00 4,725.52 Achevé 2017-11-25 2018-01-11 2018-01-20 2018-04-05 2018-07-19 2018-06-23 ipement de bureau d Upgrading nvelope CG-DURQUAP-039-F-CF / Fou rniture de Bureau-Acquisition Project Management, Coordi Single Stage - One E des fournitures de bureau et IBRD / 85880 A posteriori Demande de prix Limited 30,000.00 29,659.39 Signé 2018-07-30 2018-07-28 2018-09-24 2018-08-24 2019-03-23 nation and Evaluation nvelope consommables informatiques (marché à bon de commande ou à prix unitaire) CG-DURQUAP-040-F-CF / Re prographie-Acquisition compl émentaire des matériels de r Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 40,000.00 31,343.26 Achevé 2018-07-30 2018-08-10 2018-09-24 2018-09-06 2019-03-23 2018-11-21 eprographies, d'informatique nation and Evaluation nvelope et des mobiliers de bureau p our l'Unité de Coordination D URQuaP CG-DURQUAP-041-F-CF / Tra iteur Brazzaville-Contractuali sation avec un service traiteu Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 10,000.00 8,651.50 Signé 2018-08-05 2018-12-20 2018-09-30 2019-02-19 2019-03-29 r dans le cadre de la mise en nation and Evaluation nvelope œuvre DURQuaP à Brazzavill e (marché à bon de comman de ou à prix unitaire CG-DURQUAP-043-F-ED / Tél écom Internet-Contractualisa Project Management, Coordi Passation de marc IBRD / 85880 A posteriori Direct 10,000.00 65,709.84 Signé 2018-07-24 2019-02-22 2018-07-29 2019-02-28 2018-09-02 2019-06-24 2019-03-01 tion avec un fournisseur de l'i nation and Evaluation hé de gré à gré nternet au bureau de l'UCP D URQuaP CG-DURQUAP-061-F-ED / Ser veur + Tablettes-Acquisition Project Management, Coordi Passation de marc de 30 tablettes et un serveur IBRD / 85880 A posteriori Direct 25,000.00 25,213.09 Achevé 2018-12-05 2019-02-28 2018-12-10 2019-02-28 2019-01-14 2019-03-27 2019-07-13 2019-07-09 nation and Evaluation hé de gré à gré pour stockage des donnees d 'enquetes et comptables du projet CG-DURQUAP-088-F-ED / Loc Integration and Neighborhoo Passation de marc ation Bureaux DURQuaP aupr IBRD / 85880 A posteriori Direct 70,000.00 76,916.34 Signé 2019-01-01 2019-01-28 2019-01-06 2019-02-26 2019-02-10 2019-01-18 2019-08-09 d Upgrading hé de gré à gré es de la societe C.T (propriet aire du Loyer) CG-DURQUAP-090-F-CF / Acq uisition du mobilier de burea u destiné au RAFC et à l’Audi Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 30,000.00 26,783.86 Achevé 2019-07-27 2019-07-12 2019-09-21 2019-08-22 2020-03-19 2019-09-19 teur Interne et le meuble de r nation and Evaluation nvelope angement des documents du service de la Passation des m archés CG-DURQUAP-091-F-CF / Acq uisition du matériel informati Project Management, Coordi Single Stage - One E que et de reprographie desti IBRD / 85880 A posteriori Demande de prix Limited 15,000.00 8,401.39 Achevé 2019-07-27 2019-07-12 2019-09-21 2019-08-22 2020-03-19 2019-09-02 nation and Evaluation nvelope né au RAFC, à l’Auditeur Inte rne et à l’Assistant en passati on des marchés CG-DURQUAP-042-F-CF / Tra iteur Pointe Noire-Contractua lisation avec un service traite Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-08-05 2018-09-30 2019-03-29 ur dans le cadre de la mise e nation and Evaluation nvelope n œuvre DURQuaP à Pointe N oire (marché à bon de comm ande ou à prix unitaire) CG-DURQUAP-045-F-ED / Pu blications-Contractualisation Project Management, Coordi Passation de marc avec des sociétés de publicat IBRD / 85880 A posteriori Direct 10,000.00 0.00 Annulé 2018-07-24 2018-07-29 2018-09-02 2019-03-01 nation and Evaluation hé de gré à gré ion des avis d'appel d'offres et des avis de manifestation d'intérêt au Congo CG-DURQUAP-044-F-ED / Car burant-Contractualisation av ec une société de livraison d Project Management, Coordi Passation de marc IBRD / 85880 A posteriori Direct 20,000.00 0.00 Annulé 2018-07-23 2019-02-22 2018-07-28 2019-02-28 2018-09-01 2019-02-28 u carburant pour les véhicule nation and Evaluation hé de gré à gré s DURQuaP (marché à bon de commande ou à prix unitaire ) CG-DURQUAP-123-F-CF / Acq uisition des mobiliers de bure au et matériel informatique d u personnel complémentaire Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 100,000.00 44,253.59 Signé 2020-08-05 2020-08-04 2020-09-30 2020-09-09 2021-03-29 de l'UCP/DURQuaP nation and Evaluation nvelope (Ingénieur junior en génie, sp écialiste en sauvegardes soci ales et assistant technique in ternational en passation des marchés) CG-DURQUAP-122-F-AON / F ourniture et installation des é quipements et logiciels pour l a mission de mise en place d' Development of Institutions Single Stage - One E un observatoire urbain, la ré IBRD / 85880 A posteriori Appel d'offres Open - National 800,000.00 583,456.60 Signé 2020-08-05 2020-12-02 2020-08-10 2020-12-07 2020-09-21 2021-03-31 2020-10-21 2021-08-03 2020-11-25 2021-08-12 2021-05-24 and Capacity nvelope alisation de l'adressage et l'actualisation de la base des données des i mpôts et des recettes munici pales dans les villes de BZV e t PN Page 3 CG-DURQUAP-021-CERC-F-C F / Campagne de désinfectio Project Management, Coordi Single Stage - One E n des locaux et de salle de c IBRD / 85880 A posteriori Demande de prix Limited 86,000.00 0.00 Annulé 2020-08-15 2020-10-10 2021-04-08 nation and Evaluation nvelope ours des Etablissements de l’ Université Marien NGOUABI. CG-DURQUAP-09-F-CF-2021 / Fourniture et installation du mobilier de bureau pour la m ise en place d’un observatoir Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 97,000.00 76,784.31 Signé 2021-10-20 2021-10-18 2021-12-15 2021-11-05 2022-06-13 e urbain, pour la réalisation d nation and Evaluation nvelope e l’adressage et Equipement du nouveau Coordonnateur e n mobilier de bureau et maté riel informatique. CG-DURQUAP-14-F-CF-2021 / Fourniture et pose des plaq Development of Institutions Single Stage - One E ues d'adressage dans les qua IBRD / 85880 A posteriori Demande de prix Limited 266,000.00 269,274.49 Signé 2022-02-05 2022-01-22 2022-04-02 2022-02-08 2022-09-29 and Capacity nvelope rtiers cibles des villes de Bra zzaville et de Pointe-Noire. CG-DURQUAP-04-F-CF-2022 / Fourniture du matériel de s ensibilisation communautaire Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 29,361.00 0.00 Achevé 2022-10-15 2022-10-25 2022-12-10 2023-06-08 et d'Assainissement et entret nation and Evaluation nvelope ien des infrastructures dédié s aux CGDC des villes de Bra zzaville et de Pointe-Noire. CG-DURQUAP-05-F-CF-ED-20 22 / EQUIPEMENTS NECESSAI RES POUR LE FONCTIONNEM ENT DES MARCHES DOMANIA UX DE TCHINIAMBI ET DE SO Integration and Neighborhoo Passation de marc En attente d' IBRD / 85880 A posteriori Direct - National 95,000.00 0.00 2022-12-28 2023-01-02 2023-02-06 2023-08-05 UKISSA PUIS DES CASIERS D d Upgrading hé de gré à gré exécution E RANGEMENT AUX PRESCOL AIRES ET SPLITS POUR LES E COLES PRIMAIRES SORBONN E A BRAZZAVILLE PUIS MOUN TOU MAVOUNGOU ET PAMBO U BENJAMIN. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-DURQUAP-094-SASC-DP / Surveillance et gardiennage des locaux de l’Unité de Coor Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 30,000.00 51,921.25 Signé 2019-10-22 2019-10-23 2019-12-17 2019-10-29 2020-06-14 dination du Projet de Dévelo nation and Evaluation nvelope ppement Urbain et de Restru cturation des Quartiers Préca ires (DURQuaP). CG-DURQUAP-110-SASC-CF / Conception infographique, im Project Management, Coordi Single Stage - One E IBRD / 85880 A posteriori Demande de prix Limited 10,000.00 45,373.42 Signé 2020-03-07 2020-07-24 2020-05-02 2020-08-25 2020-10-29 pression et diffusion du bulle nation and Evaluation nvelope tin d'information trimensuel du projet DURQuaP CG-DURQUAP-113-SASC-ED / Local centre d'appel-ED/Cont Integration and Neighborhoo Passation de marc ractualisation par entente dir IBRD / 85880 A posteriori Direct 16,000.00 15,781.06 Signé 2020-03-02 2020-03-13 2020-03-07 2020-03-19 2020-04-11 2020-03-19 2020-10-08 d Upgrading hé de gré à gré ecte avec la société CT pour l a location du local du centre d'appel du DURQuaP CG-DURQUAP-119-SASC-CF / Installation serveur/Recrute Project Management, Coordi Single Stage - One E ment d'un consultant pour le IBRD / 85880 A posteriori Demande de prix Limited 29,000.00 29,035.04 Signé 2020-03-15 2020-05-15 2020-05-10 2020-05-16 2020-11-06 nation and Evaluation nvelope câblage et l'installation du se rveur d’hébergement des do nnées du DURQuaP. CG-DURQUAP-118-SASC-DP / Entretien Bureaux/Recrutem Project Management, Coordi Single Stage - One E ent de deux (02) techniciens IBRD / 85880 A posteriori Demande de prix Limited 10,000.00 85,709.40 Signé 2020-03-21 2020-06-02 2020-05-16 2020-06-30 2020-11-12 nation and Evaluation nvelope de surface pour le nettoyage des bureaux du DURQuaP CG-DURQUAP-111-SASC-CF / Production des objets promot Project Management, Coordi Single Stage - One E ionnels (plaquettes institutio IBRD / 85880 A posteriori Demande de prix Limited 35,000.00 0.00 Annulé 2020-03-17 2020-05-12 2020-11-08 nation and Evaluation nvelope nnelles, kakemonos, teeshoir ts, casquettes, etc) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-023-SC-QC / Notice d'Im pact Environnemental et Soci Sélection fondée s Integration and Neighborhoo Open - Internationa al (NIES) pour la constructio IBRD / 85880 A posteriori ur les qualification 150,000.00 154,644.09 Achevé 2017-10-05 2017-10-26 2017-12-09 2018-01-08 2018-12-19 2018-02-12 2018-08-02 2018-08-11 d Upgrading l n des voiries urbaines par pa s des consultants vage à Brazzaville et Pointe- Noire. CG-014-SC-SFQC / Supervisi Sélection fondée s Integration and Neighborhoo Open - Internationa on travaux de voiries progra IBRD / 85880 A priori ur la qualité et le 1,710,000.00 0.00 Annulé 2017-10-23 2017-11-13 2017-12-27 2018-01-24 2018-02-23 2018-03-30 2018-05-04 2019-05-04 d Upgrading l mme prioritaire phase 2 coût CG-DURQUAP-013-BIS-SC-SF Sélection fondée s Integration and Neighborhoo Open - Internationa QC / Audit-Recrutement Audi IBRD / 85880 A priori ur la qualité et le 100,000.00 40,116.16 Signé 2017-08-01 2017-08-26 2017-10-24 2018-06-21 2017-11-21 2018-08-10 2017-12-21 2018-09-07 2018-01-25 2019-01-29 2018-03-01 2019-02-15 2019-03-01 d Upgrading l teur externe coût CG-DURQUAP-001-BIS-SC-Q C / Voiries-Etudes techniques Sélection fondée s Integration and Neighborhoo et DAO des travaux de voirie IBRD / 85880 A posteriori ur les qualification Open - National 250,000.00 285,419.14 Achevé 2017-08-03 2018-04-28 2017-08-14 2017-10-18 2017-11-17 2018-06-15 2017-12-22 2018-04-05 2018-06-20 2018-12-27 d Upgrading s et d'assainissement à Brazz s des consultants aville et à Pointe-Noire Phase 1 CG-DURQUAP-002-BIS-SC-Q Sélection fondée s C / NIES site érosif-Notice d'I Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 85,000.00 82,376.22 Achevé 2017-08-01 2019-02-26 2017-08-14 2017-09-28 2019-04-05 2017-10-28 2019-04-05 2017-12-02 2018-08-31 2018-05-31 2019-09-25 mpact Environnemental et S d Upgrading s des consultants ocial (NIES) pour le site érosif à Brazzaville Page 4 CG-002-SC-QC / Notices d'im pact environnemental et soci Sélection fondée s Integration and Neighborhoo Open - Internationa al des travaux de constructio IBRD / 85880 A posteriori ur les qualification 200,000.00 0.00 Annulé 2017-07-05 2017-08-01 2017-07-26 2017-08-12 2017-09-08 2017-10-08 2017-11-12 2018-05-11 d Upgrading l n des voiries urbaines, résea s des consultants ux eau et électricité et des o uvrages antiérosifs CG-001-SC-SFQC / Etudes te chniques des travaux phase1 Sélection fondée s Integration and Neighborhoo et DAO des travaux de constr IBRD / 85880 A posteriori ur la qualité et le Open - National 385,000.00 0.00 Annulé 2017-07-28 2017-08-03 2017-08-18 2017-08-12 2017-10-01 2017-10-29 2017-11-28 2018-01-02 2018-02-06 2019-02-06 d Upgrading uction des voiries urbaines et coût assainissement à Brazzaville et Pointe-Noire phase1 CG-DURQUAP-004-SC-QC / E tudes techniques et DAO des Sélection fondée s Integration and Neighborhoo travaux de construction des IBRD / 85880 A posteriori ur les qualification Open - National 300,000.00 0.00 Annulé 2017-12-20 2018-02-07 2018-01-10 2018-02-23 2018-03-25 2018-04-29 2018-10-26 d Upgrading voiries urbaines à Brazzaville s des consultants et Pointe-Noire phase 2 CG-005-SC-SFQC / Services Sélection fondée s Integration and Neighborhoo Open - Internationa de consultant pour la maîtris IBRD / 85880 A priori ur la qualité et le 1,754,000.00 1,150,940.02 Signé 2018-04-06 2018-05-18 2018-04-13 2018-07-25 2018-05-27 2018-09-20 2018-06-24 2018-07-24 2018-12-25 2018-08-28 2019-02-05 2018-10-02 2019-02-11 2019-10-02 d Upgrading l e d'œuvre sociale à Brazzavil coût le CG-DURQUAP-014-SC-SFQC / Sélection fondée s Maîtrise d'oeuvre-Services de Integration and Neighborhoo Open - Internationa IBRD / 85880 A priori ur la qualité et le 1,754,000.00 1,129,197.47 Signé 2018-04-06 2018-05-18 2018-04-13 2018-07-25 2018-05-27 2018-09-20 2018-06-24 2018-07-24 2018-12-25 2018-08-28 2019-02-05 2018-10-02 2019-02-11 2019-10-02 consultant pour la maîtrise d' d Upgrading l coût œuvre sociale Pointe-Noire CG-006-SC-SFQC / Supervisi Sélection fondée s Integration and Neighborhoo Open - Internationa on travaux de voiries progra IBRD / 85880 A priori ur la qualité et le 855,000.00 402,833.08 Signé 2018-04-09 2018-05-11 2018-04-16 2018-05-18 2018-05-30 2018-06-27 2018-07-27 2019-07-08 2018-08-31 2019-11-27 2018-10-05 2019-11-29 2019-10-05 d Upgrading l mme prioritaire phase 1 à Br coût azzaville CG-DURQUAP-034-SC-SFQC / Sélection fondée s Supervision travaux de voirie Integration and Neighborhoo Open - Internationa IBRD / 85880 A priori ur la qualité et le 855,000.00 403,431.62 Signé 2018-04-09 2018-04-23 2018-04-16 2018-05-18 2018-05-30 2018-06-27 2018-07-27 2019-07-08 2018-08-31 2019-11-27 2018-10-05 2019-11-29 2019-10-05 s programme prioritaire phas d Upgrading l coût e1 à Pointe Noire CG-DURQUAP-003-SC-QC / R Sélection fondée s éseaux BZV-Études techniqu Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 150,000.00 233,096.02 Signé 2018-05-28 2018-06-11 2018-06-18 2018-06-12 2018-08-01 2018-12-21 2018-08-31 2019-02-27 2018-10-05 2018-12-14 2019-04-03 es et DAO pour les réseaux e d Upgrading s des consultants au et électricité à Brazzaville CG-DURQUAP-030-SC-QC / Pl Sélection fondée s an Com-Recrutement d'un co Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 200,000.00 90,294.25 Achevé 2018-06-08 2018-06-15 2018-06-22 2018-07-29 2018-10-14 2018-08-28 2018-12-17 2018-10-02 2018-10-25 2019-03-31 2019-05-06 nsultant pour l'élaboration du d Upgrading s des consultants plan de communication du Pr ojet CG-DURQUAP-035-SC-QC / R Sélection fondée s éseaux PNR-Etudes techniqu Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 150,000.00 237,867.65 Signé 2018-05-28 2018-06-18 2018-06-12 2018-08-01 2019-02-27 2018-08-31 2019-02-27 2018-10-05 2018-12-14 2019-04-03 es et DAO pour les réseaux e d Upgrading s des consultants au et électricité à Pointe-Noir e CG-DURQUAP-028-SC-QC / P AR voiries BZV-Réalisation d' Sélection fondée s Integration and Neighborhoo un plan d'action de réinstalla IBRD / 85880 A posteriori ur les qualification Open - National 75,000.00 0.00 Annulé 2018-08-30 2018-08-24 2018-09-20 2018-11-03 2018-12-03 2019-01-07 2019-07-06 d Upgrading tion (PAR) des travaux de co s des consultants nstruction des voiries par pa vage à Brazzaville CG-DURQUAP-051-SC-QC / N IES SUKISSA-Notice d'Impact Sélection fondée s Project Management, Coordi environnemental et social po IBRD / 85880 A posteriori ur les qualification Open - National 125,000.00 107,757.50 Achevé 2018-12-10 2018-12-29 2018-12-31 2019-02-13 2019-02-22 2019-03-15 2019-03-15 2019-04-19 2019-03-19 2019-10-16 2020-05-30 nation and Evaluation ur la construction du marché s des consultants de SUKISSA à Brazzaville. CG-DURQUAP-052-SC-QC / E tudes marché de TCHINIAMBI -Recrutement d'un consultan Sélection fondée s Integration and Neighborhoo t pour la réalisation des étud IBRD / 85880 A posteriori ur les qualification Open - National 400,000.00 501,431.68 Signé 2018-12-10 2019-04-12 2018-12-31 2019-06-25 2019-02-13 2019-08-26 2019-03-15 2019-11-25 2019-04-19 2019-11-20 2019-10-16 d Upgrading es techniques, DAO et charg s des consultants é de la supervision des trava ux de rahabilitation du march é TCHINIAMBI. CG-DURQUAP-054-SC-QC / N IES Eau et Electricité - Recrut ement d'un consultant pour l Sélection fondée s a réalisation de la notice d'im Project Management, Coordi IBRD / 85880 A posteriori ur les qualification Open - National 200,000.00 164,617.02 Signé 2018-12-05 2019-10-09 2018-12-26 2019-10-29 2019-02-08 2020-05-17 2019-03-10 2020-05-18 2019-04-14 2020-03-26 2019-10-11 pact environnemental et soci nation and Evaluation s des consultants al (NIES) des réseaux eau et électricité à Brazzaville et à P ointe Noire dans les quartiers cibles du projet. CG-DURQUAP-056-SC-QC / E tudes et DAO ecoles-Recrute ment d'un consultant pour la Sélection fondée s réalisation des études techni Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 450,000.00 455,075.98 Signé 2018-12-13 2019-03-20 2018-12-20 2019-03-22 2019-02-02 2019-08-09 2019-03-04 2019-09-26 2019-04-08 2019-09-06 2019-10-05 ques, DAO et chargé de la su d Upgrading s des consultants pervision des travaux de réh abilitation des écoles MOUTO U MAVOUNGOU et PAMBOU B enjamin à Pointe Noire CG-DURQUAP-062-SC-SFQ / Diagnostic-Recrutement d'un consultant pour la réalisation de l'étude diagnostique instit Project Management, Coordi Sélection fondée s Open - Internationa IBRD / 85880 A priori 1,300,000.00 267,500.03 Signé 2018-12-06 2019-02-09 2018-12-14 2019-04-10 2019-01-27 2019-11-13 2019-02-24 2020-04-16 2019-03-26 2020-06-02 2019-04-25 2020-08-27 2019-05-30 2020-09-21 2020-05-29 utionnel du secteur urbain, s nation and Evaluation ur la qualité l outien institutionnel et renfor cement des capacités du Min istère de la Construction de l' Urbanisme et de l'Habitat CG-009-SC-SFQC / Élaboratio n des Plans de restructuratio Sélection fondée s Integration and Neighborhoo n de quartiers et programme IBRD / 85880 A priori ur la qualité et le Open - National 3,000,000.00 0.00 Annulé 2018-04-10 2018-04-17 2018-05-31 2018-06-28 2018-07-28 2018-09-01 2018-10-06 2019-10-06 d Upgrading s prioritaires de Brazzaville e coût t Pointe-Noire phase 1 CG-DURQUAP-015BIS-SC-SF Q / Plans-Recrutement d'un c onsultant pour la réalisation des Plans Directeurs d'Urbani Project Management, Coordi Sélection fondée s Open - Internationa sme (PDU), des Plans d'Urba IBRD / 85880 A priori 6,800,000.00 2,479,506.89 Signé 2018-12-07 2018-12-19 2018-12-12 2018-12-25 2019-01-25 2019-05-10 2019-02-22 2019-06-28 2019-03-24 2019-07-15 2019-04-23 2019-11-26 2019-05-28 2019-12-04 2020-05-27 nation and Evaluation ur la qualité l nisme de Detail (PUD) et des Plans de Restructuration des Quartiers (PRQ) et programm es d'investissement de Brazz aville et de Pointe Noire. Page 5 CG-DURQUAP-022BIS-SC-SF Q / Adressage-Recrutement d 'un consultant pour la realisa tion de l'adressage et de l'act Project Management, Coordi Sélection fondée s Open - Internationa IBRD / 85880 A priori 2,000,000.00 0.00 Annulé 2018-12-09 2019-01-20 2018-12-14 2019-01-24 2019-01-27 2019-05-10 2019-02-24 2019-06-28 2019-03-26 2019-12-01 2019-04-25 2019-05-30 2020-05-29 ualisation de la base de donn nation and Evaluation ur la qualité l ees relatives aux impots mun icipaux, du recouvrement de s recettes et de l'observatoir e urbain à Brazzaville et à Poi nte Noire  CG-016-SC-SFQC / Assistanc Sélection fondée s Integration and Neighborhoo e technique aux municipalité IBRD / 85880 A posteriori ur la qualité et le Open - National 480,000.00 0.00 Annulé 2018-05-23 2018-05-30 2018-07-13 2018-08-10 2018-09-09 2018-10-14 2018-11-18 2019-11-18 d Upgrading s de Brazzaville et Pointe-Noi coût re CG-020-SC-SFQC / Legislatio n et reglementation-Recrute Sélection fondée s ment d'un consultant pour l' Project Management, Coordi Open - Internationa IBRD / 85880 A priori ur la qualité et le 500,000.00 437,267.52 Signé 2019-04-30 2019-02-08 2019-05-07 2019-02-11 2019-06-20 2019-11-04 2019-07-18 2020-05-25 2019-08-17 2020-08-31 2019-09-21 2020-12-09 2019-10-26 2020-12-31 2020-10-25 application de la legislation e nation and Evaluation l coût t de la reglementation actuali sees en matière d'urbanisme et d'habitat CG-DURQUAP-027-SC-QC / O utils de Sauvegarde-Etudes p Sélection fondée s Integration and Neighborhoo our la réalisation des outils d IBRD / 85880 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2018-05-15 2018-06-05 2018-07-19 2018-08-18 2018-09-22 2019-03-21 d Upgrading e sauvegarde sociale du site s des consultants en proie aux érosions CG-DURQUAP-029-SC-QC / O utils de sauvegarde Eau et El Sélection fondée s ectricité-Etudes pour la réalis Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 200,000.00 0.00 Annulé 2018-05-31 2018-06-21 2018-08-04 2018-09-03 2018-10-08 2019-04-06 ation des outils de sauvegard d Upgrading s des consultants e sociale relatives aux travau x de réseaux eau et électricit é à Brazzaville et Pointe-Noir e CG-DURQUAP-067-SC-QC / S upervision Marché Soukissa- Sélection fondée s Recrutement d'un consultant Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 250,000.00 222,532.57 Signé 2019-03-22 2019-10-11 2019-03-29 2019-10-29 2019-05-12 2020-04-24 2019-06-11 2020-05-18 2019-07-16 2020-05-07 2020-01-12 charge de la supervision des d Upgrading s des consultants travaux de réinstallation du marché de SOUKISSA à Brazz aville CG-DURQUAP-007BIS-SC-QC / Actualisation Etudes erosio Sélection fondée s n-Recrutement d'un consulta Integration and Neighborhoo Open - Internationa IBRD / 85880 A posteriori ur les qualification 300,000.00 300,428.73 Signé 2018-03-23 2019-07-29 2018-03-30 2018-05-13 2019-08-12 2018-06-12 2019-08-14 2018-07-17 2019-06-28 2019-01-13 nt chargé de l'actualisation d d Upgrading l s des consultants es études de la zone en proie aux érosions à Brazzaville CG-DURQUAP-007-SC-QC / C Sélection fondée s ontrôle Érosion-Supervision t Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 250,000.00 0.00 Annulé 2018-03-16 2018-03-26 2018-03-22 2018-03-30 2018-05-05 2018-06-04 2018-07-09 2019-01-05 ravaux de traitement de la z d Upgrading s des consultants one en proie aux érosions à Brazzaville CG-DURQUAP-004-BIS-SC-Q C / Etudes stade TATA LOBO KO: Recrutement d'un consul Sélection fondée s Integration and Neighborhoo tant pour la realisation des et IBRD / 85880 A posteriori ur les qualification Open - National 200,000.00 302,438.12 Signé 2018-12-27 2018-12-21 2019-01-03 2019-01-04 2019-02-16 2019-05-24 2019-03-18 2019-05-24 2019-04-22 2019-05-21 2019-10-19 d Upgrading udes techniques et DAO pour s des consultants la rehabilitation du stade TAT A LOBOKO a Pointe-Noire au quartier MBOUKOU CG-022-SC-SFQC / Services Sélection fondée s de consultant pour la réalisat Integration and Neighborhoo Open - Internationa IBRD / 85880 A priori ur la qualité et le 800,000.00 0.00 Annulé 2018-07-24 2018-10-25 2018-07-31 2018-09-13 2018-10-11 2018-11-10 2018-12-15 2019-01-19 2020-01-19 ion de l'adressage à Brazzavi d Upgrading l coût lle et Pointe-Noire CG-015-SC-SFQC / Plans dire Sélection fondée s Integration and Neighborhoo Open - Internationa cteurs d'urbanisme détaillés IBRD / 85880 A priori ur la qualité et le 800,000.00 0.00 Annulé 2018-08-24 2018-10-25 2018-08-31 2018-10-14 2018-11-11 2018-12-11 2019-01-15 2019-02-19 2020-02-19 d Upgrading l de Brazzaville et Pointe-Noire coût CG-013-SC-SFQC / Recrutem Integration and Neighborhoo Sélection fondée s IBRD / 85880 A priori Open - National 100,000.00 0.00 Annulé 2017-06-30 2017-08-03 2017-07-21 2018-08-15 2017-09-03 2017-10-01 2017-10-31 2017-12-05 2018-01-09 2019-01-09 ent Auditeur externe d Upgrading ur la qualité et le coût CG-DURQUAP-101-SC-QC / R ECRUTEMENT D’UN CONSULT ANT POUR LA MISE EN PLACE Sélection fondée s Project Management, Coordi D’UN CENTRE D’APPEL AFFEC IBRD / 85880 A posteriori ur les qualification Open - National 300,000.00 228,012.82 Achevé 2019-07-25 2019-06-27 2019-08-15 2019-09-06 2019-09-28 2019-11-18 2019-10-28 2020-02-13 2019-12-02 2020-01-27 2020-05-30 nation and Evaluation TE AU TRAITEMENT DES PLAI s des consultants NTES ENREGISTREES VIA LE NUMERO VERT, POUR LE CO MPTE DU PROJET DURQUAP CG-DURQUAP-097-SC-SFQC / Ecoles SORBONNE-Recrutem ent d'un consultant pour la ré alisation des études techniqu Sélection fondée s Integration and Neighborhoo es et DAO et le contrôle-supe IBRD / 85880 A posteriori ur la qualité et le Open - National 350,000.00 161,280.90 Signé 2019-11-15 2019-11-03 2019-12-06 2019-11-22 2020-01-19 2020-06-06 2020-02-16 2020-06-30 2020-03-17 2020-10-25 2020-04-21 2020-10-25 2020-05-26 2020-10-19 2021-05-26 d Upgrading rvision des travaux de réhabi coût litation des écoles primaires SORBONNE et MALONGA EC OUTE à Mounkoundzi NGOUA KA à Brazzaville. CG-DURQUAP-102-SC-QC / C omplexe sportif Soukissa/Rec rutement d'un consultant po Sélection fondée s Integration and Neighborhoo ur les études techniques, le IBRD / 85880 A posteriori ur les qualification Open - National 300,000.00 361,680.92 Signé 2020-02-13 2020-09-25 2020-03-05 2020-10-12 2020-04-18 2021-02-23 2020-05-18 2021-02-24 2020-06-22 2021-02-01 2020-12-19 d Upgrading Contrôle et la supervision de s des consultants s travaux de réhabilitation du complexe sportif Soukissa B razzaville. CG-DURQUAP-060-SC-SFQ / Reorganisation volet gestion financiere-Recrutement d'un Project Management, Coordi Sélection fondée s Open - Internationa consultant pour la réorganis IBRD / 85880 A priori 1,000,000.00 0.00 Annulé 2018-12-07 2018-12-11 2019-01-24 2019-02-21 2019-03-23 2019-04-22 2019-05-27 2020-05-26 nation and Evaluation ur la qualité l ation fonctionnelle des deux administrations municipales et Volet Gestion financière d ans les deux municipalités CG-021-SC-SFQC / Assistanc e MCUH et CGMP-Recruteme Sélection fondée s nt d'un consultant pour une Project Management, Coordi Open - Internationa IBRD / 85880 A priori ur la qualité et le 900,000.00 0.00 Annulé 2018-12-18 2018-12-24 2019-02-06 2019-03-06 2019-04-05 2019-05-10 2019-06-14 2020-06-13 assistante technique et de re nation and Evaluation l coût nforcement des capacités du MCUH et de la CGMP de la D GGT Page 6 CG-DURQUAP-009BIS-SC-SF QC / Logiciel Simba-Recrute ment d'un consultant pour la Sélection fondée s Project Management, Coordi Open - Internationa realisation du volet gestion fi IBRD / 85880 A priori ur la qualité et le 1,200,000.00 0.00 Annulé 2018-12-21 2018-12-28 2019-02-10 2019-03-10 2019-04-09 2019-05-14 2019-06-18 2020-06-17 nation and Evaluation l nanciere et de l'application d coût u logiciel Simba dans les deu x municipalités de Brazzavill e et de Pointe Noire  CG-DURQUAP-017BIS-SC-QC / Formation Mairies-Recrute Sélection fondée s ment d'un consultant pour la Project Management, Coordi IBRD / 85880 A posteriori ur les qualification Open - National 300,000.00 0.00 Annulé 2019-01-15 2019-01-19 2019-03-04 2019-04-03 2019-05-08 2019-11-04 formation des agents munici nation and Evaluation s des consultants paux et des élus des municip alités de Brazzaville et de Poi nte Noire CG-DURQUAP-108-SC-QC / N IES voiries 2/Actualisation de s études des Notice d'Impact Sélection fondée s Integration and Neighborhoo Environnementale et Sociale IBRD / 85880 A posteriori ur les qualification Open - National 120,000.00 122,219.44 Signé 2020-03-05 2020-03-13 2020-03-26 2020-05-29 2020-05-09 2020-08-11 2020-06-08 2020-10-28 2020-07-13 2020-10-19 2021-01-09 d Upgrading (NIES ) des voiries (phase 1) s des consultants pour la construction des voiri es phase 2 à Brazzaville et P ointe-Noire CG-DURQUAP-022BIS1-SC-S FQ / Adressage-Recrutement d'un consultant pour la realis ation de l'adressage et de l'a Development of Institutions Sélection fondée s Open - Internationa IBRD / 85880 A priori 2,000,000.00 2,224,895.98 Signé 2020-03-26 2020-03-11 2020-03-31 2020-05-14 2020-03-11 2020-06-11 2020-03-11 2020-07-11 2020-03-11 2020-08-10 2020-05-25 2020-09-14 2020-06-09 2021-09-14 ctualisation de la base de do and Capacity ur la qualité l nnees relatives aux impots m unicipaux, du recouvrement des recettes et de l'observat oire urbain à Brazzaville et à Pointe Noire CG-DURQUAP-027BIS-SC-SF QC / Recrutement d'un consu ltant pour la mission de gesti Sélection fondée s Development of Institutions Open - Internationa on du patrimoine urbain et d IBRD / 85880 A priori ur la qualité et le 2,200,000.00 0.00 Annulé 2020-03-14 2020-04-04 2020-05-18 2020-06-15 2020-07-15 2020-08-19 2020-09-23 2021-09-23 and Capacity l e l’assistance technique et coût amélioration de la gestion de l’infrastructure commerciale des municipalités CG-DURQUAP-016 BIS 1-SC- SFQC / Audit des municipalité Sélection fondée s Development of Institutions s-Audits urbain, organisation IBRD / 85880 A priori ur la qualité et le Open 1,400,000.00 472,805.28 Signé 2020-03-26 2020-06-19 2020-04-16 2020-06-24 2020-05-30 2021-07-27 2020-06-27 2021-10-23 2020-07-27 2022-01-03 2020-08-31 2022-08-11 2020-10-05 2022-08-29 2021-10-05 and Capacity nel et financier des municipal coût ités de Brazzaville et de Point e-Noire. CG-DURQUAP-102 BIS-SC-SF QC / Réalisation de trois (03) NIES relatives aux travaux de réhabilitation des écoles Mal Sélection fondée s Integration and Neighborhoo onga Ecoute et la Sorbonne à IBRD / 85880 A posteriori ur la qualité et le Open - National 275,000.00 297,085.52 Signé 2020-05-15 2020-04-25 2020-06-05 2020-05-20 2020-07-19 2021-02-03 2020-08-16 2021-02-03 2020-09-15 2021-02-04 2020-10-20 2021-02-04 2020-11-24 2020-12-21 2021-11-24 d Upgrading Moukoundzi Ngouaka ainsi q coût ue du centre de sante intégr é à Soukissa, et de constructi on du complexe sportif de So ukissa à Brazzaville. CG-DURQUAP-068-SC-QC / S upervision marché Tchiniamb Sélection fondée s i-Recrutement d'un consultan Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 250,000.00 0.00 Annulé 2019-05-28 2019-06-04 2019-07-18 2019-08-17 2019-09-21 2020-03-19 t charge de la supervision de d Upgrading s des consultants s travaux de reinstallation d u marché TCHINIAMBI a Poin te Noire CG-DURQUAP-099-SC-QC / C SI Soukissa/Recrutement d'u Sélection fondée s n consultant pour les études Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 300,000.00 0.00 Annulé 2020-02-10 2020-03-13 2020-03-02 2020-03-27 2020-04-15 2020-05-15 2020-06-19 2020-12-16 techniques, le Contrôle et la d Upgrading s des consultants supervision des travaux de r éhabilitation du CSI Soukissa Brazzaville. CG-DURQUAP-016BIS-SC-SF Q / Réorganisation fonctionn elle-Recrutement d'un consul tant pour la réalisation de la Project Management, Coordi Sélection fondée s Open - Internationa réorganisation fonctionnelle IBRD / 85880 A priori 1,470,000.00 0.00 Annulé 2018-12-09 2018-12-14 2019-01-27 2019-02-24 2019-03-26 2019-04-25 2019-05-30 2020-05-29 nation and Evaluation ur la qualité l de l'assistance technique aux municipalités et au renforce ment des capacités en foncti on de la demande des munici palités de BZV et de PNR CG-DURQUAP-121-SC-QC / H IMO-Renforcement des capac ités des Entreprises locales, Sélection fondée s Development of Institutions Open - Internationa ONG et Associations en tech IBRD / 85880 A posteriori ur les qualification 300,000.00 325,747.22 Signé 2020-07-28 2020-05-11 2020-08-18 2020-06-15 2020-10-01 2021-02-05 2020-10-31 2021-02-05 2020-12-05 2020-12-30 2021-06-03 and Capacity l niques HIMO pour la réhabilit s des consultants ation des infrastructures des quartiers cibles à Brazzaville et à Pointe-Noire. CG-DURQUAP-065-SC-SFQC / Supervision erosion-Recrute Sélection fondée s ment d'un consultant chargé Integration and Neighborhoo Open - Internationa IBRD / 85880 A priori ur la qualité et le 500,000.00 0.00 Annulé 2018-12-06 2018-12-13 2019-01-26 2019-02-23 2019-03-25 2019-04-29 2019-06-03 2020-06-02 du contrôle et de la supervi d Upgrading l coût sion travaux de traitement d e la zone en proie aux érosio ns à Brazzaville CG-DURQUAP-124-SC-SFQC / Recrutement d'un cabinet d' Sélection fondée s Project Management, Coordi Open - Internationa audit financier des comptes c IBRD / 85880 A posteriori ur la qualité et le 100,000.00 24,258.35 Signé 2020-08-20 2020-11-10 2020-09-10 2020-12-02 2020-10-24 2021-04-01 2020-11-21 2021-04-22 2020-12-21 2021-06-01 2021-01-25 2021-06-01 2021-03-01 2021-06-17 2022-03-01 nation and Evaluation l los au 31 décembre 2020 et coût des comptes de clôture du pr ojet DURQuaP CG - DURQUAP-004-CERC -S C / Enquêtes socio-économiq Sélection fondée s Development of Institutions ues des zones à haut risque IBRD / 85880 A posteriori ur les qualification Open - National 72,500.00 0.00 Annulé 2020-08-17 2020-08-31 2020-09-21 2020-09-28 2020-10-12 2021-05-10 and Capacity de contamination à la COVID- s des consultants 19 à Brazzaville et à Pointe N oire CG-DURQUAP-011-CERC-SC / Mission de realisation des ét udes des travaux d’assainiss ement du Marché Total de Br Sélection fondée s Development of Institutions azzaville, IBRD / 85880 A posteriori ur les qualification Open - National 50,000.00 0.00 Annulé 2020-08-28 2020-09-11 2020-10-02 2020-10-09 2020-10-23 2021-04-21 and Capacity curage et de faucardad des ri s des consultants vières LOUKA, MALADIE DU S OMMEIL' au quartier MOUKO UNDZI-NGOUAKA curage et de faucardage du cours d’ea u au quartier SOUKISSA Page 7 CG-DURQUAP-104-SC-QC / F Sélection fondée s ormation du personnel d’entr Development of Institutions IBRD / 85880 A posteriori ur les qualification Open - National 200,000.00 0.00 Annulé 2020-03-18 2020-04-08 2020-05-22 2020-06-21 2020-07-26 2021-01-22 eprises privées et des cabine and Capacity s des consultants ts de consultants CG-DURQUAP-066-SC-SFQC / Supervision Stade-Recrutem Sélection fondée s ent d'un consultant chargé d Integration and Neighborhoo IBRD / 85880 A posteriori ur la qualité et le Open - National 300,000.00 0.00 Annulé 2020-03-25 2020-04-15 2020-05-29 2020-06-26 2020-07-26 2020-08-30 2020-10-04 2021-10-04 e la supervision des travaux d Upgrading coût de réhabilitation du stade TA TA LOBOKO à Pointe Noire au quartier MBOUKOU CG-DURQUAP-064-SC-QC / S upervision travaux Eau et Ele Sélection fondée s c-Recrutement d'un consulta Integration and Neighborhoo Open - Internationa IBRD / 85880 A posteriori ur les qualification 250,000.00 0.00 Annulé 2019-05-13 2020-05-19 2019-05-27 2020-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 nt chargé de la supervision d d Upgrading l s des consultants es travaux de réseaux eau et électricité à Brazzaville et Poi nte-Noire CG-008-SC-QC / Législation Sélection fondée s Nationale-Intégration des mé Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 200,000.00 0.00 Annulé 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 sures de sauvegarde et socia d Upgrading s des consultants les dans la législation Nation ale CG-DURQUAP-057-SC-QC / S upervision stade TATA LOBO Sélection fondée s KO-Recrutement d'un consult Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 250,000.00 0.00 Annulé 2019-01-01 2019-12-31 2019-01-05 2020-01-03 2019-02-18 2019-03-20 2019-04-24 2019-10-21 ant chargé de la supervision d Upgrading s des consultants des travaux de réhabilitation du stade TATA LOBOKO à Poi nte Noire au quartier MBOUK OU CG-DURQUAP-03-SC-SFQC-2 Sélection fondée s 021 / Recrutement d'un cons Project Management, Coordi IBRD / 85880 A posteriori ur la qualité et le Open - National 50,000.00 12,137.07 Signé 2021-09-15 2021-09-21 2021-10-06 2021-10-05 2021-11-19 2021-12-01 2021-12-17 2022-01-25 2022-01-16 2022-03-21 2022-02-20 2022-04-06 2022-03-27 2022-04-07 2023-03-27 ultant pour réaliser l'audit int nation and Evaluation coût erne du projet DURQuaP. CG-DURQUAP-05-SC-QC-202 1 / Contrôle et supervision de s travaux de l'extension du p Sélection fondée s avage des voiries dans les qu Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 70,000.00 278,214.19 Signé 2021-09-28 2021-08-24 2021-10-19 2021-12-02 2022-02-11 2022-01-01 2022-02-11 2022-02-05 2021-11-25 2022-08-04 artiers MBOUKOU et TCHINIA d Upgrading s des consultants MBI 1 à Pointe-Noire & Renfo rcement de la sensibilisation de la population bénéficiaire du projet sur la pandémie du COVID-19. CG-DURQUAP-06-SC-QC-202 1 / Contrôle et supervision de s travaux de l'extension de p avage des voiries dans les qu Sélection fondée s Integration and Neighborhoo artiers MOUKOUNDZI NGOUA IBRD / 85880 A posteriori ur les qualification Open - National 70,000.00 259,587.82 Signé 2021-09-27 2021-08-24 2021-10-18 2021-12-01 2021-09-23 2021-12-31 2022-01-12 2022-02-04 2021-11-17 2022-08-03 d Upgrading KA et SUKISSA à Brazzaville s des consultants & Renforcement de la sensibi lisation de la population béné ficiaire du projet sur la pandé mie du COVID-19. CG-DURQUAP-057-SC-QC-20 21 / CONTRÔLE ET SURVEILL Sélection fondée s ANCE DES TRAVAUX DE RÉH Integration and Neighborhoo IBRD / 85880 A posteriori ur les qualification Open - National 300,000.00 0.00 Annulé 2021-06-28 2021-06-18 2021-06-28 2021-08-11 2021-09-10 2021-10-15 2022-04-13 ABILITATION DU STADE « TA d Upgrading s des consultants TA LOBOKO » DANS LE QUAR TIER MBOUKOU À POINTE-NO IRE. CG-DURQUAP-099-SC-QC-2 / CSI Soukissa/Recrutement d' un consultant pour les étude Sélection fondée s Integration and Neighborhoo s techniques, le Contrôle et l IBRD / 85880 A posteriori ur les qualification Open - National 300,000.00 0.00 Annulé 2021-03-25 2021-03-26 2021-04-15 2021-05-29 2021-06-28 2021-08-02 2022-01-29 d Upgrading a supervision des travaux de s des consultants réhabilitation du CSI Soukiss a (Arrondissement 5 : Ouenz é) à Brazzaville. CG-DURQUAP-007-CERC-SC / Mission de realisation du PGE S des travaux de : • assainissement du March Sélection fondée s é Total de Brazzaville ( curag Development of Institutions IBRD / 85880 A posteriori ur les qualification Open - National 120,000.00 0.00 Annulé 2020-08-14 2020-11-18 2020-08-28 2020-09-18 2020-09-25 2020-10-09 2020-12-08 e du réseau d'assainissemen and Capacity s des consultants t, nettoyage des sites de dép ôts sauvages d'ordures, trait ement des terre-pleins et aut res points noirs) • curage et de fauc CG - DURQUAP - 003 - CERC - SC / Etude sur la résilience sanitaire en vue d’identifier e t géolocaliser (cartographier) Sélection fondée s Development of Institutions les zones à forte contaminati IBRD / 85880 A posteriori ur les qualification Open - National 172,500.00 0.00 Annulé 2020-11-20 2020-10-24 2020-12-04 2020-12-25 2021-01-01 2021-01-15 2021-08-13 and Capacity on à la COVID-19 à et enquê s des consultants tes socio-économiques des z ones à haut risque de conta mination à la COVID-19 à Bra zzaville et à Pointe Noire. CG-DURQUAP-053-SC-QC / N IES marche TCHINIAMBI-Notic Sélection fondée s Project Management, Coordi e d'Impact Environnemental IBRD / 85880 A posteriori ur les qualification Open - National 120,000.00 0.00 Annulé 2018-12-10 2019-12-06 2018-12-31 2019-02-13 2019-03-15 2019-04-19 2019-10-16 nation and Evaluation et Social (NIES) pour la const s des consultants ruction du marché de TCHINI AMBI à Pointe-Noire. CG-DURQUAP-059-SC-QC / N IES stade TATA LOBOKO- Rec rutement d'un consultant po Sélection fondée s Project Management, Coordi ur la réalisation de la notice IBRD / 85880 A posteriori ur les qualification Open - National 160,000.00 0.00 Annulé 2018-12-18 2019-12-06 2018-12-23 2019-02-05 2019-03-07 2019-04-11 2019-10-08 nation and Evaluation d'impact environnemental et s des consultants social (NIES) du stade TATA LOBOKO à Pointe Noire au qu artier MBOUKOU. CG-DURQUAP-058-SC-QC / N IES ecoles-Recrutement d'un consultant pour la réalisation Sélection fondée s Project Management, Coordi de la notice d'impact environ IBRD / 85880 A posteriori ur les qualification Open - National 200,000.00 0.00 Annulé 2018-12-13 2019-12-06 2018-12-20 2019-02-02 2019-03-04 2019-04-08 2019-10-05 nation and Evaluation nemental et social (NIES) de s des consultants s écoles MOUTOU et de l'éco le PAMBOU Benjamin à Point e Noire à Pointe Noire Page 8 CG-DURQUAP-017 BIS1-SC-S FQC / Formation Elus locaux- Recrutement d'un consultant Sélection fondée s Development of Institutions Open - Internationa pour la formation des agents IBRD / 85880 A priori ur la qualité et le 1,000,000.00 0.00 Annulé 2020-02-27 2020-03-19 2020-05-02 2020-05-30 2020-06-29 2020-08-03 2020-09-07 2021-09-07 and Capacity l municipaux et des élus locau coût x et renforcement des capac ités en fonction de la deman de INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-010-SC-CI / Recrutement SPM-du personnel compléme Integration and Neighborhoo IBRD / 85880 A priori Individuel Open 150,000.00 48,022.31 Achevé 2017-10-02 2017-11-07 2017-11-20 2018-01-23 2017-12-11 2018-03-23 2018-01-15 2018-04-27 2018-07-14 2019-04-26 ntaire de l'Unité de Coordinat d Upgrading ion-Spécialiste en passation des marchés CG-012-SC-CI / Recrutement Integration and Neighborhoo du personnel complémentair IBRD / 85880 A priori Individuel Open 65,000.00 0.00 Annulé 2017-06-30 2017-08-18 2017-09-08 2017-10-13 2018-04-11 d Upgrading e de l'Unité de Coordination- Comptable CG-DURQUAP-018-BIS-SC-CI / Appui technique-Recruteme Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Direct 65,000.00 61,932.50 Signé 2017-01-02 2018-02-07 2017-07-12 2017-08-03 2018-06-27 2017-09-07 2017-08-17 2018-03-06 nt de l'Expert en appui tech d Upgrading nique à la Cellule CG-DURQUAP-024-SC-CI / As sistante-Recrutement du per Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Open 47,900.00 12,770.93 Achevé 2017-03-14 2017-05-19 2017-07-18 2018-06-27 2017-09-25 2018-02-07 2018-01-03 2019-02-06 sonnel complémentaire de l' d Upgrading Unité de Coordination - Assist ante CG-DURQUAP-020-SC-CI / Co mmunication-Recrutement d Integration and Neighborhoo u personnel complémentaire IBRD / 85880 A posteriori Individuel Open 171,500.00 45,762.49 Achevé 2017-03-14 2017-05-19 2017-07-18 2018-06-27 2017-09-25 2018-02-07 2018-01-03 2019-02-06 d Upgrading de l'Unité de Coordination - S pécialiste en Communication CG-DURQUAP-022-SC-CI / Su ivi-Eval-Recrutement du pers Integration and Neighborhoo onnel complémentaire de l'U IBRD / 85880 A posteriori Individuel Open 171,500.00 45,900.26 Achevé 2017-03-14 2017-05-19 2017-07-18 2018-06-27 2017-09-25 2018-02-07 2018-01-03 2019-02-06 d Upgrading nité de Coordination - Spécial iste en Suivi-Évaluation CG-DURQUAP-021-SC-CI / Dé veloppement local-Recrutem Integration and Neighborhoo ent du personnel complémen IBRD / 85880 A posteriori Individuel Open 143,600.00 38,428.13 Achevé 2017-03-14 2017-05-19 2017-07-18 2018-06-27 2017-09-25 2018-02-07 2018-01-03 2019-02-06 d Upgrading taire de l'Unité de Coordinati on - Spécialiste en en Dével oppement local CG-DURQUAP-023-SC-CI / Mi ssion Tech.-Recrutement du Integration and Neighborhoo personnel complémentaire d IBRD / 85880 A posteriori Individuel Open 143,600.00 38,312.78 Achevé 2017-03-14 2017-05-19 2017-07-18 2018-06-27 2017-09-25 2018-02-07 2018-01-03 2019-02-06 d Upgrading e l'Unité de Coordination - Ch argé de mission technique CG-DURQUAP-025-SC-CI / Re Development of Institutions IBRD / 85880 A posteriori Individuel Direct 200,000.00 0.00 Annulé 2018-02-04 2018-02-07 2018-02-14 2018-03-07 2018-04-11 2018-10-08 crutement du Coordonnateur and Capacity du Projet CG-DURQUAP-025-BIS-SC-CI Sélection de cons Integration and Neighborhoo / Recrutement du Coordonna IBRD / 85880 A priori ultants par entent Direct 220,000.00 54,383.10 Achevé 2018-03-21 2018-03-28 2018-03-31 2018-06-04 2018-05-09 2018-12-01 2019-05-08 d Upgrading teur du Projet e directe CG-018-SC-CI / Recrutement Integration and Neighborhoo de l'Expert en appui techniqu IBRD / 85880 A priori Individuel Direct 65,000.00 0.00 Annulé 2017-06-30 2017-07-10 2017-07-31 2017-09-04 2018-03-03 d Upgrading e à la Cellule CG-011-SC-CI / Recrutement du personnel complémentair Integration and Neighborhoo IBRD / 85880 A priori Individuel Open 100,000.00 0.00 Annulé 2017-06-30 2017-08-18 2017-09-08 2017-10-13 2018-04-11 e de l'Unité de Coordination- d Upgrading Spécialiste en sauvegarde CG-DURQUAP-031-SC-CI / Re Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Open 27,000.00 6,438.46 Signé 2018-03-30 2018-03-26 2018-05-11 2018-07-21 2018-06-01 2018-08-01 2018-07-06 2018-07-07 2019-01-02 crutement - Chauffeur 1 d Upgrading CG-DURQUAP-032-SC-CI / Re Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Open 27,000.00 6,413.76 Signé 2018-04-06 2018-03-26 2018-05-18 2018-08-01 2018-06-08 2018-08-01 2018-07-13 2018-07-07 2019-01-09 crutement-Chauffeur 2 d Upgrading CG-DURQUAP-033-SC-CI / Re Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Open 27,000.00 6,355.30 Signé 2018-04-06 2018-03-26 2018-05-18 2018-08-01 2018-06-08 2018-08-01 2018-07-13 2018-07-07 2019-01-09 crutement-Chauffeur 3 d Upgrading CG-DURQUAP-026-SC-CI / Re Development of Institutions crutement d'un Assistant en IBRD / 85880 A posteriori Individuel Direct 112,000.00 31,783.54 Achevé 2018-03-29 2018-04-28 2018-04-07 2018-04-28 2018-05-11 2018-06-02 2018-05-14 2018-11-29 2019-05-13 and Capacity passation des marchés CG-019-SC-CI / Evaluation d Integration and Neighborhoo IBRD / 85880 A priori Individuel Open 200,000.00 87,949.63 Achevé 2018-06-08 2018-06-07 2018-07-20 2018-09-17 2018-08-10 2018-11-02 2018-09-14 2018-11-02 2019-03-13 2019-05-21 e base du projet d Upgrading CG-DURQUAP-037-SC-CI / PA R SUKISSA-Recrutement d'un consultant individuel chargé Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Open 60,000.00 78,986.00 Achevé 2018-08-16 2018-08-24 2018-09-27 2018-10-23 2018-10-18 2018-12-14 2018-11-22 2018-11-21 2019-05-21 2019-05-27 de la préparation du plan d'a d Upgrading ction de réinstallation (PAR) du marché SUKISSA à BRAZZ AVILLE. CG-DURQUAP-049-SC-CI / St agiaire 2- Recrutement d'un Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Limited 2,000.00 780.73 Achevé 2018-06-10 2018-06-12 2018-07-03 2018-12-04 2018-08-07 2018-09-11 2019-02-03 2018-12-12 stagiaire en Sauvegardes en d Upgrading vironnementales et sociales CG-DURQUAP-048 BIS-SC-CI / Stagiaire 1- Recrutement d' Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Limited 2,000.00 780.73 Achevé 2018-06-10 2018-06-12 2018-07-03 2018-12-04 2018-08-07 2018-09-11 2019-02-03 2018-12-12 un stagiaire en Sauvegardes d Upgrading environnementales et sociale s Page 9 CG-DURQUAP-028-BIS 1-SC- CI / PAR Voiries-Recrutement d'un consultant individuel ch Project Management, Coordi argé de la réalisation du Plan IBRD / 85880 A posteriori Individuel Limited 150,000.00 212,734.65 Achevé 2018-09-04 2018-12-14 2018-09-09 2018-12-04 2018-09-30 2018-12-15 2018-11-04 2018-11-27 2019-05-03 2019-10-02 nation and Evaluation d'Action des Réinstallation po ur les travaux de constructio n des voiries par pavage à Br azzaville et à Pointe-Noire. CG-DURQUAP-048-SC-CI / St Project Management, Coordi agiaires-Recrutement des sta IBRD / 85880 A posteriori Individuel Limited 5,000.00 0.00 Annulé 2018-07-23 2018-08-10 2018-07-28 2018-08-18 2018-09-22 2019-03-21 nation and Evaluation giaires environnementale et sociale CG-DURQUAP-028 BIS-SC-CI / PAR Voiries Brazza-Réalisati Development of Institutions on d'un plan d'action de réins IBRD / 85880 A posteriori Individuel Open 75,000.00 0.00 Annulé 2018-08-30 2018-08-24 2018-10-18 2018-11-08 2018-12-13 2019-06-11 and Capacity tallation (PAR) des travaux d e construction des voiries par pavage à Brazzaville CG-DURQUAP-036-SC-CI / PA R voiries PN-Réalisation d'un Development of Institutions plan d'action de réinstallatio IBRD / 85880 A posteriori Individuel Open 75,000.00 0.00 Annulé 2018-08-30 2018-08-24 2018-10-18 2018-11-08 2018-12-13 2019-06-11 and Capacity n (PAR) des travaux de const ruction des voiries par pavag e à Brazzaville CG-DURQUAP-055-SC-CI / PA R Eau et Electricité - Recrute ment d'un consultant pour la Project Management, Coordi realisation des plans d'action IBRD / 85880 A posteriori Individuel Open 180,000.00 219,803.83 Signé 2018-12-05 2019-12-26 2019-01-23 2020-06-11 2019-02-13 2020-07-15 2019-03-20 2020-07-16 2019-09-16 nation and Evaluation de réinstallation (PAR) des re seaux eau et electricite à Bra zzaville et à Pointe Noire dan s les quartiers cibles du proje t. CG-DURQUAP-063-SC-CI / Ch auffeur de liaison-Recruteme Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Open 6,000.00 0.00 Annulé 2018-12-07 2018-12-18 2019-01-18 2019-02-08 2019-03-15 2019-09-11 nt d'un chauffeur de liaison d d Upgrading u projet DURQuaP. CG-DURQUAP-038-SC-ED / T OM2PRO-Recrutement d'un c onsultant pour la mise à jour Sélection de cons du logiciel TOM2PRO , la reco Integration and Neighborhoo En attente d'exéc IBRD / 85880 A posteriori ultants par entent Direct 20,000.00 0.00 2019-01-08 2019-01-18 2019-03-24 2019-09-20 dification du plan comptable, d Upgrading ution e directe le reparamétrage des états fi nanciers et le renforcement des capacités de l'équipe fin ancière du projet. CG-DURQUAP-077-SC-ED / D eveloppement Local-Renouv Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Direct 37,000.00 37,107.72 Achevé 2019-01-10 2019-02-09 2019-01-20 2019-02-15 2019-02-10 2019-02-19 2019-03-17 2019-02-07 2019-09-13 2020-12-31 ellement du contrat du Spéci d Upgrading aliste en Développement loc al CG-DURQUAP-069-SC-ED / C Integration and Neighborhoo oordo-Renouvellement du co IBRD / 85880 A posteriori Individuel Direct 50,000.00 50,109.30 Achevé 2019-01-10 2019-07-20 2019-01-20 2019-10-04 2019-02-10 2019-10-04 2019-03-17 2019-05-09 2019-09-13 2020-12-31 d Upgrading ntrat du Coordonnateur du Pr ojet CG-DURQUAP-070-SC-ED / C Integration and Neighborhoo hauffeur 1-Renouvellement d IBRD / 85880 A posteriori Individuel Direct 6,000.00 6,070.72 Signé 2019-05-10 2019-06-25 2019-05-20 2019-11-19 2019-06-10 2019-11-19 2019-07-15 2019-07-09 2020-01-11 d Upgrading u contrat du Chauffeur 1 CG-DURQUAP-071-SC-ED / C Integration and Neighborhoo hauffeur 2-Renouvellement d IBRD / 85880 A posteriori Individuel Direct 6,000.00 6,092.96 Signé 2019-05-10 2019-07-20 2019-05-20 2019-08-19 2019-06-10 2019-08-22 2019-07-15 2019-07-09 2020-01-11 d Upgrading u contrat du Chauffeur 2 CG-DURQUAP-072-SC-ED / C Integration and Neighborhoo hauffeur 3-Renouvellement d IBRD / 85880 A posteriori Individuel Direct 6,000.00 6,079.25 Signé 2019-05-10 2019-07-20 2019-05-20 2019-08-05 2019-06-10 2019-08-19 2019-07-15 2019-07-10 2020-01-11 d Upgrading u contrat du Chauffeur 3 CG-DURQUAP-073-SC-ED / A Integration and Neighborhoo PM-Renouvellement du contr IBRD / 85880 A posteriori Individuel Direct 32,000.00 28,782.10 Achevé 2019-03-15 2019-03-25 2019-04-15 2019-07-14 2019-05-20 2019-05-14 2019-11-16 2020-12-31 d Upgrading at de l' Assistant en passatio n des marchés CG-DURQUAP-074-SC-ED / A Integration and Neighborhoo ssistante-Renouvellement du IBRD / 85880 A posteriori Individuel Direct 12,000.00 16,391.33 Achevé 2018-12-10 2019-02-01 2018-12-20 2019-02-19 2019-01-10 2019-02-19 2019-02-14 2019-02-07 2019-08-13 2020-12-31 d Upgrading contrat de l' Assistante CG-DURQUAP-075-SC-ED / C Integration and Neighborhoo MTI-Renouvellement du contr IBRD / 85880 A posteriori Individuel Direct 37,000.00 37,186.78 Achevé 2019-01-10 2019-02-01 2019-01-20 2019-02-19 2019-02-10 2019-02-19 2019-03-17 2019-02-07 2019-09-13 2020-12-31 d Upgrading at du Chargé de mission tech nique CG-DURQUAP-076-SC-ED / S Integration and Neighborhoo uivi Eval-Renouvellement du IBRD / 85880 A posteriori Individuel Direct 43,000.00 44,279.77 Achevé 2019-01-10 2019-02-01 2019-01-20 2019-02-19 2019-02-10 2019-03-21 2019-03-17 2019-02-07 2019-09-13 2020-12-31 d Upgrading contrat du Spécialiste en Sui vi-Evaluation CG-DURQUAP-078-SC-ED / C ommunication-Renouvelleme Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Direct 43,000.00 44,793.19 Achevé 2019-01-10 2019-02-01 2019-01-20 2019-02-19 2019-02-10 2019-02-19 2019-03-17 2019-02-07 2019-09-13 2020-12-31 nt du contrat du Spécialiste d Upgrading en Communication CG-DURQUAP-079-SC-ED / C Integration and Neighborhoo omptable-Renouvellement d IBRD / 85880 A posteriori Individuel Direct 28,000.00 51,490.70 Achevé 2019-01-10 2019-08-19 2019-01-20 2019-11-19 2019-02-10 2019-11-19 2019-03-17 2019-04-08 2019-09-13 2020-12-31 d Upgrading u contrat du Comptable CG-DURQUAP-080-SC-ED / S auvegardes-Renouvellement Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Direct 37,000.00 37,071.43 Achevé 2019-01-10 2019-02-09 2019-01-20 2019-02-19 2019-02-10 2019-02-19 2019-03-17 2019-02-07 2019-09-13 2020-12-31 du contrat du Spécialiste en d Upgrading sauvegardes environnement ales et sociales CG-DURQUAP-081-SC-ED / S PM-Renouvellement du contr Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Direct 43,000.00 46,482.31 Achevé 2019-03-11 2019-08-19 2019-03-21 2019-11-25 2019-04-11 2020-11-13 2019-05-16 2019-05-07 2019-11-12 2020-12-31 at du Spécialiste en passatio d Upgrading n de marchés du projet CG-DURQUAP-082-SC-CI / Tr aitement de données-Recrut ement d'un consultant pour l Project Management, Coordi IBRD / 85880 A posteriori Individuel Open 3,000.00 1,707.56 Achevé 2019-01-21 2018-09-12 2019-03-11 2019-01-22 2019-04-01 2019-01-26 2019-05-06 2019-02-12 2019-11-02 2019-03-07 e traitement des données d'e nation and Evaluation nquête relatif à l'état des lieu x à Pointe Noire sur SPHYNX CG-DURQUAP-063BIS-SC-CI / Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Limited 6,000.00 6,117.12 Signé 2019-01-10 2018-12-26 2019-01-15 2018-12-29 2019-02-05 2019-05-31 2019-03-12 2019-04-18 2019-09-08 Recrutement chauffeur de lia d Upgrading ison Page 10 CG-DURQUAP-087-SC-CI / RA FC-Recrutement du Respons Project Management, Coordi IBRD / 85880 A posteriori Individuel Open 144,000.00 44,173.47 Achevé 2019-01-10 2018-12-31 2019-02-28 2019-04-01 2019-03-21 2019-04-01 2019-04-25 2019-03-29 2019-10-22 2020-12-31 able Administratif, Financier nation and Evaluation et Comptable (RAFC) du Proj et CG-DURQUAP-095-CI-ED / Re nouvellement de stage de m Project Management, Coordi onsieur NGAMOUYI Austève IBRD / 85880 A posteriori Individuel Direct 748.00 770.95 Signé 2015-12-15 2019-06-29 2015-12-25 2019-06-29 2016-01-15 2019-06-29 2016-02-19 2018-12-13 2016-08-17 nation and Evaluation Xavier stagiaire en sauvegar des environnementale et soci ale au projet DURQuaP CG-DURQUAP-096-CI-ED / Re nouvellement de stage de M Project Management, Coordi adame MANTOTA Brigitte Ali IBRD / 85880 A posteriori Individuel Direct 748.00 758.84 Signé 2015-01-10 2019-11-04 2015-01-20 2019-11-19 2015-02-10 2019-11-19 2015-03-17 2018-12-13 2015-09-13 nation and Evaluation ma stagiaire en sauvegardes environnementale et sociale au projet DURQuaP CG-DURQUAP-100-SC-CI / Sit e Web-Recrutement d'un con Project Management, Coordi sultant chargé de la création IBRD / 85880 A posteriori Individuel Open 15,000.00 12,539.85 Signé 2019-11-15 2019-12-23 2020-01-03 2020-05-19 2020-01-24 2020-05-19 2020-02-28 2020-05-26 2020-08-26 nation and Evaluation et de la mise à jour d'un site web du projet DURQuaP CG-DURQUAP-99-CI-ED / PAR groupés-Contractualisation p ar entente directe avec IBRA HIMA FALL pour la réalisation Integration and Neighborhoo des PAR pour les travaux de IBRD / 85880 A posteriori Individuel Direct 190,000.00 225,793.19 Signé 2020-01-17 2020-01-06 2020-01-27 2020-02-06 2020-02-17 2020-05-17 2020-03-23 2020-03-28 2020-09-19 d Upgrading construction des marchés de Tchiniambi1 et de Moukound zi Ngouaka ainsi que des ouv rages anti-érosifs de Nzoko M BIMI et MASSINA CG-DURQUAP-98-SC-ED / Etu des voiries 2-Contractualisati on par entente directe avec l Sélection de cons e bureau d'études GAUFF Ing Integration and Neighborhoo IBRD / 85880 A posteriori ultants par entent Direct 350,000.00 169,265.25 Signé 2020-01-20 2020-01-06 2020-01-30 2020-05-18 2020-04-04 2020-03-28 2020-10-01 énieur pour la réalisation des d Upgrading e directe APD et DAO des travaux de c onstruction des voiries urbai nes dans les quartiers cibles de Brazzaville et de Pointe-N oire (Phase 2) CG-017-SC-CI / Recrutement Development of Institutions Consultants pour le renforce IBRD / 85880 A priori Individuel Open 500,000.00 0.00 Annulé 2018-12-20 2019-01-31 2019-02-21 2019-03-28 2019-09-24 and Capacity ment capacités personnel de s Mairies. CG-DURQUAP-029BIS-SC-CI / TDR patrimoine-Recrutement un consultant pour l'élaborati on des termes de référence r Project Management, Coordi elatif à la gestion du patrimoi IBRD / 85880 A posteriori Individuel Open 5,000.00 0.00 Annulé 2018-12-06 2019-01-18 2019-02-08 2019-03-15 2019-09-11 nation and Evaluation ne municipal et de l'assistanc e technique en gestion de l'in frastructure commerciale de la municipalité de Brazzaville et de Pointe Noire CG-DURQUAP-089-SC-CI / TD R législation-Recrutement d' un consultant pour l'élaborati Project Management, Coordi on des termes de référence r IBRD / 85880 A posteriori Individuel Open 5,000.00 0.00 Annulé 2019-01-29 2019-03-13 2019-04-03 2019-05-08 2019-11-04 nation and Evaluation elatif à l'application de la légi slation et de la réglementatio n actualisées en matière d'ur banisme et d'habitat CG-DURQUAP-053BIS-SC-ED / NIES Marché Tchiniambi-ED/ Contractuilisation par entent Sélection de cons Integration and Neighborhoo e directe avec CAERD pour la IBRD / 85880 A posteriori ultants par entent Direct 75,000.00 105,158.73 Achevé 2020-02-25 2020-04-18 2020-03-01 2020-04-27 2020-05-05 2020-03-26 2020-11-01 2021-01-06 d Upgrading mission de la Notice d'Impact e directe Environnementale et Sociale (NIES) du marché domanial Tchiniambi 1 à Pointe Noire CG-DURQUAP-107-SC-ED / N IES marché Moukoundzi-ED-C AERD/Contractualisation par Sélection de cons entente directe avec CAERD Integration and Neighborhoo IBRD / 85880 A posteriori ultants par entent Direct 75,000.00 79,201.66 Signé 2020-02-25 2020-05-05 2020-03-06 2021-04-01 2020-05-10 2021-04-10 2020-11-06 pour la mission de la Notice d Upgrading e directe d'Impact Environnementale e t Sociale (NIES) du marché d omanial Moukoundzi Ngouak a à Brazzaville CG-DURQUAP-059 BIS-SC-ED / NIES écoles et stade-ED-SE RF/Contractualisation par ent Sélection de cons ente avec SERF BURKINA pou Integration and Neighborhoo IBRD / 85880 A posteriori ultants par entent Direct 250,000.00 419,772.06 Achevé 2020-02-25 2020-03-05 2020-03-06 2020-04-18 2020-05-10 2020-03-23 2020-11-06 2020-05-26 r la mission de la Notice d'Im d Upgrading e directe pact Environnementale et So ciale (NIES) écoles Mountou Mavoungou et Pambou Binja men, du stade TATA LOBOKO CG-DURQUAP-109-SC-CI / Re Project Management, Coordi crutement d'un spécialiste d IBRD / 85880 A posteriori Individuel Limited 45,000.00 35,594.64 Signé 2020-03-05 2020-04-07 2020-03-10 2020-04-27 2020-03-31 2020-05-18 2020-05-05 2020-05-18 2020-11-01 nation and Evaluation e sauvegarde sociale du proj et DURQuaP CG-DURQUAP-114-SC-CI / Op érateurs/Recrutement de six Project Management, Coordi IBRD / 85880 A posteriori Individuel Limited 30,000.00 7,337.40 Signé 2020-02-29 2020-07-17 2020-03-05 2020-08-04 2020-03-26 2020-09-02 2020-04-30 2020-08-31 2020-10-27 (06) opérateurs du centre d'a nation and Evaluation ppels du DURQuaP CG-DURQUAP-117-SC-ED / N IES CSI C.sportif-ED SERF/Co ntractualisation par entente Sélection de cons directe avec SERF BURKINA p Integration and Neighborhoo IBRD / 85880 A posteriori ultants par entent Direct 125,000.00 0.00 Annulé 2020-02-29 2020-03-10 2020-05-14 2020-11-10 our la mission des Notices d'I d Upgrading e directe mpact Environnementale et Sociale (NIES) centre de san té intégré et complexe sport if de Soukissa à Brazzaville CG-DURQUAP-105-SC-ED/GE Sélection de cons RAD / MOS-BZV-ED-GERAD/R Development of Institutions IBRD / 85880 A priori ultants par entent Direct 787,006.00 509,659.02 Signé 2020-04-30 2020-05-21 2020-05-10 2020-06-30 2020-07-14 2020-06-30 2021-01-10 enouvellement du contrat de and Capacity e directe la maîtrise d'œuvre sociale à Brazzaville. CG-DURQUAP-106-SC-ED/GE RAD / MOS-PNR-ED-GERAD/R Sélection de cons Development of Institutions enouvellement du contrat de IBRD / 85880 A priori ultants par entent Direct 760,368.00 525,988.32 Signé 2020-04-30 2020-05-19 2020-05-10 2020-06-15 2020-07-14 2020-06-30 2021-01-10 and Capacity la maîtrise d'œuvre sociale à e directe Pointe-Noire par entente dire cte Page 11 CG-DURQUAP-050-SC-CI / PA R TCHINIAMBI-Recrutement d 'un consultant individuel char Integration and Neighborhoo IBRD / 85880 A posteriori Individuel Open 90,000.00 0.00 Annulé 2018-12-15 2019-02-02 2019-02-23 2019-03-30 2019-09-26 gé de la préparation du Plan d Upgrading d'Action de Réinstallation (PA R) du marché de TCHINIAMBI à Pointe-Noire. CG-DURQUAP-047-SC-CI / M aintenancier Reprographie R Project Management, Coordi ecrutement d' un maintenan IBRD / 85880 A posteriori Individuel Open 10,000.00 0.00 Annulé 2018-08-23 2018-10-04 2018-11-15 2018-12-20 2019-06-18 nation and Evaluation cier du matériel de reprograp hie du projet DURQuaP à tem ps partiel CG-DURQUAP-115-CS-INDV / Project Management, Coordi Recrutement d'un ingénieur j IBRD / 85880 A posteriori Individuel Open 30,000.00 20,525.70 Achevé 2020-06-25 2020-05-20 2020-07-21 2020-11-13 2020-08-04 2020-11-13 2020-08-18 2020-07-31 2021-06-22 2020-12-31 nation and Evaluation unior en génie civil CG-DURQUAP-047BIS-SC-CI / Recrutement d'un Assistant t Project Management, Coordi IBRD / 85880 A priori Individuel Limited 240,000.00 92,084.72 Signé 2020-05-29 2020-06-05 2020-06-03 2020-06-11 2020-06-24 2020-07-20 2020-07-29 2020-07-20 2021-01-25 echnique international en pa nation and Evaluation ssation des marchés du proje t DURQuaP. CG-DURQUAP-125-SC-CI / Re crutement d'un consultant in Project Management, Coordi IBRD / 85880 A posteriori Individuel Open 40,000.00 88,433.70 Signé 2020-08-25 2020-10-07 2020-10-13 2020-12-09 2020-11-03 2021-01-20 2020-12-08 2021-01-11 2021-06-06 dividuel pour l'évaluation fin nation and Evaluation ale du projet DURQuaP CG-DURQUAP-127-CI-ED/CA RTOGRAPHES / Cartographes /Recrutement par entente dir Project Management, Coordi IBRD / 85880 A posteriori Individuel Direct 84,000.00 89,922.50 Signé 2020-08-21 2020-08-11 2020-08-31 2021-02-26 2020-09-21 2021-02-26 2020-10-26 2020-08-28 2021-04-24 ecte des cartographes pour l' nation and Evaluation Identification des zones vuln érables à Pointe Noire et Bra zzaville CG-DURQUAP-002 - CERC - S C / Recrutement d'un consult Sélection de cons Development of Institutions ant pour la Sensibilisation de IBRD / 85880 A posteriori ultants par entent Direct 181,000.00 158,500.58 Signé 2020-09-25 2020-09-11 2020-10-09 2020-09-25 2020-11-20 2020-12-02 2021-05-19 and Capacity la population sur la pandémi e directe e du COVID-19 à Pointe-Noire . CG-DURQUAP-013-CERC-SC- ED / Etudes, supervision des travaux de curage et faucard age du cours d’eau Nganda C Sélection de cons Development of Institutions ouloir et le collecteur travers IBRD / 85880 A posteriori ultants par entent Direct 110,000.00 0.00 Annulé 2020-08-31 2020-10-23 2020-09-10 2020-10-15 2021-04-13 and Capacity ant les rues Kindombi, Loualo e directe u et Likibi au quartier SOUKIS SA, Louka, Maladie du Somm eil et le Collecteur 1500 au q uartier Mokondzi Ngouaka. CG -DURQUAP-012-CERC-SC -ED / Contrôle et supervision Sélection de cons des travaux de curage et de f Development of Institutions IBRD / 85880 A posteriori ultants par entent Direct 35,000.00 0.00 Annulé 2020-08-31 2020-09-10 2020-10-15 2021-04-13 aucardage des rivières LOUK and Capacity e directe A, MALADIE DU SOMMEIL et l e collecteur ''1500 '' au quart ier MOUKOUNDZI-NGOUAKA CG -DURQUAP-005-CERC-SC -ED / Etudes techniques et co ntrôle-supervision des travau x d'assainissement du March Sélection de cons Development of Institutions é Total: curage du réseau d'a IBRD / 85880 A posteriori ultants par entent Direct 27,000.00 0.00 Annulé 2020-10-30 2020-11-18 2020-11-09 2021-01-13 2021-07-12 and Capacity ssainissement, nettoyage de e directe s sites de dépôts sauvages d' ordures, traitement des terre -pleins et autres points noirs à Brazzaville. CG -DURQUAP-004-CERC-SC -ED / Etudes techniques, cont rôle et supervision des trava ux de curage et de faucardag Sélection de cons Development of Institutions e du cours d’eau (Songolo) e IBRD / 85880 A posteriori ultants par entent Direct 59,000.00 0.00 Annulé 2020-10-30 2020-10-23 2020-11-09 2020-11-30 2021-02-28 and Capacity n amont et en aval de l’ouvra e directe ge à réhabiliter à LOANDJILI e t au cours d'eau Tchinouka e n aval de l'avenue Tonou à M BOUKOU à Pointe-Noire. CG-DURQUAP-128-SC-ED / G estion des infra/Elaboration d Sélection de cons 'un plan de gestion des infras Development of Institutions IBRD / 85880 A posteriori ultants par entent Direct 295,000.00 340,483.00 Signé 2020-12-01 2020-10-31 2020-12-11 2020-11-09 2021-01-15 2020-12-23 2021-07-14 tructures socio-collectives et and Capacity e directe commerciales financées dans le cadre du projet DURQuaP de BZV et de PNR. CG-DURQUAP-129-SC-CI / El Development of Institutions aboration de la stratégie nati IBRD / 85880 A posteriori Individuel Limited 195,000.00 266,695.65 Signé 2020-12-10 2020-10-31 2020-12-15 2020-12-02 2021-01-05 2021-02-22 2021-02-09 2021-02-01 2021-08-08 and Capacity onale de restructuration urba ine au Congo CG-DURQUAP-010-CERC-SC- ED / Etudes, supervision des Sélection de cons Development of Institutions travaux d’alimentation et/ou IBRD / 85880 A posteriori ultants par entent Direct 75,000.00 0.00 Annulé 2020-11-25 2020-10-31 2020-12-05 2021-02-08 2021-08-07 and Capacity réhabilitation des points d'ea e directe u et des toilettes des écoles à Brazzaville. CG-DURQUAP-011 BIS-CERC- SC-ED / Etudes, supervision d Sélection de cons Integration and Neighborhoo es travaux d’alimentation et/ IBRD / 85880 A posteriori ultants par entent Direct 75,000.00 0.00 Annulé 2020-12-25 2020-10-31 2021-01-04 2021-03-10 2021-09-06 d Upgrading ou réhabilitation des points d e directe 'eau et des toilettes des écol es à Pointe-Noire. CG-DURQUAP-146-SC-ED / N IES-PSR/Services de consulta nt pour l'élaboration d'une N Sélection de cons otice d'Impact Environnemen Integration and Neighborhoo IBRD / 85880 A posteriori ultants par entent Direct 70,000.00 92,250.11 Achevé 2021-01-20 2020-12-17 2021-01-30 2020-12-19 2021-04-05 2021-01-28 2021-10-02 tal et Social et d'un Plan Succ d Upgrading e directe inct de Réinstallation des tra vaux d'aménagement de l'Av enue CHARLES DE GAULLE p ar pavage à Mboukou. CG-DURQUAP-116-SC-ED / N IES écoles-ED-SERF/Contract ualisation par entente directe Sélection de cons avec SERF BURKINA pour la Integration and Neighborhoo IBRD / 85880 A posteriori ultants par entent Direct 125,000.00 0.00 Annulé 2020-03-10 2020-03-20 2020-05-24 2020-11-20 mission des Notices d'Impact d Upgrading e directe Environnementale et Sociale (NIES) écoles Malonga écout e et la Sorbonne de Moukoun dzi Ngouaka à Brazzaville. Page 12 CG-DURQUAP-046 -SC-CI / M iantenancier informatique - R Project Management, Coordi IBRD / 85880 A posteriori Individuel Open 10,000.00 0.00 Annulé 2018-08-15 2018-09-26 2018-10-17 2018-11-21 2019-05-20 ecrutement d'un maintenanci nation and Evaluation er du matériel informatique à temps partiel CG-DURQUAP-065 BIS-SC-ED / Supervision Tx Erosion/Cont ractualisation par Entente Dir Sélection de cons Integration and Neighborhoo ecte avec le bureau d'études IBRD / 85880 A posteriori ultants par entent Direct 300,000.00 0.00 Annulé 2020-02-20 2020-03-23 2020-03-01 2020-05-05 2020-11-01 d Upgrading INROS LACKNER pour le cont e directe rôle et la supervision des tra vaux des zones en proie aux érosions. CG-DURQUAP-120-SC-CI / Re vue à mi-parcours/Recrutem Project Management, Coordi ent d'un consultant pour app IBRD / 85880 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2020-04-30 2020-05-10 2020-05-05 2020-05-26 2020-06-30 2020-12-27 nation and Evaluation uyer l'UCP/DURQuaP à la réal isation de la revue à mi-parc ours du projet CG-DURQUAP-001-CERC -SC / Recrutement d'un consultan Sélection de cons Development of Institutions t pour la Sensibilisation de la IBRD / 85880 A posteriori ultants par entent Direct 207,000.00 0.00 Annulé 2020-09-25 2020-09-11 2020-10-09 2020-09-22 2020-11-13 2021-05-12 and Capacity population sur la pandémie d e directe u COVID-19 à Brazzaville CG-DURQUAP-147-SC-ED / M arché de Moukoundzi-Ngoua ka/Recrutement consultant p Sélection de cons our la réalisation des études Integration and Neighborhoo IBRD / 85880 A posteriori ultants par entent Direct 300,000.00 184,195.25 Signé 2021-04-26 2021-03-31 2021-05-06 2021-04-01 2021-07-10 2021-04-10 2022-01-06 techniques et production du d Upgrading e directe DAO pour la réhabilitation du marché de Moukoundzi-Ngou aka (Arrondissement 1 : Mak élékélé) à Brazzaville. CG-DURQUAP-145-SC -CI -ED / Recrutement d'un assistant Project Management, Coordi technique international en sa IBRD / 85880 A posteriori Individuel Direct 50,000.00 0.00 Annulé 2020-11-16 2020-11-18 2020-11-26 2021-01-15 2020-12-03 2020-12-17 2021-05-16 nation and Evaluation uvegarde environnementale et sociale du projet DURQuaP CG-DURQUAP-012-BIS-SC-CI / CI-Comptable-Recrutement Integration and Neighborhoo IBRD / 85880 A priori Individuel Limited 65,000.00 0.00 Annulé 2017-03-20 2017-05-19 2017-07-18 2017-09-25 2018-03-24 du personnel complémentair d Upgrading e de l'Unité de Coordination - Comptable CG-DURQUAP-011-BIS-SC-CI / CI-Sauvegarde-Recrutemen t du personnel complémentai Integration and Neighborhoo IBRD / 85880 A priori Individuel Limited 100,000.00 0.00 Annulé 2017-03-20 2017-05-07 2017-07-06 2017-09-25 2018-03-24 re de l'Unité de Coordination d Upgrading - Spécialiste en sauvegardes environnementales et sociale s CG-DURQUAP-04-SC-ED-202 1 / Finalisation de la mission relative à la Mise en place de Sélection de cons l’observatoire urbain, de la ré Development of Institutions IBRD / 85880 A posteriori ultants par entent Direct 602,454.00 514,341.61 Signé 2021-09-20 2021-08-23 2021-09-30 2021-09-15 2021-12-04 2021-10-21 2022-06-02 alisation de l’adressage et de and Capacity e directe l’actualisation de la base de données des impôts et des re cettes fiscales des municipali tés de Brazzaville et de Point e-Noire. CG-DURQUAP-07-SC-ED-202 1 / Contrôle et supervision de Sélection de cons s travaux de réhabilitation de Integration and Neighborhoo IBRD / 85880 A posteriori ultants par entent Direct 270,000.00 276,705.55 Signé 2021-10-25 2021-09-28 2021-11-04 2021-10-07 2022-01-08 2021-11-15 2022-07-07 l'établissement public scolair d Upgrading e directe e de Moukoundzi-Ngouaka S ORBONNE (arrondissement 1 : Makélékélé) à Brazzaville. CG-DURQUAP-08-SC-CI-ED-2 Sélection de cons Project Management, Coordi 021 / RECRUTEMENT DU SPE IBRD / 85880 A posteriori ultants par entent Direct 50,000.00 68,138.80 Signé 2021-10-20 2021-09-28 2021-10-30 2021-10-21 2022-01-03 2021-10-27 2022-07-02 nation and Evaluation CIALISTE EN GOUVERNANCE e directe TERRITORIALE. CG-DURQUAP-10-SC-CI-ED-2 021 / Evaluation de l'impact Project Management, Coordi du projet, la capitalisation de IBRD / 85880 A posteriori Individuel Direct 200,000.00 115,517.03 Signé 2021-10-25 2021-11-23 2021-11-04 2021-12-10 2021-11-25 2022-01-12 2021-12-30 2022-01-12 2022-06-28 nation and Evaluation l'expérience du DURQuaP et l 'actualisation du rapport d'ac hèvement du projet. CG-DURQUAP-11 BIS-SC-ED- Project Management, Coordi 2021 / Assistance technique i IBRD / 85880 A posteriori Individuel Direct 95,000.00 108,830.49 Achevé 2021-11-25 2021-10-08 2021-12-05 2021-12-13 2021-12-26 2021-12-13 2022-01-30 2021-11-19 2022-07-29 nation and Evaluation nternationale en passation d es marchés CG-DURQUAP-115-SC-CI / Su perviseurs/Recrutement de d Project Management, Coordi IBRD / 85880 A posteriori Individuel Limited 12,000.00 0.00 Annulé 2020-02-29 2020-05-24 2020-03-05 2020-08-04 2020-03-26 2020-04-30 2020-10-27 eux (02) superviseurs du cen nation and Evaluation tre d'appel du DURQuaP CG-DURQUAP-11-SC-CI-2021 Project Management, Coordi / Appui technique internation IBRD / 85880 A posteriori Individuel Limited 40,000.00 0.00 Annulé 2021-10-20 2021-10-25 2021-11-15 2021-12-20 2022-06-18 nation and Evaluation al en passation des marchés. CG-DURQUAP-13-SC-CI-2021 / Elaboration de la stratégie Project Management, Coordi IBRD / 85880 A posteriori Individuel Limited 38,000.00 31,683.56 Signé 2022-01-28 2022-01-06 2022-02-02 2022-01-12 2022-02-23 2022-03-07 2022-03-30 2022-03-14 2022-09-26 de communication relative à nation and Evaluation la vulgarisation des instrume nts d’urbanisme. CG - DURQUAP 001 - SC - CI - ED 2021 / Audit technique/R Project Management, Coordi ecrutement d'un consultant i IBRD / 85880 A posteriori Individuel Direct 40,000.00 0.00 Annulé 2021-04-19 2021-04-22 2021-04-24 2021-04-28 2021-05-12 nation and Evaluation ndividuel pour l'audit techni que du projet DURQuaP CG-DURQUAP-01 BIS-SC-ED- 2022 / RECRUTEMENT D’UN Sélection de cons CONSULTANT CHARGE DE LA Development of Institutions IBRD / 85880 A posteriori ultants par entent Direct 85,000.00 75,346.88 Signé 2022-06-15 2022-08-05 2022-06-25 2022-08-29 2022-08-29 2022-09-09 2023-02-25 FORMATION SUR L’AUTONO and Capacity e directe MISATION DES CGDC DES VIL LES DE BRAZZAVILLE ET DE POINTE-NOIRE. CG-DURQUAP-01-SC-ED-202 2 / RECRUTEMENT D’UNE ON Sélection de cons G CHARGE DE LA FORMATIO Development of Institutions IBRD / 85880 A posteriori ultants par entent Direct 85,000.00 0.00 Annulé 2022-03-22 2022-04-06 2022-04-01 2022-04-11 2022-06-05 2022-12-02 N SUR L’AUTONOMISATION and Capacity e directe DES CGDC DES VILLES DE BR AZZAVILLE ET DE POINTE-NO IRE Page 13 CG-DURQUAP-02-SC-CI-ED-2 Sélection de cons 022 / Renouvellement du con Project Management, Coordi En cours d'exécut IBRD / 85880 A posteriori ultants par entent Direct - National 5,581.00 0.00 2022-10-25 2022-11-10 2022-11-04 2023-01-08 2023-07-07 trat-cadre de l'Experte en go nation and Evaluation ion e directe uvernance et développement urbain. Page 14