Uzbekistan DHEEP THRESHOLDS FOR PROCUREMENT METHODS AND BANK PRIOR REVIEW Contract Value Expenditure Threshold Procurement Method Contracts Subjects to Prior Review (US$) Category (US$) >=1,000,000 ICB ICB contracts > 1,500,000 <1,000,000 NCB First 1 NCB contract Goods and Works <100,000 Shopping First Shopping contract NA DC All DC contracts >=300,000 QCBS/QBS/LCS/FBS a/ b/ >=500,000 for firms Consultant <300,000 CQS Services (including training) NA SSS all SSS contracts NA IC >=100,000 for individuals Notes: a/ Shortlist may compose entirely of national consultants for assignments of less than US$100,000 equivalent per contract. b/ As appropriate, these methods may be adopted for assignments costing less than $200,000. ICB – International Competitive Bidding NCB – National Competitive Bidding DC – Direct Contracting QCBS – Quality and Cost Based Selection QBS – Quality Based Selection LCS – Least Cost Selection FBS – Fixed Budget Selection CQS – Selection Based on Consultants’ Qualifications SSS – Single Source Selection IC – Individual Consultants REF: as available in Imagebank PROCUREMENT Uzbekistan : Modernization and Upgrade of Transmission Substations PLAN General Information Country: Uzbekistan 2016-08-22 Bank’s Approval Date of the Original Procurement Plan: 2022-10-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156584 GPN Date: 2018-02-27 Project Name: Modernization and Upgrade of Transmission Substations Loan / Credit No: / , IDA / 59170, IDA / 59160, IBRD / 86640 JSC Uzbekenergo Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MUTS/NCB/2016-1LOT-1 / C Component 1. Electricity Tra Under Imple 2021-06-0 ONTSTRUCTION AND INSTAL IBRD / 86640 Post Direct Selection Direct 0.00 2020-10-24 2020-10-30 2020-10-29 2020-11-04 2020-12-03 nsmission System Upgrade mentation 1 LATION WORKS GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MUTS/ICB-2016-2 / Procurem Component 1. Electricity Tra Open - Internationa Single Stage - One E / Prior Request for Bids 0.00 Canceled 2016-08-22 2016-08-22 2016-08-27 2016-08-22 2016-10-08 2016-11-07 2018-09-12 2016-12-12 2017-06-10 ent of electrical equipment nsmission System Upgrade l nvelope MUTS/ICB/2016-3 / Procurem Component 1. Electricity Tra Open - Internationa Single Stage - One E ent of Medium voltage and L IDA / 59170 Prior Request for Bids 1,790,622.00 Signed 2016-10-12 2018-07-25 2016-11-02 2018-08-27 2016-12-14 2018-10-08 2017-01-13 2018-11-22 2017-02-17 2018-12-04 2017-08-16 nsmission System Upgrade l nvelope ow voltage power equipment MUTS/ICB/2016-1 / Procurem Component 1. Electricity Tra Open - Internationa Single Stage - One E ent of autotransformers and t IDA / 59170 Prior Imports 19,918,200.00 Signed 2018-03-12 2018-05-15 2018-03-14 2018-04-04 2018-05-04 2018-05-17 2018-06-08 2016-12-29 2018-12-05 nsmission System Upgrade l nvelope ransformers. MUTS/ICB/2016-9 / Procurem Component 1. Electricity Tra Open - Internationa Single Stage - One E IDA / 59160 Prior Request for Bids 3,034,600.00 Completed 2018-04-23 2018-07-25 2018-04-28 2018-08-29 2018-05-28 2018-10-22 2018-06-27 2018-11-27 2018-08-01 2018-12-05 2019-01-28 2019-12-20 ent of specialized machinery nsmission System Upgrade l nvelope MUTS/ICB/2016-5 / Procurem Component 1. Electricity Tra Open - Internationa Single Stage - One E IDA / 59160 Prior Request for Bids 3,861,558.00 Signed 2018-09-06 2018-12-01 2018-09-13 2018-12-03 2018-10-25 2019-02-04 2018-11-24 2019-04-11 2019-01-14 2019-06-07 2019-07-13 ent of High Voltage Equipme nsmission System Upgrade l nvelope nt MUTS/ICB/2016-2 R / Procure Component 1. Electricity Tra Open - Internationa Single Stage - One E IDA / 59160 Prior Request for Bids 2,871,888.00 Signed 2018-09-24 2018-11-21 2018-10-01 2018-12-04 2018-11-12 2019-02-04 2018-12-12 2019-04-30 2019-01-16 2019-05-13 2019-07-15 ment of Power transformers nsmission System Upgrade l nvelope MUTS/ICB/2016-6 / Procurem Component 1. Electricity Tra Open - Internationa Single Stage - One E ent HF communication equip IDA / 59160 Prior Request for Bids 5,734,757.00 Signed 2018-11-19 2019-03-01 2018-11-30 2019-03-12 2019-01-11 2019-04-23 2019-02-10 2019-07-10 2019-03-17 2019-07-24 2019-09-13 nsmission System Upgrade l nvelope ment, Accumulator batteries and rectifiers MUTS/ICB/2016-11 / Procure Component 1. Electricity Tra Open - Internationa Single Stage - One E IDA / 59160 Prior Request for Bids 1,040,000.00 Terminated 2019-03-05 2019-03-07 2019-03-10 2019-03-13 2019-04-23 2019-04-23 2019-05-23 2019-07-10 2019-06-28 2019-09-09 2019-12-25 ment of Specialized machine nsmission System Upgrade l nvelope ry - 2 MUTS/ICB/2016-4 / Procurem ent of High-Voltage Equipme Component 1. Electricity Tra Open - Internationa Single Stage - One E nt, Communication Equipme IBRD / 86640 Prior Request for Bids 0.00 Canceled 2019-06-24 2019-07-15 2019-08-26 2019-09-25 2019-10-23 2020-04-20 nsmission System Upgrade l nvelope nt, Relay Protection and Automation MUTS/ICB/2016-13 / Implem Component 1. Electricity Tra Open - Internationa Single Stage - One E entation of the management IBRD / 86640 Prior Request for Bids 0.00 Canceled 2019-01-07 2019-01-14 2019-02-25 2019-03-27 2019-05-27 2019-11-23 nsmission System Upgrade l nvelope information system of JSC Uz bekenergo MUTS/ICB/2016-12 / Equipm Component 1. Electricity Tra Open - Internationa Single Stage - One E IBRD / 86640 Post Request for Bids 350,000.00 Completed 2019-09-11 2019-09-13 2019-10-11 2019-09-13 2019-11-22 2019-10-28 2019-12-22 2019-11-08 2020-02-02 2019-11-14 2020-06-01 2020-03-10 ent for Substation services nsmission System Upgrade l nvelope MUTS/ICB/2016-8 / Mobile su Component 1. Electricity Tra Open - Internationa Single Stage - One E Pending Impl IDA / 59160 Post Request for Bids 0.00 2019-12-23 2020-01-06 2020-02-17 2020-03-18 2020-04-29 2020-10-26 bstation nsmission System Upgrade l nvelope ementation MUTS/ICB/2016-7 / Procurem ent of Hardware. Package-1: Reinforced concr ete products. Component 1. Electricity Tra Open - Internationa Single Stage - One E IBRD / 86640 Prior Request for Bids 0.00 Canceled 2019-11-19 2019-12-19 2020-02-02 2020-03-03 2020-04-15 2020-10-12 Package-2: Metal rollings. nsmission System Upgrade l nvelope Package-3: Cables and wires. Package-4: Linear-coupling fi ttings and Insulators. MUTS/ICB/2016- 4 / Package one: High-voltage and mediu m voltage equipment Component 1. Electricity Tra Open - Internationa Single Stage - One E IBRD / 86640 Prior Request for Bids 38,732,630.47 Signed 2019-09-23 2019-09-25 2019-10-14 2019-12-16 2019-11-25 2020-02-20 2019-12-25 2020-09-22 2020-01-22 2020-10-09 2021-01-21 nsmission System Upgrade l nvelope Package two: Relay protectio n and communication equip ment MUTS/ICB/2016 -14 / Autotra Component 1. Electricity Tra Open - Internationa Single Stage - One E nsformers for 500 kV Substat IDA / 59170 Prior Request for Bids 8,799,000.00 Signed 2020-01-24 2020-03-07 2020-02-23 2020-03-19 2020-04-05 2020-05-01 2020-05-05 2020-07-08 2020-06-09 2020-08-03 2020-12-06 nsmission System Upgrade l nvelope ion “Lochin” MUTS/ICB/2016-11 R / Procu Component 1. Electricity Tra Open - Internationa Single Stage - One E IDA / 59160 Post Request for Bids 1,100,020.00 Signed 2020-03-25 2020-03-18 2020-04-09 2020-03-19 2020-05-24 2020-05-01 2020-06-23 2020-06-05 2020-07-28 2020-06-22 2021-01-24 rement of Specialized machi nsmission System Upgrade l nvelope nery - 2 MUTS/ICB/2016-7/1 / LINE C Component 1. Electricity Tra Open - Internationa Single Stage - One E IBRD / 86640 Prior Request for Bids 1,900,000.01 Signed 2020-11-27 2020-12-09 2020-12-02 2021-01-06 2021-01-13 2021-02-10 2021-02-12 2021-04-20 2021-03-19 2021-04-30 2021-09-15 OUPLING FITTINGS AND INSU nsmission System Upgrade l nvelope LATORS MUTS/ICB/2016 -13 / Enterpr Component 1. Electricity Tra Open - Internationa Single Stage - One E Pending Impl IBRD / 86640 Post Request for Bids 0.00 2021-05-27 2021-06-11 2021-07-23 2021-08-22 2021-10-11 2021-11-16 ise resource planning (ERP) nsmission System Upgrade l nvelope ementation MUTS/ICB/2016-7/2 / MUTS/I CB/2016-7/2/1: CABLE AND WIRES; Component 1. Electricity Tra Open - Internationa Single Stage - One E IBRD / 86640 Prior Request for Bids 21,587,464.35 Signed 2021-05-31 2021-06-18 2021-06-01 2021-07-12 2021-07-13 2021-08-19 2021-08-12 2021-11-04 2021-09-16 2021-11-29 2022-03-15 MUTS/ICB/2016-7/2/2: METAL nsmission System Upgrade l nvelope ROLLINGS; MUTS/ICB/2016-7/2/3: REINF ORCED CONCRETE PRODUCT S; Page 1 MUTS/ICB/2016-10 / 35 kV, 2 20 kV AND 110 kV GIS AND P Component 1. Electricity Tra Open - Internationa Single Stage - One E OWER CABLES IDA / 59170 Prior Request for Bids 6,789,000.00 Signed 2021-07-30 2021-10-28 2021-08-04 2022-01-18 2021-09-15 2022-01-25 2021-10-15 2022-04-22 2021-11-19 2022-07-05 2022-05-18 nsmission System Upgrade l nvelope FOR YUKSAK 220/110 kV SUB STATION MUTS/ICB/2016 -15 / Procure Component 1. Electricity Tra Open - Internationa Single Stage - One E Pending Impl ment of Power and Auxiliary IBRD / 86640 Prior Request for Bids 0.00 2022-10-15 2022-10-25 2022-12-06 2022-12-27 2023-02-04 2023-08-03 nsmission System Upgrade l nvelope ementation Transformers MUTS/ICB/2016 -16 / Procure Component 1. Electricity Tra Open - Internationa Single Stage - One E Pending Impl IBRD / 86640 Prior Request for Bids 0.00 2022-10-15 2022-10-20 2022-12-01 2023-01-10 2023-02-14 2023-08-13 ment of Primary Equipment nsmission System Upgrade l nvelope ementation MUTS/ICB/2016 -17 / Procure Component 1. Electricity Tra Open - Internationa Single Stage - One E Pending Impl ment of Auxiliary Сabinets (n IBRD / 86640 Prior Request for Bids 0.00 2022-10-15 2022-10-20 2022-12-01 2023-01-10 2023-02-07 2023-08-06 nsmission System Upgrade l nvelope ementation on-standard) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MUTS/CS-5 / Other key secto Component 2. Institutional D Quality And Cost- Open - Internationa Pending Impleme IDA / 59160 Post 0.00 2019-11-04 2019-11-25 2020-01-08 2020-02-05 2020-03-06 2020-04-10 2020-05-15 2021-05-15 ral studies evelopment and Technical A Based Selection l ntation ssistance MUTS/CS-6 / Capacity develo Component 2. Institutional D Quality And Cost- Open - Internationa Under Implement IDA / 59160 Post 0.00 2019-10-28 2020-01-20 2019-11-18 2020-01-01 2020-01-29 2020-02-28 2020-04-03 2020-05-08 2021-05-08 pment of sector entities evelopment and Technical A Based Selection l ation ssistance MUTS/CS-8 / Foreign advisor Component 2. Institutional D Quality And Cost- Open - Internationa s for operation management IDA / 59160 evelopment and Technical A Prior 0.00 Canceled 2019-09-20 2019-09-10 2019-10-11 2019-09-11 2019-11-24 2019-12-22 2020-01-21 2020-02-25 2020-03-31 2021-03-31 Based Selection l assistance of the National Gri ssistance d of Uzbekistan MUTS/CS-2 / Assessment of t he current state and the nee Component 2. Institutional D Quality And Cost- Open - Internationa d for modernization and expa IDA / 59160 evelopment and Technical A Prior 0.00 Canceled 2019-12-16 2020-01-06 2020-02-19 2020-03-18 2020-04-17 2020-05-22 2020-06-26 2021-06-26 Based Selection l nsion of the transmission sys ssistance tem with the new structure o f the sector MUTS/CS-7 / Current expend Component 2. Institutional D Quality And Cost- Open - Internationa IDA / 59160 Prior 0.00 Canceled 2019-09-30 2019-10-21 2019-12-04 2020-01-01 2020-01-31 2020-03-06 2020-04-10 2021-04-10 itures for PMU evelopment and Technical A Based Selection l ssistance MUTS/CS-3 / Power system p Component 2. Institutional D Quality And Cost- Open - Internationa Pending Impleme IDA / 59160 Post 0.00 2019-09-18 2019-10-09 2019-11-22 2019-12-20 2020-01-19 2020-02-23 2020-03-29 2021-03-29 lanning exercise and softwar evelopment and Technical A Based Selection l ntation e upgrade ssistance Component 2. Institutional D Quality And Cost- Open - Internationa MUTS/CS-1/2 / Entity audit IDA / 59160 Prior 0.00 Canceled 2019-11-18 2019-12-09 2020-01-22 2020-02-19 2020-03-20 2020-04-24 2020-05-29 2021-05-29 evelopment and Technical A Based Selection l ssistance MUTS/CS-1 / Project and enti Component 2. Institutional D Least Cost Selecti Open - Internationa IDA / 59160 Prior 0.00 Canceled 2019-09-23 2019-09-11 2019-10-14 2019-11-27 2019-12-25 2020-01-24 2020-02-28 2020-04-03 2020-09-30 ty audits evelopment and Technical A on l ssistance Component 2. Institutional D Consultant Qualifi Open - Internationa MUTS/CS-1/1 / Project audit IDA / 59160 Post 11,805.00 Signed 2019-10-21 2019-09-05 2019-11-11 2019-12-25 2019-10-10 2020-01-24 2019-10-16 2020-02-28 2019-10-18 2020-08-26 evelopment and Technical A cation Selection l ssistance MUTS/CS-2-2 / Transmission Component 2. Institutional D Quality And Cost- Open - Internationa Network Development and R IDA / 59170 evelopment and Technical A Prior 347,600.00 Signed 2020-01-27 2020-02-07 2020-02-17 2020-05-19 2020-04-01 2020-08-28 2020-04-29 2020-10-15 2020-05-29 2021-01-11 2020-07-03 2021-03-06 2020-08-07 2021-03-12 2021-08-07 Based Selection l enewable Energy Integration ssistance Plan MUTS/CS-10 / Feasibility stu Component 2. Institutional D Quality And Cost- Open - Internationa IDA / 59170 Post 184,858.22 Signed 2020-04-17 2020-05-11 2020-05-08 2020-05-15 2020-06-21 2020-06-10 2020-07-19 2020-08-25 2020-08-18 2020-10-05 2020-09-22 2020-10-26 2020-10-27 2021-06-07 2021-10-27 dy and Bidding documents fo evelopment and Technical A Based Selection l r ERP ssistance Component 2. Institutional D Least Cost Selecti Open - Internationa MUTS/CS-1/2. / Entity audit IDA / 59170 Post 330,000.00 Signed 2020-10-27 2020-10-27 2020-10-27 2020-12-10 2020-11-09 2021-01-07 2020-12-18 2021-02-06 2021-01-22 2021-03-13 2021-03-31 2021-04-17 2021-03-31 2021-10-14 evelopment and Technical A on l ssistance MUTS/CS-1/1/1 / Financial au Component 2. Institutional D Consultant Qualifi Open - Internationa Under Implement dit for MUTS projects for fina IBRD / 86640 evelopment and Technical A Post 0.00 2022-04-03 2022-04-01 2022-04-24 2022-06-07 2022-04-05 2022-07-07 2022-04-15 2022-08-11 2023-02-07 cation Selection l ation ncial year 2021-2022 ssistance MUTS/CS-4 / Feasibility studi Component 2. Institutional D Quality And Cost- Open - Internationa es for the proposed new tran IDA / 59160 evelopment and Technical A Post 0.00 Canceled 2019-10-08 2019-10-29 2019-12-12 2020-01-09 2020-02-08 2020-03-14 2020-04-18 2021-04-18 Based Selection l smission project ssistance INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TP/CS-3 / Projects and entity Component 2. Institutional D IDA / 59170 Prior Direct Selection Direct 0.00 Canceled 2018-10-30 2018-11-04 2018-11-20 2019-06-30 audit for 2017 evelopment and Technical A ssistance MUTS/CS-8 / Foreign advisor Component 2. Institutional D Individual Consult s for operation management IDA / 59160 evelopment and Technical A Post Open 24,000.00 Completed 2019-11-18 2019-09-06 2020-01-06 2019-09-07 2020-01-27 2019-11-11 2020-03-02 2019-11-13 2020-08-29 2020-09-03 ant Selection assistance of the National Gri ssistance d of Uzbekistan MUTS/CS-8/1 / INTERNATION AL EXPERT FOR THE POSITIO N OF DEPUTY CHAIRMAN FOR Component 2. Institutional D Individual Consult TRANSFORMATION, DIGITIZA IBRD / 86640 evelopment and Technical A Prior Open 0.00 Canceled 2021-02-10 2021-02-18 2021-03-31 2021-04-21 2021-05-26 2021-11-22 ant Selection TION AND INFORMATION TEC ssistance HNOLOGIES OF JSC “NATION AL ELECTRIC GRID OF UZBEKISTAN MUTS/CS-8/2 / INTERNATION AL EXPERT FOR THE POSITIO Component 2. Institutional D Individual Consult Under Implement N OF INTERNATIONAL FINAN IBRD / 86640 evelopment and Technical A Post Open 0.00 2021-02-10 2021-02-18 2021-03-31 2021-04-21 2021-05-26 2021-11-22 ant Selection ation CIAL MANAGER OF JSC “NATI ssistance ONAL ELECTRIC GRID OF UZBEKISTAN Page 2 MUTS/CS-8/3 / INTERNATION AL EXPERT FOR THE POSITIO Component 2. Institutional D N OF INTERNATIONAL MANA Individual Consult Under Implement IBRD / 86640 evelopment and Technical A Post Open 0.00 2021-02-10 2021-02-18 2021-03-31 2021-04-21 2021-05-26 2021-11-22 GER FOR TRANSMISSION DEV ant Selection ation ssistance ELOPMENT OF "NATIONAL EL ECTRIC GRID OF UZBEKISTAN" MUTS/CS-8/1. / INTERNATIO NAL EXPERT FOR THE POSITI Component 2. Institutional D ON OF DEPUTY CHAIRMAN F Individual Consult Pending Impleme IBRD / 86640 evelopment and Technical A Prior Open 0.00 2021-09-16 2021-11-04 2021-11-25 2021-12-30 2022-06-28 OR TRANSFORMATION, DIGIT ant Selection ntation ssistance IZATION AND INFORMATION TECHNOLOGIES OF JSC “NATI ONAL ELECTRIC GRID OF UZB EKISTAN" MUTS/CS/4-3 / Technical Sup Component 2. Institutional D port to finalize the Bidding D IBRD / 86640 evelopment and Technical A Post Direct Selection Direct 47,000.00 Signed 2022-05-23 2022-05-27 2022-06-02 2022-05-30 2022-08-06 2022-06-21 2023-02-02 ocuments for Construction of ssistance Digital Substation 500 kV "Ko ltsevaya" MUTS/CS/4-1 / Technical sup Component 2. Institutional D Individual Consult Open - Internationa Under Implement port in bid evaluation and co IBRD / 86640 evelopment and Technical A Post 0.00 2022-08-10 2022-08-10 2022-09-28 2022-10-19 2022-11-23 2023-05-22 ant Selection l ation ntract award for ERP ssistance MUTS/CS-11 / Support PIU wi th bid evaluation processes f Component 2. Institutional D Individual Consult Open - Internationa Under Implement or new 500kV SS Kolcevaya a IBRD / 86640 evelopment and Technical A Post 0.00 2022-08-10 2022-07-20 2022-09-28 2022-09-05 2022-10-19 2022-10-14 2022-11-23 2023-05-22 ant Selection l ation nd with related 220kV and 50 ssistance 0kV overhead transmission li nes MUTS/CS/4-2 / Review of the technical specifications of th e bidding documents, suppor Component 2. Institutional D Individual Consult Open - Internationa Pending Impleme t PIU with bid preparation an IBRD / 86640 evelopment and Technical A Post 0.00 2022-10-31 2022-12-19 2023-01-09 2023-02-13 2023-08-12 ant Selection l ntation d assist PIU throughout tende ssistance r process for modernization o f the Substations in the scop e of the ESTART Project Page 3