PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-02-19 2021-12-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / V1150, IDA / D2860, IDA / 62130, TF / A7130, TF / A7131 M Executing Agency(ies): inistry of Environnement/Directorate of Environment WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 39 / Aménagement de Component 4: National Single Stage - One 2019-02- bureaux pour l’unité de IDA / V1150 A posteriori Appel d'offres Open - National 81,133.59 Résilié 2018-05-07 2018-04-06 2018-05-12 2018-06-23 2018-05-07 2018-07-23 2018-05-26 2018-08-27 2018-08-29 Coordination Envelope 23 gestion du projet WACA 59 / Travaux d'aménagement du R+1 des bureaux pour l'UGP, Construction du mur de séparation, d'un parking pour 10 voitures, un poste Component 4: National Single Stage - One 2020-04- IDA / D2860 A posteriori Appel d'offres Open - National 0.00 Annulé 2019-06-27 2019-07-02 2019-08-13 2019-09-12 2019-10-17 d'hébergement (des Coordination Envelope 14 compteurs et du groupe électrogène) et aménagement de la cour (aires de circulation et jardin) 85 / Travaux d’aménagement de la cour du Ministère de Component 2: Strengthening l'environnement, du Single Stage - One 2021-01- IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 126,079.40 Signé 2020-05-19 2020-04-24 2020-07-14 2020-08-28 développement durable et de Envelope 10 Framework la protection de la nature - en un (01) lot 114 / Travaux de construction de la clôture de Component 4: National Single Stage - One En cours 2020-12- la direction régionale des IDA / D2860 A posteriori Demande de prix Open - National 0.00 2020-07-14 2020-09-08 Coordination Envelope d'exécution 08 forestiers de la réserve de Togodo Nord à ATAKPAME 88 / Travaux d'aménagement du R+1 des bureaux pour Component 4: National Single Stage - One En attente 2021-03- IDA / D2860 A posteriori Demande de prix Limited 0.00 2020-07-12 2020-09-06 l'UGP WACA ResIP, en lot Coordination Envelope d'exécution 05 unique 104 / Travaux de protection Component 3: Strengthening Passation de d’urgence de la côte par la 2021-02- IDA / D2860 National Physical and Social A posteriori marché de gré à Direct 899,211.65 Signé 2020-07-08 2020-07-03 2020-07-13 2020-08-19 2020-08-17 2020-09-17 technique de juxtaposition de 13 Investments gré puits en fûs granulitique. TG-WACA TOGO-204668- Component 3: Strengthening Single Stage - One 2021-04- CW-RFQ / Construction de TF / A7131 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2021-01-20 2021-03-18 Envelope 17 deux (02) bâtiments à Investments TOGODO TG-WACA TOGO-204671- Component 3: Strengthening CW-RFQ / Travaux de Single Stage - One 2021-09- TF / A7130 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2021-01-25 2021-03-22 construction de deux (02) Envelope 18 Investments étangs et de deux (02) forages à TOGODO Component 2: Strengthening 92 / Travaux de construction Single Stage - One 2021-02- IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2020-07-01 2020-08-26 du siège de l'ANGE Envelope 22 Framework TG-WACA TOGO-239069- National CW-RFQ / Travaux Procurement d'aménagement Component 2: Strengthening Single Stage - One Document - 1 En attente 2022-02- (réhabilitation) de la salle de IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-09-20 2021-11-15 Envelope Envelope d'exécution 13 vidéo conférence du Framework process (Non programme de licence en Bank-SPD) océanographie de l'université de Kara TG-WACA TOGO-239044- National CW-RFB / TRAVAUX DE Procurement Component 3: Strengthening CONSTRUCTION DES UNITES Single Stage - One Document - 1 En cours 2022-07- IDA / D2860 National Physical and Social A posteriori Appel d'offres Open - National 0.00 2021-10-15 2021-08-09 2021-10-20 2021-11-19 2021-12-19 2022-01-23 DE TRANSFORMATIONS DANS Envelope Envelope d'exécution 22 Investments LES AGR PILOTES EN SEPT (07) process (Non LOTS Bank-SPD) National TG-WACA TOGO-238692- Procurement CW-RFB / Construction de Component 3: Strengthening Single Stage - One Document - 1 En attente 2022-05- forage pour les sous-projets IDA / D2860 National Physical and Social A posteriori Appel d'offres Open - National 0.00 2021-10-20 2021-10-25 2021-11-24 2021-12-24 2022-01-28 Envelope Envelope d'exécution 28 communautaire en cinq (05) Investments process (Non lots Bank-SPD) TG-WACA TOGO-255574- CW-RFB / TRAVAUX DE CONSTRUCTION ET DE National REHABILITATION DE CABINES Procurement DE TOILETTES EQUIPES DE Component 3: Strengthening Single Stage - One Document - 1 En cours 2022-06- DISPOSITIFS DE LAVE-MAIN IDA / D2860 National Physical and Social A posteriori Appel d'offres Open - National 0.00 2021-10-29 2021-08-09 2021-11-03 2021-12-03 2022-01-02 2022-02-06 Envelope Envelope d'exécution 06 DANS LES ECOLES, ET DE Investments process (Non CONSTRUCTION DE TOILETTES Bank-SPD) ECOSAN DANS LES MENAGES DE LA COMMUNE DES LACS 1( en 04 lots) TG-WACA TOGO-222964- National CW-RFQ / renforcement Procurement Component 3: Strengthening (travaux de réhabilitation) du Single Stage - One Document - 1 2022-07- IDA / D2860 National Physical and Social A posteriori Demande de prix Open - National 0.00 Annulé 2021-11-02 2022-01-25 poste secours d'urgence (PSR) Envelope Envelope 24 Investments du corps des sapeurs - process (Non pompiers de la Région de Bank-SPD) Lomé Nord Page 1 TG-WACA TOGO-239057- CW-RFB / construction de National trois (03) postes de relais Procurement Component 2: Strengthening forestiers équipés de Single Stage - One Document - 1 2022-06- TF / A7130 the Policy and Institutional A posteriori Appel d'offres Open - National 0.00 Annulé 2021-10-25 2021-10-30 2021-11-29 2021-12-29 2022-02-02 panneaux solaires et de Envelope Envelope 02 Framework forages à motricité humaine process (Non dans le complexe d’aires Bank-SPD) protégées de Togodo. Request for TG-WACA TOGO-239048- Component 2: Strengthening Bids - Small Single Stage - One 2022-07- CW-RFB / Réhabilitation de la TF / A7130 the Policy and Institutional A posteriori Appel d'offres Open - National Works SPD (1 0.00 Annulé 2021-10-29 2021-11-03 2021-12-03 2022-01-02 2022-02-06 Envelope 06 brigade de Togodo Nord Framework envelope process) National Procurement TG-WACA TOGO-255877- Component 3: Strengthening Single Stage - One Document - 1 En attente 2022-07- CW-RFQ / Réhabilitation de la TF / A7130 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-12-05 2022-01-30 Envelope Envelope d'exécution 29 brigade de Togodo Nord Investments process (Non Bank-SPD) TG-WACA TOGO-255863- National CW-RFQ / renforcement Procurement Component 3: Strengthening (travaux de réhabilitation) du Single Stage - One Document - 1 En attente 2022-05- IDA / D2860 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-11-20 2022-01-15 poste secours d'urgence (PSR) Envelope Envelope d'exécution 15 Investments du corps des sapeurs - process (Non pompiers de la Région de Bank-SPD) Lomé Nord TG-WACA TOGO-255873- National CW-RFQ / construction de Procurement Component 3: Strengthening trois (03) postes de relais Single Stage - One Document - 1 En attente 2022-07- TF / A7130 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-11-24 2022-01-19 forestiers équipés de Envelope Envelope d'exécution 18 Investments panneaux solaires dans le process (Non complexe d’aires protégées Bank-SPD) de Togodo. National TG-WACA TOGO-238677- Procurement CW-RFB / Construction de Component 3: Strengthening Single Stage - One Document - 1 2022-03- toilette dans les ménages (12 IDA / D2860 National Physical and Social A posteriori Appel d'offres Open - National 0.00 Annulé 2021-08-03 2021-08-08 2021-09-07 2021-10-07 2021-11-11 Envelope Envelope 11 lots) et dans les écoles en six Investments process (Non (06) lots soit en 18 lots au Bank-SPD) total TG-WACA TOGO-204666- Component 3: Strengthening CW-RFB / Réhabilitation de 90 Single Stage - One 2021-08- TF / A7130 National Physical and Social A posteriori Appel d'offres Open - National 0.00 Annulé 2021-01-06 2021-01-11 2021-02-10 2021-03-12 2021-04-16 km de piste, 7 ponceaux et 15 Envelope 14 Investments radiers à Togodo TG-WACA TOGO-262261- Request for CW-RFQ / construction et Component 3: Strengthening Single Stage - One Quotations En attente 2022-03- équipement de trois forages TF / A7130 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-01-02 2022-02-27 Envelope (Non Bank- d'exécution 29 dans le complexe forestier de Investments SPD) Togodo GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 35 / Acquisition de matériels Component 4: National Single Stage - One IDA / V1150 A posteriori Demande de prix Limited 0.00 Annulé 2018-05-13 2018-07-08 2019-01-04 informatiques Coordination Envelope 37 / Acquisition du mobilier Component 4: National Single Stage - One de bureau pour la IDA / V1150 A posteriori Demande de prix Limited 23,847.22 Signé 2018-07-17 2018-09-03 2018-09-11 2018-10-25 2019-03-10 Coordination Envelope coordination du projet 34 / Achat de fournitures de bureau, matériels de bureau et matériels d'entretien de bureau en 03 lots. Lot 1 fournitures de bureau Component 4: National Single Stage - One IDA / V1150 A posteriori Demande de prix Limited 7,637.09 Signé 2018-02-03 2018-02-16 2018-03-31 2018-08-08 2018-09-27 (papiers rames, bics,..) Coordination Envelope Lot 2 matériels de bureau (reliure) et Lot 3 matériels d'entretien de bureau (gel désinfectant, ...). 35 BIS / Acquisition de fournitures informatiques et de matériels informatiques en 02 lots : Lot 1 fournitures informatiques (cartouches Component 4: National Single Stage - One IDA / V1150 A posteriori Demande de prix Limited 26,469.61 Signé 2018-01-09 2018-01-11 2018-03-06 2018-08-08 2018-09-02 d'encre, antivirus, disques Coordination Envelope durs) et Lot 2 matériels informatiques (ordinateurs de bureau, ordinateurs portables, scanners ..) 41BIS / Le matériel roulant sera composé comme suit : Lot 1: 2 pick-up 4x4 double Component 4: National Single Stage - One cabine tropicalisés pour les IDA / D2860 A posteriori Demande de prix Limited 172,009.80 Signé 2019-04-20 2019-10-10 2019-06-15 2020-05-26 2019-12-12 Coordination Envelope missions de terrain, Lot2: 01 station wagon , Lot3: 01 mini bus. 65 / Acquisition de matériel Component 4: National Single Stage - One roulant (moto) pour les 7 TF / A7130 A posteriori Demande de prix Limited 0.00 Annulé 2019-07-01 2019-08-26 2020-02-22 Coordination Envelope CPDD et le coursier de l'UGP 66 / Acquisition de GPS pour les CPDD (07) et l'unité de Component 4: National Single Stage - One En cours TF / A7130 A posteriori Demande de prix Limited 0.00 2019-07-02 2019-09-10 2019-08-27 2020-02-23 gestion du projet (5) soit au Coordination Envelope d'exécution total 12 GPS 58 / Acquisition de matériel et fourniture informatique pour le projet (Ordinateur bureau +portable en poste de trav, copieur, imprimante Component 4: National Single Stage - One IDA / D2860 A posteriori Demande de prix Limited 0.00 Annulé 2019-06-16 2019-08-11 2020-02-07 couleur, blanc noir, clé USB Coordination Envelope multi copieur, disque dure, vidéo projecteur, onduleurs, modem pour connexion Wifi, camera... Page 2 74 / Acquisition de 2 Component 2: Strengthening véhicules de terrain pour Single Stage - One IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2019-06-26 2019-08-21 2020-02-17 l'Agence Nationale de Gestion Envelope Framework de l'Environnement 93 / Fournitures de bureau Component 4: National Single Stage - One En attente pour l'UGP ( Accord cadre TF / A7130 A posteriori Demande de prix Open 0.00 2020-04-20 2020-06-15 2020-12-12 Coordination Envelope d'exécution attribution par article) 98 / Production des supports Component 4: National Single Stage - One IDA / D2860 A posteriori Demande de prix Open - National 16,660.05 Signé 2020-04-14 2020-06-09 2021-05-14 2020-12-06 de communications - un lot Coordination Envelope 83 / Acquisition de matériel et fourniture informatique, et matériels bureautique pour Component 2: Strengthening Single Stage - One les CPDD, l'ANGE,Direction de IDA / D2860 the Policy and Institutional A posteriori Appel d'offres Open - National 229,876.88 Signé 2020-06-25 2020-07-23 2020-06-30 2020-08-11 2020-09-25 2020-09-10 2020-10-26 2020-10-15 2021-04-23 2021-01-15 Envelope l'Environnement, Economie Framework Bleue et l'UGP WACA - Lot unique 97 / Réalisation des films Component 4: National Single Stage - One En cours IDA / D2860 A posteriori Demande de prix Open - National 0.00 2020-05-27 2020-07-22 2021-01-18 documentaires Coordination Envelope d'exécution 107 / Acquisition de Passation de Component 2: Strengthening matériels roulants pour le marchés auprès IDA / D2860 the Policy and Institutional A posteriori Direct 0.00 Annulé 2020-06-02 2020-06-07 2020-07-12 2020-09-30 Haut Conseil pour la Mer, des agences de Framework l’ANGE et l’UGP WACA ResIP l'ONU 84BIS / Acquisition de Passation de Component 2: Strengthening matériels roulants (engins TP) marchés auprès IDA / D2860 the Policy and Institutional A posteriori Direct 0.00 Annulé 2020-06-02 2020-06-07 2020-07-12 2020-11-12 pour la Mairie d’Aného – lot des agences de Framework unique l'ONU 81 / Acquisition de matériels Component 2: Strengthening roulants pour le Single Stage - One IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2020-04-13 2020-06-08 2020-12-05 développement de l'économie Envelope Framework bleue et l'ANGE - 02 Lots 109 / Acquisition de trois Component 4: National Single Stage - One (03) téléphones portables IDA / D2860 A posteriori Demande de prix Limited 3,558.26 Signé 2020-08-16 2020-09-08 2020-10-11 2020-09-14 2020-10-27 Coordination Envelope pour l’UGP WACA ResIP 118 / Acquisition de mobilier Component 2: Strengthening Single Stage - One En cours de bureau pour l'ANGE et IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2020-10-05 2021-05-18 2020-11-30 2021-01-28 Envelope d'exécution l'Economie Bleue Framework 120 / Acquisition de technologie des systèmes aériens sans pilotes (drone, Component 2: Strengthening logiciels, de matériel et Single Stage - One En cours IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2020-10-05 2020-11-30 2021-03-01 fourniture informatiques, Envelope d'exécution Framework Formations) pour la production d'une cartographie 2D et 3D de gestion de la côte TG-WACA TOGO-211741-GO- Passation de Component 2: Strengthening UN / Acquisition de matériel marchés auprès IDA / D2860 the Policy and Institutional A posteriori Direct 1,310,421.00 Signé 2020-10-15 2020-06-02 2020-10-16 2020-11-25 2020-11-22 2020-12-11 2021-02-20 roulant pour la coordination des agences de Framework et les partenaires l'ONU TG-WACA TOGO-223544-GO- RFQ / Edition et vulgarisation Component 2: Strengthening Single Stage - One En attente du guide d'intégration de IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-05-31 2021-07-26 2021-08-25 Envelope d'exécution l'économie bleu dans les Framework documents de planification TG-WACA TOGO-222191-GO- RFQ / Achat de véhicule Component 2: Strengthening Station WAGON pour le Single Stage - One En attente IDA / 62130 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-05-25 2021-07-20 2021-08-19 Ministère de la Protection Envelope d'exécution Framework côtière, de la Pêche et de l'Economie Maritime TG-WACA TOGO-223503-GO- RFQ / Equipements de suivi et Component 2: Strengthening Single Stage - One En attente surveillance pour les TF / A7130 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-07-05 2021-08-30 2021-09-29 Envelope d'exécution communautés locales (30 Framework tablettes ) TG-WACA TOGO-234936-GO- Component 2: Strengthening Single Stage - One En attente RFQ / achat de deux (02) TF / A7130 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-08-04 2021-09-29 2021-11-28 Envelope d'exécution drones Framework TG-WACA TOGO-232179-GO- RFQ / Acquisition de matériel pour la vidéoconférence pour Component 4: National Single Stage - One En attente la salle de réunion de l'UGP IDA / 62130 A posteriori Demande de prix Limited 0.00 2021-07-20 2021-09-14 2021-10-14 Coordination Envelope d'exécution (lot1) et pour la faculté de géographie de l'université de Kara (lot2) TG-WACA TOGO-249718-GO- RFQ / ACQUISITION DE Component 4: National Single Stage - One En attente MOBILIER DE BUREAU POUR IDA / D2860 A posteriori Demande de prix Limited 0.00 2021-10-05 2021-11-30 2021-12-30 Coordination Envelope d'exécution L'UNITE DE COORDINATION NATIONALE TG-WACA TOGO-223532-GO- RFQ / Acquisition d'équipement pour la mise en place d'une base de données Component 2: Strengthening Single Stage - One En attente de gestion des ouvrages IDA / D2860 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-11-20 2022-01-15 2022-04-15 Envelope d'exécution côtiers (serveur, ordinateurs Framework portables, disque durs externe, appareil photo professionnel, etc...) TG-WACA TOGO-223620-GO- RFQ / acquisition de matériel Component 2: Strengthening et équipement de laboratoire Single Stage - One En attente IDA / D2860 the Policy and Institutional A posteriori Appel d'offres Open - National 0.00 2021-11-15 2021-11-20 2021-12-20 2022-01-19 2022-02-23 2022-05-24 pour les départements de Envelope d'exécution Framework géographie des universités de Lomé et Kara Page 3 TG-WACA TOGO-260437-GO- RFB / FOURNITURE ET INSTALLATION DE MINI CENTRALES SOLAIRES AVEC RESEAU ELECTRIQUE, DE PLATEFORMES Component 3: Strengthening MULTIFONCTIONNELLES Single Stage - One En attente TF / A7130 National Physical and Social A posteriori Appel d'offres Open - National 0.00 2021-12-21 2021-12-26 2022-01-25 2022-02-24 2022-03-31 2022-07-29 ALIMENTEES PAR LA Envelope d'exécution Investments CENTRALE SOLAIRE ET DES KITS DE LAMPADAIRES AUTONOMES EN 04 LOTS DANS 04 LOCALITES (Adamé, Afito, Godjinmé et Nyamassiva) TG-WACA TOGO-265102-GO- RFQ / Fourniture et Component 4: National Single Stage - One En attente IDA / D2860 A posteriori Demande de prix Limited 0.00 2022-01-02 2022-02-27 2022-08-26 installation de groupe Coordination Envelope d'exécution électrogène NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 36 / Edition du plan d'investissement et du Component 4: National Single Stage - One document d'analyse du cadre IDA / V1150 A posteriori Demande de prix Limited 20,365.63 Signé 2018-02-21 2018-02-16 2018-04-18 2018-08-01 2018-10-15 Coordination Envelope juridique institutionnel de gestion intégrée du littoral 38 / Paramétrage du logiciel Passation de Component 4: National En cours de gestion financière du IDA / V1150 A posteriori marché de gré à Direct 0.00 2018-07-05 2018-11-14 2018-07-10 2018-11-14 2018-08-14 2019-02-10 Coordination d'exécution PGICT pour le projet WACA gré 52 / Recrutement d'un Component 4: National Single Stage - One En cours IDA / D2860 A posteriori Demande de prix Limited 0.00 2019-06-29 2020-06-08 2019-08-24 2020-02-20 service d'entretien Coordination Envelope d'exécution 77 / Police d'assurance pour Component 4: National Single Stage - One En cours le personnel recruté par le IDA / D2860 A posteriori Demande de prix Limited 0.00 2019-11-25 2019-09-10 2020-01-20 2020-07-18 Coordination Envelope d'exécution projet WACA ResIP 17 BIS / Mise en place d'un système informatisé de suivi Component 4: National Single Stage - One du projet (acquisition, IDA / D2860 A posteriori Appel d'offres Open - National 0.00 Annulé 2019-02-20 2019-05-08 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2019-12-09 Coordination Envelope installation et formation des utilisateurs) 119 / Service de gardiennage Component 4: National Single Stage - One IDA / D2860 A posteriori Demande de prix Limited 8,602.22 Signé 2020-08-17 2020-09-09 2020-10-12 2021-04-23 2021-10-09 des bureaux de l'UGP Coordination Envelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 14 / Etude de faisabilité Component 3: Strengthening Sélection fondée technique de la protection IDA / V1150 National Physical and Social A priori sur la qualité et le Open - International 0.00 Annulé 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 côtière du segment Investments coût transfrontalier Bénin-Togo 15 / Etude d'Impact Environnemental et Social Component 2: Strengthening Sélection fondée (EIES) de la protection côtière IDA / V1150 the Policy and Institutional A posteriori sur la qualité et le Open - International 0.00 Annulé 2018-02-08 2018-03-01 2018-04-14 2018-05-12 2018-06-11 2018-07-16 2018-08-20 2019-08-20 du segment transfrontalier Framework coût Bénin-Togo 19 / Etude d'Impact Environnemental et Social Sélection fondée Component 2: Strengthening (EIES) pour le curage sur les IDA / V1150 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 mécanique du chenal Gbaga qualifications des Framework et de restauration de ces consultants écosystèmes associés 46 / Evaluation du coût de la Sélection fondée Component 2: Strengthening dégradation historique de la sur les IDA / D2860 the Policy and Institutional A posteriori Open - National 149,746.25 Signé 2019-01-17 2019-05-22 2019-02-07 2019-07-08 2019-03-23 2019-11-28 2019-04-22 2020-12-22 2019-05-27 2021-04-23 2019-11-23 côte y compris la vulnérabilité qualifications des Framework des communautés côtières consultants 42BIS / Etude de faisabilité technique de l'installation Component 3: Strengthening Sélection fondée d'une vanne au niveau du IDA / D2860 National Physical and Social A priori sur la qualité et le Open - International 0.00 Annulé 2019-03-05 2019-03-26 2019-05-09 2019-06-06 2019-07-06 2019-08-10 2019-09-14 2020-09-13 pont de la lagune d'Aného et Investments coût l'étude hydrodynamique du système fluvio-lagunaire 43 / Etude approfondie de Component 3: Strengthening Sélection fondée faisabilité du traitement des IDA / 62130 National Physical and Social A priori sur la qualité et le Open - International 0.00 Annulé 2019-03-12 2019-04-02 2019-05-16 2019-06-13 2019-07-13 2019-08-17 2019-09-21 2020-09-20 boues de phosphates rejetées Investments coût en mer Sélection fondée 44 / Elaboration du plan Component 4: National IDA / D2860 A posteriori sur la qualité et le Open - International 0.00 Annulé 2019-02-11 2019-03-04 2019-04-17 2019-05-15 2019-06-14 2019-07-19 2019-08-23 2020-08-22 spatial marin et côtier Coordination coût Component 2: Strengthening Sélection fondée 45 / Evaluation du capital IDA / D2860 the Policy and Institutional A posteriori sur la qualité et le Open - International 0.00 Annulé 2019-02-12 2019-03-05 2019-04-18 2019-05-16 2019-06-15 2019-07-20 2019-08-24 2020-08-23 naturel de la zone côtière Framework coût 49 / Audits financiers et Component 4: National Sélection au comptables du projet - IDA / D2860 A posteriori Open - National 24,687.83 Signé 2019-02-11 2019-04-18 2019-03-04 2019-07-08 2019-04-17 2019-10-10 2019-05-15 2020-02-06 2019-06-14 2020-03-11 2019-07-19 2020-05-19 2019-08-23 2020-06-29 2020-02-19 Coordination moindre coût exercices 2017, 2018 et 2019 Page 4 3 BIS / Etudes de faisabilité techniques de dragage et de stabilisation des berges de la Component 3: Strengthening Sélection fondée lagune et du lac Togo, et pour IDA / D2860 National Physical and Social A posteriori sur la qualité et le Open - International 1,061,119.41 Signé 2018-10-04 2018-05-18 2018-10-25 2018-12-08 2019-08-28 2019-01-05 2019-10-10 2019-02-04 2019-10-25 2019-03-11 2019-12-13 2019-04-15 2020-08-26 2020-04-14 la Construction et le curage Investments coût de caniveau, de bassin d'orage, de retenue d'eau 48 / Etude d'Impact Environnemental et Social Sélection fondée Component 3: Strengthening (EIES) pour le curage sur les TF / A7130 National Physical and Social A posteriori Open - National 0.00 Annulé 2018-12-28 2019-01-03 2019-01-18 2019-03-03 2019-04-02 2019-05-07 2019-11-03 mécanique du chenal Gbaga qualifications des Investments et de restauration de ces consultants écosystèmes associés 47B / Etude de faisabilité technique pour le curage Component 3: Strengthening Sélection fondée mécanique du chenal de TF / A7130 National Physical and Social A priori sur la qualité et le Open - International 554,086.35 Signé 2019-04-26 2019-04-18 2019-05-17 2019-07-23 2019-06-30 2020-10-17 2019-07-28 2020-10-26 2019-08-27 2021-01-14 2019-10-01 2021-04-13 2019-11-05 2021-06-18 2020-11-04 Gbaga et de la restauration de Investments coût ces écosystèmes associés 47 / Etude de faisabilité technique du curage Component 3: Strengthening Sélection fondée mécanique du chenal Gbaga TF / A7130 National Physical and Social A posteriori sur la qualité et le Open - International 0.00 Annulé 2018-12-28 2019-01-03 2019-01-18 2019-03-03 2019-03-31 2019-04-30 2019-06-04 2019-07-09 2020-07-08 et de restauration de ces Investments coût écosystèmes associés 48B / Etude d'Impact Environnemental et Social Sélection fondée Component 3: Strengthening (EIES) pour le curage sur les En cours TF / A7130 National Physical and Social A posteriori Open - International 0.00 2019-04-26 2019-04-17 2019-05-17 2019-06-30 2019-08-13 2019-07-30 2018-08-08 2019-09-03 2020-03-01 mécanique du chenal Gbaga qualifications des d'exécution Investments et de restauration de ces consultants écosystèmes associés Sélection fondée 40 / Surveillance et contrôle Component 4: National sur les des travaux d'aménagement IDA / V1150 A posteriori Open - National 0.00 Annulé 2018-07-11 2018-08-01 2018-09-14 2018-10-14 2018-11-18 2019-05-17 Coordination qualifications des des bureaux du Projet WACA consultants 62 / Élaboration du plan Sélection fondée Component 3: Strengthening d'aménagement participatif et sur les TF / A7130 National Physical and Social A posteriori Open - International 154,345.80 Signé 2019-08-28 2020-01-07 2019-09-18 2020-06-26 2019-11-01 2020-10-26 2019-12-01 2021-02-09 2020-01-05 2021-04-23 2020-07-03 des outils de gestion de la qualifications des Investments forêt communautaire d'Avévé  consultants 63 / Elaboration du plan Sélection fondée d'aménagement participatif et Component 3: Strengthening sur les des outils de gestion de la TF / A7130 National Physical and Social A posteriori Open - International 154,345.80 Signé 2019-08-28 2020-01-07 2019-09-18 2020-06-26 2019-11-01 2020-10-15 2019-12-01 2021-02-09 2020-01-05 2021-04-23 2020-07-03 qualifications des forêt communautaire de Kodjo- Investments consultants Gati 60 / Recrutement d'une structure ( centre de Sélection fondée formation) pour la formation Component 3: Strengthening sur les En cours et l'accompagnement des TF / A7130 National Physical and Social A posteriori Open - National 244,722.82 2019-08-28 2019-08-21 2019-09-18 2019-11-01 2020-05-05 2019-12-01 2020-06-10 2020-01-05 2020-07-03 qualifications des d'exécution acteurs communautaires sur Investments consultants les bonnes pratiques en gestion durable des terres. 82 / Etude sur la situation des plantes envahissantes, Sélection fondée des modèles de gestion et de Component 3: Strengthening sur les En cours valorisation dans la sous- TF / A7130 National Physical and Social A posteriori Open - International 0.00 2019-12-30 2020-03-30 2020-01-20 2020-03-04 2020-04-03 2020-05-08 2020-11-04 qualifications des d'exécution région et les applications Investments consultants possibles dans la zone du projet 40 C / Surveillance et contrôle des travaux d'aménagement du R + 1 des Sélection fondée bureaux de l'UGP, Component 4: National sur les Construction du mur de IDA / D2860 A posteriori Open - National 0.00 Annulé 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 Coordination qualifications des séparation, d'un parking pour consultants 10 voitures, d'un poste d'achat et d'un aménagement de cour. 105 / Recrutement d'un cabinet pour l'actualisation de l'étude de faisabilité technique du projet d'assainissement Component 3: Strengthening Sélection fondée des eaux usées à la plage de En cours IDA / D2860 National Physical and Social A posteriori sur la qualité et le Open - International 0.00 2020-06-30 2020-09-16 2020-07-21 2021-01-20 2020-09-03 2021-04-15 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2022-01-09 Lomé, réhabilitation du réseau d'exécution Investments coût embryonnaire d'assainissement collectif des eaux usées de la ville de Lomé au Togo 121 / Recrutement d'un cabinet pour le contrôle et surveillance des travaux Sélection fondée Component 3: Strengthening d’urgence de protection sur les IDA / D2860 National Physical and Social A posteriori Limited 90,871.35 Signé 2020-08-07 2020-08-09 2020-08-21 2020-08-25 2020-09-20 2020-11-10 2020-10-25 2021-02-01 2021-02-24 contre l’érosion côtière des qualifications des Investments habitations vulnérables sur le consultants littoral togolais allant de Gbodjomé à Agbodrafo. TG-WACA TOGO-224375-CS- Sélection fondée CDS / Etude de faisabilité Component 3: Strengthening sur les En attente technique de la mise en place IDA / 62130 National Physical and Social A posteriori Open - International 0.00 2021-11-30 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 qualifications des d'exécution d'un bypass au port autonome Investments consultants de Lomé TG-WACA TOGO-223531-CS- CQS / Etude de faisabilité Sélection fondée Component 2: Strengthening technique pour la création et sur les IDA / D2860 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2021-06-30 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 l'opérationnalisation de qualifications des Framework l'observatoire national sur le consultants littoral TG-WACA TOGO-222420-CS- CQS / Elaboration de la carte Sélection fondée Component 2: Strengthening de vulnérabilité de la côte sur les En attente TF / A7130 the Policy and Institutional A posteriori Open - National 0.00 2021-06-10 2021-07-01 2021-08-14 2021-09-13 2021-10-18 2022-01-16 togolaise face aux menaces qualifications des d'exécution Framework de pollution par les consultants hydrocarbures (ABC) Page 5 Sélection fondée TG-WACA TOGO-223546-CS- Component 2: Strengthening sur les En attente CQS / Elaboration du plan IDA / D2860 the Policy and Institutional A posteriori Open - National 0.00 2021-07-08 2021-07-29 2021-09-11 2021-10-11 2021-11-15 2021-11-27 qualifications des d'exécution spatial marin et côtier Framework consultants Sélection fondée 78 / Assistance technique et Component 2: Strengthening sur les contrôle des activités TF / A7130 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2020-01-14 2020-01-15 2020-02-04 2020-03-19 2020-04-18 2020-05-23 2020-11-19 qualifications des communautaires Framework consultants 113 / Etude d'avant projet détaillé (APD) pour la Sélection fondée construction de la nouvelle Component 4: National sur les direction régionale des IDA / D2860 A posteriori Open - National 0.00 Annulé 2020-07-27 2020-08-17 2020-09-30 2020-10-30 2020-12-04 2021-06-02 Coordination qualifications des forestiers de la réserve de consultants faune de Togodo Nord à Atakpamé INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1 / Elaboration du Cadre de Component 2: Strengthening Gestion Environnementale et IDA / V1150 the Policy and Institutional A posteriori Individuel Limited 23,893.15 Signé 2017-07-18 2017-06-22 2017-07-23 2017-09-07 2018-01-29 2017-09-28 2018-03-05 2017-11-29 2018-07-17 Sociale (CGES) Framework 2 / Elaboration du Cadre de Component 2: Strengthening Politique de Réinstallation IDA / V1150 the Policy and Institutional A posteriori Individuel Limited 20,223.92 Signé 2017-06-22 2017-06-22 2017-08-24 2017-09-07 2017-09-29 2017-09-29 2017-11-29 2017-11-29 2018-01-12 (CPR) Framework 4 / Etude d'impact environnemental et social des Component 2: Strengthening En cours dragages et de la construction IDA / V1150 the Policy and Institutional A posteriori Individuel Limited 0.00 2017-11-12 2017-11-12 2018-01-27 2018-01-22 2018-02-17 2018-08-08 2018-03-24 2018-04-24 d'exécution des ouvrages de lutte contre Framework les inondations 13 / Elaboration de la Sélection de Component 4: National stratégie de passation des IDA / V1150 A posteriori consultants par Direct 13,130.33 Signé 2017-12-12 2017-12-12 2017-12-22 2017-12-22 2018-02-09 2018-08-29 2018-03-29 Coordination marchés (PPSD) entente directe 6 / Recrutement d'un Component 4: National spécialiste en passation des IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination marchés 8 / Recrutement d'un Component 4: National IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 spécialiste en suivi-évaluation Coordination 9 / Recrutement d'un Component 4: National spécialiste en sauvegarde IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination sociale 10 / Recrutement d'un Component 4: National IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 spécialiste en communication Coordination 9 BIS / Recrutement d'un Component 4: National En cours spécialiste en sauvegarde IDA / V1150 A posteriori Individuel Open 0.00 2018-04-26 2018-05-18 2018-06-14 2018-07-05 2019-04-18 2018-08-09 2019-02-05 Coordination d'exécution sociale 10 BIS / Recrutement d'un Component 4: National En cours IDA / V1150 A posteriori Individuel Open 0.00 2018-06-03 2018-02-18 2018-07-22 2019-04-11 2018-08-12 2019-06-28 2018-09-16 2019-03-15 spécialiste en communication Coordination d'exécution 7 / Recrutement d'un Component 4: National En cours ingénieur génie civil (génie IDA / V1150 A posteriori Individuel Open 0.00 2018-05-17 2018-08-13 2018-07-05 2018-07-26 2019-04-18 2018-08-30 2019-02-26 Coordination d'exécution côtier) 27 / Recrutement d'un Component 4: National En cours IDA / V1150 A posteriori Individuel Open 0.00 2018-05-24 2019-02-03 2018-07-12 2019-06-25 2018-08-02 2018-09-06 2019-03-05 auditeur interne du projet Coordination d'exécution 11 / Recrutement de Component 4: National IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 secrétaire caissière Coordination 7 / Recrutement d'un Component 4: National ingénieur génie civil (génie IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 Coordination côtier) 3 / Réalisation d'études Component 3: Strengthening techniques d'ouvrages de IDA / V1150 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2017-11-08 2017-11-13 2018-03-26 2018-04-30 2018-10-27 lutte contre les inondations Investments 12 / Recrutement d'un Component 4: National IDA / V1150 A posteriori Individuel Limited 0.00 Annulé 2017-11-08 2017-11-13 2017-12-04 2018-01-08 2018-07-07 Assistant technique au projet Coordination 25 / Recrutement d'un Component 4: National assistant en passation des IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-04-26 2018-06-14 2018-07-05 2018-08-09 2019-02-05 Coordination marchés 24 BIS / Recrutement d'un Component 4: National En cours spécialiste en gestion IDA / D2860 A posteriori Individuel Open 0.00 2018-08-29 2018-09-18 2018-11-02 2018-11-23 2019-04-18 2018-12-28 2019-06-26 Coordination d'exécution financière 24 / Recrutement d'un Component 4: National assistant au spécialiste en IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-08-29 2018-10-31 2018-11-21 2018-12-26 2019-06-24 Coordination gestion financière 50 / Etude pour la mise en place du système national d'informations côtières Component 2: Strengthening En cours (Définition et harmonisation IDA / D2860 the Policy and Institutional A posteriori Individuel Open 0.00 2019-04-02 2019-06-05 2019-05-21 2019-06-11 2019-07-16 2020-01-12 d'exécution des standards de collecte, Framework traitement et diffusion de données pour l'observatoire) Page 6 6 BIS / Recrutement d'un Component 4: National spécialiste en passation des IDA / D2860 A posteriori Individuel Open 37,051.31 Signé 2018-08-27 2018-10-31 2019-02-15 2018-11-21 2019-08-19 2018-12-26 2019-08-09 2019-06-24 Coordination marchés 69 / Actualisation des Component 2: Strengthening manuels de procédure de IDA / D2860 the Policy and Institutional A posteriori Individuel Open 13,023.07 Signé 2019-06-17 2019-06-07 2019-08-05 2020-11-17 2019-08-26 2020-11-23 2019-09-30 2021-04-23 2020-03-28 l'ANGE Framework 67 / Élaboration du plan de développement des Component 2: Strengthening Ressources Humaines du TF / A7130 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2019-06-19 2019-06-17 2019-08-07 2019-08-28 2019-10-02 2020-03-30 Ministère de l'Environnement, Framework du Développement Durable et de la Protection de la Nature 64 / Appui à l'analyse institutionnelle du Ministère de l'Environnement, du Développement Durable et de Component 2: Strengthening la Protection de la Nature TF / A7130 the Policy and Institutional A posteriori Individuel Open 16,668.25 Signé 2019-06-19 2019-06-07 2019-08-07 2020-11-17 2019-08-28 2020-11-23 2019-10-02 2021-04-23 2020-03-30 relative à la mise en œuvre Framework des conventions internationales signées par le Togo Component 3: Strengthening 68 / Élaboration du cadre En cours TF / A7130 National Physical and Social A posteriori Individuel Open 0.00 2019-06-17 2019-06-07 2019-08-05 2019-11-04 2019-08-26 2019-02-07 2019-09-30 2020-03-28 fonctionnel (procédural) d'exécution Investments 40B / Surveillance contrôle des Travaux d'aménagement du R+1 des bureaux pour l'UGP, Construction du mur de séparation, d'un parking pour Component 4: National IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2019-06-20 2019-08-08 2019-08-29 2019-10-03 2020-03-31 10 voitures, un poste Coordination d'hébergement (des compteurs et du groupe électrogène) et aménagement de la cour 61 / Élaboration des textes Component 2: Strengthening d'application de la loi sur le IDA / D2860 the Policy and Institutional A posteriori Individuel Open 22,801.19 Signé 2019-06-20 2019-06-07 2019-08-08 2020-12-18 2019-08-29 2021-01-04 2019-10-03 2021-04-23 2020-03-31 littoral Framework 53 / Recrutement d'un (01) Component 4: National IDA / D2860 A posteriori Individuel Open 4,603.46 Signé 2019-06-26 2019-08-21 2019-08-14 2020-05-13 2019-09-04 2020-09-03 2019-10-09 2020-09-21 2020-04-06 coursier Coordination 55 / Recrutement de deux (2) Component 4: National chauffeurs de permis IDA / D2860 A posteriori Individuel Open 20,845.12 Signé 2019-07-12 2019-08-21 2019-08-30 2020-06-02 2019-09-20 2020-07-15 2019-10-25 2020-09-21 2020-04-22 Coordination catégorie B 54 / Recrutement d'un (01) Component 4: National chauffeur de permis catégorie IDA / D2860 A posteriori Individuel Open 0.00 Annulé 2019-08-22 2019-08-21 2019-10-10 2019-10-31 2019-12-05 2020-06-02 Coordination C 75 / Recrutement d'un Component 4: National Coordonnateur du projet IDA / D2860 A posteriori Individuel Open 40,385.61 Signé 2019-08-19 2019-08-20 2019-10-07 2020-03-04 2019-10-28 2020-03-11 2019-12-02 2020-05-26 2020-05-30 Coordination WACA ResIP 75BIS / Recrutement de Component 4: National coordonnateur pour le projet IDA / D2860 A posteriori Individuel Open 40,486.37 Signé 2019-11-20 2019-11-08 2019-12-23 2020-03-13 2020-01-06 2020-03-25 2020-02-10 2020-05-26 2020-08-08 Coordination WACA ResIP 91 / Recrutement d'un Component 4: National En cours secrétaire administratif pour IDA / D2860 A posteriori Individuel Open 0.00 2020-04-09 2020-07-30 2020-05-28 2020-06-18 2020-07-23 2021-01-19 Coordination d'exécution l'UGP WACAResIP 89 / Recrutement de consultant individuel environnementaliste pour le Component 2: Strengthening contrôles des travaux TF / A7130 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 d'aménagement de la cour du Framework MEDDPN et des bureaux de l'UGP (RDC et R+1) 20 / Recrutement d'un Component 4: National spécialiste en développement IDA / V1150 A posteriori Individuel Open 0.00 Annulé 2018-06-03 2018-07-22 2019-06-25 2018-08-12 2019-08-19 2018-09-16 2019-03-15 Coordination institutionnel 106 / Recrutement d'un consultant pour la réalisation de l'EIES du projet d'assainissement des eaux Component 3: Strengthening usées à la plage de Lomé, En cours IDA / D2860 National Physical and Social A posteriori Individuel Open 0.00 2020-06-02 2020-11-11 2020-07-21 2020-08-11 2020-09-15 2021-01-15 réhabilitation du réseau d'exécution Investments embryonnaire d'assainissement collectif des eaux usées de la ville de Lomé- Togo 111 / Recrutement d'un Component 4: National expert en passation de IDA / D2860 A posteriori Individuel Open 34,987.56 Signé 2020-05-29 2020-05-25 2020-07-17 2020-07-23 2020-08-07 2020-10-02 2020-09-11 2020-11-20 2021-09-10 Coordination marché pour le projet WACA ResIP 115 / Recrutement d'un Component 4: National auditeur interne pour le projet IDA / D2860 A posteriori Individuel Open 0.00 Annulé 2020-06-03 2020-07-22 2020-08-12 2020-09-16 2021-11-30 Coordination WACA ResIP 101 / Recrutement de consultant individuel génie électromécanique pour le Component 2: Strengthening contrôle des travaux IDA / D2860 the Policy and Institutional A posteriori Individuel Open 15,039.77 Signé 2020-07-10 2020-06-16 2020-08-28 2020-09-23 2020-09-18 2021-03-24 2020-10-23 2021-04-23 2021-06-23 d'aménagement du cadre de Framework travail de l'ANGE et du bâtiment R+1 de l'UGP WACA ResiP 90 / Recrutement d’un secrétaire pour la passation Component 4: National de marché et la gestion IDA / D2860 A posteriori Individuel Open 11,146.14 Signé 2020-06-30 2020-08-11 2020-08-18 2021-03-15 2020-09-08 2021-05-10 2020-10-13 2021-06-15 2021-04-11 Coordination financière du projet WACA ResIP Page 7 117 / Recrutement d'un Component 4: National spécialiste en communication IDA / D2860 A posteriori Individuel Open 0.00 Annulé 2020-08-12 2020-09-30 2020-10-21 2020-11-25 2021-11-24 Coordination pour le projet WACA ResIP 122 / Mise en place d'un système automatisé de Component 2: Strengthening gestion des ressources TF / A7130 the Policy and Institutional A posteriori Individuel Open 30,789.27 Signé 2020-09-30 2021-03-29 2020-11-18 2021-06-28 2020-12-09 2021-08-19 2021-01-13 2021-10-14 2021-04-12 humaines et financières du Framework MEDDPN TG-WACA TOGO-204714-CS- Component 3: Strengthening INDV / élaboration d'un plan TF / A7130 National Physical and Social A posteriori Individuel Limited 25,170.94 Signé 2021-01-28 2020-12-30 2021-02-12 2021-02-04 2021-03-05 2021-06-17 2021-04-09 2021-08-03 2021-05-09 d'aménagement et de gestion Investments de la forêt classée d'Assévé 99 / Recrutement d'un consultant pour la réalisation Component 3: Strengthening d'un plan d'action de IDA / D2860 National Physical and Social A posteriori Individuel Open 0.00 Annulé 2020-04-10 2020-05-29 2020-06-19 2020-07-24 2021-01-20 réinstallation du dragage et Investments stabilisation des berges de la lagune et du lac Togo 95 / Recrutement d'un consultant pour la realisation Component 3: Strengthening d'un plan d'action de TF / A7130 National Physical and Social A posteriori Individuel Open 0.00 Annulé 2020-04-09 2020-04-14 2020-05-28 2020-06-18 2020-07-23 2021-01-19 réinstallation du complexe Investments d'aires protégées de TOGODO 102 / Recrutement de consultant individuel Component 2: Strengthening environnementaliste pour le IDA / D2860 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-04-09 2020-05-28 2020-06-18 2020-07-23 2021-01-19 contrôle des travaux Framework d'aménagement du cadre de travail de l'ANGE 94 / Recrutement de consultant individuel génie Component 2: Strengthening civil pour le contrôle des IDA / D2860 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-05-12 travaux Framework d'aménagement du cadre de travail de l'ANGE 86 / Recrutement de consultant individuel génie Component 2: Strengthening civil pour le contrôles des TF / A7130 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 travaux d'aménagement de la Framework cour du MEDDPN et des bureaux de l'UGP (RDC et R+1) 80 / Etude d'impact Component 3: Strengthening environnementale et sociale TF / A7130 National Physical and Social A posteriori Individuel Open 0.00 Annulé 2020-03-19 2020-03-30 2020-05-07 2020-05-28 2020-07-02 2020-12-29 du complexe d'aires Investments protégées de TOGODO TG-WACA TOGO-222416-CS- Component 2: Strengthening INDV / Etude pour la mise en En attente IDA / D2860 the Policy and Institutional A posteriori Individuel Open 0.00 2021-06-08 2021-07-28 2021-08-18 2021-09-22 2021-10-22 place du MRV de la zone d'exécution Framework côtière TG-WACA TOGO-222909-CS- Component 4: National En cours INDV / Elaboration du rapport IDA / D2860 A posteriori Individuel Open 0.00 2021-04-15 2021-03-29 2021-06-03 2021-08-04 2021-06-24 2021-08-16 2021-07-29 2021-08-28 Coordination d'exécution d'évaluation à mi-parcours TG-WACA TOGO-222896-CS- INDV / SELECTION D’UN Component 4: National En cours IDA / D2860 A posteriori Individuel Open 0.00 2021-06-18 2021-06-01 2021-08-06 2021-08-27 2021-10-01 2022-10-01 EXPERT OCEANOGRAPHE – Coordination d'exécution LITTORALISTE TG-WACA TOGO-222891-CS- Component 2: Strengthening INDV / Elaboration du plan IDA / D2860 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2021-05-20 2021-07-08 2021-07-29 2021-09-02 2021-10-02 spatial marin et côtier Framework Component 2: Strengthening 51 / Appui à la mise en place IDA / D2860 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2019-02-04 2019-06-05 2019-03-25 2019-04-15 2019-05-20 2019-11-16 du MRV de la zone côtière Framework TG-WACA TOGO-238696-CS- INDV / Recrutement d'un Component 4: National En attente spécialiste en développement IDA / D2860 A posteriori Individuel Open 0.00 2021-07-14 2021-09-01 2021-09-22 2021-10-27 2022-10-22 Coordination d'exécution des sous-projet communautaire et AGR pilote TG-WACA TOGO-240809-CS- INDV / RECRUTEMENT D’UN Component 4: National En cours ASSISTANT A LA MISE EN IDA / D2860 A posteriori Individuel Limited 0.00 2021-07-30 2021-06-02 2021-08-04 2021-06-10 2021-08-25 2021-08-12 2021-09-29 2021-11-04 Coordination d'exécution ŒUVRE DES ACTIVITES GENERATRICES DE REVENUS TG-WACA TOGO-240217-CS- INDV / ELABORATION DU PLAN D’ACTION POUR LA Component 3: Strengthening En attente RESTRICTION D’ACCES AUX TF / A7130 National Physical and Social A posteriori Individuel Open 0.00 2021-09-30 2021-11-18 2021-12-09 2022-01-13 2022-04-13 d'exécution RESSOURCES DES Investments ECOSYSTEMES FORESTIERS DE LA ZONE LITTORALE DU TOGO TG-WACA TOGO-223541-CS- INDV / Actualisation du Plan Component 2: Strengthening d'investissement En attente IDA / D2860 the Policy and Institutional A posteriori Individuel Open 0.00 2021-05-28 2021-07-16 2021-08-06 2021-09-10 2021-10-10 multisectoriel pour prendre d'exécution Framework en compte les considérations environnementales régionales TG-WACA TOGO-260444-CS- INDV / IDENTIFICATION, ELABORATION DES Component 3: Strengthening SPECIFICATIONS TECHNIQUES En attente TF / A7130 National Physical and Social A posteriori Individuel Open 0.00 2021-11-25 2021-12-31 2022-01-21 2022-02-25 2022-08-24 ET DETERMINATION DES d'exécution Investments COÛTS DES EQUIPEMENTS POUR LE DEVELOPPEMENT DES FILIERES AGRICOLES Page 8 TG-WACA TOGO-260449-CS- INDV / recrutement d'un Component 3: Strengthening consultant individuel pour En attente TF / A7130 National Physical and Social A posteriori Individuel Open 0.00 2021-11-30 2022-01-18 2022-02-08 2022-03-15 2022-09-11 l'appui à l’aménagement des d'exécution Investments périmètres maraichers de 04 sous projets communautaires 87 / Recrutement de consultant individuel génie electro-mécanique pour le Component 2: Strengthening contrôles des travaux TF / A7130 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 d'aménagement de la cour du Framework MEDDPN et des bureaux de l'UGP (RDC et R+1) Page 9