Public Disclosure Copy

         The World Bank                                                                                       Implementation Status & Results Report
         GEF Mainstreaming Integrated Water and Environment Management (P145897)



GEF Mainstreaming Integrated Water and Environment Management (P145897)


 EAST ASIA AND PACIFIC | China | Water Global Practice |
 Global Environment Project | Investment Project Financing | FY 2016 | Seq No: 11 | ARCHIVED on 30-Dec-2021 | ISR49679 |


 Implementing Agencies: The People's Republic of China, The Ministry of Water Resources (MWR), The Ministry of Econogical Environment (MEE),
 Water Resources Department in Hebei Province, Chengde Ecological Environment Bureau



 Key Dates


  Key Project Dates

   Bank Approval Date: 09-May-2016                                             Effectiveness Date: 27-Mar-2017
   Planned Mid Term Review Date: 30-Nov-2020                                   Actual Mid-Term Review Date: 24-Nov-2020
   Original Closing Date: 31-Dec-2021                                          Revised Closing Date: 31-Dec-2021

 pdoTable
 Project Development Objectives


  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective (PDO) is to increase water productivity and reduce pollution discharges in the project areas to mainstream
  and scale up an innovative approach to integrated water and environmental management in the three river basins entering the Bohai Sea.

  The PDO will be achieved through: (a) increasing irrigation water use efficiency and all other ways possible to effectively use water under a cap of
  water consumption; (b) reducing water pollution discharges under a cap of environment capacity and (c) increasing ecological river flows. The
  above measures will minimize the negative impacts on the ecosystem of Bohai Sea, contributing to the achievement of global environmental
  benefits (GEBs).

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name

 Component 1: Mainstreaming of Innovative Approach on Integrated Water and Environment Management:(Cost $3.45 M)
 Component 2: Demonstration in Hai Basin on Integrated Water and Environment Management:(Cost $90.10 M)
 Component 3: Scaling up the Integrated Water and Environment Management Approach in Three River Basins:(Cost $7.30 M)
 Component 4: Institutional Capacity Building and Project Management:(Cost $3.65 M)


 Overall Ratings

 Name                                                                        Previous Rating                           Current Rating

 Progress towards achievement of PDO                                         Satisfactory                             Highly Satisfactory

 Overall Implementation Progress (IP)                                        Moderately Satisfactory                  Satisfactory

 Overall Risk Rating                                                         Moderate                                 Low


 Implementation Status and Key Decisions



12/30/2021                                                                                                                     Page 1 of 9
                                                              Public Disclosure Copy

            The World Bank                                                                                     Implementation Status & Results Report
            GEF Mainstreaming Integrated Water and Environment Management (P145897)



  All of the PDO indicators have been reached or exceeded based on the M&E report updated in October 2021. Based on the updated procurement
  plan, there are totally 71 contracts have been signed and implemented under this project and will be fully completed together with all other project
  activities by December 31, 2021 of the Project Closing Date.
  Component 1 - Mainstreaming of Innovative Approach on Integrated Water and Environment Management (IWEM): by November 30, 2021, thirteen
  (13) out of 14 study reports planned under this component has been fully completed. The remaining one study report on Technical Guidelines for 3E
  (Evapotranspiration, Environment Capacity and Ecological Service) - based Integrated Water and Environment Management (IWEM) are under final
  review with comments and revisions and will be fully completed by the closing date. Altogether 11 policy recommendations based on the results of
  the studies have been included in the policy papers issued by MWR and MEE, which exceeded the target set at appraisal by seven (7).
  Component 2 - Demonstration in Hai Bain on IWEM: 100% of the demonstration activities for this component has been completed. In the
  demonstration areas of Cheng-De and Shi-Jia-Zhuang, there have been reductions of 14,695 tons of COD and 1,598 tons of NH3-N from zero
  baseline; the average water productivity increased from 1.26 baseline to 1.82 kg/m3; and reduction of 169.29 million cubic meters of groundwater
  overdraft from zero baseline. The above actuals all exceeded the targets, respectively.
  Component 3 - Scaling up the 3E-based IWEM Approach in Three River Basins: 100% of the project activities for this component has been
  completed. This approach has been scaled up by MWR in Shi-Jin Irrigation Scheme of Hai River Basin and He-Tao Irrigation Scheme of Yellow
  River Basin, and by MEE PMO in Xing-Tai, Tang-Shan and Lang-Fang of Hai River Basin and Liao River Basin. The approach has covered the
  problem areas of 181,629 km2, which exceeded the planned problem areas (153,800 km2) defined by MWR and MEE at project
  appraisal. Particularly, the 3E-based IWEM approach has been introduced and used for the project design during the recent preparation of the
  Bank’s new lending program – Yellow River Resilience Program which includes Henan and Shaanxi provinces and a river basin component at the
  Basin level.
  Component 4 - Institutional Capacity Building and Project Management: 100% of the project activities has been completed for this component.
  Training, workshops and domestic and overseas study tours as planned (or replacement of the activities due to epidemic situation with COVID-19)
  have been conducted to strengthen the institutional capacity in the PMOs of MEE, MWR and Hebei Province as planned.
  The next ICR mission is tentatively planned in March 2022.




  Risks



 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval              Previous Rating               Current Rating

  Political and Governance                                   Moderate                       Moderate                     Low
  Macroeconomic                                              Moderate                       Moderate                     Low
  Sector Strategies and Policies                             Low                            Low                          Low
  Technical Design of Project or Program                     Moderate                       Moderate                     Low
  Institutional Capacity for Implementation and
                                                             Moderate                       Moderate                     Low
  Sustainability
  Fiduciary                                                  Moderate                       Moderate                     Low
  Environment and Social                                     Moderate                       Moderate                     Low
  Stakeholders                                               Moderate                       Moderate                     Low
  Other                                                      --                              Moderate                     Moderate
  Overall                                                    Moderate                       Moderate                     Low



  Results


 PDO Indicators by Objectives / Outcomes


   PDO Indicators
   IN01083034


12/30/2021                                                                                                                    Page 2 of 9
                                                              Public Disclosure Copy

           The World Bank                                                                                      Implementation Status & Results Report
           GEF Mainstreaming Integrated Water and Environment Management (P145897)



   ►1. Policy Recommendations made under the project incorporated into the policies on water consumption control issued by MWR, and on
   pollution control issued by MEP, respectively (measuring unit: the (Number, Custom)

                                      Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                         4.00                          11.00                     4.00

   Date                             30-Jan-2017               15-Jun-2021                  19-Dec-2021             30-Jun-2021
   IN01083035
   ►2-A. Water pollution (COD) discharged into the Hutuo and Luan Rivers reduced in the two demonstration areas Chengde and Shijiazhuang
   (measuring unit: tons of COD) (Metric tons/year, Custom)

                                      Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                         13,892.00                     14,695.00                 8,074.00

    Date                              30-Jan-2017                  15-Jun-2021                   19-Dec-2021               30-Jun-2021

     IN01083096
     2-B. Water pollution (NH3-N) discharged into the Hutuo and Luan Rivers reduced in the two demonstration areas Chengde and
     Shijiazhuang (measuring unit: tons of NH3-N). (Metric tons/year, Custom Breakdown)

                                    Baseline                      Actual (Previous)            Actual (Current)            End Target

     Value                          0.00                         1,471.00                      1,598.00                    547.00

     Date                           30-Jan-2017                  15-Jun-2021                   19-Dec-2021                 30-Jun-2021

     IN01083097
     2-C. Water pollution discharged into the Hutuo and Luan Rivers reduced in the two demonstration areas Chengde and Shijiazhuang
     (measuring unit: tons of TN). (Metric tons/year, Custom Breakdown)

                                    Baseline                      Actual (Previous)            Actual (Current)            End Target

     Value                          0.00                         500.00                        924.00                      670.00

     Date                           30-Jan-2017                  15-Jun-2021                   19-Dec-2021                 30-Jun-2021

     IN01083098
     2-D. Water pollution discharged into the Hutuo and Luan Rivers reduced in the two demonstration areas Chengde and Shijiazhuang
     (measuring unit: tons of TP). (Metric tons/year, Custom Breakdown)

                                    Baseline                      Actual (Previous)            Actual (Current)            End Target

     Value                          0.00                         64.00                         176.00                      85.00

     Date                         30-Jan-2017                 15-Jun-2021                19-Dec-2021                 30-Jun-2021
   IN01083099
   ►3-A. Water productivity increased in two demonstration rural areas Gaocheng and Jinzhou (measuring unit: kg of grain production per/m3).
   (Cubic Meter(m3), Custom)

                                      Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                             1.10                         1.97                          1.82                      1.26

    Date                              30-Jan-2017                  15-Jun-2021                   19-Dec-2021               30-Jun-2021

     IN01083100
     3-B. Water productivity increased in scaling-up areas in Shijin irrigation areas (measuring unit: kg of grain production /m3) (Cubic
     Meter(m3), Custom Breakdown)

                                    Baseline                      Actual (Previous)            Actual (Current)            End Target



12/30/2021                                                                                                                     Page 3 of 9
                                                             Public Disclosure Copy

           The World Bank                                                                                    Implementation Status & Results Report
           GEF Mainstreaming Integrated Water and Environment Management (P145897)




     Value                          1.19                         1.98                         1.83                       1.29

     Date                           30-Jan-2017                  15-Jun-2021                  19-Dec-2021                30-Jun-2021

     IN01083101
     3-C. Water productivity increased in scaling-up areas in Hetao irrigation areas (measuring unit: kg of grain production /m3) (Cubic
     Meter(m3), Custom Breakdown)

                                    Baseline                     Actual (Previous)            Actual (Current)           End Target

     Value                          1.10                         1.98                         2.31                       1.26

     Date                           30-Jan-2017               15-Jun-2021                   19-Dec-2021              30-Jun-2021
   IN01083102
   ►4. Reductions achieved in overdraft of groundwater in 2 demonstration sites in Hai River Basin (Gaocheng and Jinzhou) (measuring unit:
   million m3/year). (Cubic meters/year, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                        169.28                       169.29                     72.93

    Date                              30-Jan-2017                 15-Jun-2021                  19-Dec-2021                30-Jun-2021
                                      Government has been making greater efforts on reduction of groundwater exploitation in the project
   Comments:                          areas.
   IN01083103
   ►5-A. IWEMP approach demonstrated and scaled up to cover the MWR defined problem areas in 3 river basins (measuring unit: km2)
   (Square kilometer(km2), Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                        22,736.00                    28,928.00                  28,420.00

    Date                              30-Jan-2017                 15-Jun-2021                  19-Dec-2021                30-Jun-2021

     IN01083104
     5-B. IWEMP approach demonstrated and scaled up to cover the MEP defined problem areas in 3 river basins (measuring unit: km2)
     (Square kilometer(km2), Custom Breakdown)

                                    Baseline                     Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                         110,000.00                   152,701.00                 125,380.00

     Date                           30-Jan-2017                  15-Jun-2021                  19-Dec-2021                30-Jun-2021



 Intermediate Results Indicators by Components


   Component 1: Mainstreaming of Innovative Approach on Integrated Water and Environment Management
   IN01083105
   ►1-A. All study reports prepared and completed as planned with good quality (measuring unit: the number of study reports prepared, revised
   and completed with good quality) (GEF Financed) (Number, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                        3.00                         4.00                       4.00

    Date                              30-Jan-2017                 15-Jun-2021                  19-Dec-2021                30-Jun-2021
     IN01083112



12/30/2021                                                                                                                   Page 4 of 9
                                                            Public Disclosure Copy

           The World Bank                                                                                  Implementation Status & Results Report
           GEF Mainstreaming Integrated Water and Environment Management (P145897)




     1-B. All study reports prepared and completed as planned with good quality (measuring unit: the number of study report prepared, revised
     and completed with good quality) (Government Financed) (Number, Custom Breakdown)

                                   Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                         0.00                        3.00                         5.00                       5.00

     Date                         30-Jan-2017                  15-Jun-2021               19-Dec-2021                30-Jun-2021
   IN01083113
   ►2. Operational manuals/guidelines completed and accepted with good quality (measuring unit: the number of operational manuals
   prepared, revised and completed with good quality) (Number, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                            0.00                        4.00                        5.00                      5.00

    Date                             30-Jan-2017                 15-Jun-2021                 19-Dec-2021               30-Jun-2021

   Component 2: Demonstration in Hai Basin on Integrated Water and Environment Management
   IN01083106
   ►3-A. All study reports prepared and completed as planned with good quality (measuring unit: the number of study reports prepared, revised
   and completed with good quality) (GEF Financed) (Number, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                            0.00                        7.00                        10.00                     10.00

    Date                             30-Jan-2017                 15-Jun-2021                 19-Dec-2021               30-Jun-2021
     IN01083110
     3-B. All study reports prepared and completed as planned with good quality (measuring unit: the number of study reports prepared,
     revised and completed with good quality) (Government Financed) (Number, Custom Breakdown)

                                   Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                         0.00                        7.00                         10.00                      10.00

     Date                       30-Jan-2017             15-Jun-2021                  19-Dec-2021                30-Jun-2021
   IN01083114
   ►4-A. RS/ET/EC-based TVAPs prepared and implemented with good quality for Luan sub-river basin and Hutuo sub-river basin, respectively
   (TVAP GEF Financed). (Number, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                            0.00                        2.00                        2.00                      2.00

    Date                             30-Jan-2017                 15-Jun-2021                 19-Dec-2021               30-Jun-2021
     IN01083117
     4-B. RS/ET/EC-based the IWEMPs prepared and implemented for Chengde Municipal City and Shijazhuang Municipal City and extension
     plans prepared for scaling-up areas (the IWEMP, MTR and ICR GEF Financed (Number, Custom Breakdown)

                                   Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                         0.00                        3.00                         6.00                       6.00

     Date                            30-Jan-2017                15-Jun-2021             19-Dec-2021                   31-Dec-2021
   IN01083120
   ►5. Capacity building for citizen engagement in preparation of TVAPs and IWEMPs - Channels are institutionalized for citizens to engage
   with government agencies and other stakeholders. (Number, Custom)

                                     Baseline                    Actual (Previous)           Actual (Current)          End Target



12/30/2021                                                                                                                Page 5 of 9
                                                             Public Disclosure Copy

           The World Bank                                                                                    Implementation Status & Results Report
           GEF Mainstreaming Integrated Water and Environment Management (P145897)




    Value                            0.00                        6.00                          8.00                      8.00

   Date                              30-Jan-2017                15-Jun-2021                  19-Dec-2021           30-Jun-2021
   IN01083125
   ►6. Women participation to increase water productivity and reduce water pollution through WUAs during IWEMP implementation (measuring
   unit: increased percentage of female membership in the WUAs) (Percentage, Custom)

                                     Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                            30.00                       45.00                         50.00                     50.00

   Date                             30-Jan-2017                 15-Jun-2021                 19-Dec-2021             30-Jun-2021
   IN01083126
   ►7-A. Construction of 3 small wastewater treatment plants and pipelines, 2 in Chengde County and 1 in Kuancheng County with good quality
   in demonstration areas as planned (Wastewater pollution-N) (Tones/year, Custom)

                                     Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        1,602.00                      2,855.90                  2,136.00

    Date                             30-Jan-2017                 15-Jun-2021                   19-Dec-2021              30-Jun-2021
     IN01083127
     7-B. Construction of 3 small wastewater treatment plants and pipelines, 2 in Chengde County and 1 in Kuancheng County with good
     quality in demonstration areas as planned (Wastewater pollution-P) (Tones/year, Custom Breakdown)

                                    Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                         0.00                         227.00                       330.00                     303.60

     Date                          30-Jan-2017                  15-Jun-2021                  19-Dec-2021                30-Jun-2021

     IN01083128
     7-C. Construction of 3 small wastewater treatment plants and pipelines, 2 in Chengde County and 1 in Kuancheng County with good
     quality in demonstration areas as planned (Wastewater pollution-BOD) (Tones/year, Custom Breakdown)

                                    Baseline                    Actual (Previous)            Actual (Current)           End Target

     Value                         0.00                         2,010.00                     2,830.00                   2,796.00

      Date                           30-Jan-2017                  15-Jun-2021               19-Dec-2021                30-Jun-2021
   IN01083129
   ►8. Improved irrigation technologies applied in 2 demonstration counties in Shijiazhuang Municipal City (measuring unit: No. of hectares of
   irrigated areas applied with improved irrigation technologies (Number, Custom)

                                     Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                            2,660.00                    11,000.00                     17,938.00                 13,300.00

    Date                             30-Jan-2017                 15-Jun-2021                   19-Dec-2021              30-Jun-2021

   Component 3: Scaling up the Integrated Water and Environment Management Approach in Three River Basins
   IN01083107
   ►9-A. All study reports prepared and completed as planned with good quality (measuring unit: the number of study reports prepared, revised
   and completed with good quality) (GEF Financed) (Number, Custom)

                                     Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        6.00                          7.00                      7.00

    Date                             30-Jan-2017                 11-Dec-2020                   19-Dec-2021              30-Jun-2021



12/30/2021                                                                                                                  Page 6 of 9
                                                            Public Disclosure Copy

           The World Bank                                                                                   Implementation Status & Results Report
           GEF Mainstreaming Integrated Water and Environment Management (P145897)



     IN01083109
     9-B. All study reports prepared and completed as planned with good quality (measuring unit: the number of study reports prepared,
     revised and completed with good quality) (Government Financed) (Number, Custom Breakdown)

                                    Baseline                    Actual (Previous)           Actual (Current)           End Target

     Value                         0.00                         3.00                        4.00                       4.00

     Date                        30-Jan-2017                 15-Jun-2021                19-Dec-2021               30-Jun-2021
   IN01083115
   ►10. National Water Environment Technology Extension Platform established at the MEP (measuring unit: percentage of software
   development and study progress completed with good quality) (Percentage, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        80.00                        100.00                    100.00

   Date                             30-Jan-2017                 15-Jun-2021            19-Dec-2021                30-Jun-2021
   IN01083118
   ►11. National ET Monitoring and Management Platform established at the MWR (measuring unit: percentage of software development and
   study progress completed with good quality) (GEF Financed) (Percentage, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        80.00                        100.00                    100.00

   Date                              30-Jan-2017                  15-Jun-2021                19-Dec-2021              30-Jun-2021
   IN01083121
   ►12-A. Annual scaling-up activities carried out and inspection and assessment reports prepared and completed for the up-scaling areas for
   MEP (GEF Financed) (Number, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        4.00                         6.00                      6.00

    Date                             30-Jan-2017                 15-Jun-2021                  19-Dec-2021              30-Jun-2021
     IN01083123
     12-B. Annual scaling-up activities carried out and inspection and assessment reports prepared and completed for the up-scaling areas for
     the MWR (GEF Financed) (Number, Custom Breakdown)

                                    Baseline                    Actual (Previous)           Actual (Current)           End Target

     Value                         0.00                         4.00                        6.00                       6.00

     Date                          30-Jan-2017                  15-Jun-2021                 19-Dec-2021                30-Jun-2021

   Component 4: Institutional Capacity Building and Project Management
   IN01083108
   ►13. Establishment of project website according to IW: LEARN guidelines: (measuring unit: functioning website with the number of hits
   recorded by site) (GEF Financed) (Number, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                        1.00                         1.00                      1.00

   Date                              30-Jan-2017                 15-Jun-2021                   19-Dec-2021              30-Jun-2021
   IN01083111
   ►14. Preparation of project-related experience notes (2) and one results note (1) for IW: LEARN portal: (measuring unit: completed
   documents) (GEF Financed) (Number, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)          End Target



12/30/2021                                                                                                                 Page 7 of 9
                                                               Public Disclosure Copy

           The World Bank                                                                                         Implementation Status & Results Report
           GEF Mainstreaming Integrated Water and Environment Management (P145897)




    Value                             0.00                         2.00                             3.00                      3.00

   Date                             30-Jan-2017                15-Jun-2021                19-Dec-2021                30-Jun-2021
   IN01083116
   ►15. Establishment and made operational project monitoring and evaluation (M&E) system: (measuring unit: functioning M&E system
   capable to generate semi-annual M&E reports) (GEF Financed) (Number, Custom)

                                      Baseline                      Actual (Previous)               Actual (Current)          End Target

    Value                             1.00                         6.00                             10.00                     10.00

   Date                              30-Jan-2017                    15-Jun-2021                  19-Dec-2021                30-Jun-2021
   IN01083119
   ►16. Female staff and specialists participation in the project workshops and training at the central, provincial, municipal and county levels
   (increased % of female staff & specialists of the total num (Percentage, Custom)

                                      Baseline                      Actual (Previous)               Actual (Current)          End Target

    Value                             30.00                        40.00                            50.00                     40.00

   Date                                30-Jan-2017                15-Jun-2021              19-Dec-2021         30-Jun-2021
   IN01083122
   ►17. Cooperation Framework Agreement reached to facilitate the development and implementation of TVAP/IWEMP between the respective
   administrative units responsible for environment and water at all leve (Number, Custom)

                                      Baseline                      Actual (Previous)               Actual (Current)          End Target

    Value                             0.00                         4.00                             5.00                      5.00

   Date                              30-Jan-2017               15-Jun-2021                   15-Jun-2021              30-Jun-2021
   IN01083124
   ►18. Coordination meetings between the respective administrative units to support the implementation of the framework agreements at the
   three levels on an annual basis (GEF Financed) (Number, Custom)

                                      Baseline                      Actual (Previous)               Actual (Current)          End Target

    Value                             4.00                         20.00                            24.00                     24.00

    Date                              30-Jan-2017                  15-Jun-2021                      19-Dec-2021              30-Jun-2021



 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status       Currency        Original     Revised      Cancelled      Disbursed       Undisbursed               % Disbursed


 P145897       TF-A2428          Effective    USD                9.50         9.50           0.00            8.65             0.85                      91%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date       Signing Date       Effectiveness Date       Orig. Closing Date      Rev. Closing Date

 P145897        TF-A2428          Effective   29-Sep-2016         29-Sep-2016        27-Mar-2017              31-Dec-2021             31-Dec-2021


12/30/2021                                                                                                                         Page 8 of 9
                                                       Public Disclosure Copy

         The World Bank                                                            Implementation Status & Results Report
         GEF Mainstreaming Integrated Water and Environment Management (P145897)




Cumulative Disbursements




  Restructuring History


  There has been no restructuring to date.




  Related Project(s)


 There are no related projects.




12/30/2021                                                                                        Page 9 of 9