The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Climate Resilient Agriculture and Productivity Enhancement Project (P162956) AFRICA WEST | Chad | Agriculture and Food Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 8 | ARCHIVED on 21-Feb-2022 | ISR50332 | Implementing Agencies: Republic of Chad, Ministry of Agriculture, Irrigation and Agricultural Equipment, West and Central African Council for Agricultural Research and Development (CORAF/WECARD) Key Dates Key Project Dates Bank Approval Date: 30-Apr-2018 Effectiveness Date: 30-Nov-2018 Planned Mid Term Review Date: 21-Mar-2022 Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed Project Development Objective (PDO) is to “to promote the adoption of improved technologies leading to increased productivity and to enhance the climate resilience of agricultural production systems in the areas targeted by the Project”. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Institutional support for sustainable agriculture development and climate resilience:(Cost $2.60 M) Supporting adoption of demand driven technologies and climate-smart agriculture:(Cost $18.60 M) Contingency emergency response:(Cost $15.00 M) Project management, coordination, monitoring and evaluation and knowledge management:(Cost $4.80 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Despite the challenging context (covid-19 crisis, temporary suspension of disbursement, etc.) the project has made significant progress in the implementation of its activities: (1) the adaptive research on targeted agricultural value chains have shown promising results. The average yields obtained on 26 on-farm trials are as follows; rice 2,336 t/ha against 1,340 t/ha (national yield average); maize 1,600 t/ha against 0,900 t/ha; sorghum 1,730 t/ha against 0,800 t/ha, and sesame 0,790t/ha against 0,400 t/ha. (2) The piloting of the e-agriculture activities namely the e- extension and e-voucher, have been successfully completed. 60 agriculture tablets with farming applications are now in use by producers’ organizations and extension agents. (3) The call center has received up to 15,000 calls from individual producers or representatives of producer’s organizations within a 6-month period. (4) 2,720 producers had received inputs via the electronic voucher system enabling them to cultivate 2,476 ha with improved technologies. (5) 520 sub-projects and micro-projects have been funded by the project. (6) In terms of capacity-building, 17 young 2/21/2022 Page 1 of 8 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) researchers (of which 5 women) are currently completing their trainings abroad, in West African universities; including 5 PhDs and 12 Master’s degrees (of which 2 have completed their MS and returned to ITRAD). An Additional Financing was processed to cover the financing gap of $ 15 million used to respond to the impact of Covid-19 crisis. 240,000 beneficiaries have received full ration of food basket (cereals, pulses, and vegetable oil) for a period of three months. 18,990 vulnerable farmers have received improved seeds and small agricultural equipment to preserve their productive capacity. A mid-term-review of the project is scheduled for March 21-April 2022. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic High High High Sector Strategies and Policies High Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Substantial Moderate Moderate Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Moderate Substantial Stakeholders Moderate Moderate Moderate Other -- -- -- Overall High Substantial Substantial Results PDO Indicators by Objectives / Outcomes Supporting adoption of demand-driven technologies and climate-smart agriculture IN01105832 ►Farmers reached with agricultural assets or services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 15,090.00 142,386.00 360,000.00 Date 01-Jan-2018 20-Jan-2021 31-Dec-2021 30-Jun-2023 IN01105835 Farmers reached with agricultural assets or services - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target 2/21/2022 Page 2 of 8 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Value 0.00 1,497.00 34,364.00 108,000.00 IN01105837 ►Surface area under improved technology disseminated by the Project (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 94,767.00 4,378.00 21,400.00 Date 01-Jan-2018 20-Jan-2021 31-Dec-2021 30-Jun-2023 IN01105838 Surface area under Climate-smart Agriculture technolgies/practices (Hectare(Ha), Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 580.00 623.00 10,700.00 Institutional support for sustainable agriculture development and climate resilience IN01105833 ►Percentage increase in average agriculture yield of direct beneficiaries compared to average yields in the Project area (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 Project management, coordination, M&E, and knowledge management IN01105834 ►Share of targeted beneficiaries with rating ‘Satisfied’ or above on project interventions (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 A beneficiary assessment is underway. This indicator will be updated at MTR Comments: IN01105836 Share of targeted female beneficiaries with rating ‘Satisfied’ or above on project interventions (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 90.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 Intermediate Results Indicators by Components 2/21/2022 Page 3 of 8 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Contingency emergency response IN01105840 ►Time required for the government to make requested funds available for an eligible crisis or emergency (Weeks, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4.00 4.00 4.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105844 ►Beneficiaries that received emergency food assistance (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 194,952.00 194,952.00 190,000.00 Date 03-Aug-2020 30-Nov-2020 30-Nov-2020 30-Nov-2021 IN01105848 ►Small holder farmers provided with improved seeds and small agricultural equipment (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 18,800.00 18,800.00 20,000.00 Date 03-Aug-2020 30-Dec-2020 30-Dec-2020 31-Dec-2020 Project management, coordination, monitoring and evaluation and knowledge management IN01105841 ►Annual audits submitted on time and without major qualification (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 1.00 4.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105843 ►Grievance Resolution Mechanism established and operational (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105847 ►Technical audit report for matching grants funded sub-projects (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 2/21/2022 Page 4 of 8 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Date 21-Feb-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105851 ►Grievances addressed (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 15-Apr-2021 15-Apr-2021 15-Apr-2021 29-Dec-2023 Institutional support for sustainable agriculture development and climate resilience IN01105842 ►Young researchers trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 17.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105846 Young researchers trained - female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 IN01105849 ►Quantity of foundation seeds produced - cereals (Metric ton, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 9.80 9.80 97.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105853 Quantity of foundation seeds - other crops (Metric ton, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.70 0.70 48.00 IN01105854 ►Improved technologies disseminated by the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12.00 12.00 20.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105857 ►Agriculture sector reform/ policies & strategies supported (Number, Custom) 2/21/2022 Page 5 of 8 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 1.00 5.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 Supporting adoption of demand driven technologies and climate-smart agriculture IN01105839 ►Operational regional innovation platforms (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 6.00 9.00 Date 01-Jan-2018 20-Jan-2021 31-Dec-2021 30-Jun-2023 IN01105845 ►Direct beneficiaries using agricultural climate services (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-Jan-2018 20-Jan-2021 31-Dec-2021 30-Jun-2023 IN01105850 ►Improved seeds produced by the targegeted beneficiairies (Metric ton, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 8,955.00 214.60 3,000.00 Date 01-Jan-2018 20-Jan-2021 31-Dec-2021 30-Jun-2023 IN01105852 ►Number of sub-projects to intensify sustainable production systems (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 580.00 530.00 2,100.00 Date 01-Jan-2018 20-Jan-2021 31-Dec-2021 30-Jun-2023 IN01105855 ►Number of diversification sub-projects supported (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 96.00 96.00 360.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105856 ►Number of CSA sub-projects (Number, Custom) 2/21/2022 Page 6 of 8 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 10.00 10.00 100.00 Date 01-Jan-2018 20-Jan-2021 20-Jan-2021 30-Jun-2023 IN01105858 ►Total beneficiaries who participated in Cash for Work rotations (IOM) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1,450.00 1,450.00 13,600.00 Date 09-Mar-2020 20-Jan-2021 20-Jan-2021 31-Mar-2021 IN01105859 ►Productive assets rehabilitated (IOM) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 6.00 6.00 25.00 Date 09-Mar-2020 20-Jan-2021 20-Jan-2021 31-Mar-2021 IN01105860 ►People trained (IOM) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5,100.00 Date 09-Mar-2020 20-Jan-2021 20-Jan-2021 31-Mar-2021 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P162956 IDA-D3020 Effective USD 41.00 41.00 0.00 29.81 9.85 75% P162956 IDA-D8060 Effective USD 15.00 15.00 0.00 0.00 14.69 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P162956 IDA-D3020 Effective 30-Apr-2018 19-Jun-2018 30-Nov-2018 31-Dec-2023 31-Dec-2023 P162956 IDA-D8060 Effective 06-Aug-2021 23-Aug-2021 29-Oct-2021 31-Dec-2023 31-Dec-2023 2/21/2022 Page 7 of 8 The World Bank Implementation Status & Results Report Climate Resilient Agriculture and Productivity Enhancement Project (P162956) Cumulative Disbursements PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History Level 2 Approved on 28-May-2020 ,Level Approved on 11-Jun-2020 Related Project(s) P172982-Improving food security and livelihood of refugees and host community ,P175614-Climate Resilient Agriculture and Productivity Enhancement Project (PROPAD) – Additional Financing 2/21/2022 Page 8 of 8