PROCUREMENT PLAN (Textual Part) Project information: Renewable Energy Development Project - P170236 Implementation agency: UGPE (Unidade de Gestão de Projetos Especiais) Date of the Procurement Plan: November 20, 2020 Period covered by this Procurement Plan: November 20, 2020 - May 19, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. Retroactive Financing used shall be consistent with Sections I, II and III of these Procurement Regulations and within the limits specified in the Legal Agreement. PROCUREMENT Cabo Verde : Renewable Energy and Improved Utility Performance Project PLAN General Information Country: Cabo Verde Bank’s Approval Date of the Original Procurement Plan: 2020-11-23 2021-11-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P170236 GPN Date: 2021-10-27 Project Name: Renewable Energy and Improved Utility Performance Project Loan / Credit No: / U Executing Agency(ies): nidade de Gestao de Projectos Especiais WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 002-REIUP-UGPE / Recruitment of an Engineer Consultant (Owner’s Engineer) for the control and supervision of the works and Project Implementation Quality And Cost- Under supplies in the scope of the / Support and Technical Prior Open - International 0.00 2021-11-07 2021-11-11 2021-11-14 2021-11-19 2021-12-19 2022-02-01 2022-02-22 2022-03-15 2022-03-31 2025-04-12 Based Selection Implementation sub-component 1a: small- Assistance scale renewable energy generation facilities and power evacuation lines of the project 005-REIUP-UGPE / Project Implementation Least Cost Pending Independent Financial Auditor / Support and Technical Post Open - International 0.00 2022-02-10 2022-02-11 2022-03-23 2022-04-23 2022-06-04 2022-07-09 2022-08-13 2023-02-09 Selection Implementation for the project Assistance INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 001-REP-UGPE-2020 / Recrutement d’un consultant pour l’élaboration du Cadre de la Politique de Réinstallation (CPR) et de / Electricity Sector Reform Post Direct Selection Direct 13,692.21 Signed 2020-11-30 2020-11-24 2020-12-10 2020-11-24 2021-02-13 2020-12-17 2021-08-12 Cadre de Gestion Environnementale et Sociale (CGES) pour les composant 1b : Améliorations du réseau du Projet de Développement des Énergies Renouvelables 003-REIUP-UGPE / Technical studies on distributed generation - Recruitment of a Technical Expert for the Project Implementation Individual control and supervision of the Under / Support and Technical Post Consultant Open 0.00 2021-11-07 2021-11-10 2021-11-26 2021-12-12 2022-01-01 2024-03-12 works and supplies in the Implementation Assistance Selection scope of the sub-component 1b: Resilient and Efficient Electricity Services to Public Health Facilities of the 004-REIUP-UGPE / Project Implementation Individual Electrical/Power Engineer for / Support and Technical Post Consultant Open 0.00 Under Review 2021-11-07 2021-11-10 2021-12-22 2021-12-29 2022-01-17 2023-01-17 support of the Project Assistance Selection 006-REIUP-UGPE / Project Implementation Individual Pending Environmental and Social / Support and Technical Post Consultant Open 0.00 2021-11-24 2021-12-28 2022-01-05 2022-01-06 2023-01-31 Implementation Specialist to UGPE Assistance Selection Page 1