Gansu Revitalization and Innovation Project: Procurement Plan Annex: Procurement Plan Procurement Plan of Gansu Revitalization and Innovation Project April 24, 2019 Project information: Country: The People’s Republic of China Borrower: The People’s Republic of China Project Name: Gansu Revitalization and Innovation Project Loan/Credit No: Project ID: P158215 Project Implementation Agency (PIA): Gansu Financial Holding Group Co. Ltd (line of credit PPMO) will be responsible for microcredit management under Component 1. Gansu Provincial Culture and Tourism Department (culture and tourism PPMO) will be responsible for Component 2 and 3. The culture and tourism PPMO will be centrally responsible for overseeing, coordinating, and training its cascaded PIUs at lower levels for subproject management. Both PPMOs will be responsible for liaison with the provincial PLG, municipal PLGs, and the World Bank on all aspects of project management, fiduciary, safeguards, and all other areas. The project will be implemented by eight project implementation units (PIUs) in the respective cities/districts/counties under the four prefecture municipalities. They are: Qin’an County Culture and Tourism Bureau, Maiji District Culture and Tourism Bureau, Wushan County Culture and Tourism Bureau, Lintao County Culture and Tourism Bureau, Tongwei County Culture and Tourism Bureau, Ganzhou District Culture and Tourism Bureau, Jiuquan City Culture and Tourism Bureau and Dunhuang City Culture and Tourism Bureau. Name of Components PIUs Gansu Financial Holding Group Co. Ltd (line of credit PPMO). GFHG is designated as the wholesaler FI to handle Component 1. Under the Component 1: Increased Access to direct oversight and management of the line of Financial Services for MSEs credit PPMO (GFHG), Bank of Gansu is designated as the 1st participating financial institution (PFI) to handle micro- and small credit transactions. 1. The Gansu Provincial Culture and Tourism Department (culture and tourism PPMO). The culture and tourism PPMO will be centrally Component 2: Urban-Rural Regeneration (investments by responsible for overseeing, coordinating, and county): training its cascaded PIUs at lower levels for subproject management. 2. Qin’an County PMO (Dadiwan-Longcheng Ancient Town-Shangguan Ming and Qing Dynasty 1 Gansu Revitalization and Innovation Project: Procurement Plan Historic Street Scenic Area Construction Sub- project) 3. Lintao County PMO (Majiayao Cultural Exhibition Center Construction Sub-project) 4. Ganzhou District PMO (Ganzhou District Cultural Heritage Protection and Downtown Tourism Development Subproject) 5. Dunhuang City PMO (Dunhuang City Xuanquanzhi Cultural Relic Protection Development Sub-project) 6. Jiuquan City PMO (Suzhou District Silk Road Cultural Research Center and Library Construction Sub-project) 7. Tongwei County PMO (Tongwei County Moxiang Painting and Calligraphy Town Hanmo Cultural Center Construction Sub-project) 8. Maiji District PMO (Maiji District Yellow River Carved Wooden Lacquerwares Intangible Cultural Heritage Center Construction Sub-project) 9. Wushan County PMO (Wushan County Yuanyang Jade Featured Cultural Town Construction Sub-project) Gansu Financial Holding Group Co. Ltd (line of credit PPMO) (capacity building to GFHG and selected PFIs, as well as business start-up Component 3: Institutional Strengthening advisory services for MSEs) and Global Knowledge Transfer Gansu Provincial Culture and Tourism Department (culture and tourism PPMO) and 8 county/district/city PMOs Date of the Procurement Plan: April 24, 2019 Period covered by this Procurement Plan: 2019-2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system 2 Gansu Revitalization and Innovation Project: Procurement Plan will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a. All procurement notices shall be published in a national newspaper of wide circulation, or on a widely-used website / electronic portal with free access. b. A minimum of thirty (30) days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c. Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d. Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e. Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. Winning Bidders shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f. The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g. No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h. The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of 3 Gansu Revitalization and Innovation Project: Procurement Plan and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j. The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. k.The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. l. The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. A. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. B. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable: C. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable. G. Other Relevant Procurement Information: Goods, Works and Non-Consulting Services: Prior Review Threshold: Procurement Decisions are subject to Prior Review by the Bank as stated in Annex II to the Procurement Regulations (July 2016, revised November 2017 and August 2018). Procurement Contract Value Procurement Method Bank Prior Review Category (US$) Goods & Non- ≥ 10 million International Open All contracts Consulting Competitive Procurement 4 Gansu Revitalization and Innovation Project: Procurement Plan Services (International + Open) ≥ 0.5 National Open Competitive All contracts ≥ USD 2 million. million to < Procurement (RFB) 10 million (National + Open) < 0.5 Shopping (RFQ) None million Others DS (Direct Selection) All contracts ≥ USD 2 million. Works, Supply ≥ 40 million International Open All contracts & Installation Competitive Procurement (International + Open) ≥0.5 million National Open Competitive All contracts ≥ USD 10 to Procurement (RFB) million. < 40 million (National + Open) < 0.5 Shopping (RFQ) None million N/A DS (Direct Selection) All contracts ≥ USD 10million. Notes: DS: Direct Selection NA: Not Applicable 5 Gansu Revitalization and Innovation Project Procurement Plan Procurement Packages with Methods and Time Schedule: Gansu Revitalization and Innovation Project Procurement Plan (Civil works and Goods) WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs)                         PPMO Supporting RFB/Op Post  August  October SXMB- Supporting vehicles in scenic Good 1 vehicles in scenic 12.90 1.88 en/Nati Revie 12, 12  3 PPMO HW-01 area Wuying, Longcheng  s area onal/ w 2022 2022   Qin’an                     County Urban Qin’an Regeneration of County Wuying Town of Tianshui Dadiwan construction and   TSTJ- Civil RFB/Op Post  April Culture Dadiwan Area: renovation works; Shaodian Village Februar 2 DDW- 6.50 0.95 Work en/Nati Revie 12  10 and Residential traditional houses protection and y 12, 01 s onal w 2020 Touris Houses repair works 2020 m Renovation Bureau Works Qin’an Urban County Tianshui Dadiwan infrastructure TSTJ- Regeneration of Civil RFB/Op Post  March  May Culture construction, renovation and 3 DDW- Wuying Town of 51.73 7.53 Work en/Nati Revie 12  12  15 and upgrading works ( Shaodian 02 Dadiwan Area: s onal w 2021 2021 Touris Village) Municipal works m Bureau Qin’an Urban County Regeneration of   Culture TSTJ- Wuying Town of Tianshui Dadiwan environment Civil RFB/Op Post Februar April 10  and 4 DDW- Dadiwan Area: enhancement works; Yanjiagou 3.00 0.44 Work en/Nati Revie 5 y 8  2020  Touris 03 Water River course treatment works s onal w 2020 m conservancy Bureau works Bureau 6 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) Dadiwan Cultural Tianshui Dadiwan sub-project: Qin’an Experience Zone, Digital Exhibition Hall, Academic County Incubators Space Research Exchange Training RFB/ TSTJ- Civil Post Culture and Tourist Center, Interactive Display Open/  Feb 5  April 7  5 DDW- 31.27 4.55 Work Revie 12 and Service Center Experience Hall, Intangible Nation 2020 2020 04 s w Touris Housing Cultural Heritage Folk Customs al m construction Exhibition Hall, Tourist Service Bureau works Center Urban Dadiwan housing renovation Qin’an Regeneration of works: Protection and renovation County Longcheng RFB/ TSTJ- of buildings on both sides of the Civil Post Culture Historic Town of Open/ July 10  Aug12  6 DDW- historic street of Longcheng; 19.21 2.80 Work Revie 15 and Dadiwan Area Nation 2020 2020 05 protection and renovation of s w Touris Housing al historical courtyard and Nuwa m conservation and Cultural Exhibition Hall Bureau renovation works Qin’an Urban County Regeneration of RFB/ TSTJ- Tianshui Dadiwan infrastructure Civil Post August Culture Longcheng Open/ July 6  7 DDW- construction, renovation and 53.40 7.77 Work Revie 10  16 and Historic Town of Nation 2020 06 upgrading works (Longcheng) s w 2020  Touris Dadiwan Area al m Municipal works Bureau Urban Regeneration of Shangguan Ming- Qin’an and Qing- Tianshui Qin'an Shangguan Ming County Dynasty Historic RFB/ and Qing Dynasties Ancient Street Civil Post Culture TSTJ- Street of Open/ August Oct 6  8 Building Renovation and 13.97 2.03 Work Revie 16 and GJ-01 Dadiwan Area Nation 3  2020 2020  Improvement; Infrastructure s w Touris Housing and al Renovation and Improvement. m supporting Bureau infrastructure construction works 7 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) Qin’an Dadiwan Cultural Tianshui Dadiwan: Scenic area County Experience Zone, RFB/ exhibition equipment, lighting and Post Culture QA- Incubators Space Good Opn/  March April 6  9 sound equipment, intelligent 5.77 0.84 Revie 3 and HW-01 and Tourist s Nation 6  2021 2021  systems, garbage compression w Touris Service Center: al and transportation equipment m Equipment Bureau     Maiji                     District Tianshui Carved Wooden Lacquerwares Inheritance and Development Maiji Yellow River Building Renovation and District RFB/ Lacquerware Improvement: Carved Wooden Civil Post Culture TSTJ- Open/  Feb 8  April 10  10 Creative Industry Lacquerware Intangible Cultural 50.43 7.34 Work Revie 12 and QD-01 Nation 2020 2020  and Incubator Heritage Inheritance Training s w Touris al Center Center; m Bureau Infrastructure upgrading and improvement: roads and ancillary facilities. Yellow River Maiji Tianshui Carved Wood Lacquerware District Lacquerware Inheritance and   Creative Industry RFB/Op Post  January Culture TS- Development Sub-project: Good Novemb 11 and Incubator 3.72 0.54 en/Nati Revie 10  3 and HW-01 Multimedia Equipment, Audio s er 10  Center: onal w 2021 Touris Equipment, LED Screen, 2020 Multi-media m Showcase, Exhibition Board equipment Bureau   Wushan                     County 8 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) Wushan Jade Art Creative Industry Tianshui Wushan Yuanyang Jade Wusha Exhibition and Featured Cultural Town n Incubator Construction sub-project: RFB/   County Civil Post TSTJ- Center; and Yuanyang jade culture complex, Open/ Februar April 11  Culture 12 58.81 8.56 Work Revie 16 WS-01 Urban road reconstruction along the Nation y 11  2020  and s w Regeneration of river, municipal works etc. al 2020 Touris Shandan Town of Landscape improvement along m Wushan Jade Wushan County to Shandan Town Bureau Industry Wusha Urban Tianshui Wushan Yuanyang Jade n Regeneration of Featured Cultural Town RFB/ County Shandan Town of Civil Post Februar TSTJ- Construction sub-project: River Open/ April 9  Culture 13 Wushan Jade 1.54 0.22 Work Revie y 9. 5 WS-02 course treatment: landscape Nation 2020  and Industry Water: s w 2020 improvement works on both sides al Touris conseration of the river m works Bureau Wusha n Wushan Jade Art Tianshui Wushan Yuanyang Jade RFB/ County Creative Industry Featured Cultural Town Post WS- Good Open/ March May 6  Culture 14 Exhibition and Construction sub-project: Office 1.00 0.15 Revie 3 HW-01 s Nation 6  2021 2021  and Incubator Center equipment, audio equipment, LED w al Touris Equipment screens, showcases. m Bureau   Lintao                     County 9 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) Rural Dingxi Majiaoyao Cultural regeneration of 8 Lintao Exhibition Architectural renovation villages of County and improvement RFB/ Majiayao Area: Civil Prior Decemb Culture DXTJ- 1: Renovation of exterior walls of Open/ Oct 12  15 Housing 76.22 11.09 Work Revie er 6  16 and MJY-01 residential houses on both sides of Nation 2020 renovation and s w 2020  Touris the main road; repair of roadway al infrastructure m in the village, beautification of construction Bureau roadway landscape etc. works Dingxi Majiaoyao Cultural Majiayao Cultural Exhibition Architectural renovation Lintao Exhibition, and improvement County   Research, and 2. Majiayao Cultural Exhibition Civil RFB/Op Post Culture DXTJ- Februar April 20  16 Incubator Center, Majiayao Cultural 36.91 5.37 Work en/Nati Revie 15 and MJY-02 y 20  2020  Center: Experience Center, Majiayao s onal w Touris 2020 construction Cultural Research and Exchange m works Center, Majiayao Cultural Industry Bureau Incubation Center Lintao Rural Dingxi Majiaoyao Cultural County   regeneration of 8 Exhibition Architectural renovation Civil RFB/Op Post Culture DXTJ- Februar April 22  17 villages of and improvement 2: Outdoor 12.07 1.76 Work en/Nati Revie 10 and MJY-03 y 22  2020  Majiayao Area: engineering, cultural square s onal w Touris 2020 Municipal works paving, etc. m Bureau 10 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) Lintao Majiayao Cultural Dingxi Majiaoyao Cultural County Exhibition, Exhibition Architectural renovation   RFB/Op Post Culture LT- Research, and and improvement: Cultural Good Februar April 1  18 2.25 0.33 en/Nati Revie 3 and HW-01 Incubator Exhibition equipment, office s y 1  2021  onal w Touris Center: equipment, security equipment, 2021 m Equipment information equipment etc. Bureau   Tongwei                     County Tongwei Tongwe Calligraphy and i Ink Painting Dingxi Moxiang Hot Springs Town RFB/ County Creative Industry Construction works: Civil Post  July DXTJ- Open/ Augest Culture 19 Exhibition and 1. Gallery / Cultural Products Store 37.91 5.52 Work Revie 11  12 WQ-01 Nation 1  2020  and Incubator / Maker Center, calligraphy s w 2020 al Touris Center: materials store m construction Bureau works(1) Tongwei Calligraphy and Tongei Ink Painting County RFB/ Creative Industry Dingxi Moxiang Hot Springs Town Civil Post Culture DXTJ- Open/ Feb 15  April 15  20 Exhibition and Construction works: 32.27 4.70 Work Revie 8 and WQ-02 Nation 2020 2020  Incubator 2 Hanmo Cultural Art Center s w Touris al Center: m construction Bureau works (2) Tongwei Tongwe Calligraphy and Dingxi Moxiang Hot Springs Town i RFB/ Ink Painting Infrastructure Construction and Civil Post County DXTJ- Open/ Feb 13  April 13  21 Creative Industry Improvement: 15.77 2.29 Work Revie 8 Culture WQ-03 Nation 2020 2020 Exhibition and Square pavement, calligraphy and s w and al Incubator painting street, landscape pool Touris Center: Municipal m 11 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) works Bureau Tongwei Tongwe Calligraphy and iCounty Ink Painting RFB/ Cultural relics security monitoring Post Culture TW- Creative Industry Good Open/ Feb 11  April 11  22 system, intelligent scenic spot 1.35 0.20 Revie 3 and HW-01 Exhibition and s Nation 2020 2020  system, display equipment etc. w Touris Incubator al m Center: Bureau Equipment   Zhangye                     City Zhangye Ming Dynasty Granary Zhangye Cultural Heritage Inheritance and Ganzho Discovery and Development Sub-project housing u Tourist Service upgrading and improvement: RFB/ District ZYTJ- Center; and Civil Post 1. repair of the north and west Open/ March 1, May 10, Culture 23 MLC- Rural 12.09 1.76 Work Revie 13 buildings of the Ming Dynasty Nation 2020 2020  and 01 regeneration of s w Granary; Tourist Service Center al Touris Folk Village in (New); Square paving and essays, m Wulan Ancient square lighting installation, roads Bureau Town of Zhangye and ancillary facilities. Ganzho Rural Zhangye General Military Cultural u regeneration of Heritage Protection Inheritance RFB/ District ZYTJ- Folk Village in and Development Project Building Civil Post Open/ March 9, May 11, Culture 24 ZBF- Wulan Ancient Renovation and Improvement 4.41 0.64 Work Revie 13 Nation 2020 2020  and 01 Town of 2: Renovation of the old library, s w al Touris Zhangye: installation of lighting facilities; m Municipal works Municipal works. Bureau 12 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) Rural regeneration of Ganzho Folk Village in Zhangjia Wulan Ancient Town Folk u Wulan Ancient Village Renovation and Upgrading: RFB/ District ZYTJ- Civil Post March Town of protection and repair of ancient Open/ May 13, Culture 25 WLGZ- 40.53 5.90 Work Revie 12, 16 Zhangye: houses, traditional dwellings and Nation 2020  and 01 s w 2020 Housing repair ancient buildings; Roads and al Touris and ancillary facilities. m infrastructure Bureau construction Zhangye Ming Dynasty granary Ganzho cultural heritage protection u Zhangye inheritance development project RFB/ District ZY- Discovery and Prior intelligence and office equipment Good Open/ Feb 20  April 15  Culture 26 HW— Tourist Service 18.74 2.73 Revie 3 1&2. s Nation 2021 2021  and 01 Center w Wulan Ancient Town Project: al Touris Equipment Wireless Network, Portal, Online m Booking System, Payment System Bureau Jiuqua                         n City Jiuquan City Jiuquan Silk Road Jiuquan Silk Road Cultural Heritage JQTJ- Civil RFB/Op Post Culture Culture Research Research Center Construction: March May 14  27 SWYZ- 66.02 9.61 Work en/Nati Revie 15 and Center and New Research Center; Roads and 5  2020 2020  01 s onal w Touris Library ancillary facilities. m Bureau Jiuquan Jiuquan Silk Road City RFB/ Culture Research Jiuquan Silk Road Cultural Heritage Post Culture JQ- Good Open/ Feb 21, April 20  28 Center and Research Center intelligent system 9.07 1.32 Revie 3 and HW-01 s Nation 2021 2021  Library: and office equipment w Touris al Equipment m Bureau                         Dunhuang 13 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) City Dunhuang City Xuanquanzhi Cultural Site architectural renovation and upgrading: Exhibition Center and Visitor Center; Tianshuijing Display Area, Dunhua Dunhuang Yizhan Site Display Area, Gobi ng City RFB/ DHTJ- Posthouse Landform Display Area, Civil Prior March Culture Open/ May 20  29 XQZ- Discovery and Xuanquanzhi and Surrounding 78.65 11.45 Work Revie 14  16 and Nation 2020  01 Tourist Service Environment Display Area, viewing s w 2020  Touris al Center platform, internal display road, m self-driving camp and hiking Bureau campsite, sewage treatment facilities (sewage pipelines and septic tanks), garbage disposal facilities, electricity. Dunhua Dunhuang ng City Posthouse RFB/ DH- Prior Culture Discovery and Dunhuang City Xuanquanzhi Good Open/ Feb 13, April 11  30 HW— 25.47 3.71 Revie 3 and Tourist Service Cultural Site Intelligent facilities s Nation 2021 2021  01 w Touris Center and basic equipment. al m Equipment Bureau Dunhua Dunhuang ng City DH- Posthouse Post Culture Ox cart and horse cart exhibits in Good July 13  June 13  31 HW— Discovery and 0.40 0.06 DS Revie 1 and Xuanquanzhi Relics Site in s 2021 2021 02 Tourist Service w Touris Dunhuang City Center Exhibits m Bureau Total (BF): 783.38 114.00               Legend:   First 18 months Packages Note: 14 Gansu Revitalization and Innovation Project Procurement Plan WB Estimated Cost Revie Schedule w Cate Metho No. Contract No. Contract Description Estimat Contrac Durati PIU gory d RMB USD Prior/ ed Bid t on million million Post Openin Signing (mont g Date Date hs) US$1 = CNY6.8718 6.8718 USD/RMB Exchange Rate 15 Gansu Revitalization and Innovation Project Procurement Plan Selection of Consultants: Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II to the Procurement Regulations (July 2016, revised November 2017 and August 2018): Prior Review Contract Threshold for Procuremen Selection Bank Prior Value Contracts under t Category Method Review Threshold (US$) Retroactive Financing ≥ 300,000 QCBS, QBS, Firms: All contracts Firms: All contracts >=USD 1 million; >=USD 500,000; QCBS, QBS, < 300,000 FBS, LCS, CQS Firms: All DS Firms: All DS contracts >= USD 1 contracts >= USD Others DS million; 500,000; Individual Individual Consultant: Consultants Consultant: All All contracts >= USD contracts >=0.3 200,000; million; Others IC DS for individual DS for individual consultant: All consultant: All contracts>=USD contracts>=USD 200,000 0.3 million Notes: QCBS: Quality- and Cost-Based Selection DS: Direct Selection QBS: Quality-Based Selection IC: Individual Consultant selection procedure FBS: Fixed Budget Selection NA: Not Applicable LCS: Least Cost Selection CQS: Consultants’ Qualifications-based Selection Consultancy Assignments with Selection Methods and Time Schedule: 16 Gansu Revitalization and Innovation Project Procurement Plan Consultancy Assignments with Selection Methods and Time Schedule: Gansu Revitalization and Innovation Project Procurement Plan (Consulting Services) WB Estima Cost Estimation Review ted Contra Contra Durati Contra Selection Prior Bid ct ct on Progr No. Contract Description RMB USD Owner ct No. method Review Openi Signing Amoun (mont ess (million (millio /Post ng Date t hs) ) n) Review Date QCBS/Ope May SXMB- Credit Risk Management and Post Oct 31, 1 3.09 0.45 n/Internati 31,   60   PPMO C01 Corporate Governance Review 2019 onal 2019 Financial Technology in QCBS/Ope May SXMB- Post Oct 31, 2 support of MSEs Application 2.41 0.35 n/Internati 31,   60   PPMO C02 Review 2019 and Credit Assessment onal 2019 TA to the GFGC on global Oct. SXMB- CQS/Open/ Post Dec. 15, 3 good practice in executing 1.37 0.20 31,   24   PPMO C03 National Review 2019  and managing guarantees 2019  Improve Strategic Planning  Oct. SXMB- CQS/Open/ Post Dec. 15, 4 and Regulations of Culture 1.51 0.22 31,   24   PPMO C04 National Review 2019  and Tourism Sector 2019 Oct. SXMB- Branding, Marketing & Direct Post Sep 30, 5 1.99 0.29 31, 84 PPMO C05 Promotion Selection Review 2019 2019 17 Gansu Revitalization and Innovation Project Procurement Plan WB Estima Cost Estimation Review ted Contra Contra Durati Contra Selection Prior Bid ct ct on Progr No. Contract Description RMB USD Owner ct No. method Review Openi Signing Amoun (mont ess (million (millio /Post ng Date t hs) ) n) Review Date Oct. SXMB- Training of Cultural Tourism Direct Post Sep 30, PPMO 6 1.99 0.29 31, 84 C06 Practitioners. Selection Review 2019 2019 Community Outreach and Oct. SXMB- Training on Creative Direct Post Sep 30, 7 1.99 0.29 31, 84 PPMO C07 Industries and Safeguarding Selection Review 2019 2019 Intangible Cultural Heritage Business Start-up advisory Oct. SXMB- Services for Prospective Small Direct Post Sep 30, 8 1.99 0.29 31, 84 PPMO C08 and Micro Enterprise Selection Review 2019 2019 Operators, especially women. Oct. SXMB- Skills Training of Tianshui Direct Post Sep 30, 9 1.03 0.15 31, 84 PPMO C09 Lacquer Carving. Selection Review 2019 2019 Community Outreach and Oct. SXMB- Capacity Building Services for Direct Post Sep 30, 10 1.03 0.15 31, 84 PPMO C10 Low-Income Group on Selection Review 2019 2019 Business Start-up 18 Gansu Revitalization and Innovation Project Procurement Plan WB Estima Cost Estimation Review ted Contra Contra Durati Contra Selection Prior Bid ct ct on Progr No. Contract Description RMB USD Owner ct No. method Review Openi Signing Amoun (mont ess (million (millio /Post ng Date t hs) ) n) Review Date Project Management Consulting Services, including QCBS/Ope May SXMB- Prior Oct 1, 11 socio-economic impact 17.87 2.60 n/Internati 15,   84   PPMO C11 Review 2019 evaluation and beneficiary onal 2019 satisfaction surveys. Establishment of Project QCBS/Ope Post May SXMB- Management Information Oct 15, 12 2.82 0.41 n/Internati Review 15,   24   PPMO C12 System (Procurement of 2019 onal 2019 Standard Software). Post May SXMB- Environmental Impact CQS/Open/ Oct 31, 13 1.99 0.29 Review 31,   84   PPMO C13 Assessment & Monitoring. National 2019 2019 Post May SXMB- Social Development CQS/Open/ Oct 31, 14 1.99 0.29 Review 31,   84   PPMO C14 Assessment & Monitoring. National 2019 2019 Qin’an Consulting Services for County QCBS/Ope Prior May SXMB- Design, Construction Oct 15, Culture 15 7.42 1.08 n/Internati Review 15,   12   C15 Drawings, BQs of Qin'an 2019 and onal 2019 County, Tianshui. Tourism Bureau 19 Gansu Revitalization and Innovation Project Procurement Plan WB Estima Cost Estimation Review ted Contra Contra Durati Contra Selection Prior Bid ct ct on Progr No. Contract Description RMB USD Owner ct No. method Review Openi Signing Amoun (mont ess (million (millio /Post ng Date t hs) ) n) Review Date Maiji Cultural and Tourism Consulting Services for QCBS/Ope May Bureau SXMB- Design, Construction Prior Oct 15, 16 4.26 0.62 n/Internati 15,   12   Wushan C16 Drawings, BQs of Maiji District Review 2019 onal 2019 County and Wushan County, Tianshui. Culture and Tourism Bureau Lintoa County Culture Consulting Services for and Design, Construction QCBS/Ope May Tourism SXMB- Prior Oct 15, 17 Drawings, BQs of Lintao 8.45 1.23 n/Internati 15,   12   Bureau C17 Review 2019 County and Tongwei County, onal 2019 County Dingxi City. Culture and Tourism Bureau Ganzho u Consulting Services for QCBS/Ope May District SXMB- Post Oct 15, 18 Design, Construction 3.30 0.48 n/Internati 15,   12   Culture C18 Review 2019 Drawings, BQs of Zhangye. onal 2019 and Tourism Bureau Jiuquan City Culture Consulting Services for QCBS/Ope May and SXMB- Design, Construction Prior Oct 15, 19 7.28 1.06 n/Internati 15,   12   Tourism C19 Drawings, BQs of Jiuquan and Review 2019 onal 2019 Bureau Dunhuang. Dunhua ng City Culture 20 Gansu Revitalization and Innovation Project Procurement Plan WB Estima Cost Estimation Review ted Contra Contra Durati Contra Selection Prior Bid ct ct on Progr No. Contract Description RMB USD Owner ct No. method Review Openi Signing Amoun (mont ess (million (millio /Post ng Date t hs) ) n) Review Date and Tourism Bureau Construction Supervision of QCBS/Ope SXMB- Prior Jul 31, Nov 30, 20 Qin'an, Tianshui, Tongwei and 14.29 2.08 n/Internati   84   PPMO C20 Review 2019 2019 Shandan Works. onal Construction Supervision of QCBS/Ope Prior SXMB- Jul 31, Nov 30, 21 Zhangye, Jiuquan and 7.63 1.11 n/Internati Review   84   PPMO C21 2019 2019 Dunhuang onal Prior Advisory Service with UNESCO to Strengthen Gansu Creative Industry; Intangible Heritage Direct May SXMB- Support; Dunhuang Site Prior Jun 30, 22 3.50 0.51 Selection 31,   60   PPMO C22 Management Plan; and Review 2019 of UNESCO 2019 Support Global Knowledge Sharing (on-the-job capacity strengthening) 21 Gansu Revitalization and Innovation Project Procurement Plan WB Estima Cost Estimation Review ted Contra Contra Durati Contra Selection Prior Bid ct ct on Progr No. Contract Description RMB USD Owner ct No. method Review Openi Signing Amoun (mont ess (million (millio /Post ng Date t hs) ) n) Review Date Advisory Service with UNWTO to Review and Enhance Gansu Tourism Strategy; Enhance Direct May SXMB- Marketing, Promotion and Post Jun 30, 23 2.75 0.40 Selection 31,   60   PPMO C23 Branding Strategy Efforts; and Review 2019 of UNWTO 2019 Support Global Knowledge Sharing (on-the-job capacity strengthening) Oct. SXMB- CQS/Open/ Post Sep 30, 24 Learning Exchanges 5.22 0.76 31, 42 PPMO C24 National Review 2019 2019 Establishment of Gansu Global Culture and Tourism Oct. SXMB- Knowledge Hub (curating CQS/Open/ Post Sep 30, 25 2.75 0.40 31, 84 PPMO C25 knowledge content and National Review 2019 2019 development of communication strategies) Total (BF): 109.95 16.00                     Legend: New added   Retroactive Financed Packages   packages Not e: US$1 = CNY6.8718 6.8718 USD/RMB Exchange Rate 22 PROCUREMENT China : Gansu Revitalization and Innovation Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2019-05-15 2022-02-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P158215 GPN Date: 2019-05-06 Project Name: Gansu Revitalization and Innovation Project Loan / Credit No: / , IBRD / 89700, IBRD / 89710 G Executing Agency(ies): ansu Silk PMO WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned JQTJ-SWYZ-01 / Housing construction and Component 1: Increased infrastructure construction of Single Stage - One 7,911,907.8 2021-08- IBRD / 89700 Access to Financial Services Prior Request for Bids Open - National 9,610,000.00 Signed 2020-10-15 2020-11-16 2020-10-30 2020-12-09 2020-12-11 2020-12-25 2021-01-10 2021-01-11 2021-02-14 2021-03-18 Jiuquan Silk Road Cultural Envelope 8 13 for MSEs Heritage Research Center Sub- Project DHTJ-XQZ-01 / Dunhuang City Xuanquanzhi Cultural Site architectural renovation and National upgrading: Tianshuijing Component 1: Increased Procurement Display Area, Yizhan Site Single Stage - One 1,330,313.6 2022-05- IBRD / 89700 Access to Financial Services Post Request for Bids Open - National Document - 1 2,740,000.00 Signed 2021-07-18 2021-08-15 2021-07-23 2021-09-30 2021-09-03 2021-10-09 2021-10-03 2021-12-06 2021-11-07 2021-12-30 Display Area, Gobi Landform Envelope 4 06 for MSEs Envelope process Display Area, Xuanquanzhi (Non Bank-SPD) and Surrounding Environment Dis lay Area, viewing platform, internal display road, ZYTJ-WLGZ-01 / protection and repair of ancient houses, traditional dwellings and National ancient buildings; heating Component 1: Increased Procurement Under engineering, roads, greening Single Stage - One 2022-06- IBRD / 89700 Access to Financial Services Post Request for Bids Open - National Document - 1 5,900,000.00 0.00 Implementat 2021-08-20 2021-08-15 2021-08-25 2021-10-21 2021-10-06 2021-11-26 2021-11-05 2021-12-10 works, sewage engineering, Envelope 08 for MSEs Envelope process ion rainwater engineering, electric (Non Bank-SPD) power engineering, weak electricity engineering, fire hydrants, etc. DXTJ-MJY-02 / Dingxi National Majiaoyao Cultural Exhibition Procurement Component 2: Urban-Rural Single Stage - One 6,171,766.1 2022-07- Architectural renovation and IBRD / 89710 Post Request for Bids Open - National Document - 1 5,370,000.00 Signed 2021-09-12 2021-08-15 2021-09-17 2021-10-21 2021-10-29 2021-10-19 2021-11-28 2021-11-11 2022-01-02 2021-12-27 Regeneration Envelope 6 01 improvement: construction Envelope process works (Non Bank-SPD) DXTJ-WQ-02 / Tongwei National Calligraphy and Ink Painting Procurement Under Component 2: Urban-Rural Single Stage - One 2022-10- Creative Industry Exhibition IBRD / 89710 Post Request for Bids Open - National Document - 1 4,700,000.00 0.00 Implementat 2021-12-15 2021-10-09 2021-12-20 2021-10-25 2022-01-31 2021-11-19 2022-03-02 2021-12-20 2022-04-06 Regeneration Envelope 03 and Incubator Center: Envelope process ion construction works (2) (Non Bank-SPD) DHTJ-XQZ-02 / Dunhuang City Xuanquanzhi Cultural Site architectural renovation and National upgrading:Exhibition Center Procurement Pending Component 2: Urban-Rural Single Stage - One 2023-08- and Visitor Center; sewage IBRD / 89710 Post Request for Bids Open - National Document - 1 9,580,000.00 0.00 Implementat 2022-10-20 2022-10-25 2022-12-06 2023-01-05 2023-02-09 Regeneration Envelope 08 treatment facilities (sewage Envelope process ion pipelines and septic tanks), (Non Bank-SPD) garbage disposal facilities, electricity. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SXMB-HW-02 / procurement Component 1: Increased Single Stage - One of 12 electric buses and IBRD / 89700 Access to Financial Services Post Request for Bids Open - National 967,723.16 1,278,142.26 Signed 2021-08-18 2021-08-23 2021-08-23 2021-10-21 2021-10-04 2021-10-21 2021-11-03 2021-12-06 2021-12-08 2022-01-20 2022-06-06 Envelope charging facilities for MSEs NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SXMB-C11 / Project Management Consulting Component 1: Increased Services, including socio- Quality And Cost- / Access to Financial Services Prior Open - International 2,600,000.00 1,946,550.27 Signed 2019-05-15 2019-08-20 2019-06-20 2019-09-20 2019-08-03 2020-03-05 2019-08-31 2020-07-07 2019-09-30 2020-07-10 2019-11-04 2021-03-02 2019-12-09 2021-03-18 2020-12-08 economic impact evaluation Based Selection for MSEs and beneficiary satisfaction surveys. SXMB-C02 / Financial Component 1: Increased Technology in support of Quality And Cost- Pending / Access to Financial Services Post Open - International 350,000.00 0.00 2019-05-31 2019-06-21 2019-08-04 2019-09-01 2019-10-01 2019-11-05 2019-12-10 2020-12-09 MSEs Application and Credit Based Selection Implementation for MSEs Assessment SXMB-C16 / Consulting Services for Design, Component 1: Increased Quality And Cost- Construction Drawings, BQs IBRD / 89700 Access to Financial Services Post Open - International 620,000.00 657,758.16 Signed 2019-10-15 2019-11-06 2019-11-05 2019-11-13 2019-12-19 2020-05-11 2020-01-16 2020-06-23 2020-02-15 2020-09-15 2020-03-21 2020-09-23 2020-04-25 2021-01-12 2021-04-25 Based Selection of Maiji District and Wushan for MSEs County, Tianshui. Page 1 SXMB-C17 / Consulting Services for Design, Component 1: Increased Quality And Cost- Construction Drawings, BQs IBRD / 89700 Access to Financial Services Prior Open - International 1,230,000.00 0.00 Canceled 2019-10-15 2019-11-12 2019-11-05 2019-11-13 2019-12-19 2020-03-10 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Based Selection of Lintao County and Tongwei for MSEs County, Dingxi City. SXMB-C18 / Consulting Component 1: Increased Services for Design, Quality And Cost- IBRD / 89700 Access to Financial Services Post Open - International 480,000.00 511,253.43 Signed 2019-10-15 2019-11-12 2019-11-05 2019-11-11 2019-12-19 2020-05-11 2020-01-16 2020-06-23 2020-02-15 2020-10-12 2020-03-21 2020-09-27 2020-04-25 2021-01-15 2021-04-25 Construction Drawings, BQs Based Selection for MSEs of Zhangye SXMB-C19 / Consulting Component 1: Increased Services for Design, Quality And Cost- IBRD / 89700 Access to Financial Services Post Open - International 530,000.00 0.00 Canceled 2019-10-15 2019-10-15 2019-11-05 2019-11-13 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Construction Drawings, BQs Based Selection for MSEs of Jiuquan and Dunhuang. SXMB-C12 / Establishment of Project Management Component 1: Increased Consultant Information System IBRD / 89700 Access to Financial Services Post Qualification Open - National 290,000.00 0.00 Canceled 2019-11-04 2019-11-06 2019-11-25 2020-03-17 2020-01-08 2020-10-28 2020-02-07 2020-03-13 2020-09-09 (Procurement of Standard for MSEs Selection Software). SXMB-C15 / Consulting Component 1: Increased Services for Design, Quality And Cost- IBRD / 89700 Access to Financial Services Prior Open - International 1,080,000.00 986,583.22 Signed 2019-11-11 2020-08-11 2019-12-02 2020-09-23 2020-01-15 2021-03-29 2020-02-12 2021-05-13 2020-03-13 2021-07-19 2020-04-17 2021-09-06 2020-05-22 2021-11-18 2021-05-22 Construction Drawings, BQs Based Selection for MSEs of Qin'an County, Tianshui. SXMB-C20 / Construction Component 1: Increased Quality And Cost- Supervision of Tianshui and IBRD / 89700 Access to Financial Services Prior Open - International 2,080,000.00 1,747,167.01 Signed 2020-06-19 2020-07-08 2020-08-04 2020-09-15 2020-09-30 2021-01-25 2020-11-20 2021-03-12 2020-12-20 2021-03-24 2021-01-24 2021-04-22 2021-02-28 2021-05-26 2022-02-28 Based Selection Dingxi Works. for MSEs SXMB-C21 / Construction Component 1: Increased Quality And Cost- Supervision of Zhangye, IBRD / 89700 Access to Financial Services Prior Open - International 1,100,000.00 1,012,238.09 Signed 2020-06-19 2020-07-08 2020-08-04 2020-09-15 2020-09-30 2021-01-25 2020-11-20 2021-03-12 2020-12-20 2021-03-23 2021-01-24 2021-04-22 2021-02-28 2021-05-13 2022-02-28 Based Selection Jiuquan and Dunhuang for MSEs SXMB-C35 / environment and Component 1: Increased Consultant social safeguards consulting IBRD / 89700 Access to Financial Services Post Qualification Open - National 60,000.00 96,945.59 Signed 2020-06-21 2020-06-24 2020-07-12 2020-06-24 2020-08-25 2020-07-16 2020-09-24 2020-08-17 2020-10-29 2020-08-17 2021-04-27 services for the component 1 for MSEs Selection SXMB-C13 / Environmental Component 1: Increased Consultant Impact Assessment & IBRD / 89700 Access to Financial Services Post Qualification Open - National 290,000.00 291,269.66 Signed 2020-07-10 2020-09-10 2020-07-31 2020-09-18 2020-09-13 2020-10-16 2020-10-13 2020-11-06 2020-11-17 2021-02-08 2021-05-16 Monitoring. for MSEs Selection SXMB-C14 / Social Component 1: Increased Consultant Development Assessment & IBRD / 89700 Access to Financial Services Post Qualification Open - National 290,000.00 278,892.07 Signed 2020-07-10 2020-09-10 2020-07-31 2020-09-18 2020-09-13 2020-10-16 2020-10-13 2020-11-06 2020-11-17 2021-02-05 2021-05-16 Monitoring. for MSEs Selection SXMB-C12-1 / Establishment of Project Management Component 1: Increased Consultant Information System IBRD / 89700 Access to Financial Services Post Qualification Open - National 130,000.00 128,550.48 Signed 2021-07-02 2021-07-19 2021-07-23 2021-08-03 2021-09-05 2021-08-24 2021-10-05 2021-09-30 2021-11-09 2021-10-13 2026-07-07 (Procurement of Standard for MSEs Selection Software). Component 3: Institutional Consultant SXMB-C06 / Training of Pending IBRD / 89700 Strengthening and Global Post Qualification Open - National 290,000.00 0.00 2022-03-15 2022-04-05 2022-05-19 2022-06-18 2022-07-23 2023-01-19 Cultural Tourism Practitioners Implementation Knowledge Transfer Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SXMB-C22 / Advisory Service with UNESCO to Strengthen Gansu Creative Industry; Component 3: Institutional Intangible Heritage Support; Pending IBRD / 89710 Strengthening and Global Post Direct Selection Direct 510,000.00 0.00 2022-01-29 2022-02-08 2022-04-14 2022-10-11 Dunhuang Site Management Implementation Knowledge Transfer Plan; and Support Global Knowledge Sharing (on-the- job capacity strengthening) SXMB-C23 / Advisory Service with UNWTO to Review and Enhance Gansu Tourism Strategy; Enhance Marketing, Component 3: Institutional Pending Promotion and Branding IBRD / 89700 Strengthening and Global Post Direct Selection 400,000.00 0.00 2022-01-29 2022-02-08 2022-04-14 2022-10-11 Implementation Strategy Efforts; and Support Knowledge Transfer Global Knowledge Sharing (on- the-job capacity strengthening) Page 2