PROCUREMENT PLAN (Textual Part) Project Information: Ghana Energy Sector Transformation Initiative Project (P163984) Project Implementation agency: Ministry of Energy (MoEn) Date of Procurement Plan: April 2019 Period covered by this Procurement Plan: March 2019 – September 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Ghana Public Procurement Act 2003 (Act 663) and the Ghana Public Procurement (Amendment) Act 2016 (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable. Works: Not Applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information. None. PROCUREMENT Ghana : Ghana Energy Sector Transformation Initiative Project PLAN General Information Country: Ghana 2019-04-24 Bank’s Approval Date of the Original Procurement Plan: 2022-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163984 GPN Date: Project Name: Ghana Energy Sector Transformation Initiative Project Loan / Credit No: IDA / 63030 Ministry of Energy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-MOEN-295908-CW-RFB / Request for Bids - CONSTRUCTION OF 2-STORE Component 5: Project mana Single Stage - One E Small Works SPD Pending Imp 2023-02-1 IDA / 63030 Post Request for Bids Open - National 300,000.00 0.00 2022-06-01 2022-06-06 2022-07-18 2022-08-17 2022-09-21 Y PRE-FABRICATED OFFICE B gement nvelope (1 envelope proce lementation 8 UILDING FOR MINISTRY OF E ss) NERGY GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOEN-115968-GO-RFB / Component 1: Management Single Stage - One E IDA / 63030 Post Request for Bids Open - National 140,000.00 134,923.23 Completed 2019-06-10 2019-06-28 2019-06-15 2019-07-27 2019-07-31 2019-08-26 2019-10-30 2019-09-30 2019-12-19 2020-01-28 2020-01-29 2No. 4WD Cross Country Veh of energy sector financial flo nvelope icles ws GH-MOEN-114744-GO-RFB / Component 1: Management Single Stage - One E Pending Impl IDA / 63030 Post Request for Bids Open - National 160,000.00 0.00 2020-02-14 2020-02-19 2020-03-11 2020-04-10 2020-05-22 2020-08-20 Office equipment and furnitu of energy sector financial flo nvelope ementation re ws GH-MOEN-114755-GO-RFB / Component 1: Management Open - Internationa Single Stage - One E E-Billing/E-Payment Software IDA / 63030 of energy sector financial flo Post Request for Bids 600,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 2021-07-20 l nvelope and Hardware Equipment ws GH-MOEN-114753-GO-RFB / Component 2: Sector Planni Open - Internationa Single Stage - One E E-Billing/E-Payment Software IDA / 63030 Post Request for Bids 150,000.00 0.00 Canceled 2019-08-12 2019-08-17 2019-09-28 2019-10-28 2019-12-02 2020-05-30 ng and coordination l nvelope and Hardware Equipment GH-MOEN-167989-GO-DIR / Component 5: Project mana COVID-19 Emergency Respon IDA / 63030 Prior Direct Selection Direct 10,000.00 0.00 Canceled 2020-04-13 2020-04-18 2020-05-03 2020-05-18 gement se Computer Equipment and Accessories GH-MOEN-222040-GO-DIR / Upgrade of GRIDCo’s SCADA Component 2: Sector Planni Under Imple IDA / 63030 Prior Direct Selection Direct 2,600,000.00 0.00 2021-06-30 2022-01-13 2021-07-14 2022-04-06 2021-10-06 2022-10-06 Network Management Syste ng and coordination mentation m and Telecommunications GH-MOEN-274413-GO-DIR / Completion of Supply and Ins Component 2: Sector Planni Under Imple IDA / 63030 Post Direct Selection Direct 600,000.00 0.00 2022-01-25 2022-05-11 2022-01-27 2022-02-04 2022-05-05 tallation of Outage Managem ng and coordination mentation ent System for ECG GH-MOEN-274420-GO-DIR / Completion of Supply and Ins Component 2: Sector Planni Under Imple IDA / 63030 Post Direct Selection Direct 1,770,000.00 0.00 2022-01-25 2022-05-11 2022-01-27 2022-02-04 2022-07-04 tallation of Enterprise Resour ng and coordination mentation ce Planning for ECG GH-MOEN-274434-GO-DIR / Supply and Installation of PLE Component 2: Sector Planni Under Imple IDA / 63030 Post Direct Selection Direct 400,000.00 0.00 2022-01-30 2022-05-09 2022-02-04 2022-03-18 2022-09-14 XOS Simulation Modelling Sof ng and coordination mentation tware and Training GH-MOEN-274437-GO-DIR / Component 3: Energy acces Under Imple Supply and Installation of GIS IDA / 63030 Post Direct Selection Direct 50,000.00 0.00 2022-01-30 2022-05-09 2022-02-13 2022-03-20 2022-06-18 s mentation Software and Training GH-MOEN-281245-GO-DIR / Component 3: Energy acces Under Imple Supply and Installation of PLS IDA / 63030 Post Direct Selection Direct 60,000.00 0.00 2022-03-14 2022-03-21 2022-03-19 2022-04-17 2022-06-16 s mentation CADD Powerline Software an d Training NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOEN-114762-CS-CQS / Component 1: Management Consultant Qualifi IDA / 63030 Post Open - National 50,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-13 2019-10-18 2020-01-16 Street-lighting Tariff Analysis of energy sector financial flo cation Selection ws GH-MOEN-114763-CS-LCS / Component 2: Sector Planni Least Cost Selecti Open - Internationa Gas and Power Sector Coordi IDA / 63030 Post 100,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-05-16 ng and coordination on l nation Study GH-MOEN-114850-CS-QCBS Component 1: Management Quality And Cost- Open - Internationa IDA / 63030 Post 200,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-11 2019-10-11 2019-11-15 2019-12-20 2020-04-18 / Technical Audit of Power Pla of energy sector financial flo Based Selection l nts ws GH-MOEN-114851-CS-QCBS / Satellite and Field Survey A Component 3: Energy acces Quality And Cost- Open - Internationa IDA / 63030 Post 250,000.00 198,880.00 Signed 2019-06-10 2019-09-17 2019-07-01 2019-10-10 2019-08-14 2020-03-13 2019-09-11 2020-05-11 2019-10-11 2020-09-30 2019-11-15 2020-12-18 2019-12-20 2021-01-18 2020-04-18 nalysis and Upgrade of Existi s Based Selection l ng Geospatial Software GH-MOEN-114855-CS-QCBS Component 3: Energy acces Quality And Cost- Open - Internationa / eGIS for NEDCo Techiman a IDA / 63030 Prior 1,750,000.00 1,561,500.00 Signed 2019-06-10 2019-12-05 2019-07-01 2020-01-31 2019-08-14 2020-05-27 2019-09-11 2020-07-24 2019-10-11 2020-08-25 2019-11-15 2020-11-23 2019-12-20 2020-12-10 2021-06-12 s Based Selection l nd Parts of Sunyani Operatio nal Areas Page 1 GH-MOEN-114869-CS-QCBS Quality And Cost- Open - Internationa / Feasibility study to improve IDA / 63030 Component 4: Natural gas Post 300,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-11 2019-10-11 2019-11-15 2019-12-20 2020-04-18 Based Selection l efficiency of GNGC plants GH-MOEN-114871-CS-QCBS / Study to optimize LNG to in Quality And Cost- Open - Internationa IDA / 63030 Component 4: Natural gas Post 300,000.00 0.00 Canceled 2019-06-10 2019-07-01 2019-08-14 2019-09-11 2019-10-11 2019-11-15 2019-12-20 2020-04-18 corporate bulk-breaking capa Based Selection l bilities and possibility of extr acting LPG GH-MOEN-114873-CS-QCBS Quality And Cost- Open - Internationa / Strategy for Competitive Te IDA / 63030 Component 4: Natural gas Post 150,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-06-25 Based Selection l ndering of Gas/LNG Volumes GH-MOEN-114876-CS-QCBS / Study on deregulation of tra Quality And Cost- Open - Internationa IDA / 63030 Component 4: Natural gas Post 250,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-05-16 nsportation in the petroleum Based Selection l downstream industry GH-MOEN-114880-CS-QCBS Quality And Cost- Open - Internationa / Control of Major Accident H IDA / 63030 Component 4: Natural gas Post 270,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-05-16 Based Selection l azards (COMAH) Regulations Study GH-MOEN-114882-CS-QCBS Quality And Cost- Open - Internationa / Control of Major Accident H IDA / 63030 Component 4: Natural gas Post 270,000.00 0.00 Canceled 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-05-16 Based Selection l azards (COMAH) Regulations Study GH-MOEN-114885-CS-QCBS Component 1: Management Quality And Cost- Open - Internationa / Management of Implementa IDA / 63030 of energy sector financial flo Post 400,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-08-19 Based Selection l tion of Approved VRA Restruc ws turing GH-MOEN-114886-CS-QCBS Component 2: Sector Planni Quality And Cost- Open - Internationa / Gas Regulatory Framework IDA / 63030 Post 500,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-06-20 ng and coordination Based Selection l and Institutional Setup studie s GH-MOEN-114887-CS-QCBS Component 2: Sector Planni Quality And Cost- Open - Internationa / Electricity Regulatory Fram IDA / 63030 Post 500,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-06-20 ng and coordination Based Selection l ework and Institutional Setup studies GH-MOEN-114888-CS-QCBS Component 2: Sector Planni Quality And Cost- Open - Internationa IDA / 63030 Post 200,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-06-20 / Fuel Procurement Strategy ng and coordination Based Selection l GH-MOEN-114889-CS-QCBS Component 3: Energy acces Quality And Cost- Open - Internationa IDA / 63030 Post 500,000.00 467,573.40 Signed 2019-08-12 2019-06-10 2019-09-02 2019-08-21 2019-10-16 2020-03-13 2019-11-13 2020-05-07 2019-12-13 2020-08-14 2020-01-17 2020-09-22 2020-02-21 2020-11-16 2020-08-19 / Distribution Master Plan Stu s Based Selection l dies GH-MOEN-114890-CS-QCBS Component 3: Energy acces Quality And Cost- Open - Internationa / Update of Distribution and IDA / 63030 Post 170,000.00 414,250.00 Signed 2019-08-12 2019-08-21 2019-09-02 2019-10-10 2019-10-16 2020-03-13 2019-11-13 2020-05-06 2019-12-13 2020-08-14 2020-01-17 2020-10-12 2020-02-21 2020-11-16 2020-08-19 s Based Selection l Construction Standards Studi es GH-MOEN-114891-CS-QCBS Quality And Cost- Open - Internationa / Gas market review and mar IDA / 63030 Component 4: Natural gas Post 320,000.00 0.00 Canceled 2019-08-12 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2020-08-19 Based Selection l ket development study GH-MOEN-114893-CS-QCBS Quality And Cost- Open - Internationa / Cost-Reflective Gas Tariff M IDA / 63030 Component 4: Natural gas Post 150,000.00 0.00 Canceled 2020-02-24 2020-03-16 2020-04-29 2020-05-27 2020-06-26 2020-07-31 2020-09-04 2021-01-02 Based Selection l ethodology Study GH-MOEN-114879-CS-QCBS Quality And Cost- Open - Internationa / Development of Natural Ga IDA / 63030 Component 4: Natural gas Post 300,000.00 850,414.00 Signed 2020-03-02 2020-04-03 2020-03-23 2020-04-18 2020-05-06 2020-08-26 2020-06-03 2020-09-29 2020-07-03 2020-10-11 2020-08-07 2020-11-10 2020-09-11 2021-01-28 2021-01-09 Based Selection l s Distribution franchise in Te ma GH-MOEN-114874-CS-QCBS Quality And Cost- Open - Internationa / Strategy for Balancing Natu IDA / 63030 Component 4: Natural gas Post 250,000.00 207,418.80 Signed 2020-03-02 2020-04-03 2020-03-23 2020-04-18 2020-05-06 2020-08-20 2020-06-03 2020-09-28 2020-07-03 2020-10-11 2020-08-07 2021-01-12 2020-09-11 2021-01-29 2021-03-10 Based Selection l ral Gas Demand and Supply GH-MOEN-114872-CS-QCBS Component 2: Sector Planni Quality And Cost- Open - Internationa / Grid Resilience and Reinforc IDA / 63030 Post 400,000.00 0.00 Canceled 2020-10-05 2020-10-26 2020-12-09 2021-01-06 2021-02-05 2021-03-12 2021-04-16 2021-10-13 ng and coordination Based Selection l ement Study GH-MOEN-114854-CS-QCBS / Consumer and Market Asse Component 3: Energy acces Quality And Cost- Open - Internationa IDA / 63030 Post 180,000.00 163,770.00 Signed 2020-03-03 2020-02-08 2020-03-24 2020-02-19 2020-05-07 2020-06-15 2020-06-04 2020-07-22 2020-07-04 2020-09-02 2020-08-08 2020-10-22 2020-09-12 2020-11-20 2021-01-10 ssment Study and Developm s Based Selection l ent of National Clean Cookin g Strategy for Ghana GH-MOEN-114852-CS-QCBS Component 3: Energy acces Quality And Cost- Open - Internationa Under Implement / Feasibility and Investment P IDA / 63030 Post 250,000.00 0.00 2020-07-06 2021-11-09 2020-07-27 2022-02-04 2020-09-09 2020-10-07 2020-11-06 2020-12-11 2021-01-15 2021-05-15 s Based Selection l ation lanning Studies GH-MOEN-156217-CS-QCBS Component 1: Management Quality And Cost- Open - Internationa / Legal and Financial Review IDA / 63030 of energy sector financial flo Post 150,000.00 0.00 Canceled 2020-03-02 2020-03-23 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-01-09 Based Selection l of Backlog of Power Purchase ws Agreements GH-MOEN-156224-CS-QCBS Component 1: Management Quality And Cost- Open - Internationa IDA / 63030 Post 300,000.00 294,650.00 Signed 2020-03-02 2020-10-14 2020-03-23 2020-11-17 2020-05-06 2021-02-23 2020-06-03 2021-03-26 2020-07-03 2021-04-26 2020-08-07 2021-06-17 2020-09-11 2021-09-03 2021-01-09 / Audit and Review of the Leg of energy sector financial flo Based Selection l acy Debt ws GH-MOEN-156226-CS-LCS / I Component 1: Management ndependent Assessment and Least Cost Selecti Open - Internationa IDA / 63030 of energy sector financial flo Post 80,000.00 0.00 Canceled 2020-04-06 2020-04-27 2020-06-10 2020-07-08 2020-08-07 2020-09-11 2020-10-16 2021-01-14 Drafting of all Required Chan on l ws ges in PURC Act GH-MOEN-156229-CS-QCBS / Integration of PURC Databa Component 2: Sector Planni Quality And Cost- Open - Internationa IDA / 63030 Post 300,000.00 0.00 Canceled 2020-03-02 2020-05-27 2020-03-23 2020-10-14 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-01-09 se with Utility Providers to ge ng and coordination Based Selection l t Real-time Data GH-MOEN-156230-CS-QCBS Component 2: Sector Planni Quality And Cost- Open - Internationa / Review of Ghana Petroleum IDA / 63030 Post 300,000.00 208,320.00 Completed 2020-03-02 2020-04-03 2020-03-23 2020-04-18 2020-05-06 2020-08-20 2020-06-03 2020-09-29 2020-07-03 2020-10-11 2020-08-07 2020-11-12 2020-09-11 2021-01-19 2021-01-09 2021-10-19 ng and coordination Based Selection l Products Price Build-Up GH-MOEN-156234-CS-QCBS Component 2: Sector Planni Quality And Cost- Open - Internationa IDA / 63030 Post 110,000.00 0.00 Canceled 2020-10-05 2020-10-26 2020-12-09 2021-01-06 2021-02-05 2021-03-12 2021-04-16 2021-10-13 / Gap and Regional Market A ng and coordination Based Selection l nalysis GH-MOEN-167986-CS-QCBS Component 1: Management / Cash Water-Fall Mechanism Quality And Cost- Open - Internationa IDA / 63030 of energy sector financial flo Post 100,000.00 0.00 Canceled 2020-04-20 2020-05-11 2020-06-24 2020-07-22 2020-08-21 2020-09-25 2020-10-30 2021-04-28 Real-Time IT Platform Develo Based Selection l ws pment and Implementation GH-MOEN-167993-CS-LCS / Component 1: Management Least Cost Selecti Open - Internationa IDA / 63030 Post 60,000.00 0.00 Canceled 2020-05-10 2020-05-31 2020-07-21 2020-08-18 2020-09-17 2020-10-22 2020-11-26 2021-03-06 Streetlighting Tariff Analysis of energy sector financial flo on l ws Page 2 GH-MOEN-189339-CS-QCBS Component 1: Management Quality And Cost- Open - Internationa / Consultancy for Assessment IDA / 63030 of energy sector financial flo Post 300,000.00 678,218.75 Signed 2020-08-20 2020-08-25 2020-09-03 2020-09-16 2020-10-15 2021-02-01 2020-11-12 2021-03-12 2020-12-10 2021-04-07 2021-01-07 2021-07-07 2021-02-11 2021-09-03 2021-12-08 Based Selection l of Street-lighting In Ghana ws GH-MOEN-189356-CS-QCBS Component 1: Management Quality And Cost- Open - Internationa / Consultancy Services for Te IDA / 63030 of energy sector financial flo Post 500,000.00 160,047.69 Signed 2020-08-21 2020-08-25 2020-09-11 2020-11-17 2020-10-25 2021-02-25 2020-11-22 2021-03-26 2020-12-22 2021-04-23 2021-01-26 2021-06-22 2021-03-02 2021-09-03 2021-12-27 Based Selection l chnical Audit of Power Plants ws GH-MOEN-220368-CS-QCBS Component 3: Energy acces Quality And Cost- Open - Internationa / Network Protection and Coo IDA / 63030 Post 500,000.00 327,613.00 Signed 2021-03-07 2021-04-12 2021-04-04 2021-04-28 2021-05-18 2021-08-05 2021-06-15 2021-09-03 2021-07-15 2021-10-08 2021-08-19 2021-11-10 2021-09-23 2022-02-16 2022-03-22 s Based Selection l rdination Study for NEDCo GH-MOEN-222022-CS-QCBS Component 1: Management / Development of Methodolog Quality And Cost- Open - Internationa IDA / 63030 of energy sector financial flo Post 500,000.00 0.00 Canceled 2021-03-15 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2022-03-30 ies for Competitive Selection Based Selection l ws for ECG Governance Structur e GH-MOEN-222023-CS-QCBS / Technical and Legal Suppor Quality And Cost- Open - Internationa IDA / 63030 Component 4: Natural gas Post 300,000.00 0.00 Canceled 2021-05-24 2021-06-21 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-06-08 t for Implementation of Gas A Based Selection l ggregator Role GH-MOEN-222025-CS-QCBS Component 1: Management / Update of Tariff Methodolog Quality And Cost- Open - Internationa IDA / 63030 of energy sector financial flo Post 250,000.00 0.00 Canceled 2021-03-15 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2022-03-30 y, Design and Implementatio Based Selection l ws n of Customer Satisfaction In dex (CSI) GH-MOEN-222026-CS-QCBS / Development of CRM Comm Component 2: Sector Planni Quality And Cost- Open - Internationa IDA / 63030 Post 250,000.00 0.00 Canceled 2021-03-15 2021-04-12 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2021-12-30 unication and Public Relation ng and coordination Based Selection l s Implementation Plan GH-MOEN-222027-CS-QCBS Quality And Cost- Open - Internationa / Development of COMAH an IDA / 63030 Component 4: Natural gas Post 250,000.00 167,600.00 Signed 2021-05-24 2021-08-06 2021-06-21 2021-08-16 2021-08-04 2021-10-12 2021-09-01 2021-11-26 2021-10-01 2021-12-10 2021-11-05 2021-12-22 2021-12-10 2022-02-18 2022-04-09 Based Selection l d Natural Gas Distribution Re gulations GH-MOEN-222028-CS-QCBS / Review of Natural Gas Tran Quality And Cost- Open - Internationa IDA / 63030 Component 4: Natural gas Post 300,000.00 0.00 Canceled 2021-03-15 2021-07-13 2021-04-12 2021-08-06 2021-05-26 2021-06-23 2021-07-23 2021-08-27 2021-10-01 2021-12-30 smission and Distribution Infr Based Selection l astructure Development Plan of Ghana GH-MOEN-222030-CS-QCBS / Estimation of the Value of L Component 2: Sector Planni Quality And Cost- Open - Internationa IDA / 63030 Post 250,000.00 59,200.00 Signed 2021-03-15 2021-06-17 2021-04-12 2021-08-06 2021-05-26 2021-10-14 2021-06-23 2021-11-16 2021-07-23 2021-12-02 2021-08-27 2021-12-23 2021-10-01 2022-02-18 2021-10-15 ost Load (VoLL) of Electricity ng and coordination Based Selection l Supply in Ghana GH-MOEN-222032-CS-QCBS Component 1: Management Quality And Cost- Open - Internationa / Development of Fuel Procur IDA / 63030 of energy sector financial flo Post 200,000.00 0.00 Canceled 2021-05-17 2021-06-14 2021-07-28 2021-08-25 2021-09-24 2021-10-29 2021-12-03 2022-03-03 Based Selection l ement Strategy for Ghana ws GH-MOEN-222034-CS-QCBS / Development of CRM Monit Component 2: Sector Planni Quality And Cost- Open - Internationa IDA / 63030 Post 200,000.00 142,941.35 Signed 2021-03-15 2021-08-06 2021-04-12 2021-08-06 2021-05-26 2021-10-14 2021-06-23 2021-11-16 2021-07-23 2021-12-07 2021-08-27 2021-12-22 2021-10-01 2022-02-23 2021-12-30 oring and Evaluation Framew ng and coordination Based Selection l ork and CRM Baseline Study f or NPA GH-MOEN-222036-CS-QCBS Quality And Cost- Open - Internationa IDA / 63030 Component 4: Natural gas Post 300,000.00 0.00 Canceled 2021-04-05 2021-05-03 2021-06-16 2021-07-14 2021-08-13 2021-09-17 2021-10-22 2022-04-20 / Analysis of Gas Value Chain Based Selection l Costs GH-MOEN-240109-CS-QCBS / Consultancy Services To De Component 2: Sector Planni Quality And Cost- Open - Internationa IDA / 63030 Post 300,000.00 139,792.80 Signed 2021-06-23 2021-07-09 2021-07-14 2021-08-06 2021-08-27 2021-10-14 2021-09-24 2021-11-16 2021-10-24 2021-12-09 2021-11-28 2021-12-23 2022-01-02 2022-02-21 2022-07-31 velop Of LPG Behavioural Ch ng and coordination Based Selection l ange And Public Awareness S trategy GH-MOEN-258682-CS-QCBS / Feasibility studies for NEDC Component 3: Energy acces Quality And Cost- Open - Internationa Under Implement IDA / 63030 Post 300,000.00 0.00 2021-10-31 2022-01-08 2021-11-14 2022-02-04 2021-12-12 2022-01-09 2022-01-23 2022-02-27 2022-04-10 2022-12-16 o Fibre Optic Broadband Infra s Based Selection l ation structure Deployment GH-MOEN-258685-CS-QCBS Component 3: Energy acces Quality And Cost- Open - Internationa Under Implement / Short- and Long-term Energ IDA / 63030 Post 500,000.00 0.00 2021-10-31 2021-12-13 2021-11-14 2022-02-04 2021-12-26 2022-01-23 2022-02-06 2022-03-06 2022-04-10 2022-12-16 s Based Selection l ation y and Demand Forecast INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MOEN-110263-CS-CDS / Component 5: Project mana IDA / 63030 Prior Direct Selection Direct 102,924.00 137,232.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Power Sector Specialist gement GH-MOEN-110277-CS-CDS / Component 5: Project mana IDA / 63030 Prior Direct Selection Direct 56,700.00 75,600.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Social & Gender Specialist gement GH-MOEN-110279-CS-CDS / Component 5: Project mana IDA / 63030 Prior Direct Selection Direct 40,080.00 40,080.00 Completed 2019-05-27 2019-08-28 2019-06-10 2019-09-12 2019-09-23 2019-09-27 2020-09-30 2020-09-30 Renewable Electricity Expert gement GH-MOEN-113272-CS-CDS / Component 5: Project mana IDA / 63030 Prior Direct Selection Direct 162,162.00 0.00 Canceled 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2021-12-31 Project Manager gement GH-MOEN-113274-CS-CDS / Component 5: Project mana IDA / 63030 Prior Direct Selection Direct 130,977.00 174,636.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Financial Management Speci gement alist GH-MOEN-113275-CS-CDS / Component 5: Project mana IDA / 63030 Prior Direct Selection Direct 109,161.00 145,548.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Procurement Specialist gement GH-MOEN-113276-CS-CDS / Component 5: Project mana IDA / 63030 Prior Direct Selection Direct 85,779.00 114,372.00 Signed 2019-05-27 2019-08-28 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Monitoring & Evaluation Spec gement ialist GH-MOEN-113277-CS-CDS / Component 5: Project mana IDA / 63030 Prior Direct Selection Direct 67,500.00 90,000.00 Signed 2019-05-27 2019-08-27 2019-06-24 2019-09-12 2019-09-23 2019-09-27 2021-12-31 Communication Specialist gement GH-MOEN-113280-CS-INDV / Component 5: Project mana Individual Consult IDA / 63030 Prior Open 110,200.00 133,200.00 Signed 2019-05-20 2019-06-18 2019-07-01 2019-09-16 2019-07-08 2019-09-20 2019-07-29 2019-09-30 2021-12-31 Gas Sector Specialist gement ant Selection GH-MOEN-150645-CS-INDV / Component 1: Management Individual Consult IDA / 63030 Post Limited 216,000.00 204,000.00 Signed 2019-12-24 2019-12-22 2019-12-29 2020-01-13 2020-01-08 2020-01-27 2020-01-22 2020-02-28 2023-01-21 Technical Coordinator of energy sector financial flo ant Selection ws Page 3 GH-MOEN-151138-CS-INDV / Component 1: Management Individual Consult IDA / 63030 Post Limited 108,000.00 96,000.00 Signed 2019-12-24 2019-12-22 2019-12-29 2020-01-13 2020-01-08 2020-01-27 2020-01-22 2020-04-23 2023-01-21 Policy Advisor of energy sector financial flo ant Selection ws GH-MOEN-151141-CS-INDV / Consultancy Services for the Component 1: Management Individual Consult Preparation of Procedures an IDA / 63030 of energy sector financial flo Post Limited 10,000.00 22,000.00 Completed 2019-12-24 2019-12-22 2019-12-29 2020-01-13 2020-01-08 2020-01-27 2020-01-22 2020-02-28 2020-02-21 2020-06-30 ant Selection d Operational Document for I ws mplementation of Cash Wate r-Fall Mechanism GH-MOEN-167982-CS-INDV / Component 1: Management Individual Consult Cash Water-Fall Mechanism I IDA / 63030 of energy sector financial flo Post Limited 144,000.00 144,000.00 Signed 2020-04-20 2020-06-15 2020-04-30 2020-06-22 2020-05-21 2020-07-23 2020-06-25 2020-07-29 2022-06-15 ant Selection ndependent Accountant ws GH-MOEN-167984-CS-INDV / Component 1: Management Individual Consult Cash Water-Fall Mechanism F IDA / 63030 of energy sector financial flo Post Limited 60,000.00 60,000.00 Signed 2020-04-20 2020-06-15 2020-04-30 2020-06-22 2020-05-21 2020-07-23 2020-06-25 2020-07-29 2022-06-15 ant Selection inancial Analyst ws GH-MOEN-174618-CS-INDV / Consultancy Services To Sup Component 1: Management Individual Consult port NEDCo In The Definition IDA / 63030 of energy sector financial flo Post 50,000.00 0.00 Canceled 2020-05-25 2020-05-30 2020-06-20 2020-07-14 2020-10-12 ant Selection Of An Action Plan For Improv ws ement Of Revenue Cycle And Prepayment Operations GH-MOEN-175924-CS-INDV / Consultancy Services To Sup Component 1: Management Individual Consult port NEDCo In The Definition IDA / 63030 of energy sector financial flo Post Limited 50,000.00 35,485.00 Signed 2020-06-02 2020-08-18 2020-06-07 2020-10-13 2020-06-28 2021-03-16 2020-07-26 2021-04-13 2020-10-24 ant Selection Of An Action Plan For Improv ws ement Of Revenue Cycle And Prepayment Operations GH-MOEN-202785-CS-INDV / CONSULTANCY SERVICES FO Individual Consult R LEGAL REVIEW OF THE TAK IDA / 63030 Component 4: Natural gas Post Limited 150,000.00 68,181.82 Completed 2020-11-06 2020-11-05 2020-11-11 2020-11-11 2020-11-20 2020-12-03 2020-11-27 2020-12-09 2021-01-29 2021-05-24 ant Selection ORADI GAS SALES AGREEME NT BETWEEN N-GAS AND VR A GH-MOEN-202793-CS-INDV / CONSULTANCY SERVICES FO Individual Consult R COMMERCIAL REVIEW OF T IDA / 63030 Component 4: Natural gas Post Limited 75,000.00 33,792.60 Completed 2020-11-06 2020-11-05 2020-11-11 2020-11-10 2020-11-20 2020-12-03 2020-11-27 2020-12-09 2021-01-29 2021-05-24 ant Selection HE TAKORADI GAS SALES AG REEMENT BETWEEN N-GAS A ND VRA GH-MOEN-204420-CS-INDV / Technical Assistance for Cap Component 1: Management Individual Consult acity Development and Tooli IDA / 63030 of energy sector financial flo Post Limited 60,000.00 35,485.00 Signed 2020-11-16 2020-11-12 2020-11-21 2020-11-19 2020-12-11 2021-03-10 2020-12-21 2021-03-30 2021-03-21 ant Selection ng For Regulatory Appraisal ws and Monitoring of Performan ce Improvement Projects GH-MOEN-206473-CS-INDV / INTEGRATION OF PURC DATA Component 2: Sector Planni Individual Consult IDA / 63030 Post Limited 70,000.00 0.00 Terminated 2020-11-27 2021-01-08 2020-12-02 2021-02-04 2020-12-23 2021-03-16 2021-01-27 2021-04-07 2021-03-28 BASE WITH UTILITY PROVIDE ng and coordination ant Selection RS TO GET REAL-TIME DATA I N GHANA GH-MOEN-240091-CS-INDV / PREPARATION OF ENVIRONM Component 2: Sector Planni Individual Consult ENTAL AND SOCIAL MANAGE IDA / 63030 Post Limited 70,000.00 55,866.18 Signed 2021-06-24 2021-06-25 2021-07-04 2021-07-08 2021-07-25 2021-09-09 2021-08-14 2021-09-10 2021-11-12 ng and coordination ant Selection MENT FRAMEWORK (ESMF) F OR ELECTRICITY COMPANY O F GHANA (ECG) GH-MOEN-258680-CS-INDV / Preparation of Operations Ma Individual Consult Under Implement IDA / 63030 Component 4: Natural gas Post Limited 70,000.00 0.00 2021-10-31 2021-11-27 2021-11-14 2021-12-12 2022-01-11 2022-05-11 nual For The National LPG Pr ant Selection ation omotion Programme GH-MOEN-274422-CS-CDS / Completion of Consultancy S Component 2: Sector Planni Pending Impleme IDA / 63030 Post Direct Selection Direct 150,000.00 0.00 2022-01-25 2022-01-29 2022-02-10 2022-08-09 ervices for the Supply and In ng and coordination ntation stallation of Enterprise Resou rce Planning for ECG GH-MOEN-274426-CS-INDV / Consultancy Services for the Component 2: Sector Planni Individual Consult Pending Impleme IDA / 63030 Post Limited 100,000.00 0.00 2022-01-30 2022-02-04 2022-03-06 2022-03-27 2022-06-15 Implementation of ECG Adva ng and coordination ant Selection ntation nced Metering Infrastructure (AMI) GH-MOEN-274428-CS-INDV / Consultancy Services for Nee ds Assessment for Upgrade a Component 3: Energy acces Individual Consult Under Implement IDA / 63030 Post Limited 70,000.00 0.00 2022-01-30 2022-02-26 2022-02-04 2022-02-25 2022-03-18 2022-05-07 nd ISO Accreditation of Stove s ant Selection ation Testing Laboratory At KNUST Technology Consultancy Cen tre for Energy Commission GH-MOEN-285922-CS-INDV / CONSULTANCY SERVICES FO R ASSESSMENT FOR INTEGRA Component 2: Sector Planni Individual Consult Pending Impleme IDA / 63030 Post Limited 70,000.00 0.00 2022-03-30 2022-04-06 2022-04-27 2022-05-25 2022-07-24 TION OF PURC DATABASE WI ng and coordination ant Selection ntation TH UTILITY PROVIDERS TO G ET REAL-TIME DATA IN GHAN A Page 4