Procurement Plan (P 155350) Sindh Resilience Project I. General 1. Bank’s approval Date of the procurement Plan [Original: February 28, 2016]: Revision of Updated Procurement Plan, May 2017 ] 2. Date of General Procurement Notice: August 2016 3. Period covered by this procurement plan: The procurement period of project covered from year May 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by SID 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 July 9, 2010 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] July 9, 2010 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : Sindh Resilience Project PLAN General Information Country: Pakistan 2016-11-03 Bank’s Approval Date of the Original Procurement Plan: 2022-09-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155350 GPN Date: 2016-10-28 Project Name: Sindh Resilience Project Loan / Credit No: IDA / 58880, IDA / 67940 Sindh Irrigation Department Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-2961-CW-RFP / Provi ding stone pitching between BU Bund from mile 13/3 to 3 Improving Infrastructure and Open - Internationa Single Stage - One E 5,024,100.3 2017-10-0 5/3 and indo bund from mile IDA / 58880 Prior Request for Bids Signed 2016-11-25 2017-06-02 2016-12-09 2017-06-08 2017-01-23 2017-07-24 2017-02-22 2017-10-02 2017-04-07 2017-10-27 Systems for Resilience l nvelope 6 4 0/0 to 15/6 total 15 miles and 7 furlongs in Sakro Division Mirpursakro. (Baghar Circle H yderabad). PK-SID-2963-CW-RFP / CONS TRUCTION OF BHANSAR SMA Improving Infrastructure and Single Stage - One E 2018-01-0 IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 LL/RECHARGE DAM IN NAGA Systems for Resilience nvelope 8 RPARKAR AREA (THAR REGIO N) PK-SID-2964-CW-RFP / CONS TRUCTION OF SABUSAN SMA Improving Infrastructure and Single Stage - One E 2018-01-0 IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 LL/RECHARGE DAM IN NAGA Systems for Resilience nvelope 8 RPARKAR AREA (THAR REGIO N) PK-SID-2965-CW-RFP / CONS TRUCTION OF SANKAR SMAL Improving Infrastructure and Single Stage - One E 2018-01-0 IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 L/RECHARGE DAM IN NAGAR Systems for Resilience nvelope 8 PARKAR AREA (THAR REGION ) PK-SID-2967-CW-RFP / CONS Improving Infrastructure and Single Stage - One E 2018-06-0 TRUCTION OF KONKAR RECH IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-08-01 2017-08-16 2017-09-27 2017-10-27 2017-12-08 Systems for Resilience nvelope 6 ARGE/SMALL DAM IN LOWER KOHISTAN PK-SID-2968-CW-RFP / CONS Improving Infrastructure and Single Stage - One E 2018-06-0 TRUCTION OF KARMATIANI R IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-08-01 2017-08-16 2017-09-27 2017-10-27 2017-12-08 Systems for Resilience nvelope 6 ECHARGE/SMALL DAM IN LO WER KOHISTAN PK-SID-2960-CW-RFP / Reco upment of stone Apron along S.H Bund mile 1/6 to 2/1 and Repair to damage stone pitch Improving Infrastructure and Single Stage - One E 1,042,222.8 2017-11-0 IDA / 58880 Prior Request for Bids Open - National Signed 2017-01-21 2017-06-29 2017-01-26 2017-07-07 2017-03-09 2017-08-07 2017-04-08 2017-09-21 2017-05-13 2017-10-16 ing along S.H Bund mile 1/0 t Systems for Resilience nvelope 4 9 o 3/0 (Different Reaches) and widening of S.H Bund from m ile 0/4 to 3/2 in Kalri Baghar Division Thatta.(Baghar Circl e Hyderabad). PK-SID-2962-CW-RFP / Stone pitching and Toe Wall along M.S Bund mile 29/2 to 29/5, Improving Infrastructure and Single Stage - One E 2017-11-0 36/0 to 40/0, 45/0 to 58/2, Ra IDA / 58880 Prior Request for Bids Open - National 0.00 Canceled 2017-01-21 2017-06-29 2017-01-26 2017-03-09 2017-04-08 2017-05-13 Systems for Resilience nvelope 9 ising and strengthening alon g M.S Bund mile 55/4 to 58/2 in Lower Pinyari Division Suja wal. (Pinyari Circle Hyderaba d). PK-SID-20260-CW-RFB / Prov iding Stone Pitching along M. Improving Infrastructure and Single Stage - One E 3,557,787.4 Under Imple 2018-03-3 S Bund mile 29/2 to 29/5, 36/ IDA / 58880 Post Request for Bids Open - National 2017-07-21 2017-05-20 2017-07-21 2017-08-07 2017-08-21 2017-08-07 2017-08-28 2017-09-22 2017-10-02 2017-10-17 Systems for Resilience nvelope 6 mentation 1 0 to 40/0 to 58/2 and Raising and Strengthening of M.S Bu nd mile 55/4 to 58/2. PK-SID-29036-CW-RFB / Prov iding Stone Pitching along PB Improving Infrastructure and Single Stage - One E 4,146,864.0 2018-11-0 2019-05 IDA / 58880 Post Request for Bids Open - National Completed 2017-09-19 2018-04-08 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-05 Bund from mile 0/0 to 8/5 an Systems for Resilience nvelope 3 5 -29 d 11/4 to 15/0 in Kalri Baghar Division Thatta. PK-SID-29042-CW-RFB / Eart hwork & Repair Damaged Sto Improving Infrastructure and Single Stage - One E 2018-11-0 2019-04 ne Pitching along up Stream l IDA / 58880 Post Request for Bids Open - National 791,521.35 Completed 2017-09-19 2018-04-08 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-09 Systems for Resilience nvelope 5 -02 eft side guide bund from RD 0+000 to RD 5+700 in Kotri Barrage Division Jamshoro. PK-SID-29051-CW-RFB / Prov iding Stone Pitching along M Improving Infrastructure and Single Stage - One E 6,072,151.7 2018-11-0 S Bund from mile 0/0 to 14/0 IDA / 58880 Post Request for Bids Open - National Signed 2017-09-19 2018-04-08 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-05 Systems for Resilience nvelope 7 5 and 22/0 to 24/7 in Upper Pin yari Division, Hyderabad PK-SID-29055-CW-RFB / Prov iding Stone Pitching along BU Improving Infrastructure and Single Stage - One E 2018-11-0 IDA / 58880 Post Request for Bids Open - National 969,963.22 Signed 2017-09-19 2018-04-09 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-05 Bund from mile 3/0 to 5/0 in Systems for Resilience nvelope 5 Kalri Baghar Division Thatta. PK-SID-29086-CW-RFB / Prov iding Stone Pitching along Ku ka Link Bund 0/0 to 20/6, Rai Improving Infrastructure and Single Stage - One E 4,924,242.9 2018-11-0 sing and Strengthening along IDA / 58880 Post Request for Bids Open - National Signed 2017-09-19 2018-04-08 2017-09-22 2018-04-10 2017-10-23 2018-05-10 2017-10-30 2018-06-04 2017-11-06 2018-07-04 Systems for Resilience nvelope 4 5 Kuka Wari Bund mile 3/6 to7/ 4 and Kuka Wari Retarded Bu nd mile 0/0 to 3/0 in Lower Pi nyari Division Sujawal. PK-SID-37707-CW-RFB / Rec oupment of Damaged Stone Pitching & Earth Work along Improving Infrastructure and Single Stage - One E 2019-04-1 SM Bund from mile 123/0 to IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2018-01-16 2018-01-19 2018-02-21 2018-03-07 2018-04-11 Systems for Resilience nvelope 0 172/0 (Different Reaches) in Hala Irrigation Division Hala. (95 percent from counterpar t funding). PK-SID-69711-CW-RFB / Con struction of 2Nos: Small/Rech Improving Infrastructure and Single Stage - One E 3,704,929.3 2019-11-0 IDA / 58880 Post Request for Bids Open - National Signed 2018-07-16 2018-07-18 2018-07-19 2018-07-19 2018-08-20 2018-08-27 2018-09-19 2018-09-10 2018-11-02 2018-10-01 arge Dams in Lower Khoistan Systems for Resilience nvelope 4 1 Malir namely Karmatiani and Konkar. Page 1 PK-SID-2969-CW-RFP / CONS Improving Infrastructure and Single Stage - One E 2,083,629.7 2019-11-0 TRUCTION OF ARIPIR RECHA IDA / 58880 Post Request for Bids Open - National Signed 2018-07-16 2018-07-18 2018-07-19 2018-07-19 2018-08-20 2018-08-27 2018-09-19 2018-09-13 2018-11-02 2018-10-03 Systems for Resilience nvelope 4 1 RGE/SMALL DAM IN LOWER K OHISTAN. PK-SID-2966-CW-RFP / CONS Improving Infrastructure and Single Stage - One E 3,332,375.0 2019-11-0 TRUCTION OF JUNG SHAHI RE IDA / 58880 Post Request for Bids Open - National Signed 2018-07-16 2018-07-18 2018-07-19 2018-07-19 2018-08-20 2018-08-27 2018-09-19 2018-09-10 2018-11-02 2018-10-03 Systems for Resilience nvelope 8 1 CHARGE/SMALL DAM IN LOW ER KOHISTAN PK-SID-69710-CW-RFB / Con struction of 2Nos: Small/Rech Improving Infrastructure and Open - Internationa Single Stage - One E 7,044,375.2 2019-11-1 IDA / 58880 Post Request for Bids Signed 2018-07-16 2018-07-18 2018-07-19 2018-07-20 2018-09-03 2018-09-07 2018-10-03 2018-10-22 2018-11-16 2018-11-26 arge Dams in Tharparkar na Systems for Resilience l nvelope 8 5 mely Sabusan and Sankar. PK-SID-83933-CW-RFB / Rec oupment of Damaged Stone Pitching & Earth Work along SM Bund from mile 123/0 to Improving Infrastructure and Single Stage - One E 1,063,696.5 2019-10-2 IDA / 58880 Post Request for Bids Open - National Signed 2018-10-29 2018-12-26 2018-11-01 2019-01-03 2018-12-03 2019-02-04 2019-01-02 2019-06-28 2019-01-30 2019-07-23 172/0 (Different Reaches) in Systems for Resilience nvelope 1 7 Hala Irrigation Division Hala. (100 percent payment will be made counterpart funding th rough Government of Sindh). PK-SID-93082-CW-RFB / Pack Improving Infrastructure and Single Stage - One E 2,950,660.0 2020-03-2 age No: 14 Construction of B IDA / 58880 Post Request for Bids Open - National Signed 2018-12-28 2019-01-02 2018-12-31 2019-01-03 2019-01-30 2019-02-04 2019-03-01 2019-03-27 2019-03-29 2019-04-08 Systems for Resilience nvelope 1 7 hansar/ Rathi Small storage Dam. PK-SID-93083-CW-RFB / Pack age No: 15 Lot No. 1 Constru ction of Naing-II Small/Rechar Improving Infrastructure and Single Stage - One E 6,109,757.4 2020-03-2 IDA / 58880 Post Request for Bids Open - National Signed 2018-12-28 2019-01-02 2018-12-31 2019-01-03 2019-01-30 2019-02-04 2019-03-01 2019-03-05 2019-03-29 2019-03-29 ge Dam. Systems for Resilience nvelope 1 7 Lot No. 2 Construction of Gabol and Dh al Dhoro-II Small/Recharge D ams. PK-SID-93084-CW-RFB / Pack age No: 16 Lot No. 1 Constru ction of Tikho-II and Sureshi Improving Infrastructure and Single Stage - One E 5,460,536.9 2020-03-2 Small/Recharge Dams. IDA / 58880 Post Request for Bids Open - National Signed 2018-12-28 2019-01-02 2018-12-31 2019-01-03 2019-01-30 2019-02-04 2019-03-01 2019-03-01 2019-03-29 2019-04-24 Systems for Resilience nvelope 5 7 Lot No. 2 C onstruction of Upper Mole-II Small/Recharge Dam. PK-SID-93086-CW-RFB / Pack Improving Infrastructure and Single Stage - One E 3,549,284.4 2020-03-2 age No: 17 Construction of N IDA / 58880 Post Request for Bids Open - National Signed 2018-12-28 2019-01-02 2018-12-31 2019-01-03 2019-01-30 2019-02-04 2019-03-01 2019-05-24 2019-03-29 2019-06-13 Systems for Resilience nvelope 2 7 ali and Qasim Tok Small/Rec harge Dams. PK-SID-119972-CW-RFB / Pa ckage-I: Construction and Re Improving Infrastructure and Single Stage - One E 1,248,800.0 2020-07-0 IDA / 58880 Post Request for Bids Open - National Signed 2019-06-21 2019-07-01 2019-06-24 2019-07-08 2019-07-24 2019-08-09 2019-08-23 2019-09-05 2019-10-11 2019-10-24 habilitation of Laboratory Bui Systems for Resilience nvelope 9 7 lding and Trays. 1 PK-SID-178002-CW-RFB / Co Improving Infrastructure and Single Stage - One E 1,785,852.7 2021-10-1 nstruction of Jaganwari Small IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-14 Systems for Resilience nvelope 4 3 /Recharge Dam in Khairpur M irs'. PK-SID-178003-CW-RFB / Co Improving Infrastructure and Single Stage - One E 2,032,490.0 2021-10-1 nstruction of Tungwari Small/ IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-20 Systems for Resilience nvelope 7 3 Recharge Dam in Khairpur Mi rs'. PK-SID-178008-CW-RFB / Co Improving Infrastructure and Single Stage - One E 2,075,865.1 2021-10-1 nstruction of Darig Small/Rec IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-04-28 2020-10-14 2021-06-09 Systems for Resilience nvelope 8 3 harge Dam in Khairpur Mirs'. PK-SID-178009-CW-RFB / Co Improving Infrastructure and Single Stage - One E 3,431,427.1 2021-10-1 nstruction of Samlee Small/R IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-16 Systems for Resilience nvelope 5 3 echarge Dam in Nagarparkar (Thar Region). PK-SID-178010-CW-RFB / Co nstruction of Paro Jo Wandhio Improving Infrastructure and Single Stage - One E 2,152,233.6 2021-10-1 IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-06 Small/Recharge Dam in Naga Systems for Resilience nvelope 2 3 rparkar (Thar Region). PK-SID-178011-CW-RFB / Co Improving Infrastructure and Single Stage - One E 2,466,385.3 2021-10-1 nstruction of Sehriyoon Small IDA / 58880 Post Request for Bids Open - National Signed 2020-07-01 2020-09-10 2020-07-02 2020-09-10 2020-08-03 2020-10-15 2020-09-02 2021-03-18 2020-10-14 2021-04-28 Systems for Resilience nvelope 2 3 /Recharge Dam in Nagarpark ar (Thar Region). PK-SID-182665-CW-RFB / Re Improving Infrastructure and Single Stage - One E 2021-10-0 construction of Soil Mechanic IDA / 58880 Post Request for Bids Open - National 458,800.49 Signed 2020-07-01 2020-07-17 2020-07-03 2020-07-17 2020-08-02 2020-08-19 2020-09-01 2020-11-02 2020-10-06 2020-12-08 Systems for Resilience nvelope 5 s Laboratory and Office Buildi ng at Karachi. PK-SID-220119-CW-RFB / CO Improving Infrastructure and Single Stage - One E 2,405,200.2 2022-06-0 NSTRUCTION OF BHATTA SIR IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-04-30 2021-06-09 2021-06-10 Systems for Resilience nvelope 9 8 O DAM IN NAGARPARKAR. PK-SID-220128-CW-RFB / CO Improving Infrastructure and Single Stage - One E 1,746,755.0 2022-06-0 NSTRUCTION OF SOHRIO WA IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-04-30 2021-06-09 2021-06-10 Systems for Resilience nvelope 6 8 H DAM IN NAGARPARKAR. PK-SID-220131-CW-RFB / CO Improving Infrastructure and Single Stage - One E 3,139,491.1 2022-06-0 NSTRUCTION OF NAMARO DA IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-04-28 2021-06-09 2021-06-10 Systems for Resilience nvelope 6 8 M IN NAGARPARKAR. PK-SID-220132-CW-RFB / CO Improving Infrastructure and Single Stage - One E 3,246,751.3 2022-06-0 NSTRUCTION OF VIAKASAR D IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-05-04 2021-06-09 2021-06-10 Systems for Resilience nvelope 1 8 AM IN NAGARPARKAR. PK-SID-220136-CW-RFB / CO Improving Infrastructure and Single Stage - One E 4,215,473.4 2022-06-0 NSTRUCTION OF GORDHRO-2 IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-05-17 2021-06-09 2021-07-05 Systems for Resilience nvelope 1 8 DAM IN NAGARPARKAR. PK-SID-220140-CW-RFB / CO Improving Infrastructure and Single Stage - One E 2,405,858.3 2022-06-0 NSTRUCTION OF SUDRAN DA IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-06-14 2021-06-09 2021-08-05 Systems for Resilience nvelope 5 8 M IN NAGARPARKAR. PK-SID-220141-CW-RFB / CO Improving Infrastructure and Single Stage - One E 1,990,269.1 2022-06-0 NSTRUCTION OF ADHIGAM-S IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-08-02 2021-06-09 2021-09-15 Systems for Resilience nvelope 5 8 YED ALAM DAM IN NAGARPA RKAR. PK-SID-220143-CW-RFB / CO Improving Infrastructure and Single Stage - One E 1,559,990.3 2022-06-0 NSTRUCTION OF LAYARI-1 DA IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-07-12 2021-06-09 2021-08-26 Systems for Resilience nvelope 8 8 M IN NAGARPARKAR. Page 2 PK-SID-220144-CW-RFB / CO Improving Infrastructure and Single Stage - One E 1,955,535.6 2022-06-0 NSTRUCTION OF JHANJHOO D IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-05-18 2021-06-09 2021-06-29 Systems for Resilience nvelope 3 8 AM IN NAGARPARKAR. PK-SID-220145-CW-RFB / CO Improving Infrastructure and Single Stage - One E 2,135,050.9 2022-06-0 NSTRUCTION OF PATHAR DA IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-05-04 2021-06-09 2021-06-15 Systems for Resilience nvelope 7 8 M IN NAGARPARKAR. PK-SID-220147-CW-RFB / CO Improving Infrastructure and Single Stage - One E 1,983,545.0 2022-06-0 NSTRUCTION OF TARGAAM B IDA / 67940 Post Request for Bids Open - National Signed 2021-02-17 2021-02-19 2021-02-22 2021-02-26 2021-03-26 2021-03-25 2021-04-26 2021-06-07 2021-06-09 2021-07-27 Systems for Resilience nvelope 3 8 UDHESAR DAM IN NAGARPAR KAR. Request for B PK-SID-178000-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2022-09-1 nstruction of Sangchat Jo Tar IDA / 67940 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience nvelope 0 r Small/Recharge Dam in Low nvelope proc er Kohistan. ess) PK-SID-177999-CW-RFB / Pa ckage No: 04 Request for B Lot No. 1 Construction of Gur ids - Small W rand Small/ Recharge Dam in Improving Infrastructure and Single Stage - One E 3,398,977.3 2022-09-1 IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-10-13 2021-09-11 2021-12-02 Lower Kohistan. Systems for Resilience nvelope 7 0 nvelope proc Lot No. 2 Construction of San ess) gchat Jo Tarr Small/ Recharg e Dam in Lower Kohistan. PK-SID-235601-CW-RFB / Pa ckage No: 01 Lot No. 1 Construction of Bandhaka Da Request for B m in Central Kohistan. ids - Small W Improving Infrastructure and Single Stage - One E 5,815,693.2 2022-09-1 IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-07-23 2021-09-11 2021-09-30 Lot No. 2 Systems for Resilience nvelope 4 0 nvelope proc Construction of Baaro Dam in ess) Central Kohistan. Lot No. 3 Construction of Chakhri Dam in Central Kohistan. Request for B PK-SID-235602-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2022-09-1 nstruction of Baaro Dam in C IDA / 67940 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience nvelope 0 entral Kohistan. nvelope proc ess) Request for B PK-SID-235603-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2022-09-1 nstruction of Chakhri Dam in IDA / 67940 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience nvelope 0 Central Kohistan. nvelope proc ess) PK-SID-235604-CW-RFB / Pa ckage No: 02 Request for B ids - Small W Improving Infrastructure and Single Stage - One E 5,706,731.4 2022-09-1 Lot No .1 Construction of Chu IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-27 2021-09-11 2021-10-13 Systems for Resilience nvelope 5 0 rlo Dam in Central Kohistan. nvelope proc Lot No. 2 Construction of Sun ess) n-2 Dam in Central Kohistan. Request for B PK-SID-235605-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2022-09-1 nstruction of Sunn-2 Dam in IDA / 67940 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience nvelope 0 Central Kohistan. nvelope proc ess) PK-SID-235606-CW-RFB / Pa ckage No: 03 Request for B Lot No. 1 Construction of Gad ids - Small W ap-2 Dam in Lower Kohistan. Improving Infrastructure and Single Stage - One E 10,390,809. 2022-09-1 IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-10 2021-09-11 2021-09-03 Lot No. 2 Construction of Lat- Systems for Resilience nvelope 06 0 nvelope proc 2 Dam in Lower Kohistan. ess) Lot No. 3 Construction of Khu da Bux Dam in Lower Kohista n. Request for B PK-SID-235609-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2022-09-1 nstruction of Khuda Bux Dam IDA / 67940 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience nvelope 0 in Lower Kohistan. nvelope proc ess) Request for B PK-SID-235611-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2022-09-1 nstruction of Lat-2 Dam in Lo IDA / 67940 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience nvelope 0 wer Kohistan. nvelope proc ess) Request for B PK-SID-235613-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2022-09-1 nstruction of Jharando-2 Dam IDA / 67940 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience nvelope 0 in Lower Kohistan. nvelope proc ess) PK-SID-235618-CW-RFB / Pa Request for B ckage No: 06 ids - Small W Lot No. 1 Construction of Gor Improving Infrastructure and Single Stage - One E 7,212,691.7 2022-09-1 IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-23 2021-09-11 2021-10-05 ban Bhutti Dam in Lower Koh Systems for Resilience nvelope 3 0 nvelope proc istan. ess) Lot No. 2Construction of Dah ri Sharif Dam in Lower Kohist an. Request for B PK-SID-235624-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2022-09-1 nstruction of Dahri Sharif Da IDA / 67940 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-05-31 2021-05-31 2021-07-01 2021-07-31 2021-09-11 Systems for Resilience nvelope 0 m in Lower Kohistan. nvelope proc ess) PK-SID-235630-CW-RFB / Pa Request for B ckage No: 05 ids - Small W Lot No. 1 Construction of Jhar Improving Infrastructure and Single Stage - One E 4,977,498.7 2022-09-1 IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-06 2021-09-11 2021-09-03 ando-1 Dam in Lower Kohista Systems for Resilience nvelope 7 0 nvelope proc n. ess) Lot No. 2 Construction of Jhar ando-2 Dam in Lower Kohista n. Request for B PK-SID-235632-CW-RFB / Co ids - Small W Improving Infrastructure and Single Stage - One E 2,739,368.9 2022-09-1 nstruction of Gaib Janan Dam IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-05-31 2021-05-31 2021-05-31 2021-05-31 2021-07-01 2021-07-07 2021-07-31 2021-08-06 2021-09-11 2021-09-03 Systems for Resilience nvelope 5 0 in Lower Kohistan. nvelope proc ess) Request for B PK-SID-252668-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 2,220,075.8 2022-12-2 NSTRUCTION OF NARANI DA IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-11-09 2021-12-27 2021-12-15 Systems for Resilience nvelope 2 6 M IN DISTRICT QAMBER SHA nvelope proc HDADKOT. ess) Request for B PK-SID-252670-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 1,988,146.0 2022-12-2 NSTRUCTION OF BUZEH DAM IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-11-09 2021-12-27 2021-12-15 Systems for Resilience nvelope 2 6 IN DISTRICT QAMBER SHAHD nvelope proc ADKOT. ess) Request for B PK-SID-252671-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 2,691,971.0 2022-12-2 NSTRUCTION OF KHAR GANI IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-11-22 2021-12-27 2021-12-22 Systems for Resilience nvelope 7 6 DAM IN DISTRICT QAMBER S nvelope proc HAHDADKOT. ess) Page 3 Request for B PK-SID-252673-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 2,493,630.2 2022-12-2 NSTRUCTION OF TOOPI DAM IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-11-22 2021-12-27 2021-12-22 Systems for Resilience nvelope 2 6 IN DISTRICT QAMBER SHAHD nvelope proc ADKOT. ess) Request for B PK-SID-252674-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 4,281,906.5 2022-12-2 NSTRUCTION OF KHINJI DAM I IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-11-09 2021-12-27 2021-12-17 Systems for Resilience nvelope 9 6 N DISTRICT QAMBER SHAHD nvelope proc ADKOT. ess) Request for B PK-SID-252677-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 3,422,744.9 2022-12-2 NSTRUCTION OF TUNNI DAM IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-12-06 2021-12-27 2021-12-22 Systems for Resilience nvelope 6 6 IN DISTRICT QAMBER SHAHD nvelope proc ADKOT. ess) Request for B PK-SID-252679-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 1,422,984.0 2022-12-2 NSTRUCTION OF GAARELO D IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-11-22 2021-12-27 2021-12-29 Systems for Resilience nvelope 9 6 AM IN DISTRICT QAMBER SH nvelope proc AHDADKOT. ess) Request for B PK-SID-252681-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 1,485,467.2 2022-12-2 NSTRUCTION OF KHURRAND IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-11-03 2021-12-27 2021-11-24 Systems for Resilience nvelope 8 6 DAM IN DISTRICT SHAHEED B nvelope proc ENAZIRABAD. ess) Request for B PK-SID-252683-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 2,280,308.6 2022-12-2 NSTRUCTION OF JAM DATAAR IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2021-09-09 2021-09-09 2021-09-14 2021-09-10 2021-10-15 2021-10-12 2021-11-15 2021-11-03 2021-12-27 2021-11-24 Systems for Resilience nvelope 8 6 DAM IN DISTRICT SHAHEED B nvelope proc ENAZIRABAD. ess) Request for B PK-SID-279648-CW-RFB / CO ids - Small W Improving Infrastructure and Single Stage - One E 2,977,505.8 2023-05-3 NSTRUCTION OF TIKKO-III DA IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2022-02-18 2022-02-21 2022-02-18 2022-02-22 2022-03-20 2022-03-28 2022-04-19 2022-05-13 2022-05-31 2022-06-17 Systems for Resilience nvelope 2 0 M IN DISTRICT JAMSHORO. nvelope proc ess) PK-SID-279655-CW-RFB / PA CKAGE NO: 04 LOT NO: 01 C ONSTRUCTION OF KAMAL SH Request for B ODO DAM IN DISTRICT JAMS ids - Small W HORO. Improving Infrastructure and Single Stage - One E 5,045,208.9 2023-06-0 IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2022-02-21 2022-02-21 2022-02-21 2022-02-22 2022-03-23 2022-03-28 2022-04-22 2022-05-10 2022-06-03 2022-06-09 LOT NO: 02 CONSTRUCTION Systems for Resilience nvelope 5 2 nvelope proc OF GHULAM MUSTAFA DAM I ess) N DISTRICT JAMSHORO. LOT NO: 03 CONSTRUCTION OF PIPRE BARICHA DAM IN DI STRICT JAMSHORO PK-SID-279662-CW-RFB / PA CKAGE NO: 02 Lot No: 01 CO Request for B NSTRUCTION OF ASABO DAM ids - Small W IN DISTRICT KARACHI. Improving Infrastructure and Single Stage - One E 5,803,194.4 2023-06-0 IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2022-02-21 2022-02-21 2022-02-21 2022-02-22 2022-03-23 2022-03-28 2022-04-22 2022-05-10 2022-06-03 2022-06-13 LOT NO: 02 CONSTRUCTION Systems for Resilience nvelope 2 2 nvelope proc OF KAND NAI DAM IN DISTRI ess) CT KARACHI. LOT NO: 03 CONSTRUCTION OF JANAI DAM IN DISTRICT K ARACHI. PK-SID-279663-CW-RFB / PA CKAGE NO: 03 LOT NO: 01 C Request for B ONSTRUCTION OF MOOSA KH ids - Small W Improving Infrastructure and Single Stage - One E 6,443,125.6 2023-06-0 AN SHORO DAM IN DISTRICT IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2022-02-21 2022-02-21 2022-02-21 2022-02-22 2022-03-23 2022-03-28 2022-04-22 2022-05-10 2022-06-03 2022-06-09 Systems for Resilience nvelope 7 2 JAMSHORO. nvelope proc LOT NO: 02 CONSTRUCTION ess) OF PURKHANI DAM IN DISTRI CT JAMSHORO. PK-SID-279669-CW-RFB / PA CKAGE NO: 01 LOT NO: 01 C Request for B ONSTRUCTION OF HUB-I DAM ids - Small W IN DISTRICT KARACHI. Improving Infrastructure and Single Stage - One E 5,635,141.9 2023-06-0 IDA / 67940 Post Request for Bids Open - National orks SPD (1 e Signed 2022-02-21 2022-02-21 2022-02-21 2022-02-22 2022-03-23 2022-03-28 2022-04-22 2022-05-10 2022-06-03 2022-06-09 LOT NO: 02 CONSTRUCTION Systems for Resilience nvelope 6 2 nvelope proc OF HUB-II DAM IN DISTRICT K ess) ARACHI. LOT NO: 03 CONSTRUCTION OF HUB-III DAM IN DISTRICT KARACHI. PK-SID-295550-CW-RFQ / Pa Other (with fi ving of Cement Concrete Pav Improving Infrastructure and Request for Quota Single Stage - One E Under Imple 2022-12-1 IDA / 67940 Post Open - National eld for expla 0.00 2022-05-19 2022-06-03 2022-06-17 er Blocks in the unpaved are Systems for Resilience tions nvelope mentation 4 nation) a of Soil Mechanics Laborator y Building. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-2980-GO-RFQ / Vehci Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Prior Open - National 415,398.59 Completed 2016-11-12 2016-12-19 2017-01-07 2017-03-03 2017-07-06 2018-08-10 les Systems for Resilience tions nvelope PK-SID-2979-GO-RFQ / Office Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Post Open - National 47,647.27 Completed 2016-11-11 2017-01-06 2017-04-26 2017-07-05 2017-05-19 Furniture Systems for Resilience tions nvelope PK-SID-4707-GO-RFQ / Office Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Post Open - National 39,507.07 Completed 2016-12-24 2017-02-18 2017-04-26 2017-08-17 2017-05-19 Equipment Systems for Resilience tions nvelope PK-SID-2978-GO-RFB / Office Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Post Open - National 0.00 Canceled 2016-11-11 2017-01-06 2017-07-05 Equipment Systems for Resilience tions nvelope PK-SID-15281-GO-RFQ / Purc Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Post Open - National 1,206.08 Completed 2017-05-19 2017-06-12 2017-05-31 2017-07-27 2017-10-16 hase of Motorcycles upto 70c Systems for Resilience tions nvelope c PK-SID-15303-GO-RFQ / Purc Improving Infrastructure and Request for Quota Single Stage - One E hasing of stabilizer of 11 Nos: IDA / 58880 Post Open - National 1,744.00 Completed 2017-05-19 2017-06-12 2017-09-06 2017-07-27 2017-09-13 Systems for Resilience tions nvelope for office use PK-SID-16582-GO-RFQ / Sup Improving Infrastructure and Request for Quota Single Stage - One E ply, Installation Testing and IDA / 58880 Post Open - National 12,561.52 Completed 2017-06-02 2017-10-26 2017-06-26 2017-11-16 2017-08-10 2017-12-08 Systems for Resilience tions nvelope Commissioning Diesel Gener ator 30 to 37 KVA. PK-SID-21212-GO-RFQ / Vide Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Post Open - National 17,121.64 Completed 2017-07-20 2017-08-14 2017-10-17 2017-09-28 2017-12-15 o Conference System Systems for Resilience tions nvelope Page 4 PK-SID-27863-GO-RFQ / Wor k Station, Chairs, Fixtures an d partitions in prayer area. 1. Work Stations 08 Nos. Improving Infrastructure and Request for Quota Single Stage - One E 2. Hydraulic Chairs IDA / 58880 Post Open - National 7,528.57 Completed 2017-09-08 2017-10-26 2017-10-12 2017-11-10 2017-12-11 2017-11-18 Systems for Resilience tions nvelope 08 Nos. 3. Aluminum Door with Gla ss 01 No. 4. Fixture/Partitions 01 No. PK-SID-92972-GO-RFQ / Proc Improving Infrastructure and Request for Quota Single Stage - One E urement of 2Nos: Motorcycle IDA / 58880 Post Open - National 994.49 Signed 2019-01-04 2019-02-18 2019-01-14 2019-03-04 2019-04-14 Systems for Resilience tions nvelope s for Office use. PK-SID-118848-GO-RFB / Hy Improving Infrastructure and Single Stage - One E IDA / 58880 Post Request for Bids Open - National 629,524.99 Signed 2019-06-20 2019-06-01 2019-06-27 2019-07-08 2019-07-29 2019-08-09 2019-08-28 2019-09-19 2019-09-30 2019-10-23 2020-03-28 draulic Laboratory Equipmen Systems for Resilience nvelope t. PK-SID-171224-GO-RFQ / Pro curement of Health Safety Pr Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Post Open - National 6,718.81 Signed 2020-04-30 2020-05-01 2020-05-18 2020-05-11 2020-06-17 oducts and Disinfectant for P Systems for Resilience tions nvelope roject Management Team (P MT). PK-SID-189315-GO-RFQ / Pro Improving Infrastructure and Request for Quota Single Stage - One E curement of I.T Equipment fo IDA / 58880 Post Open - National 9,058.76 Signed 2020-08-18 2020-08-31 2020-09-09 2020-10-20 2020-10-09 Systems for Resilience tions nvelope r office use. PK-SID-197646-GO-RFB / Pro curement of Equipment for Ri Improving Infrastructure and Single Stage - One E ver Morphology Study, Flood IDA / 58880 Post Request for Bids Open - National 748,297.37 Signed 2020-10-04 2020-11-12 2020-11-03 2020-11-13 2020-12-15 2020-12-17 2021-01-14 2021-02-04 2021-02-25 2021-03-17 2021-08-24 Systems for Resilience nvelope Hazard Mapping & Establish ment of DSS in Sindh. PK-SID-229375-GO-RFQ / Pro Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Post Open - National 283,488.74 Signed 2021-04-16 2021-04-20 2021-05-04 2021-05-06 2021-11-02 curement of Vehicles. Systems for Resilience tions nvelope PK-SID-275898-GO-RFQ / Soi Improving Infrastructure and Request for Quota Single Stage - One E l Mechanic Building Fixture a IDA / 67940 Post Limited 51,584.62 Signed 2022-02-02 2022-02-22 2022-03-07 2022-03-11 2022-06-05 Systems for Resilience tions nvelope nd Equipment. PK-SID-287695-GO-RFQ / Pro Improving Infrastructure and Request for Quota Single Stage - One E Pending Impl IDA / 67940 Post Open - National 0.00 2022-04-05 2022-05-02 2022-10-29 curement of 2Nos: Vehicles. Systems for Resilience tions nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-122451-NC-RFQ / Dig Improving Infrastructure and Request for Quota Single Stage - One E IDA / 58880 Post Open - National 86,680.00 Signed 2019-07-12 2019-07-31 2019-08-02 2019-09-04 2020-01-29 itization of Data Systems for Resilience tions nvelope PK-SID-243394-NC-RFQ / Dig Improving Infrastructure and Request for Quota Single Stage - One E IDA / 67940 Post Open - National 88,477.72 Signed 2021-07-14 2021-08-21 2021-08-12 2021-09-14 2022-02-08 italization and Preservation o Systems for Resilience tions nvelope f Record. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-2955-CS-QCBS / Proc urement of Project Implemen Improving Infrastructure and Quality And Cost- Open - Internationa IDA / 58880 Prior 4,433,007.04 Signed 2016-11-03 2016-11-03 2016-11-03 2016-12-17 2017-01-04 2017-01-14 2017-02-13 2017-02-13 2017-03-13 2017-03-20 2017-04-28 2017-04-24 2017-05-18 2018-04-24 tation Support and Supervisi Systems for Resilience Based Selection l on Consultant (PISSC) PK-SID-38659-CS-CQS / Orga Improving Infrastructure and Consultant Qualifi nizational Capacity Assessme IDA / 58880 Post Open - National 244,301.97 Signed 2017-12-04 2017-12-15 2017-12-19 2017-12-18 2018-02-20 2018-02-20 2018-03-23 2018-03-22 2018-05-04 2018-04-16 2018-10-31 Systems for Resilience cation Selection nt of Sindh Irrigation Depart ment. PK-SID-38661-CS-CQS / Thir Improving Infrastructure and Consultant Qualifi IDA / 58880 Post Open - National 348,297.30 Signed 2017-12-04 2017-12-15 2017-12-19 2017-12-18 2018-02-20 2018-02-20 2018-03-23 2018-03-19 2018-05-04 2018-04-13 2021-05-03 d Party Monitoring and Valida Systems for Resilience cation Selection tion. PK-SID-56147-CS-QCBS / Riv er Morphological Study, Floo Improving Infrastructure and Quality And Cost- Open - Internationa d Hazard Mapping and Establ IDA / 58880 Prior 1,924,831.00 Signed 2018-03-30 2018-05-31 2018-04-06 2018-06-22 2018-06-04 2018-12-04 2018-07-04 2019-10-18 2018-08-03 2020-01-26 2018-08-24 2020-05-10 2018-09-21 2020-06-01 2020-03-14 Systems for Resilience Based Selection l ishment of Decision Support System for Sindh Province PK-SID-61859-CS-QCBS / Fea sibility Study of 30 Nos: of S Improving Infrastructure and Quality And Cost- Open - Internationa IDA / 58880 Prior 1,095,407.73 Signed 2018-05-08 2018-07-30 2018-05-15 2018-08-10 2018-07-12 2019-04-03 2018-08-11 2019-05-20 2018-09-10 2020-03-12 2018-10-01 2020-04-24 2018-10-29 2020-07-07 2020-04-21 mall Dams in Water Scarce A Systems for Resilience Based Selection l reas in Sindh Province. PK-SID-128479-CS-CQS / Hy Improving Infrastructure and Consultant Qualifi dro Metrological Hazard Asse IDA / 58880 Post Open - National 465,544.39 Signed 2019-08-22 2019-08-23 2019-09-23 2019-08-29 2019-11-08 2019-10-24 2019-12-08 2019-11-18 2020-01-13 2019-11-25 2021-01-12 Systems for Resilience cation Selection ssment of Sindh Province. PK-SID-128488-CS-CQS / Per Improving Infrastructure and Consultant Qualifi formance Evaluation of Small IDA / 58880 Post Open - National 298,863.33 Signed 2019-08-22 2019-08-23 2019-09-23 2019-08-29 2019-11-08 2019-10-24 2019-12-13 2019-11-11 2020-01-20 2019-11-15 2020-07-18 Systems for Resilience cation Selection Dams in the Sindh Province. PK-SID-191831-CS-CQS / Ris Improving Infrastructure and Consultant Qualifi k profile for Sea Level Rise in IDA / 58880 Post Open - National 291,948.18 Signed 2020-09-23 2020-11-03 2020-10-23 2020-11-05 2020-12-23 2021-03-18 2021-01-24 2021-04-26 2021-02-28 2021-05-20 2021-11-25 Systems for Resilience cation Selection Sindh Coastal Area. PK-SID-191832-CS-CQS / Fea sibility Study for Provision of Improving Infrastructure and Consultant Qualifi Solar Pumps to Small Land H IDA / 58880 Post Open - National 293,058.35 Signed 2020-09-23 2020-11-03 2020-10-23 2020-11-05 2020-12-23 2021-03-18 2021-01-22 2021-04-12 2021-02-26 2021-04-14 2021-11-23 Systems for Resilience cation Selection older and Command Area De velopment of Selected Area S indh. PK-SID-197423-CS-QCBS / Pr oject Implementation Consult Improving Infrastructure and Quality And Cost- Open - Internationa ant for Design Review and Re IDA / 58880 Prior 2,808,665.40 Signed 2020-11-05 2020-12-03 2020-11-30 2020-12-07 2021-02-03 2021-02-21 2021-02-05 2021-02-22 2021-03-08 2021-06-08 2021-03-29 2021-06-24 2021-04-14 2021-07-23 2024-10-14 Systems for Resilience Based Selection l sident Supervision of Constru ction of Small Dams in Sindh. Page 5 PK-SID-247635-CS-QCBS / Fe asibility Study of 50 Nos. Sm Improving Infrastructure and Quality And Cost- Open - Internationa IDA / 67940 Prior 1,405,178.19 Signed 2021-08-12 2021-09-27 2021-09-02 2021-09-28 2021-09-15 2022-01-05 2021-10-17 2022-02-16 2021-10-31 2022-04-11 2021-11-17 2022-04-29 2021-12-15 2022-06-01 2023-06-12 all Dams and Lining of 50 No Systems for Resilience Based Selection l s. Ponds/Taraies in Sindh Pro vince. PK-SID-256444-CS-CQS / Thi Improving Infrastructure and Consultant Qualifi rd Party Monitoring & Validati IDA / 67940 Post Open - National 285,965.97 Signed 2021-10-05 2021-10-06 2021-10-25 2021-10-08 2021-12-24 2021-12-01 2022-01-21 2021-12-14 2022-02-25 2021-12-20 2024-08-13 Systems for Resilience cation Selection on (TPM&V). PK-SID-257409-CS-QCBS / Pr eparation of an Inventory Ind us Embankments and Breach Improving Infrastructure and Quality And Cost- Open - Internationa IDA / 67940 Post 3,503,506.74 Signed 2021-10-08 2021-10-22 2021-10-29 2021-12-13 2021-11-11 2022-01-27 2021-12-13 2022-03-09 2021-12-27 2022-06-27 2022-01-17 2022-07-06 2022-02-14 2022-07-22 2023-05-10 ing Sections, to Document th Systems for Resilience Based Selection l eir Current Conditions and fo r Informed Disaster Risk & Ha zard Mapping. PK-SID-257424-CS-CQS / Ca Improving Infrastructure and Consultant Qualifi Under Implement pacity Development Program IDA / 67940 Post Open - National 0.00 2021-10-22 2021-11-02 2021-11-11 2022-01-12 2022-02-09 2022-03-16 2024-03-05 Systems for Resilience cation Selection ation / Trainings. PK-SID-316343-CS-CQS / Sur vey, Drawing, Estimation and Re-Construction Supervision Improving Infrastructure and Consultant Qualifi Pending Impleme IDA / 67940 Post Limited 0.00 2022-09-17 2022-09-24 2022-09-27 2022-10-04 2023-04-02 of Flood/ River Embankments Systems for Resilience cation Selection ntation , Irrigation Drainage Network Under Sindh Flood Emergenc y Rehabilitation Project (SFE RP). INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-2970-CS-INDV / Finan Improving Infrastructure and Individual Consult IDA / 58880 Prior Open 56,401.20 Completed 2016-11-07 2016-11-20 2016-12-27 2016-12-22 2017-01-17 2017-01-25 2017-02-21 2017-01-05 2017-08-20 2017-12-31 ce Consultant Systems for Resilience ant Selection PK-SID-2972-CS-INDV / M & Improving Infrastructure and Individual Consult IDA / 58880 Post Open 156,315.68 Signed 2016-11-07 2016-12-15 2016-12-27 2017-03-22 2017-01-17 2017-05-02 2017-02-21 2017-06-13 2017-08-20 E Consultant Systems for Resilience ant Selection PK-SID-2973-CS-INDV / IT/GI Improving Infrastructure and Individual Consult IDA / 58880 Post Open 117,688.81 Signed 2016-11-07 2016-12-29 2016-12-27 2017-07-03 2017-01-17 2017-07-03 2017-02-21 2017-08-07 2017-08-20 S Consultant Systems for Resilience ant Selection PK-SID-2975-CS-INDV / Quali Improving Infrastructure and Individual Consult IDA / 58880 Post Open 138,661.08 Signed 2016-11-07 2017-12-15 2016-12-27 2018-02-09 2017-01-17 2018-02-09 2017-02-21 2018-02-08 2017-08-20 ty Assurance Engineer Systems for Resilience ant Selection PK-SID-2976-CS-INDV / Envir Improving Infrastructure and Individual Consult IDA / 58880 Post Open 31,029.60 Terminated 2016-11-07 2016-12-29 2016-12-27 2017-06-23 2017-01-17 2017-06-23 2017-02-21 2017-07-03 2017-08-20 onmental Consultant Systems for Resilience ant Selection PK-SID-2981-CS-INDV / Socia Improving Infrastructure and Individual Consult Under Implement IDA / 58880 Post Open 193,428.96 2016-11-07 2016-12-29 2016-12-27 2017-05-29 2017-01-17 2017-05-30 2017-02-21 2017-07-07 2017-08-20 l Safeguard Consulatnt Systems for Resilience ant Selection ation PK-SID-7391-CS-INDV / Proc Improving Infrastructure and Individual Consult urement & Contract Consulta IDA / 58880 Prior Open 209,585.66 Signed 2017-02-15 2017-02-16 2017-04-05 2017-02-28 2017-04-26 2017-04-03 2017-05-31 2017-04-03 2018-05-31 Systems for Resilience ant Selection nt (Individual Consultant) PK-SID-2971-CS-INDV / Proc Improving Infrastructure and Individual Consult IDA / 58880 Prior Open 0.00 Canceled 2016-11-07 2016-11-17 2016-12-27 2017-01-17 2017-02-21 2017-08-20 urement & Contract Consulta Systems for Resilience ant Selection nt PK-SID-27831-CS-INDV / Hiri Improving Infrastructure and Individual Consult ng of Environment Consultan IDA / 58880 Post Open 174,872.45 Signed 2017-09-08 2017-09-15 2017-10-02 2017-10-27 2017-10-04 2017-10-27 2017-10-06 2017-11-06 2018-10-06 Systems for Resilience ant Selection t (Individual Consultant) PK-SID-47074-CS-INDV / Fina Improving Infrastructure and Individual Consult IDA / 58880 Prior Open 232,652.82 Signed 2018-02-01 2018-02-01 2018-02-02 2018-02-01 2018-02-08 2018-02-01 2018-01-01 2018-02-01 nce Consultant Systems for Resilience ant Selection PK-SID-92998-CS-INDV / Fidu Improving Infrastructure and Individual Consult IDA / 58880 Post Open 87,127.23 Signed 2019-01-01 2019-02-06 2019-01-28 2019-04-11 2019-02-04 2019-04-23 2019-02-13 2019-04-29 2020-02-12 ciary Monitoring Analyst Systems for Resilience ant Selection PK-SID-114445-CS-INDV / Th Improving Infrastructure and Individual Consult e Hiring of Electro/Hydraulic I IDA / 58880 Post Open 101,408.33 Signed 2019-05-10 2019-05-13 2019-07-01 2019-05-14 2019-07-22 2019-05-15 2019-08-26 2019-05-16 2020-08-24 Systems for Resilience ant Selection ndividual Consultant. PK-SID-121794-CS-INDV / Th e Hiring of Individual Consult ant for carrying out the Socia Improving Infrastructure and Individual Consult IDA / 58880 Post Limited 6,403.07 Signed 2019-07-09 2019-07-09 2019-07-09 2019-07-10 2019-07-11 2019-07-10 2019-07-12 2019-08-08 2019-09-10 l & Environment Impact Asse Systems for Resilience ant Selection ssment of Constructed Small Dams in Sindh Province Unde r Irrigation Department. PK-SID-207688-CS-INDV / So Improving Infrastructure and Individual Consult Under Implement cial & Gender Specialist (Indi IDA / 58880 Post Limited 0.00 2020-12-04 2020-12-04 2020-12-19 2020-12-24 2020-12-30 2021-12-30 Systems for Resilience ant Selection ation vidual Consultant). PK-SID-217159-CS-INDV / Se Improving Infrastructure and Individual Consult IDA / 58880 Post Limited 133,381.16 Signed 2021-02-02 2021-02-03 2021-02-16 2021-02-15 2021-02-19 2021-03-02 2021-02-25 2021-03-08 2022-02-25 nior Water Management Spe Systems for Resilience ant Selection cialist. PK-SID-217218-CS-INDV / W Improving Infrastructure and Individual Consult IDA / 58880 Post Limited 79,971.31 Signed 2021-02-02 2021-02-03 2021-02-16 2021-02-15 2021-02-19 2021-03-02 2021-02-25 2021-03-08 2022-02-25 ater Management Specialist. Systems for Resilience ant Selection PK-SID-263942-CS-CDS / Imp act Assessment/ Performanc Improving Infrastructure and IDA / 67940 Post Direct Selection Direct 53,618.16 Signed 2021-11-18 2021-11-19 2021-11-28 2021-11-22 2022-01-17 2021-12-20 2022-07-16 e Evaluation of 14 Small Dam Systems for Resilience s in the Sindh Province. PK-SID-273736-CS-INDV / Str Improving Infrastructure and Individual Consult ucture Safety Engineer (Indiv IDA / 67940 Post Open 0.00 Canceled 2022-01-20 2022-01-21 2022-03-09 2022-03-30 2022-05-04 2023-05-03 Systems for Resilience ant Selection idual Consultant). Page 6