Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 21, 2016. 2. Date of General Procurement Notice: September 28, 2016. 3. Period covered by this procurement plan: January 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million 3. ICB (Works) Above US$ 10 million 4. NCB (Works) Above US$ 2 million 5. Non-Consultant Services Above US$2 million 6 Consultants (firms) Above US$ 1 million 7. Consultant Individuals Above 0.3 million 2. Prequalification. Not applicable. 4. Any Other Special Procurement Arrangements: Retroactive financing up to 5 million. July 9, 2010 PROCUREMENT Mexico : Energy Efficiency in Public Facilities Project (PRESEMEH) PLAN General Information Country: Mexico 2016-11-29 Bank’s Approval Date of the Original Procurement Plan: 2022-10-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149872 GPN Date: 2016-09-28 Project Name: Energy Efficiency in Public Facilities Project (PRESEMEH) Loan / Credit No: IBRD / 85940, IBRD / 88440 Secretaria de Energia Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SENER-DGESE-FIDE-LPN-AP- GTO-2017-01 / ALUMBRADO Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2018-02-2 IBRD / 85940 Posterior Open - National 7,890,213.00 0.00 Cancelado 2017-09-15 2017-09-21 2017-10-12 2017-11-08 2017-11-27 PUBLICO EN EL MUNICIPIO D nvestments s nvelope 3 E LEON, GUANAJUATO SENER-DGESE-FIDE-LPN-BA- TLAX-2017-02 / BOMBEO DE Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2018-06-2 IBRD / 85940 Posterior Open - National 676,304.00 0.00 Cancelado 2017-10-18 2017-10-23 2017-11-14 2017-11-29 2017-12-27 AGUA EN EL MUNICIPIO DE H nvestments s nvelope 7 UAMANTLA, TLAXCALA SENER-DGESE-FIDE-LPN-AP- GTO-2017-01-A / ALUMBRAD Municipal energy efficiency i Solicitud de oferta Single Stage - One E 3,351,761.0 2018-02-2 O PUBLICO EN EL MUNICIPIO IBRD / 85940 Posterior Open - National 7,890,213.00 Finalizado 2017-09-15 2017-10-12 2017-09-21 2017-10-12 2017-11-14 2017-11-08 2017-12-08 2017-11-27 2017-12-13 nvestments s nvelope 4 3 DE LEON, GUANAJUATO SENE R-DGESE-FIDE-LPN-AP-GTO-2 017-01 SENER-DGESE-FIDE-LPN-BA- TLAX-2017-02-A / BOMBEO D Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2018-10-2 E AGUA EN EL MUNICIPIO DE IBRD / 85940 Posterior Open - National 676,304.00 0.00 Cancelado 2018-03-21 2018-10-01 2018-04-03 2018-05-15 2018-11-26 2018-06-08 2018-12-12 2018-06-29 nvestments s nvelope 9 HUAMANTLA, TLAXCALA SEN ER-DGESE-FIDE-LPN-BA-TLAX -2017-02 SENER-DGESE-FIDE-LPN-EM- PUE-2018-01 / PROYECTO DE Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2018-10-3 IBRD / 85940 Posterior Open - National 360,000.00 0.00 Cancelado 2018-04-03 2018-04-25 2018-04-17 2018-05-24 2018-06-05 2018-06-11 2018-06-21 2018-07-03 EDIFICACIONES EN EL MUNIC nvestments s nvelope 1 IPIO DE PUEBLA, PUEBLA SENER-DGESE-FIDE-LPN-AP- DMH-2018-02 / PROYECTO D Municipal energy efficiency i Solicitud de oferta Single Stage - One E 3,085,967.8 2018-09-1 E ALUMBRADO PUBLICO EN L IBRD / 85940 Posterior Open - National 5,698,598.93 Finalizado 2018-04-19 2018-05-02 2018-04-25 2018-05-09 2018-05-30 2018-05-28 2018-06-18 2018-06-16 2018-07-04 nvestments s nvelope 6 4 A DELEGACION MIGUEL HIDA LGO, CIUDAD DE MEXICO SENER-DGESE-FIDE-LPN-AP- HJUAPAN-2018-04 / SUBPROY ECTO DE ALUMBRADO PUBLI Municipal energy efficiency i Solicitud de oferta Single Stage - One E 1,301,538.0 2019-01-1 IBRD / 85940 Posterior Open - National 4,000,000.00 Finalizado 2018-07-17 2018-07-31 2018-08-03 2018-09-14 2018-09-13 2018-10-03 2018-10-02 2018-10-29 2018-10-17 CO PARA EL MUNICIPIO DE H nvestments s nvelope 4 4 UAJUAPAN DE LEON OAXACA SENER-DGESE-FIDE-LPN-AP-H JUAPAN-2018-04 SENER-DGESE-FIDE-LPN-AP- OAX-2018-05 / SUBPROYECT O DE ALUMBRADO PÚBLICO Municipal energy efficiency i Solicitud de oferta Single Stage - One E 7,349,433.5 2019-05-2 IBRD / 85940 Previa Open - National 7,600,000.00 Finalizado 2018-11-26 2019-09-30 2018-12-11 2019-09-30 2019-01-01 2019-08-01 2019-02-12 2019-11-21 2019-03-06 2019-10-02 PARA EL MUNICIPIO DE OAXA nvestments s nvelope 3 0 CA DE JUÁREZ SENER-DGESE-FIDE-LPN-AP-O AX-2018-05 SENER-DGESE-FIDE-LPN-AP- COZ-2018-03 / SUBPROYECT Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2019-02-0 O DE ALUMBRADO PÚBLICO IBRD / 85940 Posterior Open - National 6,500,000.00 0.00 Cancelado 2018-08-08 2018-11-05 2018-08-23 2018-09-13 2018-10-25 2018-11-20 nvestments s nvelope 3 PARA EL MUNICIPIO DE COZU MEL SENER-DGESE-FIDE-LPN- AP-COZ-2018-03 SENER-DGESE-FIDE-LPN-AP- COZ-2019-01 / SUBPROYECT Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2,144,755.2 2020-06-3 O DE ALUMBRADO PÚBLICO IBRD / 85940 Posterior Open - National 3,250,000.00 Firmado 2019-12-27 2019-11-22 2020-01-12 2020-02-06 2020-03-03 2020-03-07 2020-03-25 2020-04-01 2020-05-20 nvestments s nvelope 0 0 PARA EL MUNICIPIO DE COZU MEL, SENER-DGESE-FIDE-LP N-AP-COZ-2019-01 SENER-DGESE-FIDE-LPN-AP- COAT-2019-02 / SUBPROYEC TO DE ALUMBRADO PÚBLICO Municipal energy efficiency i Solicitud de oferta Single Stage - One E 3,360,363.4 2020-12-0 IBRD / 85940 Posterior Open - National 4,139,780.00 Firmado 2020-02-20 2021-03-22 2020-02-25 2020-04-07 2021-04-30 2020-05-07 2021-05-28 2020-06-11 2021-06-10 PARA EL MUNICIPIO DE COAT nvestments s nvelope 6 8 ZACOALCOS, VERACRUZ, SE NER-DGESE-FIDE-LPN-AP-CO AT-2019-02 SENER-DGESE-FIDE-LPN-AP- CUL-2018-06 / SUBPROYECT Municipal energy efficiency i Solicitud de oferta Single Stage - One E 1,931,379.8 2021-05-1 O DE ALUMBRADO PÚBLICO IBRD / 85940 Posterior Open - National 2,047,099.67 Firmado 2020-06-30 2020-06-29 2020-07-15 2020-08-05 2020-08-12 2020-10-14 2020-09-01 2020-11-13 2020-09-08 nvestments s nvelope 4 2 PARA EL MUNICIPIO DE CULIA CÁN SENER-DGESE-FIDE-LPN- AP-CUL-2018-06 SENER-DGIDTFRH-FIDE-LPN- AP-RIO-2020-02 / SUBPROYE CTO DE ALUMBRADO PÚBLIC Municipal energy efficiency i Solicitud de oferta Single Stage - One E 1,727,340.8 2021-05-2 IBRD / 85940 Posterior Open - National 2,177,700.35 Firmado 2020-06-15 2020-09-21 2020-06-30 2020-08-11 2020-11-05 2020-10-20 2020-11-27 2020-11-25 2020-12-15 O PARA EL MUNICIPIO DE RÍO nvestments s nvelope 0 4 GRANDE, ZACATECAS, SENE R-DGIDTFRH-FIDE-LPN-AP-RI O-2020-02 SENER-DGIDTFRH-FIDE-LPN- AP-PINOS-2020-03 / SUBPRO YECTO DE ALUMBRADO PÚBL Municipal energy efficiency i Solicitud de oferta Single Stage - One E 1,702,909.9 2021-06-0 IBRD / 85940 Posterior Open - National 2,177,700.35 Firmado 2020-06-30 2020-12-21 2020-07-15 2020-08-26 2021-02-04 2020-11-04 2021-03-01 2020-12-10 2021-03-19 ICO PARA EL MUNICIPIO DE PI nvestments s nvelope 3 8 NOS, ZACATECAS /SENER-DG IDTFRH-FIDE-LPN-AP-PINOS-2 020-03 SENER-DGIDTFRH-FIDE-LPN- AP-XAL-2020-04 / SUBPROYE CTO DE ALUMBRADO PÚBLIC Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2,078,669.4 2021-10-1 IBRD / 85940 Posterior Open - National 2,177,700.35 Firmado 2020-10-27 2021-03-29 2020-11-11 2020-12-23 2021-05-14 2021-03-03 2021-06-10 2021-04-14 2021-06-22 O PARA EL MUNICIPIO DE XA nvestments s nvelope 5 1 LAPA, VERACRUZ / SENER-D GIDTFRH-FIDE-LPN-AP-XAL-2 020-04 Page 1 SENER-DGIDTFRH-FIDE-LPN- BA-DGO-2020-05 / BOMBEO Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2021-09-0 DE AGUA EN EL MUNICIPIO D IBRD / 85940 Posterior Open - National 2,177,700.35 0.00 Cancelado 2020-09-28 2020-10-13 2020-11-24 2021-02-02 2021-03-10 nvestments s nvelope 6 E GÓMEZ PALACIO, DURANG O / SENER-DGIDTFRH-FIDE-LP N-BA-DGO-2020-05 SENER DGESE-FIDE-LPN-MER -214640-CW-RFB / SUBPROY Municipal energy efficiency i Solicitud de oferta Single Stage - One E 2021-09-3 IBRD / 85940 Posterior Open - National 1,548,964.53 0.00 Cancelado 2021-02-22 2021-03-10 2021-04-04 2021-05-04 2021-05-29 ECTO EDIFICACIONES MUNICI nvestments s nvelope 0 PALES EN LA CIUDAD DE MÉR IDA YUCATÁN SENER-DGESE-FIDE-LPN-PCA R-214655-CW-RFB / SUBPRO Municipal energy efficiency i Solicitud de oferta Single Stage - One E 1,602,127.0 2021-10-3 YECTO ALUMBRADO PÚBLICO IBRD / 85940 Posterior Open - National 2,967,828.74 Firmado 2021-03-08 2021-03-09 2021-03-24 2021-04-18 2021-04-12 2021-05-18 2021-05-05 2021-06-12 2021-05-14 nvestments s nvelope 5 0 PARA LA CD. DE PLAYA DEL C ARMEN QUINTANA ROO SENER-DGIDTFRH-FIDE-LPN- Request for Bids - AP-MR-2022-01 / Subproyect Municipal energy efficiency i Solicitud de oferta Single Stage - One E Small Works SPD Ejecución p 2023-04-2 IBRD / 85940 Posterior Open - National 4,155,354.19 0.00 2022-07-04 2022-07-11 2022-08-22 2022-09-21 2022-10-26 o de alumbrado público para nvestments s nvelope (1 envelope proce endiente 4 el municipio de Mineral de la ss) Reforma, Hidalgo SENER-DGIDTFRH-FIDE-LPN- Request for Bids - AP-MIN-2022-02 / Subproyect Municipal energy efficiency i Solicitud de oferta Single Stage - One E Small Works SPD En ejecució 2023-04-2 IBRD / 85940 Posterior Open - National 1,125,966.94 0.00 2022-07-04 2022-10-12 2022-07-11 2022-10-14 2022-08-22 2022-09-21 2022-10-26 o de alumbrado público para nvestments s nvelope (1 envelope proce n 4 el municipio de Minatitlán, V ss) eracruz SENER-DGIDTFRH-FIDE-LPN- Request for Bids - AP-NAN-2022-03 / Subproyec Municipal energy efficiency i Solicitud de oferta Single Stage - One E Small Works SPD Ejecución p 2023-04-2 IBRD / 85940 Posterior Open - National 831,070.83 0.00 2022-07-04 2022-07-11 2022-08-22 2022-09-21 2022-10-26 to de alumbrado público en e nvestments s nvelope (1 envelope proce endiente 4 l municipio de Nanchital, Ver ss) acruz SENER-DGIDTFRH-FIDE-LPN- AP-COR-2022-07 / Subproyec Municipal energy efficiency i Solicitud de oferta Single Stage - One E Other (with field f Ejecución p 2023-01-3 IBRD / 85940 Posterior Open - National 752,278.82 0.00 2022-09-23 2022-09-28 2022-10-21 2022-11-11 2022-11-21 to de alumbrado público en e nvestments s nvelope or explanation) endiente 1 l municipio de Córdoba, Vera cruz SENER-DGIDTFRH-FIDE-LPN- AP-CAL-2022-08 / Subproyect Municipal energy efficiency i Solicitud de oferta Single Stage - One E Other (with field f Ejecución p 2023-02-2 IBRD / 85940 Posterior Open - National 1,474,530.83 0.00 2022-09-12 2022-09-17 2022-10-17 2022-11-08 2022-11-30 o de alumbrado público en el nvestments s nvelope or explanation) endiente 8 municipio de Calkiní, Campec he SENER-DGIDTFRH-FIDE-LPN- AP-DZI-2022-09 / Subproyect Municipal energy efficiency i Solicitud de oferta Single Stage - One E Other (with field f Ejecución p 2023-01-1 IBRD / 85940 Posterior Open - National 371,581.77 0.00 2022-09-09 2022-09-14 2022-10-14 2022-10-28 2022-11-07 o de alumbrado público en el nvestments s nvelope or explanation) endiente 3 municipio de Dzitbalché, Ca mpeche SENER-306002-DGIDTFRH-FI DE-LPN-HERMOSI / Subproye Municipal energy efficiency i Solicitud de oferta Single Stage - One E Other (with field f Ejecución p 2023-02-1 IBRD / 85940 Posterior Open - National 697,050.94 0.00 2022-09-09 2022-09-11 2022-10-03 2022-10-17 2022-11-11 cto de alumbrado público en nvestments s nvelope or explanation) endiente 3 el municipio de Hermosillo So nora SENER-DGIDTFRH-FIDE-LPN- AP-TUX-2022-10 / Subproyec Municipal energy efficiency i Solicitud de oferta Single Stage - One E Other (with field f Ejecución p 2023-04-2 IBRD / 85940 Posterior Open - National 3,880,417.56 0.00 2022-10-31 2022-11-07 2022-11-27 2022-12-11 2022-12-22 to de alumbrado público en e nvestments s nvelope or explanation) endiente 1 l municipio de Tuxpan Veracr uz SENER-DGIDTFRH-FIDE-LPN- AP-SPM-2022-11 / Subproyec Municipal energy efficiency i Solicitud de oferta Single Stage - One E Other (with field f Ejecución p 2023-04-3 IBRD / 85940 Posterior Open - National 1,369,896.70 0.00 2022-11-15 2022-11-21 2022-12-21 2023-01-19 2023-01-30 to de alumbrado público en e nvestments s nvelope or explanation) endiente 0 l Municipio de San Pablo del Monte, Tlaxcala SENER-DGIDTFRH-FIDE-LPN- AP-PAP-2022-12 / Subproyect Municipal energy efficiency i Solicitud de oferta Single Stage - One E Other (with field f Ejecución p 2023-04-2 IBRD / 85940 Posterior Open - National 1,971,907.96 0.00 2022-10-28 2022-11-03 2022-11-23 2022-12-13 2022-12-22 o de alumbrado público en el nvestments s nvelope or explanation) endiente 1 Municipio de Papantla, Verac ruz GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-FIDE-LPI-AP-G Municipal energy efficiency i Solicitud de oferta Open - Internationa Single Stage - One E TO-2016-01 / ALUMBRADO P IBRD / 85940 Previa 12,000,000.00 0.00 Cancelado 2017-01-27 2017-02-11 2017-03-28 2017-05-02 2017-05-27 2018-01-02 nvestments s l nvelope UBLICO EN EL MUNICIPIO DE LEON SENER-DGESE-FIDE-LPN-BA- Municipal energy efficiency i Solicitud de oferta Single Stage - One E TLAX-2016-01 / BOMBEO DE IBRD / 85940 Previa Open - National 3,600,000.00 0.00 Cancelado 2017-01-13 2017-01-28 2017-02-17 2017-03-19 2017-04-05 2017-10-23 nvestments s nvelope AGUA EN EL MUNICIPIO DE H UAMANTLA. SENER-DGESE-FIDE-LPN-LH-I MS214669-CW-RFB / SUMINIS TRO, INSTALACIÓN Y PUESTA Public Facility Energy Efficie Solicitud de oferta Single Stage - One E IBRD / 88440 Previa Open - National 7,419,571.84 0.00 Cancelado 2021-06-22 2021-06-27 2021-07-27 2021-08-16 2021-09-20 2021-10-31 EN OPERACIÓN DE LUMINARI ncy Investments s nvelope AS EN HOSPITALES DEL INSTI TUTO MEXICANO DEL SEGUR O SOCIAL (IMSS) MX-SENER-258546-LPN-HOS P- TABASCO-FIDE / Suministr Public Facility Energy Efficie Solicitud de oferta Single Stage - One E o, Instalación y Puesta en Op IBRD / 88440 Previa Open - National 2,500,000.00 0.00 Cancelado 2021-11-12 2021-11-27 2021-12-27 2022-01-16 2022-02-04 2022-06-04 ncy Investments s nvelope eración de Bienes de Alta Efi ciencia Energética en Hospit ales de Tabasco. SENER-DGIDTFRH-FIDE-LPN- EE-B1IMSS-22-01 / Suministr o, instalación y puesta en op Public Facility Energy Efficie Solicitud de oferta Single Stage - One E IBRD / 88440 Posterior Open - National 441,582.39 0.00 En ejecución 2022-04-04 2022-07-18 2022-04-11 2022-08-18 2022-05-23 2022-08-23 2022-06-22 2022-09-13 2022-07-27 2022-11-24 eración de acciones de eficie ncy Investments s nvelope ncia energética en el Bloque 1 del IMSS (Hospitales de la Ciudad de México e Hidalgo) SENER-DGIDTFRH-FIDE-LPN- EE-B2IMSS-22-02 / Suministr o, instalación y puesta en op Public Facility Energy Efficie Solicitud de oferta Single Stage - One E eración de acciones de eficie IBRD / 88440 Previa Open - National 2,649,033.17 0.00 Cancelado 2022-05-02 2022-08-26 2022-05-09 2022-06-20 2022-07-20 2022-08-24 2023-01-20 ncy Investments s nvelope ncia energética en el Bloque 2 del IMSS (5 Hospitales ubic ados en Colima, Jalisco, Guan ajuato y Michoacán) Page 2 SENER-DGIDTFRH-FIDE-LPN- EE-B3IMSS-22-03 / Suministr o, instalación y puesta en op Public Facility Energy Efficie Solicitud de oferta Single Stage - One E Ejecución pe IBRD / 88440 Posterior Open - National 1,218,578.94 0.00 2022-07-01 2022-07-06 2022-08-17 2022-09-19 2022-10-24 2023-03-23 eración de acciones de eficie ncy Investments s nvelope ndiente ncia energética en el Bloque 3 del IMSS (4 Hospitales en O axaca y Guerrero) SENER-DGIDTFRH-FIDE-LPN- EE-B4IMSS-22-04 / Suministr o, instalación y puesta en op Public Facility Energy Efficie Solicitud de oferta Single Stage - One E Ejecución pe eración de acciones de eficie IBRD / 88440 Posterior Open - National 1,385,675.74 0.00 2022-06-01 2022-06-06 2022-07-18 2022-08-17 2022-09-21 2023-02-18 ncy Investments s nvelope ndiente ncia energética en el Bloque 4 del IMSS (5 Hospitales en B aja California, Baja California Sur y Sinaloa) SENER-DGIDTFRH-FIDE-LPN- EE-B5IMSS-22-05 / Suministr o, instalación y puesta en op Public Facility Energy Efficie Solicitud de oferta Single Stage - One E Ejecución pe IBRD / 88440 Posterior Open - National 1,462,294.73 0.00 2022-09-01 2022-09-06 2022-10-18 2022-11-17 2022-12-22 2023-04-21 eración de acciones de eficie ncy Investments s nvelope ndiente ncia energética en el Bloque 5 del IMSS (5 Hospitales en S onora) SENER-DGIDTFRH-FIDE-LPN- EE-TAB-22-06 / Suministro, in Public Facility Energy Efficie Solicitud de oferta Single Stage - One E stalación y puesta en operaci IBRD / 88440 Posterior Open - National 1,414,775.65 0.00 Cancelado 2022-06-01 2022-06-06 2022-07-18 2022-08-17 2022-09-21 2023-01-19 ncy Investments s nvelope ón de acciones de eficiencia energética en 2 Hospitales d e Tabasco MX-SENER-306501-GO-RFB- 2-H-TAB-B-1 / Suministro, ins talación y puesta en operació Public Facility Energy Efficie Solicitud de oferta Single Stage - One E Ejecución pe n de acciones de eficiencia e IBRD / 88440 Posterior Open - National 1,829,446.62 0.00 2022-09-09 2022-09-15 2022-10-14 2022-11-07 2022-11-28 2023-03-28 ncy Investments s nvelope ndiente nergética en 2 Hospitales de Tabasco Bloque 1 (General D r. Desiderio G Rosado y Regi onal Dr Juan Graham) MX-SENER-306508-GO-RFB- FIDE 3 H-TAB- B-2 / Suministr o, instalación y puesta en op eración de acciones de eficie Public Facility Energy Efficie Solicitud de oferta Single Stage - One E Ejecución pe ncia energética en instalacio IBRD / 88440 Posterior Open - National 900,745.82 0.00 2022-09-09 2022-09-23 2022-10-21 2022-11-07 2022-11-29 2023-03-29 ncy Investments s nvelope ndiente nes de Salud de Tabasco Blo que 2 (Lab Regional de Salud , Hospital Regional de Alta Es pecialidad Dr. Rodolfo Nieto y Hospital del Inst de Seg So cial Tab.) SENER-DGIDTFRH-FIDE-LPN- EE-B2 IMSS-22-03 / Suministr o, instalación y puesta en op Public Facility Energy Efficie Solicitud de oferta Single Stage - One E eración de acciones de eficie IBRD / 88440 Previa Open - National 2,649,033.17 0.00 Bajo Revision 2022-09-12 2022-09-11 2022-09-19 2022-10-29 2022-11-28 2022-12-20 2023-03-31 ncy Investments s nvelope ncia energética en el Bloque 2 del IMSS (5 Hospitales ubic ados en Colima, Jalisco, Guan ajuato y Michoacán) SENER-DGIDTFRH-FIDE-LPN- EE-B1-IMSS-22-1A / Suministr o, instalación y puesta en op Public Facility Energy Efficie Solicitud de oferta Single Stage - One E Ejecución pe eración de acciones de eficie IBRD / 88440 Posterior Open - National 441,582.39 0.00 2022-10-24 2022-10-31 2022-11-21 2022-12-06 2022-12-30 2023-04-28 ncy Investments s nvelope ndiente ncia energética en el Bloque 1 del IMSS (Hospitales de la Ciudad de México e Hidalgo) Segunda Vuelta NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-CP-S-2016-02 / CAPACITACION POR PARTE DEL BANCO MUNDIAL DIRIGI DA A FUNCIONARIOS DE LA S Policy development and insti Solicitud de cotiza Single Stage - One E IBRD / 85940 Posterior Open - National 15,000.00 0.00 Cancelado 2017-01-23 2017-03-19 2017-04-06 ENER, CONUEE, UREP, MUNIC tutional strengthening ciones nvelope IPIOS Y CONSULTORES, PARA LA HERRAMIENTA CLIMATE A CTION FOR URBAN SUSTAINA BILITY (CURB) AL CONTEXTO MEXICANO. SENER-DGESE-CP-S-2016-01 / DISENO, EDICION E IMPRESI ON DE LOS INFORMES DE RE Policy development and insti Solicitud de cotiza Single Stage - One E SULTADOS DE 7 ESTUDIOS (L IBRD / 85940 Posterior Open - National 50,000.00 39,549.83 Finalizado 2016-10-31 2016-12-04 2017-02-28 2017-02-02 2017-04-28 tutional strengthening ciones nvelope EDS; HOSPITALES; CENTROS DE ACOPIO; ESCUELAS, IMPA CTO DEL PROYECTO, HOTELE S E IMPORTACIONES). SENER-DGESE-CP-S-2017-01 Policy development and insti Solicitud de cotiza Single Stage - One E / LICENCIA DE USO DEL SISTE IBRD / 85940 Posterior Limited 268.00 0.00 Cancelado 2017-06-23 2017-07-25 2018-07-25 tutional strengthening ciones nvelope MA CONTABLE CONTPAQ i SENER-DGESE-CP-S-2018-01 Policy development and insti Solicitud de cotiza Single Stage - One E / LICENCIA DE USO DEL SISTE IBRD / 85940 Posterior Limited 270.00 270.87 Finalizado 2018-11-20 2019-09-23 2018-12-22 2017-09-15 2019-12-22 2018-11-12 tutional strengthening ciones nvelope MA CONTABLE CONTPAQi MX-SENER-320470-NC-RFQ L IC CONPAQI / Renovación de Policy development and insti Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 85940 Posterior Limited 217.00 0.00 2022-11-14 2023-01-02 2023-04-28 Licencia Anual Conpaq conta tutional strengthening ciones nvelope ndiente bilidad para uso de UREP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-SCC-2016-02 / DEFINICION DE LOS PARAM Selección basada Policy development and insti ETROS A REPORTAR PARA EL IBRD / 85940 Posterior en calificaciones d Open - National 150,000.00 0.00 Cancelado 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 tutional strengthening ESTABLECIMIENTO DE UNA LI e consultores NEA BASE PARA MONITOREO DEL PRESEM Page 3 SENER-DGESE-SCC-2016-03 / DISENO Y DESARROLLO DE UNA PAGINA WEB PARA DIFU SION DE LOS RESULTADOS Y Selección basada Policy development and insti CASOS DE EXITO DEL PRESE IBRD / 85940 Posterior en calificaciones d Open - National 45,000.00 0.00 Cancelado 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 tutional strengthening M (SE ESTA REVISANDO SI SE e consultores RA UNA FIRMA O UN CONSUL TOR INDIVIDUAL, DE SER EST E ULTIMO SE HARA EL AJUST E CORRESPONDIENTE) SENER-DGESE-SCC-2016-04 / DISENO E IMPARTICION DE Selección basada 9 TALLERES DE EFICIENCIA E Policy development and insti IBRD / 85940 Posterior en calificaciones d Open - National 270,000.00 0.00 Cancelado 2017-01-06 2017-01-10 2017-02-10 2017-02-16 2017-02-27 2017-08-31 NERGETICA: 3 PARA LA REGI tutional strengthening e consultores ON NORTE, 3 PARA LA REGI ON CENTRO Y 3 PARA LA REG ION SUR SENER-DGESE-SCC-2016-06 Selección basada Policy development and insti / EVALUACION DE IMPACTO D IBRD / 85940 Posterior en calificaciones d Open - National 150,000.00 0.00 Cancelado 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 tutional strengthening EL ECOCREDITO EMPRESARIA e consultores L SENER-DGESE-SCC-2017-01 / DISEÑO DE MECANISMO PA Selección basada Policy development and insti RA EL APOYO ECONOMICO AL IBRD / 85940 Posterior en calificaciones d Open - National 45,000.00 0.00 Cancelado 2017-11-24 2017-12-11 2018-01-16 2018-02-15 2018-02-25 2018-05-26 tutional strengthening CUMPLIMIENTO DE LA NOM-0 e consultores 20-ENER PARA VIVIENDA DE I NTERES SOCIAL SENER-DGESE-SCC-2017-02 / DISENO E IMPARTICION DE Selección basada 3 TALLERES DE EFICIENCIA E Policy development and insti IBRD / 85940 Posterior en calificaciones d Open - National 80,000.00 0.00 Cancelado 2017-12-11 2018-01-30 2018-02-26 2018-03-05 2018-03-23 2018-05-25 NERGETICA EN LOS MUNICIPI tutional strengthening e consultores OS DE MONTERREY NUEVO L EON GUADALAJARA JALISCO Y VILLAHERMOSA TABASCO SENER-DGESE-SCC-2016-01 / DESARROLLO DE UNA PLAT Selección basada AFORMA EN LINEA DE SEGUI Policy development and insti IBRD / 85940 Posterior en calificaciones d Open - National 100,000.00 0.00 Cancelado 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 MIENTO DE RESULTADOS DE tutional strengthening e consultores L PRESEM (DIAGNOSTICOS Y EL MONITOREO DE LAS INTE RVENCIONES EN MUNICIPIOS ) MX-SENER-235658-CS-CQS-F IDE-NOM-13 ENER / Actualiza Selección basada Policy development and insti ción de la NOM-013-ENER-20 IBRD / 85940 Posterior en calificaciones d Open - National 150,000.00 0.00 En ejecución 2021-11-22 2022-04-21 2021-12-10 2022-10-10 2022-01-10 2022-07-22 2022-01-25 2022-02-07 2022-08-07 tutional strengthening 13 sobre la Eficiencia Energé e consultores tica de Sistemas de Alumbra do en Vialidades MX-SENER-235627-CS-CQS F IDE-NOM-020 / Estudio sobre las implicaciones energéticas Selección basada , económicas y fiscales de la Policy development and insti IBRD / 85940 Posterior en calificaciones d Open - National 150,000.00 0.00 En ejecución 2021-12-03 2022-04-21 2021-12-17 2022-01-17 2022-09-21 2022-02-16 2022-10-03 2022-03-07 2022-09-07 mejora de aislamiento térmic tutional strengthening e consultores o en el sector residencial (po r zona climática) para facilita r la implementación de la NO M-020-ENER-2011 MX-SENER-235646-CS-CQS-F IDE-NOM-08 / Actualización d Selección basada Policy development and insti e la NOM aplicable a envolve IBRD / 85940 Posterior en calificaciones d Open - National 150,000.00 0.00 Bajo Revision 2021-12-07 2022-04-21 2021-12-28 2022-01-21 2022-02-21 2022-03-17 2022-09-14 tutional strengthening nte de edificios comerciales ( e consultores NOM-008-ENER-2001) MX-SENER-235659-CS-CQS-F IDE-CAP-EE-HOSP / DISEÑO E Selección basada Policy development and insti IMPARTICIÓN DE CURSO DE E IBRD / 88440 Posterior en calificaciones d Open - National 200,000.00 0.00 En ejecución 2022-01-10 2022-04-21 2022-01-31 2022-03-01 2022-03-16 2022-04-04 2022-10-04 tutional strengthening FICIENCIA ENERGÉTICA EN H e consultores OSPITALES INTERACTIVO EN LÍNEA MX-SENER-FIDE-306264-CS- Selección basada SCC-LECCIONES AP / Consult Policy development and insti IBRD / 85940 Posterior en calificaciones d Open - National 150,000.00 0.00 Bajo Revision 2022-09-12 2022-10-07 2022-09-19 2022-10-14 2022-10-31 2022-11-11 2023-04-11 oría: Lecciones Aprendidas y tutional strengthening e consultores Análisis de Beneficios e Impa ctos del Proyecto INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-CI-3CV-2016- 02 / EJECUTIVO DE GESTION Policy development and insti FINANCIERA DE LA UNIDAD R IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-11-03 2016-11-13 2016-12-02 2016-11-20 2016-12-01 2021-10-31 tutional strengthening ESPONSABLE EJECUTORA DE L PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 03 / ASISTENTE CONTABLE D Policy development and insti IBRD / 85940 Posterior Individual Limited 99,157.26 0.00 Cancelado 2017-02-13 2017-02-28 2017-03-07 2017-03-17 2021-10-31 E LA UNIDAD RESPONSABLE tutional strengthening EJECUTORA DEL PROYECTO ( UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 04 / EJECUTIVO DE ADQUISICI Policy development and insti ONES DE LA UNIDAD RESPON IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-10-24 2016-10-25 2016-12-01 2016-10-26 2016-11-01 2021-10-31 tutional strengthening SABLE EJECUTORA DEL PROY ECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 05 / ASISTENTE EN ADQUISIC Policy development and insti IONES DE LA UNIDAD RESPO IBRD / 85940 Posterior Individual Limited 99,157.26 0.00 Cancelado 2017-02-24 2017-03-01 2017-03-22 2017-04-26 2021-10-31 tutional strengthening NSABLE EJECUTORA DEL PRO YECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 08 / ESPECIALISTA TECNICO Policy development and insti IBRD / 85940 Posterior Individual Limited 99,157.26 20,357.60 Finalizado 2016-11-21 2018-03-07 2016-12-06 2017-03-24 2016-12-20 2018-03-07 2017-01-02 2018-03-06 2021-10-31 2019-02-28 DE LA UNIDAD RESPONSABL tutional strengthening E EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- Policy development and insti 12 / GESTOR MUNICIPAL REG IBRD / 85940 Previa Individual Limited 271,446.48 0.00 Cancelado 2016-10-21 2016-10-22 2016-10-23 2016-11-01 2021-10-31 tutional strengthening ION NORTE SENER-DGESE-CI-3CV-2016- Policy development and insti IBRD / 85940 Previa Individual Limited 271,446.48 0.00 En ejecución 2016-10-21 2016-10-22 2016-10-23 2016-11-21 2021-10-31 13 / GESTOR MUNICIPAL REG tutional strengthening ION SUR Page 4 SENER-DGESE-CI-3CV-2016- 09 / EJECUTIVO EN NORMATI Policy development and insti VIDAD Y SEGUIMIENTO DE LA IBRD / 85940 Posterior Individual Limited 155,913.90 10,136.40 Finalizado 2016-03-16 2016-06-03 2016-03-21 2016-05-09 2016-05-24 2016-06-03 2016-05-31 2016-05-31 2021-10-31 2017-06-30 tutional strengthening UNIDAD RESPONSABLE EJEC UTORA DEL PROYECTO (URE P). SENER-DGESE-CI-3CV-2016- Policy development and insti 06 / ASISTENTE ADMINISTRA IBRD / 85940 Posterior Individual Limited 61,039.42 11,320.14 Finalizado 2016-03-07 2016-05-17 2016-03-12 2016-05-17 2016-05-17 2016-05-17 2016-05-20 2016-05-20 2021-10-31 2017-06-30 tutional strengthening TIVO Y DE SISTEMAS DE LA U REP SENER-DGESE-CI-3CV-2016- 01 / COORDINADOR GENERA Policy development and insti IBRD / 85940 Previa Individual Limited 460,207.73 0.00 En ejecución 2016-03-07 2016-03-12 2016-05-02 2016-05-11 2016-05-17 2021-10-31 L DE LA UNIDAD RESPONSAB tutional strengthening LE EJECUTORA DEL PROYECT O (UREP) SENER-DGESE-CI-3CV-2016- 07 / COORDINADOR TECNICO Policy development and insti IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-03-14 2016-03-19 2016-03-16 2016-04-09 2016-05-17 2021-10-31 DE LA UNIDAD RESPONSABL tutional strengthening E EJECUTORA DEL PROYECTO (UREP) SENER-DGESE-CI-3CV-2016- 14 / COORDINADOR GENERA Policy development and insti IBRD / 85940 Posterior Individual Limited 32,253.46 29,416.30 Finalizado 2017-01-13 2017-05-22 2017-01-18 2017-01-20 2017-01-23 2017-05-22 2017-02-06 2017-06-01 2017-08-05 2017-11-30 L DE LA UNIDAD RESPONSAB tutional strengthening LE EJECUTORA DEL PROYECT O UREP/PRESEM. SENER-DGESE-CI-3CV-2016- Policy development and insti 22 / ESPECIALISTA EN COMU IBRD / 85940 Posterior Individual Limited 33,000.00 28,601.85 Finalizado 2017-01-16 2017-06-30 2017-01-21 2017-10-09 2017-01-24 2017-10-09 2017-02-13 2017-10-09 2018-02-13 2018-02-28 tutional strengthening NICACION DEL PRESEM SENER-DGESE-CI-3CV-2017- 01 / ASISTENTE ADMINISTRA Policy development and insti IBRD / 85940 Posterior Individual Limited 70,363.42 13,221.06 Finalizado 2017-06-23 2017-07-26 2017-06-26 2017-07-26 2017-07-11 2017-07-26 2017-08-01 2017-08-01 2021-10-29 2018-11-30 TIVO DE LA UNIDAD RESPON tutional strengthening SABLE EJECUTORA DEL PROY ECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2017- 02 / EJECUTIVO EN NORMATI Policy development and insti VIDAD Y SEGUIMIENTO DE AC IBRD / 85940 Posterior Individual Limited 120,298.96 5,653.51 Finalizado 2017-06-23 2018-05-18 2017-06-26 2018-05-18 2017-07-17 2018-05-18 2017-08-01 2018-06-01 2021-10-29 2020-05-30 tutional strengthening UERDOS DE LA UNIDAD RESP ONSABLE EJECUTORA DEL PR OYECTO (UREP/PRESEM) SENER-DGESE-CF-SD-2017-0 1 / TALLER DE CAPACITACION Policy development and insti Selección directa EN EL MANEJO Y ENSEÑANZA IBRD / 85940 Posterior Direct 9,000.00 0.00 Cancelado 2017-09-14 2017-09-18 2017-09-29 2017-11-22 tutional strengthening de consultores DE LA HERRAMIENTA CLIMAT E ACTION FOR URBAN SUSTA INABILITY (CURB) SENER-DGESE-CI-CD-2016-1 / CONSULTOR ESPECIALISTA Policy development and insti Selección directa EN EL MANEJO Y ENSENANZA IBRD / 85940 Posterior Direct 8,000.00 0.00 Cancelado 2017-02-01 2017-02-11 2017-02-27 2017-03-06 tutional strengthening de consultores DE LA HERRAMIENTA CLIMAT E ACTION FOR URBAN SUSTA INABILITY (CURB) SENER-DGESE-CI-CD-2017-0 1 / COORDINADOR GENERAL Policy development and insti IBRD / 85940 Posterior Individual Direct 260,668.61 0.00 En ejecución 2017-11-23 2017-12-06 2017-11-23 2017-11-24 2017-12-01 2021-10-29 DE LA UNIDAD RESPONSABL tutional strengthening E EJECUTORA DEL PROYECTO 2 (UREP/PRESEM) SENER-DGESE-CF-SD-2016-0 Policy development and insti Selección directa IBRD / 85940 Posterior Direct 100,000.00 0.00 Cancelado 2017-02-15 2017-02-15 2017-03-09 2017-06-07 1 / AUDITORIA DEL PROYECT tutional strengthening de consultores O SENER-DGESE-CI-3CV-2018- 02 / EJECUTIVO DE ADQUISICI Policy development and insti ONES DE LA UNIDAD RESPON IBRD / 85940 Posterior Individual Limited 127,326.24 0.00 Cancelado 2018-02-23 2018-02-28 2018-03-21 2018-04-25 2021-10-31 tutional strengthening SABLE EJECUTORA DEL PROY ECTO (UREP/PRESEM) SENER-DGESE-CI-CD-2018-0 Policy development and insti Selección directa IBRD / 85940 Posterior Direct 180,968.32 0.00 Cancelado 2018-06-27 2018-06-27 2018-07-02 2021-10-29 1 / GESTOR MUNICIPAL tutional strengthening de consultores SENER-DGESE-CI-3CV-2018- 01 / COORDINADOR GENERA Policy development and insti IBRD / 85940 Posterior Individual Limited 260,668.61 140,980.82 Finalizado 2018-02-28 2018-08-13 2018-03-05 2018-08-13 2018-03-26 2018-08-13 2018-04-30 2018-08-13 2021-10-31 2020-12-31 L DE LA UNIDAD RESPONSAB tutional strengthening LE EJECUTORA DEL PROYECT O (UREP/PRESEM) SENER-DGESE-CI-3CV-2018- 03 / COORDINADOR TECNICO Policy development and insti IBRD / 85940 Posterior Individual Limited 119,415.00 35,842.17 Finalizado 2018-08-08 2018-09-06 2018-08-13 2018-09-06 2018-08-23 2018-09-06 2018-09-10 2018-09-06 2021-10-31 2019-03-30 DE LA UNIDAD RESPONSABL tutional strengthening E EJECUTORA DEL PROYECTO (UREP) SENER-DGESE-CI-3CV-2019- 03 / EJECUTIVO DE ADQUISICI Policy development and insti ONES DE LA UNIDAD RESPON IBRD / 85940 Posterior Individual Limited 66,081.96 0.00 Cancelado 2019-12-27 2019-12-27 2020-01-17 2020-02-21 2021-10-31 tutional strengthening SABLE EJECUTORA DEL PROY ECTO (UREP/PRESEMEH) SENER-DGESE-CI-3CV-2019- 01 / COORDINADOR TECNICO Policy development and insti IBRD / 85940 Posterior Individual Limited 66,081.96 29,868.47 Finalizado 2019-12-27 2020-02-28 2020-01-01 2020-02-28 2020-01-22 2020-02-28 2020-02-26 2020-03-01 2021-10-31 2021-10-31 DE LA UNIDAD RESPONSABL tutional strengthening E EJECUTORA DEL PROYECTO (UREP/PRESEMEH) SENER-DGESE-CI-3CV-2020- 01 / EJECUTIVO DE GESTION Policy development and insti FINANCIERA DE LA UNIDAD R IBRD / 85940 Posterior Individual Limited 64,873.60 0.00 Cancelado 2020-02-14 2020-02-18 2020-02-21 2020-03-01 2021-10-31 tutional strengthening ESPONSABLE EJECUTORA DE L PROYECTO (UREP/PRESEME H) SENER-DGESE-CI-3CV-2016- 24 / ASISTENTE TECNICO EN Policy development and insti EFICIENCIA ENERGETICA DE L IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 Cancelado 2017-04-10 2017-04-15 2017-04-24 2017-05-08 2017-11-04 tutional strengthening A UNIDAD RESPONSABLE EJE CUTORA DEL PROYECTO URE P/PRESEM 2 SENER-DGESE-CI-3CV-2016- 25 / ASISTENTE TECNICO EN Policy development and insti EFICIENCIA ENERGETICA DE L IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 Cancelado 2017-04-10 2017-04-15 2017-04-24 2017-05-08 2017-11-04 tutional strengthening A UNIDAD RESPONSABLE EJE CUTORA DEL PROYECTO URE P/PRESEM 3 SENER-DGESE-CI-3CV-2016- 23 / ASISTENTE TECNICO EN Policy development and insti EFICIENCIA ENERGETICA DE L IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 Cancelado 2017-04-10 2017-04-15 2017-04-26 2017-05-08 2017-11-04 tutional strengthening A UNIDAD RESPONSABLE EJE CUTORA DEL PROYECTO URE P/PRESEM 1 Page 5 SENER-DGESE-CI-3CV-2016- Policy development and insti 15 / EVALUACION ENERGETIC IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-10-24 tutional strengthening A URBANA EN EL MUNICIPIO 1 SENER-DGESE-CI-3CV-2016- Policy development and insti 16 / EVALUACION ENERGETIC IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 tutional strengthening A URBANA EN EL MUNICIPIO 2 SENER-DGESE-CI-3CV-2016- Policy development and insti 17 / EVALUACION ENERGETIC IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 tutional strengthening A URBANA EN EL MUNICIPIO 3 SENER-DGESE-CI-3CV-2016- Policy development and insti 18 / EVALUACION ENERGETIC IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 tutional strengthening A URBANA EN EL MUNICIPIO 4 SENER-DGESE-CI-3CV-2016- Policy development and insti 19 / EVALUACION ENERGETIC IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 tutional strengthening A URBANA EN EL MUNICIPIO 5 SENER-DGESE-CI-3CV-2016- Policy development and insti 20 / EVALUACION ENERGETIC IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 tutional strengthening A URBANA EN EL MUNICIPIO 6 SENER-DGESE-CI-3CV-2016- 11 / CONSULTOR PARA LA AD APTACION DEL "MANUAL PAR Policy development and insti IBRD / 85940 Previa Individual Limited 124,257.89 0.00 Cancelado 2017-01-20 2017-02-03 2017-02-20 2017-03-02 2021-03-01 A LA IMPLEMENTACION DE U tutional strengthening N SISTEMA DE GESTION DE L A ENERGIA DE LA CONUEE" E N MUNICIPIOS. SENER-DGESE-CI-3CV-2016- Policy development and insti 21 / DESARROLLO DE GUIA D IBRD / 85940 Posterior Individual Limited 25,000.00 0.00 Cancelado 2017-03-10 2017-03-15 2017-03-23 2017-04-05 2017-10-02 tutional strengthening E APOYOS FINANCIEROS A M UNICIPIOS SENER-DGESE-CI-3CV-2016- 10 / CONSULTOR EXPERTO P ARA SUPERVISAR LOS DIAGN Policy development and insti IBRD / 85940 Previa Individual Limited 253,042.81 0.00 Cancelado 2017-04-28 2017-05-13 2017-05-21 2017-06-01 2021-05-31 OSTICOS MUNICIPALES EN EF tutional strengthening ICIENCIA ENERGETICA Y ANA LISIS DE RESULTADOS DEL P RESEM SENER-DGESE-CI-3CV-CG-21 4705-CS-INDV / COORDINAD Policy development and insti OR GENERAL DE LA UNIDAD IBRD / 85940 Posterior Individual Limited 34,392.05 0.00 Cancelado 2021-03-01 2021-03-06 2021-03-16 2021-04-01 2021-10-31 tutional strengthening RESPONSABLE EJECUTORA D EL PROYECTO (UREP / PRESE M) SENER-DGESE-CI.3CV-EGF-2 15029-CS-INDV / “EJECUTIVO Policy development and insti IBRD / 85940 Posterior Individual Limited 20,564.29 11,339.74 Finalizado 2021-03-01 2021-06-29 2021-03-06 2021-06-29 2021-03-14 2021-06-29 2021-04-01 2021-07-01 2021-10-31 2021-10-31 DE GESTIÓN FINANCIERA DE tutional strengthening LA UREP/PRESEMEH” SENER-DGESE-CI-3CV-2016- Policy development and insti 12-30-06-2018 / GESTOR MU IBRD / 85940 Posterior Individual Limited 271,446.48 0.00 En ejecución 2021-06-21 2021-06-26 2021-07-17 2021-08-21 2021-10-31 tutional strengthening NICIPAL REGION NORTE MX-SENER-235661-CS-INDV- Policy development and insti DGIDTFRH / Gestor Municipal IBRD / 85940 Posterior Individual Limited 8,538.42 7,588.64 Finalizado 2021-06-25 2021-08-04 2021-06-30 2021-08-04 2021-07-21 2021-08-04 2021-09-01 2021-08-05 2021-10-31 2021-09-30 tutional strengthening PRESEMH-UREP MX-SENER-250381-CS-INDV / Ejecutivo en Normatividad y Policy development and insti Seguimiento de Acuerdos de IBRD / 85940 Posterior Individual Limited 2,769.54 0.00 Cancelado 2021-09-03 2021-09-06 2021-09-13 2021-09-16 2021-11-07 tutional strengthening la Unidad Responsable Ejecut ora del Proyecto (UREP / PRE SEM)” MX-SENER-254879-CS-INDV Policy development and insti DGIDTFRH-2021-2 / Gestor M IBRD / 85940 Posterior Individual Direct 4,251.77 4,179.23 Finalizado 2021-09-27 2021-10-01 2021-09-27 2021-10-01 2021-09-28 2021-10-01 2021-09-30 2021-10-01 2021-10-31 2021-10-31 tutional strengthening unicipal PRESEMH/UREP MX-SENER-258557-3CV-CI-C S-INDV-DGIDTFRH / Ejecutivo en Normatividad y Seguimien Policy development and insti IBRD / 85940 Posterior Individual Limited 32,733.17 25,622.93 Firmado 2021-10-22 2021-11-04 2021-10-22 2021-11-04 2021-10-25 2021-11-04 2021-11-01 2021-11-04 2023-04-30 to de Acuerdos de la Unidad tutional strengthening Responsable Ejecutora del Pr oyecto (UREP / PRESEM) ” MX-SENER-258560-REC-CS-I Policy development and insti NDV- DGIDTFRH / Ejecutivo d IBRD / 85940 Posterior Individual Direct 51,880.53 40,430.49 Firmado 2021-10-22 2021-10-27 2021-10-22 2021-10-27 2021-10-27 2021-10-27 2021-11-01 2021-11-01 2023-04-30 tutional strengthening e Gestión Financiera de la UR EP/PRESEMEH MX-SENER-258561-REC-CS-I Policy development and insti NDV-DGIDTFRH / Gestor Muni IBRD / 85940 Posterior Individual Direct 74,397.52 58,509.24 Firmado 2021-10-22 2021-10-27 2021-10-22 2021-10-27 2021-10-27 2021-10-27 2021-11-01 2021-11-01 2023-04-30 tutional strengthening cipal PRESEMH / UREP MX-SENER-258564-REC-CS-I NDV-DGIDTFRH / COORDINA Policy development and insti DOR TÉCNICO DE LA UNIDAD IBRD / 85940 Posterior Individual Direct 51,880.53 40,800.96 Firmado 2021-10-22 2021-10-29 2021-10-22 2021-10-29 2021-10-27 2021-10-29 2021-11-01 2021-11-01 2023-04-30 tutional strengthening RESPONSABLE EJECUTORA D EL PROYECTO (UREP / PRESE MEH) MX-SENER-258567-3-CV-CI- CS-INDV-DGIDTFRH / COORDI Policy development and insti NADOR GENERAL DE LA UNID IBRD / 85940 Posterior Individual Limited 77,120.11 58,631.03 Firmado 2021-11-15 2021-12-07 2021-11-20 2021-12-07 2021-11-30 2021-12-07 2022-01-03 2021-12-31 2023-04-30 tutional strengthening AD RESPONSABLE EJECUTOR A DEL PROYECTO (UREP / PR ESEM) MX-SENER-272040-3CV-CI-C Policy development and insti S-INDV-DGIDTFRH / Gestor M IBRD / 85940 Posterior Individual Limited 62,401.58 42,137.80 Firmado 2022-01-17 2022-02-23 2022-01-19 2022-02-23 2022-01-29 2022-02-23 2022-02-01 2022-03-01 2022-12-31 tutional strengthening unicipal Dos de la UREP/PRES EMH MX-SENER-272235-CS-INDV EJEC ADQ PRESEMH / EJECUTI Policy development and insti IBRD / 85940 Posterior Individual Direct 43,515.25 26,464.87 Firmado 2022-01-21 2022-03-28 2022-01-21 2022-03-28 2022-01-31 2022-03-28 2022-02-01 2022-04-01 2022-12-31 VO DE ADQUISICIONES DE LA tutional strengthening UREP/PRESEMH MX-SENER-306266-CS-INDV- Policy development and insti Ejecución pendien DGIDTFRH C-1-23 / Gestor M IBRD / 85940 Posterior Individual Direct - National 16,607.33 0.00 2022-11-04 2022-11-14 2022-12-14 2022-12-30 2023-04-30 tutional strengthening te unicipal Dos de la UREP/PRES EMH, C-1-2023 Page 6 MX-SENER-306468-CS-INDV- DGIDTFRH-C-1-23 / EJECUTIV Policy development and insti Ejecución pendien IBRD / 85940 Posterior Individual Direct - National 11,580.99 0.00 2022-11-04 2022-11-09 2022-11-30 2022-12-30 2023-04-30 O DE ADQUISICIONES DE LA tutional strengthening te UREP/PRESEMH C-1-2023 Page 7