PROCUREMENT PLAN (Textual Part) Project information: Eastern Recovery Project (P145196) Project Implementation agency: FSRDC Date of the Procurement Plan: February 2018 Period covered by this Procurement Plan: January 2018 – December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Eastern Recovery Project PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2018-02- 12 2022-02- Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145196 GPN Date: 18 Project Name: DRC Eastern Recovery Project Loan / Credit No: IDA / 57510, IDA / 66650 Fonds Social de la République Démocratique du Congo Executing Agency(ies): WORKS Activity Reference No. Procurement Estimate Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati High SEA/SH Process Prequalification Bidding Documents Contract / Description Component Review Type Method Document d Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Risk Status Evaluation Report as Issued Completion Type Amount (US$) Documents Justification / Invitation Opening / Minutes Recommendation (US$) Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planne d ZR-FSRDC-49337-CW-RFB Single Stage - One 350,000.0 2018-03- 2018-03- 2018-04- 2018-05- 2018-06- 2018- / Construction du bâtiment IDA / 57510 3. Capacity Building A posteriori Appel d'offres Open - National 0.00 Annulé Envelope 0 01 06 17 17 21 12-18 annexe du bureau de la CG ZR-FSRDC-232720-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 NDAWELE/NU Bank-SPD) on ZR-FSRDC-232735-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 YAKOKI/NU Bank-SPD) on ZR-FSRDC-232736-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 DIANGENDA/NU Bank-SPD) on ZR-FSRDC-232740-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 WOLO/NU Bank-SPD) on ZR-FSRDC-232743-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Ouelé/Yakoma Bank-SPD) on ZR-FSRDC-232748-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Zabo/Yakoma Bank-SPD) on ZR-FSRDC-232751-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Nzewe/Yakoma Bank-SPD) on ZR-FSRDC-232753-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Ubangi/Yakoma Bank-SPD) on ZR-FSRDC-232757-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Sorozo 1/Yakoma Bank-SPD) on ZR-FSRDC-232759-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Sorozo 2/Yakoma Bank-SPD) on ZR-FSRDC-232762-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Ya Mbongo/Yakoma Bank-SPD) on ZR-FSRDC-232765-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Yakoma/Yakoma Bank-SPD) on ZR-FSRDC-232766-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-09- 2021-10- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 04-28 Wakwa/Yakoma Bank-SPD) on ZR-FSRDC-232777-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 100,000.0 2021-09- 2021-10- 2022- RFQ / Travaux de Forage à IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 31 04-29 Kawele, Tudu et Nganza Bank-SPD) on Request for ZR-FSRDC-232886-CW- 1. Support to Community Demande de Single Stage - One 150,000.0 En attente 2021-07- 2021-08- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 RFQ / Construction de l’EP Resilience prix Envelope 0 d'exécuti 05 30 02-26 Bank-SPD) Lubala on ZR-FSRDC-232887-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 MITENGU Bank-SPD) on Request for ZR-FSRDC-232888-CW- 1. Support to Community Demande de Single Stage - One 150,000.0 En attente 2021-07- 2021-08- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 RFQ / Construction de l’EP Resilience prix Envelope 0 d'exécuti 05 30 02-26 Bank-SPD) NSELE on ZR-FSRDC-232889-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 TSHIBALA Bank-SPD) on ZR-FSRDC-232890-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 THSIMAYI Bank-SPD) on ZR-FSRDC-232891-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 KABUAYI Bank-SPD) on ZR-FSRDC-232892-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 CENTRAL Bank-SPD) on ZR-FSRDC-232893-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 LUABA NTONDO Bank-SPD) on ZR-FSRDC-232894-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 MBULU MIKONGO Bank-SPD) on ZR-FSRDC-232895-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-07- 2021-08- 2022- RFQ / Construction de l’EP IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 MPANDA Bank-SPD) on Request for ZR-FSRDC-232897-CW- 1. Support to Community Demande de Single Stage - One 150,000.0 En attente 2021-07- 2021-08- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 RFQ / Construction de l’EP Resilience prix Envelope 0 d'exécuti 05 30 02-26 Bank-SPD) TUBADI on ZR-FSRDC-236098-CW- Request for En attente RFQ / Construction de l’E.P 1. Support to Community Demande de Single Stage - One 118,530.0 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Lengi, Quartier/KAYA/ Resilience prix Envelope 0 14 09 12-06 Bank-SPD) on Commune de GBADOLITE/NU ZR-FSRDC-236353-CW- Request for En attente RFQ / Construction de l’E.P 1. Support to Community Demande de Single Stage - One 115,631.0 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti Hingaso, Quartier/LITE / Resilience prix Envelope 0 16 11 12-08 Bank-SPD) on Commune de GBADOLITE/NU ZR-FSRDC-236333-CW- RFQ / Construction de l’E.P Request for En attente 1. Support to Community Demande de Single Stage - One 123,190.9 2021-04- 2021-06- 2021- GBADOLITE, IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti Resilience prix Envelope 1 14 09 12-06 Quartier/MBANZA / Bank-SPD) on Commune de GBADOLITE/NU ZR-FSRDC-236537-CW- RFQ / Construction de l’E. Request for En attente 1. Support to Community Demande de Single Stage - One 117,749.7 2021-04- 2021-06- 2021- ZANGBINGO, IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti Resilience prix Envelope 1 11 06 12-03 Quartier/PANGOMA / Bank-SPD) on Commune de GBADOLITE/NU ZR-FSRDC-236405-CW- RFQ / Construction de l’E.P Request for En attente 1. Support to Community Demande de Single Stage - One 116,948.0 2021-04- 2021-06- 2021- MOANDA, IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti Resilience prix Envelope 3 10 05 12-02 Quartier/MOANDA / Bank-SPD) on Commune de GBADOLITE/NU ZR-FSRDC-236149-CW- Request for En attente RFQ / Construction de l’E.P 1. Support to Community Demande de Single Stage - One 104,409.8 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti MOLOMBE/ Commune de Resilience prix Envelope 5 21 16 12-13 Bank-SPD) on MOLEGBE/NU ZR-FSRDC-236038-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 110,071.9 2021-04- 2021-06- 2021- RFQ / Construction de l’E.P IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 7 21 16 12-13 FIWA/ Commune de Bank-SPD) on MOLEGBE/NU ZR-FSRDC-236406-CW- Request for En attente RFQ / Construction de l’E.P 1. Support to Community Demande de Single Stage - One 110,071.9 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti MBAYA SOKORO / Resilience prix Envelope 7 21 16 12-13 Bank-SPD) on Commune de MOLEGBE/NU ZR-FSRDC-236407-CW- Request for En attente RFQ / Construction de l’E.P 1. Support to Community Demande de Single Stage - One 106,609.1 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti MATONDI / Commune de Resilience prix Envelope 2 21 16 12-13 Bank-SPD) on MOLEGBE/NU ZR-FSRDC-236341-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 2021-04- 2021-06- 2021- RFQ / Construction du CS IDA / 66650 A posteriori Open - National Quotations (Non 89,468.33 0.00 d'exécuti Resilience prix Envelope 25 20 12-17 FADU / Commune de Bank-SPD) on MOLEGBE/NU ZR-FSRDC-236339-CW- Request for En cours RFQ / Travaux de 5 forages 1. Support to Community Demande de Single Stage - One 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Open - National Quotations (Non 92,015.00 0.00 d'exécuti au village Kawele et 1 Resilience prix Envelope 25 20 12-17 Bank-SPD) on forage à Tudu, 1 à Fadu/NU ZR-FSRDC-236167-CW- Request for En attente RFQ / Construction de l’E.P 1. Support to Community Demande de Single Stage - One 109,565.1 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti NGANZA, Quartier/NGANZA Resilience prix Envelope 5 25 20 12-17 Bank-SPD) on / Commune de NGANZA/NU ZR-FSRDC-236039-CW- Request for En attente RFQ / Construction de l’E.P 1. Support to Community Demande de Single Stage - One 111,397.6 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti BOYI, Quartier/BAMBU / Resilience prix Envelope 8 24 19 12-16 Bank-SPD) on Commune de NGANZA/NU ZR-FSRDC-236150-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 112,838.1 2021-04- 2021-06- 2021- RFQ / Construction de l’EP IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti Resilience prix Envelope 2 24 19 12-16 MOGORO/NU Bank-SPD) on ZR-FSRDC-236160-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 135,778.2 135,778. 2020-12- 2021-02- 2020-11- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Achevé construction de l'EP 2 Resilience prix Envelope 5 25 17 11 30 08-10 Bank-SPD) LUNGANDU/KANANGA (001) ZR-FSRDC-236049-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 138,055.9 138,055. 2020-12- 2020-11- 2021-02- 2020-11- 2021- IDA / 66650 A posteriori Limited Quotations (Non Signé construction de l'EP Resilience prix Envelope 5 95 20 12 14 30 08-13 Bank-SPD) NGIDILAYI/KANANGA (002) ZR-FSRDC-236413-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 130,112.4 137,704. 2020-12- 2021-02- 2020-11- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP ARC-EN- Resilience prix Envelope 5 22 22 16 30 08-15 Bank-SPD) CIEL/KANANGA (003) ZR-FSRDC-236358-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 121,136.4 121,136. 2020-12- 2021-02- 2020-11- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'E.P 1 Resilience prix Envelope 9 47 15 09 30 08-08 Bank-SPD) LUMUMBA/KANANGA (004) ZR-FSRDC-236162-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 136,988.2 136,988. 2020-12- 2021-02- 2020-11- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP Resilience prix Envelope 2 22 19 13 30 08-12 Bank-SPD) MUINDIDI/KANANGA (005) ZR-FSRDC-236343-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 137,705.2 130,112. 2020-12- 2021-02- 2020-11- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP 2 Resilience prix Envelope 2 45 11 05 30 08-04 Bank-SPD) MUKOLESHI/KANANGA (006) ZR-FSRDC-236054-CW- Request for 1. Support to Community Demande de Single Stage - One 128,633.0 128,632. 2020-12- 2020-11- 2021-02- 2020-11- 2021- RFQ / Travaux de IDA / 66650 A posteriori Limited Quotations (Non Achevé Resilience prix Envelope 0 96 13 18 07 30 08-06 construction de l'EP Bank-SPD) KAPAJIKA/KANANGA (007) ZR-FSRDC-236394-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 139,531.0 139,895. 2020-12- 2021-02- 2020-11- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Achevé construction de l'E.P Resilience prix Envelope 3 53 13 07 30 08-06 Bank-SPD) KANDIKU/KANANGA (008) ZR-FSRDC-236360-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 138,488.2 138,488. 2020-12- 2021-02- 2020-11- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP Resilience prix Envelope 2 22 24 18 30 08-17 Bank-SPD) MUFIMISHI/KANANGA (009) ZR-FSRDC-236163-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 128,651.0 128,651. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP Resilience prix Envelope 9 09 22 16 07 08-15 Bank-SPD) MUDIDIKE/KANANGA (010) ZR-FSRDC-236084-CW- Request for 1. Support to Community Demande de Single Stage - One 136,814.0 136,814. 2020-12- 2020-11- 2021-02- 2020-12- 2021- RFQ / Travaux de IDA / 66650 A posteriori Limited Quotations (Non Signé Resilience prix Envelope 3 03 21 23 15 07 08-14 construction de l'EP Bank-SPD) NGANZA/KANANGA (011) ZR-FSRDC-236410-CW- Request for RFQ / Travaux de 2. Livelihoods and Demande de Single Stage - One 135,632.0 135,632. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP Employment Generation prix Envelope 0 00 26 20 07 08-19 Bank-SPD) TSHINSAMBI/KANANGA (012) ZR-FSRDC-236395-CW- Request for 1. Support to Community Demande de Single Stage - One 127,655.0 127,655. 2020-12- 2021-02- 2020-12- 2021- RFQ / Travaux de IDA / 66650 A posteriori Open - National Quotations (Non Signé Resilience prix Envelope 0 24 22 16 07 08-15 construction de l'E.P Bank-SPD) DIKU/KANANGA (013) ZR-FSRDC-236542-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 132,095.5 132,095. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP Resilience prix Envelope 9 59 23 17 07 08-16 Bank-SPD) TOSALISANAI/KANANGA (014) ZR-FSRDC-236396-CW- Request for 1. Support to Community Demande de Single Stage - One 127,526.3 138,724. 2020-12- 2021-02- 2020-12- 2021- RFQ / Travaux de IDA / 66650 A posteriori Open - National Quotations (Non Signé Resilience prix Envelope 9 34 18 12 07 08-11 construction de l'EP Bank-SPD) DISANKA/KANANGA (015) ZR-FSRDC-236141-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 141,423.0 141,423. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP Mgr Resilience prix Envelope 0 19 26 20 07 08-19 Bank-SPD) BAKAFUA/KANANGA (016) ZR-FSRDC-236283-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 141,423.0 141,423. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'E.P Resilience prix Envelope 0 19 26 20 07 08-19 Bank-SPD) TSHIBASHI/KANANGA (017) ZR-FSRDC-236354-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 131,171.9 132,171. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP Resilience prix Envelope 5 95 26 20 07 08-19 Bank-SPD) BUSHALA BUAMBA/KANANGA (018) ZR-FSRDC-236521-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 128,306.1 128,306. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'EP NDESHA Resilience prix Envelope 6 16 23 17 14 08-16 Bank-SPD) LUSAMBO/KANANGA (019) ZR-FSRDC-236284-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 132,871.0 132,870. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'E.P Resilience prix Envelope 0 99 23 17 14 08-16 Bank-SPD) BAOLONGO/KANANGA (020) ZR-FSRDC-236507-CW- Request for En attente RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 128,246.0 2020-12- 2021-02- 2021- IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti construction de l'EP Resilience prix Envelope 0 23 17 08-16 Bank-SPD) on TSHISUMBU/KANANGA (021) ZR-FSRDC-236085-CW- Request for En cours RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 128,434.3 2020-12- 2021-02- 2021- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti construction de l'EP DIKU Resilience prix Envelope 1 26 20 08-19 Bank-SPD) on DIETU/KANANGA (022) ZR-FSRDC-236508-CW- Request for 1. Support to Community Demande de Single Stage - One 132,127.2 132,127. 2020-12- 2021-02- 2020-12- 2021- RFQ / Travaux de IDA / 66650 A posteriori Open - National Quotations (Non Signé Resilience prix Envelope 1 21 27 21 14 08-20 construction de l'EP Bank-SPD) DIAKAJA/KANANGA (023) ZR-FSRDC-236286-CW- Request for RFQ / Travaux de 1. Support to Community Demande de Single Stage - One 126,551.1 126,551. 2020-12- 2021-02- 2020-12- 2021- IDA / 66650 A posteriori Open - National Quotations (Non Signé construction de l'E.P TUYA Resilience prix Envelope 1 11 22 16 14 08-15 Bank-SPD) KUMPALA/KANANGA (024) ZR-FSRDC-236156-CW- Request for 1. Support to Community Demande de Single Stage - One 134,597.4 134,597. 2020-12- 2021-02- 2020-12- 2021- RFQ / Travaux de IDA / 66650 A posteriori Open - National Quotations (Non Signé Resilience prix Envelope 9 49 23 17 14 08-16 construction de l'EP Bank-SPD) SANKAYI/KANANGA (025) ZR-FSRDC-236361-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 135,000.0 2021-01- 2021-03- 2021- RFQ / Travaux de IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 02 08-29 construction EP Dikongayi Bank-SPD) on 2/Kananga ZR-FSRDC-239808-CW- RFQ / Construction de l'EP Request for En attente BISHIYA/Village KALUMBA 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti MANDE/Groupement BENA Resilience prix Envelope 0 14 08 03-07 Bank-SPD) on NGOYI/KALUMBA/Secteur DIBANDA_KC ZR-FSRDC-239813-CW- RFQ / Construction de l'EP Request for En attente MUAKAJI/Village 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti TSHIMANGA Resilience prix Envelope 0 17 11 03-10 Bank-SPD) on NFUMA/Groupement BENA KABIYE/ TSHIKELE/Secteur DIBANDA_KC Page 1 ZR-FSRDC-239818-CW- RFQ / Construction de l'EP1 Request for En attente DIBANDA/Village 1. Support to Community Demande de Single Stage - One 1,250,000. 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti BUNKONDE/Groupement Resilience prix Envelope 00 19 13 03-12 Bank-SPD) on BENE KALUBI/ BAKUA NDOLO/Secteur DIBANDA_KC ZR-FSRDC-239821-CW- RFQ / Construction de l'EP Request for En attente EP NDIBU KALAMBA/Village 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti TSHILOLO/Groupement Resilience prix Envelope 0 20 14 03-13 Bank-SPD) on BAKUA NDAYE/Secteur KASANGIDI_KC ZR-FSRDC-239825-CW- RFQ / Construction de l'EP Request for En attente LUAJA/Village BENA 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti NGANA/Groupement BENA Resilience prix Envelope 0 18 12 03-11 Bank-SPD) on NGALA/Secteur KASANGIDI_KC ZR-FSRDC-239830-CW- RFQ / Construction de l'EP3 Request for En attente LUKULA/Village BENA 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti NKENU/Groupement BENA Resilience prix Envelope 0 24 18 03-17 Bank-SPD) on NKENU/Secteur KASANGIDI_KC ZR-FSRDC-239832-CW- RFQ / Construction de l'EP1 Request for En attente BASANGA/Village 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti KAULU/Groupement KAULU Resilience prix Envelope 0 25 19 03-18 Bank-SPD) on MIKELE/Secteur KASANGIDI_KC ZR-FSRDC-239833-CW- RFQ / Construction de l'EP NTUADIJILU/Village BAKUA Request for En attente TSHILUNDU 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti /NFUAMBA/Groupement Resilience prix Envelope 0 25 19 03-18 Bank-SPD) on BAKUA TSHILUNDU/ NFUAMBA/Secteur KASANGIDI_KC ZR-FSRDC-239835-CW- RFQ / Construction de l'EP MAMBASAKO/Village Request for En attente 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- TSHINEMA BENA IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 26 20 03-19 MUABA/Groupement BENA Bank-SPD) on MUAMBA/Secteur KASANGIDI_KC ZR-FSRDC-239837-CW- RFQ / Construction de l'EP Request for En attente TSHIMAKAKA/Village 1. Support to Community Demande de Single Stage - One 125,000.0 2021-07- 2021-09- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti MUPOYI/Groupement Resilience prix Envelope 0 27 21 03-20 Bank-SPD) on BAKUA NKATE (MUPOYI)/Secteur KASANGIDI_KC ZR-FSRDC-239867-CW- Request for En attente Demande de Single Stage - One 184,000.0 2021-07- 2021-08- 2022- RFQ / Extension Bureaux de IDA / 66650 4. Project Management A posteriori Limited Quotations (Non 0.00 d'exécuti prix Envelope 0 05 30 02-26 l'Antenne_Kananga Bank-SPD) on ZR-FSRDC-243740-CW- RFQ / Construction de trois (3) écoles dans le Secteur de DIBANDA en 3 lots, lot 1 : EP BISHIYA dans le Groupement Request for En attente 1. Support to Community Demande de Single Stage - One 450,000.0 2021-08- 2021-10- 2022- de BENA NGOYI/KALUMBA, IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 21 16 04-14 lot 2 : EP MUAKAJI dans le Bank-SPD) on Groupement de BENA KABIYE/TSHIKELE, Lot 3 : EP1 DIBANDA dans le Groupement de KALUBI/BAKUA NDOL ZR-FSRDC-243751-CW- Request for En attente RFQ / Construction de sept 1. Support to Community Demande de Single Stage - One 1,050,000. 2021-08- 2021-10- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti (7) écoles dans le Secteur de Resilience prix Envelope 00 17 12 04-10 Bank-SPD) on KASANGIDI en 7 lots distincts ZR-FSRDC-243764-CW- Request for En attente 1. Support to Community Demande de Single Stage - One 150,000.0 2021-08- 2021-10- 2022- RFQ / Réhabilitation de IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 22 17 04-15 l’Hôpital Général de Bank-SPD) on LUKONGA ZR-FSRDC-252952-CW- RFQ / Construction de 4 écoles dans les communes d'Ibanda et Bagira en 4 lots: - lot 1: EP 2 Matendo_C/Ibanda_Q/Nden Request for En attente dere 1. Support to Community Demande de Single Stage - One 520,000.0 2021-10- 2021-12- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti - lot 2: EP Resilience prix Envelope 0 17 12 06-10 Bank-SPD) on Nguba_C/Ibanda_Q/Nyaluke mba - lot 3: EP Kahya_C/Ibanda_Q/Panzi - lot 4: EP Imani- Cahi_C/Bagira_Q/Cahi- Kasha ZR-FSRDC-252955-CW- RFQ / Construction 5 écoles Communes de kadutu et Bagira; 5 lots: lot 1: EP NIDUNGA_C/Kadutu_Q/Nya mugo lot 2: EP Request for En attente 1. Support to Community Demande de Single Stage - One 650,000.0 2021-10- 2021-12- 2022- ULINDI_C/Kadutu_Q/Kasali IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 17 12 06-10 lot 3: CS Bank-SPD) on ISTM_C/Kadutu_C/Nyakaliba lot 4: EP Kangali_C/Bagira_Q/Buholo - Kasha lot 5: EP Mgr MULINDWA_C/Kadutu_Q/Nk afu ZR-FSRDC-252956-CW- RFQ / Construction de 5 écoles dans la commune de Bagira en 5 lots - lot 1: EP Request for En attente 1. Support to Community Demande de Single Stage - One 650,000.0 2021-10- 2021-12- 2022- Mulambula_Q/Mulambula IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 23 18 06-16 - lot 2: CS Bank-SPD) on MULEZI_Q/Cikonyi - lot 3: EP MULWA_Q/Mulwa - lot 4: EP Familia DEI_Q/Ciriri - lot 5: Institut Sainte Famille_Q/Kanoshe ZR-FSRDC-236390-CW- Request for En attente RFQ / Construction de l’E.P 1. Support to Community Demande de Single Stage - One 106,609.1 2021-04- 2021-06- 2021- IDA / 66650 A posteriori Open - National Quotations (Non 0.00 d'exécuti MWANDA CECU / Commune Resilience prix Envelope 2 10 05 12-02 Bank-SPD) on de MOLEGBE/NU ZR-FSRDC-262107-CW- RFQ / (4): Construction de 2 écoles dans la Bagira/ville de Bukavu en 2 lots: Request for En attente - lot 1: EP Bulenga, Quartier 1. Support to Community Demande de Single Stage - One 260,000.0 2021-11- 2022-01- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Lumumba, Commune de Resilience prix Envelope 0 30 25 07-24 Bank-SPD) on Bagira - lot 2: EP Umoja, Quartier Nyakavogo, Commune de Bagira ZR-FSRDC-264810-GO- RFQ / (2): Construction de quatre (4) centres de santé dans le secteurs Secteurs de Request for En attente Dibataie et Kamuandu / 1. Support to Community Demande de Single Stage - One 500,000.0 2022-03- 2022-05- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Kasaï Central subdivisés en Resilience prix Envelope 0 20 15 11-11 Bank-SPD) on 4 lots: - Lot 1 : CS Ngalampata, - Lot 2: CS Bena Kazadi, - Lot 3: CS Kankuku, - Lot 4: CS Mutefu ZR-FSRDC-264813-CW- RFQ / (3): Construction de cinq (5) écoles primaires dans le Secteurs de Dibataie Request for En attente / Kasaï Central subdivisées 1. Support to Community Demande de Single Stage - One 625,000.0 2022-03- 2022-05- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti en 5 lots : - - Lot 1: EP Resilience prix Envelope 0 20 15 11-11 Bank-SPD) on Ntenda, - Lot 2: EP Milayi, - Lot 3: EP Lutambi, - Lot 4: EP Mofuayi, - Lot 5: Bena Kazadi ZR-FSRDC-264814-CW- RFQ / (4): Construction de quatre (4) écoles primaires dans le Secteurs de Dibataie Request for En attente 1. Support to Community Demande de Single Stage - One 500,000.0 2022-03- 2022-05- 2022- / Kasaï Central subdivisées IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 20 15 11-11 en 4 lots : Bank-SPD) on - Lot 1: EP Mbondo, - Lot 2: EP Lusambi, - Lot 3: EP Tudiku, - Lot 4: EP Sankayi ZR-FSRDC-264815-CW- RFQ / (5): Construction de quatre (4) écoles primaires dans le Secteurs de Dibataie Request for En attente et Kamuandu / Kasaï 1. Support to Community Demande de Single Stage - One 500,000.0 2022-03- 2022-05- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Central subdivisées en 4 Resilience prix Envelope 0 21 16 11-12 Bank-SPD) on lots : - Lot 1: EP Kapiku, - Lot 2: Mpunga, - Lot 3: EP Tudilame, - Lot 4: EP Kafudu ZR-FSRDC-264818-CW- RFQ / (6): Construction de de quatre (4) écoles primaires dans les Secteurs Request for En attente de Dibataie et Kamuandu / 1. Support to Community Demande de Single Stage - One 500,000.0 2022-03- 2022-05- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Kasaï Central subdivisées en Resilience prix Envelope 0 20 15 11-11 Bank-SPD) on 4 lots : - Lot 1: EP Kabonge, - lot 2: EP Kanuamayi, - Lot 3 : EP Dibatayi, - Lot 4: EP Tshitokololo ZR-FSRDC-264819-CW- RFQ / (7): Quatre (4) forages mécaniques dans les Secteurs de Dibataie et Request for En attente Kamuandu / Kasaï Central 1. Support to Community Demande de Single Stage - One 500,000.0 2022-03- 2022-05- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti subdivisées en 4 lots : Resilience prix Envelope 0 20 15 11-11 Bank-SPD) on - Lot 1: Kabeya lumbu, - Lot 2: Ntambwe Tshintanku, - Lot 3: Bena Nsamba - Lot 4: Mbulungu ZR-FSRDC-264805-CW- RFQ / (1): Construction de 4 centres de santé Secteur de Dibataie / Kasaï Central Request for En attente 1. Support to Community Demande de Single Stage - One 500,000.0 2022-04- 2022-05- 2022- subdivisés en 4 lots : IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 31 11-27 - Lot 1: CS Nkufulu, Bank-SPD) on - Lot 2: CS Ntambue Kayembe, - Lot 3: CS Kamuina Nsapo, - Lot 4: CS Kasende ZR-FSRDC-274058-CW- RFQ / (1) Construction de 2 écoles dans la commune de Kadutu en 2 lots : Request for En attente 1. Support to Community Demande de Single Stage - One 260,000.0 2022-04- 2022-05- 2022- - Lot 1 : EP Furaha, Quartier IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 30 11-26 CIMPUNDA Bank-SPD) on - Lot 2 : EP Kadutu centre, Quartier Mosala Sud Kivu ZR-FSRDC-274094-CW- RFQ / (41) Construction des IDB aux quartiers (MURARA, MIKENO, KATOYI, BUJOVU, Request for En attente 1. Support to Community Demande de Single Stage - One 650,000.0 2022-05- 2022-06- 2022- MAJENGO) IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 29 12-26 E.P UMOJA, E.P INJILI, E.P Bank-SPD) on MIHINI, E.P MULIKUZA, E.P NAZAREENNE_ Ville de GOMA_ NORD KIVU ZR-FSRDC-274096-CW- RFQ / (42) Construction des IDB aux quartiers (KATINDO, NDOSHO, KAYEMBE, Request for En attente 1. Support to Community Demande de Single Stage - One 520,000.0 2022-05- 2022-06- 2022- MABANGA SUD) IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 04 29 12-26 E.P.A FURAHA, Centre de Bank-SPD) on Santé BARAKA, E.P Saint JOSEPH, E.P RUTOBOKA_ Ville de GOMA _ NORD KIVU ZR-FSRDC-274098-CW- RFQ / (44) Construction des Request for En attente IDB aux groupements de 1. Support to Community Demande de Single Stage - One 260,000.0 2022-05- 2022-06- 2022- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti MUNIGI et KIBATI Resilience prix Envelope 0 04 29 12-26 Bank-SPD) on E.P MUNIGI, E.P BUJARI_ ville de GOMA_ NORD KIVU ZR-FSRDC-274708-CW- RFQ / (6) Construction des IDB aux quartiers (LEMBABO, MUZI-PELA, Request for En cours SUKISA, KINDIA et 1. Support to Community Demande de Single Stage - One 650,000.0 2022-07- 2022-08- 2023- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti SIMBILIABO)-Lot 1: E.P Resilience prix Envelope 0 05 30 02-26 Bank-SPD) on MUDJUMBE EPAINETO- Lot 2: E.P 1 BUNIA- Lot 3: E.P SUKISA - Lot 4: E.P MWANGA- Lot 5: E.P EP NYAKEZI_ ITURI ZR-FSRDC-274709-CW- RFQ / (7) Construction des IDB aux quartiers (BEMBEY, LUMUMBA, RWAMBUZI-BENI, SALONGO et dans le Request for En cours 1. Support to Community Demande de Single Stage - One 650,000.0 2022-07- 2022-08- 2023- groupement BABUCHUKA) - IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 Lot .1: E.P INGA NIZI- Lot 2: Bank-SPD) on E.P.1 MURONGO- Lot .3: E.P SIMBILYABO- Lot 4: E.P 4 NYAKASANZA- Lot 5: EP. BUNDIKASA_ ITURI ZR-FSRDC-274712-CW- RFQ / (8) Construction IDB quartiers (BIGO, HOHO, OPAS, KASEGWA et DELE) Request for En cours Lot 1 : Centre de santé BIGO 1. Support to Community Demande de Single Stage - One 650,000.0 2022-07- 2022-08- 2023- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti - Lot .2 : Centre de santé Resilience prix Envelope 0 05 30 02-26 Bank-SPD) on HOHO- Lot .3 : Centre de santé OPAS- Lot .4 : Centre de santé KASEGWA- Lot 5: Centre de santé de _ ITURI ZR-FSRDC-274713-CW- RFQ / (9) Construction des IDB aux quartiers (TSERE, LENGABO, BABULABA, BEDU Request for En cours 1. Support to Community Demande de Single Stage - One 650,000.0 2022-07- 2022-08- 2023- EZEKERE et SALONGO) Lot 1: IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 EP. MAKI MBUDHA-Lot .2: Bank-SPD) on EP. MBUNYA-Lot 3: EP.2 OLENYAMA-Lot.4: EP.BUY SABUNI-Lot 5: Centre de santé SALONGO_ ITURI ZR-FSRDC-274715-CW- RFQ / (10) Construction des IDB aux quartiers (NDIBA- KODU, LUVANGIRE, Request for En cours RWAMBUZI-FICHANA et 1. Support to Community Demande de Single Stage - One 520,000.0 2022-07- 2022-08- 2023- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti NGEZI) -Lot 1 : Centre de Resilience prix Envelope 0 05 30 02-26 Bank-SPD) on santé NDIBE-Lot.2 : Centre de santé KATOTO-Lot : 2 Forages à RWAMBUZI- FICHANA- Lot.4 : 4 Forages à NGEZI- ITURI ZR-FSRDC-274731-CW- RFQ / (40) Construction des IDB aux quartiers (LES VOLCANS, HIMBI, Request for En attente 1. Support to Community Demande de Single Stage - One 650,000.0 2022-07- 2022-08- 2023- KEYSHERO, LAC VERT, IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 MAPENDO) / Ville de Goma Bank-SPD) on Lot I.1: EP EPAIGO Lot I.2: EP MORIA Lot I.3: SAYUNI Lot I.4: EP LAC-VERT Lot I.5: EP BETHANIE _ Nord Kivu ZR-FSRDC-274733-CW- RFQ / (43) Construction des IDB aux quartiers Request for En attente (MABANGA NORD, KASIKA, 1. Support to Community Demande de Single Stage - One 520,000.0 2022-07- 2022-08- 2023- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti MUGUNGA, VIRUNGA) /Ville Resilience prix Envelope 0 05 30 02-26 Bank-SPD) on de Goma Lot 1: EP KATOYI Lot 2: EPA UJUMBE Lot 3: EP NENGAPETA Lot 4: EP BWAKYA_ Nord Kivu ZR-FSRDC-275582-CW- RFQ / (11) Construction des IDB aux quartiers (NYAKASANZA I, Request for En attente NYAKASANZA II et SAIO) 1. Support to Community Demande de Single Stage - One 390,000.0 2022-07- 2022-08- 2023- IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Lot1: 1 Forages dans le Resilience prix Envelope 0 05 30 02-26 Bank-SPD) on quartier NYAKASANZA I -Lot 2: 2 Forages dans le quartier NYAKASANZA II-Lot 2 Forage dans le quartier SAIO- V_BUNIA_ITURI ZR-FSRDC-275584-CW- RFQ / (12) Construction des IDB aux quartiers (RWANGOLE, YAMBI-YAYA et BANKOKO) Request for En attente 1. Support to Community Demande de Single Stage - One 390,000.0 2022-07- 2022-08- 2023- Lot 1: 1 Forages dans le IDA / 66650 A posteriori Limited Quotations (Non 0.00 d'exécuti Resilience prix Envelope 0 05 30 02-26 quartier RWANGOLE;-Lot 2: Bank-SPD) on 3 Forages dans le quartier YAMBI-YAYA -Lot 3: 4 Forages dans le quartier BANKOKO_ V_BUNIA_ ITURI GOODS Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual Page 2 ZR-FSRDC-49334-GO-RFQ / Acquisition de 4 tracteurs et remorques matériel - Demande de Single Stage - One 2018-03- 2018-06- 2018-04- 2018-07- 2018-10- Brigade d'entretien - OVD IDA / 57510 3. Capacity Building A posteriori Limited 185,000.00 258,572.05 Signé prix Envelope 05 22 30 26 27 1) Lot 1Nord Kivu (2), 2) Lot 2 Ituri (1), 3) Lot 3: Tanganyika (1) ZR-FSRDC-51041-GO-RFQ Demande de Single Stage - One 2018-12- 2019-01- 2019-07- / Acquisition LABOSEM IDA / 57510 3. Capacity Building A posteriori Limited 50,000.00 0.00 Annulé prix Envelope 01 26 25 phytosanitaire du Sud Kivu ZR-FSRDC-51046-GO-RFB Demande de Single Stage - One 2018-11- 2019-01- 2019-07- / Acsuisition des IDA / 57510 3. Capacity Building A posteriori Limited 45,000.00 0.00 Annulé prix Envelope 28 23 22 équipements pour LABO INERA ZR-FSRDC-49370-GO-RFQ / Acquisition des Demande de Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 57510 3. Capacity Building A posteriori Limited 40,000.00 0.00 Annulé équipements du nouveau prix Envelope 06 01 28 bureau de la CG à construire. ZR-FSRDC-232724-GO- RFQ / Acquisition des outillages (Petits matériels) En attente 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-10- 2022-04- dans le cadre de mise en IDA / 66650 A posteriori Limited 30,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 31 29 œuvre des chantiers n Thimo/cash for work à Kananga (Kit d’urgence) ZR-FSRDC-232732-GO- RFQ / Acquisition des équipements de protection En attente 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-10- 2022-04- individuelle (EPI) dans le IDA / 66650 A posteriori Limited 50,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 31 29 cadre de mise en œuvre des n chantiers Thimo/cash for work à Kananga (vague 1) ZR-FSRDC-232737-GO- RFQ / Acquisition des outillages (Petits matériels) En attente 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-10- 2022-04- dans le cadre de mise en IDA / 66650 A posteriori Limited 270,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 31 29 œuvre des chantiers n Thimo/cash for work à Kananga (vague 1) en 9 lots ZR-FSRDC-232746-GO- RFQ / Fourniture des matériels informatiques Demande de Single Stage - One 2021-06- 2021-05- 2021-08- 2021-07- 2022-02- pour les antennes IDA / 66650 4. Project Management A posteriori Limited 300,000.00 174,620.00 Signé prix Envelope 20 14 15 09 11 provinciales (Kinshasa, Nord Kivu, Sud Kivu, Kasaï Central, Nord Ubangi) du STEP 2 ZR-FSRDC-232758-GO- En attente RFQ / Acquisition et Demande de Single Stage - One 2021-06- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Limited 60,000.00 0.00 d'exécutio Installation de 2 prix Envelope 13 08 04 n Générateurs pour Kasaï Central et Nord Ubangi ZR-FSRDC-232763-GO- RFQ / Acquisition et Demande de Single Stage - One 2021-06- 2021-05- 2021-08- 2021-08- 2022-02- Installation de 3 VSAT pour IDA / 66650 4. Project Management A posteriori Limited 15,000.00 17,050.00 Signé prix Envelope 13 21 08 06 04 la connexion Internet/Nord Ubangi/Kasaï Central et Ituri ZR-FSRDC-232770-GO- RFQ / Fourniture des En attente mobiliers pour les EP Lengi, 1. Support to Community Demande de Single Stage - One 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Limited 100,000.00 0.00 d'exécutio Hingaso, Gbadolite, Resilience prix Envelope 04 29 28 n Zangbino et Moanda toutes/commune de Gbadolite ZR-FSRDC-232772-GO- En attente RFQ / Fourniture de la Demande de Single Stage - One 2021-06- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Limited 20,000.00 0.00 d'exécutio connexion Internet et prix Envelope 13 08 04 n Interphones en faveur du projet STEP II ZR-FSRDC-232774-GO- RFQ / Fourniture des En attente mobiliers pour les EP 1. Support to Community Demande de Single Stage - One 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Limited 100,000.00 0.00 d'exécutio Mwanda Cecu, Molombe, Resilience prix Envelope 04 29 28 n Fiwa, Mbaya Sokoro, Matondi et le CS Fadu tous/commune de Molegbe ZR-FSRDC-232775-GO- RFQ / Achat 11 Tablettes Demande de Single Stage - One 2021-06- 2021-05- 2021-08- 2021-06- 2022-01- IDA / 66650 4. Project Management A posteriori Limited 3,300.00 1,760.00 Signé enquêteurs TSHIMBULU ET prix Envelope 06 26 01 18 28 DIBAYA CENTRE ZR-FSRDC-232780-GO- RFQ / Acquisition des En attente outillages (Petits matériels) 2. Livelihoods and Demande de Single Stage - One 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Limited 30,000.00 0.00 d'exécutio dans le cadre de mise en Employment Generation prix Envelope 05 30 29 n œuvre des chantiers Thimo/cash for work à TSHIMBULU ZR-FSRDC-232781-GO- RFQ / Acquisition des équipements de protection En attente 2. Livelihoods and Demande de Single Stage - One 2021-10- 2021-11- 2022-05- individuelle (EPI) dans le IDA / 66650 A posteriori Limited 30,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 cadre de mise en œuvre des n chantiers Thimo/cash for work à TSHIMBULU ZR-FSRDC-232782-GO- En attente Demande de Single Stage - One 2021-07- 2021-09- 2022-03- RFQ / Acquisition d’un mini IDA / 66650 5. CERC A posteriori Limited 50,000.00 0.00 d'exécutio prix Envelope 13 07 06 bus pour le CERC n ZR-FSRDC-232783-GO- RFQ / Fourniture des En attente 1. Support to Community Demande de Single Stage - One 2021-09- 2021-10- 2022-04- mobiliers pour les EP IDA / 66650 A posteriori Limited 100,000.00 0.00 d'exécutio Resilience prix Envelope 05 31 29 Nganza, Boyi, Mogoro et le n CS Tudu/Commune de Nganza ZR-FSRDC-232786-GO- En attente RFQ / Fourniture des 1. Support to Community Demande de Single Stage - One 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Limited 100,000.00 0.00 d'exécutio mobiliers pour les EP Resilience prix Envelope 05 30 29 n Ndawele, Yakoki , Diangenda et Wolo ZR-FSRDC-232794-GO- RFQ / Acquisition des En attente outillages (Petits matériels) 2. Livelihoods and Demande de Single Stage - One 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Limited 35,000.00 0.00 d'exécutio dans le cadre de mise en Employment Generation prix Envelope 05 30 29 n œuvre des chantiers Thimo/cash for work à DIBAYA ZR-FSRDC-232805-GO- RFQ / Acquisition des équipements de protection En attente 2. Livelihoods and Demande de Single Stage - One 2021-10- 2021-11- 2022-05- individuelle (EPI) dans le IDA / 66650 A posteriori Limited 35,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 cadre de mise en œuvre des n chantiers Thimo/cash for work à DIBAYA ZR-FSRDC-232804-GO- Passation de En attente DIR / Acquisition, mise à 2021-06- 2021-06- 2021-07- 2022-01- IDA / 66650 4. Project Management A posteriori marché de gré à Direct 55,000.00 0.00 d'exécutio jour et formation sur le 15 20 25 21 gré n logiciel TOM2PRO ZR-FSRDC-232809-GO- Demande de Single Stage - One 2021-06- 2021-07- 2021-08- 2021-10- 2022-02- RFQ / Aménagement des IDA / 66650 4. Project Management A posteriori Limited 30,000.00 37,207.94 Signé prix Envelope 13 20 08 25 04 containers ZR-FSRDC-232820-GO- RFQ / Acquisition des motos 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-07- 2021-10- 2021-08- 2022-04- IDA / 66650 A posteriori Limited 42,800.00 47,650.00 Signé de terrain, lot 1: 4 pour le Employment Generation prix Envelope 05 14 31 31 29 NU et lot 2: 6 pour Kananga ZR-FSRDC-220575-GO- En attente RFQ / Acquisition de trois Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 4. Project Management A posteriori Limited 150,000.00 0.00 d'exécutio véhicules automobile 4x4 prix Envelope 24 21 18 n pour le projet STEP II ZR-FSRDC-232898-GO- En attente RFQ / Fourniture des 1. Support to Community Demande de Single Stage - One 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Limited 75,000.00 0.00 d'exécutio mobiliers pour les 5 EP de Resilience prix Envelope 04 29 28 n Tshibulu ( 5 lots) ZR-FSRDC-232899-GO- En attente RFQ / Fourniture des 1. Support to Community Demande de Single Stage - One 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Limited 90,000.00 0.00 d'exécutio mobiliers pour les 6 EP de Resilience prix Envelope 04 29 28 n DIBAYA ( 6 lots) ZR-FSRDC-233086-GO- RFQ / Acquisition des outillages (Petits matériels) En attente 2. Livelihoods and Demande de Single Stage - One 2021-07- 2021-08- 2022-02- dans le cadre de mise en IDA / 66650 A posteriori Limited 90,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 26 œuvre des chantiers n Thimo/cash for work à Yakoma pour 9 quartiers ZR-FSRDC-233089-GO- RFQ / Acquisition des équipements de protection En attente individuelle (EPI) dans le 2. Livelihoods and Demande de Single Stage - One 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Limited 90,000.00 0.00 d'exécutio cadre de mise en œuvre des Employment Generation prix Envelope 05 30 26 n chantiers Thimo/cash for work à Yakoma pour les 9 quartiers ZR-FSRDC-232764-GO- RFQ / Acquisition des outillages (Petits matériels) En attente 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-10- 2022-04- dans le cadre de mise en IDA / 66650 A posteriori Limited 100,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 31 29 œuvre des chantiers n Thimo/cash for work à Kananga (vague 3) en 9 lots ZR-FSRDC-232755-GO- RFQ / Acquisition des équipements de protection En attente individuelle (EPI) dans le 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Limited 100,000.00 0.00 d'exécutio cadre de mise en œuvre des Employment Generation prix Envelope 05 31 29 n chantiers Thimo/cash for work à Kananga (vague 3) en 9 lots ZR-FSRDC-236168-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scolaire l'EP 2 LUNGANDU/KANANGA (001) ZR-FSRDC-236139-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'EP NGIDILAYI/KANANGA (002) ZR-FSRDC-236101-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'EP ARC-EN- CIEL/KANANGA (003) ZR-FSRDC-236158-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'E.P 1 LUMUMBA/KANANGA (004) ZR-FSRDC-236105-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'EP MUINDIDI/KANANGA (005) ZR-FSRDC-236043-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'EP 2 MUKOLESHI/KANANGA (006) ZR-FSRDC-236387-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scolaire l'EP KAPAJIKA/KANANGA (007) ZR-FSRDC-236042-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scolaire l'E.P KANDIKU/KANANGA (008) ZR-FSRDC-236151-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scolaire l'EP MUFIMISHI/KANANGA (009) ZR-FSRDC-236408-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'EP MUDIDIKE/KANANGA (010) ZR-FSRDC-236051-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'EP NGANZA/KANANGA (011) ZR-FSRDC-236170-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,495.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'EP TSHINSAMBI/KANANGA (012) ZR-FSRDC-236276-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'E.P DIKU/KANANGA (013) ZR-FSRDC-236140-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'EP TOSALISANAI/KANANGA (014) ZR-FSRDC-236107-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'EP DISANKA/KANANGA (015) ZR-FSRDC-236281-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scoalire l'EP Mgr BAKAFUA/KANANGA (016) ZR-FSRDC-236391-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'E.P TSHIBASHI/KANANGA (017) ZR-FSRDC-236503-GO- RFQ / Fourniture En attente 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- d'équipements /mobilier IDA / 66650 A posteriori Limited 12,075.00 0.00 d'exécutio Resilience prix Envelope 05 02 29 scoalire l'EP BUSHALA n BUAMBA/KANANGA (018) ZR-FSRDC-236050-GO- RFQ / Fourniture En attente 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- d'équipements /mobilier IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio Resilience prix Envelope 05 02 29 scoalire l'EP NDESHA n LUSAMBO/KANANGA (019) ZR-FSRDC-236501-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,579.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'E.P BAOLONGO/KANANGA (020) ZR-FSRDC-236047-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'EP TSHISUMBU/KANANGA (021) ZR-FSRDC-236389-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'EP DIKU DIETU/KANANGA (022) ZR-FSRDC-236048-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'EP DIAKAJA/KANANGA (023) ZR-FSRDC-236058-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'E.P TUYA KUMPALA/KANANGA (024) ZR-FSRDC-236393-GO- En attente RFQ / Fourniture 1. Support to Community Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,600.00 0.00 d'exécutio d'équipements /mobilier Resilience prix Envelope 05 02 29 n scoalire l'EP SANKAYI/KANANGA (025) ZR-FSRDC-236153-GO- En attente RFQ / Fourniture 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Limited 12,285.00 0.00 d'exécutio d'équipements /mobilier Employment Generation prix Envelope 05 02 29 n scolaire EP Dikongayi 2/KANANGA ZR-FSRDC-236077-GO- RFQ / Fourniture des kits de En attente lavage des mains dans le 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 2,500.00 0.00 d'exécutio cadre de la mise en œuvre Employment Generation prix Envelope 30 25 21 n de chantiers de THIMO à Gbadolite et à Mbayi Mbongo/NU ZR-FSRDC-236142-GO- RFQ / Fourniture des kits médicaux dans le cadre de En attente la mise en œuvre de 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 4,776.25 0.00 d'exécutio chantiers de THIMO / « Employment Generation prix Envelope 30 25 21 n CASH FOR WORK » à Gbadolite (quartiers Lite, Kaya, Pangoma, Mowanda et Mbanza)/NU Page 3 ZR-FSRDC-236362-GO- RFQ / Fourniture des panneaux de mécanismes de gestion des plaintes dans En attente le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 4,020.00 0.00 d'exécutio œuvre des activités de la Employment Generation prix Envelope 27 22 18 n composante 1 (infrastructures) et de composante 2 (THIMO) dans la ville de Gbadolite et territoire de Mobayi Mbongo_ NU ZR-FSRDC-236322-GO- RFQ / Acquisition des outillages complémentaires En attente dans le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 9,550.00 0.00 d'exécutio œuvre de chantiers de Employment Generation prix Envelope 03 29 25 n THIMO / « CASH FOR WORK » à Gbadolite (quartiers Lite, Kaya, Pangoma, Mowanda et Mbanza)/NU ZR-FSRDC-236318-GO- RFQ / Acquisition des outillages complémentaires dans le cadre de la mise en En attente 2. Livelihoods and Demande de Single Stage - One 2021-04- 2021-05- 2021-11- œuvre de chantiers de IDA / 66650 A posteriori Limited 12,320.00 0.00 d'exécutio Employment Generation prix Envelope 03 29 25 THIMO / « CASH FOR WORK n » à Gbadolite (quartiers Molegbe, Fadu, Gobele, Gbau, Bakpa, Kawele et Fiwa)/NU ZR-FSRDC-236145-GO- RFQ / Fourniture des masques faciaux en tissus réutilisable dans le cadre de En attente 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- la mise en œuvre de IDA / 66650 A posteriori Limited 3,937.50 0.00 d'exécutio Employment Generation prix Envelope 30 25 21 chantiers de travaux à haute n intensité de main d’œuvre (THIMO) / « CASH FOR WORK » à Gbadolite et Mobayi Mbongo. ZR-FSRDC-236081-GO- RFQ / Fourniture de la En attente 2. Livelihoods and Demande de Single Stage - One 2021-04- 2021-06- 2021-12- limonite dans les 27 Sous IDA / 66650 A posteriori Limited 46,200.00 0.00 d'exécutio Employment Generation prix Envelope 18 13 10 projets de la ville de n Kananga en Lot unique /KNGA MOF-REF-75 / Acquisition des EPI complémentaires En attente dans le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Limited 3,167.50 0.00 d'exécutio œuvre de 5 chantiers de Employment Generation prix Envelope 18 13 10 n THIMO « cash for work » à Kananga / KNGA ZR-FSRDC-236147-GO- RFQ / Acquisition des EPI En attente complémentaires dans le 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 3,816.00 0.00 d'exécutio cadre de la mise en œuvre Employment Generation prix Envelope 16 11 07 n de 6 chantiers de THIMO « cash for work » à Kananga / KNGA ZR-FSRDC-236320-GO- RFQ / Acquisition des EPI En attente complémentaires dans le 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 5,625.00 0.00 d'exécutio cadre de la mise en œuvre Employment Generation prix Envelope 16 11 07 n de 6 chantiers de THIMO « cash for work » à Kananga / KNGA ZR-FSRDC-236516-GO- RFQ / Acquisition des EPI En attente 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- dans le cadre de la mise en IDA / 66650 A posteriori Limited 4,269.00 0.00 d'exécutio Employment Generation prix Envelope 16 11 07 œuvre de 9 chantiers de n THIMO « cash for work » 0 Kanaga/KNGA ZR-FSRDC-236323-GO- En attente RFQ / Acquisition outillage 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Limited 6,564.00 0.00 d'exécutio suplementaire ( Nganza sud, Employment Generation prix Envelope 10 07 04 n sukisa) ZR-FSRDC-236547-GO- En attente RFQ / Acquisition outillage 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Limited 6,640.00 0.00 d'exécutio suplementaire ( Employment Generation prix Envelope 10 07 04 n Mabondo,Itabayi) ZR-FSRDC-236539-GO- En attente RFQ / Acquisition outillage 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Limited 5,457.50 0.00 d'exécutio suplementaire ( Kamilabi, Employment Generation prix Envelope 10 07 04 n malanji) ZR-FSRDC-236540-GO- En attente RFQ / Acquisition outillage 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Limited 4,279.80 0.00 d'exécutio suplementaire ( Mpokolo, Employment Generation prix Envelope 10 07 04 n tukombe) ZR-FSRDC-236326-GO- En attente 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- RFQ / Acquisition Panneaux IDA / 66650 A posteriori Limited 3,510.00 0.00 d'exécutio Employment Generation prix Envelope 10 07 04 de signalisation ( Nganza, n sukisa) ZR-FSRDC-236328-GO- En attente RFQ / Acquisition Panneaux 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Limited 5,832.00 0.00 d'exécutio de signalisation ( Employment Generation prix Envelope 10 07 04 n Kamilabi,malanji) ZR-FSRDC-236397-GO- En attente RFQ / Acquisition Panneaux 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Limited 3,462.00 0.00 d'exécutio de signalisation ( Mabondo, Employment Generation prix Envelope 10 07 04 n itabayi) ZR-FSRDC-236329-GO- En attente RFQ / Acquisition Panneaux 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Limited 3,480.00 0.00 d'exécutio de signalisation ( Mpokolo, Employment Generation prix Envelope 10 07 04 n tukombe) ZR-FSRDC-236551-GO- En attente RFQ / Acquisition de trois Demande de Single Stage - One 2021-03- 2021-04- 2021-10- IDA / 66650 4. Project Management A posteriori Limited 146,950.00 0.00 d'exécutio véhicules automobiles 4x4 prix Envelope 02 27 24 n pour le projet STEP II ZR-FSRDC-236847-GO- Demande de Single Stage - One 2021-07- 2021-07- 2021-07- 2021-11- 2021-09- 2021-08- 2021-10- 2021-09- 2021-11- 2021-10- 2022-11- RFQ / Fourniture de bureau IDA / 66650 4. Project Management A posteriori Limited 40,000.00 3,660.00 Signé prix Envelope 26 16 31 27 11 09 11 21 15 11 15 et consommable informatique ZR-FSRDC-220580-GO- En cours RFQ / Acquisition de Demande de Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 66650 4. Project Management A posteriori Limited 30,000.00 0.00 d'exécutio matériels informatiques prix Envelope 24 21 18 n pour le staff du projet STEP II ZR-FSRDC-223099-GO- RFQ / Acquisition d’équipements de protection individuelle dans En attente le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 50,000.00 0.00 d'exécutio œuvre de chantiers de Employment Generation prix Envelope 13 08 04 n travaux à haute intensité de main d’œuvre (Thimo) « cash for work » à Mobayi mbongo (quartiers Ngonda, Mune, Nziamba, et Kumbu) ZR-FSRDC-223086-GO- RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en En attente œuvre de chantiers de 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 40,000.00 0.00 d'exécutio travaux à haute intensité de Employment Generation prix Envelope 13 08 04 n main d’œuvre (Thimo) « cash for work » a Gbadolite (quartiers Molegbe, Fadu, Gobele, Gbau, Bakpa, Kawele et Fiwa). ZR-FSRDC-223095-GO- RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en En attente 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- œuvre de chantiers de IDA / 66650 A posteriori Limited 40,000.00 0.00 d'exécutio Employment Generation prix Envelope 13 08 04 travaux à haute intensité de n main d’œuvre (Thimo) « cash for work » à Gbadolite (quartiers Nganza, Kambo, Tudu, et Bambu) ZR-FSRDC-49338-GO-RFQ / Acquisition de 50 tablettes 1. Support to Community Demande de Single Stage - One 2018-02- 2018-04- 2018-10- IDA / 57510 A posteriori Limited 25,000.00 0.00 Annulé pour MIS de Kalemie et Resilience prix Envelope 10 07 04 filières agricoles ZR-FSRDC-223080-GO- RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en En attente œuvre de chantiers de 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 40,000.00 0.00 d'exécutio travaux à haute intensité de Employment Generation prix Envelope 13 08 04 n main d’œuvre (Thimo) « cash for work » à Gbadolite (quartiers Kaya, Pangoma, Mbanza, Mowanda et Lite) ZR-FSRDC-223071-GO- RFQ / Acquisition d’équipements de protection individuelle dans En attente le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 50,000.00 0.00 d'exécutio œuvre de chantiers de Employment Generation prix Envelope 13 08 04 n travaux à Haute Intensité de Main d’Œuvre (THIMO) / « Cash For Work » à Gbadolite (Quartiers Kaya, Pangoma, Mbanza, Mowanda et Lite). ZR-FSRDC-223082-GO- RFQ / Acquisition d’équipements de protection individuelle dans En attente le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 50,000.00 0.00 d'exécutio œuvre de chantiers de Employment Generation prix Envelope 13 08 04 n travaux à haute intensité de main d’œuvre (Thimo) « cash for work » à Gbadolite (quartiers Molegbe, Fadu, Gobele, Gbau, Bakpa, Kawele et Fiwa). ZR-FSRDC-49609-GO-RFQ / Acquisition de 7 groupes motopompes pour Brigade d'entretien -THIMO Demande de Single Stage - One 2018-03- 2018-05- 2018-11- IDA / 57510 3. Capacity Building A posteriori Limited 30,000.00 0.00 Annulé 1) Lot 1: Nord Kivu (2), 2) prix Envelope 12 07 03 Lot 2: Sud Kivu (2), 3) Lot 3: Ituri (1), 4)Lot 4: Haut Uele (1), 5) Lot 5: Tanganyika (1) ZR-FSRDC-120255-GO- RFQ / Acquisition de 8 Demande de Single Stage - One 2019-06- 2019-08- 2020-02- IDA / 57510 3. Capacity Building A posteriori Limited 36,000.00 0.00 Annulé motos pour IPAPEL et prix Envelope 26 21 17 SENASEM pour la province de Tanganyika ZR-FSRDC-223091-GO- RFQ / Acquisition d’équipements de protection individuelle dans En attente le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 50,000.00 0.00 d'exécutio œuvre de chantiers de Employment Generation prix Envelope 13 08 04 n travaux à haute intensité de main d’œuvre (Thimo) « cash for work » à Gbadolite (quartiers Nganza, Kambo, Tudu, et Bambu) ZR-FSRDC-228078-GO- RFQ / Acquisition de deux générateurs de 20 KVA pour Demande de Single Stage - One 2021-04- 2021-05- 2021-06- 2021-07- 2021-12- IDA / 66650 4. Project Management A posteriori Limited 50,000.00 30,628.00 Signé les bâtiments du prix Envelope 17 13 12 16 09 FSRDC/Antennes du Nord Ubangi et Kasaï Central ZR-FSRDC-223142-GO- RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en En attente œuvre de chantiers de 2. Livelihoods and Demande de Single Stage - One 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Limited 40,000.00 0.00 d'exécutio travaux à haute intensité de Employment Generation prix Envelope 13 08 04 n main d’œuvre (Thimo) « cash for work » à Mobayi mbongo (quartiers Ngonda, Mune, Nziamba, et Kumbu) ZR-FSRDC-120248-GO- RFQ / Acquisition de 2 Demande de Single Stage - One 2019-06- 2019-08- 2020-02- Véhicules 4 X 4 cinq portes IDA / 57510 3. Capacity Building A posteriori Limited 100,000.00 0.00 Annulé prix Envelope 27 22 18 pour IPAPEL et SENASEM pour la province de Tanganyika ZR-FSRDC-121711-GO- RFQ / Acquisition de trois (3) appareils Topographique Demande de Single Stage - One 2019-07- 2019-09- 2020-03- IDA / 57510 3. Capacity Building A posteriori Limited 50,000.00 0.00 Annulé Station Totale pour OVD prix Envelope 18 12 10 dans les provinces de Tshopo, Ituri et Tanganyika ZR-FSRDC-49229-GO-RFQ / Acquisition de 5 vehicules additionnelles pour les Demande de Single Stage - One 2018-03- 2018-04- 2018-10- partenaires institutionnelles IDA / 57510 3. Capacity Building A posteriori Limited 225,000.00 0.00 Annulé prix Envelope 05 30 27 (OVD Bunia 1,OVD Kisangani 1, OVD Bukavu 1 OVD Kalemie 1 et OVD Nord Kivu) ZR-FSRDC-49623-GO-RFQ / Acquisition de 36 motos - pour OVD (10) et Carg (26) 1) Lot 1: Nord Kivu (9), Demande de Single Stage - One 2018-03- 2018-05- 2018-11- IDA / 57510 3. Capacity Building A posteriori Limited 90,000.00 0.00 Annulé 2) Lot 2: Sud Kivu (9), 3) prix Envelope 10 05 01 Lot 3: Ituri (9), 4)Lot 4: Haut Uele (5), 5) Lot 5: Tanganyika (2) et 6) Lot 6: Tshopo (2) ZR-FSRDC-51040-GO-RFB / Acquisition de 6 Kits pour Single Stage - One 2018-03- 2018-03- 2018-04- 2018-05- 2018-06- 2018-12- IDA / 57510 3. Capacity Building A posteriori Appel d'offres Open - National 120,000.00 0.00 Annulé Mini-LABOSEM physique Envelope 07 12 23 23 27 24 dans un corridor ZR-FSRDC-49377-GO-RFQ / Acquisition de 14 tronçonneuses pour Brigade d'entretien -THIMO: 1) Lot Demande de Single Stage - One 2018-03- 2018-05- 2018-10- IDA / 57510 3. Capacity Building A posteriori Limited 38,000.00 0.00 Annulé 1: Nord Kivu (4); 2) Lot 2: prix Envelope 06 01 28 Sud Kivu (4); 3) Lot 3; Ituri (2); 4)Lot 4: Haut Uele (2)); 5) Lot 5: Tanganyika (2) ZR-FSRDC-49335-GO-RFQ / Acquisition de 10 compacteurs manuels pour Brigade d'entretien -THIMO Demande de Single Stage - One 2018-03- 2018-05- 2018-04- 2018-10- - OVD IDA / 57510 3. Capacity Building A posteriori Limited 140,000.00 0.00 Annulé prix Envelope 05 03 30 27 1) Lot 1: Nord Kivu (2), 2) Lot 2: Sud Kivu (2), 3) Lot 3: Ituri (2), 4)Lot 4: Tshopo (2), 5) Lot 5: Tanganyika (2) ZR-FSRDC-239840-GO- RFQ / Fourniture En attente d'équipements/mobiliers 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Limited 39,000.00 0.00 d'exécutio scolaires pour l'EP BISHIYA, Resilience prix Envelope 06 01 30 n l'EP MUAKAJI et l'EP1 DIBANDA du secteur de DIBANDA_KC ZR-FSRDC-239842-GO- RFQ / Fourniture d'équipements/mobiliers En attente 1. Support to Community Demande de Single Stage - One 2021-09- 2021-10- 2022-04- scolaires pour l'EP NDIBU IDA / 66650 A posteriori Limited 39,000.00 0.00 d'exécutio Resilience prix Envelope 05 31 29 KALAMBA, l'EP LUAJA et l'EP n LUKULA du secteur de KASANGIDI_KC ZR-FSRDC-239843-GO- RFQ / Fourniture d'équipements/mobiliers En attente scolaires pour l'EP1 1. Support to Community Demande de Single Stage - One 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Limited 52,000.00 0.00 d'exécutio BASANGA, l'EP NTUADIJILU, Resilience prix Envelope 05 31 29 n l'EP MAMBASAKO et l'EP TSHIMAKAKA du secteur KASANGIDI_KC ZR-FSRDC-243750-GO- RFQ / Fourniture des En attente 1. Support to Community Demande de Single Stage - One 2021-08- 2021-10- 2022-04- mobiliers pour les EP IDA / 66650 A posteriori Limited 45,000.00 0.00 d'exécutio Resilience prix Envelope 14 09 07 BISHIYA, EP MUAKAJI et EP1 n DIBANDA dans le secteur de DIBANDA ZR-FSRDC-243758-GO- RFQ / Fourniture des mobiliers pour les EP NDIBU En attente KALAMBA, EP LUAJA, EP3 1. Support to Community Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 A posteriori Limited 105,000.00 0.00 d'exécutio LUKULA, EP1 BASANGA, EP Resilience prix Envelope 21 16 14 n NTUADIJILU, EP MAMBASAKO et EP TSHIMAKAKA dans le secteur de KASANGIDI ZR-FSRDC-244020-GO- RFQ / Acquisition des En attente Fournitures et Equipements 1. Support to Community Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 A posteriori Limited 20,000.00 0.00 d'exécutio médicaux pour l’Hôpital Resilience prix Envelope 21 16 14 n Général du quartier de LUKONGA de la ville de Kananga ZR-FSRDC-244050-GO- RFQ / Achat Kit de recrutement des bénéficiaires THIMO de En attente 2. Livelihoods and Demande de Single Stage - One 2021-08- 2021-10- 2022-04- l’antenne de IDA / 66650 A posteriori Limited 30,000.00 0.00 d'exécutio Employment Generation prix Envelope 21 16 14 Kananga/Dibaya et n Kananga/Tshimbulu (tables, chaises, agrafeuses ciseaux, bâches seau en plastique, rame papiers, cartouches, bande de sécurité….) Page 4 ZR-FSRDC-244054-GO- RFQ / Fourniture de la limonite pour les Chantiers THIMO de la ville de En attente 2. Livelihoods and Demande de Single Stage - One 2021-08- 2021-10- 2022-04- Kananga et des Cités de IDA / 66650 A posteriori Limited 100,000.00 0.00 d'exécutio Employment Generation prix Envelope 21 16 14 Tshimbulu et Dibaya, n Lot1 : 27 chantiers de Kananga et Lot 2 : 11 chantiers de Tshimbulu et Dibaya ZR-FSRDC-244077-GO- RFQ / Achat des Kits En attente Médicaux pour les 2. Livelihoods and Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 A posteriori Limited 100,000.00 0.00 d'exécutio bénéficiaires THIMO de la Employment Generation prix Envelope 21 16 14 n ville de Kananga/Phase2 et des cités de Dibaya et Tshimbulu ZR-FSRDC-244079-GO- RFQ / Acquisition des pelouses et des fleurs pour En attente 2. Livelihoods and Demande de Single Stage - One 2021-08- 2021-10- 2022-04- l'embellissement des IDA / 66650 A posteriori Limited 9,000.00 0.00 d'exécutio Employment Generation prix Envelope 21 16 14 grandes artères de la ville n de Gbadolite (Terre-plein central et autres places publiques) ZR-FSRDC-244110-GO- RFQ / Acquisition des En attente équipements de bureaux et Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Limited 20,000.00 0.00 d'exécutio matériels informatiques prix Envelope 21 16 14 n pour les bureaux de Tshimbulu et Dibaya ZR-FSRDC-244134-GO- RFQ / Acquisition et En attente installation d’un mini Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Limited 25,000.00 0.00 d'exécutio central (PABX) téléphonique prix Envelope 21 16 14 n interne du bureau de l’antenne du FSRDC Nord Ubangi ZR-FSRDC-244135-GO- RFQ / Acquisition et En attente installation de six (6) Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Limited 5,000.00 0.00 d'exécutio climatiseurs prix Envelope 21 16 14 n complémentaires dans les bureaux de l'antenne du FSRDC Nord Ubangi ZR-FSRDC-244139-GO- RFQ / Acquisition de onze Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Limited 3,300.00 0.00 Annulé (11) Tablettes enquêteurs prix Envelope 21 16 14 pour YAKOMA ZR-FSRDC-244164-GO- RFQ / Acquisition de vingt Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Limited 6,000.00 0.00 Annulé (20) tablettes pour les prix Envelope 21 16 14 enquêteurs de GOMA ZR-FSRDC-244198-GO- RFQ / Acquisition de Demande de Single Stage - One 2021-08- 2021-10- 2022-04- quarante un (41) tablettes IDA / 66650 4. Project Management A posteriori Limited 12,300.00 0.00 Annulé prix Envelope 21 16 14 pour les enquêteurs pour BUKAVU et UVIRA ZR-FSRDC-244224-GO- RFQ / Acquisition vingt neuf Demande de Single Stage - One 2021-08- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Limited 8,700.00 0.00 Annulé (29) tablettes enquêteurs prix Envelope 21 16 14 pour BUNIA ZR-FSRDC-251678-GO- RFQ / Acquisition de 97 kits smartphones pour le Suivi- 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-09- 2021-11- 2021-10- 2022-05- Evaluation et le Transfert IDA / 66650 A posteriori Limited 34,000.00 38,315.00 Signé Employment Generation prix Envelope 11 08 06 19 05 Monétaire Inconditionnel pour le Nord Ubangi, Kasaï Central et Sud Kivu. ZR-FSRDC-251682-GO- RFQ / Acquisition de matériels informations pour le TMI, en deux lots. Lot 1: 4 imprimantes, 67 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-09- 2021-11- 2021-10- 2022-05- rubans d'impression, 22 IDA / 66650 A posteriori Limited 30,000.00 20,115.00 Signé Employment Generation prix Envelope 11 08 06 19 05 cartes vierges PVC, 20 kits de nettoyage et 4 logiciels d'impression de badges Lot 2: 10 kits tablettes et 4 ordinateurs portables ZR-FSRDC-252513-GO- RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en En attente 2. Livelihoods and Demande de Single Stage - One 2021-11- 2021-12- 2022-06- œuvre des chantiers IDA / 66650 A posteriori Limited 200,000.00 0.00 d'exécutio Employment Generation prix Envelope 03 29 27 THIMO/cash for work dans n la ville de Bukavu: - Lot 1: Commune d'Ibanda - Lot 2: Commune de Kadutu - Lot 3: Commune de Bagira ZR-FSRDC-252525-GO- RFQ / Acquisition des équipements de protection individuelle (EPI) dans le En attente cadre de mise en œuvre des 2. Livelihoods and Demande de Single Stage - One 2021-11- 2021-12- 2022-06- IDA / 66650 A posteriori Limited 200,000.00 0.00 d'exécutio chantiers Thimo/cash for Employment Generation prix Envelope 03 29 27 n work dans la ville de Bukavu: - Lot 1 : commune d’Ibanda - Lot 2 : commune de Kadutu - Lot 3 : Commune de ZR-FSRDC-232729-GO- Bagira RFQ / Acquisition de 6 véhicules 4x4 munis Demande de Single Stage - One 2021-07- 2021-06- 2021-09- 2021-08- 2022-03- IDA / 66650 4. Project Management A posteriori Limited 390,000.00 381,854.30 Signé d'équipement de prix Envelope 20 01 14 03 13 communication pour les antennes du Nord-Ubangi et Kasaï Central ZR-FSRDC-257629-GO- RFQ / (1): Acquisition des En attente 2. Livelihoods and Demande de Single Stage - One 2021-11- 2022-01- 2022-07- sacs vides pour 38 chantiers IDA / 66650 A posteriori Limited 46,000.00 0.00 d'exécutio Employment Generation prix Envelope 20 15 14 THIMO de Tshimbulu, n Dibaya et Kananga phase 2 ZR-FSRDC-257637-GO- RFQ / (2): Fourniture de la En attente 2. Livelihoods and Demande de Single Stage - One 2021-11- 2022-01- 2022-07- limonite dans les 11 IDA / 66650 A posteriori Limited 150,000.00 0.00 d'exécutio Employment Generation prix Envelope 20 15 14 chantiers THIMO de la ville n de Tshimbulu et Dibaya, en lot unique. ZR-FSRDC-257639-GO- RFQ / (3): Fourniture de la En attente 2. Livelihoods and Demande de Single Stage - One 2021-11- 2022-01- 2022-07- limonite dans les 27 IDA / 66650 A posteriori Limited 300,000.00 0.00 d'exécutio Employment Generation prix Envelope 20 15 14 chantiers THIMO de la ville n de Kananga, en lot unique ZR-FSRDC-257640-GO- RFQ / (5): Acquisition des vétivers, pelouse et En attente 2. Livelihoods and Demande de Single Stage - One 2021-11- 2022-01- 2022-07- bambous, fleur pour IDA / 66650 A posteriori Limited 190,000.00 0.00 d'exécutio Employment Generation prix Envelope 20 15 14 l'embellissement de la ville n pour 38 chantiers THIMO de Tshimbulu, Dibaya et Kananga phase 2 ZR-FSRDC-262033-GO- RFQ / (2): Acquisition des fournitures et Kits de recrutement de Bénéficiaires En attente 2. Livelihoods and Demande de Single Stage - One 2021-12- 2022-02- 2022-08- dans cadre de la mise en IDA / 66650 A posteriori Limited 20,000.00 0.00 d'exécutio Employment Generation prix Envelope 29 23 22 œuvre de 20 chantiers de n travaux à haute intensité de la main d’œuvre dans 20 quartiers de Bukavu ZR-FSRDC-262039-GO- RFQ / (3): Acquisition des 420 panneaux de En attente signalisation de 20 2. Livelihoods and Demande de Single Stage - One 2022-01- 2022-03- 2022-08- IDA / 66650 A posteriori Limited 10,000.00 0.00 d'exécutio chantiers dans le cadre de la Employment Generation prix Envelope 04 01 28 n mise en œuvre de chantiers de travaux à haute intensité de la main d’œuvre dans les quartiers de la ville de Bukavu ZR-FSRDC-262040-GO- RFQ / (4): Acquisition de 40 panneaux métalliques pour le mécanisme de gestion En cours des plaintes dans le cadre 2. Livelihoods and Demande de Single Stage - One 2022-01- 2022-03- 2022-08- IDA / 66650 A posteriori Limited 10,000.00 0.00 d'exécutio de la mise en œuvre de 20 Employment Generation prix Envelope 04 01 28 n chantiers de travaux à haute intensité de la main d’œuvre dans les quartiers des communes de la ville de Bukavu ZR-FSRDC-262042-GO- RFQ / (5): Acquisition des fournitures de bureau pour En attente l’installation de 20 chantiers 2. Livelihoods and Demande de Single Stage - One 2022-01- 2022-03- 2022-08- IDA / 66650 A posteriori Limited 10,000.00 0.00 d'exécutio dans cadre de la mise en Employment Generation prix Envelope 04 01 28 n œuvre de chantier de travaux à haute intensité de la main d’œuvre à Bukavu ZR-FSRDC-262045-GO- RFQ / (6): Acquisition des Kits médicaux d’urgence En attente 2. Livelihoods and Demande de Single Stage - One 2022-01- 2022-03- 2022-08- dans le cadre de la mise en IDA / 66650 A posteriori Limited 30,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 01 28 œuvre de 20 chantiers de n travaux à haute intensité de la main d’œuvre à Bukavu ZR-FSRDC-264827-GO- RFQ / (12): Acquisition et En attente 1. Support to Community Demande de Single Stage - One 2022-03- 2022-05- 2022-11- livraison des équipements IDA / 66650 A posteriori Limited 112,500.00 0.00 d'exécutio Resilience prix Envelope 19 14 10 médicaux pour 9 centres de n santé dans deux secteurs au Kasaï Central ZR-FSRDC-244093-GO- RFQ / Acquisition des mobiliers de bureau pour le STEP II Demande de Single Stage - One 2021-08- 2021-10- 2022-04- Lot 1 : Coordination IDA / 66650 4. Project Management A posteriori Limited 300,000.00 0.00 Annulé prix Envelope 21 16 14 générale Lot 2 : Kasaï Central Lot 3 : Nord Ubangi Lot 4 : Nord Kivu Lot 5 : Sud Kivu Lot 6 : Ituri ZR-FSRDC-264841-GO- En attente RFQ / (19): Acquisition de Demande de Single Stage - One 2022-03- 2022-05- 2022-11- IDA / 66650 4. Project Management A posteriori Limited 45,000.00 0.00 d'exécutio mobiliers de bureau pour la prix Envelope 15 10 06 n province du Kasaï Central ZR-FSRDC-253625-GO- RFQ / Acquisition de 5 Demande de Single Stage - One 2021-12- 2022-01- 2022-07- véhicules 4x4 munis IDA / 66650 4. Project Management A posteriori Limited 320,000.00 0.00 Annulé prix Envelope 04 29 28 d'équipement de communication pour l'antenne du Sud-Kivu et Yakoma ZR-FSRDC-264842-GO- RFQ / (20): Acquisition de 19 véhicules 4x4 munis d’équipements de communication : - Lot 1 : 5 véhicules pour le En attente Demande de Single Stage - One 2022-03- 2022-05- 2022-11- SK IDA / 66650 4. Project Management A posteriori Limited 950,000.00 0.00 d'exécutio prix Envelope 21 16 12 - Lot 2 : 5 véhicules pour le n NK - Lot 3 : 5 véhicules pour It - Lot 4 : 2 véhicules pour le NU - Lot 5: 2 véhicules pour le KC ZR-FSRDC-264845-GO- En attente RFQ / (21): Acquisition de Demande de Single Stage - One 2022-03- 2022-05- 2022-11- IDA / 66650 4. Project Management A posteriori Limited 75,000.00 0.00 d'exécutio mobiliers de bureau pour la prix Envelope 15 10 06 n Coordination Générale ZR-FSRDC-264846-GO- En attente RFQ / (22): Acquisition de Demande de Single Stage - One 2022-04- 2022-06- 2022-12- IDA / 66650 4. Project Management A posteriori Limited 45,000.00 0.00 d'exécutio mobiliers de bureau pour la prix Envelope 19 14 11 n province du Sud-Kivu ZR-FSRDC-264847-GO- En attente RFQ / (48): Acquisition de Demande de Single Stage - One 2021-12- 2022-02- 2022-08- IDA / 66650 4. Project Management A posteriori Limited 45,000.00 0.00 d'exécutio mobiliers de bureau pour la prix Envelope 29 23 22 n province du Nord-Ubangi ZR-FSRDC-267055-GO- En attente 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- RFQ / (23): Fourniture des IDA / 66650 A posteriori Limited 14,922.00 0.00 d'exécutio Resilience prix Envelope 06 01 30 Equipements de l'EP Sœur n LEA ZR-FSRDC-267031-GO- En attente RFQ / (24): Fourniture des 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Limited 14,898.00 0.00 d'exécutio Equipements de l'EP MOTO Resilience prix Envelope 06 01 30 n MONENE ZR-FSRDC-267053-GO- En attente RFQ / (25): Fourniture des 1. Support to Community Demande de Single Stage - One 2021-12- 2022-02- 2022-07- IDA / 66650 A posteriori Limited 23,730.00 0.00 d'exécutio Equipements du Centre de Resilience prix Envelope 07 01 31 n santé de Référence de la Cité ZR-FSRDC-267006-GO- En attente 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- RFQ / (26): Fourniture des IDA / 66650 A posteriori Limited 14,910.00 0.00 d'exécutio Resilience prix Envelope 06 01 30 Equipements de l'EP n KOLOKE ZR-FSRDC-267052-GO- En attente RFQ / (27): Fourniture des 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Limited 14,922.00 0.00 d'exécutio Equipements de l'EP NDAYO Resilience prix Envelope 06 01 30 n GEREMBA ZR-FSRDC-267018-GO- En attente RFQ / (28): Fourniture des 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Limited 14,880.00 0.00 d'exécutio Equipements de l'EP Sœur Resilience prix Envelope 06 01 30 n ANTONY ZR-FSRDC-266985-GO- En attente RFQ / (29): Fourniture des 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Limited 14,910.00 0.00 d'exécutio Equipements de l'EP NZOYE Resilience prix Envelope 06 01 30 n MATA ZR-FSRDC-267019-GO- En attente RFQ / (30): Fourniture des 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Limited 14,805.00 0.00 d'exécutio Equipements de l'EP NGBASE Resilience prix Envelope 06 01 30 n KANZA ZR-FSRDC-267000-GO- En attente 1. Support to Community Demande de Single Stage - One 2021-09- 2021-11- 2022-04- RFQ / (31): Fourniture des IDA / 66650 A posteriori Limited 14,820.00 0.00 d'exécutio Resilience prix Envelope 06 01 30 Equipements de l'EP n BASAKOLI ZR-FSRDC-267013-GO- RFQ / (32): Acquisition DES PANNEAUX DE SIGNALISATION DES CHANTIERS DANS LE CADRE En attente DE LA MISE EN ŒUVRE DE 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-11- 2022-05- IDA / 66650 A posteriori Limited 3,150.00 0.00 d'exécutio CHANTIERS DE THIMO DANS Employment Generation prix Envelope 09 04 03 n LES QUARTIERS SOROZO, YAMINGU, YAKOMA, ZABO, UBANGI, UELE, WAKWA, ANCIEN COMBATTANT ET NZEWE DANS LA CITE DE YAKOMA ZR-FSRDC-267030-GO- RFQ / (33): ACQUISITION DE 18 PANNEAUX METALLIQUES POUR LE MECANISME DE En attente GESTION DES PLAINTES 2. Livelihoods and Demande de Single Stage - One 2021-10- 2021-12- 2022-06- IDA / 66650 A posteriori Limited 4,400.00 0.00 d'exécutio DANS LE CADRE DE LA MISE Employment Generation prix Envelope 09 04 02 n EN ŒUVRE DE CHANTIERS DE THIMO DANS LES QUARTIERS DE LA CITE DE YAKOMA EN TERRITOIRE DE YAKOMA ZR-FSRDC-264826-GO- RFQ / (11): Acquisition des éqpts scolaires pr 17 EP dans 2 secteurs au KC, en 4 lots: Lot1:EP Ntenda,Milayi,Lutambi,Mofu En attente ayi,Bena Kazadi 1. Support to Community Demande de Single Stage - One 2022-03- 2022-05- 2022-11- IDA / 66650 A posteriori Limited 212,500.00 0.00 d'exécutio Lot2:EP Resilience prix Envelope 23 18 14 n Mbondo,Lusambi,Tudiku,Sa nkayi Lot3:EP Kapiku,Mpunga,Tudilame,Ka fudu Lot4:EP Kabonge,Kanuamayi,Dibatay i,Tshitokololo ZR-FSRDC-272205-GO- RFQ / (26):Acq. EPI- chantiers THIMO/Bunia : Lot1:Q/Lembabo,Muzi- pela,Bigo,Kasegwa,Simbiliab o,Bembey,Ndiba kodu En cours 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- Lot2:Q/Ngezi,Lumumba,Bak IDA / 66650 A posteriori Limited 260,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 30 26 ongolo,Yambi n yaya,Hoho,Opas,Bankoko,De le Lot3:Q/NyakasanzaI et II,Saio,Rwankole,Kindiya,Sal ongo,Sukisa,Rwambuzi F.,Rwambuzi B. ZR-FSRDC-272213-GO- RFQ / (27):Acq. outillage- chantiers THIMO/Bunia : Lot1:Q/Lembabo,Muzi- p.,Bigo,Kasegwa,Simbiliabo, Bembey,Ndiba k. En cours 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- Lot2:Q/Ngezi,Lumumba,Bak IDA / 66650 A posteriori Limited 260,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 30 26 ongolo,Yambi n y.,Hoho,Opas,Bankoko,Dele Lot3:Q/NyakasanzaI et II,Saio,Rwankole,Kindiya,Sal ongo,Sukisa,Rwambuzi F.,Rwambuzi B. Page 5 ZR-FSRDC-272322-GO- RFQ / (58):Acquisition EPI ds le cadre de la mise en œuvre des chantiers THIMO à Goma: Lot1:Q/Les En attente 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- volcans,Himbi,Keyshero,Lac IDA / 66650 A posteriori Limited 200,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 30 26 Vert,Mapendo,Murara,Miken n o,Katindo gauche Lot2:Q/Bujovu,Majengo droite,Ndosho,Kayembe,Ma banga sud,Mabanga Nord,Kasika,Mugunga et Virunga ZR-FSRDC-272327-GO- RFQ / (59):Acquisition Outillages - chantiers THIMO à Goma: Lot1:Q/Les En attente volcans,Himbi,Keyshero,Lac 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Limited 200,000.00 0.00 d'exécutio Vert,Mapendo,Murara,Miken Employment Generation prix Envelope 04 30 26 n o,Katindo gauche Lot2:Q/Bujovu,Majengo droite,Ndosho,Kayembe,Ma banga sud,Mabanga Nord,Kasika,Mugunga et Virunga ZR-FSRDC-274087-GO- RFQ / (26) Acquisition des panneaux (24 grands En cours panneaux indicatifs et 480 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Limited 26,712.00 0.00 d'exécutio petits panneaux attention Employment Generation prix Envelope 04 30 26 n travaux, soit 504 panneaux) de signalisation des chantiers de THIMO à Bunia - ITURI ZR-FSRDC-274088-GO- RFQ / (33) Acquisition des fournitures des bureaux pour les bureaux des En cours 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- chantiers ( installation des IDA / 66650 A posteriori Limited 7,200.00 0.00 d'exécutio Employment Generation prix Envelope 04 30 26 chantiers) dans le cadre de n la mise en oeuvre de chantier de travaux à haute intensite de la main d’oeuvre à Bunia_ ITURI ZR-FSRDC-274089-GO- RFQ / (31) Acquisition des 240 kits de lavage des mains pour les beneficaires En cours 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- dans le cadre de la mise en IDA / 66650 A posteriori Limited 36,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 30 26 œuvre de chantiers de n travaux à haute intensite de la main d’œuvre dans les 24 quartiers de la ville de Bunia _ ITURI ZR-FSRDC-274090-GO- RFQ / (35) Fourniture des matériaux de construction pour la construction/réhabilitation En attente des petits ouvrages (ponts, 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Limited 105,000.00 0.00 d'exécutio ponceaux, dalots, buses, Employment Generation prix Envelope 04 30 26 n passerelles, etc). Lot 1 : (Quartiers Lembabo, Muzi-pela, Bigo, Kasegwa, Simbiliabo, Bembey, Ndiba kodu)_ ITURI ZR-FSRDC-274091-GO- RFQ / (36) Fourniture des matériaux de construction pour la construction/réhabilitation En attente des petits ouvrages (ponts, 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Limited 120,000.00 0.00 d'exécutio ponceaux, dalots, buses, Employment Generation prix Envelope 04 30 26 n passerelles, etc). lot 2 : (Quartiers Ngezi, Lumumba, Bakongolo, Yambi yaya, Hoho, Opas, Bankoko, Dele)- ITURI ZR-FSRDC-274092-GO- RFQ / (37) Fourniture des matériaux de construction pour la construction/réhabilitation En attente des petits ouvrages (ponts, 2. Livelihoods and Demande de Single Stage - One 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Limited 135,000.00 0.00 d'exécutio ponceaux, dalots, buses, Employment Generation prix Envelope 04 30 26 n passerelles, etc). lot 3: (Quartiers Nyakasanza I, Nyakasanza II, Saio, Rwankole, Kindiya, Salongo, Sukisa _ ITURI ZR-FSRDC-274099-GO- RFQ / (60) Acquisition des kits 18 médicaux d’urgence En attente dans le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2022-05- 2022-06- 2022-12- IDA / 66650 A posteriori Limited 18,000.00 0.00 d'exécutio œuvre de chantiers de Employment Generation prix Envelope 04 29 26 n travaux à haute intensité de la main d’œuvre à Goma dans la province du Nord Kivu ZR-FSRDC-274101-GO- RFQ / (62) Acquisition de 36 panneaux métalliques pour le mécanisme de gestion des plaintes dans le cadre En attente 2. Livelihoods and Demande de Single Stage - One 2022-05- 2022-06- 2022-12- de la mise en œuvre de 18 IDA / 66650 A posteriori Limited 9,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 29 26 chantiers de travaux à haute n intensité de la main d’œuvre dans les 18 quartiers de la ville de Goma dans la province du Nord Kivu ZR-FSRDC-274102-GO- RFQ / (63) Acquisition des 180 kits de lavage des mains pour les beneficaires En attente dans le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2022-05- 2022-06- 2022-12- IDA / 66650 A posteriori Limited 27,000.00 0.00 d'exécutio œuvre de chantiers de Employment Generation prix Envelope 04 29 26 n travaux à haute intensite de la main d’œuvre dans les 18 quartiers de la ville de Goma dans la province du Nord Kivu ZR-FSRDC-274103-GO- RFQ / (67)Fourniture des scories pour le rechargement des axes dans le cadre des chantiers En attente 2. Livelihoods and Demande de Single Stage - One 2022-05- 2022-06- 2022-12- THIMO à Goma. Répartit en IDA / 66650 A posteriori Limited 180,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 29 26 deux lots n Lot 1 : (Quartiers Les volcans, Himbi, Keyshero, Lac Vert, Mapendo, Murara, Mikeno, Katindo gauche ) lot 2 : (Quartiers Bujovu.. NK ZR-FSRDC-274104-GO- RFQ / (68) Fourniture des pavés avec des pierres volcaniques taillées à poser dans certains tronçons de la En attente 2. Livelihoods and Demande de Single Stage - One 2022-05- 2022-06- 2022-12- ville de Goma. Répartit en IDA / 66650 A posteriori Limited 270,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 29 26 deux lots. n Lot 1 : (Qrts Les volcans, Himbi, Keyshero, Lac V, Mapendo, Murara, Mikeno, Katindo gche ) lot 2 : (Qrts...) NK ZR-FSRDC-274105-GO- RFQ / (39) Fourniture de pelouse pour l’embellissement et protection des accotements En attente 2. Livelihoods and Demande de Single Stage - One 2022-06- 2022-07- 2023-01- dans le cadre des chantiers IDA / 66650 A posteriori Limited 40,000.00 0.00 d'exécutio Employment Generation prix Envelope 04 30 26 THIMO à Bunia dans la n province de l’Ituri. Répartit en trois lots. Lot 1 : (Qrts Lembabo,..Lot 2 (Qrts Ngezi,...) Lot3 (Qrts Nya...)_ ITURI ZR-FSRDC-274106-GO- RFQ / (38) Fourniture des Latérites pour le rechargement des axes dans En attente 2. Livelihoods and Demande de Single Stage - One 2022-06- 2022-07- 2023-01- le cadre des chantiers IDA / 66650 A posteriori Limited 200,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 31 27 THIMO à Bunia. Répartit en n trois lots : Lot 1 : (Qrts Lembabo...) lot 2 : (Quartiers Ngezi, ...) Lot3 (Qrts Nyakasanza... ) _ ITURI ZR-FSRDC-274728-GO- RFQ / (28) Acquisition des kits médicaux d’urgence En cours dans le cadre de la mise en 2. Livelihoods and Demande de Single Stage - One 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Limited 24,000.00 0.00 d'exécutio œuvre de chantiers de Employment Generation prix Envelope 05 30 26 n travaux à haute intensité de la main d’œuvre à Bunia dans la province de l’Ituri. ZR-FSRDC-274729-GO- RFQ / (29) Acquisition des fournitures et kits de recrutement des En cours 2. Livelihoods and Demande de Single Stage - One 2022-07- 2022-08- 2023-02- bénéficiaires dans le cadre IDA / 66650 A posteriori Limited 24,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 26 de la mise en œuvre des n chantiers de travaux à haute intensité de la main d’œuvre à Bunia dans la province de l’Ituri ZR-FSRDC-274741-GO- RFQ / (54) Acquisition des Equipements (Bancs, tables, chaises, Armoires et autres) En attente 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- pour les IDB de 5 quartiers : IDA / 66650 A posteriori Limited 62,500.00 0.00 d'exécutio Resilience prix Envelope 05 30 26 LES VOLCANS, HIMBI, n KEYSHERO, LAC VERT, MAPENDO /Ville de Goma- Nord Kivu ZR-FSRDC-274744-GO- RFQ / (55) Acquisition des Equipements (Bancs, tables, En attente chaises, Armoires et autres) 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Limited 62,500.00 0.00 d'exécutio pour les IDB de 5 quartiers : Resilience prix Envelope 05 30 26 n MURARA, MIKONO, KATINDO, BUJOVU, MAJENGO/ Ville de Goma- Nord Kivu ZR-FSRDC-274746-GO- RFQ / (56) Acquisition des Equipements (Bancs, tables, En attente chaises, Armoires et autres) 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Limited 50,000.00 0.00 d'exécutio pour les IDB de 4 quartiers : Resilience prix Envelope 05 30 26 n KATOYI, NDOSHO, KAHEMBE, MABANGA SUD/ Ville de Goma _ Nord Kivu ZR-FSRDC-274747-GO- RFQ / (57) Acquisition des Equipements (Bancs, tables, En attente chaises, Armoires et autres) 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Limited 50,000.00 0.00 d'exécutio pour les IDB de 4 quartiers : Resilience prix Envelope 05 30 26 n LES MABANGA NORD, KASIKA, MUGUNGA, VIRUNGA /Ville de Goma- Nord Kivu ZR-FSRDC-274777-GO- RFQ / Acquisition des Equipements (Bancs, tables, En attente chaises, Armoires et autres) 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Limited 25,000.00 0.00 d'exécutio pour les IDB de 2 Resilience prix Envelope 05 30 26 n groupements MUNIGI et KIBATI/ Territoire de Nyiragongo ZR-FSRDC-274722-GO- RFQ / (21)Acquisition des Eqpts (Bcs, tabls, chaises, Armrs et autres) IDB de 5 qrts : (LEMBABO, MUZI- En attente 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- PELA, SUKISA, KINDIA et IDA / 66650 A posteriori Limited 62,500.00 0.00 d'exécutio Resilience prix Envelope 05 30 26 SIMBILIABO)-Lot I.1: E.P EP n MUDJUMBE EPAINETO- Lot I.2: E.P 1 BUNIA- Lot I.3: E.P SUKISA - Lot I.4: E.P MWA_ Lot 5 E.P NYAKEZI_ITURI ZR-FSRDC-274724-GO- RFQ / (22) Acquisition ds Eqpts (Bcs, tbls, chaises, Armrs et autres) IDB de 5 qtrs : BEMBEY, LUMUMBA, En attente 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- RWAMBUZI-BENI, SALONGO IDA / 66650 A posteriori Limited 62,500.00 0.00 d'exécutio Resilience prix Envelope 05 30 26 et dans le groupt n BABUCHUKA,Lot1: E.P INGA NIZI- Lot2: E.P.1MURONGO- Lot3: E.P SIMBILYABO,Lot4: E.P4 NYAKASANZA Lot5EP BUNDIKASA_ ITURI ZR-FSRDC-275599-GO- RFQ / (24) Acquisition des Equipements pour les IDB de 5 quartiers : TSERE, En attente LENGABO BABULABA et 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Limited 75,000.00 0.00 d'exécutio BEDU EZEKERE et SALONGO Resilience prix Envelope 05 30 26 n -Lot1: EP. MAKI MBUDHA- Lot2: EP. MBUNYA-Lot 3: EP.2 SOLENYAMA-Lot 4: P.BUY SABUNI; Lot 5: Centre de santé SALONGO_ ITURI ZR-FSRDC-275603-GO- RFQ / (23) Acquisition des Equipements pour les IDB de 5 quartiers : BIGO, En attente HOHO, OPAS, KASEGWA ET 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Limited 125,000.00 0.00 d'exécutio DELE -Lot1 : Centre de Resilience prix Envelope 05 30 26 n santé BIGO- Lot2 : centre de santé HOHO- Lot 3 : Centre de santé OPAS- Lot4;- Lot5: Centre de santé de DELE_ ITURI ZR-FSRDC-275611-GO- RFQ / (61) Acquisition des fournitures et kits de recrutement des En attente 2. Livelihoods and Demande de Single Stage - One 2022-07- 2022-08- 2023-02- bénéficiaires dans le cadre IDA / 66650 A posteriori Limited 18,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 26 de la mise en œuvre des n chantiers de travaux à haute intensité de la main d’œuvre à Goma dans la province du Nord Kivu ZR-FSRDC-274726-GO- RFQ / (25) Acquisition des Equipements pour les IDB En attente centre de santé de 2 1. Support to Community Demande de Single Stage - One 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Limited 50,000.00 0.00 d'exécutio quartiers : NDIBA-KUDU et Resilience prix Envelope 05 30 26 n LUVANGIRA- Lot1 : Centre de santé NDIBE- Lot2 : Centre de santé KATOTO_ ITURI ZR-FSRDC-278111-GO- RFQ / 12 (KC-C2) Acquisition des outges mise en œuvre des chantiers THIMO dans la cité de En attente 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- Kazumba (21) et Matamba IDA / 66650 A posteriori Limited 370,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 (13),Lot 1 : Matamba n (Quartiers Miao, Katoka 1...;lot 2 Kazumba : (Quartiers du Centre, Ntshintsi nord...;lot 3 Kazumba: (Quartiers Kapanda...;_KC ZR-FSRDC-278113-GO- RFQ / 13 (KC-C2) Acquisition des kits médicaux d’urgence dans le En attente cadre de la mise en œuvre 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 40,000.00 0.00 d'exécutio de chantiers de travaux à Employment Generation prix Envelope 05 30 29 n haute intensité de la main d’œuvre à Kazumba et Matamba dans la province du Kasaï-Central (34 chantiers)_ KC ZR-FSRDC-278115-GO- RFQ / 14 (KC-C2) Acquisition des fournitures et kits de recrutement des bénéficiaires dans le cadre En attente 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- de la mise en œuvre des IDA / 66650 A posteriori Limited 40,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 chantiers de travaux à haute n intensité de la main d’œuvre à Kazumba et Matamba dans la province du Kasaï- central (34 chantiers)_ KC ZR-FSRDC-278116-GO- RFQ / 15 (KC-C2) Acquisition de 68 panneaux métalliques pr le mécanisme de gestion des plaintes ds le En attente 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- cadre de la mise en œuvre IDA / 66650 A posteriori Limited 17,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 de 34 chantiers de travaux à n haute intensité de la main d’œuvre dans les 34 quartiers de la cité de Kazumba (21) et Matamba (13) _ KC ZR-FSRDC-278119-GO- RFQ / 16 (KC-C2) Acquisition des 340 kits de En attente lavage des mains pour les 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 51,000.00 0.00 d'exécutio bénéficiaires dans le cadre Employment Generation prix Envelope 05 30 29 n de la mise en œuvre de chantiers de THIMO dans les 34 quartiers de la cité de Kazumba et Matamba _ KC ZR-FSRDC-278120-GO- RFQ / 17 (KC-C2) Acquisition de 714 panneaux de signalisation En attente 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- des chantiers dans le cadre IDA / 66650 A posteriori Limited 37,842.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 de la mise en œuvre de n chantiers de travaux à haute intensité de la main d’œuvre dans la cité de Kazumba et Matamba _ KC Page 6 ZR-FSRDC-278148-GO- RFQ / 33 (SK-C2) Fourniture des matériaux de construction pour la construction/réhabilitation En attente 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- des petits ouvrages (ponts, IDA / 66650 A posteriori Limited 300,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 etc)_ Bukavu. Lot 1 : n Quartiers Panzi, Nyalukemba...; Lot 2: Quartires Kaajan...; Lot 3 : Lumumba...;Lot 4; Chikonyi_ SK ZR-FSRDC-278152-GO- RFQ / 34 (SK-C2) Fourniture des Latérites/Limonites pour le En attente 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- rechargement des axes et IDA / 66650 A posteriori Limited 200,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 fourniture de pelouse, de n bambous, fleurs, plantes et vétivers dans le cadre des chantiers THIMO à Bukavu Répartit en quatre lots_SK ZR-FSRDC-278153-GO- RFQ / 35 (SK-C2) Acquisition des EPI dans le cadre de THIMO dans la ville d’Uvira (14 quartiers)_Lot 1 : En attente 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- Balufiru (Quartiers Kigoma, IDA / 66650 A posteriori Limited 160,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 Lemera, Luvungi, Muhungu n et Runingo);lot 2 : Plaine de Ruzizi : (Quartiers Kabunambo, Kakamba, et Luberezi); Lot 3 : Bavira.._SK ZR-FSRDC-278154-GO- RFQ / 36 (SK-C2) Acquisition des outillages (petits matériels) dans le En attente cadre THIMO dans la ville 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 160,000.00 0.00 d'exécutio d’Uvira (14 quartiers),Lot 1 : Employment Generation prix Envelope 05 30 29 n Balufiru (Quartiers Kigoma, Lemera, ...) lot 2 : Plaine de Ruzizi : (Quartiers Kabunamb..);Lot 3 : Bavira (Quartiers Bijombo, _SK ZR-FSRDC-278157-GO- RFQ / 37 (SK-C2) Acquisition des 14 kits En attente médicaux d’urgence dans le 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 15,000.00 0.00 d'exécutio cadre de la mise en œuvre Employment Generation prix Envelope 05 30 29 n de chantiers de travaux à haute intensité de la main d’œuvre à Uvira dans la province du Sud Kivu (14 chantiers)_SK ZR-FSRDC-278158-GO- RFQ / 38 (SK-C2) Acquisition des fournitures et kits de recrutement des En attente 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- bénéficiaires dans le cadre IDA / 66650 A posteriori Limited 15,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 29 de la mise en œuvre des n chantiers de travaux à haute intensité de la main d’œuvre à Uvira dans la province du Sud Kivu (14 chantiers) ZR-FSRDC-278159-GO- RFQ / 39 (SK-C2) Acquisition de 28 panneaux métalliques pour le En attente mécanisme de gestion des 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 7,000.00 0.00 d'exécutio plaintes dans le cadre de la Employment Generation prix Envelope 05 30 29 n mise en œuvre de 14 chantiers de travaux à haute intensité de la main d’œuvre dans les 14 quartiers de la ville d’Uvira _SK ZR-FSRDC-278162-GO- RFQ / 41 (SK-C2) Acquisition des 210 kits de lavage des mains pour les En attente Bénéficiaires dans le cadre 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 5,670.00 0.00 d'exécutio de la mise en œuvre de Employment Generation prix Envelope 05 30 29 n chantiers de travaux a haute intensité de la main d’œuvre dans les quartiers des communes de la ville de Bukavu_ SK ZR-FSRDC-278206-GO- RFQ / 18 (KC-C2) Acquisition des fournitures des bureaux pour les En attente bureaux des chantiers 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 10,200.00 0.00 d'exécutio (installation des chantiers) Employment Generation prix Envelope 05 30 29 n dans le cadre de la mise en œuvre de chantier de travaux à haute intensité de la main d’œuvre dans la cité de Kazumba et Matamba _ KC ZR-FSRDC-278217-GO- RFQ / 20 (KC-C2) Fourniture des mtrx de construction pour la En attente constr/réhab des petits 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 510,000.00 0.00 d'exécutio ouvrages (ponts, ponceaux, Employment Generation prix Envelope 05 30 29 n dalots...Lot 1 : Matamba (Quartiers Miao, Katoka 1...lot 2 Kazumba : (Quartiers du Centre...lot 3 Kazumba: (Q. Kapanda..._ KC ZR-FSRDC-278218-GO- RFQ / 21 (KC-C2) Fourniture des Latérites/Limonites pour le En attente rechargement des axes dans 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 238,000.00 0.00 d'exécutio le cadre des chantiers Employment Generation prix Envelope 05 30 29 n THIMO à Kazumba et Matamba. Lot 1 : Matamba (Q Miao,Katoka 1...lot 2 Kazumba : (Q. du Centre...lot 3 Kazumba: (Q. Kapanda... _ KC ZR-FSRDC-278219-GO- RFQ / 22 (KC-C2) Fourniture de pelse, de bbous, fleurs, pltes et En attente vetivers pr l’embellissmt et 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 102,000.00 0.00 d'exécutio protection des accts ds le Employment Generation prix Envelope 05 30 29 n cdre THIMO ds la cité Kazumba et Matambao Lt 1 : Matamba (Q Miao,Katoka 1...lt 2 Kazumba : (Q. du Centre...ltt 3 Kazumba: (Q. Kapanda.._KC NON CONSULTING SERVICES Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual ZR-FSRDC-139684-NC- RFQ / Recrutement d'un Consultant firme/individuel pour la traduction de 1. Support to Community Demande de Single Stage - One 2019-10- 2019-10- 2020-04- IDA / 57510 A posteriori Limited 3,500.00 0.00 Annulé documents de travail du Resilience prix Envelope 11 22 19 Fonds Social de la RDC du Français en Anglais et de l'Anglais en Français. ZR-FSRDC-232738-NC- RFQ / Souscription d’une En attente Demande de Single Stage - One 2021-06- 2021-08- 2022-02- assurance maladie en faveur IDA / 66650 4. Project Management A posteriori Limited 150,000.00 0.00 d'exécutio prix Envelope 20 15 11 du personnel du STEP2 et n leurs ayants droits ZR-FSRDC-236411-NC- RFQ / Impression et En attente Demande de Single Stage - One 2021-03- 2021-04- 2021-10- fourniture des supports de IDA / 66650 5. CERC A posteriori Limited 4,975.00 0.00 d'exécutio prix Envelope 01 26 23 visibilité pour la distribution n du cash à Kinshasa ZR-FSRDC-236346-NC- RFQ / Impression et En attente Demande de Single Stage - One 2021-02- 2021-04- 2021-10- fourniture de 100 000 flyers IDA / 66650 5. CERC A posteriori Limited 4,534.40 0.00 d'exécutio prix Envelope 23 20 17 et 1 000 affiches pour la n distribution du Cash à Kinshasa ZR-FSRDC-236549-NC- RFQ / Mise en place et suivi En attente Demande de Single Stage - One 2021-01- 2021-03- 2021-09- d’une collecte de données IDA / 66650 5. CERC A posteriori Open - National 419,220.00 0.00 d'exécutio prix Envelope 10 07 03 par téléphone mobile dans n la ville de Kinshasa ZR-FSRDC-232792-NC- En attente RFQ / Services de Paiements Demande de Single Stage - One 2021-07- 2021-09- 2022-03- IDA / 66650 5. CERC A posteriori Limited 100,000.00 0.00 d'exécutio Digitaux des Bénéficiaires prix Envelope 20 14 13 n STEP-KANANGA ZR-FSRDC-220606-NC- RFQ / Transport des équipements et matériels En attente 2. Livelihoods and Demande de Single Stage - One 2021-02- 2021-04- 2021-10- dans le cadre de la mise en IDA / 66650 A posteriori Limited 40,000.00 0.00 d'exécutio Employment Generation prix Envelope 24 21 18 œuvre de chantiers de n travaux à haute intensité de main d'œuvre (THIM) "cash work" vers Gbadolite ZR-FSRDC-190923-NC- RFB / Recrutement des Single Stage - One 2020-08- 2020-09- 2020-09- 2020-09- 2020-10- 2020-10- 2020-11- 2020-11- prestataire de Services de IDA / 66650 5. CERC A priori Appel d'offres Limited 2,000,000.00 0.00 Annulé Envelope 28 02 01 06 01 16 09 18 Paiements Digitaux des Bénéficiaires STEP-Kinshasa ZR-FSRDC-236334-NC- RFQ / Selection d'une En attente Demande de Single Stage - One 2021-02- 2021-03- 2021-09- entreprise pour assurer les IDA / 66650 5. CERC A posteriori Limited 205,737.84 0.00 d'exécutio prix Envelope 02 30 26 Services de Paiements n Digitaux des Bénéficiaires STEP-Kinshasa ZR-FSRDC-245007-NC-DIR / Recrutement par entente directe de l'entreprise Passation de 2021-08- 2021-07- 2021-08- 2021-07- 2021-10- 2021-08- 2022-03- AFRIMONEY pour assurer le IDA / 66650 5. CERC A posteriori marché de gré à Direct 765,000.00 261,000.00 Signé 22 07 27 30 01 03 30 service de paiements gré digitaux des bénéficiaires STEP Kinshasa. ZR-FSRDC-251704-NC- En attente RFQ / Institution bancaire 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-11- 2022-05- IDA / 66650 A posteriori Limited 60,000.00 0.00 d'exécutio pour le Transfert Monétaire Employment Generation prix Envelope 11 06 05 n Inconditionnel au Nord Ubangi ZR-FSRDC-267034-NC- RFQ / (35): Recrutement d’un service traiteur pour la restauration des En attente 2. Livelihoods and Demande de Single Stage - One 2021-09- 2021-11- 2022-04- participants à la session de IDA / 66650 A posteriori Limited 8,625.00 0.00 d'exécutio Employment Generation prix Envelope 06 01 30 formation de remise n à niveau des chefs de chantiers et chefs d’équipes de YAKOMA ZR-FSRDC-275604-NC- RFQ / (34) Selection des services traiteurs pour la formation des chfs des En cours 2. Livelihoods and Demande de Single Stage - One 2022-06- 2022-07- 2023-01- chtiers, chfs d’eqps, points IDA / 66650 A posteriori Limited 27,000.00 0.00 d'exécutio Employment Generation prix Envelope 05 31 27 PFE et AST dans le cadre de n la mise en œuvre de chantiers THIMO dans les 24 quartiers de la ville de Bunia_ ITURI ZR-FSRDC-275607-NC- RFQ / (66) Selection des services traiteurs pour la formation des chefs des En attente 2. Livelihoods and Demande de Single Stage - One 2022-07- 2022-08- 2023-02- chantiers, chefs d’equipes, IDA / 66650 A posteriori Limited 20,250.00 0.00 d'exécutio Employment Generation prix Envelope 05 30 26 PFE et AST dans le cadre de n la mise en œuvre de chantiers de THIMO dans les 18 quartiers de la ville de Goma_ Nord Kivu ZR-FSRDC-278208-NC- RFQ / 19 (KC-C2) Sélection des services traiteurs pour la formation des chefs des En attente chantiers (41), chefs 2. Livelihoods and Demande de Single Stage - One 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Limited 38,000.00 0.00 d'exécutio d’équipes (374), PFE et Employment Generation prix Envelope 05 30 29 n sociaux (41) et agents de suivi des terrains (41) dans le cadre de THIMO_ dans les 34 quartiers de la cité de Kazumba et Matamba_ KC CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of Contract / Description Component Review Type Method Amount Terms of Reference Request for Technical Proposals Evaluation Report Signed Contract No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal Completion (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Negotiated Planned Contract Actual Planned Actual Planned Actual ZR-FSRDC-46218-CS-UN / Recrutement de FAO pour la mise en œuvre des filières Passation de agricoles dans le corridor 2. Livelihoods and marchés auprès 2018-02- 2018-06- 2018-08- IDA / 57510 A priori Direct 1,294,186.00 1,508,910.79 Signé Kalemie-Nyunzu - bassins Employment Generation des agences de 10 21 09 de Kyoko, Kasanga-Nyemba l'ONU et Kisunkulu, Province de Tanganyika ZR-FSRDC-46235-CS-FBS / Recrutement d'une ONG Sélection dans le partenaire de la mise en 2. Livelihoods and cadre d'un 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-03- 2018-03- 2020-07- œuvre des filières agricoles IDA / 57510 A posteriori Open - National 365,880.00 0.00 Annulé Employment Generation budget 26 26 29 29 09 10 18 05 dans le bassin de Panda, déterminé corridor de Kalemie- Nyunzu, Province de Tanganyika ZR-FSRDC-232808-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-08- 2021-09- 2021-11- 2021-12- 2022-01- 2022-07- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 31 21 04 04 08 07 Construction de l’EP Ouelé/ des consultants Zabo / ZR-FSRDC-232815-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 Construction de l’EP Nzewe/ des consultants Ubangi/ ZR-FSRDC-232819-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 Construction de l’EP des consultants Sorozo1/ Sorozo 2 ZR-FSRDC-232823-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 Construction des EP des consultants Mbongo/ Yakoma ZR-FSRDC-232824-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 construction de l’EP des consultants Ouelé/Yakoma ZR-FSRDC-232827-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 construction de l’EP des consultants Zabo/Yakoma ZR-FSRDC-232829-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 construction de l’EP des consultants Ubangi/Yakoma ZR-FSRDC-232831-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 construction de l’EP Sorozo des consultants 1/Yakoma ZR-FSRDC-232832-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 construction de l’EP des consultants Yakoma/Yakoma ZR-FSRDC-232838-CS- Sélection fondée CQS / Recrutement d’un 1. Support to Community sur les En attente 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 6,000.00 0.00 bureau de contrôle pour la Resilience qualifications d'exécution 07 28 11 10 15 13 construction de l’EP des consultants Wakwa/Yakoma ZR-FSRDC-232862-CS- Sélection fondée CQS / Agence de 2. Livelihoods and sur les En attente 2021-07- 2021-08- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 50,000.00 0.00 communication pour Employment Generation qualifications d'exécution 12 02 15 15 19 18 l’élaboration du plan de des consultants communication de STEP- CERC Sélection fondée ZR-FSRDC-232901-CS- 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- CQS / Bureau de contrôle IDA / 66650 A posteriori Open - National 7,500.00 0.00 Resilience qualifications d'exécution 30 15 21 03 03 07 06 pour l'EP à KABUAYI des consultants ZR-FSRDC-232902-CS- Sélection fondée CQS / Recrutrement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à Central des consultants ZR-FSRDC-232903-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à LUABA NTONDO des consultants ZR-FSRDC-232905-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à MBULU- MIKONGO des consultants ZR-FSRDC-232906-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à MPANDA des consultants Page 7 ZR-FSRDC-232907-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à TUBADI des consultants ZR-FSRDC-232908-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à LUBALA des consultants ZR-FSRDC-232909-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à MITENGU des consultants ZR-FSRDC-232910-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à NSELE des consultants ZR-FSRDC-232911-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à THSIBALA des consultants ZR-FSRDC-232912-CS- Sélection fondée CQS / Recrutement d'un 1. Support to Community sur les En cours 2021-06- 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 7,500.00 0.00 bureau de contrôle pour l'EP Resilience qualifications d'exécution 30 15 21 03 03 07 06 à TSHIMAYI des consultants ZR-FSRDC-233375-CS- CQS / Recrutement d’une Structure chargée du Sélection fondée Renforcement de Capacités 2. Livelihoods and sur les En cours 2021-06- 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 50,000.00 0.00 des Bénéficiaires THIMO de Employment Generation qualifications d'exécution 30 06 21 03 03 07 06 1 350 bénéficiaires pour les des consultants ( Malandi, kamayi, thsinsambi, Platea, Mpemba) de la ville de Kananga ZR-FSRDC-233377-CS- CQS / Recrutement d’une Structure chargée du Sélection fondée Renforcement de Capacités 2. Livelihoods and sur les En cours 2021-06- 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- des Bénéficiaires THIMO de IDA / 66650 A posteriori Open - National 50,000.00 0.00 Employment Generation qualifications d'exécution 30 06 21 03 03 07 06 1 350 bénéficiaires pour les des consultants ( Nsele Nganza -Nord, Nganza- Sud, Saloneo- Muimba- lubi-A-Mpata- Sukisa) de la ville de Kananga ZR-FSRDC-233378-CS- CQS / Recrutement d’une Structure chargée du Sélection fondée Renforcement de Capacités 2. Livelihoods and sur les En cours 2021-06- 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 50,000.00 0.00 des Bénéficiaires THIMO de Employment Generation qualifications d'exécution 30 06 21 03 03 07 06 1 350 bénéficiaires pour les des consultants ( katokaz- Mpokolo- kelekele- Kapanda- Tukombe) de la ville de Kananga ZR-FSRDC-233379-CS- CQS / Recrutement d’une Structure chargée du Sélection fondée Renforcement de Capacités 2. Livelihoods and sur les En cours 2021-06- 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- des Bénéficiaires THIMO de IDA / 66650 A posteriori Open - National 50,000.00 0.00 Employment Generation qualifications d'exécution 30 06 21 03 03 07 06 1 350 bénéficiaires pour les des consultants ( Ndesma- Thibanda Banda- Kamilabi- Lubuwa- Kamu pongo) de la ville de Kananga ZR-FSRDC-233381-CS- CQS / Recrutement d’une Structure chargée du Sélection fondée Renforcement de Capacités 2. Livelihoods and sur les En cours 2021-06- 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- des Bénéficiaires THIMO de IDA / 66650 A posteriori Open - National 50,000.00 0.00 Employment Generation qualifications d'exécution 30 06 21 03 03 07 06 1 350 bénéficiaires pour les des consultants ( Mabondo- Itabayi- Lumumba-dikongayi- Mulunda- Tshibashi) de la ville de Kananga ZR-FSRDC-236086-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 3,400.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Lungandu/KC des consultants MOF-REF-95 / Bureau pour Sélection fondée contrôle et Surveillance des 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 travaux de l'EP Resilience qualifications d'exécution 30 20 05 04 09 05 Ngindalalyi/KC des consultants ZR-FSRDC-236398-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EPArc En Ciel/KC des consultants ZR-FSRDC-236344-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 4,400.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Lumumba 1/KC des consultants ZR-FSRDC-236029-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Muindindi/KC des consultants ZR-FSRDC-236034-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Mukoleshi/KC des consultants ZR-FSRDC-236143-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Kandiku/KC des consultants ZR-FSRDC-236399-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 4,600.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EPA Mufumishi/KC des consultants ZR-FSRDC-236345-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Mudidike/KC des consultants ZR-FSRDC-236500-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 3,760.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Nganza/KC des consultants ZR-FSRDC-236059-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Tshisambi/KC des consultants ZR-FSRDC-236517-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Diku/KC des consultants MOF-REF-107 / Bureau Sélection fondée pour contrôle et Surveillance 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 4,980.00 0.00 des travaux de l'EP Resilience qualifications d'exécution 30 20 05 04 09 05 TOSALISANA/KC des consultants ZR-FSRDC-236412-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 4,600.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Disanka/KC des consultants ZR-FSRDC-236543-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Mgr Bakafua/KC des consultants ZR-FSRDC-236374-CS- Sélection fondée CQS / Bureau pour contrôle 2. Livelihoods and sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 5,200.00 0.00 et Surveillance des travaux Employment Generation qualifications d'exécution 30 20 05 04 09 05 de l'EP Bushala Muamba/KC des consultants ZR-FSRDC-236365-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 4,600.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Ndesha/KC des consultants ZR-FSRDC-236523-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 3,000.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Baolongo/KC des consultants ZR-FSRDC-236082-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 4,200.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP TSHISUMBU/KC des consultants ZR-FSRDC-236091-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 4,600.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP Tuya Kumpala/KC des consultants ZR-FSRDC-236109-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 3,750.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP SANKAYI/KC des consultants ZR-FSRDC-236512-CS- Sélection fondée CQS / Bureau pour contrôle 1. Support to Community sur les En attente 2020-12- 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 4,950.00 0.00 et Surveillance des travaux Resilience qualifications d'exécution 30 20 05 04 09 05 de l'EP DIKONGAYI/KC des consultants ZR-FSRDC-191902-CS- CQS / Recrutement d'un Sélection fondée consultant pour la mise en sur les En attente 2020-09- 2020-09- 2020-11- 2020-12- 2021-01- 2021-07- place et suivi de l’auto- IDA / 66650 5. CERC A posteriori Open - National 100,000.00 0.00 qualifications d'exécution 07 28 11 11 15 14 enregistrement par des consultants téléphone mobile des personnes éligibles sur le registre des bénéficiaires. ZR-FSRDC-121707-CS- QCBS / Recruitment d'un consultant pour la Sélection fondée réalisation d' Audit 1. Support to Community Open - 2019-07- 2019-07- 2019-07- 2019-07- 2019-07- 2019-07- 2019-07- 2020-07- IDA / 57510 A posteriori sur la qualité et 450,000.00 0.00 Annulé technique externe du Projet Resilience International 08 10 13 14 16 18 21 20 le coût pour la Stabilisation de l'Est de la RDC pour la Paix "STEP" pour les exercices 2017, 2018 et 2019, ZR-FSRDC-46241-CS- QCBS / Recruitement d'un Sélection fondée 1. Support to Community Open - 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- 2019-03- consultant pour la IDA / 57510 A posteriori sur la qualité et 100,000.00 0.00 Annulé Resilience International 01 02 04 05 15 25 09 09 réalisation de audit financier le coût et comptable des exercices 2017, 2018 et 2019 ZR-FSRDC-87769-CS-CQS / Recrutement d'un Sélection fondée Consultant-firme pour 2. Livelihoods and sur les 2018-11- 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- 2019-03- IDA / 57510 A posteriori Open - National 300,000.00 0.00 Annulé mener l'enquête finale Employment Generation qualifications 23 07 26 10 14 31 29 d'évaluation d'impact de la des consultants composante THIMO urbain du Projet STEP. ZR-FSRDC-252569-CS- QCBS / Recrutement d'un Consultant (firme) chargé de Sélection fondée l'audit financier et Open - En cours 2021-11- 2021-10- 2021-11- 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2023-05- IDA / 66650 4. Project Management A posteriori sur la qualité et 100,000.00 0.00 comptable du Projet pour la International d'exécution 01 18 22 05 02 04 08 13 13 le coût Stabilisation de l'Est de la RDC pour la Paix "STEP 2" (Exercices 2020, 2021 et 2022) ZR-FSRDC-256194-CS- CQS / Recrutement d’une Structure chargée du Renforcement de Capacités Sélection fondée en MEDAC des Bénéficiaires 2. Livelihoods and sur les En cours 2021-11- 2021-10- 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- THIMO pour la ville de IDA / 66650 A posteriori Open - National 25,000.00 0.00 Employment Generation qualifications d'examen 30 04 21 03 05 09 06 TSHIMBULU repartis en 2 des consultants lots de 500 bénéficiaires pour chaque lot pour les quartiers TSHIABALA, LUBALA, N'SELE, MITENGU. CF obs- ci-dessous ZR-FSRDC-256197-CS- CQS / Recrutement d’une Structure chargée du Renforcement de Capacités Sélection fondée en MEDAC des Bénéficiaires 2. Livelihoods and sur les En cours 2021-11- 2021-10- 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- IDA / 66650 A posteriori Open - National 37,500.00 0.00 THIMO pour la ville de Employment Generation qualifications d'examen 30 04 21 03 05 09 06 DIBAYA repartis en 3 lots de des consultants 500 bénéficiaires pour chaque lot pour les quartiers INGA, MISSION, TUBADI, LUKULA, CENTRAL, KABUYA: ZR-FSRDC-256199-CS- CQS / Recrutement d’une Structure chargée du Renforcement de Capacités Sélection fondée en MEDAC des Bénéficiaires 2. Livelihoods and sur les En cours 2021-11- 2021-10- 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- IDA / 66650 A posteriori Open - National 175,000.00 0.00 THIMO pour la ville de Employment Generation qualifications d'examen 30 04 21 03 05 09 06 Kananga repartis en 14 lots des consultants de 500 bénéficiaires pour chaque lot pour 28 quartiers de la ville de kananga ci- dessous les lots repartis: ZR-FSRDC-244043-CS- CQS / Recrutement d’une Sélection fondée Structure chargée du 2. Livelihoods and sur les 2021-08- 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Renforcement de Capacités IDA / 66650 A posteriori Open - National 100,000.00 0.00 Annulé Employment Generation qualifications 16 29 06 20 19 24 22 en MEDAC des Bénéficiaires des consultants THIMO de 1 500 bénéficiaires de la ville de Dibaya ZR-FSRDC-244041-CS- CQS / Recrutement d’une Sélection fondée Structure chargée du 2. Livelihoods and sur les 2021-08- 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- Renforcement de Capacités IDA / 66650 A posteriori Open - National 100,000.00 0.00 Annulé Employment Generation qualifications 16 29 06 20 19 24 22 en MEDAC des Bénéficiaires des consultants THIMO de 1 250 bénéficiaires de la ville de Tshimbulu ZR-FSRDC-267050-CS- CQS / (47): Recrutement d'une ONGD Chargé Sélection fondée d’administrer les mesures 2. Livelihoods and sur les En attente 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 66650 A posteriori Open - National 37,022.00 0.00 d’accompagnement Employment Generation qualifications d'exécution 16 06 20 19 24 22 (MEDAC) aux bénéficiaires des consultants de Gbadolite des quartiers Lite, Kaya, Fiwa et Bambu ZR-FSRDC-267048-CS- CQS / (46): Recrutement d'une ONGD Chargé Sélection fondée d’administrer les mesures 2. Livelihoods and sur les En attente 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 66650 A posteriori Open - National 37,022.00 0.00 d’accompagnement Employment Generation qualifications d'exécution 16 06 20 19 24 22 (MEDAC) aux bénéficiaires des consultants de Gbadolite des quartiers Mbanza, Pangoma, Gbau et Kambo ZR-FSRDC-267004-CS- CQS / (44): Recrutement d'une ONGD Chargé Sélection fondée d’administrer les mesures 2. Livelihoods and sur les En attente 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 66650 A posteriori Open - National 37,022.00 0.00 d’accompagnement Employment Generation qualifications d'exécution 16 06 20 19 24 22 (MEDAC) aux bénéficiaires des consultants de Gbadolite des quartiers Mwanda, Molegbe, Nganza et Ngonda ZR-FSRDC-267008-CS- CQS / (43): Recrutement d'une ONGD Chargé Sélection fondée d’administrer les mesures 2. Livelihoods and sur les En attente 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 66650 A posteriori Open - National 37,022.00 0.00 d’accompagnement Employment Generation qualifications d'exécution 16 06 20 19 24 22 (MEDAC) aux bénéficiaires des consultants de Gbadolite des quartiers Gobele, Bakpa, Tudu et Mune ZR-FSRDC-267038-CS- CQS / (45): Recrutement d'une ONGD Chargé Sélection fondée d’administrer les mesures 2. Livelihoods and sur les En attente 2021-08- 2021-09- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 66650 A posteriori Open - National 37,022.00 0.00 d’accompagnement Employment Generation qualifications d'exécution 16 06 20 19 24 22 (MEDAC) aux bénéficiaires des consultants de Gbadolite des quartiers Fadu, Kawele, Kumbu, Ziamba ZR-FSRDC-277785-CS- CQS / Agence de Sélection fondée communication pour pour sur les En attente 2022-06- 2022-07- 2022-09- 2022-10- 2022-11- 2023-05- concevoir et produire les IDA / 66650 5. CERC A posteriori Open - National 50,000.00 0.00 qualifications d'exécution 30 21 03 03 07 06 supports de communication des consultants et de visibilité pour le projet STEP-KIN du FSRDC INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated Contract / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract No. Approach Amount (US$) Status Contract Completion (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-110894-CS- CDS / Recrutement de l'Institut National de Sélection de 1. Support to Community 2019-04- 2020-02- 2019-04- 2019-07- 2019-12- Préparation Professionnel « IDA / 57510 A priori consultants par Direct 400,000.00 0.00 Annulé Resilience 19 16 29 03 30 INPP » pour la formation entente directe des bénéficiaires « THIMO sociaux », deuxième phase ZR-FSRDC-232841-CS- CQS / Recrutement d'un 1. Support to Community En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Individuel Limited 10,000.00 0.00 consultant en appui au Resilience d'exécution 07 12 03 07 03 CTIC/ Nord Ubangi (consultant 1) Page 8 ZR-FSRDC-232840-CS- INDV / Recrutement d'un En cours 2021-06- 2021-07- 2021-08- 2021-08- 2021-09- 2022-03- IDA / 66650 4. Project Management A posteriori Individuel Open 42,000.00 0.00 Spécialiste, Expert en d'exécution 15 23 03 24 28 27 MEDAC du Projet STEP 2 ZR-FSRDC-232847-CS- INDV / Recrutement d'un 1. Support to Community En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Individuel Limited 10,000.00 0.00 consultant en appui au Resilience d'exécution 07 12 03 07 03 CTIC/Nord Ubangi (consultant 2) ZR-FSRDC-232849-CS- En cours 2021-06- 2021-11- 2021-08- 2021-08- 2021-09- 2022-03- INDV / Recrutement d'un IDA / 66650 4. Project Management A posteriori Individuel Open 24,000.00 0.00 d'exécution 15 11 03 24 28 27 Assistant Comptable pour le Projet STEP ZR-FSRDC-232851-CS- INDV / Contractualisation par entente directe de En cours 2021-06- 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Individuel Direct 24,000.00 0.00 Monsieur Guy BUKALANGI d'exécution 15 29 25 16 20 16 comme Assistant du Chargé des Opérations du Projet STEP 2 ZR-FSRDC-232855-CS- En cours 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 INDV / Chargé des d'exécution 30 01 18 08 13 11 MESDAC/KC ZR-FSRDC-232854-CS- INDV / Recrutement d'un En cours 2021-06- 2021-07- 2021-06- 2021-07- 2021-08- 2022-02- Consultant Secrétaire IDA / 66650 4. Project Management A posteriori Individuel Limited 12,000.00 0.00 d'exécution 15 23 20 11 15 11 Réceptionniste du Projet STEP 2 ZR-FSRDC-232859-CS- 2021-07- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- INDV / Chargé du Transfert IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 Annulé 30 23 17 08 12 11 Monétaire/KC ZR-FSRDC-232860-CS- 2021-08- 2021-06- 2021-10- 2021-11- 2021-12- 2022-06- INDV / Assistant IDA / 66650 4. Project Management A posteriori Individuel Open 18,000.00 0.00 Annulé 31 01 19 09 14 12 Administratif et Financier/KC ZR-FSRDC-232861-CS- En cours 2021-06- 2021-06- 2021-07- 2021-07- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 INDV / Caissier/KC d'exécution 30 21 05 26 30 26 ZR-FSRDC-232863-CS- En attente 2021-09- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 INDV / Chauffeur 1 des d'exécution 30 05 26 30 29 courses/KC ZR-FSRDC-232864-CS- En attente 2021-09- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 INDV / Chauffeur 2 des d'exécution 30 05 26 30 29 courses/KC ZR-FSRDC-232865-CS- En attente 2021-09- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 INDV / Chauffeur 3 des d'exécution 30 05 26 30 29 courses/KC ZR-FSRDC-232867-CS- 2021-10- 2021-12- 2022-01- 2022-02- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 Annulé INDV / Chargé de MGP/KC 29 17 07 11 10 ZR-FSRDC-232866-CS- INDV / Recrutement d'un En cours 2021-06- 2021-09- 2021-08- 2021-08- 2021-09- 2022-03- Assistant en Base de IDA / 66650 4. Project Management A posteriori Individuel Open 24,000.00 0.00 d'exécution 15 20 03 24 28 27 Données (gestion du système intégré/MIS) du Projet STEP 2 ZR-FSRDC-232868-CS- INDV / Recrutement d'un 2021-06- 2021-07- 2021-08- 2021-08- 2021-09- 2022-03- Consultant Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 Annulé 15 23 03 24 28 27 Transfert Monétaire à l'antenne du Nord Ubangi ZR-FSRDC-232870-CS- INDV / Consultant chargé de la comptabilité pour le En attente 2021-07- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 5. CERC A posteriori Individuel Open 39,600.00 0.00 Contingent Emergency d'exécution 12 30 20 25 23 Response Component ‘CERC- COVID19’ KINSHASA ZR-FSRDC-232871-CS- INDV / Recrutement d'un 2021-06- 2021-07- 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Individuel Limited 18,000.00 0.00 Annulé Assistant Administratif et 15 23 20 11 15 11 Financier du Projet STEP 2 ZR-FSRDC-232872-CS- En cours 2021-06- 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- INDV / Recrutement d'un IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 d'exécution 15 21 20 11 15 11 Caissier pour l'antenne du Nord Ubangi ZR-FSRDC-232873-CS- INDV / Recrutement d'un En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 Chauffeur n° 1 de Course du d'exécution 15 20 11 15 11 Projet STEP 2 ZR-FSRDC-232874-CS- En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- INDV / Recrutement d'un IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 d'exécution 15 20 11 15 11 Chauffeur n° 2 du Projet STEP 2 ZR-FSRDC-232876-CS- En attente 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- INDV / Recrutement d'un IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 d'exécution 15 20 11 15 11 Chauffeur N) 3 du Projet STEP 2 ZR-FSRDC-191751-CS- INDV / Recrutement du En attente 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- IDA / 66650 4. Project Management A posteriori Individuel Direct 62,400.00 0.00 Chargé des Opérations du d'exécution 07 11 13 17 23 STEP 2 (François Kabemba) ZR-FSRDC-236277-CS- 1. Support to Community En attente 2020-12- 2020-12- 2021-01- 2021-02- 2021-08- INDV / Consultant en appui IDA / 66650 A posteriori Individuel Limited 7,200.00 0.00 Resilience d'exécution 18 23 13 17 16 STIC/KC ZR-FSRDC-236355-CS- 1. Support to Community En attente 2020-12- 2021-02- 2021-02- 2021-04- 2021-09- INDV / Consultant en appui IDA / 66650 A posteriori Individuel Open 7,200.00 0.00 Resilience d'exécution 18 05 26 02 29 STIC/KC ZR-FSRDC-236035-CS- INDV / CI pour contrôle et 1. Support to Community En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 4,600.00 0.00 Surveillance des travaux de Resilience d'exécution 30 17 10 14 11 l'EP Kapajika/KC ZR-FSRDC-236161-CS- INDV / CI pour contrôle et 1. Support to Community En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 4,600.00 0.00 Surveillance des travaux de Resilience d'exécution 30 17 10 14 11 l'EP Tshibashi/KC ZR-FSRDC-236401-CS- INDV / Consultant Individuel 1. Support to Community En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 4,200.00 0.00 pour contrôle et Surveillance Resilience d'exécution 30 17 10 14 11 des travaux de l'EP Diku Dietu/KC ZR-FSRDC-236400-CS- INDV / Consultant Individuel 1. Support to Community En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 3,338.00 0.00 pour le contrôle et Resilience d'exécution 30 17 10 14 11 Surveillance des travaux de l'EP DJAKAJA/KC ZR-FSRDC-236366-CS- INDV / Sélection de 1. Support to Community En attente 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 A posteriori Individuel Open 3,800.00 0.00 Consultants formateurs des Resilience d'exécution 01 19 10 14 11 Chefs de Chantiers/NU ZR-FSRDC-236368-CS- INDV / Sélection de 1. Support to Community En attente 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 A posteriori Individuel Open 3,800.00 0.00 Consultants formateurs des Resilience d'exécution 01 19 10 14 11 Chefs de Chantiers/NU ZR-FSRDC-236347-CS- INDV / Consultant pour réaliser le suivi environnemental et social 1. Support to Community En attente 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 A posteriori Individuel Open 9,000.00 0.00 des chantiers Ecoles dans la Resilience d'exécution 01 19 10 14 11 ville de Gbadolite et la cité de Mobayi Mbongo dans le cadre du lancement du STEP II au Nord Ubangi ZR-FSRDC-236372-CS- INDV / Consultant pour réaliser les screening environnementaux et 1. Support to Community En attente 2021-03- 2021-05- 2021-06- 2021-07- 2022-01- sociaux des chantiers IDA / 66650 A posteriori Individuel Open 3,220.00 0.00 Resilience d'exécution 31 19 09 14 10 THIMO dans la ville de Gbadolite et la cité de Mobayi Mbongo dans le cadre du lancement du STEP II au Nord Ubangi ZR-FSRDC-236089-CS- INDV / Consultant pour appuyer le suivi des appels à travers les numéros verts 2. Livelihoods and En attente 2021-03- 2021-05- 2021-06- 2021-07- 2022-01- du MGP des chantiers IDA / 66650 A posteriori Individuel Open 7,200.00 0.00 Employment Generation d'exécution 31 19 09 14 10 THIMO et Ecoles dans la ville de Gbadolite et la cité de Mobayi Mbongo dans le cadre du lancement du STEP II au Nord Ubangi ZR-FSRDC-236350-CS- INDV / Consultant pour réaliser le suivi environnemental et social 2. Livelihoods and En attente 2021-03- 2021-05- 2021-06- 2021-07- 2022-01- IDA / 66650 A posteriori Individuel Open 9,000.00 0.00 des chantiers THIMO dans la Employment Generation d'exécution 31 19 09 14 10 ville de Gbadolite et la cité de Mobayi Mbongo dans le cadre du lancement du STEP II au Nord Ubangi ZR-FSRDC-236092-CS- INDV / Consultants en appui 2. Livelihoods and En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- au STHIMO pour la IDA / 66650 A posteriori Individuel Open 7,500.00 0.00 Employment Generation d'exécution 25 12 05 09 06 supervision des chantiers THIMO à Kananga ZR-FSRDC-236094-CS- INDV / Consultants en appui 2. Livelihoods and En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- au STHIMO pour la IDA / 66650 A posteriori Individuel Open 7,500.00 0.00 Employment Generation d'exécution 25 12 05 09 06 supervision des chantiers THIMO à Kananga ZR-FSRDC-236514-CS- INDV / Consultants en appui 2. Livelihoods and En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- au STHIMO pour la IDA / 66650 A posteriori Individuel Open 7,500.00 0.00 Employment Generation d'exécution 25 12 05 09 06 supervision des chantiers THIMO à Kananga ZR-FSRDC-236044-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236371-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236103-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236422-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236096-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236351-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236110-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236045-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236403-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236369-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236087-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236376-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236515-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236370-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236352-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236278-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236146-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236112-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236528-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236409-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236402-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236135-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236382-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236530-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236046-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236154-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236532-CS- 2. Livelihoods and 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé INDV / Consultants Employment Generation 24 12 02 09 05 Enquêteurs/KC ZR-FSRDC-236279-CS- 2. Livelihoods and En attente 2020-12- 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 9,000.00 0.00 INDV / Consultant en appui Employment Generation d'exécution 21 08 01 05 02 SSS/KC ZR-FSRDC-236137-CS- En attente 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- INDV / Spécialiste en IDA / 66650 4. Project Management A posteriori Individuel Open 57,810.00 0.00 d'exécution 05 24 14 19 15 Sauvegardes Environnementales ZR-FSRDC-236357-CS- En attente 2021-01- 2021-02- 2021-03- 2021-04- 2021-10- INDV / Spécialiste en Suivi IDA / 66650 4. Project Management A posteriori Individuel Open 52,800.00 0.00 d'exécution 10 28 21 25 22 et Evaluation STEP 2 ZR-FSRDC-236506-CS- INDV / Contractualisation En cours 2021-04- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- avec le Consultant Yves IDA / 66650 4. Project Management A posteriori Individuel Direct 24,600.00 0.00 d'exécution 01 04 11 02 06 03 MISSIATU comme Assistant en Passation des Marches du Projet STEP 2 ZR-FSRDC-236138-CS- INDV / Contractualisation avec le Consultant Danny KALEMBU RUTAMU comme En cours 2021-02- 2020-05- 2021-02- 2021-03- 2021-04- 2021-10- Chargé du Développement IDA / 66650 4. Project Management A posteriori Individuel Direct 49,610.00 0.00 d'exécution 15 29 25 18 22 19 Communautaire et Gestion des Conflits à l'antenne du Nord-Ubangi dans le cadre du Projet STEP 2 ZR-FSRDC-235770-CS- INDV / Contractualisation En attente 2020-08- 2020-09- 2020-09- 2020-10- 2021-04- avec le Consultant Francois IDA / 66650 4. Project Management A posteriori Individuel Direct 62,400.00 0.00 d'exécution 24 03 24 29 27 KABEMBA comme Chargé des Opérations du Projet STEP 2 ZR-FSRDC-235768-CS- INDV / Contractualisation avec le Consultant Claude En cours 2021-03- 2021-03- 2021-04- 2021-04- 2021-05- 2021-11- IDA / 66650 4. Project Management A posteriori Individuel Direct 117,730.00 0.00 OGOU comme Assistant d'exécution 22 05 01 22 27 23 Technique en Passation des Marchés du Projet STEP 2 ZR-FSRDC-236005-CS- INDV / Contractualisation avec le Consultant Magnant En cours 2020-10- 2020-09- 2020-10- 2020-11- 2020-12- 2021-06- MUBONGE MUKULUMANYA IDA / 66650 4. Project Management A posteriori Individuel Direct 54,000.00 0.00 d'exécution 14 29 24 14 19 17 comme Spécialiste en Sauvegardes Sociales du Projet STEP 2 ZR-FSRDC-236006-CS- INDV / Contractualisation avec la Consultante Sylvie En attente 2020-10- 2020-10- 2020-11- 2020-12- 2021-06- IDA / 66650 4. Project Management A posteriori Individuel Direct 22,560.00 0.00 LUZALA comme Assistant du d'exécution 19 29 19 24 22 Chargé des Opérations du Projet STEP 2 (Administration-RH) Page 9 ZR-FSRDC-236534-CS- INDV / Contractualisation avec le Consultant Ademar En cours 2021-01- 2021-01- 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 4. Project Management A posteriori Individuel Direct 12,240.00 0.00 NAMUISI KINABUNA comme d'exécution 06 05 16 06 13 09 Chauffeur du Chargé des Opérations du Projet STEP 2 ZR-FSRDC-236164-CS- INDV / Contractualisation En cours 2021-01- 2021-01- 2021-01- 2021-02- 2021-03- 2021-09- avec le Consultant D'Acquin IDA / 66650 4. Project Management A posteriori Individuel Direct 12,240.00 0.00 d'exécution 06 05 16 06 13 09 NZAU DIMAVINGA comme Chauffeur du Projet STEP 2 ZR-FSRDC-235773-CS- INDV / Contractualisation En cours 2020-10- 2020-09- 2020-10- 2020-11- 2020-12- 2021-06- avec le Consultant Adeline IDA / 66650 4. Project Management A posteriori Individuel Direct 18,480.00 0.00 d'exécution 16 29 26 16 21 19 M'BUY MANDEAK comme Caissière du Projet STEP 2 ZR-FSRDC-236525-CS- INDV / Contractualisation avec le Consultant Bernard En cours 2020-11- 2020-11- 2020-12- 2020-12- 2021-01- 2021-07- IDA / 66650 4. Project Management A posteriori Individuel Direct 47,860.00 0.00 TSHISHIKU BULULU comme d'exécution 23 11 03 24 28 27 Chargé de la Comptabilité à l'antenne du Kasai Central ZR-FSRDC-236053-CS- INDV / Contractualisation avec le Consultant Raymond BWANAHERI MAPISANO comme Chargé de En cours 2021-02- 2021-01- 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 4. Project Management A posteriori Individuel Direct 47,860.00 0.00 Développement d'exécution 15 25 25 18 22 19 Communautaire et Gestion des Conflits à l'antenne du Kasai Central dans la le cadre du Projet STEP 2 ZR-FSRDC-236057-CS- INDV / Contractualisation avec le Consultant Joslin En attente 2021-03- 2021-03- 2021-04- 2021-05- 2021-11- KAMADILU TSHIPAMBULA IDA / 66650 4. Project Management A posteriori Individuel Direct 44,400.00 0.00 d'exécution 02 12 02 07 03 comme Chargé de Suivi et Evaluation à l'angtenne du Kasai Central dans le cadre du Projet STEP 2 ZR-FSRDC-235697-CS- INDV / Contractualisation avec le Consultant Zacharie MASIALA LELI-VAKANDA En cours 2021-02- 2021-01- 2021-02- 2021-03- 2021-04- 2021-10- comme Spécialiste en IDA / 66650 4. Project Management A posteriori Individuel Direct 41,250.00 0.00 d'exécution 15 25 25 18 22 19 Travaux d'Infrastructures Communautaires à l'antenne du Kasai Central dans le cadre du Projet STEP 2 ZR-FSRDC-236148-CS- INDV / Contractualisation avec le Consultant Titien En cours 2020-10- 2020-09- 2020-10- 2020-11- 2020-12- 2021-06- IDA / 66650 4. Project Management A posteriori Individuel Direct 48,110.00 0.00 LIKONDJI BAATA comme d'exécution 14 29 24 14 19 17 Spécialiste en Infrastructure au sein du Projet STEP 2 ZR-FSRDC-236330-CS- INDV / Contractualisation avec le Consultant Serge En cours 2020-10- 2020-09- 2020-10- 2020-11- 2020-12- 2021-06- MUFENGI NZOFU comme IDA / 66650 4. Project Management A posteriori Individuel Direct 49,200.00 0.00 d'exécution 20 29 30 20 25 23 Spécialiste en Travaux à Haute Intensité de Main d’œuvre au sein du Projet STEP 2 ZR-FSRDC-236076-CS- En attente 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- INDV / Chargé en Travaux à IDA / 66650 4. Project Management A posteriori Individuel Open 56,000.00 0.00 d'exécution 06 25 15 20 16 Haute Intensité de Main d’œuvre ZR-FSRDC-236166-CS- En attente 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- INDV / Chargé des IDA / 66650 4. Project Management A posteriori Individuel Open 49,200.00 0.00 d'exécution 06 25 15 20 16 Sauvegardes Environnementales et Sociales ZR-FSRDC-235776-CS- INDV / Contractualisation En cours 2021-04- 2021-01- 2021-04- 2021-05- 2021-06- 2021-12- avec le Consultant Serge IDA / 66650 4. Project Management A posteriori Individuel Direct 12,240.00 0.00 d'exécution 19 05 29 20 24 21 ZOLA KIAMA comme Chauffeur du Projet STEP 2 ZR-FSRDC-236078-CS- En attente 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- INDV / Spécialiste en Base IDA / 66650 5. CERC A posteriori Individuel Open 108,965.00 0.00 d'exécution 01 20 10 15 11 de Données du CERC-STEP2 ZR-FSRDC-236009-CS- En attente 2021-03- 2021-04- 2021-04- 2021-05- 2021-11- INDV / Assistant en IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 d'exécution 29 03 24 29 25 Mécanisme de Gestion des Plaintes CERC Kin ZR-FSRDC-236332-CS- INDV / Chargé du suivi des En attente 2021-04- 2021-04- 2021-04- 2021-06- 2021-11- IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 activités de transfert d'exécution 02 07 28 02 29 monétaire dans le cadre du STEP-Kin ZR-FSRDC-236083-CS- INDV / Chargé du suivi des En attente 2021-04- 2021-04- 2021-04- 2021-06- 2021-11- IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 activités de transfert d'exécution 02 07 28 02 29 monétaire dans le cadre du STEP-Kin ZR-FSRDC-236027-CS- INDV / Chargé du suivi des En attente 2021-04- 2021-04- 2021-04- 2021-06- 2021-11- IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 activités de transfert d'exécution 02 07 28 02 29 monétaire dans le cadre du STEP-Kin ZR-FSRDC-236036-CS- INDV / Chargé du suivi des En attente 2021-04- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 activités de transfert d'exécution 05 10 01 05 02 monétaire dans le cadre du STEP-Kin ZR-FSRDC-236404-CS- INDV / Chargé du suivi des En attente 2021-04- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 activités de transfert d'exécution 07 12 03 07 04 monétaire dans le cadre du STEP-Kin ZR-FSRDC-236388-CS- En attente 2020-10- 2020-11- 2020-12- 2021-01- 2021-07- INDV / Expert en Transfert IDA / 66650 5. CERC A posteriori Individuel Open 44,700.00 0.00 d'exécution 05 23 14 18 17 Monétaire du CERC ZR-FSRDC-236040-CS- INDV / Chargé du suivi des 2021-04- 2021-04- 2021-04- 2021-06- 2021-11- IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 Annulé mécanismes de gestion des 01 06 27 01 28 plaintes du STEP2 ZR-FSRDC-237038-CS- 1. Support to Community En attente 2021-04- 2021-04- 2021-05- 2021-06- 2021-12- INDV / Consultant en appui IDA / 66650 A posteriori Individuel Limited 7,200.00 0.00 Resilience d'exécution 12 17 08 12 09 STIC/KC ZR-FSRDC-237039-CS- 1. Support to Community En attente 2021-04- 2021-04- 2021-05- 2021-06- 2021-12- INDV / Consultant en appui IDA / 66650 A posteriori Individuel Limited 7,200.00 0.00 Resilience d'exécution 12 17 08 12 09 STIC/KC ZR-FSRDC-237034-CS- INDV / Consultants en appui 2. Livelihoods and En attente 2021-04- 2021-04- 2021-05- 2021-06- 2021-12- au STHIMO pour la IDA / 66650 A posteriori Individuel Limited 7,500.00 0.00 Employment Generation d'exécution 12 17 08 12 09 supervision des chantiers THIMO à Kananga ZR-FSRDC-237040-CS- INDV / Consultants en appui 2. Livelihoods and En attente 2021-04- 2021-04- 2021-05- 2021-06- 2021-12- au STHIMO pour la IDA / 66650 A posteriori Individuel Limited 7,500.00 0.00 Employment Generation d'exécution 12 17 08 12 09 supervision des chantiers THIMO à Kananga ZR-FSRDC-237037-CS- INDV / Consultants en appui 2. Livelihoods and En attente 2021-04- 2021-04- 2021-05- 2021-06- 2021-12- au STHIMO pour la IDA / 66650 A posteriori Individuel Limited 7,500.00 0.00 Employment Generation d'exécution 12 17 08 12 09 supervision des chantiers THIMO à Kananga ZR-FSRDC-237035-CS- INDV / Consultants en appui 1. Support to Community En attente 2021-04- 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 A posteriori Individuel Limited 7,500.00 0.00 pour le suivi Resilience d'exécution 12 17 08 12 09 environnemental et social de kananga ZR-FSRDC-237048-CS- INDV / Contractualisation En cours 2021-06- 2021-06- 2021-07- 2021-07- 2021-09- 2022-03- IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 au poste de MEDAC avec d'exécution 30 15 10 31 04 03 Adolphe NAKAKULA ZR-FSRDC-237050-CS- 2021-07- 2021-08- 2021-08- 2021-09- 2022-03- INDV / Recrutement d'un IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 Annulé 30 04 25 29 28 MGP Kasaï Central ZR-FSRDC-220633-CS- CDS / Recrutement du Coordonnateur de la Sélection de convention de partenariat En attente 2021-05- 2021-06- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori consultants par Direct 52,000.00 0.00 FSRDC-MINAS pour le Projet d'exécution 31 10 14 10 entente directe STEP II par entente directe avec Mr Jules BISILWALA MUSUKU ZR-FSRDC-191792-CS- INDV / Recrutement du En attente 2020-09- 2020-09- 2020-10- 2020-11- 2021-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,400.00 0.00 Responsable Administratif d'exécution 07 21 12 16 15 et Financier du STEP 2 ZR-FSRDC-191764-CS- INDV / Recrutement du En attente 2020-09- 2020-09- 2020-10- 2020-10- 2021-10- IDA / 57510 4. Project Management A posteriori Individuel Open 50,400.00 0.00 Spécialiste en Passation des d'exécution 07 24 01 22 17 Marchés du Projet STEP 2 ZR-FSRDC-141795-CS- INDV / Recrutement d'un Consultant Individuel pour réaliser la mission 1. Support to Community 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- d’élaborer le Cadre de IDA / 57510 A posteriori Individuel Limited 35,000.00 0.00 Annulé Resilience 22 24 25 28 12 Politique de Réinstallation (CPR) du Projet de STEP - FA dans les provinces de Kasai, Kasai Oriental et Kasai Central ZR-FSRDC-141821-CS- INDV / Recrutement d'un Consultant Individuel pour réaliser la mission 1. Support to Community 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- d’élaborer le Cadre de IDA / 57510 A posteriori Individuel Limited 35,000.00 0.00 Annulé Resilience 22 25 26 29 13 Gestion Environnementale et Sociale (CGES) du Projet de STEP - FA dans les provinces de Kasai, Kasai Oriental et Kasai Central ZR-FSRDC-120259-CS- INDV / Recrutement de 1. Support to Community En attente 2019-06- 2019-07- 2019-07- 2019-07- 2019-07- consultants IDA / 57510 A posteriori Individuel Limited 50,000.00 0.00 Resilience d'exécution 30 02 07 17 23 individuels/panels pour appuyer le FSRDC dans les évaluations des offres. ZR-FSRDC-236830-CS- CDS / recrutement du Sélection de consultant GiveDirectly, 1. Support to Community En cours 2021-06- 2021-06- 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori consultants par Direct 735,000.00 0.00 pour la mise en œuvre du Resilience d'exécution 30 17 10 13 12 entente directe Pilote MobileAid dans le cadre du programme STEP KIN ZR-FSRDC-239849-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 21 26 16 20 19 l'EP BISHIYA dans le secteur de DIBANDA_KC ZR-FSRDC-239851-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 20 25 15 19 18 l'EP MUAKAJI dans le secteur de DIBANDA_KC ZR-FSRDC-239852-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 20 25 15 19 18 l'EP1 DIBANDA dans le secteur de DIBANDA_KC ZR-FSRDC-239853-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 20 25 15 19 18 l'EP NDIBU KALAMBA dans le secteur de KASANGIDI_KC ZR-FSRDC-239856-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 21 26 16 20 19 l'EP LUAJA dans le secteur de KASANGIDI_KC ZR-FSRDC-239857-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,500.00 0.00 contrôle et surveillance de Resilience d'exécution 22 27 17 21 20 l'EP3 LUKULA dans le secteur de KASANGIDI_KC ZR-FSRDC-239858-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 22 27 17 21 20 l'EP1 BASANGA dans le secteur de KASANGIDI_KC ZR-FSRDC-239859-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 23 28 18 22 21 l'EP NTUADIJILU dans le secteur de KASANGIDI_KC ZR-FSRDC-239860-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 26 31 21 25 24 l'EP MAMBASAKO dans le secteur de KASANGIDI_KC ZR-FSRDC-239861-CS- INDV / Recrutement d'un consultant individuel pour le 1. Support to Community En attente 2021-07- 2021-08- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 4,600.00 0.00 contrôle et surveillance de Resilience d'exécution 27 01 22 26 25 l'EP TSHIMAKAKA dans le secteur de KASANGIDI_KC ZR-FSRDC-240661-CS- INDV / Recrutement d'un En cours 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 5. CERC A posteriori Individuel Open 54,000.00 0.00 Assistant Technique d'exécution 30 25 18 08 13 11 International en transferts monétaires ZR-FSRDC-243735-CS- INDV / Recrutement de deux (2) consultants 1. Support to Community En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Individuel Open 100,000.00 0.00 Ingénieurs en Appui CTIC Resilience d'exécution 14 02 23 27 26 dans la ville de Kananga et dans les cités de Dibaya et de Tshimbulu ZR-FSRDC-243745-CS- INDV / Recrutement de trois (3) Consultant DPO pour le 1. Support to Community En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- suivi et le contrôle des IDA / 66650 A posteriori Individuel Open 22,500.00 0.00 Resilience d'exécution 14 02 23 27 26 travaux de construction des IDB dans le secteur DIBANDA (EP BISHIYA, EP MUAKAJI et EP1 DIBANDA) ZR-FSRDC-243755-CS- INDV / Recrutement de sept (7) Consultant DPO pour le suivi et le contrôle des travaux de construction des 1. Support to Community En attente 2021-08- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Individuel Open 52,500.00 0.00 IDB dans le secteur Resilience d'exécution 10 28 19 23 22 KASANGIDI (EP NDIBU KALAMBA, EP LUAJA, EP3 LUKULA, EP1 BASANGA, EP NTUADIJILU, EP MAMBASAKO et EP TSHIMAKAKA) ZR-FSRDC-244035-CS- INDV / Recrutement d’un Consultant DPO pour le 1. Support to Community En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- suivi et le contrôle des IDA / 66650 A posteriori Individuel Open 6,000.00 0.00 Resilience d'exécution 16 04 25 29 28 travaux de réhabilitation de l’Hôpital Général du quartier LUKONGA à Kananga ZR-FSRDC-244047-CS- INDV / Recrutement de neuf (9) Consultant DPO pour le 1. Support to Community En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Individuel Open 45,000.00 0.00 suivi et le contrôle des Resilience d'exécution 16 04 25 29 28 travaux de construction des IDB de YAKOMA ZR-FSRDC-244084-CS- INDV / Consultant pour En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 3. Capacity Building A posteriori Individuel Open 45,000.00 0.00 appuyer la CNR dans la d'exécution 16 04 25 29 28 transmission et gestion de la base de données ZR-FSRDC-244089-CS- INDV / Recrutement d’un En cours 2021-08- 2021-07- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 100,000.00 0.00 Spécialiste en d'exécution 16 29 04 25 29 28 Développement Communautaire du STEP 2 ZR-FSRDC-244090-CS- En cours 2021-08- 2021-06- 2021-10- 2021-10- 2021-11- 2022-05- INDV / Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Open 80,000.00 0.00 d'exécution 16 16 04 25 29 28 Chef Comptable du STEP 2 Page 10 ZR-FSRDC-244095-CS- CDS / Mise en œuvre de l’enquête par téléphone Sélection de 2021-08- 2021-08- 2021-08- 2021-08- 2021-10- 2021-09- 2022-04- auprès des ménages issus IDA / 66650 3. Capacity Building A posteriori consultants par Direct 55,000.00 44,330.00 Signé 16 13 26 27 30 06 28 de l’ECVM Kinshasa pour entente directe mesurer l’impact du Covid- 19 (avec l’Institut National Statistique) ZR-FSRDC-244097-CS- INDV / Recrutement d'un(e) 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- Assistant(e) en IDA / 66650 4. Project Management A posteriori Individuel Limited 25,000.00 0.00 Annulé 16 21 11 16 14 Communication pour le Projet STEP 2 ZR-FSRDC-244127-CS- INDV / Recrutement de En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- deux (2) superviseurs AST IDA / 66650 4. Project Management A posteriori Individuel Limited 18,000.00 0.00 d'exécution 16 21 11 16 14 pour le Kasaï Central (Tshimbulu/ Dibaya et Tshimbulu rural) ZR-FSRDC-244128-CS- INDV / Recrutement de dix 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 18,720.00 0.00 Annulé (10) enquêteurs pour le 16 04 25 29 28 Kasaï Central (Tshimbulu_Rural) ZR-FSRDC-244129-CS- INDV / Recrutement d’un Chargé de Suivi des 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé Mécanismes de Gestion des 16 04 25 29 28 Plaintes du STEP 2 pour l’antenne du Nord Ubangi ZR-FSRDC-244132-CS- INDV / Recrutement d’un 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 25,000.00 0.00 Annulé Assistant Administratif et 16 21 11 16 14 Financier du STEP 2 pour le Nord Ubangi ZR-FSRDC-244133-CS- INDV / Recrutement de trois En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 45,000.00 0.00 (3) chauffeurs du STEP 2 d'exécution 16 21 11 16 14 pour le Nord Ubangi ZR-FSRDC-244136-CS- INDV / Recrutement d'un En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 superviseur AST pour le d'exécution 16 21 11 16 14 Nord Ubangi (yakoma) ZR-FSRDC-244137-CS- INDV / Recrutement de neuf En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 16,848.00 0.00 (9) enquêteurs pour le Nord d'exécution 16 04 25 29 28 Ubangi (Yakoma) ZR-FSRDC-244140-CS- INDV / Recrutement du En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Chargé de la Comptabilité d'exécution 16 04 25 29 28 du STEP 2 pour le Nord Kivu ZR-FSRDC-244143-CS- INDV / Recrutement d’un En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- Chargé des Travaux IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 d'exécution 16 04 25 29 28 d'Infrastructure Communautaire du STEP 2 pour le Nord Kivu ZR-FSRDC-244144-CS- INDV / Recrutement d’un En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Chargé de Suivi et d'exécution 16 04 25 29 28 Evaluation du STEP 2 pour le Nord Kivu ZR-FSRDC-244147-CS- INDV / Recrutement d’un En cours 2021-08- 2021-10- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Chargé MEDAC du STEP 2 d'exécution 16 11 04 25 29 28 pour le Nord Kivu ZR-FSRDC-244148-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé Chargé de MGP du STEP 2 16 04 25 29 28 pour le Nord Kivu ZR-FSRDC-244151-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé Chargé de Transfert 16 04 25 29 28 Monétaire du STEP 2 pour le Nord Kivu ZR-FSRDC-244156-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 25,000.00 0.00 Annulé Assistant Administratif et 16 04 25 29 28 Financier du STEP 2 pour le Nord Kivu ZR-FSRDC-244162-CS- INDV / Recrutement de dix 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 31,824.00 0.00 Annulé sept (17) enquêteurs pour 16 04 25 29 28 Goma dans le Nord Kivu ZR-FSRDC-244165-CS- INDV / Recrutement du En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Chargé de la Comptabilité d'exécution 16 04 25 29 28 du STEP 2 pour le Sud Kivu ZR-FSRDC-244172-CS- INDV / Recrutement d’un En attente 2021-08- 2021-10- 2021-10- 2021-12- 2022-06- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Chargé de Suivi et d'exécution 22 10 31 05 03 Evaluation du STEP 2 pour le Sud Kivu ZR-FSRDC-244173-CS- INDV / Recrutement d’un En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- Chargé des Sauvegardes IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 d'exécution 16 04 25 29 28 Environnementales et Sociales du STEP 2 pour le Sud Kivu ZR-FSRDC-244177-CS- INDV / Recrutement d’un En cours 2021-08- 2021-10- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Chargé MEDAC du STEP 2 d'exécution 16 11 04 25 29 28 pour le Sud Kivu ZR-FSRDC-244179-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé Chargé de MGP du STEP 2 16 04 25 29 28 pour le Sud Kivu ZR-FSRDC-244181-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé Chargé de Transfert 16 04 25 29 28 Monétaire du STEP 2 pour le Sud Kivu ZR-FSRDC-244182-CS- INDV / Recrutement d’un En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Chargé de Passation des d'exécution 16 04 25 29 28 Marchés du STEP 2 pour le Nord Kivu ZR-FSRDC-244188-CS- INDV / Recrutement d’un 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 25,000.00 0.00 Annulé Assistant Administratif et 16 21 11 16 14 Financier du STEP 2 pour le Nord Kivu ZR-FSRDC-244191-CS- INDV / Recrutement de trois En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 45,000.00 0.00 (3) chauffeurs du STEP 2 d'exécution 16 21 11 16 14 pour le Sud Kivu ZR-FSRDC-244192-CS- INDV / Recrutement de En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 18,000.00 0.00 deux (2) superviseurs AST d'exécution 16 21 11 16 14 dans le Sud Kivu (Uvira et Bukavu) ZR-FSRDC-244193-CS- INDV / Recrutement de En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 79,560.00 0.00 trente quatre (34) d'exécution 16 04 25 29 28 enquêteurs pour le Sud Kivu (20 Bukavu, 14 Uvira) ZR-FSRDC-244205-CS- INDV / Recrutement d’un En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- Chargé des Travaux IDA / 66650 4. Project Management A posteriori Individuel Direct 50,000.00 0.00 d'exécution 16 26 16 21 19 d'Infrastructure Communautaire du STEP 2 pour l’Ituri ZR-FSRDC-244207-CS- INDV / Recrutement d’un En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- Chargé des Sauvegardes IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 d'exécution 16 04 25 29 28 Environnementales et Sociales du STEP 2 pour l’Ituri ZR-FSRDC-244208-CS- INDV / Recrutement d’un En attente 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- Chargé en Travaux à Haute IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 d'exécution 16 04 25 29 28 Intensité de Main d'Œuvre du STEP 2 pour l’Ituri ZR-FSRDC-244211-CS- En cours 2021-08- 2021-10- 2021-10- 2021-10- 2021-11- 2022-05- INDV / Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 d'exécution 16 11 04 25 29 28 Chargé MEDAC du STEP 2 pour l’Ituri ZR-FSRDC-244213-CS- 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- INDV / Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 16 04 25 29 28 Chargé de MGP du STEP 2 pour l’Ituri ZR-FSRDC-244214-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé Chargé de Transfert 16 04 25 29 28 Monétaire du STEP 2 pour l’Ituri ZR-FSRDC-244219-CS- INDV / Recrutement d’un 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 25,000.00 0.00 Annulé Assistant Administratif et 16 21 11 16 14 Financier du STEP 2 pour l’Ituri ZR-FSRDC-244221-CS- INDV / Recrutement de 3 En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 45,000.00 0.00 chauffeurs du STEP 2 pour d'exécution 16 21 11 16 14 l’antenne du Sud Kivu ZR-FSRDC-244222-CS- En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- INDV / Recrutement d'un IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 d'exécution 16 21 11 16 14 Superviseur AST pour l’Ituri ZR-FSRDC-244223-CS- INDV / Recrutement de 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 51,840.00 0.00 Annulé vingt quatre (24) enquêteurs 16 04 25 29 28 pour l’Ituri (Bunia) ZR-FSRDC-245019-CS- INDV / Recrutement de vingt sept (27) Consultant 2. Livelihoods and En attente 2021-08- 2021-10- 2021-10- 2021-12- 2022-06- IDA / 66650 A posteriori Individuel Open 48,600.00 0.00 enquêteurs pour la collecte Employment Generation d'exécution 22 10 31 05 03 des données de mise en œuvre des activités des THIMO et des TIC ZR-FSRDC-232836-CS- INDV / Recrutement d'un En cours 2021-08- 2021-07- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 Assistant en Communication d'exécution 23 29 28 18 23 21 et TIC du Projet STEP 2 ZR-FSRDC-245144-CS- CDS / Recrutement par entente directe de l'Institut National de l'INS pour la Sélection de En attente 2021-08- 2021-09- 2021-11- 2022-05- poursuite de la mise en IDA / 66650 5. CERC A posteriori consultants par Direct 52,448.00 0.00 d'exécution 23 02 06 05 œuvre de l'enquête par entente directe téléphone auprès des ménages issus de de l'ECVM à Kinshasa pour mesurer l'impact du Covid-19 ZR-FSRDC-246412-CS- INDV / Recrutement de Cinq (5) Chargés en Transferts Monétaires (CTM) subdivisé en 5 lots: 2021-09- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 66650 4. Project Management A posteriori Individuel Open 250,000.00 0.00 Annulé Lo 1: CTM du Kasai Central; 01 07 20 10 15 13 Lot 2: CTM du Nord Ubangi; Lot 3: CTM du Nord Kivu; Lot 4: CTM du Sud Kivu; Lot 5: CTM de l'Ituri ZR-FSRDC-247147-CS- INDV / Recrutement de cinq (5) Chargés de Suivi du Numero Vert (CSNV) subdivisé en 5 lots: En cours 2021-09- 2021-09- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 90,000.00 0.00 Lot 1: CSNV du Kasai d'examen 06 28 27 18 22 21 Central Lot 2: CSNV du Nord Ubangi Lot 3: CSNV du Nord Kivu Lot 4: CSNV du Sud Kivu Lot 5: CSNV de l'Ituri ZR-FSRDC-247148-CS- INDV / Recrutement de cinq (5) Assistants Administratif et Financier (AAF) subdivisé en 5 lots: En attente 2021-09- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 90,000.00 0.00 Lot 1: AAF du Kasai Central d'exécution 06 11 02 06 05 Lot 2: AAF du Nord Ubangi Lot 3: AAF du Nord Kivu Lot 4: AAF du Sud Kivu Lot 5: AAF de l'Ituri ZR-FSRDC-249785-CS- INDV / Recrutement de Cinq (5) Chargés en Transferts Monétaires (CTM) pour les provinces suivantes: 1. La province du Kasai En cours 2021-09- 2021-08- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 66650 4. Project Management A posteriori Individuel Limited 250,000.00 0.00 Central; d'exécution 30 24 12 02 07 05 2. La province du Nord Ubangi; 3. La province du Sud Kivu. 4. La province du Nord Kivu 5. La province d'Ituri ZR-FSRDC-251691-CS- INDV / Recrutement d'un En cours 2021-09- 2021-09- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 40,000.00 0.00 chargé en gestion de base d'exécution 06 06 11 02 06 05 de données pour le Nord Ubangi ZR-FSRDC-244175-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- Chargé en Travaux à Haute IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 16 04 25 29 28 Intensité de Main d'Œuvre du STEP 2 pour le Sud Kivu ZR-FSRDC-244206-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé Chargé de Suivi et 16 04 25 29 28 Evaluation du STEP 2 pour l’Ituri ZR-FSRDC-244145-CS- INDV / Recrutement d’un 2021-08- 2021-10- 2021-10- 2021-11- 2022-05- Chargé des Sauvegardes IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 16 04 25 29 28 Environnementales et Sociales du STEP 2 pour le Nord Kivu ZR-FSRDC-253315-CS- INDV / Renouvellement du En attente 2021-09- 2021-09- 2021-09- 2021-09- 2021-09- IDA / 66650 4. Project Management A posteriori Individuel Direct 74,400.00 0.00 contrat du Chargé des d'exécution 20 22 23 25 26 Opération du STEP II_ François KABEMBA ZR-FSRDC-253615-CS- INDV / Contractualisation par entente directe avec Mr En cours 2021-10- 2021-09- 2021-11- 2021-11- 2022-01- 2022-07- IDA / 66650 4. Project Management A posteriori Individuel Direct 40,000.00 0.00 Alain KABONGO KUMWIMBA, d'examen 29 22 08 29 03 02 Chargé de la comptabilité au Sud-Kivu ZR-FSRDC-253936-CS- 2. Livelihoods and En attente 2021-10- 2021-10- 2021-11- 2021-12- 2022-06- INDV / Recrutement de 30 IDA / 66650 A posteriori Individuel Limited 9,000.00 0.00 Employment Generation d'exécution 20 25 15 20 18 AST pour les TMI ZR-FSRDC-253638-CS- INDV / Contractualisation En cours 2021-10- 2021-09- 2021-10- 2021-10- 2021-10- 2022-10- par entente directe avec Mr IDA / 66650 4. Project Management A posteriori Individuel Direct 48,000.00 0.00 d'exécution 15 24 17 18 20 15 Pascal KINGITSI KYAVULIKIRWA, CTIC au Sud- Kivu ZR-FSRDC-253614-CS- INDV / Contractualisation par entente directe avec Mr En cours 2021-10- 2021-09- 2021-10- 2021-11- 2021-11- 2022-10- IDA / 66650 5. CERC A posteriori Individuel Direct 52,000.00 0.00 Polidor KABANGWE, Expert d'exécution 29 28 31 01 03 29 en Transfert Monétaire pour le CERC KIN ZR-FSRDC-252496-CS- CDS / Contractualisation par entente directe avec Mr En cours 2021-09- 2021-09- 2021-10- 2021-10- 2021-10- 2022-09- Christian Raphaël NDAYE IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 d'exécution 30 24 02 03 05 30 KABATANCHI, Chargé de Passation des Marchés au Sud-Kivu ZR-FSRDC-252489-CS- CDS / Contractualisation par entente directe avec Mr En cours 2021-09- 2021-09- 2021-10- 2021-10- 2021-10- 2022-09- IDA / 66650 4. Project Management A posteriori Individuel Direct 36,900.00 0.00 Augustin FUABUNA d'exécution 30 24 02 03 05 30 DOMPETELO, Chargé de THIMO au Sud-Kivu ZR-FSRDC-256712-CS- INDV / (9): Recrutement de 4 Consultants Individuels 2. Livelihoods and En attente 2021-11- 2022-01- 2022-01- 2022-02- 2022-08- Superviseur devant appuyer IDA / 66650 A posteriori Individuel Open 10,000.00 0.00 Employment Generation d'exécution 15 03 24 28 27 la supervision des chantiers THIMO dans le Sud Kivu (Bukavu) Page 11 ZR-FSRDC-256713-CS- INDV / (8): Recrutement de 20 Consultants Individuels 2. Livelihoods and En attente 2021-11- 2022-01- 2022-01- 2022-02- 2022-08- IDA / 66650 A posteriori Individuel Open 48,000.00 0.00 chef de chantier pour la Employment Generation d'exécution 15 03 24 28 27 mise en œuvre des THIMO dans le Sud Kivu (Bukavu) ZR-FSRDC-257652-CS- INDV / (12): Recrutement En cours 2021-11- 2021-11- 2022-01- 2022-01- 2022-02- 2022-08- d'un Chargé de Comptabilité IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 d'exécution 15 12 03 24 28 27 du Projet STEP 2 pour l'antenne du Sud Kivu ZR-FSRDC-257656-CS- INDV / (13): Contractualisation par entente directe avec la En cours 2021-11- 2021-11- 2021-11- 2021-11- 2021-12- 2021-11- 2022-01- 2022-07- IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 Consultante Julie Patricia d'exécution 15 11 25 24 16 25 20 19 GILABI NGINDA comme Chargée de Suivi et Evaluation du Projet STEP 2 pour l'antenne d'Ituri ZR-FSRDC-257660-CS- INDV / (16): Recrutement de En attente 2021-11- 2021-11- 2021-12- 2022-01- 2022-07- IDA / 66650 5. CERC A posteriori Individuel Limited 60,000.00 0.00 cinq (5) Assistants en d'exécution 15 20 11 15 14 Sauvegardes pour le CERC de Kinshasa ZR-FSRDC-257658-CS- INDV / (15): Contractualisation par En cours 2021-11- 2021-11- 2021-11- 2021-11- 2021-12- 2022-01- 2022-07- entente directe avec le IDA / 66650 4. Project Management A posteriori Individuel Direct 48,000.00 0.00 d'exécution 15 23 25 26 16 20 19 Consultant Gilles BIRINDWA NTUGULO comme spécialiste en Sauvegardes Sociales du Projet STEP 2 ZR-FSRDC-257651-CS- INDV / (11): Recrutement de En attente 2021-11- 2022-01- 2022-01- 2022-02- 2022-08- 20 AST dans le cadre de la IDA / 66650 4. Project Management A posteriori Individuel Open 36,000.00 0.00 d'exécution 15 03 24 28 27 mise en œuvre des THIMO et des IDB dans le Sud Kivu/Bukavu ZR-FSRDC-258471-CS- INDV / (7): Recrutement de 40 PFE pour le suivi des plans de gestion 1. Support to Community En attente 2021-11- 2022-01- 2022-02- 2022-03- 2022-09- environnementale et sociale IDA / 66650 A posteriori Individuel Open 72,000.00 0.00 Resilience d'exécution 30 18 08 15 11 (PGES) des activités des chantiers THIMO et infrastructure dans la ville de Bukavu dans la province du Sud-Kivu ZR-FSRDC-262031-CS- INDV / (1): Recrutement d'un Assistant en Gestion En attente 2021-12- 2021-12- 2022-01- 2022-02- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 des Bases des données du d'exécution 24 29 19 23 22 projet STEP2/Antenne du Kasaï Central ZR-FSRDC-262055-CS- INDV / (8): Recrutement de 4 consultants Individuels superviseurs pour le 1. Support to Community En attente 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- contrôle et surveillance des IDA / 66650 A posteriori Individuel Open 40,000.00 0.00 Resilience d'exécution 30 17 10 14 11 travaux d’infrastructures communautaires dans la ville de Bukavu, à raison d'un superviseur pour 10 IDB ZR-FSRDC-262057-CS- INDV / (9): Recrutement d'un Assistant en Gestion En attente 2021-12- 2022-01- 2022-01- 2022-03- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 des Bases des Données du d'exécution 30 04 25 01 28 Projet STEP 2/Equipe régionale de l'antenne du Sud-Kivu ZR-FSRDC-262064-CS- INDV / (10): Recrutement de 4 Consultants individuels formateurs des Chefs 2. Livelihoods and En attente 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- IDA / 66650 A posteriori Individuel Open 10,000.00 0.00 d'équipes dans la cadre de Employment Generation d'exécution 30 17 10 14 11 la mise en œuvre des THIMO à Bukavu/Equipe régionale de l'antenne du Sud-Kivu ZR-FSRDC-262066-CS- INDV / (11): Recrutement d'un Chargé de Passation En attente 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 des Marchés du Projet STEP d'exécution 30 17 10 14 11 2/Equipe régionale de l'Antenne d'Ituri ZR-FSRDC-262067-CS- INDV / (12): Recrutement d'un Assistant en Gestion En attente 2021-12- 2022-01- 2022-01- 2022-03- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 des Bases des Données du d'exécution 30 04 25 01 28 Projet STEP 2/Equipe régionale de l'Antenne d'Ituri ZR-FSRDC-262069-CS- INDV / (13): Recrutement En attente 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- d'un Chargé de la IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 d'exécution 30 17 10 14 11 Comptabilité du Projet STEP 2/Equipe régionale de l'Antenne de l'Ituri ZR-FSRDC-262076-CS- INDV / (15): Recrutement d'un Chargé de En cours 2021-12- 2022-02- 2022-02- 2022-03- 2022-04- 2022-10- IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 Développement d'exécution 30 13 17 10 14 11 Communautaire du Projet STEP 2/Equipe régionale de l'Antenne du Nord-Kivu ZR-FSRDC-262078-CS- INDV / (16): Recrutement d'un Assistant en Gestion En attente 2021-12- 2022-01- 2022-01- 2022-03- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 des Bases des Données du d'exécution 30 04 25 01 28 Projet STEP 2/Equipe régionale de l'Antenne du Nord-Kivu ZR-FSRDC-262072-CS- INDV / (14) : Contractualisation avec le consultant Derrick MANE En cours 2021-11- 2021-11- 2021-12- 2021-12- 2022-02- 2022-08- GABE BAHAYA comme IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 d'exécution 30 23 10 31 04 03 Chargé de Développement Communautaire et Gestion des Conflits du STEP II pour l'équipe régionale de l’antenne du Sud Kivu ZR-FSRDC-264821-CS- INDV / (8): Recrutement de 17 consultants individuels 1. Support to Community En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- (DPO) pour le contrôle et IDA / 66650 A posteriori Individuel Limited 95,625.00 0.00 Resilience d'exécution 16 21 11 16 12 surveillance des travaux de construction des écoles dans deux secteurs au Kasaï Central ZR-FSRDC-264823-CS- INDV / (9): Recrutement de 9 consultants individuels (DPO) pour le contrôle et 1. Support to Community En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 50,625.00 0.00 surveillance des travaux de Resilience d'exécution 16 21 11 16 12 construction des centres de santé dans deux secteurs au Kasaï central ZR-FSRDC-264825-CS- INDV / (10): Recrutement de 4 consultants individuels (DPO) pour le contrôle et 1. Support to Community En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 22,500.00 0.00 surveillance des travaux de Resilience d'exécution 17 22 12 17 13 forage mécanique d’eau dans deux secteurs du Kasaï Central ZR-FSRDC-264831-CS- INDV / (16): Recrutement de 17 PFE dans le cadre de la 1. Support to Community En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 38,250.00 0.00 construction des écoles Resilience d'exécution 16 21 11 16 12 dans les secteurs Dibataie et Kamuandu au Kasaï Central ZR-FSRDC-264834-CS- INDV / (17): Recrutement de 9 PFE dans le cadre de la 1. Support to Community En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- construction des centres de IDA / 66650 A posteriori Individuel Limited 20,250.00 0.00 Resilience d'exécution 18 23 13 18 14 santé dans les secteurs Dibataie et Kamuandu au Kasaï Central ZR-FSRDC-264837-CS- INDV / (18): Recrutement de 4 PFE dans le cadre des 1. Support to Community En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 9,000.00 0.00 travaux de forage Resilience d'exécution 16 21 11 16 12 mécanique d’eau dans les secteurs Dibataie et Kamuandu au Kasaï Central ZR-FSRDC-264848-CS- En attente 2021-12- 2022-02- 2022-03- 2022-04- 2022-10- INDV / (1): Chargé des IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 d'exécution 24 11 04 08 05 Techniques de l’Information (IT) du STEP 2 ZR-FSRDC-264849-CS- INDV / (2): Assistant en En attente 2021-12- 2021-12- 2022-01- 2022-02- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 Gestion de Base des d'exécution 24 29 19 23 22 Données pour le Kasaï Central ZR-FSRDC-264850-CS- INDV / (3): Assistant du En attente 2021-12- 2021-12- 2022-01- 2022-02- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 Suivi du Numéro Vert pour d'exécution 24 29 19 23 22 le Nord-Ubangi ZR-FSRDC-264851-CS- INDV / (4): Assistant en En attente 2021-12- 2021-12- 2022-01- 2022-02- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 Gestion de Base des d'exécution 24 29 19 23 22 Données pour le Sud-Kivu ZR-FSRDC-264852-CS- En attente 2021-12- 2021-12- 2022-01- 2022-02- 2022-08- INDV / (5): Assistant IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 d'exécution 24 29 19 23 22 Administratif et Financier pour le Sud-Kivu ZR-FSRDC-265048-CS- INDV / (1): Chargé de En attente 2022-01- 2022-03- 2022-03- 2022-04- 2022-10- Développement IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 d'exécution 12 02 23 27 24 Communautaire pour le Nord-Kivu ZR-FSRDC-265051-CS- INDV / (3): Assistant en En attente 2022-01- 2022-01- 2022-02- 2022-03- 2022-09- IDA / 66650 4. Project Management A posteriori Individuel Limited 36,600.00 0.00 Gestion de Base des d'exécution 12 17 07 14 10 Données du Nord-Kivu ZR-FSRDC-265053-CS- En attente 2022-01- 2022-01- 2022-02- 2022-03- 2022-09- INDV / (4): Assistant du IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 d'exécution 12 17 07 14 10 Suivi du Numéro Vert du Nord-Kivu ZR-FSRDC-265058-CS- En attente 2022-01- 2022-01- 2022-02- 2022-03- 2022-09- INDV / (5): Assistant IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 d'exécution 12 17 07 14 10 Administratif et Financier du Nord-Kivu ZR-FSRDC-265061-CS- En attente 2022-01- 2022-03- 2022-03- 2022-04- 2022-10- INDV / (6): Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 d'exécution 12 02 23 27 24 Comptabilité de l'Ituri ZR-FSRDC-265064-CS- INDV / (7): Chargé de En cours 2022-01- 2022-02- 2022-03- 2022-03- 2022-04- 2022-10- IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 Développement d'exécution 12 13 02 23 27 24 Communautaire de l'Ituri ZR-FSRDC-265065-CS- En attente 2022-01- 2022-01- 2022-02- 2022-03- 2022-09- INDV / (9): Assistant en IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 d'exécution 12 17 07 14 10 Gestion de Base des Données de l'Ituri ZR-FSRDC-265069-CS- En cours 2022-01- 2022-02- 2022-01- 2022-02- 2022-03- 2022-09- INDV / (10): Assistant du IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 d'exécution 12 01 17 07 14 10 Suivi du Numéro Vert de l'Ituri ZR-FSRDC-265074-CS- En attente 2022-01- 2022-03- 2022-03- 2022-04- 2022-10- INDV / (11): Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 d'exécution 12 02 23 27 24 Passation des Marchés de l'Ituri ZR-FSRDC-265075-CS- En attente 2022-01- 2022-01- 2022-02- 2022-03- 2022-09- INDV / (12): Assistant IDA / 66650 4. Project Management A posteriori Individuel Limited 24,600.00 0.00 d'exécution 12 17 07 14 10 Administratif et Financier de l'Ituri ZR-FSRDC-266503-CS- INDV / (10): Recrutement de 200 consultants individuels 2. Livelihoods and En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 240,000.00 0.00 chef d'équipe pour la mise Employment Generation d'exécution 10 15 05 10 06 en œuvre des THIMO dans le Sud-Kivu (Bukavu) ZR-FSRDC-256710-CS- INDV / (10): Recrutement de 200 Consultants Individuels 2. Livelihoods and 2021-11- 2022-01- 2022-01- 2022-02- 2022-08- IDA / 66650 A posteriori Individuel Open 240,000.00 0.00 Annulé chef d'équipe pour la mise Employment Generation 15 03 24 28 27 en œuvre des THIMO dans le Sud Kivu (Bukavu) ZR-FSRDC-266508-CS- INDV / (14): Recrutement de En attente 2022-01- 2022-01- 2022-02- 2022-03- 2022-09- IDA / 66650 4. Project Management A posteriori Individuel Limited 18,000.00 0.00 l'l'ASNV pour l'antenne du d'exécution 12 17 07 14 10 Sud-Kivu ZR-FSRDC-258478-CS- 2021-11- 2022-01- 2022-02- 2022-03- 2022-09- INDV / (14): Recrutement du IDA / 66650 4. Project Management A posteriori Individuel Open 18,000.00 0.00 Annulé 30 18 08 15 11 ASNV pour l'antenne du Sud- Kivu ZR-FSRDC-266522-CS- INDV / (4): Contractualisation par En attente 2022-01- 2022-01- 2022-02- 2022-03- 2022-09- entente directe avec Mme IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 d'exécution 12 22 12 19 15 Jocelyne KUMWUIMBA comme Chargée de Travaux à Haute Intensité de Main d'Œuvre à l'antenne du Sud- Kvu ZR-FSRDC-266524-CS- INDV / (4): Contractualisation par En attente 2022-01- 2022-01- 2022-02- 2022-03- 2022-09- entente directe avec Mr Jean IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 d'exécution 12 22 12 19 15 Paul NKONDOLO comme Chargé des Travaux à Haute Intensité de Main d'Œuvre à l'antenne de l'Ituri ZR-FSRDC-266685-CS- INDV / (14): Recrutement de 2 AST dans le cadre de la En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- construction des centres de IDA / 66650 4. Project Management A posteriori Individuel Limited 4,500.00 0.00 d'exécution 21 26 16 21 17 santé dans les secteurs de Dibataie et et Kamuandu au Kasaï Central ZR-FSRDC-266687-CS- INDV / (15): Recrutement d'un AST dans le cadre des En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 4. Project Management A posteriori Individuel Limited 2,250.00 0.00 travaux de forage d'exécution 15 20 10 15 11 mécanique d'eau dans les secteurs de Dibataie et et Kamuandu au Kasaï Central ZR-FSRDC-267027-CS- INDV / (36): RECRUTEMENT D’UN CONSULTANT INDIVIDUEL POUR LA FORMATION DES CHEFS 2. Livelihoods and En attente 2021-08- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Individuel Limited 6,900.00 0.00 D’EQUIPES DANS LE CADRE Employment Generation d'exécution 18 23 13 18 16 DE LA MISE EN ŒUVRE DE CHANTIERS DE TRAVAUX À HAUTE INTENSITÉ DE MAIN D’EOUVRE (THIMO) / « CASH FOR WORK » A YAKOMA ZR-FSRDC-267042-CS- INDV / (37): RECRUTEMENT DES DEUX CONSULTANTS INDIVIDUELS EN APPUI A LA 2. Livelihoods and En attente 2021-09- 2021-09- 2021-09- 2021-11- 2022-04- SUPERVISION DES IDA / 66650 A posteriori Individuel Limited 18,600.00 0.00 Employment Generation d'exécution 01 06 27 01 30 CHANTIERS DES TRAVAUX A HAUTE INTENSITE DE LA MAIN D’ŒUVRE (THIMO)/ « CASH FOR WORK » A YAKOMA ZR-FSRDC-266993-CS- INDV / (38): RECRUTEMENT DES NEUF CHEFS DE CHANTIERS POUR LA MISE 2. Livelihoods and En attente 2021-09- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Individuel Limited 21,600.00 0.00 EN ŒUVRE DE CHANTIERS Employment Generation d'exécution 10 15 06 10 09 DES TRAVAUX À HAUTE INTENSITÉ DE MAIN D’EOUVRE (THIMO) / « CASH FOR WORK » A YAKOMA. ZR-FSRDC-267005-CS- INDV / (39): RECRUTEMENT DES 90 CHEF D’EQUIPES POUR LA MISE EN ŒUVRE DE 2. Livelihoods and En attente 2021-09- 2021-09- 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Individuel Limited 108,000.00 0.00 CHANTIERS DES TRAVAUX À Employment Generation d'exécution 01 06 27 01 30 HAUTE INTENSITÉ DE MAIN D’EOUVRE (THIMO) / « CASH FOR WORK » A YAKOMA. ZR-FSRDC-267040-CS- INDV / (40): RECRUTEMENT DES 9 CONSULTANTS - AGENT DE SUIVI DE TERRAIN (ENQUETEURS) POUR LA 2. Livelihoods and En attente 2021-09- 2021-09- 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Individuel Limited 16,200.00 0.00 MISE EN ŒUVRE DE Employment Generation d'exécution 01 06 27 01 30 CHANTIERS DE TRAVAUX À HAUTE INTENSITÉ DE MAIN D’EOUVRE (THIMO) / « CASH FOR WORK » A YAKOMA. Page 12 ZR-FSRDC-267046-CS- INDV / (41): Recrutement des 18 consultants 2. Livelihoods and En attente 2021-11- 2021-11- 2021-12- 2022-01- 2022-07- individuels au poste de IDA / 66650 A posteriori Individuel Limited 81,000.00 0.00 Employment Generation d'exécution 23 28 19 23 22 Point Focal Environnemental et Social dans le cadre des chantiers THIMO à YAKOMA ZR-FSRDC-267016-CS- INDV / (42): RECRUTEMENT DES 30 CONSULTANTS – 2. Livelihoods and En attente 2021-10- 2021-10- 2021-11- 2021-12- 2022-06- IDA / 66650 A posteriori Individuel Limited 27,000.00 0.00 AGENT DE SUIVI DE TERRAIN Employment Generation d'exécution 10 15 05 10 08 (ENQUETEURS) POUR LA MISE EN ŒUVRE DE TMI A LEMBO ZR-FSRDC-266682-CS- INDV / (13): Recrutement de 17 AST dans le cadre de la En attente 2022-03- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 4. Project Management A posteriori Individuel Limited 15,750.00 0.00 construction des écoles d'exécution 10 15 05 10 06 dans les secteurs de Dibataie et et Kamuandu au Kasaï Central ZR-FSRDC-272096-CS- INDV / (2): Recrutement de 16 consultants Individuels DPO pour le contrôle et 1. Support to Community En attente 2022-02- 2022-03- 2022-03- 2022-04- 2022-10- IDA / 66650 A posteriori Individuel Limited 112,000.00 0.00 surveillance des travaux Resilience d'exécution 28 05 26 30 27 d’infrastructures communautaires dans la ville de Bukavu-Sud Kivu ZR-FSRDC-272099-CS- INDV / (3): Recrutement de 2 consultants Individuels superviseurs pour le 1. Support to Community En attente 2022-02- 2022-03- 2022-03- 2022-04- 2022-10- IDA / 66650 A posteriori Individuel Limited 18,000.00 0.00 contrôle et surveillance des Resilience d'exécution 28 05 26 30 27 travaux d’infrastructures communautaires dans la ville de Bukavu-Sud Kivu ZR-FSRDC-272123-CS- INDV / (16): Recrutement des 6 consultants 2. Livelihoods and En cours 2022-03- 2021-12- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 54,000.00 0.00 Individuels pour la mission Employment Generation d'examen 15 28 20 10 15 11 de supervision des chantiers THIMO dans la ville de Bunia- Ituri ZR-FSRDC-272125-CS- INDV / (17): Recrutement 2. Livelihoods and En cours 2022-03- 2021-12- 2022-03- 2022-04- 2022-05- 2022-11- des 24 consultants IDA / 66650 A posteriori Individuel Limited 57,600.00 0.00 Employment Generation d'examen 15 28 20 10 15 11 Individuels pour la mission de chef de chantier des THIMO à Bunia-Ituri ZR-FSRDC-272128-CS- INDV / (18): Recrutement des 240 consultants 2. Livelihoods and En cours 2022-03- 2021-12- 2022-03- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 288,000.00 0.00 Individuels pour la mission Employment Generation d'examen 15 28 20 10 15 11 de chef d’équipe des chantiers THIMO à Bunia- Ituri ZR-FSRDC-272131-CS- INDV / (19): Recrutement 2. Livelihoods and En cours 2022-03- 2021-12- 2022-03- 2022-04- 2022-05- 2022-11- des 24 consultants IDA / 66650 A posteriori Individuel Limited 43,200.00 0.00 Employment Generation d'examen 15 28 20 10 15 11 Individuels pour la mission de PFE des chantiers THIMO à Bunia-Ituri ZR-FSRDC-272669-CS- INDV / (20): Recrutement de 24 consultants individuels En cours 2022-03- 2021-12- 2022-04- 2022-04- 2022-05- 2022-11- IDA / 66650 4. Project Management A posteriori Individuel Limited 43,200.00 0.00 pour la mission des Agent d'examen 30 28 04 25 30 26 de Suivi de Terrain (AST) de 24 chantiers THIMO à Bunia- Ituri ZR-FSRDC-272672-CS- INDV / (49): Recrutement de 4 consultants individuels 2. Livelihoods and En attente 2022-03- 2022-04- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 36,000.00 0.00 pour la mission de Employment Generation d'exécution 30 04 25 30 26 supervision des chantiers THIMO dans la ville de Goma-Nord Kivu ZR-FSRDC-272673-CS- INDV / (50): Recrutement de 2. Livelihoods and En attente 2022-03- 2022-04- 2022-04- 2022-05- 2022-11- 18 consultants individuels IDA / 66650 A posteriori Individuel Limited 43,200.00 0.00 Employment Generation d'exécution 30 04 25 30 26 pour la mission de chef de chantier des THIMO à Goma- Nord Kivu ZR-FSRDC-272675-CS- INDV / (51): Recrutement de 180 consultants individuels 2. Livelihoods and En attente 2022-03- 2022-04- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 216,000.00 0.00 pour la mission de chef Employment Generation d'exécution 30 04 25 30 26 d'équipe des chantiers THIMO à Goma-Nord Kivu ZR-FSRDC-272676-CS- INDV / (52): Recrutement de 18 consultants individuels 2. Livelihoods and En attente 2022-03- 2022-04- 2022-04- 2022-05- 2022-11- IDA / 66650 A posteriori Individuel Limited 32,400.00 0.00 pour la mission de PFE des Employment Generation d'exécution 31 05 26 31 27 chantiers THIMO à Goma- Nord Kivu ZR-FSRDC-274022-CS- CDS / Recrutement de Price WaterHouse Coopers _ RDC Sélection de En cours 2022-02- 2022-01- 2022-03- 2022-02- 2022-05- 2022-11- pour l'audit externe des IDA / 66650 4. Project Management A posteriori consultants par Direct 25,000.00 0.00 d'exécution 28 25 10 01 14 10 comptes du STEP Exercice_ entente directe 18 septembre 2020 au 31 décembre 2021 ZR-FSRDC-274127-CS- INDV / Recrutement d'un En cours 2022-04- 2022-01- 2022-06- 2022-07- 2022-08- 2023-02- IDA / 66650 4. Project Management A posteriori Individuel Open 54,000.00 0.00 spécialiste en passation des d'exécution 29 25 17 08 12 08 marchés au sein de la CG de STEPII ZR-FSRDC-274128-CS- INDV / Recrutement d'un En cours 2022-04- 2022-01- 2022-06- 2022-07- 2022-08- 2023-02- IDA / 66650 4. Project Management A posteriori Individuel Open 54,000.00 0.00 Spécialiste Suivi et d'exécution 29 25 17 08 12 08 Evaluation au sein de la CG du STEPII ZR-FSRDC-274738-CS- INDV / (45) Recrutement de 1. Support to Community En attente 2022-06- 2022-07- 2022-07- 2022-08- 2023-02- 20 DPO pour le contrôle et IDA / 66650 A posteriori Individuel Limited 142,500.00 0.00 Resilience d'exécution 30 05 26 30 26 surveillance des travaux des IDB_ Nord Kivu ZR-FSRDC-274776-CS- INDV / Recrutement de 30 1. Support to Community En cours 2022-06- 2022-02- 2022-07- 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Individuel Limited 213,750.00 0.00 DPO pour le contrôle et Resilience d'examen 30 10 05 26 30 26 surveillance des travaux des IDB ZR-FSRDC-274720-CS- INDV / (15) Recrutement de 3 Ingénieurs Superviseurs en Appui au CTIC pour les 1. Support to Community En cours 2022-06- 2022-02- 2022-07- 2022-07- 2022-08- 2023-02- IDA / 66650 A posteriori Individuel Limited 27,000.00 0.00 travaux des IDB (1 Resilience d'examen 30 08 05 26 30 26 superviseur pour 10 IDB) et (1 500 $*6mois pour chaque superviseur) _ ITURI ZR-FSRDC-274740-CS- INDV / (48) Recrutement de 1. Support to Community En attente 2022-06- 2022-07- 2022-07- 2022-08- 2023-02- 2 Ingénieurs Superviseurs IDA / 66650 A posteriori Individuel Limited 18,000.00 0.00 Resilience d'exécution 30 05 26 30 26 en Appui au CTIC pour les travaux des IDB_ Nord Kivu ZR-FSRDC-275576-CS- INDV / Recrutement d'un En attente 2022-05- 2022-07- 2022-08- 2022-09- 2023-03- IDA / 66650 4. Project Management A posteriori Individuel Open 24,600.00 0.00 Assistant en Passation des d'exécution 31 19 09 13 12 Marchés au sein de la CG de STEPII ZR-FSRDC-275577-CS- INDV / Recrutement d'un En attente 2022-05- 2022-07- 2022-08- 2022-09- 2023-03- Chargé de Suivi -Evaluation IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 d'exécution 31 19 09 13 12 au de l'équipe provinciale du Nord Ubangi ZR-FSRDC-278087-CS- INDV / 1 (KC-C2) Recrutement des 8 2. Livelihoods and En attente 2022-08- 2022-09- 2022-09- 2022-10- 2023-04- consultants Individuels pour IDA / 66650 A posteriori Individuel Limited 72,000.00 0.00 Employment Generation d'exécution 31 05 26 31 29 la mission de supervision des chantiers THIMO dans la cité de Kazumba (5) et Matamba (3)_ KC ZR-FSRDC-278089-CS- INDV / 2 (KC-C2) Recrutement des 34 2. Livelihoods and En attente 2022-08- 2022-09- 2022-09- 2022-10- 2023-04- consultants Individuels pour IDA / 66650 A posteriori Individuel Limited 81,600.00 0.00 Employment Generation d'exécution 31 05 26 31 29 la mission de chef de chantier des THIMO à Kazumba (21) et Matamba (13)_ KC ZR-FSRDC-278096-CS- INDV / 4 (KC-C2) Recrutement des 34 2. Livelihoods and En attente 2022-08- 2022-09- 2022-09- 2022-10- 2023-04- IDA / 66650 A posteriori Individuel Limited 61,200.00 0.00 consultants Individuels pour Employment Generation d'exécution 31 05 26 31 29 la mission de PFE des chantiers THIMO à Kazumba (21) et Matamba (13)_ KC ZR-FSRDC-278098-CS- INDV / 5 (KC-C4) Recrutement des 34 En attente 2022-08- 2022-09- 2022-09- 2022-10- 2023-04- consultants Individuels pour IDA / 66650 4. Project Management A posteriori Individuel Limited 61,200.00 0.00 d'exécution 31 05 26 31 29 la mission des Agents de suivi de terrain (AST) des chantiers THIMO à Kazumba (21) et Matamba (13)_ KC ZR-FSRDC-278099-CS- INDV / 6 (KC-C2) Recrutement de deux 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Individuel Limited 18,000.00 0.00 consultants superviseurs Employment Generation d'exécution 30 05 26 30 29 des activités de PFE à Kazumba (1) et Matamba (1)_ KC ZR-FSRDC-278100-CS- INDV / 7 (KC-C4) Recrutement de deux En attente 2022-08- 2022-09- 2022-09- 2022-10- 2023-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 18,000.00 0.00 consultants superviseurs d'exécution 31 05 26 31 29 des activités des AST à Kazumba (1) et Matamba (1)_ KC ZR-FSRDC-278104-CS- INDV / 8 (KC-C4) Recrutement deux En attente 2022-08- 2022-09- 2022-09- 2022-10- 2023-04- IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 consultants points focaux d'exécution 31 05 26 31 29 de l’équipe de zone des activités à Kazumba (1) et Matamba (1)_ KC ZR-FSRDC-278105-CS- INDV / 9 (KC-C4) Recrutement un consultant En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 Assistant Administratif de d'exécution 30 05 26 30 29 l’équipe de zone des activités à Kazumba et Matamba_ KC ZR-FSRDC-278107-CS- INDV / 10 (KC-C4) En attente 2022-08- 2022-09- 2022-09- 2022-10- 2023-04- Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Limited 4,800.00 0.00 d'exécution 31 05 26 31 29 consultant logisticien de l’équipe de zone des activités à Kazumba et Matamba_ KC ZR-FSRDC-278124-CS- INDV / 23 (SK-C2) Recrutement des 3 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Individuel Limited 27,000.00 0.00 consultants Individuels pour Employment Generation d'exécution 30 05 26 30 29 la mission de supervision des chantiers THIMO dans la ville d’Uvira_ SK ZR-FSRDC-278126-CS- INDV / 24 (SK-C2) Recrutement des 14 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Individuel Limited 33,600.00 0.00 consultants Individuels pour Employment Generation d'exécution 30 05 26 30 29 la mission de chef de chantier des THIMO à Uvira (14 chantiers) _ SK ZR-FSRDC-278128-CS- INDV / 25 (SK-C2) Recrutement des 140 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Individuel Limited 168,000.00 0.00 consultants Individuels pour Employment Generation d'exécution 30 05 26 30 29 la mission de chef d’équipes des chantiers THIMO à Uvira_ SK ZR-FSRDC-278129-CS- INDV / 26 (SK-C2) 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- Recrutement des 14 IDA / 66650 A posteriori Individuel Limited 25,200.00 0.00 Employment Generation d'exécution 30 05 26 30 29 consultants Individuels pour la mission de PFE des chantiers THIMO à Uvira_SK ZR-FSRDC-278130-CS- INDV / 27 (SK-C4) Recrutement des 14 En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 25,200.00 0.00 consultants Individuels pour d'exécution 30 05 26 30 29 la mission des Agents de suivi de terrain (AST) des chantiers THIMO à Uvira_SK ZR-FSRDC-278133-CS- INDV / 28 (SK-C2) 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- Recrutement d’un IDA / 66650 A posteriori Individuel Limited 9,000.00 0.00 Employment Generation d'exécution 30 05 26 30 29 consultant superviseur des activités de PFE à Uvira_ SK ZR-FSRDC-278136-CS- INDV / 29 (SK-C4) En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 d'exécution 30 05 26 30 29 consultant superviseur des activités des AST à Uvira_SK ZR-FSRDC-278137-CS- INDV / 30 (SK-C4) En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Limited 12,000.00 0.00 d'exécution 30 05 26 30 29 consultant point focal de l’équipe de zone des activités à Uvira ZR-FSRDC-278139-CS- INDV / 31 (SK-C4) En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 d'exécution 30 05 26 30 29 consultant Assistant Administratif de l’équipe de zone pour les activités à Uvira_ SK ZR-FSRDC-278147-CS- INDV / 32 (SK-C4) En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Limited 4,800.00 0.00 d'exécution 30 05 26 30 29 consultant logisticien de l’équipe de zone pour des activités à Uvira_SK ZR-FSRDC-278164-CS- INDV / 48 (NU-C2) Recrutement de 2 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Individuel Limited 18,000.00 0.00 consultants Individuels pour Employment Generation d'exécution 30 05 26 30 29 la mission de supervision des chantiers THIMO dans la cité de Bosobolo_ NU ZR-FSRDC-278166-CS- INDV / 49 (NU-C2) 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- Recrutement de 7 IDA / 66650 A posteriori Individuel Limited 16,800.00 0.00 Employment Generation d'exécution 30 05 26 30 29 consultants Individuels pour la mission de chef de chantier des THIMO à Bosobolo_ NU ZR-FSRDC-278168-CS- INDV / 50 (NU-C2) Recrutement des 70 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Individuel Limited 84,000.00 0.00 consultants Individuels pour Employment Generation d'exécution 30 05 26 30 29 la mission de chef d’équipes des chantiers THIMO à Bosobolo_ NU ZR-FSRDC-278169-CS- INDV / 51 (NU-C2) Recrutement des 7 2. Livelihoods and En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 A posteriori Individuel Limited 12,600.00 0.00 consultants Individuels pour Employment Generation d'exécution 30 05 26 30 29 la mission de PFE des chantiers THIMO à Bosobolo_ NU ZR-FSRDC-278172-CS- INDV / 52 (NU-C4) Recrutement des 7 En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 12,600.00 0.00 consultants Individuels pour d'exécution 30 05 26 30 29 la mission des Agents de suivi de terrain (AST) des chantiers THIMO à Bosobolo_NU ZR-FSRDC-278181-CS- INDV / 55 (NU-C4) En attente 2022-09- 2022-10- 2022-10- 2022-11- 2023-05- Recrutement d’un IDA / 66650 4. Project Management A posteriori Individuel Limited 12,000.00 0.00 d'exécution 30 05 26 30 29 consultant point focal de l’équipe de zone des activités à Bosobolo_ NU Page 13