The World Bank Implementation Status & Results Report Strengthening Transparency of the Extractives Industries through EITI Implementation (P176874) Strengthening Transparency of the Extractives Industries through EITI Implementation (P176874) EAST ASIA AND PACIFIC | Mongolia | Energy & Extractives Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2022 | Seq No: 1 | ARCHIVED on 24-Oct-2022 | ISR53285 | Implementing Agencies: Ministry of Mining and Heavy Industry, Mongolia Key Dates Key Project Dates Bank Approval Date: 09-Mar-2022 Effectiveness Date: 02-May-2022 Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To support achieve transparent systematic reporting to strengthen public accountability for the management of Mongolia’s mineral wealth. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Moderately Satisfactory Implementation Status and Key Decisions The Project became operational on May 2, 2022, and is currently focused on moving forward with the procurement process and preparing terms of reference and relevant documents to enable full delivery of Year 1 activities across all components. A detailed budget and work plan for the first year of project implementation are being developed. Risks Overall Risk Rating Risk Category Rating at Approval Previous Rating Current Rating Overall Moderate -- Moderate 5. Results Project Development Objective Indicators 10/24/2022 Page 1 of 4 The World Bank Implementation Status & Results Report Strengthening Transparency of the Extractives Industries through EITI Implementation (P176874) IN01197773 ►Satisfactory Progress achieved in EITI implementation (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Meaningful Progress -- Meaningful Progress Satisfactory Progress Date 31-Jan-2022 -- 23-Sep-2022 31-Dec-2023 IN01197774 ►Number of government agencies that have implemented mainstream data reporting as required under the 2019 EITI Standard. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3.00 Date 31-Jan-2022 -- 23-Sep-2022 13-Dec-2023 Intermediate Results Indicators IN01197723 ►Training of sub-national council members, with at least one focused on gender related issues (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5.00 Date 31-Jan-2022 -- 23-Sep-2022 31-Dec-2022 IN01197724 ►Multi-Stakeholder Group reaching gender parity (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 -- 30.00 48.00 Date 31-Jan-2022 -- 23-Sep-2022 31-Dec-2022 IN01197725 ►Implementation of the Beneficial Ownership Roadmap (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 31-Jan-2022 -- 23-Sep-2022 31-Mar-2023 IN01197771 ►Completing data systemization (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes 10/24/2022 Page 2 of 4 The World Bank Implementation Status & Results Report Strengthening Transparency of the Extractives Industries through EITI Implementation (P176874) Date 31-Jan-2022 -- 23-Sep-2022 30-Jun-2023 IN01197772 ►Disclosure of EITI required data by SOE's (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5.00 Date 31-Jan-2022 -- 23-Sep-2022 31-Dec-2023 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P176874 TF-B8169 Effective USD 0.50 0.50 0.00 0.08 0.42 17% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P176874 TF-B8169 Effective 04-Mar-2022 02-May-2022 02-May-2022 31-Dec-2023 31-Dec-2023 Cumulative Disbursements 10/24/2022 Page 3 of 4 The World Bank Implementation Status & Results Report Strengthening Transparency of the Extractives Industries through EITI Implementation (P176874) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 10/24/2022 Page 4 of 4