The World Bank                                                                                         Implementation Status & Results Report
            Managing Public Resources for Service Delivery (P173178)



Managing Public Resources for Service Delivery (P173178)


 AFRICA EAST | Mozambique | Governance Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2022 | Seq No: 1 | ARCHIVED on 19-Apr-2022 | ISR50783 |


 Implementing Agencies: Ministry of Economy and Finance, Republic Of Mozambique



 Key Dates


  Key Project Dates

   Bank Approval Date: 21-Dec-2021                                                  Effectiveness Date: 16-Mar-2022
   Planned Mid Term Review Date: 06-May-2024                                        Actual Mid-Term Review Date:
   Original Closing Date: 31-Mar-2026                                               Revised Closing Date: 31-Mar-2026
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective (PDO) is to improve domestic tax management, budget execution, and transparency and accountability in the
  management of public resources.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Strengthening Domestic Tax Management:(Cost $16.00 M)
 Enhancing Public Expenditure Management and Control:(Cost $60.85 M)
 Improving Independent External Oversight:(Cost $15.15 M)
 Project management:(Cost $4.00 M)
 Contingency Emergency Response COmponent

 Overall Ratings

 Name                                                                          Previous Rating                            Current Rating

 Progress towards achievement of PDO                                           --                                         Satisfactory
 Overall Implementation Progress (IP)                                          --                                         Satisfactory
 Overall Risk Rating                                                           --                                         Substantial


 Implementation Status and Key Decisions

  The project was declared effective on March 16, 2022. The last mission in February 2022 supported the Government of Mozambique in undertaking
  activities intended to ensure a smooth launch of project activities, including the initiation of key procurement activities and the recruitment of project
  officials.




4/19/2022                                                                                                                          Page 1 of 7
            The World Bank                                                                                   Implementation Status & Results Report
            Managing Public Resources for Service Delivery (P173178)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                             Rating at Approval            Previous Rating                Current Rating

  Political and Governance                                  Substantial                  --                             Substantial
  Macroeconomic                                             Low                          --                             Low
  Sector Strategies and Policies                            Substantial                  --                             Substantial
  Technical Design of Project or Program                    Substantial                  --                             Substantial
  Institutional Capacity for Implementation and
                                                            Substantial                  --                             Substantial
  Sustainability
  Fiduciary                                                 Substantial                  --                             Substantial
  Environment and Social                                    Low                          --                             Low
  Stakeholders                                              Moderate                     --                             Moderate
  Other                                                     --                            --                             --
  Overall                                                   Substantial                  --                             Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Improved domestic tax management

    IN01120659
    ►Number of taxpayers who file returns and make payments through the Taxpayer Portal (Number, Custom)

                                       Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                              0.00                        --                          0.00                      17,500.00

    Date                               30-Sep-2021                 --                          24-Mar-2022              31-Mar-2026

                                       The indicator measures the number of people who make tax returns and payments through the taxpayer
   Comments:
                                       portal (portal do contribuinte)


   Improved budget execution

    IN01120660
    ►Aggregate expenditure outturn as a percentage of approved budgeted expenditure over three years (Percentage, Custom)

                                       Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                              15.00                       --                          15.00                     10.00

    Date                               30-Sep-2021                 --                          31-Mar-2022              31-Mar-2026


4/19/2022                                                                                                                     Page 2 of 7
            The World Bank                                                                                     Implementation Status & Results Report
            Managing Public Resources for Service Delivery (P173178)



                                       The PEFA Indicators for predictability of in-year resource allocation, expenditure arrears, payroll controls,
                                       procurement, internal controls and internal audit measure the extent to which these elements meet
   Comments:
                                       performance standards required to effectively contribute to effective expenditure management and control.
                                       The methodology used to measure these indicators will be applied to determine the indicator percentages.


   Strengthened transparency and accountability mechanisms

    IN01120756
    ►Percentage of contracts awarded through competitive methods (Percentage, Custom)

                                       Baseline                          Actual (Previous)       Actual (Current)           End Target

    Value                              36.90                         --                          36.90                      55.00

    Date                               30-Sep-2021                   --                          31-Mar-2022                31-Mar-2026

   Comments:                           The total value of contracts awarded through competitive methods

     IN01120757
     Percentage of contracts which are awarded to enterprises that are owned predominantly by women (Percentage, Custom Supplement)

                                     Baseline                       Actual (Previous)           Actual (Current)            End Target

     Value                           0.00                           --                          0.00                        40.00



 Intermediate Results Indicators by Components



   Strengthening domestic revenue management

    IN01120761
    ►Tax base broadened through integrated taxpayer registries and online filing and payment of tax (Text, Custom, PBC)

                                       Baseline                          Actual (Previous)       Actual (Current)           End Target
                                       Tax systems and                                           Tax systems and
                                       databases are not                                         databases are not          Tax systems and
    Value                              integrated; Limited           --                          integrated; Limited        databases are fully
                                       functionality of online                                   functionality of online    integrated
                                       taxpayer portal                                           taxpayer portal
    Date                               30-Sep-2021                   --                          31-Mar-2022                31-Mar-2026

                                       This indicator will monitor progress towards the broadening of the tax base through the integration of tax
   Comments:
                                       databases and improvements in functionalities that enable taxpayers to file and pay taxes online.
    IN01120764
    ►Improved Intergovernmental Fiscal Transfer System (Text, Custom, PBC)

                                       Baseline                          Actual (Previous)       Actual (Current)           End Target
                                       Transfers to provinces,                                   Transfers to provinces,
                                       districts and                                             districts and              Transfer system
                                       municipalities are neither                                municipalities are         distribution formulae
    Value                                                            --
                                       transparent nor                                           neither transparent nor    (to districts)
                                       predictable nor need-                                     predictable nor need-      revisedand published
                                       based                                                     based
    Date                               30-Sep-2021                   --                          31-Mar-2022                30-Apr-2026




4/19/2022                                                                                                                      Page 3 of 7
            The World Bank                                                                                     Implementation Status & Results Report
            Managing Public Resources for Service Delivery (P173178)



                                       Fiscal transfers formula for subnational entities revised and applied; transfers made in a predictable
   Comments:
                                       manner


   Enhancing public expenditure management and control

    IN01120758
    ►Upgraded e-procurement system is operational (Text, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target
                                                                                                                            Upgraded e-
                                                                                                                            Procurement system is
                                       eProcurement system                                       eProcurement system
    Value                                                          --                                                       operational, in line with
                                       does not exist                                            does not exist
                                                                                                                            the 2015 PPDA Act
                                                                                                                            and Regulations.
    Date                               30-Sep-2021                 --                            31-Mar-2022                31-Mar-2026

                                       The indicator will monitor the progress from the Upgraded e-Procurement system is operational
   Comments:

    IN01120763
    ►Treasury function strengthened (Text, Custom, PBC)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target
                                                                                                 Treasury management        Treasury management
                                       Treasury management
                                                                                                 financial tools to         financial tools
                                       financial tools to
                                                                                                 record the                 strengthened to enable
                                       record the commitments
                                                                                                 commitments in due         recording of
    Value                              in due time misaligned,     --
                                                                                                 time misaligned,           expenditure
                                       incomplete, and focused
                                                                                                 incomplete, and            commitments and
                                       on cash rationing
                                                                                                 focused on cash            facilitate cash planning
                                                                                                 rationing
    Date                               30-Sep-2021                 --                            31-Mar-2022                30-Apr-2026

   Comments:                           Treasury functions reestablished to support move from cash rationing to cash management



   Improving transparency and accountability mechanisms

    IN01120759
    ►Number of training events delivered on financial reporting and supervision of SOEs (Number, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                        --                            0.00                       2.00

    Date                               01-Apr-2022                 --                            31-Mar-2022                31-Mar-2026

                                       The number of training events organized by IGEPE for its officials and for those in SOEs on financial
   Comments:
                                       reporting and supervision, for which the number of participants is at least 20
    IN01120760
    ►Increased capacity to audit public expenditure (Percentage, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              46.00                       --                            46.00                      65.00




4/19/2022                                                                                                                      Page 4 of 7
            The World Bank                                                                                      Implementation Status & Results Report
            Managing Public Resources for Service Delivery (P173178)




    Date                               30-Sep-2021                    --                         31-Mar-2022                31-Mar-2026

                                       The indicator will measure the proportion of public expenditure that is subjected to audit by the Tribunal
   Comments:
                                       Administrativo, represented through the government entities that are subjected to audit
    IN01120762
    ►Number of Citizen Assemblies held (Number, Custom)

                                       Baseline                       Actual (Previous)          Actual (Current)           End Target

    Value                              0.00                           --                         0.00                       3.00

    Date                               30-Sep-2021                    --                         31-Mar-2022                31-Mar-2026

                                       The project will support the GoM to organize Citizen Assemblies to improve citizen participation in the
   Comments:
                                       budget preparation and monitoring process.


 Performance-Based Conditions




   IN01120765
   ►PBC 1 Tax base broadened through integrated taxpayer registries and online filing and payment of tax (Text, Intermediate Outcome,
   13,000,000.00, 13.54%)

                                                                                                                             1 April - March 31,
                                  Baseline                       Actual (Previous)             Actual (Current)              2026
                                  Tax systems and                                              Tax systems and
                                  databases are not                                            databases are not
    Value                         integrated; Limited            --                            integrated; Limited           --
                                  functionality of online                                      functionality of online
                                  taxpayer portal                                              taxpayer portal
    Date                          --                             --                            31-Mar-2022                   --




   IN01120766
    ►PBC 2 Treasury function strengthened (Text, Intermediate Outcome, 9,000,000.00, 9.38%)

                                                                                                                             1 April - March 31,
                                  Baseline                       Actual (Previous)             Actual (Current)              2026
                                  Treasury management
                                                                                               Treasury management
                                  financial tools to
                                                                                               financial tools to record
                                  record the commitments in
                                                                                               the commitments in due
    Value                         due time misaligned,           --                                                          --
                                                                                               time misaligned,
                                  incomplete, and focused on
                                                                                               incomplete, and focused
                                  cash rationing
                                                                                               on cash rationing

    Date                          --                             --                            31-Mar-2022                   --




   IN01120767



4/19/2022                                                                                                                         Page 5 of 7
            The World Bank                                                                                      Implementation Status & Results Report
            Managing Public Resources for Service Delivery (P173178)




    ►PBC 3 Improved Intergovernmental Fiscal Transfer System (Text, Intermediate Outcome, 12,000,000.00, 12.50%)

                                                                                                                                1 April - March 31,
                                  Baseline                        Actual (Previous)             Actual (Current)                2026
                                                                                                Transfers to provinces,
                                  Transfers to provinces,
                                                                                                districts and municipalities
                                  districts and municipalities
    Value                                                         --                            are neither transparent nor     --
                                  are neither transparent nor
                                                                                                predictable nor need-
                                  predictable nor need-based
                                                                                                based
    Date                          --                              --                            31-Mar-2022                     --



 Data on Financial Performance


 Disbursements (by loan)

 Project        Loan/Credit/TF    Status       Currency        Original   Revised       Cancelled     Disbursed       Undisbursed                  % Disbursed


 P173178        IDA-D9470         Effective    USD               80.00      80.00             0.00          0.00               78.00                        0%

 P173178        TF-B7454          Effective    USD                7.00       7.00             0.00          0.00                7.00                        0%


 Key Dates (by loan)

 Project         Loan/Credit/TF    Status      Approval Date       Signing Date       Effectiveness Date     Orig. Closing Date         Rev. Closing Date

 P173178         IDA-D9470         Effective   21-Dec-2021         25-Jan-2022        16-Mar-2022            31-Mar-2026                31-Mar-2026
 P173178         TF-B7454          Effective   14-Jan-2022         14-Jan-2022        16-Mar-2022            31-Mar-2023                31-Mar-2023


Cumulative Disbursements




4/19/2022                                                                                                                            Page 6 of 7
            The World Bank                                             Implementation Status & Results Report
            Managing Public Resources for Service Delivery (P173178)




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


 There are no related projects.




4/19/2022                                                                             Page 7 of 7