Textual Part---Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan March 29, 2017 2. Date of General Procurement Notice: July 12, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year July 2017 to December 2019. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Prior Review Comments Method Threshold US$ 1. ICB (Goods) All 2. NCB (Goods) Above US$ 2,000,000 3. ICB (Works) All 4. NCB (Works) Above US$ 10,000,000 2. Pre-qualification. Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: (Fill later) 4. Any Other Special Procurement Arrangement: None 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Description Estimat Packa Domesti Review Comments . ed ges c by Bank No. Cost Prefere (Prior / US$ nce Post) million (yes/no) 1 Summary of 66.58 21 No Prior/Post the NCB (Works) 2 Summary of 1.42 2 No Post the NCB (Goods) 3 Summary of 0.13 1 No Post Shopping packages July 13, 2017 (Works and Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$1,000,000 2. Single Source (Firms) For SSS, USD50,000 (Para 3.9 of Consultant Guidelines, January 2011) and all other SSS contracts. 3. Individual Individuals ≥ USD 0.3 million; and for essential assignments (procurement / legal consultant). For SSS, USD20,000 (Para 5.6 of Consultant Guidelines, January 2011) 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 8 QCBS and 2 IC consulting services packages will be advance procurement. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Descriptio Estimat Package Review Comment n of ed s by s Assignme Cost Bank nt US$ (Prior / million Post) Summary 6.94 9 Prior/Po QCBS of number st of contracts that will be let under QCBS Summary 2.86 15 Post CQS/IC of number July 13, 2017 of contracts that will be let under other methods July 13, 2017 PROCUREMENT Vietnam : Vietnam Coastal Cities Sustainable Environment Project PLAN General Information Country: Vietnam 2017-07-24 Bank’s Approval Date of the Original Procurement Plan: 2022-12-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156143 GPN Date: 2017-07-12 Project Name: Vietnam Coastal Cities Sustainable Environment Project Loan / Credit No: IBRD / 87450, IDA / 60270 Binh Dinh Provincial Civil and Industrial Works Project Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned QN1-3 / Construction of scho Sanitation Infrastructure Exp Single Stage - One E 2019-01-0 IDA / 60270 Post Request for Bids Open - National 627,956.00 503,232.77 Completed 2017-10-12 2018-08-31 2017-10-20 2017-11-20 2018-10-08 2017-12-10 2019-07-22 2018-01-08 2019-08-02 ol sanitation blocks ansion nvelope 8 QN1-1 / Construction of box Sanitation Infrastructure Exp Single Stage - One E 1,969,107.2 2020-01-0 culvert drainage as replace IDA / 60270 Post Request for Bids Open - National 4,990,329.00 Signed 2017-10-05 2018-08-31 2017-10-12 2017-11-13 2018-10-09 2017-12-04 2019-07-22 2018-01-01 2019-08-02 ansion nvelope 3 1 ment for Phu Hoa open chan nel drainage QN1-2 / Construction of Long Sanitation Infrastructure Exp Single Stage - One E 2,067,259.1 2021-01-0 My leachate treatment compl IDA / 60270 Post Request for Bids Open - National 4,377,921.00 Signed 2017-10-12 2018-09-07 2017-10-20 2017-11-20 2018-10-10 2017-12-11 2019-07-22 2018-01-08 2019-08-02 ansion nvelope 2 8 ex with capacity of 400 m3/d ay QN2-1 / Construction of Chu Urban Connectivity Improve Single Stage - One E 2,372,281.1 2020-01-0 IBRD / 87450 Prior Request for Bids Open - National 3,553,061.00 Signed 2017-09-12 2018-08-22 2017-09-19 2017-10-20 2018-10-08 2017-11-09 2019-03-17 2018-01-05 2019-04-25 Y bridge and Huynh Tan Phat ment nvelope 3 5 bridge QN-1.4 / Rehabilitation of Ba Sanitation Infrastructure Exp Single Stage - One E 2022-07-0 u Sen lake up-stream and Ba IDA / 60270 Post Request for Bids Open - National 1,931,441.00 837,599.10 Signed 2020-04-05 2020-05-28 2020-04-12 2020-06-04 2020-05-14 2020-06-24 2020-06-04 2020-07-23 2020-07-02 2020-08-15 ansion nvelope 2 ch Dang combine sewers QN-1.5 / Construction of drai Sanitation Infrastructure Exp Single Stage - One E 1,657,041.3 2022-09-1 IDA / 60270 Post Request for Bids Open - National 4,286,123.00 Signed 2020-06-20 2020-07-29 2020-06-27 2020-07-29 2020-08-28 2020-08-19 2020-09-08 2020-09-16 2020-09-18 nage lines in Hoc Ba Bep are ansion nvelope 1 6 a QN-1.6 / Construction of terti Sanitation Infrastructure Exp Single Stage - One E 2022-10-1 IDA / 60270 Post Request for Bids Open - National 4,816,992.00 0.00 Canceled 2020-07-20 2020-07-27 2020-08-28 2020-09-18 2020-10-16 ary sewers ansion nvelope 6 QN-1.6A / Construction of ter Sanitation Infrastructure Exp Single Stage - One E 2022-04-1 IDA / 60270 Post Request for Bids Open - National 2,000,000.00 723,927.31 Signed 2020-08-27 2020-08-15 2020-08-27 2020-09-26 2020-09-14 2020-10-06 2020-09-24 2020-10-20 2020-10-15 tiary sewers (priority 1) ansion nvelope 3 QN-1.8 / Construction, expan Sanitation Infrastructure Exp Single Stage - One E 2,201,427.2 2022-10-1 IDA / 60270 Post Request for Bids Open - National 2,730,667.00 Signed 2020-08-27 2020-08-22 2020-08-28 2020-09-27 2020-09-21 2020-10-07 2020-09-21 2020-10-21 2020-09-30 sion of Long My landfill ansion nvelope 9 1 QN-1.7 / Construction, expan Sanitation Infrastructure Exp Single Stage - One E 7,415,186.6 2022-11-0 sion and upgrading capacity IDA / 60270 Prior Request for Bids Open - National 9,290,778.00 Signed 2020-09-15 2021-01-20 2020-09-18 2020-10-18 2021-03-06 2020-10-28 2021-09-09 2020-11-11 2021-09-21 ansion nvelope 5 1 for Nhon Binh WTP to 28.000 m3/day National Procure QN-1.6B / Construction of ter Sanitation Infrastructure Exp Single Stage - One E ment Document - 1,703,494.3 2022-09-1 IDA / 60270 Post Request for Bids Open - National 2,816,992.00 Signed 2021-06-20 2021-07-08 2021-06-27 2021-07-29 2021-08-10 2021-08-19 2021-08-21 2021-09-16 2021-09-14 tiary sewers (priority 2) ansion nvelope 1 Envelope proce 7 6 ss (Non Bank-SPD ) National Procure QN-1.9 / Tertiary Sewers, Pu Sanitation Infrastructure Exp Single Stage - One E ment Document - Pending Imp 2024-02-0 mping Stations and Pressure IDA / 60270 Post Request for Bids Open - National 2,894,524.00 0.00 2022-12-14 2022-12-15 2023-01-16 2023-01-19 2023-02-02 ansion nvelope 1 Envelope proce lementation 2 Pipelines ss (Non Bank-SPD ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual QN-1.2A / Supply and install ation of transformer station 250kVA-22/0,4kV and mediu Sanitation Infrastructure Exp Request for Quota Single Stage - One E m voltage line IDA / 60270 Post Open - National 73,043.00 59,904.50 Completed 2020-04-06 2020-06-05 2020-05-07 2020-05-05 2020-11-03 2020-11-30 ansion tions nvelope of 22kV for Long My leachate treatment complex QN1-11 / Supply and installa tion of automation, odor rem Sanitation Infrastructure Exp Single Stage - One E IDA / 60270 Post Request for Bids Open - National 558,630.00 451,283.27 Signed 2017-10-20 2021-12-11 2017-10-27 2017-11-27 2022-01-14 2017-12-18 2022-03-05 2018-01-15 2022-03-15 2019-01-15 oval and operation equipmen ansion nvelope t for pumping stations and W WTPs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual QN1-22 / Construction super Sanitation Infrastructure Exp Quality And Cost- vision consultant for Comp. 1 IBRD / 87450 Prior Open - National 1,012,000.00 0.00 Canceled 2017-08-01 2017-08-14 2017-08-04 2017-08-16 2017-09-25 2018-04-11 2017-11-01 2017-12-08 2018-01-02 2018-01-26 2022-05-26 ansion Based Selection & Comp. 2 of the project QN1-25 / Consultant for mon Sanitation Infrastructure Exp Consultant Qualifi itoring of environmental and IDA / 60270 Post Open - National 134,000.00 87,260.38 Signed 2017-12-29 2018-11-05 2018-01-04 2018-02-15 2019-03-01 2018-04-04 2019-05-10 2018-04-12 2019-08-14 2022-04-12 ansion cation Selection social safeguards QN1-21 / Consultant for surv ey, detailed design and biddi Sanitation Infrastructure Exp Quality And Cost- IDA / 60270 Prior Open - National 830,000.00 0.00 Canceled 2017-07-27 2017-07-30 2017-08-01 2017-07-31 2017-09-25 2018-03-21 2017-10-31 2017-12-11 2018-01-08 2018-02-19 2019-08-19 ng documents for remaining ansion Based Selection works of Component 1 Page 1 QN 1-21 / Consultant for sur vey, detailed design and bidd Sanitation Infrastructure Exp Quality And Cost- Open - Internationa IDA / 60270 Prior 830,000.00 859,050.70 Signed 2017-07-30 2017-07-31 2018-03-30 2018-04-04 2018-05-29 2018-06-11 2018-06-18 2018-10-11 2018-07-23 2018-12-24 2018-08-20 2019-01-09 2020-02-17 ing documents for remaining ansion Based Selection l works of Component 1 QN 1-22 / Construction supe Sanitation Infrastructure Exp Quality And Cost- Open - Internationa rvision consultant for Comp. IBRD / 87450 Prior 979,380.00 858,647.42 Signed 2017-08-04 2017-08-16 2018-04-12 2018-06-04 2018-06-04 2018-07-01 2018-09-04 2018-07-30 2018-12-04 2018-08-24 2018-12-21 2022-12-24 ansion Based Selection l 1 & Comp. 2 of the project QN1-27 / Independent Auditi Sanitation Infrastructure Exp Consultant Qualifi Under Implement IDA / 60270 Post Open - National 75,000.00 0.00 2019-09-05 2019-08-26 2019-09-13 2019-10-11 2019-12-01 2019-12-10 2022-06-10 ng for Phase 1 ansion cation Selection ation QN-1.28 / Independent Audit Sanitation Infrastructure Exp Consultant Qualifi Pending Impleme IDA / 60270 Post Open - National 44,144.00 0.00 2022-12-08 2022-12-29 2023-01-19 2023-02-18 2023-03-16 2025-03-15 ing for Phase 2 ansion cation Selection ntation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual QN1-23 / Individual Team Le Sanitation Infrastructure Exp Individual Consult IDA / 60270 Prior Open 374,000.00 0.00 Canceled 2017-08-29 2017-10-20 2017-11-06 2017-12-04 2022-05-04 ader for project management ansion ant Selection QN1-24 / Independent exper Sanitation Infrastructure Exp Individual Consult t/consultant for electro-mech IDA / 60270 Post Open 154,000.00 0.00 Canceled 2020-08-25 2020-10-20 2020-11-03 2020-11-29 2022-09-29 ansion ant Selection anical and automation equip ment Page 2