PROCUREMENT PLAN PERU INTEGRATED WATER RESOURCES MANAGEMENT IN TEN BASINS PROJECT P151851 I. General 1. Bank’s approval Date of the procurement Plan: Original, February 23, 2017 2. Date of General Procurement Notice: February 23, 2017 3. Period covered by this procurement plan: all the procurement process planned II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Below US$ 2 million None 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Below US$ 10 million None 2. Project Operational/Procurement Manual: Procurement implementation details activities will be outlined in the Project Operational Manual (POM) 3. Any Other Special Procurement Arrangements: None 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 Description Estimat Packa Domest Review Commen ed ges ic by Bank ts Cost Prefere (Prior / US$ nce Post) million (yes/no ) Summary of the ICB 25.2 5 No Prior (Goods) Summary of the NCB 9.28 5 No Post (Works) Summary of the NCB 3.16 4 No Post (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 350,000 All 2. Single Source (Firms) All 3. Individual Key personnel All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 350,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Description of Estimated Package Review Comments Assignment Cost s by Bank US$ million (Prior / Post) Summary of number of 15.95 10 Prior contracts that will be let under QCBS > US$ 350 mil Summary of number of 1.20 5 Post contracts that will be let under QCBS < US$ 350 mil PROCUREMENT Peru : Integrated Water Resources Management in Ten Basins PLAN General Information Country: Peru Bank’s Approval Date of the Original Procurement Plan: 2018-03-16 Revised Plan Date(s): (comma delineated, leave blank2022-09-16 if none) Project ID: P151851 GPN Date: Project Name: Integrated Water Resources Management in Ten Basins Loan / Credit No: IBRD / 87400 National Water Authority of the Ministry of Agriculture - Autoridad Nacional del Agua (ANA) Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount ( t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) US$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LPN 003 2018 ANA PGIRH B M / PERFORACIÓN E INSTALA Component 1: Consolidating Solicitud de ofert Single Stage - One 2,205,593.0 En ejecució 2018-07-2 2018-08-0 2018-07-2 2018-08-2 2018-09-2 2018-09-0 2018-09-2 2018-09-2 2019-01- CIÓN DE 58 PIEZÓMETROS E IBRD / 87400 Posterior Open - National 0.00 IWRM at the National Level as Envelope 0 n 6 8 9 8 5 7 7 6 23 N LOS ACUÍFEROS DE ICA Y TACNA: LOTE 01 ICA Y LOTE 02 TACNA LPN 007-2018-ANA-PGIRH-B M / PERFORACION E INSTALA CION DE 58 PIEZOMETROS E N LOS ACUIFEROS DE ICA Y Component 1: Consolidating Solicitud de ofert Single Stage - One 1,664,437.0 2,141,562. 2018-10-0 2018-10-1 2018-10-0 2018-10-1 2018-11-0 2018-11-2 2018-11-1 2018-11-2 2018-12-0 2018-12-0 2019-04- IBRD / 87400 Posterior Open - National Firmado TACNA lote 1 ICA 28 perfota IWRM at the National Level as Envelope 0 01 4 2 7 2 6 1 6 8 5 5 03 ciones metodo diamantina, l ote 2 TACNA 8 perforaciones metodo diamantina, lote 3 T ACNA 22 perforaciones meto do RC CP 001 2018 ANA PGIRH BM / OBRAS PRELIMINARES Y DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-1 2018-12- CIERRE PARA LA EJECUCIÒN IBRD / 87400 Posterior Limited 21,870.00 0.00 Cancelado IWRM at the National Level aciones Envelope 1 5 30 DE PERFORACIÒN E INSTALA CION DE 28 PIEZOMETROS E N LOS ACUIFEROS DE ICA CP 002 2018 ANA PGIRH BM / OBRAS PRELIMINARES Y DE Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2018-10-2 2018-11-1 2018-12- CIERRE PARA LA EJECUCION IBRD / 87400 Posterior Limited 13,587.00 0.00 IWRM at the National Level aciones Envelope endiente 1 5 30 DE PERFORACION E INSTALA CION DE 30 PIEZOMETROS E N LOS ACUIFEROS DE TACNA CP 003 2018 ANA PGIRH BM / CONSTRUCCION DE CASET Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-04-0 2019-05-0 2019-06- IBRD / 87400 Posterior Limited 55,239.00 0.00 Cancelado AS DE PROTECCION DE 30 PI IWRM at the National Level aciones Envelope 7 2 16 EZOMETROS EN LOS ACUIFE ROS DE TACNA LPN 008 2018 ANA PGIRH / Contratación para la Constru cción - Obras Civiles para la I mplementación de la Infraes Component 1: Consolidating Solicitud de ofert Single Stage - One 2019-06-2 2019-06-2 2019-07-2 2019-07-3 2019-08-1 2020-02- IBRD / 87400 Posterior Open - National 238,806.00 0.00 Cancelado tructura del Centro de Datos IWRM at the National Level as Envelope 4 6 6 1 7 13 , Laboratorio de Instrumenta ción, Centro de Monitoreo Y Modelamiento de Recursos Hídricos de la Autoridad Naci onal del Agua PE-ANA-126672-CW-RFQ / P erforación y habilitación de Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-09-2 2019-10-3 2019-09-2 2019-12- IBRD / 87400 Posterior Open - National 180,000.00 225,104.38 Firmado 18 piezómetros en los acuife IWRM at the National Level aciones Envelope 1 1 7 15 ros de Ica, Villacurí y Lancha s PE-ANA-121004-CW-RFQ / O bras Civiles para la Impleme ntación del Centro de Datos, Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-09-1 2019-10-2 2020-04- Laboratorio de Instrumentaci IBRD / 87400 Posterior Open - National 238,806.00 0.00 Cancelado IWRM at the National Level aciones Envelope 8 6 23 ón, Centro de Monitoreo y M odelamiento de Recursos Hí dricos de la Autoridad Nacio nal del Agua PE-ANA-139769-CW-RFB / O bras Civiles para la Impleme ntación del Centro de Datos, Component 1: Consolidating Solicitud de ofert Single Stage - One 2019-10-2 2019-10-2 2019-10-2 2020-02-1 2019-12-0 2019-11-2 2019-12-1 2019-12-2 2019-12-2 2020-02-1 2020-03- Laboratorio de Instrumentaci IBRD / 87400 Posterior Open - National 410,326.94 392,098.50 Firmado IWRM at the National Level as Envelope 1 5 6 8 7 9 7 0 7 4 26 ón, Centro de Monitoreo y M odelamiento de Recursos Hí dricos de la Autoridad Nacio nal del Agua PE-ANA-145138-CW-RFQ / C onstrucción de subestación Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-11-2 2020-04-1 2019-12-0 2020-07-3 2020-02- y red de media tensión para IBRD / 87400 Posterior Limited 58,541.00 62,575.10 Firmado IWRM at the National Level aciones Envelope 2 7 6 1 04 la electrificación del Centro de Procesamiento de Datos Secundarios ICA PE-ANA-165869-NC-RFB / C ONSTRUCCIÓN DE 22 ESTRU Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-05-0 2021-01-0 2020-07-0 2021-01-0 2020-09- IBRD / 87400 Posterior Open - National 117,848.00 155,808.84 Firmado CTURAS DE MEDICIÓN DE A IWRM at the National Level aciones Envelope 6 5 1 8 29 GUA EN LA REGIÓN TUMBES PE-ANA-165872-NC-RFB / C ONSTRUCCIÓN DE 11 ESTRU Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-05-0 2021-01-0 2020-07-0 2020-11-1 2020-08- IBRD / 87400 Posterior Open - National 58,924.00 69,812.60 Firmado CTURAS DE MEDICIÓN DE A IWRM at the National Level aciones Envelope 6 4 1 2 30 GUA EN LA REGIÓN MOQUE GUA PE-ANA-165873-NC-RFB / C ONSTRUCCIÓN DE 15 ESTRU Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-05-0 2021-01-0 2020-07-0 2020-11-1 2020-08- IBRD / 87400 Posterior Open - National 80,351.00 76,073.91 Firmado CTURAS DE MEDICIÓN DE A IWRM at the National Level aciones Envelope 6 5 1 6 30 GUA EN LA REGIÓN TACNA PE-ANA-166008-CW-RFB / C ONSTRUCCIÓN DE 73 ESTRU Component 1: Consolidating Solicitud de ofert Single Stage - One En ejecució 2020-05-0 2020-12-0 2020-05-0 2020-12-2 2020-06-1 2021-01-2 2020-07-1 2021-01-2 2020-08-2 2021-01- IBRD / 87400 Posterior Open - National 391,041.00 0.00 CTURAS DE MEDICIÓN DE A IWRM at the National Level as Envelope n 1 4 6 1 7 2 7 7 1 18 GUA EN LA REGIÓN ANCASH PE-ANA-166009-CW-RFB / C ONSTRUCCIÓN DE 87 ESTRU Component 1: Consolidating Solicitud de ofert Single Stage - One 2020-05-0 2021-02-0 2020-05-0 2021-02-1 2020-06-1 2021-03-3 2020-07-1 2021-06-0 2020-08-2 2021-09-0 2021-01- IBRD / 87400 Posterior Open - National 466,035.00 389,871.39 Firmado CTURAS DE MEDICIÓN DE A IWRM at the National Level as Envelope 1 6 6 1 7 1 7 4 1 2 18 GUA EN LA REGIÓN LIMA PE-ANA-145139-CW-RFQ / C Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-11-2 2019-12-0 2020-01- ONSTRUCCIÓN DE RED MAT IBRD / 87400 Posterior Limited 30,434.00 0.00 Cancelado IWRM at the National Level aciones Envelope 2 6 20 RIZ DE AGUA Y DESAGUE PE-ANA-216706-CW-RFB / C ONSTRUCCIÓN DE 73 ESTRU Component 1: Consolidating Solicitud de ofert Single Stage - One 2021-02-0 2021-02-0 2021-02-0 2021-02-0 2021-03-2 2021-03-3 2021-03-3 2021-05-1 2021-04-0 2021-07-1 2021-10- IBRD / 87400 Posterior Open - National 391,041.00 305,112.38 Firmado CTURAS DE MEDICIÓN DE A IWRM at the National Level as Envelope 2 5 7 9 1 0 1 7 5 3 02 GUA EN LA REGIÓN ANCASH (2da Convocatoria) PE-ANA-165981-CW-RFB / C ONSTRUCCIÓN DE 131 ESTR Component 1: Consolidating Solicitud de ofert Single Stage - One Other (with field 2021-08-2 2022-01- IBRD / 87400 Posterior Open - National 701,729.85 0.00 Cancelado UCTURAS DE MEDICIÓN DE IWRM at the National Level as Envelope for explanation) 6 23 AGUA EN LA REGIÓN PIURA PE-ANA-166005-CW-RFB / C ONSTRUCCIÓN DE 95 ESTRU Component 1: Consolidating Solicitud de ofert Single Stage - One Other (with field 2021-07-0 2021-06-2 2021-07-0 2021-06-3 2021-08-1 2021-08-1 2021-09-1 2021-09-1 2021-10-2 2021-11-1 2022-04- IBRD / 87400 Posterior Open - National 508,889.00 457,627.42 Firmado CTURAS DE MEDICIÓN DE A IWRM at the National Level as Envelope for explanation) 1 5 6 0 7 3 6 7 1 5 19 GUA EN LA REGIÓN LAMBAY EQUE PE-ANA-166006-CW-RFB / C ONSTRUCCIÓN DE 80 ESTRU Component 1: Consolidating Solicitud de ofert Single Stage - One Other (with field 2021-08-0 2022-01-1 2021-08-0 2022-01-2 2021-09-1 2022-02-2 2021-10-1 2022-03-3 2021-11-2 2022-05-1 2022-05- IBRD / 87400 Posterior Open - National 428,537.31 605,807.11 Firmado CTURAS DE MEDICIÓN DE A IWRM at the National Level as Envelope for explanation) 2 4 7 3 8 2 8 1 2 9 21 GUA EN LA REGIÓN LA LIBER TAD PE-ANA-166011-CW-RFB / C ONSTRUCCIÓN DE 107 ESTR Component 1: Consolidating Solicitud de ofert Single Stage - One Other (with field En ejecució 2021-08-0 2021-09-1 2021-08-0 2021-09-1 2021-09-1 2021-10-2 2021-10-1 2021-12-2 2021-11-2 2022-06- IBRD / 87400 Posterior Open - National 573,168.66 934,950.85 UCTURAS DE MEDICIÓN DE IWRM at the National Level as Envelope for explanation) n 2 3 7 4 8 1 8 1 2 20 AGUA EN LA REGIÓN ICA PE-ANA-166012-CW-RFB / C ONSTRUCCIÓN DE 190 ESTR Component 1: Consolidating Solicitud de ofert Single Stage - One Other (with field 1,017,777.0 En ejecució 2021-07-0 2021-08-2 2021-07-0 2021-08-2 2021-08-1 2021-09-2 2021-09-1 2021-10-2 2022-06- IBRD / 87400 Posterior Open - National 0.00 UCTURAS DE MEDICIÓN DE IWRM at the National Level as Envelope for explanation) 0 n 1 5 6 5 7 4 6 1 18 AGUA EN LA REGIÓN AREQUI PA PE-ANA-251359-CW-RFB / C Request for Bids ONSTRUCCIÓN DE 111 ESTR Component 1: Consolidating Solicitud de ofert Single Stage - One - Small Works SP 2021-09-0 2021-09-0 2021-09-0 2021-09-0 2021-09-0 2021-10-1 2021-10-0 2021-11-1 2021-11-1 2021-12-3 2022-05- IBRD / 87400 Posterior Open - National 558,000.00 575,368.28 Firmado UCTURAS DE MEDICIÓN DE IWRM at the National Level as Envelope D (1 envelope pr 3 7 5 7 8 3 8 9 2 0 11 AGUA EN LA REGIÓN PIURA ocess) PE-ANA-256754-CW-RFB / C ONSTRUCCIÓN DE 190 ESTR Component 1: Consolidating Solicitud de ofert Single Stage - One Other (with field 1,037,034. 2021-10-1 2022-01-1 2021-10-1 2022-01-2 2021-11-2 2022-02-2 2021-12-1 2022-05-1 2021-12-2 2022-07-2 2022-08- IBRD / 87400 Posterior Open - National 878,750.00 Firmado UCTURAS DE MEDICIÓN DE IWRM at the National Level as Envelope for explanation) 26 1 4 6 3 7 8 2 1 7 7 24 AGUA EN LA REGIÓN AREQUI PA (2da convocatoria) PE-ANA-272357-CW-RFQ / C ONSTRUCCIÓN DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One Other (with field Ejecución p 2022-02-0 2022-04-0 2022-09- URAS DE PROTECCIÓN Y CA IBRD / 87400 Posterior Limited 40,000.00 0.00 IWRM at the National Level aciones Envelope for explanation) endiente 6 3 30 SETAS EN PIEZÓMETROS UBI CADOS EN EL ACUÍFERO CAP LINA PE-ANA-126678-CW-RFQ / C ONSTRUCCIÓN DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One Other (with field Ejecución p 2022-03-0 2022-04-1 2022-07- URAS DE PROTECCIÓN Y CA IBRD / 87400 Posterior Open - National 80,000.00 0.00 IWRM at the National Level aciones Envelope for explanation) endiente 6 5 14 SETAS EN PIEZÓMETROS UBI CADOS EN EL ACUÍFERO ICA PE-ANA-235842-CW-RFB / C ONSTRUCCIÓN DE ESTRUCT Component 1: Consolidating Solicitud de ofert Single Stage - One Other (with field 2021-06-2 2021-06-2 2021-08-0 2021-09-0 2021-10-1 2022-01- URAS DE PROTECCIÓN Y CA IBRD / 87400 Posterior Open - National 90,000.00 0.00 Cancelado IWRM at the National Level as Envelope for explanation) 2 7 8 7 2 10 SETAS EN PIEZÓMETROS UBI CADOS EN EL ACUÍFERO CAP LINA PE-ANA-279825-CW-RFB / C ONSTRUCCIÓN DE 107 ESTR Component 1: Consolidating Solicitud de ofert Single Stage - One Other (with field 2022-03-0 2022-03-0 2022-04-0 2022-04-2 2022-05-2 2022-12- IBRD / 87400 Posterior Open - National 573,168.66 0.00 Cancelado UCTURAS DE MEDICIÓN DE IWRM at the National Level as Envelope for explanation) 4 9 8 3 8 24 AGUA EN LA REGIÓN ICA PE-ANA-272263-CW-DIR / C ONSTRUCCIÓN DE MIRA DE Component 1: Consolidating Solicitud de cotiz Single Stage - One Other (with field Ejecución p 2022-04-0 2022-05-3 2022-06- IBRD / 87400 Posterior Limited 5,350.00 0.00 NIVEL DE EMBALSE 44 MIRA IWRM at the National Level aciones Envelope for explanation) endiente 5 1 30 S - PRESA CONDORAMA PE-ANA-272265-CW-DIR / C ONSTRUCCIÓN DE AFORADO Component 1: Consolidating Solicitud de cotiz Single Stage - One Other (with field Ejecución p 2022-04-0 2022-05-3 2022-06- IBRD / 87400 Posterior Limited 25,125.00 0.00 R DE FILTRACIONES Y DREN IWRM at the National Level aciones Envelope for explanation) endiente 5 1 30 E: COLECTOR Y PRINCIPAL PE-ANA-272264-CW-DIR / C ONSTRUCCIÓN DE DOS AFO Component 1: Consolidating Solicitud de cotiz Single Stage - One Other (with field Ejecución p 2022-04-0 2022-05-3 2022-06- IBRD / 87400 Posterior Limited 27,592.00 0.00 RADORES DE FILTRACIONES IWRM at the National Level aciones Envelope for explanation) endiente 5 1 30 Y DREN IZQUIERDO Y DEREC HO - PRESA SUTUNTA PE-ANA-286119-CW-RFQ / C onstrucción de 03 aforadore s de filtraciones (Presas Sutu ta y Pasto Grande); 02 cajas Component 1: Consolidating Solicitud de cotiz Single Stage - One Other (with field Ejecución p 2022-04-1 2022-05-0 2022-06- de inspección y 120 metros IBRD / 87400 Posterior Limited 61,273.00 0.00 IWRM at the National Level aciones Envelope for explanation) endiente 3 1 30 de Drenes (Presa Pasto Gran de); y Nivelación de 117 pun tos de apoyo a las miras de nivel del embalse existentes (Presa Condoroma) GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 LPI 003 2018 ANA PGIRH / S UMINISTRO, INSTALACIÓN, P UESTA EN FUNCIONAMIENTO Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2018-07-0 2019-05-3 2018-07-1 2019-06-0 2018-09-1 2019-09-3 2018-09-2 2019-10-2 2018-10-2 2019-11-1 2019-01-0 IBRD / 87400 Previa 5,786,425.49 7,376,638.41 Firmado Y CAPACITACIÓN DEL EQUIP IWRM at the National Level as al Envelope 6 0 1 3 3 0 3 8 5 3 3 AMIENTO PARA EL SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPI 004 2018 ANA PGIRH / S UMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENT Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2018-07-0 2018-07-1 2018-09-1 2018-09-2 2018-10-2 2019-01-1 IBRD / 87400 Posterior 1,418,283.54 0.00 Cancelado O Y CAPACITACIÓN DE LOS S IWRM at the National Level as al Envelope 9 4 6 6 8 1 UBSISTEMAS PARA EL SISTE MA DE SEGURIDAD Y RESPA LDO DE LA INFORMACIÓN LPN 001 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN PUESTA EN FUNCIONAMIENT O Y CAPACITACIÓN DE EQUI Component 1: Consolidating Solicitud de ofert Single Stage - One 2018-07-0 2018-08-0 2018-07-1 2018-10-1 2018-09-1 2018-10-0 2018-09-2 2018-10-3 2022-08-2 2018-12-1 2022-10-2 PAMIENTO PARA LA PLATAF IBRD / 87400 Posterior Open - National 100,250.00 151,040.00 Firmado IWRM at the National Level as Envelope 9 5 4 1 6 5 6 1 5 0 4 ORMA TECNOLÓGICA PARA L A ADQUISICIÓN, DECODIFICA CIÓN, INTEGRACIÓN Y DISTR IBUCIÓN DE DATOS DE LAS ESTACIONES AUTOMATICAS CON TELEMETRIA LPN 002 2018 ANA PGIRH B M / ADQUISICIÓN DE CATOR Component 1: Consolidating Solicitud de ofert Single Stage - One 2018-07-2 2018-08-2 2018-07-3 2018-08-3 2018-09-1 2018-09-0 2018-09-2 2018-09-2 2018-09-2 2018-10-2 CE (14) VEHÍCULOS PARA LA IBRD / 87400 Posterior Open - National 592,732.00 500,888.09 Firmado IWRM at the National Level as Envelope 6 2 1 1 7 5 5 0 7 0 SUPERVISIÓN, SEDE CENTRA L Y ADMINISTRACIÓN DE LAS CUENCAS DEL PGIRH LPN 004 2018 ANA PGIRH B M / SUMINISTRO, INSTALACI ÓN, PUESTA EN FUNCIONAMI Component 1: Consolidating Solicitud de ofert Single Stage - One 2018-07-3 2018-08-0 2018-09-0 2018-09-1 2018-10-0 2019-01-0 IBRD / 87400 Posterior Open - National 564,000.00 0.00 Cancelado ENTO Y CAPACITACIÓN DE 1 IWRM at the National Level as Envelope 1 6 5 7 4 2 41 SENSORES CON SISTEMA DE TELEMETRÍA PARA PIEZÓ METROS EN ICA Y TACNA LPI 005 2018 ANA PGIRH B M / SUMINISTRO, INSTALACI Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One En ejecució 2018-07-2 2018-09-0 2018-07-3 2018-09-0 2018-09-1 2018-11-2 2018-09-1 2018-12-1 2018-10-0 2018-12-2 ÓN, PUESTA EN FUNCIONAMI IBRD / 87400 Previa 3,200,000.00 0.00 IWRM at the National Level as al Envelope n 6 7 1 7 4 2 9 4 4 8 ENTO Y CAPACITACIÓN DE I NSTRUMENTACIÓN DE PRES AS LPN 006 2018 ANA PGIRH B M / SUMINISTRO, INSTALACI Component 1: Consolidating Solicitud de ofert Single Stage - One 2018-09-1 2018-10-1 2018-09-1 2018-10-1 2018-10-1 2018-12-0 2018-10-2 2019-01-0 2018-11-1 2019-03-2 2019-02-1 ÓN, PUESTA EN FUNCIONAMI IBRD / 87400 Posterior Open - National 645,577.00 0.30 Firmado IWRM at the National Level as Envelope 3 2 8 2 8 3 1 3 3 5 1 ENTO Y CAPACITACIÓN DE I NSTRUMENTACIÓN DE PIEZO METROS CP 010 2018 ANA PGIRH BM / ADQUISICION DE EQUIPOS I Component 3: General Proje Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-1 2018-11-0 2018-11-1 2018-12-2 2018-12-1 NFORMATICOS Y ACCESORIO IBRD / 87400 Posterior Limited 45,151.52 6,737.05 Finalizado ct Adminstration aciones Envelope 1 6 6 9 1 3 S PERIFERICOS PARA LAS CO ORDINACIONES TECNICAS D E CUENCA CP 011 2018 ANA PGIRH BM Component 3: General Proje Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-2 2018-11-0 2018-12-0 2018-12-2 2018-12-2 / ADQUISICION DE LAP TOP P IBRD / 87400 Posterior Limited 14,470.00 16,425.03 Finalizado ct Adminstration aciones Envelope 1 3 6 6 1 8 ARA LA SEDE CENTRAL LPN 002 2019 ANA PGIRH B Component 1: Consolidating Solicitud de ofert Single Stage - One 2019-02-0 2019-02-2 2019-02-1 2019-02-2 2019-03-1 2019-03-2 2019-03-2 2019-04-0 2019-04-2 2019-04-2 2019-06-1 M2 / ADQUISICIÓN DE CORR IBRD / 87400 Posterior Open - National 55,000.00 46,967.58 Firmado IWRM at the National Level as Envelope 8 5 3 6 5 8 5 3 9 4 3 ENTOMETROS LPI 001 2019 ANA PGIRH B M / SUMINISTRO, INSTALACI Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2019-02-2 2019-03-0 2019-03-0 2019-03-0 2019-04-1 2019-04-2 2019-04-2 2019-06-0 2019-06-0 2019-07-1 2020-06-0 ÓN, PUESTA EN FUNCIONAMI IBRD / 87400 Previa 3,200,000.00 2,709,756.00 Firmado IWRM at the National Level as al Envelope 4 1 1 1 7 9 4 6 6 2 5 ENTO Y CAPACITACIÓN DE L A INSTRUMENTACIÓN PARA LA SEGURIDAD DE OCHO PR ESAS CP 010 B 2018 ANA PGRIH Component 2: Improving W BM / Equipos Informaticos y Solicitud de cotiz Single Stage - One 2018-11-1 2018-11-1 2018-12-0 2018-12-0 2018-12-2 2019-01-1 IBRD / 87400 RM in Selected Pilot River B Posterior Limited 20,121.00 19,216.27 Finalizado Accesorios Perifericos para l aciones Envelope 6 6 4 4 4 5 asins as Coordinaciones Tecnicas de Cuenca. LPN 009 2018 ANA PGIRH / ADQUISICION E INSTALACIO N DE EQUIPOS DE TELEMETR IA PARA ESTRUCTURAS DE M Component 1: Consolidating Solicitud de ofert Single Stage - One 2019-02-2 2019-03-0 2019-02-2 2019-03-1 2019-03-2 2019-04-0 2019-04-2 2019-05-2 IBRD / 87400 Posterior Open - National 147,962.00 0.00 Cancelado EDICION DE AGUA CON SEN IWRM at the National Level as Envelope 2 8 6 2 8 2 0 0 SORES PARA LAS ADMINISTR ACIONES DE LOCAL DE AGU A DE TUMBES, PIURA, LAMB AYEQUE, AREQUIPA PE-ANA-116125-GO-RFB / S UMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENT Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2019-05-2 2019-05-3 2019-06-0 2019-06-0 2019-07-1 2019-08-2 2019-08-1 2019-09-2 2019-09-1 2019-09-2 2020-01-1 IBRD / 87400 Previa 2,000,000.00 2,573,999.07 Firmado O Y CAPACITACIÓN DE LOS S IWRM at the National Level as al Envelope 7 0 1 3 3 6 2 0 6 7 4 UBSISTEMAS PARA EL SISTE MA DE SEGURIDAD Y RESPA LDO DE LA INFORMACIÓN LPI 006 2018 ANA PGIRH B M / ADQUISICIÓN, INSTALACI ÓN, CAPACITACIÓN Y PUEST A EN MARCHA DE EQUIPOS Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2018-09-1 2018-09-1 2018-10-1 2018-09-1 2018-10-2 2018-11-1 2020-08-1 IBRD / 87400 Previa 3,480,149.89 0.00 Cancelado DE MEDICIÓN DE AGUA Y TR IWRM at the National Level as al Envelope 0 5 5 7 5 9 0 ANSMISIÓN DE DATOS EN LA S CAPTACIONES Y BLOQUES DE RIEGO SELECCIONADOS EN LA COSTA DEL PERU PE-ANA-116523-GO-RFB / S UMINISTRO, INSTALACIÓN, P Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2019-10-1 2020-06-2 2019-10-1 2020-06-2 2019-11-2 2020-10-0 2019-12-0 2021-01-2 2020-01-0 2020-12-2 2022-01-0 UESTA EN FUNCIONAMIENTO IBRD / 87400 Previa 7,874,768.00 4,216,634.56 Firmado IWRM at the National Level as al Envelope 0 6 9 6 3 5 8 1 4 3 3 Y CAPACITACIÓN DE 153 EST ACIONES HIDROLÓGICAS CO N 33 EHCA LPI 001 ANA PGIRH / SUMINI STRO, INSTALACIÓN, PUEST Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2019-04-0 2019-04-1 2019-06-1 2019-07-0 2019-08-3 2020-08-3 A EN FUNCIONAMIENTO Y CA IBRD / 87400 Previa 7,874,768.00 0.00 Cancelado IWRM at the National Level as al Envelope 5 4 6 7 1 0 PACITACIÓN DE 153 ESTACI ONES HIDROLÓGICAS CON 3 3 EHCA PE-ANA-121041-GO-RFP / A Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-11-1 2019-12-1 IBRD / 87400 Posterior Open - National 36,882.35 0.00 Cancelado DQUISICIÓN DE PLOTTERS E IWRM at the National Level aciones Envelope 6 8 8 IMPRESORAS LPN 005 2018 ANA PGIRH B M / SUMINISTRO , INSTALACI ÓN, PUESTA EN FUNCIONAMI Component 1: Consolidating Solicitud de ofert Single Stage - One 2019-03-0 2019-03-0 2019-04-0 2019-04-1 2019-05-0 2019-07-0 IBRD / 87400 Posterior Open - National 1,418,283.54 0.00 Cancelado ENTO Y CAPACITACIÓN DE L IWRM at the National Level as Envelope 1 2 2 3 3 2 OS SUBSISTEMAS PARA EL SI STEMA DE SEGURIDAD Y RE SPALDO DE LA INFORMACIÓ N LPN 001 2019 ANA PGIRH B M / EQUIPAMIENTO PARA LA IMPLEMENTACIÓN DE LAS SA Component 2: Improving W Solicitud de ofert Single Stage - One 2019-10-0 2020-07-2 2019-10-0 2019-11-2 2020-09-0 2019-12-0 2020-10-0 2020-01-0 2020-10-3 2020-03-0 LAS DE MONITOREO HÍDRIC IBRD / 87400 RM in Selected Pilot River B Posterior Open - National 850,000.00 870,755.10 Firmado as Envelope 1 4 9 5 4 5 5 6 0 6 O EN LOS COORDINACIÓN D asins E RECURSOS HÍDRICOS DE LAS CUENCAS DE LA VERTIE NTE DEL ATLÁNTICO PE-ANA-134184-GO-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-09-1 2019-11-2 2019-10-0 2019-12-2 2019-10-2 DQUISICION DE SOFTWARE ( IBRD / 87400 Posterior Limited 32,613.00 37,219.02 Firmado IWRM at the National Level aciones Envelope 8 5 7 0 2 INC. LICENCIA) DISEÑO DE P ROCESOS PE-ANA-155600-GO-RFQ / A DQUISICIÓN DE EQUIPOS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-01-2 2020-02-0 2020-11-0 2020-03-0 MOSTRATIVOS: CUATRO DE IBRD / 87400 Posterior Open - National 13,134.00 8,703.10 Firmado IWRM at the National Level aciones Envelope 8 4 5 5 MEDICIÓN DE AGUA Y CUAT RO DE TRANSMISIÓN DE DA TOS. PE-ANA-158249-GO-RFB / S UMINISTRO, INSTALACIÓN, P UESTA EN FUNCIONAMIENTO Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One En ejecució 2020-03-1 2020-10-2 2020-03-2 2020-11-0 2020-05-0 2021-03-0 2020-05-2 2021-06-0 2020-06-3 2021-10-2 Y CAPACITACIÓN DE INSTRU IBRD / 87400 Previa 3,822,975.00 1,912,648.39 IWRM at the National Level as al Envelope n 7 0 2 3 6 5 6 3 0 3 MENTACIÓN PARA LA MEDICI ÓN DEL AGUA EN LAS CAPTA CIONES Y BLOQUES DE RIEG O EN LA COSTA DEL PERÚ PE-ANA-155601-GO-RFQ / A DQUISICIÓN DE ACCESORIO Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-01-2 2020-03-1 2020-02-0 2020-02-2 2020-04-0 S PARA CORRENTOMETROS IBRD / 87400 Posterior Open - National 5,970.00 5,448.45 Firmado IWRM at the National Level aciones Envelope 8 2 4 7 6 ELECTROMAGNÉTICOS (BAR RA CONCENTRICA HERES) LPI 002 ANA PGIRH / SUMINI STRO INSTALACION PUESTA Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2019-04-0 2019-04-1 2019-06-2 2019-07-0 2019-07-2 2020-07-2 EN FUNCIONAMIENTO Y CAP IBRD / 87400 Previa 3,190,000.00 0.00 Cancelado IWRM at the National Level as al Envelope 5 9 0 6 1 0 ACITACION DE 110 SISTEMA MECANIZADOS DE AFOROS PE-ANA-161081-GO-RFQ / S UMINISTRO, INSTALACIÓN, P UESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE 121 SIS TEMAS MECANIZADOS DE AF Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2020-03-1 2020-07-1 2020-03-2 2020-07-1 2020-05-0 2020-10-2 2020-06-0 2020-11-1 2020-07-0 2020-12-2 2021-12-2 IBRD / 87400 Previa 3,500,000.00 5,377,304.00 Firmado OROS, 05 PASARELAS METÁ IWRM at the National Level as al Envelope 6 5 1 6 2 3 1 3 6 3 8 LICAS PARA AFOROS Y WINC HES PARA AFOROS EN SECCI ONES DE CONTROL DE ESTA CIONES HIDROLÓGICAS PAR A FINES DE GESTIÓN DE REC URSOS HÍDRICOS PE-ANA-164500-GO-RFQ / c Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-03-2 2021-01-1 2020-04-0 2020-11-1 2020-06-0 ompra de flujometros ultras IBRD / 87400 Posterior Open - National 26,000.00 32,139.47 Firmado IWRM at the National Level aciones Envelope 7 3 3 9 4 onicos portátiles PE-ANA-165163-GO-RFQ / A Component 3: General Proje Solicitud de cotiz Single Stage - One 2020-04-1 2020-05-1 2020-05-2 DQUISICIÓN DE MOBILIARIO IBRD / 87400 Posterior Open - National 30,000.00 0.00 Cancelado ct Adminstration aciones Envelope 9 4 9 PARA LAS OFICINAS DEL PGI RH PE-ANA-165181-GO-RFQ / A DQUISICION DE EQUIPAMIEN Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-06-1 2020-11-1 2020-08-1 2020-11-2 2021-02-1 IBRD / 87400 Posterior Limited 23,000.00 7,198.79 Firmado TO PARA ANALISIS HIDROBI IWRM at the National Level aciones Envelope 9 0 4 5 0 OLOGICO EN LAS CUATRO C UENCAS PE-ANA-165894-GO-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One En ejecució 2020-04-2 2020-05-0 2020-07-0 DQUISICIÓN DE 03 NIVELES IBRD / 87400 Posterior Limited 2,687.00 0.00 IWRM at the National Level aciones Envelope n 2 8 7 DE INGENIERO, INCLUIDO AC CESORIOS PE-ANA-186823-GO-RFQ / A DQUISICIÓN E INSTALACIÓN Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-09-1 2020-10-2 2020-10-0 2020-11-1 2020-12-0 IBRD / 87400 Posterior Limited 18,000.00 23,490.72 Firmado DE BASES ANTI SÍSMICAS PA IWRM at the National Level aciones Envelope 8 9 6 8 5 RA EL SISTEMA ELÉCTRICO D EL CENTRO DE DATOS PE-ANA-116126-GO-RFB / A DQUISICIÓN DE EQUIPOS DE Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2019-05-2 2019-06-0 2019-07-1 2019-08-1 2019-09-1 2020-06-1 MEDICIÓN Y TRANSMISIÓN D IBRD / 87400 Previa 3,822,971.00 0.00 Cancelado IWRM at the National Level as al Envelope 7 1 3 2 6 2 E DATOS PARA EL CONTROL DEL AGUA EN LAS CAPTACIO NES Y BLOQUES DE RIEGO PE-ANA-164478-GO-RFB / A Component 1: Consolidating Solicitud de ofert Single Stage - One 2020-04-2 2020-04-2 2020-06-0 2020-07-0 2020-08-1 2021-02-0 DQUISICIÓN DE EQUIPOS DE IBRD / 87400 Posterior Open - National 247,100.00 0.00 Cancelado IWRM at the National Level as Envelope 0 5 6 6 0 6 MEDICIÓN DE CAUDAL - TIPO ADCP PE-ANA-167427-GO-RFQ / A dquisición de equipos de me Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-04-1 2020-05-2 2020-05-0 2020-07-1 2020-06-1 IBRD / 87400 Posterior Limited 37,500.00 61,518.14 Firmado dición de caudal y medición IWRM at the National Level aciones Envelope 5 9 5 0 9 de calidad de agua en camp o PE-ANA-163933-GO-RFB / A DQUISICIÓN DE EQUIPOS MU Component 1: Consolidating Solicitud de ofert Single Stage - One En ejecució 2020-04-0 2020-10-1 2020-04-0 2020-11-2 2020-05-1 2020-11-2 2020-06-1 2020-11-2 2020-07-2 2020-09-2 LTIPARÁMETROS PORTÁTILE IBRD / 87400 Posterior Open - National 755,000.00 0.00 IWRM at the National Level as Envelope n 1 9 6 5 8 3 7 3 2 0 S PARA MEDICIÓN DE CALID AD DE AGUA SUPERFICIAL PE-ANA-190562-GO-RFQ / A DQUISICION DE EQUIPOS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One En ejecució 2020-10-0 2022-05-3 2020-10-2 2020-12-2 IBRD / 87400 Posterior Limited 38,000.00 0.00 MUESTREO Y EQUIPOS MULT IWRM at the National Level aciones Envelope n 2 0 6 5 IPARAMETROS PARA AGUAS SUBTERRANEAS Page 2 PE-ANA-190602-GO-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-09-2 2020-10-2 2020-12-2 DQUISICION DE EQUIPOS DE IBRD / 87400 Posterior Limited 43,000.00 0.00 Cancelado IWRM at the National Level aciones Envelope 9 9 8 PROSPECCION GEOFISICA PE-ANA-190604-GO-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-09-3 2020-10-2 2020-12-2 DQUISICION DE SONDA DE R IBRD / 87400 Posterior Open - National 43,000.00 0.00 Cancelado IWRM at the National Level aciones Envelope 0 6 5 ESONANCIA MAGNETICA NU CLEAR PE-ANA-190605-GO-RFQ / A DQUISICION DE EQUIPOS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-09-3 2020-11-0 2021-01-0 IBRD / 87400 Posterior Limited 30,000.00 0.00 Cancelado PERFILAJE GEOFISICO Y DE C IWRM at the National Level aciones Envelope 0 4 3 AUDAL DE POZOS PE-ANA-190610-GO-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-09-2 2020-11-0 2021-01-0 DQUISICION DE EQUIPOS SIS IBRD / 87400 Posterior Limited 40,000.00 0.00 Cancelado IWRM at the National Level aciones Envelope 9 3 2 TEMA CMT PARA SEIS PIEZO METROS PE-ANA-194534-GO-RFB / A DQUISICIÓN DE CAMIONETA Component 1: Consolidating Solicitud de ofert Single Stage - One 2020-10-1 2021-01-1 2020-10-1 2020-11-2 2021-02-1 2020-12-0 2021-02-2 2021-01-0 2021-03-1 2021-02-0 IBRD / 87400 Posterior Open - National 183,000.00 192,284.31 Firmado S PARA LA SUPERVISION - E IWRM at the National Level as Envelope 2 1 7 8 5 8 6 5 9 4 QUIPO TECNICO COORDINAD O DE EHA- SMA PE-ANA-199721-GO-RFQ / I mpresoras Multifuncional Mo Component 2: Improving W nocromática para la Implem Solicitud de cotiz Single Stage - One 2020-10-1 2020-11-0 2020-10-2 2020-11-1 2021-02-2 IBRD / 87400 RM in Selected Pilot River B Posterior Limited 50,000.00 38,366.78 Firmado entación de las Salas de Mo aciones Envelope 8 2 8 6 5 asins nitoreo Hídrico en las Coordi naciones de Recursos Hídric os de las Cuencas de la Verti ente PE-ANA-202827-GO-RFQ / S uministro, instalación y pues ta en funcionamiento de tra Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-12-0 2020-11-1 2021-01-3 2020-12-0 2021-05-0 IBRD / 87400 Posterior Limited 50,000.00 49,857.20 Firmado nsmisión de datos via el saté IWRM at the National Level aciones Envelope 6 9 1 1 1 lite GOES de la instrumentac ión de presas poechos y san Lorenzo PE-ANA-202829-GO-RFB / S uministro, instalación y pues ta en funcionamiento de sen sor de nivel de agua del em Component 1: Consolidating Solicitud de ofert Single Stage - One 2020-12-0 2020-11-1 2020-12-0 2020-11-2 2021-01-1 2020-12-1 2021-02-1 2020-12-2 2021-03-2 2021-03-2 2021-06-2 IBRD / 87400 Posterior Open - National 190,000.00 318,318.01 Firmado balse y pluviómetro y del sis IWRM at the National Level as Envelope 1 2 6 5 7 7 6 8 3 9 1 tema de transmisión de dato s via satélite GOES de la inst rumentación en las siete pre sas priorizadas del PGIRH PE-ANA-206763-GO-RFQ / A dquisición de 01 correntóme Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-12-1 2020-12-1 2020-12-2 2021-01-1 2020-12-2 IBRD / 87400 Posterior Limited 12,000.00 13,228.32 Firmado tro para aforos de bajos cau IWRM at the National Level aciones Envelope 6 5 0 2 1 dales en campo Cuenca pilot o Mayo PE-ANA-208164-GO-RFB / A dquisición de Equipos Multip Component 1: Consolidating Solicitud de ofert Single Stage - One 2020-12-3 2020-12-1 2021-01-0 2021-01-0 2021-02-1 2021-02-1 2021-03-1 2021-03-0 2021-04-2 2021-05-0 2021-06-2 IBRD / 87400 Posterior Open - National 755,000.00 426,427.39 Firmado arámetros Portátiles para Me IWRM at the National Level as Envelope 0 8 4 5 5 2 7 9 1 3 0 dición de Calidad de Agua S uperficial PE-ANA-212984-GO-RFQ / A dquisición de 2 equipos para Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-01-3 2021-02-2 2021-03-1 2021-06-2 IBRD / 87400 Posterior Open - National 36,320.00 25,390.02 Firmado Capacitación, Pruebas y Ope IWRM at the National Level aciones Envelope 0 8 6 8 ración de Sistemas Mecaniza dos de Aforos PE-ANA-161084-GO-RFQ / S UMINISTRO DE EQUIPOS E IN Component 1: Consolidating Solicitud de ofert Single Stage - One En ejecució 2020-04-1 2021-02-1 2020-04-1 2021-02-2 2020-05-2 2021-04-2 2020-06-1 2020-07-2 2020-10-3 STRUMENTACIÓN PARA LA O IBRD / 87400 Posterior Open - National 1,200,000.00 0.00 IWRM at the National Level as Envelope n 2 6 7 4 9 1 8 3 1 PERACIÓN DE SISTEMAS ME CANIZADOS DE AFORO PE-ANA-190607-GO-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2021-07-0 2021-08-1 2021-11-1 DQUISICIÓN SOFTWARES PA IBRD / 87400 Posterior Open - National 20,000.00 0.00 IWRM at the National Level aciones Envelope endiente 5 3 1 RA AGUAS SUBTERRÁNEAS Y CAPACITACIÓN. PE-ANA-236203-GO-RFB / A DQUISICION DE EQUIPO DE Component 1: Consolidating Solicitud de ofert Single Stage - One 2021-06-2 2021-07-0 2021-08-1 2021-09-1 2021-10-1 2022-01-1 IBRD / 87400 Posterior Open - National 60,000.00 0.00 Cancelado MEDICION DE CAUDAL EN P IWRM at the National Level as Envelope 6 1 2 1 6 4 OZOS (SPINNER) + WINCHE PE-ANA-236204-GO-RFB / A DQUISICION DE EQUIPO DE Component 1: Consolidating Solicitud de ofert Single Stage - One 2021-07-0 2021-07-0 2021-08-1 2021-09-1 2021-10-2 2022-01-2 IBRD / 87400 Posterior Open - National 60,000.00 0.00 Cancelado MEDICION DE CAUDAL EN P IWRM at the National Level as Envelope 3 8 9 8 3 1 OZOS (PULSO DE CALOR) + WINCHE PE-ANA-161126-GO-RFQ / S UMINISTRO, INSTALACIÓN D Component 1: Consolidating Solicitud de ofert Single Stage - One 2021-06-0 2021-06-1 2021-07-2 2021-08-2 2021-09-2 2022-03-2 IBRD / 87400 Posterior Open - National 456,716.00 0.00 Cancelado E FLUJÓMETROS Y SISTEMA IWRM at the National Level as Envelope 6 1 3 2 6 5 S DE TELEMETRÍA EN LOS Á MBITOS DE ICA Y TACNA. PE-ANA-268542-GO-RFB / S UMINISTRO DE EQUIPOS E IN Component 1: Consolidating Solicitud de ofert Single Stage - One En ejecució 2021-12-2 2022-02-1 2022-01-0 2022-02-1 2022-02-1 2022-03-3 2022-02-2 2022-06-0 2022-03-2 2022-06-2 STRUMENTACIÓN PARA LA O IBRD / 87400 Posterior Open - National 523,275.00 306,310.34 IWRM at the National Level as Envelope n 8 7 2 7 3 1 8 2 5 3 PERACIÓN DE SISTEMAS ME CANIZADOS DE AFORO (2da. Convocatoria) PE-ANA-272266-GO-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-02-0 2022-03-0 2022-04-0 DQUISICIÓN DE PIEZAS SENS IBRD / 87400 Posterior Limited 15,000.00 0.00 IWRM at the National Level aciones Envelope endiente 5 2 1 IBLES INSTRUMENTACIÓN PI EZOMETROS PE-ANA-241746-GO-RFQ / A DQUISICION DE EQUIPO DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-07-1 2021-09-1 2022-03-1 IBRD / 87400 Posterior Limited 50,000.00 0.00 Cancelado MEDICION DE CAUDAL EN P IWRM at the National Level aciones Envelope 7 1 0 OZOS (PULSO DE CALOR) + WINCHE PE-ANA-241743-GO-RFQ / A DQUISICION DE EQUIPO DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-07-1 2021-09-1 2022-03-1 IBRD / 87400 Posterior Limited 50,000.00 0.00 Cancelado MEDICION DE CAUDAL EN P IWRM at the National Level aciones Envelope 7 1 0 OZOS (SPINNER) + WINCHE PE-ANA-164501-GO-RFB / A DQUISICIÓN DE UNA COMPR Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-04-0 2020-04-2 2020-05-3 IBRD / 87400 Posterior Open - National 35,000.00 0.00 Cancelado ESORA PARA MONITOREO D IWRM at the National Level aciones Envelope 6 0 0 E AGUAS SUBTERRANEAS PE-ANA-244363-GO-RFB / A DQUISICION DE DISPOSITIVO Component 1: Consolidating Solicitud de ofert Single Stage - One 2021-08-0 2021-08-0 2021-09-2 2021-09-3 2021-10-2 2022-03-1 IBRD / 87400 Posterior Open - National 200,000.00 0.00 Cancelado S DE TELEMETRIA PARA FLUJ IWRM at the National Level as Envelope 1 6 0 0 0 9 OMETROS PREEXISTENTES E N ICA PE-ANA-272373-GO-RFB / S UMINISTRO, INSTALACION D Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One En ejecució 2022-02-2 2022-05-0 2022-03-0 2022-05-0 2022-04-1 2022-05-0 2022-05-3 2022-09-0 IBRD / 87400 Posterior 1,100,000.00 0.00 E FLUJOMETROS Y SISTEMAS IWRM at the National Level as al Envelope n 8 4 5 3 6 6 1 8 DE TELEMETRIA EN LOS AMB ITOS DE ICA Y TACNA. PE-ANA-240307-GO-RFB / S UMINISTRO, INSTALACION D Component 1: Consolidating Solicitud de ofert Open - Internation Single Stage - One 2021-07-1 2021-07-1 2021-08-2 2021-09-1 2021-10-1 2022-01-1 IBRD / 87400 Previa 2,000,000.00 0.00 Cancelado E FLUJOMETROS Y SISTEMAS IWRM at the National Level as al Envelope 1 6 7 6 1 9 DE TELEMETRIA EN LOS AMB ITOS DE ICA Y TACNA. PE-ANA-286123-GO-RFQ / A dquisición de dos (02) Geon Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-04-1 2022-05-0 2022-07-3 IBRD / 87400 Posterior Limited 7,000.00 0.00 ets nodo y de un (01) Geone IWRM at the National Level aciones Envelope endiente 3 1 0 t Supervisor para presa El Fr ayle PE-ANA-286124-GO-RFQ / A dquisición de cuatro (04) ac Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-04-1 2022-05-0 2022-08-0 IBRD / 87400 Posterior Limited 48,000.00 0.00 elerógrafos Presas Condoro IWRM at the National Level aciones Envelope endiente 6 4 2 ma, El Frayle y Pasto Grande PE-ANA-286120-NC-RFQ / C Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-04-0 2022-04-3 2022-05-3 orrentómetro para medición IBRD / 87400 Posterior Limited 10,500.00 0.00 IWRM at the National Level aciones Envelope endiente 7 0 0 de caudal de agua superficia l en canales. PE-ANA-303589-GO-RFQ / A dquisición de equipos de top Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-07-3 2022-08-1 2022-10-1 IBRD / 87400 Posterior Open - National 15,370.00 0.00 ografía para la operación de IWRM at the National Level aciones Envelope endiente 0 5 4 sistemas mecanizados de af oro PE-ANA-303599-GO-RFQ / A dquisición de equipos auxili Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-07-3 2022-08-1 2022-10-1 IBRD / 87400 Posterior Open - National 38,420.00 0.00 ares para aforos con sistema IWRM at the National Level aciones Envelope endiente 0 5 4 s mecanizados de aforo PE-ANA-303601-GO-RFQ / A dquisición de kit de herrami entas para trabajos de camp Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-07-3 2022-08-1 2022-10-1 IBRD / 87400 Posterior Open - National 8,200.00 0.00 o y comunicación de brigada IWRM at the National Level aciones Envelope endiente 0 5 4 s de campo para la operació n de sistemas mecanizados de aforo PE-ANA-303602-GO-RFQ / A dquisición de equipos de me Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-07-3 2022-08-1 2022-10-1 dición de variables eléctricas IBRD / 87400 Posterior Open - National 16,650.00 0.00 IWRM at the National Level aciones Envelope endiente 0 5 4 y electrónicas para la operac ión de sistemas mecanizado s de aforo PE-ANA-304471-GO-RFB / A DQUISICIÓN DE SEDIMENTO Component 1: Consolidating Solicitud de ofert Single Stage - One En ejecució 2022-07-2 2022-08-3 2022-07-3 2022-09-0 2022-08-2 2022-09-0 2022-09-2 2022-11-2 S DE SUSPENSIÓN PARA LA IBRD / 87400 Posterior Open - National 127,340.00 0.00 IWRM at the National Level as Envelope n 5 1 0 2 9 8 5 4 OPERACIÓN DE SISTEMAS M ECANIZADOS DE AFORO PE-ANA-314826-GO-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-10-0 2022-10-2 2023-01-2 DQUISICION DE EQUIPOS DE IBRD / 87400 Posterior Limited 35,135.00 0.00 IWRM at the National Level aciones Envelope endiente 4 2 0 MUESTREO DE AGUA SUBTE RRANEA PE-ANA-314848-GO-RFQ / A DQUISICION DE EQUIPOS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-09-2 2022-10-1 2023-01-1 IBRD / 87400 Posterior Limited 50,000.00 0.00 PERFILAJE DE CONDUCTIVID IWRM at the National Level aciones Envelope endiente 8 8 6 AD ELECTRICA EN POZOS PE-ANA-314879-GO-RFB / A DQUISICION DE 17 PERFILAD Component 1: Consolidating Solicitud de ofert Single Stage - One Ejecución p 2022-10-0 2022-10-1 2022-11-2 2022-12-0 2022-12-2 2023-03-2 ORES DE CORRIENTE CON E IBRD / 87400 Posterior Open - National 1,381,045.00 0.00 IWRM at the National Level as Envelope endiente 7 2 3 8 8 8 FECTO DOPPLER, CON ACCE SORIOS PARA AFORO Y REGI STRO DE CALIDAD DE AGUA. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CP 004 2018 ANA PGIRH BM Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-12-2 2018-10-3 2019-01-1 2019-02-1 2019-03-0 / SERVICIO DE NIVELACION Y IBRD / 87400 Posterior Limited 38,044.00 39,072.17 Rescindido IWRM at the National Level aciones Envelope 3 1 7 1 3 MONUMENTACION ICA CP 005 2018 ANA PGIRH BM Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-12-2 2018-10-3 2019-01-1 2019-02-1 2019-03-0 / SERVICIO DE NIVELACION Y IBRD / 87400 Posterior Limited 40,760.00 44,281.79 Rescindido IWRM at the National Level aciones Envelope 2 1 6 1 2 MONUMENTACION TACNA CP 008 2018 ANA PGIRH BM Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2018-10-2 2018-11-0 2018-12-2 / ADQUISICION DE DOS CAU IBRD / 87400 Posterior Limited 29,892.00 0.00 IWRM at the National Level aciones Envelope endiente 1 6 1 DALIMETROS ULTRASONICO S CP 009 2018 ANA PGIRH BM Component 1: Consolidating Solicitud de cotiz Single Stage - One En ejecució 2018-10-2 2018-11-0 2018-12-2 / ADQUISICION DE UNA CAM IBRD / 87400 Posterior Limited 29,629.00 0.00 IWRM at the National Level aciones Envelope n 1 6 1 ARA DE INSPECCION DE POZ OS Page 3 CP 014 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT URA DE MEDICION DE NIVEL DE AGUA EN BLOQUES DE RI Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-1 2018-11-2 2019-01-1 2018-12-1 EGO DE LOS VALLES DE ALG IBRD / 87400 Posterior Limited 28,528.00 129,635.34 Firmado IWRM at the National Level aciones Envelope 8 9 0 6 4 ARROBO - VALLE HERMOSO - HUALTACO I - II - IV - SOMA TE ALTO - SOMATE BAJO - VA LLE LOS INCAS - CHIPILLICO BAJO -M - MALINGAS CP 015 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT URA DE MEDICION DE NIVEL Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-1 2018-11-2 2019-01-1 2018-12-1 DE AGUA EN BLOQUES DE RI IBRD / 87400 Posterior Limited 25,934.00 207,452.42 Firmado IWRM at the National Level aciones Envelope 8 9 0 6 3 EGO DE LOS VALLES DE QUI ROZ PAMPAS-SAN ISIDRO I-II -TEJEDORES-TG-MALINGAS-Y USCAY-TABLAZO ALTO CP 016 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-11-2 2018-11-2 2019-01-1 2018-12-0 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 12,550.00 57,574.33 Firmado IWRM at the National Level aciones Envelope 2 1 5 6 7 DE AGUA EN BLOQUES DE RI EGO DE LOS VALLES DE PRA XADES-SANTA MARCELA CP 017 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-11-1 2018-11-2 2019-01-1 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 28,485.00 26,918.23 Firmado IWRM at the National Level aciones Envelope 2 2 5 6 8 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE CASCAJA L-ANITAS-ILLIMO CP 018 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-1 2018-11-2 2019-01-1 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 25,990.00 131,662.63 Firmado IWRM at the National Level aciones Envelope 8 2 0 6 0 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE MARGEN DERECHA CP 019 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2019-08-1 2018-11-2 2019-09-2 2018-12-0 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 23,103.00 20,790.00 Firmado IWRM at the National Level aciones Envelope 8 1 0 5 8 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE MIGUEL CHECA CP 020 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-1 2018-11-2 2019-01-1 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 25,636.00 20,942.09 Firmado IWRM at the National Level aciones Envelope 8 2 0 6 0 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE CASARA NA CP 021 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2018-12-1 2018-11-2 2019-01-1 2018-12-0 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 19,167.00 14,735.72 Firmado IWRM at the National Level aciones Envelope 8 3 0 7 3 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE SAN AND RES CP 022 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT URA DE MEDICION DE NIVEL Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2019-01-0 2018-11-2 2019-01-3 2018-12-2 IBRD / 87400 Posterior Limited 42,727.00 31,139.78 Firmado DE AGUA EN BLOQUES DE RI IWRM at the National Level aciones Envelope 2 9 5 0 8 EGO DE LOS VALLES DE CAP OTE-LA RAMADA-CHONGOYA OPE-PITIPO CP 023 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2019-01-0 2018-11-2 2019-02-1 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 28,485.00 85,114.40 Firmado IWRM at the National Level aciones Envelope 2 9 5 2 8 DE AGUA EN BLOQUES DE RI EGO DE LOS VALLES DE PUC ALA TUMAN-POMALCA CP 024 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2019-01-1 2018-11-2 2019-02-0 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 19,939.00 66,347.73 Firmado IWRM at the National Level aciones Envelope 2 5 5 1 0 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE LAMBAY EQUE CP 025 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2019-02-0 2018-11-2 2019-03-2 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 37,030.00 19,450.38 Firmado IWRM at the National Level aciones Envelope 2 8 5 2 9 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE TALAMB O CP 013 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-2 2018-11-2 2019-01-1 2018-12-2 IBRD / 87400 Posterior Limited 39,879.00 20,893.44 Firmado URA DE MEDICION DE NIVEL IWRM at the National Level aciones Envelope 8 3 0 6 0 DE AGUA EN BLOQUES DE RI EGO DEL VALLE CP 026 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2019-01-0 2018-11-2 2019-02-1 2018-12-2 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 42,342.00 37,500.33 Firmado IWRM at the National Level aciones Envelope 2 7 5 4 8 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE SAN PED RO CP 027 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2019-01-0 2018-11-2 2019-02-1 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 36,697.00 33,668.21 Firmado IWRM at the National Level aciones Envelope 2 7 5 3 9 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE SAN JOS É CP 028 2018 ANA PGIRH B M / ADECUACION DE ESTRU Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-11-2 2018-12-0 CTURA DE MEDICION DE NIV IBRD / 87400 Posterior Limited 14,243.00 0.00 Cancelado IWRM at the National Level aciones Envelope 2 5 7 EL DE AGUA EN BLOQUES D E RIEGO DEL VALLE DE SAN MIGUEL CP 029 2018 ANA PGIRH B M / ADECUACION DE ESTRU Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-12-1 2018-11-2 2019-01-3 2018-12-1 CTURA DE MEDICION DE NIV IBRD / 87400 Posterior Limited 19,940.00 20,805.11 Firmado IWRM at the National Level aciones Envelope 2 4 5 0 0 EL DE AGUA EN BLOQUES D E RIEGO DEL VALLE DE SAYA N CP 030 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-12-0 2018-11-2 2019-01-1 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 28,485.00 83,611.18 Firmado IWRM at the National Level aciones Envelope 2 5 5 6 8 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE LLAMAC HUPAN CP 031 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-11-2 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 25,636.00 0.00 Cancelado IWRM at the National Level aciones Envelope 2 5 5 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE HUARICA NGA CP 032 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-11-2 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 22,788.00 0.00 Cancelado IWRM at the National Level aciones Envelope 2 5 3 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE NARANJA L CP 033 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2019-08-1 2018-12-0 2019-09-2 2018-12-2 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 28,485.00 29,951.43 Firmado IWRM at the National Level aciones Envelope 2 1 5 5 8 DE AGUA EN BLOQUES DE RI EGO DE LOS VALLES DE MAC ASH-POCOS CP 034 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-11-2 2018-12-0 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 8,546.00 0.00 Cancelado IWRM at the National Level aciones Envelope 2 5 4 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE RINCON ADA CP 035 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-11-2 2018-12-0 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 17,091.00 0.00 Cancelado IWRM at the National Level aciones Envelope 2 5 8 DE AGUA EN BLOQUES DE RI EGO DE LOS VALLES DE LAT ERAL 4, 5 Y 6 CP 036 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2019-02-2 2018-11-2 2019-03-2 2018-12-1 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 37,030.00 33,424.63 Firmado IWRM at the National Level aciones Envelope 2 4 5 2 9 DE AGUA EN BLOQUES DE RI EGO DEL VALLE DE EL CHOL OQUE CP 038 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-10-2 2018-11-2 2018-11-2 2019-01-1 2018-12-0 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 22,788.00 38,281.31 Firmado IWRM at the National Level aciones Envelope 8 3 0 6 8 DE AGUA EN BLOQUES DE RI EGO DE LOS VALLES DE MAL A MUERTE-CHICAMITA CP 006 2018 ANA PGIRH BM / SERVICIO DE NIVELACION Y Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-04-0 2019-05-0 2019-06-1 IBRD / 87400 Posterior Limited 43,479.00 0.00 Cancelado MONUMENTACION ICA (POZ IWRM at the National Level aciones Envelope 7 2 6 OS RED CONTROL GLOBAL A LA, AAA, DCERH) CP 007 2018 ANA PGIRH BM / SERVICIO DE NIVELACION Y Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-04-0 2019-05-0 2019-06-1 IBRD / 87400 Posterior Limited 24,457.00 0.00 Cancelado MONUMENTACION TACNA (P IWRM at the National Level aciones Envelope 7 2 6 OZOS RED CONTROL GLOBA L ALA, AAA, DCERH) CP 012 2018 ANA PGIRH BM Component 3: General Proje Solicitud de cotiz Single Stage - One 2019-04-0 2019-04-2 2019-06-1 / CONTRATACION DE AGENCI IBRD / 87400 Posterior Limited 25,000.00 0.00 Cancelado ct Adminstration aciones Envelope 7 1 4 A PARA PUBLICACION DE AVI SOS EN DIARIOS CP 037 2018 ANA PGIRH BM / ADECUACION DE ESTRUCT Component 1: Consolidating Solicitud de cotiz Single Stage - One 2018-11-0 2018-11-2 2018-12-0 URA DE MEDICION DE NIVEL IBRD / 87400 Posterior Limited 17,091.00 0.00 Cancelado IWRM at the National Level aciones Envelope 2 5 8 DE AGUA EN BLOQUES DE RI EGO DE LOS VALLES DE MO RO-VICHANZAO PE-ANA-130327-NC-RFQ / S ERVICIO DE ELABORACIÓN D EL PLAN DE MONITOREO AR Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-09-2 2019-09-2 2019-10-0 2019-10-2 2020-02-0 IBRD / 87400 Posterior Limited 32,915.00 31,674.21 Firmado QUEOLÓGICO PARA ADECUA IWRM at the National Level aciones Envelope 0 6 7 1 4 CIÓN DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN L A ZONA SUR DE LA COSTA PE-ANA-133579-NC-RFB / AL QUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-11-0 2019-10-1 2019-11-2 2019-12-1 IBRD / 87400 Posterior Limited 8,000.00 114.45 Firmado DIENTES TÉCNICOS DE ESTR IWRM at the National Level aciones Envelope 3 6 4 2 3 UCTURAS DE MEDICIÓN GRU PO 10 SECTORES HIDRÁULIC OS CASMA, HUARMEY PE-ANA-133581-NC-RFQ / A LQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-11-0 2019-10-1 2019-11-2 2020-01-1 IBRD / 87400 Posterior Limited 12,000.00 98.48 Firmado DIENTES TÉCNICOS DE ESTR IWRM at the National Level aciones Envelope 3 6 4 2 2 UCTURAS DE MEDICIÓN GRU PO 3 SECTORES HIDRÁULICO S MyBP, SECHURA PE-ANA-133582-NC-RFQ / A LQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-10-3 2019-10-1 2019-11-2 2020-01-1 IBRD / 87400 Posterior Limited 12,000.00 92.63 Firmado DIENTES TÉCNICOS DE ESTR IWRM at the National Level aciones Envelope 3 0 4 2 2 UCTURAS DE MEDICIÓN GRU PO 5 SECTORES HIDRÁULICO S OLMOS, MOTUPE, LA LECH E PE-ANA-133583-NC-RFQ / A LQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-11-0 2019-10-1 2020-01-1 2020-01-1 DIENTES TÉCNICOS DE ESTR IBRD / 87400 Posterior Limited 12,000.00 78.52 Firmado IWRM at the National Level aciones Envelope 3 5 4 4 0 UCTURAS DE MEDICIÓN GRU PO 8 SECTORES HIDRÁULICO S MOCHE, VIRU, CHAO, GUA DALUPITO PE-ANA-133584-NC-RFQ / A LQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE Component 1: Consolidating Solicitud de cotiz Single Stage - One En ejecució 2019-10-0 2019-10-1 2020-02-0 DIENTES TÉCNICOS DE ESTR IBRD / 87400 Posterior Limited 16,000.00 0.00 IWRM at the National Level aciones Envelope n 3 4 9 UCTURAS DE MEDICIÓN GRU PO 12 SECTORES HIDRÁULIC OS CHILLÓN, RIMAC, LURIN, CAÑETE Page 4 PE-ANA-133585-NC-RFQ / A LQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-11-0 2019-10-1 2019-11-2 2020-01-1 IBRD / 87400 Posterior Limited 12,000.00 95.39 Firmado DIENTES TÉCNICOS DE ESTR IWRM at the National Level aciones Envelope 3 6 4 2 2 UCTURAS DE MEDICIÓN GRU PO 13 SECTORES HIDRÁULIC OS SAN JUAN, PISCO PE-ANA-133586-NC-RFQ / A LQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-10-3 2019-10-1 2019-11-2 2019-12-1 IBRD / 87400 Posterior Limited 8,000.00 3,297.84 Firmado DIENTES TÉCNICOS DE ESTR IWRM at the National Level aciones Envelope 3 0 4 5 3 UCTURAS DE MEDICIÓN GRU PO 14 SECTORES HIDRÁULIC OS ICA, LA ACHIRANA PE-ANA-133587-NC-RFQ / A LQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-10-0 2019-10-1 2019-11-2 2020-01-1 DIENTES TÉCNICOS DE ESTR IBRD / 87400 Posterior Limited 12,000.00 111.79 Firmado IWRM at the National Level aciones Envelope 3 1 4 2 2 UCTURAS DE MEDICIÓN GRU PO 18 SECTORES HIDRÁULIC OS IRRIG. MAJES, STA RITA D E SIGUAS, LA JOYA, VITOR Y URA PE-ANA-133588-NC-RFQ / A LQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPE DIENTES TÉCNICOS DE ESTR Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-0 2019-10-3 2019-10-1 2019-11-2 2019-12-1 IBRD / 87400 Posterior Limited 8,000.00 6,790.53 Firmado UCTURAS DE MEDICIÓN GRU IWRM at the National Level aciones Envelope 3 0 4 2 3 PO 20 SECTORES HIDRÁULIC OS IRRIG. EMM, PTA DE BOM BOM, MOQUEGUA, TORATA, LOCUMBA, SAMA, UCHUSUM A, BAJO CAPLINA PE-ANA-136558-NC-RFQ / A DECUACIÓN DE ESTRUCTUR Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2020-02-1 2019-11-1 2020-03-0 2020-01-1 AS DE MEDICIÓN DE NIVEL D IBRD / 87400 Posterior Limited 32,740.00 29,723.68 Firmado IWRM at the National Level aciones Envelope 9 8 7 5 6 E AGUA EN BLOQUES DE RIE GO EN EL SECTOR HIDRÁULI CO MENOR CAÑETE PE-ANA-136561-NC-RFQ / A DECUACIÓN DE ESTRUCTUR Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2020-03-1 2019-11-1 2020-08-2 2020-01-0 AS DE MEDICIÓN DE NIVEL D IBRD / 87400 Posterior Limited 35,680.00 28,030.30 Firmado IWRM at the National Level aciones Envelope 9 3 7 4 3 E AGUA EN BLOQUES DE RIE GO EN EL SECTOR HIDRÁULI CO MENOR PISCO I PE-ANA-137039-NC-RFQ / A DECUACIÓN DE ESTRUCTUR Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2020-03-1 2019-11-1 2020-08-2 2019-12-2 AS DE MEDICIÓN DE NIVEL D IBRD / 87400 Posterior Limited 28,312.00 23,487.57 Firmado IWRM at the National Level aciones Envelope 9 3 7 4 7 E AGUA EN BLOQUES DE RIE GO EN EL SECTOR HIDRÁULI CO MENOR PISCO II PE-ANA-137046-NC-RFQ / A DECUACIÓN DE ESTRUCTUR AS DE MEDICIÓN DE NIVEL D Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2020-06-2 2019-11-1 2020-08-2 2020-01-1 IBRD / 87400 Posterior Limited 23,452.00 36,147.55 Firmado E AGUA EN BLOQUES DE RIE IWRM at the National Level aciones Envelope 9 3 7 4 6 GO EN LOS SECTORES HIDR ÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNI ÓN PE-ANA-137047-NC-RFQ / A DECUACIÓN DE ESTRUCTUR AS DE MEDICIÓN DE NIVEL D Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2020-07-1 2019-11-1 2020-09-0 2020-01-2 IBRD / 87400 Posterior Limited 43,598.00 27,065.09 Firmado E AGUA EN BLOQUES DE RIE IWRM at the National Level aciones Envelope 9 0 7 2 7 GO EN EL SECTOR HIDRÁULI CO MENOR IRRIGACIÓN MAJ ES , VALLE DE MAJES, CAMA NÁ PE-ANA-137048-NC-RFQ / A DECUACIÓN DE ESTRUCTUR AS DE MEDICIÓN DE NIVEL D Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2020-07-2 2019-11-1 2020-09-0 2020-02-0 IBRD / 87400 Posterior Limited 40,110.00 29,982.46 Firmado E AGUA EN BLOQUES DE RIE IWRM at the National Level aciones Envelope 9 9 7 2 3 GO EN EL SECTOR HIDRÁULI CO MENOR LA JOYA, CHILI R EGULADO Y CHILI NO REGUL ADO PE-ANA-137049-NC-RFQ / A DECUACIÓN DE ESTRUCTUR AS DE MEDICIÓN DE NIVEL D Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2020-09-1 2019-11-1 2020-11-0 2020-02-0 E AGUA EN BLOQUES DE RIE IBRD / 87400 Posterior Limited 22,399.00 13,241.97 Firmado IWRM at the National Level aciones Envelope 9 8 7 3 3 GO EN EL SECTOR HIDRÁULI CO MENOR IRRIGACIÓN ENS ENADA-MEJIA-MOLLENDO Y P UNTA DE BOMBOM PE-ANA-137051-NC-RFQ / A DECUACIÓN DE ESTRUCTUR AS DE MEDICIÓN DE NIVEL D Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2020-09-2 2019-11-1 2020-11-0 2020-02-0 E AGUA EN BLOQUES DE RIE IBRD / 87400 Posterior Limited 44,793.00 33,679.65 Firmado IWRM at the National Level aciones Envelope 9 9 7 3 3 GO EN LOS SECTORES HIDR ÁULICOS MENOR MOQUEGU A, LOCUMBA, SAMA Y BAJO U CHUSUMA PE-ANA-137052-NC-RFQ / A DECUACIÓN DE ESTRUCTUR AS DE MEDICIÓN DE AGUA E Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-1 2019-11-2 2019-11-1 2020-01-0 2020-02-0 IBRD / 87400 Posterior Limited 36,795.00 24,051.35 Firmado N BLOQUES DE RIEGO EN EL IWRM at the National Level aciones Envelope 9 0 7 9 3 SECTOR HIDRÁULICO MENO R MOTUPE-OLMOS-LA LECHE PE-ANA-139771-NC-RFQ / S Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-2 2019-11-2 2020-05-0 ERVICIO PARA EJECUTAR 11 IBRD / 87400 Posterior Open - National 26,268.66 0.00 Cancelado IWRM at the National Level aciones Envelope 6 4 2 PERFILAJES GEOFISICOS PE-ANA-139772-NC-RFQ / S ERVICIO PARA LA INSTALACI Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-2 2019-11-2 2020-01-2 IBRD / 87400 Posterior Open - National 35,820.90 0.00 Cancelado ÓN Y CONSTRUCCIÓN DE CA IWRM at the National Level aciones Envelope 6 4 3 SETAS PRE FABRICADAS TAC NA PE-ANA-139773-NC-RFQ / S ERVICIO PARA LA INSTALACI Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-2 2019-11-2 2020-01-2 IBRD / 87400 Posterior Open - National 33,433.00 0.00 Cancelado ÓN Y CONSTRUCCIÓN DE CA IWRM at the National Level aciones Envelope 6 4 3 SETAS PRE FABRICADAS ICA PE-ANA-139774-NC-RFQ / S ERVICIO DE ADAPTACIÓN, S EGURIDAD PARA LA INSTRU Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-10-2 2019-11-2 2020-01-2 MENTACIÓN DE 27 POZOS Y IBRD / 87400 Posterior Open - National 29,553.00 0.00 Cancelado IWRM at the National Level aciones Envelope 6 4 3 PIEZOMETROS EN ESTADO U TILIZABLE Y 15 EN ESTADO UTILIZADO EN EL ACUIFERO DE ICA, VILLACURI Y LANCH AS PE-ANA-152835-NC-RFQ / S ERVICIO DE ALOJAMIENTO D Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-01-2 2020-01-1 2020-02-2 2020-01-2 2020-07-2 IBRD / 87400 Posterior Limited 30,000.00 60,749.10 Firmado E INFRAESTRUCTURA TECNO IWRM at the National Level aciones Envelope 5 3 1 0 0 LÓGICA DE DATA CENTER PE-ANA-154274-NC-RFQ / S ERVICIO DE ALOJAMIENTO Y ALIMENTACIÓN PARA LOS PA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-01-1 2020-01-2 2020-01-2 2020-01-2 2020-02-0 IBRD / 87400 Posterior Limited 50,000.00 53,878.72 Firmado RTICIPANTES DEL TALLER DE IWRM at the National Level aciones Envelope 8 1 6 3 2 CAPACITACIÓN PARA ESPECI ALISTAS DE CALIDAD DE RE CURSOS HIDRICOS PE-ANA-155598-NC-RFQ / S ERVICIOS DE ESTUDIOS BÁSI COS DE MECÁNICA DE SUEL OS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS PA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-0 2020-02-1 2020-03-0 2020-04-0 IBRD / 87400 Posterior Open - National 8,597.00 9,632.19 Firmado RA LA CONSTRUCCIÓN DE E IWRM at the National Level aciones Envelope 9 9 2 4 STRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RI EGO EN LOS SECTORES HID RÁULICOS VALLE DE MAJES Y VALLE SIGUAS QUILCA. PE-ANA-155595-NC-RFQ / S ERVICIO DE ESTUDIOS BÁSIC OS DE MECÁNICA DE SUELO S PARA ELABORACIÓN DE EX Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-0 2020-02-1 2020-02-2 2020-04-0 PEDIENTES TÉCNICOS PARA IBRD / 87400 Posterior Open - National 6,179.00 10,075.32 Firmado IWRM at the National Level aciones Envelope 9 9 8 4 LA CONSTRUCCIÓN DE ESTR UCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEG O EN EL SECTOR HIDRÁULIC O MENOR ALTO PIURA. PE-ANA-155594-NC-RFQ / S ERVICIO DE ESTUDIOS BÁSIC OS DE MECÁNICA DE SUELO S PARA ELABORACIÓN DE EX Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-0 2020-02-1 2020-02-2 2020-03-2 IBRD / 87400 Posterior Open - National 9,134.00 6,815.66 Firmado PEDIENTES TÉCNICOS PARA IWRM at the National Level aciones Envelope 9 9 8 0 LA CONSTRUCCIÓN DE ESTR UCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEG O EN EL SECTOR HIDRÁULIC O MENOR CHIRA. PE-ANA-155596-NC-RFQ / S ERVICIOS DE ESTUDIOS BÁSI COS DE MECÁNICA DE SUEL OS PARA ELABORACIÓN DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-0 2020-02-1 2020-02-2 2020-03-3 EXPEDIENTES TÉCNICOS PA IBRD / 87400 Posterior Open - National 8,597.00 9,329.13 Firmado IWRM at the National Level aciones Envelope 9 9 8 0 RA LA CONSTRUCCIÓN DE E STRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RI EGO EN LOS SECTORES HID RÁULICOS MENOR ZAÑA Y JE QUETEPEQUE PE-ANA-155599-NC-RFQ / S ERVICIOS DE ESTUDIOS BÁSI COS DE MECÁNICA DE SUEL OS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS PA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-0 2020-02-1 2020-03-0 2020-03-2 IBRD / 87400 Posterior Open - National 5,373.00 4,212.49 Firmado RA LA CONSTRUCCIÓN DE E IWRM at the National Level aciones Envelope 9 9 2 0 STRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RI EGO EN LOS SECTORES HID RÁULICOS CHILI NO REGULA DO Y CHILI REGULADO. PE-ANA-155597-NC-RFQ / S ERVICIOS DE ESTUDIOS BÁSI COS DE MECÁNICA DE SUEL OS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS PA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-0 2020-02-1 2020-02-2 2020-03-2 IBRD / 87400 Posterior Open - National 9,134.00 7,134.04 Firmado RA LA CONSTRUCCIÓN DE E IWRM at the National Level aciones Envelope 9 9 8 5 STRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RI EGO EN LOS SECTORES HID RÁULICOS PALPA, NASCA, A CARI, BELLA UNIÓN, CHAPAR RA, Y YAUCA. PE-ANA-158210-NC-RFQ / Al quiler de camionetas 4x4 pa ra las actividades de Supervi sión del Suministro, Instalaci Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-2 2020-02-2 2020-02-2 2020-03-0 2020-06-1 IBRD / 87400 Posterior Limited 38,500.00 38,925.20 Firmado ón, Puesta en funcionamient IWRM at the National Level aciones Envelope 0 0 9 2 3 o y Capacitación de la Instru mentación para la Seguridad de las presas Poechos, San Lorenzo, Tinajones y Gallito Ciego. PE-ANA-158215-NC-RFQ / Al quiler de camionetas 4x4 pa ra las actividades de Supervi sión del Suministro, Instalaci Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-2 2020-09-2 2020-03-0 2020-09-2 2020-06-1 IBRD / 87400 Posterior Limited 23,500.00 14,775.32 Firmado ón, Puesta en funcionamient IWRM at the National Level aciones Envelope 1 3 1 9 9 o y Capacitación de la Instru mentación para la Seguridad de las presas del Sur Condor oma, El Frayle, Sutunta y Pa sto Grande. PE-ANA-159315-NC-RFQ / S ERVICIO DE LIMPIEZA, TALA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-02-2 2020-02-1 2020-02-2 2020-02-2 2020-03-3 IBRD / 87400 Posterior Limited 23,000.00 20,343.08 Firmado Y DESBROCE, Y TRASLADO D IWRM at the National Level aciones Envelope 1 8 8 1 0 E MATERIAL ELIMINADO EN L A PRESA POECHOS PE-ANA-161087-NC-RFQ / S ERVICIO DE ALOJAMIENTO, A LIMENTACIÓN Y SALAS EQUI Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-03-0 2020-03-0 2020-03-0 2020-03-0 2020-03-0 PADAS PARA EL TALLER NAC IBRD / 87400 Posterior Limited 50,000.00 40,733.54 Firmado IWRM at the National Level aciones Envelope 2 2 5 3 7 IONAL: FORTALECIMIENTO D E LAS JUNTAS USUARIAS Y S U ROL EN EL DESARROLLO P RODUCTIVO AGRARIO Page 5 PE-ANA-161131-NC-RFQ / S ERVICIOS DE LIMPIEZA Y AD Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-03-1 2020-04-0 2020-07-0 APTACIÓN DE 15 POZOS UBI IBRD / 87400 Posterior Limited 14,925.00 0.00 Cancelado IWRM at the National Level aciones Envelope 8 4 3 CADO EN LOS ACUÍFEROS D E ICA, VILLACURI Y LANCHAS . PE-ANA-164268-NC-DIR / SE RVICIO DE ARRENDAMIENTO Component 3: General Proje Adquisición direc 2020-03-2 2020-03-0 2020-03-3 2020-03-1 2020-04-0 2020-06-3 2022-12-3 DE INMUEBLE 2 PARA EL PR IBRD / 87400 Posterior Direct 84,500.00 55,200.00 Firmado ct Adminstration ta 3 9 0 6 1 0 1 OYECTO GESTIÓN INTEGRAD A DE RECURSOS HIDRICOS E N DIEZ CUENCAS PE-ANA-164313-NC-RFQ / S Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-03-3 2020-05-2 2020-11-2 ERVICIO DE ELABORACIÓN D IBRD / 87400 Posterior Open - National 10,448.00 0.00 Cancelado IWRM at the National Level aciones Envelope 1 6 2 E CARTELES DE IDENTIFICAC IÓN POZOS PE-ANA-164550-NC-RFQ / S ERVICIO DE AGENCIAMIENTO Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-04-1 2020-05-0 2021-01-1 IBRD / 87400 Posterior Open - National 29,851.00 0.00 Cancelado DE PASAJES AÉREOS NACION IWRM at the National Level aciones Envelope 3 4 2 ALES Y INTERNACIONALES PE-ANA-164552-NC-RFQ / S ERVICIO DE PUBLICIDAD DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-04-1 2020-05-0 2021-08-0 2021-01-1 IBRD / 87400 Posterior Open - National 17,910.00 26,731.37 Firmado AVISOS RELACIONADOS A LA IWRM at the National Level aciones Envelope 3 4 9 2 S CONVOCATORIAS DEL PRO YECTO PE-ANA-164985-NC-DIR / SE RVICIO DE ARRENDAMIENTO DE INMUEBLE PARA LA SEDE Component 3: General Proje Adquisición direc 2020-03-1 2020-03-1 2020-03-2 2020-03-1 2020-04-0 2020-03-3 2022-12-3 PRINCIPAL DEL PGIRH DE LA IBRD / 87400 Posterior Direct 239,415.00 174,120.00 Firmado ct Adminstration ta 8 6 5 6 5 1 1 UNIDAD EJECUTORA N°002 MODERNIZACION DE LA GES TION DE LOS RECURSOS HID RICOS PE-ANA-165161-NC-RFQ / S Component 3: General Proje Solicitud de cotiz Single Stage - One 2020-04-1 2020-04-2 2020-08-1 2020-05-1 ERVICIO DE CABLEADO DE V IBRD / 87400 Posterior Open - National 30,000.00 29,483.43 Firmado ct Adminstration aciones Envelope 6 6 3 1 OZ Y DATA PARA LOCAL DEL PGIRH PE-ANA-165867-NC-RFB / C ULMINACIÓN DE LA ADECUA CIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-04-2 2020-06-2 2020-09-1 IBRD / 87400 Posterior Limited 42,728.00 0.00 Cancelado MEDICIÓN DE AGUA EN LOS IWRM at the National Level aciones Envelope 5 0 8 SECTORES HIDRÁULICOS ME NORES COMPRENDIDOS DES DE CHICAMA HASTA SANTA PE-ANA-165868-NC-RFB / C ULMINACIÓN DE LA ADECUA CIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-04-2 2020-06-2 2020-08-1 IBRD / 87400 Posterior Limited 26,192.00 0.00 Cancelado MEDICIÓN DE AGUA EN LOS IWRM at the National Level aciones Envelope 5 0 9 SECTORES HIDRÁULICOS ME NORES COMPRENDIDOS DES DE FORTALEZA HASTA LURÍ N PE-ANA-165877-NC-RFQ / A LQUILER DE CAMIONETA PA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-04-2 2020-04-3 2020-06-2 IBRD / 87400 Posterior Limited 9,242.00 0.00 Cancelado RA VERIFICACIÓN DE COBER IWRM at the National Level aciones Envelope 1 0 9 TURA DE TRANSMISIÓN PE-ANA-165652-GO-RFB / C ULMINACIÓN DE LA ADECUA CIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de ofert Single Stage - One 2020-06-1 2020-06-2 2020-08-0 2020-08-2 2020-09-2 2020-12-2 MEDICIÓN DE AGUA EN LOS IBRD / 87400 Posterior Open - National 130,401.14 0.00 Cancelado IWRM at the National Level as Envelope 5 0 1 1 5 4 SECTORES HIDRÁULICOS ME NORES COMPRENDIDOS DES DE TUMBES HASTA JEQUETE PEQUE PE-ANA-187094-NC-RFQ / S ERVICIO DE TELEFONIA MOV Component 3: General Proje Solicitud de cotiz Single Stage - One 2020-09-1 2020-10-1 2020-10-0 2020-11-2 2021-10-0 IL PARA EL PERSONAL DEL P IBRD / 87400 Posterior Limited 20,000.00 14,423.97 Firmado ct Adminstration aciones Envelope 7 6 1 0 1 ROYECTO DE GESTION INTE GRADA DE RECURSOS HIDRI COS EN DIEZ CUENCAS PE-ANA-187470-NC-RFQ / E LABORACION E IMPLEMENTA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-09-1 2020-09-2 2020-10-0 2020-11-0 2021-03-0 IBRD / 87400 Posterior Limited 50,000.00 49,055.79 Firmado CION DE PLANES DE MONITO IWRM at the National Level aciones Envelope 7 1 8 4 7 REO ARQUEOLÓGICO - PMA. PE-ANA-164575-NC-RFB / SE RVICIO DE ANÁLISIS DE LAB Component 1: Consolidating Solicitud de ofert Single Stage - One 2020-04-0 2020-11-2 2020-04-1 2020-12-2 2020-05-2 2021-01-1 2020-06-2 2021-02-1 2020-07-2 2021-03-0 2020-12-2 IBRD / 87400 Posterior Open - National 477,650.00 248,246.81 Firmado ORATORIO PARA MUESTRAS IWRM at the National Level as Envelope 6 2 1 1 3 3 2 2 7 4 4 DE AGUA NATURAL PE-ANA-165874-NC-RFB / EL ABORAR E IMPLEMENTAR ON Component 1: Consolidating Solicitud de ofert Single Stage - One 2020-04-3 2020-05-0 2020-06-1 2020-07-1 2020-08-2 2021-01-1 IBRD / 87400 Posterior Open - National 59,702.00 0.00 Cancelado CE (11) PLANES DE MONITO IWRM at the National Level as Envelope 0 5 6 6 0 7 REO ARQUEOLÓGICO-PMA PE-ANA-191481-NC-RFQ / S ERVICIO DE INTERNET PARA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-09-1 2020-09-2 2020-10-0 2020-10-2 2021-01-2 EL CENTRO DE PROCESAMIE IBRD / 87400 Posterior Limited 40,000.00 17,122.15 Firmado IWRM at the National Level aciones Envelope 7 3 1 3 9 NTO DE DATOS SECUNDARI O DE LA AUTORIDAD NACIO NAL DEL AGUA PE-ANA-187303-NC-RFQ / S ERVICIO DE INFRAESTRUCTU Component 3: General Proje Solicitud de cotiz Single Stage - One Ejecución p 2020-09-2 2020-10-2 2021-10-2 IBRD / 87400 Posterior Limited 32,500.00 0.00 RA Y PLATAFORMA EN LA NU ct Adminstration aciones Envelope endiente 7 2 2 BE PARA EL PROYECTO PGIR H PE-ANA-202872-NC-RFQ / C ULMINACIÓN DE LA ADECUA CIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-11-2 2021-09-2 2020-12-0 2021-11-1 2021-01-3 IBRD / 87400 Posterior Limited 40,900.00 56,535.10 Firmado MEDICIÓN DE AGUA EN LOS IWRM at the National Level aciones Envelope 2 3 1 6 0 SECTORES HIDRÁULICOS ME NORES COMPRENDIDOS DES DE CHICAMA HASTA SANTA PE-ANA-202873-NC-RFQ / C ULMINACIÓN DE LA ADECUA CIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-11-2 2021-02-1 2020-12-0 2021-03-1 2021-01-3 IBRD / 87400 Posterior Limited 25,100.00 31,352.14 Firmado MEDICIÓN DE AGUA EN LOS IWRM at the National Level aciones Envelope 2 6 1 5 0 SECTORES HIDRÁULICOS ME NORES COMPRENDIDOS DES DE FORTALEZA HASTA LURÍ N PE-ANA-206762-NC-RFQ / S ERVICIOS COMPLEMENTARIO Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-12-1 2020-12-1 2020-12-2 2020-12-2 2020-12-2 S PARA EL CENTRO DE PROC IBRD / 87400 Posterior Limited 28,000.00 21,878.55 Firmado IWRM at the National Level aciones Envelope 6 8 0 3 1 ESAMIENTO SECUNDARIO D EL MONITOREO DEL RECURS O HÍDRICO - ICA PE-ANA-208167-NC-RFQ / S Component 3: General Proje Solicitud de cotiz Single Stage - One 2020-12-1 2020-12-1 2020-12-1 2020-12-1 2020-12-1 EGURO VEHICULAR ANUAL P IBRD / 87400 Posterior Limited 37,350.00 21,521.29 Firmado ct Adminstration aciones Envelope 3 1 7 8 8 ARA LOS VEHICULOS DEL PG IRH PE-ANA-208190-NC-RFQ / S ERVICIO DE ADUANA PARA L Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-12-1 2021-01-1 2020-12-2 2021-02-0 2020-12-2 A IMPORTACION DE ESTACIO IBRD / 87400 Posterior Limited 40,000.00 35,148.56 Firmado IWRM at the National Level aciones Envelope 6 8 6 6 7 NES AUTOMATICAS (HIDROL OGICAS E HIDROMETEOROL OGICAS) PE-ANA-208191-NC-RFQ / S ERVICIO DE ADUANA PARA L A IMPORTACION DE SISTEMA Component 1: Consolidating Solicitud de cotiz Single Stage - One 2020-12-1 2021-01-1 2020-12-2 2021-02-0 2020-12-2 IBRD / 87400 Posterior Limited 40,000.00 26,899.18 Firmado S MECANIZADOS DE AFORO, IWRM at the National Level aciones Envelope 6 5 0 6 1 PASARELAS METALICAS DE A FOROS Y WINCHES PARA AF OROS PE-ANA-203041-NC-RFQ / A LQUILER DE CAMIONETA 4 X 4 PARA ACTIVIDADES DE INS Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-02-0 2021-01-2 2021-02-1 2021-02-2 2021-06-2 PECCION AL SERVICIO DE SU IBRD / 87400 Posterior Limited 21,000.00 20,459.53 Firmado IWRM at the National Level aciones Envelope 2 2 2 4 7 MINISTRO INSTALACION PUE STA EN FUNCIONAMIENTO Y CAPACITACION DE PRESAS E N PIURA PE-ANA-213295-NC-RFQ / S ERVICIO DE ALQUILER DE CA MIONETA 4X4 PARA ACTIVID ADES DE INSPECCION AL SE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-01-2 2021-01-2 2021-02-0 2021-02-2 2021-04-0 IBRD / 87400 Posterior Limited 9,334.00 9,093.12 Firmado RVICIO DE SUMINISTRO, INS IWRM at the National Level aciones Envelope 1 2 1 4 2 TALACION, PUESTA EN FUNC IONAMIENTO Y CAPACITACIO N DE PRESAS GALLITO CIEG O - CAJAMARCA PE-ANA-213296-NC-RFQ / S ERVICIO DE ALQUILER DE CA MIONETA 4X4 PARA ACTIVID ADES DE INSPECCION AL SE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-01-2 2021-01-2 2021-02-0 2021-02-2 2021-04-0 IBRD / 87400 Posterior Limited 9,167.00 8,930.75 Firmado RVICIO DE SUMINISTRO, INS IWRM at the National Level aciones Envelope 1 2 1 4 2 TALACION, PUESTA EN FUNC IONAMIENTO Y CAPACITACIO N DE PRESAS - PRESA TINAJ ONES EN CHILCAYO - GRUPO II PE-ANA-213297-NC-RFQ / S ERVICIO DE ALQUILER DE 02 CAMIONETAS 4X4 PARA ACTI Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-01-2 2021-01-2 2021-01-3 2021-02-2 2021-04-0 VIDADES DE INSPECCION AL IBRD / 87400 Posterior Limited 18,667.00 18,186.25 Firmado IWRM at the National Level aciones Envelope 1 2 1 4 1 SERVICIO DE SUMINISTRO, I NSTALACION, PUESTA EN FU NCIONAMIENTO Y CAPACITA CION DE PRESAS DEL SUR PE-ANA-213485-NC-RFQ / S ERVICIO DE DISEÑO, DIAGRA Component 3: General Proje Solicitud de cotiz Single Stage - One 2021-03-2 2021-03-2 2021-04-1 2021-05-0 2022-12-3 MACIÓN Y CORRECCIÓN DE IBRD / 87400 Posterior Limited 26,000.00 26,134.23 Firmado ct Adminstration aciones Envelope 5 9 5 3 0 ESTILO DE 11 BOLETINES DI GITALES DEL PGIRH (2021-2 022) PE-ANA-221551-NC-RFQ / C ULMINACIÓN DE LA ADECUA CIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-03-1 2021-05-0 2021-04-0 2021-07-0 2021-06-2 IBRD / 87400 Posterior Limited 49,000.00 46,889.86 Firmado MEDICIÓN DE AGUA EN LOS IWRM at the National Level aciones Envelope 3 7 6 2 2 SECTORES HIDRÁULICOS ME NORES COMPRENDIDOS DES DE TUMBES HASTA ALTO PIU RA PE-ANA-221560-NC-RFQ / C ULMINACIÓN DE LA ADECUA CIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-03-1 2021-03-0 2021-04-0 2021-05-0 2021-06-3 MEDICIÓN DE AGUA EN LOS IBRD / 87400 Posterior Limited 41,500.00 51,703.66 Firmado IWRM at the National Level aciones Envelope 3 8 6 7 0 SECTORES HIDRÁULICOS ME NORES COMPRENDIDOS DES DE OLMOS HASTA JEQUETEP EQUE PE-ANA-229523-NC-RFQ / El aboración de Planes de Moni Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-04-2 2021-04-2 2021-05-0 2021-05-0 2021-10-0 IBRD / 87400 Posterior Limited 50,000.00 10,051.39 Firmado toreo Arqueológico para Esta IWRM at the National Level aciones Envelope 1 6 7 3 4 ciones Hidrometricas PE-ANA-235377-NC-RFQ / S ervicio de movilidad para la supervisión de la culminació Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-06-0 2021-06-2 2021-09-2 IBRD / 87400 Posterior Limited 7,200.00 0.00 Cancelado n de la adecuación de las es IWRM at the National Level aciones Envelope 6 8 8 tructuras de medición de ag ua en sectores hidráulicos d esde Tumbes hasta Alto Piur a PE-ANA-235381-NC-RFQ / S ervicio de movilidad para la supervisión de la culminació Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-07-2 2021-08-1 2021-10-2 IBRD / 87400 Posterior Limited 6,000.00 0.00 Cancelado n de la adecuación de las es IWRM at the National Level aciones Envelope 0 1 6 tructuras de medición de ag ua en sectores hidráulicos d esde Chicama hasta Santa PE-ANA-202887-NC-RFB / SE RVICIO DE COMUNICACIÓN DE DATOS DE ESTRUCTURA Component 1: Consolidating Solicitud de ofert Single Stage - One Ejecución p 2021-10-0 2021-10-0 2021-11-1 2021-12-0 2021-12-2 2022-12-2 IBRD / 87400 Posterior Open - National 142,900.00 0.00 S DE MEDICIÓN DE AGUA EN IWRM at the National Level as Envelope endiente 1 6 7 2 2 7 BLOQUES DE RIEGO A PLATA FORMA DEL SNIRH, CON TEC NOLOGÍA GPRS/GSM-SMS PE-ANA-236180-NC-RFB / SE RVICIO PARA EJECUTAR PERF Component 1: Consolidating Solicitud de ofert Single Stage - One 2021-06-1 2021-06-1 2021-07-2 2021-08-1 2021-09-1 2021-09-1 IBRD / 87400 Posterior Open - National 80,000.00 0.00 Cancelado ILES GAMMA RAY, CE Y T EN IWRM at the National Level as Envelope 1 6 8 7 1 7 PIEZOMETROS CULMINADOS EN ICA Page 6 PE-ANA-241748-NC-RFQ / S ERVICIO PARA EJECUTAR PE Component 1: Consolidating Solicitud de cotiz Single Stage - One En ejecució 2021-07-2 2021-07-2 2021-09-1 2022-03-1 IBRD / 87400 Posterior Limited 40,000.00 0.00 RFILES GAMMA RAY, CE Y T IWRM at the National Level aciones Envelope n 0 2 4 3 EN PIEZOMETROS CULMINA DOS EN ICA PE-ANA-241755-NC-RFQ / S ERVICIO PARA EJECUTAR PE Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2021-07-2 2021-09-1 2022-03-1 IBRD / 87400 Posterior Limited 30,000.00 0.00 RFILES GAMMA RAY, CE Y T IWRM at the National Level aciones Envelope endiente 0 4 3 EN PIEZOMETROS CULMINA DOS EN TACNA PE-ANA-243230-NC-RFQ / S ERVICIO DE CULMINACIÓN D E LA ADECUACIÓN DE TRECE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-07-1 2021-07-1 2021-07-2 2021-09-2 2021-08-2 IBRD / 87400 Posterior Limited 10,300.00 29,595.31 Firmado (13) ESTRUCTURAS DE MEDI IWRM at the National Level aciones Envelope 5 6 7 2 6 CIÓN DE AGUA EN EL SECTO R HIDRÁULICO MENOR PISC O PE-ANA-244365-NC-RFQ / A Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2021-07-2 2021-08-0 2021-09-0 IBRD / 87400 Posterior Limited 5,000.00 0.00 DQUISICION DE TUBERIAS D IWRM at the National Level aciones Envelope endiente 6 6 5 E PVC PE-ANA-248255-NC-RFQ / S ERVICIO DE IMPRESION Y EM Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-08-3 2021-09-1 2021-10-1 PASTADO DE ESTUDIOS EJEC IBRD / 87400 Posterior Limited 2,000.00 0.00 Cancelado IWRM at the National Level aciones Envelope 0 7 7 UTADOS EN EL COMPONENT E MONITOREO DE ACUIFERO S SELECCIONADOS PE-ANA-261827-NC-DIR / SE RVICIO DE ARRENDAMIENTO Component 3: General Proje Adquisición direc 2021-11-0 2021-11-0 2021-11-1 2021-11-0 2021-11-1 2021-11-0 2022-12-3 DEL INMUEBLE N°2 PARA EL IBRD / 87400 Posterior Direct 54,000.00 46,800.00 Firmado ct Adminstration ta 9 8 0 9 5 9 1 PROYECTO GESTION INTEGR ADA DE RECURSOS HIDRICO S (2) PE-ANA-265813-NC-RFQ / El aboración y aprobación de Pl Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-12-1 2021-12-0 2021-12-2 2021-12-3 2022-03-2 anes de Monitoreo Arqueoló IBRD / 87400 Posterior Limited 30,000.00 20,943.23 Firmado IWRM at the National Level aciones Envelope 0 7 5 0 5 gico de Estaciones Hidrológi cas Automáticas en la región Cusco PE-ANA-202823-NC-RFQ / C Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-02-0 2022-03-0 2022-12-2 onductor 02 de camioneta p IBRD / 87400 Posterior Limited 10,625.00 0.00 IWRM at the National Level aciones Envelope endiente 5 1 6 ara la supervisión de EHA - S MA PE-ANA-202818-NC-RFQ / C Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-02-0 2022-03-0 2022-12-2 onductor 01 de camioneta p IBRD / 87400 Posterior Limited 10,625.00 0.00 IWRM at the National Level aciones Envelope endiente 5 1 6 ara la supervisión de EHA - S MA PE-ANA-202826-NC-RFQ / C Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-02-0 2022-03-0 2022-12-2 onductor 04 de camioneta p IBRD / 87400 Posterior Limited 10,625.00 0.00 IWRM at the National Level aciones Envelope endiente 5 1 6 ara la supervisión de EHA - S MA PE-ANA-202824-NC-RFQ / C Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-02-0 2022-04-0 2022-12-0 onductor 03 de camioneta p IBRD / 87400 Posterior Limited 10,625.00 0.00 IWRM at the National Level aciones Envelope endiente 5 2 8 ara la supervisión de EHA - S MA PE-ANA-236194-NC-RFB / SE RVICIO DE PERFILAJE E INTE RPRETACION A TRAVES DE S Component 1: Consolidating Solicitud de ofert Single Stage - One 2021-07-0 2021-07-1 2021-08-2 2021-09-2 2021-10-2 2022-01-2 IBRD / 87400 Posterior Open - National 200,000.00 0.00 Cancelado ONDAS DE RESONANCIA MA IWRM at the National Level as Envelope 5 0 1 0 5 3 GNETIA NUCLEAR (NMR) EN PIEZOMETROS EN EL AMBIT O TACNA PE-ANA-248203-NC-RFQ / S ERVICIO DE SOCIABILIZACIO N DE LA ACTIVIDAD CAMBIO Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-09-0 2021-09-1 2021-11-1 DE ARBOLES DE DESCARGA, IBRD / 87400 Posterior Limited 40,000.00 0.00 Cancelado IWRM at the National Level aciones Envelope 6 9 8 INSTALACION DE FLUJOMETR OS Y SISTEMAS DE TELEMET RIA EN POZOS UBICADOS EN EL AMBITO DE TACNA PE-ANA-244364-NC-RFQ / A DQUISICION DE EQUIPOS DE Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-07-2 2021-08-0 2021-11-0 IBRD / 87400 Posterior Limited 25,000.00 0.00 Cancelado MEDICION DE GAMA RAY, CE IWRM at the National Level aciones Envelope 7 6 4 , T°, ACCESORIOS Y CAPACIT ACION PE-ANA-236191-NC-RFQ / S ERVICIO DE INSTALACION D Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-06-1 2021-08-0 2021-09-0 IBRD / 87400 Posterior Limited 3,000.00 0.00 Cancelado E CARTELES DE IDENTIFICAC IWRM at the National Level aciones Envelope 2 7 6 ION EN POZOS Y PIEZOMETR OS AMBITO TACNA PE-ANA-236190-NC-RFQ / S ERVICIO DE INSTALACION D Component 1: Consolidating Solicitud de cotiz Single Stage - One 2021-06-1 2021-08-0 2021-10-0 IBRD / 87400 Posterior Limited 3,000.00 0.00 Cancelado E CARTELES DE IDENTIFICAC IWRM at the National Level aciones Envelope 2 7 6 ION EN POZOS Y PIEZOMETR OS AMBITO ICA (I-V-L) PE-ANA-126675-NC-RFQ / S ERVICIO DE EJECUCIÓN DE S Component 1: Consolidating Solicitud de cotiz Single Stage - One 2019-09-2 2019-10-3 2019-11-3 IETE PRUEBAS DE BOMBEO E IBRD / 87400 Posterior Open - National 45,000.00 0.00 Cancelado IWRM at the National Level aciones Envelope 1 1 0 N PIEZÓMETROS UBICADOS EN EL ACUÍFERO CAPLINA PE-ANA-161129-NC-RFQ / S ERVICIO DE ADAPTACIÓN DE Component 1: Consolidating Solicitud de ofert Single Stage - One Ejecución p 2022-02-2 2022-03-0 2022-04-1 2022-05-0 2022-06-1 2022-08-0 IBRD / 87400 Posterior Open - National 75,000.00 0.00 ÁRBOLES DE DESCARGA EN IWRM at the National Level as Envelope endiente 8 5 6 6 0 9 POZOS UBICADOS EN EL ÁM BITO DE TACNA PE-ANA-236174-NC-RFQ / S ERVICIO DE IMPLEMENTACIÓ N DE EJEMPLOS PILOTO DE MEDICIÓN DE CONSUMO DE Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-03-0 2022-03-2 2022-06-1 IBRD / 87400 Posterior Limited 50,000.00 0.00 AGUA EN POZOS DE PRODU IWRM at the National Level aciones Envelope endiente 3 1 9 CCIÓN UBICADOS EN EL ÁM BITO DE ICA A TRAVÉS FLUJ ÓMETROSELECTROMÁGNETI COS Y DE TURBINA. PE-ANA-248252-NC-RFQ / C ONDUCTOR DE VEHICULO 0 Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-03-0 2022-03-2 2022-06-1 IBRD / 87400 Posterior Limited 12,000.00 0.00 2 MONITOREO DE ACUIFERO IWRM at the National Level aciones Envelope endiente 3 1 9 S SELECCIONADOS PE-ANA-248250-NC-RFQ / C Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-03-0 2022-03-1 2022-07-1 ONDUCTOR 01 MONITOREO IBRD / 87400 Posterior Limited 12,000.00 0.00 IWRM at the National Level aciones Envelope endiente 3 6 4 DE ACUIFEROS SELECCIONA DOS PE-ANA-248201-NC-RFQ / S ERVICIO DE SOCIABILIZACIO N DE LA ACTIVIDAD SUMINIS Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-03-0 2022-03-2 2022-04-2 IBRD / 87400 Posterior Limited 10,000.00 0.00 TRO, INSTALACION DE FLUJO IWRM at the National Level aciones Envelope endiente 8 1 0 METROS Y SISTEMAS DE TEL EMTERIA EN LOS AMBITOS D E ICA PE-ANA-236182-NC-RFQ / NI VELACIÓN DE PRECISIÓN DE Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-03-0 2022-03-2 2022-06-1 IBRD / 87400 Posterior Limited 15,000.00 0.00 99 POZOS EN LOS ÁMBITOS IWRM at the National Level aciones Envelope endiente 3 1 9 DE ICA VILLACURÍ Y LANCHA S PE-ANA-236181-NC-RFQ / NI VELACIÓN PRECISIÓN DE 47 Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-03-0 2022-03-2 2022-06-1 IBRD / 87400 Posterior Limited 15,000.00 0.00 PIEZÓMETROS UBICADOS EN IWRM at the National Level aciones Envelope endiente 3 1 9 EL ÁMBITO DE TACNA PE-ANA-282138-NC-RFQ / S ERVICIO DE ALQUILER DE AL Component 1: Consolidating Solicitud de cotiz Single Stage - One 2022-03-0 2022-03-3 2022-12-3 IBRD / 87400 Posterior Limited 2,850.00 0.00 Cancelado MACEN PARA CUSTODIA DE IWRM at the National Level aciones Envelope 7 0 1 BIENES DEL PGIRH PE-ANA-283041-NC-RFQ / S ERVICIO DE TRANSPORTE DE Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-03-2 2022-04-0 2022-04-0 IBRD / 87400 Posterior Limited 7,900.00 0.00 DOS EMBARCACIONES FLUVI IWRM at the National Level aciones Envelope endiente 1 3 6 ALES A LAS REGIONES PE-ANA-286118-NC-RFQ / S ervicio de Complementación de Automatización de presas Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-04-0 2022-04-2 2022-06-2 IBRD / 87400 Posterior Limited 23,792.00 0.00 Poechos, San Lorenzo, Tinaj IWRM at the National Level aciones Envelope endiente 9 7 6 ones, Gallito Ciego, El Frayle , Condoroma y Pasto Grande PE-ANA-286122-NC-RFQ / S ervicio de ocho capacitacion es - Instrumentación instala Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-04-1 2022-05-0 2022-06-3 IBRD / 87400 Posterior Limited 14,800.00 0.00 da de Presas Poechos, San L IWRM at the National Level aciones Envelope endiente 3 1 0 orenzo, Tinajones, Gallito Ci ego. El Frayle, Condoroma, S utunta y Pasto Grande. PE-ANA-286125-NC-RFQ / In stalación y puesta en funcio Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-04-1 2022-05-0 2022-08-0 IBRD / 87400 Posterior Limited 21,139.00 0.00 namiento de Cuatro (4) Acel IWRM at the National Level aciones Envelope endiente 8 6 4 erógrafos Presas Condoroma , El Frayle y Pasto Grande PE-ANA-236175-NC-RFQ / S ERVICIO DE IMPLEMENTACIÓ N DE EJEMPLOS PILOTO DE Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-04-0 2022-04-2 2022-07-1 MEDICIÓN DE CONSUMO DE IBRD / 87400 Posterior Limited 50,000.00 0.00 IWRM at the National Level aciones Envelope endiente 2 0 9 AGUA EN POZOS DE PRODU CCIÓN UBICADOS EN EL ÁM BITO DE TACNA A TRAVÉS FL UJÓMETROSELECTROMÁGNE TICOS PE-ANA-314379-NC-RFQ / S ERVICIO DE VOZ (telefonía I Component 3: General Proje Solicitud de cotiz Single Stage - One Ejecución p 2022-09-1 2022-10-0 2023-09-2 IBRD / 87400 Posterior Limited 28,400.00 0.00 P) y DATOS (acceso a intern ct Adminstration aciones Envelope endiente 4 1 6 et) para las 2 sedes PGIRH PE-ANA-314857-NC-RFQ / S ERVICIO DE CAPACITACION E Component 1: Consolidating Solicitud de cotiz Single Stage - One Ejecución p 2022-10-0 2022-10-2 2023-02-2 IBRD / 87400 Posterior Limited 40,000.00 0.00 N EL USO DE SOFTWARES D IWRM at the National Level aciones Envelope endiente 5 7 4 E AGUAS SUBTERRANEAS CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technica Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued l Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SBCC 002 ANA MGRH / CON SULTORIA PARA LA ELABORA CIÓN DE UN PAQUETE DE EX PEDIENTES TECNICOS PARA Selección basada Component 1: Consolidating 2018-06-1 2018-06-0 2018-06-1 2018-06-2 2018-08-1 2018-07-0 2018-10-1 2018-07-1 2018-10-2 2018-07-1 2018-07-3 2018-10-1 CONSTRUCCION DE 200 EST IBRD / 87400 Posterior en calidad y cost Open - National 125,000.00 0.00 Cancelado 2018-06-01 IWRM at the National Level 3 8 8 3 0 8 2 1 6 3 1 4 RUCTURAS DE CONTROL Y M o EDICION DE AGUA EN BLOQ UES DE RIEGO EN DIECIOCH O SECTORES HIDRAULICO D E LA ZONA CENTRO DE LA C OSTA DEL PERU SBCC 003 2018 ANA PGIRH / CONSULTORÍA PARA LA EL ABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS Selección basada Component 1: Consolidating 2018-06-2 2018-06-2 2018-07-2 2018-08-0 2018-08-1 2018-10-2 2018-11-1 2019-02-1 PARA CONSTRUCCIÓN DE 27 IBRD / 87400 Posterior en calidad y cost Open - National 148,931.00 0.00 Cancelado 2018-06-15 IWRM at the National Level 5 0 3 7 6 9 6 4 4 ESTRUCTURAS DE MEDICI o ÓN DE AGUA EN BLOQUES D E RIEGO EN DOCE (12) SECT ORES HIDRÁULICOS DE LA Z ONA NORTE DE LA COSTA D EL PERÚ SBCC 001 ANA PGIRH / FOR Component 2: Improving W Selección basada MULACIÓN DE LOS PLANES Open - Internation 2018-08-0 2018-06-0 2018-07-1 2018-10-0 2018-10-1 2018-10-2 2018-11-2 2020-11-2 IBRD / 87400 RM in Selected Pilot River B Previa en calidad y cost 5,955,217.00 0.00 Cancelado 2018-06-01 DE GESTIÓN DE RECURSOS al 8 6 1 8 9 6 7 6 asins o HDRICOS EN CUATRO CUEN CAS Page 7 SBCC 004 2018 ANA PGIRH / CONSULTORIA PARA LA EL ABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS Selección basada Component 1: Consolidating 2018-07-1 2018-07-1 2018-08-0 2018-08-1 2018-09-1 2018-09-1 2018-09-2 2018-10-0 2019-01-0 PARA CONSTRUCCIÓN DE 33 IBRD / 87400 Posterior en calidad y cost Open - National 155,680.00 0.00 Cancelado 2018-07-05 IWRM at the National Level 7 1 8 5 2 9 7 5 3 7 ESTRUCTURAS DE MEDICI o ÓN DE AGUA EN BLOQUES D E RIEGO EN TREINTA (30) SE CTORES HIDRÁULICOS DE LA ZONA SUR DE LA COSTA DEL PERÚ SBC 001 2018 ANA PGIRH B M / ESTUDIO DE LÍNEA BASE Component 3: General Proje Selección basada 2018-08-0 2018-07-2 2018-08-1 2018-08-2 2018-09-1 2018-09-2 2018-09-1 2018-10-0 2018-09-1 2018-10-1 2018-09-2 2018-10-1 2018-12-2 DEL PIP 302961 GESTIÓN IN IBRD / 87400 Posterior Open - National 88,459.00 99,407.20 Firmado 2018-07-23 ct Adminstration en calidad 8 5 2 2 1 4 4 5 7 8 8 9 7 TEGRADA DE LOS RECURSO S HÍDRICOS EN DIEZ CUENC AS SBCC 005 2018 ANA PGIRH BM / FORMULACIÓN DE LOS Component 2: Improving W Selección basada PLANES DE GESTIÓN DE REC Open - Internation 2018-10-0 2018-09-0 2018-10-1 2018-09-1 2019-03-0 2018-10-1 2019-04-0 2018-10-2 2019-05-0 2018-10-2 2019-07-2 2018-11-1 2019-07-2 2020-11-0 IBRD / 87400 RM in Selected Pilot River B Previa en calidad y cost 1,809,400.00 2,537,766.50 Firmado 2018-08-22 URSOS HÍ DRICOS EN DOS C al 3 6 1 6 6 6 8 1 9 4 4 3 6 2 asins o UENCAS PILOTO DE LA VERT IENTE DEL ATLÁNTICO: MAY O Y MANTARO SBCC 006 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN DE REC Component 2: Improving W Selección basada Open - Internation 2018-10-0 2018-09-0 2018-10-1 2018-09-1 2019-03-0 2018-10-1 2019-04-0 2018-10-2 2019-05-0 2018-10-2 2019-07-2 2018-11-1 2020-05-0 URSOS HIDRICOS EN DOS C IBRD / 87400 RM in Selected Pilot River B Previa en calidad y cost 2,151,920.00 0.00 En ejecución 2018-08-22 al 3 6 1 6 6 6 8 1 9 4 4 3 6 UENCAS PILOTO DE LA VERT asins o IENTE DEL ATLÁNTICO: PAM PAS-APURIMAC Y URUBAMBA -VILCANOTA SBCC 007 2018 ANA PGIRH BM / SUPERVISIÓN DE LA PE Selección basada RFORACIÓN E INSTALACIÓN Component 1: Consolidating 2018-09-0 2018-10-1 2018-09-2 2018-10-2 2018-10-2 2018-10-3 2018-11-1 2019-03-1 IBRD / 87400 Posterior en calidad y cost Open - National 236,142.00 0.00 Cancelado 2018-09-07 DE 58 PIEZOMETROS EN LOS IWRM at the National Level 8 2 5 3 6 0 5 4 o ACUIFEROS DE ICA Y TACNA: LOTE 01 ICA Y LOTE 02 TAC NA SCC 001 2018 ANA PGIRH B Selección basada M / SERVICIO DE ASESORÍA Component 1: Consolidating 2019-01-1 2019-02-1 2019-03-2 2019-05-0 IBRD / 87400 Posterior en calificaciones Limited 190,000.00 0.00 Cancelado 2019-01-04 EN LA EJECUCIÓN DE LAS PE IWRM at the National Level 8 7 4 8 de consultores RFORACIONES EN LA REGIÓ N DE ICA Y TACNA SBCC 001 2019 ANA PGIRH BM / SUPERVISION PARA EL Selección basada SUMINISTRO, INSTALACIÓN, Component 1: Consolidating 2019-04-0 2019-02-1 2019-04-0 2019-03-3 2019-07-0 2019-04-2 2019-08-0 2019-05-0 2019-08-0 2019-05-1 2019-08-1 2019-06-1 2020-01-0 IBRD / 87400 Posterior en calidad y cost Open - National 326,071.00 0.00 En ejecución 2019-02-11 PUESTA EN FUNCIONAMIENT IWRM at the National Level 5 6 5 1 3 8 2 8 9 8 9 3 9 o O Y CAPACITACIÓN DE LA IN STRUMENTACIÓN PARA LA S EGURIDAD DE OCHO PRESA S SCC 001 2019 ANA PGIRH B Component 2: Improving W Selección basada M / SERVICIO DE CONSULTO 2019-04-2 2019-06-0 2019-07-0 2019-08-1 2020-08-1 IBRD / 87400 RM in Selected Pilot River B Posterior en calificaciones Open - National 164,180.00 0.00 Cancelado 2019-04-05 RIA PARA LA IMPLEMENTACI 6 9 9 3 2 asins de consultores ÓN DEL PLAN DE DESARROL LO DE CAPACIDADES SBCC 003 2019 ANA PGIRH Selección basada BM / SERVICIO DE CONSULT Component 1: Consolidating 2019-04-1 2019-04-1 2019-05-0 2019-05-2 2019-06-1 2019-06-2 2019-07-1 2019-11-1 IBRD / 87400 Posterior en calidad y cost Open - National 126,453.73 0.00 En ejecución 2019-04-01 ORIA PARA LA IMPLEMENTAC IWRM at the National Level 7 5 6 7 1 5 7 4 o ION DE LA FASE 0 - GOBIERN O DE DATOS PE-ANA-121030-CS-QCBS / SERVICIO DE CONSULTORÍA PARA LA PROMOCIÓN E IMPL Component 2: Improving W Selección basada EMENTACIÓN DE MECANISM 2021-07-2 2019-09-2 2021-08-1 2019-10-2 2019-11-2 2019-11-2 2019-12-1 2019-12-2 2022-03-1 IBRD / 87400 RM in Selected Pilot River B Posterior en calidad y cost Open - National 1,399,406.25 0.00 En ejecución 2019-09-19 OS DE FINANCIAMIENTO DE 7 4 1 1 0 9 3 3 2 asins o PROGRAMAS Y PROYECTOS DE LOS PLANES DE GESTIÓN INTEGRADA DE RECURSOS H ÍDRICOS DE CUENCA PE-ANA-161088-CS-QCBS / SUPERVISION DEL SUMINIST RO, INSTALACIÓN PUESTA E Selección basada Component 1: Consolidating Open - Internation 2020-05-0 2020-06-1 2020-07-1 2020-08-1 2020-09-1 2020-10-2 2021-10-2 N FUNCIONAMIENTO Y CAPA IBRD / 87400 Posterior en calidad y cost 500,000.00 0.00 Cancelado 2020-04-12 IWRM at the National Level al 3 6 4 3 7 2 2 CITACIÓN DE SISTEMAS ME o CANIZADOS DE AFOROS, PA SARELAS DE AFOROS Y WIN CHAS DE AFOROS PE-ANA-165654-CS-CQS / S Selección basada UPERVISIÓN DE LA CONSTR Component 1: Consolidating 2020-11-2 2021-01-0 2021-02-0 2021-03-1 2021-08-0 IBRD / 87400 Posterior en calificaciones Open - National 80,600.00 0.00 Cancelado 2020-11-02 UCCIÓN DE 131 ESTRUCTUR IWRM at the National Level 3 6 5 2 9 de consultores AS DE MEDICIÓN DE AGUA E N LA REGIÓN PIURA PE-ANA-165655-CS-CQS / S UPERVISIÓN DE LA CONSTR Selección basada Component 1: Consolidating 2020-06-2 2020-08-0 2020-09-0 2020-10-0 2021-03-0 UCCIÓN DE 95 ESTRUCTURA IBRD / 87400 Posterior en calificaciones Open - National 58,449.43 0.00 Cancelado 2020-06-01 IWRM at the National Level 2 5 4 9 8 S DE MEDICIÓN DE AGUA EN de consultores LA REGIÓN LAMBAYEQUE PE-ANA-165656-CS-CQS / S UPERVISIÓN DE LA CONSTR Selección basada Component 1: Consolidating 2020-06-2 2020-08-0 2020-09-0 2020-10-0 2021-03-0 UCCIÓN DE 80 ESTRUCTURA IBRD / 87400 Posterior en calificaciones Open - National 49,220.57 0.00 Cancelado 2020-06-01 IWRM at the National Level 2 5 4 9 8 S DE MEDICIÓN DE AGUA EN de consultores LA REGIÓN LA LIBERTAD PE-ANA-165657-CS-CQS / S Selección basada UPERVISIÓN DE LA CONSTR Component 1: Consolidating 2021-03-2 2020-05-2 2021-03-2 2020-07-0 2021-05-1 2020-08-0 2021-07-0 2020-09-0 2021-08-0 2021-02-0 IBRD / 87400 Posterior en calificaciones Open - National 44,913.77 109,794.54 Firmado 2020-05-01 UCCIÓN DE 73 ESTRUCTURA IWRM at the National Level 3 2 5 5 2 4 2 8 2 5 de consultores S DE MEDICIÓN DE AGUA EN LA REGIÓN ANCASH PE-ANA-165658-CS-CQS / S Selección basada UPERVISIÓN DE LA CONSTR Component 1: Consolidating 2020-05-2 2020-07-0 2020-08-0 2020-09-0 2021-02-0 IBRD / 87400 Posterior en calificaciones Open - National 44,913.77 0.00 Cancelado 2020-05-01 UCCIÓN DE 73 ESTRUCTURA IWRM at the National Level 2 5 4 8 5 de consultores S DE MEDICIÓN DE AGUA EN LA REGIÓN ANCASH PE-ANA-165659-CS-CQS / S Selección basada UPERVISIÓN DE LA CONSTR Component 1: Consolidating 2021-04-1 2020-05-2 2021-04-2 2020-07-0 2021-08-1 2020-08-0 2021-09-0 2020-09-0 2021-09-2 2021-02-0 IBRD / 87400 Posterior en calificaciones Open - National 53,527.37 116,890.84 Firmado 2020-05-01 UCCIÓN DE 87 ESTRUCTURA IWRM at the National Level 5 2 6 5 9 4 7 8 9 5 de consultores S DE MEDICIÓN DE AGUA EN LA REGIÓN LIMA PE-ANA-165660-CS-CQS / S Selección basada UPERVISIÓN DE LA CONSTR Component 1: Consolidating 2020-11-2 2021-01-0 2021-02-0 2021-03-1 2021-08-0 IBRD / 87400 Posterior en calificaciones Open - National 65,832.51 0.00 Cancelado 2020-11-02 UCCIÓN DE 107 ESTRUCTUR IWRM at the National Level 3 6 5 2 9 de consultores AS DE MEDICIÓN DE AGUA E N LA REGIÓN ICA PE-ANA-165661-CS-CQS / S UPERVISIÓN DE LA CONSTR Selección basada Component 1: Consolidating 2020-11-2 2021-01-0 2021-02-0 2021-03-1 2021-09-0 UCCIÓN DE 190 ESTRUCTUR IBRD / 87400 Posterior en calificaciones Open - National 116,898.86 0.00 Cancelado 2020-11-02 IWRM at the National Level 3 6 5 2 8 AS DE MEDICIÓN DE AGUA E de consultores N LA REGIÓN AREQUIPA SBCC 002 2019 ANA PGIRH BM / SUPERVISIÓN PARA EL Selección basada SUMINISTRO, INSTALACIÓN, Component 1: Consolidating 2019-02-2 2019-04-0 2019-05-0 2019-05-1 2019-06-0 2019-07-0 2021-01-0 IBRD / 87400 Previa en calidad y cost Open - National 629,981.44 0.00 Cancelado 2019-02-22 PUESTA EN FUNCIONAMIENT IWRM at the National Level 7 8 8 3 5 6 3 o O Y CAPACITACIÓN DE 153 E STACIONES HIDROLÓGICAS CON 33 EHCA PE-ANA-242466-CS-QCBS / SERVICIO DE CONSULTORIA PARA FORTALECER LAS CAP Component 2: Improving W Selección basada 2021-07-2 2021-08-0 2021-07-2 2021-08-2 2021-08-1 2021-09-1 2021-09-2 2021-10-1 2021-11-0 2022-11-0 ACIDADES DE LOS MIEMBRO IBRD / 87400 RM in Selected Pilot River B Posterior en calidad y cost Open - National 322,000.00 0.00 En ejecución 2021-07-15 3 5 6 0 7 7 7 2 7 7 S DE LOS CONSEJOS DE REC asins o URSOS HÍDRICOS DE LAS CU ENCAS SELECCIONADAS DE LA VERTIENTE DEL PACÍFICO PE-ANA-251936-CS-QCBS / SUPERVISIÓN DE LA CONSTR UCCIÓN DE ESTRUCTURAS D E MEDICIÓN DE AGUA EN 5 Selección basada REGIONES DE LA COSTA DEL Component 1: Consolidating 2021-09-1 2021-10-0 2021-11-1 2021-12-1 2022-01-1 2022-02-1 2022-03-2 2022-10-1 IBRD / 87400 Posterior en calidad y cost Open - National 550,000.00 0.00 Cancelado 2021-09-10 PERU IWRM at the National Level 0 1 4 2 1 5 2 8 o ITEM 1: REGION LAMBAYEQU E (95), ITEM 2: REGION ARE QUIPA (190), ITEM 3: REGIO N PIURA (111), ITEM 4: REGI ON ICA (107), ITEM 5: REGIO N LA LIBERTAD (80) PE-ANA-254267-CS-CQS / S UPERVISIÓN DE LA CONSTR Selección basada Component 1: Consolidating 2021-09-2 2021-10-0 2021-09-2 2021-10-1 2021-10-2 2021-10-1 2021-11-2 2021-11-0 2021-12-1 2022-05-0 UCCIÓN DE 95 ESTRUCTURA IBRD / 87400 Posterior en calificaciones Open - National 109,500.00 119,615.97 Firmado 2021-09-22 IWRM at the National Level 2 6 7 1 9 8 9 4 0 3 S DE MEDICIÓN DE AGUA EN de consultores LA REGIÓN LAMBAYEQUE PE-ANA-254268-CS-QCBS / SUPERVISIÓN DE LA CONSTR Selección basada Component 1: Consolidating 2021-09-2 2021-10-0 2021-10-1 2021-10-1 2022-02-0 2021-11-1 2022-03-0 2021-11-2 2022-04-2 2021-11-2 2022-04-2 2021-12-1 2022-08-1 UCCIÓN DE 190 ESTRUCTUR IBRD / 87400 Posterior en calidad y cost Open - National 183,115.00 0.00 En ejecución 2021-09-22 IWRM at the National Level 9 6 1 6 2 3 8 0 5 7 9 4 1 AS DE MEDICIÓN DE AGUA E o N LA REGIÓN AREQUIPA PE-ANA-254270-CS-QCBS / Selección basada SUPERVISIÓN DE LA CONSTR Component 1: Consolidating 2021-09-2 2021-10-0 2021-10-1 2021-10-1 2021-12-0 2021-11-1 2022-01-1 2021-11-2 2022-01-2 2021-11-2 2022-02-1 2021-12-1 2022-07-1 IBRD / 87400 Posterior en calidad y cost Open - National 127,815.00 152,231.09 En ejecución 2021-09-22 UCCIÓN DE 111 ESTRUCTUR IWRM at the National Level 9 6 1 6 1 3 2 0 6 7 0 4 2 o AS DE MEDICIÓN DE AGUA E N LA REGIÓN PIURA PE-ANA-254272-CS-QCBS / Selección basada SUPERVISIÓN DE LA CONSTR Component 1: Consolidating 2021-09-2 2021-10-0 2021-10-1 2021-10-1 2021-12-3 2021-11-1 2022-02-0 2021-11-2 2022-03-3 2021-11-2 2022-04-1 2021-12-1 2022-07-2 2022-07-1 IBRD / 87400 Posterior en calidad y cost Open - National 127,015.00 121,056.46 Firmado 2021-09-22 UCCIÓN DE 107 ESTRUCTUR IWRM at the National Level 9 6 1 6 0 3 7 0 1 7 9 4 6 2 o AS DE MEDICIÓN DE AGUA E N LA REGIÓN ICA PE-ANA-254274-CS-QCBS / SUPERVISIÓN DE LA CONSTR Selección basada Component 1: Consolidating 2021-09-2 2021-10-0 2021-10-1 2021-10-1 2022-01-1 2021-11-1 2022-02-1 2021-11-2 2022-03-1 2021-11-2 2022-03-2 2021-12-1 2022-05-2 2022-06-1 UCCIÓN DE 80 ESTRUCTURA IBRD / 87400 Posterior en calidad y cost Open - National 106,650.00 106,046.21 Firmado 2021-09-22 IWRM at the National Level 9 6 1 6 7 3 4 0 4 7 9 4 7 2 S DE MEDICIÓN DE AGUA EN o LA REGIÓN LA LIBERTAD PE-ANA-272272-CS-QCBS / SUPERVISIÓN DE CAMPO DE Selección basada Component 1: Consolidating Ejecución pendie 2022-02-1 2022-03-3 2022-04-2 2022-05-2 2022-07-0 2022-08-0 2023-01-0 L SUMINISTRO, INSTALACIÓN IBRD / 87400 Posterior en calidad y cost Open - National 100,000.00 0.00 2022-01-24 IWRM at the National Level nte 4 0 7 7 1 5 2 DE FLUJÓMETROS Y SISTEMA o S DE TELEMETRÍA EN LOS Á MBITOS DE ICA Y TACNA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCI-001 / III Administración Component 3: General Proje 2018-03-3 2018-03-1 2018-03-1 2018-03-1 2018-04-2 2018-04-1 2018-04-0 2018-10-1 General del Proyecto IBRD / 87400 Previa Individual Open 360,000.00 324,000.00 Firmado 2017-12-28 ct Adminstration 1 2 2 5 4 8 6 5 III.a Director Ejecutivo SCI 003 ANA PGIRH / Especi Component 3: General Proje 2018-05-3 2018-05-2 2018-05-2 2018-05-3 2022-11-0 IBRD / 87400 Previa Individual Limited 202,500.00 0.00 Cancelado 2018-05-22 alista en Adquisiciones ct Adminstration 0 3 9 1 6 SCI 004 ANA PGIRH / ESPECI ALISTA EN ADMINISTRACIÓN Component 3: General Proje 2018-06-0 2018-06-0 2018-06-1 2022-05-2 IBRD / 87400 Previa Individual Limited 192,000.00 0.00 Cancelado 2018-05-25 DE RECURSOS HÍDRICOS - C ct Adminstration 1 8 2 2 OORDINADOR DE LA SUPER VISIÓN TÉCNICA SCI 005 ANA PGIRH / ESPECI Component 3: General Proje 2018-06-2 2018-06-0 2018-08-2 2018-06-1 2018-08-2 2018-06-1 2018-08-2 2022-05-2 IBRD / 87400 Posterior Individual Limited 192,000.00 13,730.67 Firmado 2018-05-28 ALISTA EN AGUA SUBTERRÁ ct Adminstration 8 4 7 1 9 3 9 3 NEAS SCI 009 ANA PGIRH / GEOG Component 3: General Proje 2018-08-0 2018-06-0 2018-08-1 2018-06-1 2018-08-1 2018-06-1 2018-08-2 2021-05-2 IBRD / 87400 Posterior Individual Limited 72,000.00 7,292.52 Firmado 2018-05-28 RAFO - SIG ct Adminstration 9 4 1 1 4 3 9 8 SCI 010 ANA PGIRH / ASISTE Component 3: General Proje 2018-09-2 2018-06-0 2018-09-2 2018-06-0 2018-10-0 2018-06-1 2018-10-0 2021-05-2 IBRD / 87400 Posterior Individual Limited 71,460.00 5,955.00 Firmado 2018-05-25 NTE TECNICO TALLERES ct Adminstration 5 1 6 8 1 2 1 7 SCI 011 ANA PGIRH / COOR Component 2: Improving W 2018-06-1 2018-06-0 2018-06-1 2018-06-1 2018-07-0 2018-06-1 2018-07-0 2022-05-2 DINADOR TECNICO CUENCA IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 184,140.00 19,664.33 Firmado 2018-05-28 5 4 8 1 6 3 6 3 PILOTO URUBAMBA asins SCI 012 ANA PGIRH / COOR Component 2: Improving W 2018-06-1 2018-06-0 2018-06-1 2018-06-1 2018-07-0 2018-06-1 2018-07-0 2022-05-2 2018-10-0 DINADOR TECNICO CUENCA IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 184,140.00 19,664.33 Finalizado 2018-05-28 5 4 8 1 6 3 6 3 4 PILOTO MAYO asins Page 8 SCI 013 ANA PGIRH / COOR Component 2: Improving W 2018-07-1 2018-06-0 2018-07-2 2018-06-1 2018-07-2 2018-06-1 2018-07-3 2022-11-1 DINADOR TECNICO CUENCA IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 184,140.00 15,489.35 Firmado 2018-05-28 6 4 0 1 5 3 0 9 PILOTO PAMPAS asins SCI 014 ANA PGIRH / COOR Component 2: Improving W 2018-06-1 2018-06-0 2018-06-1 2018-06-1 2018-07-0 2018-06-1 2018-07-0 2022-05-2 DINADOR TECNICO CUENCA IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 184,140.00 17,105.99 Firmado 2018-05-28 5 4 8 1 5 3 6 3 PILOTO MANTARO asins SCI 017 ANA PGIRH / ASISTE Component 2: Improving W 2018-09-2 2018-06-1 2018-09-2 2018-06-1 2018-10-0 2018-06-2 2018-10-1 2022-06-0 NTE TECNICO DE RECURSOS IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 96,000.00 4,772.45 Firmado 2018-06-04 7 1 7 9 1 2 1 1 HIDRICOS CUENCA PILOTO asins MAYO SCI 016 ANA PGIRH / ASISTE Component 2: Improving W 2018-09-1 2018-06-1 2018-09-1 2018-06-1 2018-09-2 2018-06-2 2018-10-1 2022-06-0 NTE TECNICO DE RECURSOS IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 96,000.00 4,630.53 Firmado 2018-06-04 4 1 4 9 0 2 1 1 HIDRICOS CUENCA PILOTO asins PAMPAS SCI 018 ANA PGIRH / ASISTE Component 2: Improving W 2018-09-1 2018-06-1 2018-09-1 2018-06-1 2018-09-2 2018-06-2 2018-10-1 2022-06-0 NTE TECNICO DE RECURSOS IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 96,000.00 4,763.15 Firmado 2018-06-04 4 1 4 9 4 2 1 1 HIDRICOS CUENCA PILOTO asins MANTARO SCI 024 ANA PGIRH / ESPECI Component 2: Improving W 2018-09-2 2018-06-1 2018-09-2 2018-06-1 2018-10-0 2018-06-2 2018-10-1 2022-11-2 ALISTA SOCIAL AMBIENTAL C IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 151,200.00 6,681.43 Firmado 2018-06-04 7 1 7 9 2 2 1 8 UENCA PILOTO MAYO asins SCI 025 ANA PGIRH / ESPECI Component 2: Improving W 2018-09-2 2018-06-1 2018-09-2 2018-06-1 2018-09-2 2018-06-2 2018-10-1 2022-11-2 ALISTA SOCIAL AMBIENTAL C IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 151,200.00 6,681.43 Firmado 2018-06-04 2 1 2 9 5 2 1 8 UENCA PILOTO PAMPAS asins SCI 026 ANA PGIRH / ESPECI Component 2: Improving W 2018-09-2 2018-06-1 2018-09-2 2018-06-1 2018-09-2 2018-06-2 2018-10-1 2022-11-2 ALISTA SOCIAL AMBIENTAL C IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 151,200.00 6,434.04 Firmado 2018-06-04 2 1 2 9 5 2 1 8 UENCA PILOTO MANTARO asins SCI 027 ANA PGIRH / ASESO Component 3: General Proje 2018-06-0 2018-06-0 2018-06-1 2022-11-1 R EN GESTIÓN DE RECURSO IBRD / 87400 Posterior Individual Limited 286,200.00 0.00 Cancelado 2018-05-25 ct Adminstration 1 8 2 8 S HÍDRICOS SCI 029 ANA PGIRH / SECRE Component 3: General Proje 2018-07-2 2018-06-0 2018-08-0 2018-06-1 2018-08-0 2018-06-1 2018-08-2 2022-11-2 IBRD / 87400 Posterior Individual Limited 64,800.00 4,119.20 Firmado 2018-05-29 TARIA DE LA JEFATURA ct Adminstration 9 6 2 3 8 5 9 1 SCI 031 ANA PGIRH / CHOFE Component 3: General Proje 2018-05-2 2018-06-0 2018-08-1 2018-06-1 2018-08-2 2018-06-1 2018-08-2 2022-11-2 IBRD / 87400 Posterior Individual Limited 54,000.00 3,432.67 Firmado 2018-05-29 R DE JEFATURA ct Adminstration 9 6 5 3 4 5 9 1 SCI 035 ANA PGIRH / ASISTE Component 3: General Proje 2018-05-2 2018-06-0 2018-09-1 2018-06-1 2018-09-1 2018-06-1 2018-09-2 2021-05-3 IBRD / 87400 Posterior Individual Limited 36,000.00 2,747.18 Firmado 2018-05-29 NTE SOPORTE TECNICO ct Adminstration 9 6 3 3 4 5 8 0 SCI 036 ANA PGIRH / SECRE Component 3: General Proje 2018-09-2 2018-06-0 2018-09-2 2018-06-1 2018-09-2 2018-06-1 2018-10-0 2022-11-2 IBRD / 87400 Posterior Individual Limited 54,000.00 2,574.50 Firmado 2018-05-29 TARIA DE ADMINISTRACION ct Adminstration 0 6 6 3 8 5 1 1 Y FINANZAS SCI 037 ANA PGIRH / CHOFE Component 3: General Proje 2018-05-2 2018-06-0 2018-07-3 2018-06-1 2018-08-0 2018-06-1 2018-08-2 2022-11-2 IBRD / 87400 Posterior Individual Limited 48,600.00 3,139.64 Firmado 2018-05-29 R DE ADMINISTRACIÓN Y FIN ct Adminstration 9 6 0 3 8 5 9 1 ANZAS SCI 038 ANA PGIRH / ASISTE Component 3: General Proje 2018-05-2 2018-06-0 2018-09-2 2018-06-1 2018-10-0 2018-06-1 2018-10-0 2021-05-3 IBRD / 87400 Posterior Individual Limited 103,500.00 8,625.00 Firmado 2018-05-29 NTE DE ADQUISICIONES 1 ct Adminstration 9 6 6 3 1 5 1 0 SCI 040 ANA PGIRH / CHOFE Component 3: General Proje 2018-05-2 2018-06-0 2018-08-2 2018-06-1 2018-09-0 2018-06-1 2018-09-2 2022-11-2 IBRD / 87400 Posterior Individual Limited 48,600.00 2,354.73 Firmado 2018-05-29 R DE ADQUISICIONES ct Adminstration 9 6 3 3 7 5 4 1 SCI 042 ANA PGIRH / ASISTE Component 3: General Proje 2018-05-2 2018-06-0 2018-08-2 2018-06-1 2018-09-0 2018-06-1 2018-09-1 2021-05-2 IBRD / 87400 Posterior Individual Limited 67,500.00 6,059.71 Firmado 2018-05-28 NTE DE CONTABILIDAD ct Adminstration 8 4 4 1 4 3 7 8 SCI 043 ANA PGIRH / ESPECI Component 3: General Proje 2018-09-1 2018-06-0 2018-09-1 2018-06-1 2018-09-2 2018-06-1 2018-09-2 2022-11-1 IBRD / 87400 Posterior Individual Limited 155,250.00 7,607.80 Firmado 2018-05-28 ALISTA FINANCIERO ct Adminstration 7 4 8 1 6 3 8 9 SCI 044 ANA PGIRH / ESPECI Component 3: General Proje 2018-08-2 2018-06-0 2018-08-2 2018-06-1 2018-08-2 2018-06-1 2018-08-2 2022-11-1 IBRD / 87400 Posterior Individual Limited 194,076.00 12,680.56 Firmado 2018-05-28 ALISTA EN TESORERIA ct Adminstration 4 4 4 1 9 3 9 9 SCI 045 ANA PGIRH / ASISTE Component 3: General Proje 2018-05-2 2018-06-0 2018-07-3 2018-06-1 2018-08-0 2018-06-1 2018-08-2 2021-05-3 IBRD / 87400 Posterior Individual Limited 67,500.00 6,802.54 Firmado 2018-05-29 NTE DE TESORERIA ct Adminstration 9 6 0 3 8 5 9 0 SCI 033 ANA PGIRH / ESPECI Component 3: General Proje 2018-09-1 2018-06-1 2018-09-1 2018-06-1 2018-09-2 2018-06-2 2018-09-2 2022-11-2 IBRD / 87400 Posterior Individual Limited 155,250.00 7,378.62 Firmado 2018-06-04 ALISTA EN PRESUPUESTO ct Adminstration 1 1 3 8 4 2 4 8 SCI 002 ANA PGIRH / Especi Component 3: General Proje 2018-05-2 2018-05-2 2018-05-2 2018-05-3 2018-11-0 IBRD / 87400 Previa Individual Limited 243,000.00 0.00 Cancelado 2018-05-22 alista en Administración y Fi ct Adminstration 9 3 9 1 9 nanzas SCI 053 ANA PGIRH / ESPECI Component 3: General Proje 2018-06-2 2018-07-0 2018-08-2 2018-07-0 2018-10-0 2018-07-0 2018-10-1 2022-12-3 ALISTA EN ADMINISTRACIÓN IBRD / 87400 Previa Individual Open 243,000.00 13,500.00 Firmado 2018-06-14 ct Adminstration 1 2 2 2 9 3 0 0 Y FINANZAS SCI 054 2018 ANA PGIRH / E Component 3: General Proje 2018-06-2 2018-07-0 2018-08-0 2018-07-0 2018-10-2 2018-07-0 2018-10-2 2022-12-3 IBRD / 87400 Previa Individual Open 202,500.00 9,125.00 Firmado 2018-06-14 SPECIALISTA EN ADQUISICIO ct Adminstration 1 2 3 2 2 3 2 0 NES SCI 007-ANA-PGIRH / ESPEC Component 3: General Proje 2018-06-0 2018-06-0 2018-06-0 2022-05-1 IBRD / 87400 Posterior Individual Direct 192,000.00 0.00 Cancelado 2018-05-25 IALISTA AMBIENTAL ct Adminstration 4 6 8 8 SCI 028 2018 ANA PGIRH B Component 3: General Proje 2018-08-0 2018-07-2 2018-08-1 2018-07-3 2018-08-1 2018-07-3 2018-08-2 2022-12-3 IBRD / 87400 Posterior Individual Limited 192,000.00 13,687.88 Firmado 2018-07-19 M / ESPECIALISTA AMBIENTA ct Adminstration 8 0 0 0 9 1 9 0 L SCI 030 2018 ANA PGIRH B M / ESPECIALISTA EN ADMINI Component 3: General Proje 2018-07-2 2018-09-2 2018-07-3 2018-10-0 2018-07-3 2018-10-0 2022-12-3 STRACIÓN DE RECURSOS HÍ IBRD / 87400 Posterior Individual Limited 192,000.00 12,000.00 Firmado 2018-07-19 ct Adminstration 0 5 0 1 1 1 0 DRICOS - COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 006 2018 ANA PGIRH B Component 3: General Proje 2018-08-0 2018-07-2 2018-08-0 2018-07-3 2018-10-0 2018-07-3 2018-11-0 2022-12-3 M / ASESOR EN GESTIÓN DE IBRD / 87400 Previa Individual Limited 286,200.00 15,900.00 Firmado 2018-07-19 ct Adminstration 2 0 7 0 3 1 5 0 RECURSOS HÍDRICOS SCI 008 2018 ANA PGIRH B Component 3: General Proje 2018-08-2 2018-07-2 2018-08-2 2018-07-3 2018-08-2 2018-07-3 2018-08-2 2022-12-3 M / ESPECIALISTA EN GESTIÓ IBRD / 87400 Posterior Individual Limited 192,000.00 14,155.09 Firmado 2018-07-19 ct Adminstration 5 0 5 0 9 1 9 0 N DE RECURSOS HÍDRICOS SCI 060 2018 ANA PGIRH / E Component 2: Improving W 2018-09-1 2018-07-2 2018-09-1 2018-07-3 2018-09-2 2018-07-3 2018-10-1 2022-12-3 SPECIALISTA EN SISTEMAS D IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 151,200.00 6,434.04 Firmado 2018-07-19 4 0 4 0 5 1 1 0 E INFORMACIÓN CUENCA PIL asins OTO MANTARO SCI 061 2018 ANA PGIRH B Component 2: Improving W 2018-09-2 2018-07-2 2018-09-2 2018-07-3 2018-10-0 2018-07-3 2018-10-1 2022-12-3 M / ESPECIALISTA EN SISTEM IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 151,200.00 6,339.10 Firmado 2018-07-19 5 0 5 0 1 1 2 0 AS DE INFORMACIÓN CUENC asins A PILOTO PAMPAS SCI 062 2018 ANA PGIRH B Component 2: Improving W 2018-09-2 2018-07-2 2020-09-2 2018-07-3 2018-10-0 2018-07-3 2018-10-1 2022-12-3 M / ESPECIALISTA EN SISTEM IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 151,200.00 6,101.27 Firmado 2018-07-19 8 0 8 0 5 1 2 0 AS DE INFORMACIÓN CUENC asins A PILOTO MAYO SCI 063 2018 ANA PGIRH B Component 2: Improving W M / ASISTENTE TÉCNICO EN 2018-10-2 2018-07-2 2018-10-2 2018-07-3 2018-10-2 2018-07-3 2018-11-0 2022-12-3 IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 96,000.00 2,887.04 Firmado 2018-07-19 SISTEMAS DE INFORMACIÓN 3 0 3 0 5 1 9 0 asins CUENCA PILOTO URUBAMBA SCI 064 2018 ANA PGIRH B Component 2: Improving W M / ASISTENTE TÉCNICO EN 2018-07-1 2018-07-2 2018-09-2 2018-07-3 2018-10-0 2018-07-3 2018-10-1 2022-12-3 IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 96,000.00 4,348.05 Firmado 2018-07-19 SISTEMAS DE INFORMACIÓN 9 0 8 0 5 1 6 0 asins CUENCA PILOTO MANTARO SCI 065 2018 ANA PGIRH B Component 2: Improving W M / ASISTENTE TÉCNICO EN 2018-07-1 2018-07-2 2018-09-2 2018-07-3 2018-10-0 2018-07-3 2018-10-1 2022-12-3 IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 96,000.00 4,576.89 Firmado 2018-07-19 SISTEMAS DE INFORMACIÓN 9 0 8 0 2 1 1 0 asins CUENCA PILOTO MAYO SCI 034 2018 ANA PGIRH B Component 2: Improving W M / ASISTENTE TÉCNICO EN 2018-09-1 2018-07-2 2018-09-2 2018-07-3 2018-10-0 2018-07-3 2018-10-1 2022-12-3 IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 96,000.00 4,198.58 Firmado 2018-07-19 SISTEMAS DE INFORMACIÓN 8 0 5 0 2 1 2 0 asins CUENCA PILOTO PAMPAS SBCC 066 2018 ANA PGIRH Component 1: Consolidating 2018-08-2 2018-08-3 2018-09-0 2018-09-0 2018-09-2 2018-09-0 2018-09-2 2022-12-3 IBRD / 87400 Posterior Individual Limited 192,000.00 12,000.00 Firmado 2018-08-28 2018 / ESPECIALISTA EN HID IWRM at the National Level 8 0 7 1 8 5 8 0 ROMETRIA SCI 015 ANA PGIRH / ASISTE Component 2: Improving W 2020-02-2 2019-02-1 2020-02-2 2019-02-2 2020-03-0 2019-02-2 2020-03-0 2020-02-2 NTE TECNICO DE RECURSOS IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 16,119.48 7,099.38 Firmado 2019-02-08 0 5 4 0 2 8 2 8 HIDRICOS CUENCA PILOTO asins URUBAMBA SCI 056 2018 ANA PGIRH B Component 2: Improving W 2019-04-1 2019-02-1 2019-04-2 2019-02-2 2019-04-2 2019-02-2 2019-06-2 2020-02-2 M / COORDINADOR TECNICO IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 40,920.00 5,904.71 Firmado 2019-02-08 7 5 4 0 9 8 8 8 CUENCA URUBAMBA asins SCI 057 2018 ANA PGIRH B Component 2: Improving W 2019-07-1 2019-02-1 2019-07-1 2019-02-2 2019-07-2 2019-02-2 2019-07-3 2020-02-2 M / COORDINADOR TÉCNICO IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 40,920.00 5,511.15 Firmado 2019-02-08 2 5 8 0 4 8 1 8 CUENCA MAYO asins SCI 023 ANA PGIRH / ESPECI Component 2: Improving W 2020-02-1 2019-04-1 2020-02-2 2019-04-2 2020-03-0 2019-04-3 2020-03-0 2020-04-2 ALISTA SOCIAL AMBIENTAL C IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 33,600.00 9,939.13 Firmado 2019-04-05 8 5 4 0 2 0 2 9 UENCA PILOTO URUBAMBA asins SCI 046 ANA PGIRH / ESPECI Component 3: General Proje 2021-11-1 2019-04-1 2021-11-1 2019-04-2 2021-12-0 2019-04-3 2021-12-0 2020-04-2 ALISTA EN CONTROL PATRIM IBRD / 87400 Posterior Individual Limited 34,500.00 3,289.04 Firmado 2019-04-05 ct Adminstration 0 5 9 0 2 0 7 9 ONIAL Y ALMACEN SCI 055 2018 ANA PGIRH B Component 3: General Proje 2019-09-2 2019-05-1 2020-01-1 2019-05-2 2019-05-3 2020-05-2 M / ESPECIALISTA EN ADMINI IBRD / 87400 Posterior Individual Open 54,000.00 0.00 En ejecución 2019-04-05 ct Adminstration 0 5 5 0 1 4 STRACIÓN Y FINANZAS SCI 071 2018 ANA PGIRH B Component 3: General Proje 2019-09-2 2019-05-2 2019-05-2 2019-06-0 2020-06-0 IBRD / 87400 Previa Individual Open 55,880.63 0.00 Bajo Revision 2019-04-05 M / JEFE DE PROYECTO ct Adminstration 0 0 5 9 8 SCI 059 2018 ANA PGIRH / E Component 2: Improving W 2020-02-1 2019-04-2 2020-02-2 2019-04-2 2020-03-0 2019-05-0 2020-03-0 2020-05-0 SPECIALISTA EN SISTEMAS D IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 33,600.00 9,939.13 Firmado 2019-04-05 7 0 1 5 2 5 2 4 E INFORMACIÓN CUENCA PIL asins OTO URUBAMBA SCI 058 2018 ANA PGIRH B M / CONSULTOR EN SEGURI Component 1: Consolidating 2019-04-1 2019-04-2 2019-04-3 2019-05-3 IBRD / 87400 Posterior Individual Limited 6,000.00 0.00 Cancelado 2019-04-05 DAD DE PRESAS -SALVAGUA IWRM at the National Level 5 0 0 0 RDAS BANCO MUNDIAL PE-ANA-116127-CS-INDV / E STUDIO DE INGENIERÍA DE D ETALLE DE TELECOMUNICAC Component 1: Consolidating 2019-07-1 2019-08-0 2019-09-1 2019-12-1 IBRD / 87400 Posterior Individual Open 13,433.00 0.00 Cancelado 2019-05-31 IONES PARA LA TRANSMISIÓ IWRM at the National Level 9 9 3 2 N DE DATOS DE 396 PUNTO S DE MEDICIÓN DE NIVEL EN BLOQUES DE RIEGO PE-ANA-121010-CS-INDV / S UPERVISIÓN DE LA CONTRAT ACIÓN - OBRAS CIVILES PAR A LA IMPLEMENTACIÓN DEL Component 1: Consolidating 2020-02-0 2019-11-2 2020-02-0 2019-11-2 2020-02-2 2019-12-0 2020-02-2 2020-06-0 CENTRO DE DATOS, LABORA IBRD / 87400 Posterior Individual Open 23,880.00 24,349.99 Firmado 2019-10-01 IWRM at the National Level 4 0 3 5 6 5 6 2 TORIO DE INSTRUMENTACIÓ N, CENTRO DE MONITOREO Y MODELAMIENTO DE RECU RSOS HÍDRICOS DE LA AUTO RIDAD NACIONAL DEL AGUA PE-ANA-122155-CS-INDV / A Component 2: Improving W 2020-02-1 2019-10-0 2020-02-2 2019-10-2 2020-02-2 2019-10-3 2020-03-0 2020-10-3 SISTENTE DE COMUNICACIO IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,000.00 7,099.38 Firmado 2019-10-01 7 6 0 1 7 1 2 0 NES CUENCA URUBAMBA asins PE-ANA-122156-CS-INDV / A Component 2: Improving W 2020-02-1 2019-10-0 2020-01-2 2019-10-2 2020-03-0 2019-10-3 2020-03-0 2020-10-3 SISTENTE DE COMUNICACIO IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,000.00 7,099.38 Firmado 2019-10-01 8 6 9 1 2 1 2 0 NES CUENCA MAYO asins PE-ANA-122157-CS-INDV / E Component 2: Improving W 2020-02-1 2019-10-0 2020-01-3 2019-10-2 2020-02-2 2019-10-3 2020-03-0 2020-10-3 SPECIALISTA SOCIAL AMBIEN IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 33,600.00 9,231.08 Firmado 2019-10-01 8 6 0 1 8 1 2 0 TAL CUENCA MAYO asins PE-ANA-122158-CS-INDV / E Component 2: Improving W 2020-02-1 2019-10-0 2020-01-2 2019-10-2 2020-03-0 2019-10-3 2020-03-0 2020-10-3 SPECIALISTA SISTEMA DE IN IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 33,600.00 9,939.13 Firmado 2019-10-01 8 6 9 1 2 1 2 0 FORMACIÓN CUENCA MAYO asins Page 9 PE-ANA-122159-CS-INDV / A Component 2: Improving W 2020-02-1 2019-10-0 2020-02-2 2019-10-2 2020-03-0 2019-10-3 2020-03-0 2020-10-3 SISTENTE DE COMUNICACIÓ IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,000.00 7,101.30 Firmado 2019-10-01 8 6 1 1 2 1 3 0 N CUENCA PAMPAS asins PE-ANA-122160-CS-INDV / C Component 2: Improving W 2020-02-1 2019-10-0 2020-02-2 2019-10-2 2020-03-0 2019-10-3 2020-03-0 2020-10-3 OORDINADOR TÉCNICO CUE IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 134,220.00 61,721.04 Firmado 2019-10-01 8 6 1 1 2 1 2 0 NCA MANTARO asins PE-ANA-122161-CS-INDV / A Component 2: Improving W 2020-02-1 2019-10-0 2020-02-2 2019-10-2 2020-03-0 2019-10-3 2020-03-0 2020-10-3 SISTENTE DE COMUNICACIÓ IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,000.00 7,101.30 Firmado 2019-10-01 8 6 1 1 2 1 2 0 N CUENCA MANTARO asins SCI 047 ANA PGIRH / TECNI Component 3: General Proje 2019-04-1 2019-04-2 2019-04-3 2020-04-2 IBRD / 87400 Posterior Individual Limited 13,500.00 0.00 Cancelado 2019-04-05 CO DE ARCHIVO ct Adminstration 5 0 0 9 SCI 048 ANA PGIRH / ASISTE Component 3: General Proje 2019-04-1 2019-04-2 2019-04-3 2020-04-2 NTE EN SERVICIOS GENERAL IBRD / 87400 Posterior Individual Limited 13,500.00 0.00 Cancelado 2019-04-05 ct Adminstration 5 0 0 9 ES Y ARCHIVO SCI 069 2018 ANA PGIRH B Component 3: General Proje 2019-04-1 2019-04-2 2019-04-3 2020-04-2 M / TECNICO ADMINISTRATIV IBRD / 87400 Posterior Individual Limited 8,400.00 0.00 Cancelado 2019-04-05 ct Adminstration 5 0 0 9 O DE JEFATURA SCI 049 ANA PGIRH / ASIST Component 2: Improving W 2019-04-1 2019-04-2 2019-04-3 2020-04-2 ENTE ADMINISTRATIVO CUE IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 5 0 0 9 NCA PILOTO URUBAMBA asins SCI 050 ANA PGIRH / ASISTE Component 2: Improving W 2019-04-1 2019-04-2 2019-04-3 2020-04-2 NTE ADMINISTRATIVO CUEN IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 5 0 0 9 CA PILOTO MAYO asins SCI 051 ANA PGIRH / ASISTE Component 2: Improving W 2019-04-1 2019-04-2 2019-04-3 2020-04-2 NTE ADMINISTRATIVO CUEN IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 5 0 0 9 CA PILOTO PAMPAS asins SCI 052 ANA PGIRH / ASISTE Component 3: General Proje 2019-04-1 2019-04-2 2019-04-3 2020-04-2 NTE ADMINISTRATIVO CUEN IBRD / 87400 Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 ct Adminstration 5 0 0 9 CA PILOTO MANTARO SCI 020 ANA PGIRH / ASISTE Component 2: Improving W 2019-04-1 2019-04-2 2019-04-3 2020-04-2 NTE TECNICO CULTURA DEL IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 5 0 0 9 AGUA CUENCA PILOTO MAY asins O SCI 021 ANA PGIRH / ASISTE Component 2: Improving W 2019-04-1 2019-04-2 2019-04-3 2020-04-2 NTE TÉCNICO CULTURA DEL IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 5 0 0 9 AGUA CUENCA PILOTO PAM asins PAS SCI 019 ANA PGIRH / ASISTE Component 2: Improving W 2019-04-1 2019-04-2 2019-04-3 2020-04-2 NTE TECNICO CULTURA DEL IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 5 0 0 9 AGUA CUENCA PILOTO URU asins BAMBA SCI 022 ANA PGIRH / ASISTE Component 2: Improving W 2019-04-1 2019-04-2 2019-04-3 2020-04-2 NTE TECNICO CULTURA DEL IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 5 0 0 9 AGUA CUENCA PILOTO MANT asins ARO SCI 070 2018 ANA PGIRH B Component 3: General Proje 2019-04-1 2019-04-2 2019-04-3 2020-04-2 IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 Cancelado 2019-04-05 M / ESPECIALISTA EN INFOR ct Adminstration 5 0 0 9 MATICA PE-ANA-122164-CS-INDV / E Component 3: General Proje Ejecución pendie 2019-10-1 2019-10-2 2019-10-3 2020-10-3 SPECIALISTA EN SISTEMAS D IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 2019-10-01 ct Adminstration nte 6 1 1 0 E INFORMACIÓN SCI 067 2018 ANA PGIRH B M / Supervision de la Contrat ación - Obras Civiles para la Implementación de la Infrae Component 1: Consolidating 2019-04-1 2019-04-2 2019-04-3 2019-10-2 IBRD / 87400 Posterior Individual Limited 19,387.61 0.00 Cancelado 2019-04-05 structura del Centro de Dato IWRM at the National Level 5 0 0 7 s, Laboratorio de Instrument ación, Centro de Monitoreo Y Modelamiento de Recursos Hídricos de la Autoridad Naci onal del Agua PE-ANA-130323-CS-INDV / S UPERVISOR 01 DE LA ELABO RACIÓN DE EXPEDIENTES TÉ Component 1: Consolidating 2019-09-2 2019-09-2 2019-10-2 2019-09-2 2019-10-0 2019-09-3 2019-10-1 2020-01-2 IBRD / 87400 Posterior Individual Limited 14,330.00 8,180.28 Firmado 2019-09-18 CNICOS DE ESTRUCTURAS D IWRM at the National Level 3 3 6 6 7 0 4 8 E MEDICIÓN DE AGUA EN LO S SECTORES HIDRÁULICOS D E LA COSTA DEL PERÚ PE-ANA-130324-CS-INDV / S UPERVISOR 02 DE LA ELABO RACIÓN DE EXPEDIENTES TÉ Component 1: Consolidating 2019-09-2 2019-09-2 2019-10-0 2019-09-2 2019-10-0 2019-09-3 2019-10-1 2020-01-2 IBRD / 87400 Posterior Individual Limited 14,330.00 8,137.40 Firmado 2019-09-18 CNICOS DE ESTRUCTURAS D IWRM at the National Level 3 3 3 6 7 0 4 8 E MEDICIÓN DE AGUA EN LO S SECTORES HIDRÁULICOS D E LA COSTA DEL PERÚ PE-ANA-130325-CS-INDV / S UPERVISOR 03 DE LA ELABO RACIÓN DE EXPEDIENTES TÉ Component 1: Consolidating 2019-09-2 2019-09-2 2019-10-2 2019-09-2 2019-10-0 2019-09-3 2019-11-0 2020-01-2 IBRD / 87400 Posterior Individual Limited 14,330.00 6,259.54 Firmado 2019-09-18 CNICOS DE ESTRUCTURAS D IWRM at the National Level 3 3 3 6 7 0 4 8 E MEDICIÓN DE AGUA EN LO S SECTORES HIDRÁULICOS D E LA COSTA DEL PERÚ PE-ANA-130326-CS-INDV / S UPERVISOR 04 DE LA ELABO RACIÓN DE EXPEDIENTES TÉ Component 1: Consolidating 2019-09-2 2019-09-2 2019-10-0 2019-09-2 2019-10-0 2019-09-3 2019-10-1 2020-01-2 IBRD / 87400 Posterior Individual Limited 14,330.00 8,235.45 Firmado 2019-09-18 CNICOS DE ESTRUCTURAS D IWRM at the National Level 3 3 4 6 1 0 4 8 E MEDICIÓN DE AGUA EN LO S SECTORES HIDRÁULICOS D E LA COSTA DEL PERÚ PE-ANA-130328-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 01 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-09-1 2019-09-1 2019-12-1 RACIÓN DE LOS EXPEDIENTE IBRD / 87400 Posterior Individual Open 38,059.71 0.00 En ejecución 2019-09-05 IWRM at the National Level 2 0 1 3 2 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRÁULICOS TUMBES, SAN LORENZO PE-ANA-130329-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 03 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 IBRD / 87400 Posterior Individual Open 46,567.17 10,314.88 Firmado 2019-09-05 RACIÓN DE LOS EXPEDIENTE IWRM at the National Level 2 0 1 1 0 3 0 4 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTOR HI DRÁULICOS MyBP, SECHURA PE-ANA-130330-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 05 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2020-01-1 RACIÓN DE LOS EXPEDIENTE IBRD / 87400 Posterior Individual Open 46,567.17 10,314.88 Firmado 2019-09-05 IWRM at the National Level 2 0 1 1 0 3 0 1 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRÁULICOS OLMOS, MOTU PE, LA LECHE PE-ANA-130331-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 06 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-3 2019-09-1 2019-09-3 2020-01-1 RACIÓN DE LOS EXPEDIENTE IBRD / 87400 Posterior Individual Open 50,746.27 10,296.71 Firmado 2019-09-05 IWRM at the National Level 2 0 1 1 0 3 0 1 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRAULICOS CHANCAY-LAM BAYEQUE, CHICAMA PE-ANA-130334-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 10 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2019-12-1 IBRD / 87400 Posterior Individual Open 34,925.38 7,758.27 Firmado 2019-09-05 RACIÓN DE LOS EXPEDIENTE IWRM at the National Level 2 0 1 1 0 3 0 2 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRAULICOS CASMA HUAR MEY PE-ANA-130335-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 11 PARA LA ELABO RACIÓN DE LOS EXPEDIENTE Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2019-12-1 IBRD / 87400 Posterior Individual Open 38,059.71 7,736.16 Firmado 2019-09-05 S TÉCNICOS DE ESTRUCTUR IWRM at the National Level 2 0 1 1 0 3 0 2 AS DE MEDICIÓN SECTORES HIDRÁULICOS FORTALEZA, P ATIVILCA, SUPE, HUAURA, C H-HUARAL PE-ANA-130336-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 12 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-2 2019-09-1 2019-09-2 2020-02-1 RACIÓN DE LOS EXPEDIENTE IBRD / 87400 Posterior Individual Open 11,641.80 10,344.36 Firmado 2019-09-05 IWRM at the National Level 2 0 1 1 7 3 7 0 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRÁULICOS CHILLÓN, RIM AC, LURIN, CAÑETE PE-ANA-130337-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 13 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2020-01-1 IBRD / 87400 Posterior Individual Open 46,567.17 10,344.36 Firmado 2019-09-05 RACIÓN DE LOS EXPEDIENTE IWRM at the National Level 2 0 1 1 0 3 0 1 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRAULICOS SAN JUAN, PIS CO PE-ANA-130338-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 14 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-08-1 2019-10-0 2019-09-1 2019-12-3 IBRD / 87400 Posterior Individual Open 34,925.38 7,736.16 Firmado 2019-09-05 RACIÓN DE LOS EXPEDIENTE IWRM at the National Level 2 0 1 5 1 1 0 0 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRÁULICOS ICA, LA ACHIR ANA PE-ANA-130339-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 16 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2019-12-1 IBRD / 87400 Posterior Individual Open 38,059.71 7,692.31 Firmado 2019-09-05 RACIÓN DE LOS EXPEDIENTE IWRM at the National Level 2 0 1 1 0 3 0 2 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRÁULICOS OCOÑA, CAMA NÁ PE-ANA-132925-CS-INDV / C ONSULTORES INDIVIDUALES GRUPO 20 PARA LA ELABOR ACIÓN DE LOS EXPEDIENTES Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2019-12-1 TÉCNICOS DE ESTRUCTURAS IBRD / 87400 Posterior Individual Open 34,925.38 5,157.44 Firmado 2019-09-09 IWRM at the National Level 2 4 1 5 0 7 0 6 DE MEDICIÓN SECTORES HI DRÁULICOS Irrig. EMM, Pta d e Bombón, Moquegua, Torat a, Locumba, Sama, Uchusu ma, Bajo Caplina PE-ANA-132943-CS-INDV / E Component 1: Consolidating 2019-09-2 2019-09-2 2019-10-0 2019-09-2 2019-10-0 2019-09-3 2019-10-1 2020-01-2 SPECIALISTA EN SENSIBILIZA IBRD / 87400 Posterior Individual Limited 44,118.00 5,345.12 Firmado 2019-09-18 IWRM at the National Level 3 3 1 6 1 0 1 8 CIÓN Y CAPACITACIÓN 01 PE-ANA-132945-CS-INDV / E Component 1: Consolidating 2019-09-2 2019-09-2 2019-09-2 2019-09-3 2020-01-2 SPECIALISTA EN SENSIBILIZA IBRD / 87400 Posterior Individual Limited 44,118.00 0.00 En ejecución 2019-09-18 IWRM at the National Level 3 3 6 0 8 CIÓN Y CAPACITACIÓN 02 PE-ANA-120995-CS-INDV / E Component 1: Consolidating 2019-11-2 2019-11-2 2019-12-0 2020-03-0 SPECIALISTA EN SENSIBILIZA IBRD / 87400 Posterior Individual Open 44,118.00 0.00 Cancelado 2019-10-01 IWRM at the National Level 0 5 5 4 CIÓN Y CAPACITACIÓN 01 PE-ANA-120996-CS-INDV / E Component 1: Consolidating 2019-11-2 2019-11-2 2019-12-0 2020-03-0 SPECIALISTA EN SENSIBILIZA IBRD / 87400 Posterior Individual Open 44,118.00 0.00 Cancelado 2019-10-01 IWRM at the National Level 0 5 5 4 CION Y CAPACITACIÓN 02 PE-ANA-130340-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 18 PARA LA ELABO RACIÓN DE LOS EXPEDIENTE Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2020-01-1 IBRD / 87400 Posterior Individual Open 46,567.17 10,314.88 Firmado 2019-09-05 S TÉCNICOS DE ESTRUCTUR IWRM at the National Level 2 0 1 1 0 3 0 1 AS DE MEDICIÓN SECTORES HIDRÁULICOS IRRIG. MAJES, STA RITA DE SIGUAS, LA JOY A, VITOR, YURA PE-ANA-130332-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 08 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-0 2019-09-1 2019-09-1 2020-01-1 RACIÓN DE LOS EXPEDIENTE IBRD / 87400 Posterior Individual Open 46,567.17 10,314.88 Firmado 2019-09-05 IWRM at the National Level 2 0 1 1 2 3 0 1 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRÁULICOS MOCHE, VIRU, CHAO, GUADALUPITO Page 10 PE-ANA-130333-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 09 PARA LA ELABO Component 1: Consolidating 2019-07-2 2019-09-1 2019-08-1 2019-09-1 2019-09-1 2019-09-1 2019-09-1 2019-12-1 RACIÓN DE LOS EXPEDIENTE IBRD / 87400 Posterior Individual Open 38,059.71 7,736.16 Firmado 2019-09-05 IWRM at the National Level 2 0 1 1 0 3 0 2 S TÉCNICOS DE ESTRUCTUR AS DE MEDICIÓN SECTORES HIDRÁULICOS SANTA, NEPE ÑA, IRCHIM PE-ANA-135207-CS-INDV / E Component 3: General Proje 2021-05-1 2019-10-0 2019-10-1 2019-10-1 2020-10-1 IBRD / 87400 Previa Individual Open 45,000.00 0.00 Bajo Revision 2019-09-20 SPECIALISTA EN ADQUISICIO ct Adminstration 9 6 1 4 3 NES PE-ANA-139763-CS-INDV / C ontratación de Consultor Int Component 1: Consolidating 2019-10-2 2019-10-2 2019-10-2 2019-11-0 2019-10-2 2019-11-0 2019-10-2 2019-11-2 ernacional para apoyo técnic IBRD / 87400 Posterior Individual Direct 11,842.00 11,842.00 Firmado 2019-10-21 IWRM at the National Level 1 8 3 2 3 9 9 7 o al Taller Análisis de Modos de fallo potenciales de la pre sa Poechos PE-ANA-152038-CS-INDV / C ONSULTORES INDIVIDUALES - GRUPO 17 PARA LA ELABO RACIÓN DE LOS EXPEDIENTE Component 1: Consolidating 2020-01-1 2020-01-1 2020-01-1 2020-01-2 2020-05-2 IBRD / 87400 Posterior Individual Direct 50,000.00 0.00 En ejecución 2020-01-02 S TÉCNICOS DE ESTRUCTUR IWRM at the National Level 0 2 7 7 6 AS DE MEDICIÓN DE AGUA E N LOS SECTORES HIDRÁULIC OS MENOR VALLE DE MAJES Y VALLE SIGUAS QUILCA PE-ANA-157004-CS-INDV / C ontratación de un Especialist a Internacional para el diagn Component 1: Consolidating 2020-02-0 2020-02-0 2020-02-0 2020-02-0 2020-02-0 2020-02-0 2020-02-0 2020-05-1 IBRD / 87400 Posterior Individual Direct 66,823.00 66,382.18 Firmado 2020-01-31 óstico de situación y análisis IWRM at the National Level 3 2 3 2 4 2 3 7 de la seguridad de la presa P oechos recrecida, durante el llenado del embalse PE-ANA-155010-CS-INDV / S UPERVISOR 01 DE LA ELABO RACIÓN DE EXPEDIENTES TÉ Component 1: Consolidating 2020-02-0 2020-02-0 2020-02-0 2020-02-0 2020-02-0 2020-02-1 2020-02-0 2020-04-1 IBRD / 87400 Posterior Individual Direct 7,165.00 6,259.54 Firmado 2020-02-06 CNICOS DE ESTRUCTURAS D IWRM at the National Level 4 8 4 9 6 3 7 3 E MEDICIÓN DE AGUA EN LO S SECTORES HIDRÁULICOS D E LA COSTA DEL PERU PE-ANA-155004-CS-INDV / G RUPO 19 PARA LA ELABORA CIÓN DE LOS EXPEDIENTES Component 1: Consolidating 2020-02-0 2020-02-0 2020-02-0 2020-02-1 2020-05-1 TÉCNICOS DE ESTRUCTURAS IBRD / 87400 Posterior Individual Direct 34,925.00 0.00 En ejecución 2020-02-06 IWRM at the National Level 4 8 9 3 3 DE MEDICIÓN DE AGUA EN L OS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO. PE-ANA-154991-CS-INDV / G RUPO 07 PARA LA ELABORA CIÓN DE LOS EXPEDIENTES Component 1: Consolidating 2020-02-0 2020-02-0 2020-02-0 2020-02-1 2020-05-1 IBRD / 87400 Posterior Individual Direct 33,134.00 0.00 En ejecución 2020-02-06 TÉCNICOS DE ESTRUCTURAS IWRM at the National Level 4 8 9 4 5 DE MEDICIÓN DE AGUA EN L OS SECTORES HIDRÁULICOS ZAÑA Y JEQUETEPEQUE PE-ANA-155862-CS-INDV / G RUPO 02 - PARA ELABORACI Component 1: Consolidating 2020-02-0 2020-02-0 2020-02-0 2020-02-1 2020-05-1 IBRD / 87400 Posterior Individual Direct 38,059.00 0.00 En ejecución 2020-02-06 ÓN DE EXPEDIENTES TÉCNIC IWRM at the National Level 4 8 9 3 3 OS DE ESTRUCTURAS DE ME DICIÓN DE AGUA. PE-ANA-155863-CS-INDV / G RUPO 15 PARA ELABORACIÓ Component 1: Consolidating 2020-02-0 2020-02-0 2020-02-0 2020-02-1 2020-06-1 IBRD / 87400 Posterior Individual Direct 46,566.00 0.00 En ejecución 2020-02-06 N DE EXPEDIENTES TÉCNICO IWRM at the National Level 4 8 9 3 2 S DE ESTRUCTURAS DE MED ICIÓN DE AGUA PE-ANA-154996-CS-INDV / G RUPO 04 PARA LA ELABORA CIÓN DE LOS EXPEDIENTES Component 1: Consolidating 2020-02-0 2020-02-0 2020-02-0 2020-02-1 2020-05-1 TÉCNICOS DE ESTRUCTURAS IBRD / 87400 Posterior Individual Direct 38,060.00 0.00 En ejecución 2020-02-06 IWRM at the National Level 4 8 9 3 3 DE MEDICIÓN DE AGUA EN L OS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO PE-ANA-160683-CS-INDV / C ONSULTORES ADICIONALES AL GRUPO 07 PARA LA ELAB Component 1: Consolidating 2020-03-0 2020-03-1 2020-03-1 2020-03-2 2020-06-0 ORACIÓN DE LOS EXPEDIEN IBRD / 87400 Posterior Individual Direct 18,400.00 0.00 En ejecución 2020-03-16 IWRM at the National Level 3 8 9 4 8 TES TÉCNICOS DE ESTRUCT URAS DE MEDICIÓN DE AGU A EN LOS SECTORES HIDRÁU LICOS ZAÑA Y JEQUETEPEQU E PE-ANA-161048-CS-INDV / E Component 2: Improving W 2020-02-1 2020-03-0 2020-02-2 2020-03-1 2020-03-1 2020-03-2 2023-01-0 SPECIALISTA SOCIAL AMBIEN IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 93,170.00 8,353.32 En ejecución 2020-03-02 7 9 1 6 3 7 1 TAL CUENCA PAMPAS asins PE-ANA-161050-CS-INDV / A Component 2: Improving W 2020-03-0 2020-03-0 2020-03-1 2020-03-1 2020-03-1 2020-03-2 2020-03-1 2022-12-3 SISTENTE DE RECURSOS HID IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 93,170.00 6,151.37 Firmado 2020-03-02 2 9 0 6 0 7 3 0 RICOS CUENCA PAMPAS asins PE-ANA-161052-CS-INDV / C Component 2: Improving W 2020-03-0 2020-03-0 2020-03-1 2020-03-1 2020-03-3 2020-03-2 2020-03-3 2022-12-3 OORDINADOR TÉCNICO CUE IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 113,469.00 8,970.73 Firmado 2020-03-02 2 9 0 6 1 4 1 0 NCA URUBAMBA asins PE-ANA-163778-CS-INDV / S UPERVISOR PARA LA ADECU ACIÓN DE ESTRUCTURAS DE Component 1: Consolidating 2020-03-1 2020-03-2 2020-03-2 2020-05-2 MEDICIÓN DE NIVEL DE AGU IBRD / 87400 Posterior Individual Limited 4,776.00 0.00 Cancelado 2020-03-16 IWRM at the National Level 7 4 5 5 A EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICO S MENOR ICA, PALPA, NAZCA , ACARY Y BELLA UNIÓN. PE-ANA-163779-CS-INDV / S UPERVISOR PARA LA ADECU ACIÓN DE ESTRUCTURAS DE Component 1: Consolidating 2020-08-1 2020-03-1 2020-08-2 2020-03-2 2020-09-1 2020-03-2 2020-09-1 2020-06-0 MEDICIÓN DE NIVEL DE AGU IBRD / 87400 Posterior Individual Limited 5,970.00 7,694.18 Firmado 2020-03-16 IWRM at the National Level 0 7 6 4 5 5 5 8 A EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO ME NOR IRRIGACION MAJES, VAL LE DE MAJES, CAMANA PE-ANA-164551-CS-INDV / A POYO AL ANÁLISIS DE LA SE Component 1: Consolidating 2020-01-2 2020-04-0 2020-04-1 2020-04-2 2020-05-0 GURIDAD DE LA PRESA POE IBRD / 87400 Posterior Individual Direct 6,500.00 0.00 En ejecución 2020-04-01 IWRM at the National Level 9 8 3 0 8 CHOS RECRECIDA, DURANTE EL LLENADO DEL EMBALSE PE-ANA-164570-CS-INDV / S Component 1: Consolidating 2020-04-2 2020-04-2 2020-04-2 2020-05-1 2020-05-1 2020-06-1 2020-07-0 2020-12-3 ERVICIO DE COORDINADOR IBRD / 87400 Posterior Individual Limited 30,600.00 26,133.61 Firmado 2020-04-19 IWRM at the National Level 1 4 1 5 2 9 6 1 DE CALIDAD DE RECURSOS HIDRICOS PGIRH PE-ANA-164571-CS-INDV / S ERVICIO DE ESPECIALISTA D Component 1: Consolidating 2020-04-3 2020-04-0 2020-05-1 2020-04-1 2020-05-2 2020-05-0 2020-12-3 IBRD / 87400 Posterior Individual Limited 19,600.00 13,367.93 En ejecución 2020-03-29 E CALIDAD DE AGUA SUPERF IWRM at the National Level 0 3 1 8 9 3 1 ICIAL CUENCA URUBAMBA PE-ANA-164572-CS-INDV / S ERVICIO DE ESPECIALISTA D Component 1: Consolidating 2020-03-3 2020-04-0 2020-05-1 2020-04-1 2020-05-2 2020-05-0 2020-12-3 IBRD / 87400 Posterior Individual Limited 19,600.00 13,367.93 En ejecución 2020-03-29 E CALIDAD DE AGUA SUPERF IWRM at the National Level 0 3 1 8 9 3 1 ICIAL CUENCA PAMPAS PE-ANA-164573-CS-INDV / S ERVICIO DE ESPECIALISTA D Component 1: Consolidating 2020-04-3 2020-04-0 2021-05-1 2020-04-1 2020-05-2 2020-05-0 2020-06-0 2020-12-3 IBRD / 87400 Posterior Individual Limited 19,600.00 13,367.93 Firmado 2020-03-29 E CALIDAD DE AGUA SUPERF IWRM at the National Level 0 3 1 8 9 3 5 1 ICIAL CUENCA MAYO PE-ANA-164574-CS-INDV / S ERVICIO DE ESPECIALISTA E Component 1: Consolidating 2020-04-1 2020-04-0 2020-04-2 2020-04-1 2020-05-0 2020-05-0 2020-12-3 IBRD / 87400 Posterior Individual Limited 19,600.00 19,084.99 En ejecución 2020-03-29 N GESTION DE CALIDAD DE IWRM at the National Level 3 3 4 8 8 3 1 RECURSOS HIDRICOS CUENC A MANTARO PE-ANA-164991-CS-INDV / S ERVICIO DE APOYO EN PROC ESAMIENTO DE INFORMACIO Component 1: Consolidating 2020-04-0 2020-04-0 2020-06-2 2020-04-2 2020-07-0 2020-05-0 2020-07-0 2020-12-3 IBRD / 87400 Posterior Individual Limited 16,000.00 9,694.36 Firmado 2020-04-01 N DE ACTIVIDADES DEL COM IWRM at the National Level 1 6 4 1 2 6 2 1 PONENTE DE CALIDAD DE R ECURSOS HIDRICOS EN LA C UENCA MANTARO PE-ANA-164992-CS-INDV / S ERVICIO DE APOYO EN GESTI ONES Y MONITOREO DE EJEC Component 1: Consolidating 2020-04-0 2020-04-0 2020-04-2 2020-04-1 2020-05-0 2020-04-2 2020-07-0 2020-12-3 IBRD / 87400 Posterior Individual Limited 11,000.00 10,394.88 Firmado 2020-04-01 UCION DE ACTIVIDADES DEL IWRM at the National Level 6 6 4 1 8 1 6 1 COMPONENTE DE MONITORE O DE LA CALIDAD DE LOS RE CURSOS HIDRICOS PGIRH PE-ANA-165879-CS-INDV / S UPERVISOR PARA LA ADECU ACIÓN DE ESTRUCTURAS DE Component 1: Consolidating 2020-08-1 2020-05-2 2020-08-2 2020-05-2 2020-09-1 2020-05-2 2020-09-1 2020-07-2 MEDICIÓN DE NIVEL DE AGU IBRD / 87400 Posterior Individual Limited 5,672.00 5,134.37 Firmado 2020-05-20 IWRM at the National Level 0 1 6 8 5 9 5 7 A EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICO S MENOR ICA, PALPA, NAZCA , ACARY Y BELLA UNIÓN PE-ANA-165880-CS-INDV / S UPERVISOR PARA LA ADECU ACIÓN DE ESTRUCTURAS DE Component 1: Consolidating 2020-05-2 2020-05-2 2020-05-2 2020-08-1 MEDICIÓN DE NIVEL DE AGU IBRD / 87400 Posterior Individual Limited 7,090.00 0.00 Cancelado 2020-05-20 IWRM at the National Level 1 8 9 2 A EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO ME NOR IRRIGACIÓN MAJES , VA LLE DE MAJES, CAMANÁ PE-ANA-165881-CS-INDV / S UPERVISOR PARA LA ADECU ACIÓN DE ESTRUCTURAS DE Component 1: Consolidating 2020-08-1 2020-06-2 2020-08-2 2020-06-2 2020-09-1 2020-06-3 2020-09-1 2020-09-1 MEDICIÓN DE NIVEL DE AGU IBRD / 87400 Posterior Individual Limited 7,090.00 7,701.56 Firmado 2020-06-19 IWRM at the National Level 0 2 6 9 5 0 5 4 A EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO ME NOR LA JOYA, CHILI REGULA DO Y CHILI NO REGULADO PE-ANA-165883-CS-INDV / S UPERVISOR PARA LA ADECU ACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE AGU Component 1: Consolidating 2020-09-2 2020-06-2 2020-09-2 2020-06-2 2020-10-3 2020-06-3 2020-10-3 2020-08-2 A EN BLOQUES DE RIEGO EN IBRD / 87400 Posterior Individual Limited 5,672.00 6,417.96 Firmado 2020-06-19 IWRM at the National Level 2 2 5 9 0 0 0 8 EL SECTOR HIDRÁULICO ME NOR IRRIGACIÓN ENSENADA -MEJIA-MOLLENDO, PUNTA D E BOMBOM, MOQUEGUA, LO CUMBA, SAMA Y BAJO UCHU SUMA PE-ANA-165889-CS-INDV / B ACHILLER 01 PARA TRABAJO Component 1: Consolidating 2020-04-2 2020-05-1 2020-06-2 2022-11-0 S DE HIDROMETRÍA EN ESTR IBRD / 87400 Posterior Individual Limited 38,955.00 0.00 Cancelado 2020-04-20 IWRM at the National Level 7 8 2 9 UCTURAS DE MEDICIÓN DE AGUA, EN LA COSTA DEL PE RÚ PE-ANA-165890-CS-INDV / B ACHILLER 02 PARA TRABAJO Component 1: Consolidating 2020-04-2 2020-05-1 2020-06-2 2022-11-0 S DE HIDROMETRÍA EN ESTR IBRD / 87400 Posterior Individual Limited 38,955.00 0.00 Cancelado 2020-04-20 IWRM at the National Level 7 8 2 9 UCTURAS DE MEDICIÓN DE AGUA, EN LA COSTA DEL PE RÚ PE-ANA-165891-CS-INDV / P ROFESIONAL ESPECIALISTA Component 1: Consolidating 2020-03-3 2020-04-2 2020-04-0 2020-05-1 2020-04-1 2020-06-2 2020-07-0 2021-02-1 IBRD / 87400 Posterior Individual Limited 26,269.00 8,562.53 Firmado 2020-04-20 PARA ADECUACIÓN DE ESTR IWRM at the National Level 0 7 1 8 3 2 6 7 UCTURAS DE MEDICIÓN DE AGUA PE-ANA-165964-CS-INDV / T ÉCNICO 01: SENSIBILIZACIÓ Component 1: Consolidating 2020-04-2 2020-04-2 2020-05-1 2021-03-1 IBRD / 87400 Posterior Individual Limited 14,300.00 0.00 Cancelado 2020-04-19 N Y CAPACITACIÓN EN SISTE IWRM at the National Level 4 9 4 0 MAS HIDRÁULICOS COMUNE S DE LA COSTA PE-ANA-165971-CS-INDV / T ÉCNICO 02: SENSIBILIZACIÓ Component 1: Consolidating 2020-04-2 2020-04-2 2020-05-1 2021-03-1 IBRD / 87400 Posterior Individual Limited 14,300.00 0.00 Cancelado 2020-04-19 N Y CAPACITACIÓN EN SISTE IWRM at the National Level 4 9 4 0 MAS HIDRÁULICOS COMUNE S DE LA COSTA PE-ANA-165979-CS-INDV / T ÉCNICO EN METRADOS, COS Component 1: Consolidating 2020-04-2 2020-04-2 2020-04-2 2020-04-3 2020-06-0 2020-05-1 2020-06-0 2020-08-1 TOS Y PRESUPUESTOS 01 PA IBRD / 87400 Posterior Individual Limited 4,030.00 3,633.92 Firmado 2020-04-20 IWRM at the National Level 0 5 2 0 8 5 8 3 RA ESTANDARIZACIÓN E INT EGRACIÓN DE EXPEDIENTTE S TÉCNICOS Page 11 PE-ANA-165984-CS-INDV / T ÉCNICO EN METRADOS, COS Component 1: Consolidating 2020-04-2 2020-04-2 2020-04-2 2020-04-3 2020-06-0 2020-05-0 2020-06-0 2020-08-0 TOS Y PRESUPUESTOS 02 PA IBRD / 87400 Posterior Individual Limited 4,030.00 3,633.92 Firmado 2020-04-20 IWRM at the National Level 0 5 2 0 8 6 8 4 RA ESTANDARIZACIÓN E INT EGRACIÓN DE EXPEDIENTTE S TÉCNICOS PE-ANA-165985-CS-INDV / P ROFESIONAL ESPECIALISTA Component 1: Consolidating 2020-03-3 2020-04-2 2020-04-0 2020-04-3 2020-04-0 2020-05-0 2020-04-2 2022-01-2 IBRD / 87400 Posterior Individual Limited 81,493.00 28,070.18 Firmado 2020-04-20 EN EJECUCIÓN DE OBRAS DE IWRM at the National Level 0 5 2 0 1 6 2 6 ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165987-CS-INDV / P ROFESIONAL ASISTENTE EN Component 1: Consolidating 2020-03-3 2020-04-2 2020-04-0 2020-04-3 2020-04-0 2020-05-0 2020-04-2 2022-01-2 IBRD / 87400 Posterior Individual Limited 59,553.00 20,512.82 Firmado 2020-04-20 EJECUCIÓN DE OBRAS DE ES IWRM at the National Level 0 5 2 0 1 6 2 6 TRUCTURAS DE MEDICIÓN D E AGUA PE-ANA-165989-CS-INDV / S UPERVISIÓN DE LA CONSTR Component 1: Consolidating 2020-09-1 2020-04-2 2020-09-1 2020-04-3 2020-10-0 2020-05-1 2021-02-1 2020-08-1 IBRD / 87400 Posterior Individual Limited 14,142.00 14,011.42 Firmado 2020-04-20 UCCIÓN DE 22 ESTRUCTURA IWRM at the National Level 6 5 7 0 2 5 0 3 S DE MEDICIÓN DE AGUA EN LA REGIÓN TUMBES PE-ANA-165990-CS-INDV / S UPERVISIÓN DE LA CONSTR Component 1: Consolidating 2020-09-1 2020-04-2 2020-11-0 2020-04-3 2020-11-0 2020-05-1 2020-11-1 2020-05-2 UCCIÓN DE 11 ESTRUCTURA IBRD / 87400 Posterior Individual Limited 7,071.00 8,118.86 Firmado 2020-04-20 IWRM at the National Level 6 5 4 0 9 5 8 1 S DE MEDICIÓN DE AGUA EN LA REGIÓN MOQUEGUA PE-ANA-165991-CS-INDV / S UPERVISIÓN DE LA CONSTR Component 1: Consolidating 2020-09-1 2020-04-2 2020-09-1 2020-04-3 2020-10-0 2020-05-1 2020-11-0 2020-07-1 IBRD / 87400 Posterior Individual Limited 9,643.00 9,705.99 Firmado 2020-04-20 UCCIÓN DE 15 ESTRUCTURA IWRM at the National Level 6 5 1 0 2 5 2 4 S DE MEDICIÓN DE AGUA EN LA REGIÓN TACNA PE-ANA-165993-CS-INDV / S UPERVISOR PARA LA ADECU ACIÓN DE ESTRUCTURAS DE Component 1: Consolidating 2020-07-1 2020-04-2 2020-07-0 2020-04-3 2020-07-2 2020-05-1 2020-07-1 IBRD / 87400 Posterior Individual Limited 5,672.00 4,917.82 En ejecución 2020-04-20 MEDICIÓN DE NIVEL DE AGU IWRM at the National Level 0 5 9 0 9 5 4 A EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO ME NOR PISCO PE-ANA-165994-CS-INDV / S UPERVISIÓN PARA LA CULMI NACIÓN DE LA ADECUACIÓN Component 1: Consolidating 2020-04-2 2020-04-3 2020-05-1 2020-08-1 IBRD / 87400 Posterior Individual Limited 8,508.00 0.00 Cancelado 2020-04-20 DE ESTRUCTURAS DE MEDIC IWRM at the National Level 5 0 5 3 IÓN DE AGUA EN LOS SECTO RES HIDRÁULICOS DESDE T UMBES HASTA JEQUETEPEQ UE PE-ANA-165998-CS-INDV / S UPERVISIÓN PARA LA CULMI NACIÓN DE LA ADECUACIÓN Component 1: Consolidating 2020-04-2 2020-04-3 2020-05-1 2020-07-1 IBRD / 87400 Posterior Individual Limited 5,672.00 0.00 Cancelado 2020-04-20 DE ESTRUCTURAS DE MEDIC IWRM at the National Level 5 0 5 4 IÓN DE AGUA EN LOS SECTO RES HIDRÁULICOS DESDE C HICAMA HASTA SANTA PE-ANA-165999-CS-INDV / S UPERVISIÓN PARA LA CULMI NACIÓN DE LA ADECUACIÓN Component 1: Consolidating 2020-04-2 2020-04-3 2020-05-1 2020-07-1 IBRD / 87400 Posterior Individual Limited 5,672.00 0.00 Cancelado 2020-04-20 DE ESTRUCTURAS DE MEDIC IWRM at the National Level 5 0 5 4 IÓN DE AGUA EN LOS SECTO RES HIDRÁULICOS DESDE F ORTALEZA HASTA LURÍN PE-ANA-166000-CS-INDV / T ÉCNICO 01 PARA SUPERVISI ÓN DEL SUMINISTRO, INSTA Component 1: Consolidating 2020-04-2 2020-04-3 2020-05-1 2021-05-1 IBRD / 87400 Posterior Individual Limited 25,075.00 0.00 Cancelado 2020-04-20 LACIÓN, PUESTA EN MARCH IWRM at the National Level 5 0 5 0 A Y CAPACITACIÓN DE INSTR UMENTACIÓN PARA LA MEDI CIÓN PE-ANA-166002-CS-INDV / T ÉCNICO 02 PARA SUPERVISI ÓN DEL SUMINISTRO, INSTA Component 1: Consolidating 2020-04-2 2020-04-3 2020-05-1 2021-05-1 IBRD / 87400 Posterior Individual Limited 25,075.00 0.00 Cancelado 2020-04-20 LACIÓN, PUESTA EN MARCH IWRM at the National Level 5 0 5 0 A Y CAPACITACIÓN DE INSTR UMENTACIÓN PARA LA MEDI CIÓN PE-ANA-171096-CS-INDV / T ECNICO EN AUTOCAD 01 PA Component 1: Consolidating 2020-04-2 2020-04-2 2020-05-2 2020-05-0 2020-06-0 2020-05-0 2020-06-0 2020-08-0 IBRD / 87400 Posterior Individual Limited 4,030.00 3,648.11 Firmado 2020-04-27 RA ESTANDARIZACION E INT IWRM at the National Level 0 9 2 4 8 5 8 3 EGRACION DE PLANOS PE-ANA-171097-CS-INDV / T ECNICO EN AUTOCAD 02 PA Component 1: Consolidating 2020-04-2 2020-04-2 2020-04-2 2020-05-0 2020-06-0 2020-05-0 2020-06-0 2020-08-0 IBRD / 87400 Posterior Individual Limited 4,030.00 3,648.11 Firmado 2020-04-27 RA ESTANDARIZACION E INT IWRM at the National Level 0 9 2 4 8 5 8 3 EGRACION DE PLANOS PE-ANA-171099-CS-INDV / T ECNICO EN AUTOCAD 03 PA Component 1: Consolidating 2020-04-2 2020-04-2 2020-05-2 2020-05-0 2020-06-0 2020-05-0 2020-06-0 2020-08-0 IBRD / 87400 Posterior Individual Limited 4,030.00 3,648.11 Firmado 2020-04-27 RA ESTANDARIZACION E INT IWRM at the National Level 0 9 2 4 8 5 8 3 EGRACION DE PLANOS PE-ANA-165886-CS-INDV / P ROFESIONAL 01 PARA TRAB Component 1: Consolidating 2020-05-1 2020-06-0 2020-07-1 2022-11-2 AJOS DE HIDROMETRÍA EN E IBRD / 87400 Posterior Individual Limited 51,940.00 0.00 Cancelado 2020-05-08 IWRM at the National Level 5 5 0 7 STRUCTURAS DE MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165888-CS-INDV / P ROFESIONAL 02 PARA TRAB Component 1: Consolidating 2020-05-1 2020-06-0 2020-07-1 2022-11-2 AJOS DE HIDROMETRÍA EN E IBRD / 87400 Posterior Individual Limited 51,940.00 0.00 Cancelado 2020-05-08 IWRM at the National Level 5 5 0 7 STRUCTURAS DE MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-171926-CS-INDV / P ROFESIONAL 01 PARA ESTA Component 1: Consolidating 2020-04-1 2020-05-1 2020-04-2 2020-05-1 2020-06-0 2020-05-2 2020-06-0 2020-08-1 IBRD / 87400 Posterior Individual Limited 8,400.00 7,671.60 Firmado 2020-05-03 NDARIZACIÓN E INTEGRACIÓ IWRM at the National Level 4 3 2 6 2 0 2 8 N DE EXPEDIENTES TÉCNICO S PE-ANA-171929-CS-INDV / P ROFESIONAL 02 PARA ESTA Component 1: Consolidating 2020-04-1 2020-05-0 2020-04-2 2020-05-1 2020-06-0 2020-05-1 2020-06-0 2020-08-1 IBRD / 87400 Posterior Individual Limited 8,400.00 7,671.60 Firmado 2020-05-03 NDARIZACIÓN E INTEGRACIÓ IWRM at the National Level 4 8 2 1 2 4 2 2 N DE EXPEDIENTES TÉCNICO S PE-ANA-182711-CS-INDV / P ROFESIONAL SENIOR PARA A Component 1: Consolidating 2020-06-3 2020-07-0 2020-06-3 2020-07-0 2020-07-0 2020-07-1 2020-07-0 2020-11-1 IBRD / 87400 Posterior Individual Direct 21,000.00 19,411.82 Firmado 2020-06-30 CTUALIZAR LA POLITICA Y ES IWRM at the National Level 0 2 0 7 2 3 2 0 TRATEGIA NACIONAL DE REC URSOS HÍDRICOS. PE-ANA-187092-CS-INDV / E Component 2: Improving W 2020-09-2 2020-09-2 2020-09-2 2020-09-2 2020-10-0 2020-10-0 2020-10-0 2022-12-3 SPECIALISTA SOCIAL AMBIEN IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 73,500.00 7,416.42 Firmado 2020-09-21 3 6 4 8 2 1 2 1 TAL CUENCA MAYO - PGIRH asins PE-ANA-190830-NC-RFQ / Es Component 1: Consolidating 2020-10-0 2020-10-1 2020-11-0 2020-12-0 IBRD / 87400 Posterior Individual Limited 35,000.00 0.00 Cancelado 2020-09-28 tudio Geológico del acuífero IWRM at the National Level 3 3 8 8 Caplina PE-ANA-190616-NC-RFQ / Es Component 1: Consolidating 2020-10-0 2020-10-1 2020-11-0 2020-12-0 tudio Geológico de los acuífe IBRD / 87400 Posterior Individual Limited 35,000.00 0.00 Cancelado 2020-09-28 IWRM at the National Level 3 3 8 8 ros de Ica, Villacurí y Lancha s PE-ANA-199722-CS-INDV / P rofesional especialista para l Component 1: Consolidating 2020-11-0 2020-10-2 2020-11-0 2020-10-2 2020-11-1 2020-10-3 2020-11-2 2022-12-3 IBRD / 87400 Posterior Individual Limited 72,500.00 65,708.42 Firmado 2020-10-20 a instrumentación de las est IWRM at the National Level 2 2 5 7 3 1 5 1 ructuras de Medición de agu a en bloques de riego PE-ANA-199657-CS-INDV / E Component 3: General Proje 2020-08-2 2020-10-1 2020-10-0 2020-10-2 2020-11-1 2020-10-3 2020-11-1 2022-12-3 specialista en Administració IBRD / 87400 Posterior Individual Direct 103,000.00 53,604.25 Firmado 2020-10-14 ct Adminstration 8 8 5 3 1 1 1 0 n y Finanzas del Proyecto PG IRH PE-ANA-202833-CS-INDV / T ÉCNICO 01: SENSIBILIZACIÓ Component 1: Consolidating 2021-01-1 2020-11-2 2021-01-1 2020-11-2 2021-01-2 2020-12-0 2021-02-0 2021-03-3 IBRD / 87400 Posterior Individual Limited 20,600.00 15,062.30 Firmado 2020-11-20 N Y CAPACITACIÓN EN SISTE IWRM at the National Level 5 3 5 5 0 1 1 1 MAS HIDRÁULICOS COMUNE S DE LA COSTA PE-ANA-202851-CS-INDV / T ÉCNICO 02: SENSIBILIZACIÓ Component 1: Consolidating 2021-01-1 2020-11-2 2021-01-1 2020-11-2 2021-01-2 2020-12-0 2021-02-0 2021-03-3 IBRD / 87400 Posterior Individual Limited 20,600.00 15,058.18 Firmado 2020-11-20 N Y CAPACITACIÓN EN SISTE IWRM at the National Level 2 3 5 5 0 1 2 1 MAS HIDRÁULICOS COMUNE S DE LA COSTA PE-ANA-202855-CS-INDV / P ROFESIONAL PARA ESTANDA Component 1: Consolidating 2020-10-2 2020-11-1 2020-11-1 2020-11-1 2020-11-2 2020-12-0 2020-11-2 2021-03-0 IBRD / 87400 Posterior Individual Limited 8,200.00 7,828.59 Firmado 2020-11-09 RIZACIÓN E INTEGRACIÓN D IWRM at the National Level 8 4 1 9 4 1 6 1 E EXPEDIENTES TÉCNICOS, R EGIÓN ICA PE-ANA-202860-CS-INDV / T ÉCNICO EN AUTOCAD 01 PA Component 1: Consolidating 2020-10-2 2020-11-1 2020-11-1 2020-11-1 2020-11-2 2020-12-0 2020-11-2 2021-03-0 IBRD / 87400 Posterior Individual Limited 3,900.00 3,704.16 Firmado 2020-11-09 RA ESTANDARIZACIÓN E INT IWRM at the National Level 8 4 1 9 3 1 6 1 EGRACIÓN DE PLANOS, REGI ÓN ICA PE-ANA-202861-CS-INDV / T ÉCNICO EN METRADOS, COS Component 1: Consolidating 2020-10-2 2020-11-1 2020-11-1 2020-11-1 2020-11-2 2020-12-0 2020-11-2 2021-03-0 TOS Y PRESUPUESTOS 01 PA IBRD / 87400 Posterior Individual Limited 3,900.00 3,704.16 Firmado 2020-11-09 IWRM at the National Level 8 4 1 9 3 1 6 1 RA ESTANDARIZACIÓN E INT EGRACIÓN DE EXPEDIENTES TÉCNICOS, REGIÓN ICA PE-ANA-202862-CS-INDV / P ROFESIONAL PARA ESTANDA Component 1: Consolidating 2020-10-2 2020-11-1 2020-11-1 2020-11-1 2020-11-2 2020-12-0 2020-11-2 2021-04-3 RIZACIÓN E INTEGRACIÓN D IBRD / 87400 Posterior Individual Limited 13,600.00 13,054.83 Firmado 2020-11-09 IWRM at the National Level 8 4 1 9 3 1 6 0 E EXPEDIENTES TÉCNICOS, R EGIONES PIURA, LAMBAYEQ UE Y LA LIBERTAD PE-ANA-202863-CS-INDV / T ÉCNICO EN AUTOCAD 01 PA Component 1: Consolidating 2020-10-2 2020-11-1 2020-11-1 2020-11-1 2020-11-2 2020-12-0 2020-11-2 2021-04-3 RA ESTANDARIZACIÓN E INT IBRD / 87400 Posterior Individual Limited 6,500.00 6,180.47 Firmado 2020-11-09 IWRM at the National Level 8 4 1 9 3 1 6 0 EGRACIÓN DE PLANOS, REGI ONES PIURA, LAMBAYEQUE Y LA LIBERTAD PE-ANA-202864-CS-INDV / T ÉCNICO EN METRADOS, COS TOS Y PRESUPUESTOS 01 PA Component 1: Consolidating 2020-10-2 2020-11-1 2020-11-1 2020-11-1 2020-11-2 2020-12-0 2020-11-2 2021-04-3 IBRD / 87400 Posterior Individual Limited 6,500.00 6,173.60 Firmado 2020-11-09 RA ESTANDARIZACIÓN E INT IWRM at the National Level 8 4 1 9 3 1 6 0 EGRACIÓN DE EXPEDIENTES TÉCNICOS, REGIONES PIURA, LAMBAYEQUE Y LA LIBERTA D PE-ANA-202869-CS-INDV / T ÉCNICO 01 PARA SUPERVISI ÓN DEL SUMINISTRO, INSTA Component 1: Consolidating 2021-03-0 2020-11-2 2020-11-2 2020-12-0 2022-07-2 IBRD / 87400 Posterior Individual Limited 40,000.00 0.00 En ejecución 2020-11-20 LACIÓN, PUESTA EN MARCH IWRM at the National Level 3 2 5 1 4 A Y CAPACITACIÓN EN INSTR UMENTACIÓN PARA LA MEDI CIÓN PE-ANA-202870-CS-INDV / T ÉCNICO 02 PARA SUPERVISI ÓN DEL SUMINISTRO, INSTA Component 1: Consolidating 2021-03-0 2020-11-2 2020-11-2 2020-12-0 2022-07-2 IBRD / 87400 Posterior Individual Limited 40,000.00 0.00 En ejecución 2020-11-20 LACIÓN, PUESTA EN MARCH IWRM at the National Level 3 3 6 1 4 A Y CAPACITACIÓN EN INSTR UMENTACIÓN PARA LA MEDI CIÓN PE-ANA-202874-CS-INDV / S UPERVISIÓN PARA CULMINA CIÓN DE ADECUACIÓN DE E Component 1: Consolidating 2021-11-0 2020-11-2 2020-11-2 2020-12-0 2021-02-1 IBRD / 87400 Posterior Individual Limited 9,300.00 0.00 En ejecución 2020-11-20 STRUCTURAS DE MEDICIÓN IWRM at the National Level 8 2 5 1 4 DE AGUA EN SECTORES HID RAULICOS DESDE CHICAMA HASTA SANTA PE-ANA-202875-CS-INDV / S ERVICIO DE SUPERVISIÓN PA RA CULMINACIÓN DE ADECU Component 1: Consolidating 2020-11-2 2020-11-2 2020-12-0 2021-02-1 IBRD / 87400 Posterior Individual Limited 9,300.00 0.00 Cancelado 2020-11-20 ACIÓN DE ESTRUCTURAS DE IWRM at the National Level 2 5 1 4 MEDICIÓN DE AGUA EN SEC TORES HIDRAULICOS DESDE FORTALEZA HASTA LURÍN PE-ANA-202876-CS-INDV / P ROFESIONAL 01 PARA TRAB Component 1: Consolidating 2020-12-1 2020-11-2 2020-12-1 2020-11-2 2021-01-0 2020-12-0 2021-01-1 2022-05-2 AJOS DE HIDROMETRÍA EN E IBRD / 87400 Posterior Individual Limited 30,900.00 19,706.59 Firmado 2020-11-20 IWRM at the National Level 7 2 8 5 2 1 3 5 STRUCTURAS DE MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ Page 12 PE-ANA-202877-CS-INDV / P ROFESIONAL 02 PARA TRAB Component 1: Consolidating 2020-12-1 2020-11-2 2021-01-1 2020-11-2 2021-01-0 2020-12-0 2021-01-1 2022-05-2 AJOS DE HIDROMETRÍA EN E IBRD / 87400 Posterior Individual Limited 30,900.00 19,706.59 Firmado 2020-11-20 IWRM at the National Level 7 3 8 6 2 1 3 5 STRUCTURAS DE MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-202878-CS-INDV / B ACHILLER 01 PARA TRABAJO Component 1: Consolidating 2020-12-1 2020-11-2 2020-12-1 2020-11-2 2021-01-0 2020-12-0 2021-01-1 2022-05-2 S DE HIDROMETRÍA EN ESTR IBRD / 87400 Posterior Individual Limited 20,600.00 13,137.73 Firmado 2020-11-20 IWRM at the National Level 7 2 8 5 5 1 3 5 UCTURAS DE MEDICIÓN DE AGUA, EN LA COSTA DEL PE RÚ PE-ANA-202879-CS-INDV / B ACHILLER 02 PARA TRABAJO Component 1: Consolidating 2020-12-1 2020-11-2 2020-12-1 2020-11-2 2021-01-0 2020-12-0 2021-01-1 2022-05-2 S DE HIDROMETRÍA EN ESTR IBRD / 87400 Posterior Individual Limited 20,600.00 12,553.94 Firmado 2020-11-20 IWRM at the National Level 7 2 8 5 5 1 3 5 UCTURAS DE MEDICIÓN DE AGUA, EN LA COSTA DEL PE RÚ PE-ANA-204399-CS-CDS / DI Component 3: General Proje Selección directa 2020-07-1 2020-11-2 2020-11-1 2020-11-2 2020-11-1 2022-12-3 IBRD / 87400 Posterior Direct 156,000.00 78,870.15 Firmado 2020-11-16 RECTOR EJECUTIVO ct Adminstration de consultores 0 2 0 5 1 0 PE-ANA-202802-CS-INDV / R Component 1: Consolidating Ejecución pendie 2020-12-2 2021-01-1 2021-02-2 2022-08-1 IBRD / 87400 Posterior Individual Limited 81,274.00 0.00 2020-12-22 esponsable Jefe Supervisión IWRM at the National Level nte 7 7 1 5 EHA-SMA PE-ANA-202807-CS-INDV / A Component 1: Consolidating Ejecución pendie 2020-12-2 2021-01-1 2021-02-2 2022-08-1 IBRD / 87400 Posterior Individual Limited 71,302.00 0.00 2020-12-22 sistente Supervisión EHA-SM IWRM at the National Level nte 7 7 1 5 A PE-ANA-202808-CS-INDV / S Component 1: Consolidating 2020-12-1 2020-12-2 2020-12-1 2021-01-1 2020-12-2 2021-02-2 2021-05-0 2022-08-1 IBRD / 87400 Posterior Individual Limited 66,316.00 64,002.99 Firmado 2020-12-22 upervisor 1 - Obras Civiles E IWRM at the National Level 1 7 7 7 8 1 7 5 HA - SMA PE-ANA-202814-CS-INDV / S Component 1: Consolidating 2021-05-0 2020-12-2 2021-06-1 2021-01-1 2021-07-3 2021-02-2 2021-08-0 2022-08-1 IBRD / 87400 Posterior Individual Limited 66,316.00 51,640.48 Firmado 2020-12-22 upervisor 2 - Montaje EHA IWRM at the National Level 7 7 7 7 0 1 2 5 PE-ANA-202810-CS-INDV / S Component 1: Consolidating 2020-12-1 2020-12-2 2020-12-1 2021-01-1 2020-12-3 2021-02-2 2020-12-3 2022-08-1 IBRD / 87400 Posterior Individual Limited 66,316.00 43,029.89 Firmado 2020-12-22 upervisor 2 - Obras Civiles E IWRM at the National Level 1 7 7 7 0 1 0 5 HA -SMA PE-ANA-202811-CS-INDV / S Component 1: Consolidating 2020-12-1 2020-12-2 2020-12-1 2021-01-1 2020-12-3 2021-02-2 2020-12-3 2022-08-1 IBRD / 87400 Posterior Individual Limited 66,316.00 43,029.89 Firmado 2020-12-22 upervisor 3 - Obras Civiles E IWRM at the National Level 1 7 7 7 0 1 0 5 HA - SMA PE-ANA-202813-CS-INDV / S Component 1: Consolidating 2021-05-0 2020-12-2 2021-05-1 2021-01-1 2021-05-3 2021-02-2 2021-05-3 2022-08-1 IBRD / 87400 Posterior Individual Limited 66,316.00 64,355.70 Firmado 2020-12-22 upervisor 1 - Montaje EHA IWRM at the National Level 7 7 3 7 1 1 1 5 PE-ANA-202815-CS-INDV / S Component 1: Consolidating Ejecución pendie 2020-12-2 2021-01-1 2021-02-2 2022-08-1 IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 2020-12-22 upervisor 3 - Montaje SMA IWRM at the National Level nte 7 7 1 5 PE-ANA-202816-CS-INDV / S Component 1: Consolidating Ejecución pendie 2020-12-2 2021-01-1 2021-02-2 2022-08-1 IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 2020-12-22 upervisor 4 - Montaje SMA IWRM at the National Level nte 7 7 1 5 PE-ANA-211979-CS-INDV / E SPECIALISTA DE CALIDAD DE AGUA PARA EL MONITOREO Component 1: Consolidating 2021-10-0 2021-01-2 2021-11-0 2021-01-2 2021-11-1 2021-02-0 2021-11-1 2022-02-0 IBRD / 87400 Posterior Individual Limited 27,000.00 25,259.83 Firmado 2021-01-18 DE LA INSTALACION DE SEN IWRM at the National Level 5 0 8 5 1 1 2 1 SORES DE CALIDAD DE AGU A SUPERFICIAL EN EL AMBIT O DEL PGIRH PE-ANA-212242-CS-INDV / E SPECIALISTA EN CALIDAD DE AGUA PARA LA SUPERVISIÓN Component 1: Consolidating 2021-12-1 2021-01-1 2021-01-2 2021-01-2 2022-01-2 DE LA ELABORACIÓN DE LOS IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 En ejecución 2021-01-15 IWRM at the National Level 7 7 2 9 9 DIAGNÓSTICOS DE LA CALID AD DE LOS RECURSOS HÍDRI COS SUPERFICIALES DEL ÁM BITO DEL PGIRH PE-ANA-212246-CS-INDV / E SPECIALISTA EN CALIDAD DE AGUAPARA LA SUPERVISIÓN DEL REGISTRO DE DATOS D Component 1: Consolidating 2021-01-1 2021-01-2 2021-01-2 2022-01-2 E LAS ACTIVIDADES DE VIGIL IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 Cancelado 2021-01-15 IWRM at the National Level 7 2 9 9 ANCIA DE LA CALIDAD DE LO S RECURSOS HÍDRICOS SUP ERFICIALES DEL PERIODO 20 10 A 2020 EN LA PLATAFOR MA DEL SNIRH/DCERH EN 25 U.H. PE-ANA-212247-CS-INDV / E SPECIALISTA EN CALIDAD DE AGUA PARA LA SUPEVISION DEL REGISTRO DE DATOS D Component 1: Consolidating 2021-01-1 2021-01-2 2021-01-2 2022-01-2 E LAS ACTIVIDADES DE VIGIL IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 Cancelado 2021-01-15 IWRM at the National Level 7 2 9 9 ANCIA DE LA CALIDAD DE LO S RECURSOS HIDRICOS SUP ERFICIALES DEL PERIODO 20 10 A 2020 EM LA PLATAFOR MA DEL SNIRH/DCERH EN 17 U.H PE-ANA-212248-CS-INDV / E SPECIALISTA PARA EL GEOP ROCESAMIENTO DE INFORM ACION PARA LA SUPERVISIO N Y ELABORACION DE DIAGN Component 1: Consolidating 2021-12-1 2021-01-1 2021-01-2 2021-01-2 2022-01-2 IBRD / 87400 Posterior Individual Limited 27,000.00 0.00 En ejecución 2021-01-15 OSTICOS DE LA CALIDAD DE IWRM at the National Level 7 7 2 9 9 LOS RECURSOS HIDRICOS S UPERFICIALES Y REGISTRO D E INFORMACION DE LA PLAT AFORMA DEL SNIRH/DCERH DE LA ANA DEL AMBITO NAC IONAL PE-ANA-212257-CS-INDV / A Component 3: General Proje 2021-02-0 2021-01-2 2021-03-1 2021-01-2 2021-03-3 2021-02-0 2021-03-3 2022-12-3 IBRD / 87400 Posterior Individual Limited 68,000.00 26,623.28 Firmado 2021-01-18 SISTENTE EN ADQUISICIONE ct Adminstration 5 5 6 8 0 2 1 1 S2 PE-ANA-212262-CS-INDV / A Component 3: General Proje 2021-11-1 2021-02-2 2021-11-1 2021-02-2 2021-12-0 2021-02-2 2021-12-1 2022-12-3 IBRD / 87400 Posterior Individual Limited 76,000.00 3,289.04 Firmado 2021-02-13 SESOR LEGAL - PGIRH ct Adminstration 0 0 9 3 9 8 0 1 PE-ANA-212264-CS-INDV / E Component 3: General Proje 2021-11-1 2021-02-2 2021-11-1 2021-02-2 2021-12-0 2021-03-0 2021-12-0 2021-05-0 IBRD / 87400 Posterior Individual Limited 76,500.00 3,289.04 Firmado 2021-02-15 SPECIALISTA EN CONTABILID ct Adminstration 0 2 9 7 2 3 7 8 AD SCI 039 ANA PGIRH / ASISTE Component 3: General Proje 2019-02-1 2019-02-2 2019-02-2 2020-02-2 IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 Cancelado 2019-02-08 NTE DE ADQUISICIONES 2 ct Adminstration 5 0 8 8 SCI 068 2018 ANA PGIRH B Component 3: General Proje 2019-04-1 2019-04-2 2019-04-3 2020-04-2 IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 Cancelado 2019-04-05 M / ASESOR LEGAL ct Adminstration 5 0 0 9 PE-ANA-214176-CS-INDV / E Component 3: General Proje 2021-02-1 2021-02-2 2021-02-2 2021-02-2 2021-02-2 2021-03-0 2021-03-0 2022-12-3 SPECIALISTA EN PLANIFICACI IBRD / 87400 Posterior Individual Limited 92,000.00 40,594.30 Firmado 2021-02-15 ct Adminstration 8 2 2 7 6 3 5 0 ON, PRESUPUESTO Y EVALU ACION SCI 032 ANA PGIRH / ESPECI Component 3: General Proje 2019-04-1 2019-04-2 2019-04-3 2020-04-2 ALISTA EN PLANIFICACION, P IBRD / 87400 Posterior Individual Limited 48,000.00 0.00 Cancelado 2019-04-05 ct Adminstration 5 0 0 9 RESUPUESTO Y EVALUACIÓN PE-ANA-122163-CS-INDV / A Component 3: General Proje Ejecución pendie 2021-02-2 2021-02-2 2021-03-0 2022-12-3 IBRD / 87400 Posterior Individual Limited 58,000.00 0.00 2021-02-15 SISTENTE DE CONTABILIDAD ct Adminstration nte 2 7 3 0 SCI 041 ANA PGIRH / ESPECI Component 3: General Proje 2018-06-0 2018-06-1 2018-06-1 2022-11-1 IBRD / 87400 Posterior Individual Limited 194,076.00 0.00 Cancelado 2018-05-28 ALISTA EN CONTABILIDAD ct Adminstration 4 1 3 9 PE-ANA-122162-CS-INDV / A Component 3: General Proje 2021-02-2 2021-02-2 2021-03-1 2021-02-2 2021-03-2 2021-03-0 2021-03-3 2022-12-3 SISTENTE DE MONITOREO Y IBRD / 87400 Posterior Individual Limited 58,000.00 22,992.83 Firmado 2021-02-15 ct Adminstration 6 2 1 7 6 3 1 0 EVALUACIÓN PE-ANA-216395-CS-INDV / E Component 3: General Proje 2021-11-1 2021-02-1 2021-02-1 2021-02-2 2022-01-2 IBRD / 87400 Posterior Individual Limited 33,600.00 0.00 Bajo Revision 2021-02-08 specialista Financiero del Pr ct Adminstration 9 3 8 3 4 oyecto PE-ANA-221587-CS-INDV / S UPERVISIÓN PARA LA CULMI NACIÓN DE LA ADECUACIÓN Component 1: Consolidating 2021-05-1 2021-03-2 2021-06-0 2021-03-2 2021-06-1 2021-04-0 2021-07-0 2021-07-1 IBRD / 87400 Posterior Individual Limited 8,000.00 8,876.20 Firmado 2021-03-15 DE ESTRUCTURAS DE MEDIC IWRM at the National Level 8 0 3 5 4 9 2 0 IÓN DE AGUA EN LOS SECTO RES HIDRÁULICOS DESDE T UMBES HASTA ALTO PIURA PE-ANA-221592-CS-INDV / S UPERVISIÓN PARA LA CULMI NACIÓN DE LA ADECUACIÓN Component 1: Consolidating 2021-03-1 2021-03-2 2021-04-1 2021-03-2 2021-04-2 2021-04-0 2021-05-1 2021-07-1 IBRD / 87400 Posterior Individual Limited 8,750.00 10,020.77 Firmado 2021-03-15 DE ESTRUCTURAS DE MEDIC IWRM at the National Level 1 0 2 5 7 9 1 8 IÓN DE AGUA EN LOS SECTO RES HIDRÁULICOS DESDE O LMOS HASTA JEQUETEPEQUE PE-ANA-234084-CS-INDV / P ROFESIONAL 01 PARA EL SE Component 1: Consolidating 2021-06-1 2021-06-0 2021-06-0 2021-06-0 2021-06-2 2021-06-1 2021-07-0 2022-06-0 GUIMIENTO Y CONTROL DE L IBRD / 87400 Posterior Individual Limited 36,000.00 34,732.27 Firmado 2021-05-28 IWRM at the National Level 1 2 9 3 4 0 2 5 A EJECUCION DE OBRAS DE ESTRUCTURAS DE MEDICION DE AGUA PE-ANA-234087-CS-INDV / P ROFESIONAL 02 PARA EL SE Component 1: Consolidating 2021-06-0 2021-06-0 2021-06-0 2021-06-0 2021-06-2 2021-06-0 2021-07-0 2022-06-0 GUIMIENTO Y CONTROL DE L IBRD / 87400 Posterior Individual Limited 36,000.00 34,732.27 Firmado 2021-05-28 IWRM at the National Level 4 2 9 3 4 9 2 4 A EJECUCION DE OBRAS DE ESTRUCTURAS DE MEDICION DE AGUA PE-ANA-234089-CS-INDV / T ECNICO EN AUTOCAD, METR ADOS, COSTOS Y PRESUPUE Component 1: Consolidating 2021-06-0 2021-06-0 2021-06-0 2021-06-0 2021-06-2 2021-06-1 2021-07-0 2022-01-0 IBRD / 87400 Posterior Individual Limited 15,000.00 14,208.66 Firmado 2021-05-28 STO PARA EL SEGUIMIENTO IWRM at the National Level 4 2 9 3 4 0 2 6 Y CONTROL DE LA EJECUCIO N DE OBRAS DE ESTRUCTUR AS DE MEDICION DE AGUA PE-ANA-165885-CS-INDV / D ESARROLLO E IMPLEMENTAC Component 1: Consolidating Ejecución pendie 2021-10-0 2021-10-2 2021-12-0 2022-03-0 IÓN DE CURSO VIRTUAL: ME IBRD / 87400 Posterior Individual Limited 9,851.00 0.00 2021-10-01 IWRM at the National Level nte 8 9 3 5 DICIÓN DEL AGUA EN SISTE MAS HIDRÁULICOS COMUNE S PE-ANA-235103-CS-INDV / P ROFESIONAL PARA LA ELAB Component 1: Consolidating 2022-08-2 2021-07-0 2021-07-1 2021-07-2 2021-09-2 ORACION DE 20 EXPEDIENTE IBRD / 87400 Posterior Individual Limited 22,000.00 0.00 En ejecución 2021-07-01 IWRM at the National Level 4 6 6 8 6 S TECNICOS EN LOS SECTOR ES DE MEDIO Y BAJO PIURA Y SECHURA PE-ANA-235582-CS-INDV / T ECNICO 01 PAAR SUPERVISI ON DEL SUMINISTRO, INSTA Component 1: Consolidating 2021-07-0 2021-07-1 2021-07-2 2022-05-2 IBRD / 87400 Posterior Individual Limited 17,000.00 0.00 Cancelado 2021-07-01 LACION , PUESTA EN MARCH IWRM at the National Level 6 3 6 2 A Y CAPACITACION DE INSTR UMENTACION PARA LA MEDI CION PE-ANA-235586-CS-INDV / T ECNICO 02 PARA SUPERVISI ON DEL SUMINISTRO, INSTA Component 1: Consolidating 2021-07-0 2021-07-1 2021-07-2 2022-05-2 IBRD / 87400 Posterior Individual Limited 17,000.00 0.00 Cancelado 2021-07-01 LACION, PUESTA EN MARCH IWRM at the National Level 6 3 6 2 A Y CAPACITACION DE INSTR UMENTACION PARA LA MEDI CION PE-ANA-248241-CS-INDV / S UPERVISION DE CAMPO DE L A IMPLEMENTACION DE EJEM PLOS PILOTO DE MEDICION Component 1: Consolidating Ejecución pendie 2021-09-0 2021-09-1 2021-09-1 2021-11-1 IBRD / 87400 Posterior Individual Limited 10,000.00 0.00 2021-08-30 DE CONSUMO DE AGUA EN P IWRM at the National Level nte 4 4 8 7 OZOS DE PRODUCCION A TR AVES DE FLUJOMETROS ELE CTROMAGNETICOS Y DE TRU BINA EN LOS AMBITOS DE IC A Y TACNA PE-ANA-248244-CS-INDV / S UPERVISION DE CAMPO DE L Component 1: Consolidating Ejecución pendie 2021-09-0 2021-09-0 2021-09-1 2021-10-1 A EJECUCION DE PERFILES G IBRD / 87400 Posterior Individual Limited 3,500.00 0.00 2021-08-30 IWRM at the National Level nte 1 8 2 2 AMMA RAY, CE Y T° EN PIEZ OMETROS CULMINADOS ICA PE-ANA-248245-CS-INDV / S UPERVISION DE CAMPO DE L A CONSTRUCCION DE ESTRU Component 1: Consolidating Ejecución pendie 2021-09-0 2021-09-0 2021-09-1 2021-11-1 IBRD / 87400 Posterior Individual Limited 9,000.00 0.00 2021-08-30 CTURAS DE PROTECCION Y IWRM at the National Level nte 1 8 2 1 CASTEAS EN PIEZOMETROS UBICADOS EB EL ACUIFERO CAPLINA E ICA Page 13 PE-ANA-248246-CS-INDV / S UPERVISION DE CAMPO DE L Component 1: Consolidating Ejecución pendie 2021-09-0 2021-09-0 2021-09-1 2021-11-1 IBRD / 87400 Posterior Individual Limited 5,000.00 0.00 2021-08-30 A NIVELACION DE 99 PIEZO IWRM at the National Level nte 1 8 2 1 METROS UBICADOS EN EL A MBITO DE ICA PE-ANA-268538-CS-INDV / C Component 2: Improving W 2021-12-1 2021-12-2 2021-12-2 2021-12-2 2021-12-2 2021-12-3 2021-12-3 2022-12-3 IBRD / 87400 Posterior Individual Limited 34,000.00 36,081.13 Firmado 2021-12-20 oordinador Técnico de Cuen RM in Selected Pilot River B 6 7 0 8 9 0 1 0 ca Mantaro asins PE-ANA-270069-CS-INDV / A sesoramiento Técnico – Pane l de Expertos: Seguridad de l Component 1: Consolidating 2022-02-1 2022-02-0 2022-02-2 2022-02-2 2022-04-0 2022-10-0 IBRD / 87400 Posterior Individual Direct 11,200.00 0.00 En ejecución 2022-01-28 a presa Poechos: Propuestas IWRM at the National Level 8 7 4 8 4 1 para el diseño de la cortina de inyecciones en la presa d e Poechos PE-ANA-270321-CS-INDV / C Component 1: Consolidating 2022-02-0 2022-02-0 2022-02-2 2022-02-0 2022-02-2 2022-02-1 2022-02-2 2022-02-2 onsultor internacional para e IBRD / 87400 Posterior Individual Direct 8,500.00 7,314.62 Firmado 2022-01-28 IWRM at the National Level 8 7 1 9 1 2 3 6 ntrenamiento en recarga de acuíferos PE-ANA-272250-CS-INDV / S UPERVISOR 4 - ESPECIALIST A EN SUPERVISIÓN OBRAS CI Component 1: Consolidating 2022-02-1 2022-01-1 2022-01-2 2022-01-3 2022-12-2 IBRD / 87400 Posterior Individual Limited 22,000.00 0.00 En ejecución 2022-01-14 VILES DE ESTACIONES HIDR IWRM at the National Level 6 9 6 1 7 OLÓGICAS AUTOMÁTICAS Y DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-272253-CS-INDV / S UPERVISOR 5 - ESPECIALIST A EN SUPERVISIÓN OBRAS CI Component 1: Consolidating 2022-02-1 2022-01-2 2022-02-0 2022-02-0 2023-01-0 IBRD / 87400 Posterior Individual Limited 22,000.00 0.00 En ejecución 2022-01-20 VILES DE ESTACIONES HIDR IWRM at the National Level 6 5 1 6 2 OLÓGICAS AUTOMÁTICAS Y DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-272257-CS-INDV / S UPERVISOR 6 - ESPECIALIST A EN SUPERVISIÓN OBRAS CI Component 1: Consolidating 2022-01-1 2022-01-2 2022-01-3 2022-12-2 IBRD / 87400 Posterior Individual Limited 22,000.00 0.00 En ejecución 2022-01-14 VILES DE ESTACIONES HIDR IWRM at the National Level 9 6 1 7 OLÓGICAS AUTOMÁTICAS Y DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-272258-CS-INDV / S UPERVISOR 7 - ESPECIALIST A EN SUPERVISIÓN OBRAS CI Component 1: Consolidating 2022-01-1 2022-01-2 2022-01-3 2022-12-2 IBRD / 87400 Posterior Individual Limited 22,000.00 0.00 En ejecución 2022-01-14 VILES DE ESTACIONES HIDR IWRM at the National Level 9 6 1 7 OLÓGICAS AUTOMÁTICAS Y DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-272260-CS-INDV / S Component 1: Consolidating Ejecución pendie 2022-01-1 2022-01-2 2022-01-3 2022-04-0 UPERVISOR 1 - INSTRUMENT IBRD / 87400 Posterior Individual Limited 6,500.00 0.00 2022-01-14 IWRM at the National Level nte 9 6 1 1 ACIÓN DE PRESAS PE-ANA-272261-CS-INDV / S Component 1: Consolidating Ejecución pendie 2022-01-1 2022-01-2 2022-01-3 2022-04-0 UPERVISOR 2 - INSTRUMENT IBRD / 87400 Posterior Individual Limited 4,500.00 0.00 2022-01-14 IWRM at the National Level nte 9 6 1 1 ACIÓN DE PRESAS PE-ANA-272262-CS-INDV / S Component 1: Consolidating Ejecución pendie 2022-01-1 2022-01-2 2022-01-3 2022-04-0 UPERVISOR 3 - INSTRUMENT IBRD / 87400 Posterior Individual Limited 3,500.00 0.00 2022-01-14 IWRM at the National Level nte 9 6 1 1 ACIÓN DE PRESAS PE-ANA-272267-CS-INDV / P Component 1: Consolidating 2022-03-2 2022-01-2 2022-02-1 2022-03-2 2022-12-3 ERSONAL DE APOYO TECNIC IBRD / 87400 Posterior Individual Limited 12,000.00 0.00 En ejecución 2022-01-24 IWRM at the National Level 8 9 9 6 0 O MONITOREO DE AGUAS SU BTERRANEAS PE-ANA-272268-CS-INDV / E SPECIALISTA EN ESTUDIOS S OCIALES PARA EL FORTALEC Component 1: Consolidating 2022-02-1 2022-02-0 2022-02-2 2022-04-0 2022-07-0 IBRD / 87400 Posterior Individual Limited 7,500.00 0.00 En ejecución 2022-01-31 IMIENTO DE COMITÉS DE GE IWRM at the National Level 7 5 6 2 1 STIÓN Y LA IMPLEMENTACIÓ N DE UN PLAN DE ACCIÓN E N EL ACUÍFERO CAPLINA-TA CNA PE-ANA-272269-CS-INDV / P ROFESIONAL PARA EL FORTA Component 1: Consolidating 2022-02-1 2022-02-0 2022-02-2 2022-03-3 2022-06-1 LECIMIENTO DE COMITES DE IBRD / 87400 Posterior Individual Limited 6,000.00 0.00 En ejecución 2022-01-28 IWRM at the National Level 7 2 3 0 3 GESTION E IMPLEMENTACIO N DE PLAN DE ACCION TACN A N° 2 PE-ANA-272271-CS-INDV / P ROFESIONAL PARA FORTALE Component 1: Consolidating 2022-02-1 2022-01-2 2022-02-1 2022-03-2 2022-06-0 CIMIENTO DE COMITES DE IBRD / 87400 Posterior Individual Limited 6,000.00 0.00 En ejecución 2022-01-24 IWRM at the National Level 7 9 9 6 9 GESTION E IMPLEMENTACIO N DE PLAN DE ACCION ICA N °2 PE-ANA-202817-CS-INDV / C Component 1: Consolidating 2022-02-1 2022-02-0 2022-02-2 2022-04-0 2022-12-3 IBRD / 87400 Posterior Individual Limited 22,500.00 0.00 En ejecución 2022-01-31 oordinador Administrativo E IWRM at the National Level 6 5 6 2 1 HA - SMA PE-ANA-190831-NC-RFQ / Es Component 1: Consolidating 2020-10-0 2020-10-1 2020-11-0 2020-12-0 tudio de prospección geofísi IBRD / 87400 Posterior Individual Limited 13,000.00 0.00 Cancelado 2020-09-28 IWRM at the National Level 3 3 8 8 ca reubicación piezómetros PE-ANA-248243-CS-INDV / S UPERVISION DE CAMPO DE L Component 1: Consolidating 2021-09-0 2021-09-0 2021-09-1 2021-10-1 A EJECUCION DE SIETE PRUE IBRD / 87400 Posterior Individual Limited 4,000.00 0.00 Cancelado 2021-08-30 IWRM at the National Level 1 3 2 2 BAS DE BOMBEO EN PIEZOM ETROS UBICADOS EN EL AC UIFERO CAPLINA PE-ANA-248242-CS-INDV / S UPERVISION DE CAMPO PAR Component 1: Consolidating Ejecución pendie 2022-03-1 2022-03-1 2022-03-2 2022-06-1 A LA EJECUCION DE ADPATA IBRD / 87400 Posterior Individual Direct 9,000.00 0.00 2022-03-01 IWRM at the National Level nte 0 2 1 9 CIONES DE ARBOLES DE DES CARGA EN POZOS UBICADO S EN EL AMBITO DE TACNA PE-ANA-278962-CS-INDV / P ROFESIONAL LEGAL PARA EL Component 1: Consolidating 2022-02-1 2022-02-2 2022-03-0 2022-03-2 2022-06-0 FORTALECIMIENTO DE COMI IBRD / 87400 Posterior Individual Limited 6,000.00 0.00 En ejecución 2022-02-21 IWRM at the National Level 7 6 8 0 3 TÉS DE GESTIÓN E IMPLEME NTACIÓN DE PLAN DE ACCIÓ N TACNA N°1 PE-ANA-272270-CS-INDV / P ROFESIONAL PARA FORTALE Component 1: Consolidating 2022-02-1 2022-01-2 2022-02-1 2022-03-2 2022-06-0 CIMIENTO DE COMITES DE IBRD / 87400 Posterior Individual Limited 6,000.00 0.00 Cancelado 2022-01-24 IWRM at the National Level 1 9 9 6 9 GESTION E IMPLEMENTACIO N DE PLAN DE ACCION ICA N °1 PE-ANA-270062-CS-INDV / C apacitación en gestión de se Component 1: Consolidating 2022-02-2 2022-03-1 2022-02-2 2022-03-1 2022-03-2 2022-04-2 IBRD / 87400 Posterior Individual Direct 11,650.00 0.00 En ejecución 2022-03-04 guridad de presas a operado IWRM at the National Level 4 4 4 9 9 0 res de presas-Módulo I PE-ANA-283040-CS-INDV / E Component 2: Improving W 2022-03-1 2022-03-2 2022-03-3 2022-04-0 2022-12-3 SPECIALISTA SOCIAL AMBIEN IBRD / 87400 RM in Selected Pilot River B Posterior Individual Limited 24,491.00 0.00 En ejecución 2022-03-15 1 2 0 2 0 TAL CUENCA MANTARO asins Page 14