PROCUREMENT PLAN (Mandatory Requirements) Emergency Multi-Sector Rohingya Crisis Response Project (EMRCRP) Project Implementation Agencies: Ministry of Disaster Management and Relief (MoDMR) Department of Public Health Engineering (DPHE) Local Government Engineering Department (LGED) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Lottery in award of contracts shall not be allowed; 2) Bidders’ qualification[s]/experience requirement[s] shall be mandatory; 3) Bids shall not be rejected based on percentage above or below the estimated cost; 4) Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; 5) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 6) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 7) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Emergency Multi-Sector Rohingya Crisis Response Project PLAN General Information Country: Bangladesh 2018-12-11 Bank’s Approval Date of the Original Procurement Plan: 2022-11-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167762 GPN Date: Project Name: Emergency Multi-Sector Rohingya Crisis Response Project Loan / Credit No: IDA / D4190, / , IDA / D5900 Department of Public Health Engineering Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Strengthening EMRCRP/WD-02 / Constructi Delivery of Basic Services, R Single Stage - One E 2,174,388.9 2020-04-2 on of Mini Piped Water Suppl IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,392,344.00 Signed 2019-01-01 2019-05-14 2019-01-06 2019-02-17 2019-06-16 2019-03-19 2019-06-27 2019-04-23 2019-06-30 nvelope 5 2 y Schemes including O&M gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-6 / Construction Delivery of Basic Services, R Single Stage - One E 1,650,984.6 2020-06-2 of community latrine includin IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,674,641.00 Signed 2019-03-01 2019-05-06 2019-03-06 2019-04-17 2019-06-10 2019-05-17 2019-07-25 2019-06-21 2019-08-25 nvelope 7 0 gO&M gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-03 / Constructio Delivery of Basic Services, R Single Stage - One E 2,360,284.2 2020-06-2 n of Mini piped water supply IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,392,344.00 Signed 2019-03-03 2019-04-02 2019-03-08 2019-04-19 2019-05-06 2019-05-19 2019-05-30 2019-06-23 2019-06-16 nvelope 5 2 schemes including O&M gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-04 / Constructio Delivery of Basic Services, R Single Stage - One E 1,748,868.5 2020-01-0 n of Mini piped water supply IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,913,876.00 Signed 2019-03-17 2019-04-04 2019-03-22 2019-05-03 2019-05-06 2019-06-02 2019-06-11 2019-07-07 2019-06-23 nvelope 7 3 schemes including O&M gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-12 / Constructio Delivery of Basic Services, R n of Camp office, renovation Single Stage - One E 2020-02-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 382,775.00 356,522.57 Signed 2019-04-21 2019-04-21 2019-04-26 2019-06-07 2019-05-21 2019-07-07 2019-06-30 2019-08-11 2019-07-16 and extension of RPO and tru nvelope 7 gency Response, and Gende ck shade r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/WD-13 / Renovation Single Stage - One E 2020-03-3 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 62,201.00 51,161.73 Signed 2019-06-13 2019-03-20 2019-06-18 2019-07-30 2019-04-07 2019-08-29 2019-05-09 2019-10-03 2019-05-20 of PMU nvelope 1 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-10 / Installation Delivery of Basic Services, R Single Stage - One E 2,122,345.9 2020-06-1 of Household toilet including IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,150,537.63 Signed 2019-09-22 2019-05-05 2019-09-29 2019-10-24 2019-06-10 2019-11-08 2019-08-19 2019-12-13 2019-09-11 nvelope 9 0 renovation of existing toilets gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/WD-11 / Installation Single Stage - One E 2020-04-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 430,107.52 381,954.65 Signed 2019-10-03 2020-02-02 2019-10-10 2019-11-04 2020-02-18 2019-11-19 2020-04-14 2019-12-24 2020-05-11 of Household Bio-fill toilet nvelope 2 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/WD-07A / Installation Single Stage - One E 2020-04-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 358,422.94 330,500.24 Signed 2019-09-25 2019-09-11 2019-10-02 2019-10-27 2019-10-03 2019-11-11 2019-11-03 2019-12-16 2019-11-26 of water options (DTW) nvelope 4 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/WD-7B / Installation Single Stage - One E 2020-04-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 358,422.94 319,623.58 Signed 2019-09-30 2019-09-01 2019-10-07 2019-11-01 2019-10-06 2019-11-16 2019-10-28 2019-12-21 2019-11-26 of water options (DTW) nvelope 9 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/WD-13.1 / Renovatio Single Stage - One E 2020-09-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 57,347.67 44,561.14 Signed 2019-11-26 2019-10-31 2019-11-27 2020-01-08 2019-11-24 2020-02-07 2020-01-29 2020-03-13 2020-02-27 n & extension of RPO nvelope 9 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMRCRP/WD-01 / Test Tube- Single Stage - One E 2019-09-1 / esilient Infrastructure, Emer Post Request for Bids Open - National 66,986.00 0.00 Canceled 2019-01-30 2019-02-04 2019-03-18 2019-04-17 2019-05-22 well nvelope 9 gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/WD-14 / Suppl Delivery of Basic Services, R y and Installation with OM of Single Stage - One E 2020-11-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 358,250.00 323,682.68 Signed 2020-06-10 2020-08-25 2020-06-13 2021-02-16 2020-06-27 2020-09-06 2020-07-12 2020-10-20 2020-08-09 2020-11-04 Hand Washing Basin for COVI nvelope 7 gency Response, and Gende D-19 r-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/WD-5 / Constru Delivery of Basic Services, R ction of latrine with composti Single Stage - One E 2021-06-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 835,000.00 777,561.30 Signed 2020-06-07 2020-06-04 2020-06-10 2020-07-01 2020-07-05 2020-07-31 2020-07-05 2020-09-04 2020-09-03 ng bio-gas plant including O nvelope 1 gency Response, and Gende &M r-Based Viol ence Prevention Component 1: Strengthening EMCRP/WD-08 / Supply, Inst Delivery of Basic Services, R allation and Construction wit Single Stage - One E 1,406,841.8 2023-02-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,438,240.00 Signed 2020-11-10 2021-01-25 2020-11-13 2020-12-04 2021-02-23 2021-01-03 2021-03-24 2021-02-07 2021-04-27 h O & M of solid waste mana nvelope 0 7 gency Response, and Gende gement system. r-Based Viol ence Prevention EMCRP/AF/WD-24 / Installati Component 1: Strengthening on of Water Options includin Delivery of Basic Services, R Single Stage - One E 1,988,937.9 2023-01-0 g O & M for Host Community IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 2,151,105.00 Signed 2021-03-30 2021-05-23 2021-04-02 2021-05-02 2021-06-13 2021-06-01 2021-07-26 2021-07-06 2021-09-05 nvelope 6 7 (4"-2" dia with submersible p gency Response, and Gende ump) r-Based Viol ence Prevention Page 1 EMCRP/AF/WD-26 / Installati Component 1: Strengthening on of Water Options includin Delivery of Basic Services, R Single Stage - One E 1,420,104.8 2023-01-0 g O & M for Host Community IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,473,360.00 Signed 2021-03-30 2021-03-14 2021-04-02 2021-05-02 2021-04-11 2021-06-01 2021-07-08 2021-07-06 2021-07-14 nvelope 0 7 (4"-2" dia with submersible p gency Response, and Gende ump) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/WD-30 / Installati Delivery of Basic Services, R on of Household toilet for Ho Single Stage - One E 1,454,805.7 2022-12-1 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,555,870.00 Signed 2021-03-15 2021-03-25 2021-03-18 2021-04-08 2021-05-19 2021-05-08 2021-09-16 2021-06-12 2021-10-14 st Community ( Chakoria Upa nvelope 7 4 gency Response, and Gende zila, Cox's Bazar ) r-Based Viol ence Prevention EMCRP/AF/WD-31 / Installati Component 1: Strengthening on of Household Toilet for Ho Delivery of Basic Services, R Single Stage - One E 1,661,017.0 2022-12-2 st Community ( Cox's Bazar S IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,763,320.00 Signed 2021-03-14 2020-03-30 2021-03-17 2021-04-16 2020-05-19 2021-05-16 2021-07-27 2021-06-20 2021-09-02 nvelope 3 2 adar and Moheshkhali upazil gency Response, and Gende a) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/WD-33 / Installati Delivery of Basic Services, R on of Household Toilet for Ho Single Stage - One E 1,166,335.1 2023-01-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,201,745.00 Signed 2021-03-30 2021-04-01 2021-04-02 2021-05-02 2021-05-19 2021-06-01 2021-05-27 2021-07-06 2021-06-22 st Community (Kutubdia and nvelope 6 7 gency Response, and Gende Pekua upazila, Cox's Bazar ) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/WD-32 / Installati Delivery of Basic Services, R on of Household Toilet for Ho Single Stage - One E 1,639,371.9 2023-01-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1,694,012.00 Signed 2021-03-30 2021-04-01 2021-04-02 2021-05-02 2020-05-19 2021-06-01 2021-09-02 2021-07-06 2021-10-03 st Community (Ramu, Ukhia nvelope 6 7 gency Response, and Gende and Teknaf upazila) r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/WD-19 / Construc Delivery of Basic Services, R tion of Mini piped water suppl Single Stage - One E 1,898,626.7 2022-08-2 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 2,310,230.00 Signed 2021-05-25 2021-12-01 2021-05-28 2021-06-18 2022-01-04 2021-07-18 2022-03-13 2021-08-22 2022-04-04 y schemes including O & M f nvelope 6 2 gency Response, and Gende or Host Community. r-Based Viol ence Prevention Component 1: Strengthening National Procure EMCRP/WD/19 / Construction Delivery of Basic Services, R ment Document - of Mini Piped Water Supply S Single Stage - One E 2022-11-1 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,310,230.00 0.00 Canceled 2021-07-01 2021-07-06 2021-08-05 2021-10-04 2021-11-15 chemes including O&M for H nvelope 5 gency Response, and Gende ss (Non Bank-SPD ost Community r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/WD-23 / Installation Delivery of Basic Services, R ment Document - of Water Options including O Single Stage - One E 2022-11-1 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 530,410.00 0.00 Canceled 2021-07-05 2021-07-10 2021-08-09 2021-10-08 2021-11-19 &M for DRP ( 3"-1.5" dia with nvelope 9 gency Response, and Gende ss (Non Bank-SPD deep set pump) r-Based Viol ence Prevention ) EMCRP/WD-25 / Installation Component 1: Strengthening National Procure of Water Options Including O Delivery of Basic Services, R ment Document - Single Stage - One E Under Imple 2022-11-2 &M for Host Community ( 4"- IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,826,970.00 0.00 2021-07-11 2021-10-12 2021-07-16 2021-08-15 2021-10-14 2021-11-25 nvelope mentation 5 2" dia with submersible pum gency Response, and Gende ss (Non Bank-SPD p) r-Based Viol ence Prevention ) EMCRP/WD-25A / Installation Component 1: Strengthening National Procure of Water Options including O Delivery of Basic Services, R ment Document - Single Stage - One E 1,214,681.6 2022-12-0 &M for host community ( 4"- IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 1,090,285.00 Signed 2021-07-25 2021-10-05 2021-07-30 2021-08-29 2021-11-10 2021-10-28 2022-01-05 2021-12-09 2022-03-01 nvelope 9 9 2" dia with submersible pum gency Response, and Gende ss (Non Bank-SPD p) r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/WD-09 / Supply, Inst Delivery of Basic Services, R ment Document - allation and Construction wit Single Stage - One E Under Imple 2022-12-0 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,129,600.00 0.00 2021-09-12 2021-06-01 2021-09-15 2021-10-06 2021-07-04 2021-10-31 2021-10-25 2021-12-05 h O&M of fecal sludge manag nvelope mentation 5 gency Response, and Gende ss (Non Bank-SPD ement system r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-20 / Construc Delivery of Basic Services, R ment Document - tion of Mini piped water suppl Single Stage - One E 1,896,357.6 2023-06-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,310,230.00 Signed 2021-09-20 2021-12-01 2021-09-23 2021-10-14 2022-01-04 2021-11-13 2022-03-20 2021-12-18 2022-04-06 y schemes including O&M for nvelope 4 6 gency Response, and Gende ss (Non Bank-SPD Host Community r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-21 / Construc Delivery of Basic Services, R ment Document - tion of Mini piped water suppl Single Stage - One E 1,939,756.8 2023-06-1 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,310,230.00 Signed 2021-09-23 2021-12-01 2021-09-26 2021-10-17 2022-01-04 2021-11-16 2022-02-08 2021-12-21 2022-03-06 y schemes including O&M for nvelope 6 9 gency Response, and Gende ss (Non Bank-SPD Host Community r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-22 / Construc Delivery of Basic Services, R ment Document - tion of Mini piped water suppl Single Stage - One E 1,624,657.9 2023-06-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,021,452.14 Signed 2021-09-26 2021-12-01 2021-09-29 2021-10-20 2022-01-11 2021-11-19 2022-02-08 2021-12-24 2022-03-06 y schemes including O&M for nvelope 6 2 gency Response, and Gende ss (Non Bank-SPD Host Community r-Based Viol ence Prevention ) EMCRP/AF/WD-16 / Reconstr Component 1: Strengthening National Procure uction of the mini pipe water Delivery of Basic Services, R ment Document - supply system, water option Single Stage - One E Under Imple 2022-10-1 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 193,300.00 0.00 2022-01-31 2022-04-06 2022-02-05 2022-03-05 2022-04-20 2022-03-10 2022-05-10 2022-04-14 and toilets damaged by fire a nvelope mentation 1 gency Response, and Gende ss (Non Bank-SPD nd landslides under the budg r-Based Viol ence Prevention ) et of Miscellaneous for Imme diate Support. Component 1: Strengthening National Procure EMCRP/AF/WD-44 / Construc Delivery of Basic Services, R ment Document - Single Stage - One E Under Imple 2024-05-2 tion of WASH training facility IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,003,770.00 0.00 2022-02-01 2022-02-06 2022-02-06 2022-03-06 2022-03-08 2022-04-25 2022-04-07 2022-05-30 nvelope mentation 9 center at Cox's bazar gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-40 / Extensio Delivery of Basic Services, R ment Document - n and improvement of truck Single Stage - One E Pending Imp 2023-05-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 538,660.00 0.00 2022-01-19 2022-01-25 2022-02-24 2022-04-15 2022-05-20 shed, camp office and DPHE f nvelope lementation 0 gency Response, and Gende ss (Non Bank-SPD ield level offices r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-23 / Installati Delivery of Basic Services, R ment Document - Single Stage - One E Under Imple 2024-06-1 on of Water Options Includin IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 530,410.00 0.00 2022-04-25 2022-04-06 2022-04-28 2022-05-28 2022-04-21 2022-07-27 2022-08-31 nvelope mentation 5 g O & M for DRP gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/WD-35 / Installation Delivery of Basic Services, R ment Document - Single Stage - One E Under Imple 2023-06-2 of Household Biofill Toilet incl IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 766,150.00 0.00 2022-02-13 2022-07-17 2022-02-18 2022-03-20 2022-08-01 2022-05-19 2022-09-20 2022-06-23 nvelope mentation 3 uding O&M ( Host ) gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Page 2 Component 1: Strengthening National Procure EMCRP/AF/WO&M/07 / Opera Delivery of Basic Services, R ment Document - tion and Maintenance of Wat Single Stage - One E Pending Imp 2024-06-2 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 412,540.00 0.00 2022-09-29 2022-10-02 2022-10-23 2022-12-07 2023-01-04 er Supply & Sanitation Activit nvelope lementation 7 gency Response, and Gende ss (Non Bank-SPD ies (Piped Water) r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WO&M/11 / Opera Delivery of Basic Services, R ment Document - tion and Maintenance of Wat Single Stage - One E Pending Imp 2024-06-3 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 294,675.00 0.00 2022-10-05 2022-10-08 2022-10-29 2022-12-13 2023-01-10 er Sanitation and Hygiene ac nvelope lementation 0 gency Response, and Gende ss (Non Bank-SPD tivities (Non Piped) r-Based Viol ence Prevention ) Component 1: Strengthening National Procure Delivery of Basic Services, R ment Document - EMCRP/WD-001 / Test Tube- Single Stage - One E Pending Imp 2023-07-3 IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 66,000.00 0.00 2022-11-08 2022-11-13 2022-12-04 2023-01-03 2023-01-31 well nvelope lementation 0 gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-18 / Construc Delivery of Basic Services, R ment Document - tion of Mini Pipe Water Suppl Single Stage - One E Pending Imp 2024-03-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,021,450.00 0.00 2022-11-15 2022-11-20 2022-12-20 2023-02-03 2023-03-03 y Scheme including O & M fo nvelope lementation 2 gency Response, and Gende ss (Non Bank-SPD r DRP r-Based Viol ence Prevention ) EMCRP/AF/WD-41 / Extensio Component 1: Strengthening National Procure n & improvement of Truck Sh Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2024-03-1 ade at DPHE Teknaf, Mohesh IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 260,490.00 0.00 2022-11-20 2022-11-25 2022-12-25 2023-02-13 2023-03-13 nvelope lementation 2 khali Upazila and constructio gency Response, and Gende ss (Non Bank-SPD n of Camp office at DRP r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-27 / Installati Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-08-2 on of Rain Water Harvesting IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 353,607.00 0.00 2022-11-20 2022-11-25 2022-12-25 2023-01-24 2023-02-21 nvelope lementation 0 System for Host Community gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-28 / Installati Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2023-08-3 on of Public Toilet including IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 942,951.00 0.00 2022-11-30 2022-12-05 2023-01-04 2023-02-03 2023-03-03 nvelope lementation 0 O&M for host community gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-29 / Installati Delivery of Basic Services, R ment Document - on of Household toilet includi Single Stage - One E Pending Imp 2024-03-0 IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 2,121,640.00 0.00 2022-12-05 2022-12-10 2023-01-09 2023-02-08 2023-03-08 ng renovation of existing toil nvelope lementation 7 gency Response, and Gende ss (Non Bank-SPD ets (camp) r-Based Viol ence Prevention ) Component 1: Strengthening National Procure EMCRP/AF/WD-34 / Installati Delivery of Basic Services, R ment Document - Single Stage - One E Pending Imp 2024-04-0 on of Household bio-fill toilet IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 1 Envelope proce 766,150.00 0.00 2022-11-30 2022-12-05 2023-01-04 2023-03-05 2023-04-02 nvelope lementation 1 s including O&M (camp) gency Response, and Gende ss (Non Bank-SPD r-Based Viol ence Prevention ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMRCRP/GD-07 / Supply of C Delivery of Basic Services, R Single Stage - One E omputer with printer and sca IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 29,904.31 28,936.62 Signed 2019-01-15 2019-04-03 2019-01-20 2019-03-03 2019-04-18 2019-04-02 2019-05-23 2019-05-07 2019-06-06 2019-07-06 nvelope nner including laptop gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMRCRP/GD-08 / Supply of F Delivery of Basic Services, R Single Stage - One E urniture and Fixtures for PMU IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 23,923.44 15,107.97 Signed 2019-02-01 2019-04-18 2019-02-06 2019-03-20 2019-05-16 2019-04-19 2019-06-03 2019-05-24 2019-06-19 2019-06-23 nvelope & RPO gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMRCRP/GD-10 / Supply of A Delivery of Basic Services, R Single Stage - One E ir Conditioner for PMU and RP IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 23,923.44 18,243.68 Signed 2019-02-15 2019-04-09 2019-02-20 2019-04-03 2019-04-25 2019-05-03 2019-06-29 2019-06-07 2019-07-10 2019-07-07 nvelope O gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMRCRP/GD-11 / Equipment Delivery of Basic Services, R Single Stage - One E for Cox's Bazar Zonal Laborat IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 598,086.12 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-02-18 nvelope ory gency Response, and Gende r-Based Viol ence Prevention EMCRP/GD-11 A / Supply of Component 1: Strengthening Equipment for Cox's Bazar Z Delivery of Basic Services, R Single Stage - One E onal Laboratory, DPHE (Atom IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 478,469.00 350,917.81 Completed 2019-03-20 2019-03-13 2019-03-25 2019-05-06 2019-04-04 2019-06-05 2019-05-09 2019-07-10 2019-06-11 2020-01-06 2019-08-31 nvelope ic Absorption Spectrometer - gency Response, and Gende AAS and AAS with Graphite F r-Based Viol ence Prevention urnace) Component 1: Strengthening EMCRP/GD-11 B / Supply of Delivery of Basic Services, R Different Types of Laboratory Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 119,617.00 76,275.53 Signed 2019-04-04 2019-03-12 2019-04-09 2019-05-21 2019-03-28 2019-06-20 2019-05-09 2019-07-25 2019-06-11 2020-01-21 Equipment for Water Quality nvelope gency Response, and Gende Test r-Based Viol ence Prevention Component 1: Strengthening EMCRP/GD-01 / Supply and I Delivery of Basic Services, R Single Stage - One E nstallation of Truck based mo IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 1,194,743.13 1,141,911.52 Signed 2019-09-29 2019-12-08 2019-10-04 2019-10-29 2020-01-07 2019-11-14 2020-03-03 2019-12-19 2020-03-24 2020-02-13 nvelope bile water treatment plant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/GD-02 / Supply of Tr Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 507,765.83 353,685.08 Signed 2019-09-30 2020-03-08 2019-10-07 2019-11-01 2020-05-11 2019-11-17 2020-07-10 2019-12-22 2020-08-18 2020-02-16 uck mounted water carrier nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/GD-11.C / Supply of Delivery of Basic Services, R Single Stage - One E Laboratory Equipment for Wa IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 166,069.30 105,009.10 Signed 2019-11-27 2019-12-04 2019-12-02 2020-01-13 2019-12-29 2020-02-12 2020-01-30 2020-03-18 2020-02-17 2020-09-14 nvelope ter Quality Test gency Response, and Gende r-Based Viol ence Prevention Page 3 Component 1: Strengthening EMCRP/DPHE/GD-15-A / Sup Delivery of Basic Services, R Single Stage - One E ply of Office Equipment for IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 16,200.00 0.00 Canceled 2020-03-15 2020-03-20 2020-04-10 2020-05-10 2020-06-07 2020-08-06 nvelope PMU and RPO gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/GD-12 / Supply Delivery of Basic Services, R of Video Conferencing Syste Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 25,000.00 21,738.77 Signed 2020-03-25 2020-03-25 2020-03-26 2020-04-09 2020-04-08 2020-04-19 2020-04-16 2020-05-03 2020-05-13 2020-05-18 m and office Equipment for P nvelope gency Response, and Gende MU and RPMU r-Based Viol ence Prevention EMCRP/DPHE/13-A / Procure Component 1: Strengthening ment of Soap Bar as Hand W Delivery of Basic Services, R Request for Quota Single Stage - One E ashing Agent - for Emergenc IDA / D4190 esilient Infrastructure, Emer Post Limited 79,500.00 70,159.61 Signed 2020-04-05 2020-04-06 2020-04-24 2020-05-03 2020-05-24 tions nvelope y Support to prevent COVID- gency Response, and Gende 19 virus r-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/GD-13 / Procur Delivery of Basic Services, R ement of Hand Sanitizer for E Request for Quota Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Limited 149,650.00 141,181.70 Completed 2020-04-06 2020-04-06 2020-04-25 2020-05-03 2020-04-28 2020-06-09 mergency Support to prevent tions nvelope gency Response, and Gende COVID-19 virus . r-Based Viol ence Prevention Component 1: Strengthening EMCRP/DPHE/GD-14 / Procur Delivery of Basic Services, R ement of Water Purifying Tab Request for Quota Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Limited 53,770.00 52,220.07 Signed 2020-06-11 2020-06-07 2020-07-04 2020-06-22 2020-08-03 lets for Cyclone Amphan effe tions nvelope gency Response, and Gende cted people. r-Based Viol ence Prevention Component 1: Strengthening EMCRP/GD-3.A / Supply of V Delivery of Basic Services, R acuum tag and Mini Covered Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 672,000.00 636,830.10 Signed 2020-11-30 2020-01-07 2020-12-07 2021-01-06 2021-01-07 2021-02-05 2021-02-23 2021-03-12 2021-03-14 2021-07-10 Van (Garbage Truck) with O nvelope gency Response, and Gende &M r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GD-27 / Supply of Delivery of Basic Services, R Computer with Printer and Sc Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 24,222.00 19,741.22 Signed 2021-04-05 2021-07-27 2021-04-07 2021-04-28 2021-08-31 2021-05-28 2021-10-28 2021-07-02 2021-11-25 2021-09-30 anner including laptop and P nvelope gency Response, and Gende hotocopier r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GD-09 / Supply of Delivery of Basic Services, R Single Stage - One E Furniture & Fixtures for PMU IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 32,060.00 29,201.79 Signed 2021-04-15 2021-12-01 2021-04-17 2021-05-08 2021-12-30 2021-06-07 2022-03-22 2021-07-12 2022-04-13 2021-10-10 nvelope & RPMU gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GD-26 / Supply of Delivery of Basic Services, R Single Stage - One E Pending Impl Air Conditioner for PMU and IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 17,185.00 0.00 2022-02-15 2022-02-20 2022-03-22 2022-04-21 2022-05-26 2022-07-25 nvelope ementation RPMU gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/GD-24 / Supply of Delivery of Basic Services, R Single Stage - One E Pending Impl office stationery for PMU and IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 17,680.00 0.00 2022-04-05 2022-04-07 2022-05-02 2022-06-01 2022-07-06 2022-09-04 nvelope ementation field offices gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/GD-05 / Supply of Fie Single Stage - One E Pending Impl IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 47,150.00 0.00 2022-11-08 2022-11-13 2022-12-04 2023-01-03 2023-01-31 2023-05-01 ld Test Kits nvelope ementation gency Response, and Gende r-Based Viol ence Prevention NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening EMRCRP/NSD-01 / Support st Delivery of Basic Services, R Single Stage - One E aff/Manpower for PMU and R IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 71,770.00 51,226.58 Signed 2019-01-01 2019-03-04 2019-01-06 2019-02-17 2019-04-02 2019-03-19 2019-06-16 2019-04-23 2019-08-04 2022-04-22 nvelope PO (outsourcing) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/NSD-03 / Vehicle ren Single Stage - One E IDA / D4190 esilient Infrastructure, Emer Post Request for Bids Open - National 251,612.90 224,069.85 Signed 2019-10-13 2019-08-22 2019-10-20 2019-11-14 2019-09-16 2019-11-29 2019-10-24 2020-01-03 2020-01-02 2020-04-02 tal nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/NCSD-11 / Operation Delivery of Basic Services, R and Maintenance of Water Sa Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 295,000.00 0.00 Canceled 2022-06-20 2022-06-25 2022-07-16 2022-08-15 2022-09-05 2024-06-25 nitation and Hygiene activitie nvelope gency Response, and Gende s for DRP r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF-NCSD-7 / Operati Delivery of Basic Services, R ons and Maintenance of Wat Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 412,550.00 0.00 Canceled 2022-06-15 2022-06-20 2022-07-11 2022-08-10 2022-08-31 2024-06-20 er Supply and Sanitation Acti nvelope gency Response, and Gende vities for Host Community r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/NCSD-4 / Vehicle Single Stage - One E IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 235,740.00 0.00 Canceled 2022-06-05 2022-06-10 2022-07-01 2022-07-31 2022-08-21 2024-06-30 rental service nvelope gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/NCSD/04 / Vehicle Delivery of Basic Services, R Single Stage - One E Pending Impl Rental for PMU and RPMU of IDA / D5900 esilient Infrastructure, Emer Post Request for Bids Open - National 235,740.00 0.00 2022-11-30 2022-12-05 2023-01-04 2023-02-03 2023-03-03 2023-08-30 nvelope ementation EMCRP gency Response, and Gende r-Based Viol ence Prevention CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 EMCRP/SD-16 / Training on Component 1: Strengthening O&M for caretaker, Awarenes Delivery of Basic Services, R Quality And Cost- Open - Internationa s program on water and sanit IDA / D4190 esilient Infrastructure, Emer Post 717,703.00 496,450.34 Signed 2019-03-01 2019-02-11 2019-03-22 2019-02-20 2019-05-05 2019-06-13 2019-06-02 2019-07-24 2019-07-02 2019-08-26 2019-08-06 2019-09-08 2019-09-10 2019-12-30 2021-09-07 Based Selection l ation, hygine promotion and gency Response, and Gende BCC campaign r-Based Viol ence Prevention EMCRP/SD-14 / Monitoring a Component 1: Strengthening nd supervision of water suppl Delivery of Basic Services, R y and sanitation schemes inc Consultant Qualifi IDA / D4190 esilient Infrastructure, Emer Prior Open - National 2,200,957.00 2,134,860.70 Signed 2019-03-25 2019-04-10 2019-04-15 2019-04-10 2019-05-29 2019-05-22 2019-06-28 2019-07-11 2019-08-02 2019-09-26 2020-01-29 luding review, update of exis cation Selection gency Response, and Gende ting drawing, design and Env r-Based Viol ence Prevention ironmental and Social Impact Assessment (EIA & SIA) Component 1: Strengthening EMCRP/AF/SD-22 / Selection Delivery of Basic Services, R of Consultant for Community Quality And Cost- IDA / D5900 esilient Infrastructure, Emer Post Open - National 825,100.00 757,249.51 Signed 2021-04-15 2021-06-20 2021-05-15 2021-06-27 2021-07-29 2021-10-27 2021-08-28 2021-12-08 2021-09-27 2022-01-27 2021-11-01 2022-03-20 2021-12-06 2022-04-11 2024-05-24 mobilization and Capacity De Based Selection gency Response, and Gende velopment r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-25 / Consultin Delivery of Basic Services, R g firm for arranging foreign T Consultant Qualifi Under Implement IDA / D4190 esilient Infrastructure, Emer Post Limited 146,157.00 0.00 2021-11-18 2021-12-22 2022-01-17 2022-02-16 2022-03-23 2024-02-28 raining, Workshop, Exposure cation Selection ation gency Response, and Gende Visit etc r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SD-17 / Engagement Delivery of Basic Services, R Fixed Budget Sele Pending Impleme of Consulting Firm for Third P IDA / D4190 esilient Infrastructure, Emer Post Open - National 35,400.00 0.00 2022-07-03 2022-07-24 2022-10-06 2022-11-03 2022-12-18 2023-01-22 2023-02-12 2025-02-01 ction ntation arty Auditing gency Response, and Gende r-Based Viol ence Prevention INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening Delivery of Basic Services, R EMRCRP/SD-01 / Financial M Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 150,717.70 4,144.71 Terminated 2019-01-01 2019-01-02 2019-01-06 2019-03-25 2019-01-27 2019-03-28 2019-03-03 2019-04-18 2022-03-02 anagement Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMRCRP/SD-02 / Procureme Individual Consult / esilient Infrastructure, Emer Post Limited 129,187.00 3,552.61 Terminated 2019-01-01 2019-01-02 2019-01-06 2019-03-25 2019-01-27 2019-03-28 2019-03-03 2019-05-14 2022-03-02 nt Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMRCRP/SD-03 / Jr. Procure Individual Consult / esilient Infrastructure, Emer Post Limited 64,593.00 0.00 Canceled 2019-02-01 2019-02-06 2019-02-27 2019-04-03 2022-04-02 ment Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMRCRP/SD-04 / Water Supp Individual Consult / esilient Infrastructure, Emer Post Limited 129,187.00 2,723.67 Signed 2019-02-01 2019-01-20 2019-02-06 2019-03-25 2019-02-27 2019-03-28 2019-04-03 2019-04-16 2022-04-02 ly Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMRCRP/SD-06 / Environmen Delivery of Basic Services, R Individual Consult tal and Hydrogeologist Consu IDA / D4190 esilient Infrastructure, Emer Post Limited 129,187.00 127,848.46 Signed 2019-02-01 2019-01-20 2019-02-06 2019-05-05 2019-02-27 2019-05-06 2019-04-03 2019-05-14 2022-04-02 ant Selection ltant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMRCRP/SD-07 / M&E Consul Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 107,656.00 106,540.38 Signed 2019-02-01 2019-01-20 2019-02-06 2019-05-05 2019-02-27 2019-05-06 2019-04-03 2019-05-14 2022-04-02 tant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMRCRP/SD-09 / Social Deve Delivery of Basic Services, R Individual Consult lopment and Hygiene Promo IDA / D4190 esilient Infrastructure, Emer Post Open 107,656.00 106,540.38 Terminated 2019-03-03 2019-01-20 2019-04-21 2019-05-05 2019-05-12 2019-05-06 2019-06-16 2019-05-14 2022-06-15 ant Selection tion Consultant gency Response, and Gende r-Based Viol ence Prevention EMRCRP/SD-14 / Monitoring Component 1: Strengthening and supervision of water sup Delivery of Basic Services, R ply and sanitation schemes i IDA / D4190 esilient Infrastructure, Emer Prior Direct Selection Direct 2,200,957.00 0.00 Canceled 2019-02-01 2019-01-22 2019-02-11 2019-04-17 2022-04-16 ncluding review, update of e gency Response, and Gende xisting drawing, design and E r-Based Viol ence Prevention nvironmental and Social Imp act Assessment (EIA & SIA) Component 1: Strengthening EMRCRP/SD-05 / Sanitation a Delivery of Basic Services, R Individual Consult nd Waste Management Cons / esilient Infrastructure, Emer Post Open 129,187.00 0.00 Canceled 2019-03-03 2019-01-20 2019-04-21 2019-07-07 2019-05-12 2019-06-16 2022-06-15 ant Selection ultant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP-SD-03 / Jr. Procurem Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Open 64,593.00 1,776.30 Signed 2019-01-31 2019-01-20 2019-03-21 2019-05-13 2019-04-11 2019-03-28 2019-05-16 2019-06-18 2022-04-30 ent Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SD-15 / Design (inclu Delivery of Basic Services, R ding feasibilty and site select IDA / D4190 esilient Infrastructure, Emer Post Direct Selection Direct 315,958.00 343,006.30 Signed 2019-02-03 2019-02-13 2019-01-23 2019-04-19 2019-06-11 2020-04-13 ion) of fecal sludge and solid gency Response, and Gende waste management system r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SD-8 / Training Cons Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Open 107,656.00 106,622.46 Signed 2019-06-13 2019-05-01 2019-08-01 2019-07-07 2019-08-22 2019-07-18 2019-09-26 2019-08-06 2020-03-24 ultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SD-10 / Building Desi Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 26,786.00 26,370.00 Signed 2019-12-22 2020-01-02 2019-12-27 2020-01-02 2020-01-17 2020-02-21 2020-03-24 2020-08-19 gn Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Page 5 Component 1: Strengthening Delivery of Basic Services, R EMCRP/SD-10(A) / Architectu Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 18,184.00 17,893.93 Signed 2019-12-22 2020-01-02 2019-12-27 2020-01-02 2020-01-17 2020-02-26 2020-02-21 2020-03-24 2020-08-19 ral Drawing Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SD-11 / ICT Consulta Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 35,842.00 35,347.25 Signed 2019-12-22 2019-12-26 2019-12-27 2019-12-26 2020-01-17 2020-01-26 2020-02-21 2020-02-03 2020-08-19 nt ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/SD-2-A / Selection of Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Open 86,000.00 84,910.68 Signed 2020-01-26 2019-11-17 2020-02-24 2019-12-18 2020-03-02 2019-12-22 2020-03-16 2019-12-23 2022-03-01 Procurement Specialist ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/SD-1-A / Selection of Delivery of Basic Services, R Individual Consult Financial Management Consu IDA / D4190 esilient Infrastructure, Emer Post Limited 105,000.00 96,232.10 Signed 2020-03-25 2019-11-20 2020-03-30 2019-12-01 2020-04-06 2019-12-22 2020-04-20 2019-12-29 2022-03-31 ant Selection ltant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/DPHE/SD-3-A / Jr. Pro Individual Consult IDA / D5900 esilient Infrastructure, Emer Post Open 86,000.00 84,990.82 Signed 2020-07-30 2020-07-20 2020-09-24 2020-09-07 2020-10-15 2020-09-27 2020-11-19 2020-10-19 2023-11-04 curement Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention EMCRP/AF/SD-21 / Monitorin Component 1: Strengthening g & supervision of water sup Delivery of Basic Services, R ply and sanitation schemes i Under Implement IDA / D5900 esilient Infrastructure, Emer Prior Direct Selection Direct 2,121,640.00 0.00 2021-01-27 2021-07-25 2021-03-03 2021-11-03 2021-06-06 2023-11-23 ncluding review and update ation gency Response, and Gende of existing drawing and desig r-Based Viol ence Prevention n, EIA and SIA and establish ment of ICT Monitoring Syste m Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SD-12 / Hydraulic Individual Consult Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Limited 70,720.00 0.00 2021-07-15 2021-07-30 2021-09-28 2021-11-16 2023-11-16 Structure Consultant ant Selection ntation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-23 / Consultin Delivery of Basic Services, R g firm for conducting Trainin IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 60,502.00 57,262.61 Signed 2021-03-21 2021-06-20 2021-04-05 2021-07-27 2021-06-16 2022-01-04 2022-06-16 g on Procurement, GBV etc. gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-24 / Consultin Delivery of Basic Services, R g firm for conducting Trainin IDA / D5900 esilient Infrastructure, Emer Post Direct Selection Direct 195,792.00 186,380.14 Signed 2021-03-21 2021-06-20 2021-04-05 2021-07-27 2021-06-16 2022-01-04 2023-06-16 g on Sanitation,Waste Manag gency Response, and Gende ement, etc r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-19 / Fecal Slu Delivery of Basic Services, R Individual Consult dge & Solid Waste Managem IDA / D5900 esilient Infrastructure, Emer Post Limited 48,505.00 44,362.29 Signed 2021-03-30 2021-10-18 2021-04-06 2021-10-18 2021-05-06 2022-02-01 2021-06-10 2022-02-13 2024-04-17 ant Selection ent Consultant (FS&SWM) gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SD-18 / Rain Wat Individual Consult Under Implement IDA / D5900 esilient Infrastructure, Emer Post Limited 21,216.00 0.00 2021-05-10 2021-10-18 2021-05-17 2021-06-16 2021-07-21 2024-05-28 er Harvesting Consultant ant Selection ation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-1.B / Engagem Delivery of Basic Services, R Individual Consult ent of Financial Management IDA / D4190 esilient Infrastructure, Emer Post Limited 111,390.00 104,494.02 Signed 2022-01-31 2022-02-08 2022-02-10 2022-02-10 2022-02-15 2022-03-13 2022-03-20 2022-03-16 2024-06-07 ant Selection Consultant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-4.A / Engagem Delivery of Basic Services, R Individual Consult ent of Water Supply Consulta IDA / D4190 esilient Infrastructure, Emer Post Limited 84,900.00 58,273.98 Signed 2022-02-15 2022-02-28 2022-02-25 2022-03-09 2022-03-11 2022-04-26 2022-04-15 2022-04-28 2024-04-13 ant Selection nt gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-6.A / Engagem Delivery of Basic Services, R Individual Consult ent of Hydrogeologist & Envir IDA / D4190 esilient Infrastructure, Emer Post Limited 63,650.00 57,007.15 Signed 2022-03-10 2022-02-28 2022-03-20 2022-03-13 2022-04-10 2022-05-12 2022-05-08 2022-05-17 2023-10-30 ant Selection onment Consultant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SD-7.A / Engagem Individual Consult IDA / D4190 esilient Infrastructure, Emer Post Limited 70,720.00 63,341.28 Signed 2022-03-01 2022-02-28 2022-03-11 2022-03-14 2022-04-01 2022-05-12 2022-04-29 2022-05-17 2024-04-18 ent of M&E Consultant ant Selection gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-2-B / Engage Delivery of Basic Services, R Individual Consult ment of Procurement Consult IDA / D4190 esilient Infrastructure, Emer Post Direct 106,100.00 0.00 Canceled 2021-12-09 2021-12-14 2021-12-17 2021-12-20 2021-12-26 2024-06-30 ant Selection ant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF-SD-2-B / Engage Delivery of Basic Services, R Individual Consult ment of Procurement Consult IDA / D4190 esilient Infrastructure, Emer Prior Limited 127,230.00 100,898.77 Signed 2022-01-25 2022-01-24 2022-02-04 2022-01-06 2022-02-11 2022-04-13 2022-02-25 2022-02-02 2024-06-30 ant Selection ant gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SD-8-A / Engage Individual Consult Under Implement IDA / D5900 esilient Infrastructure, Emer Post Open 53,000.00 0.00 2022-05-30 2022-06-12 2022-07-18 2022-08-25 2022-07-25 2022-08-28 2022-08-22 2024-02-13 ment of Training Consultant ant Selection ation gency Response, and Gende r-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/SD-9-A / Engage Delivery of Basic Services, R ment of Social Development Individual Consult Under Implement IDA / D5900 esilient Infrastructure, Emer Post Open 50,000.00 0.00 2022-05-30 2022-06-14 2022-07-20 2022-07-27 2022-08-31 2024-02-22 and Hygiene Promotion Cons ant Selection ation gency Response, and Gende ultant. r-Based Viol ence Prevention Page 6 Component 1: Strengthening Delivery of Basic Services, R EMCRP/AF/SD-20 / Engagem Individual Consult Pending Impleme IDA / D5900 esilient Infrastructure, Emer Post Open 99,000.00 0.00 2022-06-15 2022-08-03 2022-08-10 2022-08-31 2024-06-30 ent of ICT and MIS consultant ant Selection ntation gency Response, and Gende r-Based Viol ence Prevention Page 7