PROCUREMENT PLAN (Textual Part) Project: 6O Regional Disaster Vulnerability Reduct. Project (P117871) Implementing agencies: PCU Grenada – Ministry of Finance and SVG – Ministry of Finance, Economic Planning, Sustainable Development, and Information Technology Date of the Procurement Plan: October 23, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. The Project was approved on June 23, 2011 and is expected to close on Dec. 31, 2018; however, an extension is being processed in parallel at the current time. All works, goods, non-consulting services and consulting services to be procured with this Project’s funds needs to be procured and contracted prior closing date for eligibility purposes. The procurement plan for this Project along with this textual part constitute the Procurement Plan. Procurement Plan The following conditions apply to all the procurement activities foreseen in the Procurement Plan: • The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. • The new Fraud & Corruption clauses shall be incorporated in all contracts to be signed after approval of the procurement plan. PROCUREMENT OECS Countries : Regional Disaster Vulnerability Reduction APL1 - Grenada and St. Vincent and the Grenadines PLAN General Information Country: OECS Countries Bank’s Approval Date of the Original Procurement Plan: 2018-11-14 2021-11-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P117871 GPN Date: Project Name: Regional Disaster Vulnerability Reduction APL1 - Grenada and St. Vincent and the Grenadines Loan / Credit No: IDA / 49860, IDA / 49850, IDA / 54500, TF / A3698, TF / 16733, TF / 11132 SVG - Ministry of Finance, Economic Planning, Sustainable Development, and Information Technology Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 2 - Regional SVGRDVRP-CW-NCB-18 / Platforms for Hazard and Risk Request for Single Stage - One 1,935,993.0 2019-12- C2.3.1 - AF: Rehabilitation of TF / A3698 Evaluation, and Applications Post Open - National 1,682,000.00 Signed 2019-02-05 2019-04-02 2019-04-29 Quotations Envelope 2 31 Chateaubelair jetty for Improved Decision Making SVGRDVRP-CW-NCB-2A / C1.2.1 Renovation of Component 1 - Prevention Request for Single Stage - One 1,138,833.8 2019-12- IDA / 54500 Post Open - National 929,990.00 Signed 2018-12-05 2019-01-30 2019-04-30 Emergency Shelters - and Adaptation Investments Quotations Envelope 4 31 Kingstown Government School SVGRDVRP-CW-NCB-16 / Pending C1.2.4 Congo Valley: Component 1 - Prevention Request for Single Stage - One 2019-11- TF / A3698 Post Open - National 550,000.00 0.00 Implementat 2019-03-20 2019-05-15 Construction of bridge No.2 and Adaptation Investments Quotations Envelope 11 ion and Road SVGRDVRP-CW-NCB-17 / Component 1 - Prevention Request for Single Stage - One 2020-10- C1.2.4 Longline Road Bridge TF / A3698 Post Open - National 750,000.00 567,006.37 Signed 2019-03-20 2019-05-15 2019-05-07 and Adaptation Investments Quotations Envelope 30 and Road - Construction Component 2 - Regional SVGRDVRP-CW-SW-8A / Platforms for Hazard and Risk Request for Single Stage - One 2019-07- C2.1.1 Backfilling at Rose Hall TF / 16733 Evaluation, and Applications Post Limited 25,000.00 15,879.16 Completed 2018-11-20 2018-10-25 2019-01-15 2018-12-21 Quotations Envelope 14 Satellite Warehouse for Improved Decision Making Component 2 - Regional SVGRDVRP-W-ICB-3 / C2.3.1 Platforms for Hazard and Risk Single Stage - One 2020-10- - Coastal defense works: IDA / 54500 Evaluation, and Applications Post Request for Bids Open - International 3,540,000.00 0.00 Canceled 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-24 Envelope 30 Georgetown for Improved Decision Making SVGRDVRP-CW-ICB-10A / Component 1 - Prevention Single Stage - One 2020-11- Rose Bank and Dark View TF / A3698 Prior Request for Bids Open - International 4,700,000.00 0.00 Canceled 2018-11-30 2018-12-05 2019-01-16 2019-02-15 2019-03-22 and Adaptation Investments Envelope 30 Slope stabilisation works SVG-RDVRP-CW-NCB-3A / Pending Component 1 - Prevention Request for Single Stage - One 2020-01- Construction of Bequia TF / 16733 Post Open - National 600,000.00 0.00 Implementat 2018-12-19 2019-03-20 and Adaptation Investments Quotations Envelope 14 Satellite Warehouse ion Component 2 - Regional SVGRDVRP-CW-ICB-6 / Platforms for Hazard and Risk C2.3.1 - Coastal defense Single Stage - One 10,560,000.0 2020-05- IDA / 54500 Evaluation, and Applications Prior Request for Bids Open - International 0.00 Canceled 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-24 works: Sans Souci and Dark Envelope 0 18 for Improved Decision View Making Component 2 - Regional SVGRDVRP-CW-RFB-21 / Platforms for Hazard and Risk Single Stage - One 2020-01- C2.3.1 Coastal Defense works- IDA / 54500 Evaluation, and Applications Post Request for Bids Open - National 2,542,584.00 0.00 Canceled 2019-03-15 2019-03-15 2019-03-20 2019-05-01 2019-05-17 2019-05-31 2019-07-05 Envelope 01 Sans Souci for Improved Decision Making Component 2 - Regional SVG-RDVRP-CW-NCB-22 / Platforms for Hazard and Risk Under Single Stage - One 2020-01- C2.3.1 Coastal Defense Works IDA / 54500 Evaluation, and Applications Post Request for Bids Open - National 1,468,845.00 0.00 Implementat 2019-03-22 2019-03-29 2019-03-27 2019-05-08 2019-05-17 2019-06-07 2019-07-12 Envelope 08 - Dark View South for Improved Decision ion Making Component 2 - Regional SVG-RDVRP-CW-NCB-24 / Platforms for Hazard and Risk Single Stage - One 4,338,031.9 2020-01- C2.3.1 Coastal Defense - IDA / 54500 Evaluation, and Applications Post Request for Bids Open - National 2,885,535.00 Signed 2019-04-05 2019-06-14 2019-04-10 2019-05-22 2019-07-26 2019-06-21 2019-11-26 2019-07-26 2020-01-29 Envelope 0 22 Georgetown for Improved Decision Making Component 2 - Regional SVG-RDVRP-CW-NCB-25 / Platforms for Hazard and Risk Single Stage - One Under 2020-01- C2.3.1 Coastal Defense IDA / 54500 Evaluation, and Applications Post Request for Bids Open - National 2,316,131.00 0.00 2019-04-12 2019-06-14 2019-04-17 2019-05-29 2019-07-26 2019-06-28 2019-08-02 Envelope Review 29 Geogetown 1B for Improved Decision Making Component 2 - Regional SVG-RDVRP-CW-NCB-26 / Platforms for Hazard and Risk Pending Single Stage - One 2020-02- C2.3.1 Coastal Defense: Dark IDA / 54500 Evaluation, and Applications Post Request for Bids Open - National 2,903,465.00 0.00 Implementat 2019-04-19 2019-04-24 2019-06-05 2019-07-05 2019-08-09 Envelope 05 View North for Improved Decision ion Making SVGRDVRP-CW-ICB-10B / Component 1 - Prevention Single Stage - One 2020-12- Dark View Slope Stabilisation TF / A3698 Prior Request for Bids Open - International 3,100,000.00 0.00 Canceled 2018-12-19 2019-03-07 2018-12-24 2019-02-04 2019-03-06 2019-04-10 and Adaptation Investments Envelope 19 Works SVG-RDVRP-W-NCB-27 / Pending Component 1 - Prevention Single Stage - One 2020-01- Dark View slope stabilization IDA / 54500 Post Request for Bids Open - National 2,947,000.00 0.00 Implementat 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 and Adaptation Investments Envelope 25 works ion Component 2 - Regional SVGRDVRP-CW-NCB-8 / Platforms for Hazard and Risk Under Single Stage - One 2020-11- C2.2.2 - River defense works IDA / 49860 Evaluation, and Applications Post Request for Bids Open - National 2,566,773.00 0.00 Implementat 2019-08-02 2020-11-08 2019-08-07 2019-09-18 2019-12-13 2019-10-18 2020-02-04 2019-11-22 Envelope 21 - Buccament for Improved Decision ion Making Page 1 Component 2 - Regional SVGRDVRP-CW-NCB-28 / Platforms for Hazard and Risk Under Single Stage - One 2020-08- C2.2.2 River defense works - IDA / 54500 Evaluation, and Applications Post Request for Bids Open - National 368,276.00 421,311.89 Implementat 2019-09-02 2019-09-06 2019-09-07 2019-10-19 2019-10-11 2019-11-18 2019-11-18 2019-12-23 Envelope 23 Carriere for Improved Decision ion Making Component 2 - Regional SVGRDVRP-CW-RFB-21A / Platforms for Hazard and Risk Under Single Stage - One 2020-08- C2.3.1 Coastal Defense works- IDA / 54500 Evaluation, and Applications Post Request for Bids Open - National 4,500,000.00 0.00 Implementat 2019-10-25 2019-10-11 2019-10-30 2019-12-11 2019-11-11 2020-01-10 2019-12-18 2020-02-14 Envelope 12 Sans Souci for Improved Decision ion Making SVG-RDVRP-W-RFQ-3 / Pending Component 1 - Prevention Request for Single Stage - One 2020-11- Ginger Village Overland drain IDA / 54500 Post Limited 75,000.00 0.00 Implementat 2020-07-19 2020-09-04 and Adaptation Investments Quotations Envelope 03 protection works ion Pending SVG-RDVRP-CW-RFB1-7A / Component 1 - Prevention Single Stage - One 2021-05- IDA / 54500 Post Request for Bids Limited 375,000.00 0.00 Implementat 2021-02-14 2021-02-15 2021-03-01 2021-03-08 2021-03-22 Belle Isle Slope Stabilisation 2 and Adaptation Investments Envelope 21 ion Component 2 - Regional SVG-RDVRP-CW-NCB-23 / Platforms for Hazard and Risk Single Stage - One 2020-01- C2.3.1 - Coastal Defense IDA / 54500 Evaluation, and Applications Post Request for Bids Open - National 1,871,935.00 0.00 Canceled 2019-03-29 2019-04-03 2019-05-15 2019-06-14 2019-07-19 Envelope 15 Rose Bank for Improved Decision Making GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRDVRP-G-SH-31 / C4 - Component 4 - Project Pending Equipment for institutional Request for Single Stage - One TF / 16733 Management and Post Limited 11,000.00 0.00 Implementati 2018-12-05 2019-01-30 2019-03-29 strengthening - PSIPMU Quotations Envelope Implementation Support on Laptops and Shredder SVGRDVRP-G-SH-3 / Equipment for institutional Component 4 - Project Request for Single Stage - One strengthening - TF / 16733 Management and Post Limited 25,000.00 10,293.91 Signed 2019-01-07 2018-12-19 2019-03-04 2019-03-26 2019-08-31 Quotations Envelope Multifunctional printer for Implementation Support PSIPMU SVG-RDVRP-GO-NCB-4 / Goods for Fisheries Component 2 - Regional Department: Platforms for Hazard and Risk Under Lot 1: Office Equipment Single Stage - One IDA / 49860 Evaluation, and Applications Post Request for Bids Open - National 100,000.00 0.00 Implementati 2019-11-22 2020-01-24 2020-01-10 2020-02-09 2020-03-09 2020-04-09 2020-08-07 2020-05-14 2020-11-10 Lot 2: Diving Equipment Envelope for Improved Decision on Lot 3: Surveying Equipment Making Lot 4: Water Quality Testing Supplies Component 4 - Project Pending SVG-RDVRP-GO-SH-32 / Request for Single Stage - One IDA / 49850 Management and Post Limited 3,000.00 0.00 Implementati 2019-11-19 2019-12-02 2019-12-13 Office furniture for PSIPMU Quotations Envelope Implementation Support on SVGRDVRP-G-RFQ-51 / Procurement of specialised Component 2 - Regional equipment for use by the Platforms for Hazard and Risk Pending Physical Planning Unit, within Request for Single Stage - One IDA / 54500 Evaluation, and Applications Post Open - National 50,000.00 0.00 Implementati 2020-05-08 2020-07-03 2020-10-01 the MoHILP to adequately Quotations Envelope for Improved Decision on execute its mandate of Making application and enforcement of the National Building Code. Component 2 - Regional SVG-RDVRP-GO-RFQ-33 / Platforms for Hazard and Risk Pending Central processing unit Request for Single Stage - One IDA / 54500 Evaluation, and Applications Post Limited 3,500.00 0.00 Implementati 2020-04-06 2020-04-23 2020-05-21 upgrade of Microsoft Office Quotations Envelope for Improved Decision on for PSIPMU officers. Making SVG-RDVRP-G-RFB-35 / IT Component 4 - Project Pending equipment (replacement Request for IDA / 54500 Management and Post 25,000.00 0.00 Implementati 2020-12-11 2021-01-29 2021-02-28 laptops, projectors), desktop Quotations Implementation Support on computers, etc. for the PIU SVG-RDVRP-G-RFQ-34 / Air Component 4 - Project Pending Request for Single Stage - One conditioning unit for IDA / 54500 Management and Post Limited 3,000.00 0.00 Implementati 2020-12-04 2021-01-29 2021-02-19 Quotations Envelope Conference Room No.2 of PIU Implementation Support on Component 2 - Regional SVG-RDVRP-G-RFQ-36 / IT Platforms for Hazard and Risk Pending equipment for the National Request for Single Stage - One IDA / 54500 Evaluation, and Applications Post Open - National 331,000.00 0.00 Implementati 2021-03-07 2021-04-01 2021-05-01 Emergency Management Quotations Envelope for Improved Decision on Organisation Making Component 2 - Regional SVG-RDVRP-G-RFQ-37 / Platforms for Hazard and Risk Pending Drones for the National Request for Single Stage - One IDA / 54500 Evaluation, and Applications Post Limited 9,000.00 0.00 Implementati 2021-03-02 2021-03-26 2021-04-25 Emergency Management Quotations Envelope for Improved Decision on Organisation Making Component 2 - Regional SVG-RDVRP-G-DIR-10 / Platforms for Hazard and Risk Pending Additional radios and IDA / 54500 Evaluation, and Applications Post Direct Selection Direct 232,500.00 0.00 Implementati 2021-02-26 2021-03-01 2021-04-01 2021-05-16 accessories for the emergency for Improved Decision on communications network Making Component 2 - Regional SVG-RDVRP-G-RFQ-38 / Platforms for Hazard and Risk Pending Request for Single Stage - One Upgrade of NEMO's ICT IDA / 54500 Evaluation, and Applications Post Limited 20,000.00 0.00 Implementati 2021-03-09 2021-04-02 2021-05-02 Quotations Envelope System to Support ECN for Improved Decision on Making Component 2 - Regional Platforms for Hazard and Risk Pending SVG-RDVRP-G-RFQ-39 / Request for Single Stage - One IDA / 54500 Evaluation, and Applications Post Limited 120,000.00 0.00 Implementati 2021-03-02 2021-03-26 2021-04-25 Vehicles for NEMO Quotations Envelope for Improved Decision on Making Page 2 Component 2 - Regional Platforms for Hazard and Risk Pending SVG-RDVRP-G-DIR-7 / Cots IDA / 54500 Evaluation, and Applications Post Direct Selection Direct 975,000.00 0.00 Implementati 2021-02-26 2021-03-01 2021-04-01 2021-05-16 for emergency shelters for Improved Decision on Making SVG-RDVRP-G-RFQ-40 / Component 2 - Regional Emergency goods - flood Platforms for Hazard and Risk Pending lights, mattresses, Request for Single Stage - One IDA / 54500 Evaluation, and Applications Post Open - National 792,500.00 0.00 Implementati 2021-03-07 2021-04-03 2021-05-03 megaphones, water tanks, Quotations Envelope for Improved Decision on generators, water jugs, Making storage containers Component 2 - Regional SVG-RDVRP-G-DIR-11 / Four- Platforms for Hazard and Risk Pending year renewal of ArcGIS IDA / 54500 Evaluation, and Applications Post Direct Selection Direct 40,000.00 0.00 Implementati 2021-04-09 2021-04-12 2021-05-13 2021-05-31 software for the Statistical for Improved Decision on Office Making SVG-RDVRP-G-DIR-8 / Component 2 - Regional Retrofitted containers Platforms for Hazard and Risk (approximately 4-20ft and 6- IDA / 54500 Evaluation, and Applications Post Direct Selection Direct 130,000.00 0.00 Canceled 2021-03-05 2021-03-08 2021-03-28 2021-04-22 40ft containers for storage of for Improved Decision emergency supplies. Making SVG-RDVRP-G-DIR-9 / Office Component 4 - Project Pending desks (2, no.) for the IDA / 54500 Management and Post Direct Selection Direct 2,000.00 0.00 Implementati 2021-10-24 2021-10-24 2021-11-26 2021-12-03 Economic Planning Division Implementation Support on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2 - Regional SVGRDVRP-NC-ICB-1A / Platforms for Hazard and Risk C2.1.3 - Emergency Single Stage - One IDA / 49860 Evaluation, and Applications Prior Request for Bids Open - International 3,500,000.00 3,616,246.49 Signed 2018-11-30 2019-02-06 2018-12-05 2019-02-19 2019-01-16 2019-04-12 2019-02-15 2019-09-02 2019-03-22 2019-09-05 2019-09-18 communications network for Envelope for Improved Decision SVG Making SVG-RDVRP-NCS-5 / Short Component 2 - Regional promotional video to elicit the Platforms for Hazard and Risk Pending public's comments on the IDA / 54500 Evaluation, and Applications Post Direct Selection Direct 2,500.00 0.00 Implementati 2021-11-22 2021-11-27 2021-12-16 2021-12-16 National Physical for Improved Decision on Development Plan Making CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2 - Regional SVGRDVRP-CS-LCS-7 / Platforms for Hazard and Risk Least Cost Pending C2.3.1 - Georgetown IDA / 54500 Evaluation, and Applications Post Open - International 200,000.00 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-02 2019-07-02 2019-08-06 2019-09-10 2020-03-08 Selection Implementation watershed study for Improved Decision Making SVGRDVRP-CS-CQS-2 / Component 2 - Regional C2.1.1 Training to support Platforms for Hazard and Risk Consultant improved application and IDA / 54500 Evaluation, and Applications Post Qualification Open - National 15,000.00 0.00 Canceled 2019-02-01 2019-04-03 2019-02-22 2019-04-07 2019-05-07 2019-06-11 2019-12-08 enforcement of building codes for Improved Decision Selection - MoHILP Making Component 2 - Regional SVGRDVRP-CS-QCBS-30 / Platforms for Hazard and Risk C2.1.5 - Review and update Quality And Cost- Pending IDA / 54500 Evaluation, and Applications Post Open - National 225,000.00 0.00 2019-02-01 2019-02-22 2019-04-07 2019-05-05 2019-06-04 2019-07-09 2019-08-13 2020-08-12 the existing draft Acts and Based Selection Implementation for Improved Decision regulations under PPCR 3.6 Making SVGRTCP-CS-CQS-3 / The Development of Legal and Component 2 - Regional Regulatory Framework for Platforms for Hazard and Risk Consultant Effluent Discharges, Including Under IDA / 54500 Evaluation, and Applications Post Qualification Open - National 60,000.00 0.00 2019-06-17 2019-07-19 2019-07-01 2019-08-14 2019-09-13 2019-10-18 2020-04-15 Minimum Sewage Effluent Implementation for Improved Decision Selection Guidelines for Coastal Areas Making in St. Vincent and the Grenadines SVGRDVRP-CS-QCBS-29 / Component 2 - Regional C2.1.2 Coastal inundation Platforms for Hazard and Risk impact modelling (storm Quality And Cost- IDA / 54500 Evaluation, and Applications Post Open - International 100,000.00 0.00 Canceled 2019-02-01 2019-02-22 2019-04-07 2019-05-05 2019-06-04 2019-07-09 2019-08-13 2020-08-12 surge, sea level rise, high Based Selection for Improved Decision energy wave action, winter Making swells, etc.) SVG-RDVRP-CS-CQS-4 / Specialist Geotechnical Consultant Component 1 - Prevention Under engineering services for IDA / 54500 Post Qualification Limited 50,000.00 0.00 2020-04-14 2020-04-28 2020-05-21 2020-06-25 2020-08-06 and Adaptation Investments Implementation review of foundation designs Selection for referral hospital INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SVGRDVRP-CS-INDV-11 / C2.1.5 - Development of Component 2 - Regional information packages for Platforms for Hazard and Risk Individual families & communities in Pending IDA / 49850 Evaluation, and Applications Post Consultant Open 35,000.00 0.00 2019-02-01 2019-03-22 2019-04-12 2019-05-17 2019-11-13 'Red Zone" expanded to a Implementation for Improved Decision Selection NEMO Public Education Making Campaign including development of the packages Page 3 SVGRDVRP-CS-INDV-15 / C2.1.5 - Preparation of a Component 2 - Regional small booklet, "Climate Platforms for Hazard and Risk Individual Pending Change Governance in SVG" ( IDA / 54500 Evaluation, and Applications Post Consultant Open 35,000.00 0.00 2019-02-01 2019-03-22 2019-04-12 2019-05-17 2019-11-13 Implementation 24-32 pp. max, for wide for Improved Decision Selection distribution amongst Making stakeholders SVGRDVRP-CS-LCS-6 / Component 2 - Regional C2.2.1 - Preparation of Platforms for Hazard and Risk Individual comprehensive integrated Pending IDA / 54500 Evaluation, and Applications Post Consultant Open 80,000.00 0.00 2019-02-01 2019-03-22 2019-04-12 2019-05-17 2019-11-13 watershed management Policy Implementation for Improved Decision Selection and Action Plan- including Making Arnos Vale SVGRDVRP-CS-INDV-28 / Component 2 - Regional C2.2.1 - Application of Platforms for Hazard and Risk Individual Relevant effluent Regulations IDA / 54500 Evaluation, and Applications Post Consultant Open 35,000.00 0.00 Canceled 2019-02-01 2019-04-02 2019-03-22 2019-04-12 2019-05-17 2019-11-13 and Standards at the Coastal for Improved Decision Selection Area - Villa Beach. Making SVGRDVRP-CS-INDV-14 / Component 2 - Regional C2.3.1 - Guidelines & Platforms for Hazard and Risk Individual Pending Outreach for Fisheries & IDA / 54500 Evaluation, and Applications Post Consultant Open 50,000.00 0.00 2019-03-15 2019-05-03 2019-05-24 2019-06-28 2019-12-25 Implementation Agriculture: Disposal of Solid for Improved Decision Selection Waste Gray & Black water Making Component 4 - Project Individual SVGRDVRP-CS-INDV-17A / TF / 16733 Management and Post Consultant Open 210,000.00 108,501.97 Signed 2019-01-02 2018-08-08 2019-02-20 2018-12-18 2019-03-13 2019-02-20 2019-04-17 2019-02-20 2020-12-31 C4 - Project Engineer Implementation Support Selection SVGRDVRP-CS-INDV-24A / Component 4 - Project Individual C4 - Procurement and Pending TF / 16733 Management and Post Consultant Open 210,000.00 0.00 2019-01-02 2019-02-20 2019-03-13 2019-04-17 2020-12-31 Contract Management Implementation Implementation Support Selection Specialist Component 4 - Project Individual SVGRDVRP-CS-INDV-30A / Pending TF / 16733 Management and Post Consultant Open 41,850.00 0.00 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2020-12-31 C4 - Procurement Assistant Implementation Implementation Support Selection SVGRDVRP-CS-INDV-38 / C4 Component 4 - Project Individual - Contract Management TF / 16733 Management and Post Consultant Direct 41,850.00 56,955.72 Signed 2018-11-15 2017-01-15 2018-11-25 2018-12-16 2018-12-16 2018-12-31 2019-02-28 2018-12-31 2020-12-31 Assistant Implementation Support Selection Component 4 - Project Individual SVGRDVRP-CS-INDV-18 / C4 TF / 16733 Management and Post Consultant Direct 120,170.00 173,604.80 Signed 2019-01-02 2014-03-31 2019-01-12 2018-12-21 2019-02-02 2018-12-31 2019-03-09 2019-01-07 2020-12-31 - Senior Quantity Surveyor Implementation Support Selection Component 4 - Project Individual SVGRDVRP-CS-INDV-16B / Pending TF / 16733 Management and Post Consultant Limited 120,710.00 0.00 2018-11-15 2018-11-20 2018-12-11 2019-01-01 2020-12-31 C4 - Project Coordinator Implementation Implementation Support Selection Component 4 - Project Individual SVGRDVRP-CS-INDV-21 / C4 TF / 16733 Management and Post Consultant Direct 214,630.00 585,926.42 Signed 2018-11-15 2013-08-12 2018-11-25 2018-12-28 2018-12-16 2018-12-31 2019-01-01 2018-12-31 2020-12-31 - Senior Engineer Implementation Support Selection Component 4 - Project Individual SVGRDVRP-C-IC-31 / C4 - Pending TF / 16733 Management and Post Consultant Direct 46,200.00 0.00 2018-11-15 2018-11-25 2018-12-16 2019-01-02 2020-12-31 Procurement Assistant Implementation Implementation Support Selection SVGRDVRP-CS-INDV-39A / Component 4 - Project Individual Under C4 - Contract Management TF / 16733 Management and Post Consultant Direct 41,850.00 0.00 2018-11-23 2018-01-16 2018-12-03 2018-12-24 2019-03-21 2020-12-31 Implementation Assistant Implementation Support Selection Component 4 - Project SVGRDVRP-CS-LCS-8 / C4 - Pending TF / 16733 Management and Post Direct Selection Direct 96,375.00 0.00 2018-11-15 2018-11-25 2019-01-29 2019-07-28 Financial Audit Implementation Implementation Support SVG-RDVRP-CV-INDV-40 / Component 4 - Project Individual Clerk of Works - Slope IDA / 54500 Management and Post Consultant Limited 16,000.00 12,915.13 Signed 2019-04-15 2019-04-04 2019-04-20 2019-05-02 2019-05-11 2019-05-16 2019-06-01 2019-05-16 2021-05-31 Stabilisation Works Implementation Support Selection SVGRDVRP-CS-INDV-41 / Component 4 - Project Individual Clerk of Works for IDA / 49860 Management and Post Consultant Limited 13,400.00 13,284.13 Signed 2019-05-17 2016-03-01 2019-05-22 2019-05-29 2019-06-12 2019-05-31 2019-07-17 2019-06-03 2020-01-13 construction of Kingstown Implementation Support Selection Government School SVGRDVRP-CV-INDV-42 / Component 4 - Project Individual Contract Management TF / 11132 Management and Post Consultant Limited 32,000.00 28,445.37 Signed 2019-05-31 2018-01-16 2019-06-05 2019-06-20 2019-06-26 2019-06-26 2019-07-31 2020-07-24 2020-01-27 Assistant Implementation Support Selection Component 2 - Regional SVGRDVP-CS-INDV-37A / Platforms for Hazard and Risk Individual The preparation of the TF / 11132 Evaluation, and Applications Post Consultant Open 90,000.00 259,496.00 Signed 2019-06-07 2019-06-14 2019-07-26 2020-10-02 2019-08-16 2020-10-13 2019-09-20 2020-10-23 2020-03-18 National Physical for Improved Decision Selection Development Plan Making SVGRDVRP-CV-INDV-43 / Component 4 - Project Individual Pending Environmental Safeguards IDA / 54500 Management and Post Consultant Limited 90,000.00 0.00 2019-07-10 2019-07-15 2019-08-05 2019-09-02 2020-12-31 Implementation Specialist Implementation Support Selection SVGRDVRP-CV-INDV-44 / Component 4 - Project Individual Under Procurement and Contract IDA / 54500 Management and Post Consultant Open 135,000.00 0.00 2019-07-23 2019-09-10 2019-10-01 2019-11-05 2020-05-03 Implementation Management Specialist Implementation Support Selection SVG-RDVRP-CS-INDV-48 / Component 4 - Project Individual Pending Clerk of Works - Fireburn IDA / 49860 Management and Post Consultant Limited 15,000.00 0.00 2019-11-22 2019-11-29 2019-12-20 2020-01-24 2020-05-31 Implementation Feeder Road Implementation Support Selection SVG-RDVRP-CS-INDV-49 / Component 4 - Project Individual Clerk of Works - Fenton, Pending IDA / 49860 Management and Post Consultant Limited 17,000.00 0.00 2019-11-22 2019-11-29 2019-12-20 2020-01-02 2020-06-30 Dauphine and Green Hill Implementation Implementation Support Selection bridges SVG-RDVRP-CS-INDV-47 / Component 4 - Project Individual Pending Engineer and Environmental IDA / 49860 Management and Post Consultant Limited 65,000.00 0.00 2019-11-22 2019-11-22 2019-11-26 2019-12-17 2020-12-31 Implementation Safeguards Officer Implementation Support Selection Page 4 Component 4 - Project Individual SVG-RDVRP-CS-INDV-16C / TF / 16733 Management and Post Consultant Direct 70,000.00 71,244.46 Signed 2019-11-24 2014-04-29 2019-11-24 2019-11-22 2019-11-24 2019-11-29 2019-12-01 2019-12-01 2020-05-29 Project Coordinator-2 Implementation Support Selection SVGRDVRP-CS-INDV-50 / To provide training to technical Component 2 - Regional practitioners, financial Platforms for Hazard and Risk Individual Under institutions and insurance IDA / 54500 Evaluation, and Applications Post Consultant Limited 50,000.00 0.00 2020-03-02 2020-03-07 2020-03-28 2020-05-02 2020-10-29 Implementation companies on the application for Improved Decision Selection and enforcement of building Making codes. SVG-RDVRP-CS-INDV-51 / Individual Specialist geotechnical Component 1 - Prevention IDA / 54500 Post Consultant Limited 30,000.00 0.00 Canceled 2020-04-10 2020-04-15 2020-05-06 2020-05-25 2020-07-06 engineering services including and Adaptation Investments Selection testing Component 4 - Project SVG-RDVRP-CS-DIR-4 / Under IDA / 54500 Management and Post Direct Selection Direct 4,500.00 0.00 2020-10-09 2020-10-26 2020-10-11 2020-10-30 2020-12-31 Assistant Safeguards Officer Implementation Implementation Support Component 4 - Project SVG-RDVRP-CS-DIR-5 / Under IDA / 54500 Management and Post Direct Selection Direct 4,000.00 0.00 2020-10-11 2020-10-15 2020-10-31 2020-12-31 Clerk of Works - Belle Isle Implementation Implementation Support SVG-RDVRP-CS-DIR-6 / Development of standard Component 4 - Project operating procedures and Pending IDA / 54500 Management and Post Direct Selection Direct 15,000.00 0.00 2021-02-26 2021-02-28 2021-03-24 2021-04-23 protocols and assessment for Implementation Implementation Support the upgrade of NEMO's network Page 5