Sample Procurement Plan ( P154908 - Livestock Development Project ( I. General 1. Bank’s approval Date of the procurement Plan September 8, 2016: Revision of Updated Procurement Plan, August 2017] 2. Date of General Procurement Notice: August 24, 2017 3. Period covered by this procurement plan: September 2017- January 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1, 500, All 000 USD 2. NCB (Goods) - None 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 5 million All 5 NCB (Works) Below 5 million None 5. (Non-Consultant Services) Below US$ 1500000 All [Direct Contracts for Goods] Above 1, 500, 000 USD The justification for all Direct Contracts shall be prior reviewed 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] ( to Complete) July 9, 2010 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by to complete 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] To complete 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary - - - - of the ICB (Works) Summary - - - - of the ICB (Goods) Summary - - - = of the NCB (Works) Summary 0.575 2 No Post of the NCB (Goods) Summary - - - - of the ICB (Non- Consultant Services) Summary - - - - of the NCB(Non- Consultant Services) Summary 0,417 1 No Prior With of Direct UN Contracts agency Summary 0,018 1 No Post of Direct Contract III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above 500,000 US $ The justification for single source shall be prior reviewed for all single source contracts 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 0,250 2 Post of number of contracts that will be let under QCBS Summary 720 9 Post CQS of number of contracts that will be let under July 9, 2010 other methods Summary 1500 25 Post CI of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Cameroon : Livestock Development Project PLAN General Information Country: Cameroon Bank’s Approval Date of the Original Procurement Plan: 2017-02-28 Revised Plan Date(s): (comma delineated, leave blank if2022-07-21 none) Project ID: P154908 GPN Date: 2017-08-24 Project Name: Livestock Development Project Loan / Credit No: IDA / Q9910, IDA / 59080 MINISTRY OF LIVESTOCK, FISHERIES AND ANIMAL INDUSTRIES Executing Agency(ies): WORKS Activity Reference No. Procurement Estimate Actual A Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl / Description Component Review Type Method Document Ty d Amount mount ( rt and Recommenda Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe (US$) US$) tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne d CM-MINEPIA-26594-CW-RF Project coordination, man Q / Réfection et aménage Demande de pri Single Stage - On En cours d 2017-09-2 2017-11-2 2017-12- IDA / 59080 agement, communication A posteriori Open - National 6,800.00 0.00 ment des bureaux de l'unit x e Envelope 'exécution 8 4 24 and monitoring é de coordination régional e de Garoua CM-MINEPIA-26602-CW-RF Project coordination, man Q / réfection et aménagem Demande de pri Single Stage - On 2017-09-2 2017-11-1 2017-10-0 2017-12- IDA / 59080 agement, communication A posteriori Open - National 6,800.00 7,864.03 Signé ent de l'unité de coordinati x e Envelope 6 5 5 15 and monitoring on régionale de Douala CM-MINEPIA-26604-CW-RF Q / Réfection et aménage Project coordination, man Demande de pri Single Stage - On 2017-10-0 2017-12-1 2018-05-2 2018-01- ment des bureaux de l'unit IDA / 59080 agement, communication A posteriori Open - National 25,000.00 54,449.22 Achevé x e Envelope 5 2 4 31 é de coordination national and monitoring e et de ceux de l'unité de coordination régionale de Yaoundé. CM-MINEPIA-74121-CW-RF Improvement of Livestock B / Construction de trois (0 Single Stage - On 243,935.4 2018-12-1 2018-09-2 2018-12-1 2019-01-1 2018-11-0 2019-02-1 2018-11-1 2019-03-2 2018-12-1 2019-08- IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 300,000.00 Signé 3) étables de soixante (60 e Envelope 2 4 8 9 8 7 7 9 4 3 21 ery ) génisses gestantes chacu ne à Louguéré CM-MINEPIA-50653-CW-RF B / Construction 3 hangars Improvement of Livestock aménagers avec matériels Single Stage - On 2018-03-1 2018-10-0 2018-03-2 2018-03-2 2018-04-2 2018-05-3 2018-10- IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 134,000.00 0.00 Annulé d'élevage et aliments, pris e Envelope 8 3 3 6 5 0 27 ery e en charge vétérinaires p our le suivi zootechnique e t sanitaire par site CM-MINEPIA-106273-CW- Improvement of Livestock Single Stage - On 2019-03-2 2019-08-0 2019-04-0 2019-05-1 2019-06-1 2019-07-1 2019-11- RFB / Travaux de réhabilita IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 83,500.00 0.00 Annulé e Envelope 9 8 3 5 4 9 16 tion à la station de Bali ery CM-MINEPIA-106272-CW- Improvement of Livestock Single Stage - On 2019-05-3 2019-06-0 2019-06-0 2019-07-1 2019-08-1 2019-09-1 2020-01- RFB / Travaux de réhabilita IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 83,500.00 0.00 Annulé e Envelope 0 7 4 6 5 9 17 tion à la station de Dogba ery CM-MINEPIA-136676-CW- Improvement of Livestock Single Stage - On 533,274.5 2019-10-0 2020-05-1 2019-10-1 2020-05-1 2019-11-1 2020-05-2 2019-12-0 2020-06-3 2019-12-3 2020-08-1 2020-06- RFB / Travaux de réhabilita IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 525,000.00 Signé e Envelope 9 8 4 3 5 2 9 2 0 1 4 28 tion de la station d'élevag ery e de Wakwa CM-MINEPIA-106280-CW- Improvement of Livestock RFB / Travaux de réhabilita Single Stage - On 2019-03-2 2019-09-2 2019-04-0 2019-05-1 2019-06-1 2019-07-1 2019-11- IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 167,000.00 0.00 Annulé tion et construction de bar e Envelope 9 0 3 5 4 9 16 ery rière à la station de Wakw a CM-MINEPIA-136678-CW- Improvement of Livestock Single Stage - On 235,661.3 2019-10-0 2020-05-1 2019-10-1 2020-05-1 2019-11-1 2020-06-1 2019-12-0 2020-06-3 2019-12-3 2021-08-1 2020-06- RFB / Travaux de réhabilita IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 217,000.00 Signé e Envelope 9 8 4 3 5 2 9 2 0 1 4 28 tion de la station d'élevag ery e de Kouden CM-MINEPIA-136682-CW- Improvement of Livestock Single Stage - On 636,718.1 2019-10-0 2020-05-1 2019-10-1 2020-05-1 2019-11-1 2020-05-2 2019-12-0 2020-06-3 2019-12-3 2020-08-1 2020-06- RFB / Travaux de réhabilita IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 620,000.00 Signé e Envelope 1 8 4 3 5 2 9 2 0 1 4 28 tion de la station d'élevag ery e de Louguere CM-MINEPIA-149086-CW- RFQ / Achèvement des tra vaux de construction de tr Improvement of Livestock Demande de pri Single Stage - On 2019-12-0 2019-12-0 2019-12-2 2019-12-1 2020-01- ois étables aménagés pour IDA / 59080 Services Access and Deliv A posteriori Limited 73,333.33 71,631.54 Signé x e Envelope 9 6 3 3 06 la quarantaine des animau ery x dans la station de Lougg uéré, Région du Nord dans le cadre du PRODEL. CM-MINEPIA-161750-CW- Improvement of Pastoral P RFQ / Recrutement d'un pr roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-2 2021-12-0 2022-04- stataire pour la matérialisa IDA / 59080 A posteriori Limited 85,947.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 7 8 07 tion de deux (02) pistes à storal Communities bétail à Tchorké et Malla d ans la Commune de Ngong CM-MINEPIA-161808-CW- Project coordination, man Demande de pri Single Stage - On 2020-06-0 2020-07-2 2020-08- RFQ / Travaux d’Entretien IDA / 59080 agement, communication A posteriori Limited 600.00 0.00 Annulé x e Envelope 3 9 28 et de Nettoyage des burea and monitoring ux à l'UCR Zone 3 CM-MINEPIA-161795-CW- Improvement of Pastoral P Other (with fiel RFQ / Travaux de construc roductivity, Access to Mar Demande de pri Single Stage - On 2022-03-0 2022-04-2 2022-08- IDA / 59080 A posteriori Limited d for explanatio 41,667.00 0.00 Annulé tion 01 forage pastoral à é kets, and Resilience of Pa x e Envelope 1 6 24 n) nergie solaire Bétaré Oya storal Communities T041PRODELUCRZ01 / Tra vaux de Réhabilitation d’u Improvement of Pastoral P n forage pastoral à énergi Other (with fiel roductivity, Access to Mar Demande de pri Single Stage - On 2022-02-2 2022-04-1 2022-08- e solaire et construction d’ IDA / 59080 A posteriori Limited d for explanatio 9,400.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 1 8 16 un abreuvoir à Tchabal Ba n) storal Communities ouro, Commune de Ngaou ndere III, Département de l a Vina, Région de l’Adama oua T020PRODELUCRZ01 / Tra vaux de Construction d'un Improvement of Pastoral P Other (with fiel parc d’intervention zoo sa roductivity, Access to Mar Demande de pri Single Stage - On 2022-03-2 2022-05-1 2022-09- IDA / 59080 A posteriori Limited d for explanatio 24,500.00 0.00 Annulé nitaire dans la localité de kets, and Resilience of Pa x e Envelope 9 8 15 n) Makilingaï, Commune de T storal Communities okombéré, Département d u Mayo Sava, Région de l'E xtrême- Nord T036PRODELUCRZ01 / Tra vaux de Réalisation de troi Improvement of Pastoral P Other (with fiel s forages pastoraux a éner roductivity, Access to Mar Demande de pri Single Stage - On 2022-03-0 2022-04-2 2022-08- IDA / 59080 A posteriori Limited d for explanatio 125,551.00 0.00 Annulé gie solaire dans les localité kets, and Resilience of Pa x e Envelope 1 6 24 n) s de la Commune de Ngao storal Communities undal, Département du DJ EREM, Région de L’ADAMA OUA T019PRODELUCRZ01 / Tra vaux de Matérialisation de Improvement of Pastoral P Other (with fiel deux pistes a bétail dans l roductivity, Access to Mar Demande de pri Single Stage - On 2019-09-1 2019-11-0 2020-03- IDA / 59080 A posteriori Limited d for explanatio 7,500.00 0.00 Annulé es localités de la Commun kets, and Resilience of Pa x e Envelope 3 8 07 n) e de Tokombéré, Départe storal Communities ment du Mayo Sava, Régio n de l'Extrême-Nord T025PRODELUCRZ01 / Tra vaux de Construction d'un Improvement of Pastoral P parc d’intervention zoo sa Other (with fiel roductivity, Access to Mar Demande de pri Single Stage - On 2019-09-1 2019-11-0 2020-03- nitaire dans la localité de IDA / 59080 A posteriori Limited d for explanatio 24,500.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 6 5 04 Salan dans la Commune d n) storal Communities e LOGONE BIRNI Départe ment du Logone Chari, Ré gion de l’Extrême-Nord. T026PRODELUCRZ01 / Tra vaux de Construction de d Improvement of Pastoral P Other (with fiel eux forages pastoraux à é roductivity, Access to Mar Demande de pri Single Stage - On 2022-02-0 2022-03-2 2022-07- IDA / 59080 A posteriori Limited d for explanatio 83,701.00 0.00 Annulé nergie solaire dans les loc kets, and Resilience of Pa x e Envelope 1 9 27 n) alités de la Commune de L storal Communities OGONE BIRNI Départeme nt du Logone Chari, Régio n de l’Extrême-Nord. T030PRODELUCRZ01 / tra vaux de Matérialisation de Improvement of Pastoral P trois pistes a bétail dans l roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 42,300.00 0.00 Annulé es localités de la Commun kets, and Resilience of Pa x e Envelope 2 7 27 e de MEIGANGA, Départem storal Communities ent du Mbéré, Région de l’ ADAMAOUA T001PRODELUCRZ01 / Tra vaux de Matérialisation de Support to livestock value Demande de pri Single Stage - On 2021-10-0 2021-11-3 2022-04- deux pistes a bétail dans l IDA / 59080 A posteriori Limited 30,676.00 0.00 Annulé chains development x e Envelope 5 0 29 es localités de la Commun e de Lagdo, Département de la Bénoué, Région du N ord. CM-MINEPIA-128475-CW- RFQ / Travaux de matériali Improvement of Pastoral P sation d’une piste a bétail roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-2 2021-10-2 2022-02- IDA / 59080 A posteriori Limited 31,806.00 0.00 Annulé dans la commune de betar kets, and Resilience of Pa x e Envelope 7 2 19 eoya : kombo-koro-bangbe storal Communities l-zembe-borongo-longa-ma li-betare oya-ndokayo. T035PRODELUCRZ01 / Co nstruction de trois parcs d’ Improvement of Pastoral P intervention zoo sanitaire roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-3 2021-11-1 2022-03- IDA / 59080 A posteriori Limited 73,400.00 0.00 Annulé dans les localités de la Co kets, and Resilience of Pa x e Envelope 0 9 19 mmune de Ngaoundal, Dé storal Communities partement du DJEREM, Ré gion de L’ADAMAOUA T007PRODELUCRZ01 / Tra vaux de Matérialisation de Support to livestock value Demande de pri Single Stage - On 2021-10-0 2021-11-3 2022-04- deux pistes a bétail dans l IDA / 59080 A posteriori Limited 32,580.00 0.00 Annulé chains development x e Envelope 5 0 29 es localités de la Commun e de GUIDER, Départemen t du Mayo Louti, Région du Nord. T002PRODELUCRZ01 / Tra vaux de Construction de d eux parcs d’intervention z Support to livestock value Demande de pri 2021-10-0 2021-11-3 2022-04- IDA / 59080 A posteriori 54,650.00 0.00 Annulé oo sanitaire avec latrines chains development x 5 0 29 VIP dans les localités de la Commune de Lagdo Dépar tement de la Bénoué, Régi on du Nord T023PRODELUCRZ01 / Tra vaux de Construction de d Improvement of Pastoral P eux parcs d’intervention z roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-3 2021-10-2 2022-02- IDA / 59080 A posteriori Limited 48,900.00 0.00 Annulé oo sanitaire dans les locali kets, and Resilience of Pa x e Envelope 1 0 17 tés de la Commune de Yag storal Communities oua, Département du May o Danay, Région du l'Extr ême-Nord. T044PRODELUCRZ02 / Tra Improvement of Pastoral P Demande de pri Single Stage - On 2021-08-3 2021-10-2 2022-02- vaux de construction d'un IDA / 59080 roductivity, Access to Mar A posteriori Limited 22,980.00 0.00 Annulé x e Envelope 1 0 17 e boucherie à Ngoura II kets, and Resilience of Pa storal Communities T037PRODELUCRZ01 / Tra vaux de Matérialisation de Improvement of Pastoral P deux pistes a bétail dans l roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 31,000.00 0.00 Annulé es localités de la Commun kets, and Resilience of Pa x e Envelope 2 7 27 e de NGAOUNDERE III, Dép storal Communities artement de la VINA, Régio n de L’ADAMAOUA T017PRODELUCRZ01 / Tra vaux de Construction d'un Improvement of Pastoral P parc d’intervention zoo sa roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-3 2021-10-2 2022-02- IDA / 59080 A posteriori Limited 24,446.00 0.00 Annulé nitaire dans la localité de kets, and Resilience of Pa x e Envelope 1 0 17 Boboyo dans la Commune storal Communities de Kaélé Département du Mayo Kani, Région de l'Ext rême-Nord T057PRODELUCRZ2+ / Tr avaux de construction d’u Improvement of Pastoral P n parc d’intervention zoo s roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-3 2021-10-1 2022-02- IDA / 59080 A posteriori Limited 27,360.00 0.00 Annulé anitaire accompagne d’un kets, and Resilience of Pa x e Envelope 0 9 16 bloc toilettes vip equipe de storal Communities deux (02) cellules dans la l ocalite de zambo, commun e de garoua boulai. T010PRODELUCRZ01 / Tra Improvement of Pastoral P vaux de Matérialisation de roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- deux pistes à bétail dans l IDA / 59080 A posteriori Limited 41,460.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 2 7 27 es localités de Commune d storal Communities e Garoua3ème, Départem ent de la Bénoué, Région d u Nord. T054PRODELUCRZ02 / Tra Improvement of Pastoral P vaux de construction d’un roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 22,946.00 0.00 Annulé hangar pour boucherie da kets, and Resilience of Pa x e Envelope 5 4 24 ns la localitede garoua bou storal Communities lai centre T033PRODELUCRZ01 / Tra vaux de Réalisation de troi Improvement of Pastoral P s forages pastoraux a éner roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-2 2021-10-1 2022-02- IDA / 59080 A posteriori Limited 125,600.00 0.00 Annulé gie solaire dans les localité kets, and Resilience of Pa x e Envelope 3 8 15 s de de la Commune de M storal Communities EIGANGA, Département du Mbéré, Région de l’ADAMA OUA T042PRODELUCRZ02 / Tra Improvement of Pastoral P vaux de construction d'un roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 27,360.00 0.00 Annulé parc de d’intervention zoo kets, and Resilience of Pa x e Envelope 2 1 21 sanitaire equipé d’un bloc l storal Communities atrine dans la localité de FI O T004PRODELUCRZ01 / Tra vaux den Matérialisation d Support to livestock value Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-04- e deux pistes a bétail dans IDA / 59080 A posteriori Limited 55,880.00 0.00 Annulé chains development x e Envelope 2 1 20 les localités de la Commun e de NGONG, Départemen t de la Bénoué, Région du Nord. T029PRODELUCRZ01 / Tra vaux de Réalisation de troi Improvement of Pastoral P s forages pastoraux a éner roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 125,550.00 0.00 Annulé gie solaire dans les localité kets, and Resilience of Pa x e Envelope 4 9 29 s de la Commune de BELE storal Communities L, Département de la VINA , Région de L’ADAMAOUA Page 1 T031PRODELUCRZ01 / Tra vaux de Construction de d Improvement of Pastoral P eux parcs d’intervention z roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-2 2021-11-1 2022-03- IDA / 59080 A posteriori Limited 48,800.00 0.00 Annulé oo sanitaire dans les locali kets, and Resilience of Pa x e Envelope 7 6 16 tés de la Commune de MEI storal Communities GANGA, Département du Mbéré, Région de l’ADAMA OUA T012PRODELUCRZ01 / Tra vaux de Construction de tr Improvement of Pastoral P ois forages pastoraux à én roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-3 2021-10-2 2022-02- IDA / 59080 A posteriori Limited 125,551.00 0.00 Annulé ergie solaire dans les aires kets, and Resilience of Pa x e Envelope 1 6 23 de pâturage la Commune storal Communities de Garoua3ème, Départe ment de la Bénoué, Région du Nord. T006PRODELUCRZ01 / Tra vaux de Construction de d eux forages pastoraux à é Support to livestock value Demande de pri Single Stage - On 2021-10-0 2021-11-3 2022-04- IDA / 59080 A posteriori Limited 83,701.00 0.00 Annulé nergie solaire dans les aire chains development x e Envelope 5 0 29 s de pâturage de la Comm une de Lagdo, Départeme nt de la Bénoué, Région du Nord. T018PRODELUCRZ01 / Tra vaux de Construction d'un Improvement of Pastoral P forage pastoral à énergie s roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-3 2022-03- olaire et d’une mini adduct IDA / 59080 A posteriori Limited 41,850.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 5 0 30 ion d'eau dans les aires de storal Communities pâturages de Boboyo, Com mune de Kaélé Départeme nt du Mayo Kani, Région d e l'Extrême-Nord. T058PRODELUCRZ2+ / Tr Improvement of Pastoral P avaux de matérialisation d roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- ’une piste a bétail dans la IDA / 59080 A posteriori Limited 32,908.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 1 6 24 commune de garoua boula storal Communities i-bindiba-mikala, bindiba-s ama, 50 km, tégion de l'Es t T015PRODELUCRZ01 / Tra vaux de Construction de tr Improvement of Pastoral P ois forages pastoraux à én roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 125,551.00 0.00 Annulé ergie solaire dans les locali kets, and Resilience of Pa x e Envelope 4 9 27 tés Commune de Pette, Dé storal Communities partement du Diamaré, Ré gion de l'Extrême-Nord T045PRODELUCRZ02 / Tra Improvement of Pastoral P vaux de Matérialisation de roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 27,400.00 0.00 Annulé deux pistes a bétail dans l kets, and Resilience of Pa x e Envelope 1 6 26 es localités de Batouri-Nya storal Communities bi-Timangolo T024PRODELUCRZ01 / Tra vaux de Construction de d Improvement of Pastoral P eux forages pastoraux à é roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- nergie solaire dans les aire IDA / 59080 A posteriori Limited 83,701.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 2 7 27 s de pâturage de la Comm storal Communities une de Yagoua, Départem ent du Mayo Danay, Régio n du l'Extrême-Nord. T013PRODELUCRZ01 / Tra vaux de Matérialisation de Improvement of Pastoral P trois pistes à bétail dans l roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 42,000.00 0.00 Annulé es localités de la Commun kets, and Resilience of Pa x e Envelope 2 7 27 e de Pette, Département d storal Communities e la Diamaré, Région de l'E xtrême-Nord. T053PRODELUCRZ02 / Tra vaux de construction d’un Improvement of Pastoral P e aire d’abattage avec pou roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 61,667.00 0.00 Annulé r annexe une borne fontai kets, and Resilience of Pa x e Envelope 5 4 24 ne, d’unbloc toilette+douc storal Communities he d’un parc d’attente et d ’un local pour gardien a yo ko sire CM-MINEPIA-161758-CW- RFQ / Travaux de construc Improvement of Pastoral P tion de 03 parcs zoo sanita roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-05- IDA / 59080 A posteriori Limited 105,116.00 0.00 Annulé ires à Saltaka, Madjele et kets, and Resilience of Pa x e Envelope 7 7 07 Beka; un forage à énergie storal Communities solaire à Saltaka dans la C ommune de Ngaoundéré 3 ème T043PRODELUCRZ02 / Tra vaux de construction d'un Improvement of Pastoral P e aire d’abattage equipé d’ roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-0 2021-11-2 2022-03- IDA / 59080 A posteriori Limited 70,725.00 0.00 Annulé une borne fontaine, d’un b kets, and Resilience of Pa x e Envelope 5 4 24 loc toilette+douche, d’un storal Communities parc d’attente avec un loc al pour gardien à Gadji T055PRODELUCR2 / Trava ux de construction d’un for Improvement of Pastoral P age pastoral equipe de troi roductivity, Access to Mar Demande de pri Single Stage - On 2021-07-3 2021-09-2 2022-01- s (03) abreuvoirs et d’un bl IDA / 59080 A posteriori Limited 76,693.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 1 5 23 oc latrines vip a deux (02) storal Communities cellules dans la localite de mombal et mborguene), c ommune de garoua boulai, T009PRODELUCRZ01 / Tra vaux de Construction de tr Improvement of Pastoral P ois forages pastoraux à én roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-02- IDA / 59080 A posteriori Limited 125,551.00 0.00 Annulé ergie solaire dans les aires kets, and Resilience of Pa x e Envelope 4 9 26 de pâturage de la Commu storal Communities ne de Guider, Départemen t du Mayo Louti, Région du Nord. T038PRODELUCRZ01 / Tra vaux de Construction de q Improvement of Pastoral P uatre parcs d’intervention roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 97,790.00 0.00 Annulé zoo sanitaire dans les local kets, and Resilience of Pa x e Envelope 4 3 21 ités de la Commune de NG storal Communities AOUNDERE III, Départeme nt de la VINA, Région de L’ ADAMAOUA CM-MINEPIA-161748-CW- RFQ / Construction de deu Improvement of Pastoral P x (02) forages équipés de roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-07- panneaux solaires à Laind IDA / 59080 A posteriori Limited 111,717.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 7 7 06 é Gouna et Mayo Bocki; et, storal Communities deux (02) parcs zoo sanitai res à Katchala Boté et Hou ro Doré dans la Commune de Lagdo CM-MINEPIA-161762-CW- RFQ / Travaux de construc Improvement of Pastoral P tion de 03 forages patorau roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-1 2021-12-1 2022-04- IDA / 59080 A posteriori Limited 116,004.00 0.00 Annulé x à énérgie solaires dans l kets, and Resilience of Pa x e Envelope 7 2 11 es localités de Meidougou, storal Communities Mbarang et Fada dans la C ommune de Meiganga CM-MINEPIA-161737-CW- RFQ / Construction de deu Improvement of Pastoral P x (02) forages équipés de roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-07- IDA / 59080 A posteriori Limited 116,004.00 0.00 Annulé panneaux solaires et de de kets, and Resilience of Pa x e Envelope 7 7 06 ux (02) parcs zoo sanitaire storal Communities s à Djamous II et Dambe d ans la Commune de Goulfe y CM-MINEPIA-161781-CW- Improvement of Pastoral P RFQ / Construction de deu roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-1 2021-12-2 2022-04- IDA / 59080 A posteriori Limited 114,474.00 0.00 Annulé x (02) forages dont un (01) kets, and Resilience of Pa x e Envelope 8 9 28 Gadji et l'autre à Fio dans l storal Communities a Commune Batouri CM-MINEPIA-161775-CW- RFQ / Construction d'un (0 Improvement of Pastoral P 1) forage à énergie solaire roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2021-12-2 2022-04- à l'abatoir de Banyo ville, IDA / 59080 A posteriori Limited 113,845.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 7 2 21 et de trois (03) parcs d'int storal Communities ervention zoo sanitaire à Mayo Forou, Bami et à Mb amti-Djoumbaré dans la C ommune de Banyo CM-MINEPIA-161719-CW- RFQ / travaux de construct Improvement of Pastoral P ion d'un parc d'interventio roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-1 2021-12-2 2022-04- IDA / 59080 A posteriori Limited 98,108.00 0.00 Annulé n zoo saniatire à Salan et kets, and Resilience of Pa x e Envelope 7 8 27 02 forages pastoraux à Go storal Communities ulma et Dilga Arabe dans l a Commune de Logone Bir ni CM-MINEPIA-161738-CW- RFQ / Travaux de construc Improvement of Pastoral P tion de deux parx d'interve roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-1 2021-12-2 2022-04- ntion zoo sanitaires à Koza IDA / 59080 A posteriori Limited 116,250.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 6 7 26 centre et à Gaboua; constr storal Communities uction d'un forage pastoral équipé à énergie solaire à Morgo dans la Commune d e Koza CM-MINEPIA-160990-CW- RFQ / Construction de deu Improvement of Pastoral P x (02) parcs zoo sanitaires roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-07- à Tchaba Tchaba et Baka; IDA / 59080 A posteriori Limited 106,922.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 7 7 06 puis, de deux (02) forages storal Communities équipés de panneaux solai res solaires à Kotraba et M beleché dans la Commune de Tokombéré CM-MINEPIA-161767-CW- RFQ / Construction de trois (03) parcs d'intervention z Improvement of Pastoral P oo sanitaires à Darang, Ng roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-05- aouhora 1 et Mayo Daneye IDA / 59080 A posteriori Limited 121,782.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 4 4 04 l et Construction de deux ( storal Communities 02) forages pastoraux à én érgie solaire à Mayo Dane yel et à Ngaouhora 1 dans la Commune de Ngaoundé ré 2ème CM-MINEPIA-161747-CW- RFQ / Travaux de construc Improvement of Pastoral P tion 02 parcs zoo sanitaire roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-07- IDA / 59080 A posteriori Limited 105,265.00 0.00 Annulé s à Bang et Koraké; 02 for kets, and Resilience of Pa x e Envelope 7 7 06 ages solaires à Ouro Bara storal Communities et Boko Doroum dans la C ommune de Guider CM-MINEPIA-161736-CW- Improvement of Pastoral P RFQ / Construction de deu roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2021-12-2 2022-04- x (02) forages pastoraux é IDA / 59080 A posteriori Limited 116,250.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 7 2 21 quipés de pompes à énerg storal Communities ie solaire à Tolkomari et à Amchidé dans la Commun e de Kolofata CM-MINEPIA-161778-CW- RFQ / Construction de deu Improvement of Pastoral P x (02) forages équipés d'u roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-1 2021-12-2 2022-06- IDA / 59080 A posteriori Limited 109,207.00 0.00 Annulé n dispositif solaire ainsi qu kets, and Resilience of Pa x e Envelope 8 9 27 e deux parcs zoo sanitaire storal Communities s à Mbitom et à Kongolo d ans la Commune Bétaré-O ya CM-MINEPIA-161726-CW- Improvement of Pastoral P RFQ / Travaux de construc roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2021-12-1 2022-06- tion 02 parcs zoo sanitaire IDA / 59080 A posteriori Limited 80,833.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 7 1 09 s à Ouro Abba et Toupka; storal Communities 01 forage à Dabbam dans la Commune de Petté CM-MINEPIA-161742-CW- RFQ / Travaux de construc Improvement of Pastoral P tion de 04 parcs d'interven roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-05- IDA / 59080 A posteriori Limited 113,845.00 0.00 Annulé tion zoo sanitaires à Guissi kets, and Resilience of Pa x e Envelope 7 7 07 a, Guidinding, Toukso et D storal Communities adjanka dans la Commune de Doukoula Kar-Hay CM-MINEPIA-161755-CW- Improvement of Pastoral P RFQ / travaux de construct roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-1 2021-12-2 2022-06- ion de 02 forages pastorar IDA / 59080 A posteriori Limited 105,116.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 6 7 25 aux et 02 parcs d'intervent storal Communities ion zoo sanitaires dans la c ommune Rey-Bouba CM-MINEPIA-161754-CW- Improvement of Pastoral P RFQ / Construction de deu roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-07- IDA / 59080 A posteriori Limited 102,389.00 0.00 Annulé x (02) parcs d'intervention kets, and Resilience of Pa x e Envelope 7 7 06 zoo sanitaires et deux (02) storal Communities forages pastoraux à Bibém i CM-MINEPIA-161773-CW- RFQ / Travaux de construc Improvement of Pastoral P tion de 03 parc d'intervent roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-1 2021-12-2 2022-06- IDA / 59080 A posteriori Limited 119,055.00 0.00 Annulé ion zoo sanitaires à Tongo, kets, and Resilience of Pa x e Envelope 6 7 25 Ngongon 3 et Tibati ville ai storal Communities nsi que 01 forage à énergi e solaire à Djombi dans la Commune de Tibati CM-MINEPIA-161734-CW- Improvement of Pastoral P RFQ / Travaux de construc roductivity, Access to Mar Demande de pri Single Stage - On 2021-07-3 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 110,138.00 0.00 Annulé tion des infrastructures pa kets, and Resilience of Pa x e Envelope 1 5 23 storales dans la Commune storal Communities de Kaélé CM-MINEPIA-161745-CW- RFQ / Extension de l'aire d Improvement of Pastoral P e pâturage de Djalingo et roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-1 2021-12-1 2022-06- IDA / 59080 A posteriori Limited 90,256.00 0.00 Annulé construction d'un forage s kets, and Resilience of Pa x e Envelope 6 1 09 olaire et d'un parc zoo sani storal Communities taire dans la Commune d e Garoua 3ème CM-MINEPIA-161731-CW- RFQ / Recrutement d'un pr estataire pour la sécurisati Improvement of Pastoral P on et l'aménagement des roductivity, Access to Mar Demande de pri 2021-10-3 2022-01-1 2022-07- IDA / 59080 A posteriori 113,738.00 0.00 Annulé aires de pâturages de Mou kets, and Resilience of Pa x 0 0 09 ri et de Djafgadji; puis Mat storal Communities érialisation des pistes à bé tail de l'aire de pâturage d e Mouri et Djafgadi dans la Commune de Yagoua T060PRODELUCRZ2+ / Tr Improvement of Pastoral P avaux de construction d’u roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- n forage pastoral équipé d IDA / 59080 A posteriori Limited 35,000.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 4 9 27 e deux abreuvoirs dans la l storal Communities ocalité de gbiti dans la co mmune de Kette Page 2 T0256PRODELUCRZ2+ / T Improvement of Pastoral P ravaux de construction d’u roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- n forage pastoral equipe d IDA / 59080 A posteriori Limited 35,000.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 4 9 27 e deux (02) abreuvoirs dan storal Communities s la localite de yoko sire, C ommune de Garoua-Boulaï T016PRODELUCRZ01 / Tra vaux de Matérialisation de Improvement of Pastoral P trois pistes a bétail dans le roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 20,058.00 0.00 Annulé s localités de la Commune kets, and Resilience of Pa x e Envelope 4 9 27 de Kaelé, Département du storal Communities Mayo Kani, Région de l'Ext rême Nord. T049PRODELUCRZ02 / Tra Improvement of Pastoral P vaux de construction d’un roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- e aire d’abattage avec pou IDA / 59080 A posteriori Limited 61,667.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 2 1 19 r annexe un bloc toilette+ storal Communities douche parc d’attente et d ’un localpour gardien a nd okayo T022PRODELUCRZ01 / Tra vaux de Matérialisation de Improvement of Pastoral P sept (07) pistes a bétail da roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 36,800.00 0.00 Annulé ns les localités de la Com kets, and Resilience of Pa x e Envelope 1 6 24 mune de Yagoua, Départe storal Communities ment du Mayo Danay, Régi on de l'Extrême-Nord T051PRODELUCRZ02 / Tra Improvement of Pastoral P vaux de construction de d roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- eux forages pastoraux equ IDA / 59080 A posteriori Limited 70,000.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 4 9 27 ipes de deux abreuveoirs d storal Communities ans les localites de ndokay o et borongo T032PRODELUCRZ01 / Tra vaux de Réhabilitation d’u Improvement of Pastoral P n parc d’intervention zoo s roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 7,400.00 0.00 Annulé anitaire dans les localités kets, and Resilience of Pa x e Envelope 4 3 21 de la Commune de MEIGA storal Communities NGA, Département du Mbé ré, Région de l’ADAMAOUA T034PRODELUCRZ01 / Tra vaux de Matérialisation de Improvement of Pastoral P deux pistes a bétail dans l roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 17,300.00 0.00 Annulé es localités de la Commun kets, and Resilience of Pa x e Envelope 1 6 24 e de Ngaoundal, Départem storal Communities ent du DJEREM, Région de L’ADAMAOUA T047PRODELUCRZ02 / Tra Improvement of Pastoral P vaux devConstruction de d roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- eux forages pastoraux à é IDA / 59080 A posteriori Limited 35,000.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 3 8 26 nergie solaire équipés de 0 storal Communities 2 abreuvoirs dans les local ités de Gadji et Mobé T059PRODELUCRZ2+ / Tr avaux de construction d’u Improvement of Pastoral P n marché a bétail constitu roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-2 2021-10-1 2022-02- IDA / 59080 A posteriori Limited 84,530.00 0.00 Annulé e d’un parc a bétail, d’un h kets, and Resilience of Pa x e Envelope 4 3 10 angar, d’un quai d’embarq storal Communities uement et d’un bloc toilett e vip dans la localité de gb iti CM-MINEPIA-161752-CW- Improvement of Pastoral P RFQ / Travaux de construc roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-2 2021-10-2 2022-02- IDA / 59080 A posteriori Limited 105,116.00 0.00 Annulé tion des infrastructures pa kets, and Resilience of Pa x e Envelope 9 4 21 storales dans la Commune storal Communities de Mayo-Oulo CM-MINEPIA-161756-CW- Improvement of Pastoral P RFQ / Travaux de construc roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-03- IDA / 59080 A posteriori Limited 108,470.00 0.00 Annulé tion des infrastructures pa kets, and Resilience of Pa x e Envelope 4 9 28 storales dans la Commune storal Communities de Mayo Hourna (Barnaké) T048PRODELUCRZ02 / Tra Improvement of Pastoral P vaux de construction d’un roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- e aire d’abattage avec pou IDA / 59080 A posteriori Limited 61,667.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 4 3 21 r annexe un bloc toilette+ storal Communities douche d’un parc d’attent e et d’un local pour gardie n a borongo T050PRODELUCRZ02 / tra Improvement of Pastoral P vaux de construction d’un roductivity, Access to Mar Demande de pri Single Stage - On 2021-07-2 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 27,360.00 0.00 Annulé parc d’intervention zoo sa kets, and Resilience of Pa x e Envelope 8 2 20 nitaire equipe de toilette vi storal Communities p dans la localite de betar e oya CM-MINEPIA-161764-CW- RFQ / Construction de deu Improvement of Pastoral P x 02 forages à énergie sol roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-3 2021-12-2 2022-06- IDA / 59080 A posteriori Limited 108,470.00 0.00 Annulé aire à Goundjel et Tello; de kets, and Resilience of Pa x e Envelope 0 5 23 ux (02) parcs zoo saniatire storal Communities s à Mayo Badi et Selat-Djat ou dans la Commune de B élel T021PRODELUCRZ01 / Tra vaux Construction de deux Improvement of Pastoral P forages pastoraux à énergi roductivity, Access to Mar Demande de pri Single Stage - On 2021-07-3 2021-09-2 2022-01- e solaire dans les aires de IDA / 59080 A posteriori Limited 83,701.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 1 5 23 pâturage de la Commune storal Communities de Tokombéré,Départeme nt du Mayo Sava, Région d e l'Extrême- Nord CM-MINEPIA-161743-CW- RFQ / Construction de trois Improvement of Pastoral P (03) parcs zoo sanitaires à roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-3 2022-01-1 2022-07- IDA / 59080 A posteriori Limited 127,197.00 0.00 Annulé Maporé, Domba et Dongro kets, and Resilience of Pa x e Envelope 0 0 09 us; deux 02 forages solaire storal Communities s à Dziguilao II et Danhou à dans la Commune de Dzi guilao CM-MINEPIA-161783-CW- Improvement of Pastoral P RFQ / Construction de deu roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-2 2021-12-1 2022-04- x (02) forages pastoraux e IDA / 59080 A posteriori Limited 113,587.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 9 0 09 t de deux (02) parcs à Bo storal Communities ubara et Timangolo dans l a Commune Ketté CM-MINEPIA-161766-CW- RFQ / Construction de deu Improvement of Pastoral P x (02) forages et de deux ( roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-3 2022-01-1 2022-07- IDA / 59080 A posteriori Limited 116,250.00 0.00 Annulé 02) parcs zoo sanitaires à kets, and Resilience of Pa x e Envelope 0 0 09 Labaré Modibo, dans le Ma storal Communities yo Wandou et Mayo Tignèr e dans la Commune de Tig nère T005PRODELUCRZ01 / Tra vaux de Construction de d eux parcs d’intervention z Support to livestock value Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 54,650.00 0.00 Annulé oo sanitaire dans les locali chains development x e Envelope 2 7 25 tés de la Commune de Ng ong Département de la Bé noué, Région du Nord T046PRODELUCRZ02 / Tra vaux de Construction d’un Improvement of Pastoral P marché à bétail constitué roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 84,530.00 0.00 Annulé d’un parc à bétail, d’un ha kets, and Resilience of Pa x e Envelope 3 2 20 ngar et d’un quai d’embar storal Communities quement et d’un bloc toile tte VIP dans la localité de MOBE T014PRODELUCRZ01+ / T ravaux de Construction de Improvement of Pastoral P trois parcs d’intervention z roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 73,400.00 0.00 Annulé oo sanitaire dans les locali kets, and Resilience of Pa x e Envelope 3 8 26 tés de la commune de Pett storal Communities e Département du Diamar é, Région de l’Extrême-Nor d T003PRODELUCRZ01 / Tra vaux de Construction de d eux forages pastoraux à é Support to livestock value Demande de pri Single Stage - On 2020-06-0 2020-07-2 2020-12- IDA / 59080 A posteriori Limited 83,701.00 0.00 Annulé nergie solaire dans les loc chains development x e Envelope 3 3 20 alités de la Commune de L agdo, Département de la B énoué, Région du Nord. T061PRODEUCRZ2 / Trava Improvement of Pastoral P ux de construction de 03 h roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-0 2021-10-2 2022-02- IDA / 59080 A posteriori Limited 68,837.00 0.00 Annulé angars pour boucherie dan kets, and Resilience of Pa x e Envelope 4 4 21 s les localites de kette cen storal Communities tre boubara et gbiti T027PRODELUCRZ01 / Tra Improvement of Pastoral P vaux de Matérialisation d’u roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-1 2021-11-1 2022-03- ne piste à bétail dans les l IDA / 59080 A posteriori Limited 42,246.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 5 0 10 ocalités de la Commune d storal Communities e BELEL, Département de l a VINA, Région de l’ADAMA OUA T028PRODELUCRZ01 / Tra vaux de Construction de d Improvement of Pastoral P eux parcs de vaccination d roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-1 2021-11-1 2022-03- IDA / 59080 A posteriori Limited 48,900.00 0.00 Annulé ans les localités de la Co kets, and Resilience of Pa x e Envelope 5 0 10 mmune de BELEL, Départe storal Communities ment de la VINA, Région d e L’ADAMAOUA T011PRODELUCRZ01 / Tra vaux de Construction de d Improvement of Pastoral P eux parcs d’intervention z roductivity, Access to Mar Demande de pri Single Stage - On 2019-09-0 2019-10-3 2020-02- IDA / 59080 A posteriori Limited 54,646.00 0.00 Annulé oo sanitaire dans les locali kets, and Resilience of Pa x e Envelope 4 0 27 tés de la Commune de Gar storal Communities oua 3ème, Département d e la Bénoué, Région du No rd. T039PRODELUCRZ01 / Ré habilitation de deux (02) p Improvement of Pastoral P arcs d’intervention zoo san roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-2 2021-11-1 2022-03- IDA / 59080 A posteriori Limited 14,300.00 0.00 Annulé itaire dans les localités de kets, and Resilience of Pa x e Envelope 9 8 18 la Commune de NGAOUND storal Communities ERE III, Département de la Vina, Région de l’Adamaou a CM-MINEPIA-161761-CW- RFQ / Construction de deu Improvement of Pastoral P x (02) parcs d'intervention roductivity, Access to Mar Demande de pri Single Stage - On 2021-10-2 2022-01-0 2022-05- zoo sanitaires à Ngalbidie IDA / 59080 A posteriori Limited 102,389.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 7 7 07 et à Pangar et de deux for storal Communities ages pastoraux à Danfili et Ngaoundal-Gare dans la C ommune de Ngaoundal T040PRODELUCRZ01 / Tra vaux de Réalisation d’un f Improvement of Pastoral P orage pastoral à énergie s roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-3 2021-10-2 2022-02- IDA / 59080 A posteriori Limited 41,850.00 0.00 Annulé olaire dans la localité de T kets, and Resilience of Pa x e Envelope 1 6 23 CHABBAL DJALINGO, Com storal Communities mune de NGAOUNDERE III, Département de la VINA, R égion de l’Adamaoua CM-MINEPIA-161779-CW- Improvement of Pastoral P RFQ / Travaux de construc roductivity, Access to Mar Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01- IDA / 59080 A posteriori Limited 103,898.00 0.00 Annulé tion des infrastructures pa kets, and Resilience of Pa x e Envelope 4 9 27 storales dans la Commune storal Communities Garoua-Boulaï CM-MINEPIA-130165-CS-C Improvement of Livestock Single Stage - On 2019-09-0 2020-04-1 2019-09-0 2019-10-2 2019-11-1 2019-12-2 2020-06- QS / Travaux de réhabilitat IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 167,000.00 0.00 Annulé e Envelope 3 8 8 0 9 4 21 ion de la station de Lougu ery éré CM-MINEPIA-106275-CW- Improvement of Livestock RFB / Travaux de réhabilita Single Stage - On 2019-03-2 2020-05-2 2019-04-0 2019-05-1 2019-06-1 2019-07-1 2019-11- IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 167,000.00 0.00 Annulé tion et construction de bar e Envelope 9 9 3 5 4 9 16 ery rière à la station de Lougu éré CM-MINEPIA-161806-CW- Project coordination, man RFQ / Travaux d’Aménage Demande de pri Single Stage - On 2021-08-0 2021-09-2 2021-11- IDA / 59080 agement, communication A posteriori Limited 3,333.00 0.00 Annulé ment d’une salle abritant l x e Envelope 4 9 13 and monitoring e Serveur et les Équipeme nts Internet à l'UCR Zone 3 CM-MINEPIA-127188-CW- Improvement of Livestock Single Stage - Tw 2019-09-2 2020-05-1 2019-10-0 2019-11-1 2020-06-1 2020-01-2 2020-02-2 2020-08- RFB / Travaux réhabilitatio IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 167,000.00 0.00 Annulé o Envelope 6 1 1 2 9 5 9 27 n et construction barrière ery à la station de kouden National Procur CM-MINEPIA-238109-CW- Improvement of Livestock ement Docume Single Stage - On 2021-07-3 2021-08-0 2021-09-1 2021-10-1 2021-11-1 2022-01- RFB / travaux d'aménage IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National nt - 1 Envelope 583,333.00 0.00 Annulé e Envelope 0 4 5 5 9 18 ment du site de la foire ery process (Non B ank-SPD) CM-MINEPIA-161804-CW- RFQ / Travaux d’aménage ment des bureaux de l’UC Project coordination, man Other (with fiel R 2 (fabrication et pose de Demande de pri Single Stage - On 2020-07-2 2020-09-2 2020-11- IDA / 59080 agement, communication A posteriori Limited d for explanatio 6,916.67 0.00 Annulé s meubles de rangement d x e Envelope 9 3 07 and monitoring n) ans 3 bureau de la zone 2 Coordonnateur Régional, R esponsables des ressource s pastorales et chaine de v aleurs CM-MINEPIA-215679-CW- Improvement of Livestock Other (with fiel RFB / ALLOTEMENT , PARC Open - Internatio Single Stage - On 2021-07-1 2021-07-1 2021-08-3 2021-09-1 2021-10-1 2022-02- IDA / 59080 Services Access and Deliv A posteriori Appel d'offres d for explanatio 224,299.00 0.00 Annulé ELLISATION DES STATIONS nal e Envelope 4 9 0 3 8 15 ery n) ET ADDUCTION D'EAU STA TION GOODS Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amou Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) nt (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-MINEPIA-8656-GO-UN / Acquisition de quatre vé hicules TOYOTA 4 X4 Hi-Lu Passation de m Project coordination, man x Pick Up. Un véhicule 4X4 archés auprès d 2017-02-2 2017-03-0 2017-03-0 2017-03-1 2016-11-2 2017-06-1 IDA / Q9910 agement, communication A priori Direct 300,000.00 598,703.01 Signé Land Cruiser Prado TXT 7 s es agences de l' 7 4 2 5 2 3 and monitoring eater 3.0 Turbo. Un véhicu ONU le 4X4 Land Cruiser SW ST D 9 seater 4.5L et 4 Land Cruiser HT Semi LWB, 10 s eater 4.2L Diesel. Page 3 CM-MINEPIA-23689-GO-RF Improvement of Livestock Single Stage - On 2017-10-2 2018-02-1 2017-11-2 2018-03-2 2018-01-0 2018-04-1 2018-02-0 2018-04-2 2018-03-2 2018-06-1 2018-06-2 2019-04-2 B / Achat des kits de vacci IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 417,000.00 373,657.42 Achevé e Envelope 0 3 1 1 2 7 1 3 2 3 8 2 nation et de conservation ery de vaccins CM-MINEPIA-23749-GO-RF Project coordination, man Single Stage - On 2017-09-0 2017-09-1 2017-10-1 2017-11-2 2017-10-2 2017-12-2 2017-11-0 2018-02-0 2017-12-0 2018-04-0 2018-05-0 IDA / 59080 A posteriori Appel d'offres Open - National 158,000.00 168,025.83 Achevé B / Achat équipement de T agement, communication e Envelope 7 1 0 1 3 1 6 1 5 2 8 IC and monitoring CM-MINEPIA-23758-GO-RF Improvement of Livestock Q / Fourniture de bureau e Demande de pri Single Stage - On 2017-09-1 2017-12-1 2018-08-1 2018-05-0 IDA / 59080 Services Access and Deliv A posteriori Open - National 17,000.00 19,801.51 Signé t petits équipements pour x e Envelope 9 5 4 9 ery appui logistique à l'ONVC CM-MINEPIA-23769-GO-RF Q / Acquisition de matériel Improvement of Livestock Demande de pri Single Stage - On 2017-10-2 2018-01-1 2018-04-2 2018-07-1 2018-05-1 s de cartographie et de pr IDA / 59080 Services Access and Deliv A posteriori Open - National 50,000.00 44,684.52 Achevé x e Envelope 4 8 5 7 6 otection individuelle (agen ery ts de terrain et personnels du projet) CM-MINEPIA-23966-GO-RF Improvement of Livestock Q / Production de matériel Demande de pri Single Stage - On 2017-11-1 2018-02-1 2018-12-1 2018-07-1 2022-01-2 IDA / 59080 Services Access and Deliv A posteriori Open - National 17,000.00 11,290.05 Achevé s de sensibilisation dans le x e Envelope 4 3 3 5 0 ery cadre de la campagne de vaccination contre la PPR CM-MINEPIA-24333-GO-RF Project coordination, man Demande de pri Single Stage - On 2017-09-2 2017-12-0 2018-02-1 2017-12-2 2018-03-1 IDA / 59080 A posteriori Open - National 10,000.00 21.58 Achevé Q / Equipement son et ima agement, communication x e Envelope 7 6 3 6 2 ge UCP and monitoring CM-MINEPIA-24404-GO-RF Q / Signalétique extérieure et intérieure des bâtiment s des Antennes régionales: Project coordination, man Demande de pri Single Stage - On 2017-10-0 2017-12-1 2018-02-1 2018-01-3 2018-03-1 Production et pose des ens IDA / 59080 agement, communication A posteriori Open - National 12,000.00 14,340.60 Achevé x e Envelope 5 4 3 1 2 eignes lumineuses de faça and monitoring de et caissons, panneaux i ndicatifs de(extérieur) et p laques indicatives (intérieu r), chevalets nominatifs et chevalets de tab CM-MINEPIA-24424-GO-RF Q / Personnalisation de la papeterie et documents de Project coordination, man travail au logo du PRODEL: Demande de pri Single Stage - On 2017-10-1 2018-06-1 2017-12-2 2018-07-2 2018-01-2 2018-09-0 IDA / 59080 agement, communication A posteriori Open - National 34,000.00 33,266.30 Achevé papier en-tête, cartes de vi x e Envelope 0 1 6 5 5 6 and monitoring site, enveloppes, badges, chemise cartonnées, bloc- notes, couvertures de rapp ort, cartons compliments... CM-MINEPIA-24427-GO-RF Improvement of Livestock Demande de pri Single Stage - On En cours d' 2017-09-3 2017-12-1 2018-01-1 Q / Extension e la flotte de IDA / 59080 Services Access and Deliv A posteriori Open - National 65,000.00 0.00 x e Envelope exécution 0 0 8 communication du Projet e ery t du RESCAM CM-MINEPIA-24330-GO-RF Project coordination, man Demande de pri Single Stage - On 2017-10-0 2017-12-1 2018-05-2 2018-02-0 2018-06-2 Q / Equipement de photoc IDA / 59080 agement, communication A posteriori Open - National 20,000.00 19,830.79 Achevé x e Envelope 5 9 2 2 2 opie UCP et les UCR and monitoring CM-MINEPIA-24338-GO-RF Project coordination, man Demande de pri Single Stage - On 2017-09-2 2017-12-0 2017-11-1 2018-01-1 2018-05-0 Q / Equipement électrique IDA / 59080 agement, communication A posteriori Open - National 66,000.00 49,154.90 Achevé x e Envelope 4 3 3 7 8 UCP et les trois UCR and monitoring CM-MINEPIA-24092-GO-RF Project coordination, man Demande de pri Single Stage - On 2017-09-2 2017-11-2 2017-11-0 2018-01-1 2018-02-2 IDA / 59080 A posteriori Open - National 83,000.00 76,366.72 Achevé Q / Mobilier de bureau UCP agement, communication x e Envelope 4 6 6 0 6 et des trois UCR and monitoring CM-MINEPIA-24398-GO-RF Project coordination, man Q / Acquisition du logiciel i Demande de pri Single Stage - On 2017-09-1 2017-12-0 2018-01-1 IDA / 59080 agement, communication A posteriori Open - National 75,000.00 0.00 Annulé nformatisé de gestion com x e Envelope 8 4 8 and monitoring ptable et déploiement dan s les UCR (TOMPRO) CM-MINEPIA-26522-GO-RF Q / Acquisition du logiciel i Project coordination, man Passation de m 2017-08-3 2017-08-2 2017-09-0 2017-10-2 2017-10-1 2018-01-2 2018-10-1 2018-05-2 nformatisé de gestion com IDA / 59080 agement, communication A posteriori arché de gré à g Direct 75,000.00 63.85 Achevé 0 5 9 3 2 3 2 2 ptable, monitoring, march and monitoring ré é et déploiement dans les UCR (TOMPRO) CM-MINEPIA-23732-GO-RF Improvement of Livestock Single Stage - On 2017-10-1 2017-11-0 2017-12-2 2018-02-0 2018-04-1 2018-09-1 B / Achat d'animaux (ex. v IDA / 59080 Services Access and Deliv A priori Appel d'offres Open - National 267,000.00 0.00 Annulé e Envelope 0 9 8 9 2 9 aches, petits ruminants, et ery c.) CM-MINEPIA-47786-GO-RF Q / Acquisition des équipe Project coordination, man Demande de pri Single Stage - On 2018-03-2 2018-05-1 2018-07-0 2018-06-1 2018-08-0 ments pour mise en place IDA / 59080 agement, communication A posteriori Open - National 61,500.00 54,041.38 Achevé x e Envelope 0 8 4 7 3 du SIG (tablettes, pochette and monitoring pour tablette, powerbank, parasurtenseurs, serveur, ) CM-MINEPIA-47790-GO-RF Q / Aménagement réfectio Project coordination, man Demande de pri Single Stage - On 2018-03-2 2019-06-2 2018-05-1 2019-08-0 2018-06-1 n des bureaux IDA / 59080 agement, communication A posteriori Open - National 33,500.00 33,673.00 Signé x e Envelope 0 1 1 6 0 (Acquisition et installation and monitoring des rideaux et moquettes dans les UCR et UCP ) CM-MINEPIA-47797-GO-RF Q / Connexion internet - in Project coordination, man Demande de pri Single Stage - On 2018-03-2 2018-06-1 2018-04-2 2018-08-1 2018-06-2 2018-10-2 tranet - serveur IDA / 59080 agement, communication A posteriori Open - National 17,000.00 34,628.20 Achevé x e Envelope 0 2 7 3 6 0 Acquisition et installation d and monitoring es réseaux internet dans l es trois (03) UCR CM-MINEPIA-47801-GO-RF Project coordination, man Demande de pri Single Stage - On 2018-03-2 2018-06-0 2018-04-2 2018-07-2 2018-06-2 2018-09-2 Q / Équipement électrique IDA / 59080 agement, communication A posteriori Open - National 15,000.00 11,556.11 Achevé x e Envelope 0 5 7 5 6 8 de 12 climatiseurs dans le and monitoring s UCR du PRODEL CM-MINEPIA-47806-GO-RF Project coordination, man Q / Entretien /fonctionnem Demande de pri Single Stage - On 2018-03-2 2018-05-0 2018-09-0 2018-11-0 IDA / 59080 agement, communication A posteriori Open - National 6,950.00 7,299.87 Signé ent matériels informatique x e Envelope 0 8 3 4 and monitoring s et internet-intranet UCP CM-MINEPIA-47809-GO-RF Project coordination, man Q / Installation du système Demande de pri Single Stage - On 2018-03-2 2018-07-0 2018-05-2 2018-08-1 2019-05-2 IDA / 59080 agement, communication A posteriori Open - National 12,000.00 12,390.07 Signé de tracking de véhicules d x e Envelope 7 6 2 7 2 and monitoring u PRODEL et système de tr acking CM-MINEPIA-48005-GO-RF Q / Production des support Support to livestock value Demande de pri Single Stage - On En cours d' 2018-03-1 2018-04-2 2018-05-1 IDA / 59080 A posteriori Open - National 6,950.00 0.00 s de formation (aide-mém chains development x e Envelope exécution 2 6 0 oire) en éducation financiè re CM-MINEPIA-48030-GO-RF Improvement of Livestock Demande de pri Single Stage - On 2018-03-2 2018-05-2 2018-05-2 2018-06-2 2018-06-2 Q / Acquisition de matériel IDA / 59080 Services Access and Deliv A posteriori Open - National 25,000.00 19,695.25 Achevé x e Envelope 7 2 2 1 2 informatique pour le RESC ery AM CM-MINEPIA-24401-GO-RF Project coordination, man Demande de pri Single Stage - On 2017-10-2 2017-12-2 2017-12-1 2018-12-2 2018-02-2 IDA / 59080 A posteriori Open - National 20,000.00 17,367.67 Achevé Q / Connexion internet - in agement, communication x e Envelope 3 3 5 3 2 tranet - routeur and monitoring CM-MINEPIA-50650-GO-RF Improvement of Livestock Q / Location de camions, a Demande de pri Single Stage - On 2018-03-2 2018-05-1 2018-06-1 IDA / 59080 Services Access and Deliv A posteriori Limited 62,000.00 0.00 Annulé ménagements camions, pr x e Envelope 3 8 7 ery ise en charge de bergers CM-MINEPIA-50654-GO-RF Improvement of Livestock Demande de pri Single Stage - On 2018-04-0 2018-10-0 2018-05-2 2018-11-0 2018-08-2 2018-12-1 Q / Acquisition des produit IDA / 59080 Services Access and Deliv A posteriori Limited 34,500.00 39,407.54 Achevé x e Envelope 3 3 9 7 7 1 s vétérinaires et des matér ery iels d'identification CM-MINEPIA-50679-GO-RF Improvement of Livestock Q / Acquisition des kits de Demande de pri Single Stage - On 2018-06-0 2018-08-1 2018-07-2 2018-11-0 2018-10-1 2018-12-1 IDA / 59080 Services Access and Deliv A posteriori Limited 34,900.00 41,172.42 Achevé tuberculose au profit des a x e Envelope 5 4 1 7 9 1 ery gents du RESCAM dans le cadre PRODEL CM-MINEPIA-50682-GO-RF Q / Acquisition des disposit Improvement of Livestock Demande de pri Single Stage - On 2018-05-0 2018-08-1 2018-06-1 2018-10-2 2018-07-2 2019-01-1 ifs de lutte anti vectorielle IDA / 59080 Services Access and Deliv A posteriori Limited 66,667.00 68,497.53 Achevé x e Envelope 1 4 5 3 5 1 en faveur des éleveurs et l ery eurs organisations en zone s infestés dans le cadre du PRODEL CM-MINEPIA-50745-GO-RF Improvement of Livestock Demande de pri Single Stage - On 2018-06-1 2018-05-1 2018-07-2 2018-06-2 2018-08-1 2018-07-1 Q / Acquisition du matériel IDA / 59080 Services Access and Deliv A posteriori Limited 5,000.00 5,175.69 Achevé x e Envelope 0 8 1 2 1 1 de bureau pour le siège ery CM-MINEPIA-50832-GO-RF Improvement of Pastoral P Q / Acquisition des fournitu roductivity, Access to Mar Demande de pri Single Stage - On 2018-06-1 2018-08-1 2018-07-2 2018-10-2 2018-09-0 2019-01-1 IDA / 59080 A posteriori Limited 75,000.00 87,639.07 Achevé re de dispositifs de lutte a kets, and Resilience of Pa x e Envelope 0 3 6 3 9 1 nti vectorielle dans le cadr storal Communities e du PRODEL CM-MINEPIA-50880-GO-RF Q / Acquisition du matériel de communication (station Project coordination, man Demande de pri Single Stage - On 2018-03-2 2018-07-0 2018-04-2 2018-08-1 2018-06-0 2018-09-2 de montage, deux écrans i IDA / 59080 agement, communication A posteriori Limited 20,000.00 16,607.26 Achevé x e Envelope 6 2 5 7 9 4 7 une carte d'acquisition fi and monitoring rewire, une carte son profe ssionnelle, deux micropho nes professionnelle une ca rte TV intégrée CM-MINEPIA-23753-GO-RF B / Acquisitions de kits de Improvement of Livestock diagnostic de laboratoire, Single Stage - On 2017-11-0 2018-02-1 2017-12-0 2018-01-2 2018-03-1 2018-02-2 2018-03-2 2018-05-1 2018-05-0 2018-11-1 2019-02-0 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 300,000.00 380,258.12 Achevé de collecte et de transport e Envelope 2 3 4 1 9 0 9 4 4 0 8 ery d'échantillon pour la survei llance des maladies (petits équipements et consomm ables) CM-MINEPIA-23773-GO-RF Improvement of Livestock Q / Edition et multiplicatio Demande de pri Single Stage - On 2017-10-2 2018-01-1 2018-06-1 IDA / 59080 Services Access and Deliv A posteriori Open - National 25,000.00 0.00 Annulé n des bulletins et des outil x e Envelope 5 7 4 ery s de collecte des données sanitaires CM-MINEPIA-23774-GO-RF Improvement of Livestock Demande de pri Single Stage - On 2017-10-3 2018-01-3 2018-05-1 Q / Edition et multiplicatio IDA / 59080 Services Access and Deliv A posteriori Open - National 17,000.00 0.00 Annulé x e Envelope 1 0 5 n des manuels d'inspectio ery n sanitaire vétérinaire CM-MINEPIA-47803-GO-RF Project coordination, man Demande de pri Single Stage - On 2018-05-2 2018-05-0 2018-07-1 2018-07-0 2018-08-1 2018-07-0 Q / Fourniture matériels de IDA / 59080 agement, communication A posteriori Open - National 10,000.00 7,467.06 Achevé x e Envelope 1 9 6 3 5 6 bureau et fournitures diver and monitoring ses UCNP CM-MINEPIA-50675-GO-RF Improvement of Livestock B / Acquisition de génisses Open - Internatio Single Stage - On 2018-05-1 2018-05-3 2018-07-1 2018-07-3 2018-08-2 2019-01-2 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres 1,200,000.00 0.00 Annulé pleines + transport, assura nal e Envelope 6 1 0 0 9 6 ery nce, transitaire, aliments a ppropriés CM-MINEPIA-50635-GO-DI R / Acquisition des vaccins Improvement of Livestock Passation de m 2018-04-1 2018-04-1 2018-04-2 2018-04-1 2018-05-2 2018-07-2 2018-09-2 (800 000 doses) et élabora IDA / 59080 Services Access and Deliv A posteriori arché de gré à g Direct 1,400,000.00 1,508,707.20 Résilié 8 8 3 8 8 4 5 tion du guide de bonnes pr ery ré atiques de vaccination et d e prélèvement CM-MINEPIA-50665-GO-RF B / Acquisition de 420 télé Improvement of Livestock Demande de pri Single Stage - On 2018-05-0 2018-07-1 2018-06-2 2018-08-3 2018-08-2 phones/tablettes et crédit IDA / 59080 Services Access and Deliv A posteriori Limited 143,460.00 166,166.74 Signé x e Envelope 1 2 6 0 5 de communication pour 12 ery mois (flotte) au 1200 agen ts RESCAM dans le cadre d u PRODEL CM-MINEPIA-56627-GO-RF Project coordination, man Q / Fourniture et installatio Demande de pri Single Stage - On 2018-04-0 2018-05-2 2018-04-0 2018-06-1 2018-04-3 IDA / 59080 agement, communication A posteriori Open - National 8,332.00 7,118.90 Achevé n des meubles (salle à ma x e Envelope 3 9 3 3 0 and monitoring nger, tente moderne de ca mping) CM-MINEPIA-50661-GO-RF Improvement of Livestock Demande de pri Single Stage - On 2018-07-3 2018-10-0 2018-09-2 2018-11-0 2018-12-2 2019-03-1 Q / Acquisition de doses de IDA / 59080 Services Access and Deliv A posteriori Limited 67,000.00 74,085.48 Achevé x e Envelope 1 3 5 7 4 8 semences bovines de race ery s exotiques CM-MINEPIA-50739-GO-RF Improvement of Livestock Q / Acquisition des estamp Demande de pri Single Stage - On 2018-05-2 2018-08-1 2018-07-2 2018-11-0 2018-10-2 2019-06-2 IDA / 59080 Services Access and Deliv A posteriori Limited 84,000.00 97,596.10 Achevé illes, encreurs et encre ble x e Envelope 8 3 4 7 2 6 ery u dans le cadre PRODEL CM-MINEPIA-61604-GO-DI Improvement of Livestock Passation de m R / Acquisition de génisses 2018-06-0 2018-09-0 2018-06-1 2018-09-1 2018-07-3 2019-01-2 2018-10-2 IDA / 59080 Services Access and Deliv A posteriori arché de gré à g Direct 1,200,000.00 986,302.89 Signé pleines + transport, assura 4 5 9 7 1 2 9 ery ré nce, transitaire, aliments a ppropriés CM-MINEPIA-64711-GO-U N / Acquisition de 03 véhic Passation de m Project coordination, man ules TOYOTA 4WD Land Cr archés auprès d 2018-05-3 2018-06-0 2018-07-1 2018-04-2 2019-01-0 IDA / 59080 agement, communication A priori Direct 400,000.00 286,451.55 Signé uiser 150-series Prado TX es agences de l' 1 5 0 7 6 and monitoring moteur diesel et de 07 véh ONU icules Toyota 4WD Hilux D ouble Cabin moteur turbo diesel CM-MINEPIA-68565-GO-RF Project coordination, man Demande de pri Single Stage - On 2018-07-1 2018-05-1 2018-09-0 2018-07-0 2018-11-0 2018-07-1 Q / Assurances des dix (10 IDA / 59080 agement, communication A posteriori Limited 6,700.00 6,705.15 Achevé x e Envelope 4 4 8 4 7 3 ) véhicules du PRODEL and monitoring CM-MINEPIA-68613-GO-RF Project coordination, man Demande de pri Single Stage - On 2018-09-0 2018-10-2 2021-11-1 2018-12-2 2022-03-0 Q / Production des support IDA / 59080 agement, communication A posteriori Open - National 35,000.00 23,464.05 Achevé x e Envelope 3 9 5 8 9 s de communication and monitoring CM-MINEPIA-68625-GO-RF Project coordination, man Demande de pri Single Stage - On 2018-08-2 2018-10-1 2018-10-2 2018-12-1 2018-12-2 2019-03-1 IDA / 59080 A posteriori Open - National 25,000.00 17,697.91 Achevé Q / matériels de suivi éval agement, communication x e Envelope 7 5 2 3 1 4 uation and monitoring CM-MINEPIA-50852-GO-RF Improvement of Pastoral P B / Acquisition des équipe roductivity, Access to Mar Single Stage - On 2018-06-2 2018-06-2 2018-07-2 2018-08-1 2018-09-0 2019-01-0 IDA / 59080 A priori Appel d'offres Open - National 500,000.00 0.00 Annulé ments et fournitures pour l kets, and Resilience of Pa e Envelope 0 5 5 4 3 1 es femmes et les groupes storal Communities de femmes CM-MINEPIA-68668-GO-RF Project coordination, man B / Fourniture du repas à l Demande de pri Single Stage - On 2018-07-3 2017-12-0 2018-09-2 2018-04-2 2018-11-2 2018-04-3 IDA / 59080 agement, communication A posteriori Limited 5,500.00 5,745.09 Achevé a commission ad oc charg x e Envelope 1 1 5 5 4 0 and monitoring ée du recrutement du rest e du personnel du PRODEL Page 4 CM-MINEPIA-68669-GO-RF Q / Fourniture de petits ma Project coordination, man Demande de pri Single Stage - On 2018-07-3 2017-12-0 2018-09-2 2018-03-2 2018-10-0 2018-04-3 tériels de bureau (matériel IDA / 59080 agement, communication A posteriori Limited 3,750.00 3,972.31 Achevé x e Envelope 1 1 5 5 5 0 s de travail) pour la commi and monitoring ssion ad oc chargée du rec rutement du personnel du PRODEL CM-MINEPIA-73927-GO-RF Improvement of Livestock Single Stage - Tw 2018-08-1 2018-08-1 2018-08-1 2018-09-1 2018-09-2 2018-09-2 2018-10-1 2018-09-2 2018-11-1 2018-10-2 2019-02-0 B / KITS SOLAIRES DE REF IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 341,667.00 357,022.33 Signé o Envelope 4 0 9 1 8 4 3 7 1 3 9 RIGERATION ET DE CONGE ery LATION CM-MINEPIA-74109-GO-RF Project coordination, man Q / Production de supports Demande de pri Single Stage - On 2018-08-2 2018-08-1 2018-11-0 2018-10-1 2018-12-0 IDA / 59080 agement, communication A posteriori Limited 28,500.00 20,119.33 Signé de communication dans le x e Envelope 8 4 8 6 8 and monitoring cadre de la vaccination co ntre la PPR CM-MINEPIA-74111-GO-RF Project coordination, man Q / Production des support Demande de pri Single Stage - On 2018-09-0 2018-08-1 2018-11-1 2018-10-1 2018-12-1 2018-11-2 IDA / 59080 agement, communication A posteriori Limited 32,100.00 30,185.45 Achevé s de visibilité dans le cadre x e Envelope 3 3 4 6 4 6 and monitoring des activités du PRODEL CM-MINEPIA-67731-GO-RF Project coordination, man Demande de pri Single Stage - On 2018-07-0 2018-08-2 2019-02-2 IDA / 59080 A posteriori Limited 6,700.00 0.00 Annulé Q / Assurance de véhicules agement, communication x e Envelope 3 8 4 du PRODEL and monitoring CM-MINEPIA-50686-GO-RF Q / Edition, multiplication Improvement of Livestock Demande de pri Single Stage - On 2018-06-0 2018-07-1 2018-09-1 des fiches d'alerte, des gui IDA / 59080 Services Access and Deliv A posteriori Limited 66,667.00 0.00 Annulé x e Envelope 3 8 6 des des activités et des bu ery lletins épidémiologiques d ans le cadre du PRODEL CM-MINEPIA-50640-GO-RF Improvement of Livestock B / Acquisition du matériel Single Stage - Tw 2018-03-2 2018-05-0 2018-04-0 2018-05-0 2018-05-0 2018-05-1 2018-06-1 2018-10-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 341,667.00 0.00 Annulé de froid (58 congélateurs-r o Envelope 9 2 3 9 3 8 6 4 ery éfrigérateurs à énergie sol aire) au PRODEL CM-MINEPIA-98784-GO-RF Project coordination, man Demande de pri Single Stage - On 2019-04-2 2018-12-0 2019-06-2 2019-01-1 2019-08-2 IDA / 59080 A posteriori Limited 6,800.00 7,039.74 Signé Q / Diffusion des spots pub agement, communication x e Envelope 9 7 4 6 3 licitaires and monitoring CM-MINEPIA-24420-GO-RF Project coordination, man Demande de pri Single Stage - On 2017-10-0 2017-12-1 2018-01-1 Q / Matérialisation du logo IDA / 59080 agement, communication A posteriori Open - National 17,000.00 0.00 Annulé x e Envelope 5 4 8 sur les véhicules et motos and monitoring CM-MINEPIA-50666-GO-RF Improvement of Livestock Demande de pri Single Stage - On 2018-04-0 2018-06-0 2018-09-3 IDA / 59080 A posteriori Limited 22,000.00 0.00 Annulé Q / Acquisition de litres d'a Services Access and Deliv x e Envelope 7 2 0 zote ery CM-MINEPIA-106180-GO-R Improvement of Livestock FB / Acquisition du matérie Single Stage - On 2019-05-2 2019-08-2 2019-06-0 2019-09-1 2019-07-1 2019-09-2 2019-08-1 2019-10-0 2019-09-1 2019-11-2 2019-12-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 142,000.00 90,497.77 Signé l de froid dans les services e Envelope 9 3 3 0 5 7 4 4 8 2 7 ery déconcentrés du MINEPIA CM-MINEPIA-106283-GO-R Improvement of Livestock Demande de pri Single Stage - On 2019-07-0 2019-10-2 2019-08-2 2019-12-1 2019-11-2 IDA / 59080 A posteriori Limited 17,000.00 15,237.90 Signé FQ / Acquisitions d'azote li Services Access and Deliv x e Envelope 3 1 8 9 6 quide ery CM-MINEPIA-106284-GO-R Improvement of Livestock Demande de pri Single Stage - On 2019-07-0 2019-10-2 2019-08-2 2019-12-0 2019-12-2 2020-02-1 FQ / Fourniture de semenc IDA / 59080 Services Access and Deliv A posteriori Limited 50,000.00 76,028.91 Achevé x e Envelope 3 1 8 9 6 4 es et réalisation de champ ery s semenciers CM-MINEPIA-106348-GO-R Project coordination, man Single Stage - On 2019-05-3 2019-01-1 2019-06-0 2019-07-1 2019-02-1 2019-08-1 2019-02-2 2019-09-2 2019-03-2 2020-09-1 FQ / Assurance tous les vé IDA / 59080 agement, communication A posteriori Appel d'offres Open - National 67,000.00 64,201.70 Signé e Envelope 1 5 5 7 9 6 7 0 6 9 hicules du PRODEL and monitoring CM-MINEPIA-106350-GO-R Project coordination, man Single Stage - On 2019-05-3 2019-01-2 2019-06-0 2019-07-1 2019-02-1 2019-08-1 2019-02-2 2019-09-2 2019-03-2 2020-09-1 FQ / Assurances immobilis IDA / 59080 agement, communication A posteriori Appel d'offres Open - National 25,000.00 8,247.47 Signé e Envelope 1 2 5 7 9 6 5 0 6 9 ations (équipements/bâtim and monitoring ents) PRODEL CM-MINEPIA-108086-GO-R FB / Fourniture des kits vét Improvement of Pastoral P érinaires en complément d roductivity, Access to Mar Single Stage - On En cours d' 2019-05-2 2019-06-0 2019-05-2 2019-06-2 2019-07-0 2019-07-2 2019-08-0 2019-09-1 2019-11-1 IDA / 59080 A posteriori Appel d'offres Open - National 167,000.00 0.00 es actifs productifs pour le kets, and Resilience of Pa e Envelope exécution 3 7 8 1 9 5 8 2 1 s ménages affectés par les storal Communities conflits dans les régions d u Nord et de l'Extrême-Nor d CM-MINEPIA-98741-GO-RF Improvement of Livestock Q / Acquisition de matériel Single Stage - On 2019-03-2 2019-06-0 2019-04-0 2019-05-1 2019-06-1 2019-07-1 2019-10-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 80,000.00 0.00 Annulé informatique pour le dispo e Envelope 8 7 2 4 3 8 6 ery sitif d'information sanitaire CM-MINEPIA-50672-GO-RF Q / Fourniture des service Improvement of Livestock Demande de pri Single Stage - On 2018-05-2 2018-07-0 2018-07-2 de messagerie et de trans IDA / 59080 Services Access and Deliv A posteriori Limited 25,000.00 0.00 Annulé x e Envelope 7 9 3 port des échantillons à des ery tination de LANAVET de Bo klé à Yaoundé CM-MINEPIA-93110-GO-RF Q / Fourniture, édition des Improvement of Livestock Demande de pri Single Stage - On 2019-01-1 2019-03-0 2019-05-3 fiches de prélèvement de IDA / 59080 Services Access and Deliv A posteriori Limited 6,800.00 0.00 Annulé x e Envelope 5 1 0 dénombrement de petits r ery uminants et de carnets de vaccination dans le cadre du PRODEL CM-MINEPIA-98751-GO-RF Q / Edition, multiplication e Improvement of Livestock Demande de pri Single Stage - On 2019-04-0 2019-05-2 2019-07-2 t édition des guides des ac IDA / 59080 Services Access and Deliv A posteriori Limited 7,500.00 0.00 Annulé x e Envelope 1 7 6 tivités d'un chef de centre ery pour le MINEPIA et écoles de formation (CNFZV) - UC NP CM-MINEPIA-127215-GO-R Improvement of Livestock FQ / Fourniture des recueil Demande de pri Single Stage - On 2019-08-1 2019-05-1 2019-09-1 2019-05-2 2019-10-1 2019-07-1 IDA / 59080 Services Access and Deliv A posteriori Limited 3,300.00 3,020.42 Achevé de textes regissant l'éléva x e Envelope 9 7 9 0 9 8 ery ge au cameroun 3ème édit ion CM-MINEPIA-127216-GO-R Project coordination, man Demande de pri Single Stage - On 2019-08-1 2019-05-0 2019-09-1 2019-05-2 2019-10-1 FQ / Réalisation de petits t IDA / 59080 agement, communication A posteriori Limited 6,500.00 6,632.33 Signé x e Envelope 9 8 9 7 9 ravaux de réhabilitation de and monitoring s bureaux UCNP CM-MINEPIA-127217-GO-R Project coordination, man FQ / Couverture médiatiqu Demande de pri Single Stage - On 2019-08-1 2019-06-0 2019-09-1 2019-07-1 2019-10-1 IDA / 59080 agement, communication A posteriori Limited 6,500.00 7,080.97 Signé e cérémonie de remise offi x e Envelope 9 3 9 6 9 and monitoring cielle des actifs productifs (moutons et chèvres) CM-MINEPIA-127222-GO-R Project coordination, man Demande de pri Single Stage - On 2019-08-1 2019-09-1 2019-09-1 2019-10-2 2019-10-1 2019-10-2 FQ / Fourniture matériel de IDA / 59080 agement, communication A posteriori Limited 6,500.00 7,129.20 Achevé x e Envelope 9 6 9 4 9 5 bureau à l'UCNP du PRODE and monitoring L CM-MINEPIA-127224-GO-R FQ / Fourniture du matériel Project coordination, man Demande de pri Single Stage - On 2019-08-1 2019-05-1 2019-09-1 2019-06-2 2019-10-1 2019-09-1 de démonstration pour les IDA / 59080 agement, communication A posteriori Limited 1,200.00 3,033.19 Achevé x e Envelope 9 7 9 0 9 3 exercices de simulation da and monitoring ns la gestion des crises à l' UCNP du PRODEL CM-MINEPIA-127225-GO-R Project coordination, man Demande de pri Single Stage - On 2019-08-1 2019-07-2 2019-09-1 2019-08-2 2019-10-1 FQ / Fourniture des Conso IDA / 59080 agement, communication A posteriori Limited 6,500.00 6,934.35 Signé x e Envelope 9 9 9 8 9 mmables informatiques and monitoring CM-MINEPIA-127226-GO-R Project coordination, man Demande de pri Single Stage - On 2019-08-2 2018-12-0 2019-09-2 2019-01-2 2019-10-2 IDA / 59080 A posteriori Limited 6,500.00 6,755.00 Signé FQ / Fourniture des calend agement, communication x e Envelope 1 7 1 2 1 riers 2019 and monitoring CM-MINEPIA-127228-GO-D Improvement of Livestock Passation de m 2019-08-2 2021-05-1 2019-08-2 2021-03-0 2019-09-2 2021-07-2 2020-03-2 IR / Acquisition deuxième IDA / 59080 Services Access and Deliv A posteriori arché de gré à g Direct 1,400,000.00 94,126,767.26 Signé 0 2 5 9 9 1 7 vague de génisses pleines ery ré au PRODEL CM-MINEPIA-127229-GO-D Improvement of Livestock Passation de m 2019-08-2 2021-06-0 2019-08-2 2021-06-2 2019-09-2 2021-07-2 2020-03-2 2022-03-0 IDA / 59080 A posteriori Direct 416,667.00 15,426,556.77 Achevé IR / Acquisition de géniteur Services Access and Deliv arché de gré à g 0 2 5 9 9 9 7 4 s porcins ery ré CM-MINEPIA-130168-GO-R Project coordination, man Demande de pri Single Stage - On 2019-09-0 2019-07-1 2019-11-0 2019-07-2 2020-05-0 FQ / Fourniture des service IDA / 59080 agement, communication A posteriori Limited 6,950.00 7,129.88 Signé x e Envelope 8 5 3 5 1 d'entretien des locaux de l' and monitoring UCNP du PRODEL CM-MINEPIA-130169-GO-R Project coordination, man FQ / Fourniture du matériel Demande de pri Single Stage - On 2019-09-0 2019-08-1 2019-11-0 2019-08-2 2020-05-0 IDA / 59080 agement, communication A posteriori Limited 6,950.00 7,062.45 Signé de bureau pour le fonction x e Envelope 8 2 3 9 1 and monitoring nement la CSPM du PRODE L CM-MINEPIA-130170-GO-R Project coordination, man FQ / Fourniture des access Demande de pri Single Stage - On 2019-09-0 2019-08-0 2019-11-0 2019-09-0 2020-05-0 IDA / 59080 agement, communication A posteriori Limited 6,950.00 7,029.33 Signé oires pour les véhicules du x e Envelope 8 3 3 9 1 and monitoring PRODEL ( installation pare -buffles) CM-MINEPIA-135889-GO-R FQ / Fourniture d'un serve Improvement of Livestock ur HPE ML350 Gen10 Xeon Demande de pri Single Stage - On 2019-10-0 2019-07-0 2019-11-0 2019-07-2 2019-12-0 IDA / 59080 Services Access and Deliv A posteriori Limited 7,000.00 6,933.33 Signé -S 41110 et accessoires da x e Envelope 2 3 1 5 1 ery ns le cadre de la mise en o euvre des activités du suiv i évaluation du PRODEL CM-MINEPIA-98838-GO-RF Improvement of Livestock B / Acquisition du matériel Single Stage - On 2019-02-2 2019-09-2 2019-02-2 2019-03-1 2019-03-1 2019-03-2 2019-09-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé pour le fonctionnement du e Envelope 0 0 2 4 7 1 7 ery système d'information (un serveur) CM-MINEPIA-136696-GO-R Improvement of Livestock FQ / Fourniture des spots p Demande de pri Single Stage - On 2019-10-2 2019-09-0 2019-11-2 2019-11-2 2019-12-0 IDA / 59080 Services Access and Deliv A posteriori Limited 6,900.00 7,073.01 Signé ublicitaires dans le cadre d x e Envelope 2 3 1 7 6 ery e la campagne de vaccinat ion contre les petits rumin ants CM-MINEPIA-136702-GO-R Improvement of Livestock Demande de pri Single Stage - On 2019-10-2 2019-09-0 2019-11-2 2019-11-2 2019-12-0 FQ / Fourniture des mantel IDA / 59080 Services Access and Deliv A posteriori Limited 5,900.00 5,870.11 Signé x e Envelope 3 6 2 6 7 ets et badges au PRODEL ery CM-MINEPIA-136709-GO-R FQ / Fourniture des plaque Improvement of Livestock Demande de pri Single Stage - On 2019-10-2 2019-09-1 2019-11-2 2019-11-2 2019-12-0 ttes pour le lancement offi IDA / 59080 Services Access and Deliv A posteriori Limited 3,000.00 2,957.45 Signé x e Envelope 3 3 2 7 7 ciel de la campagne de va ery ccination des petits rumin ants du PRODEL CM-MINEPIA-141288-GO-R FB / Fourniture de kits de Improvement of Livestock Single Stage - On En cours d' 2019-10-2 2019-11-2 2019-10-3 2019-11-2 2019-12-1 2020-06-0 2020-01-1 2020-02-1 2020-05-1 matériel de prélèvement e IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 130,000.00 0.00 e Envelope exécution 5 5 0 5 1 2 0 4 4 t de diagnostic dans le cad ery re de l'enquête post-vacci nale sur la PPR CM-MINEPIA-136692-GO-R Improvement of Livestock Demande de pri Single Stage - On 2019-10-1 2019-05-0 2019-11-1 2019-09-2 2019-12-1 FQ / Fourniture des alimen IDA / 59080 Services Access and Deliv A posteriori Limited 6,900.00 5,915.06 Signé x e Envelope 5 9 4 4 4 ts pour génisses dans le ca ery dre du PRODEL CM-MINEPIA-130163-GO-R FQ / Fourniture du matériel Project coordination, man de bureau et petit équipe Demande de pri Single Stage - On 2019-11-1 2019-08-1 2020-01-1 2019-08-2 2020-02-0 IDA / 59080 agement, communication A posteriori Limited 6,900.00 7,067.90 Signé ment pour le fonctionnem x e Envelope 9 2 4 9 3 and monitoring ent de la Commission spéc iale de Passation des Marc hés du PRODEL CM-MINEPIA-137092-GO-U Passation de m N / Acquisition de cent mot Improvement of Livestock archés auprès d 2019-11-1 2019-09-2 2019-11-2 2019-11-0 2019-12-0 2019-11-1 2020-05-2 ocyclettes tout terrain au IDA / Q9910 Services Access and Deliv A posteriori Direct 276,400.00 281,475.43 Signé es agences de l' 5 5 0 7 1 3 9 profit des jeunes docteurs ery ONU vétérinaires et de certaine s communes dans le cadre du PRODEL CM-MINEPIA-127230-GO-D Improvement of Pastoral P Passation de m 2019-12-2 2019-06-0 2020-01-0 2019-06-1 2020-02-0 2019-07-2 2020-08-0 IR / Fournitures des alimen IDA / 59080 roductivity, Access to Mar A posteriori arché de gré à g Direct 157,725.00 159,727.51 Signé 8 4 2 0 6 9 4 ts pour bétail par la SODE kets, and Resilience of Pa ré COTON storal Communities CM-MINEPIA-127195-CW- RFB / Fourniture des moto Improvement of Livestock cyclettes tout terrain au pr Single Stage - Tw 2019-08-1 2019-08-1 2019-09-3 2019-12-1 2020-01-1 2020-05-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 450,000.00 0.00 Annulé ofit des jeunes docteurs vé o Envelope 4 9 0 3 7 6 ery térinaires et de certaines c ommunes dans le cadre du PRODEL en un lot unique. CM-MINEPIA-98005-GO-RF Improvement of Livestock B / Acquisition du matériel Single Stage - On 2019-02-2 2020-01-0 2019-03-0 2019-04-1 2019-05-1 2019-06-2 2019-09-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 341,667.00 0.00 Annulé de froid (58 congélateurs-r e Envelope 8 6 5 6 6 0 8 ery éfrigérateurs à énergie sol aire) au PRODEL CM-MINEPIA-141283-GO-R Improvement of Livestock FB / Fourniture de 10 kits d Single Stage - On 2019-10-2 2019-11-2 2019-10-3 2019-11-2 2019-12-1 2020-02-1 2020-01-1 2020-02-1 2020-05-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 108,500.00 0.00 Annulé e dispositifs rapproché de e Envelope 5 5 0 5 1 2 0 4 4 ery riposte et de gestion des f oyers/crises sanitaires CM-MINEPIA-159859-GO-R FB / Fourniture des kits au Improvement of Livestock Single Stage - On En cours d' 2020-06-1 2020-06-1 2020-06-2 2020-06-2 2020-07-2 2020-08-2 2020-08-0 2020-08-2 2020-11-1 x agents de vaccination da IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 300,000.00 0.00 e Envelope exécution 8 1 3 4 3 1 2 0 8 ns le cadre de la campagn ery e de vaccination contre la PPR en 2020 CM-MINEPIA-216202-GO-R Improvement of Livestock FQ / ACQUISITION MATERI Demande de pri 2021-05-3 2021-07-2 2022-02-0 2021-10-2 IDA / 59080 Services Access and Deliv A posteriori 84,112.00 16,580.21 Signé ELS DE COLLECTES POUR x 1 7 7 5 ery LES EQUIPES BILAN FOURR AGER CM-MINEPIA-161812-GO-R Project coordination, man FQ / Fourniture des service Demande de pri Single Stage - On 2021-08-1 2020-05-1 2021-10-1 2020-06-2 2021-11-2 IDA / 59080 agement, communication A posteriori Limited 6,000.00 3,211.43 Signé s d’Entretien du Materiel I x e Envelope 5 9 0 4 4 and monitoring nformatique, des Copieurs et Serveurs à l'UCR Zone 3 CM-MINEPIA-161902-GO-R Project coordination, man Demande de pri Single Stage - On 2021-08-1 2020-04-0 2021-10-1 2020-04-1 2021-11-1 FQ / Fourniture des Conso IDA / 59080 agement, communication A posteriori Limited 6,667.00 3,569.74 Signé x e Envelope 5 8 0 3 9 mmables Informatiques à l and monitoring ’UCR Zone 3 CM-MINEPIA-161817-GO-R Project coordination, man FQ / Fourniture des service Demande de pri Single Stage - On 2021-08-1 2020-05-2 2021-10-1 2020-06-2 2021-11-2 IDA / 59080 agement, communication A posteriori Limited 600.00 2,141.84 Signé s d’Entretien et de Mainte x e Envelope 5 6 0 5 4 and monitoring nance du Materiel électriq ue à l'UCR Zone 3 Page 5 CM-MINEPIA-237637-GO-R FB / FOURNITURE DES VAC Improvement of Pastoral P CINS CONTRE LA PESTE DE roductivity, Access to Mar Single Stage - On 2021-06-0 2021-06-1 2021-06-0 2021-06-1 2021-06-1 2021-06-2 2021-06-2 2021-07-0 2021-08-0 2021-10-0 IDA / 59080 A posteriori Appel d'offres Open - National 125,000.00 120,302.99 Signé S PETITS RUMINANTS DAN kets, and Resilience of Pa e Envelope 1 7 4 7 7 4 3 8 6 6 S LE CADRE DU PROJET DE storal Communities DEVELOPPEMENT DE L’ELE VAGE (PRODEL) CM-MINEPIA-224689-GO-D Improvement of Livestock Passation de m 2021-06-1 2021-03-2 2021-06-2 2021-04-2 2021-07-2 2021-07-2 2022-01-2 IR / ACQUISITION DE CENT IDA / 59080 Services Access and Deliv A posteriori arché de gré à g Direct 183,334.00 904,696.77 Signé 5 6 0 8 5 1 1 (100) GENITEURS PORCINS ery ré CM-MINEPIA-236911-GO-R FB / FOURNITURE DES GEN ITEURS (PETITS RUMINANT S) POUR LES MENAGES PA Improvement of Pastoral P UVRES ET AFFECTES PAR L roductivity, Access to Mar Single Stage - On 2021-07-1 2021-09-2 2021-07-2 2021-08-1 2021-10-2 2021-09-0 2021-11-0 2021-09-2 2022-01-1 2021-12-2 IDA / 59080 A posteriori Appel d'offres Open - National 1,416,667.00 575,407.66 Signé ES CONFLITS DANS LES RE kets, and Resilience of Pa e Envelope 5 0 0 0 0 9 5 3 8 2 GIONS DU NORD ET DE L’E storal Communities XTREME-NORD DU CAMER OUN LE CADRE DU PROJET DE DEVELOPPEMENT DE L’ ELEVAGE (PRODEL), EN PR OCEDURE D’URGENCE » D CM-MINEPIA-224696-GO-D OUZE (12) LOTS Improvement of Livestock Passation de m 2021-05-3 2021-03-2 2021-06-0 2021-05-0 2021-07-1 2021-07-2 2022-01-0 2021-07-2 IR / ACQUISITION DE CENT IDA / 59080 Services Access and Deliv A posteriori arché de gré à g Direct 975,000.00 918,961.17 Achevé 1 6 5 6 0 1 6 1 SOIXANTE (165) GENISSES ery ré MONTBELIARDES CM-MINEPIA-224728-GO-R FQ / FOURNITURE DES DIS Improvement of Livestock Single Stage - On 2021-07-0 2021-05-1 2021-07-1 2021-08-2 2021-06-1 2021-09-2 2021-06-2 2021-10-2 2021-08-0 2022-04-2 POSITIFS DE LUTTE ANTIVE IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 150,000.00 122,220.85 Signé e Envelope 8 7 3 4 6 3 3 8 6 6 CTORIELLE EN FAVEUR DE ery S COMITES DE LUTTE ANTI VECTORIELLE (CLAV) CM-MINEPIA-224787-GO-R FQ / FOUNITURE DES SUPP ORTS DE CAMAPGNE DE V Improvement of Livestock Demande de pri Single Stage - On 2021-07-1 2021-09-1 2021-08-0 2021-10-2 2022-01-2 ACCINATION CONTRE LA P IDA / 59080 Services Access and Deliv A posteriori Open - National 41,667.00 41,251.19 Achevé x e Envelope 9 3 5 8 0 ESTE DES PETITS RUMINA ery NTS POUR LE COMPTE DE L'ANNEE 2021. Mention pr atiques commerciales sup primée CM-MINEPIA-238093-GO-R Improvement of Livestock FQ / acquisition des équipe Demande de pri Single Stage - On 2021-06-0 2021-10-0 2021-08-0 2021-11-1 2021-09-0 IDA / 59080 Services Access and Deliv A posteriori Limited 58,333.00 16,955.68 Signé ments pour le service infor x e Envelope 8 6 3 7 2 ery matique de la DEPCS-MINE PIA CM-MINEPIA-237612-GO-R FB / FOURNITURE DES KITS DE TRAVAIL AUX SERVICES D’INSPECTION SANITAIRE Improvement of Pastoral P VETERINAIRE ET AUTRES P roductivity, Access to Mar Single Stage - On 2021-06-0 2021-06-1 2021-06-0 2021-06-1 2021-06-1 2021-06-2 2021-07-0 2021-07-3 2021-08-1 2022-01-2 IDA / 59080 A posteriori Appel d'offres Open - National 133,333.00 199,339.26 Signé ROFESSIONNELS DES DEN kets, and Resilience of Pa e Envelope 1 8 4 8 8 5 6 0 2 6 REES ALIMENTAIRES D’ORI storal Communities GINE ANIMALE ET HALIEUT IQUE DANS LE CADRE DU PROJET DE DEVELOPPEME NT DE L’ELEVAGE (PRODEL ), EN PROCEDURE D’URGE CM-MINEPIA-245251-GO-R NCE Improvement of Pastoral P FQ / FOURNITURE DES MA roductivity, Access to Mar Demande de pri Single Stage - On 2021-07-2 2021-09-2 2021-08-0 2022-03-2 IDA / 59080 A posteriori Open - National 66,667.00 42,769.69 Signé NUELS D'INSPECTION SANI kets, and Resilience of Pa x e Envelope 8 2 6 1 TAIRE VETERINAIRE DANS storal Communities LE CADRE DU PRODEL CM-MINEPIA-245254-GO-R Improvement of Livestock FQ / FOURNITURE DU MAT Demande de pri Single Stage - On 2021-07-2 2021-09-2 2021-08-1 2022-03-2 IDA / 59080 Services Access and Deliv A posteriori Open - National 29,167.00 24,603.42 Signé ERIEL DE TRAVAIL AU RES x e Envelope 8 2 1 1 ery CAM DANS LE CADRE DU P RODEL CM-MINEPIA-245276-GO-R FQ / FOURNITURE DES SER Project coordination, man Demande de pri Single Stage - On 2021-07-2 2021-09-2 2022-01-1 2022-03-2 VICES D'INSTALLATION DU IDA / 59080 agement, communication A posteriori Open - National 23,333.00 11,548.66 Signé x e Envelope 8 2 4 1 SYSTEME D'INSTALLATION and monitoring DE TRACKING DES VEHICU LES DU PRODEL CM-MINEPIA-245470-GO-R FB / Acquisition et distribut ion des géniteurs pour la p oursuite de la mise en oeu Support to livestock value Single Stage - On 2021-10-2 2021-10-2 2021-10-2 2021-12-0 2021-11-3 2022-01-0 2021-12-0 2022-02-0 2022-01-1 2022-08-0 vre des plans d'actions en IDA / 59080 A posteriori Appel d'offres Open - National 339,333.00 327,699.34 Signé chains development e Envelope 0 2 5 6 0 5 8 9 8 8 faveur des peuples autoch tones BAKAS dans les Dép ments de la BOUMBA et N GOKO et HAUT-NYONGn R égion de l'EST dans le cadr e du PRODEL en trois (03) l CM-MINEPIA-245519-GO-R ots FB / Fourniture des vaccins Support to livestock value Single Stage - On 2021-10-2 2021-05-1 2021-11-1 2021-12-2 2021-06-1 2022-01-2 2021-06-2 2022-02-2 2021-08-0 2022-08-1 IDA / 59080 A posteriori Appel d'offres Open - National 200,000.00 177,379.50 Signé PPR pour la constitution de chains development e Envelope 9 1 2 4 7 3 3 0 6 9 s stock (deux millions de d ose) CM-MINEPIA-215650-GO-R FQ / ACQUISITION DES EQ Project coordination, man Demande de pri Single Stage - On 2022-01-0 2022-02-2 2021-11-0 2022-04-1 UIPEMENTS INFORMATIQU IDA / 59080 agement, communication A posteriori Open - National 33,645.00 28,116.66 Signé x e Envelope 2 7 8 3 ES COMPLEMENTAIRES PO and monitoring UR LE COMPTE DE L'UNITE DE CORDINATION NATION ALE DU PROJET CM-MINEPIA-216208-GO-R Improvement of Livestock FQ / ACQUISITION DES EQ Demande de pri Single Stage - On 2021-12-0 2022-02-0 2021-11-1 2022-08-0 IDA / 59080 Services Access and Deliv A posteriori Open - National 65,421.00 17,242.80 Signé UIPEMENTS POUR LE SYST x e Envelope 8 9 7 8 ery EME D'INFORMATION DE L A DEPCS CM-MINEPIA-223626-GO-R Improvement of Pastoral P FQ / ACQUISITION DES EQ roductivity, Access to Mar Demande de pri Single Stage - On 2021-06-2 2021-10-0 2021-08-2 2021-11-1 2021-10-2 2022-05-1 IDA / 59080 A posteriori Limited 16,667.00 17,124.02 Achevé UIPEMENTS ET FORMATIO kets, and Resilience of Pa x e Envelope 8 6 3 7 2 0 N DES CADRES DE LA DEP storal Communities CS CM-MINEPIA-161848-GO-R Improvement of Livestock FQ / Edition des fiches tec Demande de pri Single Stage - On 2021-08-1 2021-10-0 2021-11-0 IDA / 59080 Services Access and Deliv A posteriori Limited 7,500.00 0.00 Annulé hniques pour une intensific x e Envelope 0 5 4 ery ation progressive et durab le des systèmes pastoraux CM-MINEPIA-161858-GO-R Improvement of Livestock Demande de pri Single Stage - On 2021-09-2 2021-11-2 2022-04-2 FQ / Opérationnalisation d IDA / 59080 Services Access and Deliv A posteriori Open - National 100,000.00 0.00 Annulé x e Envelope 8 3 2 e l'insémination artificielle ery (IA) CM-MINEPIA-161837-GO-R Improvement of Livestock Demande de pri Single Stage - On 2021-09-0 2021-10-2 2022-04-2 FQ / Fourniture des alime IDA / 59080 Services Access and Deliv A posteriori Limited 62,667.00 0.00 Annulé x e Envelope 1 7 5 nts pour porcs et bovins ery CM-MINEPIA-176071-GO-R FB / Fourniture de matériel Improvement of Livestock de travail aux agents des s Single Stage - On 2021-07-2 2021-07-2 2021-09-0 2021-10-0 2021-11-1 2022-05-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 334,000.00 0.00 Annulé tructures de base du MINE e Envelope 2 7 7 7 1 0 ery PIA dans le cadre des activ ités de surveillance des m aladies animales (CZV) CM-MINEPIA-161845-GO-R Improvement of Livestock FQ / Fourniture d'une t mo Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-01-2 IDA / 59080 Services Access and Deliv A posteriori Limited 66,667.00 0.00 Annulé to, kit d’insémination, bido x e Envelope 3 8 6 ery ns de lait et kits de contrôl e CM-MINEPIA-162095-GO-R Improvement of Livestock Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-03-2 FQ / Fourniture des semen IDA / 59080 Services Access and Deliv A posteriori Limited 70,000.00 0.00 Annulé x e Envelope 4 9 8 ces de bovins exotiques da ery ns le cadre du PRODEL CM-MINEPIA-161872-GO-R FQ / Fourniture des service Project coordination, man Demande de pri 2021-09-0 2021-10-3 2022-04-2 s de maintenance préventi IDA / 59080 agement, communication A posteriori 3,333.00 0.00 Annulé x 4 0 8 ves et curatives des climat and monitoring iseurs plomberie et petit t ravaux à menuiserie CM-MINEPIA-159866-GO-R Improvement of Livestock FB / Fourniture des kits de Single Stage - On 2020-06-2 2020-08-0 2020-07-0 2020-08-1 2020-09-1 2020-10-1 2021-01-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 108,500.00 0.00 Annulé riposte aux srvice déconc e Envelope 9 6 4 5 4 9 7 ery entrés (DDPIA) dans le cad re du PRODEL CM-MINEPIA-162103-GO-R Project coordination, man Single Stage - On 2020-05-1 2020-06-2 2020-05-1 2020-06-3 2020-07-3 2020-09-0 2021-09-0 FB / Assurance des véhicul IDA / 59080 agement, communication A posteriori Appel d'offres Open - National 66,666.67 0.00 Annulé e Envelope 4 4 9 0 0 3 3 es du PRODEL pour l'anné and monitoring e 2020-2021 CM-MINEPIA-161860-GO-R FQ / Fourniture et installati Project coordination, man Demande de pri Single Stage - On 2021-10-0 2021-11-3 2022-01-1 on des rideaux et moquett IDA / 59080 agement, communication A posteriori Limited 6,916.67 0.00 Annulé x e Envelope 5 0 4 es dans les UCR et UCP (FF and monitoring ), construction d'un hangar pour le groupe électrogèn e CM-MINEPIA-161825-GO-R Project coordination, man FQ / Réfection 2ème bâtim Demande de pri Single Stage - On 2021-08-1 2021-10-1 2022-02-0 IDA / 59080 agement, communication A posteriori Limited 5,833.00 0.00 Annulé ent prévu pour l'archivage x e Envelope 5 0 7 and monitoring et magasinage à l'UCR 1 CM-MINEPIA-161882-GO-R Project coordination, man Demande de pri Single Stage - On 2021-08-1 2021-10-0 2021-12-0 FQ / Fourniture de service IDA / 59080 agement, communication A posteriori Limited 5,000.00 0.00 Annulé x e Envelope 4 9 8 de nettoyage bureau inter and monitoring ne et externe de l’UCR1 CM-MINEPIA-161874-GO-R FQ / Fourniture du matéri el informatiques (un ordin Project coordination, man Demande de pri Single Stage - On 2020-04-1 2020-06-0 2020-07-2 ateur portable pour l'assist IDA / 59080 agement, communication A posteriori Limited 5,083.00 0.00 Annulé x e Envelope 3 8 3 ant du Projet, un vidéo pro and monitoring jecteur) et électrique (un p etit groupe électrogène po ur les déplacements) à l'U CR 1 CM-MINEPIA-161895-GO-R Project coordination, man Demande de pri Single Stage - On 2020-05-2 2020-07-2 2020-09-2 FQ / Fourniture d’un Copie IDA / 59080 agement, communication A posteriori Limited 5,000.00 0.00 Annulé x e Envelope 7 2 0 ur Multifonction à l’UCR Zo and monitoring ne 3 CM-MINEPIA-161832-GO-R FQ / Fourniture des disposi Improvement of Livestock Demande de pri Single Stage - On 2020-06-1 2020-08-1 2020-10-0 tifs de lutte (30 kits comm IDA / 59080 Services Access and Deliv A posteriori Limited 50,000.00 0.00 Annulé x e Envelope 5 0 9 unes, 350 kits bénéficiaire ery s génisses et 03 kits statio ns - UCNP (suivi UCR) CM-MINEPIA-161890-GO-R Project coordination, man Demande de pri Single Stage - On 2020-07-2 2020-09-1 2021-03-1 FQ / Fourniture des access IDA / 59080 agement, communication A posteriori Limited 7,000.00 0.00 Annulé x e Envelope 5 9 8 oires pour véhicule à l'UCR and monitoring Zone 1 CM-MINEPIA-161881-GO-R Project coordination, man Demande de pri Single Stage - On 2020-04-2 2020-06-1 2020-08-0 FQ / Achat divers fournitur IDA / 59080 agement, communication A posteriori Limited 6,000.00 0.00 Annulé x e Envelope 3 8 2 es de bureau (papiers, che and monitoring mises, etc.) CM-MINEPIA-161869-GO-R Project coordination, man FQ / Fourniture des service Demande de pri Single Stage - On 2020-07-2 2020-09-1 2021-03-1 IDA / 59080 agement, communication A posteriori Limited 5,000.00 0.00 Annulé s de maintenance réseau é x e Envelope 1 5 4 and monitoring lectrique, du groupe électr ogène à l’UCNP (sur 1 an) CM-MINEPIA-161899-GO-R Project coordination, man Demande de pri Single Stage - On 2020-06-2 2020-08-1 2020-09-2 FQ / Achat de Supports de IDA / 59080 agement, communication A posteriori Limited 4,167.00 0.00 Annulé x e Envelope 1 6 5 Communication à l’UCR Zo and monitoring ne 3 CM-MINEPIA-161822-GO-R Project coordination, man FQ / Fourniture des service Demande de pri Single Stage - On 2020-08-0 2020-09-2 2021-03-2 IDA / 59080 agement, communication A posteriori Limited 400.00 0.00 Annulé s d’Entretien et de Mainte x e Envelope 2 7 6 and monitoring nance du Circuit Electrique et d’Eau à l'UCR Zone 3 CM-MINEPIA-161861-GO-R Project coordination, man Demande de pri Single Stage - On 2020-07-0 2020-08-3 2020-09-2 FQ / Fourniture du matériel IDA / 59080 agement, communication A posteriori Limited 41,667.00 0.00 Annulé x e Envelope 5 0 9 roulant 01 véhicule pour l' and monitoring UCR1 CM-MINEPIA-161908-GO-R Project coordination, man Demande de pri Single Stage - On 2021-08-2 2021-10-1 2021-12-1 FQ / Achat des Fournitures IDA / 59080 agement, communication A posteriori Limited 5,000.00 0.00 Annulé x e Envelope 3 8 7 de bureaux de PFD à l’UCR and monitoring Zone 3 CM-MINEPIA-161885-GO-R Project coordination, man FQ / Fourniture des service Demande de pri Single Stage - On 2021-09-2 2021-11-2 2021-12-2 IDA / 59080 agement, communication A posteriori Limited 3,000.00 0.00 Annulé s d'Entretien matériels info x e Envelope 8 3 3 and monitoring rmatiques à l'UCR Zone 1 CM-MINEPIA-161827-GO-R Improvement of Livestock FB / Fourniture du matériel Single Stage - On 2020-07-2 2020-08-2 2020-08-0 2020-09-0 2020-09-1 2020-10-2 2021-03-2 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 166,667.00 0.00 Annulé de prélèvement dans le ca e Envelope 8 1 2 1 6 1 0 ery dre des enquêtes post vac cinales sur la PPR CM-MINEPIA-161905-GO-R Project coordination, man Demande de pri Single Stage - On 2020-06-0 2020-07-3 2020-09-1 FQ / Fourniture des Fourni IDA / 59080 agement, communication A posteriori Limited 6,667.00 0.00 Annulé x e Envelope 4 0 3 tures de bureaux de l’UCR and monitoring 3 CM-MINEPIA-98777-GO-RF Q / Production, édition et Improvement of Livestock Demande de pri Single Stage - On 2019-07-0 2019-08-1 2019-09-1 multiplication des guides p IDA / 59080 Services Access and Deliv A posteriori Limited 4,200.00 0.00 Annulé x e Envelope 1 6 5 roduits check list de bioséc ery uité, normes et standard d e qualité sanitaire) - UCN¨ P et UCR CM-MINEPIA-98766-GO-RF Improvement of Livestock Q / Production et édition d Demande de pri Single Stage - On 2019-07-0 2019-08-1 2019-09-1 IDA / 59080 Services Access and Deliv A posteriori Limited 5,900.00 0.00 Annulé es guides de contrôle et d x e Envelope 2 7 6 ery e lutte contre les maladies vectorielles CM-MINEPIA-161852-GO-R Improvement of Livestock FQ / Production des suppor Demande de pri Single Stage - On 2020-04-0 2020-05-2 2020-07-2 IDA / 59080 Services Access and Deliv A posteriori Limited 3,500.00 0.00 Annulé ts dans le cadre de la surv x e Envelope 1 7 6 ery eillance des maladies anim ales CM-MINEPIA-215680-GO-R Improvement of Livestock Open - Internatio Single Stage - On 2021-10-2 2021-11-0 2021-12-1 2022-01-1 2022-02-1 2022-08-1 IDA / 59080 A posteriori Appel d'offres 672,897.00 0.00 Annulé FB / ACHAT DE DEUX (02) Services Access and Deliv nal e Envelope 8 2 4 3 7 6 TRACTEURS ery CM-MINEPIA-106313-GO-R Improvement of Livestock Demande de pri Single Stage - On 2019-06-0 2019-09-0 2019-07-3 2020-01-2 IDA / 59080 A posteriori Limited 52,000.00 0.00 Annulé FQ / Acquisition des produi Services Access and Deliv x e Envelope 5 4 1 7 ts vétérinaires ery Page 6 CM-MINEPIA-98763-GO-RF Improvement of Livestock Q / Production des support Demande de pri Single Stage - On 2019-10-0 2019-12-0 2019-12-3 IDA / 59080 Services Access and Deliv A posteriori Limited 3,500.00 0.00 Annulé s dans le cadre de la surve x e Envelope 6 1 1 ery illance des maladies anima les CM-MINEPIA-265527-GO-R FB / FOURNITURE DES VAC Improvement of Livestock Single Stage - On En cours d' 2021-12-2 2022-01-1 2022-01-0 2022-02-1 2022-03-2 2022-04-2 2022-07-2 CINS CONTRE LA FIEVRE A IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 750,000.00 0.00 e Envelope exécution 3 4 7 8 0 4 3 PHTEUSE DANS LE CADRE ery DU PROJET DE DEVELOPPE MENT DE L’ELEVAGE (PRO DEL) CM-MINEPIA-224703-GO-R Improvement of Livestock FQ / ACQUISITION ET INST Demande de pri Single Stage - On 2021-05-0 2021-06-2 2021-08-2 IDA / 59080 Services Access and Deliv A posteriori Limited 25,000.00 0.00 Annulé ALLATION DU MATERIEL IN x e Envelope 1 6 5 ery FORMATIQUE A LA RESCA M CM-MINEPIA-227853-GO-R FB / FOURNITURE D'UN SE Improvement of Livestock RVEUR ET D'UN DISPOSITI Open - Internatio Single Stage - On 2021-06-2 2021-07-2 2021-08-0 2021-08-1 2021-09-1 2022-07-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres 1,833,333.00 0.00 Annulé F PHOTOVOLTAIQUE POUR nal e Envelope 2 2 6 3 7 4 ery ENERGIE SOLAIRE AU LAB ORATOIRE NATIONAL VETE RINAIRE (LANAVET) CM-MINEPIA-98780-GO-RF Q / Édition et multiplicatio n des plans opérationnels Improvement of Livestock de lutte contre les maladie Demande de pri Single Stage - On 2019-05-0 2019-06-3 2019-08-2 IDA / 59080 Services Access and Deliv A posteriori Limited 6,500.00 0.00 Annulé s animales prioritaires et d x e Envelope 5 0 9 ery es outils de gestion et des plans de contingence des crises et situations d'urgen ce éligibles dans le sous-s ecteur de l'élevage UCNP CM-MINEPIA-98842-GO-RF Improvement of Livestock B / Acquisition du matériel Single Stage - On 2019-02-2 2020-05-2 2019-02-2 2019-03-1 2019-03-1 2019-03-2 2019-05-2 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 80,000.00 0.00 Annulé informatique pour le dispo e Envelope 0 9 5 2 7 4 3 ery sitif d'information sanitaire CM-MINEPIA-136691-GO-R Project coordination, man FQ / Fourniture du matériel Demande de pri Single Stage - On 2019-10-1 2019-11-1 2019-12-1 IDA / 59080 agement, communication A posteriori Limited 6,850.00 0.00 Annulé de Camping pour l'espace x e Envelope 2 1 1 and monitoring de restauration à l'UCNP P RODEL CM-MINEPIA-141290-GO-R FB / Fourniture des réactifs /consommables de laborat oires et analyse des échan Improvement of Livestock Single Stage - On 2019-12-1 2020-05-2 2019-12-1 2020-01-2 2020-02-2 2020-03-3 2023-03-3 tillons des enquêtes de ba IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 334,000.00 0.00 Annulé e Envelope 0 9 5 6 5 1 1 se (PPR, PPCB, FA, PPA, M ery NC) et post-vaccinale (PPR ) dans le cadre de la survei llance et le contrôle des m aladies animales prioritair es au Cameroun CM-MINEPIA-161862-GO-R Project coordination, man Demande de pri Single Stage - On 2020-07-0 2020-08-3 2021-02-2 FQ / Fourniture du matériel IDA / 59080 agement, communication A posteriori Limited 13,333.00 0.00 Annulé x e Envelope 5 0 6 de bureau à l’UCNP, semes and monitoring tre 1 et semestre 2 CM-MINEPIA-161864-GO-R Project coordination, man Demande de pri Single Stage - On 2020-05-2 2020-07-2 2020-09-0 FQ / Fourniture des conso IDA / 59080 agement, communication A posteriori Limited 20,000.00 0.00 Annulé x e Envelope 6 1 4 mmables informatiques et and monitoring d’un copieur à l’UCNP CM-MINEPIA-176259-GO-R FQ / Fourniture des masqu Support to livestock value Demande de pri Single Stage - On 2020-06-0 2020-07-3 2021-01-2 IDA / 59080 A posteriori Limited 5,000.00 0.00 Annulé es de protection personnal chains development x e Envelope 4 0 6 isés dans le cadre de la lut te contre le COVID-19 CM-MINEPIA-190090-GO-R Improvement of Pastoral P FQ / Fourniture petit matér roductivity, Access to Mar Demande de pri Single Stage - On 2021-09-2 2021-11-2 2021-12-2 iel de collecte des échantill IDA / 59080 A posteriori Limited 6,800.00 0.00 Annulé kets, and Resilience of Pa x e Envelope 9 4 4 ons pour la formation des storal Communities cadres du MINEPIA/Bilan fo urager CM-MINEPIA-161877-GO-R Project coordination, man Demande de pri Single Stage - On 2021-08-3 2021-10-2 2021-11-2 IDA / 59080 A posteriori Limited 3,083.00 0.00 Annulé FQ / Achat Consommables agement, communication x e Envelope 1 6 5 informatiques and monitoring CM-MINEPIA-176273-GO-R Support to livestock value Demande de pri Single Stage - On 2021-07-2 2021-09-2 2022-03-2 FQ / Fourniture du matériel IDA / 59080 A posteriori Limited 5,000.00 0.00 Annulé chains development x e Envelope 8 2 1 divers (nettoyage des bur eaux de l'UCNP) CM-MINEPIA-236913-GO-R FB / Sélection des ONG/Pre stataires pour la fourniture Improvement of Pastoral P des géniteurs en vue de la roductivity, Access to Mar Single Stage - On 2021-06-2 2021-09-2 2021-06-2 2021-09-2 2021-07-1 2021-07-1 2021-08-0 2021-10-0 IDA / 59080 A posteriori Appel d'offres Open - National 383,309.00 0.00 Annulé poursuite des appuis à la r kets, and Resilience of Pa e Envelope 2 0 7 9 1 8 8 7 ésilience des ménages aff storal Communities ectés par les conflits dans les trente-cinq (35) comm unes restantes - douze (12 ) dans la Région de l’Extrê CM-MINEPIA-237641-GO-R me Nord FB / FOURNITURE DES VAC Improvement of Pastoral P CINS CONTRE LA FIEVRE A roductivity, Access to Mar Open - Internatio Single Stage - On 2021-06-0 2021-07-0 2021-06-0 2021-06-2 2021-08-0 2021-07-0 2021-09-1 2021-08-0 2021-11-0 IDA / 59080 A posteriori Appel d'offres 750,000.00 0.00 Annulé PHTEUSE DANS LE CADRE kets, and Resilience of Pa nal e Envelope 1 8 6 0 5 4 7 8 6 DU PROJET DE DEVELOPPE storal Communities MENT DE L’ELEVAGE (PRO DEL), EN PROCEDURE D’U RGENCE CM-MINEPIA-245288-GO-R Support to livestock value Single Stage - On 2021-09-0 2021-09-0 2021-10-1 2021-11-1 2021-12-2 2022-06-2 FB / ACQUISITION DE DOU IDA / 59080 A posteriori Appel d'offres Limited 50,000.00 0.00 Annulé chains development e Envelope 1 6 8 7 2 0 ZE (12) MOTOS DANS LE C ADRE DU PRODEL CM-MINEPIA-237940-GO-R FQ / FOURNITURE DES PRO Project coordination, man DUITS VETERINAIRES A L'U Demande de pri Single Stage - On 2021-06-2 2021-08-2 2022-02-1 IDA / 59080 agement, communication A posteriori Limited 100,000.00 0.00 Annulé NITE DE COORDINATION N x e Envelope 6 1 7 and monitoring ATIONALE ET AUX TROIS U NITES DE COORDINATION REGIONALES DU PRODEL CM-MINEPIA-238097-GO-R FB / fourniture et installati Support to livestock value Single Stage - On 2021-06-3 2021-07-0 2021-08-1 2021-09-1 2021-10-2 2022-01-1 IDA / 59080 A posteriori Appel d'offres Open - National 500,000.00 0.00 Annulé on d'une autoclave et du chains development e Envelope 0 5 6 5 0 8 matériel de froid au LANAV ET CM-MINEPIA-238098-GO-R Project coordination, man FB / fourniture du matériel Single Stage - On 2021-06-3 2021-07-0 2021-08-1 2021-09-1 2021-10-2 2021-11-1 IDA / 59080 agement, communication A posteriori Appel d'offres Open - National 300,000.00 0.00 Annulé de travail aux responsable e Envelope 0 5 6 5 0 9 and monitoring s des unités opérationnelle s du MINEPIA CM-MINEPIA-238094-GO-R Improvement of Livestock Demande de pri Single Stage - On 2021-11-2 2022-01-2 2022-07-2 FQ / acquisition du matérie IDA / 59080 Services Access and Deliv A posteriori Open - National 50,000.00 0.00 Annulé x e Envelope 8 3 2 l roulant au profit des équi ery pes des faitières CM-MINEPIA-245501-GO-R FQ / Fourniture de matériel Support to livestock value Demande de pri Single Stage - On 2021-08-2 2021-09-2 2021-10-2 de prélèvement aux servic IDA / 59080 A posteriori Limited 50,000.00 0.00 Annulé chains development x e Envelope 5 2 2 es vétérinaires dans les zo nes à risque de Peste des Petits Ruminants CM-MINEPIA-245495-GO-R FQ / Fourniture de kits de r Support to livestock value Demande de pri Single Stage - On 2021-10-2 2021-12-2 2022-06-1 IDA / 59080 A posteriori Limited 41,667.00 0.00 Annulé iposte (atomiseurs) dans l chains development x e Envelope 5 0 8 e cadre de gestion des foy ers de PPR CM-MINEPIA-245282-GO-R Project coordination, man FQ / Acquisition du matéri Demande de pri Single Stage - On 2021-07-2 2021-09-2 2022-03-2 IDA / 59080 agement, communication A posteriori Limited 38,333.00 0.00 Annulé el informatique compléme x e Envelope 8 2 1 and monitoring ntaire pour l'UCNP PRODEL CM-MINEPIA-223624-GO-R FQ / ACQUISITION DES FO Improvement of Pastoral P URNITURES POUR LA MISE roductivity, Access to Mar Demande de pri Single Stage - On 2021-07-0 2021-08-2 2021-09-2 IDA / 59080 A posteriori Limited 16,667.00 0.00 Annulé EN PLACE DU DISPOSITIF D kets, and Resilience of Pa x e Envelope 4 9 8 E SUIVI DES RESSOURCES storal Communities FOURRAGERES ET ELABOR ATION DU BILAN FOURRAG ER CM-MINEPIA-215678-GO-R Improvement of Livestock Demande de pri Single Stage - On 2021-05-3 2021-07-2 2021-10-2 FQ / FOURNITURE DE GENI IDA / 59080 Services Access and Deliv A posteriori Limited 140,187.00 0.00 Annulé x e Envelope 0 5 3 TEURS DE PETITS RUMINA ery NTS CM-MINEPIA-215653-GO-R FQ / ACQUISITION DES FO Project coordination, man Demande de pri Single Stage - On 2022-03-0 2022-03-0 2022-04-0 2022-03-2 2022-04-0 URNITURES COMPLEMENT IDA / 59080 agement, communication A posteriori Limited 16,822.00 18,173.04 Signé x e Envelope 7 7 4 8 7 AIRES POUR LE COMPTE D and monitoring E L'UNITE DE COORDINATI ON NATIONALE DU PROJET CM-MINEPIA-215651-GO-R FQ / ACQUISITION DES CO Project coordination, man NSOMMABLES INFORMATI Demande de pri Single Stage - On 2022-03-0 2022-03-0 2022-04-0 2022-03-2 2022-05-0 IDA / 59080 agement, communication A posteriori Limited 16,822.00 18,090.08 Signé QUES COMPLEMENTAIRES x e Envelope 5 8 2 9 2 and monitoring POUR LE COMPTE DE L'UNI TE DE CORDINATION NATI ONALE DU PROJET CM-MINEPIA-215657-GO-R FQ / ACQUISITION, INSTALL Project coordination, man Demande de pri Single Stage - On 2021-11-0 2022-01-0 2022-02-0 ATION ET AMENAGEMENT IDA / 59080 agement, communication A posteriori Open - National 37,383.00 0.00 Annulé x e Envelope 4 6 5 D'UN CONTENEUR POUR L' and monitoring ARCHIVAGE DES DOCUME NTS DU PRODEL CM-MINEPIA-215681-GO-R Improvement of Livestock Single Stage - On 2021-09-3 2021-10-0 2021-11-1 2021-12-1 2022-01-2 2022-04-2 FB / ACQUSITION DES ALIM IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 201,869.00 0.00 Annulé e Envelope 0 5 6 6 0 0 ENTS ET MATIERES PREMIE ery RES CM-MINEPIA-216210-GO-R Improvement of Livestock FQ / ACQUISITION DES MA Demande de pri Single Stage - On 2021-08-0 2021-10-2 2022-04-1 IDA / 59080 Services Access and Deliv A posteriori Open - National 56,075.00 0.00 Annulé TERIELS ROULANTS AU PR x e Envelope 5 1 9 ery OFIT DES EQUIPES DES FAI TIERES CM-MINEPIA-216197-GO-R Improvement of Livestock Demande de pri Single Stage - On 2021-06-0 2021-07-1 2021-07-3 FQ / ACQUISITION CARBUR IDA / 59080 Services Access and Deliv A posteriori Open - National 16,822.00 0.00 Annulé x e Envelope 5 0 1 ANT POUR LES EQUIPES D ery E BILAN FOURRAGER CM-MINEPIA-161884-GO-R FQ / Fourniture des service Project coordination, man Demande de pri Single Stage - On 2020-07-0 2020-08-2 2021-02-2 s d'Entretien Clim, circuit é IDA / 59080 agement, communication A posteriori Limited 6,833.34 0.00 Annulé x e Envelope 1 6 2 lectriques, remplacement and monitoring des lampes, groupes électr ogène, extincteur et autre s CM-MINEPIA-224102-GO-R Improvement of Livestock Demande de pri Single Stage - On 2021-10-0 2021-11-3 2022-05-2 IDA / 59080 A posteriori Limited 50,000.00 0.00 Annulé FQ / ACQUISITION DES ALI Services Access and Deliv x e Envelope 5 0 9 MENTS PORCINS ery CM-MINEPIA-216215-GO-R FQ / ACQUISITION DES EQ Improvement of Livestock Demande de pri Single Stage - On 2021-06-0 2021-07-2 2021-07-3 UIPEMENTS ET MATERIELS IDA / 59080 Services Access and Deliv A posteriori Open - National 93,458.00 0.00 Annulé x e Envelope 8 5 1 POUR LES MAISONS DES E ery LEVEURS, LES MAISONS D ES APICULTEURS ET LE SIT E DE FOIRE CM-MINEPIA-216115-GO-R FQ / ACQUISITION DU MAT Improvement of Livestock Demande de pri Single Stage - On 2021-06-2 2021-08-1 2021-09-2 ERIEL POUR L'ORGANISATI IDA / 59080 Services Access and Deliv A posteriori Open - National 18,692.00 0.00 Annulé x e Envelope 0 5 9 ON DES EXERCICES DE SI ery MULATION DES CRISES CLI MATIQUES CM-MINEPIA-245514-GO-R FQ / Fourniture de glacière Support to livestock value Demande de pri Single Stage - On 2021-09-2 2021-10-2 2022-01-2 s à longue durée de conse IDA / 59080 A posteriori Open - National 41,667.00 0.00 Annulé chains development x e Envelope 8 6 4 rvation au profit des servic es vétérinaires à fort risqu e de Peste de Petits Rumin ants CM-MINEPIA-215975-GO-R Improvement of Livestock FB / FOURNITURE DE TREN Open - Internatio Single Stage - On 2021-05-1 2021-05-2 2021-06-0 2021-07-2 2021-08-2 2022-02-2 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres 229,907.00 0.00 Annulé TE CINQ (35) TONNES DE S nal e Envelope 2 6 9 4 8 4 ery EMENCES FOURRAGERES CM-MINEPIA-238108-GO-R FB / fourniture de matériel Improvement of Livestock Single Stage - On 2021-10-2 2021-10-2 2021-12-0 2022-01-0 2022-02-0 2022-03-1 s devant servir aux bonnes IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 104,166.00 0.00 Annulé e Envelope 0 5 6 5 9 1 pratiques d'hygiène et de ery salubrité aux acteurs de la filière viande CM-MINEPIA-136706-GO-R Project coordination, man FQ / Fourniture de caméra, Demande de pri Single Stage - On 2019-10-2 2019-11-2 2019-12-0 IDA / 59080 agement, communication A posteriori Limited 6,900.00 0.00 Annulé microphone et lampe pour x e Envelope 3 2 7 and monitoring la communication du PRO DEL CM-MINEPIA-265528-GO-R FB / FOURNITURE EN SEPT (07) LOTS DES GENITEURS Improvement of Pastoral P (PETITS RUMINANTS) POU roductivity, Access to Mar Single Stage - On En cours d' 2022-03-3 2022-04-0 2022-05-0 2022-06-1 2022-07-1 2022-08-2 2022-11-1 R LES MENAGES PAUVRES IDA / 59080 A posteriori Appel d'offres Open - National 826,388.88 0.00 kets, and Resilience of Pa e Envelope exécution 1 4 6 7 7 1 9 AFFECTES PAR LES CONFLI storal Communities TS DANS LES REGIONS DU NORD ET DE L’EXTREME-N ORD CAMEROUN DANS LE CADRE DU PROJET DE DEV ELOPPEMENT DE L’ELEVAG ECM-MINEPIA-223628-GO-R (PRODEL) Improvement of Livestock Demande de pri Single Stage - On 2022-04-0 2022-06-1 2022-04-2 2022-07-2 FQ / ACQUISITION DES SE IDA / 59080 Services Access and Deliv A posteriori Open - National 53,334.00 41,666.10 Signé x e Envelope 5 4 9 9 MENCES FOURRAGER ery CM-MINEPIA-285903-GO-D IR / Fourniture de 40 moto Improvement of Livestock Passation de m 2022-05-1 2022-01-1 2022-05-2 2022-01-2 2022-06-0 2022-03-3 2022-12-0 2022-05-1 cyclettes tout terrain dans IDA / 59080 Services Access and Deliv A posteriori arché de gré à g Direct 133,333.00 103,099.02 Achevé 8 0 3 2 6 1 3 1 le cadre de l’appui à l’insta ery ré llation des jeunes vétérinai res (40) CM-MINEPIA-285907-CW- Improvement of Livestock RFB / Mise en place d’un s Open - Internatio Single Stage - On 2022-04-1 2022-06-2 2022-05-0 2022-06-1 2022-07-0 2022-07-1 2022-12-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres 2,333,333.00 0.00 Annulé ystème solaire photovoltaï nal e Envelope 4 3 2 3 7 3 0 ery que pour l’alimentation éle ctrique du LANAVET Page 7 CM-MINEPIA-297813-GO-R Project coordination, man En attente FQ / Supports de marquag Demande de pri Single Stage - On 2022-08-0 2022-09-1 2022-10-1 IDA / 59080 agement, communication A posteriori Limited 16,666.67 0.00 d'exécutio e des sites (communicatio x e Envelope 6 0 0 and monitoring n n muette -plaques diverse s et écriteaux) CM-MINEPIA-297817-GO-R Project coordination, man FQ / Acquisition des autres Demande de pri Single Stage - On En cours d' 2022-07-2 2022-08-2 2022-09-2 IDA / 59080 agement, communication A posteriori Limited 63,541.67 0.00 fournitures de bureau pour x e Envelope exécution 0 4 3 and monitoring le compte de l'année 2022 CM-MINEPIA-300375-GO-R FB / Fourniture des réactifs Improvement of Livestock En attente et consommables de labor Single Stage - On 2022-08-0 2022-08-0 2022-08-2 2022-09-1 2022-09-2 2022-12-2 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 325,928.00 0.00 d'exécutio atoire au LANAVET dans le e Envelope 1 6 7 0 4 3 ery n cadre de la gestion du foy er de grippe aviaire en cou rs à l'Ouest Cameroun CM-MINEPIA-286036-GO-R Project coordination, man En attente FQ / Fourniture des Conso Demande de pri Single Stage - On 2022-07-0 2022-07-3 2022-08-2 IDA / 59080 agement, communication A posteriori Limited 56,875.00 0.00 d'exécutio mmables informatiques po x e Envelope 5 0 9 and monitoring n ur le compte de l'année 20 22 CM-MINEPIA-285981-GO-R Improvement of Pastoral P Demande de pri Single Stage - On En cours d' 2022-07-0 2022-07-3 2022-09-2 FQ / Acquisition d’aliment IDA / 59080 roductivity, Access to Mar A posteriori Open - National 93,333.00 0.00 x e Envelope exécution 2 1 9 pour bovins (3ème vague) kets, and Resilience of Pa storal Communities CM-MINEPIA-285995-GO-R FQ / ACQUISITION, INSTALL Project coordination, man ATION ET AMENAGEMENT Demande de pri Single Stage - On En cours d' 2022-07-0 2022-09-0 2022-11-0 IDA / 59080 agement, communication A posteriori Open - National 61,137.00 0.00 DES CONTENEURS POUR L' x e Envelope exécution 5 4 3 and monitoring ARCHIVAGE PHYSIQUE AU PROJET DE DEVELOPPEME NT DE L'ELEVAGE (PRODEL ) CM-MINEPIA-285985-GO-R Improvement of Pastoral P Demande de pri Single Stage - On En cours d' 2022-06-2 2022-08-0 2022-10-0 FQ / Acquisition d’aliment IDA / 59080 roductivity, Access to Mar A posteriori Open - National 66,666.00 0.00 x e Envelope exécution 8 7 6 pour porcins (2ème vague) kets, and Resilience of Pa storal Communities CM-MINEPIA-285986-GO-R Improvement of Pastoral P Demande de pri Single Stage - On En cours d' 2022-06-2 2022-07-2 2022-09-2 FQ / Acquisition des semen IDA / 59080 roductivity, Access to Mar A posteriori Limited 50,000.00 0.00 x e Envelope exécution 8 9 7 ces bovines kets, and Resilience of Pa storal Communities CM-MINEPIA-285905-GO-R Improvement of Livestock FQ / Fourniture de 40 kits i Demande de pri Single Stage - On En cours d' 2022-07-2 2022-08-2 2022-10-0 IDA / 59080 Services Access and Deliv A posteriori Limited 75,000.00 0.00 nformatiques dans le cadr x e Envelope exécution 0 0 4 ery e de l’appui à l’installation des jeunes vétérinaires CM-MINEPIA-285901-GO-R Improvement of Livestock En attente FB / Fourniture de vaccins Single Stage - On 2022-06-3 2022-07-0 2022-08-0 2022-08-1 2022-08-2 2022-11-2 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 450,000.00 0.00 d'exécutio pour le contrôle de la PPR e Envelope 0 5 4 8 6 4 ery n dans les zones à risque (S W, NW, EN, NO, AD, ES) CM-MINEPIA-285902-GO-R FB / Fourniture de matériel Improvement of Livestock de contrôle et d’éradicatio Single Stage - On En cours d' 2022-06-3 2022-07-1 2022-07-0 2022-08-0 2022-08-1 2022-08-2 2022-11-1 IDA / 59080 Services Access and Deliv A posteriori Appel d'offres Open - National 150,000.00 0.00 n de la PPR (lot 1 : matérie e Envelope exécution 0 5 5 4 1 1 9 ery l de froid, lot 2 : matériel d e prélèvement et lot 3 : m atériel de riposte) pour les zones à risque CM-MINEPIA-297808-GO-D Passation de m En attente IR / Fourniture de médica Support to livestock value Direct - Internati 2022-07-2 2022-08-0 2022-08-1 2022-10-1 IDA / 59080 A posteriori arché de gré à g 76,667.00 0.00 d'exécutio ments dans le cadre de la chains development onal 9 3 7 6 ré n mise en place de 2000 pro tocoles PRID CM-MINEPIA-305176-GO-R Improvement of Livestock En attente FB / Mise en place d’un sys Open - Internatio Single Stage - On 2022-07-2 2022-08-0 2022-09-1 2022-10-0 2022-11-0 2023-01-3 IDA / 59080 Services Access and Deliv A priori Appel d'offres 2,333,333.00 0.00 d'exécutio tème solaire photovoltaïqu nal e Envelope 9 3 4 4 1 0 ery n e pour l’alimentation élect rique du LANAVET NON CONSULTING SERVICES Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amou Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) nt (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-MINEPIA-24478-NC-RF Project coordination, man Demande de pri Single Stage - On 2017-09-2 2017-12-1 2018-05-2 2018-12-1 2018-08-1 IDA / 59080 A posteriori Open - National 80,000.00 78,247.25 Achevé Q / Assurances diverses agement, communication x e Envelope 4 2 5 2 0 and monitoring CM-MINEPIA-31466-NC-RF Q / Gardiennage des burea Project coordination, man Demande de pri Single Stage - On 2017-11-1 2018-01-2 2018-01-1 2019-01-2 ux de l'Unité de Coordinati IDA / 59080 agement, communication A posteriori Open - National 35,000.00 37,893.41 Signé x e Envelope 8 0 5 0 on Nationale et des 03 Uni and monitoring tés de Coordinations Régio nales du PRODEL CM-MINEPIA-50668-NC-RF Improvement of Livestock Demande de pri Single Stage - On 2018-06-0 2018-07-3 2019-01-2 B / Opérationnalisation de IDA / 59080 Services Access and Deliv A posteriori Limited 100,000.00 0.00 Annulé x e Envelope 5 1 7 l'IA (insémination artificiell ery e) CM-MINEPIA-68579-NC-RF Project coordination, man Q / Dédouanement et enlè Demande de pri Single Stage - On 2018-07-1 2018-04-1 2018-09-1 2018-09-2 2018-10-1 IDA / 59080 agement, communication A posteriori Limited 28,500.00 26,232.42 Signé vement de dix (10) véhicul x e Envelope 6 0 0 8 0 and monitoring es du PRODEL au port de Douala CM-MINEPIA-68663-NC-RF Q / ENTRETIEN DES BUREA Project coordination, man Demande de pri Single Stage - On 2018-07-2 2018-07-0 2018-09-1 2018-08-0 2018-10-2 2019-07-0 UX DE L'UNITE DE COOOR IDA / 59080 agement, communication A posteriori Limited 6,950.00 7,383.07 Achevé x e Envelope 4 3 8 1 4 8 DINATION NATIONALE DU and monitoring PROJET DE DEVELOPPEME NT DE L'ELEVAGE (PRODEL ) CM-MINEPIA-91400-NC-RF Project coordination, man Q / Fourniture d'un service Demande de pri Single Stage - On En cours d' 2019-01-2 2019-06-0 2019-03-3 2020-03-3 IDA / 59080 agement, communication A posteriori Limited 3,340.00 0.00 pour l'entretien, le nettoya x e Envelope exécution 7 7 1 0 and monitoring ge et la logistique dans le s locaux de l'UCR Zone 2 CM-MINEPIA-91404-NC-RF Project coordination, man Q / Recrutement prestatair Demande de pri Single Stage - On En cours d' 2019-01-2 2019-06-0 2019-03-3 2020-03-3 IDA / 59080 agement, communication A posteriori Limited 3,340.00 0.00 e pour l'entretien, le netto x e Envelope exécution 7 7 1 0 and monitoring yage et la logistique dans l es des locaux de l'UCR Zo ne 1 CM-MINEPIA-93266-NC-RF Q / Fourniture de transport Improvement of Livestock Passation de m de génisses gestantes (aér 2019-01-0 2019-01-2 2019-01-2 2019-01-2 2019-02-2 2019-03-2 2019-03-2 IDA / 59080 Services Access and Deliv A posteriori arché de gré à g Direct 38,500.00 33,246.90 Signé oport Garoua à station de 7 3 2 5 6 6 8 ery ré Louguéré) et formalités do uanières relatif à l'acquisiti on des génisses gestantes CM-MINEPIA-68586-NC-RF Improvement of Livestock Q / Location de camions p Demande de pri Single Stage - On 2018-08-2 2018-10-2 2018-11-2 IDA / 59080 Services Access and Deliv A posteriori Limited 62,000.00 0.00 Annulé our transport d'animaux p x e Envelope 6 1 0 ery our lieu de débarquement au lieu de quarantaine CM-MINEPIA-106347-NC-R Project coordination, man Demande de pri Single Stage - On 2019-06-1 2019-08-3 2019-05-3 2020-08-2 2019-06-1 FQ / Assurance maladie de IDA / 59080 agement, communication A posteriori Open - National 83,500.00 65,497.92 Achevé x e Envelope 2 0 1 9 8 s personnels PRODEL and monitoring CM-MINEPIA-98849-NC-RF Improvement of Livestock Demande de pri Single Stage - On 2019-06-0 2019-07-0 2019-08-0 Q / Production des bulletin IDA / 59080 Services Access and Deliv A posteriori Limited 4,167.00 0.00 Annulé x e Envelope 5 4 3 s épidémiologiques ery CM-MINEPIA-159862-NC-R Improvement of Livestock Demande de pri Single Stage - On 2020-06-3 2020-09-0 2020-07-2 2020-09-2 2020-08-2 FQ / Production des suppor IDA / 59080 Services Access and Deliv A posteriori Limited 41,666.67 40,584.37 Signé x e Envelope 0 3 5 1 4 ts de vaccination dans le c ery adre du PRODEL CM-MINEPIA-98925-NC-RF Q / Edition, multiplication e Improvement of Livestock Demande de pri Single Stage - On 2019-02-2 2019-04-0 2019-05-0 t édition des guides des ac IDA / 59080 Services Access and Deliv A posteriori Limited 7,500.00 0.00 Annulé x e Envelope 8 9 9 tivités d'un chef de centre ery pour le MINEPIA et écoles de formation (CNFZV) - UC NP CM-MINEPIA-176269-NC-R Support to livestock value Demande de pri Single Stage - On 2020-06-3 2020-08-0 2020-08-0 2020-09-1 2020-08-2 2021-11-1 FQ / Production des suppor IDA / 59080 A posteriori Limited 50,000.00 31,533.16 Achevé chains development x e Envelope 0 7 7 5 8 2 ts de communications dan s le cadre du PRODEL CM-MINEPIA-238089-NC-R Project coordination, man Demande de pri Single Stage - On 2021-06-0 2021-12-2 2021-08-0 2022-02-0 2021-09-0 FQ / contractualisation des IDA / 59080 agement, communication A posteriori Limited 33,333.00 17,479.77 Signé x e Envelope 8 2 3 8 2 couvertures médiatiques and monitoring CM-MINEPIA-245274-NC-R Project coordination, man FQ / FOURNITURE DES PRE Demande de pri Single Stage - On 2021-07-2 2021-09-2 2021-11-1 2022-03-2 IDA / 59080 agement, communication A posteriori Open - National 44,800.00 27,325.08 Signé STATION DE GARDIENNAG x e Envelope 8 2 5 1 and monitoring E AU PROJET DE DEVELOPP EMENT DE LM'ELEVAGE CM-MINEPIA-215998-NC-R Project coordination, man Demande de pri 2021-06-2 2021-08-0 2022-07-2 FQ / CONCEPTION ET DIFF IDA / 59080 agement, communication A posteriori 18,692.00 0.00 Annulé x 9 3 9 USION DES SPOTS PUBLICI and monitoring TAIRES CM-MINEPIA-176253-NC-R Improvement of Livestock FQ / Édition et multiplicatio Demande de pri Single Stage - On 2021-08-0 2021-09-2 2022-03-2 IDA / 59080 Services Access and Deliv A posteriori Open - National 17,000.00 0.00 Annulé n des manuels d'inspectio x e Envelope 4 9 8 ery n sanitaire dans le cadre d u PRODEL CM-MINEPIA-215654-NC-R FQ / ACQUISITION D'UNE C Project coordination, man Demande de pri Single Stage - On 2021-06-2 2021-08-0 2022-07-3 ONNEXION INTERNET ET I IDA / 59080 agement, communication A posteriori Open - National 14,953.00 0.00 Annulé x e Envelope 3 4 0 NTRANET A L'UNITE DE CO and monitoring ORDINATION NATIONALE D U PROJET CM-MINEPIA-159863-NC-R Improvement of Livestock Demande de pri Single Stage - On 2020-05-0 2020-06-0 2020-07-0 FQ / Édition et multiplicatio IDA / 59080 Services Access and Deliv A posteriori Limited 7,500.00 0.00 Annulé x e Envelope 5 7 7 n du Manuel d'ISV dans le ery cadre du PRODEL CM-MINEPIA-162120-NC-R Project coordination, man Demande de pri Single Stage - On 2020-05-2 2020-07-2 2021-07-2 FQ / Fourniture des servic IDA / 59080 agement, communication A posteriori Limited 4,600.00 0.00 Annulé x e Envelope 5 7 7 es de nettoyage des burea and monitoring ux de l'UCR zone 1 CM-MINEPIA-68581-NC-RF Improvement of Livestock Demande de pri Single Stage - On 2018-08-1 2018-10-1 2018-12-1 Q / Opérationnalisation de IDA / 59080 Services Access and Deliv A posteriori Limited 100,000.00 0.00 Annulé x e Envelope 4 6 5 l'insémination artificielle (I ery A) CM-MINEPIA-176265-NC-R FQ / Diffusion d'un spot pu Support to livestock value Demande de pri Single Stage - On 2020-06-0 2020-07-0 2020-07-1 blicitaire de 17h55 à 22h s IDA / 59080 A posteriori Limited 7,200.00 0.00 Annulé chains development x e Envelope 3 4 9 ur Canal2 et 16h à 20h sur Vision 4 dans le cadre de l a campagne de vaccinatio n au PRODEL CM-MINEPIA-190088-NC-R Project coordination, man FQ / Fourniture des service Demande de pri Single Stage - On 2021-09-2 2021-11-2 2021-12-2 IDA / 59080 agement, communication A posteriori Limited 6,800.00 0.00 Annulé s de couverture médiatiqu x e Envelope 9 4 4 and monitoring e pour la campagne de va ccination CM-MINEPIA-215656-NC-R Project coordination, man Demande de pri Single Stage - On 2021-07-2 2021-09-1 2022-03-1 FB / ACQUISITION D'UNE A IDA / 59080 agement, communication A posteriori Open - National 56,075.00 0.00 Annulé x e Envelope 5 9 8 SSURANCE VEHICULES DU and monitoring PRODEL CM-MINEPIA-215655-NC-R FB / ACQUISITION D'UNE A Project coordination, man Demande de pri Single Stage - On 2021-07-1 2021-09-0 2022-03-0 SSURANCE MALADIE POUR IDA / 59080 agement, communication A posteriori Open - National 87,850.00 0.00 Annulé x e Envelope 4 8 7 LE COMPTE DU PERSONNE and monitoring L DU PRODEL ET DE LEURS AYANTS DROITS CM-MINEPIA-238096-NC-R FQ / acquisition d'une flott Improvement of Livestock Demande de pri Single Stage - On 2021-07-1 2021-09-0 2022-09-0 e de communication dans l IDA / 59080 Services Access and Deliv A posteriori Limited 83,333.00 0.00 Annulé x e Envelope 4 8 3 e cadre du système d'infor ery mations de la Direction de la Santé Vétérinaire (SI/DS V) CM-MINEPIA-215997-NC-R Project coordination, man Demande de pri Single Stage - On 2021-10-2 2021-12-0 2022-12-0 FQ / RELECTURE, PRODUC IDA / 59080 agement, communication A posteriori Limited 37,383.00 0.00 Annulé x e Envelope 7 8 3 TION ET IMPRESSION MAG and monitoring AZINE PAPIER CM-MINEPIA-215682-NC-R FQ / RECRUTEMENT D'UN Project coordination, man Demande de pri Single Stage - On 2021-05-0 2021-06-2 2022-06-1 PRESTATAIRE POUR LA SE IDA / 59080 agement, communication A posteriori Open - National 50,243.00 0.00 Annulé x e Envelope 5 3 8 CURISATION DES LOCAUX and monitoring ABRITANT L'UNITE DE COO RDINATION NATIONALE DU PROJET CM-MINEPIA-215649-NC-R Project coordination, man FQ / ENTRETIEN DU MATER Demande de pri Single Stage - On 2021-06-0 2021-07-0 2022-06-2 IDA / 59080 agement, communication A posteriori Open - National 13,458.00 0.00 Annulé IEL INFORMATIQUE ET DU x e Envelope 5 2 7 and monitoring SERVEUR DE L'UNITE DE C OORDINATION DU PROJET CM-MINEPIA-223858-NC-R Improvement of Livestock Demande de pri Single Stage - On 2021-06-2 2021-08-2 2022-08-1 FQ / RECRUTEMENT D'UN IDA / 59080 Services Access and Deliv A posteriori Limited 48,334.00 0.00 Annulé x e Envelope 8 3 8 PRESTATAIRE POUR LE TR ery ANSPORT D'ANIMAUX CM-MINEPIA-216000-NC-R Project coordination, man Demande de pri Single Stage - On 2022-04-2 2022-05-2 2023-02-1 FQ / ENTRETIEN DES VEHI IDA / 59080 agement, communication A posteriori Limited 22,430.00 0.00 Annulé x e Envelope 2 0 4 CULES DE L'UNITE DE COO and monitoring RDINATION DU PROJET CM-MINEPIA-265526-NC-R Project coordination, man Demande de pri Single Stage - On 2022-04-2 2022-06-2 2023-07-1 FQ / FOURNITURE DE CON IDA / 59080 agement, communication A posteriori Limited 21,666.66 0.00 Annulé x e Envelope 7 2 7 NEXION INTERNET EN LIAI and monitoring SON SPECIALISEE (LS) CONSULTING FIRMS Activity Reference No. Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Intere Request for Proposa Opening of Technica Evaluation of Techn / Description Component Review Type Method Terms of Reference Request for Proposa n Report and Draft Signed Contract Contract Completion No. ch ount (US$) nt (US$) s st Notice ls as Issued l Proposals / Minutes ical Proposal ls Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 8 CM-MINEPIA-24430-CS-CQ Sélection fondé S / Elaboration d'une strat Improvement of Livestock e sur les qualific 2017-10-0 2017-09-0 2017-10-2 2017-12-2 2017-10-3 2018-01-2 2018-02-0 2018-02-2 2018-03-1 2018-05-2 égie nationale d'améliorati IDA / 59080 Services Access and Deliv A posteriori Open - National 150,000.00 124,936.52 Signé ations des cons 5 6 6 1 0 0 9 4 4 5 on génétique animale, ass ery ultants orti d'un plan d'investisse ment des cinq stations d'él evage CM-MINEPIA-24438-CS-QC Improvement of Pastoral P Sélection fondé BS / Elaboration des plans roductivity, Access to Mar Open - Internatio 2017-12-0 2018-01-0 2018-02-1 2018-05-2 2018-06-1 2018-08-2 2018-11-0 2019-05-0 IDA / 59080 A priori e sur la qualité 750,000.00 0.00 Annulé de gestion des ressources kets, and Resilience of Pa nal 7 6 9 0 9 4 7 6 et le coût pastorales assortis dessou storal Communities s projets des communes (4 lots) CM-MINEPIA-24456-CS-CQ Improvement of Livestock Sélection fondé 2017-08-3 2017-07-2 2017-09-2 2017-11-1 2017-08-2 2017-12-1 2017-10-1 2018-01-2 2017-11-0 2018-04-2 2018-07-0 S / Elaboration d'un plan d IDA / 59080 Services Access and Deliv A posteriori e sur les qualific Open - National 82,000.00 69,256.79 Achevé 1 3 8 1 8 1 0 6 3 6 9 e formation des acteurs du ery ations des cons secteur de l'élevage ultants CM-MINEPIA-24471-CS-CQ Sélection fondé S / Etude du marché de via Support to livestock value e sur les qualific 2017-11-0 2017-11-3 2018-01-1 2018-02-1 2018-04-0 2018-07-0 IDA / 59080 A posteriori Open - National 50,000.00 0.00 Annulé nde de porcs, volailles et d chains development ations des cons 2 0 3 2 2 1 e bétail (bovins et petits ru ultants minants) CM-MINEPIA-24479-CS-CQ Project coordination, man Sélection fondé 2017-09-2 2017-09-0 2017-10-1 2017-12-1 2017-10-1 2018-01-1 2017-12-0 2018-03-0 2018-01-0 2018-06-2 2018-06-2 S / Étude de référence du IDA / 59080 agement, communication A posteriori e sur les qualific Open - National 70,000.00 93,625.18 Achevé 8 4 9 9 5 8 6 1 5 9 1 Projet and monitoring ations des cons ultants CM-MINEPIA-24451-CS-CQ Sélection fondé S / Révision des plans de l Improvement of Livestock e sur les qualific 2017-09-0 2016-06-1 2017-10-0 2017-11-1 2016-11-2 2017-12-1 2018-01-3 2018-02-1 2018-02-2 2018-05-1 2018-07-3 utte contre les maladies a IDA / 59080 Services Access and Deliv A posteriori Open - National 70,000.00 51,237.86 Achevé ations des cons 7 7 5 8 7 8 1 4 7 5 0 nimales prioritaires (PPR, F ery ultants A, PPCB, MNC, GA, PPA) as sortis des plans de riposte CM-MINEPIA-31961-CS-CQ Sélection fondé S / Elaboration d'un plan st Improvement of Livestock e sur les qualific Open - Internatio 2016-06-1 2017-10-1 2016-07-0 2017-10-2 2017-11-2 2017-11-2 2017-12-2 2018-03-0 ratégique et d'un plan opé IDA / 59080 Services Access and Deliv A posteriori 60,000.00 0.00 Annulé ations des cons nal 7 1 8 3 7 2 7 7 rationneldecontrôle et de l ery ultants utte contre les maladies a nimales prioritaires au Ca meroun CM-MINEPIA-47993-CS-QC Sélection fondé BS / Recrutement des Con Support to livestock value Open - Internatio 2018-02-2 2018-03-1 2018-04-2 2018-05-0 2018-05-1 2018-06-1 2018-07-2 2019-01-1 IDA / 59080 A priori e sur la qualité 250,000.00 0.00 Annulé sultants pour l'accompagn chains development nal 2 5 8 8 8 8 3 9 et le coût ement des OP dans leur d éveloppement organisatio nnel CM-MINEPIA-48131-CS-CQ Sélection fondé Support to livestock value Open - Internatio 2018-03-2 2018-04-1 2018-06-0 2018-07-0 2018-08-0 2019-02-0 S / Etude de marchés de fil IDA / 59080 A posteriori e sur les qualific 84,000.00 0.00 Annulé chains development nal 9 9 2 2 6 2 ières de viande de porcs ations des cons ultants CM-MINEPIA-48142-CS-CQ Sélection fondé Support to livestock value Open - Internatio 2018-03-2 2018-04-1 2018-06-0 2018-07-0 2018-08-0 2019-02-0 S / Etude de marchés de fil IDA / 59080 A posteriori e sur les qualific 84,000.00 0.00 Annulé chains development nal 9 9 2 2 6 2 ières de viande de volaille ations des cons s ultants CM-MINEPIA-48143-CS-CQ Sélection fondé Support to livestock value Open - Internatio 2018-03-2 2018-04-1 2018-05-2 2018-06-2 2018-07-3 2019-01-2 S / Etude de marchés de fil IDA / 59080 A posteriori e sur les qualific 84,000.00 0.00 Annulé chains development nal 2 2 6 5 0 6 ières de viande de bétail ations des cons ultants CM-MINEPIA-50634-CS-CQ S / Sélection ONG en vue d Improvement of Pastoral P Sélection fondé e l'octroi des appuis aux in roductivity, Access to Mar e sur les qualific 2018-03-1 2018-07-1 2018-04-0 2018-04-2 2018-09-0 2018-05-0 2018-10-1 2018-06-0 2018-12-1 2018-12-0 IDA / 59080 A posteriori Open - National 25,000.00 9,375.70 Signé vestissements dans les int kets, and Resilience of Pa ations des cons 1 0 1 5 5 5 6 5 3 2 erventions agricoles relati storal Communities ultants ves à la nutrition dans les régions de l'Extrême-Nord CM-MINEPIA-50638-CS-CQ S / Sélection ONG pour l'él Sélection fondé aboration et la mise en œu Support to livestock value e sur les qualific 2018-03-2 2018-03-2 2018-04-1 2018-04-1 2018-05-0 2018-05-2 2018-05-1 2018-07-1 2018-06-2 2018-07-2 2018-10-2 vre d'un plan d'actions spé IDA / 59080 A posteriori Open - National 30,000.00 32,135.94 Signé chains development ations des cons 5 6 5 7 9 5 9 1 3 5 1 cifiques en faveur des pop ultants ulations pygmées (Bakas) dans le département de la Boumba et Ngoko, région de l'EST CM-MINEPIA-50643-CS-CQ S / Sélection ONG pour l'él Sélection fondé aboration et la mise en œu Support to livestock value e sur les qualific 2018-03-2 2018-03-2 2018-04-1 2018-04-1 2018-05-0 2018-05-2 2018-05-1 2018-07-1 2018-06-2 2018-07-2 2018-10-2 IDA / 59080 A posteriori Open - National 30,000.00 321,359.40 Signé vre d'un plan d'actions spé chains development ations des cons 5 6 5 7 9 5 9 1 3 5 1 cifiques en faveur des pop ultants ulations pygmées (Bakas) dans le département de la Cadey CM-MINEPIA-50648-CS-CQ S / Sélection ONG pour l'él Sélection fondé aboration et la mise en œu Support to livestock value e sur les qualific 2018-03-2 2018-03-2 2018-04-1 2018-04-1 2018-05-0 2018-05-2 2018-05-1 2018-07-1 2018-06-2 2018-07-2 2018-10-2 IDA / 59080 A posteriori Open - National 27,000.00 28,922.35 Signé vre d'un plan d'actions spé chains development ations des cons 5 6 5 7 9 5 9 1 3 5 1 cifiques en faveur des pop ultants ulations pygmées (Bakas) dans le département du H aut Nyong CM-MINEPIA-50844-CS-CQ S / Recrutement d'une ON G/Association pour la Séle Improvement of Pastoral P Sélection fondé ction des femmes bénéfici roductivity, Access to Mar e sur les qualific 2018-05-0 2018-07-1 2018-05-2 2018-07-0 2018-09-0 2018-07-1 2018-10-1 2018-08-0 2018-12-1 2018-11-0 aires, l'Identification des b IDA / 59080 A posteriori Open - National 83,133.00 51,065.94 Signé kets, and Resilience of Pa ations des cons 8 0 9 3 5 8 6 5 3 3 esoins en investissements storal Communities ultants relatifs aux stratégies de c ommunication pour le cha ngement de comportemen t et l'accompagnement de s groupes de femmes CM-MINEPIA-61491-CS-CQ S / Accompagnement des Sélection fondé Organisations des Product Support to livestock value e sur les qualific 2018-05-0 2018-04-2 2018-05-2 2018-05-3 2018-07-0 2018-07-1 2018-08-0 2018-08-1 2018-09-0 2018-10-1 2021-12-3 IDA / 59080 A posteriori Open - National 63,500.00 124,355.36 Signé eurs à l'élaboration et à la chains development ations des cons 2 7 3 0 6 2 5 7 9 7 1 mise en oeuvre des plans ultants d'affaires dans la zone 1 ( Adamaoua, Extrême-Nord, Nord) CM-MINEPIA-61493-CS-CQ S / Accompagnement des Sélection fondé Organisations des Product Support to livestock value e sur les qualific 2018-05-0 2018-04-2 2018-05-2 2018-05-3 2018-07-0 2018-07-2 2018-08-0 2018-08-1 2018-09-1 2018-10-1 2021-12-3 IDA / 59080 A posteriori Open - National 63,500.00 124,318.09 Résilié eurs à l'élaboration et à la chains development ations des cons 4 7 5 0 8 0 7 7 1 7 1 mise en oeuvre des plans ultants d'affaires dans la zone 2 ( Centre, Sud et Est) CM-MINEPIA-61494-CS-CQ S / Accompagnement des Sélection fondé Organisations des Product Support to livestock value e sur les qualific 2018-05-0 2018-04-2 2018-05-2 2018-05-3 2018-07-0 2018-07-1 2018-08-0 2018-10-1 2018-09-1 2018-10-1 2021-12-3 IDA / 59080 A posteriori Open - National 69,200.00 270,726.13 Résilié eurs à l'élaboration et à la chains development ations des cons 4 7 5 0 8 2 7 7 1 7 1 mise en oeuvre des plans ultants d'affaires dans la zone 3 (L ittoral Nord-Ouest, Sud-Ou est et Ouest) CM-MINEPIA-24449-CS-LC Project coordination, man Sélection au mo Open - Internatio 2017-09-0 2017-09-2 2017-11-1 2017-12-0 2018-01-0 2018-02-1 2018-04-0 2018-05-0 IDA / 59080 A priori 42,000.00 0.00 Annulé S / Audit des comptes PPA agement, communication indre coût nal 7 8 1 9 8 2 6 6 2017 et 2018 and monitoring CM-MINEPIA-24470-CS-CQ Sélection fondé S / Elaboration de modèles Support to livestock value e sur les qualific 2017-10-0 2017-10-2 2017-12-0 2018-01-0 2018-02-1 2018-05-1 IDA / 59080 A posteriori Open - National 80,000.00 0.00 Annulé bancables et régionalisés chains development ations des cons 4 5 8 7 8 9 de plans d'affaires des OP ultants à cofinancer par le PRODE L CM-MINEPIA-50636-CS-CQ S / Sélection ONG en vue d Improvement of Pastoral P Sélection fondé e l'octroi des appuis aux in roductivity, Access to Mar e sur les qualific 2018-03-1 2018-08-1 2018-04-0 2018-04-2 2018-05-0 2018-06-0 2018-12-0 IDA / 59080 A posteriori Open - National 25,000.00 0.00 Annulé vestissements dans les int kets, and Resilience of Pa ations des cons 1 3 1 5 5 9 6 erventions agricoles relati storal Communities ultants ves à la nutrition dans la r égion du Nord CM-MINEPIA-91465-CS-CQ Sélection fondé Project coordination, man S / Recrutement d'un cons e sur les qualific 2019-01-0 2018-11-1 2019-01-2 2019-03-1 2018-12-3 2019-04-1 2019-02-0 2019-05-1 2019-03-2 2019-08-1 IDA / 59080 agement, communication A posteriori Open - National 2,800.00 27,082.15 Signé ultant individuel pour la mi ations des cons 7 2 8 3 1 2 1 7 5 5 and monitoring se en place d'un système i ultants ntégré d'archivage CM-MINEPIA-74114-CS-CQ Sélection fondé S / Élaboration des guides Improvement of Livestock e sur les qualific 2018-09-2 2018-10-1 2018-12-3 2019-01-3 2019-03-0 2019-06-0 de bonnes pratiques d'hyg IDA / 59080 Services Access and Deliv A posteriori Open - National 83,500.00 0.00 Annulé ations des cons 7 8 1 0 6 4 iène et de biosécurité le lo ery ultants ng des chaines de valeurs ciblées par le PRODEL CM-MINEPIA-106210-CS-C Improvement of Pastoral P Sélection fondé QS / Enquête et évaluation roductivity, Access to Mar e sur les qualific 2019-04-2 2019-03-2 2019-05-2 2019-06-2 2019-05-1 2019-07-1 2019-06-1 2019-08-0 2019-07-2 2020-02-2 IDA / 59080 A posteriori Open - National 120,000.00 117,463.44 Signé des ressources pastorales kets, and Resilience of Pa ations des cons 5 8 5 9 0 4 7 1 5 7 dans les communes de Go storal Communities ultants ulfe, Kolofata, koza CM-MINEPIA-106211-CS-C Improvement of Pastoral P Sélection fondé QS / Enquête et évaluation roductivity, Access to Mar e sur les qualific 2019-04-2 2019-03-2 2019-05-2 2019-06-3 2019-05-1 2019-07-1 2019-06-1 2019-08-0 2019-07-2 2020-02-2 IDA / 59080 A posteriori Open - National 93,000.00 76,693.07 Signé des ressources pastorales kets, and Resilience of Pa ations des cons 6 8 6 0 0 5 7 2 5 8 dans les communes de Dzi storal Communities ultants guilao, Doukoula Kar-Hay CM-MINEPIA-106213-CS-C Improvement of Pastoral P Sélection fondé QS / Enquête et évaluation roductivity, Access to Mar e sur les qualific 2019-04-2 2018-03-2 2019-05-2 2019-06-3 2019-07-1 2019-07-1 2019-07-1 2019-08-0 2019-09-0 2020-02-2 IDA / 59080 A posteriori Open - National 93,000.00 167,185.99 Signé des ressources pastorales kets, and Resilience of Pa ations des cons 6 8 6 0 0 5 8 2 3 8 dans les communes de Bib storal Communities ultants émi et Rey Bouba CM-MINEPIA-108507-CS-C QS / Mise en oeuvre des ac tivités d'appui à la résilien Improvement of Pastoral P Sélection fondé ce des ménages pauvres a roductivity, Access to Mar e sur les qualific 2019-04-2 2018-07-1 2019-05-1 2019-06-2 2018-09-2 2019-07-2 2018-10-1 2019-08-3 2018-12-1 2020-02-2 IDA / 59080 A posteriori Open - National 46,000.00 47,414.08 Signé ffectés par les conflits et le kets, and Resilience of Pa ations des cons 3 0 4 7 6 7 6 1 3 7 s investissements en fave storal Communities ultants ur des femmes dans la rég ion du Nord Département de la Bénoué et du Mayo L outi CM-MINEPIA-108509-CS-C QS / Mise en oeuvre des ac tivités d'appui à la résilien Improvement of Pastoral P Sélection fondé ce des ménages pauvres a roductivity, Access to Mar e sur les qualific 2019-04-2 2018-07-1 2019-05-1 2019-06-1 2018-09-2 2019-07-0 2018-10-1 2019-07-2 2018-12-1 2020-01-1 2020-10-2 IDA / 59080 A posteriori Open - National 40,000.00 40,864.45 Achevé ffectés par les conflits et le kets, and Resilience of Pa ations des cons 3 0 4 8 6 3 6 1 3 7 0 s investissements en fave storal Communities ultants ur des femmes dans la rég ion de l'Extrême-Nord, Dép artement Mayo Sava et Lo gone et Chari CM-MINEPIA-108510-CS-C QS / Mise en oeuvre des ac tivités d'appui à la résilien Improvement of Pastoral P Sélection fondé ce des ménages pauvres a roductivity, Access to Mar e sur les qualific 2019-04-2 2018-07-1 2019-05-1 2019-06-1 2018-09-2 2019-07-0 2018-10-1 2019-07-2 2018-12-1 2020-01-1 IDA / 59080 A posteriori Open - National 56,000.00 50,294.77 Signé ffectés par les conflits et le kets, and Resilience of Pa ations des cons 3 0 4 8 6 3 6 1 3 7 s investissements en fave storal Communities ultants ur des femmes dans la rég ion de l'extrême-nord, Dép artement du Diamaré et d u Mayo Tsanaga CM-MINEPIA-108549-CS-C Improvement of Pastoral P Sélection fondé QS / Elaboration des plans roductivity, Access to Mar e sur les qualific 2019-04-2 2018-03-2 2019-05-2 2019-06-2 2019-05-1 2019-07-1 2019-07-1 2019-08-0 2019-09-0 2020-02-2 de gestion des ressources IDA / 59080 A posteriori Open - National 93,000.00 1,671,859.87 Signé kets, and Resilience of Pa ations des cons 5 8 5 9 0 4 8 1 3 7 pastorales dans les comm storal Communities ultants unes de Mayo Oulo et May o Hourna CM-MINEPIA-108550-CS-C Improvement of Pastoral P Sélection fondé QS / Elaboration des plans roductivity, Access to Mar e sur les qualific 2019-04-2 2019-03-2 2019-05-2 2019-06-2 2019-06-0 2019-07-1 2019-06-1 2019-08-0 2019-07-2 2020-02-2 IDA / 59080 A posteriori Open - National 93,000.00 69,307.93 Signé des ressources pastorales kets, and Resilience of Pa ations des cons 5 8 5 9 3 4 7 1 5 7 des communes de Ngaoun storal Communities ultants déré II et Tignere CM-MINEPIA-93103-CS-CQ S / Mise en oeuvre des acti vités d'appui à la résilienc Improvement of Pastoral P Sélection fondé e des ménages pauvres aff roductivity, Access to Mar e sur les qualific 2019-04-2 2018-07-1 2019-05-1 2019-06-2 2018-09-2 2019-07-0 2018-10-1 2019-07-2 2018-12-1 2019-10-2 IDA / 59080 A posteriori Open - National 46,000.00 56,722.72 Signé ectés par les conflits et les kets, and Resilience of Pa ations des cons 5 0 6 0 6 5 6 3 3 1 investissements en faveur storal Communities ultants des femmes dans la région de l'extrême-nord, Départ ement du Diamaré et du M ayo Tsanaga CM-MINEPIA-93104-CS-CQ S / Mise en oeuvre des acti vités d'appui à la résilienc Improvement of Pastoral P Sélection fondé e des ménages pauvres aff roductivity, Access to Mar e sur les qualific 2019-04-2 2020-04-1 2019-05-1 2019-06-2 2018-09-2 2019-07-0 2018-10-1 2019-07-2 2018-12-1 2019-10-2 IDA / 59080 A posteriori Open - National 50,000.00 18,878.97 Signé ectés par les conflits et les kets, and Resilience of Pa ations des cons 5 8 6 0 6 5 6 3 3 1 investissements en faveur storal Communities ultants des femmes dans la région de l'Extrême-Nord, Départ ement Mayo Sava et Logo ne et Chari CM-MINEPIA-24448-CS-CQ Sélection fondé S / Elaboration d'une strat Improvement of Livestock e sur les qualific 2017-11-0 2019-01-2 2017-12-0 2018-01-2 2018-02-2 2018-04-1 2018-07-1 égie de l'alimentation ani IDA / 59080 Services Access and Deliv A posteriori Open - National 80,000.00 0.00 Annulé ations des cons 9 8 7 5 4 2 1 male au Cameroun assorti ery ultants e d'un plan de mise en œu vre dans le cadre du PROD EL CM-MINEPIA-114718-CS-C Improvement of Livestock Sélection fondé 2019-05-3 2019-04-1 2019-06-2 2019-08-0 2019-05-1 2019-09-0 2019-05-1 2019-10-0 2019-06-2 2019-10-1 2019-08-2 QS / Formation des format IDA / 59080 Services Access and Deliv A posteriori e sur les qualific Open - National 40,000.00 47,799.00 Achevé 0 6 0 3 3 2 1 7 4 7 0 eurs aux outils LEGS ery ations des cons ultants CM-MINEPIA-127231-CS-C QS / Mise en oeuvre des ac tivités d'appui à la résilien Improvement of Pastoral P Sélection fondé ce des ménages pauvres a roductivity, Access to Mar e sur les qualific 2019-08-1 2018-07-1 2019-09-0 2019-10-0 2018-07-0 2019-10-2 2018-10-1 2019-11-1 2018-12-1 2020-02-0 IDA / 59080 A posteriori Open - National 40,545.00 55,508.47 Signé ffectés par les conflits et le kets, and Resilience of Pa ations des cons 4 0 4 9 5 4 6 1 3 9 s investissements en fave storal Communities ultants ur des femmes dans la rég ion de l'Extrême-Nord, Dép artement Mayo Danay et Mayo Kani CM-MINEPIA-106215-CS-C QS / Développement d'une Improvement of Pastoral P Sélection fondé stratégie de communicatio roductivity, Access to Mar e sur les qualific 2019-05-3 2019-07-2 2019-06-3 2019-08-0 2019-08-1 2019-09-0 2020-02-0 n sur la base du portail d'i IDA / 59080 A posteriori Open - National 104,000.00 0.00 Annulé kets, and Resilience of Pa ations des cons 1 6 0 4 9 6 3 nformation CAMAGRO/Amé storal Communities ultants lioration de l'accès de la c ommunaté pastorale aux i nformations du marché de s produits d'élevage CM-MINEPIA-137082-CS-C QS / Sélection d'un Cabine Sélection fondé t pour l'accompagnement Support to livestock value e sur les qualific 2019-10-1 2019-06-2 2019-11-0 2019-12-1 2019-09-1 2020-01-1 2020-01-3 2020-02-2 2020-05-1 2022-08-2 des Organisations des Pro IDA / 59080 A posteriori Open - National 117,000.00 172,247.56 Signé chains development ations des cons 5 0 5 9 1 8 0 2 1 3 ducteurs (OP) à l'élaborati ultants on et la mise en œuvre de s plans d'affaires dans le c adre du PRODEL (zone 2) CM-MINEPIA-141291-CS-C Sélection fondé QS / Etude pour la collecte Improvement of Livestock e sur les qualific 2019-11-0 2019-10-1 2019-11-2 2020-01-1 2020-01-3 2020-02-1 2020-03-2 2020-03-1 2020-07-1 2020-05-1 des données sur certains i IDA / 59080 Services Access and Deliv A posteriori Open - National 63,500.00 67,551.15 Signé ations des cons 8 5 9 2 0 1 7 7 6 6 ndicateurs du projet et éva ery ultants luation du niveau de satisf action des bénéficiaires Page 9 CM-MINEPIA-223857-CS-C Improvement of Livestock Sélection fondé 2021-07-2 2021-08-1 2021-09-2 2021-10-2 2021-11-2 2022-11-2 QS / RECRUTEMENT D'UN IDA / 59080 Services Access and Deliv A posteriori e sur les qualific Open - National 250,000.00 0.00 Annulé 0 0 3 3 7 2 CABINET POUR LA MISE EN ery ations des cons OEUVRE DE LA CERC ultants CM-MINEPIA-227854-CS-C QS / RECRUTEMENT D'UN CABINET POUR LA MAITRIS Sélection fondé E D'OEUVRE COMPLETE (A Improvement of Livestock e sur les qualific 2021-11-1 2021-06-1 2021-12-0 2022-01-2 2021-06-3 2022-02-2 2021-07-2 2022-03-2 2022-01-2 2023-03-2 2022-03-2 PD, APS ET DCE) RELATIVE IDA / 59080 Services Access and Deliv A posteriori Open - National 166,667.00 161,337.87 Achevé ations des cons 7 0 8 1 0 0 8 7 4 2 4 A LA FOURNITURE D'UN SE ery ultants RVEUR ET D'UN DISPOSITI F PHOTOVOLTAIQUE POUR ENERGIE SOLAIRE AU LAB ORATOIRE NATIONAL VETE RINAIRE (LANAVET) CM-MINEPIA-161923-CS-C Sélection fondé Project coordination, man QS / sélection d'un consult e sur les qualific 2020-07-0 2020-08-0 2020-07-2 2020-08-2 2020-08-2 2020-09-3 2020-12-2 IDA / 59080 agement, communication A posteriori Open - National 63,333.00 0.00 Annulé ant pour l’évaluation des i ations des cons 8 5 9 4 6 0 9 and monitoring mpacts socio-économiques ultants et environnementaux CM-MINEPIA-161917-CS-C QS / Sélection d'un consult ant pour l’Assistance tech Improvement of Pastoral P Sélection fondé nique avec des opérateurs roductivity, Access to Mar e sur les qualific 2021-08-1 2021-09-0 2021-10-2 2021-11-2 2021-12-2 2022-04-0 IDA / 59080 A posteriori Open - National 50,000.00 0.00 Annulé pour l’accompagnement d kets, and Resilience of Pa ations des cons 9 9 3 2 7 6 es Communes à la mise en storal Communities ultants œuvre des sous-projets y c ompris la promotion et l'ap pui aux mécanismes de ré solution des conflits. CM-MINEPIA-236852-CS-C Sélection fondé Improvement of Livestock QS / Assistance technique e sur les qualific Open - Internatio 2021-05-2 2021-06-1 2021-07-3 2021-08-3 2021-10-0 2022-04-0 IDA / 59080 Services Access and Deliv A posteriori 83,500.00 0.00 Annulé à la mise en œuvre des pla ations des cons nal 7 7 1 0 4 2 ery ns d'investissement des st ultants ations CM-MINEPIA-161913-CS-C QS / Sélection d'un consult Sélection fondé Improvement of Livestock ant pour l'Appui aux servic e sur les qualific 2020-07-1 2020-08-0 2020-08-0 2020-09-1 2020-10-1 2020-11-2 2021-03-2 IDA / 59080 Services Access and Deliv A posteriori Open - National 15,000.00 0.00 Annulé es du MINEPIA pour le cont ations des cons 6 6 6 9 9 3 3 ery rôle de qualité des aliment ultants s du bétail et des semence s fourragères fournis aux OP CM-MINEPIA-161920-CS-C QS / Sélection d'un consult ant pour l'élaboration des f Improvement of Pastoral P Sélection fondé iches techniques pour une roductivity, Access to Mar e sur les qualific 2020-07-2 2020-04-2 2020-08-1 2020-09-2 2020-10-2 2020-11-2 2021-03-0 intensification progressive IDA / 59080 A posteriori Open - National 133,333.00 0.00 Annulé kets, and Resilience of Pa ations des cons 2 3 2 5 5 9 9 et durable des systèmes p storal Communities ultants astoraux et formation/acco mpagnent des groupemen ts d'éleveurs à l'adoption d es innovations dans la ges tion durable des RP CM-MINEPIA-161941-CS-C Sélection fondé Project coordination, man QS / Recrutement d'un con e sur les qualific 2020-07-2 2020-08-0 2020-08-1 2020-09-2 2020-10-2 2020-11-3 2021-05-2 IDA / 59080 agement, communication A posteriori Open - National 41,500.00 0.00 Annulé sultant pour évaluer la con ations des cons 3 5 3 6 6 0 9 and monitoring tribution du Projet aux effe ultants ts de changement climatiq ues CM-MINEPIA-176284-CS-C QS / Formation des cadres Improvement of Pastoral P Sélection fondé du MINEPIA et du PRODEL roductivity, Access to Mar e sur les qualific 2020-06-1 2020-07-2 2020-07-0 2020-08-1 2020-09-1 2020-10-2 2021-04-2 IDA / 59080 A posteriori Open - National 51,400.00 0.00 Annulé à la mise en place d'un dis kets, and Resilience of Pa ations des cons 5 2 6 9 8 3 1 positif national d’évaluatio storal Communities ultants n et du suivi des ressource s fourragères (bilan fourra ger) au Cameroun CM-MINEPIA-146039-CS-C Improvement of Pastoral P Sélection fondé 2020-05-2 2020-08-0 2020-06-1 2020-07-3 2020-08-3 2020-10-0 2021-04-0 QS / Formation en marketi IDA / 59080 roductivity, Access to Mar A posteriori e sur les qualific Open - National 25,000.00 0.00 Annulé 7 5 7 1 0 4 2 ng des produits d'élevage kets, and Resilience of Pa ations des cons storal Communities ultants CM-MINEPIA-106188-CS-C Sélection fondé QS / Appui aux centres rég Improvement of Livestock e sur les qualific 2019-07-2 2020-07-1 2019-08-1 2019-09-1 2019-10-0 2019-10-2 2020-10-2 ionaux d'information et de IDA / 59080 Services Access and Deliv A posteriori Open - National 40,500.00 0.00 Annulé ations des cons 4 5 4 8 3 1 0 promotion des ''Maisons d' ery ultants éleveurs'' / Appui aux Mai sons des Eleveurs CM-MINEPIA-106209-CS-C Sélection fondé QS / Assistance technique Improvement of Livestock e sur les qualific 2019-06-2 2020-07-1 2019-07-1 2019-08-2 2019-09-0 2019-09-2 2020-01-2 pour l'élaboration d'un pla IDA / 59080 Services Access and Deliv A posteriori Open - National 83,500.00 0.00 Annulé ations des cons 8 5 9 3 7 5 3 n de développement de se ery ultants mences et de fourrages de qualité CM-MINEPIA-106214-CS-C Improvement of Pastoral P Sélection fondé QS / Promotion de la gesti roductivity, Access to Mar e sur les qualific 2019-06-2 2020-07-1 2019-07-2 2019-08-3 2019-09-1 2019-10-0 2020-03-0 on intercommunale de la t IDA / 59080 A posteriori Open - National 96,500.00 0.00 Annulé kets, and Resilience of Pa ations des cons 7 5 7 1 5 3 1 ranshumance/Promotion et storal Communities ultants appui aux mécanismes de résolution de conflits CM-MINEPIA-106201-CS-C Sélection fondé Improvement of Livestock QS / Assistance technique e sur les qualific 2019-06-2 2020-07-1 2019-07-1 2019-08-1 2019-08-3 2019-09-1 2020-03-1 IDA / 59080 Services Access and Deliv A posteriori Open - National 83,500.00 0.00 Annulé à la mise en œuvre des pla ations des cons 0 5 1 5 0 7 5 ery ns d'investissement des st ultants ations CM-MINEPIA-106315-CS-C Improvement of Pastoral P Sélection fondé QS / Assainissement des p roductivity, Access to Mar e sur les qualific 2019-06-2 2020-07-1 2019-07-2 2019-09-0 2019-09-1 2019-10-0 2020-03-0 IDA / 59080 A posteriori Open - National 125,000.00 0.00 Annulé âtures: lutte contre les pla kets, and Resilience of Pa ations des cons 8 5 8 1 6 4 2 ntes envahissantes et lutte storal Communities ultants antivectorielle CM-MINEPIA-50840-CS-CQ S / Recrutement d'une ON Improvement of Pastoral P Sélection fondé G/Association pour l'identif roductivity, Access to Mar e sur les qualific 2018-05-1 2020-07-1 2018-06-0 2018-06-2 2018-07-0 2018-07-2 2018-11-2 IDA / 59080 A posteriori Open - National 83,133.00 0.00 Annulé ication des bénéficiaires d kets, and Resilience of Pa ations des cons 5 5 5 8 8 6 3 es actifs productif, l'élabor storal Communities ultants ation et la mise en oeuvre d'un plan de renforcement des capacités CM-MINEPIA-228809-CS-Q CBS / RECRUTEMENT D’UN CABINET POUR L’AUDIT FI Improvement of Livestock Sélection fondé NANCIER ET COMPTABLE D Open - Internatio 2021-05-1 2021-06-0 2021-07-2 2021-08-1 2021-09-1 2021-10-2 2021-11-2 2023-09-2 IDA / 59080 Services Access and Deliv A posteriori e sur la qualité 100,000.00 0.00 Annulé U PROJET DE DEVELOPPEM nal 7 7 1 8 7 2 6 3 ery et le coût ENT DE L’ELEVAGE (PROD EL) POUR LES EXERCICES 2020, 2021, 2022 AU 31 JA NVIER 2023 (Y COMPRIS L E PERIODE DE GRACE) CM-MINEPIA-261590-CS-Q CBS / RECRUTEMENT D'UN CABINET CHARGE DE LA R Project coordination, man EALISATION DE L'AUDIT FI Sélection au mo 2021-12-2 2021-09-1 2022-01-1 2022-02-2 2022-01-2 2022-03-2 2022-02-2 2022-04-2 2022-03-1 2022-05-2 2022-03-2 2022-07-0 2022-04-2 2023-01-3 IDA / 59080 agement, communication A posteriori Open - National 56,667.00 20,599.58 Signé NANCIER ET COMPTABLE D indre coût 0 4 0 3 5 3 2 2 1 7 5 1 5 1 and monitoring U PROJET DE DEVELOPPEM ENT DE L'ELEVAGE (PROD EL) EXERCICES 2021, 2022 AU 31 JANVIER 2023 (Y CO MPRIS LA PERIODE DE GRA CM-MINEPIA-237844-CS-C CE) QS / RECRUTEMENT D'UNE MAITRISE D'OEUVRE CHAR Sélection fondé Improvement of Livestock GEE DE LA CONCEPTION, e sur les qualific Open - Internatio 2021-06-0 2021-06-2 2021-08-0 2021-09-0 2021-10-1 2022-08-0 IDA / 59080 Services Access and Deliv A posteriori 166,666.00 0.00 Annulé DU CONTROLE DE QUALIT ations des cons nal 2 3 6 5 0 6 ery E ET SUIVI DE LA MISE EN ultants PLACE D'UN SYSTEME D'E NERGIE SOLAIRE PHOTOV OLTAIQUE AU LANAVET A GAROUA CM-MINEPIA-98852-CS-CQ Sélection fondé S / Recrutement de 2 cons Improvement of Livestock e sur les qualific 2019-04-0 2020-08-0 2019-04-0 2019-04-2 2019-05-0 2019-05-0 2019-07-0 ultants (1OIE et 1 expert ju IDA / 59080 Services Access and Deliv A posteriori Open - National 32,500.00 0.00 Annulé ations des cons 1 5 6 5 2 8 7 ridique) pour animer l'ateli ery ultants er de formation à la métho dologie du cadre règlemen taire CM-MINEPIA-106208-CS-C Improvement of Livestock Sélection fondé 2019-05-3 2020-07-1 2019-06-2 2019-07-2 2019-08-0 2019-08-2 2019-10-2 QS / Assistance technique IDA / 59080 Services Access and Deliv A posteriori e sur les qualific Open - National 83,500.00 0.00 Annulé 0 5 0 5 9 7 6 pour semences et formatio ery ations des cons n ultants CM-MINEPIA-106320-CS-C Sélection fondé QS / Études et enquêtes d Support to livestock value e sur les qualific 2019-05-2 2020-07-1 2019-06-2 2019-07-2 2019-08-1 2019-08-2 2019-11-2 e marchés relatifs à l'ident IDA / 59080 A posteriori Open - National 90,900.00 0.00 Annulé chains development ations des cons 2 5 1 6 0 8 6 ification, à la caractérisatio ultants n et au diagnostic des pro ducteurs et des potentiels acheteurs CM-MINEPIA-108551-CS-C Improvement of Pastoral P Sélection fondé QS / Elaboration des plans roductivity, Access to Mar e sur les qualific 2019-04-2 2020-05-2 2019-05-2 2019-06-2 2019-07-1 2019-08-0 2020-02-2 IDA / 59080 A posteriori Open - National 93,000.00 0.00 Annulé de gestion des ressources kets, and Resilience of Pa ations des cons 5 9 5 9 4 1 7 pastorales dans les comm storal Communities ultants unes de Banyo et Tibati CM-MINEPIA-127232-CS-C Improvement of Pastoral P Passation de m DS / Recrutement d'un con roductivity, Access to Mar archés auprès d 2022-01-2 2022-07-2 IDA / 59080 A posteriori Direct 415,000.00 0.00 Annulé sultant pour évaluer la con kets, and Resilience of Pa es agences de l' 4 3 tribution du Projet aux effe storal Communities ONU ts de changement climatiq ues CM-MINEPIA-227855-NC-R Sélection fondé FQ / Recrutement d'un Con Improvement of Livestock e sur les qualific 2021-10-1 2021-11-0 2021-12-1 2022-01-1 2022-02-2 2022-08-1 sultant pour l'organisation IDA / 59080 Services Access and Deliv A posteriori Open - National 22,500.00 0.00 Annulé ations des cons 3 3 7 6 0 9 des stages/formations prat ery ultants iques pour des cadres du MINEPIA et du secteur priv é CM-MINEPIA-223623-CS-I Sélection fondé Support to livestock value 2022-02-0 2022-02-2 2022-04-0 2022-05-0 2022-06-1 2022-12-1 NDV / Recrutement d'un C IDA / 59080 A posteriori e sur les qualific Open - National 9,738.75 0.00 Annulé chains development 3 4 9 9 3 0 abinet pour produire des fi ations des cons ches techniques (UCNP) ultants CM-MINEPIA-216209-CS-Q CBS / RECRUTEMENT D'UN Improvement of Pastoral P Sélection fondé CABINET POUR RENFORCE roductivity, Access to Mar e sur les qualific Open - Internatio 2022-02-0 2022-02-2 2022-04-0 2022-05-0 2022-06-1 2022-12-1 IDA / 59080 A posteriori 43,341.00 0.00 Annulé R LES CAPACITES D'ORGA kets, and Resilience of Pa ations des cons nal 3 4 9 9 3 0 NISATION ET D'OPERATION storal Communities ultants NALISATION DES COMITES DE GESTION DES MARCHE S A BETAILS (UCNP) CM-MINEPIA-237939-CS-C Sélection fondé QS / RECRUTEMENT D'UN Support to livestock value e sur les qualific 2021-07-2 2021-08-1 2021-09-2 2021-10-2 2021-11-2 2022-05-2 CONSULTANT POUR L'APP IDA / 59080 A posteriori Open - National 183,333.00 0.00 Annulé chains development ations des cons 0 0 3 3 7 6 UI A LA MISE EN OEUVRE D ultants U PROGRAMME NATIONAL D'INSEMINATION-CAMPAG NE 2021 CM-MINEPIA-215658-CS-C Improvement of Pastoral P Sélection fondé QS / SELECTION D'UN CON roductivity, Access to Mar e sur les qualific 2022-01-2 2022-02-1 2022-03-2 2022-04-2 2022-05-3 2022-11-2 IDA / 59080 A posteriori Open - National 112,150.00 0.00 Annulé SULTANT POUR L'ASSISTA kets, and Resilience of Pa ations des cons 0 0 6 5 0 6 NCE TECHNIQUE AUX STAT storal Communities ultants IONS D'ELEVAGE CM-MINEPIA-182434-CS-C QS / Formation des cadres Improvement of Pastoral P Sélection fondé communaux, des opérateu roductivity, Access to Mar e sur les qualific 2022-03-2 2022-04-1 2022-05-1 2022-06-0 2022-07-0 2022-09-2 rs et du MINEPIA en gestio IDA / 59080 A posteriori Open - National 35,000.00 0.00 Annulé kets, and Resilience of Pa ations des cons 3 3 8 2 1 9 n durable des ressources p storal Communities ultants astorales dans le cadre de la mise en œuvre des sous -projets des communes pa rtenaires du PRODEL. CM-MINEPIA-224721-CS-C Improvement of Pastoral P Sélection fondé QS / RECRUTEMENT D'UN roductivity, Access to Mar e sur les qualific 2021-04-3 2021-05-2 2021-07-0 2021-08-0 2021-09-0 2022-03-0 CABINET DE CONTROLE DE IDA / 59080 A posteriori Open - National 29,167.00 0.00 Annulé kets, and Resilience of Pa ations des cons 0 1 4 3 7 6 S TRAVAUX DU SITE DE LA storal Communities ultants FOIRE A BETAIL DE NGAOU NDERE CM-MINEPIA-224734-CS-C Sélection fondé Improvement of Livestock QS / RECRUTEMENT DES I e sur les qualific 2021-04-2 2021-05-1 2021-07-0 2021-07-3 2021-09-0 2022-03-0 IDA / 59080 Services Access and Deliv A posteriori Open - National 125,000.00 0.00 Annulé NSTITUTIONS POUR LES ST ations des cons 7 8 1 1 4 3 ery AGES ET LES FORMATIONS ultants DES SPECIALISTES CM-MINEPIA-216109-CS-C QS / RECRUTEMENT D'UN Improvement of Pastoral P Sélection fondé CABINET POUR LA MISE EN roductivity, Access to Mar e sur les qualific 2021-11-3 2021-12-2 2022-02-0 2022-03-0 2022-04-0 2022-10-0 IDA / 59080 A posteriori Open - National 140,425.00 0.00 Annulé OEUVRE DE LA STRATEGIE kets, and Resilience of Pa ations des cons 0 1 3 5 9 6 DE COMMUNICATION RELA storal Communities ultants TIVE AU MARCHE DES PRO DUITS D'ELEVAGE CM-MINEPIA-224690-CS-C Sélection fondé Improvement of Livestock QS / RECRUTEMENT DES C e sur les qualific 2021-12-2 2022-01-1 2022-02-2 2022-03-2 2022-05-0 2022-10-2 IDA / 59080 Services Access and Deliv A posteriori Open - National 125,000.00 0.00 Annulé ONSULTANTS POUR LA ST ations des cons 2 2 5 7 1 8 ery RUCTURATION DES ORGA ultants NISATIONS FAITIERES CM-MINEPIA-224791-CS-C QS / RECRUTEMENT D'UN Sélection fondé Improvement of Livestock CONSULTANT POUR LE DIA e sur les qualific 2021-06-1 2021-07-0 2021-08-1 2021-09-1 2021-10-1 2022-04-1 IDA / 59080 Services Access and Deliv A posteriori Open - National 53,334.00 0.00 Annulé GNOSTIC DES FILIERES PO ations des cons 0 1 4 3 8 6 ery RCINES ET AVICOLES ET EL ultants EBORATION D'UN PLAN DE RENFORCEMENT DES CAP ACITES CM-MINEPIA-224725-CS-C Sélection fondé Improvement of Livestock QS / RECRUTEMENT DES C e sur les qualific 2021-05-1 2021-06-0 2021-07-1 2021-08-1 2021-09-1 2022-03-1 IDA / 59080 Services Access and Deliv A posteriori Open - National 208,334.00 0.00 Annulé ONSULTANTS POUR LA FO ations des cons 2 2 6 5 9 8 ery RMATION ET L'ACCOMPAG ultants NEMENT DES PRODUCTEU RS CM-MINEPIA-286021-CS-C Sélection fondé Project coordination, man QS / Recrutement d'un Ca e sur les qualific En attente d'ex 2022-07-2 2022-08-0 2022-08-3 2022-09-0 2022-09-2 2022-11-1 IDA / 59080 agement, communication A posteriori Open - National 73,333.00 0.00 binet pour l'évaluation d'i ations des cons écution 8 2 0 6 0 9 and monitoring mpact socio-économique d ultants u PRODEL CM-MINEPIA-286025-CS-C Sélection fondé Project coordination, man QS / Recrutement d'un Ca e sur les qualific En attente d'ex 2022-08-1 2022-08-2 2022-09-0 2022-09-1 2022-09-2 2022-12-2 IDA / 59080 agement, communication A posteriori Open - National 98,333.00 0.00 binet/bureau d'études pou ations des cons écution 5 9 8 5 9 8 and monitoring r l'évaluation finale du PRO ultants DEL CM-MINEPIA-237867-CS-C QS / SELECTION DE BUREA UX D'ETUDES/CABINETS/IN STITUTIONS UNIVERSITAIR Improvement of Pastoral P Sélection fondé ES CHARGES DE LA FORM roductivity, Access to Mar e sur les qualific En attente d'ex 2022-03-3 2022-04-2 2022-06-0 2022-07-0 2022-08-0 2022-09-0 IDA / 59080 A posteriori Open - National 180,170.00 0.00 ATION ET DE L'ORGANISAT kets, and Resilience of Pa ations des cons écution 1 1 4 4 8 7 ION DES STAGES PRATIQU storal Communities ultants ES DES ACTEURS DE LA FI LIERE APICOLE, LAITIERE, BOVIN, VIANDE, BOUCHERI E ET CHARCUTERIE DANS LE CADRE DU PRODEL Page 10 CM-MINEPIA-285912-CS-C QS / Sélection d'un Consult Improvement of Pastoral P Sélection fondé ant pour l'assistance techn roductivity, Access to Mar e sur les qualific En attente d'ex 2022-08-0 2022-08-1 2022-09-0 2022-09-1 2022-10-1 2022-12-0 IDA / 59080 A posteriori Open - National 100,000.00 0.00 ique pour l’accompagnem kets, and Resilience of Pa ations des cons écution 5 2 5 9 0 9 ent zootechnique, le contr storal Communities ultants ôle et la surveillance des tr avaux dans les stations d’ élevage INDIVIDUAL CONSULTANTS Activity Reference No. Invitation to Identifi Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co / Description Component Review Type Method Terms of Reference ed/Selected Consult Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract ant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-MINEPIA-8657-CS-IND V / Recrutement d'un cons Project coordination, man ultant Individuel, Traducte 2017-02-2 2017-01-1 2017-03-2 2017-03-0 2017-03-2 2017-03-1 2017-04-0 2017-03-1 2017-05-0 IDA / Q9910 agement, communication A posteriori Individuel Open 5,000.00 5,722.00 Signé ur pour la traduction en la 7 8 1 7 6 5 7 7 7 and monitoring ngue française du docume nt d'évaluation du PRODEL et de l'accord de financem ent. CM-MINEPIA-24477-CS-CQ Support to livestock value 2017-09-2 2017-08-2 2017-10-2 2017-09-2 2017-11-1 2017-09-2 2017-12-1 2017-09-1 2018-02-0 2018-09-1 IDA / 59080 A posteriori Individuel Open 6,800.00 7,694.96 Achevé S / Elaboration du Manuel chains development 0 2 4 4 4 6 9 8 2 1 guide des OP CM-MINEPIA-26607-CS-IN DV / Élaboration du guide Support to livestock value 2017-08-3 2017-02-1 2017-10-1 2017-02-2 2017-11-0 2017-12-2 2017-12-1 2017-10-0 2018-02-1 2018-01-2 sur les Institutions Financi IDA / 59080 A posteriori Individuel Open 6,900.00 2,338.47 Achevé chains development 0 7 8 4 8 7 3 3 1 3 ères Partenaires (IFP) desti nés aux Organisations des Producteurs (OP) CM-MINEPIA-24472-CS-CQ Improvement of Pastoral P S / Elaboration du Manuel roductivity, Access to Mar 2017-09-2 2017-07-2 2017-11-1 2017-10-0 2017-12-0 2017-10-0 2018-01-1 2017-12-2 2018-02-2 2018-04-1 IDA / 59080 A posteriori Individuel Open 20,000.00 13,673.65 Achevé guide de mise en œuvre d kets, and Resilience of Pa 8 8 6 5 7 2 1 0 5 8 es activités de la sous com storal Communities posante 2.3. CM-MINEPIA-31708-CS-IN Improvement of Livestock 2017-10-2 2019-04-1 2017-12-1 2019-05-1 2018-01-0 2019-05-1 2018-02-1 2019-06-2 2018-05-1 DV / Étude pour Formation IDA / 59080 Services Access and Deliv A posteriori Individuel Open 92,000.00 42,786.43 Signé 3 6 2 0 2 1 3 4 4 des formateurs aux outils ery LEGS CM-MINEPIA-31710-CS-IN Improvement of Livestock DV / Élaboration des outils 2017-10-2 2017-08-2 2017-12-1 2018-03-0 2018-01-0 2018-03-1 2018-02-1 2018-06-0 2018-05-1 IDA / 59080 Services Access and Deliv A posteriori Individuel Open 94,000.00 880,316.02 Signé de gestion des crises éligi 3 3 6 9 6 6 7 8 8 ery ble dans le sous-secteur d e l'élevage CM-MINEPIA-47776-CS-IN DV / Recrutement d'un Exp Project coordination, man ert pour l'installation et la 2018-02-1 2018-02-0 2018-04-0 2018-02-0 2018-04-2 2018-02-2 2018-05-3 2018-04-2 2018-11-2 IDA / 59080 agement, communication A posteriori Individuel Open 33,500.00 21,052.36 Signé formation du personnel à l' 5 2 5 2 6 8 1 7 7 and monitoring utilisation des logiciels TO M2PRO, TOM2MARCHE et TOM2MONOTORING CM-MINEPIA-47785-CS-IN DV / Mise en place du syst Project coordination, man 2018-03-1 2019-01-3 2018-04-1 2019-03-1 2018-04-2 2019-03-1 2018-05-1 2019-04-1 2018-08-1 ème d'information géogra IDA / 59080 agement, communication A posteriori Individuel Open 28,000.00 28,117.21 Signé 5 1 3 4 7 8 7 7 5 phique du SIG dans le disp and monitoring ositif du suivi évaluation d u PRODEL CM-MINEPIA-48032-CS-IN DV / Etude de faisabilité d Improvement of Livestock es mandats sanitaires (pla 2018-03-1 2018-05-0 2018-05-2 2018-06-2 2018-02-2 2018-09-2 2018-07-2 IDA / 59080 Services Access and Deliv A posteriori Individuel Open 85,000.00 91,546.84 Achevé ns d'affaires types ou mod 5 3 4 8 0 6 7 ery èles d'investissement des vétérinaires sanitaires de c atégories A et B CM-MINEPIA-48116-CS-IN DV / Recrutement d'un Co nsultants (coach) pour l'ac Support to livestock value 2018-03-2 2018-08-1 2018-05-1 2018-10-0 2018-05-1 2018-10-3 2018-06-1 2018-11-0 2018-12-0 2019-05-2 compagnement des Institu IDA / 59080 A posteriori Individuel Open 6,950.00 15,284.56 Signé chains development 2 3 0 8 5 0 0 7 7 7 tions Financières Partenair es (IFP) à Yaoundé pour le développement des produi ts de crédit adapté dans le domaine de l'élevage CM-MINEPIA-48119-CS-IN DV / Recrutement d'un Co nsultants (coach) pour l'ac Support to livestock value 2018-03-2 2018-08-1 2018-05-1 2018-10-0 2018-05-1 2018-10-1 2018-06-1 2018-11-0 2018-12-1 compagnement des Institu IDA / 59080 A posteriori Individuel Open 6,950.00 7,579.36 Signé chains development 2 3 0 2 5 2 9 7 6 tions Financières Partenair es (IFP) à Maroua pour le développement des produi ts de crédit adapté dans le domaine de l'élevage CM-MINEPIA-48121-CS-IN DV / Recrutement d'un Co nsultants (coach) pour l'ac Support to livestock value 2018-03-2 2018-08-1 2018-05-1 2018-10-0 2018-05-1 2018-10-1 2018-06-1 2018-11-0 2018-12-1 compagnement des Institu IDA / 59080 A posteriori Individuel Open 6,950.00 7,642.28 Signé chains development 2 3 0 8 5 2 9 7 6 tions Financières Partenair es (IFP) à Bafoussam pour le développement des pro duits de crédit adapté dan s le domaine de l'élevage CM-MINEPIA-48125-CS-IN DV / Recrutement d'un Co nsultants (coach) pour l'ac Support to livestock value 2018-03-2 2018-08-1 2018-05-1 2018-10-0 2018-05-1 2018-10-1 2018-06-1 2018-11-0 2018-12-1 compagnement des Institu IDA / 59080 A posteriori Individuel Open 6,950.00 15,158.72 Signé chains development 2 3 0 8 5 2 9 7 6 tions Financières Partenair es (IFP) à Douala pour le d éveloppement des produit s de crédit adapté dans le domaine de l'élevage CM-MINEPIA-31714-CS-IN Improvement of Livestock 2017-10-2 2017-12-1 2018-01-0 2018-02-1 2018-05-1 DV / Exercice de simulatio IDA / 59080 Services Access and Deliv A posteriori Individuel Open 52,000.00 0.00 Annulé 3 1 1 2 3 n du plan de riposte contre ery la grippe aviaire CM-MINEPIA-50735-CS-IN DV / Etude de faisabilité e Improvement of Livestock 2018-06-1 2018-07-2 2018-06-1 2018-08-1 2018-06-2 2018-09-1 2018-07-1 2018-11-0 2018-08-3 nvironnemental et sanitair IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 8,125.00 11,837.57 Signé 0 4 5 3 9 0 7 2 1 e dans le cadre des opérat ery ions d'importation des rac es améliorées importées CM-MINEPIA-50763-CS-IN Improvement of Livestock DV / Evaluation finale du P 2018-02-2 2017-11-2 2018-02-2 2017-11-1 2018-03-1 2017-11-3 2018-03-2 2018-02-0 2018-04-2 2018-02-1 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 2,500.00 2,798.85 Achevé ACA, Analyse complément 3 2 8 5 4 0 4 5 3 9 ery aire dans le cadre du PRO DEL CM-MINEPIA-50885-CS-IN Project coordination, man 2018-07-0 2018-10-0 2018-07-1 2018-10-1 2018-07-3 2018-11-0 2018-08-1 2019-04-0 2018-12-1 DV / Mise en place d'un sit IDA / 59080 agement, communication A posteriori Individuel Limited 6,667.00 6,942.52 Signé 5 3 0 5 1 5 8 2 6 e internet du PRODEL and monitoring CM-MINEPIA-50891-CS-IN Project coordination, man 2018-03-2 2018-03-2 2018-04-0 2018-04-0 2018-04-2 2018-04-1 2018-05-1 2018-04-2 2018-06-0 2018-05-1 DV / Conception d'une cha IDA / 59080 agement, communication A posteriori Individuel Limited 41,667.00 2,744.66 Achevé 9 8 3 2 4 6 0 6 9 4 rte graphique du PRODEL and monitoring CM-MINEPIA-50802-CS-CD Improvement of Pastoral P Sélection de co S / Recrutement d'une ON roductivity, Access to Mar 2018-05-2 2018-04-1 2018-06-0 2018-04-1 2018-07-1 2018-06-2 2018-11-0 2019-03-2 IDA / 59080 A posteriori nsultants par en Direct 140,000.00 149,625.04 Achevé G/Association de 4 PGRP e kets, and Resilience of Pa 4 0 3 6 2 6 9 9 tente directe t des sous projets dans 4 c storal Communities ommunes de la région du Nord CM-MINEPIA-50960-CS-CD S / Recrutement d'une ON Improvement of Pastoral P Sélection de co G/Association pour l'élabor roductivity, Access to Mar 2018-05-2 2018-04-1 2018-06-0 2018-04-1 2018-07-0 2018-06-0 2018-12-0 2019-03-2 IDA / 59080 A posteriori nsultants par en Direct 122,405.00 138,958.50 Achevé ation de 4 PGRP et des sou kets, and Resilience of Pa 7 0 6 0 9 8 6 1 tente directe s projets dans 4 commune storal Communities s dans la région de l'Adam aoua et de l'Est dans le ca dre du PRODEL CM-MINEPIA-50816-CS-CD Improvement of Pastoral P S / Recrutement d'une ON Sélection de co roductivity, Access to Mar 2018-05-2 2018-04-1 2018-06-0 2018-04-1 2018-07-1 2018-06-2 2018-11-0 2019-01-1 G/Association l'élaboration IDA / 59080 A posteriori nsultants par en Direct 139,700.00 149,327.01 Achevé kets, and Resilience of Pa 9 0 8 0 1 7 8 8 de 5 PGRP et des sous proj tente directe storal Communities ets dans 5 communes de l a région de l'Extrême Nord par CADEPI CM-MINEPIA-50670-CS-QC Improvement of Livestock BS / Audit technique et org 2018-06-2 2018-11-0 2018-08-0 2019-02-2 2018-08-3 2019-03-2 2018-10-0 2019-05-2 2018-12-0 2019-09-1 IDA / 59080 Services Access and Deliv A posteriori Individuel Open 13,500.00 24,145.96 Achevé anisationnel de l'ONVC et 1 1 9 2 0 9 4 1 3 1 ery élaboration d'un plan de d éveloppement à CML term es CM-MINEPIA-50732-CS-IN Improvement of Livestock DV / Elaboration d'un guid 2018-07-2 2018-07-2 2018-07-3 2018-08-1 2018-08-1 2018-09-1 2018-08-3 2018-11-0 2018-11-0 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 6,700.00 12,781.15 Signé e des activités du chef de 5 3 0 3 3 0 1 2 9 ery centre vétérinaire dans le cadre du PRODEL CM-MINEPIA-67730-CS-IN DV / Contrôle des travaux Project coordination, man 2018-06-2 2018-02-1 2018-08-1 2018-02-1 2018-09-0 2018-03-0 2018-10-1 2018-06-0 2019-02-0 pour la réhabilitation des b IDA / 59080 agement, communication A posteriori Individuel Open 6,700.00 6,530.53 Signé 8 5 6 5 6 7 1 1 8 ureaux de l'UCNP PRODEL and monitoring à Yaoundé et de l'UCR Zon e 2 du PRODEL à Yaoundé CM-MINEPIA-68592-CS-IN Project coordination, man DV / Recrutement d'un Co 2018-07-2 2018-07-2 2018-07-3 2018-07-2 2018-08-2 2018-10-1 2018-09-2 2018-10-2 2019-03-2 IDA / 59080 agement, communication A posteriori Individuel Limited 65,000.00 99,904.22 Signé nsultant Individuel pour ap 6 5 1 3 1 8 5 3 4 and monitoring pui mise en place dispositi f Suivi Evaluation CM-MINEPIA-50922-CS-IN Improvement of Pastoral P DV / Recrutement d'un con roductivity, Access to Mar 2018-06-0 2018-06-1 2018-07-0 2018-07-1 2018-11-1 IDA / 59080 A posteriori Individuel Limited 6,950.00 0.00 Annulé trôleur technique pour le s kets, and Resilience of Pa 5 0 1 7 4 uivi des travaux dans la zo storal Communities ne2B au PRODEL CM-MINEPIA-50821-CS-IN Improvement of Pastoral P DV / Recrutement d'un con roductivity, Access to Mar 2018-06-0 2018-06-0 2018-06-2 2018-07-1 2018-12-0 trôleurs pour le suivi des tr IDA / 59080 A posteriori Individuel Limited 6,950.00 0.00 Annulé kets, and Resilience of Pa 3 8 2 2 9 avaux dans les commune storal Communities s de la zone 1A dans le ca dre du PRODEL CM-MINEPIA-50919-CS-IN Improvement of Pastoral P DV / Recrutement d'un con roductivity, Access to Mar 2018-06-0 2018-06-1 2018-07-0 2018-07-1 2018-11-1 IDA / 59080 A posteriori Individuel Limited 6,950.00 0.00 Annulé trôleur technique et suivi d kets, and Resilience of Pa 5 0 1 7 4 es travaux dans la zone 3 storal Communities dans le cadre du PRODEL CM-MINEPIA-50914-CS-IN Improvement of Pastoral P DV / Recrutement d'un con roductivity, Access to Mar 2018-06-0 2018-06-1 2018-07-0 2018-07-1 2018-11-1 IDA / 59080 A posteriori Individuel Limited 6,950.00 0.00 Annulé trôleur technique et suivi d kets, and Resilience of Pa 5 0 1 9 6 es travaux de la zone1B d storal Communities ans le cadre du PRODEL CM-MINEPIA-50921-CS-IN Improvement of Pastoral P DV / Recrutement d'un con roductivity, Access to Mar 2018-06-0 2018-06-1 2018-07-0 2018-07-1 2018-11-1 IDA / 59080 A posteriori Individuel Limited 6,950.00 0.00 Annulé trôleur technique et suivi kets, and Resilience of Pa 5 0 1 7 4 des travaux dans la zone 1 storal Communities C dans le cadre du PRODE L CM-MINEPIA-68666-CS-IN Project coordination, man 2018-07-1 2018-02-1 2018-07-2 2018-02-1 2018-08-1 2018-03-0 2018-09-1 2018-06-2 2019-09-1 DV / Réalisation des servic IDA / 59080 agement, communication A posteriori Individuel Limited 3,340.00 3,513.36 Signé 9 2 4 2 4 5 8 5 8 es d'entretien des locaux d and monitoring e l'UCR zone 3 CM-MINEPIA-67821-CS-CD S / Élaboration et accompa Improvement of Pastoral P gnement dans la mise en Sélection de co roductivity, Access to Mar 2018-06-2 2018-04-0 2018-07-0 2018-04-1 2018-09-1 2018-07-2 2019-03-1 2019-03-2 œuvre de quatre (04) plan IDA / 59080 A posteriori nsultants par en Direct 122,500.00 125,102.18 Achevé kets, and Resilience of Pa 8 1 8 0 1 5 0 9 s de gestion des ressource tente directe storal Communities s pastorales (PGRP) et des sous projets dans quatre c ommunes de la région de l 'Est CM-MINEPIA-68659-CS-CD S / REALISATION DES ENQ UETES DE BASE SUR TROI Improvement of Livestock Sélection de co S MALADIES ANIMALES PRI 2018-07-1 2017-08-2 2018-07-2 2018-02-1 2018-09-2 2018-07-1 2019-01-2 IDA / 59080 Services Access and Deliv A posteriori nsultants par en Direct 186,000.00 195,005.68 Signé ORITAIRES AU CAMEROUN 2 3 2 6 5 2 3 ery tente directe : PESTE DES PETITS RUMIN ANTS (PPR), PERIPNEUMO NIE CONTAGIEUSE BOVINE (PPCB) ET FIEVRE APHTEU SE (FA) CM-MINEPIA-67729-CS-CD Project coordination, man Sélection de co S / Audit externe comptabl 2018-08-0 2018-03-1 2018-08-1 2018-04-0 2018-10-1 2018-07-0 2020-08-2 2018-08-1 IDA / 59080 agement, communication A posteriori nsultants par en Direct 67,100.00 48,002.22 Achevé e et financier du PRODEL p 2 8 2 2 6 4 3 7 and monitoring tente directe our les exercices 2017, 20 18 et 2019 CM-MINEPIA-74107-CS-IN DV / Sélection d'un Consult Support to livestock value 2018-08-2 2018-07-2 2018-08-2 2018-07-2 2018-09-1 2018-08-2 2018-10-2 2018-10-0 2019-04-2 ant Individuel devant appu IDA / 59080 A posteriori Individuel Limited 47,000.00 51,315.95 Signé chains development 3 7 8 7 8 8 3 9 1 yer la mise en œuvre des activités de développemen t des chaines de valeur du PRODEL CM-MINEPIA-74112-CS-IN DV / Sélection d'un Consult Project coordination, man ant Individuel pour la finali 2018-08-2 2018-11-1 2018-08-2 2018-08-0 2018-09-1 2018-08-2 2018-10-2 2018-10-2 2018-11-0 IDA / 59080 agement, communication A posteriori Individuel Limited 1,250.00 1,288.92 Signé sation conceptuelle et arti 3 2 8 3 8 3 3 3 6 and monitoring stique des supports de visi bilité dans les cadre des a ctivités du PRODEL CM-MINEPIA-50655-CS-CD Improvement of Livestock Sélection de co S / Appui technique de IRLI 2018-05-2 2018-06-0 2018-07-1 2018-10-0 IDA / 59080 Services Access and Deliv A posteriori nsultants par en Direct 83,333.33 0.00 Annulé à la mise en place d'un rés 7 6 1 9 ery tente directe eau de surveillance en séc urité sanitaire des AOA CM-MINEPIA-50609-CS-IN DV / Sélection de deux con Improvement of Livestock 2018-03-2 2018-03-2 2018-04-0 2018-05-0 2018-05-1 sultants OIE pour animer l' IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 24,385.00 0.00 Annulé 0 5 4 5 9 atelier de formation à la m ery éthodologie du cadre reglé mentaire CM-MINEPIA-50916-CS-IN Improvement of Pastoral P DV / Recrutement de 05 co roductivity, Access to Mar 2018-06-2 2018-08-2 2018-06-2 2018-07-1 2018-08-0 2018-08-1 ntrôleurs technique et suiv IDA / 59080 A posteriori Individuel Limited 25,000.00 0.00 Annulé kets, and Resilience of Pa 0 3 5 6 3 3 i des travaux dans la zone storal Communities 1 et zone 2 dans le cadre du PRODEL CM-MINEPIA-50647-CS-CD S / Élaboration d'un plan d Improvement of Livestock Sélection de co e développement des sem 2018-04-3 2018-05-1 2018-06-1 2018-09-1 IDA / 59080 Services Access and Deliv A posteriori nsultants par en Direct 166,667.00 0.00 Annulé ences et des fourrages de 0 0 4 2 ery tente directe qualité dans les stations d e Wakwa Louguéré et Do gba PRODEL-ILRI Page 11 CM-MINEPIA-48145-CS-IN DV / Recrutement d'un Co Support to livestock value 2018-03-2 2018-08-1 2018-05-1 2018-05-3 2018-07-0 2018-08-0 IDA / 59080 A posteriori Individuel Open 6,950.00 0.00 Annulé nsultant pour la supervisio chains development 2 3 0 1 5 4 n des sessions de formatio n en éducation financière CM-MINEPIA-74117-CS-IN DV / Sélection d'un Consult Project coordination, man 2018-08-1 2018-07-1 2018-08-2 2018-07-2 2018-09-2 2018-09-1 2018-10-2 2018-10-2 2019-04-2 ant Individuel pour appuye IDA / 59080 agement, communication A posteriori Individuel Limited 75,000.00 114,821.84 Signé 6 6 1 3 0 1 5 4 3 r la mise en place du systè and monitoring me de suivi évaluation du PRODEL CM-MINEPIA-91446-CS-IN Improvement of Livestock DV / Recrutement d'un con 2019-01-2 2019-02-1 2019-02-0 2019-02-1 2019-02-2 2019-02-2 2019-03-0 2019-03-2 2019-05-1 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 6,800.00 7,170.82 Signé sultant individuel pour le c 2 5 1 9 2 8 4 2 3 ery ontrôle de la fourniture du matériel de froid CM-MINEPIA-106184-CS-I Improvement of Livestock 2019-05-1 2020-01-3 2019-05-2 2020-02-0 2019-06-2 2020-02-2 2019-07-2 2020-04-2 2020-07-2 NDV / Développement d'u IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 33,500.00 7,237.36 Signé 7 0 2 6 1 6 6 0 5 n système d'information d ery u sous secteur EPIA CM-MINEPIA-106328-CS-I Project coordination, man 2019-07-2 2019-08-2 2019-09-1 2019-10-0 2019-10-0 2019-10-1 2019-11-0 2019-11-0 2020-02-0 IDA / 59080 A posteriori Individuel Open 41,500.00 52,215.75 Signé NDV / Évaluation à mis par agement, communication 5 0 2 7 3 4 7 6 5 cours du Projet and monitoring CM-MINEPIA-106339-CS-I Project coordination, man 2019-05-3 2018-11-0 2019-07-1 2019-01-1 2019-08-0 2019-02-0 2019-09-1 2019-03-2 2019-12-1 NDV / Mise en place d'un s IDA / 59080 agement, communication A posteriori Individuel Open 28,000.00 37,525.52 Signé 0 7 8 1 8 1 2 2 1 ystème intégré d'archivag and monitoring e au PRODEL CM-MINEPIA-106343-CS-I Project coordination, man 2019-05-3 2019-03-2 2019-07-1 2019-05-0 2019-08-0 2019-05-1 2019-09-1 2019-06-2 2020-03-1 2021-01-1 NDV / Suivi des ménages à IDA / 59080 agement, communication A posteriori Individuel Open 41,500.00 61,158.54 Achevé 0 8 8 6 8 3 2 7 0 5 l'utilisation des bio-digeste and monitoring urs CM-MINEPIA-106351-CS-I NDV / Recrutement d'un C Project coordination, man 2019-04-3 2019-03-1 2019-06-1 2019-06-2 2019-07-0 2019-07-1 2019-08-1 2019-08-2 2020-02-0 onsultant pour la planificat IDA / 59080 agement, communication A posteriori Individuel Open 100,000.00 39,966.00 Signé 0 8 8 8 9 5 3 8 9 ion des activités et encadr and monitoring ement des ressources hum aines du PRODEL CM-MINEPIA-48129-CS-IN DV / Recrutement d'un Co nsultants (coach) pour l'ac Support to livestock value 2018-03-2 2018-08-1 2018-05-1 2018-10-0 2018-05-1 2019-01-2 2018-06-1 2018-12-1 compagnement des Institu IDA / 59080 A posteriori Individuel Open 6,950.00 0.00 Annulé chains development 2 3 0 8 5 8 9 6 tions Financières Partenair es (IFP) à Kumba pour le d éveloppement des produit s de crédit adapté dans le domaine de l'élevage CM-MINEPIA-48120-CS-IN DV / Recrutement d'un Co nsultants (coach) pour l'ac Support to livestock value 2018-03-2 2018-08-1 2018-05-1 2018-10-0 2018-05-1 2019-01-2 2018-06-1 2018-12-1 compagnement des Institu IDA / 59080 A posteriori Individuel Open 6,950.00 0.00 Annulé chains development 2 3 0 8 5 8 9 6 tions Financières Partenair es (IFP) à Bamenda pour le développement des produ its de crédit adapté dans l e domaine de l'élevage CM-MINEPIA-74120-CS-IN DV / Sélection d'un Consult ant Individuel devant men Improvement of Livestock 2018-09-2 2018-11-0 2018-09-2 2019-01-2 2018-10-2 2018-11-2 2019-01-2 er les études de faisabilité IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 6,800.00 0.00 Annulé 0 5 5 8 5 9 8 technique pour la construc ery tion de trois étables de soi xante génisses gestantes c hacune à Louguéré CM-MINEPIA-114637-CS-I NDV / Recrutement d'un C Improvement of Pastoral P onsultant Individuel pour l' roductivity, Access to Mar 2019-06-2 2019-03-2 2019-08-1 2019-05-0 2019-09-0 2019-05-1 2019-10-1 2019-06-2 2020-04-0 IDA / 59080 A posteriori Individuel Open 64,000.00 60,666.26 Signé accompagnement de 40 fe kets, and Resilience of Pa 8 8 6 9 6 3 1 7 8 mmes dans l'utilisation de storal Communities s biodigesteurs modèle CM 2013 dans la région du No rd CM-MINEPIA-114641-CS-I NDV / Recrutement d'un C Improvement of Pastoral P onsultant Individuel pour l' roductivity, Access to Mar 2019-06-2 2019-03-2 2019-08-1 2019-05-1 2019-09-0 2019-05-1 2019-10-1 2019-06-2 2020-04-0 accompagnement de 30 fe IDA / 59080 A posteriori Individuel Open 50,000.00 45,963.44 Signé kets, and Resilience of Pa 8 8 6 0 6 3 1 7 8 mmes dans les départeme storal Communities nts du Mayo Kani, Mayo Ts anaga et Mayo Danay pour l'utilisation des biogigeste urs modèles CM2013 CM-MINEPIA-98756-CS-IN Improvement of Livestock DV / Appui à la mise en pla 2019-05-3 2019-06-0 2019-06-0 2019-06-2 2019-07-3 2019-10-2 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 52,250.00 0.00 Annulé ce des GEVS (groupement 0 7 4 5 0 8 ery d'éleveurs à vocation sanit aire) (en lots) CM-MINEPIA-98774-CS-IN DV / Développement des c Improvement of Livestock 2019-04-2 2019-06-1 2019-04-3 2019-05-3 2019-07-0 2019-08-0 heck list de mesures de bi IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 16,000.00 0.00 Annulé 5 3 0 0 4 3 osécurité, normes et satnd ery ards de qualité le long des chaines de valeur ciblées ( en lots) CM-MINEPIA-98831-CS-CQ S / Recrutement d'un cons ultant Individuel pour la mi Improvement of Livestock se à jour du système d'info 2019-04-2 2019-06-0 2019-06-1 2019-07-0 2019-08-0 2020-02-0 IDA / 59080 Services Access and Deliv A posteriori Individuel Open 6,614.00 0.00 Annulé rmation et de gestion des 6 7 4 5 9 5 ery données sanitaires, déploi ement sur le terrain (du ni veau central et déconcentr é et formation des acteurs majeurs CM-MINEPIA-91430-CS-IN DV / Recrutement d'un con Improvement of Livestock 2019-01-1 2019-06-0 2019-01-2 2019-02-1 2019-03-2 2019-07-1 sultant individuel pour le c IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 6,800.00 0.00 Annulé 4 7 4 4 1 9 ontrôle des travaux de la c ery onstruction des étables à l a station de Louguere CM-MINEPIA-98769-CS-IN Improvement of Livestock DV / Recrutement d'un exp 2019-06-1 2019-06-1 2019-06-1 2019-07-0 2019-08-1 2019-09-1 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 25,000.00 0.00 Annulé ert international pour l'exe 1 3 6 7 1 0 ery rcice de simulation des pla ns de risques CM-MINEPIA-50731-CS-IN Improvement of Livestock 2018-06-0 2019-07-2 2018-06-0 2018-06-2 2018-07-0 2019-01-0 DV / Appui au recrutement IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 6,950.00 0.00 Annulé 3 6 8 2 8 4 d'un conseil juridique et sa ery prise en charge CM-MINEPIA-98013-CS-CD Improvement of Livestock Sélection de co S / Appui à la surveillance 2019-02-2 2019-08-0 2019-03-2 2019-05-2 2019-10-2 IDA / 59080 Services Access and Deliv A posteriori nsultants par en Direct 240,000.00 0.00 Annulé des maladies animales pri 8 8 0 4 1 ery tente directe oritaires au Cameroun dan s le cadre du PRODEL CM-MINEPIA-50753-CS-IN DV / Traduction (francais-A Improvement of Livestock 2018-07-0 2018-12-2 2018-07-1 2019-06-1 2018-07-2 2019-07-2 2018-08-0 2018-09-2 nglais) des fiches d'alerte, IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 1,667.00 0.00 Annulé 5 6 0 3 4 3 9 3 des guides et des bulletins ery dans le cadre des activités de la santé animale au PR ODEL CM-MINEPIA-98733-CS-CQ S / Recrutement d'un cons ultant pour la mise à jour d Improvement of Livestock u système d'information et 2019-04-3 2019-06-1 2019-05-0 2019-05-2 2019-06-3 2019-12-2 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 66,000.00 0.00 Annulé de gestion des données sa 0 3 5 6 0 7 ery nitaires, déploiement sur l e terrain (du niveau centra l et déconcentré) et format ion des acteurs majeurs - UCNP CM-MINEPIA-136690-CS-I NDV / Sélection d'un Cons ultant Individuel pour la tr Project coordination, man 2019-10-1 2019-10-1 2019-10-1 2019-10-2 2019-11-0 2019-11-1 2019-12-1 2019-12-1 2020-12-1 aduction des documents d IDA / 59080 agement, communication A posteriori Individuel Limited 5,800.00 7,099.36 Signé 1 8 6 5 6 4 1 7 0 u PRODEL y compris ceux and monitoring de la Commission spéciale de passation des marchés placée auprès du PRODEL CM-MINEPIA-114635-CS-I NDV / Recrutement d'un C onsultant Individuel spécia Improvement of Pastoral P lisé pour l'accompagneme roductivity, Access to Mar 2019-12-3 2019-03-2 2020-02-1 2019-05-0 2020-03-1 2019-05-1 2020-04-1 2019-06-2 2020-10-1 IDA / 59080 A posteriori Individuel Open 50,000.00 50,169.71 Signé nt de 30 femmes bénéficia kets, and Resilience of Pa 1 8 8 9 0 3 4 7 1 ires dans les département storal Communities du Diamaré, Logone et Ch ari et Mayo-Sava à l'utilisat ion des biodigesteurs mod èle CM2013 CM-MINEPIA-162098-CS-C DS / FORMATION ET ACCO MPAGNEMENT DES ELEVE Improvement of Livestock Sélection de co 2020-04-0 2020-01-3 2020-04-1 2020-04-2 2020-06-2 2020-06-3 2020-12-1 URS ET GROUPEMENTS D’ IDA / 59080 Services Access and Deliv A posteriori nsultants par en Direct 115,000.00 93,898.72 Signé 6 0 6 4 0 0 7 ELEVEURS A L’ADOPTION ery tente directe DES INNOVATIONS DANS L A GESTION DURABLE DES RESSOURCES PASTORALES CM-MINEPIA-127235-CS-C Improvement of Pastoral P Sélection de co DS / Accompagnement des roductivity, Access to Mar 2020-04-3 2020-03-2 2020-05-1 2020-04-2 2020-07-1 2020-07-1 2021-01-1 IDA / 59080 A posteriori nsultants par en Direct 47,000.00 35,656.73 Signé communes à la mise en œ kets, and Resilience of Pa 0 8 0 4 4 6 0 tente directe uvre des sous projets dans storal Communities l'Adamaoua) (3ème vague ) CM-MINEPIA-127233-CS-C Improvement of Pastoral P DS / Accompagnement des Sélection de co roductivity, Access to Mar 2020-06-3 2020-03-2 2020-07-1 2020-04-2 2020-09-1 2020-07-1 2021-03-1 communes à la mise en œ IDA / 59080 A posteriori nsultants par en Direct 45,000.00 44,811.61 Signé kets, and Resilience of Pa 0 8 0 4 3 6 2 uvre des sous projets dans tente directe storal Communities l'extrême-Nord (3ème vag ue) CM-MINEPIA-127237-CS-C Improvement of Pastoral P DS / Accompagnement des Sélection de co roductivity, Access to Mar 2020-04-2 2020-03-2 2020-05-0 2020-04-2 2020-07-1 2020-07-1 2021-01-0 communes à la mise en œ IDA / 59080 A posteriori nsultants par en Direct 47,000.00 37,382.70 Signé kets, and Resilience of Pa 9 8 9 4 3 0 9 uvre des sous projets dans tente directe storal Communities EST (GEOBET) (3ème vag ue) CM-MINEPIA-172404-CS-I NDV / Sélection d’un consu ltant individuel local pour l Improvement of Livestock 2020-07-2 2020-02-1 2020-07-2 2020-02-1 2020-08-1 2020-03-1 2020-09-2 2020-05-1 2021-03-2 2021-08-0 a réalisation des enquêtes IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 50,000.00 41,858.16 Achevé 2 0 7 4 7 3 1 1 0 6 de base et post-vaccinale ery sur les maladies animales prioritaires et zoonoses m ajeures dans le cadre du P RODEL CM-MINEPIA-176255-CS-I NDV / Élaboration d'un ma sque de saisie, formation d Improvement of Livestock es agents de saisie, contrô 2020-05-2 2018-07-1 2020-06-0 2020-04-0 2020-06-0 2020-04-2 2020-06-1 2020-05-1 2020-07-2 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 5,000.00 4,577.24 Signé le et apurement des donné 9 1 3 3 8 7 8 5 3 ery es de dénombrement des enquêtes de base et de va ccination contra la peste d es petits ruminants (PPR) dans le cadre du PRODEL CM-MINEPIA-176279-CS-I NDV / Formation des chauf feurs sur la conduite défen Project coordination, man 2020-05-3 2019-12-1 2020-06-0 2020-01-0 2020-06-1 2020-01-2 2020-06-2 2020-05-2 2020-08-2 sive et offensive des véhic IDA / 59080 agement, communication A posteriori Individuel Limited 5,900.00 5,200.50 Signé 0 1 4 2 1 7 1 2 0 ules légers, le sauvetage e and monitoring t le secourisme au travail, l es gestion et la maintenan ce du parc automobile du PRODEL CM-MINEPIA-176286-CS-I NDV / Appui au développe Improvement of Livestock ment d'un système d'infor 2020-05-2 2020-02-1 2020-06-0 2020-02-1 2020-06-2 2020-03-1 2020-07-2 2020-05-1 2021-01-2 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 50,000.00 59,059.46 Signé mations zoo sanitaire d'ale 9 2 3 5 4 6 9 1 5 ery rte instantanée et géo réfé rencée au DSV-MINEPIA da ns le cadre du PRODEL CM-MINEPIA-190085-CS-I Project coordination, man NDV / Recrutement d'un C 2021-09-2 2019-08-1 2021-09-2 2019-09-3 2021-10-2 2019-10-1 2021-11-2 2019-11-0 2022-05-2 2021-01-2 IDA / 59080 agement, communication A posteriori Individuel Limited 120,000.00 53,209.71 Achevé onsultant Individuel pour u 4 9 9 0 0 4 4 4 3 1 and monitoring ne mission d'Assistance te chnique au PRODEL CM-MINEPIA-190097-CS-C DS / Consultant Individuel Project coordination, man pour le poste de Spécialist En cours d'exéc 2021-07-0 2020-11-2 2021-08-2 2021-09-1 2021-10-2 2022-04-2 IDA / 59080 agement, communication A posteriori Individuel Open 65,609.00 0.00 e National en Passation de ution 9 3 7 7 2 0 and monitoring s Marchés (SNPM) du Proje t de Développement de l’E levage (PRODEL) CM-MINEPIA-190092-CS-C DS / Consultant Individuel Project coordination, man En attente d'ex 2021-07-1 2021-09-0 2021-09-2 2021-10-2 2022-04-2 pour le poste de Comptabl IDA / 59080 agement, communication A posteriori Individuel Open 50,794.00 0.00 écution 6 3 4 9 7 e Nationale (CONA) au Proj and monitoring et de Développement de l’ Elevage (PRODEL) CM-MINEPIA-237927-CS-I NDV / RECRUTEMENT D'UN CONSULTANT INDIVIDUEL Support to livestock value En cours d'exéc 2021-07-0 2021-03-0 2021-08-2 2021-09-1 2021-10-2 2022-04-2 POUR L'ACCOMPAGNEMEN IDA / 59080 A posteriori Individuel Open 83,333.00 0.00 chains development ution 9 4 7 7 2 0 T DE LA STRUCTURATION DE L'INTERPROFESSION AP ICOLE ET LA PROMOTION DES PRODUITS DE LA RUC HE CM-MINEPIA-237841-CS-I NDV / RECRUTEMENT D'UN CONSULTANT INDIVIDUEL Support to livestock value 2021-10-2 2021-03-0 2021-12-1 2021-06-3 2022-01-0 2021-07-0 2022-02-0 2021-09-1 2022-08-0 DANS LE CADRE DE L'APP IDA / 59080 A posteriori Individuel Open 25,000.00 18,795.47 Signé chains development 6 4 4 0 4 6 8 4 7 UI A LA MISE EN PLACE D'U NE INTERCOMMUNALITE P OUR LA PROMOTION DES P RODUITS DE L'ELEVAGE A U CAMEROUN CM-MINEPIA-236835-CS-Q CBS / Audit Financier et Co Project coordination, man Sélection de co En cours d'exéc 2021-07-1 2020-06-1 2021-07-2 2021-09-2 2022-03-2 mptable du Projet de Déve IDA / 59080 agement, communication A posteriori nsultants par en Direct 28,333.33 0.00 ution 5 7 5 8 7 loppement de l’Elevage (P and monitoring tente directe RODEL) pour l'Exercice clo s au 31 Décembre 2020 CM-MINEPIA-223627-CS-I NDV / RECRUTEMENT D'UN CONSULTANT INDIVIDUEL Support to livestock value 2021-05-0 2021-07-1 2021-05-1 2021-07-0 2021-06-0 2021-08-3 2021-07-0 2022-01-2 2022-01-0 IDA / 59080 A posteriori Individuel Limited 13,913.00 13,461.85 Signé POUR LA PRODUCTIONN D' chains development 6 5 1 9 1 1 6 4 2 UN RECEUIL DE DOCUMEN TS LEGAUX SUR LE PASTO RALISME (UCNP) Page 12 CM-MINEPIA-245271-CS-I NDV / RECRUTEMENT D'UN CONSULTANT INDIVIDUEL Support to livestock value En cours d'exéc 2021-07-2 2021-02-0 2021-09-1 2021-10-0 2021-11-0 2022-05-0 DANS LE CADRE DE L'APP IDA / 59080 A posteriori Individuel Open 11,667.00 0.00 chains development ution 3 2 0 1 5 4 UI A LA ?MISE EN PLACE D' UNE INTERCOMMUNALITE POUR LA PROMOTION DES PRODUITS D'ELEVAGE AU CAMEROUN CM-MINEPIA-223720-CS-I NDV / RECRUTEMENT D'UN CONSULTANT INDIVIDUEL Improvement of Pastoral P POUR L'ELEBORATION DE roductivity, Access to Mar En cours d'exéc 2021-10-2 2021-07-1 2021-12-1 2022-01-0 2022-02-1 2022-08-0 LA STRATEGIE ET LE PLAN IDA / 59080 A posteriori Individuel Open 46,667.00 0.00 kets, and Resilience of Pa ution 8 5 6 6 0 9 DE MISE EN PLACE DES IN storal Communities STANCES INTERCOMMUNA LES DE GESTION DES RESS OURCES PASTORALES CO MMUNES Y COMPRIS LA TR ANSHUMANCE CM-MINEPIA-172408-CS-I NDV / Sélection d’un consu Improvement of Livestock ltant individuel pour l’élab 2021-08-0 2021-08-0 2021-08-2 2021-10-0 2022-03-3 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 50,000.00 0.00 Annulé oration d’un manuel illustr 2 7 8 2 1 ery é et pratique d’inspection sanitaire vétérinaire dans l e cadre du PRODEL CM-MINEPIA-177374-CS-I NDV / Sélection d'un consu Project coordination, man 2020-06-3 2020-07-2 2020-07-0 2020-07-2 2020-07-3 2021-07-3 ltant individuel pour la con IDA / 59080 agement, communication A posteriori Individuel Limited 6,000.00 0.00 Annulé 0 2 5 0 0 0 ception et production des and monitoring supports de communicatio n dans le cadre du PRODE L CM-MINEPIA-128470-CS-I NDV / Sélection d'un consu ltant individuel pour le sui Improvement of Pastoral P vi/contrôle des travaux de roductivity, Access to Mar 2020-04-1 2020-07-2 2020-04-2 2020-05-1 2020-06-1 2020-10-1 IDA / 59080 A posteriori Individuel Limited 2,934.00 0.00 Annulé Construction de trois parcs kets, and Resilience of Pa 8 2 3 4 8 6 d’intervention zoo sanitair storal Communities e dans les localités de la c ommune de Pette Départ ement du Diamaré, Région de l’Extrême-Nord CM-MINEPIA-177378-CS-I NDV / Sélection d'un consu Project coordination, man 2020-07-1 2020-07-2 2020-07-2 2020-08-0 2020-08-1 2021-08-1 ltant individuel pour l'entr IDA / 59080 agement, communication A posteriori Individuel Limited 5,000.00 0.00 Annulé 7 2 2 6 6 6 etien et l'actualisation du s and monitoring ite internet du PRODEL (co ntractualisation d'un Web marter) CM-MINEPIA-127234-CS-C Improvement of Pastoral P Sélection de co DS / Accompagnement des roductivity, Access to Mar 2020-05-2 2020-08-0 2020-06-0 2020-08-0 2021-02-0 IDA / 59080 A posteriori nsultants par en Direct 47,000.00 0.00 Annulé communes à la mise en œ kets, and Resilience of Pa 6 6 5 9 5 tente directe uvre des sous projets dans storal Communities NO (SNV) (3 ème vague) CM-MINEPIA-136714-CS-I Improvement of Livestock NDV / Sélection d'un Cons 2019-10-2 2020-05-2 2019-10-2 2019-11-1 2019-12-2 2020-01-0 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 2,500.00 0.00 Annulé ultant Individuel pour la ré 0 9 5 5 0 4 ery alisation d'un documentair e sur la vaccination CM-MINEPIA-136718-CS-I NDV / Sélection d'un Cons Improvement of Livestock ultant Individuel devant ré 2019-10-2 2020-07-1 2019-10-2 2019-11-1 2019-12-2 2020-01-1 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 6,900.00 0.00 Annulé aliser une émission radio c 1 5 6 6 1 1 ery ommunautaire, une campa gne SMS et une campagne Facebook dans le cadre de la vaccination CM-MINEPIA-190089-CS-I Improvement of Livestock 2021-09-2 2021-09-2 2021-10-2 2021-11-2 2022-01-2 NDV / Révision du plan de IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 6,800.00 0.00 Annulé 4 9 0 4 3 formation du PRODEL ery CM-MINEPIA-106326-CS-I NDV / Mise en place d'un s ystème d'information en li Support to livestock value 2019-06-2 2020-05-2 2019-08-1 2019-09-0 2019-10-1 2020-01-0 gne sur les marchés, les pr IDA / 59080 A posteriori Individuel Open 33,500.00 0.00 Annulé chains development 8 9 6 6 1 9 ix, les services et les prod uits financiers, la technolo gie, les OP, etc. ouvert à to us les acteurs de la chaîne de valeur. CM-MINEPIA-106296-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-05-2 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 18,500.00 0.00 Annulé nce des travaux de forage kets, and Resilience of Pa 1 9 9 9 3 1 s, dans les communes de storal Communities Garoua 3, Guider CM-MINEPIA-106310-CS-I NDV / Contrôle des travau Improvement of Pastoral P x de construction de bouc roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 9,500.00 0.00 Annulé heries, marché à bétail , m kets, and Resilience of Pa 1 5 9 9 3 1 atérialisation d'une piste à storal Communities bétail dans la commune d e Garoua Boulai, CM-MINEPIA-106297-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 nce des pars d'interventio IDA / 59080 A posteriori Individuel Open 17,000.00 0.00 Annulé kets, and Resilience of Pa 1 5 9 9 3 1 ns zoosanitaires, pistes à b storal Communities étail dans les communes d e Lagdo, Ngong CM-MINEPIA-106309-CS-I NDV / Contrôle des travau Improvement of Pastoral P x de construction de bouc roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 15,700.00 0.00 Annulé heries, marché à bétail , m kets, and Resilience of Pa 1 5 9 9 3 1 atérialisation d'une piste à storal Communities bétail dans les communes de Ketté, Batouri CM-MINEPIA-106293-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 nce des travaux de parcs z IDA / 59080 A posteriori Individuel Open 9,200.00 0.00 Annulé kets, and Resilience of Pa 1 5 9 9 3 1 oosanitaires, pistes à bétai storal Communities l dans les communes de P étté, Tokombéré CM-MINEPIA-106304-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 nce des pars d'interventio IDA / 59080 A posteriori Individuel Open 19,200.00 0.00 Annulé kets, and Resilience of Pa 1 5 9 9 3 1 ns zoosanitaires, pistes à b storal Communities étail dans les communes d eMeiganga, Ngaoundal CM-MINEPIA-106299-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 nce des pars d'interventio IDA / 59080 A posteriori Individuel Open 15,500.00 0.00 Annulé kets, and Resilience of Pa 1 5 9 9 3 1 ns zoosanitaires, pistes à b storal Communities étail dans les communes d e Garoua 3, Guider CM-MINEPIA-106308-CS-I Improvement of Pastoral P NDV / Contrôle des travau roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 x de construction de bouc IDA / 59080 A posteriori Individuel Open 10,000.00 0.00 Annulé kets, and Resilience of Pa 1 5 9 9 3 1 heries, aire d'abbatage , m storal Communities atérialisation d'une piste à bétail dans la commune de Batouri CM-MINEPIA-106307-CS-I NDV / Contrôle des travau Improvement of Pastoral P x de construction de deux roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 7,500.00 0.00 Annulé (2) forages pastoraux à én kets, and Resilience of Pa 1 5 9 9 3 1 ergie solaire dans les locali storal Communities tés de Mombal et Mborgué né (Commune de Garoua- Boulaï) CM-MINEPIA-106303-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 22,300.00 0.00 Annulé nce des travaux de forage kets, and Resilience of Pa 1 5 9 9 3 1 s, dans les communes de storal Communities Meiganga, Ngaoundal CM-MINEPIA-106306-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 nce des pars d'interventio IDA / 59080 A posteriori Individuel Open 19,500.00 0.00 Annulé kets, and Resilience of Pa 1 5 9 9 3 1 ns zoosanitaires, pistes à b storal Communities étail dans les communes d e Bélel, Ngaoundéré 3, Bél el CM-MINEPIA-106294-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 nce des travaux de parcs z IDA / 59080 A posteriori Individuel Open 7,650.00 0.00 Annulé kets, and Resilience of Pa 1 5 9 9 3 1 oosanitaires, pistes à bétai storal Communities l, points d'eau dans les co mmunes de Yagoua CM-MINEPIA-106300-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 18,500.00 0.00 Annulé nce des travaux de forage kets, and Resilience of Pa 1 5 9 9 3 1 s, dans les communes de storal Communities Bélel, Ngaoundéré 3 CM-MINEPIA-106295-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 18,500.00 0.00 Annulé nce des travaux de forage kets, and Resilience of Pa 1 5 9 9 3 1 s, dans les communes de L storal Communities agdo, Ngong CM-MINEPIA-106311-CS-I Improvement of Pastoral P NDV / Contrôle des travau roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 x de construction des aires IDA / 59080 A posteriori Individuel Open 6,700.00 0.00 Annulé kets, and Resilience of Pa 1 5 9 9 3 1 d'abbatage, piste à bétail , storal Communities parc d'intervention zoosan itaires dans la commune d e Bétaré Oya CM-MINEPIA-106290-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 15,000.00 0.00 Annulé nce des travaux de forage kets, and Resilience of Pa 1 5 9 9 3 1 s/AEP dans les communes storal Communities de Kaélé, Yagoua CM-MINEPIA-106291-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 9,500.00 0.00 Annulé nce des travaux de parcs z kets, and Resilience of Pa 1 5 9 9 3 1 oosanitaires, pistes à bétai storal Communities l dans les communes de K aélé CM-MINEPIA-106288-CS-I Improvement of Pastoral P NDV / Contrôle et surveilla roductivity, Access to Mar 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2020-03-1 IDA / 59080 A posteriori Individuel Open 26,000.00 0.00 Annulé nce des travaux de forage kets, and Resilience of Pa 0 5 8 8 2 0 s dans les communes de P storal Communities etté, Tokombéré, Logone B irni CM-MINEPIA-98754-CS-IN DV / Recrutement d'un Co nsultant individuel pour a Improvement of Livestock nimer l'atelier de formatio 2019-04-2 2020-07-1 2019-04-3 2019-05-2 2019-06-2 2019-08-2 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 32,500.00 0.00 Annulé n à la méthodologie du ca 5 5 0 1 5 4 ery dre réglementaire et propo ser 02 projets de textes (s écurité sanitaire et systèm e de compensation en tem ps de crises) CM-MINEPIA-106344-CS-I Project coordination, man NDV / Recrutement d'un c 2019-05-3 2020-07-1 2019-07-1 2019-08-0 2019-09-1 2019-12-1 IDA / 59080 agement, communication A posteriori Individuel Open 41,500.00 0.00 Annulé onsultant pour évaluer la c 1 5 9 9 3 2 and monitoring ontribution du Projet aux e ffets de changement clima tiques CM-MINEPIA-128474-CS-I NDV / Sélection d'un consu ltant individuel pour le sui Improvement of Pastoral P vi/contrôle des travaux de roductivity, Access to Mar 2021-07-2 2021-08-0 2021-08-2 2021-09-2 2022-01-2 IDA / 59080 A posteriori Individuel Limited 5,023.00 0.00 Annulé Construction de trois forag kets, and Resilience of Pa 8 2 3 7 5 es pastoraux à énergie sol storal Communities aire dans les localités Com mune de Pette, Départem ent du Diamaré, Région de l'Extrême-Nord CM-MINEPIA-190087-CS-I Improvement of Livestock NDV / Recrutement d'un C 2021-09-2 2021-09-2 2021-10-2 2021-11-2 2022-02-2 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 42,000.00 0.00 Annulé onsultant Individuel pour l' 4 9 0 4 2 ery assistance technique dans la station d'élévage de Wa kwa CM-MINEPIA-190102-CS-C DS / Consultant Individuel Project coordination, man pour le poste de Coordonn 2021-07-0 2021-08-2 2021-09-1 2021-10-2 2022-04-1 IDA / 59080 agement, communication A posteriori Individuel Open 65,609.00 0.00 Annulé ateur Régional de la zone 8 6 6 1 9 and monitoring 3 (LITTORAL/NORD-OUEST/ OUEST/SUD-OUEST) du Pro jet de Développement de l ’Elevage (PRODEL) CM-MINEPIA-216214-CS-I Improvement of Pastoral P NDV / RECRUTEMENT D'UN roductivity, Access to Mar 2021-07-0 2021-09-0 2021-09-2 2021-10-1 2022-04-1 CONSULTANT INDIVIDUEL IDA / 59080 A posteriori Individuel 224,299.00 0.00 Annulé kets, and Resilience of Pa 1 4 5 6 4 POUR L'APPUI A LA MISE E storal Communities N OEUVRE DU PROGRAMM E NATIONAL D'IA CM-MINEPIA-245268-CS-I NDV / SELECTION D'UN CO NSULTANT INDIVIDUEL REL Improvement of Pastoral P ATIF A L'APPROPRIATIONV roductivity, Access to Mar 2021-07-2 2021-07-2 2021-08-1 2021-09-2 2022-03-2 ULGARISATION DU PLAN N IDA / 59080 A posteriori Individuel Limited 7,750.00 0.00 Annulé kets, and Resilience of Pa 3 8 8 2 1 ATIONAL DE CONTINGENC storal Communities E PASTORALE ET FIORMATI ON DES ACTEURS LOCAUX AUX OUTILS LEGS (PRISE E N CHARGE ET ACCOMPAG NEMENT DES EXPERTS LE CM-MINEPIA-245258-CS-I GS) NDV / SELECTION D'UN CO NSULTANT INDIVIDUEL PO Improvement of Pastoral P UR LA MISSION DE CONTR roductivity, Access to Mar 2021-07-2 2021-07-2 2021-08-1 2021-09-2 2022-03-2 IDA / 59080 A posteriori Individuel Limited 6,667.00 0.00 Annulé OLE RELATIVE A LA FOURN kets, and Resilience of Pa 3 8 8 2 1 ITURE DE LA 2ème VAGUE storal Communities DE CENT SOIXANTE (165) GENISSES GESTANTES DE RACE MONTBELIARDE DAN S LE CADRE DU PRODEL CM-MINEPIA-190099-CS-C DS / Consultant Individuel Project coordination, man pour le poste de Coordonn 2021-11-1 2022-01-0 2022-01-2 2022-03-0 2022-08-2 IDA / 59080 agement, communication A posteriori Individuel Open 65,609.00 0.00 Annulé ateur Régional de la zone 7 5 6 2 9 and monitoring 2 (ADAMAOUA/EST/SUD) d u Projet de Développemen t de l’Élevage (PRODEL). Page 13 CM-MINEPIA-237936-CS-I NDV / SELECTION DE CON SULTANTS INDIVIDUELS (U N PAR LOT) POUR LES MIS Improvement of Livestock 2021-08-1 2021-10-0 2021-10-2 2021-11-2 2022-05-2 SIONS D'ACCOMPAGNEME IDA / 59080 Services Access and Deliv A posteriori Individuel Open 58,333.00 0.00 Annulé 6 4 5 9 8 NT DES ELEVEURS A LA VA ery CCINATION CONTRE LA FIE VRE APHTEUSE POUR LES SITES DE KAELE, MAROUA, GAROUA, GUIDER, MEIGAN GA, VINA 1, VINA 2, LIBON GCM-MINEPIA-238076-CS-I ET TIBATI NDV / SELECTION DE TROI S (03) CONSULTANTS INDI VIDUELS (un par lot) POUR Improvement of Livestock LES MISSIONS DE CONTRO 2021-07-0 2021-07-1 2021-08-0 2021-09-0 2022-03-0 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 17,750.00 0.00 Annulé LE RELATIVES A LA REHABI 9 4 4 8 7 ery LITATION DE TROIS (03) ST ATIONS D’ELEVAGE DANS LE CADRE DU PRODEL LOT 1 : KOUNDEN (OUEST) , LOT 2 : LOUGUERRE (NO RD) ET LOT 3: WAKWA CM-MINEPIA-190101-CS-C DS / Consultant Individuel Project coordination, man 2021-07-0 2021-08-2 2021-09-1 2021-10-2 2022-04-2 pour le poste de Spécialist IDA / 59080 agement, communication A posteriori Individuel Open 65,609.00 0.00 Annulé 9 7 7 2 0 e Nationale du Suivi-évalu and monitoring ation (SNSE) du Projet de Développement de l’Eleva ge (PRODEL) CM-MINEPIA-238085-CS-I NDV / MAITRISE D’ŒUVRE POUR LA FOURNITURE DE Improvement of Livestock 2021-06-0 2021-06-0 2021-06-2 2021-08-0 2021-12-0 LA DEUXIEME VAGUE DES IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 88,333.00 0.00 Annulé 3 8 9 3 1 GENISSES GESTANTES DE ery RACE MONTBELIARDE D ANS LE CADRE DU PROJET DE DEVELOPPEMENT DE L’ ELEVAGE (PRODEL) CM-MINEPIA-190100-CS-C DS / Consultant Individuel Project coordination, man 2021-07-0 2021-08-2 2021-09-1 2021-10-2 2023-10-1 pour le poste de Coordonn IDA / 59080 agement, communication A posteriori Individuel Open 65,609.00 0.00 Annulé 8 6 6 1 1 ateur Régional de la zone and monitoring 1 (AD/EN/NO) du Projet de Développement de l’Eleva ge (PRODEL) CM-MINEPIA-159864-CS-I NDV / Sélection d'un consu Improvement of Livestock ltant individuel pour la sais 2022-01-2 2022-01-3 2022-02-1 2022-03-0 2022-05-0 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 16,666.67 0.00 Annulé ie et traitement des donné 5 0 4 6 5 ery es de vaccination, des enq uêtes de base et de l'enqu ête post-vaccinale PPR dan s le cadre du prodel CM-MINEPIA-162106-CS-I NDV / Recrutement d'un C Improvement of Livestock 2022-03-2 2022-03-2 2022-04-1 2022-05-2 2022-11-2 onsultant Individuel pour l' IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 50,000.00 0.00 Annulé 4 9 9 4 0 appui aux enquêtes de réf ery érence sur les maladies pri oritaires dans le cadre du PRODEL CM-MINEPIA-224687-CS-I NDV / RECRUTEMENT D'UN Improvement of Livestock CONSULTANT INTERNATIO 2021-06-1 2021-06-2 2021-07-1 2021-08-1 2021-10-0 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 29,167.00 0.00 Annulé NAL POUR L'APPUI A L'ORG 7 2 3 7 1 ery ANISATION DES EXERCIXE S DE SIMULATION DES CRI SES CLIMATIQUES CM-MINEPIA-216105-CS-I Project coordination, man NDV / RECRUTEMENT D'UN 2021-10-2 2021-12-1 2022-01-0 2022-02-0 2023-02-0 IDA / 59080 agement, communication A posteriori Individuel Open 33,645.00 0.00 Annulé CONSULTANT POUR L'ASSI 7 5 5 9 4 and monitoring STANCE JURIDIQUE DU PR ODEL CM-MINEPIA-216104-CS-I NDV / RECRUTEMENT D'UN Project coordination, man CONSULTANT POUR L'APP 2021-10-2 2021-10-2 2021-11-1 2021-12-2 2022-06-1 IDA / 59080 agement, communication A posteriori Individuel Limited 9,346.00 0.00 Annulé UI A LA MISE EN PLACE D'U 1 6 6 1 9 and monitoring N SYSTEME D'ARCHIVAGE NUMERIQUE ET PHYSIQUE DES DOCUMENTS DU PROJ ET CM-MINEPIA-216102-CS-I NDV / RECRUTEMENT D'UN Project coordination, man 2021-09-2 2021-09-2 2021-10-1 2021-11-2 2022-11-1 CONSULTANT INDIVIDUEL IDA / 59080 agement, communication A posteriori Individuel Limited 10,093.00 0.00 Annulé 0 5 6 0 5 POUR L'INFOGRAPHIE-VIDE and monitoring ASTE-MONTEUR POUR UNE PERIODE DE DOUZE (12) M OIS CM-MINEPIA-24442-CS-CQ Improvement of Livestock Sélection de co S / Appui à la surveillance 2017-10-2 2017-11-1 2018-06-1 2018-01-2 2018-06-2 IDA / 59080 Services Access and Deliv A posteriori nsultants par en Direct 240,000.00 0.00 Annulé des maladies animales et z 9 8 1 2 1 ery tente directe oonoses prioritaires au Ca meroun CM-MINEPIA-224098-CS-I NDV / RECRUTEMENT D'UN Improvement of Livestock 2021-12-1 2021-06-1 2021-07-0 2021-08-1 2022-02-0 CONSULTANT INDIVIDUEL IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 25,000.00 0.00 Annulé 5 5 6 0 6 POUR L'ELABORATION D'U ery N REFERENTIEL TECHNICO ECONOMIQUE ET EDITION CM-MINEPIA-278083-CS-I NDV / RECRUTEMENT D'UN Project coordination, man En attente d'ex 2022-03-2 2022-03-3 2022-04-2 2022-05-2 2022-11-2 CONSULTANT INDIVIDUEL IDA / 59080 agement, communication A posteriori Individuel Limited 20,000.00 0.00 écution 5 0 0 5 1 POUR LA REALISATION DE and monitoring SEPT (07) PUBLI-REPORTA GE POUR LE COMPTE DU P RODEL CM-MINEPIA-285987-CS-I Improvement of Pastoral P NDV / Recrutement des co roductivity, Access to Mar En attente d'ex 2022-07-1 2022-07-2 2022-08-1 2022-09-1 2023-03-1 nsultants individuels pour l IDA / 59080 A posteriori Individuel Limited 133,333.00 0.00 kets, and Resilience of Pa écution 5 0 0 4 3 a réalisation de deux mille storal Communities (2 000) inséminations artifi cielles en 2022 CM-MINEPIA-286016-CS-I Project coordination, man NDV / Recrutement d'un C En attente d'ex 2022-08-2 2022-08-2 2022-09-0 2022-09-1 2022-10-1 IDA / 59080 agement, communication A posteriori Individuel Limited 66,666.00 0.00 onsultant Individuel pour l' écution 4 9 5 9 9 and monitoring élaboration du rapport d'a chèvement du PRODEL CM-MINEPIA-286030-CS-I Improvement of Pastoral P NDV / Recrutement d'un C roductivity, Access to Mar En attente d'ex 2022-07-2 2022-08-0 2022-08-1 2022-08-2 2022-11-2 onsultant Individuel pour l IDA / 59080 A posteriori Individuel Limited 58,333.00 0.00 kets, and Resilience of Pa écution 7 1 5 9 7 a réalisation de l'Audit Env storal Communities ironnemental et Social du PRODEL CM-MINEPIA-190095-CS-C DS / Consultant Individuel Project coordination, man 2022-02-0 2022-03-3 2022-04-2 2022-05-2 2022-11-2 pour le poste de Spécialist IDA / 59080 agement, communication A posteriori Individuel Open 65,609.00 0.00 Annulé 9 0 0 5 1 e National en Santé Anima and monitoring le (SNSA) du Projet de Dév eloppement de l’Elevage ( PRODEL) CM-MINEPIA-190094-CS-C DS / Consultant Individuel Project coordination, man pour le poste de Comptabl 2022-02-0 2022-03-3 2022-04-2 2022-05-2 2022-11-2 IDA / 59080 agement, communication A posteriori Individuel Open 42,329.00 0.00 Annulé e Régionale de la zone 2 ( 9 0 0 5 1 and monitoring EST/SUD/ADAMAOUA) du P rojet de Développement d e l’Elevage (PRODEL) CM-MINEPIA-237938-CS-I NDV / RECRUTEMENT DE C ONSULTANTS INDIVIDUELS Support to livestock value 2022-04-1 2021-03-2 2022-05-1 2021-09-2 2022-05-1 2021-09-2 2022-05-2 2022-06-0 2022-07-2 IDA / 59080 A posteriori Individuel Open 83,333.00 77,734.00 Signé POUR L'APPUI A LA MISE E chains development 5 5 1 4 6 9 8 1 7 N OEUVRE DU PROGRAMM E NATIONAL D'INSEMINATI ON-CAMPAGNE 2021 CM-MINEPIA-237869-CS-I NDV / RECRUTEMENT D'UN Improvement of Pastoral P CONSULTANT INDIVIDUEL roductivity, Access to Mar En attente d'ex 2022-04-1 2022-06-0 2022-06-2 2022-08-0 2023-01-2 IDA / 59080 A posteriori Individuel Open 46,500.00 0.00 SPECIALISTE NATIONAL EN kets, and Resilience of Pa écution 9 7 8 2 9 VIRONNEMENTAL ET SOCI storal Communities AL DU PROJET DE DEVELO PPEMENT DE L'ELEVAGE CM-MINEPIA-297823-CS-I NDV / Production d'un doc Project coordination, man En attente d'ex 2022-08-0 2022-08-0 2022-08-2 2022-10-0 2022-10-3 umentaire de onze (11) mi IDA / 59080 agement, communication A posteriori Individuel Limited 20,000.00 0.00 écution 1 6 7 1 1 nutes construit sur le mod and monitoring èle de développement tria ngulaire - PRODEL CM-MINEPIA-285915-CS-I NDV / Recrutement d'un C Improvement of Pastoral P onsultant Individuel en vue roductivity, Access to Mar En attente d'ex 2022-08-0 2022-08-0 2022-08-2 2022-09-1 2022-10-1 IDA / 59080 A posteriori Individuel Limited 16,666.00 0.00 du renforcement des capa kets, and Resilience of Pa écution 1 6 0 0 0 cités du personnel du MIN storal Communities EPIA pour le contrôle de qu alité de l’alimentation du b étail CM-MINEPIA-285897-CS-I NDV / Recrutement d’un C Improvement of Livestock onsultant Individuel pour l En attente d'ex 2022-08-0 2022-08-1 2022-08-2 2022-09-0 2023-03-0 IDA / 59080 Services Access and Deliv A posteriori Individuel Limited 25,000.00 0.00 a Capitalisation des résult écution 5 0 4 7 6 ery ats des campagnes de vac cination et actualisation du PNCE-PPR (phase éradicati on) - Cameroun Page 14