PROCUREMENT PLAN (Textual Part) Project information: [Sudan] [Sudan Family Support Program] (SFSP) (P173521) Project Implementation agency: [Ministry of Finance & Economic Planning/ PIU] Date of the Procurement Plan: [31/08/2020] Period covered by this Procurement Plan: [18 Month] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Sudan procurement contracting and disposal of assets law 2010], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. [Applicable as provide in section 5 paragraph 5.3 to 5.6 of procurement REGULATION for IPF Borrowers] When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable is for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. [N/A] PROCUREMENT Sudan : Sudan Family Support Project PLAN General Information Country: Sudan 2020-11-22 Bank’s Approval Date of the Original Procurement Plan: 2022-09-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173521 GPN Date: Project Name: Sudan Family Support Project Loan / Credit No: IDA / D7350, TF / B4259 Ministry of Finance and Economic Planning Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota SD-MOFEP-294285-CW-DIR / Component 2: Establish Deli tions - Small Work Pending Imp 2023-03-2 work for Bahary registration IDA / D7350 very Systems and Build Insti Post Direct Selection Direct - National s (Emergency) SP 12,500.00 0.00 2022-08-18 2022-08-23 2022-09-27 lementation 6 center tutional Capacity D -Non Competiti ve GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOWSS-202443-GO-RFQ Component 2: Establish Deli Request for Quota Single Stage - One E Pending Impl / ICT Hardware / USSD Gatew IDA / D7350 very Systems and Build Insti Post Limited 190,000.00 0.00 2020-11-06 2021-01-01 2021-06-30 tions nvelope ementation ay tutional Capacity SD-MOWSS-202446-GO-RFQ Component 2: Establish Deli Request for Quota Single Stage - One E / Laptops for physical Registr IDA / D7350 very Systems and Build Insti Post Limited 125,000.00 197,696.39 Completed 2020-11-06 2021-05-05 2021-01-01 2021-07-05 2021-06-30 2021-09-04 tions nvelope ation tutional Capacity SD-MOWSS-202448-GO-RFQ Component 2: Establish Deli Request for Quota Single Stage - One E / Tablets for physical registra IDA / D7350 very Systems and Build Insti Post Limited 60,000.00 85,016.64 Completed 2020-11-06 2021-02-18 2021-01-01 2021-03-18 2021-06-30 2021-04-19 tions nvelope tion tutional Capacity SD-MOWSS-202449-GO-RFQ Component 2: Establish Deli Request for Quota Single Stage - One E Pending Impl / Rent bandwidth for USSD (t IDA / D7350 very Systems and Build Insti Post Limited 3,000.00 0.00 2020-11-06 2021-01-01 2021-06-30 tions nvelope ementation hree Telcos) tutional Capacity Component 2: Establish Deli SD-MOWSS-202639-GO-RFQ Request for Quota Single Stage - One E Pending Impl IDA / D7350 very Systems and Build Insti Post Limited 10,000.00 0.00 2020-11-09 2021-01-04 2021-07-03 / CRM Software tions nvelope ementation tutional Capacity SD-MOWSS-202640-GO-RFQ Component 2: Establish Deli Request for Quota Single Stage - One E Pending Impl / Vehicle for Mobile registrati IDA / D7350 very Systems and Build Insti Post Limited 1,375,000.00 0.00 2020-11-09 2021-01-04 2021-07-03 tions nvelope ementation on tutional Capacity SD-MOWSS-202642-GO-RFQ Component 2: Establish Deli Request for Quota Open - Internationa Single Stage - One E / Satellite Communication for IDA / D7350 very Systems and Build Insti Post 125,000.00 0.00 Canceled 2020-11-09 2021-01-04 2021-07-03 tions l nvelope registration vehicles tutional Capacity Component 2: Establish Deli SD-MOFEP-235901-GO-RFB / Single Stage - One E IDA / D7350 very Systems and Build Insti Post Request for Bids Open - National 750,000.00 1,372,202.00 Signed 2021-05-24 2021-05-30 2021-05-30 2021-06-30 2021-07-15 2021-07-26 2021-07-21 2021-07-29 2021-09-06 2021-08-15 Supply of Tablets nvelope tutional Capacity Component 2: Establish Deli SD-MOFEP-236095-GO-RFQ / Request for Quota Single Stage - One E IDA / D7350 very Systems and Build Insti Post Limited 100,000.00 193,394.16 Completed 2021-07-05 2021-05-05 2021-08-30 2021-05-16 2022-02-26 2021-06-22 Supply of tablets tions nvelope tutional Capacity SD-MOFEP-238895-GO-RFB / Component 2: Establish Deli Single Stage - One E Procurement of four servers, IDA / D7350 very Systems and Build Insti Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-06-20 2021-06-25 2021-08-06 2021-09-05 2021-10-10 2022-04-08 nvelope firewall and related items tutional Capacity Component 3: Project Manag SD-MOFEP-247188-GO-RFQ / Request for Quota Single Stage - One E IDA / D7350 ement, Monitoring and Evalu Post Open - National 120,000.00 119,201.77 Completed 2021-08-13 2021-10-08 2021-08-04 2022-04-06 2021-12-18 Vehicle for PIU Staff tions nvelope ation, and Learning SD-MOFEP-247316-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Supply of IT Equipment for G IDA / D7350 ement, Monitoring and Evalu Post Open - National 33,000.00 21,536.48 Completed 2021-08-14 2021-10-09 2021-07-25 2022-04-07 2021-11-27 tions nvelope D at MOFEM ation, and Learning SD-MOFEP-247318-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Optical Fiber for Network bet IDA / D7350 ement, Monitoring and Evalu Post Open - National 5,000.00 2,729.86 Completed 2021-08-14 2021-10-09 2021-08-05 2022-04-07 2021-09-04 tions nvelope ween NCR and MOFEP ation, and Learning SD-MOFEP-247319-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Spare Parts for UNAMID Vehi IDA / D7350 ement, Monitoring and Evalu Post Open - National 50,000.00 30,820.74 Completed 2021-08-14 2021-10-09 2021-10-12 2022-04-07 2021-11-22 tions nvelope cles ation, and Learning SD-MOFEP-247322-GO-DIR / Component 3: Project Manag Supply of 32 vehicles from U IDA / D7350 ement, Monitoring and Evalu Post Direct Selection Direct 100,000.00 101,041.57 Completed 2021-08-09 2021-04-05 2021-08-14 2021-03-29 2021-09-18 2021-05-05 2022-03-17 2021-08-31 NAMID IN SUDAN ation, and Learning SD-MOFEP-247323-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Supply of IT Equipment or SF IDA / D7350 ement, Monitoring and Evalu Post Open - National 50,000.00 17,769.80 Completed 2021-08-14 2021-10-09 2021-10-10 2022-04-07 2021-10-12 tions nvelope SP PIU ation, and Learning Component 3: Project Manag SD-MOFEP-249644-GO-RFQ / Request for Quota Single Stage - One E IDA / D7350 ement, Monitoring and Evalu Post Open - National 36,000.00 28,785.47 Completed 2021-09-03 2021-10-29 2021-10-14 2022-04-27 2021-10-16 PIU Furniture tions nvelope ation, and Learning SD-MOFEP-249645-GO-RFQ / Component 2: Establish Deli Request for Quota Single Stage - One E Procurement of Servers and r IDA / D7350 very Systems and Build Insti Post Open - National 193,000.00 268.67 Completed 2021-09-03 2021-10-29 2021-09-19 2022-04-27 2021-12-26 tions nvelope elated equipment tutional Capacity Component 2: Establish Deli SD-MOFEP-249652-GO-RFB / Single Stage - One E Pending Impl IDA / D7350 very Systems and Build Insti Post Request for Bids Open - National 450,000.00 0.00 2021-09-08 2021-09-13 2021-10-25 2021-11-24 2021-12-29 2022-06-27 Enrollment Mobile Stations nvelope ementation tutional Capacity Component 3: Project Manag SD-MOFEP-249653-GO-RFQ / Request for Quota Single Stage - One E Pending Impl IDA / D7350 ement, Monitoring and Evalu Post Open - National 20,000.00 0.00 2021-09-21 2021-11-16 2022-05-15 Printing & media Material tions nvelope ementation ation, and Learning Page 1 SD-MOFEP-252434-GO-RFB / Component 2: Establish Deli Single Stage - One E Under Imple Procurement of USSD for MO IDA / D7350 very Systems and Build Insti Post Request for Bids Open - National 325,000.00 0.00 2021-09-09 2020-12-27 2021-09-14 2021-10-26 2021-11-25 2021-12-30 2022-06-28 nvelope mentation FEP tutional Capacity Component 2: Establish Deli SD-MOFEP-252438-GO-RFB / Open - Internationa Single Stage - One E Pending Impl IDA / D7350 very Systems and Build Insti Post Request for Bids 550,000.00 0.00 2021-09-09 2021-09-14 2021-10-26 2021-11-25 2021-12-30 2022-06-28 GRM Software for MOFEP l nvelope ementation tutional Capacity Component 2: Establish Deli SD-MOFEP-252440-GO-RFB / Open - Internationa Single Stage - One E Pending Impl IDA / D7350 very Systems and Build Insti Prior Request for Bids 1,500,000.00 0.00 2021-09-08 2021-09-13 2021-10-25 2021-11-24 2021-12-29 2022-06-27 Data Center for MOFEP l nvelope ementation tutional Capacity SD-MOFEP-252446-GO-RFB / Component 2: Establish Deli Open - Internationa Single Stage - One E Pending Impl Two DR Sites one for MOFEP IDA / D7350 very Systems and Build Insti Prior Request for Bids 8,000,000.00 0.00 2021-09-08 2021-09-13 2021-10-25 2021-11-24 2021-12-29 2022-06-27 l nvelope ementation and other for NCR tutional Capacity SD-MOFEP-290281-GO-RFQ / Component 3: Project Manag Supply of IT equipment for t Request for Quota Single Stage - One E Pending Impl IDA / D7350 ement, Monitoring and Evalu Post Limited 10,000.00 0.00 2022-08-26 2022-10-21 2023-04-19 he PIU and server spare part tions nvelope ementation ation, and Learning s (MoFEP Data Center) SD-MOFEP-290924-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl Transport 21 vehicles from El IDA / D7350 ement, Monitoring and Evalu Post Open - National 15,000.00 0.00 2022-04-22 2022-06-17 2022-12-14 tions nvelope ementation -Fashir to Khartoum ation, and Learning NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Manag SD-MOWSS-202694-NC-RFQ Request for Quota Single Stage - One E IDA / D7350 ement, Monitoring and Evalu Post Limited 11,000.00 12,338.25 Completed 2020-11-09 2021-07-20 2021-01-04 2021-07-26 2021-07-03 2021-08-02 / Office furniture tions nvelope ation, and Learning Component 3: Project Manag SD-MOWSS-202703-NC-RFQ Request for Quota Single Stage - One E Pending Impl IDA / D7350 ement, Monitoring and Evalu Post Limited 5,000.00 0.00 2020-11-09 2021-01-04 2021-07-03 / Software Packages tions nvelope ementation ation, and Learning Component 2: Establish Deli SD-MOWSS-202704-NC-RFQ Request for Quota Single Stage - One E Pending Impl IDA / D7350 very Systems and Build Insti Post Limited 10,000.00 0.00 2020-11-09 2021-01-04 2021-07-03 / Cell Phone tions nvelope ementation tutional Capacity Component 2: Establish Deli SD-MOWSS-202705-NC-RFQ Request for Quota Single Stage - One E IDA / D7350 very Systems and Build Insti Post Limited 3,000.00 930.96 Completed 2020-11-09 2021-08-09 2021-01-04 2021-09-20 2021-07-03 2021-09-20 / Stationery tions nvelope tutional Capacity Component 2: Establish Deli SD-MOWSS-202707-NC-RFQ Request for Quota Single Stage - One E Pending Impl IDA / D7350 very Systems and Build Insti Post Limited 14,000.00 0.00 2020-11-09 2021-01-04 2021-07-03 / monitors/docking stations tions nvelope ementation tutional Capacity Component 2: Establish Deli SD-MOWSS-202708-NC-RFQ Request for Quota Single Stage - One E IDA / D7350 very Systems and Build Insti Post Limited 20,000.00 26,174.56 Completed 2020-11-09 2021-06-12 2021-01-04 2021-07-15 2021-07-03 2021-08-14 / Vehicle rent for Sr staff tions nvelope tutional Capacity SD-MOFEP-207302-NC-RFQ / Component 2: Establish Deli Request for Quota Single Stage - One E Pending Impl Data Protection Authority / In IDA / D7350 very Systems and Build Insti Post Limited 300,000.00 0.00 2020-12-06 2021-01-31 2021-07-30 tions nvelope ementation stitutional arrangments tutional Capacity SD-MOFEP-238397-NC-RFP / Component 1: Provision of C Request for Propo Open - Internationa Pending Impl IDA / D7350 Prior 1,000,000.00 0.00 2021-06-22 2021-09-07 2021-09-07 2021-06-27 2021-11-16 2022-05-25 2023-11-16 Procurement of cash card ash Transfers sals l ementation Component 2: Establish Deli SD-MOFEP-249654-NC-RFQ / Request for Quota Single Stage - One E Pending Impl IDA / D7350 very Systems and Build Insti Post Limited 15,000.00 0.00 2021-09-28 2021-11-23 2022-05-22 Cost of SMS Messages tions nvelope ementation tutional Capacity SD-MOFEP-280513-NC-DIR / Component 2: Establish Deli Pending Impl Renting Tablets for enrollme TF / B4259 very Systems and Build Insti Post Direct Selection Direct 20,000.00 0.00 2022-02-27 2022-03-04 2022-04-08 2022-10-05 ementation nt process for SPSP Project tutional Capacity SD-MOFEP-290291-GO-DIR / Component 3: Project Manag Pending Impl Maintenance Vehicles by Ba IDA / D7350 ement, Monitoring and Evalu Post Direct Selection Direct - National 15,000.00 0.00 2022-08-21 2022-08-26 2022-09-30 2023-03-29 ementation shir Motor ation, and Learning SD-MOFEP-294297-NC-DIR / Receiving the World Bank del Component 2: Establish Deli Pending Impl egation and Minister of Finan IDA / D7350 very Systems and Build Insti Post Direct Selection Direct - National 2,000.00 0.00 2022-08-18 2022-08-23 2022-09-27 2023-03-26 ementation ce & Economic Planning in B tutional Capacity ahary Registration Center SD-MOFEP-295335-NC-DIR / Component 3: Project Manag Pending Impl Supply of Spare Parts and m IDA / D7350 ement, Monitoring and Evalu Post Direct Selection Direct 25,000.00 0.00 2022-05-15 2022-05-20 2022-06-24 2022-12-21 ementation aintenances ation, and Learning CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Establish Deli SD-MOWSS-202671-CS-QCB Quality And Cost- Open - Internationa Pending Impleme IDA / D7350 very Systems and Build Insti Post 250,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 S / Reconciliation Audit Based Selection l ntation tutional Capacity SD-MOWSS-202673-CS-QCB Component 2: Establish Deli Quality And Cost- Open - Internationa Pending Impleme S / Payment Services Provide IDA / D7350 very Systems and Build Insti Post 150,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 Based Selection l ntation rs (MNOs, Banks, Other) tutional Capacity Component 2: Establish Deli SD-MOWSS-202679-CS-QCB Quality And Cost- Open - Internationa Pending Impleme IDA / D7350 very Systems and Build Insti Post 200,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 S / MIS Development (Firm) Based Selection l ntation tutional Capacity Component 2: Establish Deli SD-MOWSS-202680-CS-QCB Quality And Cost- Open - Internationa Pending Impleme IDA / D7350 very Systems and Build Insti Post 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 S / MEL Framework (Firm) Based Selection l ntation tutional Capacity Page 2 Component 2: Establish Deli SD-MOWSS-202681-CS-QCB Quality And Cost- Pending Impleme IDA / D7350 very Systems and Build Insti Post Open - National 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 S / Media Content Creation Based Selection ntation tutional Capacity Component 2: Establish Deli SD-MOWSS-202682-CS-QCB Quality And Cost- Pending Impleme IDA / D7350 very Systems and Build Insti Post Open - National 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 S / Media Punchers Based Selection ntation tutional Capacity SD-MOFEP-238888-CS-CQS / Component 3: Project Manag Consultant Qualifi Pending Impleme Design the FM System for the IDA / D7350 ement, Monitoring and Evalu Post Limited 20,000.00 0.00 2021-06-17 2021-07-01 2021-07-31 2021-09-04 2022-03-03 cation Selection ntation PIU ation, and Learning SD-MOFEP-252456-CS-QCBS Component 2: Establish Deli Quality And Cost- Open - Internationa Pending Impleme / Consultancy firm to conduct IDA / D7350 very Systems and Build Insti Post 300,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-10 2022-01-09 2022-02-13 2022-03-20 2023-03-20 Based Selection l ntation SFSP Base line Survey tutional Capacity SD-MOFEP-252465-CS-QCBS Component 2: Establish Deli Quality And Cost- Pending Impleme / Capacity Building on M&E fo IDA / D7350 very Systems and Build Insti Post Open - National 15,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-10 2022-01-09 2022-02-13 2022-03-20 2023-03-20 Based Selection ntation r government Institutions tutional Capacity Component 3: Project Manag SD-MOFEP-252470-CS-QCBS Quality And Cost- Open - Internationa Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post 450,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-10 2022-01-09 2022-02-13 2022-03-20 2023-03-20 / MEL Survey Provider Based Selection l ntation ation, and Learning SD-MOFEP-252479-CS-QCBS Component 2: Establish Deli Quality And Cost- Open - Internationa Pending Impleme / SFSP Impact Evaluation Stu IDA / D7350 very Systems and Build Insti Post 450,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-10 2022-01-09 2022-02-13 2022-03-20 2023-03-20 Based Selection l ntation dy tutional Capacity SD-MOFEP-252488-CS-CQS / Component 3: Project Manag Consultant Qualifi Pending Impleme National Consultant to condu IDA / D7350 ement, Monitoring and Evalu Post Open - National 50,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-12 2022-01-16 2022-07-15 cation Selection ntation ct Program ICRR ation, and Learning SD-MOFEP-252515-CS-CQS / Component 2: Establish Deli Institutional Capacity buildin Consultant Qualifi Pending Impleme IDA / D7350 very Systems and Build Insti Post Open - National 100,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-12 2022-01-16 2022-07-15 g for the creation of a releva cation Selection ntation tutional Capacity nt independent data protecti on oversight body Component 2: Establish Deli SD-MOFEP-252516-CS-QBS / Quality Based Sel Pending Impleme IDA / D7350 very Systems and Build Insti Post Open - National 50,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-10 2022-01-09 2022-02-08 2022-03-15 2023-03-15 GVB Legal aid ection ntation tutional Capacity Component 2: Establish Deli SD-MOFEP-252523-CS-QBS / Quality Based Sel Pending Impleme IDA / D7350 very Systems and Build Insti Post Open - National 100.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-10 2022-01-09 2022-02-08 2022-03-15 2023-03-15 NCR Law Reform ection ntation tutional Capacity SD-MOFEP-252524-CS-QBS / Component 2: Establish Deli Quality Based Sel Pending Impleme Enabling Data Protection Leg IDA / D7350 very Systems and Build Insti Post Open - National 25,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-10 2022-01-09 2022-02-08 2022-03-15 2023-03-15 ection ntation al Framework tutional Capacity SD-MOFEP-252527-CS-CQS / Component 2: Establish Deli Consultant Qualifi Pending Impleme Reform Relevant Laws ((Cyb IDA / D7350 very Systems and Build Insti Post Open - National 25,000.00 0.00 2021-09-08 2021-09-29 2021-11-12 2021-12-12 2022-01-16 2022-07-15 cation Selection ntation ercrime, Access to Informatio tutional Capacity n, NIC)) SD-MOFEP-294823-CS-QBS / USSD-A platform that enable Component 2: Establish Deli Quality Based Sel Pending Impleme s Operators to introduce mes IDA / D7350 very Systems and Build Insti Post Open - National 350,000.00 0.00 2022-05-11 2022-06-01 2022-07-15 2022-08-12 2022-09-11 2022-10-11 2022-11-15 2023-11-15 ection ntation saging services with USSD as tutional Capacity the bearer, enabling faster re sponse times SD-MOFEP-308051-CS-LCS / Recruitment of an audit firm for auditing the financial stat Component 3: Project Manag Least Cost Selecti Pending Impleme ements of the Sudan Family IDA / D7350 ement, Monitoring and Evalu Post Open - National 100,000.00 0.00 2022-08-18 2022-09-08 2022-10-22 2022-11-19 2022-12-19 2023-01-23 2023-02-27 2023-08-26 on ntation Support Project at the Ministr ation, and Learning y of Finance & Economic Plan ning (MoFEP) of the Sudan G overnment INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOWSS-201613-CS-CQS Component 3: Project Manag Individual Consult / ENROLLMENT MA / Enrolm IDA / D7350 ement, Monitoring and Evalu Post Open 12,000.00 3,542.32 Terminated 2020-11-02 2021-02-22 2020-12-21 2021-02-18 2021-01-11 2021-02-14 2021-02-15 2021-02-21 2021-08-14 ant Selection ent Manager ation, and Learning Component 3: Project Manag SD-MOWSS-202658-CS-INDV Individual Consult IDA / D7350 ement, Monitoring and Evalu Post Open 12,000.00 1,575,000.00 Signed 2020-11-02 2021-02-22 2020-12-21 2021-01-17 2021-01-11 2021-02-14 2021-02-15 2021-02-21 2021-08-14 / Payment Manager ant Selection ation, and Learning Component 3: Project Manag SD-MOWSS-202659-CS-INDV Individual Consult Under Implement IDA / D7350 ement, Monitoring and Evalu Post Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 / Information Security ant Selection ation ation, and Learning Component 3: Project Manag SD-MOWSS-202657-CS-INDV Individual Consult IDA / D7350 ement, Monitoring and Evalu Prior Open 12,000.00 0.00 Under Review 2020-11-02 2021-08-02 2020-12-21 2021-01-11 2021-02-15 2021-08-14 / Communication Manager ant Selection ation, and Learning Component 3: Project Manag SD-MOWSS-202663-CS-INDV Individual Consult IDA / D7350 ement, Monitoring and Evalu Post Limited 40,000.00 7,590.68 Signed 2020-11-04 2021-02-22 2020-11-09 2021-06-30 2020-11-30 2021-07-07 2021-01-04 2021-07-13 2021-07-03 / Program Manager ant Selection ation, and Learning Component 3: Project Manag SD-MOWSS-202660-CS-INDV Individual Consult Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Open 12,000.00 0.00 2020-11-02 2020-12-21 2021-01-11 2021-02-15 2021-08-14 / MIS Manager ant Selection ntation ation, and Learning Component 3: Project Manag SD-MOWSS-202661-CS-INDV Individual Consult IDA / D7350 ement, Monitoring and Evalu Post Open 12,000.00 3,542.32 Signed 2020-11-02 2021-02-22 2020-12-21 2021-01-02 2021-01-11 2021-02-15 2021-02-15 2021-04-21 2021-08-14 / MEL Manager ant Selection ation, and Learning Component 3: Project Manag SD-MOWSS-202664-CS-INDV Individual Consult Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 / Database Administrator ant Selection ntation ation, and Learning Component 3: Project Manag SD-MOWSS-202666-CS-INDV Individual Consult Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 / Network Administration ant Selection ntation ation, and Learning Page 3 SD-MOWSS-202667-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / Family Enrolment Lead Offic IDA / D7350 ement, Monitoring and Evalu Post Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 ant Selection ntation er ation, and Learning SD-MOWSS-202668-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / Registration Focal Points pe IDA / D7350 ement, Monitoring and Evalu Post Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 ant Selection ntation r State ation, and Learning Component 3: Project Manag SD-MOWSS-202649-CS-INDV Individual Consult Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 / Payments Officer ant Selection ntation ation, and Learning Component 3: Project Manag SD-MOWSS-202651-CS-INDV Individual Consult Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 / Grievance Redress Officer ant Selection ntation ation, and Learning SD-MOWSS-202652-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / Privacy and Digital Ethics Of IDA / D7350 ement, Monitoring and Evalu Post Limited 21,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 ant Selection ntation ficer ation, and Learning SD-MOWSS-202653-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / Civil Society and Communit IDA / D7350 ement, Monitoring and Evalu Post Limited 21,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 ant Selection ntation y Outreach Officer ation, and Learning SD-MOWSS-202655-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / State-level Communication IDA / D7350 ement, Monitoring and Evalu Post Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 ant Selection ntation Coordinator ation, and Learning SD-MOWSS-202656-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / Gender / Social Impact Spec IDA / D7350 ement, Monitoring and Evalu Post Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 ant Selection ntation ialist ation, and Learning SD-MOWSS-202670-CS-INDV Component 3: Project Manag Individual Consult / Project Procurement Special IDA / D7350 ement, Monitoring and Evalu Prior Limited 21,000.00 0.00 Under Review 2020-11-04 2021-02-22 2020-11-09 2021-01-03 2020-11-30 2021-01-04 2021-07-03 ant Selection ist ation, and Learning Component 3: Project Manag SD-MOFEP-236088-CS-CDS / Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Direct Selection Direct 42,000.00 0.00 2021-06-15 2021-06-25 2021-08-29 2022-02-25 Hiring of Legal advisor ntation ation, and Learning SD-MOFEP-236097-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / Digital Channel Enrollment IDA / D7350 ement, Monitoring and Evalu Post Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 ant Selection ntation Officer ation, and Learning SD-MOFEP-236104-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / Family Enrollment Team lea IDA / D7350 ement, Monitoring and Evalu Post Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 ant Selection ntation der ation, and Learning Component 3: Project Manag SD-MOFEP-236106-CS-INDV Individual Consult Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 / Business Analyst ant Selection ntation ation, and Learning Component 3: Project Manag SD-MOFEP-236111-CS-INDV Individual Consult Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 / hiring of Payment Officer ant Selection ntation ation, and Learning SD-MOFEP-236113-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / hiring of Social Media Assoc IDA / D7350 ement, Monitoring and Evalu Post Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 ant Selection ntation iate ation, and Learning SD-MOFEP-238413-CS-INDV Component 3: Project Manag Individual Consult Pending Impleme / Accountant Assistance Offic IDA / D7350 ement, Monitoring and Evalu Post Open 30,000.00 0.00 2021-06-15 2021-08-03 2021-08-24 2021-09-28 2022-03-27 ant Selection ntation er ation, and Learning SD-MOFEP-238427-CS-CDS / Component 2: Establish Deli WFP will work as an Intermed Pending Impleme IDA / D7350 very Systems and Build Insti Prior Direct Selection Direct 1,000,000.00 0.00 2021-06-15 2021-06-25 2021-08-29 2022-02-25 iary Support Provider to distri ntation tutional Capacity bute cash transfers to famili es in remote areas Component 2: Establish Deli SD-MOFEP-238444-CS-CDS / Pending Impleme IDA / D7350 very Systems and Build Insti Prior Direct Selection Direct 1,000,000.00 0.00 2021-06-15 2021-06-25 2021-08-29 2022-02-25 Save the Children as ISP ntation tutional Capacity SD-MOFEP-238884-CS-INDV Component 3: Project Manag Individual Consult / Procurement Assistant Offic IDA / D7350 ement, Monitoring and Evalu Post Open 30,000.00 0.00 Canceled 2021-06-15 2021-08-03 2021-08-24 2021-09-28 2022-03-27 ant Selection er ation, and Learning Component 3: Project Manag SD-MOFEP-252414-CS-INDV Individual Consult IDA / D7350 ement, Monitoring and Evalu Post Open 30,000.00 0.00 Under Review 2021-09-09 2021-07-01 2021-10-28 2021-11-18 2021-12-23 2022-06-21 / SFPS Procurement Officer ant Selection ation, and Learning SD-MOFEP-252425-CS-INDV Component 3: Project Manag Individual Consult / SFSP Financial Management IDA / D7350 ement, Monitoring and Evalu Post Open 30,000.00 0.00 Under Review 2021-09-09 2021-01-03 2021-10-28 2021-11-18 2021-12-23 2022-06-21 ant Selection Officer ation, and Learning Component 3: Project Manag SD-MOFEP-252426-CS-INDV Individual Consult Pending Impleme IDA / D7350 ement, Monitoring and Evalu Post Open 30,000.00 0.00 2021-09-09 2021-10-28 2021-11-18 2021-12-23 2022-06-21 / SFSP Safeguard Officer ant Selection ntation ation, and Learning SD-MOFEP-252476-CS-INDV Component 2: Establish Deli Individual Consult Pending Impleme / National Consultant to eval IDA / D7350 very Systems and Build Insti Post Open 5,000.00 0.00 2021-09-08 2021-10-27 2021-11-17 2021-12-22 2022-06-20 ant Selection ntation uate the registration process tutional Capacity SD-MOFEP-252478-CS-INDV Component 2: Establish Deli Individual Consult Pending Impleme / National Consultant to Eval IDA / D7350 very Systems and Build Insti Post Open 5,000.00 0.00 2021-09-08 2021-10-27 2021-11-17 2021-12-22 2022-06-20 ant Selection ntation uate the payment Process tutional Capacity Page 4