Procurement Plan 1. For each contract to be financed by the Loan, the different procurement methods or consultant selection methods, the need for pre-qualification, estimated costs, prior review requirements, and time frame are agreed between the Borrower and the Bank in the Procurement Plan (Annex 6). The procurement plan, which covers the entire project, and its updates or modifications, shall be subject to the Bank’s prior review and no objection before implementation. The Procurement Plan and its updates will be published in the Bank’s external website. Thresholds for Procurement Methods 2. The same procurement thresholds for SPAP will apply and this is reflected in the procurement plan (see Annex 6). 3. Goods: Goods and equipment estimated to cost US$300,000 or more will be procured through International Competitive Bidding (ICB). Goods estimated to cost less than $300,000 and more than $100,000 will be procured through National Competitive Bidding (NCB). Readily available off-the-shelf goods estimated to cost less than US$100,000 each may be procured through Shopping (SH) on the basis of at least three written quotations obtained from qualified suppliers. 4. Works: Works estimated to cost US$4,000,000 and more will be procured through ICB. Works estimated to cost less than US$4,000,000 and more than US$100,000 will be procured through NCB. Contracts estimated to cost less than US$100,000 each may be procured through Shopping (SH) procedures on the basis of at least three written quotations obtained from qualified contractors. 5. Consultant Services: Consultancy services to be provided by consulting firms estimated to cost US$300,000 or more will be procured through Quality and Cost Based Selection (QCBS) method. Consultancy services to be provided by consulting firms estimated to cost less than US$300,000 may be procured through Consultants’ Qualifications (CQ) method. For assignments estimated to cost less than US$ 100,000, the shortlist may comprise only of national firms according to the paragraph 2.7 of the Consultant Guidelines. However, if foreign firms express interest, they shall be considered. Individual Consultants will be selected in accordance with Section V of the Consultant Guidelines. Prior Review Thresholds 6. Prior Review thresholds are proposed as follows: - All ICB and first two NCB contracts each for Goods and Works; - All DC contracts; - All contracts with consulting firms estimated to cost US$100,000 or more and all Single Source Selection contracts; - All contracts with individual consultants estimated to cost US$50,000 or more and all Single Source Selection contracts. PROCUREMENT Armenia : Armenia Social Protection Administration II Project PLAN General Information Country: Armenia 2016-09-15 Bank’s Approval Date of the Original Procurement Plan: 2022-08-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146318 GPN Date: Project Name: Armenia Social Protection Administration II Project Loan / Credit No: IDA / 53980 Ministry of Labor and Social Affairs Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SPAP II W-1-1-1/1-G / Refurbi Roll-Out of Integrated Social Single Stage - One E Under Imple 2018-03-1 IDA / 53980 Post Request for Bids Open - National 0.00 0.00 2016-11-15 2016-11-09 2016-11-20 2016-12-18 2017-02-01 2017-03-15 shment of Shengavit ISPC Protection Service Delivery nvelope mentation 5 1-1-1-1-A / Refubrishment of Roll-Out of Integrated Social Single Stage - One E 2017-08-0 IDA / 53980 Prior Request for Bids Open - National 480,092.00 428,441.00 Signed 2016-04-20 2016-04-27 2016-05-25 2016-08-16 2016-11-13 2016-09-07 2016-09-07 Vanadzor ISPC Protection Service Delivery nvelope 7 SPAP II 1-1-1-1-F / Refurbish Roll-Out of Integrated Social Single Stage - One E 2018-05-1 IDA / 53980 Post Request for Bids Open - National 0.00 455,029.26 Signed 2016-11-17 2016-11-17 2016-11-22 2016-12-20 2016-12-16 2017-03-20 2017-03-27 2017-04-24 2017-04-28 ment of Hrazdan ISPC Protection Service Delivery nvelope 3 SPAP II 1-1-1-1-H / Akhoorya Roll-Out of Integrated Social Single Stage - One E 2018-02-1 IDA / 53980 Post Request for Bids Open - National 0.00 0.00 Canceled 2017-01-10 2017-05-30 2017-01-15 2017-02-12 2017-07-10 2017-05-13 2017-10-30 2017-06-17 n ISPC refurbushment Protection Service Delivery nvelope 2 SPAP II 1-1-1/1-I / Refubrish Roll-Out of Integrated Social Single Stage - One E Pending Imp 2018-11-0 IDA / 53980 Post Request for Bids Open - National 0.00 0.00 2017-06-01 2017-06-06 2017-07-04 2017-10-02 2017-11-06 ment of Tashir ISPC Protection Service Delivery nvelope lementation 6 SPAP II 1-1-1-1-H-R / Refubri Roll-Out of Integrated Social Single Stage - One E 2018-12-2 IDA / 53980 Post Request for Bids Open - National 229,279.00 169,352.47 Signed 2018-02-09 2018-02-26 2018-02-11 2018-03-13 2018-03-26 2018-05-10 2018-06-07 shment of Akhuryan ISPC Protection Service Delivery nvelope 7 SPAP II W 1-1-1/1-C / Constr Roll-Out of Integrated Social Single Stage - One E Pending Imp 2018-12-3 IDA / 53980 Post Request for Bids Open - National 994,968.00 0.00 2018-07-27 2018-07-27 2018-07-27 2018-07-27 2018-07-27 uction of Stepanavan ISPC Protection Service Delivery nvelope lementation 0 SPAP II W 1-1-1/1-J / Refubris Roll-Out of Integrated Social Single Stage - One E 2018-12-3 IDA / 53980 Post Request for Bids Open - National 211,358.00 151,561.51 Completed 2018-08-06 2018-09-27 2018-08-08 2018-09-05 2018-10-31 2018-10-05 2018-12-10 2018-11-02 2019-01-14 hment of Caxkahovit ISPC Protection Service Delivery nvelope 0 SPAP II W 1-1-1/1-K / Refubri Roll-Out of Integrated Social Single Stage - One E 2020-03-2 IDA / 53980 Post Request for Bids Open - National 197,402.00 0.00 Canceled 2018-12-10 2018-12-15 2019-01-12 2019-02-06 2019-02-11 2019-04-30 2019-03-25 shment of Meghri CSSTC Protection Service Delivery nvelope 4 SPAP II W 1-1-1/1-C-1 / Const Roll-Out of Integrated Social Single Stage - One E 2020-11-3 IDA / 53980 Post Request for Bids Open - National 606,127.00 596,841.06 Signed 2019-01-24 2019-02-01 2019-01-29 2019-02-26 2019-03-03 2019-03-28 2019-06-25 2019-05-09 2019-08-02 ruction of Stepanavan CSSTC Protection Service Delivery nvelope 0 SPAP II W 1-1-1/1-L / Refubri Roll-Out of Integrated Social Single Stage - One E 2019-12-2 IDA / 53980 Post Request for Bids Open - National 170,405.00 134,631.81 Signed 2019-01-30 2019-07-19 2019-02-04 2019-08-29 2019-03-04 2019-08-26 2019-04-03 2019-09-25 2019-05-15 2019-10-23 shment of Sevan CSSTC Protection Service Delivery nvelope 6 SPAP II W 1-1-1/1-M / Recons Roll-Out of Integrated Social Single Stage - One E 2020-04-2 truction and refubrishment of IDA / 53980 Post Request for Bids Open - National 198,116.00 131,076.91 Signed 2019-01-30 2019-07-19 2019-02-04 2019-08-29 2019-03-04 2019-08-26 2019-04-03 2019-09-26 2019-05-15 2019-10-16 Protection Service Delivery nvelope 9 Aparan CSSTC SPAP II W 1-1-1/1-N / Refubri Roll-Out of Integrated Social Single Stage - One E 2019-12-2 IDA / 53980 Post Request for Bids Open - National 198,335.00 156,043.90 Signed 2019-01-31 2019-07-30 2019-02-05 2019-08-29 2019-03-05 2019-08-27 2019-04-04 2019-09-26 2019-05-16 2019-10-17 shment of Martuni CSSTC Protection Service Delivery nvelope 7 SPAP II W 1-1-1/1-O / Refubri Roll-Out of Integrated Social Single Stage - One E 2019-12-1 IDA / 53980 Post Request for Bids Open - National 218,191.00 178,429.87 Signed 2019-01-31 2019-07-19 2019-02-05 2019-08-29 2019-03-05 2019-08-29 2019-04-04 2019-09-25 2019-05-16 2019-11-01 shment of Goris CSSTC Protection Service Delivery nvelope 2 SPAP II W 1-1-1/1-K-R / Refur Roll-Out of Integrated Social Single Stage - One E 2020-11-3 IDA / 53980 Post Request for Bids Open - National 197,402.00 192,165.46 Signed 2019-07-29 2019-08-06 2019-08-03 2019-09-05 2019-08-31 2019-09-03 2019-09-30 2019-09-26 2019-11-04 2019-10-16 bishment of Meghri CSSTC Protection Service Delivery nvelope 0 SPAP II W 1.1.1/1.P / Refurbi Roll-Out of Integrated Social Single Stage - One E 2020-11-1 IDA / 53980 Post Request for Bids Open - National 197,254.00 148,302.67 Signed 2019-08-19 2019-10-25 2019-08-24 2019-09-21 2019-11-26 2019-10-21 2020-01-22 2019-12-02 2020-02-11 shment of Dilijan CSSTC Protection Service Delivery nvelope 6 SPAP II W 1.1.1/1.R / Refurbi Roll-Out of Integrated Social Single Stage - One E 2020-06-3 IDA / 53980 Post Request for Bids Open - National 286,301.00 0.00 Canceled 2019-08-20 2019-10-24 2019-08-25 2019-09-22 2019-11-25 2019-10-22 2020-01-23 2019-12-03 shment of Kapan CSSTC Protection Service Delivery nvelope 0 SPAP II W 1.1.1/1.S / Reconst Roll-Out of Integrated Social Single Stage - One E 2020-11-3 ruction and Refurbishment of IDA / 53980 Post Request for Bids Open - National 806,145.00 721,997.55 Signed 2019-08-21 2019-10-24 2019-08-26 2019-09-23 2019-11-29 2019-10-23 2020-01-20 2019-12-04 2020-02-06 Protection Service Delivery nvelope 0 Gyumri CSSTC SPAP II W 1.1.1/1.T / Reconst Roll-Out of Integrated Social Single Stage - One E 2020-11-3 IDA / 53980 Post Request for Bids Open - National 643,564.00 613,523.75 Signed 2019-08-20 2019-10-24 2019-08-25 2019-09-22 2019-11-21 2019-10-22 2020-01-22 2019-12-03 2020-02-06 ruction of Alaverdi CSSTC Protection Service Delivery nvelope 0 SPAP II W 1-1-1/1-U / Refurbi Roll-Out of Integrated Social Single Stage - One E 2020-11-3 IDA / 53980 Post Request for Bids Open - National 510,580.00 414,981.02 Signed 2019-10-24 2019-10-29 2019-10-29 2019-11-26 2019-11-28 2019-12-26 2020-01-24 2020-02-06 2020-02-05 shment of Ijevan CSSTC Protection Service Delivery nvelope 0 SPAP II W 1-1-1/1-V / Refurbi Roll-Out of Integrated Social Single Stage - One E 2020-11-3 IDA / 53980 Post Request for Bids Open - National 395,017.00 309,207.60 Signed 2019-10-25 2019-10-25 2019-10-30 2019-11-27 2019-11-26 2019-12-27 2020-01-20 2020-01-31 2020-02-11 shment of Gavar CSSTC Protection Service Delivery nvelope 0 SPAP II W 1.1.1/1.R-1 / Refur Roll-Out of Integrated Social Single Stage - One E 2020-11-3 IDA / 53980 Post Request for Bids Open - National 286,301.00 0.00 Canceled 2020-03-02 2020-03-02 2020-03-07 2020-03-04 2020-04-04 2020-05-04 2020-06-15 bishment of Kapan CSSTC Protection Service Delivery nvelope 0 SPAP II W 1.1.1/1.Q / Refurbi Roll-Out of Integrated Social Single Stage - One E 2020-11-3 IDA / 53980 Post Request for Bids Open - National 570,506.00 0.00 Canceled 2019-08-16 2019-08-21 2019-08-23 2019-09-22 2019-11-03 shment of Artik CSSTC Protection Service Delivery nvelope 0 SPAP II W 1.1.1/1.W / Refurbi Roll-Out of Integrated Social Single Stage - One E 2021-01-0 IDA / 53980 Post Request for Bids Open - National 144,058.00 171,323.88 Signed 2020-04-07 2020-04-10 2020-05-05 2020-05-07 2020-05-12 2020-06-06 2020-06-25 2020-07-11 2020-07-17 shment of Berd CSSTC Protection Service Delivery nvelope 7 SPAP II W 1.1.1/1.X / Constru Roll-Out of Integrated Social Single Stage - One E 2021-11-0 IDA / 53980 Post Request for Bids Open - National 136,693.00 125,232.14 Signed 2020-04-08 2020-04-10 2020-04-13 2020-05-11 2020-05-12 2020-06-10 2020-06-25 2020-07-15 2020-07-20 ction and refurbishmen of Jer Protection Service Delivery nvelope 7 muk CSSTC SPAP II W 1.1.1/1.R-2 / Refur Roll-Out of Integrated Social Single Stage - One E 2021-02-1 IDA / 53980 Post Request for Bids Open - National 286,301.00 232,925.79 Signed 2020-04-19 2020-04-17 2020-04-21 2020-05-19 2020-05-15 2020-06-18 2020-07-10 2020-07-23 2020-08-03 bishment of Kapan CSSTC Protection Service Delivery nvelope 8 SPAP II W-1.1.1/1.Y / Refurbi Roll-Out of Integrated Social Single Stage - One E 2022-01-0 IDA / 53980 Post Request for Bids Open - National 164,865.00 143,599.35 Signed 2020-06-08 2020-06-16 2020-06-13 2020-07-11 2020-07-15 2020-08-10 2020-08-20 2020-09-14 2020-10-07 shment of Yeghegnadzor CS Protection Service Delivery nvelope 7 STC SPAP II W1.1.1/1.Q-R-1 / Rec Roll-Out of Integrated Social Single Stage - One E 2022-06-0 IDA / 53980 Post Request for Bids Open - National 365,260.00 338,801.50 Signed 2020-06-23 2020-07-07 2020-06-28 2020-07-26 2020-08-05 2020-09-09 2020-10-16 2020-10-14 2020-11-12 onstruction of Artik CSSTC Protection Service Delivery nvelope 6 Page 1 SPAP II W1.1.1/1.Z / Reconst Roll-Out of Integrated Social Single Stage - One E 2021-11-1 ruction and Refurbishment of IDA / 53980 Post Request for Bids Open - National 485,845.00 0.00 Canceled 2020-08-25 2020-09-23 2020-08-30 2020-09-27 2020-10-23 2020-11-11 2020-12-09 2020-11-18 Protection Service Delivery nvelope 7 Abovyan CSSTC SPAP II W1.1.1/1.Z-R / Recon Roll-Out of Integrated Social Single Stage - One E 2022-06-1 struction and Refurbishment IDA / 53980 Post Request for Bids Open - National 485,845.00 372,683.91 Signed 2021-03-10 2021-03-15 2021-03-11 2021-04-08 2021-04-12 2021-05-08 2021-07-12 2021-06-19 2021-06-23 Protection Service Delivery nvelope 8 of Abovyan CSSTC SPAP II W 1.1.1/1-1-A / Refur Roll-Out of Integrated Social Single Stage - One E 2022-06-2 IDA / 53980 Post Request for Bids Open - National 382,453.00 316,637.52 Signed 2021-03-17 2021-03-31 2021-03-24 2021-04-02 2021-04-14 2021-04-21 2021-05-14 2021-06-10 2021-06-25 2021-06-29 bishment of Ashtarak CSSTC Protection Service Delivery nvelope 5 SPAP II W 1.1.1/1-1-B / Refur Roll-Out of Integrated Social Single Stage - One E 2022-07-2 IDA / 53980 Post Request for Bids Open - National 375,905.00 369,118.21 Signed 2021-03-17 2021-06-04 2021-03-22 2021-04-02 2021-04-12 2021-06-25 2021-05-12 2021-08-13 2021-06-23 2021-12-02 bishment of Sisian CSSTC Protection Service Delivery nvelope 3 SPAP II W 1.1.1/1-1-C / Const Roll-Out of Integrated Social Single Stage - One E 2022-09-0 IDA / 53980 Post Request for Bids Open - National 842,865.00 823,452.51 Signed 2021-03-17 2021-04-14 2021-03-22 2021-04-12 2021-05-05 2021-05-12 2021-06-10 2021-06-23 2021-06-29 ruction of Spitak CSSTC Protection Service Delivery nvelope 1 SPAP II W 1.1.1/1-1-D / Refur Roll-Out of Integrated Social Request for Quota Single Stage - One E 2021-08-1 bishment of the reception of IDA / 53980 Post Open - National 8,332.00 0.00 Canceled 2021-04-18 2021-06-13 Protection Service Delivery tions nvelope 2 the MLSA of RA SPAP II W 1.1.1/1-1-D-R / Ref Request for Quota Roll-Out of Integrated Social Request for Quota Single Stage - One E 2021-10-2 urbishment of the reception IDA / 53980 Post Open - National tions (Non Bank-S 8,330.00 11,926.10 Signed 2021-08-04 2021-09-22 2022-06-17 Protection Service Delivery tions nvelope 2 of the MLSA of RA (rebid) PD) SPAP II W1.1.1/1.Q-R / Recon Roll-Out of Integrated Social Single Stage - One E 2020-11-3 IDA / 53980 Post Request for Bids Open - National 365,260.00 0.00 Canceled 2020-03-18 2020-03-18 2020-03-23 2020-04-20 2020-04-16 2020-05-20 2019-10-16 2020-06-23 struction of Artik CSSTC Protection Service Delivery nvelope 0 SPAP II W 1.1.1/1-1-F / Reco Roll-Out of Integrated Social Single Stage - One E Other (with field f 2022-10-2 nstruction and Refurbishmen IDA / 53980 Post Request for Bids Open - National 429,000.00 409,811.71 Signed 2021-10-29 2021-11-08 2021-11-03 2021-11-24 2021-11-30 2021-12-22 2022-01-10 2022-01-17 2022-02-22 Protection Service Delivery nvelope or explanation) 4 t of Vagharshapat USS territ orial center SPAP II W 1.1.1/1-1-E / Refur Roll-Out of Integrated Social Single Stage - One E Other (with field f 2022-10-2 IDA / 53980 Post Request for Bids Open - National 326,000.00 272,540.71 Signed 2021-10-29 2021-11-08 2021-11-01 2021-11-22 2021-12-03 2021-12-20 2022-01-21 2022-01-15 2022-02-18 bishment of Vayq USS territo Protection Service Delivery nvelope or explanation) 2 rial center SPAP II W 1.1.1/1.R-2-AD / A Roll-Out of Integrated Social Request for Quota Single Stage - One E Other (with field f Under Imple 2022-07-0 dditional renovation works fo IDA / 53980 Post Limited 4,930.00 0.00 2022-05-02 2022-06-02 2022-06-08 Protection Service Delivery tions nvelope or explanation) mentation 8 r Kapan USSTC GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Contract 2.5.1 / Equipment f Roll-Out of Integrated Social Request for Quota Open - Internationa IDA / 53980 Prior 0.00 39,315.07 Signed 2015-07-06 or PIU and PCU Protection Service Delivery tions l SPAPII-G-2.1-4.1, Lot 2 / Equi Roll-Out of Integrated Social Open - Internationa Single Stage - One E pment for MLSA, SSSS, Nork IDA / 53980 Prior Request for Bids 107,350.00 41,205.30 Signed 2016-02-29 2016-04-21 Protection Service Delivery l nvelope CJSC, NILRS, SEA and MCPO, Lot 2 SPAP II G-2.1-4.1, Lot 1 / Equ Roll-Out of Integrated Social Open - Internationa Single Stage - One E ipment for MLSA, SSSS, Nork IDA / 53980 Prior Request for Bids 531,000.00 407,283.24 Signed 2016-03-01 2016-04-12 Protection Service Delivery l nvelope CJSC, NILSR, SEA and MCPO, Lot 1 SPAPII-G-2.1-4.1, Lot 4 / Equi Roll-Out of Integrated Social Open - Internationa Single Stage - One E pment for MLSA, SSSS, Nork IDA / 53980 Prior Request for Bids 84,000.00 67,502.01 Signed 2016-02-29 2016-04-21 Protection Service Delivery l nvelope CJSC, NILRS, SEA and MCPO, Lot 4 SPAP II 2-3-2 / Upgrading ele ctronic pension information s Modernization of the Pension Single Stage - One E IDA / 53980 Prior Request for Bids Open - National 0.00 0.00 Canceled 2016-11-22 2017-01-23 2016-11-27 2016-12-25 2017-02-20 2017-01-24 2017-06-20 2017-02-28 2018-02-28 ystem software with interfac System nvelope es with other databases SPAP II 2-1-3 / Upgrade and Development of information Roll-Out of Integrated Social Single Stage - One E Pending Impl subsystem of complex social IDA / 53980 Post Request for Bids Open - National 0.00 0.00 2017-04-10 2017-04-15 2017-05-13 2017-08-11 2017-09-15 2018-10-31 Protection Service Delivery nvelope ementation services provision (Upgrade and development of ISPCs' M IS) SPAP II 2-3-3 / Development Modernization of the Pension Single Stage - One E of the new risk-based control IDA / 53980 Post Request for Bids Open - National 0.00 0.00 Canceled 2017-08-07 2017-08-12 2017-09-09 2017-12-08 2018-01-12 2018-08-07 System nvelope and supervision information s ystem software SPAP II 2-4-3 / Development Strengthen MLSI Analytical C Single Stage - One E and introduction of internal p IDA / 53980 apacity and Monitoring and Post Request for Bids Open - National 0.00 0.00 Canceled 2017-01-10 2017-05-30 2017-01-15 2017-02-12 2017-07-19 2017-05-13 2017-11-03 2017-06-17 2018-06-10 nvelope ortal for MLSI management s Evaluation Systems ystem SPAP II 2-4-4 / Development Strengthen MLSI Analytical C and introduction of electronic Single Stage - One E IDA / 53980 apacity and Monitoring and Post Request for Bids Open - National 0.00 0.00 Canceled 2017-08-15 2017-08-20 2017-09-17 2017-12-16 2018-01-20 2018-10-15 system of monitoring and ev nvelope Evaluation Systems aluation of efficiency of socia l SPAP II 2-1-2/1 / Procuremen Roll-Out of Integrated Social Single Stage - One E Pending Impl t of furniture for Talin, Vana IDA / 53980 Post Request for Bids Open - National 0.00 0.00 2017-06-05 2017-06-10 2017-07-08 2017-10-06 2017-11-10 2018-01-09 Protection Service Delivery nvelope ementation dzor, Amasia, Malatia-Sebasti a SPAP II G-2-1-4-1/3AR / Air C Modernization of the Pension Request for Quota Single Stage - One E IDA / 53980 Post Limited 0.00 0.00 Canceled 2017-07-15 2017-07-14 2017-09-03 2018-03-02 onditioners for MLSA, SSSS, System tions nvelope NILSR SPAP II G-2-3-2R / Upgrading electronic pension informatio Modernization of the Pension Single Stage - One E IDA / 53980 Post Request for Bids Open - National 0.00 0.00 Canceled 2017-07-20 2017-07-25 2017-08-22 2017-09-21 2017-10-26 2018-04-24 n system software with interf System nvelope aces with other databases SPAP II G-2-1-1/2 / Procurem ent of technical (household) Roll-Out of Integrated Social Request for Quota Single Stage - One E IDA / 53980 Post Limited 0.00 0.00 Canceled 2017-12-20 2018-02-03 2018-03-20 means for Talin, Vanadzor, A Protection Service Delivery tions nvelope masia, Talin, Malatia-Sebasti a SPAP II G-2-1-2/2 / Procurem Roll-Out of Integrated Social Single Stage - One E Pending Impl ent of furniture for SEA, AMS IDA / 53980 Post Request for Bids Open - National 0.00 0.00 2017-12-20 2017-12-24 2018-01-21 2018-03-27 2018-04-24 2018-06-23 Protection Service Delivery nvelope ementation E and Malatia-Sebastia Page 2 SPAP II G-2-1-1/1 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E ent of printers and scanners f IDA / 53980 Post Limited 0.00 55,872.35 Completed 2017-12-20 2017-12-08 2018-01-26 2018-02-21 2018-03-12 2018-04-20 Protection Service Delivery tions nvelope or State Social Security Servi ce (SSSS) SPAP II G-2-1-1/3 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E ent of computer equipments IDA / 53980 Post Open - National 186,000.00 58,735.93 Completed 2018-02-25 2018-06-14 2018-06-07 2018-08-13 2018-08-06 Protection Service Delivery tions nvelope for AMSE TCs SPAP II 2-4-3-R / Developme Strengthen MLSI Analytical C Single Stage - One E nt and introduction of interna IDA / 53980 apacity and Monitoring and Post Request for Bids Open - National 240,000.00 166,753.60 Terminated 2018-02-12 2018-03-20 2018-02-17 2018-03-19 2018-04-17 2018-05-16 2018-06-22 2018-12-27 nvelope l portal for MLSI managemen Evaluation Systems t system SPAP II G-2-1-1/5 / Procurem ent of household appliances Roll-Out of Integrated Social Request for Quota Single Stage - One E means for Talin, Vanadzor, A IDA / 53980 Post Limited 69,600.00 0.00 Canceled 2018-04-15 2018-05-21 2018-06-03 2018-08-02 Protection Service Delivery tions nvelope masia, Malatia-Sebastia, Hra zdan, Shengavit, Tashir, Akh uryan CSSTCs SPAP II G-2-1-1/6 / Procurem ent of Computer Equipment f Roll-Out of Integrated Social Single Stage - One E or Vanadzor, Talin, Amasia, IDA / 53980 Post Request for Bids Open - National 118,800.00 113,670.78 Completed 2018-04-30 2018-04-27 2018-05-05 2018-06-02 2018-06-11 2018-07-02 2018-08-27 2018-07-30 2018-09-28 2018-09-28 2018-10-27 Protection Service Delivery nvelope Malatia-Sebastia,Shengavit, Hrazdan, Tashir and Akhurya n CSSTC-s SPAP II G-2-1-2/3 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E Pending Impl ent of furniture and other m IDA / 53980 Post Limited 63,036.00 0.00 2018-07-14 2018-09-01 2018-10-31 Protection Service Delivery tions nvelope ementation eans for Hrazdan and Tashir CSSTC-s SPAP II-G-2-1-4-1-3/AR-II / Pr Modernization of the Pension Request for Quota Single Stage - One E Pending Impl ocurement of Air Conditioner IDA / 53980 Post Open - National 60,000.00 0.00 2018-09-15 2018-10-28 2018-12-27 System tions nvelope ementation s for MLSA and SSSS SPAP II G-2-1-1/5-R / Procure ment of household appliance Roll-Out of Integrated Social Request for Quota Single Stage - One E Pending Impl s means for Talin, Vanadzor, IDA / 53980 Post Open - National 69,600.00 0.00 2018-09-15 2018-10-28 2018-12-27 Protection Service Delivery tions nvelope ementation Amasia, Malatia-Sebastia, Hr azdan, Shengavit, Tashir, Ak huryan CSSTCs SPAP II G-2-1-2/4 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E Pending Impl ent of furniture and other me IDA / 53980 Post Limited 67,414.00 0.00 2018-11-03 2018-12-29 2019-02-27 Protection Service Delivery tions nvelope ementation ans for Shengavit and Akhury an CSSTC-s SPAP II G-2-1-2/5 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E Pending Impl IDA / 53980 Post Limited 49,530.00 0.00 2018-11-12 2019-01-07 2019-03-08 ent of furniture for MLSA Protection Service Delivery tions nvelope ementation SPAP II G-2-1-1/4 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E ent of Tablets and Docking St IDA / 53980 Post Limited 73,200.00 0.00 Canceled 2019-03-30 2019-05-18 2019-07-17 Protection Service Delivery tions nvelope ations for the CSSTC-s SPAP II G-2-1-1/7 / Procurem Roll-Out of Integrated Social Single Stage - One E ent of Computer Equipment f IDA / 53980 Post Request for Bids Open - National 601,200.00 0.00 Canceled 2018-12-10 2018-12-15 2019-01-12 2019-02-09 2019-03-23 2019-05-22 Protection Service Delivery nvelope or SSSS and SEA SPAP II G-2-1-2/6 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E ent and installation of furnitu IDA / 53980 Post Limited 30,753.00 0.00 Canceled 2019-07-28 2019-08-01 2019-09-01 2019-10-31 Protection Service Delivery tions nvelope re for Tsaghkahovit CSSTC SPAP II 2-2-3 / Procurement Support the Implementation of furniture for the "State Em Request for Quota Single Stage - One E IDA / 53980 of the New Employment Stra Post Open - National 0.00 0.00 Canceled 2017-08-12 2017-10-30 2018-04-02 ployment Service" Agency an tions nvelope tegy by the Government d "Professional Orientation M ethodical Center" POMC SPAP II 2-2-2 / Modernization Support the Implementation Single Stage - One E of "Gorts" information syste IDA / 53980 of the New Employment Stra Post Request for Bids Open - National 0.00 0.00 Canceled 2017-05-15 2017-05-20 2017-06-17 2017-09-15 2017-10-20 2018-10-15 nvelope m of employment sector tegy by the Government SPAP II 2-2-4 / Development Support the Implementation and introduction of informati Request for Quota Single Stage - One E IDA / 53980 of the New Employment Stra Post Open - National 0.00 0.00 Canceled 2017-06-16 2017-09-03 2018-09-03 on system for assuring meth tions nvelope tegy by the Government odical assistance to professio nal orientation SPAP II 2-2-5 / Drafting and i ntroduction of online consult Support the Implementation ancy and distance-training pr Request for Quota Single Stage - One E IDA / 53980 of the New Employment Stra Post Open - National 0.00 0.00 Canceled 2017-10-15 2018-01-02 2018-10-31 ograms implemented via the tions nvelope tegy by the Government web page of "Professional Ori entation Methodical Center" POMC SPAP II 2-2-6 / Development Support the Implementation Request for Quota Single Stage - One E and installation of software f IDA / 53980 of the New Employment Stra Post Open - National 0.00 0.00 Canceled 2017-05-06 2017-07-24 2018-05-01 tions nvelope or testing of professional orie tegy by the Government ntation SPAP II G-2-1-1/8 / Procurem Roll-Out of Integrated Social Single Stage - One E IDA / 53980 Post Request for Bids Open - National 441,600.00 307,705.07 Signed 2019-09-27 2019-10-24 2019-10-02 2019-10-30 2019-11-21 2019-11-29 2019-12-16 2020-01-10 2020-02-17 2020-03-10 ent of Computer Equipment f Protection Service Delivery nvelope or SEA SPAP II G-2-1-1/9 / Procurem ent of Electronic Queuing Ter Roll-Out of Integrated Social Request for Quota Single Stage - One E IDA / 53980 Post Open - National 66,000.00 54,980.72 Completed 2019-12-03 2019-12-18 2019-12-08 2020-02-14 2019-12-22 2020-02-28 2020-01-21 2020-04-03 2020-02-18 2020-04-17 2020-05-18 2020-08-14 minals and Video Surveillanc Protection Service Delivery tions nvelope e and Related Equipment for the CSSTC-s SPAP II G-2-1-2/6-R / Procure Roll-Out of Integrated Social Request for Quota Single Stage - One E Under Imple ment and installation of furni IDA / 53980 Post Open - National 29,450.00 0.00 2019-12-25 2020-02-14 2020-02-22 2020-05-22 Protection Service Delivery tions nvelope mentation ture for Tsaghkahovit CSSTC SPAP II G-2-1-2/7 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E Under Imple ent and installation of furnitu IDA / 53980 Post Open - National 31,873.00 0.00 2020-03-09 2020-05-13 2020-07-12 Protection Service Delivery tions nvelope mentation re for Sevan CSSTC SPAP II G-2-1-1/10 / Procure Roll-Out of Integrated Social Single Stage - One E IDA / 53980 Post Request for Bids Open - National 448,800.00 40,082.62 Signed 2020-03-25 2020-03-26 2020-03-30 2020-04-27 2020-04-27 2020-05-27 2020-08-25 2020-06-24 2020-10-05 2020-09-22 ment of Computer Equipmen Protection Service Delivery nvelope t for SATA/D SPAP II G-2-1-2/8 / "Procure ment of additional furniture it Roll-Out of Integrated Social Request for Quota Single Stage - One E ems for Shengavit, Malatia-S IDA / 53980 Post Open - National 29,139.00 20,302.41 Signed 2020-05-05 2020-06-22 2020-07-01 2020-08-21 Protection Service Delivery tions nvelope ebastia, Talin, Vanadzor, Tas hir, Akhuryan, Hrazdan CSST C-s and MSEA" SPAP II G-2-1-2/9 / Procurem Roll-Out of Integrated Social Request for Quota Single Stage - One E ent and installation of furnitu IDA / 53980 Post Open - National 82,350.00 59,021.52 Completed 2020-05-18 2020-07-22 2020-08-10 2020-09-20 2020-10-09 Protection Service Delivery tions nvelope re for Martuni and Meghri CS STCs Page 3 SPAP II G-2-1-2/10 / Procure Roll-Out of Integrated Social Request for Quota Single Stage - One E ment and installation of furni IDA / 53980 Post Open - National 43,913.00 37,710.26 Signed 2020-07-15 2020-09-01 2020-10-05 2020-10-31 Protection Service Delivery tions nvelope ture for Dilijan andAparan CS STCs SPAP II G-2-1-1/11 / Procure ment of appliances means fo Roll-Out of Integrated Social Request for Quota Single Stage - One E r Tsaghkahovit, Stepanavan, IDA / 53980 Post Open - National 37,800.00 32,417.39 Signed 2020-08-25 2020-10-22 2020-11-25 2020-12-21 Protection Service Delivery tions nvelope Meghri, Sevan, Martuni, Goris , Aparan, Gavar, Dilijan and Ij evan CSSTCs SPAP II G-2-1-2/11 / Procure Roll-Out of Integrated Social Request for Quota Single Stage - One E ment and installation of furni IDA / 53980 Post Open - National 57,517.00 0.00 Canceled 2020-10-26 2020-11-28 2021-02-26 Protection Service Delivery tions nvelope ture for Gavar and Goris CSS TCs SPAP II G-2-1-2/13 / Procure Roll-Out of Integrated Social Request for Quota Single Stage - One E ment of furnishing means for IDA / 53980 Post Open - National 11,271.00 12,010.25 Signed 2021-02-21 2021-03-04 2021-04-04 2021-05-10 2021-06-03 Protection Service Delivery tions nvelope Gavar and Goris CSSTCs SPAP II G-2-1-2/12 / Procure Roll-Out of Integrated Social Request for Quota Single Stage - One E ment and installation of furni IDA / 53980 Post Open - National 46,175.00 48,726.85 Signed 2021-02-20 2021-03-04 2021-04-03 2021-05-10 2021-06-02 Protection Service Delivery tions nvelope ture for Gavar and Goris CSS TCs SPAP II 2-1-1/12 / Procureme Roll-Out of Integrated Social Single Stage - One E nt of computer and comput IDA / 53980 Post Request for Bids Open - National 583,200.00 551,247.73 Signed 2021-04-12 2021-03-03 2021-04-17 2021-05-08 2021-05-17 2021-06-07 2021-06-07 2021-07-19 2021-07-12 2021-10-17 Protection Service Delivery nvelope er related equipments for SA TA/D and SSS SPAP II G-2-1-2/14 / Procure ment and installation of furni Roll-Out of Integrated Social Request for Quota Single Stage - One E IDA / 53980 Post Open - National 73,405.00 78,703.34 Signed 2021-04-18 2021-06-09 2021-07-01 2021-08-08 ture for Ijevan, Jermuk, Kapa Protection Service Delivery tions nvelope n, Stepanavan United Social services /USSs/ SPAP II G-2-1-2/15 / Procure ment and installation of furni Roll-Out of Integrated Social Request for Quota Single Stage - One E IDA / 53980 Post Open - National 18,920.00 19,326.09 Signed 2021-04-20 2021-06-11 2021-07-01 2021-08-10 shing means for Ijevan, Jerm Protection Service Delivery tions nvelope uk, Kapan, Stepanavan Unite d Social services /USSs/ SPAP II G-2-1-1/13 / Procure ment of Electronic Queuing T Roll-Out of Integrated Social Single Stage - One E IDA / 53980 Post Request for Bids Open - National 100,800.00 73,575.40 Signed 2021-06-15 2021-06-25 2021-06-21 2021-07-12 2021-07-19 2021-08-02 2021-08-09 2021-09-03 2021-12-07 2021-12-02 erminals and Video Surveilla Protection Service Delivery nvelope nce and Related Equipment f or the USSTC-s SPAP II G-2-1-2/16 / Procure ment and installation of furni Roll-Out of Integrated Social Request for Quota Single Stage - One E IDA / 53980 Post Open - National 36,500.00 0.00 Canceled 2021-07-28 2021-09-04 2021-11-03 ture for United Social service Protection Service Delivery tions nvelope s of Alaverdi and Berd teritori al centers /USSs/ SPAP II G-2-1-2/17 / Procure ment and installation of furn Roll-Out of Integrated Social Request for Quota Single Stage - One E ishing means for United Soci IDA / 53980 Post Open - National 10,700.00 0.00 Canceled 2021-07-28 2021-09-24 2021-09-04 2021-11-03 Protection Service Delivery tions nvelope al services of Alaverdi and Be rd teritorial centers /USSs/ SPAP II G-2-1-2/19 / Procure ment and installation of interi Roll-Out of Integrated Social Request for Quota Single Stage - One E or decoration and accommod IDA / 53980 Post Open - National 5,245.00 0.00 Canceled 2021-11-03 2021-12-18 2022-02-16 Protection Service Delivery tions nvelope ation articles for Yeghegnadz or United Social service /USS / SPAP II G-2-1-2/18 / Procure ment and installation of furni Roll-Out of Integrated Social Request for Quota Single Stage - One E IDA / 53980 Post Open - National 18,300.00 0.00 Canceled 2021-11-03 2021-12-18 2022-02-16 ture for Yeghegnadzor Unite Protection Service Delivery tions nvelope d Social service /USS/ SPAP II G-2-1-1/20 / Procure ment and installation of furni Roll-Out of Integrated Social Single Stage - One E ture and interior decoration a IDA / 53980 Post Request for Bids Open - National 70,750.00 77,809.08 Signed 2021-12-10 2021-12-14 2021-12-15 2022-01-05 2022-01-04 2022-02-04 2022-01-24 2022-03-11 2022-02-24 2022-05-10 Protection Service Delivery nvelope nd accommodation articles f or Alaverdi, Berd and Yegheg nadzor USSTCs. SPAP II G-2-1-1/14 / Procure Roll-Out of Integrated Social Request for Quota Single Stage - One E Under Imple ment of household appliance IDA / 53980 Post Open - National 54,000.00 0.00 2022-07-16 2022-08-27 2022-10-26 Protection Service Delivery tions nvelope mentation s for USSTC-s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SPAP II- C- 3.4.1 / Implement ation of Monitoring, Develop ment and Introduction of Des Roll-Out of Integrated Social Consultant Qualifi Open - Internationa IDA / 53980 Prior 0.00 171,705.86 Signed 2016-01-06 2016-01-15 criptions of Efficiency Evaluat Protection Service Delivery cation Selection l ion and Monitoring Indicators of the Social Services Implem ented Through the MoLSA 3-4-3 / Assessment of needs Strengthen MLSI Analytical C Consultant Qualifi of the primary beneficiaries o IDA / 53980 apacity and Monitoring and Prior Open - National 204,000.00 202,414.06 Signed 2016-02-24 2016-03-16 2016-07-19 2016-09-22 2016-11-13 2016-09-26 2016-09-26 2018-08-10 cation Selection f programs piloted in the SP s Evaluation Systems ystem SPAP II 3-2-2 / Fulfillment of Support the Implementation public awareness activities o Consultant Qualifi Pending Impleme IDA / 53980 of the New Employment Stra Post Open - National 0.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-05-20 n reforms and programs impl cation Selection ntation tegy by the Government emented in the sector of labo r and employment SPAP II 3-1-2-B/1 / Implemen Support the Implementation tation of technical supervisio Consultant Qualifi Pending Impleme IDA / 53980 of the New Employment Stra Post Open - National 0.00 0.00 2016-12-29 2017-01-12 2017-02-09 2017-02-16 2017-03-23 2018-12-31 n of refurbishment of Sheng cation Selection ntation tegy by the Government avit, and Malatia-Sebastia ISP Cs, SEA, and AMSE Page 4 SPAP II 3-1-7 / Development of methodical manuals and o ther training materials assuri Roll-Out of Integrated Social Consultant Qualifi ng the provision of integrate IDA / 53980 Post Open - National 0.00 0.00 Canceled 2017-07-10 2017-07-31 2017-09-13 2017-10-13 2017-11-17 2018-05-16 Protection Service Delivery cation Selection d social protection delivery s ervices, delivery and follow u p support of distance-training system SPAP II 3-2-1 / Preparing of fi lms about professions and ca Support the Implementation Consultant Qualifi Pending Impleme rtoon animations for the prof IDA / 53980 of the New Employment Stra Post Open - National 0.00 0.00 2017-11-06 2017-11-27 2018-01-10 2018-02-09 2018-03-16 2018-10-31 cation Selection ntation essional orientation of primar tegy by the Government y school-aged children and p eople with mental disabilities SPAP II-C-3-1-8 / Preparation of Interior Designs, Specificat ions and Cost Estimates of N Roll-Out of Integrated Social Consultant Qualifi Under Implement ecessary Goods for Furnishin IDA / 53980 Post Open - National 77,424.20 0.00 2018-01-30 2018-01-29 2018-02-20 2022-02-07 2018-04-05 2018-05-05 2018-05-26 2019-04-11 Protection Service Delivery cation Selection ation g the CSSTC-s renovated and built under SPAP II and follow on supervision of goods to be supplied. /23 Centers/ SPAP II-C-3-1-1I / Preparatio n of design-cost estimate doc Roll-Out of Integrated Social Consultant Qualifi Pending Impleme uments for refurbishment of IDA / 53980 Post Open - National 75,518.60 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-05-21 2018-10-28 Protection Service Delivery cation Selection ntation Kentron and Erebuni CSSTCs and implementation of autho r's supervision SPAP II-C-3-1-1J / Preparatio n of design-cost estimate doc Roll-Out of Integrated Social Consultant Qualifi Under Implement uments for refurbishment of IDA / 53980 Post Open - National 18,852.00 0.00 2018-03-15 2018-03-05 2018-03-29 2018-05-12 2018-06-11 2018-07-02 2018-12-29 Protection Service Delivery cation Selection ation Artik CSSTC and implementat ion of author's supervision SPAP II-C-3-1-1K / Preparatio n of design-cost estimate doc Roll-Out of Integrated Social Consultant Qualifi Pending Impleme uments for refurbishment of IDA / 53980 Post Open - National 52,736.40 0.00 2018-04-09 2018-04-23 2018-06-06 2018-06-20 2018-07-11 2018-12-30 Protection Service Delivery cation Selection ntation Dilijan, Ijevan and Berd ISPC s and implementation of aut hor's supervision SPAP II-C-3-1-1L / Preparatio n of design-cost estimate doc Roll-Out of Integrated Social Consultant Qualifi Pending Impleme uments for refurbishment of IDA / 53980 Post Open - National 32,790.00 0.00 2018-04-10 2018-04-24 2018-06-07 2018-06-21 2018-07-12 2018-12-30 Protection Service Delivery cation Selection ntation Gyumri and Spitak ISPCs an d implementation of author's supervision SPAP II-C-3-1-1M / Preparatio n of design-cost estimate doc Roll-Out of Integrated Social Consultant Qualifi Pending Impleme uments for refurbishment of IDA / 53980 Post Open - National 39,696.00 0.00 2018-04-10 2018-04-24 2018-06-07 2018-06-21 2018-07-12 2018-12-30 Protection Service Delivery cation Selection ntation Ashtarak and Vagharshapat i mplementation of author's su pervision SPAP II-C-3-1-1N / Preparatio n of design-cost estimate doc uments for refurbishment of Roll-Out of Integrated Social Consultant Qualifi Pending Impleme IDA / 53980 Post Open - National 72,885.60 0.00 2018-04-10 2018-04-24 2018-06-07 2018-06-21 2018-07-12 2018-12-30 Arabkir, Nor Norq, Qanaqer-Z Protection Service Delivery cation Selection ntation eytun CSSTCs and implemen tation of author's supervision SPAP II C 3-1-2-E / Implemen tation of technical supervisio Roll-Out of Integrated Social Consultant Qualifi n of construction/rehabilitatio IDA / 53980 Post Open - National 9,317.00 4,838.12 Signed 2018-07-30 2020-04-15 2018-08-13 2018-09-26 2020-06-17 2018-10-03 2020-07-22 2018-10-17 2020-07-21 2018-12-30 Protection Service Delivery cation Selection n works of Yeghegbadzor, Va yq and Jermouk CSSTCs /ISP Cs/ SPAP II C-3-1-2-F / Implemen tation of technical supervisio Roll-Out of Integrated Social Consultant Qualifi n of construction/rehabilitatio IDA / 53980 Post Open - National 11,387.00 13,193.17 Signed 2018-07-30 2018-07-13 2018-08-13 2018-09-26 2019-10-25 2018-10-03 2019-11-28 2018-10-17 2019-11-29 2018-12-30 Protection Service Delivery cation Selection n works of Ashtarak, Aparan and Abovyan CSSTCs /ISPCs/ SPAP II C-3-1-2-G / Impleme ntation of technical supervisi Roll-Out of Integrated Social Consultant Qualifi Pending Impleme on of construction/rehabilitati IDA / 53980 Post Open - National 10,973.00 0.00 2018-07-30 2018-08-13 2018-09-26 2018-10-03 2018-10-17 2018-12-30 Protection Service Delivery cation Selection ntation on works of Nor-Norq, Erebun i and Qanaqer-Zeytun CSSTC s /ISPCs/ SPAP II C-3-1-2-H / Implemen tation of technical supervisio Roll-Out of Integrated Social Consultant Qualifi Pending Impleme n of construction/rehabilitatio IDA / 53980 Post Open - National 16,563.00 0.00 2018-07-30 2018-08-13 2018-09-26 2018-10-03 2018-10-17 2018-12-30 Protection Service Delivery cation Selection ntation n works of Kentron, Arabkir a nd Vagharshapat CSSTCs /IS PCs/ SPAP II C-3-1-2-I / Implement ation of technical supervision Roll-Out of Integrated Social Consultant Qualifi Under Implement IDA / 53980 Post Open - National 16,563.00 0.00 2018-07-30 2019-11-04 2018-08-13 2018-09-26 2018-10-03 2018-10-17 2018-12-30 of construction/rehabilitation Protection Service Delivery cation Selection ation works of Gyumri, Artik and S pitak CSSTCs /ISPCs/ SPAP II C-3-1-2-J / Implement ation of technical supervision Roll-Out of Integrated Social Consultant Qualifi IDA / 53980 Post Open - National 11,387.00 10,561.74 Signed 2018-07-30 2019-01-16 2018-08-13 2018-09-26 2019-03-27 2018-10-03 2019-06-12 2018-10-17 2019-07-25 2018-12-30 of construction/rehabilitation Protection Service Delivery cation Selection works of Goris, Kapan and M eghri CSSTCs /ISPCs/ SPAP II C-3-1-2-K / Implemen tation of technical supervisio Roll-Out of Integrated Social Consultant Qualifi n of construction/rehabilitatio IDA / 53980 Post Open - National 12,836.00 10,445.56 Signed 2018-07-30 2019-01-17 2018-08-13 2018-09-26 2019-10-25 2018-10-03 2019-11-29 2018-10-17 2019-11-29 2018-12-30 Protection Service Delivery cation Selection n works of Gavar, Martuni an d Sevan CSSTCs /ISPCs/ SPAP II-C-2-2-7 / “Developm Support the Implementation ent and Introduction of an Inf Consultant Qualifi IDA / 53980 of the New Employment Stra Post Open - National 299,000.00 0.00 Canceled 2019-09-05 2019-10-10 2019-09-19 2019-12-02 2019-11-02 2019-12-02 2019-12-17 2020-11-14 ormation System supporting cation Selection tegy by the Government the Development of the RoA Employment Sector” SPAP II C-3-1-2-L / Implemen tation of technical supervisio Roll-Out of Integrated Social Consultant Qualifi Under Implement IDA / 53980 Post Open - National 13,359.00 0.00 2019-08-26 2019-11-04 2019-09-09 2019-10-23 2019-11-06 2019-11-27 2020-11-30 n of construction/rehabilitatio Protection Service Delivery cation Selection ation n works of Dilijan, Ijevan and Berd CSSTCs /ISPCs/ SPAP II-C-3-1-1-Q / Preparati on of design-cost estimate d ocuments and implementatio Roll-Out of Integrated Social Consultant Qualifi Under Implement n of follow-on supervision for IDA / 53980 Post Open - National 48,606.00 0.00 2020-10-21 2020-11-04 2020-11-04 2020-12-02 2020-12-16 2020-12-23 2022-10-31 Protection Service Delivery cation Selection ation the establishment of Integrat ed (Complex) Social Services Central Office, Kentron and Erebuni CSSTCs Page 5 SPAP II-C-3.5.1/1 / Project Au Least Cost Selecti IDA / 53980 Project Management Post Open - National 11,200.00 8,553.22 Signed 2021-03-09 2021-03-12 2021-03-16 2021-04-06 2021-03-31 2021-04-13 2021-04-09 2021-04-20 2021-04-09 2021-05-11 2021-04-30 2021-05-19 2021-06-03 2022-10-31 dit /for the years 2020, 2021, on 2022/ SPAP II-C-3-1-1-R / Preparati on of design-cost estimate d ocuments and implementatio Roll-Out of Integrated Social Consultant Qualifi IDA / 53980 Post Open - National 8,650.00 0.00 Canceled 2021-11-29 2021-12-10 2021-12-13 2022-01-31 2022-01-17 2022-01-31 2022-03-07 2022-10-31 n of follow-on supervision for Protection Service Delivery cation Selection the establishment of Nor Nor k United Social Service territ orial center SPAP II-C-3-1-1-S / Preparati on of design-cost estimate d ocuments and implementatio Roll-Out of Integrated Social Consultant Qualifi IDA / 53980 Post Open - National 28,900.00 42,671.84 Signed 2021-12-10 2021-12-17 2021-12-24 2022-01-31 2022-01-28 2022-03-10 2022-02-11 2022-04-20 2022-02-23 2022-05-01 2022-10-31 n of follow-on supervision for Protection Service Delivery cation Selection the establishment of Arabkir United Social Service territori al center SPAP II-C-3-1-1-R. / Preparati on of design-cost estimate d ocuments and implementatio Roll-Out of Integrated Social Consultant Qualifi IDA / 53980 Post Open - National 25,600.00 0.00 Canceled 2021-12-10 2021-12-10 2021-12-24 2022-01-28 2022-03-10 2022-02-18 2022-05-01 2022-03-11 2022-10-31 n of follow-on supervision for Protection Service Delivery cation Selection the establishment of Nor Nor k United Social Service territ orial center SPAP II C-3-1-2-M / Impleme ntation of Technical Supervisi Roll-Out of Integrated Social Consultant Qualifi IDA / 53980 Post Open - National 6,015.00 5,983.63 Signed 2021-12-14 2021-12-15 2021-12-24 2022-01-21 2022-02-02 2022-02-11 2022-02-16 2022-02-21 2022-02-18 2022-10-31 on of Rehabilitation/Refurbis Protection Service Delivery cation Selection hment works of Vagharshapa t USSTC SPAP II-NC- 3-1-7 / Trainings Roll-Out of Integrated Social Quality Based Sel Open - Internationa Under Implement of the staff of the Unified Soc IDA / 53980 Post 200,000.00 0.00 2022-01-24 2022-01-27 2022-02-14 2022-02-10 2022-03-21 2022-03-31 2022-04-11 2022-05-02 2022-05-23 2022-06-13 2022-10-31 Protection Service Delivery ection l ation ial Service's Structural Subdi visions SPAP II-C-2-1-3 / Application Roll-Out of Integrated Social Consultant Qualifi s Management System (AMS) IDA / 53980 Post Open - National 285,000.00 266,120.00 Signed 2022-03-23 2022-04-05 2022-04-06 2022-04-25 2022-04-22 2022-04-30 2022-06-07 2022-05-03 2022-06-07 2022-10-30 Protection Service Delivery cation Selection of the Social Protection Sphe re of the RA Strengthen MLSI Analytical C SPAP II-C-3.4.5 / Surveys on Consultant Qualifi Pending Impleme IDA / 53980 apacity and Monitoring and Post Open - National 43,460.00 0.00 2022-05-25 2022-06-08 2022-07-06 2022-07-20 2022-08-03 2022-10-30 project indicators cation Selection ntation Evaluation Systems SPAP II-C-3-1-9 / Implementa tion of Measurement Service s for the Premises/Land Plots Roll-Out of Integrated Social Consultant Qualifi Under Implement IDA / 53980 Post Open - National 3,000.00 0.00 2022-06-10 2022-06-10 2022-06-20 2022-07-25 2022-08-08 2022-08-14 2022-10-13 for the Establishment of Kent Protection Service Delivery cation Selection ation ron, Stepanavan, Alaverdi an d Spitak Territorial Centers of the Unified Social Service (US S) SPAP II-C-3-1-1-T / Preparati on of design-cost estimate d ocuments and implementatio Roll-Out of Integrated Social Consultant Qualifi Under Implement IDA / 53980 Post Open - National 40,000.00 0.00 2022-06-14 2022-06-16 2022-06-28 2022-07-28 2022-08-02 2022-08-12 2022-08-16 2022-10-30 n of follow-on supervision for Protection Service Delivery cation Selection ation the establishment of Nor Nor k United Social Service territ orial centre SPAP II-C-3.4.6 / PILOTING A Strengthen MLSI Analytical C ND VALIDATION OF HYBRID Quality And Cost- Open - Internationa Pending Impleme IDA / 53980 apacity and Monitoring and Post 70,000.00 0.00 2022-05-25 2022-06-08 2022-07-20 2022-08-03 2022-08-24 2022-09-14 2022-09-28 2022-11-17 MEANS TESTED TARGETING Based Selection l ntation Evaluation Systems APPROACH IN ARMENIA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Roll-Out of Integrated Social Individual Consult SPAP II-C-3.5.7-b / Engineer IDA / 53980 Prior Open 0.00 146,365.35 Signed 2015-04-09 2015-04-11 Protection Service Delivery ant Selection Roll-Out of Integrated Social Individual Consult SPAP II-C-3.5.7-c / Engineer IDA / 53980 Prior Open 0.00 73,173.93 Signed 2015-04-09 2015-04-11 Protection Service Delivery ant Selection CONTRACT SPAP II-C-3.5.3r / Roll-Out of Integrated Social Individual Consult Social Protection Project Impl IDA / 53980 Prior Open 0.00 113,768.81 Signed 2015-06-15 2015-06-15 Protection Service Delivery ant Selection ementation Specialist SPAPII-C-3.5.11 / Information Roll-Out of Integrated Social Individual Consult IDA / 53980 Prior Open 0.00 79,765.11 Signed 2015-07-28 2015-08-17 Systems Specialist Protection Service Delivery ant Selection SPAP-C-3.5.2 / Project Coordi Roll-Out of Integrated Social IDA / 53980 Prior Direct Selection Direct 96,000.00 37,748.69 Terminated 2015-03-02 nator Protection Service Delivery SPAP II-C-3.5.6 / Technical S Roll-Out of Integrated Social Individual Consult upport and Communication T IDA / 53980 Prior Open 0.00 72,273.39 Signed 2015-04-06 2015-04-10 Protection Service Delivery ant Selection echnologies (TSCT) Specialist SPAP II-C-3.5.4 / Specialist o Roll-Out of Integrated Social Individual Consult IDA / 53980 Prior Open 0.00 133,874.84 Signed 2015-04-08 2015-04-10 n Project Monitoring and Eval Protection Service Delivery ant Selection uation Roll-Out of Integrated Social Individual Consult SPAP II-C-3.5.7-a / Engineer IDA / 53980 Prior Open 0.00 109,863.34 Signed 2015-04-09 2015-04-11 Protection Service Delivery ant Selection 3-5-13 / Social Safeguards S Individual Consult Under Implement IDA / 53980 Project Management Post Open 0.00 0.00 2016-10-25 2016-10-25 2016-12-13 2017-01-03 2017-02-07 2017-08-06 pecialist ant Selection ation SPAP II C 3-5-2A / Coordinato IDA / 53980 Project Management Prior Direct Selection Direct 17,920,971.00 89,889.00 Completed 2017-09-25 2017-09-30 2017-10-14 2017-10-06 2018-12-09 2019-06-21 r for PCU SPAP II-C-3-5-5/A / Engineer Individual Consult IDA / 53980 Project Management Post Open 0.00 49,180.63 Signed 2017-12-21 2017-12-20 2018-02-08 2018-02-26 2018-03-01 2018-02-26 2018-03-22 2018-03-01 2018-09-18 - Environmental Specialist ant Selection Individual Consult SPAP II-C-3-5-7-D / Engineer IDA / 53980 Project Management Prior Open 16,666.00 47,458.54 Completed 2018-03-20 2018-03-22 2018-05-13 2018-04-17 2018-05-18 2018-08-07 2018-05-20 2018-06-13 2018-12-26 2019-09-19 ant Selection SPAP II C-3-5-14 / PCU Techn Individual Consult IDA / 53980 Project Management Post Open 2,025.00 14,158.44 Terminated 2018-05-20 2018-12-17 2018-06-22 2018-07-03 2018-07-13 2018-07-06 2018-08-02 2018-07-20 2018-12-30 ical Assistant ant Selection Page 6 SPAP II-C-3-1-1P / Making A mendments in Design-Cost E stimate Documents for Refur Roll-Out of Integrated Social Under Implement bishment Works of Tashir Co IDA / 53980 Post Direct Selection Direct 4,950.00 0.00 2018-06-11 2018-06-06 2018-06-16 2018-06-30 2018-12-30 Protection Service Delivery ation mplex Social Services Territo rial Center (CSSTC) in Lori Ma rz and Implementing Follow-o n Supervision SPAP II C-3-5-9 / Assistant to Individual Consult Under Implement IDA / 53980 Project Management Post Open 43,767.00 0.00 2018-11-05 2014-11-07 2018-11-05 2015-02-02 2018-11-05 2015-02-25 2018-11-05 2018-11-30 Project Coordinator ant Selection ation SPAP II-C-3-5-15 / Software, Individual Consult Telecommunication Technolo IDA / 53980 Project Management Post Open 33,100.00 29,620.09 Signed 2019-01-24 2019-01-16 2019-03-14 2019-02-27 2019-03-28 2019-04-15 2019-04-09 2019-05-02 2020-11-30 ant Selection gies and Technical Support S pecialist SPAP II C 3-5-2/B / Project co IDA / 53980 Project Management Prior Direct Selection Direct 40,800.00 100,005.34 Completed 2019-07-15 2019-07-16 2019-07-15 2019-07-22 2019-07-20 2019-07-25 2020-11-30 2020-10-30 ordinator Individual Consult SPAP II-C-3-5-7-E / Engineer IDA / 53980 Project Management Post Open 20,415.00 9,737.98 Signed 2019-10-17 2019-10-17 2019-12-05 2019-11-29 2019-12-12 2019-11-29 2019-12-26 2019-12-02 2020-06-25 ant Selection Individual Consult SPAP II-C-3-5-7-F / Engineer IDA / 53980 Project Management Post Open 20,415.00 52,693.02 Signed 2019-10-17 2019-10-17 2019-12-05 2019-11-29 2019-12-12 2019-11-29 2019-12-26 2019-12-02 2020-06-25 ant Selection SPAP II-C-3-5-16 / Financial Individual Consult IDA / 53980 Project Management Prior Open 21,000.00 59,741.50 Signed 2019-10-25 2019-10-28 2019-12-13 2019-12-03 2019-12-20 2019-12-04 2020-01-01 2019-12-06 2020-06-29 management specialist ant Selection SPAP II C 3-5-17 / Procureme IDA / 53980 Project Management Prior Direct Selection Direct 19,221.00 58,006.00 Signed 2019-12-24 2020-01-08 2019-12-26 2020-01-09 2020-01-18 2020-01-16 2020-11-30 nt Specialist SPAP II-C-3.5.1 / Project Audi Under Implement IDA / 53980 Project Management Post Direct Selection Direct 40,500.00 0.00 2020-03-23 2020-03-24 2020-03-24 2020-03-24 2020-11-29 t ation Individual Consult SPAP II-C-3-5-7-G / Engineer IDA / 53980 Project Management Post Open 43,188.00 19,151.22 Signed 2020-07-13 2020-07-09 2020-08-24 2020-07-31 2020-08-24 2020-07-31 2020-09-16 2020-08-06 2022-10-30 ant Selection SPAP II C-3-5-14-A / PCU Tec Individual Consult IDA / 53980 Project Management Post Open 11,123.00 8,779.40 Signed 2020-10-20 2020-10-30 2020-12-08 2021-03-19 2020-12-29 2021-03-31 2021-01-12 2021-04-01 2022-11-01 hnical Assistant ant Selection SPAP II C 3-5-2/C / Project co Individual Consult IDA / 53980 Project Management Post Limited 62,750.00 59,929.96 Signed 2020-11-06 2020-11-04 2020-11-07 2020-11-11 2020-11-09 2020-11-19 2020-11-12 2020-11-20 2022-10-31 ordinator ant Selection SPAP II C-3-1-2-N / Implemen tation of Technical Supervisio Roll-Out of Integrated Social n of Rehabilitation works of t IDA / 53980 Post Direct Selection Direct 300.00 248.45 Completed 2021-12-15 2021-12-17 2021-12-19 2022-01-10 2021-12-27 2022-01-17 2022-02-25 2022-02-28 Protection Service Delivery he reception of the MLSA of RA /Government House 3/ SPAP II C 3-5-18 / Unified Inf Individual Consult IDA / 53980 Project Management Post Limited 18,600.00 17,356.74 Signed 2022-04-21 2022-04-22 2022-04-26 2022-05-03 2022-05-01 2022-05-05 2022-05-19 2022-05-12 2022-10-31 ormation System Project coor ant Selection dinator SPAP II C 3-5-19 / Legal Cons Individual Consult IDA / 53980 Project Management Post Limited 4,850.00 4,284.51 Signed 2022-06-08 2022-06-14 2022-06-13 2022-06-17 2022-06-23 2022-06-28 2022-06-27 2022-07-01 2022-10-31 ultant ant Selection Page 7