The World Bank                                                                                    Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)



India Energy Efficiency Scale-up Program (P162849)


 SOUTH ASIA | India | Energy & Extractives Global Practice | Requesting Unit: SACIN | Responsible Unit: ISAE1
 IBRD/IDA | Program-for-Results Financing | FY 2018 | Team Leader(s): Ivan Jaques Goldenberg, Defne Gencer


 Seq No: 6 | ARCHIVED on 21-Apr-2022 | ISR50846 | Created by: Ivan Jaques Goldenberg on 29-Mar-2022 | Modified by: Ivan Jaques Goldenberg
 on 20-Apr-2022


 Program Development Objectives

  PDO Table
  Program Development Objective (from Program Appraisal Document)
  The program and project development objectives are to scale up energy savings in residential and public sectors, strengthen EESL’s institutional
  capacity, and enhance its access to commercial financing.

 Overall Ratings

 Name                                                                        Previous Rating                          Current Rating

 Progress towards achievement of PDO                                         Satisfactory                            Satisfactory
 Overall Implementation Progress (IP)                                        Satisfactory                            Moderately Satisfactory


 Implementation Status and Key Decisions

  The India Energy Efficiency Scale-Up operation was approved by the World Bank Group Board of Directors on May 17, 2018, and the PforR loan
  for this operation became effective on November 6, 2018. The Program is making steady and satisfactory overall implementation progress in
  Result Areas 1 and 2, and Results Areas 3 and 4 are progressing with some delays. The Disbursement Linked Results are being achieved but were
  slowed down and delayed due to COVID-19 disruption in FY21 and FY22. DLI 5 is delayed by 24 months and EESL has conveyed to the Bank that
  this DLR will be achieved by Q4 FY22. The overall Program has disbursed over 64 percent, but this percentage will go up to 70 once EESL submits
  a withdrawal application for the fourth round of results achievement (approved by the Bank on April 5, 2022).



 Data on Financial Performance


 Disbursements (by loan)

 Project        Loan/Credit/TF    Status       Currency        Original   Revised     Cancelled     Disbursed       Undisbursed             % Disbursed


 P162849        IBRD-88570        Effective    USD             220.00      220.00            0.00        141.57           78.43                      64%


 Key Dates (by loan)

 Project         Loan/Credit/TF    Status      Approval Date       Signing Date     Effectiveness Date      Orig. Closing Date    Rev. Closing Date

 P162849         IBRD-88570        Effective   17-May-2018         28-Aug-2018      06-Nov-2018             30-Sep-2022           30-Sep-2022




4/21/2022                                                                                                                    Page 1 of 11
            The World Bank                                                                            Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)



 DLI Disbursement

                                                                                  Achievement      Disbursed amount in    Disbursement % for
 DLI ID       DLI Type      Description                     Coc    DLI Amount
                                                                                  Status           Coc                    DLI

 Loan: IBRD88570-001

                             DLI1 (i) No of LED bulb &
  1.1         Regular                                       USD   17,110,000.00   Fully Achieved        17,110,000.00                 100 %
                             tubes sold P1
                             DLI1 (ii) No of LED bulb &
  1.2         Regular                                       USD   19,000,000.00   Fully Achieved        18,888,433.00                 99 %
                             tubes sold P2
                             DLI1 (iii) No of LED bulb&                           Partially
  1.3         Regular                                       USD   19,090,000.00                          2,504,509.00                 13 %
                             tubes sold P3                                        Achieved
                             DLI1 (iv) No of LED bulb&
  1.4         Regular                                       USD    9,900,000.00   Not Achieved                    0.00
                             tubes sold P4
                             DLI1 (v) No of LED bulb &
  1.5         Regular                                       USD     900,000.00    Not Achieved                    0.00
                             tubes sold P5
                             DLI2 (i) No of EE ceiling
  2.1         Regular                                       USD    3,400,000.00   Fully Achieved         3,400,000.00                 100 %
                             fans sold P1
                             DLI2 (ii) No of EE ceiling                           Partially
  2.2         Regular                                       USD    4,540,000.00                          2,746,498.00                 60 %
                             fans sold P2                                         Achieved
                             DLI2 (iii) No of EE ceiling
  2.3         Regular                                       USD    4,990,000.00   Not Achieved                    0.00
                             fans sold P3
                             DLI2 (iv) No of EE ceiling
  2.4         Regular                                       USD    4,540,000.00   Not Achieved                    0.00
                             fans sold P4
                             DLI2 (v) No of EE ceiling
  2.5         Regular                                       USD    4,530,000.00   Not Achieved                    0.00
                             fans sold P5
                             DLI 3 (i) No of LED strt
  3.1         Regular                                       USD   19,250,000.00   Fully Achieved        19,250,000.00                 100 %
                             lights inst P1
                             DLI 3 (ii) No of LED strt
  3.2         Regular                                       USD   19,250,000.00   Fully Achieved        19,250,000.00                 100 %
                             lights inst P2
                             DLI3 (iii) No of LED strt
  3.3         Regular                                       USD   19,250,000.00   Fully Achieved        19,242,000.00                 100 %
                             lights ins P3
                             DLI3 (iv) No of LED strt
  3.4         Regular                                       USD   16,040,000.00   Fully Achieved         8,131,746.00                 51 %
                             lights ins P4
                             DLI3 (v) No of LED strt
  3.5         Regular                                       USD    3,210,000.00   Fully Achieved                  0.00
                             lights ins P5
                             DLI 4 Sustainability Action
  4           Regular                                       USD   14,000,000.00   Fully Achieved        14,000,000.00                 100 %
                             Imple
                             DLI 5 Bus model for Collab
  5           Regular                                   USD        8,000,000.00   Not Achieved                    0.00
                             Pvt sec ESCO
                             DLI6 (i) Est of sus dev unit
  6.1         Regular                                       USD   16,500,000.00   Fully Achieved        16,500,000.00                 100 %
                             report
                             DLI6 (ii) Est of sus dev unit
  6.2         Regular                                      USD    15,950,000.00   Not Achieved                    0.00
                             report

 Program Action Plan




4/21/2022                                                                                                           Page 2 of 11
            The World Bank                                                                                  Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)



                                  EESL will update EESL Guidelines, Policy and Procedure for Procurement of Goods, Works and Non-Consulting
  Action Description              Services (“Guidelines”), Standard Bidding Documents; Standard MOU Template with SOEs and ULBs, and adopt all
                                  these Guidelines.

  Source                          DLI#                  Responsibility          Timing                 Timing Value               Status

  Fiduciary Systems                                     EESL                    Due Date               31-Mar-2019                Completed

  Completion Measurement          This Program Action was delayed beyond the agreed deadline of March 31, 2019 but has now been completed.

  Comments



                                  EESL will develop, adopt, and/or disseminate its Quality Assurance Manuals by September 30, 2018 and dispense
  Action Description              training on quality assurance in street and domestic lighting and ceiling fans programs to staff and vendors.



  Source                          DLI#                  Responsibility          Timing                 Timing Value               Status

  Environmental and Social
                                                        EESL                    Due Date               31-Mar-2019                Completed
  Systems

                                  This Program Action has been completed in January 2019. The Quality Assurance Manuals have been prepared,
  Completion Measurement
                                  adopted and hosted on EESL’s Website.

  Comments



  Action Description              EESL Audit Committee of the Board (ACB) shall include two independent directors as its members.

  Source                          DLI#                  Responsibility          Timing                 Timing Value               Status

  Fiduciary Systems                                     EESL                    Due Date               30-Sep-2018                Completed

                                  Achieved, but the action is rendered infructuous due to change in law: EESL had two independent directors (ID) on
  Completion Measurement          the Board of Directors. Due to certain changes in the Companies act and rules, appointment of IDs is no longer
                                  mandatory for EESL.

                                  Due to the above, appointment was not pursued by EESL with the Ministry/GoI. The present Audit Committee
  Comments
                                  comprises of three nominee directors.



                                  EESL will prepare, adopt and implement finance manual(s) covering all financial management functions in line with
  Action Description
                                  current systems and issue an internal notification of their application as of April 1, 2019.

  Source                          DLI#                  Responsibility          Timing                 Timing Value               Status

  Fiduciary Systems                                     EESL                    Due Date               31-Mar-2019                Completed

                                  The Finance Manuals have been finalized, approved by competent authority (MD) on 25-Sept-2021, and
  Completion Measurement
                                  operationalized.

  Comments                        Approval of the manuals from the Board of EESL is in process. The action is delayed.




4/21/2022                                                                                                                  Page 3 of 11
            The World Bank                                                                                     Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)



                                  EESL shall ensure that its audit committee approves terms of reference acceptable to the Bank to strengthen EESL’s
  Action Description
                                  internal audit function; and such internal audit function is performed in accordance with approved terms of reference.

  Source                          DLI#                   Responsibility           Timing                  Timing Value               Status

  Fiduciary Systems                                      EESL                     Due Date                30-Sep-2018                Completed

                                  Internal audit is conducted by a private audit firm on ToR approved by the Audit Committee. Audit is completed up to
  Completion Measurement
                                  FY2021. EESL has revised the ToR with enhanced focus on risk-based approach.

  Comments



                                  EESL shall develop, adopt and report to the Bank on its strategy on energy efficiency market transformation of
  Action Description              residential lighting including reporting on bulk procurement, quality assurance, environmental sustainability, marketing
                                  and outreach, etc.

  Source                          DLI#                   Responsibility           Timing                  Timing Value               Status

  Technical                                              EESL                     Due Date                31-Mar-2019                In Progress

                                  This Program Action is Not Yet Completed. The draft Strategy document prepared and submitted by EESL to the
  Completion Measurement
                                  World Bank has many gaps and need to be revised. The revised report has not yet been submitted to the Bank.

  Comments



                                  EESL shall produce and make publicly available a report (i) containing an independent review and evaluation of the
  Action Description              agricultural EE and DSM models examined/tested by the EESL; and (ii) reporting on EESL's sustainability actions and
                                  indicators

  Source                          DLI#                   Responsibility           Timing                  Timing Value               Status

  Technical                                              EESL                     Due Date                31-Mar-2020                In Progress

                                  EESL has initiated this work in March 2020 with a consultant. The completion timelines will be delayed due to
  Completion Measurement
                                  disruption caused by COVID 19 and EESL has requested to move the completion date for this PAP.

  Comments



                                  EESL to develop and implement a plan for systematic and periodic independent evaluation of each of its program
  Action Description              under implementation, including program impact assessment, challenge identification, and consumer perspectives
                                  collection, and report them.

  Source                          DLI#                   Responsibility           Timing                  Timing Value               Status

  Other                                                  EESL                     Due Date                31-Mar-2020                In Progress

                                  EESL has initiated this work but progress got delayed on account of disruption caused by COVID 19. EESL has
  Completion Measurement
                                  requested the Bank to extend the compliance date.

  Comments




4/21/2022                                                                                                                     Page 4 of 11
            The World Bank                                                                                     Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)



                                  EESL will develop and adopt a training program, and install a training center, for EE capacity building and training of
  Action Description              the EESL’s staff, EE private sector targeting private sector ESCOs and other EE service providers, and the EESL’s
                                  customers.

  Source                          DLI#                   Responsibility           Timing                  Timing Value                Status

  Technical                                              EESL                     Due Date                31-Mar-2020                 In Progress

                                  EESL has established an EESL Knowledge Centre (EKC) learning platform in order to develop the capability of the
  Completion Measurement          EESL workforce. The Bank team commented on the report by EESL in May 2020, but the revised document has not
                                  yet been submitted.

  Comments



                                  EESL will (i) develop a baseline of the number of women it employs at each level (managerial, technical,
  Action Description
                                  administrative); and (ii) track, on an ongoing basis, how many women it employs at each level.

  Source                          DLI#                   Responsibility           Timing                  Timing Value                Status

  Environmental and Social
                                                         EESL                     Due Date                31-Mar-2020                 In Progress
  Systems

                                  The EESL Gender Baseline Report had been prepared in 2019 and submitted to the World Bank. The update with
  Completion Measurement
                                  tracking has not been provided.

  Comments



                                  EESL will strengthen, complete and operationalize the complete Environmental, Occupational Health & Safety and
  Action Description
                                  Social (EHSS) Manual (details described in #11 in Annex 8 of PAD)

  Source                          DLI#                   Responsibility           Timing                  Timing Value                Status

  Environmental and Social
                                                         EESL                     Due Date                31-Mar-2019                 Completed
  Systems

                                  This Program Action was completed. EESL is also continuously udating the EHSS Manual for all activities which
  Completion Measurement
                                  qualifies as ‘program under implementation’ as defined under the program.

  Comments



                                  EESL, with financial advisors’ support, shall develop, and its management shall approve, a long-term financial
  Action Description
                                  resource mobilization plan.

  Source                          DLI#                   Responsibility           Timing                  Timing Value                Status

  Other                                                  EESL                     Due Date                31-Mar-2019                 In Progress

                                  The PAP is under progress. The draft financial resource mobilization plan for EESL and document detailing the
  Completion Measurement          Funding Options was sent by EESL to the World Bank but has not yet been finalized and formally submitted to meet
                                  the PAP requirements.

  Comments



4/21/2022                                                                                                                      Page 5 of 11
            The World Bank                                                                                      Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval               Previous Rating               Current Rating

  Political and Governance                                   --                               Low                          Low
  Macroeconomic                                              --                               Low                          Low
  Sector Strategies and Policies                             --                               Low                          Low
  Technical Design of Project or Program                     --                               Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                             --                               Low                          Low
  Sustainability
  Fiduciary                                                  --                               Moderate                     Moderate
  Environment and Social                                     --                               Moderate                     Moderate
  Stakeholders                                               --                               Moderate                     Moderate
  Other                                                      --                               High                         High
  Overall                                                    --                               Moderate                     Moderate




  Results


 PDO Indicators by Objectives / Outcomes


  To scale up energy savings in residential and public sectors
   IN01122662
   ►PDO Indicator 1- Projected lifetime energy savings from LED bulbs, tube lights, EE ceiling fans and LED Street Lights sold via EESL
   programs. (Gigawatt-hour (GWh), Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              197,900.00                  224,252.00                    327,867.00                 403,400.00

    Date                               31-Mar-2017                 10-Sep-2021                   11-Apr-2022               31-Mar-2022
                                       These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                       as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of
    Comments
                                       February 25, 2022.
   IN01122665
   ►PDO Indicator 2- Avoided CO2 emissions associated with projected lifetime savings from LED bulbs, LED tube lights, energy efficient
   ceiling fans and LED street lights sold via EESL programs (Metric ton, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              160,700,000.00              181,644,314.50                265,973,612.00             326,800,000.00

    Date                               31-Mar-2017                 10-Sep-2021                   11-Apr-2022               31-Mar-2022




4/21/2022                                                                                                                     Page 6 of 11
            The World Bank                                                                                      Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)



                                       These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                       as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of
    Comments
                                       February 25, 2022.


  Enhance EESL's access to commercial financing
   IN01122663
    ►PDO Indicator 3- Amount of commercial financing leveraged by the IBRD guarantee (Amount(USD), Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         0.00                          0.00                       200,000,000.00

    Date                               31-Mar-2017                  10-Sep-2021                   11-Apr-2022                31-Mar-2022

    Comments

  Strengthen EESL's institutional capacity
    IN01122664
    ►PDO Indicator 4 - Establishment of Sustainable Development Unit and report on implementation of updated EHSS Manual covering all
   EESL programs under implementation (Yes/No, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              No                           No                            No                         Yes

    Date                               31-Mar-2017                  10-Sep-2021                   11-Apr-2022                31-Mar-2022
                                       Only Part (i) of the DLI 6 associated with this indicator has been achieved. Part (ii) of DLI 6 associated with
    Comments                           this indicators remains to be completed (as of April 2022)


 Intermediate Results Indicators by Results Areas



  RA 1- Energy savings and EE market transformation in the residential sector
   IN01122721
    ►IR Indicator 1.1- Number of LED bulbs and tube lights sold via EESL program (Number, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              216,000,000.00               344,448,362.00                351,186,649.00             437,000,000.00

    Date                               31-Mar-2017                  10-Sep-2021                   11-Apr-2022                31-Mar-2022
                                       These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                       as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of
    Comments
                                       February 25, 2022.
    IN01122725
    ►IR Indicator 1.2- Estimated number of beneficiaries (of which women) of LED bulbs sold via EESL program (Number, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              336,000,000.00               539,479,101.00                550,192,417.00             656,000,000.00

    Date                               31-Mar-2017                  10-Sep-2021                   11-Apr-2022                31-Mar-2022




4/21/2022                                                                                                                      Page 7 of 11
            The World Bank                                                                                      Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)



                                       These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                       as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of
    Comments
                                       February 25, 2022.
    IN01122729
    ►IR Indicator 1.3 - Number of energy efficient ceiling fans sold via EESL program (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              587,795.00                   2,215,735.00                 2,300,316.00               6,408,000.00

    Date                               31-Mar-2017                  10-Sep-2021                  11-Apr-2022               31-Mar-2022
                                       These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                       as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of
    Comments
                                       February 25, 2022.
   IN01122731
   ►IR Indicator 1.4- Approval of EESL strategy for sustainable LED market transformation in residential lighting, including set of indicators
   EESL will monitor and track (Yes/No, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              No                           No                           No                         Yes

    Date                               31-Mar-2017                  10-Sep-2021                  11-Apr-2022               31-Mar-2022

    Comments
    IN01122732
    ►IR Indicator 1.0- Direct employment (number of jobs) created of which women (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              366.00                       366.00                       366.00                     500.00

    Date                               31-Mar-2017                  10-Sep-2021                  11-Apr-2022               31-Mar-2022

                                       This data is still awaited from EESL.
    Comments



  RA 2- Energy savings and EE market transformation in street lighting
   IN01122722
    ►IR Indicator 2.1- Number of LED street lights installed under SLNP (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              1,967,000.00                 7,462,431.00                 9,406,563.00               9,167,000.00

    Date                               31-Mar-2017                  10-Sep-2021                  11-Apr-2022               31-Mar-2022
                                       These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                       as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of
    Comments
                                       February 25, 2022.
   IN01122726
   ►IR Indicator 2.2 - Number of municipalities/towns/villages/gram panchayats with LED street lights installed through SLNP (Number,
   Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                              500.00                       700.00                       700.00                     1,250.00



4/21/2022                                                                                                                     Page 8 of 11
            The World Bank                                                                                    Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)




    Date                               31-Mar-2017                 10-Sep-2021                  10-Sep-2021                31-Mar-2022
                                       These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                       as reported by EESL for the period up to December 31, 2020, through their Results Notification letter of
    Comments
                                       April 29, 2020. No additional DLRs were achieved for these DLIs 1, 2 and 3 in CY2021.



  RA 3- Development of sustainable business models in new EE market segments
   IN01122723
    ►IR Indicator 3.1 - EESL implementation of the three EE AC sustainability actions approved (Yes/No, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                              No                          Yes                          Yes                        Yes

    Date                               31-Mar-2017                 10-Sep-2021                  11-Apr-2022                30-Sep-2021

   Comments
   IN01122727
   ►IR Indicator 3.2 - EESL approval of business model for collaboration with private sectur ESCOs in the implementation of EESL's Builidng
   EE activities (Yes/No, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                              No                          No                           No                         Yes

    Date                               31-Mar-2017                 10-Sep-2021                  11-Apr-2022                31-Mar-2020

    Comments



  RA 4- Institutional strengthening for sustainable EE scale-up
   IN01122724
    ►IR Indicator 4.1- Periodic independent evaluations of EESL programs (Yes/No, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                              No                          No                           No                         Yes

    Date                               31-Mar-2017                 10-Sep-2021                  11-Apr-2022                31-Mar-2022

   Comments
   IN01122728
   ►IR Indicator 4.2- Approval of capacity buidling and training program for EE provate sector to facilitate support and participation in EE market
   segments (Yes/No, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                              No                          No                           No                         Yes

    Date                               31-Mar-2017                 10-Sep-2021                  11-Apr-2022                31-Mar-2020

   Comments
   IN01122730
   ►IR Indicator 4.3 - Adoption by EESL managemnet of standardized procurement documents" "Guidelines", SBDs and MOU formats (Yes/No,
   Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target


4/21/2022                                                                                                                    Page 9 of 11
            The World Bank                                                                                     Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)




    Value                              No                          No                            No                        Yes

    Date                               31-Mar-2017                 10-Sep-2021                   11-Apr-2022               31-Mar-2019

                                       The relevant and associated PAP action # 1 has been delayed beyond its deadline of Match 31, 2019.
    Comments


 Disbursement Linked Indicators
 DLI_IND_TABLE
    ►DLI 1 DLI 1- Number of LED bulbs and tube lights sold by EESL under the UJALA program (Output, 66,000,000.00, 54%)

                                                                                                                            Six Months Period
                                                                                                                            ending 31-Mar-2022
                                                                                                                            (Cumulative
                                  Baseline                       Actual (Previous)            Actual (Current)              number)

    Value                         216,000,000.00                 344,348,362.00               351,186,649.00                439,000,000.00

    Date                          --                             10-Sep-2021                  11-Apr-2022                   --
                                  These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                  as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of February
    Comments                      25, 2022.
                                  Additional disbursements of $2,051,486 were approved on April 5, 2022, which haven't been drawn down yet.



    ►DLI 2 DLI 2- Number of energy efficient ceiling fans sold by EESL under the UJALA program (Output, 22,000,000.00, 27%)

                                                                                                                            Six Months Period
                                                                                                                            ending 31-Mar-2022
                                                                                                                            (Cumulative
                                  Baseline                       Actual (Previous)            Actual (Current)              number)

    Value                         590,000.00                     2,215,735.00                 2,300,316.00                  6,410,000.00

    Date                          --                             10-Sep-2021                  11-Apr-2022                   --
                                  These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
                                  as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of February
    Comments                      25, 2022.
                                  Additional disbursements of $328,051 were approved on April 5, 2022, which haven't been drawn down yet.



    ►DLI 3 DLI 3- Number of LED steet lights installed by EESL under the SLNP program (Output, 77,000,000.00, 66%)

                                                                                                                            Six Months Period
                                                                                                                            ending 31-Mar-2022
                                                                                                                            (Cumulative
                                  Baseline                       Actual (Previous)            Actual (Current)              number)

    Value                         2,000,000.00                   7,462,431.00                 9,406,563.00                  9,200,000.00

    Date                          --                             10-Sep-2021                  11-Apr-2022                   --
                                  These results are calculated based on verified results of Disbursement Linked Indicators 1, 2 and 3,
    Comments                      as reported by EESL for the period up to March 31, 2021, through their Results Notification letter of February
                                  25, 2022.



4/21/2022                                                                                                                   Page 10 of 11
            The World Bank                                                                                    Implementation Status & Results Report
            India Energy Efficiency Scale-up Program (P162849)



                                  Additional disbursements of $11,126,254 were approved on April 5, 2022, which haven't been drawn down
                                  yet.



    ►DLI 4 DLI 4- EESL implementation of EE AC sustainability actions (Process, 14,000,000.00, 0%)

                                                                                                                            Six Months Period
                                                                                                                            ending 31-Mar-2022
                                                                                                                            (Cumulative
                                  Baseline                       Actual (Previous)             Actual (Current)             number)

    Value                         No                             Yes                           Yes                           Yes

    Date                          --                             10-Sep-2021                  11-Apr-2022                   --

    Comments


   ►DLI 5 DLI 5- Business model for collaboration with private sector ESCOs in the implementation of EESL's Building EE Program (Output,
   8,000,000.00, 0%)

                                                                                                                            Six Months Period
                                                                                                                            ending 31-Mar-2022
                                                                                                                            (Cumulative
                                  Baseline                       Actual (Previous)             Actual (Current)             number)

    Value                         No                             No                            No                            Yes

    Date                          --                             10-Sep-2021                  11-Apr-2022                   --

    Comments



    ►DLI 6 DLI 6 - Establishment of Sustainable Developmnet Unit (Process, 32,450,000.00, 51%)

                                                                                                                            Six Months Period
                                                                                                                            ending 31-Mar-2022
                                                                                                                            (Cumulative
                                  Baseline                       Actual (Previous)             Actual (Current)             number)

    Value                         No                             No                            No                            Yes

    Date                          --                             10-Sep-2021                  11-Apr-2022                   --
                                  Part (i) of the DLI 6 has been achieved. Hence $16.5 million (of the total $32.45 million) has been disbursed.
    Comments                      Part (ii) of DLI 6 remains to be completed.




4/21/2022                                                                                                                   Page 11 of 11