PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, National Quality Infrastructure Development Project, P 160279 Project Implementation agency: Ministry of Science and Technology Date of the Procurement Plan: March 14, 2017 Period covered by this Procurement Plan: March 29, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Proclamation 649/2009 of the Federal Democratic Republic of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Ethiopia : Ethiopia: National Quality Infrastructure Development Project PLAN General Information Country: Ethiopia 2017-03-21 Bank’s Approval Date of the Original Procurement Plan: 2022-10-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160279 GPN Date: 2017-08-17 Project Name: Ethiopia: National Quality Infrastructure Development Project Loan / Credit No: IDA / 59830, / Ministry of Science and Technology Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-MOST-43007-CW-RFB / La Component 1: Strengthening Single Stage - One E 2020-04-2 boratory and office upgrades IDA / 59830 Institutional Capacity for Nat Post Request for Bids Open - National 2,170,000.00 0.00 Canceled 2019-07-07 2019-07-12 2019-08-23 2019-09-22 2019-10-27 nvelope 4 and refurbishment ional Quality Infrastructure Development GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOST-27858-GO-RFB / Pr Component 1: Strengthening ocurement of office furniture Institutional Capacity for Nat Single Stage - One E IDA / 59830 Post Request for Bids Open - National 250,000.00 493,028.73 Completed 2017-10-31 2017-11-24 2017-11-05 2017-11-24 2017-12-17 2018-03-06 2018-01-16 2018-04-24 2018-02-20 2018-05-10 2018-08-19 2018-05-10 and office equipment for Ethi ional Quality Infrastructure nvelope opian Standards Agency. Development ET-MOST-10798-GO-UN / Pro Component 1: Strengthening UN Agencies (Dire curement of Calibration servi IDA / 59830 Institutional Capacity for Nat Prior Direct 2,300,000.00 0.00 Canceled 2017-03-27 2017-04-06 2017-04-01 2017-09-07 2017-05-06 2017-11-02 ct) ce and other vehicles. ional Quality Infrastructure Development ET-MOST-32012-GO-DIR / pr Component 1: Strengthening ocurement of Software for O Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 180,000.00 0.00 Canceled 2017-10-31 2017-11-05 2017-12-10 2018-06-08 nline Accreditation Applicatio ional Quality Infrastructure n and Accreditation Solution. Development ET-MOST- 10798- GO-UN / C Component 1: Strengthening alibration Service and other IDA / 59830 Institutional Capacity for Nat Prior Direct Selection Direct 2,300,000.00 325,945.50 Completed 2017-03-27 2017-04-01 2017-05-06 2017-11-27 2017-11-02 2017-11-27 Vehicles ional Quality Infrastructure Development ET-MOST-37136-GO-RFQ / Of Component 3: Project Manag Request for Quota Single Stage - One E fice furniture and office equip IDA / 59830 ement and Monitoring and E Post Limited 50,000.00 15,818.73 Completed 2017-11-22 2018-01-02 2018-01-17 2018-03-01 2018-07-16 2018-03-01 tions nvelope ment for NQI-PIU valuation ET-MOST-38417-GO-RFB / Pr ocurement of Inductively Cou Component 1: Strengthening pled Plasma Mass Spectrosco Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 1,000,000.00 379,581.39 Completed 2017-11-29 2018-01-10 2017-12-04 2018-01-15 2018-01-15 2017-03-06 2018-02-14 2018-05-22 2018-03-21 2018-07-19 2018-09-17 2021-05-30 py (ICP-MS), Microwave diges ional Quality Infrastructure l nvelope ter and ION ANALYZER for Et Development hiopian Conformity Assessme nt Enterprise (ECAE). ET-MOST-51048-GO-RFB / Pr Component 1: Strengthening ocurement of calibration equi Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 1,000,000.00 129,594.24 Completed 2018-03-07 2018-03-10 2018-03-12 2018-03-12 2018-04-23 2018-05-23 2018-07-12 2018-06-27 2018-07-25 2018-12-24 2020-06-10 pment in the areas of light, c ional Quality Infrastructure l nvelope olor, time and frequency me Development asurement. ET-MOST-54969-GO-RFB / Pr Component 1: Strengthening ocurement of Measuring equi Institutional Capacity for Nat Open - Internationa Single Stage - One E Under Imple IDA / 59830 Prior Request for Bids 3,000,000.00 4,351,588.46 2018-03-28 2018-09-21 2018-04-02 2018-09-25 2018-05-14 2018-12-21 2018-06-13 2019-05-17 2018-07-18 2019-07-01 2019-01-14 2021-07-13 pment and Standards for Nat ional Quality Infrastructure l nvelope mentation ional Metrology Institute of Et Development hiopia (NMIE) ET-MOST-55451-GO-DIR / Pr Component 1: Strengthening ocurement of spare parts for Institutional Capacity for Nat Maintenance and repair of m IDA / 59830 Prior Direct Selection Direct 20.00 4,475.11 Completed 2018-03-30 2018-04-30 2018-04-04 2018-06-14 2018-05-09 2018-06-27 2018-11-05 2021-06-11 ional Quality Infrastructure ajor test equipment of ECAE f Development rom Toni Technik Baustoffpru fsysteme GMBH ET-MOST-46838-GO-DIR / Pr Component 1: Strengthening ocurement of spare parts for Institutional Capacity for Nat Maintenance and repair of m IDA / 59830 Prior Direct Selection Direct 40,000.00 11,539.61 Completed 2018-03-21 2018-04-30 2018-03-26 2018-06-19 2018-04-30 2018-07-17 2018-10-27 2019-04-25 ional Quality Infrastructure ajor test equipment of ECAE f Development rom Agilent Technologies Int ernational ET-MOST-46941-GO-DIR / Pr Component 1: Strengthening ocurement of spare parts for Institutional Capacity for Nat Maintenance and repair of m IDA / 59830 Prior Direct Selection Direct 40,000.00 5,249.52 Completed 2018-03-21 2018-04-30 2018-03-26 2018-06-19 2018-04-30 2018-09-24 2018-10-27 2020-12-15 ional Quality Infrastructure ajor test equipment of ECAE f Development rom LMT Lichtmesstechnik G mbH ET-MOST-23208-GO-RFB / Pr Component 1: Strengthening Open - Internationa Single Stage - One E ocurement of testing and cali IDA / 59830 Institutional Capacity for Nat Prior Request for Bids 19,840,000.00 0.00 Canceled 2017-10-30 2017-11-04 2017-12-16 2018-01-15 2018-02-19 2018-08-18 l nvelope bration laboratory equipment ional Quality Infrastructure and standards Development ET-MOST-59628-GO-RFB / Pr Component 1: Strengthening ocurement of laboratory equi Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Prior Request for Bids 8,747,000.00 0.00 Canceled 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 2019-02-16 pment for food and agricultur ional Quality Infrastructure l nvelope al product, textile and leathe Development r product testing ET-MOST-62379-GO-RFQ / Pr Component 3: Project Manag Request for Quota Single Stage - One E ocurement of office furniture IDA / 59830 ement and Monitoring and E Post Limited 10,000.00 609.08 Completed 2018-06-04 2018-07-19 2018-07-30 2018-07-25 2019-01-26 2019-08-23 tions nvelope and equipment valuation ET-MOST-63878-GO-RFB / Pr Component 1: Strengthening ocurement of chemical metr Institutional Capacity for Nat Open - Internationa Single Stage - One E Under Imple ology standards and equipm IDA / 59830 Prior Request for Bids 4,000,000.00 1,178,651.74 2018-06-29 2019-04-15 2018-07-04 2019-05-02 2018-08-15 2019-07-15 2018-09-14 2020-02-04 2018-10-19 2020-05-29 2019-04-17 2021-07-15 ional Quality Infrastructure l nvelope mentation ent for National Metrology In Development stitute of Ethiopia (NMIE) ET-MOST-73809-GO-RFQ / Pr Component 1: Strengthening Request for Quota Single Stage - One E ocurement of Canopies For N IDA / 59830 Institutional Capacity for Nat Post Limited 50,000.00 20,697.33 Completed 2018-09-03 2018-11-14 2018-10-29 2019-02-20 2019-04-27 2019-07-02 tions nvelope MIE Calibration vans ional Quality Infrastructure Development ET-MOST-73815-GO-RFB / Pr Component 3: Project Manag Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 1,200,000.00 265,780.63 Completed 2018-08-27 2018-10-17 2018-09-01 2018-10-17 2018-10-13 2018-12-05 2018-11-12 2019-01-10 2018-12-17 2019-02-14 2019-06-15 2021-08-12 ocurement of Vehicles ement and Monitoring and E l nvelope valuation Page 1 ET-MOST-81229-GO-RFB / Pr Component 1: Strengthening ocurement of laboratory equi Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Prior Request for Bids 8,747,000.00 5,074,200.98 Signed 2018-10-12 2018-11-20 2018-10-17 2019-01-03 2018-11-28 2019-02-19 2018-12-28 2019-08-08 2019-02-01 2020-01-31 2019-07-31 2021-05-21 pment for food and agricultur ional Quality Infrastructure l nvelope al product, textile and leathe Development r product testing ET-MOST-117351-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E IDA / 59830 Post Limited 25,000.00 12,008.45 Completed 2019-06-15 2019-08-15 2019-08-10 2019-12-16 2020-02-06 2021-06-11 Procurement of office furnitur ement and Monitoring and E tions nvelope e for PIU valuation ET-MOST-62381-GO-RFQ / Pr Component 1: Strengthening ocurement of assessment art Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 100,000.00 0.00 Canceled 2018-07-05 2018-08-30 2019-02-26 ifacts for Ethiopian National ional Quality Infrastructure tions nvelope Accreditation Office (ENAO) Development ET-MOST-56714-GO-RFB / pr Component 1: Strengthening Request for Quota Open - Internationa Single Stage - One E ocurement of laboratory equi IDA / 59830 Institutional Capacity for Nat Post 87,000.00 0.00 Canceled 2018-04-30 2018-06-25 2018-12-22 tions l nvelope pment for inspection ional Quality Infrastructure Development ET-MOST-132844-GO-DIR / P Component 1: Strengthening rocurement of I solution from Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 30,000.00 5,031.45 Completed 2019-09-12 2019-09-17 2019-09-17 2019-10-15 2019-10-22 2019-12-11 2020-04-19 2021-07-14 International Standard Organ ional Quality Infrastructure ization (ISO) for Ethiopian Sta Development ndards Agency (ESA) ET-MOST-130374-NC-DIR / P Component 1: Strengthening rocurement of spare parts an Institutional Capacity for Nat d repair service of Micro Pipe IDA / 59830 Post Direct Selection Direct 30,000.00 7,124.00 Terminated 2019-09-12 2019-09-16 2019-09-17 2019-10-22 2019-10-22 2019-11-30 2020-04-19 ional Quality Infrastructure tte calibrator from Mettler-To Development ledo for National Metrology I nstitute of Ethiopia (NMIE) ET-MOST-130574-GO-RFB / P Component 1: Strengthening rocurement of Laboratory eq Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Prior Request for Bids 2,260,000.00 6,087,498.90 Signed 2019-09-12 2019-10-31 2019-09-17 2019-11-29 2019-10-29 2020-02-06 2019-11-28 2020-08-31 2020-01-02 2020-11-30 2020-06-30 uipment for Ethiopian Confor ional Quality Infrastructure l nvelope mity Assessment Enterprise ( Development ECAE) ET-MOST-55454-GO-RFQ / Pr Component 1: Strengthening Request for Quota Open - Internationa Single Stage - One E ocurement of Certified Refer IDA / 59830 Institutional Capacity for Nat Post 70,000.00 0.00 Canceled 2018-04-04 2018-05-30 2018-11-26 tions l nvelope ence Material (CRM) for ECAE ional Quality Infrastructure . Development ET-MOST-138924-GO-RFB / P rocurement of training equip Component 2: Enhancing Pri Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 800,000.00 176,379.98 Signed 2019-12-03 2019-12-20 2019-12-08 2019-12-20 2020-01-19 2020-02-21 2020-02-18 2021-06-04 2020-03-24 2021-06-15 2020-09-20 ment for NMIE’s National Equ vate Sector Engagement l nvelope ipment Maintenance Training Center ET-MOST-132847-GO-RFB / P Component 3: Project Manag Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 250,000.00 0.00 Canceled 2019-09-12 2019-09-18 2019-09-17 2019-09-18 2019-10-29 2019-11-28 2020-01-02 2020-06-30 rocurement of Automobiles S ement and Monitoring and E l nvelope edans valuation ET-MOST-147952-GO-RFB / P Component 3: Project Manag Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 250,000.00 148,570.85 Completed 2019-12-06 2020-01-14 2019-12-11 2020-01-15 2020-01-22 2020-02-25 2020-02-21 2020-04-13 2020-03-27 2020-04-13 2020-09-23 2020-06-10 rocurement of Automobile Se ement and Monitoring and E l nvelope dans valuation ET-MOST-118076-GO-RFQ / Component 3: Project Manag Request for Quota Single Stage - One E IDA / 59830 Post Limited 50,000.00 0.00 Canceled 2019-06-16 2019-08-15 2019-08-11 2020-02-07 Procurement of office equip ement and Monitoring and E tions nvelope ment for PIU, valuation ET-MOST-151099-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Procurement of office equip IDA / 59830 Institutional Capacity for Nat Post Open - National 100,000.00 26,312.15 Completed 2020-01-13 2020-03-09 2020-06-01 2020-09-05 2020-12-31 tions nvelope ment for PIU and MoTI NQI fu ional Quality Infrastructure nction Development ET-MOST-149028-GO-RFQ / Component 1: Strengthening Procurement of Electric hoist Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 60,000.00 8,871.00 Terminated 2019-12-25 2020-01-24 2020-02-19 2021-04-21 2020-08-17 , single girder overhead cran ional Quality Infrastructure tions nvelope e system for NMIE heavy ma Development ss/ force laboratory ET-MOST-149039-GO-RFQ / Component 1: Strengthening Procurement of GNSS SYNCH Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 12,000.00 11,950.00 Terminated 2019-12-25 2020-01-17 2020-02-19 2020-12-23 2020-08-17 RONIZED RUBIDIUM TIME AN ional Quality Infrastructure tions nvelope D FREQUENCY STANDARD Development ET-MOST-149041-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Procurement of MULTI-GNSS IDA / 59830 Institutional Capacity for Nat Post Limited 18,000.00 9,382.79 Terminated 2020-01-07 2020-01-17 2020-03-03 2021-01-22 2020-08-30 tions nvelope NTP SERVER ional Quality Infrastructure Development ET-MOST-150441-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Procurement of PRECISION F IDA / 59830 Institutional Capacity for Nat Post Limited 9,000.00 3,674.00 Completed 2020-01-14 2020-01-18 2020-03-10 2020-12-23 2020-09-06 2022-07-26 tions nvelope REQUENCY COUNTER/TIMER ional Quality Infrastructure Development ET-MOST-150442-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Procurement of NTP TIME DIS IDA / 59830 Institutional Capacity for Nat Post Limited 11,000.00 3,726.25 Signed 2020-01-07 2020-01-18 2020-03-03 2021-01-21 2020-08-30 tions nvelope PLAYS ional Quality Infrastructure Development ET-MOST-150443-GO-RFQ / Component 1: Strengthening Procurement of ELECTRONIC Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 6,000.00 1,689.16 Completed 2020-01-14 2020-10-01 2020-03-10 2020-10-22 2020-09-06 2020-12-31 STOPWATCHES / TIMERS and ional Quality Infrastructure tions nvelope mechanical stopwatches Development ET-MOST-150445-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E procurement of LASER INTER IDA / 59830 Institutional Capacity for Nat Post Limited 98,000.00 84,006.63 Terminated 2020-01-14 2020-01-24 2020-03-10 2020-10-26 2020-09-06 tions nvelope FEROMETER SYSTEM ional Quality Infrastructure Development ET-MOST-150446-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E procurement of UNIVERSAL L IDA / 59830 Institutional Capacity for Nat Post Limited 95,000.00 84,315.00 Terminated 2020-01-21 2020-01-24 2020-03-17 2020-10-27 2020-09-13 tions nvelope ENGTH MEASURING SYSTEM ional Quality Infrastructure Development ET-MOST-150448-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E procurement of MEASURING IDA / 59830 Institutional Capacity for Nat Post Limited 65,000.00 27,468.95 Signed 2020-01-14 2020-01-24 2020-03-10 2021-11-10 2020-09-06 tions nvelope MICROSCOPE ional Quality Infrastructure Development ET-MOST-159774-GO-DIR / P Component 1: Strengthening rocurement of verifying mate Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 10,000.00 7,426.61 Completed 2020-02-25 2020-03-27 2020-03-01 2020-03-28 2020-04-05 2020-05-01 2020-10-02 2021-11-02 rial for ION analyzer from AV ional Quality Infrastructure ANT GRADE INC FZCO (ET-M Development OST-159774-GO-DIR) ET-MOST-168606-GO-RFB / P rocurement of Computer, Pri Component 1: Strengthening nter, Server, Network items Institutional Capacity for Nat Open - Internationa Single Stage - One E and related IT equipment for IDA / 59830 Post Request for Bids 300,000.00 387,181.94 Signed 2020-05-22 2020-05-14 2020-05-27 2020-05-15 2020-07-08 2020-07-10 2020-08-07 2020-12-19 2020-09-11 2021-02-24 2021-03-10 ional Quality Infrastructure l nvelope Ethiopian National Accreditat Development ion Office (ENAO) and Ethiopi an Conformity Assessment E nterprise (ECAE) ET-MOST-150447-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E procurement of AUTOMATED IDA / 59830 Institutional Capacity for Nat Post Limited 25,000.00 0.00 Canceled 2020-01-14 2020-01-24 2020-03-10 2020-09-06 tions nvelope SIEVE CALIBRATION SYSTEM ional Quality Infrastructure Development Page 2 ET-MOST-192151-GO-RFB / P Component 1: Strengthening rocurement of Laboratory Eq Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Prior Request for Bids 4,200,000.00 2,429,211.66 Signed 2020-09-30 2021-03-09 2020-10-05 2021-04-01 2020-11-16 2021-06-01 2020-12-16 2022-03-29 2021-01-20 2022-05-09 2021-07-19 uipment for National Metrolo ional Quality Infrastructure l nvelope gy Institute of Ethiopia Development ET-MOST-169628-GO-RFQ / Procurement of original softw Component 1: Strengthening are-based conference room s Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 100,000.00 0.00 Canceled 2020-05-20 2020-07-15 2021-01-11 olution for Online Meetings, T ional Quality Infrastructure tions nvelope raining & Technical Support e Development tc for MoTI, PIU and NQI instit utions; ET-MOST-191493-GO-RFB / P rocurement of on shelf Busin Component 1: Strengthening ess Process Automation Soft Institutional Capacity for Nat Open - Internationa Single Stage - One E ware and IT Office Equipmen IDA / 59830 Post Request for Bids 1,500,000.00 1,657,385.17 Signed 2020-11-16 2020-10-26 2020-11-21 2020-10-27 2021-01-02 2021-03-25 2021-02-01 2021-11-03 2021-03-08 2022-02-28 2021-09-04 ional Quality Infrastructure l nvelope t for Ethiopian Standards Age Development ncy , National Metrology Insti tute of Ethiopia, and Ethiopia n Conformity Assessment Ent erprise ET-MOST-149035-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Procurement of Forklifts for N IDA / 59830 Institutional Capacity for Nat Post Limited 10,000.00 0.00 Canceled 2019-12-25 2020-01-24 2020-02-19 2020-08-17 tions nvelope MIE heavy mass / force labor ional Quality Infrastructure atory Development ET-MOST-200532-GO-DIR / P Component 1: Strengthening rocurement of AUTOMATED S IDA / 59830 Institutional Capacity for Nat Post Direct Selection Direct 25,000.00 0.00 Canceled 2020-11-16 2020-11-21 2020-12-26 2021-06-24 IEVE CALIBRATION SYSTEM ional Quality Infrastructure Development ET-MOST-228354-GO-RFB / P Component 1: Strengthening rocurement of office furnitur Institutional Capacity for Nat Single Stage - One E IDA / 59830 Post Request for Bids Open - National 300,000.00 104,619.70 Signed 2021-04-21 2021-06-17 2021-04-26 2022-01-25 2021-06-07 2022-03-11 2021-07-07 2022-06-06 2021-08-11 2022-06-30 2022-02-07 e and office equipment for Et ional Quality Infrastructure nvelope hiopian National Accreditatio Development n Office (ENAO) ET-MOST-228469-GO-RFB / P rocurement of Digital Out Lat Component 1: Strengthening e IT equipment’s, ID Digitaliz Institutional Capacity for Nat Single Stage - One E IDA / 59830 Post Request for Bids Open - National 125,000.00 131,756.28 Signed 2021-04-30 2021-06-07 2021-05-05 2021-06-13 2021-06-16 2021-08-03 2021-07-16 2022-01-25 2021-08-20 2022-03-15 2022-02-16 ation, professional Software, ional Quality Infrastructure nvelope Digital Barcode System and Development related items for ENAO and E CAE ET-MOST-236223-GO-RFB / P Component 1: Strengthening rocurement of measurement Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 100,000.00 0.00 Canceled 2021-06-15 2021-09-27 2021-06-20 2021-09-28 2021-08-01 2021-03-15 2021-08-31 2022-03-28 2021-10-05 2022-06-15 standards for ENAO to assess ional Quality Infrastructure l nvelope calibration laboratories Development ET-MOST-241465-GO-RFB / P Component 1: Strengthening rocurement of equipment for Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 1,400,000.00 1,073,398.17 Signed 2021-07-07 2021-09-17 2021-07-12 2021-09-21 2021-08-23 2021-11-29 2021-09-22 2022-02-19 2021-10-27 2022-04-18 2022-04-25 NMIE's Equipment Maintenan ional Quality Infrastructure l nvelope ce Training Center Development ET-MOST-265657-GO-RFB / P rocurement of 4 inspection V Component 1: Strengthening ans for Market surveillance in Institutional Capacity for Nat Single Stage - One E IDA / 59830 Post Request for Bids Open - National 350,000.00 108,933.78 Signed 2022-02-17 2022-02-16 2022-02-22 2022-02-16 2022-04-05 2022-03-24 2022-05-05 2022-06-06 2022-06-09 2022-07-14 2022-12-06 spection directorate and Agr ional Quality Infrastructure nvelope icultural import surveillance i Development nspection directorate of MoT RI ET-MOST-276856-GO-RFB / P rocurement of the supply, ins tallation and commissioning Component 1: Strengthening of Router, Distribution/ core / Institutional Capacity for Nat Open - Internationa Single Stage - One E Under Imple IDA / 59830 Post Request for Bids 615,500.00 0.00 2022-02-25 2022-10-03 2022-03-02 2022-10-03 2022-04-13 2022-05-13 2022-06-17 2022-12-14 Aggregate switches, Blade S ional Quality Infrastructure l nvelope mentation ervers, Ms SQL Server 2019 Development Standard, Wireless Access Po ints for data center of NMIE, ECAE and ESA ET-MOST-276891-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Under Imple Procurement of Forklifts for N IDA / 59830 Institutional Capacity for Nat Post Limited 10,000.00 0.00 2022-03-02 2022-09-26 2022-04-27 2022-10-24 tions nvelope mentation MIE heavy mass / force labor ional Quality Infrastructure atory Development ET-MOST-276893-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Under Imple Procurement of MULTI-GNSS IDA / 59830 Institutional Capacity for Nat Post Limited 18,000.00 0.00 2022-03-02 2022-03-30 2022-04-27 2022-10-24 tions nvelope mentation NTP SERVER ional Quality Infrastructure Development ET-MOST-281229-GO-RFB / P Component 1: Strengthening Open - Internationa Single Stage - One E rocurement of Desktop and l IDA / 59830 Institutional Capacity for Nat Post Request for Bids 250,000.00 0.00 Canceled 2022-03-10 2022-03-25 2022-03-15 2022-03-26 2022-04-26 2022-04-29 2022-05-26 2022-07-20 2022-06-30 2022-12-27 l nvelope aptop computer, photocopier ional Quality Infrastructure , scanner Development ET-MOST-281234-GO-DIR / D irect Procurement of addition Component 1: Strengthening al parts and components for Institutional Capacity for Nat Under Imple ICP MS/MS, Xevo-TQ-UHPLC/ IDA / 59830 Post Direct Selection Direct 198,000.00 0.00 2022-03-24 2022-03-20 2022-03-29 2022-03-21 2022-05-03 2022-10-30 ional Quality Infrastructure mentation MS, GC/MS/MS, GC/FID/MS, G Development C FID and Real Time PCR for ECAE supplied by HTDS Inter national ET-MOST-281227-GO-DIR / P Component 1: Strengthening Under Imple rocurement of MET /TEAM co IDA / 59830 Institutional Capacity for Nat Post Direct Selection Direct 10,000.00 0.00 2022-03-17 2022-03-28 2022-03-22 2022-03-30 2022-04-26 2022-10-23 mentation mmerce directly from FLUKE ional Quality Infrastructure corporation Development ET-MOST-280769-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Under Imple Procurement of Automobiles IDA / 59830 Institutional Capacity for Nat Post Limited 95,000.00 0.00 2022-03-20 2022-04-01 2022-05-15 2022-11-11 tions nvelope mentation Sedans and Minibus ional Quality Infrastructure Development ET-MOST-277037-GO-RFQ / Component 1: Strengthening Publication of NQIDP Annual Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 20,000.00 0.00 Canceled 2022-02-26 2022-04-23 2022-10-20 Work and Budget plans, Ann ional Quality Infrastructure tions nvelope ual reports and various cons Development ultant reports ET-MOST-293961-GO-DIR / D Component 1: Strengthening irect Procurement of a Multi- Institutional Capacity for Nat Under Imple Channel Pipette Calibrator (M IDA / 59830 Post Direct Selection Direct 95,000.00 0.00 2022-05-20 2022-06-21 2022-05-25 2022-06-23 2022-06-29 2022-12-26 ional Quality Infrastructure mentation CP) for the Ethiopian Metrolo Development gy Institute (EMI) from Sartor ius ET-MOST-276890-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Procurement of multichannel IDA / 59830 Institutional Capacity for Nat Post Limited 95,000.00 0.00 Canceled 2022-03-02 2022-04-27 2022-10-24 tions nvelope pipette calibrator for NMIE ional Quality Infrastructure Development ET-MOST-298451-GO-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Procurement of Microsoft SQ IDA / 59830 Institutional Capacity for Nat Post Limited 20,000.00 55,524.32 Signed 2022-06-25 2022-06-21 2022-08-20 2022-08-22 2022-12-09 tions nvelope L 2019 and Microsoft Server ional Quality Infrastructure 2019 Development Page 3 ET-MOST-298295-GO-DIR / D Component 1: Strengthening irect procurement of data ce Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 65,000.00 0.00 Canceled 2022-06-22 2022-06-27 2022-08-01 2022-12-02 nter components and parts fr ional Quality Infrastructure om Del corporation Development ET-MOST-297016-GO-DIR / D Component 1: Strengthening irect procurement of overhea IDA / 59830 Institutional Capacity for Nat Post Direct Selection Direct 15,000.00 40,000.00 Signed 2022-06-28 2022-06-30 2022-06-30 2022-07-07 2022-07-17 2022-08-18 2022-10-20 d crane for the force laborato ional Quality Infrastructure ry from CCCC. Development ET-MOST-298294-GO-DIR / D Component 1: Strengthening irect Procurement of NMIE la IDA / 59830 Institutional Capacity for Nat Post Direct Selection Direct 300,000.00 0.00 Canceled 2022-06-28 2022-06-30 2022-07-03 2022-07-07 2022-08-07 2022-12-10 boratory furniture from CCCC ional Quality Infrastructure Development ET-MOST-312965-GO-RFQ / Component 1: Strengthening Procurement of Computers, p Institutional Capacity for Nat Request for Quota Single Stage - One E Pending Impl rinters, photocopier, scanner IDA / 59830 Post Limited 95,000.00 0.00 2022-09-20 2022-11-01 2023-03-01 ional Quality Infrastructure tions nvelope ementation and LCD to MoTRI. and Ethio Development pian Accreditation office ET-MOST-313207-GO-DIR / P Component 1: Strengthening rocurement of variation work Institutional Capacity for Nat Direct - Internation Pending Impl IDA / 59830 Post Direct Selection 25,000.00 0.00 2022-09-15 2022-09-20 2022-10-25 2023-04-23 s for data center developmen ional Quality Infrastructure al ementation t directly from IE network sol Development ution NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOST-87778-NC-DIR / Su Component 1: Strengthening pport the laboratory testing f Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 74,000.00 110,507.04 Completed 2019-02-28 2019-02-20 2019-03-05 2019-02-22 2019-04-09 2019-04-02 2019-10-06 2021-01-27 or essential parameters for E ional Quality Infrastructure SA standards development Development ET-MOST-109114-NC-RFQ / Component 1: Strengthening Request for Quota Single Stage - One E Recruitment of a firm for the IDA / 59830 Institutional Capacity for Nat Post Limited 30,000.00 1,828.86 Completed 2019-04-16 2019-05-30 2019-06-11 2019-08-30 2019-12-08 2019-12-11 tions nvelope printing of publication materi ional Quality Infrastructure als Development ET-MOST-109118-NC-RFQ / Component 1: Strengthening Recruitment of a firm for the Institutional Capacity for Nat Request for Quota Single Stage - One E production and broadcast of IDA / 59830 Post Limited 95,000.00 22,735.78 Signed 2019-04-16 2019-09-19 2019-06-11 2019-12-27 2019-12-08 2021-05-01 ional Quality Infrastructure tions nvelope TV Panel Discussion, Docume Development ntary Film and advertising TV and Radio Spot ET-MOST-51047-NC-DIR / Su Component 1: Strengthening pport the laboratory testing f Institutional Capacity for Nat Request for Quota Open - Internationa Single Stage - One E IDA / 59830 Post 74,000.00 0.00 Canceled 2018-03-26 2018-05-21 2018-11-17 or essential parameters for E ional Quality Infrastructure tions l nvelope SA standards development. Development ET-MOST-60289-NC-RFQ / D Component 1: Strengthening Request for Quota Open - Internationa Single Stage - One E emonstrating traceablity thro IDA / 59830 Institutional Capacity for Nat Post 30,000.00 0.00 Canceled 2018-05-28 2018-07-23 2019-01-19 tions l nvelope ugh Proficiency Testing (PT) ional Quality Infrastructure Participation. Development ET-MOST-132877-NC-RFQ / S Component 2: Enhancing Pri Request for Quota Single Stage - One E upport Testing and Analysis s IDA / 59830 Post Limited 25,000.00 71.18 Terminated 2019-09-24 2020-11-24 2019-11-19 2020-12-25 2020-05-17 vate Sector Engagement tions nvelope ervice of Sugar content (C4) of honey. ET-MOST-132865-NC-RFQ / P rocurement of calibration ser vice for Leather Industry Dev Component 2: Enhancing Pri Request for Quota Single Stage - One E IDA / 59830 Post Limited 40,000.00 0.00 Canceled 2019-09-24 2019-10-22 2019-11-19 2020-05-17 elopment Institute (LIDI) testi vate Sector Engagement tions nvelope ng equipment by an accredit ed calibration laboratory or N MI ET-MOST-166812-NC-DIR / D emonstrating traceablity of LI Component 2: Enhancing Pri IDA / 59830 Post Direct Selection Direct 50,000.00 2,693.24 Completed 2020-04-10 2020-05-02 2020-04-15 2020-05-06 2020-05-20 2020-07-11 2020-11-16 2021-08-05 DI testing labs through Profic vate Sector Engagement iency Testing (PT) Participati on. ET-MOST-181651-NC-RFQ / P rocurement of calibration ser Component 2: Enhancing Pri Request for Quota Single Stage - One E IDA / 59830 Post Limited 90,000.00 0.00 Canceled 2020-09-20 2020-10-13 2020-11-15 2021-05-14 vice for textile testing labs u vate Sector Engagement tions nvelope nder the support of the proje ct ET-MOST-182085-NC-RFQ / P Component 2: Enhancing Pri Request for Quota Single Stage - One E rocurement of Proficiency Te IDA / 59830 Post Limited 50,000.00 6,325.76 Signed 2020-09-27 2020-11-16 2020-11-22 2021-07-26 2021-05-21 2022-05-30 vate Sector Engagement tions nvelope sting Service for textile testi ng labs ET-MOST-166810-NC-DIR / P rocurement of calibration ser Component 3: Project Manag vice for Leather Industry Dev IDA / 59830 ement and Monitoring and E Post Direct Selection Direct 40,000.00 0.00 Canceled 2020-04-03 2020-05-02 2020-05-13 2020-05-06 2020-06-17 2020-12-14 elopment Institute (LIDI) testi valuation ng equipment by an accredit ed calibration laboratory or N MI ET-MOST-181630-NC-DIR / P Component 2: Enhancing Pri rocurement of Proficiency Te IDA / 59830 Post Direct Selection Direct 50,000.00 10,024.90 Completed 2020-10-13 2020-10-12 2020-10-18 2020-10-20 2020-11-22 2021-07-08 2021-05-21 2022-05-17 vate Sector Engagement sting Service for honey testin g labs ET-MOST-196417-NC-RFQ / P roduction and broadcast of T Component 1: Strengthening V Panel Discussion, Documen Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 35,000.00 19,734.42 Completed 2020-10-23 2020-10-27 2020-12-18 2021-01-25 2021-06-16 2022-03-31 tary Film, advertising TV and ional Quality Infrastructure tions nvelope Radio Spot and developing Development Magazine for Ethiopian Natio nal Accreditation Office (ENA O) ET-MOST-201349-NC-RFQ / E thiopian Conformity Assessm Component 1: Strengthening ent Enterprise (ECAE’s) Servi Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 70,000.00 18,829.94 Signed 2020-11-21 2021-07-16 2021-01-16 2021-07-27 2021-07-15 2022-07-29 ce Publicity through TV Panel ional Quality Infrastructure tions nvelope Discussion, Documentary Fil Development m and advertising TV and Ra dio Spot ET-MOST-204258-NC-RFB / p rocurement of supply installa tion and commissioning of se Component 1: Strengthening parate Datacenter solution fo Institutional Capacity for Nat Open - Internationa Single Stage - One E IDA / 59830 Post Request for Bids 1,400,000.00 1,050,441.02 Signed 2020-11-30 2021-01-11 2020-12-05 2021-01-20 2021-01-16 2021-05-06 2021-02-15 2022-01-17 2021-03-22 2022-03-31 2021-09-18 r Ethiopia Conformity Assess ional Quality Infrastructure l nvelope ment Enterprise (ECAE) Natio Development nal Metrology Institute of Ethi opia (NMIE) and Ethiopian St andard Agency (ESA) Page 4 ET-MOST-208115-NC-RFQ / P Component 3: Project Manag ublication of NQIDP Annual W Request for Quota Single Stage - One E IDA / 59830 ement and Monitoring and E Post Limited 3,000.00 32,524.32 Completed 2020-12-20 2021-07-08 2021-02-14 2021-11-04 2021-08-13 2022-02-16 ork and Budget plans, Annual tions nvelope valuation reports and various consulta nt reports ET-MOST-201359-NC-RFQ / Component 1: Strengthening Design, Produce and develop Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 20,000.00 18,875.61 Completed 2020-11-22 2021-03-30 2021-01-17 2021-05-26 2021-07-16 2022-02-28 Magazine for Ethiopian Natio ional Quality Infrastructure tions nvelope nal Accreditation Office (ENA Development O) ET-MOST-200534-NC-RFQ / E thiopian Conformity Assessm Component 1: Strengthening ent Enterprise (ECAE’s) Servi Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 70,000.00 0.00 Canceled 2020-11-30 2021-01-25 2021-07-24 ce Publicity through TV Panel ional Quality Infrastructure tions nvelope Discussion, Documentary Fil Development m and advertising TV and Ra dio Spot ET-MOST-215586-NC-RFB / T raining on inspection of textil Component 2: Enhancing Pri Open - Internationa Single Stage - One E es, garments, leather and lea IDA / 59830 Post Request for Bids 100,000.00 39,905.00 Completed 2021-02-04 2021-03-01 2021-02-09 2021-07-18 2021-03-23 2021-09-08 2021-04-22 2021-09-09 2021-05-27 2021-10-08 2021-11-23 2022-02-23 vate Sector Engagement l nvelope ther products (including foot wear), honey, fruit and veget ables for inspection bodies ET-MOST-228483-NC-RFQ / P rocurement of Calibration Ser Component 2: Enhancing Pri Request for Quota Open - Internationa Single Stage - One E IDA / 59830 Post 25,000.00 10,992.31 Completed 2021-04-17 2021-06-12 2021-10-12 2021-12-09 2022-05-09 vice for textile and leather te vate Sector Engagement tions l nvelope sting labs under the support of NQI project ET-MOST-241467-NC-RFQ / T Component 3: Project Manag Request for Quota Single Stage - One E esting & Analysis Service of S IDA / 59830 ement and Monitoring and E Post Limited 75,000.00 2,717.09 Completed 2021-07-21 2021-08-25 2021-09-15 2021-10-13 2022-03-14 2021-11-16 tions nvelope ugar Content (C4) of Honey valuation ET-MOST-265877-NC-RFQ / P Component 1: Strengthening roduction and broadcast of T Institutional Capacity for Nat Request for Quota Single Stage - One E Under Imple IDA / 59830 Post Limited 20,000.00 0.00 2022-01-05 2022-04-01 2022-03-02 2022-08-29 V Panel Discussion, Documen ional Quality Infrastructure tions nvelope mentation tary Film, advertising TV and Development Radio spot for MoTI ET-MOST-208117-NC-RFQ / Component 1: Strengthening Measurement traceability of Institutional Capacity for Nat Request for Quota Single Stage - One E IDA / 59830 Post Limited 50,000.00 0.00 Canceled 2020-12-27 2021-02-09 2021-02-21 2021-08-20 NMIE Equipment and Standar ional Quality Infrastructure tions nvelope ds by recognized National M Development etrology Institutes ET-MOST-276880-NC-RFQ / Recruitment of a certification body to certify selected priva Component 2: Enhancing Pri Request for Quota Single Stage - One E Under Imple te firms in Ethiopia against B IDA / 59830 Post Limited 95,000.00 0.00 2022-03-02 2022-09-21 2022-04-27 2022-10-24 vate Sector Engagement tions nvelope mentation usiness Social Compliance Ini tiative (BSCI) and Worldwide Responsible Accredited Prod uction (WRAP) ET-MOST-276884-NC-RFQ / Recruitment of a certification body to certify selected priva Component 2: Enhancing Pri Request for Quota Single Stage - One E IDA / 59830 Post Limited 60,000.00 6,322.76 Completed 2022-03-02 2022-05-30 2022-04-27 2022-07-27 2022-10-24 2022-08-31 te firms in Ethiopia against S vate Sector Engagement tions nvelope ustainable Textile Production (STeP) By OEKO-TEX and OE KO-TEX 100 ET-MOST-276887-NC-RFQ / Recruitment of a certification Component 2: Enhancing Pri Request for Quota Single Stage - One E Under Imple body to certify selected priva IDA / 59830 Post Limited 20,000.00 0.00 2022-03-02 2022-04-27 2022-10-24 vate Sector Engagement tions nvelope mentation te firms in Ethiopia against L eather Working Group (LWG) ET-MOST-276886-NC-RFQ / Recruitment of a certification Component 2: Enhancing Pri Request for Quota Single Stage - One E Under Imple body to certify selected priva IDA / 59830 Post Limited 60,000.00 0.00 2022-03-02 2022-04-27 2022-10-24 vate Sector Engagement tions nvelope mentation te firms in Ethiopia against C ertification of Better Cotton I nitiative (BCI) ET-MOST-281236-NC-RFQ / P Component 3: Project Manag ublication of NQIDP Annual W Request for Quota Single Stage - One E Under Imple IDA / 59830 ement and Monitoring and E Post Limited 20,000.00 0.00 2022-03-21 2022-05-16 2022-11-12 ork and Budget plans, Annual tions nvelope mentation valuation reports and various consulta nt reports ET-MOST-280766-NC-RFQ / Recruitment of a certification Component 2: Enhancing Pri Request for Quota Single Stage - One E Under Imple body to certify selected priva IDA / 59830 Post Limited 150,000.00 0.00 2022-03-22 2022-06-02 2022-11-29 vate Sector Engagement tions nvelope mentation te firms in Ethiopia against IS O 22000, HACCP, and BRC ET-MOST-280768-NC-RFQ / Recruitment of a certification Component 2: Enhancing Pri Request for Quota Single Stage - One E Under Imple IDA / 59830 Post Limited 350,000.00 0.00 2022-03-20 2022-05-31 2022-11-27 body to certify selected priva vate Sector Engagement tions nvelope mentation te firms in Ethiopia against IS O 9001, and ISO 14001 ET-MOST-265499-NC-RFQ / P Component 1: Strengthening rocurement of National stan Institutional Capacity for Nat Request for Quota Single Stage - One E dards in textile, leather and a IDA / 59830 Post Limited 45,000.00 0.00 Canceled 2022-01-04 2022-03-01 2022-08-28 ional Quality Infrastructure tions nvelope gro processing sector from ot Development her National Standard Bodies (NSBs) ET-MOST-312963-NC-DIR / L Component 1: Strengthening ength and pressure measure Institutional Capacity for Nat Direct - Internation Pending Impl IDA / 59830 Post Direct Selection 20,000.00 0.00 2022-09-14 2022-09-19 2022-10-18 2023-02-15 ment traceability through Ge ional Quality Infrastructure al ementation rman Metrology Institute (PT Development B) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOST-23186-CS-CQS / co Component 1: Strengthening nsultancy services for design Institutional Capacity for Nat Consultant Qualifi IDA / 59830 Post Open - National 30,000.00 29,226.76 Completed 2017-07-31 2017-08-16 2017-08-21 2017-08-22 2017-10-04 2018-01-12 2017-11-03 2018-07-06 2017-12-08 2018-07-18 2018-06-06 2019-04-09 and supervision of laboratory ional Quality Infrastructure cation Selection and office refurbishment of N Development MIE ET-MOST-31495-CS-CQS / Re Component 1: Strengthening cruitment of a consulting fir Institutional Capacity for Nat Consultant Qualifi Open - Internationa m to improve the Information IDA / 59830 Post 100,000.00 84,080.93 Completed 2017-10-10 2017-12-01 2017-10-31 2017-12-06 2017-12-14 2018-02-19 2018-01-13 2018-08-01 2018-02-17 2018-08-06 2018-08-16 2019-06-19 ional Quality Infrastructure cation Selection l and Communication Technol Development ogy (ICT) infrastructure of NQ I institutions. Page 5 ET-MOST-32015-CS-CQS / Re cruitment of a consulting fir Component 1: Strengthening m for Green building Constru Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 200,000.00 0.00 Canceled 2017-10-31 2017-11-21 2018-01-04 2018-02-03 2018-03-10 2018-09-06 ction design (layout and spec ional Quality Infrastructure cation Selection l ifications) of establishment o Development f new agro processing testin g laboratory. ET-MOST-43978-CS-LCS / Re Component 3: Project Manag Least Cost Selecti IDA / 59830 Post Open - National 10,000.00 1,816.41 Completed 2018-01-22 2018-02-16 2018-02-12 2018-03-28 2018-03-06 2018-04-25 2018-05-25 2018-06-20 2018-06-29 2018-06-20 2018-08-03 2018-07-02 2019-01-30 2020-12-08 cruitment of external auditor ement and Monitoring and E on valuation ET-MOST-21710-CS-UN / Pro curement of individual consul Component 1: Strengthening tants for the Preparation of t Institutional Capacity for Nat UN Agencies (Dire IDA / 59830 Prior Direct 75,000.00 0.00 Canceled 2017-09-02 2018-03-01 echnical equipment specifica ional Quality Infrastructure ct) tion for food and agro, inspec Development tion, textile and leather testi ng labs of ECAE ET-MOST-60833-CS-CQS / Re cruitment of a consulting fir Component 2: Enhancing Pri Consultant Qualifi Open - Internationa IDA / 59830 Post 75,000.00 169,275.00 Completed 2018-05-04 2018-05-21 2018-05-25 2018-05-22 2018-07-08 2018-07-31 2018-08-07 2018-12-10 2018-09-11 2018-12-10 2019-03-10 2020-03-26 m to carry out a baseline and vate Sector Engagement cation Selection l client engagement survey. ET-MOST-43011-CS-CQS / Co nsultancy service for the Esta Component 1: Strengthening blishment of internationally r Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 170,000.00 0.00 Canceled 2018-09-11 2018-03-27 2018-10-02 2018-03-27 2018-11-15 2018-12-15 2019-01-19 2019-07-18 ecognized or accredited food ional Quality Infrastructure cation Selection l safety management system Development certification for food agro pro cessing sector. ET-MOST-43014-CS-CQS / Co nsultancy service for the Esta Component 1: Strengthening blishment of internationally r Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 70,000.00 0.00 Canceled 2018-09-11 2018-03-27 2018-10-02 2018-03-27 2018-11-15 2018-12-15 2019-01-19 2019-07-18 ecognized or accredited, envi ional Quality Infrastructure cation Selection l ronmental, management syst Development em certification for textile an d leather sector . ET-MOST-43022-CS-CQS / Co Component 1: Strengthening nsultancy service to develop Institutional Capacity for Nat Consultant Qualifi Open - Internationa a long-term business plan an IDA / 59830 Post 50,000.00 0.00 Canceled 2018-10-01 2018-03-30 2018-10-22 2018-03-30 2018-12-05 2019-01-04 2019-02-08 2019-08-07 ional Quality Infrastructure cation Selection l d proposal for financial fundi Development ng for equipment and infrastr ucture ET-MOST-69291-CS-CQS / Re Component 1: Strengthening Consultant Qualifi Open - Internationa cruitment of consulting firm f IDA / 59830 Institutional Capacity for Nat Post 100,000.00 97,904.57 Completed 2018-07-19 2018-08-15 2018-08-09 2018-08-21 2018-09-22 2019-03-01 2018-10-22 2019-04-01 2018-11-26 2019-04-01 2019-05-25 2019-10-09 cation Selection l or standards need assessme ional Quality Infrastructure nt survey Development ET-MOST-37071-CS-CQS / Co Component 1: Strengthening nsultancy service for the dev Institutional Capacity for Nat Consultant Qualifi Open - Internationa elopment and installation of IDA / 59830 Post 180,000.00 0.00 Canceled 2017-11-16 2018-01-01 2017-12-07 2018-01-03 2018-01-20 2018-02-10 2018-02-19 2018-03-26 2018-09-22 ional Quality Infrastructure cation Selection l software for online accreditat Development ion application and accredita tion solution of ENAO ET-MOST-27862-CS-CQS / Re Component 1: Strengthening Consultant Qualifi cruitment of local consultant IDA / 59830 Institutional Capacity for Nat Post Open - National 30,000.00 0.00 Canceled 2017-09-30 2017-10-12 2017-10-21 2017-11-02 2017-12-04 2018-01-31 2018-01-03 2018-02-07 2018-08-06 cation Selection s for standards need assess ional Quality Infrastructure ment survey Development ET-MOST-69935-CS-CQS / Re cruitment of a consulting fir Component 1: Strengthening m to develop a long-term bu Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 100,000.00 183,907.69 Completed 2018-07-24 2018-09-04 2018-08-14 2018-09-26 2018-09-27 2019-02-05 2018-10-27 2019-04-08 2018-12-01 2019-04-16 2019-05-30 2020-03-26 siness plan and proposal for f ional Quality Infrastructure cation Selection l inancial funding for equipme Development nt and infrastructure for ECA E ET-MOST-60652-CS-CQS / co Component 1: Strengthening nsultancy service for upgradi Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 120,000.00 113,761.51 Completed 2018-05-21 2018-08-24 2018-06-11 2018-10-05 2018-07-25 2019-05-13 2018-08-24 2019-10-28 2018-09-28 2019-10-30 2019-03-27 2021-08-02 ng of mechanical, electrical ional Quality Infrastructure cation Selection l and electronic workshop skill Development s development ET-MOST-73979-CS-QCBS / Recruitment of a consulting fi Component 1: Strengthening rm to support for the develop Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 180,000.00 207,000.00 Signed 2018-08-22 2018-08-24 2018-09-12 2018-10-12 2018-10-26 2019-03-01 2018-11-23 2019-10-22 2018-12-23 2019-10-22 2019-01-27 2019-10-22 2019-03-03 2019-10-07 2020-03-02 ment and installation of soft ional Quality Infrastructure Based Selection l ware for online accreditation Development application and accreditation solution of ENAO. ET-MOST-68549-CS-CQS / Re cruitment of a consulting fir Component 1: Strengthening m for the Establishment of in Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 70,000.00 0.00 Canceled 2018-07-14 2018-07-17 2018-07-21 2018-08-15 2018-09-03 2018-10-03 2018-11-07 2019-05-06 ternationally recognized or a ional Quality Infrastructure cation Selection l ccredited, environmental, ma Development nagement system certificatio n for textile and leather sect or. ET-MOST-68548-CS-CQS / Re cruitment of a consulting fir Component 1: Strengthening m for the Establishment of in Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 170,000.00 0.00 Canceled 2018-07-14 2018-07-18 2018-07-21 2018-08-15 2018-09-03 2018-10-03 2018-11-07 2019-05-06 ternationally recognized or a ional Quality Infrastructure cation Selection l ccredited food safety manag Development ement system certification fo r food agro processing sector .. ET-MOST-88794-CS-QCBS / Recruitment of a consulting fi Component 1: Strengthening rm to support selected privat Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 200,000.00 241,566.13 Completed 2018-12-07 2018-12-20 2018-12-28 2018-12-31 2019-02-10 2019-03-01 2019-03-10 2019-08-15 2019-04-09 2019-08-15 2019-05-14 2019-08-26 2019-06-18 2019-10-10 2020-06-17 2022-08-26 e and public calibration labor ional Quality Infrastructure Based Selection l atories in Ethiopia for interna Development tional accreditation as per IS O/IEC 17025:2017 ET-MOST-55464-CS-QCBS / S cope expansion in Inspection Component 1: Strengthening accreditation sub scopes of f Institutional Capacity for Nat Quality And Cost- Open - Internationa ood, vehicle, pharmaceutical IDA / 59830 Prior 750,000.00 0.00 Canceled 2018-06-01 2018-06-29 2018-06-22 2018-07-30 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 ional Quality Infrastructure Based Selection l products ,abattoirs, construc Development tion, textile and leather, carg o ,labor, mechanical equipme nt, and lift (ENAO), ET-MOST-55470-CS-QCBS / S cope expansion in Certificati Component 1: Strengthening on accreditation sub scopes Institutional Capacity for Nat Quality And Cost- Open - Internationa of Food Safety Management IDA / 59830 Prior 1,000,000.00 0.00 Canceled 2018-07-01 2018-08-20 2018-07-22 2018-08-28 2018-09-04 2018-10-02 2018-11-01 2018-12-06 2019-01-10 2020-01-10 ional Quality Infrastructure Based Selection l System (FSMS), Environment Development al Management System (EMS ) and sub scopes of product f or ENAO Page 6 ET-MOST-89912-CS-QCBS / Recruitment of a consulting fi Component 1: Strengthening rm to support selected privat Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 300,000.00 448,580.50 Completed 2018-12-21 2019-01-15 2019-01-11 2019-02-20 2019-02-24 2019-07-25 2019-03-24 2019-09-06 2019-04-23 2019-11-08 2019-05-28 2019-12-10 2019-07-02 2020-01-24 2020-07-01 2021-11-01 e testing laboratories in Ethio ional Quality Infrastructure Based Selection l pia for international accredit Development ation as per ISO/IEC 17025:2 017 ET-MOST-93431-CS-QCBS / Recruitment of a consulting fi rm for the Preparation of an Component 3: Project Manag Environmental and Social Im Quality And Cost- Open - Internationa IDA / 59830 ement and Monitoring and E Post 120,000.00 97,993.22 Completed 2019-01-15 2019-01-08 2019-02-05 2019-01-11 2019-03-21 2019-04-03 2019-04-18 2019-05-03 2019-05-18 2020-01-13 2019-06-22 2019-06-10 2019-07-27 2019-07-05 2020-07-26 2019-11-19 pact Assessment (ESIA) for N Based Selection l valuation ational Metrology Institute of Ethiopia (NMIE) and Ethiopia n Conformity Assessment Ent erprise (ECAE) ET-MOST-69934-CS-QCBS / Recruitment of a consulting fi rm for ENAO Component 1: Strengthening Assessor training in selected Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 250,000.00 0.00 Canceled 2018-08-16 2018-09-04 2018-09-06 2018-10-03 2018-10-20 2018-11-17 2018-12-17 2019-01-21 2019-02-25 2020-02-25 fields of ISO/IEC 17025 ional Quality Infrastructure Based Selection l Traceability, flexible scope, v Development alidation and verification, pro ficiency testing ET-MOST-51019-CS-CQS / Re cruitment of a consulting fir Component 2: Enhancing Pri Consultant Qualifi Open - Internationa m for industry needs assess IDA / 59830 Prior 250,000.00 0.00 Canceled 2018-03-07 2018-03-20 2018-03-28 2018-04-10 2018-05-11 2018-08-10 2018-06-10 2018-07-15 2019-01-11 vate Sector Engagement cation Selection l ment (TA to industry and Priv ate NQI service providers) ET-MOST-105555-CS-CQS / R ecruitment of a consulting fir Component 2: Enhancing Pri Consultant Qualifi Open - Internationa m for industry needs assess IDA / 59830 Post 250,000.00 250.00 Completed 2019-03-15 2019-03-15 2019-04-05 2019-05-19 2019-03-20 2019-06-18 2019-03-20 2019-07-23 2019-03-01 2020-01-19 2019-10-25 vate Sector Engagement cation Selection l ment (TA to industry and Priv ate NQI service providers) ET-MOST-55466-CS-QCBS / S Component 1: Strengthening cope expansion testing sub s Institutional Capacity for Nat Quality And Cost- Open - Internationa copes of Forensic testing, Bio IDA / 59830 Prior 750,000.00 0.00 Canceled 2018-07-01 2018-07-22 2018-09-04 2018-10-02 2018-11-01 2018-12-06 2019-01-10 2020-01-10 ional Quality Infrastructure Based Selection l technology labs, radiation lab Development s, calibration and verification labs (ENAO) ET-MOST-43015-CS-CQS / Co nsultancy service for the Esta Component 1: Strengthening blishment of internationally r Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 60,000.00 0.00 Canceled 2018-09-11 2018-10-02 2018-11-15 2018-12-15 2019-01-19 2019-07-18 ecognized or accredited occu ional Quality Infrastructure cation Selection l pational, health and safety m Development anagement system certificati on for textile and leather sec tor ET-MOST-43016-CS-CQS / Co nsultancy service for the Esta Component 1: Strengthening blishment of internationally r Institutional Capacity for Nat Consultant Qualifi Open - Internationa IDA / 59830 Post 270,000.00 0.00 Canceled 2018-09-11 2018-10-02 2018-11-15 2018-12-15 2019-01-19 2019-07-18 ecognized or accredited Prod ional Quality Infrastructure cation Selection l uct certification system- in f Development ood and agro-processing sect or ET-MOST-43019-CS-CQS / Co Component 1: Strengthening nsultancy service for the Esta Institutional Capacity for Nat Consultant Qualifi Open - Internationa blishment of internationally r IDA / 59830 Post 250,000.00 0.00 Canceled 2018-09-11 2018-10-02 2018-11-15 2018-12-15 2019-01-19 2019-07-18 ional Quality Infrastructure cation Selection l ecognized or accredited Prod Development uct certification system- in te xtile sector ET-MOST-43021-CS-CQS / Co Component 1: Strengthening nsultancy service for the Esta Institutional Capacity for Nat Consultant Qualifi Open - Internationa blishment of internationally r IDA / 59830 Post 180,000.00 0.00 Canceled 2018-09-11 2018-10-02 2018-11-15 2018-12-15 2019-01-19 2019-07-18 ional Quality Infrastructure cation Selection l ecognized or accredited Prod Development uct certification system- in l eather sector ET-MOST-126948-CS-QCBS / Consultancy Services for Pre paration of an Environmental Component 1: Strengthening and Social Impact Assessmen Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 120,000.00 23,516.91 Completed 2019-08-19 2019-08-19 2019-09-09 2019-08-23 2019-10-23 2019-11-12 2019-11-20 2019-12-06 2019-12-20 2020-02-28 2020-01-24 2020-03-19 2020-02-28 2020-04-10 2021-02-27 2020-10-30 t (ESIA) for Design and Cons ional Quality Infrastructure Based Selection l truction and Operation of NM Development IE laboratories; ECAE, ENAO and ERPA offices; and Custo mer Property Stores ET-MOST-128130-CS-QCBS / Component 1: Strengthening Recruitment of a consulting fi Institutional Capacity for Nat Quality And Cost- Open - Internationa rm to assess needs for Natio IDA / 59830 Post 120,000.00 0.00 Canceled 2019-08-27 2019-09-11 2019-09-17 2019-09-24 2019-10-31 2019-12-24 2019-11-28 2020-01-28 2019-12-28 2020-03-03 2020-02-01 2020-04-13 2020-03-07 2021-03-07 ional Quality Infrastructure Based Selection l nal Quality Infrastructure (NQ Development I) curriculum in universities ET-MOST-128075-CS-QCBS / Expansion of Accreditation sc Component 1: Strengthening ope and Training & capacity Institutional Capacity for Nat Quality And Cost- Open - Internationa building programme of Ethio IDA / 59830 Prior 500,000.00 630,559.00 Signed 2019-09-11 2019-09-25 2019-10-02 2019-09-29 2019-11-15 2020-02-19 2019-12-13 2020-04-27 2020-01-12 2020-11-09 2020-02-16 2021-05-18 2020-03-22 2021-05-31 2021-03-22 ional Quality Infrastructure Based Selection l pian Conformity Assessment Development Enterprise (ECAE) through co ntractual arrangement with i nternationally recognised CA Bs ET-MOST-60300-CS-CQS / Pr Component 3: Project Manag eparation of equipment tech Consultant Qualifi Open - Internationa IDA / 59830 ement and Monitoring and E Post 120,000.00 0.00 Canceled 2018-05-24 2018-09-14 2018-06-14 2018-09-18 2018-07-28 2018-08-27 2018-10-01 2019-03-30 nical specification for Nation cation Selection l valuation al Equipment Training Center ET-MOST-42088-CS-QCBS / Recruitment of a consulting fi Component 1: Strengthening rm for Green building Constr Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 200,000.00 0.00 Canceled 2018-01-03 2018-02-16 2018-01-24 2018-02-24 2018-03-09 2018-05-04 2018-04-06 2018-05-06 2018-06-10 2018-07-15 2019-07-15 uction design (layout and spe ional Quality Infrastructure Based Selection l cifications) of establishment Development of new agro processing testin g laboratory. ET-MOST-130583-CS-QCBS / Component 1: Strengthening Develop National Standards Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 125,000.00 0.00 Canceled 2019-09-12 2019-09-16 2019-10-03 2019-11-01 2019-11-16 2019-12-14 2020-01-13 2020-02-17 2020-03-23 2021-03-23 Detail implementation busine ional Quality Infrastructure Based Selection l ss plan for Ethiopian Standar Development ds Agency ET-MOST-167395-CS-QCBS / Component 3: Project Manag Recruitment of a consulting fi Quality And Cost- Open - Internationa IDA / 59830 ement and Monitoring and E Post 10,000.00 56,470.76 Completed 2020-04-13 2020-05-02 2020-05-04 2020-05-24 2020-06-17 2020-10-06 2020-07-15 2020-11-16 2020-08-14 2021-01-22 2020-09-18 2021-03-27 2020-10-23 2021-04-27 2021-10-23 2022-05-26 rm for Gender Mainstreaming Based Selection l valuation Guideline Development Page 7 ET-MOST-168414-CS-QCBS / Component 1: Strengthening Recruitment of a consulting fi Institutional Capacity for Nat Quality And Cost- Open - Internationa Under Implement rm to assess needs for Natio IDA / 59830 Post 120,000.00 0.00 2020-04-30 2020-05-02 2020-05-21 2020-05-24 2020-07-04 2020-10-06 2020-08-01 2020-11-17 2020-08-31 2021-02-23 2020-10-05 2022-01-18 2020-11-09 2021-11-09 ional Quality Infrastructure Based Selection l ation nal Quality Infrastructure (NQ Development I) curriculum in universities ET-MOST-144279-CS-QCBS / Training and technical assist Component 1: Strengthening ance for Ethiopian Standards Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 350,000.00 0.00 Canceled 2019-11-19 2019-11-29 2019-12-10 2019-12-04 2020-01-23 2020-02-20 2020-03-21 2020-04-25 2020-05-30 2021-05-30 Agency (ESA) through Contra ional Quality Infrastructure Based Selection l ctual arrangement with other Development competent National Standard s body ET-MOST-191788-CS-QCBS / Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 20,000.00 0.00 Under Review 2020-09-20 2020-09-23 2020-10-11 2020-11-24 2020-12-22 2021-01-21 2021-02-25 2021-04-01 2022-04-01 Training on ISO/IEC 17043:20 vate Sector Engagement Based Selection l 10 ET-MOST-192091-CS-LCS / R Component 3: Project Manag Least Cost Selecti IDA / 59830 Post Open - National 10,000.00 4,466.97 Signed 2020-09-30 2020-09-23 2020-10-21 2020-12-04 2021-02-18 2021-01-01 2021-06-30 2021-01-31 2021-03-18 2021-03-07 2021-11-01 2021-04-11 2021-11-30 2021-10-08 ecruitment of external audito ement and Monitoring and E on r valuation ET-MOST-196413-CS-QCBS / Training of Trainers (ToT) for Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 40,000.00 29,200.41 Completed 2020-10-11 2020-10-02 2020-11-01 2020-10-14 2020-12-15 2021-03-23 2021-01-12 2021-09-08 2021-02-11 2021-09-08 2021-03-18 2021-10-01 2021-04-22 2021-11-09 2022-04-22 2022-04-26 Improving the Technical Skill vate Sector Engagement Based Selection l s across the Cotton Value Ch ain. ET-MOST-196414-CS-QCBS / Training of Trainers (ToT) for Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 110,000.00 106,072.55 Completed 2020-10-11 2020-10-02 2020-11-01 2020-10-14 2020-12-15 2021-02-20 2021-01-12 2021-09-08 2021-02-11 2021-09-08 2021-03-18 2021-10-10 2021-04-22 2021-11-14 2022-04-22 2022-07-13 Improving the Technical Skill vate Sector Engagement Based Selection l s across Leather Value Chain. ET-MOST-196415-CS-QCBS / Training of Trainers (ToT) for Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 120,000.00 108,231.67 Completed 2020-10-11 2020-10-02 2020-11-01 2020-10-14 2020-12-15 2021-03-23 2021-01-12 2021-09-08 2021-02-11 2021-09-08 2021-03-18 2021-09-08 2021-04-22 2021-11-11 2022-04-22 2022-04-21 Improving the Technical Skill vate Sector Engagement Based Selection l s across the Textiles and Gar ments Value Chain. ET-MOST-177718-CS-QCBS / Training on inspection of text iles, garments, leather and le Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 100,000.00 0.00 Canceled 2020-06-19 2020-08-20 2020-07-10 2020-08-30 2020-08-23 2020-09-20 2020-10-20 2020-11-24 2020-12-29 2021-12-29 ather products (including foo vate Sector Engagement Based Selection l t wear), honey, fruit and veg etables for inspection bodies ET-MOST-218309-CS-QCBS / Support selected Textile and Component 2: Enhancing Pri Quality And Cost- Open - Internationa leather industries in Ethiopia IDA / 59830 Post 125,000.00 40,920.32 Signed 2021-02-28 2021-04-02 2021-03-21 2021-04-11 2021-05-04 2021-07-30 2021-06-01 2021-09-07 2021-07-01 2021-11-11 2021-08-05 2021-12-27 2021-09-09 2022-02-04 2022-09-09 vate Sector Engagement Based Selection l for Certification of Business S ocial Compliance Initiative (B SCI) ET-MOST-218316-CS-QCBS / Support selected Textile and Component 2: Enhancing Pri Quality And Cost- Open - Internationa leather industries in Ethiopia IDA / 59830 Post 125,000.00 93,505.14 Signed 2021-02-28 2021-04-02 2021-03-21 2021-04-11 2021-05-04 2021-07-30 2021-06-01 2021-09-02 2021-07-01 2021-11-12 2021-08-05 2021-12-27 2021-09-09 2022-02-08 2022-09-09 vate Sector Engagement Based Selection l for Certification of Worldwide Responsible Accredited Prod uction (WRAP) ET-MOST-218319-CS-QCBS / Support selected Textile and Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 80,000.00 106,844.39 Completed 2021-02-28 2021-04-02 2021-03-21 2021-04-11 2021-05-04 2021-07-31 2021-06-01 2021-09-07 2021-07-01 2021-11-10 2021-08-05 2021-12-27 2021-09-09 2022-02-28 2022-09-09 2022-04-21 leather industries in Ethiopia vate Sector Engagement Based Selection l for Certification of OEKO-TEX 100 ET-MOST-218323-CS-QCBS / Support selected Textile indu Component 2: Enhancing Pri Quality And Cost- Open - Internationa stries in Ethiopia for Certifica IDA / 59830 Post 70,000.00 14,621.87 Signed 2021-02-28 2021-04-02 2021-03-21 2021-04-11 2021-05-04 2021-07-31 2021-06-01 2021-09-06 2021-07-01 2021-11-12 2021-08-05 2021-12-27 2021-09-09 2022-02-04 2022-09-09 vate Sector Engagement Based Selection l tion of Sustainable Textile Pr oduction (STeP) By OEKO-TE X ET-MOST-218322-CS-QCBS / Support selected Textile and Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 150,000.00 52,357.49 Signed 2021-02-28 2021-04-02 2021-03-21 2021-04-11 2021-05-04 2021-07-31 2021-06-01 2021-09-08 2021-07-01 2021-11-11 2021-08-05 2021-12-27 2021-09-09 2022-02-04 2022-09-09 leather industries in Ethiopia vate Sector Engagement Based Selection l for Certification of Better Cot ton Initiative (BCI) ET-MOST-218320-CS-QCBS / Support selected Textile and Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 90,000.00 33,037.60 Signed 2021-02-28 2021-04-02 2021-03-21 2021-09-14 2021-05-04 2021-11-17 2021-06-01 2021-12-23 2021-07-01 2022-03-07 2021-08-05 2022-03-16 2021-09-09 2022-05-03 2022-09-09 leather industries in Ethiopia vate Sector Engagement Based Selection l for Certification of Leather W orking Group (LWG) ET-MOST-228380-CS-QCBS / Recruitment of a consulting fi Component 2: Enhancing Pri Quality And Cost- Open - Internationa rm to support selected privat IDA / 59830 Post 110,000.00 0.00 Canceled 2021-04-22 2021-04-22 2021-05-13 2021-05-20 2021-06-26 2021-09-22 2021-07-24 2021-11-01 2021-08-23 2022-02-19 2021-09-27 2022-03-16 2021-11-01 2022-11-01 vate Sector Engagement Based Selection l e organizations in Ethiopia fo r Certification against Global Gap standards ET-MOST-228394-CS-QCBS / Recruitment of a consulting fi Component 2: Enhancing Pri Quality And Cost- Open - Internationa rm to support selected privat IDA / 59830 Post 100,000.00 50,405.69 Signed 2021-04-22 2021-04-22 2021-05-13 2021-05-16 2021-06-26 2021-09-29 2021-07-24 2021-11-09 2021-08-23 2022-02-19 2021-09-27 2022-03-28 2021-11-01 2022-05-23 2022-11-01 vate Sector Engagement Based Selection l e organizations in Ethiopia fo r Certification against Food S afety Systems Standards ET-MOST-228395-CS-QCBS / Recruitment of a consulting fi rm to support selected privat Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 70,000.00 44,705.81 Signed 2021-04-21 2021-04-22 2021-05-12 2021-05-15 2021-06-25 2021-09-22 2021-07-23 2021-11-02 2021-08-22 2022-02-19 2021-09-26 2022-03-28 2021-10-31 2022-05-18 2022-10-31 e organizations in Ethiopia fo vate Sector Engagement Based Selection l r Certification against ISO 90 01:2015 and ISO 14001:2015 ET-MOST-231185-CS-QCBS / Lead Auditors Training on EM S, Global Gap, FSMS, FSSC, B Component 2: Enhancing Pri Quality And Cost- Open - Internationa IDA / 59830 Post 140,000.00 102,263.15 Signed 2021-04-29 2021-04-26 2021-05-20 2021-05-19 2021-07-03 2021-10-01 2021-07-31 2021-11-10 2021-08-30 2022-02-19 2021-10-04 2022-03-28 2021-11-08 2022-05-02 2022-11-08 RC, SA 8000 and OHS vate Sector Engagement Based Selection l For Supporting Certification B odies Develop their Auditing Skills ET-MOST-196416-CS-QCBS / Training of Trainers (ToT) for Component 2: Enhancing Pri Quality And Cost- Open - Internationa improving Technical skill acr IDA / 59830 Post 350,000.00 0.00 Canceled 2020-10-11 2020-10-02 2020-11-01 2020-10-14 2020-12-15 2021-03-23 2021-01-12 2021-09-08 2021-02-11 2021-09-08 2021-03-18 2021-10-09 2021-04-22 2022-04-22 vate Sector Engagement Based Selection l oss honey, fruits and vegeta bles producers value chain ET-MOST-266135-CS-QCBS / Training of Trainers (ToT) for Component 2: Enhancing Pri Quality And Cost- Open - Internationa Under Implement IDA / 59830 Post 120,000.00 0.00 2021-12-15 2022-02-18 2022-01-05 2022-02-18 2022-05-31 2022-03-18 2022-07-05 2022-04-17 2022-08-02 2022-05-22 2022-06-26 2023-06-26 improving Technical skill acr vate Sector Engagement Based Selection l ation oss fruits and vegetables pro cessors value chain Page 8 ET-MOST-266136-CS-QCBS / Training of Trainers (ToT) for Component 2: Enhancing Pri Quality And Cost- Open - Internationa Under Implement IDA / 59830 Post 115,000.00 0.00 2021-12-15 2022-02-18 2022-01-05 2022-02-25 2022-02-18 2022-05-31 2022-03-18 2022-07-04 2022-04-17 2022-08-02 2022-05-22 2022-06-26 2023-06-26 improving Technical skill acr vate Sector Engagement Based Selection l ation oss fruits and vegetables pro ducer value chain ET-MOST-266141-CS-QCBS / Training of Trainers (ToT) for Component 2: Enhancing Pri Quality And Cost- Open - Internationa Under Implement IDA / 59830 Post 115,000.00 0.00 2021-12-15 2022-02-18 2022-01-05 2022-02-18 2022-05-31 2022-03-18 2022-07-06 2022-04-17 2022-08-02 2022-05-22 2022-06-26 2023-06-26 improving Technical skill acr vate Sector Engagement Based Selection l ation oss honey value chain ET-MOST-276888-CS-QCBS / Component 3: Project Manag Quality And Cost- Open - Internationa Under Implement Impact assessment and clien IDA / 59830 ement and Monitoring and E Post 180,000.00 0.00 2022-03-17 2022-03-18 2022-04-04 2022-09-14 2022-04-20 2022-05-20 2022-05-30 2022-06-21 2022-07-07 2022-12-30 Based Selection l ation t satisfaction survey valuation ET-MOST-276861-CS-QCBS / Component 1: Strengthening Training Material Developme Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 120,000.00 0.00 Canceled 2022-03-17 2022-03-20 2022-04-04 2022-03-31 2022-04-20 2022-05-27 2022-05-20 2022-05-30 2022-06-21 2022-07-07 2022-12-09 nt on ISO/IEC 17025 & ISO 15 ional Quality Infrastructure Based Selection l 189, ISO/IEC 17020, ISO/IEC Development 17065,17021,17024 ET-MOST-204260-CS-QCBS / Component 1: Strengthening Quality And Cost- Open - Internationa Training on Accreditation Sof IDA / 59830 Institutional Capacity for Nat Post 50,000.00 0.00 Canceled 2020-11-30 2020-11-17 2020-12-21 2021-08-09 2021-02-03 2021-03-03 2021-04-02 2021-05-07 2021-06-11 2022-06-11 Based Selection l tware of ENAO ional Quality Infrastructure Development ET-MOST-276860-CS-QCBS / Scope expansion in Inspecti Component 1: Strengthening on accreditation sub scopes Institutional Capacity for Nat Quality And Cost- Open - Internationa IDA / 59830 Post 175,000.00 0.00 Canceled 2022-03-17 2022-03-20 2022-04-04 2022-03-29 2022-04-20 2022-05-20 2022-05-30 2022-06-21 2022-07-07 2022-12-24 of pharmaceutical products ional Quality Infrastructure Based Selection l inspection (FDA), cargo insp Development ection, and mechanical equip ment inspection INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOST-9966-CS-INDV / Re Component 3: Project Manag cruitment of Financial Manag Individual Consult IDA / 59830 ement and Monitoring and E Post Open 66,430.00 1,073.98 Signed 2017-03-21 2017-03-27 2017-04-11 2017-07-21 2017-04-14 2017-07-21 2017-05-01 2017-08-01 2018-04-29 2017-08-01 ement Specialist for the Proj ant Selection valuation ect Implementation unit (PIU) ET-MOST-10128-CS-INDV / R Component 3: Project Manag ecruitment of Monitoring and Individual Consult IDA / 59830 ement and Monitoring and E Post Open 66,430.00 1,073.98 Signed 2017-03-21 2017-03-27 2017-04-11 2017-07-19 2017-04-14 2017-07-21 2017-05-01 2017-08-01 2018-04-29 2018-02-16 Evaluation Specialist for PIU ant Selection valuation under Ethiopian NQI develop ment Project ET-MOST-10129-CS-INDV / R Component 3: Project Manag Individual Consult IDA / 59830 Post Open 53,144.00 859.18 Signed 2017-03-21 2017-03-27 2017-04-11 2017-07-19 2017-04-14 2017-07-21 2017-05-01 2017-08-01 2018-04-29 2017-08-01 ecruitment of Safeguard Spe ement and Monitoring and E ant Selection cialist valuation ET-MOST-10135-CS-INDV / R Component 3: Project Manag Individual Consult IDA / 59830 Post Open 39,858.00 644.39 Signed 2017-03-21 2017-03-27 2017-04-11 2017-07-19 2017-04-14 2017-07-21 2017-05-01 2017-08-01 2018-04-29 2017-08-01 ecruitment of project officer ement and Monitoring and E ant Selection valuation ET-MOST-10136-CS-INDV / R Component 3: Project Manag Individual Consult IDA / 59830 Post Open 31,887.00 1,031.02 Signed 2017-03-21 2017-03-27 2017-04-11 2017-07-19 2017-04-14 2017-07-21 2017-05-01 2017-08-01 2018-04-29 2017-08-01 ecruitment of an Accountant ement and Monitoring and E ant Selection valuation ET-MOST-10727-CS-INDV / R Component 3: Project Manag Individual Consult IDA / 59830 Prior Open 106,289.00 1,710.68 Completed 2017-03-23 2017-04-03 2017-05-06 2017-07-24 2017-05-09 2017-08-21 2017-05-23 2017-08-01 2018-05-23 2017-08-01 ecruitment of project Coordin ement and Monitoring and E ant Selection ator valuation ET-MOST-9966-CS-IWDV / Re Component 3: Project Manag cruitment of Procurement Sp Individual Consult / ement and Monitoring and E Prior Open 66,430.00 0.00 Canceled 2017-03-21 2017-04-06 2017-04-11 2017-04-14 2017-05-01 2018-04-29 ecialist for Ethiopian NQI Dev ant Selection valuation elopment Project Implement ation Office ET-MOST-23206-CS-INDV / R Component 3: Project Manag Individual Consult ecruitment of private engage IDA / 59830 ement and Monitoring and E Post Open 66,430.00 917.09 Completed 2017-08-08 2017-08-09 2017-09-26 2017-10-14 2017-10-17 2017-10-14 2017-11-21 2017-10-23 2018-11-21 2020-10-31 ant Selection ment specialist valuation ET-MOST-23184-CS-INDV / R Component 3: Project Manag Individual Consult IDA / 59830 Prior Open 66,430.00 920.29 Signed 2017-07-31 2017-09-14 2017-10-20 2017-10-05 2017-11-02 2017-11-09 2017-11-03 2018-05-08 ecruitment of a procurement ement and Monitoring and E ant Selection specialist valuation ET-MOST-23209-CS-INDV / R Component 3: Project Manag Individual Consult ecruitment of an individual c IDA / 59830 ement and Monitoring and E Post Open 10,000.00 10,000.00 Completed 2017-08-09 2017-08-15 2017-09-27 2017-10-10 2017-10-18 2017-10-18 2017-11-22 2017-10-23 2018-05-21 2017-11-01 ant Selection onsultant to prepare a FM ma valuation nual ET-MOST-27864-CS-INDV / R Component 1: Strengthening ecruitment of short term loca Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 50,000.00 24,898.94 Completed 2017-09-30 2017-10-19 2017-11-18 2018-01-16 2017-12-09 2018-02-02 2018-01-13 2018-02-02 2018-07-12 2018-02-05 l expert for standards imple ional Quality Infrastructure ant Selection mentation strategy develop Development ment ET-MOST-31514-CS-CQS / To recruit a local consultant that develops baseline document Component 3: Project Manag Individual Consult on general environmental & IDA / 59830 ement and Monitoring and E Post Open 20,000.00 16,411.50 Completed 2017-10-19 2017-11-01 2017-12-07 2018-02-03 2017-12-28 2018-03-16 2018-02-01 2018-03-19 2018-07-31 2018-03-19 ant Selection social issues consideration of valuation NQI institutions to help know the current status for the NQI D project. ET-MOST-34974-CS-CDS / Pr eparation of technical specifi Component 1: Strengthening cation for chemical metrolog Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 25,000.00 13,447.64 Completed 2017-11-08 2017-11-24 2017-11-18 2017-11-28 2018-01-22 2018-03-10 2018-07-21 2018-06-01 y (NMIE) with twinning arran ional Quality Infrastructure gement with National Metrol Development ogy Institute (NMI) of South Africa. ET-MOST-34981-CS-CDS / Co Component 1: Strengthening nsultancy service for procure Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 10,000.00 7,201.29 Completed 2017-11-08 2017-12-01 2017-11-18 2017-12-01 2018-01-22 2018-10-27 2018-07-21 2018-12-14 ment of Torque Measuremen ional Quality Infrastructure t Training by Experts in NMIE' Development s laboratory facility. ET-MOST-34883-CS-INDV / R Component 1: Strengthening ecruitment of resident Advise Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 96,000.00 96,000.00 Completed 2017-11-08 2017-12-01 2017-12-27 2018-02-01 2018-01-17 2018-04-14 2018-02-21 2018-04-17 2018-08-20 2018-04-17 r for Ethiopian Conformity As ional Quality Infrastructure ant Selection sessment Enterprise ( ECAE). Development ET-MOST-34884-CS-INDV / R Component 1: Strengthening ecruitment of Resident Advis Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 96,000.00 96,000.00 Completed 2017-11-08 2017-12-01 2017-12-27 2018-02-01 2018-01-17 2018-03-02 2018-02-21 2018-03-14 2018-08-20 2018-03-29 er to Ethiopian National Accr ional Quality Infrastructure ant Selection editation Office (ENAO). Development Page 9 ET-MOST-34902-CS-INDV / R Component 1: Strengthening Individual Consult ecruitment of resident adviso IDA / 59830 Institutional Capacity for Nat Post Open 96,000.00 96,000.00 Completed 2017-11-08 2017-12-01 2017-12-27 2018-02-01 2018-01-17 2018-02-15 2018-02-21 2018-02-28 2018-08-20 2018-04-11 ant Selection r for Ethiopian Standards Age ional Quality Infrastructure ncy (ESA) Development ET-MOST-37138-CS-INDV / R Component 1: Strengthening Individual Consult ecruitment of resident advis IDA / 59830 Institutional Capacity for Nat Post Open 120,000.00 120,000.00 Completed 2017-11-17 2018-01-01 2018-01-05 2018-02-01 2018-01-26 2018-02-08 2018-03-02 2018-02-28 2018-08-29 2018-03-10 ant Selection or to NMIE ional Quality Infrastructure Development ET-MOST-31998-CS-INDV / R Component 1: Strengthening ecruitment of consultants For Institutional Capacity for Nat Individual Consult the Scope expansion in inspe IDA / 59830 Post Open 48,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 ional Quality Infrastructure ant Selection ction accreditation sub scope Development s of Pharmaceutical products inspection ET-MOST-31999-CS-INDV / R Component 1: Strengthening ecruitment of consultants For Institutional Capacity for Nat Individual Consult the Scope expansion in inspe IDA / 59830 Post Open 48,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 ional Quality Infrastructure ant Selection ction accreditation sub scope Development s of Abattoirs inspection. ET-MOST-32000-CS-INDV / R Component 1: Strengthening ecruitment of consultants Fo Institutional Capacity for Nat Individual Consult r the Scope expansion in insp IDA / 59830 Post Open 48,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 ional Quality Infrastructure ant Selection ection accreditation sub scop Development es of Construction inspectio n. ET-MOST-32001-CS-INDV / R Component 1: Strengthening ecruitment of consultants Fo Institutional Capacity for Nat Individual Consult r the Scope expansion in insp IDA / 59830 Post Open 48,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 ional Quality Infrastructure ant Selection ection accreditation sub scop Development es of Textile and leather ins pection ET-MOST-32002-CS-INDV / R Component 1: Strengthening ecruitment of consultants Fo Institutional Capacity for Nat Individual Consult r the Scope expansion in insp IDA / 59830 Post Open 48,000.00 0.00 Canceled 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 ional Quality Infrastructure ant Selection ection accreditation sub scop Development es of Cargo inspection. ET-MOST-32006-CS-INDV / R Component 1: Strengthening ecruitment of a consultant Fo Institutional Capacity for Nat Individual Consult r Training on traceability, fixe IDA / 59830 Post Open 50,000.00 0.00 Canceled 2018-01-30 2018-07-06 2018-03-20 2018-04-10 2018-05-15 2018-11-11 ional Quality Infrastructure ant Selection d scope, method validation a Development nd verification, proficiency te sting. ET-MOST-39506-CS-INDV / S Component 1: Strengthening hort term consultant to desig Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 40,000.00 34,949.28 Completed 2017-12-13 2018-01-01 2018-01-31 2018-04-06 2018-02-21 2018-05-08 2018-03-28 2018-05-09 2018-09-24 2018-05-09 n communication materials a ional Quality Infrastructure ant Selection nd media engagements. Development ET-MOST-39652-CS-INDV / R ecruitment of individual cons Component 3: Project Manag ultant to conduct gender imp Individual Consult IDA / 59830 ement and Monitoring and E Post Open 10,000.00 9,117.23 Completed 2017-12-14 2018-01-08 2018-02-01 2018-03-30 2018-02-22 2018-04-17 2018-03-29 2018-04-11 2018-09-25 2018-04-17 act analysis of existing and u ant Selection valuation pcoming policies and strategi es and gender responsivenes s of NQI institutions ET-MOST-39653-CS-INDV / R ecruitment individual consult ant to developing the particip Component 3: Project Manag atory communication and im Individual Consult IDA / 59830 ement and Monitoring and E Post Open 8,000.00 6,541.11 Completed 2017-12-14 2018-01-08 2018-02-01 2018-03-30 2018-02-22 2018-04-17 2018-03-29 2018-05-01 2018-09-25 2018-05-08 plementation strategies for ant Selection valuation men and women during proje ct activity and channels that address and capture the nee d and interest of the gender ET-MOST-31515-CS-CQS / Re cruitment of a local consulta nt to develop Safeguard Oper Component 3: Project Manag Individual Consult ational Manual (SOM) to serv IDA / 59830 ement and Monitoring and E Post Open 30,000.00 0.00 Canceled 2017-10-19 2017-11-07 2017-12-07 2017-12-28 2018-02-01 2018-07-31 ant Selection e as reference for safeguard valuation tools development necessary during project life span and b eyond for the project. ET-MOST-42980-CS-CDS / Re cruit individual consultant to Component 1: Strengthening support the technical evaluat Institutional Capacity for Nat Individual Consult ion of Green building Constru IDA / 59830 Post Open 20,000.00 1,814.03 Completed 2018-01-23 2018-03-29 2018-03-13 2018-07-12 2018-04-03 2018-07-20 2018-05-08 2018-07-24 2018-11-04 2019-04-09 ional Quality Infrastructure ant Selection ction design (layout and spec Development ifications) of establishment o f new agro processing testin g laboratory ET-MOST-49989-CS-INDV / R Component 3: Project Manag Individual Consult ecruitment of Monitoring and IDA / 59830 ement and Monitoring and E Post Open 66,430.00 12,253.49 Completed 2018-02-28 2018-03-08 2018-04-18 2018-04-07 2018-05-09 2018-04-19 2018-06-13 2018-04-19 2018-12-10 2018-04-19 ant Selection evaluation specialist for NQI valuation project office ET-MOST-38427-CS-INDV / R ecruitment of consultant for i Component 2: Enhancing Pri Individual Consult IDA / 59830 Prior Open 250,000.00 0.00 Canceled 2017-12-04 2018-01-22 2018-02-12 2018-03-19 2018-09-15 ndustry needs assessment (T vate Sector Engagement ant Selection A to Private NQI service provi ders ET-MOST-38426-CS-INDV / R Component 2: Enhancing Pri Individual Consult ecruitment of consultant for i IDA / 59830 Prior Open 250,000.00 0.00 Canceled 2017-11-29 2018-01-17 2018-02-07 2018-03-14 2018-09-10 vate Sector Engagement ant Selection ndustry needs assessment (T A to industry) ET-MOST-55476-CS-INDV / R Component 3: Project Manag Individual Consult IDA / 59830 Post Open 66,430.00 66,430.00 Terminated 2018-03-31 2018-04-04 2018-05-19 2019-01-08 2018-06-09 2019-01-08 2018-07-14 2019-01-21 2019-01-10 ecruitment of Project assista ement and Monitoring and E ant Selection nt valuation ET-MOST-55480-CS-INDV / R Component 1: Strengthening Individual Consult ecruitment of a procurement IDA / 59830 Institutional Capacity for Nat Prior Open 66,430.00 0.00 Canceled 2018-03-31 2018-04-03 2018-05-19 2018-05-30 2018-06-09 2018-07-14 2019-01-10 ant Selection Specialist ional Quality Infrastructure Development ET-MOST-35144-CS-INDV / S Component 1: Strengthening hort term expert for developi Institutional Capacity for Nat Individual Consult ng National Quality Policy (N IDA / 59830 Post Open 60,000.00 0.00 Canceled 2017-11-09 2017-12-01 2017-12-28 2018-02-24 2018-01-18 2018-02-22 2018-08-21 ional Quality Infrastructure ant Selection QP) and to conduct related c Development onsultation for its implement ation ET-MOST-60298-CS-INDV / R ecruitment of individual cons Component 3: Project Manag Individual Consult ultant to support the establis IDA / 59830 ement and Monitoring and E Post Open 75,000.00 0.00 Canceled 2018-04-24 2018-06-07 2018-06-12 2018-07-03 2018-08-07 2019-02-03 ant Selection hment of regional and Ethio valuation pian Consumer association Page 10 ET-MOST-42989-CS-INDV / R Component 3: Project Manag ecruitment of consultants tha Individual Consult IDA / 59830 ement and Monitoring and E Post Open 50,000.00 0.00 Canceled 2019-07-07 2018-04-05 2019-08-25 2019-09-15 2019-10-20 2020-04-17 t carry out client engagemen ant Selection valuation t and satisfaction survey ET-MOST-66236-CS-INDV / R Component 1: Strengthening Individual Consult ecruitment of a procurement IDA / 59830 Institutional Capacity for Nat Prior Open 107,000.00 17,318.64 Signed 2018-06-19 2018-07-10 2018-07-26 2018-09-12 2018-08-16 2018-09-21 2018-09-20 2018-09-25 2019-03-19 ant Selection specialist ional Quality Infrastructure Development ET-MOST-32004-CS-INDV / R Component 1: Strengthening ecruitment of consultants Fo Institutional Capacity for Nat Individual Consult r the Scope expansion in cert IDA / 59830 Post Open 48,000.00 0.00 Canceled 2018-01-30 2018-03-20 2018-04-10 2018-05-15 2018-11-11 ional Quality Infrastructure ant Selection ification accreditation sub sc Development opes of product certification. ET-MOST-73788-CS-INDV / R ecruitment of individual cons Component 1: Strengthening ultant to support WINNER me Institutional Capacity for Nat Individual Consult chanical workshop and METE IDA / 59830 Post Open 80,000.00 0.00 Canceled 2018-08-20 2018-08-24 2018-10-08 2018-10-29 2018-12-03 2019-06-01 ional Quality Infrastructure ant Selection C Quality Engineering Center Development to become accredited body f or mass calibration laborator y Services ET-MOST-73791-CS-INDV / R ecruitment of individual cons Component 1: Strengthening ultant to support METEC Qual Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 60,000.00 0.00 Canceled 2018-08-20 2018-08-23 2018-10-08 2018-10-29 2018-12-03 2019-06-01 ity Engineering Center to bec ional Quality Infrastructure ant Selection ome accredited body for elec Development trical calibration laboratory S ervices ET-MOST-73795-CS-INDV / R ecruitment of individual cons Component 1: Strengthening ultant to support METEC Qual Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 60,000.00 0.00 Canceled 2018-08-20 2018-08-23 2018-10-08 2018-10-29 2018-12-03 2019-06-01 ity Engineering Center to bec ional Quality Infrastructure ant Selection ome accredited body for pres Development sure calibration laboratory Se rvices ET-MOST-73796-CS-INDV / R ecruitment of individual cons Component 1: Strengthening ultant to support METEC Qual Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 60,000.00 0.00 Canceled 2018-08-20 2018-08-23 2018-10-08 2018-10-29 2018-12-03 2019-06-01 ity Engineering Center to bec ional Quality Infrastructure ant Selection ome accredited body for tem Development perature calibration laborator y Services ET-MOST-73988-CS-INDV / R ecruitment of individual cons Component 2: Enhancing Pri Individual Consult ultant to support BLESS agro IDA / 59830 Post Open 80,000.00 0.00 Canceled 2018-08-29 2018-08-30 2018-10-17 2018-11-07 2018-12-12 2019-06-10 vate Sector Engagement ant Selection testing laboratory to become accredited body for honey te sting laboratory Services ET-MOST-93425-CS-INDV / R Component 3: Project Manag Individual Consult ecruitment of Gender and So IDA / 59830 ement and Monitoring and E Post Open 66,430.00 14,788.73 Signed 2019-01-15 2019-01-08 2019-03-05 2019-02-07 2019-03-26 2019-02-14 2019-04-30 2019-02-18 2019-10-27 ant Selection cial Safeguard Specialist valuation ET-MOST-93429-CS-INDV / R Component 2: Enhancing Pri Individual Consult ecruitment of Industrial Parks IDA / 59830 Post Open 50,000.00 8,525.25 Completed 2019-01-15 2019-05-15 2019-03-05 2019-07-24 2019-03-26 2019-08-01 2019-04-30 2019-08-07 2019-10-27 2020-09-01 vate Sector Engagement ant Selection Quality Assurance Service Co nsultant ET-MOST-101122-CS-CDS / E xpansion of Accreditation sco Component 1: Strengthening pe and Training & capacity b Institutional Capacity for Nat IDA / 59830 Prior Direct Selection Direct 3,470,000.00 540,097.50 Signed 2019-04-03 2019-05-15 2019-04-13 2019-06-06 2019-06-17 2019-11-27 2019-12-14 uilding programme of ENAO t ional Quality Infrastructure hrough twinning arrangemen Development t with ILAC/IAF MRA signatori es ET-MOST-109077-CS-INDV / Recruitment of individual con Component 1: Strengthening sultant for training on ISO/IE Institutional Capacity for Nat Individual Consult IDA / 59830 Post Limited 60,000.00 9,580.00 Completed 2019-04-11 2019-05-28 2019-04-16 2019-05-30 2019-05-07 2019-08-19 2019-06-11 2019-08-17 2019-12-08 2019-12-30 C 17025 laboratory Manage ional Quality Infrastructure ant Selection ment system for National Me Development trology Institute of Ethiopia ( NMIE) ET-MOST-111270-CS-INDV / Recruitment of individual con Component 1: Strengthening sultant to support the technic Institutional Capacity for Nat Individual Consult IDA / 59830 Post Limited 20,000.00 7,589.00 Completed 2019-06-04 2019-06-14 2019-06-09 2019-07-24 2019-06-30 2019-08-20 2019-08-04 2019-08-18 2020-01-31 2019-11-06 al evaluation for Procuremen ional Quality Infrastructure ant Selection t of chemical metrology Stan Development dards & equipment for NMIE ET-MOST-127173-CS-INDV / Component 1: Strengthening Procurement of NQI technical Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 70,000.00 18,326.21 Terminated 2019-08-23 2019-12-09 2019-10-11 2020-03-20 2019-11-01 2020-03-30 2019-12-06 2020-04-13 2020-06-03 adviser to Ministry of Trade a ional Quality Infrastructure ant Selection nd Industry to NQI and Regul Development atory function ET-MOST-111276-CS-INDV / Component 3: Project Manag Individual Consult Recruitment of a procuremen IDA / 59830 ement and Monitoring and E Prior Open 20,000.00 0.00 Canceled 2019-06-07 2019-06-18 2019-07-26 2019-08-16 2019-09-20 2020-03-18 ant Selection t specialist valuation ET-MOST-117349-CS-CDS / E xpansion of Accreditation sco Component 1: Strengthening pe and Training & capacity b Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 500,000.00 0.00 Canceled 2019-06-10 2019-06-18 2019-06-20 2019-07-10 2019-08-24 2020-02-20 uilding programme of ECAE t ional Quality Infrastructure hrough contractual arrangem Development ent with internationally recog nised CABs ET-MOST-111292-CS-INDV / Component 1: Strengthening Recruitment of an Individual Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 75,000.00 0.00 Canceled 2019-04-26 2019-06-14 2019-07-05 2019-08-09 2020-02-05 Consultant to Develop Nation ional Quality Infrastructure ant Selection al Standards detail Implemen Development tation Business plan ET-MOST-143008-CS-INDV / Recruitment of Textile and l Component 2: Enhancing Pri Individual Consult IDA / 59830 Post Open 60,000.00 1,098.90 Signed 2019-11-08 2019-11-18 2019-12-27 2019-12-27 2020-01-17 2020-01-27 2020-02-21 2020-01-27 2020-08-19 eather expert to support the vate Sector Engagement ant Selection NQI Development Project ET-MOST-144680-CS-INDV / Component 1: Strengthening Individual Consult Recruitment of IT expert to s IDA / 59830 Institutional Capacity for Nat Post Open 60,000.00 9,588.04 Completed 2019-11-25 2019-11-29 2020-01-13 2020-03-10 2020-02-03 2020-03-20 2020-03-09 2020-04-14 2020-09-05 2021-08-06 ant Selection upport NQI institutions (NMIE ional Quality Infrastructure , ESA and ECAE) Development ET-MOST-149191-CS-INDV / Component 3: Project Manag Individual Consult Recruitment of Monitoring an IDA / 59830 ement and Monitoring and E Post Open 40,000.00 1,288.45 Signed 2019-12-16 2020-01-10 2020-02-03 2020-02-26 2020-02-24 2020-02-28 2020-03-30 2020-03-02 2020-09-26 ant Selection d Evaluation specialist valuation Page 11 ET-MOST-151115-CS-INDV / Recruitment of individual co Component 1: Strengthening nsultant for Local Intensive T Institutional Capacity for Nat Individual Consult IDA / 59830 Post Limited 25,000.00 9,897.22 Completed 2020-01-15 2020-01-16 2020-01-20 2020-02-05 2020-02-10 2020-05-20 2020-03-16 2020-05-27 2020-09-12 2020-09-23 raining on Cleaner Productio ional Quality Infrastructure ant Selection n Implementation techniques Development and Cleaner production tools ET-MOST-151326-CS-INDV / Component 3: Project Manag Recruitment of food and agr Individual Consult IDA / 59830 ement and Monitoring and E Post Open 60,000.00 13,186.81 Signed 2019-12-20 2020-01-14 2020-02-07 2020-02-21 2020-02-28 2020-02-23 2020-04-03 2020-02-24 2020-09-30 o expert to support the NQI D ant Selection valuation evelopment Project ET-MOST-159781-CS-CDS / T raining and Technical assista Component 2: Enhancing Pri IDA / 59830 Post Direct Selection Direct 150,000.00 135,260.80 Completed 2020-03-14 2020-03-27 2020-03-24 2020-04-21 2020-05-28 2021-02-22 2020-11-24 2022-06-16 nce for Leather Industry Dev vate Sector Engagement elopment Institute (LIDI) for SATRA accreditation ET-MOST-172582-CS-CDS / T raining and technical assista Component 1: Strengthening nce for Ethiopian Standards Institutional Capacity for Nat IDA / 59830 Post Direct Selection Direct 485,000.00 494,881.00 Signed 2020-05-29 2020-05-20 2020-06-08 2020-06-08 2020-08-12 2021-05-17 2021-02-08 Agency (ESA) through Contra ional Quality Infrastructure ctual arrangement with other Development competent National Standard s body ET-MOST-151113-CS-INDV / Component 1: Strengthening Recruitment of individual con Institutional Capacity for Nat Individual Consult IDA / 59830 Post Limited 20,000.00 0.00 Canceled 2020-01-08 2020-02-12 2020-01-13 2020-02-27 2020-02-03 2020-03-09 2020-09-05 sultant to develop Academic ional Quality Infrastructure ant Selection Training programme for ESA Development ET-MOST-144273-CS-INDV / Training on producing certifie Component 1: Strengthening d reference materials (CRMs) Institutional Capacity for Nat Individual Consult IDA / 59830 Post Limited 11,000.00 0.00 Canceled 2019-11-12 2019-11-18 2019-11-17 2019-12-06 2019-12-08 2020-01-12 2020-07-10 and testing their stability and ional Quality Infrastructure ant Selection homogeneity in accordance Development with the relevant internation al standards ET-MOST-201360-CS-INDV / Component 3: Project Manag Individual Consult Recruitment of an individual IDA / 59830 ement and Monitoring and E Post Open 20,000.00 23,079.82 Completed 2020-11-17 2020-11-13 2021-01-05 2021-08-09 2021-01-26 2021-09-21 2021-03-02 2021-10-22 2021-08-29 2022-07-13 ant Selection consultant for Gender strateg valuation y Development ET-MOST-212458-CS-INDV / Component 1: Strengthening Procurement of technical adv Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 30,000.00 0.00 Canceled 2021-02-04 2021-01-30 2021-03-25 2021-04-15 2021-05-20 2021-11-16 iser to Ministry of Trade and I ional Quality Infrastructure ant Selection ndustry on Regulatory functi Development on ET-MOST-212456-CS-INDV / Component 1: Strengthening Recruitment of technical advi Institutional Capacity for Nat Individual Consult IDA / 59830 Post Open 30,000.00 1,410.60 Signed 2021-02-04 2021-01-30 2021-03-25 2022-01-11 2021-04-15 2022-01-11 2021-05-20 2021-12-25 2021-11-16 ser on National Quality Infras ional Quality Infrastructure ant Selection tructure (NQI) to Ministry of T Development rade and Industry ET-MOST-208231-CS-INDV / Component 3: Project Manag Individual Consult Recruitment of deputy projec IDA / 59830 ement and Monitoring and E Post Open 36,000.00 0.00 Canceled 2021-01-20 2021-01-22 2021-03-10 2021-03-31 2021-05-05 2021-11-01 ant Selection t coordinator valuation ET-MOST-241466-CS-INDV / Component 3: Project Manag Individual Consult Recruitment of Contract Man IDA / 59830 ement and Monitoring and E Post Open 48,000.00 0.00 Canceled 2021-07-09 2021-08-22 2021-08-27 2021-09-17 2021-10-22 2022-04-20 ant Selection agement Expert valuation ET-MOST-278328-CS-CDS / T raining and technical assista Component 1: Strengthening nce for National Metrology In Institutional Capacity for Nat Under Implement IDA / 59830 Post Direct Selection Direct 150,000.00 0.00 2022-02-28 2022-03-06 2022-03-10 2022-05-04 2022-05-14 2022-11-10 stitute of Ethiopia (NMIE) thr ional Quality Infrastructure ation ough Contractual arrangeme Development nt with a competent other N MIs ET-MOST-250905-CS-INDV / Component 3: Project Manag Individual Consult IDA / 59830 Post Open 24,000.00 0.00 Canceled 2021-09-05 2021-09-15 2021-10-24 2022-03-17 2021-11-14 2021-12-19 2022-06-17 Contract Management Expert ement and Monitoring and E ant Selection valuation ET-MOST-23184- CS- INDV / Component 1: Strengthening Individual Consult Recruitment of Procurement IDA / 59830 Institutional Capacity for Nat Post Open 132,860.00 0.00 Canceled 2017-07-31 2017-09-18 2017-10-09 2018-01-02 2017-11-13 2018-05-12 ant Selection Specialist ional Quality Infrastructure Development Page 12