The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) Gaza Solid Waste Management Project (P121648) MIDDLE EAST AND NORTH AFRICA | West Bank and Gaza | Urban, Resilience and Land Global Practice | Special Financing | Investment Project Financing | FY 2014 | Seq No: 19 | ARCHIVED on 23-Dec-2022 | ISR54273 | Implementing Agencies: Municipal Development and Lending Fund, Palestine Liberation Organization (for the benefit of the Palestinian Authority) Key Dates Key Project Dates Bank Approval Date: 31-Mar-2014 Effectiveness Date: 09-Jul-2014 Planned Mid Term Review Date: 04-Dec-2017 Actual Mid-Term Review Date: 04-Dec-2017 Original Closing Date: 30-Jun-2022 Revised Closing Date: 31-Dec-2022 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of this project is to improve solid waste management services in the Gaza Strip. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured) To improve solid waste management services in the Gaza Strip through provision of more efficient, environmentally and socially sound waste management systems. Components Table Name Component 1: Solid Waste Transfer and Disposal Facilities:(Cost $23.89 M) Component 2: Institutional Strengthening:(Cost $1.40 M) Component 3: Primary Collection and Resource Recovery:(Cost $2.20 M) Component 4: Project Management:(Cost $5.11 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating High Substantial Implementation Status and Key Decisions The Gaza Solid Waste Management Project (GSWMP) has been under implementation since 2014. During the nine-year implementation period, the project was able to achieve all of the results envisioned under the project development objective (PDO) aimed at improving solid waste management services in the Gaza Strip. Around 96 percent of waste generated in the project area is disposed at the sanitary landfill constructed under the project, which became operational in 2019. The landfill, transfer stations and other ancillary facilities are serving an estimated 948,000 beneficiaries’ population in the project area. The project also closed and rehabilitated three major dumpsites, covering a total area of 12.2 hectares. 12/23/2022 Page 1 of 9 The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) An additional financing (AF) of US$ 3.25 million (US$2.00 million from the Global Partnership for Results-Based Approaches (GPRBA) and US$1.25 million from the Partnership for Infrastructure Development – Multi-Donor Trust Fund Partnership (PID-MDTF) was approved in August 2020 and became effective in November 2020. The GPRBA AF provided key operational funding support for the Joint Services Council for Khan Younis, Rafah and Middle Area (JSC-KRM), solid waste service provider in southern Gaza. Improved and upgraded Standard Operating Procedures (SOPs) have been developed and adopted by the JSC-KRM since September 2020 and Key Performance Indicators (KPIs) for service delivery improvements and cost recovery were introduced. The project fully achieved all the Results-Based KPIs in four reporting periods (July 1, 2020-June 30, 2022), independently monitored and verified by an IVA. All the remaining project activities are near completion, and the project funds are expected to be fully (100%) utilized by the end of disbursement date. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- High High Macroeconomic -- High High Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and -- High Substantial Sustainability Fiduciary -- Substantial Substantial Environment and Social -- Substantial Substantial Stakeholders -- High Moderate Other -- Low Low Overall -- High Substantial Results PDO Indicators by Objectives / Outcomes Improve solid waste management services in the Gaza Strip through more efficient solid waste systems IN01228424 ►Percentage increase in fees collected annually within the JSC towards cost recovery (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 71.12 71.12 60.00 Date 16-Jul-2014 31-Aug-2022 31-Aug-2022 31-Dec-2022 12/23/2022 Page 2 of 9 The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) Improve solid waste management in the Gaza Strip through more environmentally sound SW systems IN01228425 ►Contaminated land managed or dump-sites closed under the project (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 10.00 12.20 10.00 Date 15-Dec-2017 09-Dec-2019 15-Dec-2022 31-Dec-2022 IN01228432 ►Solid Waste collected from the targeted populations, disposed in a new sanitary landfill developed under the project (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 96.31 96.31 80.00 Date 09-Jul-2014 31-Aug-2022 31-Aug-2022 31-Dec-2022 Improve solid waste management in the Gaza Strip through more socially sound SW systems IN01228422 ►Wastepickers whose lives depend on the existing SW context integrated into inclusion programs (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 16.00 16.00 16.00 Date 20-Dec-2017 18-Feb-2019 18-Feb-2019 31-Dec-2022 IN01228423 ►Direct project beneficiaries (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 948,000.00 948,000.00 948,000.00 Date 15-May-2014 01-Mar-2022 01-Mar-2022 31-Dec-2022 IN01228431 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 49.00 49.00 49.00 Intermediate Results Indicators by Components Component 1: Solid Waste Transfer and Disposal Facilities IN01228433 ►Two transfer stations in targeted area are constructed and are fully equipped and operational by the end of the project (Number, Custom) 12/23/2022 Page 3 of 9 The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 2.00 Date 15-May-2014 18-Dec-2019 18-Dec-2019 31-Dec-2022 The construction of Rafah Transfer Station was completed in December 2019. The Khan Younis transfer station has been rehabilitated and the facility started small scale medical waste treatment operation in late Comments: 2019. IN01228437 ►Closure of existing dumpsites at Sofa and Dier el Balah (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No Yes Yes Date 01-Mar-2018 31-Aug-2022 15-Dec-2022 31-Dec-2022 Contracts for civil works and supervision was signed in June 2021. The Sofa rehabilitation and closure works are competed (October 2022) and the Diei el Balah site is at the last stage of completion, with 95% of the civil works completed, and remaining task at the site is fully expected to be completed by project Comments: closing. IN01228441 ►Interim cell is constructed in a sanitary manner to accommodate incoming MSW from target area during the construction of the new Sanitary landfill (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Mar-2018 09-Dec-2019 09-Dec-2019 31-Dec-2022 IN01228445 ►Sanitary Landfill in the Southern Gaza Strip (Sofa/Al-Fukhari) is constructed and operational (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 15-May-2014 02-Oct-2019 02-Oct-2019 31-Dec-2022 IN01228451 ►Industrial and municipal waste disposal capacity created under the project (Metric ton, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,490,000.00 2,490,000.00 2,350,000.00 Date 15-May-2014 09-Dec-2019 09-Dec-2019 31-Dec-2022 Target updated based on landfill and short-term cell design capacity. The short-term cell capacity is Comments: 350,000metric tons; The total landfill capacity is 2,350,000 metric tons. IN01228453 ►Temporary jobs created (person-day) under the various activities of Component 1 (Number, Custom) 12/23/2022 Page 4 of 9 The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 50,800.00 51,200.00 40,000.00 Date 15-May-2014 31-Aug-2022 15-Dec-2022 31-Dec-2022 Component 2: Institutional Strengthening IN01228436 ►Intended beneficiaries aware of project info. and project investments (%) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 56.00 56.00 50.00 Date 15-May-2014 31-Aug-2022 31-Aug-2022 31-Dec-2022 Comments: IN01228440 ►% of female project beneficiaries aware of solid waste management practices (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 69.00 69.00 50.00 Date 12-Mar-2014 31-Aug-2022 31-Aug-2022 31-Dec-2022 IN01228444 ►Increased the participation and role of women in decision making of the JSC-KRM through formation of a “women's committee” (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Jul-2020 22-Feb-2021 22-Feb-2021 31-Dec-2022 This is newly added indicator under the additional financing. The Women committee has been formed and Comments: the committee is regularly participating/ actively attending JSC-KRM's decision meetings. IN01228448 ►Training days provided to the Technical Operations Unit and other JSC-KRM staff and Board members as part of the targeted capacity building activities financed under Component 2 (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 299.00 299.00 150.00 Date 15-May-2014 31-Aug-2022 31-Aug-2022 31-Dec-2022 Technical trainings and other capacity strengthening supports are ongoing and will continue through out the project implementation period. These trainings were also provided by the international Comments: Professionalization Contractor hired to provide technical and capacity building support to the JSC staff. IN01228449 12/23/2022 Page 5 of 9 The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) ►Service contracts are signed with member municipalities and UNRWA (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 18.00 18.00 18.00 Date 01-Mar-2018 22-Feb-2021 22-Feb-2021 31-Dec-2022 JSC-KRM has updated its bylaw to apply to all member municipalities and this bylaw will be used in lieu of individual service agreements with each local government units/municipalities and UNRWA.  Updated bylaw acts as one document unified document governing the relationship between JSC and member LGUs (the 17 municipalities), that is to govern all common services provided by JSC and its unit price (the JSC Board approved to use a unified rate for service): 1. Comments: Secondary Collection, 2. Landfill Disposal Operations. Service contract between JSC-KRM and with UNRWA has already been signed.  Particular MoU: was done to govern particular activities that can apply to specific members such as the use and operation of Rafah Transfer Station, where the JSC signed an agreement with Rafah City, agreement that governs the use of shared facility. IN01228452 ►New JSC Bylaw is approved and operational plans are defined (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Mar-2018 02-Oct-2019 02-Oct-2019 31-Dec-2022 IN01228454 ►Percentage of grievances that have been responded in a timely manner (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 96.00 96.00 90.00 Date 12-Mar-2014 31-Aug-2022 31-Aug-2022 31-Dec-2022 IN01228455 ►Improved citizens satisfaction with JSC-KRM performance (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 57.00 91.00 91.00 90.00 Date 20-Nov-2017 31-Aug-2022 31-Aug-2022 31-Dec-2022 This is indicator is added under the additional financing; A baseline survey from the first Beneficiary Impact Assessment (BIA) conducted in 2017 were used and subsequent service satisfaction surveys were Comments: conducted annually to gauge the percent improvement from the baseline to reach the desired target. Component 3: Primary Collection and Resource Recovery IN01228435 ►JSC has assumed agreed responsibilities for management of the upgraded transfer and disposal services (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target 12/23/2022 Page 6 of 9 The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) Value No Yes Yes Yes Date 01-Mar-2018 17-Dec-2018 17-Dec-2018 31-Dec-2022 JSC has assumed full responsibility for managing the operations of the new sanitary landfill and upgraded Comments: transfer stations at Rafah and Khan Younis governorates. IN01228438 ►A strategy plan for the elimination of random dumping in the targeted area is created by end of the project (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Mar-2018 09-Dec-2019 09-Dec-2019 31-Dec-2022 IN01228442 ►A strategy plan for optimizing waste recovery in the targeted area is created by the end of the project (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Mar-2018 09-Dec-2019 09-Dec-2019 31-Dec-2022 IN01228447 ►A strategy plan for optimization of primary collection and transportation of solid waste in the targeted areas is created by the end of the project (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 15-May-2014 09-Dec-2019 09-Dec-2019 31-Dec-2022 Component 4: Project Management IN01228434 ►Interim IFRs and Progress Reports are submitted to Financing Partners in a timely and satisfactory manner (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 15-May-2014 16-Sep-2021 16-Sep-2021 31-Dec-2022 IN01228439 ►MDLF-PDSU maintains adequate staffing for project management, environmental and social safeguards and fiduciary staff throughout the life of the Project (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 15-May-2014 22-Feb-2021 22-Feb-2021 31-Dec-2022 IN01228443 12/23/2022 Page 7 of 9 The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) ►Results based payments received for achieving service improvement related targets (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 80.00 Date 01-Jul-2020 01-Mar-2022 01-Mar-2022 30-Jun-2022 All results based indicators related to JSC service improvements are fully achieved as verified by the four Comments: IVA reporting period spanning July 1, 2020 to June 30, 2022. IN01228446 ►Results based payments received for achieving cost recovery related related targets (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 80.00 Date 01-Jul-2020 01-Mar-2022 01-Mar-2022 30-Jun-2022 All results based indicators related to cost recovery are fully achieved, as verified by four IVA reporting Comments: period, spanning July 1, 2020 to June 30, 2022. IN01228450 ►Adoption of the improved protocols and procedures as defined in the Standard operating procedures for all JSC services (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Jul-2020 15-Sep-2020 15-Sep-2020 31-Dec-2022 New standard operating procedures and protocols have been adopted by the JSC-KRM on September 15, Comments: 2020. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P121648 TF-16835 Effective USD 10.00 10.00 0.00 9.94 0.06 99% P121648 TF-B3582 Closed USD 1.00 1.00 0.00 1.00 0.00 100% P121648 TF-B3583 Closed USD 1.00 1.00 0.00 1.00 0.00 100% P121648 TF-B3584 Effective USD 1.25 1.25 0.00 0.80 0.45 64% Key Dates (by loan) 12/23/2022 Page 8 of 9 The World Bank Implementation Status & Results Report Gaza Solid Waste Management Project (P121648) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P121648 TF-16835 Effective 24-Apr-2014 24-Apr-2014 09-Jul-2014 30-Nov-2019 31-Dec-2022 P121648 TF-B3582 Closed 28-Aug-2020 16-Sep-2020 05-Nov-2020 30-Jun-2022 30-Jun-2022 P121648 TF-B3583 Closed 28-Aug-2020 16-Sep-2020 05-Nov-2020 30-Jun-2021 30-Jun-2022 P121648 TF-B3584 Effective 28-Aug-2020 16-Sep-2020 05-Nov-2020 30-Jun-2022 31-Dec-2022 Cumulative Disbursements Restructuring History Level 2 Approved on 06-Apr-2018 ,Level 2 Approved on 30-Apr-2021 ,Level 2 Approved on 28-Jun-2022 Related Project(s) P171328-ADDITIONAL FINANCE :GAZA SOLID WASTE MANAGEMENT PROJECT 12/23/2022 Page 9 of 9