PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western and Central Africa : West Africa Coasta Areas Resilience Investment Project PLAN General Information Country: Western and Central Africa 2018-05-21 Bank’s Approval Date of the Original Procurement Plan: 2022-06-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coasta Areas Resilience Investment Project Loan / Credit No: IDA / V1250, IDA / 62150, IDA / 62120 WACCA SENEGAL- Direction de l'Environnement Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4.4.5 / Maintenance des équi Component 4: National Coor Single Stage - One E 2020-06-2 IDA / V1250 A posteriori Demande de prix Limited 35,735.98 Signé 2019-11-02 2019-11-18 2019-12-28 2019-12-17 pements et réfection du local dination nvelope 5 du Projet 31308 / Sélection directe du Groupement GIE Eco garde Component 3: Strengthening Passation de marc 2020-10-2 pour le reboisement de dix ( IDA / V1250 National Physical and Social A posteriori Direct 44,174.14 Signé 2020-03-20 2020-04-22 2020-03-25 2020-04-29 2020-04-29 2020-07-20 hé de gré à gré 6 10) hectares de filaos dans le Investments parc national de la Langue d e Barbarie T_2021_32201 / Travaux de construction et d'équipement Component 3: Strengthening Single Stage - One E En cours d'e 2021-11-2 en kit solaire d'un atelier de IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-04-05 2021-04-29 2021-05-31 nvelope xécution 7 couture (lot1) et travaux de c Investments onstruction d'un atelier de co iffure (lot 2) à Diougop T_2021_31309 / Travaux de Component 3: Strengthening reboisement de dix (10) ha d Passation de marc 2021-10-2 IDA / 62150 National Physical and Social A posteriori Direct 29,533.46 Signé 2021-03-16 2021-03-16 2021-03-21 2021-03-21 2021-04-25 2021-04-09 e filao et huit (08) ha de man hé de gré à gré 2 Investments grove au PNLB à Saint-Louis T_2021_31310 / Travaux de Component 3: Strengthening Passation de marc 2021-10-2 reboisement de dix (10) ha d IDA / 62150 National Physical and Social A posteriori Direct 18,325.44 Signé 2021-03-16 2021-03-16 2021-03-21 2021-03-21 2021-04-25 2021-04-21 hé de gré à gré 2 e filoas à l'AMP de Saint-Loui Investments s T_2021_31302 / Travaux de Component 3: Strengthening construction d'une unité de v Single Stage - One E 2021-11-2 IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 60,337.70 Signé 2021-04-04 2021-03-22 2021-05-30 2021-04-29 alorisation durables des arch nvelope 6 Investments es à Moumbaye (PNLB) F_2021_31302_8 / Travaux d Component 3: Strengthening En cours d'e 2022-04-1 e construction d'un Poste de IDA / 62150 National Physical and Social A posteriori Demande de prix 0.00 2021-08-23 2021-08-09 2021-10-18 xécution 6 Garde au niveau de l'AMP de Investments Saint-Louis Request for SD-PNLB-31302-T / Travaux Component 3: Strengthening Passation de marc Quotations ( En attente d 2022-06-2 de reboisement de 10 ha de f IDA / 62150 National Physical and Social A posteriori Direct 0.00 2022-06-29 2022-06-29 2022-06-29 hé de gré à gré Non Bank-SP 'exécution 9 ilaos et 12 ha de mangrove d Investments D) ans le PNLB Request for SD-DEFCCS-31302-T / Trava Component 3: Strengthening Passation de marc Quotations ( En attente d 2023-02-0 ux de reboisement de 08 ha IDA / 62150 National Physical and Social A posteriori Direct 0.00 2022-06-29 2022-07-04 2022-08-08 hé de gré à gré Non Bank-SP 'exécution 4 d'eaucalyptus dans le cordon Investments D) dunaire de Potou GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 100 / Acquisition d'un logicie Component 4: National Coor Single Stage - One E l comptable et mise en place IDA / V1250 A posteriori Demande de prix Limited 25,469.17 Signé 2018-04-17 2018-07-03 2018-06-12 2018-10-11 2018-12-09 dination nvelope d'un système d'information 4.4.7 / Acquisition d'une mot Component 4: National Coor Single Stage - One E IDA / V1250 A posteriori Demande de prix Limited 2,764.60 Signé 2019-11-02 2021-02-27 2019-12-28 2021-06-14 2020-06-25 o dination nvelope DC4-2018 / Acquisition de v Component 4: National Coor Single Stage - One E IDA / V1250 A posteriori Demande de prix Limited 60,771.35 Signé 2018-04-24 2020-01-18 2018-06-19 2020-03-02 2018-12-16 éhicule dination nvelope 4.4.1 / Acquisition de mobili Component 4: National Coor Single Stage - One E IDA / V1250 A posteriori Demande de prix Limited 25,804.96 Signé 2019-12-04 2019-11-27 2020-01-29 2019-12-19 2020-07-27 er de bureau dination nvelope 4.4.8 / Acquisition de matéri Component 4: National Coor Single Stage - One E IDA / V1250 A posteriori Demande de prix Limited 21,941.18 Signé 2019-12-04 2019-11-27 2020-01-29 2019-12-17 2020-07-27 el de bureau dination nvelope 4.4.2 / Acquisition de matéri Component 4: National Coor Single Stage - One E IDA / V1250 A posteriori Demande de prix Limited 58,041.90 Signé 2019-11-02 2019-11-27 2019-12-28 2020-03-03 2020-06-25 el informatique dination nvelope 4.4.4 / Acquisition de fournit Component 4: National Coor Single Stage - One E ures de bureau, consommabl IDA / V1250 A posteriori Demande de prix Limited 26,927.28 Signé 2019-11-02 2020-04-07 2019-12-28 2020-06-02 2020-06-25 dination nvelope es informatiques et produits d'entretien DC1-2018 / Acquisition de m Component 2: Strengthening Single Stage - One E atériels et équipement (maté IDA / V1250 the Policy and Institutional F A posteriori Demande de prix Limited 0.00 Annulé 2018-04-11 2018-06-06 2018-12-03 nvelope riel et mobilier de bureau etc ramework ...) pour le SIG DC2-2018 / Achat de donnée Component 2: Strengthening s de référence (support carto Single Stage - One E IDA / V1250 the Policy and Institutional F A posteriori Demande de prix Limited 0.00 Annulé 2019-11-30 2020-01-25 2020-07-23 graphique, images satellite .. nvelope ramework ..) avec équipement et conso mmables. 420106 / Acquisition de deu Component 4: National Coor Single Stage - One E IDA / 62150 A posteriori Demande de prix Limited 108,438.77 Signé 2021-01-23 2021-01-20 2021-03-20 2021-03-04 2021-09-16 x (02) véhicules dination nvelope 32201 / Acquisition de denré Component 3: Strengthening es alimentaires (Lot 1) et de Single Stage - One E IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 19,974.46 Signé 2021-02-13 2021-03-11 2021-04-10 2021-04-02 2021-10-07 produits divers (Lot 2) pour l nvelope Investments a Centrale d'achat de Diougo p N° F_31302_2021 / Acquisiti Component 3: Strengthening Single Stage - One E on de drones suivie d'une for IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 12,972.75 Signé 2021-04-13 2021-03-31 2021-06-08 2021-04-26 2021-12-05 nvelope mation sur l’utilisation du ma Investments tériel Page 1 N° F_42104_2021 / Acquisiti on de fournitures de bureau ( Component 4: National Coor Single Stage - One E IDA / 62150 A posteriori Demande de prix Limited 25,388.44 Signé 2021-04-11 2021-03-29 2021-06-06 2021-04-28 2021-12-03 lot1), consommables informa dination nvelope tiques (lot 2) et produits d’en tretien (lot 3) F_32102_2021 / Acquisition de fournitures de bureau (lot 1), mobilier de bureau (lot 2), Component 3: Strengthening Single Stage - One E En attente d' matériel de bureau (lot 3), et IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-04-10 2021-06-05 2021-12-02 nvelope exécution matériel informatique (lot 4), Investments pour l’appui institutionnel de s commissions de gestion de s plaintes et des DREEC F_43102_21 / Acquisition et i Component 4: National Coor Single Stage - One E nstallation de bornes tactiles IDA / 62150 A posteriori Demande de prix Limited 1,733.32 Signé 2021-07-12 2021-09-03 2021-09-06 2021-10-27 2022-03-05 dination nvelope au profit du Projet WACA 42104 / Acquisition de fourni tures de bureau, de consom Component 4: National Coor Single Stage - One E En attente d' IDA / 62150 A posteriori Demande de prix Limited 0.00 2022-03-02 2022-04-27 2022-10-24 mables informatiques et de p dination nvelope exécution roduits d'entretiens pour le p rojet WACA 31103/F3-2022 / Acquisition Component 3: Strengthening Single Stage - One E En attente d' de drones et GPS au profit d IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-03-27 2022-05-22 2022-11-18 nvelope exécution e l'UGP WACA, pour la surveil Investments lance 31302/F1-2022 / Acquisition Component 3: Strengthening et Dotation d'une embarcatio En attente d' IDA / 62150 National Physical and Social A posteriori Demande de prix 0.00 2022-04-10 2022-06-05 2022-12-02 n motorisée à l'AMP-SL pour l exécution Investments es balades écotouristiques 31302/F2-2022 / Acquisition Component 3: Strengthening Single Stage - One E En attente d' de deux (02) quads et d'un ( IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-04-10 2022-06-05 2022-12-02 nvelope exécution 01) tricycle au profit de l'AMP Investments et du PNLB 31302/F4-2022 / Acquisition Component 3: Strengthening d'équipements les postes de Single Stage - One E En attente d' IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-04-10 2022-06-05 2022-12-02 garde de l'AMP et du PNLB (r nvelope exécution Investments éserve d'eau, équipements s olaire, etc.) 32101/F1-2021 / Acquisition Component 3: Strengthening et dotation en équipements Single Stage - One E En attente d' IDA / 62150 National Physical and Social A posteriori Demande de prix Limited 0.00 2022-03-23 2022-05-18 2022-11-14 d'aménagement et d'entretie nvelope exécution Investments n de la plage de Pilote Bar (G andiol) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S_2021_42105 / Maintenanc Component 4: National Coor Single Stage - One E IDA / 62150 A posteriori Demande de prix Limited 0.00 Annulé 2021-03-29 2021-05-24 2021-11-20 e des équipements du Projet dination nvelope WACA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF7-2018 / Sélection d'un ca binet d'étude pour l'élaborati Component 3: Strengthening Sélection fondée s on des TDRs d'études techni IDA / V1250 National Physical and Social A posteriori ur les qualification Open - National 48,356.12 Signé 2018-04-10 2018-05-16 2018-05-01 2018-06-14 2018-10-09 2018-07-14 2019-01-04 2018-08-18 2019-02-12 2019-02-14 ques et l'assistance au recrut Investments s des consultants ement des Cabinets devant r éaliser ces études. CF5-2018 / Sélection d'un ca binet pour l'élaboration des é Component 3: Strengthening Sélection fondée s Open - Internationa tudes de faisabilités et du pla IDA / V1250 National Physical and Social A priori ur la qualité et le 0.00 Annulé 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2021-06-09 l n d'adaptation des îles de l'e Investments coût stuaire du Fleuve Casamance CF8-2018 / Sélection d'un ca Component 2: Strengthening Sélection fondée s binet pour l'élaboration du Pl Open - Internationa IDA / V1250 the Policy and Institutional F A posteriori ur la qualité et le 0.00 Annulé 2019-11-20 2020-03-30 2019-12-11 2020-03-30 2020-01-24 2020-02-21 2020-03-22 2020-04-26 2020-05-31 2021-05-31 an national GIZC et du Plan l l ramework coût ocal de Ziguinchor 2.2.2 / Sélection d'un cabine Component 2: Strengthening Sélection fondée s t chargé de l'étude de faisabi IDA / V1250 the Policy and Institutional F A posteriori ur les qualification Limited 0.00 Annulé 2019-10-31 2019-11-14 2019-12-14 2020-01-18 2020-07-16 lité et design de l'Organe Nat ramework s des consultants ional de Gestion Intégré du Li ttoral (ONGIL) 31102 / Sélection d'un cabin Component 3: Strengthening Sélection fondée s et pour l'EIES et PAR pour G IDA / V1250 National Physical and Social A posteriori ur les qualification Open - National 0.00 Annulé 2020-04-22 2020-07-03 2020-05-13 2020-06-26 2020-07-26 2020-08-30 2021-02-26 orée et Corniches Investments s des consultants 3111 / Sélection d'un Cabine t pour les études techniques (APS, APD, DAO) et l’élaborat Component 3: Strengthening Sélection fondée s ion des Termes de Référence Open - Internationa IDA / V1250 National Physical and Social A posteriori ur la qualité et le 687,372.85 Signé 2019-12-18 2019-12-18 2020-01-08 2020-02-21 2020-05-06 2020-03-20 2020-06-25 2020-04-19 2020-08-13 2020-05-24 2020-09-17 2020-06-28 2020-11-17 2021-06-28 pour le contrôle des travaux l Investments coût des corniches Est et Ouest d e Dakar et l’île de Gorée et él aboration des tdrs pour le co ntrôle des travaux 221011 / Sélection d'un Cabi Component 2: Strengthening Sélection fondée s Open - Internationa IDA / V1250 A posteriori 459,445.87 Signé 2020-03-23 2020-03-23 2020-04-13 2020-05-27 2020-07-02 2020-06-24 2020-08-18 2020-07-24 2020-08-27 2020-08-28 2020-10-28 2020-10-02 2020-12-09 2021-10-02 net pour SNGIZC,PNGIZC et the Policy and Institutional F ur la qualité et le l ONGIL ramework coût 22101 / Sélection Firme : (i) l’actualisation de la SNGIZC, (ii) l’élaboration du PNGIZC, ( Component 2: Strengthening Sélection fondée s iii) la déclinaison du PNGIZC Open - Internationa IDA / V1250 the Policy and Institutional F A posteriori ur la qualité et le 0.00 Annulé 2020-04-10 2020-03-23 2020-05-01 2020-04-09 2020-06-14 2020-06-30 2020-07-12 2020-08-18 2020-08-11 2020-08-27 2020-09-15 2020-10-20 2021-10-20 dans les documents de planif l ramework coût ication et d’aménagement du territoire,locaux (iv) l’étude d e faisabilité de l’Organe Nati onal de Gestion Intégré Page 2 3.1.1 / Sélection d'un Cabine t pour les études techniques Component 3: Strengthening Sélection fondée s (APS, APD, DAO) et l’élaborat Open - Internationa IDA / V1250 National Physical and Social A posteriori ur la qualité et le 0.00 Annulé 2020-01-07 2019-12-18 2020-01-28 2020-01-08 2020-03-12 2020-05-14 2020-04-09 2020-06-25 2020-05-09 2020-08-13 2020-06-13 2020-07-18 2021-07-18 ion des Termes de Référence l Investments coût pour le contrôle des travaux des corniches Est et Ouest d e Dakar et l’île de Gorée Sélection fondée s 461075 / Assurances maladi Component 4: National Coor En cours d'exécut IDA / 62150 A posteriori ur les qualification Limited 0.00 2020-12-31 2021-01-20 2021-01-14 2021-02-13 2021-03-20 2021-09-16 e dination ion s des consultants 31104 / Sélection d’un Cons ultant//Cabinet pour la réalis Component 3: Strengthening Sélection fondée s ation de l’étude d’impact env IDA / 62150 National Physical and Social A posteriori ur les qualification Open - National 95,204.83 Signé 2020-06-30 2020-07-13 2020-07-21 2020-09-03 2020-09-01 2020-10-03 2021-01-04 2020-11-07 2021-01-04 2021-05-06 ironnemental et social des tr Investments s des consultants avaux de protection au nivea u de l’ile de Gorée 311103 / Sélection d’un Con sultant/Cabinet pour la réalis Component 3: Strengthening Sélection fondée s ation de l’étude d’impact env IDA / 62150 National Physical and Social A posteriori ur les qualification Open - National 131,720.47 Signé 2020-06-30 2020-07-03 2020-07-21 2020-09-03 2020-09-01 2020-10-03 2021-01-04 2020-11-07 2021-01-04 2021-05-06 ironnemental et social des tr Investments s des consultants avaux de stabilisation des co rniches Est et Ouest de Daka r 313026 / SELECTION D’UN C ONSULTANT POUR LA FORMA TION ET L’ENCADREMENT DE Component 3: Strengthening Sélection fondée s S MARAICHERS DE L’AIRE MA IDA / 62150 National Physical and Social A posteriori ur les qualification Limited 2,688.98 Signé 2020-09-21 2020-08-28 2020-10-05 2020-09-01 2020-11-04 2021-01-25 2020-12-09 2021-01-25 2021-06-07 RINE PROTEGEE COMMUNAU Investments s des consultants TAIRE DE SAINT-LOUIS SUR L ES TECHNIQUES DE MARAICH AGE AGROECOLOGIQUE 3.1.4.1 / Sélection d'un cabi Component 3: Strengthening Sélection fondée s net pour la réalisation de l'ét IDA / V1250 National Physical and Social A posteriori ur la qualité et le Open - National 0.00 Annulé 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2021-06-09 ude de faisabilité pour l'inves Investments coût tissement pour la petite côte et la grande côte 21302 / Sélection d'un Cabin et pour la mise en œuvre du Component 2: Strengthening Sélection fondée s En cours d'exame plan de renforcement des ca IDA / 62150 the Policy and Institutional F A posteriori ur les qualification Open - National 0.00 2022-03-15 2022-05-05 2022-04-05 2022-05-19 2022-06-18 2022-07-23 2023-01-19 n pacités (Comité de pilotage, ramework s des consultants comité technique, UGP...) 22101-2022 / Sélection d'un Component 2: Strengthening Sélection fondée s Cabinet pour élaborer l'Evalu En attente d'exéc IDA / 62150 the Policy and Institutional F A posteriori ur les qualification Open - National 0.00 2022-03-01 2022-03-22 2022-05-05 2022-06-04 2022-07-09 2023-01-05 ation Environnementale, Soci ution ramework s des consultants ale Stratégique de la SNGIZC 31103/C1-2022 / Sélection d 'un Cabinet pour la formation des acteurs impliqués dans l Component 3: Strengthening Sélection fondée s e CT de suivi: i)suivi biologiq En attente d'exéc IDA / 62150 National Physical and Social A posteriori ur les qualification Open - National 0.00 2022-02-13 2022-03-06 2022-04-19 2022-05-19 2022-06-23 2022-12-20 ue, (ii) techniques de détecti ution Investments s des consultants on et d'utilisation des capteu rs, ii) plongée sous-marine et iii) instruments de sauvegard es E& S de la Banque mondia le 32201/C1-2022 / Sélection d Component 3: Strengthening Sélection fondée s 'un Cabinet pour la réalisatio En attente d'exéc IDA / 62150 National Physical and Social A posteriori ur les qualification Open - National 0.00 2022-08-22 2022-09-12 2022-10-26 2022-11-25 2022-12-30 2023-06-28 n des études de faisabilité te ution Investments s des consultants chnique des sous-projets soci o-économiques 31107/C1 / Sélection d'un C Component 3: Strengthening Sélection fondée s Open - Internationa En cours d'exécut abinet chargé du contrôle de IDA / 62150 National Physical and Social A posteriori ur la qualité et le 0.00 2022-02-01 2022-02-10 2022-02-22 2022-02-10 2022-04-07 2022-05-05 2022-06-04 2022-07-09 2022-08-13 2023-08-13 l ion s travaux de protection de l'îl Investments coût e de Gorée CI-32102-22 / Sélection d'un cabinet pour la conception et Component 3: Strengthening Sélection fondée s En cours d'exécut la production des supports d IDA / 62150 National Physical and Social A posteriori ur les qualification Open - National 0.00 2022-01-25 2022-01-28 2022-02-15 2022-03-31 2022-04-30 2022-06-04 2022-12-01 ion e communication sur le méca Investments s des consultants nisme de gestion des plainte s 31502/C-2022 / Sélection d' un cabinet chargé de la réali Component 3: Strengthening Sélection fondée s En attente d'exéc sation des études d'impact e IDA / 62150 National Physical and Social A posteriori ur les qualification Limited 0.00 2022-03-15 2022-03-29 2022-04-28 2022-06-02 2022-11-29 ution nvironnementales et sociale ( Investments s des consultants EIES) pour la protection du lit toral de MBAO 31501 / Sélection d'un consu ltant en charge de la réalisati Component 3: Strengthening Sélection fondée s on des études techniques AP IDA / 62150 National Physical and Social A posteriori ur les qualification Open - National 0.00 Annulé 2021-11-30 2021-12-16 2021-12-21 2022-02-03 2022-03-05 2022-04-09 2022-10-06 S, APD, DAO et le contrôle de Investments s des consultants s travaux de protection côtiè re du littoral de Mbao. 31501_ / Sélection d’un Cabi net en charge de la réalisatio n des études APS, APD, DAO Component 3: Strengthening Sélection fondée s En cours d'exécut et de l’élaboration des terme IDA / 62150 National Physical and Social A posteriori ur les qualification Open - National 0.00 2022-03-09 2022-03-03 2022-03-30 2022-05-13 2022-06-12 2022-07-17 2023-01-13 ion s de référence pour la sélecti Investments s des consultants on d’un cabinet chargé du co ntrôle des travaux de protect ion côtière du littoral de Mba o 31107 / Sélection d'un cabin et Chargé du contrôle des tra Component 3: Strengthening Sélection fondée s Open - Internationa En cours d'exécut vaux de stabilisation des Cor IDA / 62150 National Physical and Social A posteriori ur la qualité et le 0.00 2022-02-22 2022-01-31 2022-03-15 2022-02-10 2022-04-28 2022-05-26 2022-06-25 2022-07-30 2022-09-03 2023-09-03 l ion niches Est et Ouest de Dakar Investments coût : site de l'Université Cheikh A nta DIOP de Dakar 31401 / Sélection d'un cabin Component 3: Strengthening Sélection fondée s En attente d'exéc et chargé du suivi du trait côt IDA / 62150 National Physical and Social A posteriori ur les qualification Open - National 0.00 2022-06-21 2022-07-12 2022-08-25 2022-09-24 2022-10-29 2023-04-27 ution e Investments s des consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI1-2017 / PSélection d'un(e ) Consultant(e) individuel(le) pour élaborer un Cadres De Gestion Environnementale et Component 4: National Coor IDA / V1250 A posteriori Individuel Limited 50,075.58 Signé 2017-09-04 2017-06-12 2017-09-09 2017-06-23 2017-09-30 2017-07-10 2017-11-04 2017-07-10 2018-05-03 Sociale (CGES) sur la zone cô dination tière et une étude d'impact e nvironnementale et sociale ( EIES) sur la repress and repli cation of the textbooks for sc hools Page 3 CI2-2018 / Recrutement d'un (e) Consultant(e) individuel(l Component 4: National Coor IDA / V1250 A posteriori Individuel Limited 30,045.35 Signé 2017-10-05 2017-07-04 2017-10-10 2017-07-03 2017-10-31 2017-07-10 2017-12-05 2018-02-20 2018-06-03 e) pour élaborer un Cadre de dination Politique de Réinstallation (C PR) CI4-2017 / Sélection d'un co Component 4: National Coor nsultant individuel spécialist IDA / V1250 A posteriori Individuel Limited 64,711.65 Signé 2017-11-17 2017-09-05 2017-11-22 2017-07-04 2017-12-13 2017-12-06 2018-01-17 2017-12-06 2018-07-16 dination e en passation de marchés (a u temps passé) CI3-2018 / Sélection d'un co nsultant pour l'élaboration du Component 4: National Coor manuel d'exécution du projet IDA / V1250 A posteriori Individuel Limited 19,553.16 Signé 2017-12-06 2017-12-28 2017-12-11 2017-12-23 2018-01-01 2018-01-22 2018-02-05 2018-01-22 2018-08-04 dination et du manuel de procédures f inancières et administratives CI14-2018 / Sélection d'un C onsultant Individuel pour le D iagnostic Institutionnel, tech Component 4: National Coor IDA / V1250 A posteriori Individuel Limited 17,832.00 Signé 2018-05-15 2019-02-22 2018-05-20 2019-03-14 2018-06-10 2019-03-15 2018-07-15 2019-05-06 2019-01-11 nique et organisationnel de l' dination Inspection du Ministère de l'E nvironnement et du Dévelop pement Durable (MEED) CI13-2018 / Sélection d'un C Component 3: Strengthening onsultant Individuel pour l'El IDA / V1250 National Physical and Social A posteriori Individuel Limited 14,567.44 Signé 2018-05-08 2018-02-05 2018-05-13 2018-06-13 2018-06-03 2018-06-21 2018-07-08 2018-06-21 2019-01-04 aboration d'un Manuel de Sui Investments vi-Evaluation 3141 / Etude de faisabilité p our une solution d'adaptation Component 3: Strengthening Sélection de cons Direct - Internation aux changements climatique IDA / V1250 National Physical and Social A posteriori ultants par entent 0.00 Annulé 2019-05-23 2018-10-31 2019-05-30 2019-06-14 2019-07-14 al s en zone côtière pour la gra Investments e directe nde Côte et la petite Côte 4.1.4 / Sélection d'un consul Component 2: Strengthening IDA / V1250 A posteriori Individuel Limited 37,840.94 Signé 2019-07-18 2019-11-29 2019-07-23 2020-07-27 2019-08-13 2020-01-02 2019-09-17 2020-01-02 2020-03-15 tant individuel en suivi-évalu the Policy and Institutional F ation ramework 2.1.3 / Élaboration du plan d Component 2: Strengthening IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2019-10-21 2019-10-26 2019-11-16 2019-12-21 2020-06-18 e renforcement des capacité the Policy and Institutional F s ramework 4.1.8 / Sélection d'un consul Component 4: National Coor IDA / V1250 A posteriori Individuel Limited 47,177.28 Signé 2020-01-31 2020-05-13 2020-02-05 2020-05-19 2020-02-26 2020-06-23 2020-04-01 2020-06-26 2020-09-28 tant individuel en Génie Civil dination 41110 / Sélection d'un Cons Component 4: National Coor ultant Individuel en Passation IDA / V1250 A posteriori Individuel Direct 32,129.10 Signé 2020-01-07 2017-07-04 2020-01-17 2020-01-02 2020-02-07 2020-01-02 2020-03-13 2020-01-02 2020-09-09 dination des Marchés 31303 / Sélection d'un Cons Component 3: Strengthening ultant Individuel en vue de l' IDA / V1250 National Physical and Social A posteriori Individuel Limited 14,279.60 Signé 2020-04-15 2020-07-20 2020-04-20 2020-07-30 2020-05-11 2020-08-17 2020-06-15 2020-08-19 2020-12-12 évaluation environnementale Investments pour la relance de l'écotouris me 21501 / Sélection d'un Cons ultant Individuel pour la revu Component 2: Strengthening e du cadre réglementaire rel IDA / V1250 the Policy and Institutional F A posteriori Individuel Limited 35,342.01 Signé 2020-05-06 2020-12-07 2020-05-11 2020-07-23 2020-06-01 2020-09-02 2020-07-06 2020-09-07 2021-01-02 ativement aux protocoles ad ramework ditionnels de la Convention d 'Abidjan 41509 / Sélection directe po Sélection de cons ur l’acquisition d'un logiciel d Component 4: National Coor IDA / V1250 A posteriori ultants par entent Direct 9,562.33 Signé 2020-04-21 2020-02-10 2020-05-01 2020-04-03 2020-07-05 2020-06-08 2021-01-01 e programmation et de suivi- dination e directe évaluation Multi-Projet « Ruc he » 2.1.5 / Sélection d'un Consul tant chargé de l'établisseme Component 2: Strengthening nt des critères de sélection e IDA / V1250 the Policy and Institutional F A posteriori Individuel Limited 0.00 Annulé 2019-09-18 2019-09-23 2019-10-14 2019-11-18 2020-05-16 t d'attribution des bourses du ramework master GAED pour la gestion des risques liés aux activités pétrolières et gazières 4.1.15 / Sélection d'un consu ltant individuel expert social j Component 4: National Coor IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2019-10-10 2020-04-09 2019-10-15 2019-11-05 2019-12-10 2020-06-07 unior en charge du mécanis dination me de gestion des plaintes CF2-2018 / Sélection d'un ob Component 2: Strengthening Sélection de cons servatoire de référence pour IDA / V1250 the Policy and Institutional F A posteriori ultants par entent Direct 0.00 Annulé 2019-11-27 2020-02-11 2019-12-07 2020-02-10 2020-08-08 l'accompagnement et la mise ramework e directe en place de l'observatoire na tional du littoral 41107 / Sélection d'un Cons Component 4: National Coor ultant Individuel spécialiste e IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2020-05-04 2020-05-09 2020-05-30 2020-07-04 2020-12-31 dination n gestion pétrolière et gazièr e offshore 4.1.9 / Sélection d'un consul Component 4: National Coor tant individuel en Développe IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2019-11-04 2019-11-09 2019-11-30 2020-01-04 2020-07-02 dination ment Institutionnel 41109 / Sélection d'un Cons Component 4: National Coor ultant Individuel spécialiste e IDA / V1250 A posteriori Individuel Limited 0.00 Annulé 2020-05-18 2020-05-23 2020-06-13 2020-07-18 2021-01-14 dination n développement institutionn el 31402 / Sélection d'un Cons ultant Individuel pour l'élabor Component 3: Strengthening ation d'un document de proje IDA / V1250 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2020-05-06 2020-05-11 2020-06-01 2020-07-06 2021-01-02 t relatif à la réparation aux in Investments vestissements additionnel 4110 / Sélection d'un consul Sélection de cons Component 4: National Coor tant individuel en passation d IDA / 62150 A posteriori ultants par entent Direct 32,672.34 Signé 2021-01-18 2020-12-22 2021-01-28 2020-12-28 2021-04-03 2021-01-04 2021-09-30 dination es marchés e directe 313025 / SELECTION D’UN C ONSULTANT POUR LA FORMA TION DES FEMMES DU PNLB SUR LES TECHNIQUES AMELI Component 3: Strengthening OREES DE TRANSFORMATION IDA / 62150 National Physical and Social A posteriori Individuel Limited 2,708.64 Signé 2021-01-19 2021-02-04 2021-01-24 2021-03-03 2021-02-14 2021-06-21 2021-03-21 2021-06-21 2021-09-17 DES PRODUITS HALIEUTIQUE Investments S ET L’APPUI A LA MAITRISE D’ŒUVRE DU PROJET DE VAL ORISATION DES ARCHES DU VILLAGE DE MOUBAYE Page 4 CI_2021_32102 / Sélection d' un consultant individuel char Component 3: Strengthening gé de l'élaboration d'une étu IDA / 62150 National Physical and Social A posteriori Individuel Limited 14,341.20 Signé 2021-03-19 2021-04-01 2021-03-24 2021-06-15 2021-04-14 2021-07-15 2021-05-19 2021-07-14 2021-11-15 de sur la situation de référen Investments ce genre dans les zones d'int ervention du Projet WACA SD_42109_2021 / Acquisitio Sélection de cons Component 4: National Coor n et installation d'un Logiciel IDA / 62150 A posteriori ultants par entent Direct 5,371.74 Signé 2021-04-05 2021-04-15 2021-04-15 2021-05-17 2021-06-19 2021-05-20 2021-12-16 dination TOMPRO/Etats Financiers e directe SD-32103-1 / Sélection direc Component 3: Strengthening Sélection de cons te avec la RTS2, pour la visib En cours d'exécut IDA / 62150 National Physical and Social A posteriori ultants par entent Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 ilité et la vulgarisation des ac ion Investments e directe tivités du du Projet WACA SD-32103-2 / Sélection direc Component 3: Strengthening Sélection de cons te avec Le groupe Futurs Mé En cours d'exécut IDA / 62150 National Physical and Social A posteriori ultants par entent Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 dias pour la visibilité et la vul ion Investments e directe garisation des activités du Pr ojet WACA SD-32103-3 / Sélection direc Component 3: Strengthening Sélection de cons te avec la Radio SUD FM pour En cours d'exécut IDA / 62150 National Physical and Social A posteriori ultants par entent Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 la visibilité et la vulgarisation ion Investments e directe des activités du Projet WACA SD-32103-4 / Sélection direc Component 3: Strengthening Sélection de cons En cours d'exécut te avec l'Union des Radios As IDA / 62150 National Physical and Social A posteriori ultants par entent Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 ion sociatives et Communautaire Investments e directe s (URAC) SD-32103-5 / Sélection direc Component 3: Strengthening Sélection de cons te avec la voix du Littoral po En cours d'exécut IDA / 62120 National Physical and Social A posteriori ultants par entent Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 ur la visibilité et la vulgarisati ion Investments e directe on des activités du Projet WA CA SD-32103-6 / Sélection Direc Component 3: Strengthening Sélection de cons En cours d'exécut te avec Le site en ligne Daka IDA / 62150 National Physical and Social A posteriori ultants par entent Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 ion r actu Investments e directe SD-32103-7 / Sélection direc Component 3: Strengthening Sélection de cons te avec le Groupe Walfadjri p En cours d'exécut IDA / 62150 National Physical and Social A posteriori ultants par entent Direct 0.00 2021-05-24 2021-06-30 2021-06-03 2021-08-07 2022-02-03 our la visibilité et la vulgarisa ion Investments e directe tion des activités du Projet W ACA CI_2021_45106 / Sélection d' Component 4: National Coor un consultant individuel pour IDA / 62150 A posteriori Individuel Limited 63,070.70 Signé 2021-06-03 2021-06-04 2021-06-08 2021-06-23 2021-06-29 2021-07-15 2021-08-03 2021-07-15 2022-01-30 dination la revue à mi-parcours du Pro jet WACA SD_2021_4117 / Sélection Di Sélection de cons recte d'un Cabinet chargé du Component 4: National Coor IDA / 62150 A posteriori ultants par entent Direct 0.00 Annulé 2021-06-09 2021-06-07 2021-06-19 2021-06-15 2021-08-23 2022-02-19 recrutement d'un comptable dination e directe pour le Projet WACA CI_43102_21 / Sélection d'un Consultant Individuel pour la Component 4: National Coor En cours d'exécut IDA / 62150 A posteriori Individuel Limited 0.00 2021-07-07 2001-10-31 2021-07-12 2021-08-02 2021-09-06 2022-03-05 conception et la mise en œu dination ion vre de la communication digi tale SD-41101-2021 / Sélection d Sélection de cons irecte d'un cabinet chargé du Component 4: National Coor En attente d'exéc IDA / 62150 A posteriori ultants par entent Direct 0.00 2021-12-30 2022-01-09 2022-03-15 2022-09-11 recrutement de quatre exper dination ution e directe ts de l'UGP du Projet WACA 32102/CI1-2022 / Sélection Component 3: Strengthening d'un consultant individuel po En attente d'exéc IDA / 62150 National Physical and Social A posteriori Individuel Limited 0.00 2022-08-05 2022-08-10 2022-08-31 2022-10-05 2023-04-03 ur la formation des acteurs d ution Investments u MGP sur les VBG/HS/EAS CI-32102-21 / Sélection d'un consultant individuel pour la Component 3: Strengthening conception et la production d IDA / 62150 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2021-05-24 2021-10-31 2021-05-29 2021-06-19 2021-07-24 2022-01-20 es supports de communicatio Investments n sur le mécanisme de gestio n des plaintes Page 5