PROCUREMENT PLAN (Textual Part) Project information: ARAB REPUBLIC OF EGYPT, EGYPT: GREATER CAIRO AIR POLLUTION MANAGEMENT AND CLIMATE CHANGE PROJECT Project Implementation agency: Ministry of Environment Date of the Procurement Plan: 25 August 2020 Period covered by this Procurement Plan: First 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Completio Expecte Contract Contract Estimat Bank Selectio award d # Contract Description ed Cost Oversig Market Approach n Type n Launch $ ht Method Date Component 1: Enhancing the Air Quality Management (AQM) & Response System USD 4.53 M 1 Integrated Climate and Air Open/ RFP Jun 21 Dec Consulting Quality Management “Action” 0.43 M Post International 21 Services Plan 2 Establishing an Open/ RFP Sep 20 Jan Consulting integrated emission International 21 Services inventory database for Greater pollution emission inventory, and its integration with SLCP and 0.5 M Post GHG emissions inventory Cairo and Egypt: Technical Support Contract for EEAA to support the refinement of existing air 3 Establishing an Open/ RFB Sep 20 Jan Consulting SLCP/GHG monitoring International 21 Services network for Greater Cairo: Technical support contract for EEAA to provide 1.5 M Post recommendations on the deployment, operation and maintenance of proposed network. 4 AQ Skills Training and U. Open/ RFP Jun 21 Dec Consulting 0.7 M Post Curriculum Development International 21 Services 5 Economic/BCA Analysis Open/ RFP Jun 21 Dec Consulting 0.6 M Post International 21 Services 6 Equipment for Improving Air Open/ RFB Jan 21 Jul Goods 0.4 M Post Quality Forecasting International 21 7 Integrating and analyzing the Open/ RFP Aug 21 Feb Consulting 0.1 M Post air quality forecasting data International 22 Services Completio Expecte Contract Contract Estimat Bank Selectio award d # Contract Description ed Cost Oversig Market Approach n Type n Launch $ ht Method Date 8 Establishing institutional Open/ RFP Dec 21 Jun Consulting response mechanisms to high 0.3 M Post International 22 Services pollution days Component 2: Support the operationalization of SWM Master Plans in Greater Cairo USD 96 M 9 Preparation of detailed Open/ National RFP Sep 20 Oct Consulting engineering design & bidding 20 Services documents for 10th of Ramadan 0.35 M Post infrastructure and MSW landfill (including supervision) 10 Infrastructure construction Open/ RFB Dec 20 Apr Works 15.5 M Prior works for 10th of Ramadan International 21 11 MSW landfill construction works Open/ RFB Jan 21 Jun Design, build 20.5 M Prior for 10th of Ramadan International 21 and operate 12 Project management and Open/ RFP Oct 20 Mar Consulting supervision consultant for the International 21 Services 10th of Ramadan planning, 1.7 M Post management and monitoring of works and major technical assistance 13 10th of Ramadan- Open/National RFP Oct 20 April Consulting Construction and 21 Services demolition waste facility: Preparation of a bidding document, 1.5 M Post following a Design, Build and Operate modality, on the basis of analysis and studies prepared by MoE. 14 Consulting service to prepare, Open/ RFP Dec 20 Jun Consulting the detailed engineering study, International 21 Services bidding documents and to 1.2 M Post supervise closing and rehabilitation of Abou Zaabal 15 Consulting service to prepare, Open/ RFP Sep 20 Feb Consulting 1.8 M Post detailed feasibility study, International 21 Services Completio Expecte Contract Contract Estimat Bank Selectio award d # Contract Description ed Cost Oversig Market Approach n Type n Launch $ ht Method Date bidding documents, contracts, safeguard documents and to supervise the hazardous waste treatment and final disposal facility 16 Infrastructure construction wor RFP Nov 21 Jun Design, Build ks for final disposal facility 19 M Prior Open/ 22 and Operate International 17 Consulting service to prepare, RFP Nov 20 May Consulting the detailed engineering study, Open/ 21 Services bidding documents, safeguard 0.3 M Post International documents and to supervise to construct the transfer stations. 18 Infrastructure construction Open/ RFP Nov 21 Apr 5M Prior work for transfer stations. International 22 Works 19 Feasibility study for the Open/ RFP May 21 Aug Consulting environmental upgrade of El- 2M Post International 21 Services Akrasha Area, Qalyubia. 20 Technical assistance for Open/ RFP May 21 Aug Consulting establishing and/or improving 4M Post International 21 Services waste management systems 21 Provision of steam sterilization Open/ RFB Jun 21 Dec Goods equipment (autoclaves) COVID- 7.5 M Prior International 21 19 23 Provision of personal protective Open/ Local RFP Consulting equipment for enhanced safety Dec 20 Apr Services and security in solid waste 21 0.3 M Post collection – including identification of target groups and needs assessment 25 System development and Open/ RFP Consulting training for healthcare staff on International Services 2.2 M Post safe handling, transport, and April Sep disposal of healthcare waste 21 21 24 Institutional support to solid Open/ RFB Goods waste management agencies International Dec 20 Apr Prior (MoE, MoLD and SW Unit in 4M 21 Qalyubia Governorate) Completio Expecte Contract Contract Estimat Bank Selectio award d # Contract Description ed Cost Oversig Market Approach n Type n Launch $ ht Method Date Component 3: Vehicle Emission Reduction USD 4 M 26 Study for electric bus routes Open/ RFP Sep 20 Nov Consulting 0.5 M Prior (detailed Designs) International 20 Services 27 Retrofitting of existing bus Open/ RFP Apr 21 Jul Works 3.5 M Prior depot International 21 28 Procurement of e-buses Open/ RFB May 21 Sep Goods 30 M Prior International 21 Component 4: Stakeholders engagement, awareness raising and communication USD 1.91 M 29 Political economy analysis, Open/ RFP Nov 20 Feb Consulting stakeholder mapping and 0.2 M Post International 21 Services consultation 30 Implementation of SEP Open/ RFP Feb 21 May Consulting 0.45 M Post activities International 21 Services 31 Development and Open/ RFP Feb 21 May Consulting implementation of 0.22 M Post International 21 Services communication plans 32 Behavior change - community Open/ RFP Mar 21 Jun Consulting based social marketing 0.28M Post International 21 Services interventions (CBSM) 33 Implementation of priority AQM Open/ RFP Mar 21 Jun Consulting 0.22 M Post awareness campaigns International 21 Services 34 Pilot activities with NGOs, CSOs Open/ national RFP May 21 Aug Consulting 0.32 M Post 21 Services 35 Communication material, Open/Internatio RFP May 21 Aug Consulting 0.22M Post knowledge products nal 21 Services Component 5: Project Management and Monitoring & Evaluation USD 1.9 M 36 Individual consultants to Open/ RFP Sep 20 Oct Consulting 0.2 M Post support the PCU International 20 Services 37 Procurement of office furniture Open/ RFQ Sep 20 Sep Goods 0.2 M Post and IT equipment for PCU National 20 PROCUREMENT Egypt, Arab Republic of : Greater Cairo Air Pollution Management and Climate Change Project PLAN General Information Country: Egypt, Arab Republic of 2021-04-29 Bank’s Approval Date of the Original Procurement Plan: 2022-11-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172548 GPN Date: Project Name: Greater Cairo Air Pollution Management and Climate Change Project Loan / Credit No: IBRD / 91660 Egyptian Environmental Affairs Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B EG-EEAA-326981-CW-RFB / Support the Operationalizati ids - Works ( Works of the Primary Infrastr Open - Internationa Single Stage - One E Pending Imp 2024-11-0 IBRD / 91660 on of SWM Master Plans in G Prior Request for Bids without preq 0.00 2022-11-30 2022-12-05 2023-01-16 2023-05-16 2023-06-20 ucture of the 10th of Ramada l nvelope lementation 1 reater Cairo ualification) n Integrated Solid Waste Man SPD agement Facility GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-EEAA-273227-GO-RFQ / I Project Management and Mo Request for Quota Single Stage - One E IBRD / 91660 Post Limited 31,552.04 Signed 2022-02-01 2022-01-23 2022-03-29 2022-02-15 2022-09-25 T - Equipment nitoring & Evaluation tions nvelope EG-EEAA-298113-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E Under Imple IBRD / 91660 Post Open - National 0.00 2022-07-13 2022-08-10 2022-09-09 roject Vehicle nitoring & Evaluation tions nvelope mentation EG-EEAA-302306-GO-RFQ / P Support the Operationalizati Request for Quota Single Stage - One E Under Imple IBRD / 91660 Post Limited 0.00 2022-07-07 2022-07-31 2022-07-31 2022-08-31 roject Office Furniture on of SWM Master Plans in G tions nvelope mentation reater Cairo EG-EEAA-302310-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E Under Imple IBRD / 91660 Post Limited 0.00 2022-07-07 2022-08-22 2022-08-07 2022-09-06 roject Office Air Condition nitoring & Evaluation tions nvelope mentation EG-EEAA-302313-GO-RFQ / I Support the Operationalizati Request for Quota Single Stage - One E Pending Impl T Equipment for MOLD, Cairo IBRD / 91660 on of SWM Master Plans in G Post Limited 0.00 2022-07-12 2022-08-15 2022-09-14 tions nvelope ementation and Qualubeya Governorates reater Cairo NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-EEAA-170002- CS-QCBS / Maximize the newly establish Support the Operationalizati Quality And Cost- Open - Internationa ed WMRA financial resources IBRD / 91660 on of SWM Master Plans in G Post 73,455.52 Signed 2021-04-21 2021-04-20 2021-04-21 2021-05-04 2021-05-04 2021-06-10 2021-05-18 2021-07-07 2021-05-19 2021-07-07 2021-05-20 2021-07-11 2021-05-24 2021-08-09 2021-11-17 Based Selection l in line with the most recent reater Cairo Waste Management Regulati on Law No. 202 of 2020 EG-EEAA-170001- CS-QCBS / Project Management and Mo Quality And Cost- IBRD / 91660 Post Open - National 0.00 Canceled 2021-04-21 2021-04-30 2021-04-25 2021-05-04 2021-05-10 2021-05-30 2021-05-30 2021-06-03 2021-07-01 2022-07-01 Project Coordinator nitoring & Evaluation Based Selection EG-EEAA-239496-CS-QCBS / Consultancy for 10th of Ram adan for the Integrated Wast Support the Operationalizati e Management Facility Quality And Cost- IBRD / 91660 on of SWM Master Plans in G Post Open - National 115,849.41 Signed 2021-06-16 2021-06-30 2021-06-17 2021-06-30 2021-07-08 2021-09-21 2021-08-29 2021-11-07 2021-08-29 2021-11-30 2021-09-09 2022-01-02 2021-10-10 2022-02-02 2022-01-10 Preparation of Detailed Engin Based Selection reater Cairo eering Design and Tender Do cuments for Basic Infrastructure & Site Supervision of Construction Works EG-EEAA-252242-CS-QCBS / Electric Bus (e-bus) Demonst Quality And Cost- Open - Internationa Under Implement ration Project Detailed Planni IBRD / 91660 Vehicle Emissions Reduction Prior 0.00 2021-09-16 2021-10-20 2021-10-07 2021-11-17 2021-11-20 2022-02-08 2022-01-04 2022-03-27 2022-01-04 2022-06-26 2022-02-08 2022-11-17 2022-02-27 2023-05-30 Based Selection l ation ng and Design Study for Cair o Transport Authority (CTA) EG-EEAA-247116-CS-QCBS / Management and Technical S upport Consultant for AQM - advisory services and technic Enhancing the Air Quality M Quality And Cost- Open - Internationa Under Implement al assistance in managing an IBRD / 91660 anagement & Response Syst Prior 0.00 2021-09-16 2021-10-13 2021-09-22 2021-11-11 2021-10-27 2022-01-17 2021-12-11 2022-03-10 2021-12-11 2022-04-21 2021-12-22 2022-01-26 2026-07-11 Based Selection l ation d implementing the project a em cross a range of topics relate d to AQM planning to address air pollution and climate miti gation in Greater Cairo. EG-EEAA-273225-CS-QCBS / Project Structuring and Trans Support the Operationalizati action Advisory Services for t Quality And Cost- Open - Internationa Under Implement IBRD / 91660 on of SWM Master Plans in G Post 0.00 2022-01-20 2022-01-18 2022-02-10 2022-03-31 2022-03-26 2022-07-08 2022-04-23 2022-08-18 2022-05-23 2022-10-05 2022-06-27 2022-08-01 2023-08-01 he establishment of an Integr Based Selection l ation reater Cairo ated Solid Waste Manageme nt Facility for Qalyubia Gover norate EG-EEAA-273226-CS-QCBS / Support the Operationalizati Management and Technical S Quality And Cost- Open - Internationa Under Implement IBRD / 91660 on of SWM Master Plans in G Prior 0.00 2022-01-20 2022-03-21 2022-02-10 2022-03-31 2022-03-26 2022-07-26 2022-04-23 2022-09-08 2022-05-23 2022-10-17 2022-06-27 2022-08-01 2025-08-01 upport for Solid Waste Mana Based Selection l ation reater Cairo gement Component EG-EEAA-273277-CS-FBS / M Enhanced Capacity, Behavio Quality And Cost- IBRD / 91660 Post Open - National 0.00 Canceled 2022-02-06 2022-02-27 2022-04-12 2022-05-10 2022-06-09 2022-07-14 2022-08-18 2025-08-18 edia and Branding ral Change and Communicat Based Selection ion EG-EEAA-289919-CS-CQS / T Project Management and Mo Consultant Qualifi Under Implement IBRD / 91660 Post Limited 0.00 2022-04-14 2022-06-02 2022-04-21 2022-04-28 2022-05-15 2023-05-15 ranslation Service nitoring & Evaluation cation Selection ation Page 1 EG-EEAA-289928-CS-CQS / E Enhancing the Air Quality M Consultant Qualifi Pending Impleme IBRD / 91660 Post Limited 0.00 2022-04-24 2022-05-08 2022-06-07 2022-07-12 2023-07-12 SIA Advisory Services anagement & Response Syst cation Selection ntation em EG-EEAA-292985-CS-CQS / Enhanced Capacity, Behavio Consultant Qualifi Under Implement IBRD / 91660 Post Limited 0.00 2022-05-01 2022-05-16 2022-05-15 2022-06-14 2022-07-19 2023-07-19 Media and Branding (1) ral Change and Communicat cation Selection ation ion EG-EEAA-308070-CS-LCS / E Project Management and Mo Least Cost Selecti Under Implement IBRD / 91660 Post Open - National 0.00 2022-08-14 2022-08-15 2022-09-04 2022-09-25 2022-10-18 2022-11-15 2022-12-15 2023-01-19 2023-02-23 2025-03-02 xternal Financial Audit nitoring & Evaluation on ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-EEAA-233536-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Open 53,554.35 Signed 2021-05-10 2021-04-30 2021-06-14 2021-07-07 2021-06-16 2021-07-28 2021-07-01 2021-08-19 2022-07-31 Project Coordinator nitoring & Evaluation ant Selection EG-EEAA-244229-CS-CDS / S Project Management and Mo IBRD / 91660 Post Direct Selection Direct 35,143.95 Signed 2021-07-16 2021-07-27 2021-07-26 2021-08-16 2021-08-01 2021-08-19 2022-08-01 enior Procurement Specialist nitoring & Evaluation EG-EEAA-244233-CS-CDS / S Project Management and Mo enior Legal and Governance IBRD / 91660 Post Direct Selection Direct 40,303.53 Signed 2021-07-18 2021-07-27 2021-07-28 2021-08-16 2021-08-01 2021-08-19 2022-08-01 nitoring & Evaluation Professional EG-EEAA-244235-CS-CDS / S Support the Operationalizati IBRD / 91660 Post Direct Selection Direct 40,303.53 Signed 2021-07-18 2021-07-27 2021-07-28 2021-08-16 2021-08-01 2021-08-19 2022-08-01 enior Waste Management Pro on of SWM Master Plans in G fessional reater Cairo EG-EEAA-250539-CS-INDV / Enhancing the Air Quality M Individual Consult IBRD / 91660 Post Limited 18,479.21 Signed 2021-08-30 2021-08-31 2021-09-06 2021-08-15 2021-09-12 2021-08-20 2021-09-17 2021-09-01 2022-09-17 Environmental Specialist anagement & Response Syst ant Selection em EG-EEAA-253220-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 37,211.67 Signed 2021-09-21 2021-10-01 2021-09-26 2021-09-01 2021-09-29 2021-09-15 2021-10-04 2021-10-23 2022-09-29 Senior Financial Specialist nitoring & Evaluation ant Selection EG-EEAA-253223-CS-INDV / Project Management and Mo Individual Consult Pending Impleme IBRD / 91660 Post Limited 0.00 2021-09-21 2021-09-23 2021-09-26 2021-10-01 2022-09-29 Secretary nitoring & Evaluation ant Selection ntation EG-EEAA-253225-CS-INDV / Project Management and Mo Individual Consult Pending Impleme IBRD / 91660 Post Limited 0.00 2021-09-21 2021-09-26 2021-09-28 2021-10-04 2022-09-29 Project Assistant nitoring & Evaluation ant Selection ntation EG-EEAA-253333-CS-CDS / P reparation of Environmental Support the Operationalizati and social instrument for the IBRD / 91660 on of SWM Master Plans in G Post Direct Selection Direct 24,626.86 Signed 2021-09-26 2022-03-14 2021-10-06 2022-05-08 2021-10-31 2022-06-01 2022-04-29 10th of Ramadan Basic Infras reater Cairo tructure of the Integrated Wa ste Management Facility pac kage EG-EEAA-253222-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 0.00 Canceled 2022-01-15 2022-01-25 2022-01-20 2022-02-10 2022-01-24 2022-02-15 2022-02-01 2023-01-31 Senior Procurement Specialis nitoring & Evaluation ant Selection t (2) EG-EEAA-250536-CS-INDV / Enhancing the Air Quality M Individual Consult Social Development and Gen IBRD / 91660 anagement & Response Syst Post Open 14,362.93 Signed 2022-01-05 2021-10-07 2022-02-23 2021-11-21 2022-02-25 2022-02-26 2022-03-12 2022-05-26 2023-03-11 ant Selection der Specialist em EG-EEAA-271141-CS-INDV / Enhanced Capacity, Behavio Individual Consult IBRD / 91660 Post Open 0.00 Canceled 2021-12-30 2022-01-18 2022-02-17 2022-03-10 2022-04-01 2023-03-30 Communication Senior Advis ral Change and Communicat ant Selection or ion EG-EEAA-253428-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 8,533.92 Signed 2021-12-30 2022-01-18 2022-01-04 2022-01-27 2022-01-09 2022-01-27 2022-01-16 2022-04-18 2023-01-15 Operational Manual Preparati nitoring & Evaluation ant Selection on EG-EEAA-286893-CS-INDV / Technical Evaluation Consult ant - Electric Bus (e-bus) De Individual Consult IBRD / 91660 Vehicle Emissions Reduction Post Limited 2,056.39 Signed 2022-03-26 2022-04-05 2022-03-27 2022-04-08 2022-03-29 2022-04-08 2022-03-30 2022-04-10 2022-04-30 monstration Project Detailed ant Selection Planning and Design Study fo r Cairo Transport Authority (C TA) EG-EEAA-288479-CS-INDV / Technical Evaluation Consult ant (2) - Electric Bus (e-bus) Individual Consult IBRD / 91660 Vehicle Emissions Reduction Post Limited 1,503.92 Signed 2022-04-06 2022-04-10 2022-04-07 2022-04-13 2022-04-07 2022-04-12 2022-04-10 2022-04-14 2022-05-10 Demonstration Project Detail ant Selection ed Planning and Design Stud y for Cairo Transport Authorit y (CTA) EG-EEAA-291298-CS-INDV / Enhanced Capacity, Behavio Individual Consult IBRD / 91660 Post Limited 14,023.09 Signed 2022-04-24 2022-04-27 2022-05-15 2022-08-07 2022-05-19 2022-08-07 2022-06-01 2022-09-01 2023-05-28 Communication Specialist ral Change and Communicat ant Selection ion EG-EEAA-298186-CS-CDS / S Support the Operationalizati Under Implement IBRD / 91660 Post Direct Selection Direct 0.00 2022-06-05 2022-08-15 2022-06-12 2022-06-15 2023-06-15 olid Waste Management Con on of SWM Master Plans in G ation sultant reater Cairo EG-EEAA-302288-CS-INDV / Project Management and Mo Individual Consult Under Implement IBRD / 91660 Post Limited 0.00 2022-07-14 2022-08-07 2022-07-17 2022-07-24 2022-08-10 2023-08-09 M&E Specialist nitoring & Evaluation ant Selection ation EG-EEAA-308069-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 28,842.66 Signed 2022-08-07 2022-07-15 2022-08-07 2022-06-15 2022-08-07 2022-06-15 2022-08-07 2022-07-19 2023-07-31 2. Senior Procurement Specia nitoring & Evaluation ant Selection list EG-EEAA-310322-CS-CDS / 1 Project Management and Mo IBRD / 91660 Post Direct Selection Direct - National 30,400.79 Signed 2022-08-19 2022-09-15 2022-08-24 2022-08-02 2022-08-25 2022-08-02 2023-07-30 .Senior Procurement Speciali nitoring & Evaluation st EG-EEAA-310335-CS-CDS / P Project Management and Mo Under Implement IBRD / 91660 Post Direct Selection Direct - National 0.00 2022-08-19 2022-09-15 2022-08-24 2022-08-02 2022-08-28 2023-07-30 roject Coordinator nitoring & Evaluation ation EG-EEAA-310342-CS-CDS / S Support the Operationalizati Under Implement enior Solid Waste Manageme IBRD / 91660 on of SWM Master Plans in G Post Direct Selection Direct - National 0.00 2022-08-19 2022-09-15 2022-08-25 2022-08-28 2023-07-30 ation nt Advisor reater Cairo EG-EEAA-322034-CS-CDS / T Support the Operationalizati Pending Impleme echnical Consultant - SUPB (S IBRD / 91660 on of SWM Master Plans in G Post Direct Selection Direct - National 0.00 2022-10-20 2022-10-27 2022-10-27 2023-02-27 ntation ingle Use Plastic Bags) reater Cairo EG-EEAA-322049-CS-CDS / T Support the Operationalizati Pending Impleme echnical Consultant (2) - SUP IBRD / 91660 on of SWM Master Plans in G Post Direct Selection Direct - National 0.00 2022-10-20 2022-10-27 2022-10-27 2023-02-27 ntation B (Single Use of Plastic Bags) reater Cairo EG-EEAA-322061-CS-CDS / E Project Management and Mo Under Implement IBRD / 91660 Post Direct Selection Direct - National 0.00 2022-10-20 2022-08-15 2022-10-25 2022-10-25 2023-08-30 nvironmental Specialist nitoring & Evaluation ation Page 2 EG-EEAA-326989-CS-INDV / Enhancing the Air Quality M Individual Consult Open - Internationa Pending Impleme Lead Advisory Consultant for IBRD / 91660 anagement & Response Syst Post 0.00 2022-11-24 2023-01-12 2023-02-02 2023-03-09 2023-09-05 ant Selection l ntation Component (1) em Page 3