PROCUREMENT PLAN (Textual Part) Project information: Tonga, Climate Resilience Project P161539 Project Implementation agency: Ministry of Infrastructure Date of the Procurement Plan: March 12, 2018 Period covered by this Procurement Plan: [March – December] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in N/A, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). N/A Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) N/A Other Relevant Procurement Information. The project is proposed as an Agile Project covered by the Agile Pilots waiver memorandum issued by the World Bank’s Senior Vice President, Operations. The request to have this initiation memorandum instead of a project concept note and a concept review meeting has been approved by the Practice Manager of the Task Team Leader and by OPCS Vice-Presidency on December 4, 2017. Estimated Activity Reference Review Market Category Amount No. / Description: Type Approach (US$) MOI/TCRTPPST/IC06B Consultant / Social Safeguards Post Open 35,000.00 Services Specialist MOI/TCRRPPST/IC06A / Environment Consultant Post Open 45,000.00 Safeguards Services Specialist MOI/TCRTPPST/IC06C Consultant / Local Safeguards Post Open 20,000.00 Services Specialist MOI/TCRTO-PST/SSS- Consultant Post Direct 79,697.00 01 / Project Manager Services MOI/TCRTP-PST/SSS- Consultant 02 / Contracts Post Direct 39,223.00 Services Manager MOI/TCRTP-PST/SSS- Consultant 03 / Project Post Direct 26,213.00 Services Accountant MOI/TCRTP-PST/SSS- Consultant 04 / Procurement Post Direct 27,606.00 Services Officer MOI/TCRTP-PST/SSS- Consultant 05 / Administrative Post Direct 14,290.00 Services Assistance Estimated Activity Reference Review Market Category Amount No. / Description: Type Approach (US$) MOI/TCRTP-LTD/CF- 07 / Feasibility Study, Detail Engineering Design Bid Evaluation and Consultant Open - Prior 500,000.00 Construction Services International Supervision of Tongatapu and Outer Island Roads Works in Tonga TAL/TCRTP/CF-08 / Design, Procurement and Supervision Services: Consultant Open - Post 150,000.00 Resurfacing of Services International Runway at Salote Pilolevu Airport, Ha'apai, Tonga PROCUREMENT Tonga : Tonga Climate Resilient Transport Project PLAN General Information Country: Tonga 2018-03-12 Bank’s Approval Date of the Original Procurement Plan: 2023-01-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161539 GPN Date: 2018-03-22 Project Name: Tonga Climate Resilient Transport Project Loan / Credit No: IDA / D3890, / Ministry of Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI-WK-1 / Resurfacing wor Component 2: Climate Resili Open - Internationa Single Stage - One E 4,278,020.1 2019-11-1 IDA / D3890 Prior Request for Bids Signed 2019-04-01 2019-11-27 2019-04-06 2019-12-02 2019-05-18 2020-02-10 2019-06-17 2020-04-22 2019-07-22 2020-08-03 ks on the Ha'apai Airport Run ent Infrastructure Solutions l nvelope 5 9 way MOI-WK-2 / Port works in the Component 2: Climate Resili Single Stage - One E 2019-09-1 IDA / D3890 Prior Request for Bids Open - National 0.00 Canceled 2018-10-15 2019-01-09 2018-10-30 2019-01-10 2019-01-14 2019-03-05 2019-02-13 2019-03-20 2019-03-20 outer islands: Lot 1 Eua Lot ent Infrastructure Solutions nvelope 6 2: Niuas MOI-WK-2-2 / Port Works in t Component 2: Climate Resili Single Stage - One E 2,595,330.1 2020-03-2 he Outer Island: Lot No. 1 Eu IDA / D3890 Prior Request for Bids Open - National Signed 2019-04-29 2019-04-30 2019-05-06 2019-05-08 2019-05-27 2019-06-13 2019-06-17 2020-02-05 2019-07-29 2020-01-24 ent Infrastructure Solutions nvelope 1 9 a and Lot No. 2 Niuas MOI-WK-3-PB-1 / Rehabilitati on and Upgrade and Routine Component 2: Climate Resili Single Stage - One E 3,076,953.2 2025-09-2 IDA / D3890 Prior Request for Bids Open - National Signed 2020-04-20 2020-08-13 2020-05-11 2020-08-21 2020-06-22 2020-09-30 2020-08-21 2021-01-11 2020-09-29 2021-04-26 Maintenance of Priority Road ent Infrastructure Solutions nvelope 7 8 s in Vava'u North West MOI-WK-3-PB-2 / Rehabilitati on and Upgrade and Routine Component 2: Climate Resili Single Stage - One E 2025-08-3 IDA / D3890 Post Request for Bids Open - National 0.00 Canceled 2020-04-20 2020-08-06 2020-05-11 2020-06-22 2020-09-30 2020-07-23 2021-05-20 2020-08-31 Maintenance of Priority Road ent Infrastructure Solutions nvelope 0 s in Vava'u South West MOI-WK-3-PB-3 / Rehabilitati on of Priority Roads and Net Component 2: Climate Resili Single Stage - One E 3,428,071.2 2025-10-2 IDA / D3890 Post Request for Bids Open - National Signed 2020-05-20 2020-08-06 2020-06-10 2020-07-22 2020-09-30 2020-09-20 2021-01-11 2020-10-29 work Wide Performance Base ent Infrastructure Solutions nvelope 0 8 d Maintenance (PBM-3), 'Eua MOI-WK-3-TR-C2 / Rehabilita Component 2: Climate Resili Single Stage - One E 1,386,619.0 2024-02-2 tion and Upgrading of Priority IDA / D3890 Prior Request for Bids Open - National Signed 2020-10-19 2021-06-16 2020-11-09 2021-06-27 2020-12-18 2021-08-13 2021-01-15 2022-02-02 2021-02-23 2022-04-28 ent Infrastructure Solutions nvelope 1 3 Roads in Tongatapu MOI-WK-3-TR-C1 / Rehabilita Component 2: Climate Resili Open - Internationa Single Stage - One E 2023-08-2 tion and Upgrading Road Wor IDA / D3890 Prior Request for Bids 0.00 Canceled 2020-10-19 2020-11-09 2020-12-18 2021-01-15 2021-02-23 ent Infrastructure Solutions l nvelope 5 ks on Tongatapu MOI-WK-3-TRC-1 / Rehabilita Component 2: Climate Resili Open - Internationa Single Stage - One E 2021-11-1 tion and Upgrading Road Wor IDA / D3890 Prior Request for Bids 0.00 Canceled 2021-01-29 2021-02-03 2021-03-17 2021-04-16 2021-05-21 ent Infrastructure Solutions l nvelope 7 ks on Tongatapu Liku Road Request for B MOI-WK-3-PB-2-2 / REHABILI ids - Small W TATION OF ROAD SECTIONS Component 2: Climate Resili Single Stage - One E 2027-03-1 IDA / D3890 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-09-15 2021-09-14 2021-10-25 2021-10-28 2021-12-06 2022-04-14 2022-01-25 2022-07-06 2022-03-11 V2 & V12 AND MAINTENANCE ent Infrastructure Solutions nvelope 0 nvelope proc SERVICES OF ROADS IN SOU ess) TH WEST, VAVA'U Request for B MOI-WK2-01 / Rehabilitation ids - Small W Component 2: Climate Resili Single Stage - One E Under Imple 2024-09-2 of Liku Road (Fua'amotu - 'Ut IDA / D3890 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-09-12 2022-11-08 2022-09-26 2022-11-30 2022-10-26 2022-11-16 2022-12-30 ent Infrastructure Solutions nvelope mentation 0 ulau) Tongatapu 3 Lots nvelope proc ess) Request for B MOI-WK-3-PB-2-3 / Rehabilit ids - Small W ation of Road Sections V2 & Component 2: Climate Resili Single Stage - One E Pending Imp 2028-05-0 IDA / D3890 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-02-01 2023-02-08 2023-03-08 2023-03-22 2023-05-03 12 and Maintenance Services ent Infrastructure Solutions nvelope lementation 1 nvelope proc of Roads in South West, Vava ess) 'u (2 Lots) MOI-WK-3-TR-C3 / Rehabilita Request for B tion and Upgrading of Priority ids - Small W Roads in Tongatapu, Lot 1 T5 Component 2: Climate Resili Single Stage - One E Pending Imp 2024-08-0 IDA / D3890 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-01-27 2023-02-10 2023-03-12 2023-04-02 2023-05-16 - Loto Road (Makapaeo - Mat ent Infrastructure Solutions nvelope lementation 8 nvelope proc ahau Road 3.6km), and Lot 2 ess) T1 - Taufa'ahau Road (Hoi-Ko longa Road 6.3km Request for B MOI-WK-2-3 / Safety Improv Component 2: Climate Resili Single Stage - One E ids - Small W Pending Imp 2024-11-0 ement Works at Futu Port, Ni IDA / D3890 Post Request for Bids Open - National 0.00 2023-01-27 2023-02-11 2023-03-13 2023-04-03 2023-05-18 ent Infrastructure Solutions nvelope orks SPD (1 e lementation 8 uafo'ou nvelope proc ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI-GO-1 / Transport Sector Component 3: Strengthening Request for Quota Single Stage - One E / Post Limited 0.00 Canceled 2019-10-06 2019-12-01 2020-01-30 Safety Campaign the Enabling Environment tions nvelope MOI-GO-2 / Laboratory Testi Component 3: Strengthening Request for Quota Single Stage - One E IDA / D3890 Post Limited 100,290.32 Completed 2019-08-24 2019-12-02 2019-11-02 2019-12-31 2020-01-31 2021-08-09 ng Equipment the Enabling Environment tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MOI/TCRTP-LTD/CF-07 / Feas ibility Study, Detail Engineeri Component 2: Climate Resili Quality And Cost- Open - Internationa ng Design Bid Evaluation and IDA / D3890 Prior 2,685,757.80 Signed 2018-03-08 2018-03-08 2018-05-16 2018-03-23 2018-05-18 2018-05-04 2018-08-06 2018-05-18 2018-09-05 2018-06-01 2018-11-26 2018-06-15 2018-12-13 2020-12-14 ent Infrastructure Solutions Based Selection l Construction Supervision of T ongatapu and Outer Island R oads Works in Tonga MOI-CS-FIRM-4 / Obstacle Li Component 1: Sectoral and Consultant Qualifi Open - Internationa IDA / D3890 Post 0.00 Canceled 2019-04-01 2019-03-18 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 mitation Study - Eua Airport Spatial Planning Tools cation Selection l MOI-CS-FIRM-5 / Vulnerabilit Component 1: Sectoral and Consultant Qualifi Open - Internationa y Assessment of Road Netwo / Post 0.00 Canceled 2018-10-15 2019-04-12 2018-11-05 2019-05-01 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Spatial Planning Tools cation Selection l rks in Outer Islands TAL/TCRTP/CF-08 / Design, P rocurement and Supervision Component 2: Climate Resili Quality And Cost- Open - Internationa IDA / D3890 Post 342,247.86 Signed 2018-03-08 2017-12-05 2018-03-20 2019-04-09 2018-04-17 2018-06-21 2018-05-15 2018-08-01 2018-05-29 2018-08-22 2018-06-12 2018-09-13 2018-06-26 2018-11-20 2019-09-24 2020-07-31 Services: Resurfacing of Run ent Infrastructure Solutions Based Selection l way at Salote Pilolevu Airport , Ha'apai, Tonga MOI-CS-FIRM-7 / Detailed De Component 2: Climate Resili Consultant Qualifi IDA / D3890 Post Open - National 0.00 Canceled 2019-10-01 2019-10-22 2019-12-05 2020-01-04 2020-02-08 2020-04-28 sign for Road Safety Works ent Infrastructure Solutions cation Selection MOI-CS-FIRM-1 / Supervision Component 2: Climate Resili Consultant Qualifi of Safety Improvement Work IDA / D3890 Post Open - National 112,791.13 Signed 2018-10-16 2019-01-02 2018-11-06 2019-04-11 2018-12-20 2019-01-15 2019-01-19 2019-03-29 2019-02-23 2019-04-17 2019-08-22 ent Infrastructure Solutions cation Selection s in Eua Port MOI-CS-FIRM-2 / Supervision Component 2: Climate Resili Consultant Qualifi of Safety Improvement Work IDA / D3890 Post Open - National 144,967.23 Signed 2018-10-15 2018-01-02 2018-11-05 2019-04-11 2018-12-19 2019-01-15 2019-01-18 2019-03-28 2019-02-22 2019-04-23 2019-08-21 ent Infrastructure Solutions cation Selection s in Niuatoputapu Port MOI-CS-FIRM-5-2 / Vulnerabil Component 1: Sectoral and Quality And Cost- Open - Internationa ity assessment of the road n IDA / D3890 Post 383,635.66 Signed 2019-07-10 2019-07-10 2019-07-31 2019-09-13 2019-08-22 2019-10-11 2019-10-04 2019-11-10 2019-11-15 2019-12-15 2019-12-12 2020-01-19 2019-12-20 2021-01-18 Spatial Planning Tools Based Selection l etworks in Vavau and Eua MOI-CS-FIRM-8 / Active Tran Component 1: Sectoral and Consultant Qualifi Open - Internationa IDA / D3890 Post 0.00 Canceled 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 sportation Opportunities Stud Spatial Planning Tools cation Selection l y MOI-CS-FIRM-9 / Supervision Component 2: Climate Resili Consultant Qualifi Under Implement of Safety Improvement Work IDA / D3890 Post Open - National 0.00 2022-10-10 2022-11-25 2022-10-31 2022-12-05 2022-11-28 2022-12-12 2022-12-26 2024-06-18 ent Infrastructure Solutions cation Selection ation s at Futu Port, Niuafo'ou INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI/TCRTO-PST/SSS-01 / Pro Component 3: Strengthening Individual Consult IDA / D3890 Post Direct 48,418.45 Completed 2018-04-02 2018-05-18 2018-04-12 2018-05-18 2018-05-03 2018-05-23 2018-06-07 2018-06-15 2018-12-04 2019-02-28 ject Manager the Enabling Environment ant Selection MOI/TCRTP-PST/SSS-02 / Con Component 3: Strengthening Individual Consult IDA / D3890 Post Direct 23,866.82 Completed 2018-04-02 2018-05-16 2018-04-12 2018-05-18 2018-05-03 2018-05-23 2018-06-07 2018-06-15 2018-12-04 2019-02-28 tracts Manager the Enabling Environment ant Selection MOI/TCRTP-PST/SSS-03 / Proj Component 3: Strengthening Individual Consult IDA / D3890 Post Direct 15,925.57 Completed 2018-04-02 2018-05-16 2018-04-12 2018-05-18 2018-05-03 2018-05-22 2018-06-07 2018-06-15 2018-12-04 2019-02-28 ect Accountant the Enabling Environment ant Selection MOI/TCRTP-PST/SSS-04 / Pro Component 3: Strengthening Individual Consult IDA / D3890 Post Direct 15,950.65 Completed 2018-04-02 2018-05-18 2018-04-12 2018-05-18 2018-05-03 2018-05-23 2018-06-07 2018-06-15 2018-12-04 2019-02-28 curement Officer the Enabling Environment ant Selection MOI/TCRTP-PST/SSS-05 / Ad Component 3: Strengthening Individual Consult IDA / D3890 Post Direct 8,681.82 Completed 2018-04-02 2018-05-16 2018-04-12 2018-05-18 2018-05-03 2018-05-23 2018-06-07 2018-06-15 2018-12-04 2019-02-28 ministrative Assistance the Enabling Environment ant Selection MOI/TCRTPPST/IC06B / Socia Individual Consult / Post Open 0.00 Canceled 2018-03-20 2018-01-29 2018-04-17 2018-04-24 2018-05-02 2018-09-09 l Safeguards Specialist ant Selection MOI/TCRRPPST/IC06A / Envir Individual Consult / Post Open 0.00 Canceled 2018-03-22 2018-04-19 2018-04-26 2018-05-04 2018-09-11 onment Safeguards Specialis ant Selection t MOI/TCRTPPST/IC06C / Local Individual Consult / Post Open 0.00 Canceled 2018-03-20 2018-04-17 2018-04-24 2018-05-02 2018-08-09 Safeguards Specialist ant Selection MOI/TCRTPPST/IC06B/2 / Soc Component 3: Strengthening Individual Consult IDA / D3890 Post Limited 33,656.00 Completed 2018-03-22 2018-01-29 2018-03-27 2018-03-02 2018-04-17 2018-03-13 2018-05-22 2018-04-27 2018-09-19 2018-07-30 ial Safeguards Specialist the Enabling Environment ant Selection MOI/TCRRPPST/IC06A /2 / En Component 3: Strengthening Individual Consult IDA / D3890 Post Limited 42,323.60 Completed 2018-03-22 2018-01-29 2018-03-27 2018-03-02 2018-04-17 2018-04-27 2018-05-22 2018-04-27 2018-09-19 2018-07-30 vironment Safeguards Specia the Enabling Environment ant Selection list MOI/TCRTP/IC-09 / Internatio Component 3: Strengthening Individual Consult nal Technical Adviser (Procur IDA / D3890 Post Limited 28,443.23 Completed 2018-07-24 2018-06-11 2018-07-29 2018-07-17 2018-08-19 2018-08-22 2018-09-23 2018-07-24 2019-01-21 2018-11-26 the Enabling Environment ant Selection ement - Roads) MOI/TCRTP/IC-10 / Gender a Component 3: Strengthening Individual Consult IDA / D3890 Post Limited 7,200.00 Completed 2018-07-24 2018-07-09 2018-07-29 2018-07-06 2018-08-19 2018-08-31 2018-09-23 2018-08-31 2018-10-23 2018-09-30 nd Gender Based Violence Co the Enabling Environment ant Selection nsultant MOI-CS-INDV-1 / Project Man Component 3: Strengthening Individual Consult / Post Open 0.00 Canceled 2018-10-22 2018-12-10 2018-12-31 2019-02-04 2021-03-28 ager the Enabling Environment ant Selection MOI-CS-INDV-2 / Contracts M Component 3: Strengthening Individual Consult IDA / D3890 Post Open 116,606.91 Completed 2018-10-22 2019-02-01 2018-12-10 2019-02-04 2018-12-31 2019-06-03 2019-02-04 2019-06-28 2021-03-28 2022-01-03 anager the Enabling Environment ant Selection MOI-CS-INDV-3 / Procuremen Component 3: Strengthening Individual Consult IDA / D3890 Post Open 111,523.90 Completed 2018-10-22 2019-04-01 2018-12-10 2019-07-02 2018-12-31 2019-07-08 2019-02-04 2019-07-12 2021-03-28 2021-11-22 t Officer the Enabling Environment ant Selection Component 3: Strengthening Individual Consult MOI-CS-INDV-4 / Accountant IDA / D3890 Post Open 99,317.71 Completed 2018-10-22 2018-12-14 2018-12-10 2019-02-04 2018-12-31 2019-03-11 2019-02-04 2019-02-18 2021-03-28 2022-04-12 the Enabling Environment ant Selection MOI-CS-INDV-5 / Administrati Component 3: Strengthening Individual Consult IDA / D3890 Post Open 16,533.72 Completed 2018-10-22 2018-12-16 2018-12-10 2019-02-15 2018-12-31 2019-02-15 2019-02-04 2019-02-22 2021-03-28 2020-04-14 ve Assistant the Enabling Environment ant Selection MOI-CS-INDV-6 / Communica Component 3: Strengthening Individual Consult / Post Open 52,188.00 Completed 2019-03-01 2018-12-16 2019-04-19 2019-02-28 2019-05-10 2019-02-28 2019-06-14 2019-03-01 2021-08-05 2020-01-07 tions and M & E Officer the Enabling Environment ant Selection MOI-CS-FIRM-3 / Training an Component 3: Strengthening / Post Direct Selection Direct 0.00 Canceled 2019-07-08 2019-07-18 2019-09-21 2020-03-19 d Capacity Building the Enabling Environment Page 2 MOI-CS-INDV-7 / Safeguards Component 3: Strengthening Individual Consult IDA / D3890 Post Open 34,751.67 Completed 2019-03-01 2018-12-16 2019-04-19 2019-02-22 2019-05-10 2019-04-03 2019-06-14 2019-07-12 2021-08-05 2020-07-31 Specialist the Enabling Environment ant Selection MOI-CS-INDV-1-2 / Project M Component 3: Strengthening Individual Consult IDA / D3890 Post Direct 130,036.15 Completed 2018-10-29 2018-12-16 2018-11-08 2019-02-22 2018-11-29 2019-02-22 2019-01-03 2019-02-22 2019-09-20 2020-02-28 anager the Enabling Environment ant Selection MOI-CS-CDS-1 / Technical M Component 3: Strengthening IDA / D3890 Post Direct Selection Direct 45,000.00 Completed 2019-03-06 2019-03-07 2019-03-16 2019-02-19 2019-04-05 2019-03-25 2019-07-14 2019-11-22 aritime Advisor the Enabling Environment MOI/TCRTPPST/IC06C/2 / Loc Component 3: Strengthening Individual Consult IDA / D3890 Post Limited 8,783.28 Completed 2018-03-22 2018-01-29 2018-03-27 2018-03-02 2018-04-17 2018-04-18 2018-05-22 2018-04-27 2018-09-19 2018-07-30 al Safeguards Specialist the Enabling Environment ant Selection MOI-CS-INDV-8 / Obstacle Li Component 1: Sectoral and Individual Consult IDA / D3890 Post Open 23,135.62 Completed 2019-04-22 2019-06-12 2019-06-24 2019-05-25 2019-07-15 2019-05-25 2019-08-19 2019-06-19 2019-09-08 2019-09-13 mitation Study in Eua Spatial Planning Tools ant Selection MOI-CS-INDV-9 / Laboratory Component 3: Strengthening Individual Consult IDA / D3890 Post Open 53,117.00 Completed 2019-04-29 2019-06-20 2019-06-22 2019-09-12 2019-07-06 2019-09-12 2019-07-27 2019-09-23 2019-10-25 2020-12-10 Adviser the Enabling Environment ant Selection MOI-CS-FIRM-6 / Road Safety Component 3: Strengthening Audit Training and Monitorin / Post Direct Selection Direct 0.00 Canceled 2019-06-03 2019-07-11 2019-06-13 2019-08-17 2019-11-25 the Enabling Environment g and Attachment MOI-CS-INDV-1-2-2 / TCRTP Component 3: Strengthening Individual Consult IDA / D3890 Post Open 141,563.58 Completed 2020-01-01 2019-12-19 2020-01-23 2020-02-20 2020-01-23 2020-02-21 2020-02-09 2020-02-21 2022-02-08 2021-09-28 Project Manager the Enabling Environment ant Selection MOI/CS/INDV-6-1 / Communi Component 3: Strengthening Individual Consult IDA / D3890 Post Open 53,474.85 Completed 2020-01-14 2020-01-16 2020-02-14 2020-03-09 2020-02-21 2020-03-05 2020-03-13 2020-03-11 2022-03-13 2022-03-23 cations, Monitoring & Evaluat the Enabling Environment ant Selection ion Officer MOI-CS-INDV-10 / Driving Ins Component 3: Strengthening Individual Consult IDA / D3890 Post Open 0.00 Canceled 2020-01-17 2020-01-28 2020-03-06 2020-03-27 2020-05-01 2020-10-28 tructor for commercial licens the Enabling Environment ant Selection e MOI-CS-INDV-5-1 / Administr Component 3: Strengthening Individual Consult IDA / D3890 Post Open 26,586.00 Completed 2020-04-14 2020-04-20 2020-05-17 2020-06-15 2020-05-24 2020-06-15 2020-06-13 2020-06-16 2022-06-13 2021-09-30 ative Assistant the Enabling Environment ant Selection MOI-CS-INDV-7-1 / Safeguar Component 3: Strengthening Individual Consult IDA / D3890 Post Open 55,235.50 Completed 2020-05-01 2020-06-02 2020-06-19 2020-07-30 2020-07-10 2020-07-30 2020-08-14 2020-08-05 2022-08-14 2022-04-12 ds Officer the Enabling Environment ant Selection MOI-ICS-INDV-12 / Legal Con Component 3: Strengthening Individual Consult IDA / D3890 Post 64,838.32 Signed 2020-09-28 2020-09-24 2020-10-08 2020-09-30 2020-10-18 2021-01-22 2020-10-28 2021-01-26 2021-06-25 sultant the Enabling Environment ant Selection MOI-ICS-INDV-13 / Technical Component 3: Strengthening Individual Consult IDA / D3890 Post Open 225,776.42 Signed 2020-11-02 2020-11-13 2020-12-21 2021-02-10 2021-01-11 2021-03-04 2021-02-15 2021-03-22 2022-11-07 Adviser - Roads the Enabling Environment ant Selection MOI-CS-INDV-4-1 / Project Ac Component 3: Strengthening Individual Consult IDA / D3890 Post 0.00 Canceled 2020-10-19 2020-12-07 2020-12-28 2021-02-01 2023-02-01 countant the Enabling Environment ant Selection MOI-CS-INDV-5-2 / Administr Component 3: Strengthening Individual Consult IDA / D3890 Post Open 23,987.81 Signed 2021-10-15 2021-11-29 2021-12-13 2022-03-21 2021-12-14 2022-03-24 2022-01-01 2022-04-13 2024-01-01 ative Assistant the Enabling Environment ant Selection MOI-PMU-SSS-06 / TCRTP Pro Component 3: Strengthening Individual Consult IDA / D3890 Post Direct 57,042.69 Signed 2021-11-01 2021-12-15 2021-11-11 2021-10-14 2021-11-25 2022-01-03 2021-12-05 2022-01-03 2022-12-05 ject Manager the Enabling Environment ant Selection MOI-PMU-INDV-4-1 / Project Component 3: Strengthening Individual Consult IDA / D3890 Post Open 75,020.43 Signed 2021-11-30 2021-11-29 2022-01-31 2022-03-24 2022-02-07 2022-03-28 2022-03-22 2022-04-13 2023-12-31 Accountant the Enabling Environment ant Selection MOI-PMU-INDV-3-1 / Procure Component 3: Strengthening Individual Consult IDA / D3890 Post Open 78,421.68 Signed 2021-11-30 2021-11-29 2022-01-31 2022-02-25 2022-02-21 2022-02-28 2022-03-28 2022-03-07 2023-12-31 ment Officer the Enabling Environment ant Selection MOI-PMU-INDV-2-1 / Contrac Component 3: Strengthening Individual Consult IDA / D3890 Post Open 72,284.95 Signed 2021-11-30 2021-11-29 2022-01-31 2022-03-24 2022-02-21 2022-03-28 2022-03-28 2022-04-13 2023-12-31 ts Manager the Enabling Environment ant Selection MOI-PMU-INDV-6-2 / Commu Component 3: Strengthening Individual Consult nication, Monitoring & Evalua IDA / D3890 Post Open 74,961.90 Signed 2021-11-30 2021-11-29 2022-02-05 2022-04-01 2022-02-12 2022-04-06 2022-03-28 2022-05-02 2023-12-31 the Enabling Environment ant Selection tion Officer MOI-CS-SSS-07 / Aviation Te Component 3: Strengthening Individual Consult chnical Advisor (Regulatory C IDA / D3890 Post Direct 80,717.70 Signed 2022-03-14 2022-03-28 2022-03-24 2022-05-24 2022-04-14 2022-05-24 2022-05-19 2022-05-24 2023-05-19 the Enabling Environment ant Selection ompliance Specialist) MOI-CS-INDV-7-2 / Safeguar Component 3: Strengthening Individual Consult IDA / D3890 Post Open 0.00 Signed 2022-06-01 2022-06-10 2022-07-11 2022-10-14 2022-07-25 2022-10-26 2022-08-06 2024-08-05 d Officer the Enabling Environment ant Selection MOI-CS-INDV-14 / Determini Component 1: Sectoral and Individual Consult Open - Internationa Pending Impleme ng Measures to Alleviate Traf IDA / D3890 Post 0.00 2023-02-15 2023-04-14 2023-05-05 2023-05-26 2023-09-23 Spatial Planning Tools ant Selection l ntation fic Congestions in Nuku'alofa, Tongatapu. Page 3