The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) EAST ASIA AND PACIFIC | China | Agriculture and Food Global Practice | Requesting Unit: EACCF | Responsible Unit: SEAAG IBRD/IDA | Program-for-Results Financing | FY 2022 | Team Leader(s): Ladisy Komba Chengula, Wendao Cao Seq No: 1 | ARCHIVED on 06-Jul-2022 | ISR51183 | Created by: Yunqing Tian on 24-Apr-2022 | Modified by: Ladisy Komba Chengula on 29-Jun- 2022 Program Development Objectives PDO Table Program Development Objective (from Program Appraisal Document) The Program Development Objective (PDO) is to enhance environmentally sustainable agricultural and rural infrastructure development in selected areas of Guangxi and Guizhou. Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Satisfactory Implementation Status and Key Decisions This is the first ISR for the Green Agricultural and Rural Revitalization Program-Phase I. The program was approved by the Executive Directors of the Board of the Bank on March 31, 2022. The government is working on the internal procedures for signing. It is expected the project could be signed in July 2022. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed Not P177590 IBRD-93570 USD 170.00 170.00 0.00 0.00 170.00 0% Effective Not P177590 IBRD-93580 USD 150.00 150.00 0.00 0.00 150.00 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P177590 IBRD-93570 31-Mar-2022 -- -- 30-Jun-2028 30-Jun-2028 Effective Not P177590 IBRD-93580 31-Mar-2022 -- -- 30-Jun-2028 30-Jun-2028 Effective Program Action Plan 7/6/2022 Page 1 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) 1. Issue an official notification that no contract will be awarded to either a firm or an individual appearing on either the Action Description World Bank’s debarred list or under temporary suspension list. Source DLI# Responsibility Timing Timing Value Status No later than loan Fiduciary Systems RPMO/PPMO Other Not Yet Due effectiveness Completion Measurement Provincial/Regional official notifications to counties are issued and copies are shared with the World Bank Comments 2. Regularly inform the World Bank of any credible and material allegations of fraud and/or corruption regarding the Action Description PforR’s activities as part of the overall PforR’s reporting requirements. Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems RPMO/PPMO Recurrent Semi-Annually Not Yet Due Completion Measurement Reflected in the PforR’s quarterly/annual progress reports Comments 3. Guangxi and Guizhou to Issue updated policies related to funds integration and budget performance evaluation Action Description measures that increase the discretion of the county governments to utilize funds in line with their development plans and priorities. Source DLI# Responsibility Timing Timing Value Status RPMO/PPMO and Fiduciary Systems relevant government Due Date 31-Dec-2022 Not Yet Due agency Document is issued by the relevant government agencies and shared with the World Bank. Completion Measurement Comments 4. Implement measures to improve rural solid waste transfer stations by enhancing leachate and odour management Action Description facilities and providing PPE, sanitation and resting facilities for workers. Source DLI# Responsibility Timing Timing Value Status Environmental and Social DLI 8 PHURDD, county Recurrent Continuous Not Yet Due Systems HURDBs RPMO/PPMO submit transfer stations’ completion acceptance reports as well as semi-annual progress reports to the Completion Measurement World Bank, to provide information about completion and operation of the relevant facilities. Comments 7/6/2022 Page 2 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) 5. Undertake measures to ensure availability of adequate operations and maintenance (O&M) funding for the Action Description wastewater treatment facilities. Source DLI# Responsibility Timing Timing Value Status Environmental and Social DLI 8 PEEDs, county Recurrent Continuous Not Yet Due Systems EEBs RPMO/PPMO submit O&M funding arrangement documents as well as semi-annual progress reports to the Bank, to Completion Measurement provide information about O&M funding arrangement Comments 6. Prepare and implement detailed training and capacity building plans: (a) GA skills training plan; (b) training plan for Action Description the O&M of the rural solid waste and wastewater facilities; and (c) capacity building plans supporting the achievement of DLIs. Source DLI# Responsibility Timing Timing Value Status RPMO/PPMO and Other Recurrent Yearly Not Yet Due CPMOs The training and capacity building plans are prepared by PMOs and cleared by the Bank. Records of the people Completion Measurement trained in various skills are kept in the MIS. Comments Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Low -- Low Macroeconomic Low -- Low Sector Strategies and Policies Low -- Low Technical Design of Project or Program Moderate -- Moderate Institutional Capacity for Implementation and Substantial -- Substantial Sustainability Fiduciary Substantial -- Substantial Environment and Social Substantial -- Moderate Stakeholders Low -- Low Other -- -- -- Overall Substantial -- Substantial RiskComments 7/6/2022 Page 3 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Comments This is an initial ISR for the GARR I following its Board approval on March 31, 2022. Implementation has not yet started because the LA and PAs have not been signed; and the GARR I is not effective. Results PDO Indicators by Objectives / Outcomes To enhance environmentally sustainable agricultural and rural infrastructure development IN01133280 ►1. Nutrient load reduction (Ammonia-Nitrogen (NH3N), Total Phosphorus (TP)) achieved under the PforR in program counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 34,787.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative quantities of the annual reduction of nutrient loads (NH3N, TP) achieved due to fertilizer use Comments reduction and increase in efficiency in selected value chains (e.g., rice, fruits and vegetables). IN01133291 ►2. Chemical Oxygen Demand (COD) pollution load reduction achieved under the PforR in program counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 226,667.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative quantities of the annual reduction of pollution load (COD) achieved due to the improved Comments management of livestock and poultry manure and wastewater treatment in demonstration villages in program counties. IN01133292 ►3. Greenhouse gas (GHG) emissions reduction achieved under the PforR in the program counties (Metric tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2,260,000.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 This indicator measures the reduction in metric tons of GHG emissions from the activity of chemical fertilizer Comments reduction, manure management, plastic recycled, and solid waste incineration IN01133293 ►4. Beneficiaries reached with assets or public services (disaggregated by gender and ethnic minority) under the PforR in program counties (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 6,790,971.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Number of the people in program counties who directly derive benefits (disaggregated by gender and ethnic Comments minority) from program intervention (i.e., IT-based systems, green value chain development, wastewater and solid waste treatment and other public services etc.). IN01133294 (a) female (Number, Custom Supplement) 7/6/2022 Page 4 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3,270,095.00 IN01133295 (b) ethnic minority (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 3,354,744.00 Intermediate Results Indicators by Results Areas Results Area 1: Strengthening institutional capacity for governance IN01133297 ►1. Development and use of a comprehensive IT-based M&E system for rural infrastructure and public services (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 27.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Establishment of an IT-based system that enables provinces to expand the scope of IT-based rural infrastructure (or assets) management system to include wastewater and solid waste activities. The IT- Comments based system will enable county governments to monitor and evaluate investments, O&M of facilities, and whether the rural infrastructure meet the provincial environmental standards. IT-based systems will also be used for decision-making support/tool and to improve transparency and accountability. IN01133301 ►2. Development and use of an IT-based system for green agricultural program-based budgeting and expenditure reporting (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 27.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Establishment of an IT-based program-based budgeting plans and expenditure reporting system that adopts RRS plan expenditure classification. The platform would enable county governments to consolidate or pool Comments fiscal resources from various earmarked budgets to finance priority sub-programs and track expenditures under the RRS plan. This will show the contribution of PforR to green agricultural development. IN01133303 ►3. Number of agro-products certified and/or registered in the PforR counties as either green, organic or GI using the approved regional/provincial regulations, standards and guidelines (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 255.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 This indicator measures both number of product certificates and the number of geographical indication (GI) registered by using the approved regional/provincial regulations, standards and guidelines.. Product Comments certification is defined as agri-products certified as organic and green according to national standards set by MARA. Geographical indication (GI) certificates are done according to national standards. IN01133306 ►4. Number of program counties have adopted the evidence-based 15th rural revitalization five-year plan (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 7/6/2022 Page 5 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Value 0.00 -- 0.00 27.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 This indicator focuses on tracking the impact of the M&E system of rural revitalization program on the Comments development of rural revitalization strategy. It is measured by the number of counties that have adopted the 15th rural revitalization five-year plan using the information collected through the M&E system. Results Area 2 - Greening selected agricultural value chains IN01133298 ►Tonnes of chemical fertilizer reduced due to the adoption of green technologies and sustainable practices in selected crop production systems in the Program Counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 137,376.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Comments IN01133300 ►5. Quantity of organic fertilizer used in the program counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5,455,113.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative quantities of organic fertilizer used by farmers in various crop production systems as a Comments replacement for the chemical fertilizers. IN01133304 ►6. Quantity of formula fertilizer used in the program counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 450,411.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative quantities of formula fertilizers used by farmers in various crop production systems as Comments substitutes to chemical fertilizers. IN01133307 ►7. Area under fertigation in program counties (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 22,597.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative number of hectares (ha) under fertigation practices. Fertigation is the injection of fertilizers, used Comments for soil nutrients amendments, water amendments and other water soluble products into an irrigation system. Fertigation is related to chemigation, the injection of chemicals into an irrigation system IN01133309 ►8. Area under green manure in the program counites (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target 7/6/2022 Page 6 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Value 0.00 -- 0.00 81,199.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative number of hectares under green manure (nitrogen fixing crops), including vetch (genus Vicia), Comments which will be incorporated into the soil to increase organic matter and nutrients and improve soil structure. IN01133311 ►9. Beneficiaries who have been trained in the green agricultural technologies and practices (farmers, input suppliers, enterprises/agri- businesses, extension staff), disaggregated by gender) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 66,680.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative number of people (farmers, input suppliers, enterprises/agri-businesses, extension staff) trained Comments in green agricultural technologies and practices disaggregated by gender/ethnic minority IN01133312 Of which female (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 10,521.00 IN01133314 ►10. Beneficiaries who have adopted green agricultural technologies and practices (farmers, input suppliers, enterprises/agri-businesses, extension staff), disaggregated by gender) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 -- 0.00 80.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Percentage of the people who have been trained and have adopted green agricultural technologies and Comments practices. IN01133315 Of which female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 -- 0.00 80.00 IN01133316 ►Tons of livestock and poultry manure treated and recycled in the PforR counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20,343,528.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Comments IN01133317 ►11. Manure treated by large farms in the program counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 6,666,670.00 7/6/2022 Page 7 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative quantity (tons) of livestock and poultry manure that are collected, treated and recycled by large Comments farms into organic fertilizer, biogas/energy generation, and irrigation water in the program counties. IN01133318 ►12. Manure treated at centralized and small-scale manure treatment facilities constructed for small and medium scale farms in the program counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 13,676,858.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative quantity (tons) of livestock and poultry manure that are collected, treated and recycled by Comments centralized and small-scale manure treatment facilities for small and medium scale farms in program counties IN01133319 ►13. Centralized manure treatment facilities constructed for small and medium scale farms in the program counties (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 156.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative number of centralized manure treatment facilities newly constructed for small and medium scale farms in the program counties. Small and medium-scale animal farms are defined as less than 500 head of Comments pigs, less than 2,000 egg chickens (Layers), less than 10,000 meat chicken (Broilers), and/or less than 30 head of cattle. IN01133320 ►14. Manure treatment facilities constructed for small scale farms in the program counties (Guizhou) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2,558.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative number of small scale manure treatment facilities newly constructed for small and medium scale Comments farms in the program counties in Guizhou. IN01133321 ►Tons of agricultural plastics recovered and recycled in the PforR counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 37,869.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Comments IN01133322 ►15. Quantity of agricultural plastic film recovered and recycled in the program counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 35,427.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative quantity (tons) of agricultural plastic mulch film (dry weight of plastic wastes) recovered, treated Comments and recycled in the program counties. 7/6/2022 Page 8 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) IN01133323 ►16. Quantity of agricultural chemical (fertilizer, pesticide, fungicide) packaging materials recycled in the program counties in program counties (Tons/year, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2,442.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative number (tons) of agricultural chemical (fertilizer, pesticide, fungicide) packaging materials Comments recovered, treated and recycled in the program counties Results Area 3 - Increasing access to solid waste and wastewater services IN01133296 ►Number of spatial Integrated Village Development Plans (IVDPs) approved by the relevant PforR counties’ authorities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 336.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Comments IN01133299 ►17. Counties implementing the approved guidelines for wastewater and solid waste management in rural villages in the program counties (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 27.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Development of guidelines for wastewater and solid waste management in rural villages by Comments provincial/regional government and approved and used in program counties IN01133302 ►18. Beneficiaries trained in O&M of rural villages wastewater and solid waste management systems in program counties (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 49,311.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Cumulative number of people trained in O&M of rural villages wastewater and solid waste management Comments systems in the program counties IN01133305 ►Number of demonstration villages with newly constructed or rehabilitated climate resilient wastewater treatment facilities and established solid waste collection, sorting and transfer systems (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 112.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Comments IN01133308 ►19. Percentage of rural domestic wastewater facilities in demonstration villages meeting effluent discharge standards (Percentage, Custom) 7/6/2022 Page 9 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Percentage of wastewater properly treated and managed per the rural wastewater management guideline in Comments the pilot villages. IN01133310 ►20. Percentage of rural domestic solid waste and agricultural plastic film in demonstration villages that is collected, sorted and transferred (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 70.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 Percentage of rural solid waste and agricultural plastic waste collected, sorted and treated according to the Comments per the rural solid waste management guideline in the pilot villages. IN01133313 ►21. Percentage of newly created and upgraded jobs held by women in the transformation of agricultural value chain and in the rural waste management and environmental rehabilitation (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Date 01-Jul-2021 -- 15-Jun-2022 30-Jun-2028 The indicator will be calculated as the percentage of women or female employees in entities that receive the Comments Program support in the transformation of production, processing, packaging, marketing and sales of green agricultural products and in the newly constructed rural wastewater management facilities. Disbursement Linked Indicators DLI_IND_TABLE ►DLI 1 DLI1: Development and use of a comprehensive IT-based M&E system for rural infrastructure, public services and profile of rural villages (Guizhou) (Output, 6,800,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 0.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 2 DLI1: Development and use of a comprehensive M&E system for the implementation of the Rural Revitalization Program (Guangxi) (Output, 5,984,991.25, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 0.00 Date -- -- 15-Jun-2022 -- Comments 7/6/2022 Page 10 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) ►DLI 3 DLI2: Development and use of an IT-based system for green agricultural program-based budgeting and expenditure reporting (Guizhou) (Output, 11,900,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 0.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 4 DLI2: Development and use of an IT-based system for green agricultural program-based budgeting and expenditure reporting (Guangxi) (Output, 10,473,750.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 0.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 5 DLI3: Adoption of regulations, standards and guidelines on GAP and number of products produced in the Program Counties that are certified and/or registered as either green, organic or GI (Guizhou) (Output, 6,800,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 28.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 6 DLI3: Adoption of regulations, standards and guidelines on GAP and number of products produced in the Program Counties that are certified and/or registered as either green, organic or GI (Guangxi) (Output, 5,985,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 23.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 7 DLI4: Tonnes of chemical fertilizer reduced due to the adoption of green technologies and sustainable practices in selected crop production systems in the Program counties (Guizhou) (Output, 25,500,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 29,956.00 Date -- -- 15-Jun-2022 -- 7/6/2022 Page 11 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Comments ►DLI 8 DLI4: Tonnes of chemical fertilizer reduced due to the adoption of green technologies and sustainable practices in selected crop production systems in the Program counties (Guangxi) (Output, 2.24, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 16,467.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 9 DLI5: Percentage increase of treated and recycled livestock and poultry manure from large scale and small scale farms in the Program Counties (Guizhou) (Output, 30,600,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 82.00 -- 0.00 5.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 10 DLI5: Percentage increase of treated and recycled livestock and poultry manure from large scale and small scale farms in the Program Counties (Guangxi) (Output, 26,932,500.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 85.00 -- 0.00 5.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 11 DLI6: Percentage increase of recovered and recycled agricultural plastics in the Program Counties (Guizhou) (Output, 18,700,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 79.00 -- 0.00 1.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 12 DLI6: Percentage increase of recovered and recycled agricultural plastics in the Program Counties (Guangxi) (Output, 16,458,750.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 7/6/2022 Page 12 of 13 The World Bank Implementation Status & Results Report Green Agricultural and Rural Revitalization Program for Results - Phase I (P177590) Value 82.00 -- 0.00 1.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 13 DLI7: Number of Integrated Village Development Plans (IVDPs) approved by Program Counties (Guizhou) (Output, 13,600,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 35.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 14 DLI7: Number of Integrated Village Development Plans (IVDPs) approved by Program Counties (Guangxi)) (Output, 11,969,880.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 20.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 15 DLI8: Number of demonstration villages with newly constructed or rehabilitated existing climate resilient wastewater treatment and solid waste collection, sorting and transfer systems (Guizhou)) (Output, 56,100,000.00, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 15.00 Date -- -- 15-Jun-2022 -- Comments ►DLI 16 DLI8: Number of demonstration villages with newly constructed or rehabilitated existing climate resilient wastewater treatment and solid waste collection, sorting and transfer systems (Guangxi)) (Output, 4.93, 0%) Baseline Actual (Previous) Actual (Current) 2027 Value 0.00 -- 0.00 10.00 Date -- -- 15-Jun-2022 -- Comments 7/6/2022 Page 13 of 13