Sample Procurement Plan I. General 1. Project Information : Disaster Risk Management and Urban Development Project (P145268) /Gouvernement de la République du Niger 2. Bank’s approval Date of the procurement Plan 19-oct.-15 3. Date of General Procurement Notice: March 17, 2015 4. Period covered by this procurement plan: Juillet 2017- Décembre 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,000,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) NA 5. (Non-Consultant Services) Above US$ 1,000,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing July 9, 2010 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Domesti Review Comments No. on ed c by Bank Cost Prefere (Prior / US$ nce Post) million (yes/no) Summary 16.734 1 N/A Prior of the ICB (Work) Summary 0 0 N/A Post of the ICB (Goods) Summary 26.993 24 N/A Post of the NCB (Works) Summary 0.449 2 N/A Post of the NCB (Goods) Summary 0 0 N/A Post of the ICB (Non Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold (en US$ 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 100,000 3. Individual (Comparison of CVs) Above US$ 100,000 Individual (Single source) Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] July 9, 2010 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 3.124 11 Prior of number of contracts that will be let under QCBS Summary 1.886 18 Post CQS, of number CDS, I C of contracts that will be let under other methods July 9, 2010 PROCUREMENT Niger : Niger Disaster Risk Management and Urban Development Project PLAN General Information Country: Niger 2017-10-19 Bank’s Approval Date of the Original Procurement Plan: 2022-08-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145268 GPN Date: Project Name: Niger Disaster Risk Management and Urban Development Project Loan / Credit No: IDA / 53400, IDA / Q8620, IDA / 64130 Projet de Gestion des Risques de Catastrophes et de DéveloppementUrbain (PGRC-DU) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NE-PGRC-DU-21866-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 1,926,017.1 2018-05-1 / TRAVAUX DE REALISATION IDA / 53400 A posteriori Appel d'offres Open - National 1,666,666.00 Achevé 2017-07-25 2018-01-01 2017-07-30 2017-09-10 2017-08-14 2017-10-10 2017-12-25 2017-11-14 2018-01-31 ment Investments nvelope 3 3 DE LA DIGUE ROUTE DE DOS SO NE-PGRC-DU-21896-CW-RFB / Réhabilitation et constructio Comp. 1: Flood Risk Manage Single Stage - One E 2018-05-1 n d'infrastructures scolaires IDA / 53400 A posteriori Appel d'offres Open - National 320,667.00 0.00 Annulé 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 ment Investments nvelope 3 dans les zones touchées par l es inondations à Diffa NE-PGRC-DU-22531-CW-RFB / REHABILITATION D'INFRAST Comp. 1: Flood Risk Manage Single Stage - One E 2018-07-2 IDA / 53400 A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 RUCTURES SCOLAIRES DANS ment Investments nvelope 9 LES REGIONS DE DOSSO ET T ILLABERY NE-PGRC-DU-22568-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-07-2 / Construction d'infrastructur IDA / 53400 A posteriori Appel d'offres Open - National 280,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 ment Investments nvelope 1 e scolaires et de sante à SEN O NE-PGRC-DU-22586-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-09-2 / Travaux d'Extension du rés IDA / 53400 A posteriori Appel d'offres Open - National 430,000.00 0.00 Annulé 2017-12-04 2017-12-09 2018-01-20 2018-02-19 2018-03-26 ment Investments nvelope 2 eau AEP à SENO NE-PGRC-DU-22598-CW-RFB / Réhabilitation des infrastruc Comp. 1: Flood Risk Manage Single Stage - One E 2018-09-2 IDA / 53400 A posteriori Appel d'offres Open - National 83,333.00 0.00 Annulé 2017-12-11 2017-12-16 2018-01-27 2018-02-26 2018-04-02 tures scolaires dans les Régi ment Investments nvelope 9 ons de Dosso et Tillabery NE-PGRC-DU-22601-CW-RFB / Travaux de construction du Comp. 1: Flood Risk Manage Single Stage - One E 2018-07-2 IDA / 53400 A posteriori Appel d'offres Open - National 141,667.00 0.00 Annulé 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 mur de clôture de l'Hôpital d ment Investments nvelope 1 e district de Kollo Région de Tillabéry NE-PGRC-DU-22611-CW-RFB / Travaux de construction de Comp. 1: Flood Risk Manage Single Stage - One E 2018-08-0 IDA / 53400 A posteriori Appel d'offres Open - National 700,000.00 0.00 Annulé 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 10 blocs de 3 classes en mat ment Investments nvelope 4 ériaux définitifs dans la Régi on de Diffa NE-PGRC-DU-22626-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2019-01-1 IDA / 53400 A posteriori Appel d'offres Open - National 800,000.00 0.00 Annulé 2018-04-02 2018-04-07 2018-05-19 2018-06-18 2018-07-23 / Electrification de 23 carrefo ment Investments nvelope 9 urs NE-PGRC-DU-22649-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-05-1 / Travaux de réhabilitation de IDA / 53400 A priori Appel d'offres Open - National 6,000,000.00 0.00 Annulé 2017-07-28 2018-07-27 2017-08-02 2017-09-13 2017-10-13 2017-11-17 ment Investments nvelope 6 s AHA de DOSSO NE-PGRC-DU-22674-CW-RFB / Construction de Treize (13) Comp. 1: Flood Risk Manage Single Stage - One E 2,028,538.5 2018-05-1 IDA / 53400 A posteriori Appel d'offres Open - National 3,453,443.00 Achevé 2017-07-28 2016-08-15 2017-08-02 2017-09-13 2016-09-02 2017-10-13 2016-10-26 2017-11-17 2017-03-01 Casernes de Sapeurs Pompie ment Investments nvelope 5 6 rs reparties sur les 4 Régions du Niger en 13 lots NE-PGRC-DU-22681-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-05-1 / Construction/renforcement IDA / 53400 A posteriori Appel d'offres Open - National 2,795,280.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 ment Investments nvelope 6 3 Digues de protection a Nia mey NE-PGRC-DU-22592-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-08-2 / Travaux de réhabilitation de IDA / 53400 A posteriori Appel d'offres Open - National 1,666,667.00 0.00 Annulé 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 ment Investments nvelope 5 s AHA de Diffa NE-PGRC-DU-34098-CW-RFB / Réalisation des travaux de Comp. 1: Flood Risk Manage Single Stage - One E 2018-09-1 Traitement des Koris de Kar IDA / 53400 A posteriori Appel d'offres Open - National 2,000,000.00 0.00 Annulé 2017-12-01 2017-12-06 2018-01-17 2018-02-16 2018-03-23 ment Investments nvelope 9 ma, Youri et Gourou Kaina en 3 lots, Region de Tillabery NE-PGRC-DU-48784-CW-RFB / Construction de CSI Type II Comp. 1: Flood Risk Manage Single Stage - One E 2019-02-1 à Kanya, d'une maternité à G IDA / 53400 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 ment Investments nvelope 6 oubey et d'un mur de cloture à l'hôpital de district de Kollo NE-PGRC-DU-22620-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-07-1 / Construction de la route Mai IDA / 53400 A posteriori Appel d'offres Open - National 4,000,000.00 0.00 Annulé 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-15 ment Investments nvelope 4 ne soroa-Gaidam NE-PGRC-DU-22528-CW-RFB / Rehabilitation et constructio n d'INFRASTRUCTURES SCOL Comp. 1: Flood Risk Manage Single Stage - One E 2018-05-1 IDA / 53400 A posteriori Appel d'offres Open - National 997,917.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 AIRES ET SANITAIRES dans le ment Investments nvelope 6 s zones touchées par les inon dationsdans la region de Tilla béri NE-PGRC-DU-34095-CW-RFB Comp. 1: Flood Risk Manage Open - Internationa Single Stage - One E 2019-03-2 / Travaux de réalisation de la IDA / 53400 A posteriori Appel d'offres 4,000,000.00 0.00 Annulé 2018-06-03 2018-06-08 2018-07-20 2018-08-19 2018-09-23 ment Investments l nvelope 2 Route Mainé-Gaidam NE-PGRC-DU-22535-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-11-2 IDA / 53400 A posteriori Appel d'offres Open - National 1,833,333.00 0.00 Annulé 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 / Réalisation caniveaux de D ment Investments nvelope 4 osso Page 1 NE-PGRC-DU-22512-CW-RFB / Viabilisation site de recase ment SENO: blocs sanitaires LOT1, Construction et Equipe Comp. 1: Flood Risk Manage Single Stage - One E 2018-05-1 ment de classes (2 blocs de o IDA / 53400 A posteriori Appel d'offres Open - National 1,558,333.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 ment Investments nvelope 6 f six classes, bloc administrat if, case gardien, latrines et cl ôture) LO2, Construction de Centre de santé intégré de ty pe II (avec maternité) NE-PGRC-DU-22554-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-09-2 / Travaux de réalisation de fo IDA / 53400 A posteriori Appel d'offres Open - National 2,416,667.00 0.00 Annulé 2017-12-11 2017-12-16 2018-01-27 2018-02-26 2018-04-02 ment Investments nvelope 9 rages, puits et caniveaux à Ti llabery NE-PGRC-DU-57981-CW-RFQ / Fixation des dunes (clayonn Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 age, plantations, ensemence IDA / Q8620 A posteriori Demande de prix Open - National 50,000.00 62,377.47 Achevé 2018-04-20 2018-06-15 2018-08-17 ment Investments nvelope 2 ment et gardiennage) dans l a Région de Diffa commune de Chetimari Zone N°1 NE-PGRC-DU-58098-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 28,744.00 26,280.83 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-02 ment Investments nvelope 2 erres de 2015 et 2016 dans l es départements de Loga et Tibiri (7 sites) NE-PGRC-DU-58096-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 111,145.00 64,222.67 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-06 ment Investments nvelope 2 erres de 2015 et 2016 dans l a région de Diffa (9 sites) NE-PGRC-DU-58076-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 15,617.00 23,729.21 Achevé 2018-04-20 2018-06-15 2018-08-02 ment Investments nvelope 2 erres de 2015 et 2016 dans l es départements de Doutchi et Dosso (11 sites) NE-PGRC-DU-58100-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 64,000.00 45,814.12 Achevé 2018-04-20 2018-06-15 2018-07-16 ment Investments nvelope 2 erres de 2015 et 2016 dans l e département de Mainé-Sor oa (7 sites) NE-PGRC-DU-58101-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 37,138.00 12,208.12 Achevé 2018-04-20 2018-06-15 2018-08-02 ment Investments nvelope 2 erres de 2015 et 2016 dans l es départements de Kollo et Niamey V (6 sites) NE-PGRC-DU-58106-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 30,234.00 26,399.61 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-02 ment Investments nvelope 2 erres de 2015 et 2016 dans l e département de Filingue (1 2 sites) NE-PGRC-DU-58103-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 15,409.00 41,956.95 Achevé 2018-04-20 2018-06-15 2018-08-13 ment Investments nvelope 2 erres de 2015 et 2016 dans l es départements de Ouallam (9 sites) NE-PGRC-DU-58104-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 16,398.00 42,224.84 Achevé 2018-04-20 2018-06-15 2018-08-02 ment Investments nvelope 2 erres de 2015 et 2016 dans l e département de Tillabery ( 8 sites) NE-PGRC-DU-58109-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 40,258.00 55,126.08 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-10 ment Investments nvelope 2 erres de 2015 et 2016 dans l es départements de Tera, To rodi et Bankilaré (9 sites) NE-PGRC-DU-57987-CW-RFQ / Fixation des dunes (clayonn Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 age, plantations, ensemence IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 124,847.48 Achevé 2018-04-20 2018-06-15 2018-08-27 ment Investments nvelope 2 ment et gardiennage) dans l a Région de Diffa Commune de Chetimari Zone N°2 NE-PGRC-DU-58051-CW-RFQ / Fixation des dunes (clayonn Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 age, plantations, ensemence IDA / Q8620 A posteriori Demande de prix Open - National 60,000.00 124,831.28 Signé 2018-04-20 2018-06-15 2018-08-16 ment Investments nvelope 2 ment et gardiennage) dans l a Région de Diffa commune de Chetimari Zone 5 NE-PGRC-DU-58057-CW-RFQ / Fixation des dunes (clayonn Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 age, plantations, ensemence IDA / Q8620 A posteriori Demande de prix Open - National 30,000.00 62,750.54 Achevé 2018-04-20 2018-06-15 2018-08-16 ment Investments nvelope 2 ment et gardiennage) dans l a Région de Diffa commune de Chetimari Zone 7 NE-PGRC-DU-58111-CW-RFQ / Réalisation de 75 km de cor Comp. 1: Flood Risk Manage Single Stage - One E En cours d'e 2018-12-1 dons de pierres sèches sur le IDA / Q8620 A posteriori Demande de prix Open - National 37,500.00 0.00 2018-04-20 2018-06-15 ment Investments nvelope xécution 2 s versants des plateaux dans la Région de Tillabéry NE-PGRC-DU-58112-CW-RFQ / Réalisation de 75 km de cor Comp. 1: Flood Risk Manage Single Stage - One E En cours d'e 2018-12-1 IDA / Q8620 A posteriori Demande de prix Open - National 37,500.00 0.00 2018-04-20 2018-06-15 dons de pierres sèches sur le ment Investments nvelope xécution 2 s versants des plateaux dans la Région de Dosso NE-PGRC-DU-58073-CW-RFQ / Réalisation des regarnis sur Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 les sites de récuperation de t IDA / Q8620 A posteriori Demande de prix Open - National 41,652.00 29,706.83 Achevé 2018-04-20 2018-07-17 2018-06-15 2018-08-02 ment Investments nvelope 2 erres de 2015 et 2016 dans l es départements de Boboye et Dioudou (10 sites) NE-PGRC-DU-57993-CW-RFQ / Fixation des dunes (clayonn Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 age, plantations, ensemence IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 62,768.43 Achevé 2018-04-20 2018-06-15 2018-08-16 ment Investments nvelope 2 ment et gardiennage) dans l a Région de Diffa commune de Chetimari Zone 3 Page 2 NE-PGRC-DU-58041-CW-RFQ / Fixation des dunes (clayonn Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 age, plantations, ensemence IDA / Q8620 A posteriori Demande de prix Open - National 120,000.00 62,124.13 Achevé 2018-04-20 2018-06-15 2018-08-16 ment Investments nvelope 2 ment et gardiennage) dans l a Région de Diffa commune de Chetimari Zone 3 NE-PGRC-DU-58060-CW-RFQ / Fixation des dunes (clayonn Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-1 age, plantations, ensemence IDA / Q8620 A posteriori Demande de prix Open - National 80,000.00 62,246.44 Achevé 2018-04-20 2018-06-15 2018-08-16 ment Investments nvelope 2 ment et gardiennage) dans l a Région de Diffa commune de Chetimari Zone 6 NE-PGRC-DU-59864-CW-RFB / TRAVAUX DE REHABILITATI Comp. 1: Flood Risk Manage Open - Internationa Single Stage - One E 16,734,385.0 16,657,746. 2017-11-2 ON DES AMENAGEMENTS HY IDA / 53400 A priori Appel d'offres Signé 2017-02-06 2017-02-11 2017-03-25 2017-04-24 2018-05-02 2017-05-29 2018-01-05 ment Investments l nvelope 0 32 5 DRO-AGRICOLE DANS LES REGIONS DE TILLA BERY ET NIAMEY EN 6 (SIX) LOTS NE-PGRC-DU-39244-CW-RFB / Travaux de réhabilitation de Comp. 1: Flood Risk Manage Open - Internationa Single Stage - One E 16,734,385.0 2018-09-2 IDA / 53400 A priori Appel d'offres 0.00 Annulé 2017-12-04 2018-04-17 2017-12-09 2018-01-20 2018-02-19 2018-03-26 s Aménagement Hydro Agric ment Investments l nvelope 0 2 oles dans les Régions de Nia mey et Tillabéry NE-PGRC-DU-22589-CW-RFB / TRAVAUX DE PROTECTION Comp. 1: Flood Risk Manage Single Stage - One E 2018-12-2 MECANIQUE DES BERGES DE IDA / 53400 A posteriori Appel d'offres Open - National 333,333.00 0.00 Annulé 2018-03-05 2018-04-30 2018-03-10 2018-04-21 2018-05-21 2018-06-25 ment Investments nvelope 2 KORIS (9 KORIS A NIAMEY, D O et TY + TAGABATTI ET YOU RI NE-PGRC-DU-22561-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-10-0 IDA / 53400 A posteriori Appel d'offres Open - National 500,000.00 0.00 Annulé 2017-12-18 2017-12-23 2018-02-03 2018-03-05 2018-04-09 / Réalisation Piste SENO ment Investments nvelope 6 NE-PGRC-DU-103840-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-1 B / Construction des canivea IDA / 53400 A posteriori Appel d'offres Open - National 781,250.00 582,292.03 Achevé 2019-04-01 2019-06-12 2019-04-06 2019-06-12 2019-05-18 2019-07-10 2019-06-17 2019-07-30 2019-07-22 2019-09-10 ment Investments nvelope 8 ux dans la région de Tillabéri NE-PGRC-DU-103785-CW-RF Comp. 2: Capacity Building f B / Installer des feux tricolore Single Stage - One E 2019-12-2 IDA / 53400 or Urban Development and A posteriori Appel d'offres Open - National 572,916.67 258,372.49 Résilié 2019-03-04 2019-03-07 2019-03-09 2019-04-20 2019-04-02 2019-05-20 2019-04-16 2019-06-24 2019-05-06 s et passages cloutés au nive nvelope 1 Disaster Risk Management au de 23 carrefours de la vill e de Niamey NE-PGRC-DU-103831-CW-RF B / Travaux de Construire de Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-0 IDA / 53400 A posteriori Appel d'offres Open - National 684,027.78 783,695.23 Signé 2019-03-20 2019-06-17 2019-03-25 2019-06-19 2019-05-06 2019-07-17 2019-06-05 2019-07-30 2019-07-10 2019-09-23 s forages et puits villageois d ment Investments nvelope 6 ans la région de Tillabéri NE-PGRC-DU-103819-CW-RF B / Réhabiliter les stations de Comp. 1: Flood Risk Manage Single Stage - One E 2020-02-0 IDA / 53400 A posteriori Appel d'offres Open - National 868,055.56 948,715.39 Signé 2019-04-20 2020-01-23 2019-04-25 2020-04-10 2019-06-06 2020-05-14 2019-07-06 2020-06-09 2019-08-10 2020-09-17 pompage et de drainage de l' ment Investments nvelope 6 AHA de Saga dans la région de Niamey NE-PGRC-DU-103833-CW-RF B / Construction de salles de Comp. 1: Flood Risk Manage Single Stage - One E 2020-02-0 IDA / 53400 A posteriori Appel d'offres Open - National 260,416.67 260,873.12 Signé 2019-04-20 2019-05-20 2019-04-25 2019-05-21 2019-06-06 2019-06-24 2019-07-06 2019-07-10 2019-08-10 2019-09-03 classes en matériaux définitif ment Investments nvelope 6 s dans la region de Diffa NE-PGRC-DU-103795-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-1 Q / Construction mur de clôtu IDA / 53400 A posteriori Demande de prix Limited 17,361.11 16,637.89 Achevé 2019-05-20 2019-08-30 2019-07-15 2019-09-27 ment Investments nvelope 1 re de l'école de Bandabari NE-PGRC-DU-103787-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-1 Q / Construire le mur de clôt IDA / 53400 A posteriori Demande de prix Limited 104,166.67 83,009.84 Achevé 2019-05-20 2019-08-22 2019-07-15 2019-09-26 ment Investments nvelope 1 ure du l'Hopital de district de Kollo NE-PGRC-DU-103844-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-1 IDA / 53400 A posteriori Demande de prix Limited 104,166.67 84,073.65 Achevé 2019-05-20 2019-08-25 2019-07-15 2019-09-23 Q / Construire une maternité ment Investments nvelope 1 à Goubey NE-PGRC-DU-103829-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-1 Q / Réhabilitation de la case IDA / 53400 A posteriori Demande de prix Limited 86,805.56 83,382.04 Achevé 2019-05-20 2019-08-19 2019-07-15 2019-11-12 ment Investments nvelope 1 de santé de Ajé Muraba en C SI (Gaya) NE-PGRC-DU-103799-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-1 Q / Construire le mur de clotu IDA / 53400 A posteriori Demande de prix Limited 43,402.78 57,759.16 Achevé 2019-05-20 2019-08-22 2019-07-15 2019-09-26 ment Investments nvelope 1 re du CSI de Moussa Dey NE-PGRC-DU-103828-CW-RF Q / Réhabiliter du service des Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-1 IDA / 53400 A posteriori Demande de prix Limited 104,166.67 86,616.49 Achevé 2019-05-20 2019-08-19 2019-07-15 2019-10-02 urgences de l'Hôpital de Distr ment Investments nvelope 1 ict de Mainé Soroa NE-PGRC-DU-103812-CW-RF B / Réaliser les travaux de pr Comp. 1: Flood Risk Manage Single Stage - One E 2020-02-0 IDA / 53400 A posteriori Appel d'offres Open - National 225,694.44 282,887.18 Signé 2019-04-20 2020-06-08 2019-04-25 2020-06-12 2019-06-06 2020-07-10 2019-07-06 2020-08-14 2019-08-10 2020-09-30 otection des berges des koris ment Investments nvelope 6 dans la région de Dosso NE-PGRC-DU-103813-CW-RF B / Réaliser les travaux de pr Comp. 1: Flood Risk Manage Single Stage - One E En attente d 2020-02-0 otection des berges du kori d IDA / 53400 A posteriori Appel d'offres Open - National 138,888.89 0.00 2019-04-20 2019-04-25 2019-06-06 2019-07-06 2019-08-10 ment Investments nvelope 'exécution 6 e Bangou Koira Zéno et Sag a Fondo , région de Tillabéri NE-PGRC-DU-103794-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-02-0 B / Travaux de realisation de IDA / 53400 A posteriori Appel d'offres Open - National 319,444.44 459,054.58 Signé 2019-04-20 2020-01-24 2019-04-25 2020-01-29 2019-06-06 2020-02-27 2019-07-06 2020-03-24 2019-08-10 2020-04-21 ment Investments nvelope 6 l'Ouvrage de franchissement de Sirfi Koira NE-PGRC-DU-103826-CW-RF B / Travaux de realisation de Comp. 1: Flood Risk Manage Single Stage - One E 2020-04-2 IDA / 53400 A posteriori Appel d'offres Open - National 781,250.00 985,222.89 Achevé 2019-07-03 2019-04-16 2019-07-08 2019-05-15 2019-08-19 2019-05-15 2019-09-18 2019-06-07 2019-10-23 2019-07-07 s Ouvrages de protection dan ment Investments nvelope 0 s les régions d'Agadez et Tah oua NE-PGRC-DU-103832-CW-RF Q / Selection des ONGs pour l Comp. 1: Flood Risk Manage Single Stage - One E 2019-12-1 a realisation des activités de IDA / 53400 A posteriori Demande de prix Limited 170,000.00 235,466.15 Signé 2019-04-25 2019-06-11 2019-06-20 2019-08-27 ment Investments nvelope 7 renforcement des fixations d es dunes sur 300 HA en 3 Lot à Diffa NE-PGRC-DU-103825-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-02-2 B / Travaux de Construction IDA / 53400 A posteriori Demande de prix Open - National 187,500.00 0.00 Annulé 2019-06-30 2019-08-25 ment Investments nvelope 1 puits villageois Dosso Page 3 NE-PGRC-DU-103791-CW-RF Q / Selection des ONGs pour Comp. 1: Flood Risk Manage Single Stage - One E En attente d 2019-12-1 IDA / Q8620 A posteriori Demande de prix Limited 138,888.89 0.00 2019-04-25 2019-06-20 Assurer le regarnis des sites ment Investments nvelope 'exécution 7 de restauration des terres d e 2015,2016 et 2017 NE-PGRC-DU-34154-CW-RFB / travaux supplémentaires de Comp. 1: Flood Risk Manage Passation de marc 2018-08-1 rehabilitation des routes en t IDA / 53400 A posteriori Direct 44,560.00 0.00 Annulé 2018-01-08 2018-01-13 2018-02-17 ment Investments hé de gré à gré 6 erres Région de Dosso Lot 2: SIA-ADIGA-KAWRAN DEBE (3 1 km) NE-PGRC-DU-22521-CW-RFB / Rehabilitation ou constructi Comp. 1: Flood Risk Manage Single Stage - One E 2018-05-1 on de latrines dans les zones IDA / 53400 A posteriori Appel d'offres Open - National 333,333.00 0.00 Annulé 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 ment Investments nvelope 6 touchées par les inondations dans la Région de Tillabéri NE-PGRC-DU-22624-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-11-2 / Travaux de construction de IDA / 53400 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 Annulé 2018-02-05 2018-02-10 2018-03-24 2018-04-23 2018-05-28 ment Investments nvelope 4 la Digue de DIFFA NE-PGRC-DU-22547-CW-RFB Comp. 1: Flood Risk Manage Single Stage - One E 2018-08-2 / Travaux de réalisation de d IDA / 53400 A posteriori Appel d'offres Open - National 450,000.00 0.00 Annulé 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 ment Investments nvelope 5 e Puits et Mini AEP dans la Ré gion de Diffa NE-PGRC-DU-103839-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-01-1 Q / Construire le mur de clôt IDA / 53400 A posteriori Demande de prix Limited 86,805.56 0.00 Annulé 2019-05-20 2019-07-15 ment Investments nvelope 1 ure du l'Hopital de district de Kollo NE-PGRC-DU-138616-CW-RF Comp. 2: Capacity Building f Q / Construction d'un mur de Single Stage - One E 2020-06-1 IDA / Q8620 or Urban Development and A posteriori Demande de prix Limited 60,000.00 55,142.76 Signé 2019-10-20 2019-12-05 2019-12-15 2020-01-08 clôture de la Caserne de Sap nvelope 2 Disaster Risk Management eurs Pompiers de la ville de Diffa NE-PGRC-DU-103842-CW-RF B / Réalisation des Collecteur Comp. 1: Flood Risk Manage Single Stage - One E 2,432,852.9 2020-09-0 s Prioritaires du Bassin versa IDA / 53400 A posteriori Appel d'offres Open - National 2,400,000.00 Signé 2019-11-17 2019-12-09 2019-11-22 2019-12-10 2020-01-03 2020-01-17 2020-02-02 2020-02-13 2020-03-08 2020-03-12 ment Investments nvelope 6 4 nt S3 dans l’Arrondissement Communal n°1 de Niamey NE-PGRC-DU-145434-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-09-0 B / Travaux de construction d IDA / 53400 A posteriori Appel d'offres Open - National 220,000.00 191,818.82 Signé 2019-11-14 2019-09-23 2019-11-19 2020-01-09 2019-12-31 2019-11-18 2020-01-30 2019-12-19 2020-03-05 2020-02-13 ment Investments nvelope 1 e 10 puits cimentés dans la R égion de Dosso NE-PGRC-DU-151386-CW-RF B / Travaux de pose de Pierre Comp. 1: Flood Risk Manage Single Stage - One E 2020-11-0 s sèches et gabions 4350 m/l IDA / 53400 A posteriori Appel d'offres Open - National 945,455.00 364,234.40 Signé 2020-01-20 2021-04-09 2020-01-25 2021-04-09 2020-03-07 2021-05-13 2020-04-06 2021-05-25 2020-05-11 2021-07-07 ment Investments nvelope 7 sur les sites de TAGAZAR, BO GHOL, ELIWALANE à Tirozeri ne Region d'Agadez NE-PGRC-DU-151515-CW-RF Q / Ouvrage d’épandage sur Comp. 1: Flood Risk Manage Single Stage - One E 2020-10-1 IDA / 64130 A posteriori Demande de prix Limited 181,818.00 0.00 Annulé 2020-02-20 2020-04-16 des terres pastorales  à Agar ment Investments nvelope 3 égaré (INGALL) Region d'Aga dez : NE-PGRC-DU-151414-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-12-0 B / Travaux de réalisation de IDA / 64130 A posteriori Appel d'offres Open - National 263,636.00 0.00 Annulé 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 ment Investments nvelope 3 800 ml de canivaux dans la V ille de Tahoua NE-PGRC-DU-151421-CW-RF B / Travaux de pavage de rue Comp. 1: Flood Risk Manage Single Stage - One E En attente d 2020-12-0 IDA / 64130 A posteriori Appel d'offres Open - National 589,091.00 0.00 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 (9km)/ chaussées drainantes ment Investments nvelope 'exécution 3 dans la Ville de Tahoua NE-PGRC-DU-151419-CW-RF Q / Travaux de rehabilitation Comp. 1: Flood Risk Manage Single Stage - One E En attente d 2020-11-1 IDA / 64130 A posteriori Demande de prix Limited 63,636.00 0.00 2020-03-20 2020-05-15 de 20 puits maraichers (com ment Investments nvelope 'exécution 1 plement) à Iferouna Région d 'Agadez NE-PGRC-DU-151415-CW-RF B / Travaux d'Aménagements mare de Babaye (Endigueme Comp. 1: Flood Risk Manage Single Stage - One E 2020-12-0 IDA / 64130 A posteriori Appel d'offres Open - National 530,000.00 0.00 Annulé 2020-02-15 2020-02-20 2020-04-02 2020-05-02 2020-06-06 nt &plantation) et travaux de ment Investments nvelope 3 traitement de Koris de Mabo ya Amaré (Region de Tahoua ) NE-PGRC-DU-151361-CW-RF B / Travaux de Construction Comp. 1: Flood Risk Manage Single Stage - One E 1,136,708.1 2020-12-2 IDA / 64130 A posteriori Appel d'offres Open - National 586,364.00 Signé 2020-03-10 2021-12-13 2020-03-15 2022-01-14 2020-04-26 2022-01-12 2020-05-26 2022-02-21 2020-06-30 2022-04-26 de 2250 ml de chaussées dra ment Investments nvelope 8 7 inantes dans la Ville de Konni Region de Tahoua NE-PGRC-DU-151416-CW-RF Comp. 2: Capacity Building f Single Stage - One E En attente d 2020-11-0 Q / Rehabilitation des salles IDA / 64130 or Urban Development and A posteriori Demande de prix Limited 36,000.00 0.00 2020-03-15 2020-05-10 nvelope 'exécution 6 de classes à Loubé (Deoulé/B Disaster Risk Management ouza) NE-PGRC-DU-151387-GO-RF B / Traitement mécanique et biologique le plateau et les b Comp. 1: Flood Risk Manage Single Stage - One E 2020-12-2 IDA / 53400 A posteriori Appel d'offres Open - National 345,455.00 0.00 Annulé 2020-03-10 2020-03-15 2020-04-26 2020-05-26 2020-06-30 erges du Koris à Loubé /Bou ment Investments nvelope 7 za commune rurale de Déoul é et à Bado dans la commun e d’Illéla NE-PGRC-DU-151364-CW-RF Q / Travaux de construction Comp. 1: Flood Risk Manage Single Stage - One E En attente d 2020-11-0 IDA / 64130 A posteriori Demande de prix Limited 127,273.00 0.00 2020-03-15 2020-05-10 d’un seuil radier à Toumboul ment Investments nvelope 'exécution 6 commune d’Illéla NE-PGRC-DU-151359-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2020-12-0 Q / Activité de fixation des du IDA / Q8620 A posteriori Demande de prix Limited 181,000.00 132,369.56 Signé 2020-04-15 2020-08-17 2020-06-10 2020-09-30 ment Investments nvelope 7 nes dans la Région de Diffa NE-PGRC-DU-151516-CW-RF Q / Travaux de construction Comp. 1: Flood Risk Manage Single Stage - One E 2020-11-0 IDA / 53400 A posteriori Demande de prix Limited 109,000.00 90,865.66 Signé 2020-03-15 2020-02-25 2020-05-10 2020-04-09 d’un seuil radier à Kourki et S ment Investments nvelope 6 afar Banqui (Tera) NE-PGRC-DU-151411-CW-RF Q / Travaux de réhabilitation Comp. 1: Flood Risk Manage Single Stage - One E 2020-11-0 IDA / 64130 A posteriori Demande de prix Limited 68,182.00 0.00 Annulé 2020-03-15 2020-05-10 de 750 ml de caniveaux dans ment Investments nvelope 6 la ville de Konni Page 4 NE-PGRC-DU-153648-CW-RF Q / Appui à l'amélioration et Comp. 1: Flood Risk Manage Single Stage - One E En cours d'e 2020-09-1 construction des latrines fa IDA / 64130 A posteriori Demande de prix Limited 181,818.00 123,036.14 2020-01-22 2020-04-09 2020-03-18 ment Investments nvelope xécution 4 miliales (500 latrines) au prof it des menages sur les sites de déplacés NE-PGRC-DU-151409-CW-RF B / Travaux de construction d Comp. 1: Flood Risk Manage Single Stage - One E 2021-03-0 IDA / 64130 A posteriori Appel d'offres Open - National 498,545.00 378,475.52 Signé 2020-05-18 2020-08-27 2020-05-23 2020-09-11 2020-07-04 2021-01-28 2020-08-03 2021-02-23 2020-09-07 2021-03-26 e la cité de l'Innovation sur le ment Investments nvelope 6 site de Sadoré (ANSI) NE-PGRC-DU-151423-CW-RF B / Construction/Equipement Comp. 1: Flood Risk Manage Single Stage - One E 2021-02-1 IDA / 64130 A posteriori Appel d'offres Open - National 400,000.00 352,740.85 Signé 2020-04-29 2020-10-21 2020-05-04 2020-11-02 2020-06-15 2020-12-02 2020-07-15 2021-02-22 2020-08-19 2021-04-14 de 20 salles de classes dans l ment Investments nvelope 5 a Région d'Agadez NE-PGRC-DU-151418-CW-RF B / Amenagement de la mare Comp. 1: Flood Risk Manage Single Stage - One E 2021-01-0 de Maboya Amare et Traitem IDA / 64130 A posteriori Appel d'offres Open - National 267,273.00 0.00 Annulé 2020-03-16 2020-03-21 2020-05-02 2020-06-01 2020-07-06 ment Investments nvelope 2 ent biologique du plateau de Koloma et Koureya Commun e Urbaine de Tahoua NE-PGRC-DU-171206-CW-RF Q / Travaux de construction Comp. 1: Flood Risk Manage Single Stage - One E 2021-01-0 IDA / 53400 A posteriori Demande de prix Limited 30,000.00 32,361.98 Signé 2020-05-15 2020-06-02 2020-07-10 2020-08-06 d'un mur de clôture de la cas ment Investments nvelope 6 erne de sapeurs pompiers de la ville de Gaya NE-PGRC-DU-171649-CW-RF Q / Travaux de Nettoyage du Comp. 1: Flood Risk Manage Single Stage - One E 2021-01-0 IDA / 64130 A posteriori Demande de prix Limited 52,000.00 53,715.39 Signé 2020-05-16 2020-04-21 2020-07-11 2020-06-29 lit mineur du Kori en vue de l ment Investments nvelope 7 a protection de la digue d'Ifér ouane NE-PGRC-DU-185456-CW-RF Q / Travaux d’aménagement Comp. 1: Flood Risk Manage Single Stage - One E 2021-04-0 IDA / 53400 A posteriori Demande de prix Limited 28,000.00 0.00 Annulé 2020-08-09 2020-10-04 de passage cloutés autour de ment Investments nvelope 2 s feux optiques solaires réalis és par le PGRC DU NE-PGRC-DU-185463-CW-RF Q / Travaux de réalisation d'u Comp. 1: Flood Risk Manage Single Stage - One E 2021-04-2 IDA / 53400 A posteriori Demande de prix Limited 55,000.00 64,648.82 Signé 2020-09-02 2020-12-15 2020-10-28 2021-02-03 n ouvrage hydraulique (Puit ment Investments nvelope 6 pastoral) à dans le Départem ent de NGOURTI (Diffa) NE-PGRC-DU-185476-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2021-04-0 Q / Travaux de realisation du IDA / 64130 A posteriori Demande de prix Limited 90,000.00 95,584.96 Signé 2020-08-16 2020-09-04 2020-10-11 2020-11-25 ment Investments nvelope 9 CSI de Kehel Departement de Gaya NE-PGRC-DU-185627-CW-RF Q / Travaux d'amenagement des terrains de cultures dans Comp. 1: Flood Risk Manage Single Stage - One E En attente d 2021-06-0 le cadre de la mise en oeuvr IDA / 64130 A posteriori Demande de prix Limited 30,000.00 0.00 2020-10-11 2020-12-06 ment Investments nvelope 'exécution 4 e des mesures sociales autou r de l'Amenagement Hydro A gricole de DAIKAINA Region d e Tillabery NE-PGRC-DU-103792-CW-RF Q / Traitement mécanique et Comp. 1: Flood Risk Manage Single Stage - One E 2019-12-1 IDA / Q8620 A posteriori Demande de prix Limited 52,083.33 0.00 Annulé 2019-04-25 2019-06-20 biologique du plateau et du b ment Investments nvelope 7 assin versant de Youri NE-PGRC-DU-185475-CW-RF Comp. 1: Flood Risk Manage Single Stage - One E 2021-07-1 Q / Travaux de Rehaussemen IDA / 64130 A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2020-11-22 2021-01-17 ment Investments nvelope 6 t de la Digue de NDOUNGA NE-PGRC-DU-275409-CW-RF Q / Contruction de 4 classes Request for Quota Comp. 1: Flood Risk Manage Single Stage - One E 2022-09-2 en materiaux definitifs dans l IDA / 53400 A posteriori Demande de prix Limited tions (Non Bank-S 90,000.00 73,759.87 Signé 2022-02-05 2022-02-28 2022-04-02 2022-03-22 ment Investments nvelope 9 es Regions de Tahoua (Loube PD) ) et Region de Tillabery (Sako ira) NE-PGRC-DU-275413-CW-RF Request for Quota Q / Contruction d'un Mur de c Comp. 1: Flood Risk Manage Single Stage - One E 2022-09-2 IDA / 53400 A posteriori Demande de prix Limited tions (Non Bank-S 30,000.00 40,711.73 Signé 2022-02-05 2022-03-17 2022-04-02 2022-04-06 loture dans une Ecole Primair ment Investments nvelope 9 PD) e à Niamey (Ecole Zabarkan) NE-PGRC-DU-275418-CW-RF Q / Rehabilitation d'un CSI à Wanzarbé Region de Tillaber Request for Quota Comp. 1: Flood Risk Manage Single Stage - One E 2022-09-2 y, Construction d'un Mur de c IDA / 53400 A posteriori Demande de prix Limited tions (Non Bank-S 105,000.00 113,216.69 Signé 2022-02-05 2022-01-18 2022-04-02 2022-03-03 ment Investments nvelope 9 loture de 450 ml au CSI Aje PD) Muraba (Gaya) et un mur de cloture au CSI de Birnin Loko yo (Matankari) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22700-GO-RFB / Fournitures pour l'Assainiss Comp. 1: Flood Risk Manage Single Stage - One E ement Piloté par les Commu IDA / 53400 A posteriori Appel d'offres Open - National 360,000.00 0.00 Annulé 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2018-06-13 ment Investments nvelope nautés (ATPC) dans les régio ns de Diffa, Tillabéri, Dosso NE-PGRC-DU-34106-GO-RFB / Fourniture et installation de panneaux de signalisation et Comp. 1: Flood Risk Manage Open - Internationa Single Stage - One E rehabilitation de 42 feux tric IDA / 53400 A posteriori Appel d'offres 800,000.00 968,388.84 Signé 2017-12-04 2018-01-02 2017-12-09 2018-01-20 2019-04-02 2018-02-19 2019-04-19 2018-03-26 2019-05-02 2018-09-22 ment Investments l nvelope olores avec amenagement d es passages cloutés à proxim ité des feux dans la ville de N iamey NE-PGRC-DU-34111-GO-RFB / Acquisition de divers materi Comp. 1: Flood Risk Manage Single Stage - One E IDA / 53400 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2017-11-15 2017-11-20 2018-01-01 2018-01-31 2018-03-07 2018-09-03 els informatiques et mobilier ment Investments nvelope s au profit des partennaires d u PGRC-DU NE-PGRC-DU-34117-GO-RFQ / Acquisition de mobiliers pou Comp. 1: Flood Risk Manage Single Stage - One E IDA / 53400 A posteriori Demande de prix Limited 27,000.00 19,517.66 Achevé 2017-11-20 2018-01-15 2018-01-24 2018-07-14 2018-08-07 r equiper 9 salles de classe d ment Investments nvelope ans la Région de Diffa Page 5 NE-PGRC-DU-34142-GO-RFQ / Acquisition de mobiliers pou Comp. 1: Flood Risk Manage Single Stage - One E IDA / 53400 A posteriori Demande de prix Limited 10,000.00 27,708.96 Achevé 2017-11-20 2018-08-14 2018-01-15 2018-02-06 2018-07-14 2018-04-12 r equiper 6 salles de classe d ment Investments nvelope ans la Région de Tillabery NE-PGRC-DU-34091-GO-DIR / Travaux de fourniture et po Comp. 1: Flood Risk Manage Passation de marc IDA / 53400 A posteriori Direct 40,000.00 0.00 Annulé 2017-11-15 2017-11-20 2017-12-25 2018-06-23 se de 80 panneaux de signali ment Investments hé de gré à gré sation pour les 40 mini AEP s olaire de Diffa NE-PGRC-DU-48782-GO-RFB / Acquisition des équipement Comp. 1: Flood Risk Manage Open - Internationa Single Stage - One E IDA / 53400 A posteriori Appel d'offres 200,000.00 160,045.69 Achevé 2018-05-15 2018-10-09 2018-05-20 2018-10-15 2018-07-01 2018-10-23 2018-07-31 2018-12-06 2018-09-04 2019-01-21 2019-03-03 2019-12-10 s de recyclage des déchets pl ment Investments l nvelope astiques dans les communes urbaines NE-PGRC-DU-32968-GO-RFB / Fourniture de 1072 pompes solaires installation et forma Comp. 4: Contingency Com Open - Internationa Single Stage - One E IDA / 53400 A priori Appel d'offres 5,788,800.00 4,347,188.22 Signé 2018-02-27 2018-04-18 2018-03-04 2018-04-27 2018-04-15 2018-06-18 2018-05-15 2018-10-16 2018-06-19 2018-12-26 2018-12-16 tion des utilisateurs dans les ponent l nvelope Régions de Tahoua et Agade z dans le cadre du MRI-2017 NE-PGRC-DU-50933-GO-RFQ Comp. 1: Flood Risk Manage Single Stage - One E / Acquisition des gadgets pub IDA / 53400 A posteriori Demande de prix Limited 26,000.00 25,924.94 Achevé 2018-03-03 2018-02-27 2018-04-28 2018-03-20 2018-10-25 2018-05-17 ment Investments nvelope licitaires 2018 NE-PGRC-DU-49754-GO-DIR / Acquisition de 3 cameras d' Comp. 1: Flood Risk Manage Passation de marc évaluation de catastrophes e IDA / 53400 A posteriori Direct 69,900.00 59,954.94 Achevé 2018-02-28 2018-04-17 2018-03-05 2018-04-09 2018-04-09 2018-04-26 2018-10-06 2018-07-12 ment Investments hé de gré à gré t formation des agents de la protection civile sur leur utili sation NE-PGRC-DU-54042-GO-RFQ / Acquisition des semences e Comp. 1: Flood Risk Manage Single Stage - One E t l'ensemencement des sites IDA / Q8620 A posteriori Demande de prix Limited 100,000.00 73,458.42 Achevé 2018-04-14 2018-07-18 2018-06-09 2018-08-07 2018-12-06 2018-08-15 ment Investments nvelope de récupération des terres d e 2015, 2016 et 2017 NE-PGRC-DU-54044-GO-RFQ Comp. 1: Flood Risk Manage Single Stage - One E / Acquisition des Pneu pour le IDA / 53400 A posteriori Demande de prix Limited 6,500.00 6,100.68 Achevé 2018-03-24 2018-04-26 2018-05-19 2018-04-25 2018-11-15 2018-06-21 ment Investments nvelope Parc des UEP ( Tillabéry et D osso) NE-PGRC-DU-80731-GO-RFQ / Acquisition d'Equipement et Comp. 1: Flood Risk Manage Single Stage - One E de matériel informatique pou IDA / 53400 A posteriori Demande de prix Limited 60,000.00 60,996.79 Achevé 2018-10-25 2018-12-19 2018-12-20 2019-01-07 2019-06-18 2019-02-14 ment Investments nvelope r l'opérationnalisation SAP-D NPGCA et des dispositifs loca ux d'alerte précoce. NE-PGRC-DU-80656-GO-RFQ / Acquisition et installation d Comp. 1: Flood Risk Manage Single Stage - One E es lampes solaires dans la vil IDA / 53400 A posteriori Demande de prix Limited 56,000.00 51,884.03 Achevé 2018-10-25 2018-11-22 2018-12-20 2018-12-06 2019-06-18 2019-06-26 ment Investments nvelope le de Niamey en appui au pro gramme Niamey Nyalla NE-PGRC-DU-80707-GO-RFQ Comp. 1: Flood Risk Manage Single Stage - One E / Acquisition de Gabgets publ IDA / 53400 A posteriori Demande de prix Limited 18,200.00 16,858.11 Achevé 2018-11-04 2018-12-05 2018-12-30 2018-12-26 2019-06-28 2019-03-04 ment Investments nvelope icitaires 2019 NE-PGRC-DU-103808-GO-RF B / Acquisition des materiaux Comp. 1: Flood Risk Manage Single Stage - One E pour l'appui à l'amélioration IDA / 53400 A posteriori Appel d'offres Open - National 120,000.00 140,874.28 Achevé 2019-04-15 2020-03-26 2019-04-20 2020-03-26 2019-06-01 2020-04-27 2019-07-01 2020-06-29 2019-08-05 2020-08-07 2020-02-01 2020-10-06 ment Investments nvelope des latrines familiales dans l es régions de Diffa, Dosso et Tillabéri NE-PGRC-DU-103836-GO-RF Q / Assurer l'acquisition des s Comp. 1: Flood Risk Manage Single Stage - One E En cours d'ex emences et l'ensemencemen IDA / Q8620 A posteriori Demande de prix Limited 34,722.22 0.00 2019-04-27 2019-08-02 2019-06-22 2019-12-19 ment Investments nvelope écution t des sites de récupération d es terres de 2015, 2016; et 2 017 NE-PGRC-DU-103834-GO-RF Comp. 1: Flood Risk Manage Single Stage - One E Q / Acquisition de mobilier de IDA / 53400 A posteriori Demande de prix Limited 5,208.33 0.00 Annulé 2019-05-20 2019-07-15 2020-01-11 ment Investments nvelope bureau pour les UEP de Taho ua et Agadez NE-PGRC-DU-103843-GO-RF Q / Acquisition de serveurs et Comp. 1: Flood Risk Manage Single Stage - One E IDA / 53400 A posteriori Demande de prix Limited 26,041.67 27,879.73 Achevé 2019-04-25 2019-05-20 2019-06-20 2019-05-26 2019-12-17 2019-08-08 les equipements accessoires ment Investments nvelope pour la base des données PG RC-DU NE-PGRC-DU-103796-GO-RF Comp. 2: Capacity Building f Q / Acquisition des equipeme Single Stage - One E IDA / 53400 or Urban Development and A posteriori Demande de prix Open - National 475,694.00 553,813.84 Achevé 2019-07-13 2019-12-30 2019-09-07 2020-04-16 2020-03-05 2021-09-30 nts informatique pour les par nvelope Disaster Risk Management tennaires dans le cadre de la composante NTIC NE-PGRC-DU-103827-GO-RF Q / Acquisition des Autres éq Comp. 1: Flood Risk Manage Single Stage - One E En attente d' IDA / 53400 A posteriori Demande de prix Open - National 63,574.00 0.00 2019-07-06 2019-08-31 2020-02-27 uipements techniques (Ondul ment Investments nvelope exécution aire, projecteur vidéo, panne au solaire) NTIC NE-PGRC-DU-103807-GO-RF Comp. 1: Flood Risk Manage Open - Internationa Single Stage - One E B / Acquisition de drones pou IDA / 53400 A posteriori Appel d'offres 118,924.00 159,342.71 Signé 2019-07-01 2020-06-25 2019-07-06 2020-06-26 2019-08-17 2020-08-07 2019-09-16 2021-02-16 2019-10-21 2021-03-29 2020-04-18 ment Investments l nvelope r les partenaires NTIC NE-PGRC-DU-103823-GO-RF B / Acquisition du matériel d’ Comp. 1: Flood Risk Manage Open - Internationa Single Stage - One E IDA / 53400 A posteriori Appel d'offres 781,250.00 793,664.65 Signé 2019-07-08 2020-06-09 2019-07-13 2020-06-12 2019-08-24 2020-07-13 2019-09-23 2020-08-14 2019-10-28 2020-09-30 2020-04-25 assainissement pour les com ment Investments l nvelope munes urbaines d’Agadez et de Tahoua NE-PGRC-DU-103810-GO-RF Comp. 1: Flood Risk Manage Single Stage - One E En attente d' B / Acquisition de materiel de IDA / 53400 A posteriori Demande de prix Open - National 88,585.00 0.00 2019-07-20 2019-09-14 2020-03-12 ment Investments nvelope exécution cartographie NTIC NE-PGRC-DU-54058-GO-RFQ Comp. 1: Flood Risk Manage Single Stage - One E / Acquisition fourniture de bu IDA / 53400 A posteriori Demande de prix Limited 5,500.00 0.00 Annulé 2018-03-31 2018-05-26 2018-11-22 ment Investments nvelope reau UCP et UEP (Diffa, Doss o et Tillabéry) NE-PGRC-DU-138597-GO-RF Q / Acquisition des intrants (s emences de riz, semences po Comp. 1: Flood Risk Manage Single Stage - One E tagères et engrais) pour app IDA / Q8620 A posteriori Demande de prix Limited 35,000.00 38,504.41 Achevé 2019-10-08 2019-06-17 2019-12-03 2019-08-15 2020-05-31 2019-08-19 ment Investments nvelope uyer les producteurs opérant autour des Aménagements H ydro Agricoles de la Région d e Tillabery. Page 6 NE-PGRC-DU-138610-GO-RF Comp. 1: Flood Risk Manage Single Stage - One E Q / acquisition des plants pou IDA / Q8620 A posteriori Demande de prix Limited 73,000.00 0.00 Annulé 2019-10-20 2019-12-15 2020-06-12 ment Investments nvelope r les activités de regarnis 20 19 NE-PGRC-DU-34100-GO-RFB / Fourniture et installation de Comp. 1: Flood Risk Manage Single Stage - One E IDA / 53400 A posteriori Appel d'offres Open - National 140,000.00 0.00 Annulé 2017-11-07 2018-07-01 2017-11-12 2017-12-24 2018-05-31 2018-01-23 2018-07-06 2018-02-27 2018-08-26 deux (02) groupes électrogé ment Investments nvelope nes au profit du MAH/GC et l' UEP de Diffa NE-PGRC-DU-145419-GO-RF Comp. 3: Project Manageme Single Stage - One E Q / Acquisition des gadgets p IDA / 64130 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2019-11-26 2020-01-21 2020-07-19 nt nvelope ublicitaires 2020 NE-PGRC-DU-151417-GO-RF Comp. 2: Capacity Building f Q / Acquisition des Autres éq Single Stage - One E En cours d'ex IDA / 64130 or Urban Development and A posteriori Demande de prix Limited 65,455.00 0.00 2020-03-15 2021-01-14 2020-05-10 2020-11-06 uipements techniques (pann nvelope écution Disaster Risk Management eaux solaires) NTIC NE-PGRC-DU-151396-GO-RF B / Acquisition de matériels i Comp. 1: Flood Risk Manage Single Stage - One E nformatiques et mobiliers de IDA / 64130 A posteriori Appel d'offres Open - National 360,000.00 287,360.47 Signé 2020-04-20 2020-08-11 2020-04-25 2020-08-14 2020-06-06 2020-09-18 2020-07-06 2020-12-02 2020-08-10 2021-02-09 2021-02-06 ment Investments nvelope bureau pour équiper le codin g academy de l'ANSI NE-PGRC-DU-151413-GO-RF Q / Acquisition des equipeme Comp. 2: Capacity Building f nts complementaires (ordinat Single Stage - One E IDA / 53400 or Urban Development and A posteriori Demande de prix Limited 27,000.00 30,893.59 Achevé 2020-01-15 2020-04-23 2020-03-11 2020-05-27 2020-09-07 2020-07-28 eurs, imprimantes, panneaux nvelope Disaster Risk Management solaires) pour l'operationalisa tion SAP à travers les OSV/SC AP/RU NE-PGRC-DU-153645-GO-RF Comp. 1: Flood Risk Manage Single Stage - One E Q / Acquisition de 10 Kits san IDA / 64130 A posteriori Demande de prix Limited 27,000.00 46,577.03 Achevé 2020-01-22 2020-03-12 2020-03-18 2020-03-29 2020-09-14 2020-11-04 ment Investments nvelope itaires pour la région de Diffa NE-PGRC-DU-151512-GO-RF Comp. 2: Capacity Building f Q / Acquisition de consomabl Single Stage - One E En attente d' IDA / 64130 or Urban Development and A posteriori Appel d'offres Open - National 130,000.00 0.00 2020-03-15 2020-03-20 2020-05-01 2020-05-31 2020-07-05 2021-01-01 es informatiques pour les par nvelope exécution Disaster Risk Management tennaires dans le cadre de la composante NTIC NE-PGRC-DU-153650-GO-RF Q / Acquisitions de 334 moto pompes dans le cadre des Tr Comp. 4: Contingency Com Single Stage - One E avaux d'amenagement de 5h IDA / Q8620 A posteriori Demande de prix Limited 182,000.00 157,928.35 Achevé 2020-01-22 2020-02-07 2020-03-18 2020-02-18 2020-09-14 2020-08-10 ponent nvelope a de sites maraichers féminin s et la réhabilitation de 152 h a d’aménagement hydro agri cole le long de la Komadougo u NE-PGRC-DU-160891-GO-RF B / Appui à l'amélioration des Comp. 2: Capacity Building f latrines familiales au profit d Single Stage - One E IDA / 64130 or Urban Development and A posteriori Appel d'offres Open - National 120,000.00 0.00 Annulé 2020-02-24 2020-02-26 2020-04-08 2020-05-08 2020-06-12 2020-12-09 es ménages sur les sites de d nvelope Disaster Risk Management éplacés (acquisition de matér iels et matériaux de construc tion) NE-PGRC-DU-151513-GO-RF Q / Acquisition de Drones po Comp. 1: Flood Risk Manage Single Stage - One E IDA / 64130 A posteriori Demande de prix Limited 54,545.00 0.00 Annulé 2020-03-15 2020-05-10 2020-11-06 ur la Direction de la Protectio ment Investments nvelope n Civile dans le cadre de la c omposante NTIC NE-PGRC-DU-185477-GO-RF Q / Acquisition et installation Comp. 2: Capacity Building f d'un groupe électrogène au P Single Stage - One E IDA / 53400 or Urban Development and A posteriori Demande de prix Limited 50,000.00 64,316.56 Achevé 2020-08-16 2020-09-29 2020-10-11 2020-10-14 2021-04-09 2020-10-27 rofit du Ministère de l'Action nvelope Disaster Risk Management Humanitaire et de la Gestion de Catastrophe dans le cadre de la composante NTIC NE-PGRC-DU-185478-GO-RF Q / Acquisition de matériel d Comp. 1: Flood Risk Manage Open - Internationa Single Stage - One E IDA / 64130 A posteriori Demande de prix 136,000.00 94,187.70 Achevé 2020-08-09 2020-10-28 2020-10-04 2020-12-30 2021-04-02 2021-03-31 e cartographie dans le cadre ment Investments l nvelope de la composante NTIC NE-PGRC-DU-185474-GO-RF Q / Appui à la réalisation de 4 Comp. 4: Contingency Com Single Stage - One E IDA / 64130 A posteriori Demande de prix Limited 128,000.00 133,830.19 Achevé 2020-07-28 2020-04-09 2020-09-22 2020-06-19 2021-03-21 2020-09-30 00 latrines familiales dans pl ponent nvelope usieurs villages dans le cadre de l'Urgence Diffa NE-PGRC-DU-151517-GO-RF Q / Acquisition de matériel d Comp. 1: Flood Risk Manage Single Stage - One E IDA / 64130 A posteriori Demande de prix Limited 88,585.00 0.00 Annulé 2020-01-25 2020-03-21 2020-09-17 e cartographie dans le cadre ment Investments nvelope de la composante NTIC NE-PGRC-DU-203837-GO-RF Q / Acquisition des petits et g Comp. 2: Capacity Building f ros ruminants au profit du gr Single Stage - One E En attente d' IDA / 64130 or Urban Development and A posteriori Appel d'offres Limited 130,000.00 0.00 2020-12-16 2020-12-21 2021-02-01 2021-03-03 2021-04-07 2021-10-04 oupement des femmes dans nvelope exécution Disaster Risk Management le cadre des activités AGR au tour des Aménagements Hyd ro Agricole de Tillabery NE-PGRC-DU-103800-GO-RF Q / Acquisition de matériel d' etuvage et autres activités d Comp. 1: Flood Risk Manage Single Stage - One E En attente d' IDA / 53400 A posteriori Demande de prix Limited 45,000.00 0.00 2020-12-20 2021-02-14 2021-08-13 ans le cadre de l'AGR Tillaber ment Investments nvelope exécution y (site de NDOUNGA, DAIKAI NA, YELWANI 1 et 2, et SAGA ) NE-PGRC-DU-209128-GO-RF Q / Acquisition de 6 tronçonn Comp. 1: Flood Risk Manage Single Stage - One E IDA / 64130 A posteriori Demande de prix Limited 15,000.00 5,687.02 Signé 2020-12-21 2021-02-09 2021-02-15 2021-02-23 2021-08-14 euses au Profit de la Directio ment Investments nvelope n Générale de l'Environneme nt NE-PGRC-DU-209238-GO-RF Q / Acquisition de 380 sacs d Comp. 2: Capacity Building f Single Stage - One E En cours d'ex e Riz PADY au profit des prod IDA / 64130 or Urban Development and A posteriori Demande de prix Limited 19,700.00 0.00 2020-12-22 2021-01-14 2021-02-16 2021-08-15 nvelope écution ucteurs intervenants sur les Disaster Risk Management Aménagements Hydro Agrico le de la Région de Tillabery NE-PGRC-DU-255054-GO-RF Q / ACQUISITION DE 2 VEHIC Comp. 3: Project Manageme Single Stage - One E IDA / 64130 A posteriori Demande de prix Limited 150,000.00 126,378.19 Achevé 2021-10-05 2021-12-23 2021-11-30 2022-03-15 2022-05-29 2022-04-28 ULES POUR LE COMPTE DE L' nt nvelope UCP du PGRC DU Page 7 NE-PGRC-DU-275419-GO-RF Comp. 2: Capacity Building f Q / Acquisition de matériels c Single Stage - One E IDA / 64130 or Urban Development and A posteriori Demande de prix Limited 50,000.00 60,246.09 Signé 2022-02-05 2022-02-17 2022-04-02 2022-02-28 2022-09-29 omplémentaires pour le "Cod nvelope Disaster Risk Management ing Academy" au profit de l'A NSI NE-PGRC-DU-305130-GO-RF Q / Fourniture des équipeme Comp. 2: Capacity Building f Single Stage - One E En attente d' nts pour la réhabilitation des IDA / 64130 or Urban Development and A posteriori Demande de prix Limited 75,000.00 0.00 2022-07-30 2022-09-24 2023-03-23 nvelope exécution feux tricolores installes sur 1 Disaster Risk Management 1 carrefours dans la ville de Niamey NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-53790-NC-RFQ / Réalisation de Spot publicit Comp. 1: Flood Risk Manage Single Stage - One E IDA / 53400 A posteriori Demande de prix Limited 23,000.00 26,576.63 Achevé 2018-03-24 2018-04-24 2018-05-19 2018-06-20 2018-11-15 2018-07-05 aire sur la sensibilisation à l'u ment Investments nvelope tilisation civique des lignes d' appel d'urgence 18 NE-PGRC-DU-68111-NC-RFQ / Appui pour l'Acquisition et i Comp. 1: Flood Risk Manage Single Stage - One E IDA / 53400 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-07-28 2018-09-22 2019-03-21 nstallation d'un logiciel de ge ment Investments nvelope stion du parc auto pour le co mpte de la primature NE-PGRC-DU-139716-GO-RF Q / Confection des plaques d e visibilité pour les infrastruc Comp. 3: Project Manageme Single Stage - One E tures réalisées dans le cadre IDA / 53400 A posteriori Demande de prix Limited 45,000.00 33,817.69 Achevé 2019-10-20 2020-01-24 2019-12-15 2020-02-17 2020-06-12 2020-06-26 nt nvelope du PGRC-DU dans différentes zones d'intervention du Proje t (Diffa, Dosso, Tillabery, Nia mey, Tahoua et Agadez) NE-PGRC-DU-151683-NC-RF Q / Confection de Gadgets p Comp. 3: Project Manageme Single Stage - One E IDA / 64130 A posteriori Demande de prix Limited 20,000.00 15,344.17 Achevé 2019-12-30 2019-12-26 2020-02-24 2020-01-11 2020-08-22 2020-01-31 ublicitaires 2020 pour l'UCP e nt nvelope t les differents UEP du PGRC- DU NE-PGRC-DU-160922-NC-RF Comp. 2: Capacity Building f Open - Internationa Single Stage - One E B / Acquisition et installation IDA / 64130 or Urban Development and A posteriori Appel d'offres 360,000.00 352,704.49 Signé 2020-04-06 2020-12-24 2020-04-11 2020-12-24 2020-05-23 2021-01-28 2020-06-22 2021-05-18 2020-07-27 2021-07-08 2021-01-23 l nvelope d'un VSAT et accessoires au Disaster Risk Management profit de l'ANSI NE-PGRC-DU-172387-NC-RF Q / Acquisition d’équipement Comp. 2: Capacity Building f Single Stage - One E s et logiciels pour l'operation IDA / 64130 or Urban Development and A posteriori Demande de prix Limited 27,000.00 28,058.42 Signé 2020-05-23 2020-12-15 2020-07-18 2021-01-04 2021-01-14 nvelope alisation du Systeme d'Alerte Disaster Risk Management Precose SAP/DNPGCA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22707-CS-QCB S / Etudes et base de donnée Comp. 2: Capacity Building f Sélection fondée s Open - Internationa s en ligne sur l'occupation de IDA / 53400 or Urban Development and A posteriori ur la qualité et le 438,000.00 0.00 Annulé 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-24 l s zones inondables et pistes Disaster Risk Management coût pour la réduction des risques NE-PGRC-DU-22713-CS-QCB S / Etude d'avant projet som maire (APS), d'avant projet d Sélection fondée s Comp. 1: Flood Risk Manage Open - Internationa En attente d'exéc étaillé (APD) et dossiers d'ap IDA / 53400 A posteriori ur la qualité et le 576,000.00 0.00 2017-11-20 2017-12-11 2018-01-24 2018-02-21 2018-03-23 2018-04-27 2018-06-01 2019-06-01 ment Investments l ution pel d'offres (DAO) et s uivi co coût ntrôle des travaux pour la co nstruction de collecteurs S3, S4, S5, S8 et S10 NE-PGRC-DU-22716-CS-QCB S / Elaboration de plans urbai ns de référence de 13 Comm Comp. 2: Capacity Building f Sélection fondée s Open - Internationa unes , de l'audit urbain des vi IDA / 53400 or Urban Development and A posteriori ur la qualité et le 300,000.00 0.00 Annulé 2017-12-25 2018-01-15 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 l lles des 4 Régions d'intervent Disaster Risk Management coût ion du Projet et de l'audit org anisationnel et financier des communes NE-PGRC-DU-22718-CS-QCB Comp. 2: Capacity Building f Sélection fondée s Open - Internationa S / Elaboration des PDCs de 2 IDA / 53400 or Urban Development and A posteriori ur la qualité et le 360,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-29 2017-11-28 2018-01-02 2018-02-06 2019-02-06 l 4 communes Disaster Risk Management coût NE-PGRC-DU-22719-CS-QBS Comp. 2: Capacity Building f Sélection fondée s / Réalisation de l'audit organi IDA / 53400 or Urban Development and A posteriori Open - National 100,712.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-06 2018-07-06 2018-08-05 2018-09-09 2019-09-09 ur la qualité sationnel et financier des co Disaster Risk Management mmunes NE-PGRC-DU-22720-CS-LCS / APS APS EIES DAOet suivi co Comp. 1: Flood Risk Manage Sélection au moin En cours d'exécut IDA / 53400 A posteriori Open - National 100,000.00 0.00 2017-07-28 2019-03-12 2017-08-18 2017-10-01 2017-10-29 2017-11-28 2018-01-02 2018-02-06 2018-08-05 ntrôle des travaux d'aménag ment Investments dre coût ion ement d'une décharge pour l a ville de Niamey NE-PGRC-DU-22724-CS-CQS / Etude d'avant projet détaill Sélection fondée s Comp. 1: Flood Risk Manage é (APD) et dossiers d'appel d' IDA / 53400 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 ment Investments offres (DAO) et suivi contrôle s des consultants des travaux pour la digue rou te de Dosso NE-PGRC-DU-22726-CS-QCB Sélection fondée s S / APS APD EIES DAO pour la Comp. 1: Flood Risk Manage Open - Internationa IDA / 53400 A posteriori ur la qualité et le 300,000.00 0.00 Annulé 2017-09-04 2017-09-25 2017-11-08 2017-12-06 2018-01-05 2018-02-09 2018-03-16 2019-03-16 construction de canaux et re ment Investments l coût profilage le long du Gounty Y ena (9 km) NE-PGRC-DU-22727-CS-CQS / Etudes APD/EIES/DAO et sui Sélection fondée s Comp. 1: Flood Risk Manage En cours d'exame vi contrôle pour les travaux d IDA / 53400 A posteriori ur les qualification Open - National 120,500.00 0.00 2017-07-28 2017-07-17 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 ment Investments n e construction de caniveaux s des consultants puits et forages à Tillabery Page 8 NE-PGRC-DU-22728-CS-CQS / ETUDES COMPLEMENTAIRE Sélection fondée s Comp. 1: Flood Risk Manage S ET SUIVI CONTRÖLE DES T IDA / 53400 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 ment Investments RAVAUX DE REALISATION DE s des consultants LA DIGUE ROUTE DE DOSSO NE-PGRC-DU-22733-CS-CQS Sélection fondée s / ETUDES APS APD DAO REH Comp. 1: Flood Risk Manage IDA / 53400 A posteriori ur les qualification Open - National 150,000.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 ABILITATION CONSTRUCTION ment Investments s des consultants PUITS ET CANIVEAU DOSSO NE-PGRC-DU-22734-CS-QCB Sélection fondée s Comp. 1: Flood Risk Manage Open - Internationa S / Actualisation études et su IDA / 53400 A posteriori ur la qualité et le 200,000.00 290,289.49 Achevé 2017-07-28 2018-01-08 2017-08-18 2017-10-01 2018-03-05 2017-10-29 2018-05-06 2017-11-28 2018-05-15 2018-01-02 2018-05-31 2018-02-06 2018-06-03 2019-02-06 2018-08-15 ment Investments l ivi contrôle Route Mainé-Gaid coût am NE-PGRC-DU-22740-CS-CQS / RECRUTEMENT D'UNE ONG Sélection fondée s Comp. 1: Flood Risk Manage POUR ACCOMPAGNEMENT D IDA / 53400 A posteriori ur les qualification Open - National 244,152.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 ment Investments ES ACTIVITES AGR AMENAGE s des consultants MENT DOSSO (Sakongui, Tar a et Kessa) NE-PGRC-DU-22741-CS-CQS / ACTUALISATION ETUDES ET SUIVI CONTRÔLE DES TRAVA Sélection fondée s Comp. 1: Flood Risk Manage UX DE CONSTRUCTION DES 1 IDA / 53400 A posteriori ur les qualification Open - National 90,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 ment Investments 0 BLOCS DE 3 CLASSES EN P s des consultants LAQUE ECOLOGIQUE DANS L E CADRE DE L'URGENCE RE GION DE DIFFA NE-PGRC-DU-22742-CS-CQS / Elaboration de la politique n Comp. 2: Capacity Building f Sélection fondée s ationale de l'action humanita IDA / 53400 or Urban Development and A posteriori ur les qualification Open - National 200,000.00 0.00 Annulé 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 ire et de la gestion des catas Disaster Risk Management s des consultants trophes et de son plan d'acti ons NE-PGRC-DU-70949-CS-INDV / CONCEPTION ET HEBERGEM ENT D'UN SITE WEB POUR L Comp. 3: Project Manageme Sélection fondée s En cours d'exécut IDA / 53400 A posteriori Open - National 10,181.00 0.00 2018-07-31 2018-09-25 2018-08-21 2019-01-15 2018-10-04 2018-10-17 2018-11-01 2018-12-01 2018-12-31 2019-02-04 2020-02-04 E PROJET DE GESTION DES RI nt ur la qualité ion SQUES DE CATASTROPHES ET DU DÉVE LOPPEMENT URBAIN (PGRC-D U) NE-PGRC-DU-80733-CS-QCB S / Recrutement d'un auditeu Sélection fondée s Comp. 1: Flood Risk Manage En cours d'exécut r Externe pour la réalisation IDA / 53400 A posteriori ur la qualité et le Open - National 50,000.00 0.00 2018-11-01 2018-11-09 2018-11-22 2018-11-19 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2020-05-12 ment Investments ion d'audit des compte exercice coût 2018, 2019, 2020 et cloture NE-PGRC-DU-80700-CS-CQS / Recrutement d'un consultan t chargé de la mise à jour de Sélection fondée s Comp. 1: Flood Risk Manage 8 plans de Developpement C IDA / 53400 A posteriori ur les qualification Open - National 120,000.00 147,948.08 Signé 2018-11-10 2019-03-20 2018-12-01 2019-05-09 2019-01-14 2019-06-25 2019-02-13 2019-08-25 2019-03-20 2019-08-29 2019-09-16 ment Investments ommunaux (PDC) en intégra s des consultants nt les dimensions ''changem ents climatiques, paix et sec urité" NE-PGRC-DU-96507-CS-QCB S / Recrutement d'un auditeu Sélection fondée s Comp. 3: Project Manageme Open - Internationa r Externe pour la réalisation IDA / 53400 A posteriori ur la qualité et le 50,000.00 37,490.67 Achevé 2018-12-31 2019-02-05 2019-01-21 2019-02-28 2019-03-06 2019-01-03 2019-04-03 2019-02-28 2019-05-03 2019-02-28 2019-06-07 2019-04-02 2019-07-12 2019-05-10 2020-07-11 2019-06-28 nt l d'audit des compte exercice coût 2018, 2019, 2020 et cloture NE-PGRC-DU-96510-CS-QCB Sélection fondée s S / Recrutement d'un cabinet Comp. 3: Project Manageme Open - Internationa IDA / 53400 A posteriori ur la qualité et le 15,000.00 13,208.92 Achevé 2018-12-31 2019-02-26 2019-01-21 2019-02-28 2019-03-06 2019-04-19 2019-04-03 2019-05-06 2019-05-03 2019-05-17 2019-06-07 2019-05-24 2019-07-12 2019-06-11 2020-07-11 2019-07-26 chargé de sélectionner le coo nt l coût rdonnateur National du PGRC -DU NE-PGRC-DU-103786-CS-CQ Comp. 2: Capacity Building f Sélection fondée s S / Appui à l'amélioration des IDA / 53400 or Urban Development and A posteriori ur les qualification Open - National 50,000.00 0.00 Annulé 2019-04-15 2019-05-06 2019-06-19 2019-07-19 2019-08-23 2020-02-19 latrines familiales dans les ré Disaster Risk Management s des consultants gions de Diffa, Dosso et Tilla béri NE-PGRC-DU-103793-CS-CQ Sélection fondée s S / Suivi contrôle des travaux Comp. 1: Flood Risk Manage IDA / 53400 A posteriori ur les qualification Open - National 27,777.78 0.00 Annulé 2019-03-15 2019-04-05 2019-05-19 2019-06-18 2019-07-23 2020-01-19 de l'Ouvrage de franchissem ment Investments s des consultants ent de Sirfi Koira NE-PGRC-DU-103841-CS-CQ S / Recrutement d'un cabinet Sélection fondée s Comp. 1: Flood Risk Manage pour realiser les Etudes tech IDA / 53400 A posteriori ur les qualification Open - National 130,208.33 89,390.56 Signé 2019-03-15 2020-01-30 2019-04-05 2019-05-19 2020-07-27 2019-06-18 2020-08-31 2019-07-23 2020-09-29 2020-01-19 ment Investments niques et environementales t s des consultants ravaux prévus dans le cadre du Fonds additioonnel NE-PGRC-DU-22722-CS-CQS / Etude d'avant projet détaill Sélection fondée s Comp. 1: Flood Risk Manage é (APD) et dossiers d'appel d' IDA / 53400 A posteriori ur les qualification Open - National 110,000.00 0.00 Annulé 2017-09-04 2017-09-25 2017-11-08 2017-12-08 2018-01-12 2018-07-11 ment Investments offres (DAO) pour les travaux s des consultants de réalisation des caniveaux de Dosso NE-PGRC-DU-22717-CS-QBS Comp. 2: Capacity Building f Sélection fondée s / Elaboration d'un guide sur l' IDA / 53400 or Urban Development and A posteriori Open - National 100,000.00 0.00 Annulé 2018-04-02 2018-04-23 2018-06-06 2018-07-04 2018-08-03 2018-09-02 2018-10-07 2019-10-07 ur la qualité intercollectivité Disaster Risk Management NE-PGRC-DU-22709-CS-QCB S / Etude de faisabilité pour l Sélection fondée s Comp. 1: Flood Risk Manage Open - Internationa a régulation des écoulement IDA / 53400 A posteriori ur la qualité et le 250,000.00 0.00 Annulé 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2019-04-13 ment Investments l s dans les bassins versants d coût e la SIRBA et du GOROUBI NE-PGRC-DU-22710-CS-QCB S / Elaboration d'une politiqu Sélection fondée s Comp. 1: Flood Risk Manage Open - Internationa e nationale d'assainissement IDA / 53400 A posteriori ur la qualité et le 400,000.00 0.00 Annulé 2017-11-15 2017-12-06 2018-01-19 2018-02-16 2018-03-18 2018-04-22 2018-05-27 2019-05-27 ment Investments l (eaux pluviales, eaux usées, coût assainissement de base, déc hets solides) NE-PGRC-DU-34174-CS-QBS Sélection fondée s / Etude-Suivi-contrôle des tra Comp. 1: Flood Risk Manage IDA / 53400 A posteriori ur les qualification Open - National 20,000.00 0.00 Annulé 2017-12-04 2017-12-25 2018-02-07 2018-03-09 2018-04-13 2018-10-10 vaux supplementaire sur la R ment Investments s des consultants oute en Terre SIA-ADIGA NE-PGRC-DU-22729-CS-CQS / ETUDES COMPLEMENTAIRE Sélection fondée s Comp. 1: Flood Risk Manage S ET SUIVI CONTRÖLE DES T IDA / 53400 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 ment Investments RAVAUX DE REALISATION DE s des consultants S CANIVEAUX DE DOSSO Page 9 NE-PGRC-DU-22731-CS-CQS Sélection fondée s Comp. 1: Flood Risk Manage / ETUDES APS APD DAO CON IDA / 53400 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 ment Investments FORTATION AHA KARMA s des consultants NE-PGRC-DU-22732-CS-CQS Sélection fondée s Comp. 1: Flood Risk Manage / ETUDES APS APD DAO CON IDA / 53400 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-04-11 2018-05-11 2018-06-15 2018-12-12 ment Investments FORTATION AHA KARMA s des consultants NE-PGRC-DU-138614-CS-CQ S / Recrutement d'une ONG p our faciliter les Activités Gén Comp. 2: Capacity Building f Sélection fondée s En cours d'exécut ératrices de revenus au profi IDA / Q8620 or Urban Development and A posteriori ur les qualification Open - National 60,000.00 0.00 2019-10-03 2019-07-08 2019-10-24 2019-12-07 2020-01-06 2020-02-10 2020-08-08 ion t des groupements des femm Disaster Risk Management s des consultants es autour des Aménagement s Hydro Agricoles de Tillaber y NE-PGRC-DU-91457-CS-CQS Sélection fondée s / Recrutement d'un cabinet c Comp. 3: Project Manageme Open - Internationa IDA / 53400 A priori ur la qualité et le 15,000.00 0.00 Annulé 2018-12-19 2019-02-26 2019-01-09 2019-02-22 2019-03-22 2019-04-21 2019-05-26 2019-06-30 2020-06-29 hargé de sélectionner le coor nt l coût donnateur National du PGRC- DU NE-PGRC-DU-151514-CS-CQ Sélection fondée s S / Etudes techniques et envi Comp. 1: Flood Risk Manage IDA / 53400 A posteriori ur les qualification Open - National 36,000.00 0.00 Annulé 2020-02-15 2020-03-07 2020-04-20 2020-05-20 2020-06-24 2020-12-21 ronnementale de la Digue de ment Investments s des consultants Kirkissoye Niamey NE-PGRC-DU-151420-CS-CQ S / Etudes et suivi contrôle d Comp. 2: Capacity Building f Sélection fondée s es travaux de construction d IDA / 64130 or Urban Development and A posteriori ur les qualification Open - National 44,000.00 42,779.31 Signé 2020-01-20 2020-03-16 2020-02-10 2020-03-25 2020-03-27 2020-04-24 2020-04-07 2020-05-29 2020-05-18 2020-11-25 e la cité de l'innovation dans Disaster Risk Management s des consultants le cadre de la composante N TIC NE-PGRC-DU-151510-CS-CQ S / Recrutement d'une firme Comp. 2: Capacity Building f Sélection fondée s pour l'etude sur le transfert e IDA / 53400 or Urban Development and A posteriori ur les qualification Open - National 85,000.00 0.00 Annulé 2020-06-10 2020-07-01 2020-08-14 2020-09-13 2020-10-18 2021-04-16 t le financement des compet Disaster Risk Management s des consultants ences municipales dans les z ones d'intervention du Projet NE-PGRC-DU-171196-CS-CQ S / Élaboration e diffusion d'u Comp. 2: Capacity Building f Sélection fondée s n spot de sensibilisation sur l IDA / 53400 or Urban Development and A posteriori ur les qualification Open - National 37,600.00 0.00 Annulé 2020-04-30 2020-05-21 2020-07-04 2020-08-03 2020-09-07 2021-03-06 a conduite à tenir au niveau Disaster Risk Management s des consultants des carrefours dotés des feu x tricolores solaires financés dans le cadre du PGRC-DU NE-PGRC-DU-22735-CS-CQS / Actualisation des études et Sélection fondée s suivi contrôle des travaux de Comp. 1: Flood Risk Manage IDA / 53400 A posteriori ur les qualification Open - National 90,000.00 0.00 Annulé 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 construction d'infrastructures ment Investments s des consultants scolaires et sanitaires dans la régions de Dosso et Tillabery NE-PGRC-DU-209129-CS-CQ S / Etudes de faisabilité tech Sélection fondée s Comp. 4: Contingency Com nique, environnementales et IDA / 64130 A posteriori ur les qualification Open - National 90,000.00 0.00 Annulé 2020-12-22 2021-01-12 2021-02-25 2021-03-27 2021-05-01 2021-10-28 ponent sociales des aménagements s des consultants et assainissements urbains NE-PGRC-DU-209132-CS-CQ Sélection fondée s S / Etudes sommaires pour la Comp. 4: Contingency Com IDA / 64130 A posteriori ur les qualification Open - National 55,000.00 0.00 Annulé 2020-12-22 2021-01-12 2021-02-25 2021-03-27 2021-05-01 2021-10-28 réhabilitation des sites marai ponent s des consultants chers endommagés par les in ondations NE-PGRC-DU-209130-CS-CQ S / Etudes de faisabilité tech nique, environnementale et s Sélection fondée s Comp. 4: Contingency Com ociale pour la Réalisation des IDA / 64130 A posteriori ur les qualification Open - National 85,000.00 0.00 Annulé 2020-12-22 2021-01-12 2021-02-25 2021-03-27 2021-05-01 2021-10-28 ponent travaux de protection des Be s des consultants rges sur le Goulbi Maradi (Du plex Maradi Kolia, Tibiri Korin Garin Daouré et Tibiri Korin K awkaye) NE-PGRC-DU-221036-CS-QB S / Recrutement d'un consult Comp. 2: Capacity Building f Sélection fondée s ant Acquisition d’images à ha Open - Internationa IDA / 64130 or Urban Development and A posteriori ur les qualification 108,000.00 134,963.56 Signé 2021-03-15 2021-03-12 2021-04-05 2021-04-15 2021-05-19 2021-07-19 2021-06-18 2021-08-18 2021-07-23 2021-10-27 2022-01-19 ute résolution spatiale et pro l Disaster Risk Management s des consultants duction de produits d’inform ation dans le cadre de la com posante NTIC NE-PGRC-DU-247088-CS-QC BS / Sélection d'un Cabinet p Sélection fondée s our conduire l'Audit Externe Comp. 3: Project Manageme IDA / 64130 A posteriori ur la qualité et le Open - National 35,000.00 24,972.91 Signé 2021-08-23 2021-09-22 2021-09-13 2021-10-11 2021-10-27 2022-01-14 2021-11-24 2022-02-21 2021-12-24 2022-04-08 2022-01-28 2022-04-20 2022-03-04 2022-05-12 2023-03-04 des comptes pour les Exercic nt coût es 2021, 2022 et la Période d e grâce pour le PGRC DU et l es activités du MRI2020 NE-PGRC-DU-258868-CS-CQ Comp. 2: Capacity Building f Sélection fondée s S / Sélection d'un cabinet cha IDA / 64130 or Urban Development and A posteriori ur les qualification Open - National 15,000.00 31,212.02 Signé 2021-10-26 2021-11-12 2021-11-16 2021-11-24 2021-12-30 2022-01-25 2022-01-29 2022-01-25 2022-03-05 2022-02-08 2022-09-01 rgé de l'Elaboration d'un Man Disaster Risk Management s des consultants uel d'un Manuel d'Exécution du PIDUREM NE-PGRC-DU-258865-CS-CQ S / Sélection d'un consultant Comp. 2: Capacity Building f Sélection fondée s pour l'Elaboration du Manuel IDA / 64130 or Urban Development and A posteriori ur les qualification Open - National 25,000.00 24,364.03 Signé 2021-10-26 2021-11-12 2021-11-16 2021-12-03 2021-12-30 2022-01-14 2022-01-29 2022-01-21 2022-03-05 2022-01-31 2022-09-01 de Procédure de Gestion Ad Disaster Risk Management s des consultants ministrative, Financière et Pa ssation de Marchés du PIDUR EM INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PGRC-DU-22736-CS-INDV / consultant Pour conduire la Comp. 2: Capacity Building f collecte des données sur les IDA / 53400 or Urban Development and A priori Individuel Direct 150,000.00 0.00 Annulé 2017-07-28 2017-08-07 2017-08-28 2017-10-02 2018-03-31 bâtiments et les terrains agri Disaster Risk Management coles dans la commune V, le quartier de Goudel et le quar tier de Lossa-Goungou NE-PGRC-DU-22739-CS-INDV Comp. 1: Flood Risk Manage IDA / 53400 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2017-07-28 2017-08-02 2017-08-23 2017-09-27 2018-03-26 / EIES DIGUE ROUTE DIFFA ment Investments Page 10 NE-PGRC-DU-48768-CS-INDV / Recrutement d'un consultan t chargé de la mise à jour du cadre de Gestion Environnem Comp. 4: Contingency Com IDA / 53400 A posteriori Individuel Limited 13,090.00 9,531.15 Achevé 2018-02-13 2018-01-10 2018-02-18 2018-02-09 2018-03-11 2018-02-20 2018-04-15 2018-04-13 2018-10-12 2018-08-02 entale et Sociales (CGES) du ponent PGRC-DU pour couvrir les rég ions d'Agadez et de Tahoua d ans le cadre de l'extension d u projet NE-PGRC-DU-48770-CS-INDV / Recrutement d'un consultan t chargé de la mise à jour du cadre de politique de Réinsta Comp. 4: Contingency Com IDA / 53400 A posteriori Individuel Limited 9,430.00 7,975.05 Achevé 2018-02-13 2018-01-24 2018-02-18 2018-02-09 2018-03-11 2018-03-11 2018-04-15 2018-04-12 2018-10-12 2018-11-02 llation des Populations (CPRP ponent ) du PGRC-DU pour couvrir le s régions d'Agadez et de Tah oua dans le cadre de l'extens ion du projet NE-PGRC-DU-48772-CS-INDV / Recrutement d'un consultan t chargé de la mise à jour du Comp. 4: Contingency Com plan anti-parasitaires et Gest IDA / 53400 A posteriori Individuel Limited 8,430.00 9,505.78 Achevé 2018-02-13 2018-02-02 2018-02-18 2018-02-09 2018-03-11 2018-03-13 2018-04-15 2018-04-12 2018-10-12 2018-12-18 ponent ion des Pesticides (GPP) du P GRC-DU pour couvrir les régi ons d'Agadez et de Tahoua d ans le cadre de l'extension d u projet NE-PGRC-DU-48773-CS-INDV / Recrutement d'un consultan Comp. 3: Project Manageme IDA / 53400 A posteriori Individuel Limited 15,000.00 6,866.61 Achevé 2018-03-19 2018-05-07 2018-03-24 2018-05-03 2018-04-14 2018-06-06 2018-05-19 2018-06-11 2018-11-15 2018-08-06 t pour la mise à jour du Manu nt el de procédure du PGRC-DU NE-PGRC-DU-58280-CS-INDV / Recrutement d'un consultan Comp. 1: Flood Risk Manage IDA / 53400 A posteriori Individuel Limited 8,500.00 6,866.61 Achevé 2018-04-16 2018-05-01 2018-04-21 2018-06-08 2018-05-12 2018-06-25 2018-06-16 2018-07-08 2018-12-13 2018-09-10 t pour la mise à jour de la ba ment Investments se de données "PGRC-DU" NE-PGRC-DU-50930-CS-CDS Sélection de cons / Recrutement consultant en Comp. 1: Flood Risk Manage IDA / 53400 A posteriori ultants par entent Direct 33,000.00 23,938.03 Achevé 2018-07-31 2018-09-26 2018-08-10 2018-09-26 2018-10-14 2018-10-08 2019-04-12 2018-12-05 Infrastructure pour le suivi de ment Investments e directe s activités du PGRC-DU NE-PGRC-DU-92303-CS-INDV / Recrutement de consultant Comp. 3: Project Manageme local pour la poursuite de la IDA / 53400 A posteriori Individuel Limited 20,000.00 17,523.92 Signé 2018-12-26 2019-01-15 2018-12-31 2019-12-02 2019-01-21 2019-12-18 2019-02-25 2019-12-24 2019-08-24 nt mise en place d'une base de données suivi -évaluation au sein du PGRC-DU NE-PGRC-DU-103835-CS-IND V / Recrutement d'un consult Comp. 1: Flood Risk Manage IDA / 53400 A posteriori Individuel Limited 17,361.00 0.00 Annulé 2019-04-20 2019-04-25 2019-05-16 2019-06-20 2019-12-17 ant pour l'Elaboration du cad ment Investments re réglementaire et juridique des drones NE-PGRC-DU-108338-CS-IND Comp. 1: Flood Risk Manage En cours d'exécut V / Recrutement du Coordon IDA / 53400 A posteriori Individuel Open 85,750.00 0.00 2019-04-08 2019-04-09 2019-05-27 2019-06-17 2019-07-22 2020-01-18 ment Investments ion nateur National du PGRC-DU NE-PGRC-DU-109638-CS-IND V / Recrutement d'un consult ant pour réaliser les Etudes d 'Impact Environnemental et Comp. 1: Flood Risk Manage Sociale EIES dans le cadre de IDA / 53400 A posteriori Individuel Limited 17,800.00 16,668.79 Achevé 2019-04-15 2019-04-10 2019-04-20 2019-04-12 2019-05-11 2019-04-30 2019-06-15 2019-05-02 2019-12-12 2019-06-18 ment Investments réalisation des infrastructure s Socio Economiques et les o uvrages de protection des ter res et d'habitation dans la Ré gion d'Agadez NE-PGRC-DU-110369-CS-IND V / Recrutement d'un consult ant pour la Préparation d'un Plan d'Action de Réinstallatio Comp. 1: Flood Risk Manage IDA / 53400 A posteriori Individuel Limited 14,600.00 15,883.62 Achevé 2019-04-17 2019-04-19 2019-04-22 2019-04-26 2019-05-13 2019-05-22 2019-06-17 2019-06-05 2019-12-14 2019-07-15 n (PAR) des Personnes Affect ment Investments ées par les Travaux de constr uction des trois collecteurs d ans l'Arrondissement Commu nal 1 de Niamey NE-PGRC-DU-22743-CS-INDV Comp. 1: Flood Risk Manage / ETUDES ET SUIVI CONTRÔL IDA / 53400 A posteriori Individuel Limited 20,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2018-05-31 ment Investments E ROUTE EN TERRE SIA ADIG UA NE-PGRC-DU-22737-CS-INDV Comp. 2: Capacity Building f / Etude sur les procédures o IDA / 53400 or Urban Development and A posteriori Individuel Limited 20,000.00 0.00 Annulé 2018-01-08 2018-01-13 2018-02-03 2018-03-10 2018-09-06 pérationnelles pour l'alerte a Disaster Risk Management ux catastrophes NE-PGRC-DU-22738-CS-INDV / AUDIT ENVIRONNEMENTAL Comp. 1: Flood Risk Manage IDA / 53400 A posteriori Individuel Limited 18,000.00 0.00 Annulé 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2018-05-31 ET SOCIAL REHABILITATION B ment Investments ASSINS VERSANTS NE-PGRC-DU-22744-CS-CDS Comp. 2: Capacity Building f Sélection de cons / IEC SAMPLAT (POURSUITE IDA / 53400 or Urban Development and A priori ultants par entent Direct 144,000.00 0.00 Annulé 2018-01-16 2018-01-26 2018-04-01 2018-09-28 3 MOIS) Disaster Risk Management e directe NE-PGRC-DU-138600-CS-IND V / Recrutement d'un Assista Comp. 3: Project Manageme En cours d'exécut IDA / 53400 A posteriori Individuel Open 36,000.00 0.00 2019-10-03 2019-10-21 2019-11-21 2019-12-12 2020-01-16 2020-07-14 nt comptable pour servir à l' nt ion UCP de Niamey NE-PGRC-DU-138604-CS-IND Comp. 3: Project Manageme En cours d'exécut V / Recrutement d'un Coordo IDA / 53400 A posteriori Individuel Open 48,000.00 0.00 2019-10-03 2019-10-21 2019-11-21 2019-12-12 2020-01-16 2020-07-14 nt ion nnateur Régional pour l'UEP de Niamey NE-PGRC-DU-103830-CS-CD S / Recrutement d'une ONG p Comp. 2: Capacity Building f Sélection de cons our faciliter les Activités Gén IDA / 53400 or Urban Development and A posteriori ultants par entent Direct 60,763.89 0.00 Annulé 2019-04-22 2019-05-02 2019-07-06 2020-01-02 ératrices de revenus au profi Disaster Risk Management e directe t des groupements des femm es NE-PGRC-DU-145431-CS-IND V / Recrutement d’un consult ant international individuel p Comp. 1: Flood Risk Manage our l’Organisation d’un Atelie IDA / 64130 A posteriori Individuel Limited 17,000.00 17,774.86 Signé 2019-11-24 2020-01-23 2019-11-29 2020-02-11 2019-12-20 2020-08-12 2020-01-24 2020-08-13 2020-07-22 ment Investments r d’Information sur les Drone s et l’appui à la finalisation d e la législation des drones au Niger. Page 11 NE-PGRC-DU-146425-CS-IND V / Recrutement d’un consult ant charge de la Réalisation Comp. 1: Flood Risk Manage d’une étude d’impact environ IDA / 53400 A posteriori Individuel Limited 19,000.00 17,396.95 Achevé 2019-11-27 2020-01-21 2019-12-02 2020-02-07 2019-12-23 2020-02-18 2020-01-27 2020-02-24 2020-07-25 2020-03-18 ment Investments nemental et social du sous-pr ojet des travaux de traiteme nt et la protection des berges du Kori de Dosso NE-PGRC-DU-151365-CS-IND Comp. 4: Contingency Com V / Recrutement d'un consult IDA / 53400 A posteriori Individuel Limited 50,000.00 34,932.19 Signé 2020-04-10 2020-05-20 2020-04-15 2020-10-12 2020-05-06 2020-10-16 2020-06-10 2020-10-28 2020-12-07 ponent ant pour l'evaluation des acti vités du MRI NE-PGRC-DU-153657-CS-IND V / Mise à jour de l'Etude EIE Comp. 1: Flood Risk Manage IDA / 64130 A posteriori Individuel Limited 9,000.00 9,708.37 Achevé 2020-01-17 2020-01-16 2020-01-22 2020-01-20 2020-02-12 2020-01-26 2020-03-18 2020-02-05 2020-09-14 2020-05-12 S pour la réhabilitation de l’A ment Investments ménagement Hydro Agricole de SAGA NE-PGRC-DU-160921-CS-IND V / RECRUTEMENT D’UN CON SULTANT NTIC EXPERT EN TR Comp. 2: Capacity Building f En cours d'exécut ANSFORMATION NUMÉRIQUE IDA / 64130 or Urban Development and A posteriori Individuel Open 35,000.00 0.00 2020-02-25 2020-02-21 2020-04-14 2020-05-05 2020-06-09 2020-12-06 ion DES TERRITOIRES AUPRÈS D Disaster Risk Management E L’AGENCE NATIONALE POU R LA SOCIÉTÉ DE L’INFORMA TION (ANSI). NE-PGRC-DU-171203-CS-IND V / Recrutement d’un consult ant pour l'Evaluation thémati que de la prise en compte de Comp. 1: Flood Risk Manage En cours d'exécut la question du genre et l’incl IDA / 53400 A posteriori Individuel Limited 40,000.00 0.00 2020-05-04 2020-06-26 2020-05-09 2020-05-30 2020-07-04 2020-12-31 ment Investments ion usion des groupes vulnérable s dans le cadre des interventi ons du Projet de Gestion des Risques de Catastrophes et d e Développement Urbain NE-PGRC-DU-171212-CS-IND V / Elaboration de Plans de G estion Environnementale et S ociale (PGES), en document s Comp. 1: Flood Risk Manage En cours d'exame éparés par site, des ouvrages IDA / 53400 A posteriori Individuel Limited 20,000.00 0.00 2020-05-10 2020-06-26 2020-05-15 2020-06-05 2020-07-10 2021-01-06 ment Investments n de protection des villages de Bado, Toumboul et de Loubé dans les départements d’Illél a et de Bouza et le traitemen t des bassins versants adja NE-PGRC-DU-171408-CS-IND V / Conception d'un message de sensibilisation des populat Comp. 4: Contingency Com En attente d'exéc IDA / 53400 A posteriori Individuel Limited 8,000.00 0.00 2020-05-10 2020-05-15 2020-06-05 2020-07-10 2021-01-06 ions bénéficiaires sur l'utilisa ponent ution tion et la sauvegarde des infr astructures réalisées dans le cadre du PGRC DU NE-PGRC-DU-191050-CS-IND V / Recrutement d'un consult Comp. 4: Contingency Com ant pour l’élaboration du Pro IDA / 64130 A posteriori Individuel Limited 6,000.00 7,378.12 Achevé 2020-08-31 2020-08-29 2020-09-05 2020-09-01 2020-09-26 2020-09-07 2020-10-31 2020-09-08 2021-04-29 2020-09-22 ponent gramme de mise en Oeuvre du MRI Niger au titre de l'ann ée 2020 NE-PGRC-DU-191055-CS-IND V / Recrutement d'un consult Comp. 1: Flood Risk Manage En cours d'exame ant pour l’élaboration d'un Pl IDA / 64130 A posteriori Individuel Limited 25,000.00 0.00 2020-09-07 2020-09-15 2020-09-12 2020-10-03 2020-11-07 2021-05-06 ment Investments n an de Gestion des Sites resta urés dans le cadre du PGRC DU NE-PGRC-DU-191052-CS-IND V / Recrutement d'un consult Comp. 4: Contingency Com ant en vue de l'actualisation IDA / 64130 A posteriori Individuel Limited 6,000.00 0.00 Annulé 2020-08-31 2020-08-30 2020-09-05 2020-09-26 2020-10-31 2021-04-29 ponent du Manuel d'opération du Mé canisme de Riposte Immédia te MRI 2020 NE-PGRC-DU-196011-CS-IND V / Recrutement d'un Spécial Comp. 3: Project Manageme iste en Sauvegarde Environn IDA / 64130 A posteriori Individuel Limited 21,000.00 35,358.34 Signé 2020-09-28 2020-09-17 2020-10-03 2021-01-11 2020-10-24 2021-02-23 2020-11-28 2021-03-01 2021-05-27 nt ementales et Sociales pour le compte de l'UCP du PGRC DU NE-PGRC-DU-209114-CS-IND V / Recrutement d’un Spécial iste en Sauvegardes environ Comp. 3: Project Manageme nementales en appui au Proj IDA / 64130 A posteriori Individuel Limited 35,000.00 23,142.03 Signé 2020-12-16 2021-02-05 2020-12-21 2021-02-10 2021-01-11 2021-03-03 2021-02-15 2021-03-10 2021-08-14 nt et de Gestion des Risques de Catastrophes et de Développ ement Urbain (PGRC-DU) pou r la mise en œuvre du MRI20 20 NE-PGRC-DU-209116-CS-IND V / Recrutement d’un Spécial iste en Sauvegarde sociale e Comp. 3: Project Manageme n appui au Projet de Gestion IDA / 64130 A posteriori Individuel Limited 35,000.00 21,169.70 Signé 2020-12-16 2021-02-05 2020-12-21 2021-02-09 2021-01-11 2021-02-15 2021-02-15 2021-03-10 2021-08-14 nt des Risques de Catastrophes et de Développement Urbain (PGRC-DU) pour la mise en œ uvre du MRI2020 NE-PGRC-DU-209118-CS-IND V / RECRUTEMENT D'UN CON Comp. 3: Project Manageme SULTANT POUR L'ÉVALUATIO IDA / 64130 A posteriori Individuel Limited 5,500.00 0.00 Annulé 2020-12-15 2020-12-20 2021-01-10 2021-02-14 2021-08-13 nt N DES DOMMAGES, PERTES E T BESOINS POST INONDATIO NS AU NIGER EN 2020 NE-PGRC-DU-221031-CS-IND V / RECRUTEMENT D’UN CON SULTANT NTIC EXPERT EN TR ANSFORMATION NUMÉRIQUE Comp. 3: Project Manageme IDA / 64130 A posteriori Individuel Limited 20,000.00 17,074.36 Signé 2021-02-26 2021-03-08 2021-03-03 2021-03-08 2021-03-24 2021-04-16 2021-04-28 2021-05-10 2021-10-25 DES TERRITOIRES AUPRÈS D nt E L’AGENCE NATIONALE POU R LA SOCIÉTÉ DE L’INFORMA TION (ANSI) DANS LE CADRE DE LA COMPOSANTE NTIC NE-PGRC-DU-241469-CS-IND V / Recrutement d'un Spécial Comp. 3: Project Manageme En cours d'exécut IDA / 64130 A posteriori Individuel Limited 35,000.00 0.00 2021-06-30 2021-07-19 2021-07-05 2021-07-16 2021-07-26 2021-08-30 2022-02-26 iste en infrastructure pour le nt ion compte de l'UCP NE-PGRC-DU-243797-CS-IND V / Recrutement d’un consult Comp. 1: Flood Risk Manage ant charge de l’Elaboration d IDA / 64130 A posteriori Individuel Limited 15,000.00 18,658.15 Signé 2021-07-19 2021-07-28 2021-07-24 2021-08-19 2021-08-14 2021-09-13 2021-09-18 2021-09-30 2022-03-17 ment Investments u cadre de politique de Réins tallation des populations (CP RP) du PIDUREM Page 12 NE-PGRC-DU-243801-CS-IND V / Recrutement d’un consult Comp. 1: Flood Risk Manage ant chargé de l’Elaboration d IDA / 64130 A posteriori Individuel Limited 13,000.00 29,443.12 Achevé 2021-07-19 2021-07-28 2021-07-24 2021-08-19 2021-08-14 2021-09-13 2021-09-18 2021-09-30 2022-03-17 2022-02-15 ment Investments u Cadre de Gestion Environn ementale et Sociale (CGES) d u PIDUREM NE-PGRC-DU-243806-CS-IND V / Recrutement d’un consult Comp. 1: Flood Risk Manage ant chargé de l’Elaboration d IDA / 64130 A posteriori Individuel Limited 15,000.00 0.00 Annulé 2021-07-19 2021-07-24 2021-08-14 2021-09-18 2022-03-17 ment Investments u Plan de Gestion des Pestes et Pesticides (PGPP) du PIDU REM NE-PGRC-DU-243816-CS-IND V / Recrutement d’un consult ant chargé de l’Elaboration d Comp. 1: Flood Risk Manage IDA / 64130 A posteriori Individuel Limited 20,000.00 14,189.40 Achevé 2021-07-19 2021-07-28 2021-07-24 2021-08-19 2021-08-14 2021-09-14 2021-09-18 2021-09-30 2022-03-17 2022-02-15 u Plan de Gestion de la Main ment Investments d’œuvre (PGMO) et d’un Plan de Mobilisation des Parties Pr enantes (PMPP) du PIDUREM NE-PGRC-DU-243823-CS-IND V / Recrutement d’un consult Comp. 1: Flood Risk Manage En cours d'exécut ant chargé de l’Elaboration d IDA / 64130 A posteriori Individuel Limited 12,000.00 0.00 2021-07-19 2021-07-28 2021-07-24 2021-08-19 2021-08-14 2021-09-18 2022-03-17 ment Investments ion u Plan de Gestion de la Sécur ité (PGS) du PIDUREM NE-PGRC-DU-247082-CS-IND V / Recrutement d'un consult ant pour l’évaluation des outi Comp. 1: Flood Risk Manage En cours d'exame ls de planification et investiss IDA / 64130 A posteriori Individuel Limited 7,000.00 0.00 2021-08-23 2021-10-06 2021-08-28 2021-09-18 2021-10-23 2022-04-21 ment Investments n ements prioritaires des collec tivités dans le cadre de la pr éparation du PIDUREM (Zone 1: Maradi, Zinder et Diffa) NE-PGRC-DU-248182-CS-IND V / Recrutement d'un consult ant pour l'évaluation des outi Comp. 1: Flood Risk Manage En cours d'exame ls de planification et investiss IDA / 64130 A posteriori Individuel Limited 7,000.00 0.00 2021-08-23 2021-10-06 2021-08-28 2021-09-18 2021-10-23 2022-04-21 ment Investments n ements prioritaires des collec tivités dans le cadre de la pr éparation du PIDUREM (Zone 2 : Agadez, Tahoua et Dosso) NE-PGRC-DU-248183-CS-IND V / Recrutement d'un consult ant pour l'évaluation des outi ls de planification et investiss Comp. 1: Flood Risk Manage En cours d'exécut ements prioritaires des collec IDA / 64130 A posteriori Individuel Limited 5,000.00 0.00 2021-08-23 2021-10-06 2021-08-28 2021-09-18 2021-10-23 2022-04-21 ment Investments ion tivités dans le cadre de la pr éparation du PIDUREMRecrut ement d'un consultant pour l' évaluation des outils de plani fication et investisseme NE-PGRC-DU-248185-CS-IND V / Selection d'un consultant pour l'evaluation de la Gestio Comp. 1: Flood Risk Manage En cours d'exécut n des Collectivités Territorial IDA / 64130 A posteriori Individuel Limited 7,000.00 0.00 2021-08-23 2021-10-06 2021-08-28 2021-09-18 2021-10-23 2022-04-21 ment Investments ion es (CT), pour servir de situati on de référence pour le PIDU REM . (Zone 2: Agadez, Taho ua et Dosso) NE-PGRC-DU-248187-CS-IND V / Recrutement d'un consult ant pour l'évaluation des syst Comp. 1: Flood Risk Manage En cours d'exame IDA / 64130 A posteriori Individuel Limited 5,000.00 0.00 2021-08-30 2021-10-05 2021-09-04 2021-09-25 2021-10-30 2022-04-28 èmes de gestion des collectiv ment Investments n ités dans le cadre de la Prépa ration du PIDUREM (Zone 3 : Niamey et Tillabery) NE-PGRC-DU-247080-CS-IND V / Recrutement d'un consult ant pour l’évaluation des syst Comp. 1: Flood Risk Manage En cours d'exame IDA / 64130 A posteriori Individuel Limited 7,000.00 0.00 2021-08-30 2021-10-06 2021-09-04 2021-09-25 2021-10-30 2022-04-28 èmes de gestion des collectiv ment Investments n ités dans le cadre de la Prépa ration du PIDUREM (Zone 1: Maradi, Zinder et Diffa) NE-PGRC-DU-250488-CS-CD Sélection de cons S / Poursuite du suivi contrôl Comp. 1: Flood Risk Manage En cours d'exécut IDA / 64130 A posteriori ultants par entent Direct 30,000.00 0.00 2021-09-06 2021-10-26 2021-09-16 2021-11-20 2022-05-19 e des travaux de réalisation ment Investments ion e directe des collecteurs à Niamey NE-PGRC-DU-259451-CS-IND V / Sélection d’un consultant Comp. 2: Capacity Building f pour l’élaboration de la Strat IDA / 64130 or Urban Development and A posteriori Individuel Limited 20,000.00 0.00 Annulé 2021-10-26 2021-10-31 2021-11-21 2021-12-26 2022-06-24 égie de la passation de marc Disaster Risk Management hés pour le développement d urable PPSD du PIDUREM NE-PGRC-DU-260800-CS-IND Comp. 2: Capacity Building f V / Recrutement d'un Consult IDA / 64130 or Urban Development and A posteriori Individuel Direct 20,000.00 27,159.30 Achevé 2021-11-05 2021-11-12 2021-11-15 2021-11-15 2021-12-06 2021-11-19 2022-01-10 2021-11-30 2022-07-09 2022-03-23 ant Individuel qui sera charg Disaster Risk Management é de l'Elaboration de la PPSD du PIDUREM NE-PGRC-DU-271965-CS-IND V / Sélection d'un Consultant chargé de l'Elaboration des T Comp. 1: Flood Risk Manage IDA / 64130 A posteriori Individuel Limited 8,500.00 13,971.54 Signé 2022-01-07 2022-01-14 2022-01-12 2022-01-17 2022-02-02 2022-01-24 2022-03-09 2022-01-27 2022-09-05 ermes de Références (TDRs) ment Investments pour la réalisation des Etude s prioritaires dans le cadre d u PIDUREM NE-PGRC-DU-305324-CS-IND V / Sélection d'un consultant pour l’appui à l’élaboration d Comp. 3: Project Manageme En attente d'exéc u rapport d’achèvement (ICR IDA / 64130 A posteriori Individuel Limited 35,000.00 0.00 2022-07-25 2022-07-30 2022-08-20 2022-09-24 2023-03-23 nt ution ) du Projet de Gestion des Ris ques de Catastrophes et de Développement Urbain (PGR C-DU) Page 13