PROCUREMENT PLAN (Updated 27 October 2021) Project Implementation Agency : General Education Improvement Project (GEIP) Date of the Procurement Plan : 27 October 2021 Period Covered by this Procurement Plan (18 months): September 2021 to March 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016; Revised November 2017, August 2018 and November 2020) (“Procurement Regulations for IPF Borrower – 4th Edition”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Government of the Kingdom of Cambodia’s Updated Standard Operating Procedures and Procurement Manual for All Externally Financed Projects/Programs, promulgated through the Sub‐decree 181 ANK/BK dated December 2, 2019, which is issued pursuant to Article 3 of the Government of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be open to eligible firms from any country; ii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights as per attached confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including format; iii. Each Project shall put in place an effective complaint review system that includes review by the implementing agency and subsequent review by another party not involved in the in the procurement process, if not satisfied with the review of the implementing agency When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Procurement Method and Prior Review Thresholds Procurement at Open (USD) Prior Review National Level Threshold International National RFQ (*) Moderate Risk Goods At or above below 600,000.00 6 Below100,00 4,000,000.00 600,000 0.00 Works At or above Below Below 15,000,000.00 2,000,000.00 2,000,000.00 200,000.00 Consulting firm At or above Below 200,000.00 N//A 2,000,000.00 200,000.00 Individual Consultant N/A 400,000.00 (*) if the estimated cost over USD 25,000, SPN is required. Procurement at Sub-National Levels (Community-based Procurement) Contract Value Procurement Prior Review Thresholds Comments Methods Threshold ($’000) (US$) All Procurement Packages for Community- The detail Community-Based Procurement are Based procedure will be N/A subject to Post Review to be Procurement provided in POM. conducted by the External Auditor I. Goods and Works and non-consulting services. 1.1 Procurement (Goods) Packages with Methods and Time Schedule 1 2 3 4 5 6 7 8 9 Revie Domesti w Expected Procurem c Ref. Estimated Prequalificat by Bidding Doc Commen Contract (Description) ent Prefere No. Cost ion (yes/no) Bank Launch ts Method nce (Prior Date (yes/no) / Post) Open 1 Construction Equipment (D-GPS) and Safety Tool 34,500.00 No No Post 17 Jan 2022 National IT Equipment for setting up E-Learning Classroom for Schools -ECED (Early Childhood Education) Open 1 March Estimated 213 units x $1,500 = $ 319,500.00 2,449,500.0 2 Internatio No No Post 2022 cost to be -PED (Primary Education) 1000 units x $ 1,500 = $ 0 revised nal 1,500,000.00 -GSED ( Secondary Education) 420 units x $ 1,500 = $ 630,000 Laptop to store and manage student data Open 1 March (secondary) GSED (420 units x $2,200=924,000), 1,074,000.0 3 Internatio No No Post 2022 Ed-Tech for Math Computers in 5 pilot schools GSED 0 nal (100 units x$ 1,500=150,000) Open 01 Feb Estimated ICT equipment for schools, DOE (District Office 1,812,300.0 4 Internatio No No Post 2022 cost to be of Education ) and POE (Provincial Office of 0 nal revised Education) -Computers Laptop for POE (ECE) 1 per POE – (25 units x$ 2,100=$ 52,500) -Computers Laptop for POE (PED)-1 per POE – (25 units x $ 2,100=$ 52,500) -Computers Laptop for POE ( GSED) 1 per POE – (25 units x $ 2,100=$ 52,500) -Computers for DoE (one per DOE) GSED- (203 units x $ 2,100=$ 426,300) -LCD for secondary schools GSED – (1,533 units x $400=613,200) -Printers for secondary schools GSED – (1,533 units x$ 400=613,200) Office Equipment for TUP (Teacher Upgrading Open 04 April 5 Program) /LUP 432,930.00 No No Post National 2022 ( Leadership Upgrading Program) Special Education Department -Printing machines for braille scripts (Braille Printer): 5 units x $60,000 = $300,000.00 -3D Braille Printers (EZ-FORM BRAILON DUPLICATOR): 5 units x $ 7,000 = $35,000.00 04 April Open 6 -Music equipment: 5 units x $7,000 = $35,000 467,500.00 No No Post 2022 National -Desktop Computers to connect to Printers : 5 units x $2,000 = $ 10,000.00 -Desktop Computers for ICT lessons for students: 5 units x 5 schools x $1,500 = $37,500 -Equipment for checking hearing: 5 units x $10,000 = $50,000.00 Office Equipment -Computer Laptop for M&E and EQAD (Education Quality Assurance Department): 10 units x $2,200 = Open 17 Jan 2022 7 $ 22,000.00. 350,300.00 No No Post National -Equipment for Central (PU: $ 23000,FU:$ 23000, ADMIN: $ 23000, ECED: $ 37000, PED:$ 50000, SHD: $ 26700, TUP: $ 84000, DoC:$ 33600, SED:$ 28000) Occluder (Eye Examination) and Tuning Fork (Ear Open 04 April 8 175,760.00 No No Post Examination) National 2022 Vehicles Pick-ups Open 9 (SGED 2, PED2, DOC2, ECED1,FU1, PU1, PMT1, 540,000.00 No No Post 1-Nov-21 National TUP1,DIT1) Furniture for School Buildings Phase 1 and 10 Open 1-Jan- 22 Furniture for Teacher's Houses Phase 1 819,000.00 No No Post National Furniture for School Buildings Phase 2 and Furniture 11 Open 1-Dec- 22 for Teacher's Houses Phase 2 795,000.00 No No Post National 12 Furniture for PSTTC and Furniture for Kandal RTTC Open 1-Dec- 22 160,000.00 No No Post National Open Science materials (for 3 rooms of the secondary) 13 960,000.00 Internatio No No Post 2-Mar-22 GSED nal Total Amount for Goods 10,070,79 0.00 1.2 Procurement (Works) Packages with Methods and Time Schedule 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procureme Prequalificat Domestic Review Expecte Comme No. (Description) Package Cost nt ion (yes/no) Preferen by Bank d nts s Method ce (Prior / Bid- (yes/no) Post) Openin g Date Community Construction for Existing Targeted Multiple Based 1-Jan- 1 Schools package 2,871,000.00 procuremen No No Post 22 Phase 1(33 sites x $ 87,000) s t Construction for New Location School Multipl Community (Targeted Communes)Phase 1(15 sites x e Based 1-Jan- 2 1,305,000.00 No No Post $ 87,000) packag procuremen 22 es t Construction for Teacher's House (Rural Multipl Community 1-Jan- 3 630,000.00 No No Post and Remote Schools)Phase 1(15 sites x e Based 22 $ 42,000) packag procuremen es t Multipl Community Renovation Schools Building and e Based 1-Jan- 4 Installation Laboratories Phase 1 (110 3,300,000.00 No No Post sites x $30,000) packag procuremen 22 es t Multipl Community Laboratories Installation Phase 1 (40 e Based 1-Jan- 5 800,000.00 No No Post sites x $20,000) packag procuremen 22 es t Renovation the labs to check hearing Multipl Community aids (Support students with e Based 1-Jan- 6 16,000.00 No No Post disabilities) (2 sites x $ packag procuremen 22 8,000) es t Construction PSTTC (Preschool Teacher 1-Mar- 7 Training Center):(1 site x 720,000) 1 720,000.00 NCB No No Post 22 Construction Kandal RTTC (Regional 1-Mar- 8 Teacher TrainingCenter):(1 site x 1 720,000.00 NCB No No Post 22 720,000) Construction special schools for Multipl Community students with disability in 2Provinces e Based 1-Mar- 9 (Battambang 755,000.00 No No Post packag procuremen 22 & Kandal) es t Multipl Community Construction for Existing Targeted e Based 1-Dec- 10 Schools Phase 2(45 sites x $ 3,915,000.00 No No Post 87,000) packag procuremen 22 es t Multipl Community Construction for New Location School e Based 1-Dec- 11 (Targeted Communes)Phase 2 (15 sites 1,305,000.00 No No Post x $ 87,000) packag procuremen 22 es t Multipl Community Construction for Teacher's House (Rural e Based 1-Dec- 12 and Remote Schools)Phase 2(15 sites x 630,000.00 No No Post $ 42,000) packag procuremen 22 es t Renovation Schools Building and Multipl Community Installation Laboratories Phase 2(110 e 3,300,000.00 Based 1-Dec- 13 sites x $ 30,000) No No Post packag procuremen 22 es t Installation Laboratories Phase 2 Multipl Community (40 sites x $20,000.00) e 800,000.00 Based 1-Dec- 14 No No Post packag procuremen 22 es t Construction renovation works for Multipl school building in Kandal Province. e 1-Apr- 15 (105,000 *01buildings) 105,000.00 Shopping No No Post packag 22 es Multipl Construction renovation works for e 1-Apr- 16 school building in Kandal Province. 105,000.00 Shopping No No Post (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 17 school building in Kandal Province. 105,000.00 Shopping No No Post (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 18 school building in Kandal Province. 105,000.00 Shopping No No Post (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 19 school building in Kampong Speu 105,000.00 Shopping No No Post Province. (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 20 school building in Kampong Speu 105,000.00 Shopping No No Post Province. (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 21 school building in Kampong Speu 105,000.00 Shopping No No Post Province. (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 22 school building in Kampong Speu 105,000.00 Shopping No No Post Province. (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 23 school building in Prey Veng province. 105,000.00 Shopping No No Post (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 24 school building in Prey Veng province. 105,000.00 Shopping No No Post (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 25 school building in Prey Veng province. 105,000.00 Shopping No No Post (105,000 *01buildings) packag 22 es Multipl Construction renovation works for e 1-Apr- 26 school building in Prey Veng province. 105,000.00 Shopping No No Post (105,000 *01buildings) packag 22 es 22,327,000. Total Amount for Civil Works 00 II. Selection of Consultants 1 2 3 4 5 6 7 Selection Review Expected Ref. Estimated Method by Bank Proposals Commen No. Description of Assignment Cost (Firm of (Prior / Submission ts Individual) Post) Date 1 Architect and Civil Engineer to provide new design and concepts of Library, E- Learning, PSTTC, RTTC and Special 30,000.00 IC Post 1-Nov-21 School (2 Person x 2,500 x 6 Month) 2 National Third Party Consultant (1 Person x 2000 x 36) 72,000.00 IC Post 1-Nov-21 3 Site Engineers 1,350,000.00 IC Post 1-Nov-21 (25 Person x 1,500 x 36) 4 Consulting Firm for Water Well Testing (100 school x 54) 5,400.00 DC Post 1-Jul-22 5 National Procurement Consultants ( 2 x 60 x 2,000) 240,000.00 IC Post 1-Nov-21 6 IT Consultant Support Procurement Unit 90,000.00 IC Post 1-Nov-21 (1 x 60 x 1,500) 7 Project Admin Assistant for PU (2 x 60 x 900) 108,000.00 IC Post 1-Nov-21 8 National Financial Management Consultant (DoF) 150,000.00 IC Post 1-Nov-21 (1 x 60 x 2,500) 9 National Project Coordinator (1 x 60 x 5,000) 300,000.00 IC Post 1-Nov-21 10 IT Analyst for School Data (1 x 24 x 2,500) 60,000.00 IC Post 1-Nov-21 11 TA of Safeguards 36,000.00 IC Post 1-Nov-21 (1 x 12 x 3,000) 12 Project National Administration Consultant for PMT(1 x 60 60,000.00 IC Post 1-Nov-21 x 1,000) 13 Consulting Firm for Software license development design 750,000.00 QBS Post 1-Nov-21 EdTech for Grade 7 mathematics 14 Consulting firm to verify the achievement of PBCs 450,000.00 QBS Post 1-Nov-21 (90k per year for five years) 15 External Auditor Firm (Procured by MEF) 100,000.00 Total Amount for Services 3,701,4.00 Grand Total Goods + Civil Works + Service of Cost 36,199,190.0 Estimate for Advance Procurement 0 PROCUREMENT Cambodia : Cambodia General Education Improvement Project PLAN General Information Country: Cambodia 2022-05-09 Bank’s Approval Date of the Original Procurement Plan: 2022-10-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174335 GPN Date: 2022-08-16 Project Name: Cambodia General Education Improvement Project Loan / Credit No: IDA / 70240 Ministry of Education Youth and Sport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-GEIP-NS-G-001 / Con Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl struction Equipment and Saf IDA / 70240 Sector Development and Pro Post Open - National 34,500.00 0.00 2022-05-18 2022-07-16 2022-09-14 tions nvelope ementation ety Tool ject Management MOEYS-GEIP-ICB-G-003 / ICT equipment for schools, DOE ( Component 1: Improving Stu Open - Internationa Single Stage - One E Pending Impl IDA / 70240 Post Request for Bids 1,810,200.00 0.00 2022-05-23 2022-06-07 2022-07-22 2022-11-19 2022-12-30 2023-06-28 District Office of Education ) dent Learning Outcomes l nvelope ementation and POE (Provincial Office of Education) MOEYS-GEIP-ICB-G-001 / IT E Component 1: Improving Stu Open - Internationa Single Stage - One E Pending Impl quipment for setting up E-Le IDA / 70240 Prior Request for Bids 2,449,500.00 0.00 2022-08-08 2022-08-23 2022-10-07 2023-02-04 2023-03-17 2023-09-13 dent Learning Outcomes l nvelope ementation arning Classroom for School s MOEYS-GEIP-ICB-G-002 / Lap Component 1: Improving Stu Open - Internationa Single Stage - One E Pending Impl top to store and manage stu IDA / 70240 Post Request for Bids 1,074,000.00 0.00 2022-06-26 2022-07-11 2022-08-25 2022-12-23 2023-02-02 2023-08-01 dent Learning Outcomes l nvelope ementation dent data (secondary) GSED MOEYS-GEIP-NCB-G-005 / 12 Component 2: Strengthening Double Cab Pick-Up Truck (S Single Stage - One E Pending Impl IDA / 70240 Sector Development and Pro Post Request for Bids Open - National 540,000.00 0.00 2022-06-13 2022-06-23 2022-07-23 2022-10-21 2022-12-01 2023-03-01 GED 2, PED2, DoC2, ECED1, nvelope ementation ject Management FU1, PU1, PMT1, TUP1, DIT1) MOEYS-GEIP-NCB-G-003 / Off Component 2: Strengthening ice Equipment for Central: M Single Stage - One E Pending Impl IDA / 70240 Sector Development and Pro Post Request for Bids Open - National 350,300.00 0.00 2022-05-08 2022-05-18 2022-06-17 2022-09-15 2022-10-26 2023-01-24 &E, EQAD, PU, FU, Admin, EC nvelope ementation ject Management ED, PED, SHD, TUP, DoC, GSE D MOEYS-GEIP-NCB-G-001 / Off Component 2: Strengthening ice Equipment for Teacher U Single Stage - One E Pending Impl IDA / 70240 Sector Development and Pro Post Request for Bids Open - National 432,930.00 0.00 2022-07-30 2022-08-09 2022-09-08 2022-12-07 2023-01-17 2023-04-17 pgrading Program/ Leadershi nvelope ementation ject Management p Upgrading Program MOEYS-GEIP-NCB-G-004 / Oc Component 1: Improving Stu Single Stage - One E cluder (Eye Examination) and IDA / 70240 Post Request for Bids Open - National 175,760.00 0.00 Canceled 2022-07-30 2022-08-09 2022-09-08 2022-12-07 2023-01-17 2023-04-17 dent Learning Outcomes nvelope Turning Fork (Ear Examinatio n) MOEYS-GEIP-NCB-G-002 / "S pecial Education Department -5 Printing machines for braill e scripts (Braille Printer), 3D Component 1: Improving Stu Single Stage - One E Pending Impl IDA / 70240 Post Request for Bids Open - National 467,500.00 0.00 2022-07-30 2022-08-09 2022-09-08 2022-12-07 2023-01-17 2023-04-17 Braille Printers (EZ-FORM BR dent Learning Outcomes nvelope ementation AILON DUPLICATOR): 5 units, Music equipment: 5 units, 10 desktops, 5 equipment for ch ecking hearing MOEYS-GEIP-ICB-G-004 / Sci Component 1: Improving Stu Open - Internationa Single Stage - One E Pending Impl ence materials (for 3 rooms o IDA / 70240 Post Request for Bids 960,000.00 0.00 2022-06-26 2022-07-11 2022-08-25 2022-12-23 2023-02-02 2023-08-01 dent Learning Outcomes l nvelope ementation f the secondary) GSED Component 2: Strengthening MOEYS-GEIP-NS-G-002 / Tur Request for Quota Single Stage - One E Pending Impl IDA / 70240 Sector Development and Pro Post Open - National 80,000.00 0.00 2022-10-12 2022-12-10 2023-04-09 ning Fork (Ear Examination) tions nvelope ementation ject Management MOEYS-GEIP-NS-G-003 / Acc Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl ounting Software and Server IDA / 70240 Sector Development and Pro Post Open - National 10,000.00 0.00 2022-10-20 2022-12-18 2023-02-16 tions nvelope ementation Maintenance ject Management NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-GEIP-QBS-01 / Consu lting Firm for Software licens Component 1: Improving Stu Quality Based Sel Open - Internationa Pending Impleme IDA / 70240 Post 750,000.00 0.00 2022-09-15 2022-10-15 2022-12-13 2022-12-27 2023-01-26 2023-02-09 2023-03-09 2024-03-08 e development design EdTec dent Learning Outcomes ection l ntation h for Grade 7 mathematics MOEYS-GEIP-QBS-02 / Consu Component 2: Strengthening Quality Based Sel Pending Impleme lting firm to verify the achiev IDA / 70240 Sector Development and Pro Post Open - National 450,000.00 0.00 2022-06-01 2022-06-15 2022-07-29 2022-08-26 2022-09-25 2022-10-25 2022-11-12 2026-11-30 ection ntation ement of PBCs ject Management INDIVIDUAL CONSULTANTS Page 1 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEYS-GEIP-IC-003 / Nation Component 2: Strengthening Individual Consult Under Implement al Third Party Consultant (1 P IDA / 70240 Sector Development and Pro Post Open 72,000.00 0.00 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 ant Selection ation erson x 2000 x 36) ject Management Component 2: Strengthening MOEYS-GEIP-IC-004 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-14 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 1 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-029 / Nation Individual Consult IDA / 70240 Sector Development and Pro Post Open 120,000.00 110,000.00 Signed 2022-06-06 2022-05-30 2022-08-04 2022-07-19 2022-08-25 2022-07-25 2022-09-22 2022-08-01 2026-11-30 al Procurement Consultant 1 ant Selection ject Management MOEYS-GEIP-IC-031 / IT Cons Component 2: Strengthening Individual Consult Under Implement ultant Support Procurement IDA / 70240 Sector Development and Pro Post Open 90,000.00 0.00 2022-06-06 2022-05-13 2022-08-04 2022-08-25 2022-09-22 2026-11-30 ant Selection ation Unit (1 consultant) ject Management Component 2: Strengthening MOEYS-GEIP-IC-032 / Project Individual Consult Under Implement IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 2022-06-06 2022-05-30 2022-08-04 2022-08-25 2022-09-22 2026-11-30 Admin Assistant 1 for PU ant Selection ation ject Management MOEYS-GEIP-IC-034 / Nation Component 2: Strengthening Individual Consult Under Implement al Financial Management Con IDA / 70240 Sector Development and Pro Post Open 150,000.00 0.00 2022-06-06 2022-05-13 2022-08-04 2022-08-25 2022-09-22 2026-11-30 ant Selection ation sultant (DoF) ject Management MOEYS-GEIP-IC-036 / IT Anal Component 2: Strengthening Individual Consult Under Implement yst for School Data (1 x 24 x IDA / 70240 Sector Development and Pro Post Open 60,000.00 0.00 2022-06-01 2022-08-05 2022-07-30 2022-08-20 2022-09-17 2024-09-06 ant Selection ation 2,500) ject Management MOEYS-GEIP-IC-037 / Nation Component 2: Strengthening Individual Consult Under Implement al Environmental and Social IDA / 70240 Sector Development and Pro Post Open 36,000.00 0.00 2022-06-01 2022-07-29 2022-07-30 2022-08-20 2022-09-17 2023-09-12 ant Selection ation Specialist/TA of Safeguards ject Management MOEYS-GEIP-IC-038 / Project Component 2: Strengthening Individual Consult Under Implement National Administration Cons IDA / 70240 Sector Development and Pro Post Open 60,000.00 0.00 2022-06-01 2022-07-29 2022-07-30 2022-08-20 2022-09-17 2026-11-30 ant Selection ation ultant for PMT ject Management Component 2: Strengthening MOEYS-GEIP-IC-005 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-14 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 2 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-006 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-14 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 3 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-007 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-14 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 4 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-008 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 5 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-009 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 6 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-010 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 7 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-011 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 8 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-012 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 9 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-013 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 10 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-014 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 11 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-015 / Site En Individual Consult IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 Canceled 2022-06-19 2022-07-29 2022-08-17 2022-09-07 2022-10-05 2025-09-19 gineer 12 ant Selection ject Management Component 2: Strengthening MOEYS-GEIP-IC-030 / Nation Individual Consult IDA / 70240 Sector Development and Pro Post Open 120,000.00 110,000.00 Signed 2022-06-06 2022-05-30 2022-08-04 2022-07-26 2022-08-25 2022-07-25 2022-09-22 2022-08-01 2026-11-30 al Procurement Consultant 2 ant Selection ject Management MOEYS-GEIP-IC-033 / Project Component 2: Strengthening Individual Consult Under Implement Administration Assistant 2 for IDA / 70240 Sector Development and Pro Post Open 54,000.00 0.00 2022-06-06 2022-05-30 2022-08-04 2022-08-25 2022-09-22 2026-11-30 ant Selection ation Project Procurement Unit ($ ject Management 900 x 60 m) Component 2: Strengthening MOEYS-GEIP-IC-001 / Archite Individual Consult Pending Impleme IDA / 70240 Sector Development and Pro Post Open 15,000.00 0.00 2022-04-29 2022-06-27 2022-07-18 2022-08-15 2023-02-11 ct and Civil Engineer 1 ant Selection ntation ject Management Component 2: Strengthening MOEYS-GEIP-IC-002 / Archite Individual Consult Pending Impleme IDA / 70240 Sector Development and Pro Post Open 15,000.00 0.00 2022-04-29 2022-06-17 2022-07-08 2022-08-11 2023-02-07 ct and Civil Engineer 2 ant Selection ntation ject Management MOEYS-GEIP-DC-001 / Consu Component 2: Strengthening Pending Impleme lting Firm for Water Well Test IDA / 70240 Sector Development and Pro Post Direct Selection Direct 5,400.00 0.00 2022-09-28 2022-10-08 2023-01-01 2023-04-01 ntation ing ject Management MOEYS-GEIP-IC-035 / Senior Component 2: Strengthening Individual Consult National Project Management IDA / 70240 Sector Development and Pro Post Open 300,000.00 0.00 Canceled 2022-07-04 2022-05-30 2022-09-01 2022-09-22 2022-10-20 2026-11-30 ant Selection and Technical Advisor ject Management MOEYS-GEIP-IC-035/1 / Natio Component 2: Strengthening Individual Consult Under Implement nal Consultant for SCS, TUP/L IDA / 70240 Sector Development and Pro Post Open - National 15,000.00 0.00 2022-08-26 2022-09-08 2022-10-24 2022-11-14 2022-12-12 2026-11-30 ant Selection ation UP ject Management Page 2 MOEYS-GEIP-IC-035/2 / Natio Component 2: Strengthening Individual Consult Under Implement nal Project Management Con IDA / 70240 Sector Development and Pro Post Open - National 150,000.00 0.00 2022-08-26 2022-09-02 2022-10-24 2022-11-07 2022-12-05 2026-11-23 ant Selection ation sultant ject Management Component 2: Strengthening MOEYS-GEIP-IC-004-015 / 12 Individual Consult Under Implement IDA / 70240 Sector Development and Pro Prior Open - National 648,000.00 0.00 2022-10-03 2022-09-15 2022-12-01 2022-12-22 2023-01-19 2026-01-03 Site Engineers Phase 1 ant Selection ation ject Management Page 3