REPUBLIC OF MOZAMBIQUE MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT Agriculture and Natural Resources Landscape Management Project (ANRLMP) Project No: P149620 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 2017] 2. Date of General Procurement Notice: July 26, 2016. 3. Period covered by this procurement plan: April 2017 to October 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ All 1,500,000 2. NCB (Goods) and (Non- Above US$ All Consultant Services) 1,500,000 3. ICB (Works) Above US$ All 5,000,000 4. NCB (Works) Above US$ All 5,000,000 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 1 Date: April 19, 2017 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As per paragraphs 3.17 of the Guidelines and Project Procurement Manual. 1 2 3 4 5 6 7 Estimated Domesti Review Ref Cost c Packa by Bank Comme . Description US$ Prefere ges (Prior / nts No. thousand nce Post) s (yes/no) Summary of the 1 1,791,00 5 No Post NCB (Works) Summary of NCB 2 1,822,60 7 No Post (Goods) Summary of the NCB (Non- 3 775,00 1 No Prior Consulting Services) Summary of the 4 249,6 6 No Post Shopping (Goods) Summary of the Shopping (Non- 5 20,00 1 No Post Consulting Services) 4. Reference to (if any) Project Operational/Procurement Manual: Items to be financed under this Credit/Grants will be procured in line with rules in the Operational Manual, Credit/Grants Agreement and Project Procurement Manual. 5. Any Other Special Procurement Arrangements: Not Applicable. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2 Date: April 19, 2017 Selection Method Prior Review Comment Threshold 1. Competitive Methods ≥ 200,000 (Firms) 2. Individual ≥ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Description Estimated Review Ref. No. of Cost Packag by Bank Comment Assignment US$ es (Prior / s thousands Post) Summary of number of contracts that 17.800,00 6 Prior 1 will be let under QCBS 2 Individuals 495.00 6 Prior 3 Individuals 2.210,8 32 Post 3 Date: April 19, 2017 PROCUREMENT Mozambique : Moz Agriculture and Natural Resources Landscape Management Project PLAN General Information Country: Mozambique 2016-07-13 Bank’s Approval Date of the Original Procurement Plan: 2022-09-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149620 GPN Date: 2016-07-28 Project Name: Moz Agriculture and Natural Resources Landscape Management Project Loan / Credit No: IDA / 58550, IDA / Q9900, IDA / D1190, IDA / D5020 MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT - International Funds Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Securing Land Tenure Rights 64/W/ANRLMP/17 / Rehabilit Single Stage - One E 2018-04-2 IDA / 58550 and Increasing Natural Reso Post Request for Bids Open - National 366,000.00 372,560.56 Signed 2017-06-30 2017-07-17 2017-07-07 2017-08-18 2017-09-18 2017-10-12 2017-10-23 2017-11-16 ation of the data center nvelope 3 urces Resilience 01/ARLMP/W/16 / Rural Road Agriculture and Forest-Base Single Stage - One E 2018-04-0 IDA / 58550 Post Request for Bids Open - National 270,000.00 213,326.94 Signed 2017-06-12 2017-07-10 2017-06-19 2017-07-31 2017-08-08 2017-08-30 2017-08-23 2017-10-04 2017-09-20 s Spot Improvements d Value Chain Development nvelope 2 02/W/ARLNMP/16 / Rural Roa Agriculture and Forest-Base Single Stage - One E 2018-04-0 IDA / 58550 Post Request for Bids Open - National 300,000.00 205,391.14 Signed 2017-06-15 2017-07-10 2017-06-21 2017-08-02 2017-08-08 2017-09-01 2017-08-25 2017-10-06 2017-09-26 ds Spot Improvement d Value Chain Development nvelope 4 79/W/ANRLMP/17 / Construct Agriculture and Forest-Base Request for Quota Single Stage - One E 2018-12-0 IDA / D1190 Post Open - National 70,000.00 0.00 Canceled 2018-04-09 2018-06-06 ions of PACES Warehouses d Value Chain Development tions nvelope 3 153/W/ANRLMP/19 / Rural R Agriculture and Forest-Base Single Stage - One E 2020-04-1 oads Spot Improvement - Na IDA / 58550 Post Request for Bids Open - National 600,000.00 285,080.85 Signed 2019-05-01 2019-04-01 2019-05-06 2019-06-17 2019-05-23 2019-07-17 2019-09-20 2019-08-21 2019-11-28 d Value Chain Development nvelope 7 mpula Province 151/W/ANRLMP/19 / Rural R Agriculture and Forest-Base Single Stage - One E 2020-04-1 oads Spot Improvement - Za IDA / 58550 Post Request for Bids Open - National 900,000.00 620,429.77 Signed 2019-05-01 2019-04-25 2019-05-06 2019-06-17 2019-05-29 2019-07-17 2019-05-05 2019-08-21 2019-11-28 d Value Chain Development nvelope 7 mbezia Province 156/W/ANRLMP/19 / Rehabili Agriculture and Forest-Base Single Stage - One E 2020-12-2 tation of existing Irrigation Sc IDA / D1190 Post Request for Bids Open - National 500,000.00 346,261.93 Signed 2019-09-02 2020-01-19 2019-09-09 2019-10-21 2020-03-27 2019-11-20 2019-07-31 2019-12-25 2019-12-31 d Value Chain Development nvelope 4 hemes - Nampula Province 157/W/ANRLMP/19 / Rehabili Agriculture and Forest-Base Single Stage - One E 2020-06-2 tation of existing Irrigation Sc IDA / D1190 Post Request for Bids Open - National 500,000.00 324,114.04 Signed 2019-09-02 2019-04-25 2019-09-09 2019-10-21 2019-05-23 2019-11-20 2019-09-20 2019-12-25 2019-12-31 d Value Chain Development nvelope 2 hemes - Zambezia Province Securing Land Tenure Rights 164/W/ANRLMP/20 / Rehabili Request for Quota Single Stage - One E Pending Imp 2021-06-1 IDA / D5020 and Increasing Natural Reso Post Limited 60,000.00 0.00 2020-10-19 2020-12-14 tation of SPGC in Nampula tions nvelope lementation 2 urces Resilience 165/W/ANRLMP/2020 / Reha Securing Land Tenure Rights Single Stage - One E Under Imple 2021-08-0 bilitation of SPGC in Zambézi IDA / D5020 and Increasing Natural Reso Post Request for Bids Open - National 500,000.00 0.00 2020-10-15 2021-01-03 2020-10-20 2020-12-01 2021-02-11 2020-12-31 2021-02-04 nvelope mentation 3 a urces Resilience 183/W/ANRLMP/2020 / Exec Securing Land Tenure Rights ution of Emergency Work for Under Imple 2021-08-1 IDA / D5020 and Increasing Natural Reso Post Direct Selection Direct 45,000.00 0.00 2021-01-07 2021-01-04 2021-01-12 2021-01-04 2021-02-16 the Rehabilitation of the Roof mentation 5 urces Resilience ing of the SPGC Building in Z ambézia National Procure 180/W/ANRLMP/2021 / Reha ment Document - Agriculture and Forest-Base Single Stage - One E Under Imple 2022-06-1 bilitation of Rural Roads in Za IDA / 58550 Post Request for Bids Open - National 1 Envelope proce 900,000.00 0.00 2021-08-22 2022-02-02 2021-08-27 2021-10-08 2021-11-07 2021-12-12 d Value Chain Development nvelope mentation 0 mbézia Province ss (Non Bank-SPD ) National Procure 181/W/ANRLMP/2021 / Reha ment Document - Agriculture and Forest-Base Single Stage - One E Under Imple 2022-05-1 bilitation of Rural Roads in N IDA / 58550 Post Request for Bids Open - National 1 Envelope proce 900,000.00 0.00 2021-07-29 2022-02-02 2021-08-03 2021-09-14 2021-10-14 2021-11-18 d Value Chain Development nvelope mentation 7 ampula Province ss (Non Bank-SPD ) National Procure 182/W/ANRLMP/2021 / Reha ment Document - Agriculture and Forest-Base Single Stage - One E Under Imple 2022-06-0 bilitation of Rural Roads in M IDA / 58550 Post Request for Bids Open - National 1 Envelope proce 500,000.00 0.00 2021-08-15 2022-02-02 2021-08-20 2021-10-01 2021-10-31 2021-12-05 d Value Chain Development nvelope mentation 3 anica Province ss (Non Bank-SPD ) 219/W/ANRLMP/RFQ/2022 / Request for Quota Road Spot improvement - Co Agriculture and Forest-Base Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-07-2 nstruction of bridge over the IDA / D5020 Post Limited 170,000.00 0.00 2022-11-30 2023-01-25 d Value Chain Development tions nvelope s (Emergency) SP lementation 4 Namitatare River (NC INTXOT D -Competitive XA - PURY (Km:31+100) ZAM BÉZIA PROVINCE GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Coordination and Ma Single Stage - One E 01/G/ANRLMP/16 / Vehicles IDA / Q9900 Post Request for Bids Open - National 200,000.00 255,031.59 Signed 2016-08-29 2016-08-29 2016-09-03 2016-10-15 2016-10-11 2016-11-14 2016-11-07 2017-03-20 2016-12-30 2017-09-16 nagement nvelope Securing Land Tenure Rights 10/G/ANRLMP/16 / Satelite pi Single Stage - One E IDA / 58550 and Increasing Natural Reso Prior Request for Bids Open - National 775,000.00 0.00 Canceled 2016-11-01 2016-11-07 2016-12-20 2017-01-19 2017-02-23 2017-08-22 cture aquisition nvelope urces Resilience 6/G/ARLNMP/16 / IT Equipam Project Coordination and Ma Single Stage - One E IDA / 58550 Post Request for Bids Open - National 219,600.00 133,711.91 Signed 2017-03-30 2017-04-04 2017-05-16 2017-10-27 2017-06-15 2017-11-13 2017-10-19 2017-11-30 2018-02-12 ent nagement nvelope 73/G/ANRLMP/17 / Aquisition Agriculture and Forest-Base Single Stage - One E for tractors and accessories f IDA / D1190 Post Request for Bids Open - National 1,107,000.00 952,461.70 Signed 2017-05-19 2017-05-23 2017-05-24 2017-07-05 2017-06-22 2017-08-04 2017-08-01 2017-09-08 2017-09-11 2018-03-07 d Value Chain Development nvelope or Small Emerging Commerci al Farmers 71/G/ANRLMP/17 / IT Equipa Project Coordination and Ma Request for Quota Single Stage - One E IDA / D1190 Post Limited 29,000.00 24,285.55 Signed 2017-06-08 2017-06-12 2017-06-29 2017-06-22 2017-12-26 ment for Matching Grant Unit nagement tions nvelope Securing Land Tenure Rights 07/G/ARLNMP/16 / Motorcycl Single Stage - One E IDA / D1190 and Increasing Natural Reso Post Request for Bids Open - National 78,000.00 51,789.28 Signed 2017-10-02 2017-08-16 2017-10-09 2017-11-21 2017-10-27 2017-12-21 2017-11-17 2018-01-25 2017-11-30 2018-07-24 es nvelope urces Resilience Page 1 86/G/ANRLMP/17 / Motorcycl Agriculture and Forest-Base Request for Quota Single Stage - One E e for production officer and IDA / D1190 Post Open - National 75,000.00 79,226.22 Signed 2017-11-27 2018-01-22 2017-10-23 2018-07-21 d Value Chain Development tions nvelope market liaison/Zambezia Pro vince 85/G/ANRLMP/17 / Acquisitio Agriculture and Forest-Base Request for Quota Single Stage - One E IDA / 58550 Post Open - National 75,000.00 67,384.96 Signed 2017-12-13 2018-02-07 2017-11-13 2018-08-06 n of combine harvester/tresh d Value Chain Development tions nvelope er 87/G/ANRLMP/17 / Acquisitio Agriculture and Forest-Base Request for Quota Single Stage - One E IDA / 58550 Post Open - National 75,000.00 32,256.77 Signed 2017-12-20 2018-02-14 2017-11-03 2018-08-13 n Irrigation kits d Value Chain Development tions nvelope 72/G/ANRLMP/17 / IT Equipa Project Coordination and Ma Request for Quota Single Stage - One E ment for Agriculture Hidrauli IDA / D1190 Post Limited 52,500.00 87,160.96 Signed 2018-03-21 2018-05-09 2018-05-16 2018-07-09 2018-11-12 nagement tions nvelope c/Irrigation team Project Coordination and Ma Single Stage - One E 08/ARLNMP/G/16 / Vehicles IDA / 58550 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2017-10-31 2017-11-07 2017-12-19 2018-01-18 2018-05-24 2018-11-20 nagement nvelope 94/G/ANRLMP/17 / Office Fur Agriculture and Forest-Base Request for Quota Single Stage - One E IDA / D1190 Post Limited 11,000.00 28,910.86 Signed 2018-02-11 2018-04-13 2018-04-19 2018-05-25 2018-10-16 niture for new staff for PIU na d Value Chain Development tions nvelope mpula 93/G/ANRLMP/17 / Acquisitio Agriculture and Forest-Base Request for Quota Single Stage - One E IDA / D1190 Post Limited 29,000.00 21,506.59 Signed 2018-02-12 2018-05-09 2018-04-09 2018-06-22 2018-10-06 n IT Equipment d Value Chain Development tions nvelope 95/G/ANRLMP/17 / Motorcycl Agriculture and Forest-Base Request for Quota Single Stage - One E e for Production officer and IDA / D1190 Post Open - National 75,000.00 77,990.19 Signed 2018-02-06 2018-04-04 2017-10-23 2018-10-01 d Value Chain Development tions nvelope market liaison - Nampula Pro vince 113/G/ANRLMP/18 / Acquisiti Agriculture and Forest-Base Request for Quota Single Stage - One E on of plants for forest restora IDA / D1190 Post Limited 75,000.00 20,186.61 Signed 2018-03-16 2018-02-27 2018-05-11 2018-02-28 2018-11-09 d Value Chain Development tions nvelope tion for Nampula Province 111/G/ANRLMP/18 / Acquisiti Agriculture and Forest-Base Request for Quota Single Stage - One E on of Plants for Forest Restor IDA / D1190 Post Limited 75,000.00 30,344.83 Signed 2018-01-30 2018-01-18 2018-03-27 2018-01-31 2018-09-24 d Value Chain Development tions nvelope ation at Zambezia Province 92/G/ANRLMP/17 / Vehicles f Agriculture and Forest-Base Single Stage - One E or PIU/Nampula and Zambezi IDA / D1190 Post Request for Bids Open - National 285,000.00 234,333.75 Signed 2018-03-15 2018-04-02 2018-03-26 2018-05-08 2018-05-02 2018-06-07 2018-04-25 2018-07-12 2018-06-06 2019-01-08 d Value Chain Development nvelope a Provinces 114/G/ANRLMP/18 / Aquisitio n of seedlings for restoration Agriculture and Forest-Base Single Stage - One E IDA / D1190 Post Request for Bids Limited 215,000.00 100,693.60 Signed 2018-07-02 2018-07-02 2018-07-18 2018-07-12 2018-09-06 2018-08-09 2018-10-16 2018-08-31 2018-11-20 2018-09-04 2019-11-20 of degraded areas in the Pro d Value Chain Development nvelope vinces of Nampula and Zamb ezia 128/G/ANRLM/18 / Printing o Project Coordination and Ma Request for Quota Single Stage - One E f the project Pogress report- IDA / D1190 Post Limited 33,500.00 28,255.62 Signed 2018-11-06 2018-11-08 2019-01-01 2018-11-29 2019-07-01 nagement tions nvelope First Production cycle report 91/G/ANRLMP/17 / Acquisitio Agriculture and Forest-Base Single Stage - One E n for Trucks for Emerging Co IDA / D1190 Post Request for Bids Open - National 1,345,000.00 0.00 Canceled 2018-10-31 2018-11-12 2018-12-31 2019-01-30 2019-03-06 2019-09-02 d Value Chain Development nvelope mmercial Farmers 89/G/ANRLMP/17 / Acquisitio Agriculture and Forest-Base Single Stage - One E n for tractor for Small Emergi IDA / D1190 Post Request for Bids Open - National 1,245,000.00 0.00 Canceled 2018-10-31 2018-11-08 2018-12-20 2019-01-21 2019-02-25 2019-08-26 d Value Chain Development nvelope ng Commercial Farmers 90/G/ANRLMP/17 / Acquisitio n of Agricultural implements Agriculture and Forest-Base Single Stage - One E IDA / D1190 Post Request for Bids Open - National 648,500.00 0.00 Canceled 2018-09-03 2018-09-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 and trailers for Small Emergi d Value Chain Development nvelope ng Commercial Farmers 05/G/ARLNMP/16 / IT Equipa Project Coordination and Ma Request for Quota Single Stage - One E IDA / D1190 Post Open - National 5,000.00 0.00 Canceled 2018-04-09 2018-06-04 2018-12-05 ment nagement tions nvelope 154-1/CER/NCS/ANRLMP/19 / Hiring Service Provider to ex Contingency Emergency Res UN Agencies (Dire IDA / D1190 Prior Direct 10,000,000.00 10,000,000.00 Signed 2019-05-03 2019-05-08 2019-06-12 2019-05-07 2019-12-09 ecute the Agricultural and Liv ponse ct) estock Recovery Plan post cy clone IDAI 166/G/ANRLMP/EMERG/20 / Securing Land Tenure Rights Acquisition of protective equi Request for Quota Single Stage - One E IDA / D5020 and Increasing Natural Reso Post Limited 48,000.00 0.00 Canceled 2020-03-25 2020-05-20 2020-11-16 pment, spraying and pesticid tions nvelope urces Resilience e for activities of control of th e red grasshopper 61/G/ANRLMP/17 / IT Equipm Securing Land Tenure Rights Single Stage - One E ent for revitalization of the d IDA / 58550 and Increasing Natural Reso Post Request for Bids Open - National 207,000.00 0.00 Canceled 2020-02-27 2020-03-05 2020-04-16 2020-05-17 2020-06-21 2020-12-18 nvelope ata center in the field of insti urces Resilience tutional support 62/G/ANRLMP/17 / Office fur Securing Land Tenure Rights Request for Quota Single Stage - One E niture in the scope of instituti IDA / 58550 and Increasing Natural Reso Post Limited 60,000.00 0.00 Canceled 2020-02-01 2020-03-28 2020-09-24 tions nvelope onal support urces Resilience Securing Land Tenure Rights 63/G/ANRLMP/17 / Equipmen Single Stage - One E IDA / 58550 and Increasing Natural Reso Post Request for Bids Open - National 182,000.00 0.00 Canceled 2020-03-02 2020-03-09 2020-04-21 2020-05-21 2020-06-25 2020-12-22 t for datacenter revitalization nvelope urces Resilience 60/G/ANRLMP/2016 / Office Project Coordination and Ma Request for Quota Single Stage - One E IDA / Q9900 Post Limited 56,500.00 0.00 Canceled 2016-12-14 2017-02-08 2017-08-07 Suplies nagement tions nvelope 09/G/ARLNMP/16 / Office Su Project Coordination and Ma Request for Quota Single Stage - One E IDA / D1190 Post Open - National 46,600.00 0.00 Canceled 2017-04-04 2017-05-30 2017-11-26 pplies nagement tions nvelope 166/G/ANRLMP/EMERG/20-2 / Acquisition of protective eq Contingency Emergency Res IDA / D5020 Post Direct Selection Direct 150,000.00 106,869.86 Signed 2020-04-24 2020-04-16 2020-04-29 2020-04-16 2020-06-03 2020-04-27 2020-11-30 uipment, spraying and pestic ponse ide for activities of control of the red grasshopper 174/G/ANRLMP/20 / Purchas Securing Land Tenure Rights Single Stage - One E e vehicle for PIU - Manica, So IDA / D5020 and Increasing Natural Reso Post Request for Bids Open - National 400,000.00 435,467.91 Signed 2020-06-30 2020-08-13 2020-07-05 2020-08-16 2020-09-17 2020-09-15 2021-04-21 2020-10-20 2021-05-28 2021-04-18 nvelope fala and Cabo Delgado Provin urces Resilience ce 175/G/ANRLMP/20 / Purchas Agriculture and Forest-Base Single Stage - One E e of motorcycle for PIU - Mani IDA / D5020 Post Request for Bids Open - National 108,000.00 0.00 Canceled 2020-06-30 2020-07-05 2020-08-16 2020-09-15 2020-10-20 2021-04-18 d Value Chain Development nvelope ca, Sofala and Cabo Delgado Province 176/G/ARNLMP/20 / Purchas Agriculture and Forest-Base Request for Quota Single Stage - One E e a Tablets and Laptops for a IDA / D5020 Post Limited 26,280.00 0.00 Canceled 2020-09-05 2020-10-31 2021-04-29 d Value Chain Development tions nvelope PIU - Manica, Sofala and Cab o Delgado Province Page 2 173/CD/ANRLMP/G/20 / Upgr Securing Land Tenure Rights ading the ArcGIS Desktop Sta IDA / 58550 and Increasing Natural Reso Post Direct Selection Direct 10,000.00 8,893.15 Signed 2020-06-30 2020-04-30 2020-07-05 2020-07-06 2020-08-09 2020-07-06 2021-02-05 ndard license to Advanced a urces Resilience nd purchasing Argis Online C redits 177/ANRLMP/G/2020 / IT Equ Project Coordination and Ma Request for Quota Single Stage - One E ipment for the management IDA / Q9900 Post Limited 35,000.00 0.00 Canceled 2020-08-23 2021-07-21 2020-10-18 2021-04-16 nagement tions nvelope of expressions of interest - B aia Produtiva 178/G/ANRLMP/20 / Acquisiti Agriculture and Forest-Base Single Stage - One E on of seedlings for restoratio IDA / 58550 Post Request for Bids Open - National 250,000.00 66,036.14 Signed 2020-08-18 2020-08-13 2020-08-23 2020-09-14 2020-10-04 2020-09-18 2020-11-03 2020-10-29 2020-12-08 2020-11-20 2021-06-06 d Value Chain Development nvelope n component 179/ANRLMP/G/20 / Acquisiti on of T-shirts, masks and pre vention material from COVID Agriculture and Forest-Base Request for Quota Single Stage - One E IDA / 58550 Post Open - National 100,000.00 0.00 Canceled 2020-10-06 2020-12-07 2021-06-05 19 for training extension wor d Value Chain Development tions nvelope kers in Sofala, Manica, Cabo Delgado and Zambézia Provi nces. 176-1/G/ANRLMP/20 / Purcha se of tablets and laptops for Agriculture and Forest-Base Request for Quota Single Stage - One E IDA / D5020 Post Limited 70,000.00 74,407.05 Signed 2020-12-06 2020-11-30 2021-01-31 2021-01-14 2021-07-30 a PIU - Manica, Sofala and Ca d Value Chain Development tions nvelope bo Delgado Province 191/G/ANRLMP/2021 / Produ ction and supply of seedlings Agriculture and Forest-Base Single Stage - One E to replace the properties of S IDA / D5020 Post Request for Bids Open - National 366,000.00 439,025.52 Signed 2021-08-31 2021-08-02 2021-09-05 2021-10-17 2021-09-01 2021-11-16 2021-12-27 2021-12-21 2022-01-31 2022-06-19 d Value Chain Development nvelope USTENTA beneficiaries in the landscapes of Cabo Delgado, Manica and Sofala 176-2/G/ANRLMP/20 / Purcha Project Coordination and Ma Request for Quota Single Stage - One E se of printer and laptops for IDA / D5020 Post Limited 10,500.00 12,430.11 Signed 2021-11-02 2021-10-22 2021-12-28 2021-11-30 2022-06-26 nagement tions nvelope a PIU - Nampula and Zambez ia Provinces 213/ANRLMP/G/21 / Office fu Project Coordination and Ma Request for Quota Single Stage - One E IDA / 58550 Post Limited 30,000.00 18,023.74 Signed 2022-01-04 2021-12-17 2022-03-01 2022-02-11 2022-08-28 rniture for new staff for PIU S nagement tions nvelope ofala 167/G/ANRLMP/EMERG/20 / Securing Land Tenure Rights Acquisition of fuel to supply v Request for Quota Single Stage - One E IDA / D5020 and Increasing Natural Reso Post Limited 7,000.00 0.00 Canceled 2020-03-25 2020-05-20 2020-11-16 ehicles and helicopters for th tions nvelope urces Resilience e activities of control of the r ed grasshopper 215/G/ANRLMP/RFQ/2022 / A Project Coordination and Ma Request for Quota Single Stage - One E IDA / D5020 Post Limited 25,000.00 22,934.70 Signed 2022-10-03 2022-08-19 2022-11-28 2022-09-09 2023-05-27 cquisition of eight Laptops nagement tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Securing Land Tenure Rights 10/NC/ANRLMP/16 / Satelite Single Stage - One E IDA / 58550 and Increasing Natural Reso Prior Request for Bids Open - National 775,000.00 621,474.24 Signed 2016-11-01 2016-10-13 2016-11-04 2016-10-27 2016-12-16 2016-11-15 2017-01-16 2017-01-30 2017-02-20 2017-05-17 2017-08-19 Picture Aquisition nvelope urces Resilience 21/NC/ANRLMP/16 / Hiring a Project Coordination and Ma Request for Quota Single Stage - One E company to create the sloga IDA / D1190 Post Open - National 20,000.00 0.00 Canceled 2016-10-16 2016-12-11 2017-06-09 nagement tions nvelope n, website, logo. 83/NCS/ANRLMP/17 / Transla Project Coordination and Ma Request for Quota Single Stage - One E IDA / D1190 Post Open - National 50,000.00 43,882.07 Signed 2017-10-09 2017-12-04 2017-10-24 2018-06-02 tion Service nagement tions nvelope 20/NC/ANRLMP/16 / Hiring c ompany to advertise material Project Coordination and Ma Request for Quota Single Stage - One E IDA / D1190 Post Open - National 20,000.00 0.00 Canceled 2018-02-28 2018-04-25 2019-04-25 supply (Posters, Printing, Flye nagement tions nvelope rs and other placartes) 123/NC/ANRLMP/18 / Acquisi Securing Land Tenure Rights tion of Aerial Images for Syst Open - Internationa Single Stage - One E IDA / 58550 and Increasing Natural Reso Prior Request for Bids 775,000.00 0.00 Canceled 2018-08-30 2018-09-11 2018-10-23 2018-11-22 2018-12-27 2021-12-11 ematic Land Regularization i l nvelope urces Resilience n Zambezia and Nampula pr ovinces 124/NC/ANRLMP/18 / Acquisi Securing Land Tenure Rights tion of Aerial Images for Syst Open - Internationa Single Stage - One E Under Imple IDA / 58550 and Increasing Natural Reso Post Request for Bids 775,000.00 0.00 2018-08-10 2018-08-13 2018-08-15 2018-09-26 2018-09-12 2018-10-26 2018-10-18 2018-11-30 2019-05-29 ematic Land Regularization i l nvelope mentation urces Resilience n Zambezia and Nampula pr ovinces 154/CER/NCS/ANRLMP/19 / H iring Service Provider to exec Contingency Emergency Res UN Agencies (Dire IDA / D1190 Prior Direct 10,000,000.00 0.00 Canceled 2019-04-24 2019-04-29 2019-06-03 2020-01-29 ute the Agricultural and Lives ponse ct) tock Recovery Plan post cycl one IDAI 124/NC/ANRLMP/18-2 / Aeria Securing Land Tenure Rights l Images for Systematic Regu Open - Internationa Single Stage - One E IDA / 58550 and Increasing Natural Reso Post Request for Bids 775,000.00 780,000.00 Signed 2019-08-22 2018-08-13 2019-08-27 2019-10-08 2018-09-12 2019-11-07 2018-10-18 2019-12-12 2019-01-31 2020-06-09 larization of Lands in the Pro l nvelope urces Resilience vinces of Nampula and Zamb ézia. 163/NCS/ANRLMP/19 / Renov Project Coordination and Ma Request for Quota Single Stage - One E IDA / D1190 Post Limited 15,000.00 13,136.01 Signed 2020-01-20 2020-01-28 2020-03-16 2020-03-12 2020-09-12 ation of project design softw nagement tions nvelope are licenses CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 18/ARLNMP/C/16 / Design an Securing Land Tenure Rights Quality And Cost- Open - Internationa d Supervision of Irrigation Sc IDA / 58550 and Increasing Natural Reso Prior 500,000.00 0.00 Canceled 2016-08-08 2016-12-14 2016-08-29 2016-10-12 2016-11-09 2016-12-09 2017-01-13 2017-02-17 2018-02-17 Based Selection l hemes (Rehabilitation) urces Resilience 19/CS/ANRLMP/16 / Service Securing Land Tenure Rights Quality And Cost- Open - Internationa Provider for Sistematic comm IDA / 58550 and Increasing Natural Reso Prior 6,000,000.00 6,310,924.41 Signed 2016-08-26 2016-09-30 2016-09-01 2016-09-27 2017-01-09 2016-10-25 2017-03-14 2016-11-24 2017-04-15 2016-12-29 2017-10-04 2017-02-02 2017-10-06 2018-02-02 Based Selection l unity land delimitation urces Resilience 14-CS/ANRLMP/16 / River ba Agriculture and Forest-Base Consultant Qualifi Open - Internationa IDA / 58550 Prior 750,000.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-20 2016-11-19 2016-12-22 2017-10-30 sin Studies d Value Chain Development cation Selection l Page 3 15-CS/ANRLMP/16 / River ba Agriculture and Forest-Base Consultant Qualifi Open - Internationa IDA / 58550 Prior 750,000.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-20 2016-11-21 2016-12-26 2017-06-24 sin studies d Value Chain Development cation Selection l 14/CS/ANRLMP/16 / River Ba Agriculture and Forest-Base Quality And Cost- Open - Internationa IDA / D1190 Prior 750,000.00 788,705.62 Signed 2016-08-29 2016-09-28 2016-09-19 2016-11-02 2016-12-07 2016-11-30 2017-02-16 2016-12-30 2017-04-06 2017-02-03 2017-08-24 2017-03-10 2017-09-06 2018-03-10 sin Studies d Value Chain Development Based Selection l 15/CS/ANRLMP/16 / River Ba Agriculture and Forest-Base Quality And Cost- Open - Internationa IDA / D1190 Prior 750,000.00 819,643.12 Signed 2016-08-29 2016-09-29 2016-09-19 2016-11-02 2016-12-07 2016-11-30 2017-02-16 2016-12-30 2017-03-30 2017-02-03 2017-08-24 2017-03-10 2017-09-06 2018-03-10 sin Studies d Value Chain Development Based Selection l 18/CS/ANRLMP/16 / Service Securing Land Tenure Rights Consultant Qualifi Open - Internationa Provider for systematic com IDA / 58550 and Increasing Natural Reso Prior 2,993,980.00 0.00 Canceled 2016-08-16 2016-09-06 2016-10-22 2016-11-21 2016-12-26 2017-06-24 cation Selection l munity land delimitation urces Resilience 32-CS/ANRLMP/16 / Baseline Project Coordination and Ma Quality And Cost- IDA / Q9900 Post Open - National 127,000.00 0.00 Canceled 2016-08-30 2016-08-29 2016-09-20 2016-11-03 2016-12-01 2017-01-01 2017-02-05 2017-03-12 2018-03-12 Survey nagement Based Selection 32/CS/ANRLMP/16 / Baseline Project Coordination and Ma Quality And Cost- Open - Internationa IDA / Q9900 Prior 200,000.00 345,948.67 Signed 2016-10-06 2016-09-30 2016-10-27 2016-10-06 2016-12-09 2017-03-20 2017-01-06 2017-04-21 2017-02-06 2017-07-10 2017-03-13 2018-01-29 2017-04-17 2018-03-12 2018-04-17 Sutudy nagement Based Selection l 21/CS/ANRLMP/16 / Hiring a Project Coordination and Ma Consultant Qualifi company to create the sloga IDA / D1190 Post Open - National 10,000.00 0.00 Canceled 2016-10-10 2016-10-31 2016-12-14 2017-01-14 2017-02-18 2017-08-17 nagement cation Selection n, website,logo MZ-UGFI-4758-CS-QCBS / Hir Agriculture and Forest-Base Quality And Cost- Open - Internationa e service provider to adminis IDA / D1190 Prior 300,000.00 436,412.61 Signed 2017-01-16 2017-01-25 2017-02-06 2017-02-01 2017-03-22 2017-05-09 2017-04-19 2017-06-23 2017-05-19 2017-08-01 2017-06-26 2018-01-29 2017-07-31 2018-03-13 2018-07-31 d Value Chain Development Based Selection l ter the partial credit guarant ee scheme 11/CS/ANRLMP/16 / Service Agriculture and Forest-Base Quality And Cost- Open - Internationa IDA / D1190 Prior 6,000,000.00 0.00 Canceled 2016-08-26 2016-08-31 2016-09-16 2016-10-30 2016-12-27 2016-11-27 2017-03-07 2016-12-27 2017-04-15 2017-01-31 2017-10-13 2017-03-07 2018-03-07 Provider for Value Chain dev d Value Chain Development Based Selection l elopment 97/CS/ANRLMP/17 / Service Agriculture and Forest-Base Quality Based Sel Open - Internationa IDA / D1190 Prior 1,500,000.00 2,632,313.75 Signed 2017-12-11 2018-02-07 2018-01-08 2018-02-14 2018-02-27 2018-06-15 2018-03-27 2018-07-18 2018-04-26 2018-08-23 2018-05-28 2018-10-26 2018-07-02 2018-10-29 2020-07-01 Provider for Quality Control a d Value Chain Development ection l nd Finance 12/CS/ANRLMP/16 / Service Agriculture and Forest-Base Quality And Cost- Open - Internationa IDA / 58550 Prior 4,000,000.00 0.00 Canceled 2017-01-16 2017-02-06 2017-03-22 2017-04-19 2017-05-19 2017-06-23 2017-07-28 2018-07-28 Provider-Restauration of degr d Value Chain Development Based Selection l aded land 130/CQS/ANRLMP/18 / Provis ion of service for training you Agriculture and Forest-Base Consultant Qualifi IDA / 58550 Post Open - National 70,000.00 0.00 Canceled 2019-02-01 2019-02-22 2019-04-08 2019-05-08 2019-06-12 2019-12-09 ng people in sustainable entr d Value Chain Development cation Selection epreneurship in agribusiness 153A/CS/ANRLMP/20 / Super Agriculture and Forest-Base Consultant Qualifi vision for works of rural road IDA / D5020 Post Open - National 30,500.00 115,042.06 Signed 2020-05-13 2020-06-03 2020-06-03 2020-06-12 2020-07-17 2020-12-23 2020-08-16 2022-01-25 2020-09-20 2021-01-27 2021-03-19 d Value Chain Development cation Selection s spot improvement in Namp ula Province 151A/CS/ANRLMP/20 / Super Agriculture and Forest-Base Consultant Qualifi Under Implement vision for works of rural road IDA / D5020 Post Open - National 73,000.00 0.00 2020-05-29 2020-06-03 2020-06-19 2020-06-12 2020-08-02 2020-09-01 2020-10-06 2021-04-04 d Value Chain Development cation Selection ation s spot improvement in Zamb ezia Province 157A/CS/ANRLMP/20 / Super vision for works of rehabilitat Agriculture and Forest-Base Consultant Qualifi IDA / D5020 Post Open - National 50,000.00 99,632.85 Signed 2020-05-29 2020-06-03 2020-06-19 2020-06-12 2020-08-03 2020-12-23 2020-09-02 2021-01-26 2020-10-07 2021-01-28 2021-04-05 ion of existing irrigation sche d Value Chain Development cation Selection mes - Ninthulo- Zambezia Pr ovince 156A/CS/ANRLMP/20 / Super vision for works of rehabilitat Agriculture and Forest-Base Consultant Qualifi IDA / D5020 Post Open - National 50,000.00 182,257.17 Signed 2020-06-02 2020-06-03 2020-06-23 2020-06-12 2020-08-06 2020-10-09 2020-09-07 2021-08-29 2020-10-12 2021-08-31 2021-04-10 ion of existing irrigation sche d Value Chain Development cation Selection mes - Micheche in Nampula P rovince 165A/CS/ANRLMP/2020 / Sup Securing Land Tenure Rights Consultant Qualifi ervision of the Rehabilitation IDA / D5020 and Increasing Natural Reso Post Open - National 50,000.00 0.00 Under Review 2020-10-22 2021-07-22 2020-11-12 2020-12-26 2021-01-25 2021-03-01 2021-08-28 cation Selection Works of the SPGC of Zambé urces Resilience zia 182/ANRLMP/DC/20 / Hiring Project Coordination and Ma Consultant Qualifi Pending Impleme a firm to prepare the Environ IDA / D5020 Post Limited 160,000.00 0.00 2020-11-10 2020-11-24 2020-12-24 2021-01-28 2021-07-27 nagement cation Selection ntation mental and Social Instrument s 181A/CS/ANRLMP/2021 / Sup Securing Land Tenure Rights Consultant Qualifi Under Implement ervision of Rehabilitation of R IDA / 58550 and Increasing Natural Reso Post Open - National 150,000.00 0.00 2021-07-30 2022-02-01 2021-08-20 2021-10-03 2021-11-02 2021-12-07 2022-06-05 cation Selection ation ural Roads in Nampula Provin urces Resilience ce 182A/CS/ANRLMP/2021 / Sup Securing Land Tenure Rights Consultant Qualifi Under Implement ervision of Rehabilitation of R IDA / 58550 and Increasing Natural Reso Post Open - National 100,000.00 0.00 2021-07-30 2022-02-01 2021-08-20 2021-10-03 2021-11-02 2021-12-07 2022-06-05 cation Selection ation ural Roads in Manica Provinc urces Resilience e 180A/CS/ANRLMP/2021 / Sup Securing Land Tenure Rights Consultant Qualifi Under Implement ervision of Rehabilitation of IDA / 58550 and Increasing Natural Reso Post Open - National 150,000.00 0.00 2021-07-30 2022-01-24 2021-08-20 2021-10-03 2021-11-02 2021-12-07 2022-06-05 cation Selection ation Rural Roads in Zambézia Pro urces Resilience vince 200/ANRLMP/CS/2021 / Cons ultancy services for evaluatio Securing Land Tenure Rights Quality And Cost- Under Implement n IDA / 58550 and Increasing Natural Reso Post Open - National 200,000.00 0.00 2021-11-03 2021-10-12 2021-11-24 2021-12-15 2022-01-07 2022-05-17 2022-02-04 2022-03-06 2022-04-10 2022-05-15 2023-05-15 Based Selection ation the satisfaction of beneficiari urces Resilience es, and the impact of PGIARN interventions 216/CS/ANRLMP/CQS/2022 / Hiring an Independent Firm t o Audit the Beneficiaries of G Agriculture and Forest-Base Consultant Qualifi Under Implement IDA / 58550 Post Open - National 150,000.00 0.00 2022-10-28 2022-08-04 2022-11-18 2022-08-18 2023-01-01 2023-01-31 2023-03-07 2023-09-03 rants from the Integrated Agr d Value Chain Development cation Selection ation iculture and Natural Resourc es Management Project (Lan dscape) 217/CS/ANRLMP/QCBS/2022 / Final Evaluation of the Integ Project Coordination and Ma Quality And Cost- IDA / 58550 Post Open - National 250,000.00 0.00 Under Review 2022-11-30 2022-08-04 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-06-10 rated Management of Agricul nagement Based Selection ture and Natural Resources P roject (PGIARN) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 38/IC/ANRLMP/16 / Matching Project Coordination and Ma Individual Consult IDA / 58550 Post Open 108,000.00 60,000.00 Signed 2016-10-19 2016-08-29 2016-12-07 2017-01-18 2016-12-28 2017-01-24 2017-02-01 2017-02-01 2017-07-31 Grants Manager nagement ant Selection Page 4 41/IC/ANRLMP/16 / Financial Project Coordination and Ma Individual Consult IDA / 58550 Post Open 54,000.00 36,000.00 Signed 2016-10-19 2017-02-28 2016-12-07 2017-04-18 2016-12-28 2017-04-20 2017-02-01 2017-04-21 2017-07-31 and Admnistrative Officer nagement ant Selection 53/IC/ANRLMP/16 / Administr Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 10,800.00 7,200.00 Signed 2017-12-26 2017-05-19 2018-02-13 2017-08-25 2018-03-06 2017-08-25 2018-04-10 2017-08-30 2018-10-07 ative and Financial Assistant nagement ant Selection 36/IC/ANRLMP/16 / Finance Project Coordination and Ma Individual Consult IDA / Q9900 Prior Open 72,000.00 0.00 Canceled 2017-02-13 2017-08-28 2017-04-03 2017-04-24 2017-05-29 2018-11-20 Assistant nagement ant Selection 40/IC/ANRLMP/16 / Technical Project Coordination and Ma Individual Consult IDA / 58550 Post Open 72,000.00 48,000.00 Signed 2017-02-14 2017-02-27 2017-04-04 2017-04-18 2017-04-25 2017-04-20 2017-05-30 2017-05-01 2018-11-21 Advisor for Matching Grant nagement ant Selection 47/IC/ANRLMP/16 / Administr Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 10,800.00 0.00 Canceled 2018-02-14 2018-04-04 2018-04-25 2018-05-30 2019-11-21 ative and Financial Assistant nagement ant Selection 39/IC/ANRLMP/16 / Technical Project Coordination and Ma Individual Consult IDA / 58550 Post Open 72,000.00 48,000.00 Signed 2017-02-14 2017-02-27 2017-04-04 2017-04-18 2017-04-25 2017-04-20 2017-05-30 2017-04-21 2018-11-21 Advisor for Matching Grant nagement ant Selection CS23 / Procurement Speciali Project Coordination and Ma Individual Consult IDA / Q9900 Prior Open - National 99,000.00 0.00 Canceled 2016-07-13 2016-07-13 2016-08-31 2016-09-21 2016-10-26 2018-06-30 st nagement ant Selection 74/IC/ANRLMP/17 / Project C Project Coordination and Ma Individual Consult IDA / D1190 Post Open 82,500.00 0.00 Canceled 2017-06-05 2017-06-02 2017-06-19 2017-06-19 2017-07-10 2018-01-06 oordinator for ANRLMP nagement ant Selection 65/IC/ANRLMP/17 / Senior Ag Project Coordination and Ma Individual Consult IDA / D1190 Post Open 84,000.00 81,000.00 Canceled 2017-04-05 2017-04-25 2017-05-01 2017-07-07 2017-05-08 2017-07-17 2017-06-05 2017-08-15 2017-12-02 ricultural Hidraulics Specialist nagement ant Selection 23/IC/ANRLMP/16 / National Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 129,600.00 0.00 Canceled 2017-05-30 2017-07-18 2017-08-08 2017-09-12 2018-03-11 Coordinator nagement ant Selection 29/IC/ANRLMP/16 / Environm Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 ental/Resilience Specialist nagement ant Selection 26/IC/ANRLMP/16 / Rural De Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 velopment Specialist nagement ant Selection 31/IC/ANRLMP/16 / Procurem Project Coordination and Ma Individual Consult IDA / Q9900 Prior Open 90,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 ent Manager nagement ant Selection 27/IC/ANRLMP/16 / Land Ad Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 ministration Specialist nagement ant Selection 52/IC/ANRLMP/16 / Natural R Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 esaurce Specialist Field Oper nagement ant Selection ator 35/IC/ANRLMP/16 / Procurem Project Coordination and Ma Individual Consult IDA / Q9900 Prior Open 72,000.00 0.00 Canceled 2017-12-29 2018-02-19 2018-03-12 2018-04-16 2018-10-13 ent Assistant nagement ant Selection 42/IC/ANRLMP/16 / Provincial Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 90,000.00 0.00 Canceled 2017-08-02 2017-09-20 2017-10-11 2017-11-15 2018-05-14 Coordinator nagement ant Selection 33/IC/ANRLMP/16 / Procurem Project Coordination and Ma Individual Consult IDA / Q9900 Prior Open 72,000.00 0.00 Canceled 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2018-02-11 ent Assistant nagement ant Selection 37/IC/ANRLMP/16 / M&E Spe Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 90,000.00 0.00 Canceled 2017-05-02 2017-05-19 2017-06-20 2017-07-11 2017-08-15 2018-02-11 cialist nagement ant Selection 25/IC/ANRLMP/16 / Value Ch Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 111,600.00 0.00 Canceled 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 ain Specialist nagement ant Selection 30/IC/ANRLMP/16 / GIS Speci Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 72,000.00 0.00 Canceled 2017-07-03 2017-08-21 2017-09-11 2017-10-16 2018-04-14 alist nagement ant Selection 28/IC/ANRLMP/16 / Communi Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-10-04 2017-11-22 2017-12-13 2018-01-17 2018-07-16 cation Specialist nagement ant Selection 51/IC/ANRLMP/16 / Land Spe Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 cialist Field Operator nagement ant Selection 50/IC/ANRLMP/16 / Value Ch Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 ain Specialist Field Operator nagement ant Selection 49/IC/ANRLMP/16 / Infraestru Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 ture Specialist Field Operato nagement ant Selection r 44/IC/ANRLMP/16 / Value Ch Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 ain Specialist Field Operator nagement ant Selection 48/IC/ANRLMP / Provincial Co Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 90,000.00 0.00 Canceled 2017-08-02 2017-09-20 2017-10-11 2017-11-15 2018-05-14 ordinator nagement ant Selection 46/IC/ANRLMP/16 / Natural R Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 esaurce Specialist Field Oper nagement ant Selection ator 45/IC/ANRLMP/16 / Land Spe Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2017-12-27 2018-02-14 2018-03-07 2018-04-11 2018-10-08 cialist Field Operator nagement ant Selection 35/SS/ANRLMP/17 / Procure Project Coordination and Ma IDA / D1190 Prior Direct Selection Direct 96,000.00 104,000.00 Signed 2017-05-30 2017-06-22 2017-06-09 2018-06-22 2017-08-14 2017-06-01 2019-08-04 ment Assistant nagement 37/SS/ANRLMP/17 / M&E Spe Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-05-29 2017-06-01 2017-06-08 2017-05-19 2017-08-12 2017-06-01 2019-08-02 cialist nagement 48/SS/ANRLMP/17 / Provincia Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-06-30 2017-06-22 2017-07-10 2017-08-14 2017-09-13 2017-08-24 2019-09-03 l Coordinator nagement 29/SS/ANRLMP/17 / Environ Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 ment and Social Safeguards nagement Specialist 31/SS/ANRLMP/17 / Procure Project Coordination and Ma IDA / D1190 Prior Direct Selection Direct 120,000.00 130,000.00 Signed 2017-05-29 2017-06-05 2017-06-12 2017-06-22 2017-08-16 2017-06-01 2019-08-06 ment Manager nagement Page 5 24/SS/ANRLMP/17 / Natural r Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 esaurces and forestry Special nagement ist 27/SS/ANRLMP/17 / Land Ad Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-05-29 2017-06-02 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 ministration Specialist nagement 28/SS/ANRLMP/17 / Commun Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-07-05 2017-06-01 2017-07-17 2017-08-31 2017-09-20 2017-09-04 2019-09-10 ications Specialist nagement 26/SS/ANRLMP/17 / Rural De Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 144,000.00 144,000.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-19 2017-08-16 2017-06-01 2019-08-06 velopment Specialist nagement 30/SS/ANRLMP/17 / GIS Spec Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 96,000.00 96,000.00 Signed 2017-07-05 2017-06-05 2017-07-17 2017-09-18 2017-09-20 2017-09-26 2019-09-10 ialist nagement 33/SS/ANRLMP/17 / Procure Project Coordination and Ma IDA / D1190 Prior Direct Selection Direct 96,000.00 96,000.00 Signed 2017-11-15 2018-03-11 2017-11-27 2018-03-15 2018-01-31 2018-02-02 2020-01-21 ment Assistant nagement 51/SS/ANRLMP/17 / Land Ad Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-06-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2019-04-29 ministration Specialist Field nagement Operator 44/SS/ANRLMP/17 / Value Ch Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 ain Specialist Field Operator nagement 49/SS/ANRLMP/17 / Infraestr Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 uture Specialist Field Operat nagement or 52/SS/ANRLMP/17 / Natural Project Coordination and Ma Resaurces and Forestry Speci IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-06-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 nagement alist Field Operator 45/SS/ANRLMP/17 / Land Ad Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2017-05-01 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 ministration Specialist Field nagement Operator 46/SS/ANRLMP/17 / Natural Project Coordination and Ma Resaurces and Forestry Speci IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 nagement alist Field Operator 50/SS/ANRLMP/17 / Value Ch Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 ain Specialist Field Operator nagement 43/SS/ANRLMP/17 / Infraestr Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 84,000.00 84,000.00 Signed 2018-08-15 2018-08-27 2017-07-03 2018-10-31 2017-07-13 2020-10-20 uture Specialist Field Operat nagement or 23/SS/ANRLMP/17 / National Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 172,800.00 190,080.00 Signed 2017-05-29 2017-06-01 2017-06-12 2017-05-26 2017-08-16 2017-06-01 2019-08-06 Coordinator nagement 17/IC/ANRLMP/16 / Facilitatio Securing Land Tenure Rights Individual Consult n of the development of a Co IDA / 58550 and Increasing Natural Reso Post Open 30,000.00 0.00 Canceled 2017-03-10 2017-05-01 2017-05-22 2017-06-26 2017-09-24 ant Selection mmon Landscape Vision urces Resilience 24/IC/ANRLMP/16 / Forest Sp Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 108,000.00 0.00 Canceled 2017-05-01 2017-06-19 2017-07-10 2017-08-14 2018-02-10 ecialist nagement ant Selection 34/SS/ANRLMP/17 / Financial Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-07-31 2017-02-27 2017-08-14 2017-03-13 2017-10-18 2017-03-23 2019-08-09 Manager nagement 69/IC/ANRLMP/17 / Environm Project Coordination and Ma Individual Consult IDA / D1190 Post Open 12,000.00 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 ental and Social Safeguard S nagement ant Selection pecialist 68/IC/ANRLMP/17 / GIS Speci Project Coordination and Ma Individual Consult IDA / D1190 Post Open 16,000.00 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 alist nagement ant Selection 67/IC/ANRLMP/17 / Topograp Project Coordination and Ma Individual Consult IDA / D1190 Post Open 24,000.00 0.00 Canceled 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 her nagement ant Selection 76/IC/ANRLMP/17 / safeguar Project Coordination and Ma Individual Consult IDA / D1190 Post Open 50,400.00 50,400.00 Signed 2017-10-02 2017-09-27 2017-12-04 2017-12-21 2017-12-25 2017-12-21 2018-01-29 2017-12-28 2018-07-28 d social and environmental s nagement ant Selection pecialist 77/IC/ANRLMP/17 / Agribusin Agriculture and Forest-Base Individual Consult ess Expert (Member of Invest IDA / D1190 Post Open 2,400.00 2,400.00 Signed 2017-09-24 2017-11-01 2017-09-26 2017-11-15 2017-09-27 2017-12-20 2017-09-28 2018-06-18 d Value Chain Development ant Selection iment Committee) 78/IC/ANRLMP/17 / Agribusin Agriculture and Forest-Base Individual Consult ess Community representativ IDA / D1190 Post Open 2,400.00 2,400.00 Signed 2017-09-24 2017-09-12 2017-10-30 2017-09-26 2017-11-14 2017-09-27 2017-12-19 2017-09-28 2018-06-17 d Value Chain Development ant Selection e (Member of the Investimen t Committee) 82/CS/ANRLMP/17 / Supervis Agriculture and Forest-Base ion for works of rural roads s IDA / D1190 Post Direct Selection Direct 30,000.00 69,301.25 Signed 2017-10-20 2017-12-19 2017-10-30 2018-06-06 2018-01-03 2018-03-30 2018-07-02 d Value Chain Development pot improvement/Zambezia 81/CS/ANRLMP/17 / Supervis Agriculture and Forest-Base ion for works of Rural roads s IDA / D1190 Post Direct Selection Direct 27,000.00 31,302.14 Signed 2017-10-20 2017-12-19 2017-10-30 2018-01-03 2018-03-30 2018-07-02 d Value Chain Development pot improvement/Nampula 96/IC/ANRLMP/17 / Hiring a c onsultant to support MSME to Agriculture and Forest-Base develop Business Plans for N IDA / D1190 Post Direct Selection Direct 60,000.00 98,784.00 Signed 2017-11-29 2017-12-04 2017-12-11 2017-12-14 2018-02-14 2018-02-28 2018-08-13 d Value Chain Development on-timber Forest Products in Nampula and Zambezia Provi nces 98/IC/ANRLMP/17 / Specialist Agriculture and Forest-Base Individual Consult IDA / D1190 Post Open 92,400.00 92,400.00 Signed 2017-11-30 2017-12-04 2018-01-20 2017-12-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 in Business Development d Value Chain Development ant Selection 99/IC/ANRLMP/17 / Knowledg Agriculture and Forest-Base Individual Consult IDA / D1190 Post Open 92,400.00 92,400.00 Signed 2017-11-30 2017-12-04 2018-01-22 2017-12-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 e transfer Specialist d Value Chain Development ant Selection 101/IC/ANRLMP/17 / Financia Agriculture and Forest-Base Individual Consult IDA / D1190 Post Open 66,000.00 66,000.00 Signed 2017-11-30 2017-12-04 2018-01-22 2018-01-29 2018-02-12 2018-01-05 2018-03-19 2018-01-19 2020-03-18 l administration/Nampula Pro d Value Chain Development ant Selection vince 102/IC/ANRLMP/17 / Financia Agriculture and Forest-Base Individual Consult IDA / D1190 Post Open 66,000.00 66,000.00 Signed 2017-11-30 2017-12-04 2018-01-22 2017-12-29 2018-02-12 2018-01-15 2018-03-19 2018-01-19 2020-03-18 l administration/Zambezia Pr d Value Chain Development ant Selection ovince Page 6 103/IC/ANRLMP/17 / Account Agriculture and Forest-Base Individual Consult ants (3 for Nampula Province IDA / D1190 Post Open 223,200.00 51,921.60 Signed 2017-11-30 2017-12-04 2018-01-22 2018-05-14 2018-02-12 2018-05-17 2018-03-19 2018-05-29 2020-03-18 d Value Chain Development ant Selection and 3 for Zambezia Province) 104/IC/ANRLMP/17 / Provinci Agriculture and Forest-Base Individual Consult al Assistant of Value Chain I IDA / D1190 Post Open 84,000.00 84,000.00 Signed 2017-12-20 2018-02-07 2017-12-29 2018-02-28 2018-01-05 2018-04-04 2018-01-19 2018-10-01 d Value Chain Development ant Selection mplementation/Nampula Pro vince 105/IC/ANRLMP/17 / Provinci Agriculture and Forest-Base Individual Consult al Assistant of Value Chain I IDA / D1190 Post Open 84,000.00 84,000.00 Signed 2017-12-20 2018-02-07 2017-12-29 2018-02-28 2018-01-05 2018-04-04 2018-01-19 2018-10-01 d Value Chain Development ant Selection mplementation/Zambezia Pro vince 80/IC/ANRLMP/17 / Elaborati Agriculture and Forest-Base Individual Consult on of the Warehouse Constru IDA / D1190 Post Open 5,000.00 0.00 Canceled 2018-01-31 2018-03-21 2018-04-11 2018-05-16 2018-11-12 d Value Chain Development ant Selection ction Project for the PACES 66/IC/ANRLMP/17 / Civil Engi Project Coordination and Ma Individual Consult IDA / D1190 Post Open 60,000.00 0.00 Canceled 2018-02-01 2018-03-26 2018-04-16 2018-05-21 2020-05-10 neer nagement ant Selection 84/IC/ANRLMP/17 / Supervisi Agriculture and Forest-Base Individual Consult IDA / D1190 Post Open 7,000.00 0.00 Canceled 2018-02-01 2018-03-26 2018-04-16 2018-05-21 2018-11-17 on of Warehouse Constructio d Value Chain Development ant Selection n 42/SS/ANRLMP/17 / Provincia Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 120,000.00 120,000.00 Signed 2017-06-30 2017-06-22 2017-07-10 2017-08-14 2017-09-13 2017-08-24 2019-09-03 l Coordinator nagement 34/IC/ANRLMP/16 / Finance Project Coordination and Ma Individual Consult IDA / Q9900 Prior Open 90,000.00 0.00 Canceled 2017-03-18 2017-03-23 2017-05-08 2017-05-29 2017-07-03 2017-12-30 Manager nagement ant Selection 65/IC/ ANRLMP/17 / Senior A Securing Land Tenure Rights Individual Consult gricultural hidraulics Speciali IDA / D1190 and Increasing Natural Reso Post Open 84,000.00 0.00 Canceled 2017-06-13 2017-08-01 2017-08-22 2017-09-26 2018-09-26 ant Selection st urces Resilience 43/IC/ANRLMP/16 / Infraestru Project Coordination and Ma Individual Consult IDA / Q9900 Post Open 63,000.00 0.00 Canceled 2018-04-09 2018-05-28 2018-06-18 2018-07-23 2019-01-19 ture Specialist Field Operator nagement ant Selection 25/SS/ANRLMP/17 / Value Ch Project Coordination and Ma IDA / D1190 Post Direct Selection Direct 148,800.00 148,800.00 Signed 2017-11-01 2017-11-03 2017-11-13 2017-12-08 2018-01-17 2017-12-22 2020-01-07 ain Specialist nagement 110/SS/ANRLMP/17 / Consult ant for the Review of the Bus Agriculture and Forest-Base iness Plans of the PACES of t IDA / 58550 Post Direct Selection Direct 13,000.00 12,160.00 Signed 2018-01-17 2018-01-26 2018-02-05 2017-12-27 2018-04-11 2018-02-28 2018-10-08 d Value Chain Development he Provinces of Nampula and Zambezia covered by PGIAR N 118/SS/ANRLMP/18 / Admini Project Coordination and Ma strative and financial assista IDA / 58550 Post Direct Selection Direct 10,800.00 12,000.00 Signed 2018-06-27 2018-06-27 2018-07-09 2018-01-11 2018-09-12 2018-03-01 2020-09-11 nagement nt - Zambezia 83/IC/ANRLMP/17 / Supervisi Securing Land Tenure Rights Individual Consult on for works rehabilitation of IDA / D1190 and Increasing Natural Reso Post Open 18,000.00 15,074.38 Signed 2018-08-31 2018-08-17 2018-10-22 2018-07-31 2018-11-12 2018-11-21 2018-12-17 2018-11-21 2019-03-17 ant Selection the data center in Nampula urces Resilience Province 124/IC/ANRLM/18 / Supervisi Securing Land Tenure Rights Individual Consult on for works rehabilitation of IDA / D1190 and Increasing Natural Reso Post Open 18,000.00 18,375.72 Signed 2018-08-31 2018-08-17 2018-10-22 2018-05-24 2018-11-12 2018-11-16 2018-12-17 2018-11-16 2019-03-17 ant Selection the data center in Zambezia urces Resilience Province 126/SS/ANRLMP/18 / Advisor Project Coordination and Ma for Institutional Relations and IDA / 58550 Post Direct Selection Direct 28,800.00 28,800.00 Signed 2018-08-31 2018-09-12 2018-09-11 2018-09-21 2018-09-20 2018-09-28 2019-03-19 nagement Cooperation 127/IC/ANRLMP/18 / Operati Project Coordination and Ma Individual Consult IDA / 58550 Post Open 120,000.00 120,000.00 Signed 2018-09-20 2018-09-12 2018-11-12 2018-09-26 2018-12-03 2018-09-24 2019-01-07 2018-10-12 2020-12-27 onal Chief for ANRLMP nagement ant Selection 117/SS/ANRLMP/18 / Technic Project Coordination and Ma IDA / 58550 Post Direct Selection Direct 48,000.00 0.00 Canceled 2018-06-27 2018-03-08 2018-07-09 2018-09-12 2019-09-12 al Adviser for Matching Grant nagement s Unit 116/SS/ANRLMP/18 / Technic Project Coordination and Ma IDA / 58550 Post Direct Selection Direct 48,000.00 0.00 Canceled 2018-06-27 2018-05-10 2018-07-09 2018-09-12 2019-09-12 al Adviser for Matching Grant nagement s Unit 115/SS/ANRLMP/18 / Matchin Project Coordination and Ma IDA / 58550 Post Direct Selection Direct 120,000.00 0.00 Canceled 2018-06-27 2018-07-09 2018-09-12 2019-03-11 g Grants Unit Manager nagement 122/SS/ANRLMP/18 / Financi Project Coordination and Ma IDA / 58550 Post Direct Selection Direct 36,000.00 0.00 Canceled 2018-08-30 2018-09-10 2018-11-14 2019-11-09 al and Administrative Officer nagement (MGU) 149/IC/ANRLMP/19 / Executi Project Coordination and Ma Individual Consult IDA / 58550 Post Open 18,000.00 18,000.00 Signed 2019-05-15 2019-03-28 2019-07-03 2019-06-19 2019-07-24 2019-06-19 2019-08-28 2019-07-24 2020-08-27 ve Secretary for Zambezia Pr nagement ant Selection ovince 150/IC/ANRLMP/19 / Platform Project Coordination and Ma Individual Consult IDA / 58550 Post Open 6,000.00 6,000.00 Signed 2019-05-15 2019-03-28 2019-07-03 2019-07-31 2019-07-24 2019-08-02 2019-08-28 2019-08-02 2020-08-27 Assistant for Zambezia Provi nagement ant Selection nce 148/IC/ANRLMP/19 / Platform Project Coordination and Ma Individual Consult IDA / 58550 Post Open 6,000.00 89.02 Signed 2019-05-15 2019-03-28 2019-07-03 2019-09-17 2019-07-24 2019-09-19 2019-08-28 2019-09-30 2020-08-27 Assistant for Nampula Provin nagement ant Selection ce 146/SSS/ANRLMP/19 / Consu ltancy for the updating of the Project Coordination and Ma instruments of environmenta IDA / 58550 Post Direct Selection Direct 15,000.00 16,100.00 Signed 2019-03-15 2019-03-15 2019-03-25 2019-03-19 2019-05-29 2019-05-27 2019-07-28 nagement l and social safeguards for th e ANRLMP- Additional Financi ng 147/IC/ANRLMP/19 / Executi Project Coordination and Ma Individual Consult IDA / 58550 Post Open 18,000.00 266.47 Signed 2019-05-15 2019-03-28 2019-07-03 2019-09-17 2019-07-24 2019-09-19 2019-08-28 2019-09-24 2020-02-24 ve Secretary for Nampula Pro nagement ant Selection vince 155/IC/ANRLMP/19 / Procure Project Coordination and Ma Individual Consult IDA / 58550 Prior Open 48,000.00 0.00 Canceled 2019-06-21 2019-05-30 2019-08-12 2019-07-31 2019-09-02 2019-10-07 2020-10-06 ment specialist nagement ant Selection 160/SSS/ ANRLM/2019 / Proc Project Coordination and Ma IDA / D1190 Prior Direct Selection Direct 120,000.00 120,000.00 Signed 2019-08-06 2019-08-07 2019-08-20 2019-07-19 2019-10-24 2019-08-01 2021-10-13 urement Specialist II nagement 161/SSS/ANRMP?2019 / Proc Project Coordination and Ma IDA / D1190 Prior Direct Selection Direct 96,000.00 96,000.00 Signed 2019-08-06 2019-08-07 2019-08-16 2019-07-19 2019-10-21 2019-08-01 2021-10-10 urement Specialist III nagement 119/SS/ANRLMP/18 / Recruit ment of consultant to carry o Project Coordination and Ma ut Qualitative evaluation of t IDA / D1190 Post Direct Selection Direct 3,500.00 0.00 Canceled 2018-06-27 2018-07-11 2018-09-14 2018-09-29 nagement he Mid-term Review Report o f the SUSTAINABILITY Implem entation Page 7 152/SSS/ANRLMP/19 / Recrui Agriculture and Forest-Base tment of consultant to suppo IDA / 58550 Post Direct Selection Direct 45,000.00 0.00 Canceled 2019-05-23 2019-06-04 2019-08-08 2020-03-05 d Value Chain Development rt the implementation of the Guarantee Fund 161/IC/ANRLMP/19 / Consult ant for risk assessment of ge Project Coordination and Ma Individual Consult IDA / D5020 Post Open 15,000.00 0.00 Canceled 2019-09-19 2019-09-19 2019-11-08 2019-11-29 2020-01-03 2020-04-01 nder based violence at the Pr nagement ant Selection oject area, Additional Financi ng Project . 161-2/SSS/ANRLMP/19 / Con sultant for risk assessment of Agriculture and Forest-Base IDA / D5020 Post Direct Selection Direct 15,000.00 24,563.00 Signed 2019-11-10 2019-11-10 2019-11-20 2019-11-06 2020-01-24 2019-11-18 2020-07-22 gender based violence at the d Value Chain Development Project area, additional finan cing Project 129/IC/ANRLMP/18 / Financia Project Coordination and Ma Individual Consult l Administrative Assistant/Za IDA / 58550 Post Open 26,928.00 0.00 Canceled 2018-11-15 2019-01-07 2019-01-28 2019-03-04 2020-03-03 nagement ant Selection mbezia Province 162/SS/ANRLMP/19 / Trainin g of technicians and benefici Securing Land Tenure Rights aries of the SUSTENTA Projec Individual Consult IDA / D5020 and Increasing Natural Reso Post Limited 10,000.00 0.00 Canceled 2019-10-31 2019-10-01 2019-11-05 2019-11-28 2019-11-26 2019-12-31 2020-06-28 t on restoration approach an ant Selection urces Resilience d agroforestry systems in Na mpula and Zambezia landsca pes 164A/IC/ANRLMP/2020 / Sup Securing Land Tenure Rights Individual Consult Under Implement ervision of the Rehabilitation IDA / D5020 and Increasing Natural Reso Post Limited 6,000.00 0.00 2020-10-21 2022-06-01 2020-10-26 2022-08-29 2020-11-16 2022-09-13 2020-12-21 2021-06-19 ant Selection ation Works of the SPGC of Nampul urces Resilience a 189/DC/ANRLMP/2021 / Hirin Securing Land Tenure Rights g of the Platform of Province IDA / D5020 and Increasing Natural Reso Post Direct Selection Direct 78,000.00 0.00 Canceled 2021-04-23 2021-05-10 2021-07-14 2022-01-10 of Cabo Delgado urces Resilience 190/DS/ANRLMP/2021 / Hirin Securing Land Tenure Rights g of the Plataform of Provinc IDA / D5020 and Increasing Natural Reso Post Direct Selection Direct 78,000.00 77,199.01 Signed 2021-04-23 2021-07-02 2021-05-10 2022-07-11 2021-07-14 2022-07-18 2022-01-10 e of Nampula urces Resilience 155/IC/ANRLMP/19-2 / Procur Project Coordination and Ma Individual Consult IDA / 58550 Prior Open 72,000.00 0.00 Canceled 2019-12-09 2020-01-22 2020-01-30 2020-02-20 2020-03-26 2021-03-26 ement Specialist IV nagement ant Selection 197/CS/ANRLMP/2021 / Servi Agriculture and Forest-Base ce Provider for Quality Contr IDA / 58550 Post Direct Selection Direct 370,000.00 369,852.00 Signed 2021-07-30 2021-07-14 2021-08-16 2021-07-23 2021-10-20 2021-07-30 2022-04-18 d Value Chain Development ol and Finance 198/CS/ANRLMP/2021 / Servi Securing Land Tenure Rights ce Provider for Systematic co IDA / 58550 and Increasing Natural Reso Post Direct Selection Direct 750,000.00 749,762.33 Signed 2021-07-20 2021-07-08 2021-08-04 2021-08-09 2021-10-08 2021-08-25 2022-04-06 mmunity land delimitation urces Resilience 189-1/CS/ANRLMP/2021 / Hir Securing Land Tenure Rights ing of the Plataform of Zamb IDA / D5020 and Increasing Natural Reso Post Direct Selection Direct 78,000.00 100,873.38 Signed 2021-07-14 2021-07-02 2021-07-26 2021-07-02 2021-09-29 2021-07-27 2022-03-28 ézia Province urces Resilience 201/ANRLMP/CS/21 / Hiring c onsultancy services for techn Agriculture and Forest-Base Under Implement IDA / 58550 Post Direct Selection Direct 45,500.00 0.00 2021-12-30 2022-06-22 2022-01-09 2022-03-15 2022-09-11 ical assistance in the incubati d Value Chain Development ation on of young PACES and chick en production 202/ANRLMP/CS/21 / Hiring c onsultancy services for techn Agriculture and Forest-Base IDA / 58550 Post Direct Selection Direct 94,000.00 93,460.90 Signed 2021-12-22 2021-12-13 2022-01-01 2021-12-08 2022-03-07 2021-10-19 2022-09-03 ical assistance in the incubati d Value Chain Development on of young PACES in the see d production sector 212/ANRLMP/IC/21 / Hiring Fi Project Coordination and Ma Individual Consult Under Implement IDA / 58550 Post Open 54,000.00 0.00 2021-12-08 2022-02-14 2022-01-26 2022-02-16 2022-03-23 2023-03-18 nancial Assistant for PIU Map nagement ant Selection ation uto 203/ANRLMP/IC/21 / Hiring P Project Coordination and Ma Individual Consult oultry Value Chain Assistant f IDA / 58550 Post Open 63,000.00 63,000.00 Signed 2021-12-29 2022-01-24 2022-02-16 2022-04-14 2022-03-09 2022-04-22 2022-04-13 2022-04-29 2023-04-08 nagement ant Selection or PIU Nampula 205/ANRLMP/IC/21 / Hiring a Project Coordination and Ma Individual Consult IDA / 58550 Post Open 54,000.00 514.66 Signed 2021-12-20 2021-12-01 2022-02-07 2022-07-20 2022-02-28 2022-07-21 2022-04-04 2022-07-26 2022-10-01 Safeguards Assistant for PIU nagement ant Selection Zambezia 207/ANRLMP/IC/21 / Hiring o Project Coordination and Ma Individual Consult IDA / 58550 Post Open 63,000.00 0.00 Canceled 2021-12-22 2022-01-28 2022-02-09 2022-03-02 2022-04-06 2022-10-03 f Restoration Technician for P nagement ant Selection IU Sofala 204/ANRLMP/IC/21 / Hiring a Project Coordination and Ma Individual Consult IDA / 58550 Post Open 63,000.00 63,000.00 Signed 2021-12-22 2022-01-24 2022-02-09 2022-04-14 2022-03-02 2022-04-22 2022-04-06 2022-04-29 2023-04-01 Value Chain Assistant for PIU nagement ant Selection Zambezia 210/ANRLMP/IC/21 / Hiring a Project Coordination and Ma Individual Consult Knowledge Transfer Technici IDA / 58550 Post Open 54,000.00 0.00 Canceled 2021-12-22 2022-01-24 2022-02-09 2022-03-02 2022-04-06 2023-04-01 nagement ant Selection an for PIU Manica 211/ANRLMP/IC/21 / Hiring a Project Coordination and Ma Individual Consult Under Implement Business and Accounting Offi IDA / 58550 Post Open 54,000.00 0.00 2021-12-22 2022-02-14 2022-02-09 2022-03-02 2022-04-06 2022-05-12 nagement ant Selection ation cer for PIU Manica 209/ANRLMP/IC/21 / Hiring a Project Coordination and Ma Individual Consult IDA / 58550 Post Open 63,000.00 0.00 Canceled 2021-12-22 2022-02-14 2022-02-09 2022-03-02 2022-04-06 2022-10-03 Restoration Technician for PI nagement ant Selection U Manica 214/IC/ANRLMP/2022 / Procu Project Coordination and Ma Individual Consult Under Implement IDA / 58550 Prior Open 95,000.00 0.00 2022-05-27 2022-03-11 2022-07-15 2022-08-12 2022-08-05 2022-09-09 2023-03-08 rement Specialist nagement ant Selection ation 206/ANRLMP/IC/21 / Hiring a Project Coordination and Ma Individual Consult IDA / 58550 Post Open 54,000.00 0.00 Canceled 2021-12-28 2021-12-01 2022-02-15 2022-03-08 2022-04-12 2023-04-07 Safeguards Assistant for PIU nagement ant Selection Sofala 208/ANRLMP/IC/21 / Hiring a Project Coordination and Ma Individual Consult IDA / 58550 Post Open 54,000.00 0.00 Canceled 2021-12-22 2021-12-01 2022-02-09 2022-03-02 2022-04-06 2022-10-03 Safeguards Assistant for PIU nagement ant Selection Manica 218/CS/ANRLMP/DS/2022 / H iring of Consulting Services f Agriculture and Forest-Base IDA / 58550 Post Direct Selection Direct - National 120,000.00 0.00 Canceled 2022-10-30 2022-08-15 2022-11-09 2023-01-13 2023-07-12 or the Implementation of Bus d Value Chain Development iness Plans on the Field of th e beneficiary PACES Page 8