Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 10, 2017 (Original procurement plan). 2. Date of General Procurement Notice: NA 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. Goods Above US$ 4 million All 2. Works Above US$ 15 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. NA. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: The Project Implementation Manual (PIM) makes reference to all applicable procurement guidelines and manuals including the Commune/Sangkat Fund PIM for small-scale infrastructure activities carried out by the sub-national levels (Commune/Sangkat), has been developed for this project. 4. Any Other Special Procurement Arrangements: 5 packages (goods) would be financed under retroactive financing 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comments No. on ed stic by Bank Cost Prefe (Prior / US$ rence Post) million (yes/ no) Communi 5.48 60 No Post procured by ty Communes/ June 12, 2017 infrastruc Sangkats tures individually for the whole life of the project Procure 0.92 8 No Post will be ment of procured vehicles, centrally at office the beginning of equipme project nt, office implementa furniture, tion motorcyc (shopping les, etc. method) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Selection of Consulting firms Above US$ 2 million All 2. Selection of Individual Above US$ All Consultant 400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 11 individual consultants would be financed through retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 6 7 Ref. Description Estimate Pac Review Comments No. d kag by Bank Cost es (Prior / US$ Post) million Producer Group 0.34 1 Post QCBS method Mobilization for June 12, 2017 Siem Reap (NGO package) Self-help Group 0.27 1 Post QCBS method Mobilization for SRP (NGO) Human Resources 0.92 2 Post QBS method Development Services Provider (HRDSP) for Siem Reap (NGO/Firm) Consulting firms for 0.175 1 Post CQS method baseline survey, impact survey, and final impact survey, and External financial auditing Individual 2.93 126 Post Selection of consultants for individual supporting the consultant. national level and sub-national level project entities (finance, procurement, infrastructure, community development, micro-finance experts, livelihood specialists, etc.) June 12, 2017 PROCUREMENT Cambodia : KH - Livelihood Enhancement and Association of the Poor Project (LEAP) PLAN General Information Country: Cambodia 2017-06-12 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank 2023-01-18 if none) Project ID: P153591 GPN Date: Project Name: KH - Livelihood Enhancement and Association of the Poor Project (LEAP) Loan / Credit No: IDA / 59600 Ministry of Interior Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Report Loan / Credit N Market Approac Procurement Pr Prequalification High SEA/SH Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Contract Comple Description Component Review Type Method Document Typ Amount (U mount (U and Recommendatio Signed Contract o. h ocess (Y/N) Risk tatus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes tion e S$) S$) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KH-MOI-99874-CW-RFQ / Off Component 3: Project Mana Request for Quota Single Stage - One Pending Im 2019-05-1 IDA / 59600 Post Open - National 30,000.00 0.00 2019-03-06 2019-04-17 ice Renovation at PCO-MOI gement tions Envelope plementatio 7 n KH-MOI-99875-CW-CDD / Th e rehabilitation laterite road Component 1: Improving Liv Pending Im (Length 2400m, Width 4.00 Community Drive 2019-09-0 IDA / 59600 elihoods for Rural Poor and Post Open - National 28,341.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 m, 0.15m thick) and Single Pi n Development 9 Vulnerable Households n pe Culvert Ø 1.0m (2 units) f or Anlong Samnar, Chi Kraen g. KH-MOI-99886-CW-CDD / Th e rehabilitation laterite road Component 1: Improving Liv Pending Im ( Length 1500m, Width 4.00 Community Drive 2019-08-1 IDA / 59600 elihoods for Rural Poor and Post Open - National 29,208.00 0.00 plementatio 2019-03-01 2019-03-08 2019-04-30 2019-05-07 2019-05-21 m, 0.15m Thick) and Constru n Development 9 Vulnerable Households n ction of Box Culver heigth 2 m with Stop Log (1 unit) for Doun Kaev, Puok. KH-MOI-99878-CW-CDD / Th Component 1: Improving Liv Pending Im e rehabilitation laterite road Community Drive 2019-07-1 IDA / 59600 elihoods for Rural Poor and Post Open - National 25,921.00 0.00 plementatio 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 (Length 2419m, Width 3.50 n Development 1 Vulnerable Households n m, 0.15m thick) for Chi Krae ng, Chi Kraeng. KH-MOI-99880-CW-CDD / Th e rehabilitation laterite road (Length 2090m, Width 4.00 Component 1: Improving Liv Pending Im m, 0.15m thick) and Constru Community Drive 2019-07-1 IDA / 59600 elihoods for Rural Poor and Post Open - National 30,721.00 0.00 plementatio 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 ction of Single Pipe Culvert Ø n Development 1 Vulnerable Households n 0.6m (1 unit), Single Pipe Cul vert Ø 0.8m (1 unit) and Sing le Pipe Culvert Ø 1.0m (1unit ) for Dan Run, Soutr Nikom. KH-MOI-99881-CW-CDD / Th e rehabilitation laterite road (Length 1550m, Width 4.00 Component 1: Improving Liv Pending Im Community Drive 2019-09-1 m, 0.15m thick), Single Pipe IDA / 59600 elihoods for Rural Poor and Post Open - National 29,965.00 0.00 plementatio 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 n Development 9 Culvert Ø 1.0m (1unit) and C Vulnerable Households n onstruction of Double Pipe C ulvert Ø 0.8m (5units), for Ba llangk, Prasat Bakong. KH-MOI-99887-CW-CDD / Co nstruction of Box Culvert hei gth 2m with stop Log (1unit), Component 1: Improving Liv Pending Im Community Drive 2019-09-0 Box Culvert heigth 1.5m with IDA / 59600 elihoods for Rural Poor and Post Open - National 29,896.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 stop Log (1unit) Pipe Culver Vulnerable Households n Ø 0.8m with Stop Log (1unit) and Single Pipe Culvert Ø 0.8 m (4 unit) for Sasar Sdam, P uok. KH-MOI-99888-CW-CDD / Co nstruction of Reinforced Con Component 1: Improving Liv Pending Im Community Drive 2019-09-0 crete Road (Lengh 260m, wi IDA / 59600 elihoods for Rural Poor and Post Open - National 30,417.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 dth 5.00m, 0.15m thick) for Vulnerable Households n Kampong Thkov, Kralanh. To tal: 0.260 km KH-MOI-99890-CW-CDD / Th e rehabilitation ponds size (6 Component 1: Improving Liv Pending Im Community Drive 2019-07-1 0mx30mx5m), (30mx25mx5 IDA / 59600 elihoods for Rural Poor and Post Open - National 29,949.00 0.00 plementatio 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 n Development 1 m), (40mx20mx5m), (50mx5 Vulnerable Households n 0mx5m) for Slaeng Spean, Sr ei Snam. Total:4 Places KH-MOI-99891-CW-CDD / Th e rehabilitation laterite road Component 1: Improving Liv Pending Im Community Drive 2019-09-0 (1.450km) and Single Pipe C IDA / 59600 elihoods for Rural Poor and Post Open - National 32,660.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 ulvert Ø 1.0m (3 units) for Sv Vulnerable Households n ay Chek, Angkor Thum. KH-MOI-99892-CW-CDD / Th e rehabilitation laterite road Component 1: Improving Liv Pending Im ( Length 2520m, Width 4.00 Community Drive 2019-09-0 IDA / 59600 elihoods for Rural Poor and Post Open - National 34,064.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 m, 0.15 Thick) and Construct n Development 9 Vulnerable Households n ion of Single Pipe Culvert Ø 1 .0m (2 unit) for Leang Dai, A ngkor Thum. KH-MOI-99893-CW-CDD / Th e rehabilitation laterite road (Length 1080m, Width 4.00 Component 1: Improving Liv Pending Im Community Drive 2019-08-0 m, 0.15m thick) and Constru IDA / 59600 elihoods for Rural Poor and Post Open - National 27,869.20 0.00 plementatio 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-05-07 n Development 5 ction of Single Pipe Culvert Ø Vulnerable Households n 0.8m (1 unit) and Triple Pipe Culvert, Ø 1.0m (3 unit) for Ta Siem, Svay Leu. KH-MOI-99894-CW-CDD / Co nstruction of Reinforced Con Component 1: Improving Liv Pending Im Community Drive 2019-09-0 crete Road (Length 445m, W IDA / 59600 elihoods for Rural Poor and Post Open - National 48,510.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 idth 3.50m, 0.15m thick) for Vulnerable Households n khnang Phnum, Svay Leu. KH-MOI-99889-CW-CDD / Th e rehabilitation laterite road Component 1: Improving Liv Pending Im Community Drive 2019-09-0 (Length 2600m, Width 5.00 IDA / 59600 elihoods for Rural Poor and Post Open - National 29,932.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 m, 0.15m thick) for Klang Ha Vulnerable Households n y, Srei Snam. Total: 2.600 k m KH-MOI-110153-CW-CDD / C onstruction:1- Reinforcement concrete road:(L353m, W 4m Component 1: Improving Liv Pending Im Community Drive 2019-09-0 , T0.15m) and drainage syste IDA / 59600 elihoods for Rural Poor and Post Open - National 89,712.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 m (L353m, 0.6m ) and 2-Rein Vulnerable Households n forcement concrete road (L3 57m, W 4m, T 0.15m) in San gkat Dangkao, Khan Dangka o KH-MOI-110154-CW-CDD / C onstruction of Reinforcement concrete road and Drainage Component 1: Improving Liv Pending Im System: 1- Road (100m) , 2- Community Drive 2019-09-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 98,080.00 0.00 plementatio 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 Road (171m ), 3-Road (52m), n Development 4 Vulnerable Households n 4- Road(88m) ,5- Road (90m) , 6- Road (93m) and 7-Road ( L128m) in Sangkat Prey Vea eng, Khan Dangkao KH-MOI-110159-CW-CDD / C onstruction of reinforcement concrete road:(466m, width Component 1: Improving Liv Pending Im Community Drive 2019-09-2 5m, thickness 0.15m ), 2-Roa IDA / 59600 elihoods for Rural Poor and Post Open - National 105,204.00 0.00 plementatio 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 n Development 4 d:(312m, width 4m, thicknes Vulnerable Households n s 0.15m ) and drainage syste m:(312m,cross section 0.6m) in Sangkat Kork Roka, Khan Preak Pnov KH-MOI-110165-CW-CDD / C onstruction of reinforcement concrete road and and drain Component 1: Improving Liv Pending Im age system in Prey Spueu & Community Drive 2019-10-0 IDA / 59600 elihoods for Rural Poor and Post Open - National 84,579.00 0.00 plementatio 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 Prey Sandaek, Sangkat Chao n Development 9 Vulnerable Households n m Chau 2, Khan Por Sen Che y (663m) and drainage syste m (523m) in Sangkat Chaom Chau 2, Khan Por Sen Chey KH-MOI-110174-CW-CDD / C onstruction of reinforcement concrete: 1- Road(124m), 2- Component 1: Improving Liv Pending Im Community Drive 2019-10-0 Road (137m). 3- Road (117m IDA / 59600 elihoods for Rural Poor and Post Open - National 30,250.00 0.00 plementatio 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 n Development 9 ). 4-Installation of Sola street Vulnerable Households n lighting and poles (117m), a nd (139m ) in Sangkat Chbar Ampov Ti Pir, Khan Chbar Am pov Page 1 KH-MOI-110155-CW-CDD / C onstruction of reinforcement concrete: 1- Road (99m) ,1- Road(101m), 2-Road(60m), 3 Component 1: Improving Liv Pending Im Community Drive 2019-12-2 -Drainage system:(9m), 4-Ins IDA / 59600 elihoods for Rural Poor and Post Open - National 28,703.49 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 tallation of Sola street lightin Vulnerable Households n g and poles (120m),(439m),( 439m) and (98m) in Sangkat Chrang Chamreas Ti Muoy,K han Russey Keo KH-MOI-110151-CW-CDD / C onstruction: 1-Reinforcement concrete road (340m) and dr ainage system:(448m), 2-Ro Component 1: Improving Liv Pending Im Community Drive 2019-12-2 ad (L130m) and drainage sys IDA / 59600 elihoods for Rural Poor and Post Open - National 171,670.08 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 tem (130m), 3-Road (120m) Vulnerable Households n and drainage system:(250m) , 4- Road (238m) and draina ge system (238m) in Sangka t Trapeang Krasang, Khan Po r Sen Chey KH-MOI-110147-CW-CDD / C onstruction:1-Reinforcement concrete road, Drainage (L17 1m),Installation of Sola stree Component 1: Improving Liv Pending Im Community Drive 2019-12-2 t lighting and poles(171m), 2 IDA / 59600 elihoods for Rural Poor and Post Open - National 43,476.23 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 -Reinforcement concrete roa Vulnerable Households n d(147m),drainage(48m), Inst allation of Sola street lightin g and poles (147m) in Sangk at Khmuonh, Khan Saen Sok h KH-MOI-110144-CW-CDD / C onstruction: 1-Reinforcement concrete road:(L262m, w 2.6 m, T 0.12m) ,Drainage syste Component 1: Improving Liv Pending Im Community Drive 2019-12-2 m:(262m,0.6m), 2- Installatio IDA / 59600 elihoods for Rural Poor and Post Open - National 71,818.97 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 n:(18 Sola street lighting and Vulnerable Households n poles for 262m) and 3-Concr ete bridge: (L206m, width1.5 0m, T0.07m) in Sangkat Srah Chak, Khan Daun Penh KH-MOI-110162-CW-CDD / C onstruction of reinforcement concrete:1- road:(L102m, wi Component 1: Improving Liv Pending Im dth 2.5m, thickness 0.12m) a Community Drive 2019-12-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 37,878.83 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 nd drainage system:(114m). n Development 5 Vulnerable Households n 2- road:(169m, width 3.5m, t hickness 0.15m) and drainag e system:(169m) in Sangkat Boeng Kak 1, Khan Tuol Kork KH-MOI-110173-CW-CDD / C onstruction of reinforcement concrete: 1- Road(110m, wid Component 1: Improving Liv Pending Im Community Drive 2019-12-2 th 4m, thickness 0.15m), 2- IDA / 59600 elihoods for Rural Poor and Post Open - National 30,281.06 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 Road(100m),2-Installation of Vulnerable Households n Sola street lighting and poles (250m) in Khtor,Sangkat Pre ak Leap, Khan Chroy Changv ar KH-MOI-110168-CW-CDD / C onstruction of reinforcement concrete:1- road(158m) and drainage (138m), 2-Road an Component 1: Improving Liv Pending Im Community Drive 2019-10-0 d drainage system (77m),3- r IDA / 59600 elihoods for Rural Poor and Post Open - National 73,334.73 0.00 plementatio 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 n Development 9 oad(261m) and drainage (20 Vulnerable Households n 7m),4-Installation of Sola str eet lighting and poles(158m) , (77m)and (261m) in Sangk at Chak Angrae Leu, Khan M ean Chey KH-MOI-140916-CW-CDD / R Component 1: Improving Liv Pending Im epair Dike 78 for Sangkat Kr Community Drive 2020-02-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 30,005.00 0.00 plementatio 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 abei Riel, Siem Reap Municip n Development 7 Vulnerable Households n ality ( Size 2.95Km length, 4. 00m width, 2.00m height) KH-MOI-140917-CW-CDD / C onstruction of Reinforced Co Component 1: Improving Liv Pending Im Community Drive 2020-02-2 ncrete Road for Kampong Khl IDA / 59600 elihoods for Rural Poor and Post Open - National 30,248.00 0.00 plementatio 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 n Development 7 eang Commune, Sotr Nikom Vulnerable Households n District ( Size 0.25Km length, 5.00m width, 0.15m thick) KH-MOI-140918-CW-CDD / U pgrade Earth Road to Laterit e Pavement for Sangkat Cho Component 1: Improving Liv Pending Im ng Khneas, Siem Reap Munic Community Drive 2020-02-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 27,191.00 0.00 plementatio 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 ipality ( Size 0.80Km length, n Development 7 Vulnerable Households n 4.00m width, 0.15m thick), i ncluding 1 unit of culvert con struction, 0.60m Diameter, 1 6.00m length. KH-MOI-146743-CW-CDD / D igging Community Pond one place (size 100mx75mx6.00 m) including fence constructi Component 1: Improving Liv Pending Im Community Drive 2020-04-1 on and Earth Dam with lateri IDA / 59600 elihoods for Rural Poor and Post Open - National 45,730.00 0.00 plementatio 2019-12-06 2019-12-13 2019-12-27 2020-01-03 2020-01-17 n Development 6 te pavement 4.00 meter wid Vulnerable Households n th, 2.00 meter heigh surroun ding the pond and 2 reinforc ed concrete stairs, access lat erite road 170m length, 4.00 m wid KH-MOI-146745-CW-CDD / U nlined Earth Canal Rehabilita tion with 1500m Length, 2m bed, 1.60m Depth including t Component 1: Improving Liv Pending Im Community Drive 2020-04-1 he Construction of Cented Ca IDA / 59600 elihoods for Rural Poor and Post Open - National 41,288.00 0.00 plementatio 2019-12-06 2019-12-13 2019-12-27 2020-01-03 2020-01-17 n Development 6 useway with pipe 0.80m dia Vulnerable Households n meter, 8m length, 4m width 5 places and Construction of Trapezoidal Section Lined Co ncrete canal with 16m length ,2 KH-MOI-162028-CW-CDD / E arth Road Repair and Laterit e Pavement 2 lines for Sangk at Svay Dangkum, Siem Rea Component 1: Improving Liv Pending Im Community Drive 2020-07-2 p Municipality (For line 1: 0.8 IDA / 59600 elihoods for Rural Poor and Post Open - National 22,511.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 7 Km length, 4.00 m width, 0 Vulnerable Households n .15m thick including 1 unit of single culvert construction, 1 .00m Diameter, 7.00m lengt h ( For line 2: 0.60 Km le KH-MOI-162399-CW-CDD / R einforced Concrete Road for Component 1: Improving Liv Pending Im Community Drive 2020-07-2 Kampong Thkov Commune, IDA / 59600 elihoods for Rural Poor and Post Open - National 29,950.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 Kralanh District ( 0.26 Km le Vulnerable Households n ngth,4.50m Width, 0.15 thick ). KH-MOI-162400-CW-CDD / E arth Road Repair and Laterit e Pavement for Svay Leu Co Component 1: Improving Liv Pending Im Community Drive 2020-07-2 mmune, Svay Leu District ( 3 IDA / 59600 elihoods for Rural Poor and Post Open - National 55,881.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 .70 Km length, 4.00 m width, Vulnerable Households n 0.15m thick), including 2 unit s of double culvert constructi on, 1.00 m Diameter, 6.00 m length. KH-MOI-162401-CW-CDD / E arth Road Repair and Laterit e Pavement for Ta Siem Com Component 1: Improving Liv Pending Im Community Drive 2020-07-2 mune, Svay Leu District ( 2.3 IDA / 59600 elihoods for Rural Poor and Post Open - National 35,980.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 35 Km length, 4.50 m width, Vulnerable Households n 0.15m thick), including 1 unit of single culvert construction , 1.00m Diameter, 6.00 m le ngth. KH-MOI-162402-CW-CDD / E arth Road Repair and Laterit e Pavement for Boeng Meale Component 1: Improving Liv Pending Im a Commune, Svay Leu Distri Community Drive 2020-07-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 44,027.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 ct ( 2.80 Km length, 5.00 m n Development 0 Vulnerable Households n width, 0.15m thick), includin g 2 units of single culvert co nstruction, 0.60m&0.80 Dia meter, 6.00 m length. KH-MOI-162403-CW-CDD / E arth Road Repair and Laterit e Pavement 3 lines for Peak Snaeng Commune, Angkor T Component 1: Improving Liv Pending Im Community Drive 2020-07-2 hom District ( For Line1: 1.95 IDA / 59600 elihoods for Rural Poor and Post Open - National 54,983.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 Km length, 4.00 m width, 0.1 Vulnerable Households n 5m thick including 2 units of single culvert construction, 1 .00 m Diameter, 5.00 m leng th & 1 unit of single culver Page 2 KH-MOI-162406-CW-CDD / E arth Road Repair and Laterit e Pavement 5 lines for Kamp Component 1: Improving Liv Pending Im Community Drive 2020-07-3 ong Kdei Commune, Chi krae IDA / 59600 elihoods for Rural Poor and Post Open - National 59,812.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 ng District, ( Total length 319 Vulnerable Households n 0m, 4.00m width, 0.15 thick i ncluding 1 unit of Double bo x culvert 2.00m heigh, 6.00 m length) KH-MOI-162407-CW-CDD / E arth Road Repair and Literat e Pavement 3 lines for Chi kr aeng Commune, Chi kraeng Component 1: Improving Liv Pending Im Community Drive 2020-07-3 District, ( Total length 1680 IDA / 59600 elihoods for Rural Poor and Post Open - National 39,802.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 m, 4.00m, 0.15 thick width in Vulnerable Households n cluding 2 units of single pipe culvert 0.60m diameter, 6.00 m length and 3 units of singl e pipe culvert 1.00m diam KH-MOI-162408-CW-CDD / R einforced Concrete Bridge Co Component 1: Improving Liv Pending Im Community Drive 2020-07-3 nstruction for Tram Sasar Co IDA / 59600 elihoods for Rural Poor and Post Open - National 30,100.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 mmune, Srei Snam District ( Vulnerable Households n 4.00m Heigh, 11.00m length, 4.00m width). KH-MOI-162409-CW-CDD / E arth Road Repair and Laterit e Pavement for Mean Chey C Component 1: Improving Liv Pending Im Community Drive 2020-07-3 ommune, Brasat Bakong Dist IDA / 59600 elihoods for Rural Poor and Post Open - National 31,649.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 rict ( Length 1800m, 4.00m Vulnerable Households n width, 0.15 thick and 1 unit o f single box culvert with wate r gate, 2.50m heigh, 5.90m l ength ) KH-MOI-162410-CW-CDD / E arth Road Repair and Laterit e Pavement for Roluos Com mune, Brasat Bakong District Component 1: Improving Liv Pending Im Community Drive 2020-07-3 , ( Length 4625m, 4.00m wid IDA / 59600 elihoods for Rural Poor and Post Open - National 49,078.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 th, 0.15 thick including 1 unit Vulnerable Households n s of single pipe culvert 0.60 m diameter, 6.00m length an d 2 units of single pipe culve rt 0.80m diameter, 6.00m le n KH-MOI-162412-CW-CDD / E arth Road Repair and Laterit e Pavement 2 lines for Kantr Component 1: Improving Liv Pending Im Community Drive 2020-07-3 eang Commune, Brasat Bako IDA / 59600 elihoods for Rural Poor and Post Open - National 19,225.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 ng District, ( Total length 150 Vulnerable Households n 0m, 4.00m width, 0.15 thick i ncluding 1 unit of single pip e culvert 0.80m diameter, 5. 00m length) KH-MOI-162414-CW-CDD / E arth Road Repair and Laterit e Pavement for Ballangk Co Component 1: Improving Liv Pending Im Community Drive 2020-07-3 mmune, Brasat Bakong Distri IDA / 59600 elihoods for Rural Poor and Post Open - National 20,670.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 ct, ( Length 985m, 4.00m wi Vulnerable Households n dth, 0.15 thick including 3 un its of single pipe culvert 0.6 0m diameter, 5.00m length) KH-MOI-162415-CW-CDD / E arth Road Repair and Laterit Component 1: Improving Liv Pending Im Community Drive 2020-07-3 e Pavement for Dan Run Co IDA / 59600 elihoods for Rural Poor and Post Open - National 26,913.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 mmune, Sotr Nikom District, Vulnerable Households n ( Length 2600m, 4.00m widt h, 0.15m thick ) KH-MOI-162416-CW-CDD / L aterite Road Construction for Prey Chruk Commune, Pouk Component 1: Improving Liv Pending Im District ( 3614 m length, 4.0 Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and Post Open - National 62,129.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 0m width, 0.15 thick includin n Development 0 Vulnerable Households n g 5 units of single pipe culve rt, 0.60m Diameter, length 6. 00m and 1 unit of single pipe culvert 0.80m diameter, leng th 6.00m ) KH-MOI-162417-CW-CDD / L aterite Road Construction for Doun Kaev Commune, Pouk Component 1: Improving Liv Pending Im District ( 2500 m length, 4.0 Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and Post Open - National 49,293.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 0m width, 0.15 thick includin n Development 0 Vulnerable Households n g 1 unit of single pipe culvert ,0.80m Diameter length 6.00 m and 1 unit of single pipe c ulvert 1.00m diameter, lengt h 6.00m ) KH-MOI-162418-CW-CDD / D igging Community Pond 2 pl aces for Kdei Run Commune, Component 1: Improving Liv Pending Im Community Drive 2020-07-3 Pouk District including fence IDA / 59600 elihoods for Rural Poor and Post Open - National 34,396.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 construction surrounding the Vulnerable Households n pond and 2 doors ( Size: 60mx33mx5m and 6 0mx24mx5m) KH-MOI-162419-CW-CDD / R einforced Concrete Road Con struction for Khnat Commun Component 1: Improving Liv Pending Im e, Pouk District ( 400m lengt Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and Post Open - National 57,625.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 h, 5.00m width, 0.15m thick i n Development 0 Vulnerable Households n ncluding 1 unit of single pipe culvert 0.60 diameter, 6.00m length and 1 unit of single pi pe culvert 0.80 diameter, 6.0 0m length KH-MOI-162420-CW-CDD / L aterite Road Construction for Component 1: Improving Liv Pending Im Sasar Sdam Commune, Pouk Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and Post Open - National 39,060.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 District ( 1500m length, 5.00 n Development 0 Vulnerable Households n m width, 0.15 thick including 2 units of single pipe culvert, 0.80m Diameter length 6.00 m) KH-MOI-162421-CW-CDD / L aterite Road Construction for Component 1: Improving Liv Pending Im Lvea Commune, Pouk Distric Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and Post Open - National 38,419.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 t ( 2200m length, 4.00m widt n Development 0 Vulnerable Households n h, 0.15 thick including 3 unit s of single pipe culvert,0.60 m Diameter length 6.00m) KH-MOI-162422-CW-CDD / U nlined Earth Canal Rehabilita Component 1: Improving Liv Pending Im tion for Spean Tnoat Commu Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and Post Open - National 33,487.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 ne, Chi Kraeng District ( 210 n Development 0 Vulnerable Households n 0m length, 1.20m bed, 1.20 Depth including of 6 units of single pipe culvert with wate r gate) KH-MOI-162423-CW-CDD / R einforced Concrete Bridge up grade in Phum 2, Sangkat Sr ah Chak, Khan Daun Pend ( T Component 2: Improving Liv Pending Im Community Drive 2020-08-0 otal length 73m, 1.20m widt IDA / 59600 elihoods for Urban Poor and Post Open - National 65,309.00 0.00 plementatio 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 n Development 9 h, 1.50 heigh, 0.07m thickne Vulnerable Households n ss), Reinforced Concrete Roa d in Phum 20, Sangkat Srah Chak, Khan Daun Penh ( Tota l length 60m, 2.40m widt, 0. 15m thi KH-MOI-162424-CW-CDD / R einforced Concrete Road in P hum 3, Sangkat Boeung Kak 1, Khan Toul Kork( Total leng Component 2: Improving Liv Pending Im Community Drive 2020-08-0 th 46m, 2m width, 0.15m thi IDA / 59600 elihoods for Urban Poor and Post Open - National 9,333.00 0.00 plementatio 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 n Development 9 ckness) and Drainage syste Vulnerable Households n m (Total length 34m, 0.6m di ameter). Reinforced concrete road in Phum 4, Sangkat Boe ung Kak 1, Khan Toul kork(To tal le KH-MOI-162425-CW-CDD / R einforced Concrete Road in T alei Village, Sangkat Dangka o, Khan Dangkao( Total lengt Component 2: Improving Liv Pending Im Community Drive 2020-08-1 h 149m, 3.5m width, 0.15m t IDA / 59600 elihoods for Urban Poor and Post Open - National 50,729.00 0.00 plementatio 2020-04-06 2020-04-13 2020-04-27 2020-05-04 2020-05-18 n Development 6 hickness) and Drainage syste Vulnerable Households n m (Total length 67m, 0.6m di ameter). Reinforced concrete road in Khva Village, Sangkat Dangkao, Khan Dangkao(Tot al KH-MOI-162426-CW-CDD / R einforced Concrete Road in T Component 2: Improving Liv Pending Im Community Drive 2020-08-1 oap Boss Village, Sangkat Pr IDA / 59600 elihoods for Urban Poor and Post Open - National 40,542.00 0.00 plementatio 2020-04-06 2020-04-13 2020-04-27 2020-05-04 2020-05-18 n Development 6 ey Veang, Khan Dangkao( To Vulnerable Households n tal length 310m, 4m width, 0 .15m thickness) Page 3 KH-MOI-162428-CW-CDD / R einforced Concrete Road in P reak Leap Village, Sangkat Pr Component 2: Improving Liv Pending Im Community Drive 2020-08-0 eak Leap, Khan Chroy Chang IDA / 59600 elihoods for Urban Poor and Post Open - National 55,323.00 0.00 plementatio 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 n Development 9 var( Total length 287m, 3.5m Vulnerable Households n width, 0.15m thickness) and drainage system (Total lengt h 287m, 0.6m diameter) KH-MOI-162429-CW-CDD / R einforced Concrete Road in S en Sok Ty Mouy Village, San Component 2: Improving Liv Pending Im Community Drive 2020-08-1 gkat Khmounh, Khan Sen So IDA / 59600 elihoods for Urban Poor and Post Open - National 111,552.00 0.00 plementatio 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 n Development 3 k( Total length 547m, 4m wi Vulnerable Households n dth, 0.15m thickness) and dr ainage system (Total length 550m, 0.6m diameter) KH-MOI-162430-CW-CDD / R einforced Concrete Road in S amaki 5 Village, Sangkat Tra peang Krasang, Khan Pou Se Component 2: Improving Liv Pending Im Community Drive 2020-08-1 n Chey( Total length 196m, 6 IDA / 59600 elihoods for Urban Poor and Post Open - National 64,039.00 0.00 plementatio 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 n Development 3 m width, 0.15m thickness) R Vulnerable Households n einforced Concrete Road in S amaki 6 Village, Sangkat Tra peang Krasang, Khan Pou Se n Chey( Total length 121m, 4 m & 5m KH-MOI-162432-CW-CDD / R einforced Concrete Road in C hrey Koang Village, Sangkat Choam Chau 2, Khan Pou Se Component 2: Improving Liv Pending Im Community Drive 2020-08-1 n Chey( Total length 287m, 5 IDA / 59600 elihoods for Urban Poor and Post Open - National 177,610.00 0.00 plementatio 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 n Development 3 m width, 0.15m thickness) a Vulnerable Households n nd Drainage System(Total Le ngth 287, 0.6m diameter) , R einforced Concrete Road in P rey Lvea Village, Sangkat Ch oam Ch KH-MOI-162433-CW-CDD / R einforced Concrete Road in A ndong 1 & Andong 2 Villages Component 2: Improving Liv Pending Im Community Drive 2020-08-1 , Sangkat Kork Roka, Khan P IDA / 59600 elihoods for Urban Poor and Post Open - National 42,245.00 0.00 plementatio 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 n Development 3 eeak Phnov( Total length 211 Vulnerable Households n m, 4m width, 0.15m thicknes s) and Drainage System(Tot al Length 211m, 0.6m diame ter) KH-MOI-162435-CW-CDD / R einforced Concrete Road in D Component 2: Improving Liv Pending Im aeum Sleng Village, Sangkat Community Drive 2020-08-2 IDA / 59600 elihoods for Urban Poor and Post Open - National 28,928.00 0.00 plementatio 2020-04-10 2020-04-17 2020-05-01 2020-05-08 2020-05-22 Chbar Ampov 2, Khan Chbar n Development 0 Vulnerable Households n Ampov ( Total length 234m, 3.4m width, 0.15m thickness ) KH-MOI-169345-CW-CDD / S olar LED Power Street lightin g in Phum 2, Sangkat Srah C hak, Khan Daun Pend ( Total Component 2: Improving Liv Pending Im Community Drive 2020-09-1 sets 22 sets), Solar LED Pow IDA / 59600 elihoods for Urban Poor and Post Open - National 13,469.00 0.00 plementatio 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 n Development 4 er Street lighting in Phum 2 Vulnerable Households n 2, Sangkat Srah Chak, Khan Daun Pend ( Total sets 11 se ts), Solar LED Power Street li ghting in Phum 24, Sangkat KH-MOI-169346-CW-CDD / S Component 2: Improving Liv Pending Im olar LED Power street lightin Community Drive 2020-09-1 IDA / 59600 elihoods for Urban Poor and Post Open - National 3,613.00 0.00 plementatio 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 g in Phum 8, Sangkat Boeun n Development 4 Vulnerable Households n g Kak 1, Khan Toul Kork( Tot al sets 11 sets) KH-MOI-169347-CW-CDD / S olar LED Power street lightin g in Khva Village, Sangkat D Component 2: Improving Liv Pending Im Community Drive 2020-09-1 angkao, Khan Dangkao( Tota IDA / 59600 elihoods for Urban Poor and Post Open - National 15,774.00 0.00 plementatio 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 n Development 4 l sets 26 sets), Solar LED Po Vulnerable Households n wer street lighting in Mol Vill age, Sangkat Dangkao, Khan Dangkao(Total sets 23 sets) KH-MOI-169348-CW-CDD / S olar LED Power street lightin Component 2: Improving Liv Pending Im Community Drive 2020-09-1 g in Phum 3, Sangkat Chrang IDA / 59600 elihoods for Urban Poor and Post Open - National 5,495.00 0.00 plementatio 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 n Development 4 Chamreas Ty Mouy, Khan Ru Vulnerable Households n ssei Kao( Total sets 17 sets) KH-MOI-169349-CW-CDD / S Component 2: Improving Liv Pending Im olar LED Power street lightin Community Drive 2020-09-1 IDA / 59600 elihoods for Urban Poor and Post Open - National 9,674.00 0.00 plementatio 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 g in Khtor Village, Sangkat Pr n Development 5 Vulnerable Households n eak Leap, Khan Chroy Chang Var( Total sets 30 sets) KH-MOI-169350-CW-CDD / S olar LED Power street lightin Component 2: Improving Liv Pending Im Community Drive 2020-09-1 g in Svay Ckek Thmei Village IDA / 59600 elihoods for Urban Poor and Post Open - National 15,064.00 0.00 plementatio 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 n Development 5 , Dandong 1&2 Villages, San Vulnerable Households n gkat Kork Roka, Khan Preak Phnov( Total sets 47 sets) KH-MOI-169351-CW-CDD / S olar LED Power street lightin Component 2: Improving Liv Pending Im g in Daeum Sleng, Daeum Sl Community Drive 2020-09-1 IDA / 59600 elihoods for Urban Poor and Post Open - National 21,978.00 0.00 plementatio 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 eng I, Daeum Chan I Villages n Development 5 Vulnerable Households n , Sangkat Chbar Ampov 2, Kh an Chbar Ampov( Total sets 69 sets) KH-MOI-191867-CW-CDD / R einforced Concrete Road Con Component 1: Improving Liv Pending Im struction for Khnang Phnum Community Drive 2020-12-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 20,181.00 0.00 plementatio 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 Commune,Svay Leu District, n Development 6 Vulnerable Households n Siem Reap Province ( Length : 0.18 Km, Width 5.00 m, 0.1 5m thick) KH-MOI-191856-CW-CDD / E arth Road Repair and Laterit e Pavement for Anlong Samn Component 1: Improving Liv Pending Im Community Drive 2021-08-2 ar, Siem Reap Province ( Len IDA / 59600 elihoods for Rural Poor and Post Open - National 27,338.00 0.00 plementatio 2021-04-15 2021-04-22 2021-05-06 2021-05-13 2021-05-27 n Development 5 gth 1.80 Km, Width 4.00 m, Vulnerable Households n 0.15m thick including 2 units of single culvert construction , Ø0.80m, length 6.00m) KH-MOI-191857-CW-CDD / E arth Road Repair and Laterit e Pavement two lines for San gkat Krabei Riel, Siem Reap Component 1: Improving Liv Pending Im Community Drive 2021-07-2 Municipality, Siem Reap Prov IDA / 59600 elihoods for Rural Poor and Post Open - National 45,396.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 ince ( For line1: Length: 1.86 Vulnerable Households n 8 Km, Width 5.00m, 0.15 thic k including 2 units of single c ulverts, Ø 0.80m, length 7.00 m and Ø1.00m, length 7.0 KH-MOI-191859-CW-CDD / E arth Road Repair and Laterit e Pavement for Sangkat Tue k Vil ,Siem Reap Municipality Component 1: Improving Liv Pending Im Community Drive 2021-07-2 , Siem Reap Province ( Lengt IDA / 59600 elihoods for Rural Poor and Post Open - National 64,903.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 h: 2.325 Km , Width: 5.00 m, Vulnerable Households n 0.15m thick), including 5 unit s of single culvert constructio n, 1 Unit Ø1.00 m, length 6.0 0 m, 4 units Ø1.00 m, l KH-MOI-191860-CW-CDD / R einforced Concrete Road Con Component 1: Improving Liv Pending Im struction for Kampong Khlea Community Drive 2021-06-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 33,774.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 ng Commune, Sotr Nikom Di n Development 5 Vulnerable Households n strict, Siem Reap Province ( L ength 0.25 Km, Width 5.00 m, 0.15m thick) KH-MOI-162413-CW-CDD / E arth Road Repair and Laterit e Pavement for Bakong Com Component 1: Improving Liv Pending Im Community Drive 2021-07-2 mune, Brasat Bakong District IDA / 59600 elihoods for Rural Poor and Post Open - National 42,032.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 , ( Length 1.60 Km, 4.00m wi Vulnerable Households n dth, 0.15 thick including 3 un its of double pipe culvert 1.0 0m diameter, 5.00m length) KH-MOI-191861-CW-CDD / R einforced Concrete Road Con Component 1: Improving Liv Pending Im struction for Kampong Phluk Community Drive 2021-06-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 39,635.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Commune, Brasat Bakong Di n Development 5 Vulnerable Households n strict, Siem Reap Province ( L ength 0.23 Km, Width 6.00 m, 0.15m thick) Page 4 KH-MOI-191862-CW-CDD / E arth Road Repair and Laterit e Pavement 2 lines for Trape Component 1: Improving Liv Pending Im ang Thum Commune ,Brasat Community Drive 2021-07-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 36,380.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Bakong District, Siem Reap P n Development 5 Vulnerable Households n rovince ( For line1: Length 0 .50 Km, Width 4.00m, 0.15 t hick , For line 2: Length 3.05 Km, Width 4.00m, 0.15 thick) KH-MOI-191863-CW-CDD / L aterite Road Construction 2 li nes for Reul Commune ,Pouk Component 1: Improving Liv Pending Im Community Drive 2021-07-2 District, Siem Reap Province IDA / 59600 elihoods for Rural Poor and Post Open - National 31,787.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 (For line Length 2.09 Km, Wi Vulnerable Households n dth 4.00m, 0.15 thick , For li ne 2: Length 0.75 Km, Width 4.00m, 0.15 thick) KH-MOI-191865-CW-CDD / D rilled wells Construction with Component 1: Improving Liv Pending Im Community Drive 2021-06-2 Afridev Pump for Yeang Com IDA / 59600 elihoods for Rural Poor and Post Open - National 11,429.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 mune ,Pouk District, Siem Re Vulnerable Households n ap Province for 5 places KH-MOI-191864-CW-CDD / L aterite Road Construction 2 li nes for Trei Nhoar Commune ,Pouk District, Siem Reap Pro Component 1: Improving Liv Pending Im Community Drive 2021-07-2 vince ( For line 1: Length 1.2 IDA / 59600 elihoods for Rural Poor and Post Open - National 35,805.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 0 Km, Width 4.00m, 0.15 thic Vulnerable Households n k , For line 2: Length 1.45 K m, Width 4.00m, 0.15 thick i ncluding 1 unit of double cul vert Ø0.60m, length 6.0 KH-MOI-191866-CW-CDD / D rilled wells with solar Pump a Component 1: Improving Liv Pending Im nd Water Distributed Connec Community Drive 2021-07-2 IDA / 59600 elihoods for Rural Poor and Post Open - National 47,530.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 tion 4 places for Chrouy Nea n Development 5 Vulnerable Households n ng NguonCommune ,Srei Sna m District, Siem Reap Provin ce KH-MOI-162411-CW-CDD / C onstruction of Community Sh elter for Ampil Commune, Br asat Bakong District ( Size: 8 Component 1: Improving Liv Pending Im Community Drive 2021-09-2 mx12m, with steel frame, rei IDA / 59600 elihoods for Rural Poor and Post Open - National 15,377.00 0.00 plementatio 2021-05-14 2021-05-21 2021-06-04 2021-06-11 2021-06-25 n Development 3 nforced concrete slab 0.10m Vulnerable Households n thick and zinc roof ) includin g one latrine construction wit h 4 separated rooms and inst allation of one unit of wa KH-MOI-251230-CW-RFQ / L aterite Road Construction for Mukh Paen Commune, Pouk Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-1 District, Siem Reap Province IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 26,739.00 0.00 plementatio 2021-09-11 2021-10-16 tions Envelope 4 ( 2 lines, for line1: Length= 1 Vulnerable Households SPD) n .20 Km, Width= 5.00m, Thick =0.15m , For line 2: Length= 0.85 Km, Width= 4.00m, Thi ck=0.15m) KH-MOI-251231-CW-RFQ / L aterite Road Construction for Samraong Yea Commune, Po Component 1: Improving Liv Request for Quot Pending Im uk District, Siem Reap Provin Request for Quota Single Stage - One 2022-01-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 36,214.00 0.00 plementatio 2021-09-11 2021-10-16 ce (04 Lines, Total Length= tions Envelope 4 Vulnerable Households SPD) n 3.16 Km, Width= 4.00m, Thi ck=0.15m including 1 unit of double culvert construction, Ø0.60 m, length 6.00m) KH-MOI-253012-CW-RFQ / E arth Road Repair and Laterit e Pavement for Kandeak Co Component 1: Improving Liv Request for Quot Pending Im mmune, Brasat Bakong Distri Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 32,966.00 0.00 plementatio 2021-09-22 2021-10-27 ct, Siem Reap Province ( 5 lin tions Envelope 5 Vulnerable Households SPD) n es, Total Length=2.77 Km, W idth= 4.00 m, Thick=0.15m including 1 unit of single culv ert construction, Ø1.00m, len gth 6.00m KH-MOI-253013-CW-RFQ / L aterite Road Construction for Kaev Poar Commune, Pouk D istrict, Siem Reap Province ( Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 2 lines, For line1: Length= 0. IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 30,147.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 53 Km, Width= 4.00m, Thick Vulnerable Households SPD) n =0.15 m , For line 2: Length 1.15 Km, Width: 4.00m, 0.15 thick including 4 units of sing le culvert construction, KH-MOI-253014-CW-RFQ / E arth Road Repair and Laterit e Pavement for Svay Chek C Component 1: Improving Liv Request for Quot Pending Im ommune, Angkor Thum Distri Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 33,360.00 0.00 plementatio 2021-09-22 2021-10-27 ct, Siem Reap Province (Leng tions Envelope 5 Vulnerable Households SPD) n th= 2.10 Km, Width= 5.00 m , Thick=0.15m including 1 un it of single culvert constructi on, Ø1.00m, length= 7.00m) KH-MOI-253015-CW-RFQ / E arth Road Repair and Laterit e Pavement for Leang Dai Co mmune, Angkor Thum Distric Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 t, Siem Reap Province ( For l IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 37,682.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 ine one, Length= 0.922 Km, Vulnerable Households SPD) n Width= 4.00 m, Thick=0.15 m including 3 units of single culvert construction, Ø0.80m , length= 6.00m, 1 units of s ing KH-MOI-253016-CW-RFQ / E arth Road Repair and Laterit e Pavement for Sangkat Sva y Dangkum , Siem Reap Mun Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 icipality, Siem Reap Province IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 61,110.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 (Total Length= 1.799 Km, Wi Vulnerable Households SPD) n dth= 5.00 m, Thick=0.15m i ncluding 1 unit of single culv ert construction, Ø1.00m, len gth= 7.00m and 1 unit of do uble c KH-MOI-253017-CW-RFQ / E arth Road Repair and Laterit Component 1: Improving Liv Request for Quot Pending Im e Pavement for Sangkat Krab Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 9,885.00 0.00 plementatio 2021-09-22 2021-10-27 ei Riel , Siem Reap Municipali tions Envelope 5 Vulnerable Households SPD) n ty, Siem Reap Province ( Tot al Length= 0.315 Km, Width = 5.00 m, Thick=0.15m ) KH-MOI-253018-CW-RFQ / E arth Road Repair and Laterit e Pavement for Sangkat Tue Component 1: Improving Liv Request for Quot Pending Im k Vil , Siem Reap Municipalit Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 20,757.00 0.00 plementatio 2021-09-22 2021-10-27 y, Siem Reap Province ( Total tions Envelope 5 Vulnerable Households SPD) n Length= 0.54 Km, Width= 5. 00 m, Thick=0.15m includin g 1 unit of single culvert con struction, Ø1.00m, length= 7 .00m ) KH-MOI-253019-CW-RFQ / E arth Road Repair and Laterit e Pavement for Bakong Com mune , Brasat Bakong Distric Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 t, Siem Reap Province ( Total IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 24,131.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 Length= 1.015 Km, Width= Vulnerable Households SPD) n 4.00 m, Thick=0.15m includi ng 6 unist of single culvert c onstruction, Ø0.60m, Length = 5.00m, 1 unist of single cul ver KH-MOI-253020-CW-RFQ / E arth Road Repair and Laterit Component 1: Improving Liv Request for Quot Pending Im e Pavement for Kantreang C Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 37,561.00 0.00 plementatio 2021-09-22 2021-10-27 ommune , Brasat Bakong Dis tions Envelope 5 Vulnerable Households SPD) n trict, Siem Reap Province ( T otal Length= 3.695 Km, Widt h= 4.00 m, Thick=0.15m) KH-MOI-253021-CW-RFQ / R einforced Concrete Road Con Component 1: Improving Liv Request for Quot Pending Im struction for Kandeak Comm Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 32,469.00 0.00 plementatio 2021-09-22 2021-10-27 une, Brasat Bakong District, tions Envelope 5 Vulnerable Households SPD) n Siem Reap Province ( Total L ength= 0.265 Km, Width= 4. 00 m, Thick=0.15m) Page 5 KH-MOI-253022-CW-RFQ / E arth Road Repair and Laterit Component 1: Improving Liv Request for Quot Pending Im e Pavement for Roluos Com Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 37,913.00 0.00 plementatio 2021-09-22 2021-10-27 mune, Brasat Bakong District tions Envelope 5 Vulnerable Households SPD) n , Siem Reap Province ( Total Length= 3.892 Km, Width= 4.00 m, Thick=0.15m) KH-MOI-253023-CW-RFQ / D rilled Wells with Pump 8 plac Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 es for Sasar Sdam Commune IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 16,174.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 , Pouk District, Siem Reap Pr Vulnerable Households SPD) n ovince (Depth=5m, Ø150mm ) KH-MOI-253024-CW-RFQ / D rilled Wells with Pump 3 plac Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 es for Doun Kaev Commune, IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 6,065.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 Pouk District, Siem Reap Pro Vulnerable Households SPD) n vince (Depth=5m, Ø150mm) KH-MOI-253025-CW-RFQ / E arth Road Repair and Laterit e Pavement for Khnat Com Component 1: Improving Liv Request for Quot Pending Im mune, Pouk District, Siem Re Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 27,381.00 0.00 plementatio 2021-09-22 2021-10-27 ap Province ( Total Length= tions Envelope 5 Vulnerable Households SPD) n 1.617 Km, Width= 4.00 m, T hick=0.15m including 1 singl e culvert construction, Ø0.60 m, length= 6.00m ) KH-MOI-253026-CW-RFQ / E arth Road Repair and Laterit e Pavement for Lvea Comm Component 1: Improving Liv Request for Quot Pending Im une, Pouk District, Siem Rea Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 46,633.00 0.00 plementatio 2021-09-22 2021-10-27 p Province ( Total Length= 2. tions Envelope 5 Vulnerable Households SPD) n 225 Km, Width= 4.00 m, Thi ck=0.15m including 3 places of double culvert constructio n, Ø1.00m, length= 6.00m ) KH-MOI-253027-CW-RFQ / D rilled Wells with Pump 21 pla Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 ces for Mukh Paen Commune IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 42,456.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 , Pouk District, Siem Reap Pr Vulnerable Households SPD) n ovince, (Depth=5m, Ø150m m) KH-MOI-253028-CW-RFQ / D rilled Wells with Pump 11 pla Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 ces for Prey Chruk Commune IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 22,239.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 , Pouk District, Siem Reap Pr Vulnerable Households SPD) n ovince, (Depth=5m, Ø150m m) KH-MOI-253029-CW-RFQ / E arth Road Repair and Laterit e Pavement for Reul Commu Component 1: Improving Liv Request for Quot Pending Im ne, Pouk District, Siem Reap Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 47,248.00 0.00 plementatio 2021-09-22 2021-10-27 Province ( Total Length= 1.6 tions Envelope 5 Vulnerable Households SPD) n 0 Km, Width= 4.00 m, Thick =0.15m including 4 places of single culvert construction, Ø 0.80m, length= 6.00m ) KH-MOI-253030-CW-RFQ / E arth Road Repair and Laterit e Pavement for Samraong Ye Component 1: Improving Liv Request for Quot Pending Im a Commune, Pouk District, Si Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 45,144.00 0.00 plementatio 2021-09-22 2021-10-27 em Reap Province ( Total Len tions Envelope 5 Vulnerable Households SPD) n gth= 2.10 Km, Width= 4.00 m, Thick=0.15m including 4 places of single culvert const ruction, Ø0.60m, length= 6.0 0m ) KH-MOI-253031-CW-RFQ / E arth Road Repair and Laterit e Pavement for Chob Ta Trav Commune, Angkor Thum Dis Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 trict, Siem Reap Province ( T IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 41,040.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 otal Length= 1.772 Km, Widt Vulnerable Households SPD) n h= 4.00 m, Thick=0.15m incl uding 2 places of single culv ert construction, Ø1.00m, len gth= 6.00m and 1double cul vert KH-MOI-253032-CW-RFQ / W Component 1: Improving Liv Request for Quot Pending Im ater gate Construction 2 plac Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 45,000.00 0.00 plementatio 2021-09-22 2021-10-27 es for Chob Ta Trav Commun tions Envelope 5 Vulnerable Households SPD) n e, Angkor Thum District, Sie m Reap Provincial KH-MOI-253033-CW-RFQ / E arth Road Repair and Laterit e Pavement for Leang Dai Co Component 1: Improving Liv Request for Quot Pending Im mmune, Angkor Thum Distric Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 22,163.00 0.00 plementatio 2021-09-22 2021-10-27 t, Siem Reap Province ( Total tions Envelope 5 Vulnerable Households SPD) n Length= 0.974Km, Width= 4 .00 m, Thick=0.15m includin g 3 places of single culvert c onstruction, Ø1.00m, length = 5.00m) KH-MOI-253034-CW-RFQ / E arth Road Repair and Laterit e Pavement for Peak Snaeng Commune, Angkor Thum Dis Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 trict, Siem Reap Province ( T IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 35,005.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 otal Length= 0.98 Km, Width Vulnerable Households SPD) n = 4.00 m, Thick=0.15m inclu ding 1 place of single culvert construction, Ø1.00m, length = 6.00m, 1triple culvert KH-MOI-253035-CW-RFQ / E arth Road Repair and Laterit e Pavement for Svay Chek C Component 1: Improving Liv Request for Quot Pending Im ommune, Angkor Thum Distri Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 24,196.00 0.00 plementatio 2021-09-22 2021-10-27 ct, Siem Reap Province ( Tot tions Envelope 5 Vulnerable Households SPD) n al Length= 0.943 Km, Width = 4.00 m, Thick=0.15m inclu ding 1 place of single culvert construction, Ø1.00m, length = 7.00m) KH-MOI-253036-CW-RFQ / E arth Road Repair and Laterit e Pavement for Boeng Meale Component 1: Improving Liv Request for Quot Pending Im a Commune, Svay Leu Distri Request for Quota Single Stage - One 2022-01-2 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 23,729.00 0.00 plementatio 2021-09-22 2021-10-27 ct, Siem Reap Province ( Tot tions Envelope 5 Vulnerable Households SPD) n al Length= 1.15 Km, Width= 4.00 m, Thick=0.15m includi ng 2 places of single culvert construction, Ø1.00m, length = 6.00m) KH-MOI-253037-CW-RFQ / E arth Road Repair and Laterit e Pavement for Svay Leu Co mmune, Svay Leu District, Si Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 em Reap Province ( Total Len IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 38,068.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 gth= 1.05 Km, Width= 5.00 Vulnerable Households SPD) n m, Thick=0.15m including 1 place of single culvert constr uction, Ø1.00m, length= 7.0 0m, 2 places of double culve rt con KH-MOI-253038-CW-RFQ / E arth Road Repair and Laterit e Pavement for Ta Siem Com mune, Svay Leu District, Sie Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-2 m Reap Province ( Total Leng IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 22,587.00 0.00 plementatio 2021-09-22 2021-10-27 tions Envelope 5 th= 0.771 Km, Width= 5.00 Vulnerable Households SPD) n m, Thick=0.15m including 1 single culvert , Ø0.80m, leng th= 6.00m, 1 single and dou ble culvert,Ø1.00m KH-MOI-253039-CW-RFQ / R einforced Concrete Road upg rade in Trapeang Krasang, K han Pou Sen Chey ( Total len Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-1 gth 275m, 4m width, 0.15m t IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 86,535.67 0.00 plementatio 2021-09-16 2021-10-21 tions Envelope 9 hickness) and Reinforced Co Vulnerable Households SPD) n ncrete Road in Sangkat Trap eang Krasang, Khan Pou Sen Chey ( Total length 178m, 4 m width, 1.50) with Drainage System KH-MOI-253040-CW-RFQ / R einforced Concrete Road in P hum Andong 1 & Phum Ando Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-1 ng 2, Sangkat Kork Roka, Kh IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 78,963.02 0.00 plementatio 2021-09-16 2021-10-21 tions Envelope 9 an Preak Phnov ( Total lengt Vulnerable Households SPD) n h 561m, 4m width, 0.15m thi ckness) and Drainage syste m (Total length 244m, 0.6m diameter). Page 6 KH-MOI-253041-CW-RFQ / R einforced Concrete Road in Sangkat Choam Chau 2, Kha n Pou Sen Chey (Total length Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-1 60m, 4.50m width, 0.15m thi IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 59,825.69 0.00 plementatio 2021-09-16 2021-10-21 tions Envelope 9 ckness, 89m, 4m width, 0.15 Vulnerable Households SPD) n m thickness, 223m, 3m lengt h, 0.15m thickness) and Drai nage System ( Total length 3 77m, 0.6m diameter) KH-MOI-253042-CW-RFQ / R einforced Concrete Road in Sangkat Prey Vaeng, Khan D angkao ( Total length 104m, Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-01-1 5m width, 0.15m thickness, IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 56,055.11 0.00 plementatio 2021-09-16 2021-10-21 tions Envelope 9 82m, 4m width, 0.15m thick Vulnerable Households SPD) n ness, 128m, 3m length, 0.15 m thickness) and Drainage S ystem ( Total length 190m, 0.6m diameter, 135m, 0.4m diameter). KH-MOI-259610-CW-RFQ / R einforced Concrete Road Con Component 1: Improving Liv Request for Quot Pending Im struction for Pou Treay Com Request for Quota Single Stage - One 2022-03-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 42,895.00 0.00 plementatio 2021-11-07 2021-12-12 mune ,Pouk District, Siem Re tions Envelope 2 Vulnerable Households SPD) n ap Province ( Total Length=0 .23 Km, Width= 5.00 m, Thic k=0.15m) KH-MOI-259611-CW-RFQ / C onstruction of ring concrete water storage system with m esh fence surrounding, steel Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-03-1 frame building with plastics z IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 27,159.00 0.00 plementatio 2021-11-07 2021-12-12 tions Envelope 2 inc roof , water pipe distribut Vulnerable Households SPD) n ed connection, and installati on of automatic solar pump 340W, for Khnang Phnum Co mmune, Svay Leu District KH-MOI-259612-CW-RFQ / C onstruction of livestock buildi Component 1: Improving Liv Request for Quot Pending Im ng and Chicken Incubator 2 p Request for Quota Single Stage - One 2022-04-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 16,422.00 0.00 plementatio 2021-12-06 2022-01-10 laces for Anlong Samnar Co tions Envelope 0 Vulnerable Households SPD) n mmune ,Chi Kraeng District, Siem Reap Province, (Size: 4 mx8m, 4mx8m) KH-MOI-259613-CW-RFQ / C onstruction of livestock buildi Component 1: Improving Liv Request for Quot Pending Im ng and Chicken Incubator 3 p Request for Quota Single Stage - One 2022-04-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 24,633.00 0.00 plementatio 2021-12-06 2022-01-10 laces for Kampong Kdei Com tions Envelope 0 Vulnerable Households SPD) n mune ,Chi Kraeng District, Si em Reap Province, (Size: 5m x8m) KH-MOI-259614-CW-RFQ / C onstruction of livestock buildi Component 1: Improving Liv Request for Quot Pending Im ng and Chicken Incubator 1 p Request for Quota Single Stage - One 2022-04-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 8,211.00 0.00 plementatio 2021-12-06 2022-01-10 lace for Chrouy Neang Nguo tions Envelope 0 Vulnerable Households SPD) n n Commune ,Srei Snam Distr ict, Siem Reap Province, (Siz e: 5mx8m) KH-MOI-267134-CW-RFQ / E arth Road Repair and Laterit e Pavement for Sambuor Co Component 1: Improving Liv Request for Quot Pending Im mmune, Kralanh District, Sie Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 20,000.00 0.00 plementatio 2022-01-05 2022-02-09 m Reap Province (Length= 1. tions Envelope 0 Vulnerable Households SPD) n 05 Km, Width= 4.00 m, Thick =0.15m including 1 unit of si ngle culvert construction, Ø0 .80m, length 7.00m) KH-MOI-267135-CW-RFQ / U nlined Earth Canal Rehabilita tion for Khlang Hay Commun e, Srei Snam District,Siem Re Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-1 ap Province ( Length=3.35 K IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 63,783.00 0.00 plementatio 2022-01-05 2022-02-09 tions Envelope 0 m, Depth= 1.50 m including Vulnerable Households SPD) n 2 units of single culvert with gate, Ø1.00m,length 6.00m, 1 unit of single culvert with g ate, Ø0.60m, length= 6.0m KH-MOI-267137-CW-RFQ / E arth Road Repair and Laterit e Pavement for Slaeng Spea Component 1: Improving Liv Request for Quot Pending Im n Commune, Srei Snam Distr Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 61,875.00 0.00 plementatio 2022-01-05 2022-02-09 ict, Siem Reap Province ( Len tions Envelope 0 Vulnerable Households SPD) n gth= 3.35 Km, Width= 4.00 m, Thick=0.15m including 1 unit of double culvert constr uction, Ø1.00m, length 6.00 m.. KH-MOI-267138-CW-RFQ / R Component 1: Improving Liv Request for Quot Pending Im ehabilitation of Community P Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 28,518.00 0.00 plementatio 2022-01-05 2022-02-09 ond 2 places for Chi Kraeng tions Envelope 0 Vulnerable Households SPD) n Commune, Chi Kraeng Distri ct, Siem Reap Province KH-MOI-267140-CW-RFQ / R ehabilitation of Community P Component 1: Improving Liv Request for Quot Pending Im ond and Construction of wat Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 16,184.00 0.00 plementatio 2022-01-05 2022-02-09 er tank's support 2 places for tions Envelope 0 Vulnerable Households SPD) n Kouk Thlork Kraom Commun e, Chi Kraeng District, Siem Reap Province. KH-MOI-267141-CW-RFQ / D rilled Wells Construction with Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-1 Pump 1 place for Spean Tnoa IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 7,998.00 0.00 plementatio 2022-01-05 2022-02-09 tions Envelope 0 t Commune, Chi Kraeng Distr Vulnerable Households SPD) n ict, Siem Reap Province. KH-MOI-267142-CW-RFQ / E arth Road Repair and Laterit e Pavement for Dan Run Co mmune , Sotr Nikom District, Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-1 Siem Reap Province ( Total L IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 20,199.00 0.00 plementatio 2022-01-05 2022-02-09 tions Envelope 0 ength= 1.60 Km, Width= 5.0 Vulnerable Households SPD) n 0 m, Thick=0.15m including 1 unit of double culvert const ruction with water gate, Ø1.0 0m, Length= 5.00m ) KH-MOI-267143-CW-RFQ / R ehabilitation of Community P Component 1: Improving Liv Request for Quot Pending Im onds two place for Kampong Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 25,234.00 0.00 plementatio 2022-01-05 2022-02-09 Khleang Commune , Sotr Nik tions Envelope 0 Vulnerable Households SPD) n om District, Siem Reap Provi nce (Size:35mx35mx5m & 4 0mx40mx5m ) KH-MOI-267144-CW-RFQ / E arth Road Repair and Laterit e Pavement for Ballangk Co Component 1: Improving Liv Request for Quot Pending Im mmune , Brasat Bakong Dist Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 32,490.00 0.00 plementatio 2022-01-05 2022-02-09 rict, Siem Reap Province ( To tions Envelope 0 Vulnerable Households SPD) n tal Length= 1.240 Km, Width = 4.00 m, Thick=0.15m incl uding 3 unist of single culver t construction, Ø1.00m, Leng th= 6.00m, . KH-MOI-267145-CW-RFQ / U nlined Earth Canal Rehabilita tion for Mean Chey Commun Component 1: Improving Liv Request for Quot Pending Im e, Brasat Bakong District, Sie Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 29,031.00 0.00 plementatio 2022-01-05 2022-02-09 m Reap Province ( Total Leng tions Envelope 0 Vulnerable Households SPD) n th= 1.25 Km, Width= 1.50 m , Depth=2.00m including one place of box culvert with wat er gate 3mx2.50mx5m) KH-MOI-267146-CW-RFQ / Di gging Community Pond 2 pla Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-1 ces for Kaev Poar Commune, IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 52,270.00 0.00 plementatio 2022-01-05 2022-02-09 tions Envelope 0 Pouk District, Siem Reap Pro Vulnerable Households SPD) n vince, (Size: 60mx50mx5m) KH-MOI-267147-CW-RFQ / Di ke Rehabilitation for Trapea ng Thum Commune, Brasat B Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-1 akong District, Siem Reap Pr IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 38,935.00 0.00 plementatio 2022-01-05 2022-02-09 tions Envelope 0 ovince ( Total Length= 0.80 Vulnerable Households SPD) n Km, Depth=1.50m including six place of single culvert wit h water gate, Ø1.00m, Lengt h= 6.00m) Page 7 KH-MOI-267149-CW-RFQ / R einforced Concrete Road Con Component 1: Improving Liv Request for Quot Pending Im struction for Pou Treay Com Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 39,500.00 0.00 plementatio 2022-01-05 2022-02-09 mune ,Pouk District, Siem Re tions Envelope 0 Vulnerable Households SPD) n ap Province ( Total Length=0 .23 Km, Width= 5.00 m, Thic k=0.15m) KH-MOI-267151-CW-RFQ / Di gging Community Pond for Tr Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-1 ei Nhoar Commune, Pouk Dis IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 47,500.00 0.00 plementatio 2022-01-05 2022-02-09 tions Envelope 0 trict, Siem Reap Province, 4 Vulnerable Households SPD) n places (Size: 50mx30mx5m) KH-MOI-267152-CW-RFQ / Di gging Community Pond for Y Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-1 eang Commune, Pouk Distric IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 34,016.00 0.00 plementatio 2022-01-05 2022-02-09 tions Envelope 0 t, Siem Reap Province, 1 plac Vulnerable Households SPD) n es (Size:100mx50mx5m) KH-MOI-267153-CW-RFQ / E arth Road Repair and Laterit e Pavement for Sambuor Co Component 1: Improving Liv Request for Quot Pending Im mmune, Kralanh District, Sie Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 21,086.00 0.00 plementatio 2022-01-05 2022-02-09 m Reap Province ( Total Leng tions Envelope 0 Vulnerable Households SPD) n th= 0.95Km, Width= 4.00 m, Thick=0.15m including 1 pla ce of single culvert construct ion, Ø1.00m, length= 7.00m ) KH-MOI-267154-CW-RFQ / E arth Road Repair and Laterit e Pavement for Tram Sasar C Component 1: Improving Liv Request for Quot Pending Im ommune, Srei Snam District, Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 58,347.00 0.00 plementatio 2022-01-05 2022-02-09 Siem Reap Province ( Total L tions Envelope 0 Vulnerable Households SPD) n ength= 2.00Km, Width= 4.0 0 m, Thick=0.15m including 1 place of single culvert cons truction, Ø0.80m, length= 7. 00m, . KH-MOI-267156-CW-RFQ / E arth Road Repair and Laterit Component 1: Improving Liv Request for Quot Pending Im e Pavement for Kouk Thlork Request for Quota Single Stage - One 2022-05-1 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 50,569.00 0.00 plementatio 2022-01-05 2022-02-09 Kraom Commune, Kouk Chi K tions Envelope 0 Vulnerable Households SPD) n raeng District, Siem Reap Pro vince ( Total Length= 2.385 Km, Width= 4.00 m, Thick=0 .15m .. KH-MOI-267157-CW-RFQ / C onstruction of safe place for community evacuation for Sa Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-1 ngkat Chong Khneas, Siem R IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 57,605.00 0.00 plementatio 2022-01-05 2022-02-09 tions Envelope 0 eap Municilpality, Siem Reap Vulnerable Households SPD) n Province (Length=0.52Km, Width=20m) including1 unit of latrine construction with 4 rooms. KH-MOI-267160-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-0 g in Phum Trapeang Anhcha IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 2,523.40 0.00 plementatio 2022-01-05 2022-03-02 tions Envelope 1 nh 6, Sangkat Trapeang kras Vulnerable Households SPD) n ang, Khan Pou Sen Chey (Tot al Set 12 sets) KH-MOI-267165-CW-RFQ / S Component 2: Improving Liv Request for Quot Pending Im olar LED Power Street lightin Request for Quota Single Stage - One 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,610.90 0.00 plementatio 2022-01-05 2022-03-02 g in Phum Saen Sok 1, Sang tions Envelope 1 Vulnerable Households SPD) n kat Khmounh, Khan Saen So k (Total Set 37 sets) KH-MOI-267219-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-0 g in Phum Andong1, Phum A IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,817.00 0.00 plementatio 2022-01-05 2022-03-02 tions Envelope 1 ndong 2, Sangkat Kork Roka, Vulnerable Households SPD) n Khan Prek Phnov (Total set 3 8 sets) KH-MOI-267220-CW-RFQ / S Component 2: Improving Liv Request for Quot Pending Im olar LED Power Street lightin Request for Quota Single Stage - One 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 2,317.70 0.00 plementatio 2022-01-05 2022-03-02 g in Phum Talei, Sangkat Da tions Envelope 1 Vulnerable Households SPD) n ngkao, Khan Dangkao (Total set 11 sets) KH-MOI-267223-CW-RFQ / S Component 2: Improving Liv Request for Quot Pending Im olar LED Power Street lightin Request for Quota Single Stage - One 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 5,403.20 0.00 plementatio 2022-01-05 2022-03-02 g in Phum 3 & 4 , Sangkat Bo tions Envelope 1 Vulnerable Households SPD) n eung Kak 1, Khan Toul Kork ( Total set 26 sets) KH-MOI-267224-CW-RFQ / S Component 2: Improving Liv Request for Quot Pending Im olar LED Power Street lightin Request for Quota Single Stage - One 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 6,637.40 0.00 plementatio 2022-01-05 2022-03-02 g in Phum 2, Sangkat Chrang tions Envelope 1 Vulnerable Households SPD) n Chamreas 1, Khan Russei Ka o (Total set 32 sets) KH-MOI-267260-CW-RFQ / S Component 2: Improving Liv Request for Quot Pending Im olar LED Power Street lightin Request for Quota Single Stage - One 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 3,757.60 0.00 plementatio 2022-01-05 2022-03-02 g in Phum Prek Leap, Sankat tions Envelope 1 Vulnerable Households SPD) n Prek Leap, Khan Chroy Chan gvar (Total set 18 Sets) KH-MOI-267261-CW-RFQ / S Component 2: Improving Liv Request for Quot Pending Im olar LED Power Street lightin Request for Quota Single Stage - One 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 10,340.00 0.00 plementatio 2022-01-05 2022-03-02 g in Phum 15 & 16, Sangkat tions Envelope 1 Vulnerable Households SPD) n Srah Chak, Khan Daun Penh (Total set 50 sets) KH-MOI-267262-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-05-0 g in Phum Prek Tanou, Sangk IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 6,431.70 0.00 plementatio 2022-01-05 2022-03-02 tions Envelope 1 at Chak Angrae Leu, Khan M Vulnerable Households SPD) n ean Chey (Total set 31 sets) KH-MOI-267263-CW-RFQ / R einforced concrete road in Ph Component 2: Improving Liv Request for Quot Pending Im um Saen Sok 1, Sangkat Kh Request for Quota Single Stage - One 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 18,925.00 0.00 plementatio 2022-01-05 2022-03-02 mounh, Khan Saen Sok (Tota tions Envelope 1 Vulnerable Households SPD) n l length 148m, 4m width, 0,1 5m thickness) Pipe culvert (T otal length 6m, Ǿ80 Diamete r) KH-MOI-297191-CW-RFQ / R einforced concrete Road in P hum Trapeang Anhchanh 3 & Phum Trapeang Anhchanh 5, Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-10-2 Sangkat Trapeang Krasang, IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 47,187.35 0.00 plementatio 2022-06-20 2022-07-25 tions Envelope 3 Khan Pou Sen Chey (Total le Vulnerable Households SPD) n ngth 104m, 4m width, 165m, 4m width, 0,15 thickness) Pi pe Drainage ( Total length 26 9m, Ǿ60 Diameter) KH-MOI-297193-CW-RFQ / R einforced concrete Road in P Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-10-2 hum Khmer Leu Thmei, Sang IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 40,573.39 0.00 plementatio 2022-06-20 2022-07-25 tions Envelope 3 kat Kork Roka, Khan Prek Ph Vulnerable Households SPD) n nov (Total length 383m, 4m width, 0,15m thickness) KH-MOI-297195-CW-RFQ / R einforced concrete Road in P hum Prey Veng Lek, Sangkat Prey Veng, Khan Dangkao (T Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-10-2 otal length 86m, 4m width, 3 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 17,766.00 0.00 plementatio 2022-06-20 2022-07-25 tions Envelope 3 9m, 3m width, 74m, 2,5m wi Vulnerable Households SPD) n dth, 0,15m thickness) and Re inforced concrete Road in Ph um Komreang Sangkat Prey Veng ( Total length 94m) KH-MOI-297196-CW-RFQ / R einforced concrete Road in P Component 2: Improving Liv Request for Quot Pending Im hum Anlong Kngan & Phum T Request for Quota Single Stage - One 2022-10-2 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 30,062.60 0.00 plementatio 2022-06-20 2022-07-25 rapeang Rang, Sangkat Khm tions Envelope 3 Vulnerable Households SPD) n ounh, Khan Saen Sok(Total le ngth 120m, 3m width, 18.5m , 2.6m width, 171m, 4m widt h) KH-MOI-297198-CW-RFQ / R einforced concrete Road in P hum Thmar Kol 1, Sangkat C hoam Chau 2, Khan Pou Sen Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-10-2 chey (Total length 306m, 3m IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 55,356.59 0.00 plementatio 2022-06-20 2022-07-25 tions Envelope 3 width, 0,15m thickness) Rein Vulnerable Households SPD) n forced concrete Road in Phu m Prey Lvea, Sangkat Choa m Chau 2, Khan Pou Senchey (Total length 128m, 4m widt h, 0,15m ) Page 8 KH-MOI-297199-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-11-0 g in Phum Serei Deidos & Ph IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 21,366.76 0.00 plementatio 2022-07-05 2022-08-09 tions Envelope 7 um Toul Sambo, Sangkat Pre Vulnerable Households SPD) n y Veng , Khan Dangkao (Tota l set 111 Sets) KH-MOI-297200-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im g in Phum Khmer Leu Thmei Request for Quota Single Stage - One 2022-11-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 20,227.63 0.00 plementatio 2022-07-05 2022-08-09 , Phum Chres Thmei & Phum tions Envelope 7 Vulnerable Households SPD) n Andong 3, Sangkat Kork Rok a , Khan Prek Phnov (Total se t 111 Sets) KH-MOI-297201-CW-RFQ / R einforced concrete Road in P Component 2: Improving Liv Request for Quot Pending Im hum Sampore Thmei & Phum Request for Quota Single Stage - One 2022-11-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 13,270.01 0.00 plementatio 2022-07-05 2022-08-09 Chres Thmei, Sangkat Kork R tions Envelope 7 Vulnerable Households SPD) n oka, Khan Prek Phnov (Total l ength 70m, 4m width, 67m, 3m width, 0,15m thickness) KH-MOI-297202-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-11-0 g in Phum Sen Sok 5 & Phu IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,446.96 0.00 plementatio 2022-07-05 2022-08-09 tions Envelope 7 m Anlong Kra Ngan, Sangkat Vulnerable Households SPD) n Khmounh , Khan Sen Sok (To tal set 35 Sets) KH-MOI-308334-CW-RFQ / E arth road repair and laterite pavement at Kok Tlok Krom Commune,Chikreang District Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-0 , Siem Reap Province(1 line l IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 14,832.01 0.00 plementatio 2022-09-04 2022-10-09 tions Envelope 7 ength 0.600Km, width 4.00m Vulnerable Households SPD) n , laterite thickness 0.15m inc luding 1 single pipe culvert Ø 0.80m length 6m and 1 doub le pipe culvert Ø1.00m, leng 7m KH-MOI-308335-CW-RFQ / E arth road repair and laterite pavement at Spean Tnot Co mmune, Chikreang District,Si Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-0 em Reap Province (6 line len IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 50,504.18 0.00 plementatio 2022-09-06 2022-10-11 tions Envelope 9 gth 2.400Km,width 4.00m & Vulnerable Households SPD) n 6m,laterite thickness 0.15m i ncluding 1single pipe culvert Ø1.00m length 6m and 1dou ble pipe culvert Ø0.80m, len gth7m KH-MOI-308336-CW-RFQ / R einforced concrete road cons truction at Sangkat Svay Dan Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-0 gkum, Siem Reap Municilpali IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 30,901.96 0.00 plementatio 2022-09-06 2022-10-11 tions Envelope 9 ty, Siem Reap Province (1line Vulnerable Households SPD) n length 0.157Km, width 5m, t hickness 0.15m and lean con crete thickness 0.05m). KH-MOI-308340-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Sangkat Krabei Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 34,276.00 0.00 plementatio 2022-09-06 2022-10-11 Riel, Siem Reap Municilpality tions Envelope 9 Vulnerable Households SPD) n , Siem Reap Province ( 1 line length 1.153Km, width 4.00 m, laterite thickness 0.15m). KH-MOI-308344-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Sangkat Tuek V Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 32,644.33 0.00 plementatio 2022-09-06 2022-10-11 il, Siem Reap Municilpality, Si tions Envelope 9 Vulnerable Households SPD) n em Reap Province ( 3 line len gth 1.190Km, width 4.00m, l aterite thickness 0.15m). KH-MOI-308346-CW-RFQ / R einforced concrete road cons truction at Ampil Commune, Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-0 Brasat Bakong District, Siem IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 28,513.00 0.00 plementatio 2022-09-06 2022-10-11 tions Envelope 9 Reap Province(1line length 0 Vulnerable Households SPD) n .200Km, width 5m, thickness 0.15m and lean concrete thi ckness 0.05m). KH-MOI-308347-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Ballangk Comm Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 13,912.00 0.00 plementatio 2022-09-06 2022-10-11 une, Brasat Bakong District, tions Envelope 9 Vulnerable Households SPD) n Siem Reap Province ( 1 line l ength 1.380Km, width 4.50m , laterite thickness 0.15m). KH-MOI-308348-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Kampong Phlou Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 11,630.00 0.00 plementatio 2022-09-06 2022-10-11 k Commune, Brasat Bakong tions Envelope 9 Vulnerable Households SPD) n District, Siem Reap Province ( 1 line length 0.610Km, widt h 7.00m, laterite thickness 0. 15m). KH-MOI-308349-CW-RFQ / E arth road repair and laterite pavement at Kantreang Com Component 1: Improving Liv Request for Quot Pending Im mune, Brasat Bakong District Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 28,305.00 0.00 plementatio 2022-09-06 2022-10-11 , Siem Reap Province ( 1 line tions Envelope 9 Vulnerable Households SPD) n length 2.340Km, width 4.00 m, laterite thickness 0.15m i ncluding 2 single pipe culver t with water gate Ø0.80m len gth 6m). KH-MOI-308350-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Mean Chey Co Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 22,180.00 0.00 plementatio 2022-09-06 2022-10-11 mmune, Brasat Bakong Distri tions Envelope 9 Vulnerable Households SPD) n ct, Siem Reap Province ( 3 lin e length 2.180Km, width 4.0 0m, laterite thickness 0.15m ). KH-MOI-308351-CW-RFQ / E arth road repair and laterite pavement at Trapeang Thum Component 1: Improving Liv Request for Quot Pending Im Commune, Brasat Bakong Di Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 14,804.00 0.00 plementatio 2022-09-06 2022-10-11 strict, Siem Reap Province ( tions Envelope 9 Vulnerable Households SPD) n 1 line length 1.650Km, width 5.00m, laterite thickness 0.1 5m including 1 double pipe c ulvert Ø1.00m, length 7m). KH-MOI-308352-CW-RFQ / R einforced concrete road cons truction at Mukh Paen Comm Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-0 une, Pouk District, Siem Rea IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 15,945.92 0.00 plementatio 2022-09-06 2022-10-11 tions Envelope 9 p Province(1line length 0.100 Vulnerable Households SPD) n Km, width 4.00m, thickness 0.15m and lean concrete thi ckness 0.05m) KH-MOI-308353-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Samrong Yea C Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 15,013.94 0.00 plementatio 2022-09-06 2022-10-11 ommune, Pouk District, Siem tions Envelope 9 Vulnerable Households SPD) n Reap Province ( 2 line length 0.710Km, width 4.00m, lateri te thickness 0.15m) KH-MOI-308354-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Roeul Commun Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 15,857.46 0.00 plementatio 2022-09-06 2022-10-11 e, Pouk District, Siem Reap P tions Envelope 9 Vulnerable Households SPD) n rovince ( 1 line length 0.850 Km, width 4.00m, laterite thi ckness 0.15m) KH-MOI-308355-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Trei Nhor Com Request for Quota Single Stage - One 2023-01-0 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 13,194.23 0.00 plementatio 2022-09-06 2022-10-11 mune, Pouk District, Siem Re tions Envelope 9 Vulnerable Households SPD) n ap Province ( 1 line length 0. 650Km, width 4.00m, laterite thickness 0.15m) KH-MOI-308356-CW-RFQ / E arth road repair and laterite pavement at Yeang Commun e, Pouk District, Siem Reap P Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-0 rovince (1 line length 0.616K IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 38,310.02 0.00 plementatio 2022-09-06 2022-10-11 tions Envelope 9 m, width 4.00m, laterite thic Vulnerable Households SPD) n kness 0.15m including 2 sing le pipe culvert Ø1.00m lengt h 6m and 1 single pipe culve rt Ø1.00m, length 10m). Page 9 KH-MOI-308358-CW-RFQ / E arth road repair and laterite pavement at Chroy Neang N goun Commune, Srei Snom Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-0 District, Siem Reap (1 line le IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 26,958.64 0.00 plementatio 2022-09-06 2022-10-11 tions Envelope 9 ngth 0.900Km, width 5.00m,l Vulnerable Households SPD) n aterite thickness 0.15m inclu ding 1 small spillway length 50m, width 3.00m and 1 tripl e pipe culvert Ø1.00,length 2 0m) KH-MOI-308359-CW-RFQ / E arth road repair and laterite pavement at Leang Dai Com mune, Angkor Thom District, Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-0 Siem Reap (1 line length 0.6 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 21,613.52 0.00 plementatio 2022-09-06 2022-10-11 tions Envelope 9 00Km, width 4.00m, laterite t Vulnerable Households SPD) n hickness 0.15m including 1 s ingle pipe culvert Ø1.00m le ngth 8m and 3 double pipe c ulvert Ø1.00m, length 6m) KH-MOI-308361-CW-RFQ / R einforced concrete Road in P hum Prey Veng Lek, Sangkat Component 2: Improving Liv Request for Quot Pending Im Prey Veng, Khan Dangkao (T Request for Quota Single Stage - One 2023-01-1 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 27,518.93 0.00 plementatio 2022-09-13 2022-10-18 otal length 86m width, 0,15 tions Envelope 6 Vulnerable Households SPD) n m thickness) and Reinforced concrete Road in Phum Komr eang Sangkat Prey Veng ( To tal length 94m, width, 0.15m thickness) KH-MOI-308362-CW-RFQ / R einforced concrete Road in P Component 2: Improving Liv Request for Quot Pending Im hum Toul Sambo, Sangkat Pr Request for Quota Single Stage - One 2023-01-1 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 15,831.22 0.00 plementatio 2022-09-13 2022-10-18 ey Veng, Khan Dangkao (Tot tions Envelope 6 Vulnerable Households SPD) n al length 82m, 5m width, 0,1 5m thickness) Pipe Drainage (Total length 82m, Ǿ60 Diam eter) KH-MOI-308363-CW-RFQ / R einforced concrete Road in P Component 2: Improving Liv Request for Quot Pending Im hum Svay Chek Thmei, Sang Request for Quota Single Stage - One 2023-01-1 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 68,451.63 0.00 plementatio 2022-09-13 2022-10-18 kat Kork Roka (Total length 4 tions Envelope 6 Vulnerable Households SPD) n 20m, 5m width, 0.15m thick ness, Pipe (drainageTotal len gth 420m, Ǿ60 Diameter) KH-MOI-308365-CW-RFQ / R einforced concrete Road in P hum Prek Takong, Sangkat C Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-1 hak Angrae Leu, Khan Mean IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 33,748.78 0.00 plementatio 2022-09-13 2022-10-18 tions Envelope 6 Chey ( Total length 331m, 1, Vulnerable Households SPD) n 9m width, 0,15m thickness) Pipe drainage (Total length 3 31m,Ǿ60 Diameter) KH-MOI-308367-CW-RFQ / R einforced concrete Road in P hum Samaki 1 & Phum Sama Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-03-1 ki 2, Sangkat Trapeang Krasa IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 49,180.01 0.00 plementatio 2022-11-14 2022-12-19 tions Envelope 9 ng, Khan Pou Sen Chey (Tota Vulnerable Households SPD) n l length 303m, 5m width, 0,1 5m thickness) Pipe drainage (Total length 202m, Ǿ60 Dia meter) KH-MOI-308369-CW-RFQ / R einforced concrete Road in P hum Thmar Kol 2, Sangkat C Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-03-1 hoam Chau 2, Khan Pou Sen IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 58,664.38 0.00 plementatio 2022-11-14 2022-12-19 tions Envelope 9 Chey (Total length 223m, 5m Vulnerable Households SPD) n width, 230m, 4m width, 0,1 5m thickness) Pipe Drainage (Total length 95m, Ǿ60 Dia meter) KH-MOI-308373-CW-RFQ / R einforced concrete Road in P hum Prey Lvea, Sangkat Cho Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-03-1 am Chau 2, Khan Pou Sench IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 21,069.09 0.00 plementatio 2022-11-14 2022-12-19 tions Envelope 9 ey (Total length 128m, 4m w Vulnerable Households SPD) n idth, 0,15m thickness) Pipe d rainage (Total length 128m, Ǿ60 Diameter) KH-MOI-308377-CW-RFQ / R einforced concrete Road in P Component 2: Improving Liv Request for Quot Pending Im hum 8, Sangkat Boeung Kak Request for Quota Single Stage - One 2022-11-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 6,267.27 0.00 plementatio 2022-09-06 2022-10-04 1, Khan Toul Kork (Total leng tions Envelope 3 Vulnerable Households SPD) n th 60m, 2m width, 0,15m thi ckness) and Pipe drainage (T otal length 60m, Ǿ50 Diamet er) KH-MOI-308399-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-01-1 g in Phum Sampore Thmei & IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 9,548.35 0.00 plementatio 2022-11-14 2022-12-19 tions Envelope 8 Phum Andong 4, Sangkat Kor Vulnerable Households SPD) n kroka, Khan Praek Phnov (To tal set 48 Sets) KH-MOI-308400-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im g in Phum Khmer Leu Thmei Request for Quota Single Stage - One 2022-11-1 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 20,227.63 0.00 plementatio 2022-09-06 2022-10-11 , Phum Chres Thmei & Phum tions Envelope 0 Vulnerable Households SPD) n Andong 3, Sangkat Kork Rok a , Khan Prek Phnov (Total se t 115 Sets) KH-MOI-308404-CW-RFQ / R einforced concrete Road in P Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-12-0 hum Trapeng Reang Chas, S IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 23,178.21 0.00 plementatio 2022-09-06 2022-10-04 tions Envelope 3 angkat Khmounh, Khan Sen Vulnerable Households SPD) n Sok (Total length 201m, 4m width, 0,15m thickness) KH-MOI-308407-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-12-0 g in Phum Samaki 3 & Phum IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 10,995.89 0.00 plementatio 2022-09-06 2022-10-04 tions Envelope 3 Samaki 4, Sangkat Trapeang Vulnerable Households SPD) n Krasang, Khan Pou Senchey ( Total set 57 Sets) KH-MOI-308408-CW-RFQ / R einforced concrete Road in P hum Samaki1, Sangkat Trap Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-12-0 eng Krasang, Khan Pou Sen IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 18,293.00 0.00 plementatio 2022-09-06 2022-10-04 tions Envelope 3 Chey (Total length 101m, 5m Vulnerable Households SPD) n width, 0,15m thickness) and Pipe drainage (Total length 1 01m, Ǿ60 Diameter) KH-MOI-308411-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im g in Phum Trapeang Chak, P Request for Quota Single Stage - One 2022-12-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,422.16 0.00 plementatio 2022-09-06 2022-10-04 hum Prey Veng Lech and Phu tions Envelope 3 Vulnerable Households SPD) n m Kamreang , Sangkat Prey Veng , Khan Dangkao (Total set 38 Sets) KH-MOI-308412-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2022-12-0 g in Phum Serei Deidos & Ph IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 21,366.76 0.00 plementatio 2022-09-06 2022-10-04 tions Envelope 3 um Toul Sambo, Sangkat Pre Vulnerable Households SPD) n y Veng , Khan Dangkao (Tota l set 111 Sets) KH-MOI-308413-CW-RFQ / S Component 2: Improving Liv Request for Quot Pending Im olar LED Power Street lightin Request for Quota Single Stage - One 2023-03-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 3,982.03 0.00 plementatio 2022-12-06 2023-01-03 g in Phum Mol, Sangkat Dan tions Envelope 4 Vulnerable Households SPD) n gkao , Khan Dangkao (Total s et 21 Sets) KH-MOI-308416-CW-RFQ / R einforced concrete Road in P hum Daeum Slaeng 1, Sangk Component 2: Improving Liv Request for Quot Pending Im at Chbar Ampov 2, Khan Chb Request for Quota Single Stage - One 2023-03-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 19,091.50 0.00 plementatio 2022-12-06 2023-01-03 ar Ampov (Total length 218m tions Envelope 4 Vulnerable Households SPD) n , 2,8m everage width, 0,15m thickness) and Solar LED Po wer Street lighting in Phum Daeum Chan total set ( 15 S ets) KH-MOI-308420-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-03-0 g in Phum Prek Takong 3 , S IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 5,684.32 0.00 plementatio 2022-12-06 2023-01-03 tions Envelope 4 angkat Chak Angrae Leu, Kh Vulnerable Households SPD) n an Meanchey (Total set 30 S ets) KH-MOI-308422-CW-RFQ / S Component 2: Improving Liv Request for Quot Pending Im olar LED Power Street lightin Request for Quota Single Stage - One 2023-03-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 11,697.35 0.00 plementatio 2022-12-06 2023-01-03 g in Phum 3 & Phum 12, San tions Envelope 4 Vulnerable Households SPD) n gkat Srah Chak, Khan Daun P enh (Total set 70 Sets) Page 10 KH-MOI-308423-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-03-0 g in Phum Sen Sok 5 & Phu IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,446.96 0.00 plementatio 2022-12-06 2023-01-03 tions Envelope 4 m Anlong Kra Ngan, Sangkat Vulnerable Households SPD) n Khmounh , Khan Sen Sok (To tal set 35 Sets) KH-MOI-308424-CW-RFQ / S olar LED Power Street lightin Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One 2023-03-0 g in Phum Andong 5 & Phum IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 11,697.35 0.00 plementatio 2022-12-06 2023-01-03 tions Envelope 4 Andong 6, Sangkat Kork Rok Vulnerable Households SPD) n a, Khan Prek Phnov (Total set 85Sets) KH-MOI-308425-CW-RFQ / R einforced concrete Road in P Component 2: Improving Liv Request for Quot Pending Im hum Sampore Thmei & Phum Request for Quota Single Stage - One 2023-03-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 13,270.01 0.00 plementatio 2022-12-06 2023-01-03 Chres Thmei, Sangkat Kork R tions Envelope 4 Vulnerable Households SPD) n oka, Khan Prek Phnov (Total l ength 70m, 4m width, 67m, 3m width, 0,15m thickness) KH-MOI-335443-CW-RFQ / E arth road repair and laterite Component 1: Improving Liv Request for Quot Pending Im pavement at Anlong Samnor Request for Quota Single Stage - One 2023-05-3 IDA / 59600 elihoods for Rural Poor and Post Open - National ations (Non Bank- 14,567.66 0.00 plementatio 2023-01-25 2023-03-01 Commune, Chikreang Distric tions Envelope 0 Vulnerable Households SPD) n t, Siem Reap Province ( 1 lin e length 1Km, width 4.00m, l aterite thickness 0.15m) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pr Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h ocess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-14029-GO-RFQ / Offi Component 3: Project Mana Request for Quota Single Stage - One Pending Impl ce Furniture for National Lev IDA / 59600 Post Open - National 27,380.00 0.00 2017-07-14 2017-09-03 2017-10-18 gement tions Envelope ementation el and Sub National Level KH-MOI-14017-GO-RFQ / Sof Component 3: Project Mana Request for Quota Single Stage - One Pending Impl IDA / 59600 Post Open - National 10,000.00 0.00 2017-07-31 2017-09-20 2017-11-19 twares ( Accounting) for PCO gement tions Envelope ementation -MOI 1 unit KH-MOI-26199-GO-RFB / Mot Component 1: Improving Liv orcycles plus helmets for Nat Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Request for Bids Open - National 226,100.00 0.00 2017-10-02 2017-10-16 2017-11-15 2017-12-06 2018-01-03 2018-03-04 ional level and Sub-National ( Envelope ementation Vulnerable Households Total 133 Units) KH-MOI-26827-GO-RFB / Lot 1: Develop Management Info rmation System (MIS) Syste Component 3: Project Mana Single Stage - One Pending Impl m Lot2: Server, Net IDA / 59600 Post Request for Bids Open - National 140,000.00 0.00 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 gement Envelope ementation work, Tablet, website, etc.) Lot 3:MIS webside maintena nce for PCO-MOI KH-MOI-33988-GO-RFQ / 4 L Component 3: Project Mana Request for Quota Single Stage - One Pending Impl IDA / 59600 Post Open - National 9,200.00 0.00 2017-11-05 2017-12-05 2017-12-20 aptop Computers for Manage gement tions Envelope ementation ment KH-MOI-34259-GO-RFB / Offi Component 3: Project Mana Single Stage - One Under Imple ce Equipment for National an IDA / 59600 Post Request for Bids Open - National 132,200.00 0.00 2017-11-08 2019-01-10 2017-11-13 2017-12-15 2019-02-15 2018-01-14 2018-02-18 2018-04-19 gement Envelope mentation d Sub National Leve KH-MOI-36613-GO-UN / Lot1 :Vehicles (Station Wagon) 3 units for -PCO-MOI and 1 unit Component 1: Improving Liv UN Agencies (Dire Pending Impl s for MEF, IDA / 59600 elihoods for Rural Poor and Post Direct 330,000.00 0.00 2017-11-17 2017-11-22 2017-12-25 2018-02-23 ct) ementation Lot2:Vehicles (Pick up Cars) f Vulnerable Households or 1units for GDA-MAFF, 3 un its for Siem Reap and 2 units for PPM. The total Vehicles: 10 Units KH-MOI-34266-GO-UN / Vehi Component 1: Improving Liv cles (Station Wagon) 3 units UN Agencies (Dire IDA / 59600 elihoods for Rural Poor and Post Direct 132,000.00 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-02-23 for -PCO-MOI and 1 units for ct) Vulnerable Households MEF, Total Vehicles: 4 Units KH-MOI-11051-GO-RFB / Veh Component 1: Improving Liv icles (Pick up Cars) for 1units Single Stage - One IDA / 59600 elihoods for Rural Poor and Post Request for Bids Open - National 198,000.00 0.00 Canceled 2017-10-02 2017-10-16 2017-11-15 2017-12-15 2018-01-07 2018-05-07 for GDA-MAFF, 3 units for Sie Envelope Vulnerable Households m Reap and 2 units for PPM. Total Vehicles: 6 Units KH-MOI-99858-GO-RFQ / Tot Component 3: Project Mana Request for Quota Single Stage - One Pending Impl IDA / 59600 Post Open - National 4,900.00 0.00 2019-03-06 2019-04-03 2019-04-17 al 7 Air Conditioners for PCO gement tions Envelope ementation and MAFF KH-MOI-99860-GO-RFQ / Offi Component 3: Project Mana Request for Quota Single Stage - One Pending Impl IDA / 59600 Post Open - National 20,000.00 0.00 2019-03-06 2019-04-03 2019-05-03 ce Furniture for MOI-PCO gement tions Envelope ementation KH-MOI-99861-GO-RFQ / Pri Component 1: Improving Liv nting Material and Thumbpri Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 22,644.00 0.00 2019-03-06 2019-04-03 2019-05-03 nt pad for SHG/producer gro tions Envelope ementation Vulnerable Households up/commune federation for 2 019 KH-MOI-99863-GO-RFQ / Mat Component 1: Improving Liv erial for SHG/producer group Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 31,250.00 0.00 2019-03-06 2019-04-24 2019-05-24 /commune federation (Boxes tions Envelope ementation Vulnerable Households for keeping documents and c ash) KH-MOI-99865-GO-RFQ / Eq Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl uipment for Commune/Sangk IDA / 59600 elihoods for Rural Poor and Post Open - National 10,000.00 0.00 2019-03-06 2019-04-03 2019-04-18 tions Envelope ementation at Investment Projects (SRP Vulnerable Households and PPCH) KH-MOI-99868-GO-RFQ / 72 Component 1: Improving Liv Tablets for MIS (3 MoI, 3 GDA Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 24,840.00 0.00 2019-04-06 2019-05-04 2019-06-03 , 3 PPCH, 3 Pro. S_Reap, 47 c tions Envelope ementation Vulnerable Households ommune, 13 Sangkat) KH-MOI-99869-GO-RFQ / Pri Component 1: Improving Liv nting Materials (Logos, Printe Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 20,250.00 0.00 2019-05-06 2019-06-03 2019-06-24 d Folder, Factsheets, Newslet tions Envelope ementation Vulnerable Households ters, Brochures, Posters and Standing Poster) KH-MOI-99871-GO-RFQ / Pri Component 1: Improving Liv Request for Quota Single Stage - One Under Imple nting Materials for SHG/prod IDA / 59600 elihoods for Rural Poor and Post Open - National 20,145.00 0.00 2019-12-06 2020-01-04 2020-02-03 tions Envelope mentation ucer group/commune federat Vulnerable Households ion for 2020 KH-MOI-26829-GO-RFB / Mat erial for SHG/Poducer group/ Component 1: Improving Liv commune federation(books k Single Stage - One IDA / 59600 elihoods for Rural Poor and Post Request for Bids Open - National 126,250.70 0.00 Canceled 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 eeping, cash book, pay and l Envelope Vulnerable Households oan record book, SHG box fo r keeping docs. And Thumpri nt pad) for SRP KH-MOI-121052-GO-RFQ / Pr Component 3: Project Mana Request for Quota Single Stage - One Pending Impl ocurement of supply Server IDA / 59600 Post Open - National 20,000.00 0.00 2019-07-10 2019-08-04 2019-09-03 gement tions Envelope ementation and network for LEAP Project KH-MOI-136652-GO-RFQ / Of Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl fice Furniture for Skill Develo IDA / 59600 elihoods for Rural Poor and Post Open - National 4,400.00 0.00 2019-10-16 2019-11-11 2019-11-25 tions Envelope ementation pment Activities Vulnerable Households KH-MOI-136666-GO-RFQ / M Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl otorcycles for Skill Developm IDA / 59600 elihoods for Rural Poor and Post Open - National 17,500.00 0.00 2019-10-16 2019-11-11 2019-11-25 tions Envelope ementation ent Activities (10 Units) Vulnerable Households KH-MOI-168855-GO-RFQ / V Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl ehicles (VAN) 1 units for -PC IDA / 59600 elihoods for Rural Poor and Post Open 30,000.00 0.00 2020-04-29 2020-06-05 2020-07-05 tions Envelope ementation O-MOI ( Import tax will be ex Vulnerable Households empted) KH-MOI-168856-GO-RFQ / Of Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl fice Furniture for Sub Nation IDA / 59600 elihoods for Rural Poor and Post Open - National 16,915.00 0.00 2020-05-02 2020-05-28 2020-06-27 tions Envelope ementation al Level (PCO, SRP ) Vulnerable Households KH-MOI-168859-GO-RFQ / St udy Equipment (Hummer Tes Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl t, DCP Test, Autormatic Level IDA / 59600 elihoods for Rural Poor and Post Open - National 11,000.00 0.00 2020-05-06 2020-05-29 2020-06-13 tions Envelope ementation , GPS…2sets) for Commnune Vulnerable Households /Sangkat Investment Projects (SRP) Page 11 KH-MOI-168860-GO-RFQ / Pr inting Communication Materi Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl als (LEAP Newsletters semi-a IDA / 59600 elihoods for Rural Poor and Post Open - National 12,000.00 0.00 2020-06-20 2020-07-18 2020-08-08 tions Envelope ementation nnual (2time/years) in Khmer Vulnerable Households and English 2time/year) KH-MOI-168861-GO-RFQ / Pr Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl inting Communication Materi IDA / 59600 elihoods for Rural Poor and Post Open - National 4,000.00 0.00 2020-09-06 2020-10-04 2020-10-25 tions Envelope ementation als ( Success Story 4 time/ye Vulnerable Households ar) KH-MOI-168862-GO-RFQ / Vi Component 1: Improving Liv Request for Quota Single Stage - One Pending Impl deo Production of project ach IDA / 59600 elihoods for Rural Poor and Post Open - National 7,000.00 0.00 2020-09-06 2020-09-29 2020-10-29 tions Envelope ementation ievement (15 Minute) Vulnerable Households KH-MOI-226724-GO-RFB / Ve Component 1: Improving Liv hicles (VAN) 1 units for -PCO- Single Stage - One Under Imple IDA / 59600 elihoods for Rural Poor and Post Request for Bids Open - National 130,000.00 0.00 2021-04-18 2021-04-23 2021-04-23 2021-04-27 2021-05-23 2021-06-22 2021-07-27 2021-08-02 MOI, Vehicles (Pick up Cars) Envelope mentation Vulnerable Households 2 units for Siem Reap KH-MOI-226726-GO-UN / SU Component 2: Improving Liv UN Agencies (Dire Pending Impl V Vehicles 1 units for PPCH( IDA / 59600 elihoods for Urban Poor and Post Direct 40,000.00 0.00 2021-04-18 2021-04-21 2021-06-02 2021-08-31 ct) ementation Import tax will be exempted) Vulnerable Households KH-MOI-226728-GO-RFQ / M Component 1: Improving Liv Request for Quota Single Stage - One Under Imple otorcycles( 12 Units for SRP IDA / 59600 elihoods for Rural Poor and Post Open - National 30,000.00 0.00 2021-04-19 2021-04-27 2021-05-29 2021-06-28 tions Envelope mentation and 3 Units for MAFFs) Vulnerable Households KH-MOI-226744-GO-RFQ / Of fice Equipment: (4 Laptops f or PCO, 2 Laptops for PPCH , Component 3: Project Mana Request for Quota Single Stage - One Under Imple IDA / 59600 Post Open - National 33,032.00 0.00 2021-04-26 2021-05-21 2021-06-23 2021-07-23 5 Laptops for MAFF , 4 Note gement tions Envelope mentation Book for SC, 2 Desktops for P PCH, 1 Printer for MAFF, and 15 Tablets for New CF-SRP) KH-MOI-226750-GO-RFQ / Pr ocurement of 1 unit Stability Camera Stand ,1 unit Zoom- Component 3: Project Mana Request for Quota Single Stage - One Pending Impl IDA / 59600 Post Open - National 7,400.00 0.00 2021-05-02 2021-06-15 2021-07-15 Len Camera ,1 Unit Drone Ca gement tions Envelope ementation mera for SRP and 1Unit Zoo m-Len Camera,1set Equipme nt of video conference for PP CH KH-MOI-226753-GO-RFQ / In Component 3: Project Mana Request for Quota Single Stage - One Pending Impl stallation Microphone Syste IDA / 59600 Post Open - National 20,000.00 0.00 2021-06-02 2021-07-16 2021-08-15 gement tions Envelope ementation m for PCO-LEAP meeting roo m KH-MOI-226767-GO-RFQ / M aterials for SHG/producer gro up (14000 Cash book for SH Component 1: Improving Liv Request for Quota Single Stage - One Under Imple Gs member, 1200 SHGs Savi IDA / 59600 elihoods for Rural Poor and Post Open - National 30,400.00 0.00 2021-04-26 2021-04-27 2021-06-23 2021-07-23 tions Envelope mentation ng, Loan & Repayment Book Vulnerable Households s,1200 SHG minute books, 4 000 SHG minute books and 1 200 Thumbprint pad for SHG 2021 KH-MOI-226770-GO-RFQ / Pu Component 1: Improving Liv rchase 25 Booth for PGs to p Request for Quota Single Stage - One Under Imple IDA / 59600 elihoods for Rural Poor and Post Open - National 6,875.00 0.00 2021-05-04 2021-06-10 2021-07-10 romote agriculture products tions Envelope mentation Vulnerable Households for weekend Market for SMT- SRP KH-MOI-226776-GO-RFQ / Pr inting Communication Materi Component 1: Improving Liv Request for Quota Single Stage - One Under Imple als (LEAP Newsletters semi-a IDA / 59600 elihoods for Rural Poor and Post Open - National 8,500.00 0.00 2021-05-08 2021-11-10 2021-06-05 2021-12-02 tions Envelope mentation nnual (2time/years) in Khmer Vulnerable Households and English 2time/year) 202 1 KH-MOI-226782-GO-RFQ / Pr Component 1: Improving Liv inting 140 Produce PCV Bann Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 9,400.00 0.00 2021-04-19 2021-05-25 2021-06-15 er and 11200 leaflets on Skill tions Envelope ementation Vulnerable Households s Development information f or SRP and PPCH KH-MOI-226783-GO-RFQ / Pr inting Tools to Provide techni cal training for CAHEWs in Q Component 1: Improving Liv 1 and Q2 on (Chicken Eggs I Request for Quota Single Stage - One Under Imple IDA / 59600 elihoods for Rural Poor and Post Open - National 52,500.00 0.00 2021-05-04 2021-11-01 2021-06-30 2021-12-27 ncubator Making), (how to u tions Envelope mentation Vulnerable Households se vaccination kits), 50 Sets ( chicken raising ) (Pig Raising ) and 50 Sets PCV Banner Tr aining Tools (Fish (rice and v egetable production) KH-MOI-226784-GO-RFQ / D Component 1: Improving Liv esign and print out banner to Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 3,000.00 0.00 2021-05-04 2021-06-09 2021-06-30 mainstream information on g tions Envelope ementation Vulnerable Households ender to target beneficiaries KH-MOI-283063-GO-RFQ / Pr Component 1: Improving Liv inting Newsletters semi-annu Request for Quota Single Stage - One Under Imple IDA / 59600 elihoods for Rural Poor and Post Open - National 12,750.00 0.00 2022-05-06 2022-11-22 2022-06-03 2022-06-24 al (2 time/year) and Success tions Envelope mentation Vulnerable Households Story leaflet (SRP and PPCH) KH-MOI-283065-GO-RFQ / Pr Component 1: Improving Liv inting Material for SHG (SHG Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 5,500.00 0.00 2022-04-20 2022-05-18 2022-06-08 s cash, bank book, SHGs savi tions Envelope ementation Vulnerable Households ng, loan & repayment book) total 2000books KH-MOI-283066-GO-RFQ / D Component 1: Improving Liv esign and print out Poster to Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 3,000.00 0.00 2022-04-20 2022-05-18 2022-06-08 mainstream information on g tions Envelope ementation Vulnerable Households ender to target beneficiaries (SHGs1,000) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pr Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h ocess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-99864-NC-RFQ / Dev Component 3: Project Mana Request for Quota Single Stage - One Under Imple IDA / 59600 Post Open - National 5,600.00 0.00 2019-03-06 2019-04-03 2019-05-03 elop Website for LEAP Projec gement tions Envelope mentation Component 1: Improving Liv KH-MOI-99870-NC-RFQ / Fou Request for Quota Single Stage - One Pending Impl IDA / 59600 elihoods for Rural Poor and Post Open - National 20,000.00 0.00 2019-07-06 2019-08-17 2019-10-16 r (4) Video Spots tions Envelope ementation Vulnerable Households KH-MOI-226780-NC-RFQ / Vi Component 3: Project Mana Request for Quota Single Stage - One Under Imple deo Production of project ach IDA / 59600 Post Open - National 7,000.00 0.00 2021-07-06 2021-09-20 2021-08-17 2021-10-16 gement tions Envelope mentation ievement 2021 KH-MOI-283064-NC-RFQ / Pr Component 3: Project Mana Request for Quota Single Stage - One Under Imple oduce short video stories (15 IDA / 59600 Post Open - National 7,000.00 0.00 2022-06-06 2022-10-27 2022-07-18 2022-09-16 gement tions Envelope mentation minutes) on project achieve ments (PCO) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interes Short List and Draft R Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) t Notice equest for Proposals s as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-39863-CS-CQS / Imp act Survey (3nd year of the p Component 3: Project Mana Consultant Qualifi Pending Impleme IDA / 59600 Post Open - National 30,000.00 0.00 2020-01-02 2020-01-23 2020-03-07 2020-04-06 2020-05-11 2020-11-07 roject/Mid-term review) (Loc gement cation Selection ntation al Firm) at PCO-MOI KH-MOI-39867-CS-CQS / Fin al Impact Survey ( (5th year Component 3: Project Mana Consultant Qualifi Pending Impleme IDA / 59600 Post Open - National 40,000.00 0.00 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 of Project evaluation and co gement cation Selection ntation mpletion report) (Local Firm) at PCO-MOI KH-MOI-82848-CS-CQS / Dev elopment of Community Insti Component 1: Improving Liv Consultant Qualifi Under Implement tutions of the Poor for 4 Distr IDA / 59600 elihoods for Rural Poor and Post Open - National 280,000.00 0.00 2018-10-22 2019-01-18 2018-11-12 2019-01-11 2019-02-10 2019-03-17 2022-11-30 cation Selection ation icts​​  (Angkor Thum, Kralanh, Vulnerable Households Pouk and Srei Snam District) Page 12 KH-MOI-82083-CS-CQS / Dev elopment of Community Insti Component 1: Improving Liv Consultant Qualifi Under Implement tutions of the Poor for 5 Distr IDA / 59600 elihoods for Rural Poor and Post Open - National 290,000.00 0.00 2018-10-22 2018-12-21 2018-11-12 2019-01-11 2019-03-22 2019-02-10 2019-03-17 2022-12-05 cation Selection ation icts ( Chi Kraeng, Prasat Bak Vulnerable Households ong, Siem Reap, Soutr Nikom and Svay Leu District) KH-MOI-70310-CS-QCBS / H Component 1: Improving Liv Quality And Cost- Open - Internationa uman Resource Developmen IDA / 59600 elihoods for Rural Poor and Prior 784,000.00 0.00 Canceled 2018-12-14 2019-01-13 2019-01-16 2019-02-26 2019-05-10 2019-04-12 2019-05-12 2019-06-16 2019-07-21 2023-06-30 Based Selection l t Service Provider (HRDSP) fo Vulnerable Households r SRP and PPCH KH-MOI-39858-CS-QCBS / H Component 2: Improving Liv uman Resources Developme Quality And Cost- Open - Internationa IDA / 59600 elihoods for Urban Poor and Post 367,932.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 nt Services Provider(HRDSP) Based Selection l Vulnerable Households for PPM (NGO/Firm) KH-MOI-39860-CS-CQS / Bas Component 3: Project Mana Consultant Qualifi eline Survey (1st year)(Local IDA / 59600 Post Open - National 30,000.00 0.00 Canceled 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 gement cation Selection Firm) at PCO-MOI KH-MOI-39857-CS-QCBS / H Component 1: Improving Liv uman Resources Developme Quality And Cost- Open - Internationa IDA / 59600 elihoods for Rural Poor and Post 545,936.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 nt Services Provider(HRDSP) Based Selection l Vulnerable Households for SRP (NGO/Firm) KH-MOI-187154-CS-CQS / Tr Component 1: Improving Liv acer Study Consultant for 24 Consultant Qualifi Under Implement IDA / 59600 elihoods for Rural Poor and Post Open - National 45,000.00 0.00 2020-08-10 2020-08-07 2020-08-31 2020-08-23 2020-10-14 2020-11-13 2020-12-18 2022-12-08 months (one firm consultant cation Selection ation Vulnerable Households will be hired for both SRP an d PPCH) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-13893-CS-INDV / Pro Component 1: Improving Liv Individual Consult Under Implement vincial Operation and M&E S IDA / 59600 elihoods for Rural Poor and Post Open 120,000.00 0.00 2017-06-26 2017-12-07 2017-08-23 2018-04-30 2017-09-06 2018-04-30 2017-10-11 2022-10-10 ant Selection ation pecialist for SRP (60 Months) Vulnerable Households KH-MOI-13901-CS-INDV / Pro Component 3: Project Mana Individual Consult Pending Impleme IDA / 59600 Post Open 18,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2020-10-24 ject Assistant for PCO-MOI (6 gement ant Selection ntation 0 Months) KH-MOI-13903-CS-INDV / Na Component 2: Improving Liv Individual Consult Pending Impleme tional Operation and M&E Sp IDA / 59600 elihoods for Urban Poor and Post Open 150,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2022-10-10 ant Selection ntation ecialist for PPM (60 Months) Vulnerable Households KH-MOI-13905-CS-INDV / Pro Component 1: Improving Liv Individual Consult Pending Impleme vincial Finance Management IDA / 59600 elihoods for Rural Poor and Post Open 72,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2020-10-10 ant Selection ntation Specialist for SRP (36 Months Vulnerable Households ) KH-MOI-13907-CS-INDV / Pro Component 1: Improving Liv Individual Consult Pending Impleme ject Assistant for SRP (60 Mo IDA / 59600 elihoods for Rural Poor and Post Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 ant Selection ntation nths) Vulnerable Households KH-MOI-13910-CS-INDV / Pro Component 2: Improving Liv Individual Consult Pending Impleme ject Assistant for PPM (60 Mo IDA / 59600 elihoods for Urban Poor and Post Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 ant Selection ntation nths) Vulnerable Households KH-MOI-13913-CS-INDV / 01 Component 2: Improving Liv Individual Consult Pending Impleme PPM Infrastructure Specialist IDA / 59600 elihoods for Urban Poor and Post Open 72,000.00 0.00 2017-07-17 2017-09-13 2017-09-27 2017-11-01 2020-10-31 ant Selection ntation at PPM (36 Months) Vulnerable Households KH-MOI-11055-CS-INDV / Na Component 3: Project Mana Individual Consult Pending Impleme tional Project Management a IDA / 59600 Post Open 180,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2022-11-30 gement ant Selection ntation nd M&E consultant at PCO-M OI KH-MOI-11263-CS-INDV / Na Component 1: Improving Liv Individual Consult Pending Impleme tional Finance Management IDA / 59600 elihoods for Rural Poor and Post Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 ant Selection ntation Specialist for MOI/PPM(36 Mo Vulnerable Households nths) KH-MOI-13886-CS-INDV / Na Component 2: Improving Liv Individual Consult Pending Impleme tional procurement Specialist IDA / 59600 elihoods for Urban Poor and Post Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 ant Selection ntation based at PCO Vulnerable Households KH-MOI-30826-CS-INDV / Pro Component 1: Improving Liv Individual Consult Pending Impleme vincial Infrastructure Speciali IDA / 59600 elihoods for Rural Poor and Post Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 ant Selection ntation st (P M & E Engineer) at SRP Vulnerable Households (36 Months) KH-MOI-30834-CS-INDV / Pro Component 1: Improving Liv vincial Infrastructure Speciali Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and Post Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 st (Building Construction Eng ant Selection ntation Vulnerable Households ineer) at SRP (36 Months) KH-MOI-30840-CS-INDV / Pro Component 1: Improving Liv vincial Infrastructure Speciali Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and Post Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 st (Rural Road Construction E ant Selection ntation Vulnerable Households ngineer) at SRP (36 Months) KH-MOI-39794-CS-INDV / Int Component 3: Project Mana Individual Consult Pending Impleme ernational Micro-Finance Exp IDA / 59600 Post Open 60,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-07-16 gement ant Selection ntation ert at PCO-MOI(60 days) KH-MOI-39797-CS-INDV / Na Component 3: Project Mana Individual Consult Pending Impleme tional Communication Specia IDA / 59600 Post Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 gement ant Selection ntation list at PCO-MOI (36 Months) KH-MOI-39798-CS-INDV / Na Component 3: Project Mana Individual Consult Pending Impleme tional MIS Specialist at PCO- IDA / 59600 Post Open 60,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 gement ant Selection ntation MOI (24 Months) KH-MOI-39800-CS-INDV / Na Component 1: Improving Liv Individual Consult Pending Impleme tional Agriculture Likelihood IDA / 59600 elihoods for Rural Poor and Post Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 ant Selection ntation Specialist for GDA-MAFF (36 Vulnerable Households Months) KH-MOI-39817-CS-INDV / Na Component 1: Improving Liv Individual Consult Pending Impleme tional HR Development Speci IDA / 59600 elihoods for Rural Poor and Post Open 48,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 ant Selection ntation alist for SRP (24 Months) Vulnerable Households KH-MOI-39821-CS-INDV / Na Component 2: Improving Liv Individual Consult Pending Impleme tional HR Development Speci IDA / 59600 elihoods for Urban Poor and Post Open 48,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2020-05-06 ant Selection ntation alist for PPM ( 24 Months) Vulnerable Households KH-MOI-39888-CS-INDV / 7 Component 1: Improving Liv Individual Consult Pending Impleme District Facilitators (7 DF x 5 IDA / 59600 elihoods for Rural Poor and Post Open 336,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 ant Selection ntation 5 Months) at Siem Reap Vulnerable Households KH-MOI-40438-CS-INDV / Pro Component 1: Improving Liv Individual Consult Pending Impleme vincial Micro-Finance Speciali IDA / 59600 elihoods for Rural Poor and Post Open 72,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 ant Selection ntation st for SRP ( 36 Months) Vulnerable Households KH-MOI-40440-CS-INDV / Se Component 1: Improving Liv Individual Consult Pending Impleme nior Livelihood/business dev IDA / 59600 elihoods for Rural Poor and Post Open 90,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 ant Selection ntation elopment Specialist for SRP ( Vulnerable Households 36 Months) KH-MOI-40447-CS-INDV / 47 Component 1: Improving Liv Individual Consult Pending Impleme Commune Facilitators (47CFs IDA / 59600 elihoods for Rural Poor and Prior Open 564,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 ant Selection ntation x55 Months) for SRP Vulnerable Households KH-MOI-40449-CS-INDV / 47 Component 1: Improving Liv Commune Animal Health & E Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and Post Open 338,400.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 xtension Workers (47 CAHE ant Selection ntation Vulnerable Households W x 55 Months) for SRP KH-MOI-40453-CS-INDV / 4 L Component 2: Improving Liv Individual Consult Pending Impleme ocal Coordinator for urban p IDA / 59600 elihoods for Urban Poor and Post Open 96,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 ant Selection ntation oor(4CLUPs x 55 Months) for Vulnerable Households PPM KH-MOI-99872-CS-INDV / Pro Component 3: Project Mana Individual Consult Pending Impleme IDA / 59600 Post Open 15,000.00 0.00 2019-03-01 2019-04-21 2019-05-05 2019-06-09 2022-06-08 ject Assistant for MAFF gement ant Selection ntation Page 13 KH-MOI-99873-CS-INDV / Tra Component 1: Improving Liv Individual Consult cer Study Consultant (60 Wo IDA / 59600 elihoods for Rural Poor and Post Open 18,000.00 0.00 Canceled 2019-06-03 2019-07-22 2019-07-29 2019-08-12 2019-10-11 ant Selection rking Days) Vulnerable Households KH-MOI-136635-CS-INDV / In Component 1: Improving Liv ternational Skill Developmen Individual Consult Under Implement IDA / 59600 elihoods for Rural Poor and Post Open 112,800.00 0.00 2019-10-04 2019-10-18 2019-11-10 2019-11-15 2019-11-28 2020-03-27 t Advisor (120 days x 1 pax) ant Selection ation Vulnerable Households for (20day-2019, 80 days-20 20 and 20 days-2021) KH-MOI-136641-CS-INDV / N Component 2: Improving Liv Individual Consult Pending Impleme ational Skills Development S IDA / 59600 elihoods for Urban Poor and Post Open 85,000.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 ant Selection ntation pecialist (34 monthsx1pax) f Vulnerable Households or PCO-LEAP KH-MOI-136643-CS-INDV / H Component 2: Improving Liv Individual Consult Pending Impleme uman Resource Developmen IDA / 59600 elihoods for Urban Poor and Post Open 190,400.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 ant Selection ntation t Facilitators for SRP (34mont Vulnerable Households h x 7 paxes) KH-MOI-136648-CS-INDV / H Component 1: Improving Liv Individual Consult Pending Impleme uman Resource Developmen IDA / 59600 elihoods for Rural Poor and Post Open 81,600.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 ant Selection ntation t Facilitators for PPCH (34mo Vulnerable Households nth x 3 paxes) KH-MOI-168864-CS-INDV / N Component 1: Improving Liv ational Consultant for Market Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and Post Open 56,000.00 0.00 2020-05-24 2020-07-12 2020-08-02 2020-09-06 2022-09-06 Linkage Study (Intermittent) ant Selection ntation Vulnerable Households for 3 year (2020-2022) KH-MOI-168866-CS-INDV / N Component 1: Improving Liv ational Consultant for Sturdy Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and Post Open 31,200.00 0.00 2020-05-01 2020-06-19 2020-07-10 2020-08-14 2022-08-14 research promote Linkage wi ant Selection ntation Vulnerable Households th formal Financial sector for 3 year (2020-20220) KH-MOI-220888-CS-INDV / Pr Component 1: Improving Liv Individual Consult Under Implement ocure to replacement of Ms. IDA / 59600 elihoods for Rural Poor and Post Open 33,360.00 0.00 2021-03-01 2021-02-23 2021-04-03 2021-04-08 2021-04-22 2022-04-22 ant Selection ation Teng Ratana Resigned on 22 Vulnerable Households July 2020 KH-MOI-226811-CS-INDV / O ne National procurement Sp Component 2: Improving Liv Individual Consult Under Implement ecialist based at PCO (12 mo IDA / 59600 elihoods for Urban Poor and Post Open 30,000.00 0.00 2021-04-08 2021-04-23 2021-06-05 2021-06-19 2021-07-24 2022-07-24 ant Selection ation nths) to replacement Mr. Cha Vulnerable Households y Ponlork Resigned on 01 Oc t 2019 KH-MOI-226812-CS-INDV / O ne National Independent aud Component 3: Project Mana Individual Consult Under Implement IDA / 59600 Post Open 6,000.00 0.00 2021-05-03 2022-11-23 2021-06-21 2021-07-12 2021-08-16 2021-10-15 itor for Infrastructure with (2 gement ant Selection ation month 2021) Based in PCO KH-MOI-226814-CS-INDV / O Component 1: Improving Liv Individual Consult Under Implement ne National Agriculture Likeli IDA / 59600 elihoods for Rural Poor and Post Open 30,000.00 0.00 2021-04-08 2021-04-23 2021-05-27 2021-06-17 2021-07-22 2022-07-22 ant Selection ation hood Specialist for GDA-MAF Vulnerable Households F (12 Months) KH-MOI-226815-CS-INDV / Pr ovincial Infrastructure Specia Component 1: Improving Liv list (Rural Road Construction Individual Consult Under Implement IDA / 59600 elihoods for Rural Poor and Post Open 24,000.00 0.00 2021-04-08 2021-04-23 2021-05-27 2021-06-17 2021-07-22 2022-07-22 Engineer) at SRP (12 Months) ant Selection ation Vulnerable Households to replacement Mr Set Cham roeun Resigned on 31 Jan 21 KH-MOI-226816-CS-INDV / O Component 3: Project Mana Individual Consult ne Junior Finance/Admin Offi IDA / 59600 Post Open 9,600.00 0.00 Under Review 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 gement ant Selection cer Based in PCO (12 Months ) KH-MOI-226817-CS-INDV / O Component 2: Improving Liv Individual Consult ne Junior Finance/Admin Offi IDA / 59600 elihoods for Urban Poor and Post Open 9,600.00 0.00 Under Review 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 ant Selection cer Based in SMT-PPCH (12 Vulnerable Households Months) KH-MOI-226818-CS-INDV / O Component 1: Improving Liv Individual Consult ne Junior Finance/Admin Offi IDA / 59600 elihoods for Rural Poor and Post Open 9,600.00 0.00 Under Review 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 ant Selection cer Based in SMT- SRP (12 M Vulnerable Households onths) KH-MOI-226819-CS-INDV / O Component 1: Improving Liv ne Promote finance linkage f Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and Post Open 9,600.00 0.00 2021-05-03 2021-06-09 2021-06-23 2021-07-26 2022-07-26 acilitators Base in SMT-SRP ( ant Selection ntation Vulnerable Households 1pax x12 Months) KH-MOI-259609-CS-INDV / G Component 3: Project Mana Individual Consult Under Implement IDA / 59600 Post Open 6,000.00 0.00 2021-11-02 2022-02-03 2021-12-21 2022-01-11 2022-02-15 2022-03-17 ender specialist (20 working gement ant Selection ation days) Page 14